JP3728654B2 - Building dismantling and construction methods - Google Patents
Building dismantling and construction methods Download PDFInfo
- Publication number
- JP3728654B2 JP3728654B2 JP2000118578A JP2000118578A JP3728654B2 JP 3728654 B2 JP3728654 B2 JP 3728654B2 JP 2000118578 A JP2000118578 A JP 2000118578A JP 2000118578 A JP2000118578 A JP 2000118578A JP 3728654 B2 JP3728654 B2 JP 3728654B2
- Authority
- JP
- Japan
- Prior art keywords
- building
- lower structure
- floor slab
- dismantling
- existing building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Working Measures On Existing Buildindgs (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、既存建物を解体し、その後に同じ場所に新たに建物を構築するための建物の解体・構築方法に関するものである。
【0002】
【従来の技術】
周知のように、既存建物を解体し、その後に同じ場所に新たに建物を構築する際には、既存建物を上部構造および下部構造を含めて解体し、解体に伴い発生した解体材を除去するとともに、その後に同じ場所に、山留め等の仮設支保工を設置して、そこに新たに構築すべき建物の下部構造を施工し、さらに、下部構造の施工終了後に、下部構造上に上部構造を構築するといった方法が通常用いられる。
また、いうまでもなく、このような建物の施工終了後には、仮設支保工は撤去される。
【0003】
【発明が解決しようとする課題】
しかしながら、上述の建物の解体・構築方法においては、建物の解体、解体材の除去、仮設支保工の設置、下部構造の施工、上部構造の施工等の各工事が順次、行われることとなるために、これらのうち一つの工事に作業上の不都合等が生じると全体の工期が遅れてしまうという問題点がある。
【0004】
また、このように、既存建物の存在していた場所に新たに建物を構築する際には、当然に、建物自体の建築材料費に加え、解体費用、仮設費用等が別個に発生するため、これらの費用をできる限り低減することのできる技術が求められている。
【0005】
本発明は、このような事情に鑑みなされたものであり、工期を短縮することが可能であり、なおかつ低コストで実現できるような建物の解体・構築方法を提供することを課題とする。
【0006】
【課題を解決するための手段】
上記課題を解決するために本発明においては以下の手段を採用した。
すなわち、請求項1記載の発明は、既存建物を、その下部構造を残して解体し、
該下部構造を山留めとして利用しつつ、該下部構造の内側に、新たに構築すべき建物の下部構造を新設する一方、新たに構築すべき建物の上部構造を前記既存建物の下部構造の上方位置に新設する建物の解体・構築方法であって、
前記既存建物の下部構造を山留めとして利用する際には、新たに構築すべき建物の床スラブを前記既存建物の下部構造の内部に設置して該床スラブを切り梁として利用し、
前記既存建物を解体する際には、発生した解体材を前記既存建物の下部構造の内部に集積させ、集積させた解体材の上面を前記床スラブを構築する際の作業床として利用し、
前記床スラブを構築する際には、集積させた前記解体材の上面から、前記既存建物の下部構造を貫通してその下方の地盤にまで到達するような掘削孔を形成するとともに、該掘削孔内に基礎杭を構築しておき、該基礎杭の杭頭に支持材を立設し、該支持材を介して前記床スラブの荷重を前記基礎杭から支持させることを特徴としている。
【0007】
このような構成により、山留め設置に係る仮設費用を省略することができる。また、新たに設置した下部構造を既存躯体の下部構造と一体化させれば、仮設除去に係る費用をも省略することができる。
【0009】
また、このような構成により、切り梁設置に係る仮設費用を省略するとともに、本設構造を利用して信頼性の高い切り梁を実現できる。
【0013】
さらに、このような構成により、床スラブの構築作業を容易に行うことができる。
【0015】
加えて、このような構成により、基礎杭の施工と同時に、床スラブを支持するための支持材を設置することができ、これにより、床スラブの下方の解体材を除去する作業を、基礎杭の設置後すぐに行うことができる。
【0018】
【発明の実施の形態】
以下、本発明の実施の形態を、図面に基づいて説明する。
図1は、本発明の一実施の形態である建物1を、その地下躯体(下部構造)2を中心に示したものである。この建物1は既存建物を解体し、それと同位置に新設されたものであり、その地下躯体2が、上部構造が解体された既存躯体の下部構造3の内側に、下部構造3と一体的に形成されている。
【0019】
また、この地下躯体2は、その下面を構成するマットスラブ4と、既存建物の下部構造3の側壁部3aを補強するためのバットレス補強体5と、バットレス補強体5の内側に形成された側壁部6と、側壁部6およびバットレス補強体5間に充填されたコンクリートグラウト7とにより概略構成されている。
【0020】
この地下躯体2は既存建物の下部構造3の底面3bを貫通して、その下方の地盤Gに至るように設けられた基礎杭8,8,…により支持される構成となっている。基礎杭8は、場所打ちコンクリート杭として形成されたものであり、その杭頭部8aには構真柱(支持材)9が一体的に立設されている。また、その構真柱9は、その上端部9aが建物1の1階床スラブ10に接続されており、これにより、構真柱9,9,…を介して1階床スラブ10が基礎杭8,8,…側から支持された構成となっている。
【0021】
次に、既存建物を解体してこのような建物1を構築するための方法について説明する。
これには、まず、図2に示すように、既存建物の上部構造12を解体する。この際、予め、既存建物の下部構造3の側壁部3aを補強するためのバットレス補強体5を形成しておくとともに、下部構造3の底面3bの二重ピット13内にコンクリートグラウト14を施しておく。そして、既存建物をその下部構造3を残して解体する。この際、発生した解体材15は、下部構造3内部に集積させて敷き詰めておく。
【0022】
次に、図3に示すように、集積した解体材15の上面15aを作業床として利用しつつ、解体材15の上面15aから地盤Gに向けて掘削孔16を形成し、この掘削孔16内に基礎杭8を構築する。この場合、基礎杭8の杭頭部8aの上面が下部構造3の底面3bと略同一レベルに位置するようにする。
また、基礎杭8の施工と同時に、基礎杭8の杭頭部8aから解体材15の上面15aと同一レベルにまで至るように構真柱9を設置する。
【0023】
次に、図4に示すように、集積した解体材15の上面15a上に、建物1の1階床スラブ10を構真柱9に支持させた状態に形成する。この場合、1階床スラブ10の一部には、図示しない開口部を設けておく。
【0024】
さらに、1階床スラブ10の構築が終了したら、1階床スラブ10の下方に位置する解体材15を1階床スラブ10に設けられた開口部を通じて撤去し、さらに、地下躯体2の底面となるマットスラブ4を既存躯体の下部構造3の底面の上方に一体的に形成する。
【0025】
そして、図6に示すように、1階床スラブ10の下方に位置する地下躯体2の側壁部6その他の施工作業を行い、また、この施工作業と同時に、1階床スラブ10の上方に位置することとなる新たに構築すべき建物1の上部構造18を構築していく。これにより建物1を完成させることができる。
【0026】
以上述べた建物の解体・構築方法においては、既存建物を解体する際に、その下部構造3を一部を残すこととし、さらに、この下部構造3を山留めとして利用しつつ、下部構造3の内側に新たに建物1の地下躯体2を新設し、さらに、新たに構築すべき建物1の上部構造18を既存建物の下部構造3の上方位置に新設するようになっている。これにより、新たに構築すべき建物1の地下躯体2を施工する際に、山留め設置に係る仮設費用を省略することができ、低コストでの施工が可能となる。また、新たに設けた地下躯体2を既存建物の下部構造3と一体化させるようにすることにより、従来と比較した場合、仮設除去に係る費用を省略することができ、より一層低コスト化に貢献することが可能となる。
【0027】
また、この建物の解体・構築方法においては、既存建物の下部構造3を山留めとして利用する際に、新たに構築すべき建物1の1階床スラブ10を既存建物の下部構造3内部に設置し、この1階床スラブ10を切り梁として利用するようにしたため、切り梁設置に係る仮設費用を省略することができ、より一層のコスト削減を図ることが可能となる。さらに、切り梁として本設構造を利用することができるために、その信頼性が高く、安全な施工を行うことが可能となる。
【0028】
また、上述の建物の解体・構築方法においては、1階床スラブ10を構築した後に、新たに構築すべき建物の上部構造18および地下躯体2を1階床スラブ10の上下において同時に施工することできるために、新たに設置すべき建物1の工事工程を短縮化することができ、建物の解体・構築作業全体の短工期化を図ることが可能となる。
【0029】
さらに、上述の建物の解体・構築方法においては、既存建物を解体する際に発生した解体材15を既存建物の下部構造3の内部に集積させ、集積させた解体材15の上面15aを新たに構築すべき建物1の1階床スラブ10を構築する際の作業床として利用するようにしたために、1階床スラブ10の型枠設置・配筋等を含めた構築作業を容易に行うことができ、施工性がよい。
【0030】
さらに、上述の建物の解体・構築方法においては、1階床スラブ10を構築する際に集積させた解体材15の上面15aから既存建物の下部構造3を貫通してその下方の地盤Gにまで到達するような掘削孔16を形成するとともに、掘削孔16内に基礎杭8を構築しておき、さらに、基礎杭8の杭頭部8aに立設した構真柱9により、1階床スラブ10の荷重を基礎杭8側から支持させるようにしたために、1階床スラブ10を構築すると同時にその荷重を支持することができ、これによって、1階床スラブ10の下方に位置する解体材15の除去作業を、仮設設置などを要することなく、1階床スラブ10の設置後に速やかに行うことができ、施工期間が短縮されることとなる。
【0031】
また、上述の建物1においては、上部構造12が解体された既存建物の下部構造3の内側に地下躯体2が設置され、この地下躯体2が既存建物の下部構造3を貫通して地盤Gに至るように設置された基礎杭8により支持された構成とされるとともに、この基礎杭8の杭頭部8a上に立設された構真柱9により1階床スラブ10が基礎杭8側から支持された構成となっているために、施工時に既存建物の下部構造3を地下躯体2設置時の山留め壁として利用することができるとともに、1階床スラブ10を山留め壁を支持するための切り梁として用いることができ、これにより、従来に比較して仮設費用を大幅に削減することができ、建設コストの大幅な削減を図ることができる。また山留め壁や切り梁などの仮設支保工が必要とならず、なおかつ、上部構造18および地下躯体2を同時施工できるために、大きく工期を短縮することが可能となる。
以上により、既存建物を解体した場所に低コストかつ短工期で新たな建物1を構築することが可能となる。
【0032】
【発明の効果】
以上説明したように、請求項1に係る建物の解体・構築方法においては、既存建物を解体する際に、その下部構造を一部を残すこととし、さらに、この下部構造を山留めとして利用しつつ、下部構造の内側に新たに建物の下部構造を新設し、さらに、新たに構築すべき建物の上部構造を既存建物の下部構造の上方位置に新設するようになっているために、新たに構築すべき建物の下部構造を施工する際に、山留め設置に係る仮設費用を省略することができ、これにより低コストでの施工が可能となる。また、新たに設けた下部構造を既存建物の下部構造と一体化することにより、従来と比較した場合、仮設除去に係る費用を省略することができ、より一層低コスト化に貢献することが可能となる。
【0033】
また、請求項1に係る建物の解体・構築方法においては、既存建物の下部構造を山留めとして利用する際に、新たに構築すべき建物の床スラブを既存建物の下部構造内部に設置し、この床スラブを切り梁として利用するようにしたため、切り梁設置に係る仮設費用を省略することができ、より一層のコスト削減を図ることが可能となる。さらに、切り梁として本設構造を利用することができるために、その信頼性が高く、安全な施工を行うことが可能となる。
【0035】
さらに、請求項1に係る建物の解体・構築方法においては、既存建物を解体する際に発生した解体材を既存建物の下部構造の内部に集積させ、集積させた解体材の上面を新たに構築すべき建物の床スラブを構築する際の作業床として利用するようにしたために、床スラブの構築作業を容易に行うことができ、施工性がよい。
【0036】
加えて、請求項1に係る建物の解体・構築方法においては、床スラブを構築する際に、集積させた解体材の上面から既存建物の下部構造を貫通してその下方の地盤にまで到達するような掘削孔を形成するとともに、掘削孔内に基礎杭を構築しておき、さらに、基礎杭の杭頭に立設した支持材により、床スラブの荷重を基礎杭側から支持させるようにしたために、床スラブを構築すると同時にその荷重を支持させることができ、これによって、床スラブの下方に位置する解体材の除去作業を、仮設設置などを要することなく、床スラブ設置後に速やかに行うことができ、施工期間が短縮されることとなる。
【図面の簡単な説明】
【図1 】 本発明の一実施の形態である建物をその地下躯体を中心に示した立断面図である。
【図2 】 既存建物を解体して、それと同位置に図1に示した建物を構築する際の工程を示す図であって、既存建物を解体した場合の状況を示す立断面図である。
【図3 】 図2の次工程を示す立断面図である。
【図4 】 図3の次工程を示す立断面図である。
【図5 】 図4の次工程を示す立断面図である。
【図6 】 図5の次工程を示す立断面図である。
【符号の説明】
1 建物
2 地下躯体(下部構造)
3 (既存建物の)下部構造
8 基礎杭
8a 杭頭部
9 構真柱(支持材)
10 1階床スラブ
12 (既存建物の)上部構造
15 解体材
15a 上面
16 掘削孔
18 (新設建物の)上部構造[0001]
BACKGROUND OF THE INVENTION
The present invention is to dismantle the existing building, is relates to the subsequent dismantling and construction how the building for the newly constructed building in the same location.
[0002]
[Prior art]
As is well known, when dismantling an existing building and then building a new building at the same location, dismantle the existing building, including the superstructure and substructure, and remove the dismantling material generated by the dismantling At the same time, install a temporary support such as a mountain stop in the same place, and construct the lower structure of the building to be newly constructed there. Furthermore, after the construction of the lower structure is completed, the upper structure is built on the lower structure. A method such as construction is usually used.
Needless to say, the temporary support is removed after the construction of such a building is completed.
[0003]
[Problems to be solved by the invention]
However, in the building demolition / construction method described above, each work such as building demolition, removal of demolition materials, installation of temporary support works, construction of the substructure, construction of the superstructure, etc. will be performed sequentially. In addition, there is a problem that if one of these works causes inconvenience in work, the entire construction period is delayed.
[0004]
In addition, in this way, when building a new building in the place where the existing building existed, naturally, in addition to the building material cost of the building itself, dismantling cost, temporary cost, etc. will occur separately, There is a need for a technique that can reduce these costs as much as possible.
[0005]
The present invention has been made in view of such circumstances, it is possible to shorten the construction period, yet it is an object to provide a dismantling-building how the building as realized at a lower cost.
[0006]
[Means for Solving the Problems]
In order to solve the above problems, the present invention employs the following means.
That is, the first aspect of the present invention, the existing building, disassembled leaving the substructure,
The lower structure of the building to be newly constructed is newly installed inside the lower structure while the lower structure is used as a mountain retaining, while the upper structure of the building to be newly constructed is positioned above the lower structure of the existing building. Is a method of dismantling and building a new building,
When using the lower structure of the existing building as a mountain stop, install the floor slab of the building to be newly constructed inside the lower structure of the existing building and use the floor slab as a cut beam,
When dismantling the existing building, the generated dismantling material is accumulated in the lower structure of the existing building, and the upper surface of the accumulated dismantling material is used as a work floor when constructing the floor slab,
When constructing the floor slab, the excavation hole is formed from the upper surface of the accumulated demolition material so as to penetrate the lower structure of the existing building and reach the ground below the excavation hole. A foundation pile is built in, a support material is erected on the pile head of the foundation pile, and the load of the floor slab is supported from the foundation pile via the support material .
[0007]
With such a configuration, it is possible to omit a temporary cost related to the installation of the mountain mount. Moreover, if the newly installed lower structure is integrated with the lower structure of the existing housing, the cost for temporary removal can be omitted.
[0009]
Further, with such a configuration , it is possible to realize a highly reliable beam using the main structure while omitting the temporary cost for installing the beam.
[0013]
Furthermore, the construction work of the floor slab can be easily performed by such a configuration.
[0015]
In addition, with such a configuration, a support material for supporting the floor slab can be installed simultaneously with the construction of the foundation pile, thereby removing the dismantling material below the floor slab. Can be done immediately after installation.
[0018]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIG. 1 shows a building 1 according to an embodiment of the present invention centering on an underground structure (lower structure) 2 thereof. This building 1 was constructed by dismantling an existing building and newly installed at the same position. The
[0019]
In addition, the
[0020]
This
[0021]
Next, a method for dismantling an existing building and constructing such a building 1 will be described.
For this, first, as shown in FIG. 2, the
[0022]
Next, as shown in FIG. 3, the
Simultaneously with the construction of the
[0023]
Next, as shown in FIG. 4, the first-
[0024]
Further, when the construction of the
[0025]
And as shown in FIG. 6, the
[0026]
In the building dismantling / construction method described above, when the existing building is dismantled, a part of the
[0027]
Further, in this building demolition and construction method, when the
[0028]
Moreover, in the above-mentioned building dismantling / construction method, after constructing the
[0029]
Furthermore, in the above-mentioned building dismantling / construction method, the dismantling
[0030]
Further, in the building demolition / construction method described above, from the
[0031]
Moreover, in the above-mentioned building 1, the
As described above, a new building 1 can be constructed at a low cost and in a short construction period in a place where an existing building is demolished.
[0032]
【The invention's effect】
As described above, in the building dismantling / construction method according to claim 1, when dismantling the existing building, a part of the lower structure is left, and the lower structure is used as a mountain stop. New construction of the lower structure of the building inside the lower structure, and further construction of the upper structure of the building to be newly constructed above the lower structure of the existing building When constructing the lower structure of a building to be constructed, temporary costs related to the installation of mountain retaining can be omitted, thereby enabling construction at a low cost. In addition, by integrating the newly installed substructure with the substructure of the existing building, the cost of temporary removal can be omitted compared to the conventional structure, which can contribute to further cost reduction. It becomes.
[0033]
Further, in the building dismantling / construction method according to claim 1 , when the lower structure of the existing building is used as a mountain stop, the floor slab of the building to be newly constructed is installed inside the lower structure of the existing building. Since the floor slab is used as a cut beam, the temporary cost for installing the cut beam can be omitted, and the cost can be further reduced. Further, since the main structure can be used as a cutting beam, its reliability is high and safe construction can be performed.
[0035]
Furthermore, in the building demolition / construction method according to claim 1 , the demolition material generated when demolishing the existing building is accumulated inside the lower structure of the existing building, and the upper surface of the accumulated demolition material is newly constructed. Since it is used as a work floor when building a floor slab of a building to be built, the building work of the floor slab can be easily performed and the workability is good.
[0036]
In addition, in the building demolition / construction method according to claim 1, when building the floor slab, it penetrates the lower structure of the existing building from the upper surface of the accumulated demolition material to reach the ground below it. The foundation pile was built in the excavation hole, and the load of the floor slab was supported from the foundation pile side by the support material standing on the pile head of the foundation pile. In addition, the load can be supported at the same time that the floor slab is constructed, so that the dismantling material located below the floor slab can be removed quickly after the floor slab is installed without requiring temporary installation. The construction period will be shortened.
[Brief description of the drawings]
FIG. 1 is an elevational sectional view showing a building according to an embodiment of the present invention centering on an underground skeleton.
FIG. 2 is a vertical sectional view showing a process when the existing building is dismantled and the building shown in FIG. 1 is constructed at the same position, and the existing building is dismantled.
FIG. 3 is an elevational sectional view showing a step subsequent to that in FIG. 2;
FIG. 4 is an elevational sectional view showing a step subsequent to that in FIG. 3;
FIG. 5 is an elevational sectional view showing a next process of FIG. 4;
6 is an elevational sectional view showing a step subsequent to FIG. 5. FIG.
[Explanation of symbols]
1
3 Substructure 8 (existing building) Foundation pile
10
Claims (1)
該下部構造を山留めとして利用しつつ、該下部構造の内側に、新たに構築すべき建物の下部構造を新設する一方、新たに構築すべき建物の上部構造を前記既存建物の下部構造の上方位置に新設する建物の解体・構築方法であって、
前記既存建物の下部構造を山留めとして利用する際には、新たに構築すべき建物の床スラブを前記既存建物の下部構造の内部に設置して該床スラブを切り梁として利用し、
前記既存建物を解体する際には、発生した解体材を前記既存建物の下部構造の内部に集積させ、集積させた解体材の上面を前記床スラブを構築する際の作業床として利用し、
前記床スラブを構築する際には、集積させた前記解体材の上面から、前記既存建物の下部構造を貫通してその下方の地盤にまで到達するような掘削孔を形成するとともに、該掘削孔内に基礎杭を構築しておき、該基礎杭の杭頭に支持材を立設し、該支持材を介して前記床スラブの荷重を前記基礎杭から支持させることを特徴とする建物の解体・構築方法。The existing building, dismantled, leaving the lower structure,
The lower structure of the building to be newly constructed is newly installed inside the lower structure while the lower structure is used as a mountain retaining, while the upper structure of the building to be newly constructed is positioned above the lower structure of the existing building. Is a method of dismantling and building a new building,
When using the lower structure of the existing building as a mountain stop, install the floor slab of the building to be newly constructed inside the lower structure of the existing building and use the floor slab as a cut beam,
When dismantling the existing building, the generated dismantling material is accumulated in the lower structure of the existing building, and the upper surface of the accumulated dismantling material is used as a work floor when constructing the floor slab,
When constructing the floor slab, the excavation hole is formed from the upper surface of the accumulated demolition material so as to penetrate the lower structure of the existing building and reach the ground below the excavation hole. Building demolition characterized in that a foundation pile is built in, a support material is erected on the pile head of the foundation pile, and the load of the floor slab is supported from the foundation pile via the support material -Construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000118578A JP3728654B2 (en) | 2000-04-19 | 2000-04-19 | Building dismantling and construction methods |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000118578A JP3728654B2 (en) | 2000-04-19 | 2000-04-19 | Building dismantling and construction methods |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001303599A JP2001303599A (en) | 2001-10-31 |
JP3728654B2 true JP3728654B2 (en) | 2005-12-21 |
Family
ID=18629689
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000118578A Expired - Lifetime JP3728654B2 (en) | 2000-04-19 | 2000-04-19 | Building dismantling and construction methods |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3728654B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110792101A (en) * | 2019-11-04 | 2020-02-14 | 广东省重工建筑设计院有限公司 | Underground building and implementation method thereof |
CN111576439A (en) * | 2020-05-26 | 2020-08-25 | 中铁十二局集团有限公司 | Concrete support dismantling prestressed support and construction method thereof |
Families Citing this family (22)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3752560B2 (en) * | 2001-11-09 | 2006-03-08 | 株式会社テノックス | Basic structure for constructing a new building in an existing basement and its construction method |
JP3977700B2 (en) * | 2002-07-11 | 2007-09-19 | 鹿島建設株式会社 | Demolition and new construction method using existing underground structure |
JP4164857B2 (en) * | 2003-03-03 | 2008-10-15 | 清水建設株式会社 | Reconstruction method using existing underground structure |
JP2005307688A (en) * | 2004-04-26 | 2005-11-04 | Nippon Steel Corp | Construction method of mountain retaining wall for new underground structure and construction method of new structure using the method |
JP4427456B2 (en) * | 2005-01-11 | 2010-03-10 | 戸田建設株式会社 | Mountain-crested parent pile construction method |
JP4359570B2 (en) * | 2005-03-25 | 2009-11-04 | 株式会社竹中工務店 | Rebuilding method |
JP5038170B2 (en) * | 2008-01-28 | 2012-10-03 | 株式会社竹中工務店 | How to rebuild a structure |
JP4997207B2 (en) * | 2008-10-01 | 2012-08-08 | 日本環境製造株式会社 | Construction method for underground structures |
WO2011114507A1 (en) * | 2010-03-19 | 2011-09-22 | 日本環境製造株式会社 | Method of constructing underground structure to be newly built |
JP6119074B2 (en) * | 2012-12-06 | 2017-04-26 | 株式会社竹中工務店 | Construction method and rebuilding method |
JP6229294B2 (en) * | 2013-04-19 | 2017-11-15 | 株式会社大林組 | Method of rebuilding a structure having an underground structure and underground structure |
JP6378873B2 (en) * | 2013-11-29 | 2018-08-22 | 株式会社竹中工務店 | Artificial ground and construction method of artificial ground |
JP6265736B2 (en) * | 2013-12-26 | 2018-01-24 | 株式会社竹中工務店 | Underground demolition method |
JP6274406B2 (en) * | 2013-12-27 | 2018-02-07 | 清水建設株式会社 | Construction method of new underground structure with dismantling of existing underground structure |
JP6499834B2 (en) * | 2014-07-10 | 2019-04-10 | 株式会社竹中工務店 | Building foundation structure |
JP6471565B2 (en) * | 2015-03-20 | 2019-02-20 | 株式会社大林組 | Structure |
JP6774774B2 (en) * | 2016-04-04 | 2020-10-28 | 株式会社竹中工務店 | Pile foundation structure |
JP6827256B2 (en) * | 2016-08-02 | 2021-02-10 | 大成建設株式会社 | How to rebuild the building |
JP7029901B2 (en) * | 2017-08-09 | 2022-03-04 | 株式会社竹中工務店 | Dismantling method |
CN108060683B (en) * | 2017-12-18 | 2019-09-03 | 烟建集团有限公司 | A kind of middle weathering geology top-down construction method |
JP7085464B2 (en) * | 2018-11-26 | 2022-06-16 | 株式会社竹中工務店 | How to build a retaining wall structure in the reverse striking method |
CN115198765B (en) * | 2022-07-28 | 2024-05-14 | 中建六局建设发展有限公司 | Method for dismantling support in foundation pit |
-
2000
- 2000-04-19 JP JP2000118578A patent/JP3728654B2/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110792101A (en) * | 2019-11-04 | 2020-02-14 | 广东省重工建筑设计院有限公司 | Underground building and implementation method thereof |
CN110792101B (en) * | 2019-11-04 | 2021-11-23 | 广东省重工建筑设计院有限公司 | Underground building and implementation method thereof |
CN111576439A (en) * | 2020-05-26 | 2020-08-25 | 中铁十二局集团有限公司 | Concrete support dismantling prestressed support and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP2001303599A (en) | 2001-10-31 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3728654B2 (en) | Building dismantling and construction methods | |
KR101014796B1 (en) | Top-down construction method using ready-made concrete pillar member | |
KR101205783B1 (en) | The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously | |
KR101212240B1 (en) | Structure for underground downward extension of structural remodeling and methode thereof | |
JP3799036B2 (en) | Building basic structure and construction method | |
KR20200122037A (en) | The construction method using a exterio wall of undergound structure | |
KR20210012525A (en) | Steel structures and top-down method using it | |
KR100976621B1 (en) | Underground foundation construction method for basement extension service | |
KR100976620B1 (en) | Underground foundation construction method for basement extension service | |
JPH1162248A (en) | Construction method of building frame using existing outer wall | |
KR101138499B1 (en) | Method for Head Setting of Micro-Pile and Apparatus for the Same | |
JP5378066B2 (en) | Mountain fastening method | |
JP3033538B2 (en) | Construction method of building frame using existing foundation slab | |
JP2964295B2 (en) | Basement floor construction method | |
JP2950325B1 (en) | Construction method of seismic isolation building | |
JP3172694B2 (en) | Embedding method of straight pillar in reverse hitting method | |
JP2736542B2 (en) | Construction method of underground structure omitting temporary materials | |
JPH10317374A (en) | Method for constructing underground column made of reinforced concrete | |
JP3281554B2 (en) | How to rebuild underground structures | |
JPH1130053A (en) | Construction method of seismic isolation building | |
KR102408334B1 (en) | The construction method of underground structure using foundation of existing undergound structure | |
KR101524302B1 (en) | Construction method for underground structure without temporary structure | |
KR101516746B1 (en) | Construction method for girder and construction method for underground structure without temporary structure using the same | |
KR102583537B1 (en) | Top-down construction method for uneven-slope site | |
JP2000282695A (en) | Existing building seismic isolation method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20050530 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20050607 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050726 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050830 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050920 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3728654 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111014 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111014 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121014 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121014 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131014 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131014 Year of fee payment: 8 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131014 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141014 Year of fee payment: 9 |
|
EXPY | Cancellation because of completion of term |