KR20130006420A - Method of constructing underground structure to be newly built - Google Patents

Method of constructing underground structure to be newly built Download PDF

Info

Publication number
KR20130006420A
KR20130006420A KR1020127014104A KR20127014104A KR20130006420A KR 20130006420 A KR20130006420 A KR 20130006420A KR 1020127014104 A KR1020127014104 A KR 1020127014104A KR 20127014104 A KR20127014104 A KR 20127014104A KR 20130006420 A KR20130006420 A KR 20130006420A
Authority
KR
South Korea
Prior art keywords
underground
new
sphere
existing
concrete
Prior art date
Application number
KR1020127014104A
Other languages
Korean (ko)
Inventor
요시오 카마타
카즈마사 야마
Original Assignee
니혼 칸쿄우 세이조우 가부시키 카이샤
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 니혼 칸쿄우 세이조우 가부시키 카이샤 filed Critical 니혼 칸쿄우 세이조우 가부시키 카이샤
Publication of KR20130006420A publication Critical patent/KR20130006420A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0007Base structures; Cellars
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D13/00Large underground chambers; Methods or apparatus for making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

기존 지하 구체에 관한 신설 지하 구체의 하중 부담을 저감시키는 동시에, 신설 지반 구체의 구축하기 위한 공비의 감축을 도모하는 것이 가능한 신설 지하 구조물의 시공 방법을 제공하는 것을 목적으로 한다. 거주 공간으로서 이용 가능한 지하실과, 배관 설비 등을 수용하기 위한 지하 시설인 지하 피트를 갖는 신설 지하 구조물(100)로써, 기존 지하 콘크리트 구체(200)와, 신설 지하 콘크리트 구체(400)의 사이에 유동화 토양 벽(300)을 배치하도록 구축되어 있다.It aims at providing the construction method of the new underground structure that can reduce the load burden of the new underground sphere about an existing underground sphere, and can also reduce the public affairs to build a new ground sphere. A new underground structure 100 having a basement that can be used as a living space and an underground pit that is an underground facility for accommodating plumbing facilities, and fluidized between the existing underground concrete sphere 200 and the new underground concrete sphere 400. It is constructed to arrange the soil wall 300.

Description

신설 지하 구조물의 시공 방법{METHOD OF CONSTRUCTING UNDERGROUND STRUCTURE TO BE NEWLY BUILT}Construction method of new underground structure {METHOD OF CONSTRUCTING UNDERGROUND STRUCTURE TO BE NEWLY BUILT}

본 발명은 신설 지하 구조물의 시공 방법에 관한 것으로서, 특히, 기존 지하 구조물에 관한 신설 지하 구조물의 하중 부담을 저감시키고, 공비(공사비용)의 감축을 도모할 수 있는 신설 지하 구조물의 시공 방법에 관한 것이다.The present invention relates to a construction method of a new underground structure, and more particularly, to a construction method of a new underground structure that can reduce the load burden of the new underground structure for the existing underground structure, and can reduce the cost of construction (construction cost) will be.

빌딩 등의 각종 건물을 개축할 때에는 기존의 건물을 해체할 필요가 있지만, 지하층 등의 지하 구조물을 구비하고 있는 건물에서는 기존 지하 구조물도 해체할 필요가 있다. 그런데, 그 기존 지하 구조물을 구성하는 지하 외벽이나 기둥, 지중 빔, 기초 등은 주변 지반으로부터의 토압을 부담하고 있고, 무계획적으로 해체하면 지산(地山)의 붕락이나 지반 변위 등을 초래하고, 인접지역에 다대한 영향을 줄 우려가 있다. When rebuilding various buildings such as buildings, existing buildings need to be dismantled, but in existing buildings with underground structures such as basement floors, existing structures must also be dismantled. However, underground outer walls, columns, underground beams, foundations, and the like that constitute the existing underground structure bear earth pressure from the surrounding ground, and when disintegrated unintentionally, it causes collapse and ground displacement of the mountain. There is a risk of significant impact on neighboring areas.

그래서, 기존 지하 구조물을 해체하는 일 없이, 지하 구조물을 신설하는 방법이 특허문헌 1에 제안되고 있다.Therefore, Patent Literature 1 proposes a method of establishing an underground structure without dismantling the existing underground structure.

특허문헌 1에서 제안되어 있는 지하 구조물의 시공법은 우선, 지하 1층의 기존 지하 외벽의 층고 중앙부에 절량(切梁; short strut)을 설치하고, 잭으로 외벽 방향을 향해 절량에 부하를 가하면서, 바닥빔(floor beam)을 철거한다. 이 일련의 작업을 각 층에서 실행하고, 기존 지하 외벽의 내측에 신설벽을 타설하고, 기존 지하 외벽과의 합성벽을 구축하며, 그 후, 바닥 빔을 철거한다. 이 일련의 작업을 각 층에서 실행하고, 신설 지하 구조물의 시공을 실행한다.In the construction method of the underground structure proposed in Patent Literature 1, first, a short strut is installed at the center of the floor height of the existing underground outer wall of the first basement, and a load is applied to the external wall direction with a jack. The floor beam is demolished. This series of work is carried out on each floor, a new wall is placed inside the existing basement outer wall, a composite wall is built with the existing basement outer wall, and the floor beam is then demolished. This series of work is carried out on each floor and construction of the new underground structure is carried out.

일본국 특허공개공보 제2005-201007호Japanese Patent Publication No. 2005-201007

그러나, 특허문헌 1에서 개시되어 있는 지하 구조물의 시공법에 의하면, 구축되는 합성벽은 기존 지하 외벽과 신설 벽을 일체화시키는 것이기 때문에, 층 아래에 관한 하중 부담이 증대한다. 그 때문에, 이 하중을 지지하기 위해 더욱 많은 지지력이 필요하게 되고 그를 위한 공비가 커진다고 하는 문제가 있다.However, according to the construction method of the underground structure disclosed by patent document 1, since the composite wall to be constructed integrates an existing underground outer wall and a new wall, the load burden on a layer below increases. Therefore, there is a problem that more support force is required to support this load, and the cost for it increases.

본 발명은 이러한 문제를 감안해서 이루어진 것으로써, 기존 지하 구체(軀體; 뼈대)에 관한 신설 지하 구체의 하중 부담을 저감시키는 동시에, 신설 지하 구체를 구축하기 위한 공비의 감축을 도모하는 것이 가능한 지하 구조물의 시공 방법을 제공하는 것을 목적으로 한다.The present invention has been made in view of such a problem, and it is possible to reduce the load burden on a new underground sphere with respect to an existing underground sphere, and also to reduce the cost of constructing a new underground sphere. The purpose is to provide a construction method.

본 발명은 상기 목적을 달성하기 위해, 기존 지하 구체를 모두 해체 철거하는 일 없이 신설 지하 구체를 구축하는 신설 지하 구조물의 시공 방법에 있어서, 해당 기존 지하 구체의 내주면에 유동화 토양(soil)을 충전하여 유동화 토양 벽을 구축하고, 해당 유동화 토양 벽의 내주면에 신설 콘크리트 구체를 구축하는 것을 특징으로 하는 신설 지하 구조물의 시공 방법을 제공하는 것이다.In order to achieve the above object, the present invention provides a method for constructing a new underground structure without dismantling and removing all existing underground spheres, by filling fluidized soil in the inner circumferential surface of the existing underground sphere. It is to provide a construction method of a new underground structure, characterized in that the fluidized soil wall is constructed, and a new concrete sphere is built on the inner circumferential surface of the fluidized soil wall.

또, 본 발명은 상기 목적을 달성하기 위해, 기존 지하 구체를 모두 해체 철거하는 일 없이 해당 기존 지하 구체의 일부를 이용하여 신설 지하 구체를 구축하는 신설 지하 구조물의 시공 방법에 있어서, 해당 기존 지하 구체의 내주면에 해당 기존 지하 구체와 소정 간격을 두고 제 1 형틀(거푸집)체를 입설(세워 설치)하고, 해당 기존 지하 구체와 해당 제 1 형틀체의 사이에 유동화 토양을 충전하여 유동화 토양 벽을 구축하고, 해당 유동화 토양 벽의 내주면에 해당 유동화 토양 벽과 소정 간격을 두고 제 2 형틀체를 입설하고, 해당 유동화 토양 벽과 해당 제 2 형틀체의 사이에 콘크리트를 타설하여 신설 콘크리트 구체를 구축하는 것을 특징으로 하는 신설 지하 구조물의 시공 방법을 제공하는 것이다.In addition, the present invention, in order to achieve the above object, in the construction method of a new underground structure to build a new underground sphere using a part of the existing underground sphere without dismantling and removing all the existing underground sphere, the existing underground sphere Build a fluidized soil wall by placing (installing) the first mold (form) on the inner circumferential surface of the mold at a predetermined distance from the existing underground sphere, and filling the fluidized soil between the existing underground sphere and the first mold. And placing a second mold body on the inner circumferential surface of the fluidized soil wall at a predetermined distance from the fluidized soil wall, and placing concrete between the fluidized soil wall and the second mold body to construct a new concrete sphere. It is to provide a construction method of a new underground structure characterized in.

이 경우, 상기 제 1 틀체와 상기 제 2 틀체는 세퍼레이터에 의해서 그 입설 상태가 유지되어 있는 것이 바람직하고, 또, 상기 제 1 틀체와 상기 제 2 틀체는 강제의 판형상의 재질을 정면 대략 방형상이고 또한 단면 대략 각파(角波)형상으로 절곡<접어 구부림> 절단 가공하여 성형한 형틀 패널인 것이 바람직하다.In this case, it is preferable that the erected state of the said 1st frame and the said 2nd frame is hold | maintained by a separator, and the said 1st frame and the said 2nd frame are substantially square in front of the plate | board material of a steel plate. Moreover, it is preferable that it is a mold panel shape | molded by carrying out the bending | flexing | cutting process by bending | folding in the shape of a substantially angular wave shape of a cross section.

본 발명에 따르면, 신설 지하 구조물을 구축할 때에, 기존 지하 구체에 형성하는 신설 지하 구체를, 유동화 토양 벽과 신설 콘크리트 구체에 의해서 구축하고 있기 때문에, 신설 지하 구체를 신설 콘크리트 구체만으로 구축하는 것보다도, 콘크리트의 사용량을 줄일 수 있다. 또, 유동화 토양은 콘크리트보다 비중이 낮기 때문에, 기존 지하 구체에 관한 신설 지하 구체의 하중 부담을 저감시킬 수 있다.According to the present invention, when constructing a new underground structure, the new underground sphere formed in the existing underground sphere is constructed by the fluidized soil wall and the new concrete sphere, so that the new underground sphere is constructed only by the new concrete sphere. This can reduce the amount of concrete used. In addition, since the fluidized soil has a specific gravity lower than that of concrete, it is possible to reduce the load burden on the new underground spheres related to the existing underground spheres.

도 1은 본 실시형태에 관한 신설 지하 구조물의 구성을 나타내는 도면,
도 2는 본 실시형태에서 사용하는 형틀 패널의 개략 구성도,
도 3은 도 2에 나타내는 형틀 패널의 A-A 단면을 나타낸 도면,
도 4는 도 1에 나타내는 지하 구조물의 X-X 단면을 나타낸 횡단면도,
도 5는 본 실시형태에 관한 신설 지하 구조물의 시공 방법의 수순을 나타낸 흐름도,
도 6은 본 실시형태에 관한 신설 지하 구조물의 시공 방법의 개략도,
도 7은 본 실시형태에 관한 신설 지하 구조물의 시공 방법의 개략도,
도 8은 본 실시형태에 관한 신설 지하 구조물의 시공 방법의 개략도,
도 9는 본 실시형태에 관한 신설 지하 구조물의 시공 방법의 개략도,
도 10은 본 실시형태에 관한 신설 지하 구조물의 시공 방법의 개략도,
도 11은 본 실시형태에 관한 신설 지하 구조물의 시공 방법의 개략도.
BRIEF DESCRIPTION OF THE DRAWINGS The figure which shows the structure of the newly built underground structure which concerns on this embodiment.
2 is a schematic configuration diagram of a mold panel used in the present embodiment;
3 is a view showing an AA cross section of the mold panel shown in FIG.
4 is a cross-sectional view showing a XX cross section of the underground structure shown in FIG. 1;
5 is a flowchart showing a procedure of a construction method of a newly installed underground structure according to the present embodiment;
6 is a schematic view of a construction method of a newly installed underground structure according to the present embodiment;
7 is a schematic view of a construction method of a newly installed underground structure according to the present embodiment;
8 is a schematic view of a construction method of a newly installed underground structure according to the present embodiment;
9 is a schematic view of a construction method of a new underground structure according to the present embodiment;
10 is a schematic view of a construction method of a newly installed underground structure according to the present embodiment;
11 is a schematic view of a construction method of a new underground structure according to the present embodiment.

이하, 도면을 참조하면서 본 실시형태에 관한 신설 지하 구조물의 시공 방법에 대해 설명한다.Hereinafter, the construction method of the newly built underground structure which concerns on this embodiment is demonstrated, referring drawings.

도 1은 본 실시형태에 관한 시공 방법에 의해서 구축되는 지하 구조물의 구조를 나타내는 종단 측면도이다.1 is a longitudinal side view showing the structure of an underground structure constructed by the construction method according to the present embodiment.

도 1에 나타내는 바와 같이, 본 실시형태에 관한 시공 방법에 의해서 구축되는 지하 구조물은 거주 공간으로서 이용 가능한 지하실과, 배관 설비 등을 수용하기 위한 지하 시설인 지하 피트를 갖는 신설 지하 구조물로써, 기존 지하 콘크리트 구체(200)와, 신설 지하 콘크리트 구체(400)의 사이에 유동화 토양 벽(300)을 배치하도록 구축되어 있다.As shown in FIG. 1, the underground structure constructed by the construction method which concerns on this embodiment is a new underground structure which has a basement which can be used as a living space, and an underground pit which is an underground facility for accommodating piping facilities, etc. It is constructed to arrange the fluidized soil wall 300 between the concrete sphere 200 and the new underground concrete sphere 400.

또한, 이 지하 구조물에 있어서의 지하 피트는 배관 설비 등을 수용하기 위한 지하 공간으로서, 배관 설비 등을 지하실에 수용하는 공간이 있으면, 지하 피트를 마련할 필요는 없다. 또, 도 1에 나타내는 지하 구조물에서는 지하 1층만의 지하 구조물로 되어 있지만, 지하의 층수는 몇 층이어도 좋고, 그 경우에 있어서도 구성 및 시공 방법에는 아무런 변화는 없다.In addition, the underground pit in this underground structure is an underground space for accommodating plumbing facilities, and if there is a space for accommodating plumbing facilities in the basement, it is not necessary to provide an underground pit. In addition, in the underground structure shown in FIG. 1, although it is an underground structure of only one underground level, the number of underground floors may be sufficient, and even in that case, there is no change in a structure and a construction method.

기존 지하 구조물을 해체할 때, 구조물을 구축하고 있던 기둥 등은 해체 철거되고, 기존 빔(201), 기존 내력벽(202), 기존 기초(기초/지중 빔)(203)로 이루어지는 기존 지하 콘크리트 구체(200)만이 잔존한 형태로 되어 있다.When dismantling the existing underground structure, the columns, etc., which were constructing the structure, are dismantled and dismantled, and the existing underground concrete sphere consisting of the existing beam 201, the existing bearing wall 202, and the existing foundation (base / ground beam) 203 ( Only 200 is in the remaining form.

이 기존 지하 콘크리트 구체(200)의 내측에, 유동화 토양 벽(300)을 구축한다. 이 유동화 토양 벽(300)은 유동화 토양(미리 공장에서 시멘트를 배합 관리한 슬러리형상의 뒤채움토로 펌프 타설 가능한 유동화된 뒤채움재)을 충전해서 구축되는 것이다. 구체적으로는 기존 지하 콘크리트 구체(200)의 내측에 소정의 간격을 두고 형틀 패널(500)을 박아 넣고, 이 기립 상태를 세퍼레이터(501)로 유지하고, 이 형틀 패널(500)과 기존 지하 콘크리트 구체(200)의 사이에 유동화 토양을 충전하고 고화하여 유동화 토양 벽(300)을 구축하는 것이다.Inside the existing underground concrete sphere 200, a fluidized soil wall 300 is constructed. The fluidized soil wall 300 is constructed by filling fluidized soil (a fluidized backfill material that can be pumped into a slurry-like backfill soil in which cement is managed in advance in a factory). Specifically, the mold panel 500 is driven at a predetermined interval inside the existing concrete concrete sphere 200, and the standing state is maintained by the separator 501, and the mold panel 500 and the existing underground concrete sphere are kept. The fluidized soil is filled and solidified between 200 to build the fluidized soil wall 300.

그리고, 유동화 토양 벽(300)의 내측에, 새로운 구체, 즉 신설 지하 콘크리트 구체(400)를 구축한다. 신설 지하 콘크리트 구체(400)는 지하실의 바닥 및 지하 피트의 천정을 구성하는 신설 슬라브(401)와, 신설 빔(402)과, 신설 벽(403)으로 구성된다. 이 신설 지하 콘크리트 구체(400)는 유동화 토양 벽(300)의 내측에 새로이 형틀 패널(600)을 소정의 간격을 두고 박아 넣고, 이 형틀 패널(600)과 전술한 유동화 토양 벽(300)의 형틀 패널(500)을 세퍼레이터(601)로 연결하여 기립 상태를 유지하고, 유동화 토양 벽(300)의 형틀 패널(500)과 새로운 형틀 패널(600)의 사이에 콘크리트를 타설하여 구축하는 것이다.Then, inside the fluidized soil wall 300, a new sphere, that is, a new underground concrete sphere 400, is constructed. The new underground concrete sphere 400 is composed of a new slab 401, a new beam 402, and a new wall 403 constituting a ceiling of a basement floor and an underground pit. The newly formed underground concrete sphere 400 drives the mold panel 600 newly at predetermined intervals inside the fluidized soil wall 300, and the mold of the mold panel 600 and the fluidized soil wall 300 described above. The panel 500 is connected to the separator 601 to maintain the standing state, and the concrete is poured between the mold panel 500 of the fluidized soil wall 300 and the new mold panel 600 to be constructed.

도 2 및 도 3은 본 실시형태에 관한 지하 구조물의 시공 방법에 사용하는 형틀 패널(500, 600)의 구성을 나타내는 도면이다.FIG.2 and FIG.3 is a figure which shows the structure of the mold panels 500 and 600 used for the construction method of the underground structure which concerns on this embodiment.

도 2에 나타내는 바와 같이, 형틀 패널(500, 600)은 강제의 판형상의 재질을, 정면 대략 방형상이고 또한 단면 대략 각파형상으로 절곡하고, 절단 가공하여 성형한 매살(기초 공사 등에 사용한 가설부재를 철거하지 않고 그대로 매립해서 토사 등의 뒤채움을 하는 것)형의 형틀 패널이다. 이 형틀 패널(500)은 패널 강판을 단면 대략 각파형상으로 절곡함으로써, 서로 평행한 복수의 리지(ridge)(11)가 소정 간격으로 병설되고, 패널 자체의 강도를 보강하고 있다. 또, 패널 단면을 등변 각파형으로 성형함으로써, 특히 표면 또는 이면측으로부터의 힘에 대해 우수한 강도를 발휘할 수 있다.As shown in Fig. 2, the mold panels 500 and 600 are made of steel plate (for temporary foundations used for foundation work, etc.) formed by bending and cutting a steel plate material having a substantially rectangular front face and an approximately angular wave shape in cross section. It is a form panel of type) that is buried as it is without being removed and filled with earth and sand. In the mold panel 500, a panel steel sheet is bent in a substantially rectangular cross-sectional shape, so that a plurality of ridges 11 parallel to each other are arranged at predetermined intervals to reinforce the strength of the panel itself. In addition, by forming a panel cross section into an equilateral angular waveform, it is possible to exhibit particularly excellent strength with respect to the force from the front or back surface side.

또한, 본 실시형태에 있어서, 이 리지(11)의 형성 방향을 형틀 패널(500)의 길이 방향으로 하고, 형틀 패널(500)에 있어서 그 길이 방향에 수직인 방향을 폭 방향으로 한다.In addition, in this embodiment, the formation direction of this ridge 11 is made into the longitudinal direction of the mold panel 500, and in the mold panel 500, the direction perpendicular | vertical to the longitudinal direction is made into the width direction.

도면에 나타내는 바와 같이, 이 리지(11)는 상면(31)과, 이 상면(31)의 양 폭 방향으로 연이어 마련되어 있는 2면의 측면(32)에 의해 구성되어 있다. 또, 각 리지(11)간의 오목면에는 소정 간격마다, 복수의 폭 방향의 단면 볼록형상의 리브(12)와, 폭 방향의 단면 오목형상의 홈부(16)가, 리지(11)에 평행하게 반복 형성되어 있다.As shown in this figure, this ridge 11 is comprised by the upper surface 31 and the side surface 32 of the two surface provided in connection with the width direction of this upper surface 31 in both directions. In the concave surface between the ridges 11, a plurality of cross-sectional convex ribs 12 in the width direction and grooves 16 in the cross-sectional concave shape in the width direction are repeated in parallel with the ridges at predetermined intervals. Formed.

또한, 리지(11)의 패널 폭 방향의 양단, 즉 리브(12)와 그 리브(12)에 인접하는 홈부(16)의 사이의 경계선상에는 소정 길이의 잘라냄(13)이, 소정 간격으로 리지(11)와 평행하게 파선형상으로 마련되어 있다. 이 파선형상의 잘라냄(13)의 열을 따라 형틀 패널(500)을 소정의 각도로 절곡하는 것에 의해, 형틀의 코너부를 형성할 수 있도록 되어 있다. 또, 이 파선형상의 잘라냄(13)의 열을 따라, 형틀 패널(500)을 정역방향으로 수회 반복하여 절곡하는 것에 의해, 형틀 패널(500)을 원하는 사이즈로 용이하게 절단할 수 있도록 되어 있다.Moreover, the cutting 13 of predetermined length ridges at predetermined intervals on the both ends of the panel width direction of the ridge 11, ie, on the boundary line between the rib 12 and the groove part 16 adjacent to the rib 12. It is provided in broken line parallel to (11). The corner part of the mold can be formed by bending the mold panel 500 at a predetermined angle along the row of the broken lines 13. In addition, the mold panel 500 can be easily cut to a desired size by repeatedly bending the mold panel 500 in the forward / reverse direction along the row of the broken line cutouts 13. .

이 잘라냄(13)은 형틀 패널(500)의 표리에 관통한 미소 폭, 소정 길이의 잘라냄이다. 이 잘라냄(13)은 콘크리트의 타설이나 유동화 토양의 충전 후에, 그 잘라냄(13)으로부터, 콘크리트나 유동화 토양에 포함되는 여분의 수분이 배출 가능한 정도이며, 액상의 콘크리트나 유동화 토양이 누출하지 않을 정도의 폭(간극) 및 길이로 형성되어 있다.This cutting | disconnection 13 is the cutting | disconnection of the small width and predetermined length which penetrated the front and back of the mold panel 500. FIG. This cutting 13 is the extent to which the excess moisture contained in the concrete and the fluidized soil can be discharged from the cutting 13 after the concrete is poured or the filling of the fluidized soil, and liquid concrete or the fluidized soil does not leak. It is formed in the width | variety (gap) and length of the degree which it does not have.

리지(11)의 상면(31)측에는 복수의 덮개형상의 덮개부(14)가 마련되어 있다. 이 덮개부(14)는 개방시키는 것에 의해, 세퍼레이터 삽입 구멍을 형성한다. 이 세퍼레이터 삽입 구멍에, 전술한 세퍼레이터(501, 601)를 삽입하여 소정 방법으로 체결함으로써, 형틀 패널(500, 600)의 입설 상태를 유지할 수 있다.On the upper surface 31 side of the ridge 11, a plurality of lid-shaped lid portions 14 are provided. The cover portion 14 is opened to form a separator insertion hole. By inserting the above-mentioned separators 501 and 601 into this separator insertion hole and fastening by a predetermined method, the standing state of the mold panels 500 and 600 can be maintained.

도 4는 도 1의 X-X단면을 나타내는 도면이다.4 is a cross-sectional view taken along the line X-X of FIG.

도면에 나타내는 바와 같이, 신설 지하 구조물은 기존 지하 콘크리트 구체(200)와, 신설 지하 콘크리트 구체(400)의 사이에 유동화 토양 벽(300)을 갖는 구조로 되어 있다.As shown in the figure, the newly built underground structure has a structure having a fluidized soil wall 300 between the existing underground concrete sphere 200 and the newly built underground concrete sphere 400.

유동화 토양 벽(300)을 구축하기 위해서는 우선, 형틀 패널(500)을 박아 넣고, 다음에, 기존 지하 콘크리트 구체(200)에 앵커(307)를 박아 넣고, 이 박힌 앵커(307)에 세퍼레이터(501)를 연결하며, 이 세퍼레이터(501)에 의해서 형틀 패널(500)을 기립 상태로 유지하고, 이 상태에 있어서 유동화 토양을 충전하고 구축한다.In order to build the fluidized soil wall 300, first, the mold panel 500 is driven, and then, the anchor 307 is driven into the existing underground concrete sphere 200, and the separator 501 is embedded in the embedded anchor 307. ), The mold panel 500 is held in the standing state by the separator 501, and the fluidized soil is filled and constructed in this state.

형틀 패널(500)과 세퍼레이터(501)의 접속 개소에는 양단이 구부림 가공된 와셔(301, 302)가 마련되어 있다. 와셔(301)는 형틀 패널(500)의 이면측(기존 지하 콘크리트 구체(200)측)에 마련되어 있고, 너트(303)에 의해서 형틀 패널(500)에 체결된다. 와셔(302)는 형틀 패널(500)의 표면측(신설 지하 콘크리트 구체(400)측)에 마련되어 있다. 와셔(302)는 긴쪽 방향으로 긴 와셔이며, 형틀 패널(500)로부터 돌출된 세퍼레이터(501)의 선단에 긴 너트(304)에 의해서 체결된다. 그리고, 기존 지하 콘크리트 구체(200)와, 형틀 패널(500)의 사이에 유동화 토양을 충전하여, 유동화 토양 벽(300)을 구축한다.Washers 301 and 302 having both ends bent are provided at the connection point between the mold panel 500 and the separator 501. The washer 301 is provided on the back side of the mold panel 500 (the existing underground concrete sphere 200 side) and is fastened to the mold panel 500 by the nut 303. The washer 302 is provided on the surface side (new basement concrete sphere 400 side) of the mold panel 500. The washer 302 is a long washer in the longitudinal direction and is fastened by the long nut 304 to the tip of the separator 501 protruding from the mold panel 500. Then, the fluidized soil is filled between the existing underground concrete sphere 200 and the mold panel 500 to build the fluidized soil wall 300.

신설 지하 콘크리트 구체(400)는 전술한 바와 같이, 유동화 토양 벽(300)의 내측에 새로이 형틀 패널(600)을 소정의 간격을 두고 박아 넣고, 이 형틀 패널(600)과 유동화 토양 벽(300)의 형틀 패널(500)을 세퍼레이터(601)로 연결하여 기립 상태를 유지하고, 유동화 토양 벽(300)의 형틀 패널(500)과 새로운 형틀 패널(600)의 사이에 콘크리트를 타설하여 구축하는 것이다. 이 때, 긴 너트(304)에 세퍼레이터(601)의 일단을 연결시키고, 타단을 형틀 패널(600)에 연결하며, 형틀 패널(600)의 기립 상태를 유지시키고, 형틀 패널(600)의 표면측에 파이프(305)를 마련하여, 이것을 홈 타이(306)로 고정시킨다. 이 상태에서, 형틀 패널(500)과 형틀 패널(600)의 사이에 콘크리트를 타설함으로써, 신설 지하 콘크리트 구체(400)가 구축된다.As described above, the newly formed underground concrete sphere 400 is driven into the mold panel 600 at predetermined intervals inside the fluidized soil wall 300, and the mold panel 600 and the fluidized soil wall 300 are formed. The form panel 500 is connected to the separator 601 to maintain the standing state, and the concrete is poured between the form panel 500 and the new form panel 600 of the fluidized soil wall 300 to be constructed. At this time, one end of the separator 601 is connected to the long nut 304, the other end is connected to the mold panel 600, the standing state of the mold panel 600 is maintained, and the surface side of the mold panel 600 is maintained. The pipe 305 is provided in this and it is fixed by the groove tie 306. In this state, the new underground concrete sphere 400 is constructed by pouring concrete between the mold panel 500 and the mold panel 600.

도 5는 지하 구조물의 시공 수순을 나타낸 흐름도이고, 도 6∼도 11은 이 시행 수순에 의거하여 실행되는 본 실시형태에 관한 지하 구조물의 시공 방법을 나타내는 도면이다.Fig. 5 is a flowchart showing the construction procedure of the underground structure, and Figs. 6 to 11 are diagrams showing the construction method of the underground structure according to the present embodiment executed based on this trial procedure.

이하, 도 5의 시공 수순을 나타내는 흐름도에 의거하여, 도 6∼도 11을 참조하면서, 지하 구조물의 시공 방법에 대해 설명한다.Hereinafter, the construction method of an underground structure is demonstrated, referring FIGS. 6-11 based on the flowchart which shows the construction procedure of FIG.

또한, 도 6(a)는 기존 지하 콘크리트 구체의 일부를 철거한 후의 도면이고, 도 6(b)는 기존 지하 콘크리트 구체의 일부를 철거한 후, 지하 피트에 토사를 반입한 도면이며, 도 7(a)는 기존 지하 콘크리트 구체내에 토사를 반입한 도면이고, 도 7(b)는 기초의 일부에 신설 말뚝을 설치한 도면이며, 도 8(a)는 기존 내력벽과 기존 빔이 토압에 견디는 깊이까지 뒤채워진 토사를 제거하고, 흙막이용 절량 웨일(wale)의 설치를 실행하는 도면이고, 도 8(b)는 지하 피트에 유동화 토양 벽을 마련한 도면이며, 도 9(a)는 지하 피트에 신설 내압반(耐壓盤)의 콘크리트 구체를 마련한 도면이고, 도 9(b)는 지하 피트에 신설 콘크리트 기초, 슬라브를 마련한 도면이며, 도 10(a)는 흙막이용 절량 웨일의 해체 철거를 실행하는 도면이고, 도 10(b)는 지하실에 유동화 토양 벽을 마련한 도면이며, 도 11(a)는 지하실에 신설 콘크리트 구체용의 형틀 패널을 조립한 도면이고, 도 11(b)는 지하실에 신설 콘크리트 구체를 마련한 도면이다.In addition, Figure 6 (a) is a view after removing a part of the existing concrete concrete spheres, Figure 6 (b) is a view of bringing in the soil pit to the underground pit after removing a portion of the existing underground concrete spheres, Figure 7 (a) is a view in which the soil is brought into the existing underground concrete sphere, Figure 7 (b) is a view of installing a new pile on a part of the foundation, Figure 8 (a) is a depth that the existing bearing wall and the existing beam withstand the earth pressure Figure 6 (b) is a drawing of a fluidized soil wall in an underground pit, Figure 9 (a) is newly installed in an underground pit It is a figure which provided the concrete sphere of the pressure-resistant board, FIG. 9 (b) is a figure which installed the new concrete foundation and slab in the underground pit, and FIG. 10 (b) is a view of a fluidized soil wall in the basement. And, FIG. 11 (a) is a view of assembling a formwork panel for concrete for new concrete basement, Figure 11 (b) is a view prepared by the new concrete in concrete basement.

<기존 지하 콘크리트 구체의 일부의 철거><Removal of a part of existing underground concrete spheres>

우선, 도 6(a)에 나타내는 바와 같이, 지상 부분의 구조물을 철거한 후에, 기존 지하 콘크리트 구체(200)의 지하실 및 지하 피트에 구축된 기존 기둥(204)을 해체 철거하고, 지하실 및 지하 피트의 슬라브(205, 206)를 해체에 의해 개구를 마련하고(기존 빔(201)을 남기고 해체하여 토압을 받는 경우도 있음), 기존 내압반(208)의 일부를 해체하여 개구를 마련한다(스텝 S100). 그리고, 기존 기둥(204)의 해체 철거에 의해, 지하실 및 지하 피트에 신설 구체를 구축하기 위한 공간을 확보하는 동시에, 기존 빔(201)을 남기고 슬라브(205, 206)를 해체하여 개구를 마련하고, 작업 현장의 확보를 실행한다.First, as shown in FIG. 6 (a), after the structure of the ground portion is demolished, the existing pillar 204 constructed in the basement and the underground pit of the existing underground concrete sphere 200 is dismantled and removed, and the basement and the underground pit are removed. Open the slabs 205 and 206 by dismantling (in some cases, the original beam 201 may be dismantled and subjected to earth pressure), and a part of the existing pressure plate 208 is dismantled to prepare an opening (step). S100). In addition, by dismantling and removing the existing column 204, a space for constructing a new sphere in the basement and the underground pit is secured, while the slab 205 and 206 are dismantled to leave an existing beam 201 to prepare an opening. To secure the work site.

또한, 본 실시형태에 있어서, 기존 지하 콘크리트 구체(200)는 기존 빔(201)과, 기존 내력벽(202)과, 기존 기초(203)를 연속한 기존 외벽으로서, 지중으로부터의 토압을 지지하기 위한 흙막이 벽으로서 이용한다.In addition, in the present embodiment, the existing underground concrete sphere 200 is an existing outer wall in which the existing beam 201, the existing bearing wall 202, and the existing foundation 203 are continuous, for supporting earth pressure from the ground. It is used as a retaining wall.

<뒤채움 작업 및 신설 말뚝의 설치><Setting of backfill work and new pile>

다음에, 도 6(b)에 나타내는 바와 같이, 슬라브(205, 206)를, 기존 빔(201)을 남기고 해체하여 마련된 개구로부터 기존 지하 콘크리트 구체(200)의 지하 피트내에 토사를 반입하고, 도 7(a)에 나타내는 바와 같이, 지하실내에 토사를 반입하여, 기존 지하 콘크리트 구체(200)내를 토사로 뒤채움을 실행한다(스텝 S101). 이 뒤채움 작업에 의해, 흙막이 벽으로서 이용하고 있는 기존 지하 콘크리트 구체(200)에 가해지는 토압의 부담을 경감할 수 있다. 또, 뒤채움 작업에 의해서, 지상 부분에 중기(도시하지 않음)의 작업 장소의 확보와, 중기의 중량의 지지가 가능하게 되고, 이 중기에 의해, 도 7(b)에 나타내는 바와 같이, 기존 내압반(208)에 미리 개구된 구멍부(405)에 신설 말뚝(405a)의 설치를 실행할 수 있다(스텝 S102). 이 신설 말뚝(405a)은 기존 지하 콘크리트 구체(200)의 내측에 구축하는 신설 구체(주로 신설하는 벽)의 중량을 지지하기 위한 것이다.Next, as shown in FIG. 6 (b), the soil is introduced into the underground pits of the existing underground concrete sphere 200 from the opening provided by dismantling the slabs 205 and 206, leaving the existing beam 201. As shown to 7 (a), earth and sand are carried in in a basement, and backfilling is performed inside the existing underground concrete sphere 200 with earth and sand (step S101). By this backfilling operation, the burden of earth pressure applied to the existing underground concrete sphere 200 used as the wall of the soil can be reduced. In addition, the backfilling operation enables securing of a work place of heavy machinery (not shown) and support of the weight of heavy machinery in the ground portion. As shown in FIG. Installation of the new pile 405a can be performed in the hole 405 previously opened in the pressure-resistant plate 208 (step S102). This new pile 405a is for supporting the weight of the new sphere (mainly a new wall) built inside the existing underground concrete sphere 200.

또한, 신설 말뚝(405a)의 설치는 기존 지하 콘크리트 구체(200)의 기존 기초(203)와 기존 내압반(208)의 내압 성능과 지반의 지지력인 지내력(地耐力)에 따라서는 필요없다.In addition, the installation of the new pile 405a is not necessary depending on the pressure resistance performance of the existing foundation 203 and the existing pressure plate 208 of the existing underground concrete sphere 200 and the bearing capacity of the ground.

<뒤채움의 토사의 철거 및 흙막이용 절량 웨일의 설치><Demolition of earth and sand of backfilling and setting of saving quantity wale for mudguard>

다음에, 도 8(a)에 나타내는 바와 같이, 신설 말뚝(405a)의 설치 후, 뒤채움에 사용한 토사를 지하실내 및 지하 피트내로부터 기존 내력벽(202)과 기존 빔(201)이 토압에 견디는 깊이까지 뒤채운 토사를 제거하고(스텝 S103), 잔존하는 기존 빔(201)을 철거한다. 다음에, 기존 빔(201)의 해체 철거와 뒤채움에 사용한 토사의 제거에 의해서, 주위의 지중으로부터 기존 지하 콘크리트(200)에 가해지는 토압이 증대하기 때문에, 일시적인 보조로서 흙막이용 절량 웨일(406)을 기존 빔(201)의 일부분에 설치한다(스텝 S104). 흙막이용 절량 웨일(406)은 단면이 H형인 흙막이 H강을 사용한다. 이것에 의해, 기존 지하 콘크리트 구체(200)에 가해지는 토압을 흙막이용 절량 웨일(406)에 의해서 저감시킬 수 있다. 흙막이용 절량 웨일(406)의 설치 후에, 나머지의 뒤채움에 사용한 토사를 제거한다(스텝 S105).Next, as shown in Fig. 8 (a), after the installation of the new pile 405a, the earth-bearing wall 202 and the existing beam 201 withstand the earth pressure from the basement and the underground pit from the earth and sand used for backfilling. The soil piled up to the depth is removed (step S103), and the existing beam 201 remaining is removed. Next, the earth pressure applied to the existing underground concrete 200 from the surrounding ground increases by the removal of the earth and sand used for dismantling removal and backfilling of the existing beam 201. ) Is installed in a portion of the existing beam 201 (step S104). Digging wale 406 for mud use a mud H steel having a cross section of H type. Thereby, the earth pressure applied to the existing underground concrete sphere 200 can be reduced by the mud-proofing wale 406. After installation of the retaining cut wale 406, the earth and sand used for the remaining backfill is removed (step S105).

<지하 피트의 유동화 토양 벽의 구축><Construction of fluidized soil walls of underground pits>

다음에, 도 8(b)에 나타내는 바와 같이, 주위의 지중으로부터의 토압을 기존 지하 콘크리트 구체(200)와 흙막이용 절량 웨일(406)로 지지한 상태에서, 지하 피트에 유동화 토양 벽(300)을 구축한다. 이 유동화 토양 벽(300)을 구축하기 위해, 우선, 지하 피트의 벽으로 되어 있는 기존 기초(203)에 복수의 앵커(307)를 박아 넣고, 이 앵커(307)의 각각에 세퍼레이터(501)를 연결시킨다(스텝 S106). 다음에, 전술한 형틀 패널(500)을 기존 지하 콘크리트 구체(200)의 내측의 형상에 맞추도록 해서 조립하고, 이 형틀 패널(500)을 세퍼레이터(501)에 의해서 기립 상태를 유지시킨다(스텝 S107). 또, 형틀 패널(500)과 세퍼레이터(501)는 전술한 바와 같이, 와셔(301, 302)와 너트(303)로 체결함으로써 고정되어 있다.Next, as shown in FIG. 8 (b), the fluidized soil wall 300 is placed on the underground pit in a state where the earth pressure from the surrounding ground is supported by the existing underground concrete sphere 200 and the quasi-toning wale 406. Build it. In order to build this fluidized soil wall 300, first, a plurality of anchors 307 are driven into an existing foundation 203 which is a wall of an underground pit, and a separator 501 is attached to each of these anchors 307. FIG. It connects (step S106). Next, the above-mentioned form panel 500 is assembled so as to conform to the shape of the inside of the existing underground concrete sphere 200, and the form panel 500 is maintained by the separator 501 (step S107). ). In addition, the mold panel 500 and the separator 501 are fixed by fastening with the washers 301 and 302 and the nut 303 as mentioned above.

다음에, 기존 기초(203)와 형틀 패널(500)의 사이에 유동화 토양을 충전하여 경화시키는 것에 의해 유동화 토양 벽(300)을 지하 피트내에 구축한다(스텝 S108). 여기서, 사용하는 유동화 토양은 미리 공장에서 시멘트를 배합 관리한 슬러리형상의 뒤채움 흙이며, 생 콘크리트 믹서차로 운반해서 펌프 타설 가능한 뒤채움 흙이다. 그리고, 유동화 토양 벽(300)을 구축할 때에, 형틀 패널(500)을 사용함으로써, 이 형틀 패널(500)에 마련된 잘라냄(13)에 의해서 여분의 수분을 배출할 수 있고, 유동화 토양의 경화 시간을 단축시키는 것이 가능하다.Next, the fluidized soil wall 300 is constructed in the underground pit by filling and hardening the fluidized soil between the existing foundation 203 and the mold panel 500 (step S108). Here, the fluidized soil to be used is a slurry-type backfilling soil in which cement is pre-mixed and managed in a factory, and is a backfilling soil which can be pumped and poured into a live concrete mixer car. And when constructing the fluidized soil wall 300, by using the mold panel 500, the excess moisture can be discharged by the cutting 13 provided in this mold panel 500, and hardening of the fluidized soil is carried out. It is possible to shorten the time.

<지하 피트의 신설 콘크리트 구체의 구축><Building of new concrete sphere of underground pit>

다음에, 도 9(a)에 나타내는 바와 같이, 지하 피트의 기존 내압반(208)상에 신설 내압반(407)을 구축하기 위한 철근(도시하지 않음)을 조립하고(스텝 S109), 신설 내압반(407)을 구축하기 위한 콘크리트를 타설한다(스텝 S110). 다음에, 도 9(b)에 나타내는 바와 같이, 신설 슬라브(401) 및 신설 기초(기초/지중 빔)(404)를 구축하기 위해, 유동화 토양 벽(300)의 내측에 형틀 패널(600)을 설치한다(스텝 S111). 우선, 유동화 토양 벽(300)의 내측에 철근을 조립하고(스텝 S112), 세퍼레이터(601)를 형틀 패널(500)로부터 돌출된 세퍼레이터(501)에 연결시키고, 이 세퍼레이터(601)에 의해서 조립한 형틀 패널(600)을 기립 상태로 유지시킨다. 또, 지하 피트용의 신설 슬라브(401)를 구축하기 위해, 형틀 패널(600)을 지지기둥으로 지지하면서, 슬라브의 형상으로 되도록, 형틀 패널(600)을 마련한다. 이 때, 형틀 패널(600)에 마련되어 있는 잘라냄(13)을 따라 용이하게 형틀 패널(600)을 절곡할 수 있기 때문에, 슬라브 형상으로 형틀 패널(600)을 조립할 수 있다. 또, 기립 상태로 유지된 형틀 패널(600)과 슬라브 형상으로 조립한 형틀 패널(600)은 서로 연이어 마련되도록 해서 설치되어 있다.Next, as shown in Fig. 9 (a), a reinforcing bar (not shown) for assembling the new internal pressure plate 407 is assembled on the existing internal pressure plate 208 of the underground pit (step S109), and the new internal pressure is obtained. Concrete for pouring the board 407 is poured (step S110). Next, as shown in FIG. 9 (b), in order to construct the new slab 401 and the new foundation (base / ground beam) 404, the mold panel 600 is placed inside the fluidized soil wall 300. It installs (step S111). First, the reinforcing bar is assembled inside the fluidized soil wall 300 (step S112), the separator 601 is connected to the separator 501 protruding from the mold panel 500, and assembled by this separator 601. The mold panel 600 is kept in an upright state. Moreover, in order to build the new slab 401 for underground pits, the mold panel 600 is provided so that it may become a slab shape, supporting the mold panel 600 with a support pillar. At this time, since the mold panel 600 can be easily bent along the cutting 13 provided in the mold panel 600, the mold panel 600 can be assembled into a slab shape. Moreover, the mold panel 600 hold | maintained in the standing state and the mold panel 600 assembled in the slab shape are provided so as to be mutually provided.

이와 같이 해서 설치된 형틀 패널(600)에는 콘크리트를 타설했을 때에 형틀 패널(600)에 가해지는 즉압을 지지하기 위해, 전술한 바와 같이, 형틀 패널(600)의 표면측에 형틀 패널(600)의 긴쪽 방향으로 긴 파이프(305)를 홈 타이(306)로 고정시킨다. 다음에, 콘크리트를 타설하는 것에 의해 신설 슬라브(401) 및 신설 기초(404)를 구축한다(스텝 S113). 이것에 의해, 지하 피트에 신설 콘크리트 기초 구체(400)를 구축할 수 있다.In order to support the instantaneous pressure applied to the mold panel 600 when concrete is poured into the mold panel 600 installed in this way, as described above, the longer side of the mold panel 600 is placed on the surface side of the mold panel 600. Direction pipe 305 is secured with a groove tie 306. Next, the new slab 401 and the new foundation 404 are constructed by pouring concrete (step S113). Thereby, the newly built concrete foundation sphere 400 can be built in the underground pit.

또, 신설 콘크리트 구체(400)를 구축했을 때, 형틀 패널(600)에 마련되어 있는 잘라냄(13)은 콘크리트를 타설했을 때에, 콘크리트의 누출을 방지하는 동시에, 콘크리트중의 여분의 수분을 배출할 수 있다.In addition, when the new concrete sphere 400 is constructed, the cutting 13 provided in the mold panel 600 prevents the leakage of concrete and discharges excess moisture in the concrete when the concrete is poured. Can be.

<지하실의 유동화 토양 벽의 구축><Construction of fluidized soil wall of basement>

다음에, 도 10(a)에 나타내는 바와 같이, 기존 빔(201)에 설치되어 있는 흙막이용 절량 웨일(406)을 해체 철거하고(스텝 S114), 도 10(b)에 나타내는 바와 같이, 지하실에 유동화 토양 벽(300)을 구축한다.Next, as shown in FIG. 10 (a), the earthquake-saving wale 406 provided in the existing beam 201 is dismantled and removed (step S114), and as shown in FIG. 10 (b), in the basement. Construct a fluidized soil wall 300.

우선, 기존 지하 콘크리트 구체(200)의 기존 빔(201)과 기존 내력벽(202)에, 복수의 앵커(307)를 박아 넣고, 각각의 앵커(307)에 세퍼레이터(501)를 연결시킨다(스텝 S115). 다음에, 지하 피트에 설치한 형틀 패널(500)에 연이어 마련하도록 해서 형틀 패널(500)을 조립하고, 세퍼레이터(501)에 의해서 기립 상태를 유지시킨다(스텝 S116). 이 때, 형틀 패널(500)과 세퍼레이터(501)는 와셔(301, 302)와 너트(303)로 체결하여 고정된다.First, a plurality of anchors 307 are driven into the existing beam 201 and the existing bearing wall 202 of the existing underground concrete sphere 200, and the separator 501 is connected to each anchor 307 (step S115). ). Next, the mold panel 500 is assembled so as to be provided in succession to the mold panel 500 provided in the underground pit, and the standing state is maintained by the separator 501 (step S116). At this time, the mold panel 500 and the separator 501 are fixed by fastening with the washers 301 and 302 and the nut 303.

그리고, 기존 지하 콘크리트 구체(200)와 형틀 패널(500)의 사이에 유동화 토양을 충전하여, 유동화 토양 벽(300)을 구축한다(스텝 S117). 이것에 의해, 지하 피트에 구축한 유동화 토양 벽(300)과, 지하실에 구축한 유동화 토양 벽(300)이 연속된 1개의 벽으로서 구축된다. 그리고, 이 유동화 토양 벽(300)의 하중은 기존 지하 콘크리트 구체(200)를 구성하는 기존 빔(201), 기존 내력벽(202), 기존 기초(203)의 일부가 지지한다.Then, the fluidized soil is filled between the existing underground concrete sphere 200 and the mold panel 500 to build the fluidized soil wall 300 (step S117). Thereby, the fluidized soil wall 300 constructed in the underground pit and the fluidized soil wall 300 constructed in the basement are constructed as one continuous wall. The load of the fluidized soil wall 300 is supported by a portion of the existing beam 201, the existing bearing wall 202, and the existing foundation 203 constituting the existing underground concrete sphere 200.

<지하실의 신설 콘크리트 구체의 구축><Building of new concrete sphere of basement>

다음에, 도 11(a)에 나타내는 바와 같이, 지하 피트에 구축한 신설 지하 콘크리트 구체(400)의 상부에, 우선, 신설 지하 콘크리트 구체(400)로 되는 기둥, 빔, 벽, 바닥을 구축하기 위한 철근을 조립한다(스텝 S118). 다음에, 지하실용으로 구축한 유동화 토양 벽(300)의 형틀 패널(500)로부터 돌출된 세퍼레이터(501)에 세퍼레이터(601)를 연결시키고(스텝 S119), 이 세퍼레이터(601)에 의해서 형틀 패널(600)을 기립 상태로 유지시킨다. 그리고, 지하실용의 신설 슬라브(401) 및 신설 빔(402)을 구축하기 위한 형틀 패널(600)을 조립한다(스텝 S120). 이 형틀 패널(600)은 지지기둥에 의해서 지지되어 있다.Next, as shown to Fig.11 (a), the column, the beam, the wall, and the floor which become the new underground concrete sphere 400 are first constructed on the upper part of the new underground concrete sphere 400 built in the underground pit. Assemble the reinforcing bar (step S118). Next, the separator 601 is connected to the separator 501 protruding from the mold panel 500 of the fluidized soil wall 300 constructed for basement (step S119), and the mold panel (601) is connected by this separator 601. 600) is standing up. Then, the mold panel 600 for building the new slab 401 and the new beam 402 for the basement is assembled (step S120). The mold panel 600 is supported by a support column.

또한, 기립 상태로 유지된 형틀 패널(600)과, 슬라브 및 빔의 형상으로 조립된 형틀 패널(600)은 연속된 형틀 패널(600)로 되도록 연결시켜 조립한다.In addition, the mold panel 600 maintained in the standing state and the mold panel 600 assembled in the shape of the slab and the beam are assembled by connecting to form the continuous mold panel 600.

다음에, 신설 슬라브(401)용의 철근을 조립하고(스텝 S121), 유동화 토양 벽(300)과 형틀 패널(600)의 사이에 콘크리트를 타설한다(스텝 S122). 이것에 의해, 지하실용의 신설 콘크리트 구체(400)를 구축할 수 있다. 또, 지하 피트에 구축된 신설 콘크리트 구체(400)와, 지하실에 구축된 신설 콘크리트 구체(400)는 연속된 신설 콘크리트 구체로서, 이 구체의 하중은 신설 말뚝(405a)에 의해서 지지된다.Next, reinforcing bars for the newly formed slab 401 are assembled (step S121), and concrete is poured between the fluidized soil wall 300 and the mold panel 600 (step S122). Thereby, the new concrete sphere 400 for basements can be constructed. Moreover, the new concrete sphere 400 constructed in the underground pit and the new concrete sphere 400 constructed in the basement are continuous new concrete spheres, and the load of this sphere is supported by the new pile 405a.

이상의 설명으로부터, 본 실시형태에 관한 지하 구조물의 시공 방법은 기존 지하 콘크리트 구체를 해체하는 일 없이, 이 기존 지하 콘크리트 구체를 흙막이 벽으로서 이용하고, 내측에, 유동화 토양 벽과, 신설 콘크리트 구체를 구축함으로써, 신설 지하 구조물을 시공할 수 있다.From the above description, in the method of constructing the underground structure according to the present embodiment, the existing underground concrete sphere is used as a retaining wall without dismantling the existing underground concrete sphere, and the fluidized soil wall and the new concrete sphere are constructed inside. By doing so, a new underground structure can be constructed.

그리고, 기존 지하 콘크리트 구체의 내측에 구축되는 유동화 토양 벽과 신설 콘크리트 구체는 형틀 패널을 사이에 두고, 각각이 독립되어 있고, 유동화 토양 벽의 하중은 기존 지하 콘크리트 구체와 접하고 있는 부분에서 지지할 수 있고, 신설 콘크리트 구체의 하중은 사전에 마련된 신설 말뚝이나 기존 지하 콘크리트 구체의 기초 부분에서 지지할 수 있다.In addition, the fluidized soil walls and the new concrete spheres built inside the existing underground concrete spheres have a frame panel between them, each of which is independent, and the load of the fluidized soil walls can be supported at the part facing the existing underground concrete spheres. In addition, the load of the new concrete sphere can be supported at the foundation of the new pile or the existing underground concrete sphere prepared in advance.

이것에 의해, 유동화 토양 벽과 신설 콘크리트 구체의 하중을 기존 지하 콘크리트 구체로 분산해서 지지시킬 수 있기 때문에, 기존 지하 콘크리트 구체가 지지하는 부담을 경감할 수 있다.As a result, the load of the fluidized soil wall and the new concrete sphere can be dispersed and supported by the existing underground concrete sphere, thereby reducing the burden of supporting the existing underground concrete sphere.

또, 기존 지하 콘크리트 구체와 신설 지하 콘크리트 구체의 사이에 유동화 토양 벽을 마련함으로써, 본래, 기존 지하 콘크리트 구체에 직접, 신설 지하 콘크리트 구체를 마련하는 공법에 대해, 유동화 토양 벽의 존재에 의해 신설 지하 콘크리트 구체의 두께를 얇게 할 수 있기 때문에, 콘크리트의 양을 줄일 수 있다.In addition, by providing a fluidized soil wall between an existing underground concrete sphere and a new underground concrete sphere, the construction method of providing a new underground concrete sphere directly to an existing underground concrete sphere will be established underground by the existence of a fluidized soil wall. Since the thickness of the concrete sphere can be made thin, the amount of concrete can be reduced.

또, 본 실시형태에 관한 형틀 패널은 패널 강판을 단면 대략 각파형상으로 절곡함으로써, 평행한 복수의 리지가 소정 간격으로 병설되기 때문에, 패널 자체의 강도를 보강할 수 있다. 이것에 의해, 유동화 토양을 충전한 경우나, 콘크리트를 타설한 경우에도 형틀 패널에 가해지는 즉압에 대해 충분히 견딜 수 있다. 그리고, 이 형틀 패널에 마련되어 있는 소정 길이의 잘라냄이 형틀 패널 자체가 절곡을 용이하게 하는 동시에, 유동화 토양이나 콘크리트의 누출을 방지하면서, 여분의 수분의 배출을 재촉할 수 있다. 이것에 의해, 코너에서의 형틀 패널이 절곡 가공을 용이하게 하면서, 유동화 토양 벽이나 신설 지하 콘크리트 구체의 구축을 빠르게 할 수 있다.In addition, in the mold panel according to the present embodiment, the plurality of parallel ridges are arranged side by side at predetermined intervals by bending the panel steel sheet into a substantially angular waveform in cross section, so that the strength of the panel itself can be reinforced. As a result, even when the fluidized soil is filled or when concrete is poured, it can withstand the immediate pressure applied to the mold panel. And the cutting of the predetermined length provided in this mold panel facilitates bending of the mold panel itself, and can prevent the excess moisture to be discharged while preventing the leakage of fluidized soil or concrete. Thereby, while a form panel in a corner makes bending process easy, the construction of a fluidized soil wall and a new underground concrete sphere can be quickened.

11 리지 12 리브
13 잘라냄 14 덮개부
16 홈부 31 상면
32 측면 200 기존 지하 콘크리트 구체
201 기존 빔 202 기존 내력벽
203 기존 기초(기초/지중 빔)
204 기존 기둥 205, 206 슬라브
208 기존 내압반 300 유동화 토양 벽
301, 302 와셔 303 너트
304 긴 너트 305 파이프
306 홈 타이 307 앵커
400 신설 지하 콘크리트 구체
401 신설 슬라브 402 신설 빔
403 신설 벽 404 신설 기초(기초/지중 빔)
405 신설 구멍 405a 신설 말뚝
406 흙막이용 절량 웨일 407 신설 내압반
500, 600 형틀 패널 501, 601 세퍼레이터
11 Ridges 12 Ribs
13 Cut 14 Cover
16 Groove 31 Top
32 side 200 existing underground concrete sphere
201 Conventional beam 202 Conventional bearing wall
203 Existing Foundations (Basic / Underground Beams)
204 Original Column 205, 206 Slabs
208 Existing Pressure Plate 300 Fluidized Soil Wall
301, 302 Washer 303 Nut
304 long nut 305 pipe
306 Home Tie 307 Anchor
400 new underground concrete spheres
401 new slab 402 new beam
403 new wall 404 new foundation (foundation / underground beam)
405 new hole 405a new pile
406 saving wall wedge 407 new pressure plate
500, 600 mold panel 501, 601 separator

Claims (4)

기존 지하 구체를 모두 해체 철거하는 일 없이 신설 지하 구체를 구축하는 신설 지하 구조물의 시공 방법에 있어서,
해당 기존 지하 구체의 내주면에 유동화 토양을 충전하여 유동화 토양 벽을 구축하고, 해당 유동화 토양 벽의 내주면에 신설 콘크리트 구체를 구축하는 것을 특징으로 하는 신설 지하 구조물의 시공 방법.
In the construction method of the new underground structure to build a new underground sphere without dismantling and removing all existing underground spheres,
A method of constructing a new underground structure, characterized by filling the fluidized soil on the inner circumferential surface of the existing underground sphere, and building a new concrete sphere on the inner circumferential surface of the fluidized soil wall.
기존 지하 구체를 모두 해체 철거하는 일 없이 해당 기존 지하 구체의 일부를 이용하여 신설 지하 구체를 구축하는 신설 지하 구조물의 시공 방법에 있어서,
해당 기존 지하 구체의 내주면에 해당 기존 지하 구체와 소정 간격을 두고 제 1 형틀체를 입설하고,
해당 기존 지하 구체와 해당 제 1 형틀체의 사이에 유동화 토양을 충전하여 유동화 토양 벽을 구축하고,
해당 유동화 토양 벽의 내주면에 해당 유동화 토양 벽과 소정 간격을 두고 제 2 형틀체를 입설하고,
해당 유동화 토양 벽과 해당 제 2 형틀체의 사이에 콘크리트를 타설하여 신설 콘크리트 구체를 구축하는 것을 특징으로 하는 신설 지하 구조물의 시공 방법.
In the construction method of a new underground structure that uses a portion of the existing underground sphere to build a new underground sphere without dismantling and removing all existing underground spheres,
The first frame is placed on the inner circumference of the existing underground sphere at a predetermined distance from the existing underground sphere.
Filling the fluidized soil between the existing subterranean sphere and the first mold body to build a fluidized soil wall,
The second mold is placed on the inner circumferential surface of the fluidized soil wall at a predetermined distance from the fluidized soil wall.
A method of constructing a new underground structure, wherein concrete is poured between the fluidized soil wall and the second frame to construct a new concrete sphere.
제 2 항에 있어서,
상기 제 1 틀체와 상기 제 2 틀체는 세퍼레이터에 의해서 그 입설 상태가 유지되어 있는 것을 특징으로 하는 신설 지하 구조물의 시공 방법.
The method of claim 2,
A method for constructing a new underground structure, wherein the first frame and the second frame are held in a standing state by a separator.
제 2 항 또는 제 3 항에 있어서,
상기 제 1 틀체와 상기 제 2 틀체는 강제의 판형상의 재질을 정면 대략 방형상이고 또한 단면 대략 각파형상으로 절곡 절단 가공하여 성형한 형틀 패널인 것을 특징으로 하는 신설 지하 구조물의 시공 방법.
The method according to claim 2 or 3,
And said first frame and said second frame are frame panels formed by bending and shaping a steel plate-like material having a substantially square front face and a substantially angular cross section.
KR1020127014104A 2010-03-19 2010-03-19 Method of constructing underground structure to be newly built KR20130006420A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2010/054796 WO2011114507A1 (en) 2010-03-19 2010-03-19 Method of constructing underground structure to be newly built

Publications (1)

Publication Number Publication Date
KR20130006420A true KR20130006420A (en) 2013-01-16

Family

ID=44648634

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020127014104A KR20130006420A (en) 2010-03-19 2010-03-19 Method of constructing underground structure to be newly built

Country Status (4)

Country Link
US (1) US20130008125A1 (en)
KR (1) KR20130006420A (en)
CN (1) CN102713080A (en)
WO (1) WO2011114507A1 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691311A (en) * 2012-06-06 2012-09-26 上海市城市建设设计研究总院 Precast assembled comprehensive pipe gallery fan house
CN102691310A (en) * 2012-06-06 2012-09-26 上海市城市建设设计研究总院 Precast assembled comprehensive pipe gallery downcast shaft
CN102691312A (en) * 2012-06-06 2012-09-26 上海市城市建设设计研究总院 Precast assembled pipeline combined shaft
CN103195090B (en) * 2013-04-15 2015-04-01 合肥建工集团有限公司 Soft-form-shaped strut structure formed by filling concrete through small hole on underground cavity
CN103775100B (en) * 2014-02-26 2016-05-04 华瀚管道系统科技有限公司 A kind of prefabricated assembled city integrated piping lane
JP6474653B2 (en) * 2015-03-13 2019-02-27 公益財団法人鉄道総合技術研究所 Connection structure for new and existing underground structures
JP6827256B2 (en) * 2016-08-02 2021-02-10 大成建設株式会社 How to rebuild the building
CN108203994A (en) * 2018-03-14 2018-06-26 中建四局第建筑工程有限公司 Along the method for subinverse construction technology on a kind of basement
CN115233700A (en) * 2022-08-29 2022-10-25 中建三局集团华南有限公司 Supporting beam conversion structure in foundation pit and construction method thereof

Family Cites Families (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3232022A (en) * 1961-11-21 1966-02-01 Morton M Rosenfeld Method of making a family blast shelter in a basement
US3416322A (en) * 1966-11-14 1968-12-17 Albert G. Bodine Sonic method and apparatus for implanting underground concrete walls
US4040216A (en) * 1975-05-19 1977-08-09 A & T Development Corporation Pillars, walls and buildings
US4263762A (en) * 1979-03-09 1981-04-28 Reed Stanley B Structural foundation assembly
US4508472A (en) * 1982-11-03 1985-04-02 Iowa State University Research Foundation, Inc. Method for controlling moisture-expansive clay supporting building foundations
CA1230461A (en) * 1987-02-20 1987-12-22 Stuart R. Walkinshaw Enclosure conditioned housing system
US5331782A (en) * 1988-12-12 1994-07-26 Wohlgemuth Franz F Basement enclosure
US5845456A (en) * 1989-03-06 1998-12-08 Read; Robert R. Basement waterproofing
US5035095A (en) * 1989-12-15 1991-07-30 Joseph Bevilacqua Basement wall structure to prevent water leakage
US5199233A (en) * 1990-05-23 1993-04-06 Misawa Homes Co. Ltd. Prefabricated concrete basement and process for constructing the same
US5301918A (en) * 1992-01-06 1994-04-12 Miller C B Form assembly for construction of concrete culverts
US5735090A (en) * 1995-08-08 1998-04-07 Papke; William Modular foundation construction and method
JP3283730B2 (en) * 1995-08-17 2002-05-20 柳原 実典 Formwork panel
JP3099040B2 (en) * 1996-12-20 2000-10-16 鹿島建設株式会社 Embankment culvert
US6606836B2 (en) * 1999-07-02 2003-08-19 Elmer Jefferson Miller Flexible liner for a concrete container
JP3728654B2 (en) * 2000-04-19 2005-12-21 清水建設株式会社 Building dismantling and construction methods
JP3956133B2 (en) * 2000-08-04 2007-08-08 柳原 実典 Formwork panel and panel holding member
US6991402B2 (en) * 2002-10-17 2006-01-31 Stormtrap Llc Methods and modules for an underground assembly for storm water retention or detention
US7017309B2 (en) * 2002-11-04 2006-03-28 Mcnett Thomas J Waterproof sealing system for a building foundation
US6990775B2 (en) * 2003-06-18 2006-01-31 Masonry Technology, Inc. Moisture drainage product, wall system incorporating such product and method therefore
EP1697616B1 (en) * 2003-10-28 2008-10-22 Daniel Warren Method for reparing in-ground tunnel structures
US20060096204A1 (en) * 2004-11-05 2006-05-11 Titan Structural L.L.C. Structural wall apparatuses, systems, and methods
US7313891B2 (en) * 2005-04-20 2008-01-01 Showers Robert J Wall finishing system
US7181888B1 (en) * 2006-01-12 2007-02-27 George Facaros Interconnected double hull construction for basements
US7905067B2 (en) * 2006-12-04 2011-03-15 Composite Panel Systems, Llc Support pads and support brackets, and structures supported thereby
JP4997207B2 (en) * 2008-10-01 2012-08-08 日本環境製造株式会社 Construction method for underground structures
US8375671B1 (en) * 2011-08-12 2013-02-19 Thrasher Basement Systems, Inc. System and method for providing basement wall stabilization

Also Published As

Publication number Publication date
CN102713080A (en) 2012-10-03
WO2011114507A1 (en) 2011-09-22
US20130008125A1 (en) 2013-01-10

Similar Documents

Publication Publication Date Title
KR20130006420A (en) Method of constructing underground structure to be newly built
JP4812324B2 (en) Retaining wall and its construction method
KR102234513B1 (en) Block type reinforcement retaining wall structure and constructing method for the same
KR101140378B1 (en) Reinforcement
KR20140121119A (en) PHC pile for Prestressed Concrete Member, Manufacturing method of PHC pile amd Construction method of retaining wall using PHC pile
KR101187170B1 (en) Application of under pinning method in remodeling
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
JP2000352296A (en) Method o constructing passage just under underground structure
JP4997207B2 (en) Construction method for underground structures
JP5228862B2 (en) Underground structure, construction method of underground structure
KR100808977B1 (en) Connecting structure of corner supporting beam for temporary soil sheathing work
CN212801564U (en) Foundation ditch steel sheet pile supporting construction
KR102355446B1 (en) Vertical underground structure and method for constructing the same
KR20210119935A (en) Underground structure using strut and method construturing the same
JP7386095B2 (en) Underground structure construction method
JP6860895B2 (en) Retaining wall and its construction method
KR100417487B1 (en) Filling crushed stone type retainingwall
JP6938198B2 (en) Construction method
KR101037502B1 (en) Reinforcement
JP6827256B2 (en) How to rebuild the building
KR101256311B1 (en) Structual deepening method
JP2571427B2 (en) Heavy load work floor method using existing underground structure
KR102197109B1 (en) Slab unit implanted with means for pressing pile and the method for carrying out the construction of the retaining wall using it
JP7248481B2 (en) deep foundation structure
KR100515971B1 (en) Soil retaining method using H-pile having large section

Legal Events

Date Code Title Description
WITN Application deemed withdrawn, e.g. because no request for examination was filed or no examination fee was paid