KR20210012525A - Steel structures and top-down method using it - Google Patents

Steel structures and top-down method using it Download PDF

Info

Publication number
KR20210012525A
KR20210012525A KR1020190090409A KR20190090409A KR20210012525A KR 20210012525 A KR20210012525 A KR 20210012525A KR 1020190090409 A KR1020190090409 A KR 1020190090409A KR 20190090409 A KR20190090409 A KR 20190090409A KR 20210012525 A KR20210012525 A KR 20210012525A
Authority
KR
South Korea
Prior art keywords
pile
casing
steel structure
phc
support plate
Prior art date
Application number
KR1020190090409A
Other languages
Korean (ko)
Inventor
이규철
Original Assignee
이규철
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이규철 filed Critical 이규철
Priority to KR1020190090409A priority Critical patent/KR20210012525A/en
Publication of KR20210012525A publication Critical patent/KR20210012525A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a steel structure for coupling a pile and a top-down construction method using the same, wherein the steel structure for coupling a pile is installed on an upper surface of a PHC pile inserted into a support layer to function as an underground column of a building in the top-down construction method. The steel structure for coupling a pile includes: a beam embedded in the ground at an upper side of the support layer; a support plate fixed to a lower end of the beam to be mounted on an upper end of the PHC pile; and an insertion steel pipe fixed to the bottom of the support plate to be inserted into a central hole of the PHC pile, thereby easily connecting the beam functioning as the underground column to the PHC pile so that constructability can be improved.

Description

파일 결합 철골구조물과 이를 이용한 탑다운 공법{Steel structures and top-down method using it}Steel structures and top-down method using it}

본 발명은 파일 결합 철골구조물과 이를 이용한 탑다운 공법에 관한 것으로서, 특히 기 시공되어 있는 PHC파일에 건축물의 기둥 역할을 하는 빔을 용이하게 연결할 수 있는 파일 결합 철골구조물과 이를 이용한 탑다운 공법에 관한 것이다.The present invention relates to a pile-coupled steel structure and a top-down method using the same, and in particular, to a pile-coupled steel structure capable of easily connecting a beam serving as a pillar of a building to a previously constructed PHC pile, and a top-down method using the same. will be.

일반적으로 건물의 지하층 구조물을 구축하는 방식으로는 종래로부터 여러 시공법이 개발되어 있으며 이를 분류하는 방식도 여러 가지가 있을 수 있지만, 이들을 지하구조물을 구축 시공하는 방향에 따라 분류하면 크게 순타(順打)공법과 역타(逆打)공법으로 대별할 수 있다.In general, as a method of constructing the basement structure of a building, several construction methods have been developed from the prior art, and there may be several methods of classifying them, but if these are classified according to the direction of constructing and constructing the underground structure, it is largely pure. It can be roughly divided into a construction method and a reverse stroke method.

이 중 역타 공법은 일명 탑다운(Top-Down) 공법이라고도 하는데, 이는 건축물의 지상고가 높아지고 이에 필요한 지하구조물이 깊어짐에 따라 지상층과 지하층을 동시에 완성할 수 있는 방법으로 고안된 공법으로서, 지하 터파기에 앞서 지하 외벽과 지하 기둥을 시공한 후 층별 터파기 작업과 함께 바닥 슬래브와 같은 지하구조물을 병행 시공함으로써 지하공사 시공 중의 안정성 및 전체공기의 단축효과를 기대할 수 있다.Among them, the back hitting method is also called the top-down method, which is a method devised as a method to simultaneously complete the ground floor and the basement layer as the ground height of the building increases and the required underground structure deepens. After constructing the basement outer wall and the basement pillar, it is possible to expect stability during underground construction and shortening of the total air by constructing an underground structure such as a floor slab in parallel with the excavation for each floor.

이러한 종래의 탑다운 공법은 지하 기둥을 시공할 때 지지층의 천공홀에 철근망을 삽입한 후 레미콘을 타설하여 PHC파일을 만들고, 그 PHC파일 위에 빔과 같은 철골구조물을 삽입한 후 다시 레미콘을 타설하여 PHC파일과 빔이 일체화되도록 한다.In this conventional top-down construction method, when constructing an underground pillar, a steel reinforcing bar is inserted into the perforated hole of the support layer, and then ready-mixed concrete is placed to create a PHC pile, and a steel structure such as a beam is inserted on the PHC pile, and then the ready-mixed concrete is poured again. Thus, the PHC pile and the beam are integrated.

이와 같은 종래의 방법은 기 시공된 PHC파일과 철골구조물의 연결이 용이하지 않은 문제점이 있다.Such a conventional method has a problem in that it is not easy to connect the previously constructed PHC pile and the steel structure.

등록특허 10-0788623Registered Patent 10-0788623

본 발명은 상기한 종래기술의 문제점을 해결하기 위하여 안출된 것으로서, 건축물의 기둥 역할을 하는 빔과 PHC파일을 용이하고 견고하게 연결하여 시공성을 향상시킬 수 있는 파일 결합 철골구조물과 이를 이용한 탑다운 공법을 제공하는데 그 목적이 있다.The present invention was devised to solve the problems of the prior art, and a pile-coupled steel structure capable of improving workability by easily and firmly connecting a beam serving as a pillar of a building and a PHC pile, and a top-down method using the same Its purpose is to provide.

상기한 과제를 해결하기 위한 본 발명에 의한 파일 결합 철골구조물은 지지층에 삽입된 PHC파일의 상면에 설치되어 탑다운 공법에서 건축물의 지하기둥 역할을 수행하는 것으로서; 상기 지지층 상측의 지중에 매설되는 빔과; 상기 빔의 하단에 고정되어 상기 PHC파일의 상단에 안착되는 지지판과; 상기 지지판의 저면에 고정되어 상기 PHC파일의 중앙홀에 삽입되는 삽입강관;으로 구성된다.The pile-coupled steel structure according to the present invention for solving the above problems is installed on the upper surface of the PHC pile inserted in the support layer to serve as a pillar of the building in the top-down construction method; A beam buried in the ground above the support layer; A support plate fixed to the lower end of the beam and seated at the upper end of the PHC pile; It consists of an insertion steel pipe fixed to the bottom of the support plate and inserted into the central hole of the PHC pile.

여기서, 상기 삽입강관은 하측부가 하단으로 갈수록 직경이 작아진다.Here, the diameter of the inserted steel pipe becomes smaller as the lower portion goes toward the lower end.

그리고, 상기 빔과 지지판을 연결하는 보강브라켓이 더 설치된다.In addition, a reinforcing bracket connecting the beam and the support plate is further installed.

또한, 상기 지지판에는 시멘트 밀크 또는 레미콘이 유입되는 유입홀이 형성되고, 상기 유입홀 옆에는 에어배출구가 구비된다.In addition, an inlet hole through which cement milk or ready-mixed concrete is introduced is formed in the support plate, and an air outlet is provided next to the inlet hole.

한편, 본 발명에 의한 파일 결합 철골구조물을 이용한 탑다운 공법은 지반을 천공하면서 천공홀 내에 케이싱을 삽입하는 단계와; 상기 케이싱 삽입 후 지반 밑의 지지층을 일정깊이로 천공하는 단계와; 상기 케이싱 내에 시멘트 밀크를 주입하는 단계와; PHC파일의 상단에 보조파일을 연결한 후 케이싱 내에 삽입하는 단계와; 연결된 PHC파일과 보조파일을 경타하는 단계와; 상기 PHC파일에서 보조파일을 분리한 후 인양하는 단계와; 상기한 본 발명의 파일 결합 철골구조물을 케이싱 내에 삽입하여 상기 PHC파일과 연결하는 단계와; 상기 파일 결합 철골구조물의 빔을 회전시켜 상기 빔을 정렬시키는 단계와; 상기 케이싱 내에 시멘트 밀크 또는 레미콘을 타설하는 단계와; 상기 케이싱 내에 토사를 채워 넣는 단계와; 상기 케이싱을 인양하는 단계와; 상기 케이싱 인양 후 천공홀 내에 토사를 채워 넣는 단계;를 포함하여 구성된다.On the other hand, the top-down method using a pile-coupled steel structure according to the present invention includes the steps of inserting a casing into the perforated hole while perforating the ground; Drilling the supporting layer under the ground to a predetermined depth after inserting the casing; Injecting cement milk into the casing; Connecting the auxiliary pile to the top of the PHC pile and inserting it into the casing; Hitting the connected PHC file and the auxiliary file; Separating and lifting the auxiliary file from the PHC file; Inserting the pile-coupled steel structure of the present invention into a casing and connecting it to the PHC pile; Aligning the beams by rotating the beams of the pile-coupled steel structure; Pouring cement milk or ready-mixed concrete into the casing; Filling soil into the casing; Lifting the casing; And filling the soil into the perforated hole after lifting the casing.

여기서, 상기 파일 결합 철골구조물과 상기 PHC파일을 연결한 후 시멘트 밀크 또는 레미콘을 타설할 때 철골구조물의 지지판 상단까지 타설한다.Here, after connecting the pile-bonded steel structure and the PHC pile, when cement milk or ready-mixed concrete is poured, it is poured to the top of the support plate of the steel structure.

상기와 같이 구성되는 본 발명의 파일 결합 철골구조물과 이를 이용한 탑다운 공법은 빔에 고정된 지지판과 PHC파일에 삽입되는 삽입강관을 통하여 지지층 아래에 삽입되어 있는 PHC파일에 건축물의 지하기둥 역할을 하는 빔을 용이하게 연결할 수 있어서 시공성이 좋은 이점이 있다.The pile-coupled steel structure of the present invention constructed as described above and the top-down method using the same are applied to the PHC pile inserted under the support layer through the support plate fixed to the beam and the inserted steel pipe inserted into the PHC pile. Since the beam can be easily connected, there is an advantage of good workability.

도 1 및 도 2는 본 발명에 의한 파일 결합 철골구조물을 보인 도.
도 3은 본 발명에 의한 파일 결합 철골구조물을 이용한 탑다운 공법을 간단히 보인 블록도.
도 4 내지 도 16은 도 3에서 설명한 탑다운 공법을 도시화하여 순차적으로 보인 도.
1 and 2 are views showing the steel structure combined with the pile according to the present invention.
Figure 3 is a block diagram showing a simple top-down method using a pile-coupled steel structure according to the present invention.
4 to 16 are views sequentially showing the top-down method described in FIG. 3.

이하, 본 발명에 의한 파일 결합 철골구조물의 실시 예를 첨부된 도면을 참조하여 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, an embodiment of the steel structure combined with a pile according to the present invention will be described in detail.

도 1 및 도 2는 본 발명에 의한 파일 결합 철골구조물을 보인 도이다.1 and 2 are views showing a pile-coupled steel structure according to the present invention.

본 발명에 의한 파일 결합 철골구조물은 지반 아래의 지지층(E2)에 삽입된 PHC파일(P)의 상면에 설치되어 탑다운 공법에서 건축물의 지하기둥 역할을 수행하는 것으로서, 빔(10)과, 상기 빔(10)의 하단에 고정되는 지지판(20)과, 상기 지지판(20)의 저면에 고정되는 삽입강관(30)을 포함하여 구성된다.The pile-coupled steel structure according to the present invention is installed on the upper surface of the PHC pile (P) inserted in the support layer (E2) under the ground to serve as a pillar of the building in the top-down method, and the beam (10) and the It is configured to include a support plate 20 fixed to the lower end of the beam 10, and an insertion steel pipe 30 fixed to the bottom surface of the support plate 20.

상기 빔(10)은 지지층(E2) 상측의 지중에 수직으로 매설되고 상측부가 지면(E1) 위로 돌출되어 건축물의 견고한 지하기둥이 된다. 이러한 빔(10)은 H빔, 사각빔, 원형빔 등 다양한 형상으로 이루어질 수 있다.The beam 10 is vertically buried in the ground above the support layer E2, and the upper portion protrudes above the ground E1 to become a solid pillar of the building. The beam 10 may have various shapes such as an H beam, a square beam, and a circular beam.

상기 지지판(20)은 용접 등의 방법에 의하여 빔(10)의 하단에 고정되어 PHC파일(P)의 상단에 안착된다.The support plate 20 is fixed to the lower end of the beam 10 by a method such as welding, and is mounted on the upper end of the PHC pile P.

부연하면, PHC파일(P)은 중앙부분이 관통된 플레이트(P1)가 상단에 볼팅되어 구비되고, 주지하다시피 가운데에 상하방향으로 중앙홀(P2)이 길게 형성되어 있다. 이러한 PHC파일(P)의 플레이트(P1) 상면에 지지판(20)이 안착되되, 플레이트(P1)의 상면에 형성된 고리(P3) 안쪽에 위치되도록 설치된다.Incidentally, in the PHC pile P, a plate P1 through which a central portion is passed is bolted to the upper end, and as is well known, a central hole P2 is formed in the center in the vertical direction. The support plate 20 is mounted on the upper surface of the plate P1 of the PHC pile P, and is installed to be located inside the ring P3 formed on the upper surface of the plate P1.

이렇게 설치되는 지지판(20)은 빔(10)이 좌우로 흔들리는 것을 막을 뿐만 아니라 빔(10)이 PHC파일(P)의 중앙홀(P2)로 빠지는 것을 방지한다.The support plate 20 installed in this way not only prevents the beam 10 from shaking left and right, but also prevents the beam 10 from falling into the central hole P2 of the PHC pile P.

한편, 상기 빔(10)과 지지판(20) 사이에는 이 둘을 연결하는 보강브라켓(40)이 용접 등의 방법으로 설치되어 빔(10)을 견고하게 잡아주고 하중을 분산한다.On the other hand, between the beam 10 and the support plate 20, a reinforcing bracket 40 connecting the two is installed by welding or the like to hold the beam 10 firmly and distribute the load.

그리고 지지판(20)에는 유입홀(21)이 형성되고, 에어배출구(22)가 구비된다.In addition, an inlet hole 21 is formed in the support plate 20 and an air outlet 22 is provided.

상기 유입홀(21)은 시멘트 밀크 또는 레미콘이 유입되는 구멍으로서, 이 곳을 통해 유입된 시멘트 밀크 또는 레미콘에 의해 PHC파일(P)과 본 발명의 철골구조물이 견고하게 일체화된다.The inlet hole 21 is a hole through which cement milk or ready-mixed concrete is introduced, and the PHC pile (P) and the steel structure of the present invention are rigidly integrated by the cement milk or ready-mixed concrete introduced through this place.

상기 에어배출구(22)는 유입홀(21)의 옆에 구비되는 것으로서, 지지판(20)의 상면에 일정높이로 돌출된다. 유입홀(21)을 통해 시멘트 밀크 또는 레미콘이 유입될 때 에어배출구(22)를 통해 공기가 외부로 배출된다.The air outlet 22 is provided next to the inlet hole 21 and protrudes to a predetermined height on the upper surface of the support plate 20. When cement milk or ready-mixed concrete is introduced through the inlet hole 21, air is discharged to the outside through the air outlet 22.

상기 삽입강관(30)은 지지판(20)의 저면에 용접 등의 방법으로 고정되어, 지지판(20)이 PHC파일(P)의 플레이트(P1) 상면에 안착되었을 때 PHC파일(P)의 중앙홀(P2)에 삽입된다.The inserted steel pipe 30 is fixed to the bottom of the support plate 20 by welding or the like, and when the support plate 20 is seated on the upper surface of the plate P1 of the PHC pile P, the central hole of the PHC pile P It is inserted in (P2).

이러한 삽입강관(30)은 그 외경이 PHC파일(P)의 중앙홀(P2) 직경과 같거나 거의 유사하게 형성되어 빔(10)이 흔들리는 것을 방지한다.The inserted steel pipe 30 has an outer diameter equal to or substantially similar to the diameter of the central hole P2 of the PHC pile P to prevent the beam 10 from shaking.

그리고, 삽입강관(30)은 하측부가 하단으로 갈수록 직경이 작아지게 형성된다. 따라서 PHC파일(P)의 중앙홀(P2) 내부로 삽입강관(30)이 용이하게 삽입될 수 있다.In addition, the insertion steel pipe 30 is formed to have a smaller diameter as the lower portion goes toward the lower end. Therefore, the insertion steel pipe 30 can be easily inserted into the central hole P2 of the PHC pile P.

이하에서는 본 발명에 의한 파일 결합 철골구조물을 이용한 탑다운 공법의 실시 예를 설명한다.Hereinafter, an embodiment of a top-down method using a pile-coupled steel structure according to the present invention will be described.

도 3은 본 발명에 의한 파일 결합 철골구조물을 이용한 탑다운 공법을 간단히 보인 블록도이고, 도 4 내지 도 16은 도 3에서 설명한 탑다운 공법을 도시화하여 순차적으로 보인 도이다.3 is a schematic block diagram showing a top-down method using a pile-coupled steel structure according to the present invention, and FIGS. 4 to 16 are views sequentially showing the top-down method described in FIG. 3.

상기와 같이 구성된 본 발명에 의한 파일 결합 철골구조물을 이용한 탑다운 공법은 몇 단계의 과정을 거쳐 완성된다.The top-down construction method using the pile-coupled steel structure according to the present invention configured as described above is completed through a process of several steps.

첫 번째 단계(S1)는 CIP(Cast in place pile) 공법에 의한 흙막이 시공 및 차수 그라우팅 시공을 한 후 오거를 이용하여 지반을 천공하면서 이때 형성된 천공홀에 케이싱(C)을 삽입하는 과정이다. 지반을 천공하면서 케이싱(C)을 바로 삽입하므로 토사가 붕괴되어 천공홀이 매몰되는 것을 방지할 수 있다.The first step (S1) is a process of inserting the casing (C) into the hole formed at this time while drilling the ground using an auger after performing the soil barrier construction and order grouting by the CIP (Cast in place pile) method. Since the casing (C) is directly inserted while drilling the ground, it is possible to prevent the soil from collapsing and the drilling hole from being buried.

두 번째 단계(S2)는 첫 번째 단계(S1)에서 케이싱(C) 삽입이 완료되고 난 후에, 지반 아래에 있으면서 지반보다 경질인 지지층(E2) 아래로 일정깊이 천공하는 과정이다. 이때 케이싱(C)은 지지층(E2)에는 삽입되지 않고 지지층(E2) 위의 지중에만 삽입된다.In the second step (S2), after the casing (C) insertion is completed in the first step (S1), a certain depth is drilled under the support layer (E2) that is harder than the ground while being under the ground. At this time, the casing (C) is not inserted into the support layer (E2), but is inserted only in the ground above the support layer (E2).

여기서 좀 더 부가설명을 하면, 탑다운 공법에서 지지층(E2)에서부터 지면(E1)까지의 지중 공간은 순차적으로 일정깊이씩 굴착된 후 바닥 슬래브를 시공하는 과정을 거치면서 건축물의 지하층을 이루는 공간이 된다.To explain more here, in the top-down method, the underground space from the support layer (E2) to the ground (E1) is excavated to a certain depth in sequence, and then the space that forms the basement layer of the building goes through the process of constructing the floor slab. do.

세 번째 단계(S3)는 케이싱(C) 내부에 시멘트 밀크를 주입하는 과정이다. 이때 주입되는 시멘트 밀크는 지지층(E2)에 형성된 천공홀 내에 일정높이로 채워진다.The third step (S3) is a process of injecting cement milk into the casing (C). At this time, the injected cement milk is filled to a certain height in the hole formed in the support layer E2.

네 번째 단계(S4)는 PHC파일(P)의 상단에 보조파일(50)을 연결한 후 케이싱(C) 내에 삽입하는 과정이다. PHC파일(P)과 보조파일(50)을 연결할 때 출원번호 10-2017-0174029 (발명의 명칭: 보조파일 연결 및 해체장치 및 이를 이용한 파일 시공 방법)에서 제시하고 있는 보조파일 연결 및 해체장치를 이용하면 좀 더 편리하게 연결작업을 수행할 수 있다.The fourth step (S4) is a process of connecting the auxiliary pile 50 to the top of the PHC pile (P) and inserting it into the casing (C). When connecting the PHC file (P) and the auxiliary file (50), use the auxiliary file connection and disassembly device suggested in Application No. 10-2017-0174029 (Name of the invention: auxiliary file connection and disassembly device and file construction method using the same). If you use it, you can perform the connection work more conveniently.

다섯 번째 단계(S5)는 연결된 PHC파일(P)과 보조파일(50)을 함마(H)로 경타하는 과정이다.The fifth step (S5) is a process of hitting the connected PHC file (P) and the auxiliary file (50) with a hammer (H).

여섯 번째 단계(S6)는 PHC파일(P)에서 보조파일(50)을 분리한 후 PHC파일(P)은 그대로 놔두고 보조파일(50)만을 인양하는 과정이다. 앞서 기재한 것처럼 PHC파일(P)과 보조파일(50)의 연결시 출원번호 10-2017-0174029 (발명의 명칭: 보조파일 연결 및 해체장치 및 이를 이용한 파일 시공 방법)에서 제시하고 있는 보조파일 연결 및 해체장치를 이용하면 PHC파일(P)에서 보조파일(50)을 분리했을 때 PHC파일(P)의 상단에 플레이트(P1)가 남아 있게 된다. In the sixth step (S6), after separating the auxiliary file 50 from the PHC file P, the PHC file P is left as it is and only the auxiliary file 50 is lifted. As described above, when connecting the PHC file (P) and the auxiliary file (50), the auxiliary file connection suggested in Application No. 10-2017-0174029 (Name of the invention: auxiliary file connection and dismantling device and file construction method using the same) And when the disassembly device is used, the plate P1 remains at the top of the PHC pile P when the auxiliary pile 50 is separated from the PHC pile P.

일곱 번째 단계(S7)는 위에서 설명한 본 발명에 의한 파일 결합 철골구조물(100)을 케이싱(C) 내에 삽입하여 PHC파일(P)과 연결하는 과정이다.The seventh step (S7) is a process of inserting the pile-coupled steel structure 100 according to the present invention described above into the casing (C) and connecting it to the PHC pile (P).

본 발명의 파일 결합 철골구조물(100)을 케이싱(C) 내에 삽입하면 지지판(20)이 PHC파일(P)의 플레이트(P1) 상면에 밀착되면서 삽입강관(30)은 PHC파일(P)의 중앙홀(P2)에 삽입된다.When the pile-coupled steel structure 100 of the present invention is inserted into the casing (C), the support plate 20 is in close contact with the upper surface of the plate (P1) of the PHC pile (P), and the inserted steel pipe (30) is the center of the PHC pile (P). It is inserted into the hole P2.

여덟 번째 단계(S8)는 파일 결합 철골구조물(100)의 빔(10)을 회전시켜 빔(10)을 정렬시키는 과정이다. The eighth step (S8) is a process of aligning the beam 10 by rotating the beam 10 of the pile-coupled steel structure 100.

건축물의 지하기둥 역할을 수행하는 빔(10)은 일정방향을 향하도록 설계되는데, 시공 중에 빔(10)의 방향이 설계된 대로 안 되는 경우가 있다. 이때는 빔(10)의 길이방향을 중심으로 빔(10)을 시계방향 또는 반시계방향으로 회전시켜 설계된 대로 좌우정렬을 시킨다.The beam 10, which serves as an underground pillar of a building, is designed to face a certain direction, but there are cases where the direction of the beam 10 is not as designed during construction. In this case, the beam 10 is rotated clockwise or counterclockwise around the longitudinal direction of the beam 10 to align the left and right as designed.

아홉 번째 단계(S9)는 케이싱(C) 내에 시멘트 밀크 또는 레미콘을 타설하는 과정이다. 이렇게 시멘트 밀크 또는 레미콘을 타설할 때 철골구조물(100)의 지지판(20) 상단까지 타설하는 것이 바람직하다. 그래야만 철골구조물(100)과 PHC파일(P)의 결합력을 높여 견고하게 일체화시킬 수 있다.The ninth step (S9) is a process of pouring cement milk or ready-mixed concrete into the casing (C). When pouring cement milk or ready-mixed concrete in this way, it is preferable to pour it up to the top of the support plate 20 of the steel structure 100. Only then can the steel structure 100 and the PHC pile (P) increase the bonding force to be solidly integrated.

그리고, 이렇게 시멘트 밀크 또는 레미콘을 타설할 때 지지판(20)의 유입홀(21)을 통해 삽입강관(30)과 PHC파일(P) 내부로 시멘트 밀크 또는 레미콘이 유입된다.And, when the cement milk or ready-mixed concrete is poured in this way, the cement milk or ready-mixed concrete is introduced into the insertion steel pipe 30 and the PHC pile P through the inlet hole 21 of the support plate 20.

열 번째 단계(S10)는 케이싱(C) 내에 토사를 채워 넣는 과정이다. 일곱 번째 단계(S9)에서 시멘트 밀크에 의해 채워지지 않은 공간을 토사로 채워 넣는다.The tenth step (S10) is a process of filling soil in the casing (C). In the seventh step (S9), the space not filled by cement milk is filled with soil.

열한 번째 단계(S11)는 천공홀 내부에 삽입되어 있는 케이싱(C)을 인양하는 과정이다.The eleventh step (S11) is a process of lifting the casing (C) inserted into the perforated hole.

열두 번째 단계(S12)는 케이싱(C) 인양 후 천공홀 내에 토사를 채워 넣는 과정이다.The twelfth step (S12) is a process of lifting the casing (C) and filling the soil in the hole.

이와 같은 과정을 통해서 본 발명의 파일 결합 철골구조물(100)과 PHC말뚝(P)이 일체화되어 천공홀 내에 안정적으로 위치된 이후에는, 그 다음 단계(S13)로 위쪽에서부터 아래쪽으로 계획굴착심도까지 지면을 굴착한 후 지하1층 바닥 슬래브를 시공하고, 다시 계획굴착심도까지 굴착을 계속하여 지하2층 바닥 슬래브를 시공하며, 이렇게 굴착과 바닥 슬래브의 시공 과정을 반복하면서 건축물의 지하층을 시공한다.Through this process, after the pile-coupled steel structure 100 and the PHC pile (P) of the present invention are integrated and stably positioned in the perforated hole, the next step (S13) goes from the top to the bottom to the planned excavation depth. After excavation, the first basement floor slab is constructed, and the second basement floor slab is constructed by continuing to excavate again to the planned excavation depth, and the basement layer of the building is constructed by repeating the excavation and construction process of the floor slab.

10: 빔 20: 지지판
21: 유입홀 22: 에어배출구
30: 삽입강관 40: 보강브라켓
100: 파일 결합 철골구조물 50: 보조파일
C: 케이싱 P: PHC파일
P1: 플레이트 P2: 중앙홀
P: 고리
10: beam 20: support plate
21: inlet hole 22: air outlet
30: insert steel pipe 40: reinforcement bracket
100: pile-coupled steel structure 50: auxiliary pile
C: Casing P: PHC pile
P1: Plate P2: Central hole
P: ring

Claims (6)

지지층(E2)에 삽입된 PHC파일(P)의 상면에 설치되어 탑다운 공법에서 건축물의 지하기둥 역할을 수행하는 것으로서,
상기 지지층(E2) 상측의 지중에 매설되는 빔(10)과;
상기 빔(10)의 하단에 고정되어 상기 PHC파일(P)의 상단에 안착되는 지지판(20)과;
상기 지지판(20)의 저면에 고정되어 상기 PHC파일(P)의 중앙홀(P2)에 삽입되는 삽입강관(30);으로 구성된 것을 특징으로 하는 파일 결합 철골구조물.
It is installed on the upper surface of the PHC pile (P) inserted in the support layer (E2), and plays the role of a pillar of the building in the top-down method,
A beam 10 buried in the ground above the support layer E2;
A support plate 20 fixed to the lower end of the beam 10 and seated at the upper end of the PHC pile P;
An insert steel pipe 30 fixed to the bottom of the support plate 20 and inserted into the central hole P2 of the PHC pile P.
청구항 1에 있어서,
상기 삽입강관(30)은 하측부가 하단으로 갈수록 직경이 작아지는 것을 특징으로 하는 파일 결합 철골구조물.
The method according to claim 1,
The inserted steel pipe 30 is a pile-coupled steel structure, characterized in that the diameter decreases toward the lower side of the lower side.
청구항 1에 있어서,
상기 빔(10)과 지지판(20)을 연결하는 보강브라켓(40)이 더 설치되는 것을 특징으로 하는 파일 결합 철골구조물.
The method according to claim 1,
A pile-coupled steel structure, characterized in that a reinforcing bracket (40) connecting the beam (10) and the support plate (20) is further installed.
청구항 1에 있어서,
상기 지지판(20)에는 시멘트 밀크 또는 레미콘이 유입되는 유입홀(21)이 형성되고, 상기 유입홀(21) 옆에는 에어배출구(22)가 구비된 것을 특징으로 하는 파일 결합 철골구조물.
The method according to claim 1,
The support plate 20 is formed with an inlet hole 21 through which cement milk or ready-mixed concrete is introduced, and an air outlet 22 is provided next to the inlet hole 21.
지반을 천공하면서 천공홀 내에 케이싱(C)을 삽입하는 단계(S1)와;
상기 케이싱(C) 삽입 후 지반 밑의 지지층(E2)을 일정깊이로 천공하는 단계(S2)와;
상기 케이싱(C) 내에 시멘트 밀크를 주입하는 단계(S3)와;
PHC파일(P)의 상단에 보조파일(50)을 연결한 후 케이싱(C) 내에 삽입하는 단계(S4)와;
연결된 PHC파일(P)과 보조파일(50)을 경타하는 단계(S5)와;
상기 PHC파일(P)에서 보조파일(50)을 분리한 후 인양하는 단계(S6)와;
청구항 1 내지 청구항 4 중 어느 하나의 파일 결합 철골구조물(100)을 케이싱(C) 내에 삽입하여 상기 PHC파일(P)과 연결하는 단계(S7)와;
상기 파일 결합 철골구조물(100)의 빔(10)을 회전시켜 상기 빔(10)을 정렬시키는 단계(S8)와;
상기 케이싱(C) 내에 시멘트 밀크 또는 레미콘을 타설하는 단계(S9)와;
상기 케이싱(C) 내에 토사를 채워 넣는 단계(S10)와;
상기 케이싱(C)을 인양하는 단계(S11)와;
상기 케이싱(C) 인양 후 천공홀 내에 토사를 채워 넣는 단계(S12);를 포함하여 구성된 것을 특징으로 하는 파일 결합 철골구조물을 이용한 탑다운 공법.
Inserting the casing (C) into the drilling hole while drilling the ground (S1);
Drilling the supporting layer (E2) under the ground to a predetermined depth after insertion of the casing (C) (S2);
Injecting cement milk into the casing (C) (S3);
Connecting the auxiliary file 50 to the upper end of the PHC file P and inserting it into the casing C (S4);
A step (S5) of hitting the connected PHC file (P) and the auxiliary file (50);
Separating and lifting the auxiliary file 50 from the PHC file P (S6);
Inserting any one of the pile-coupled steel structure 100 of claims 1 to 4 into the casing (C) and connecting it to the PHC pile (P) (S7);
Aligning the beam 10 by rotating the beam 10 of the pile-coupled steel structure 100 (S8);
Pouring cement milk or ready-mixed concrete into the casing (C) (S9);
A step (S10) of filling soil into the casing (C);
Lifting the casing (C) (S11);
Top-down construction method using a pile-coupled steel structure comprising a; step (S12) of filling the soil into the perforated hole after lifting the casing (C).
청구항 5에 있어서,
상기 파일 결합 철골구조물(100)과 상기 PHC파일(P)을 연결한 후 시멘트 밀크 또는 레미콘을 타설할 때 철골구조물(100)의 지지판(20) 상단까지 타설하는 것을 특징으로 하는 파일 결합 철골구조물을 이용한 탑다운 공법.
The method of claim 5,
After connecting the pile-bonded steel structure 100 and the PHC pile (P), when pouring cement milk or ready-mixed concrete, a pile-coupled steel structure, characterized in that pouring to the top of the support plate 20 of the steel structure 100 Top-down method used.
KR1020190090409A 2019-07-25 2019-07-25 Steel structures and top-down method using it KR20210012525A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190090409A KR20210012525A (en) 2019-07-25 2019-07-25 Steel structures and top-down method using it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190090409A KR20210012525A (en) 2019-07-25 2019-07-25 Steel structures and top-down method using it

Publications (1)

Publication Number Publication Date
KR20210012525A true KR20210012525A (en) 2021-02-03

Family

ID=74572435

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190090409A KR20210012525A (en) 2019-07-25 2019-07-25 Steel structures and top-down method using it

Country Status (1)

Country Link
KR (1) KR20210012525A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114134898A (en) * 2021-11-26 2022-03-04 中建三局第三建设工程有限责任公司 Top-down construction method one-pile one-column connecting structure and construction method thereof
KR102604726B1 (en) * 2022-09-16 2023-11-22 최상호 Composite micropile for spreading loads and installation method thereof
KR102604734B1 (en) * 2022-09-16 2023-11-22 최상호 Device for connecting composite pile and installation method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100788623B1 (en) 2006-05-08 2007-12-26 (주)씨.에스 구조 엔지니어링 Top-down method using precast-concrete colum

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100788623B1 (en) 2006-05-08 2007-12-26 (주)씨.에스 구조 엔지니어링 Top-down method using precast-concrete colum

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114134898A (en) * 2021-11-26 2022-03-04 中建三局第三建设工程有限责任公司 Top-down construction method one-pile one-column connecting structure and construction method thereof
CN114134898B (en) * 2021-11-26 2023-01-06 中建三局第三建设工程有限责任公司 Top-down construction method one-pile one-column connecting structure and construction method thereof
WO2023093115A1 (en) * 2021-11-26 2023-06-01 中建三局第三建设工程有限责任公司 Connection structure for one pile and one column in top-down construction method, and construction method therefor
KR102604726B1 (en) * 2022-09-16 2023-11-22 최상호 Composite micropile for spreading loads and installation method thereof
KR102604734B1 (en) * 2022-09-16 2023-11-22 최상호 Device for connecting composite pile and installation method thereof

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR100788623B1 (en) Top-down method using precast-concrete colum
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
JP3728654B2 (en) Building dismantling and construction methods
KR20210012525A (en) Steel structures and top-down method using it
JPH08296243A (en) Construction method for underground structure by precast concrete central pillar
KR100849226B1 (en) C.i.p temporary wall and method for constructing thereof
KR100976621B1 (en) Construction method for basement extention
JP2000352296A (en) Method o constructing passage just under underground structure
JP6043454B1 (en) Construction method of underground structure and underground structure
JP7085464B2 (en) How to build a retaining wall structure in the reverse striking method
JP5456627B2 (en) Connection structure and method of connection between pile and steel column
KR102156277B1 (en) Basic file construction method of soft ground and thereof foundation file device
JP6461690B2 (en) Foundation structure and foundation construction method
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
KR102043582B1 (en) Construction method of retaining wall using panel having base for reinforce
KR20210090100A (en) In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
KR101304659B1 (en) Vertical column construction method of none-excavation underground structure
KR102199684B1 (en) Connector between beam and PHC Pile and top-down method using it
KR200428941Y1 (en) Strut system of temporary retaining wall
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
KR20210073076A (en) Phc pile for soil retaining wall
KR100722198B1 (en) Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same
KR102502549B1 (en) Upper PHC Pile for removeable auxiliary pile and construction method of PHC top-down foundation pile using of the same
JP6534026B2 (en) Seismic isolation building and its construction method

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right