KR20210090100A - In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures - Google Patents

In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures Download PDF

Info

Publication number
KR20210090100A
KR20210090100A KR1020210001429A KR20210001429A KR20210090100A KR 20210090100 A KR20210090100 A KR 20210090100A KR 1020210001429 A KR1020210001429 A KR 1020210001429A KR 20210001429 A KR20210001429 A KR 20210001429A KR 20210090100 A KR20210090100 A KR 20210090100A
Authority
KR
South Korea
Prior art keywords
underground
ground
temporary transition
retaining wall
transition structure
Prior art date
Application number
KR1020210001429A
Other languages
Korean (ko)
Inventor
임인식
이범택
김대영
한주옥
최지훈
Original Assignee
임인식
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 임인식 filed Critical 임인식
Publication of KR20210090100A publication Critical patent/KR20210090100A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to a reverse drilling method of building construction, and provides a construction period shortened reverse drilling method and a structure enabling early ground-frame construction by using a temporary transition structure in a building where an underground structure for construction is a wall-type structure. In a building where an underground structure is a wall-type structure, a temporary transition structure such as transition slabs or transition beams is installed in consideration of the load of an above-ground frame constructed in an UP-UP method or Top-Down method on a top basement floor (reverse drilling start floor). Therefore, in the case of underground construction, it is possible to shorten the construction period by allowing simultaneous construction of above-ground frames. The present invention includes a retaining wall and a plurality of main posts.

Description

지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법 및 구조{In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures}In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures}

본 발명은 지하구조물이 벽식구조로 되어 있는 건물을 하향구축함에 있어 지하 최상층에 가설전이구조물을 형성하여 그 상부에서 지하골조의 시공과 지상골조의 조기착수가 병행하여 가능하도록 하는 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법 및 구조에 관한 것이다.The present invention is a wall-type structure for an underground structure that enables the construction of an underground frame and the early start of the above-ground structure at the top by forming a temporary transition structure on the uppermost basement level in the downward construction of a building in which the underground structure is a wall-type structure. It relates to a short-term reverse drilling method and structure in which an early ground framing can be started using a temporary transition structure in a building.

빌딩, 아파트와 같은 건축구조물의 시공은, 일정 지하층의 깊이까지 지면을 굴착한 후, 굴착된 지하에서부터 상부로 각각의 지하층의 골조를 충분히 형성하고 지상 구조물을 시공하는 탑다운 방식인 역타공법을 선택한다.For the construction of architectural structures such as buildings and apartments, after excavating the ground to a certain depth of the basement floor, the frame of each basement level is sufficiently formed from the excavated basement to the upper part, and the top-down method of constructing the above-ground structure is selected. do.

이러한 역타공법은 지하의 토사가 무너지는 것을 방지하기 위하여 지하공간의 외벽에 흙막이를 설치하여 토압을 지지하며, 굴착된 지하 공간 및 면적이 증가할수록 흙막이에 작용하는 토압과 함께 지상시공 구조물의 하중을 견디기 위한 지하구조가 증가하여 시공기간이 길어지게 된다.In this reverse drilling method, earth pressure is supported by installing a retaining barrier on the outer wall of the underground space to prevent the soil from collapsing, and as the excavated underground space and area increase, the earth pressure acting on the earth barrier and the load of the above-ground construction structure are reduced. As the underground structure to withstand the increase increases, the construction period becomes longer.

역타공법에서 지하층의 지지구조는, 지상구조물의 시공을 위한 수직 및 수평 하중을 충분히 버틸 수 있는 구조를 만드는 것으로서, 메인포스트의 기초바닥을 타설하여 시공하고, 순차적으로 지하외벽, 지하층들 각각의 바닥부와 코어벽체, 및 메인포스트의 RC피복에 의한 SRC, 램프 등을 구성하게 된다.In the reverse drilling method, the support structure of the basement floor is to create a structure that can sufficiently withstand vertical and horizontal loads for the construction of above-ground structures. SRC, lamp, etc. by RC coating of part and core wall, and main post are constituted.

이처럼 기존의 역타공법은, 지하구조물의 굴착작업 후에 바닥부터 기초콘크리트와 슬래브의 순차 타설이 완료된 후 지상구조물을 시공해야 하는 것으로서, 지하 굴착작업 후에 지상구조물을 설치해야 했다.As such, in the conventional reverse drilling method, the above-ground structure must be constructed after the sequential pouring of the foundation concrete and slab from the floor is completed after excavation of the underground structure, and the above-ground structure must be installed after the underground excavation operation.

일반적으로, 보와 기둥으로 되어 있는 지하구조물이 라멘형식으로 되어 있으면, 지하구조물을 역타시공하는 방식에 있어 UP-UP방식 또는 Top-Down방식을 적용한다.In general, if an underground structure composed of beams and columns is of the Ramen type, the UP-UP method or Top-Down method is applied in reverse construction of the underground structure.

참고적으로, UP-UP방식은 지하층바닥 하향시공과 기초시공 완료 후 지하잔여골조 시공시 지상골조를 병행 시공하는 방식이며, Top-Down방식은 지하층 바닥 하향시공과 지상골조를 동시에 병행하는 방식이다.For reference, the UP-UP method is a method of concurrently constructing the above-ground framing when constructing the basement floor after the basement floor is down-constructed and the foundation construction is completed. .

이러한 UP-UP방식과 Top-Down방식은, 주동부 기둥위치와 엘리베이터와 계단실 등으로 이루어져 있는 코어 주변에 수개의 지상골조 병행시공용 현장타설말뚝과 선시공철골기둥을 시공함으로써 지하시공과 지상골조의 병행시공이 가능해진다.The UP-UP method and the Top-Down method are designed to improve underground construction and above-ground framing by constructing several cast-in-place piles for parallel construction of above-ground structures and pre-construction steel pillars around the core consisting of the main eastern column position and the elevator and stairwell. Parallel construction is possible.

그러나, 건축물의 지하구조물이 벽식구조로 되어 있는 경우, 길고 짧은 모든 벽체에 대하여 지상골조 병행시공을 가능하게 하는 현장타설말뚝과 선시공 철골기둥을 시공한다는 것은 사실상 불가능하다.However, when the underground structure of a building is a wall-type structure, it is virtually impossible to construct cast-in-place piles and pre-construction steel columns that enable parallel construction of above-ground frames for all long and short walls.

따라서, 위와 같은 조건의 지하 벽식구조에서는, 지하역타를 지하바닥의 하향시공과 기초시공, 지하잔여골조시공(벽체 등)을 모두 완료한 후, 지상골조를 착수하는 Down-UP공법을 적용할 수밖에 없어서 공기단축이 불가능한 어려운 측면이 있었다.Therefore, in the underground wall-type structure under the above conditions, the Down-UP method of starting the above-ground framing after completing all of the down-construction of the basement floor, the foundation construction, and the remaining underground framing (walls, etc.) must be applied. There was a difficult aspect in which it was impossible to shorten the construction period.

한국등록특허 제10-1632701호 (2016.06.22. 공고)Korean Patent Registration No. 10-1632701 (2016.06.22. Announcement)

본 발명은 상기의 공기단축상의 문제점을 해경하기 위해 창안된 것으로서, 지하구조물이 벽식구조로 되어 있는 건물에서 지하 최상층바닥(역타 시작층)에 UP-UP방식 또는 Top-Down방식으로 시공되는 지상골조의 하중을 고려하여 전이슬래브 또는 전이보와 같은 가설용 전이구조물을 설치함으로써 지하 시공 시에도 지상골조의 병행시공을 할 수 있도록 하여 공기단축이 가능토록 하게 하는, 시공용 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법 및 구조를 제공하는 것이다.The present invention was devised to solve the above-mentioned problem of shortening the period, and in a building in which the underground structure is a wall-type structure, the above-ground frame is constructed in the UP-UP method or the Top-Down method on the uppermost basement floor (reverse start floor) By installing temporary transition structures such as transition slabs or transition beams in consideration of the load of It is to provide a short-term reverse drilling method and structure that enables early ground frame construction by using a temporary transition structure.

상기의 목적을 달성하기 위한 본 발명에 따른 시공용 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법구조는, 지하공간을 형성하기 위한 흙막이; 상기 흙막이의 내부에 위치하며, 상기 흙막이의 내부에서 지반에 직립 설치되는 복수의 메인포스트; 상기 흙막이의 내부에서 상기 복수의 메인포스트의 일부에 탑재되어 설치되며, 지상구조물의 지지를 위한 시공영역을 마련하도록 지면에 수평하게 설치되는 가설용 전이구조물; 상기 가설용 전이구조물에 대응하는 지하의 각층에서 상기 가설용 전이구조물을 지지하는 상기 복수의 메인포스트의 일부를 수평 연결하는 제1 수평 연결부; 및 상기 가설용 전이구조물의 외측에서 상기 흙막이와 가설용 전이구조물을 연결하는 제2 수평 연결부;를 포함한다.According to the present invention for achieving the above object, an air shortening type reverse drilling method structure in which an early ground framing can be initiated using a temporary transition structure in a building in which the underground structure for construction is a wall structure, comprising: a retainer for forming an underground space; a plurality of main posts located inside the retaining wall and installed upright in the ground from the inside of the retaining wall; a temporary transition structure mounted on a portion of the plurality of main posts from the inside of the retaining wall and installed horizontally on the ground to provide a construction area for supporting the above-ground structure; a first horizontal connection part horizontally connecting a portion of the plurality of main posts supporting the temporary transition structure on each basement floor corresponding to the temporary transition structure; and a second horizontal connection part connecting the retaining wall and the temporary transition structure from the outside of the temporary transition structure.

본 발명은 상기 복수의 메인포스트의 각 층별로 상부에서 하부로 타설되는 복수의 지하층 슬래브; 및 상기 가설용 전이구조물에 대응하는 지하 영역 내에서 상기 지하층 슬래브와 함께 타설되어 설치되는 복수의 지하벽체;를 더 포함할 수 있다.The present invention includes a plurality of basement slabs poured from the top to the bottom for each floor of the plurality of main posts; and a plurality of underground walls installed and installed together with the basement slab in an underground area corresponding to the temporary transition structure.

본 발명은 상기 흙막이의 내부에서 상기 메인포스트가 매립된 지반 상에 타설되는 기초콘크리트; 상기 기초콘크리트 상에서 상기 복수의 메인포스트의 각 층별로 하부에서 상부로 순차적으로 타설되는 복수의 지하층 슬래브; 및 상기 가설용 전이구조물에 대응하는 지하 영역 내에서 상기 지하층 슬래브와 함께 타설되어 설치되는 복수의 지하벽체;를 더 포함할 수 있다.The present invention is a base concrete that is poured on the ground in which the main post is buried in the interior of the retaining wall; a plurality of basement slabs sequentially poured from the bottom to the top for each floor of the plurality of main posts on the foundation concrete; and a plurality of underground walls installed and installed together with the basement slab in an underground area corresponding to the temporary transition structure.

상기 가설용 전이구조물은, 전이슬래브 또는 전이보로 마련되며, 상기 제1 수평 연결부와 제2 수평 연결부는, 스트럿 또는 슬래브로 마련될 수 있다.The temporary transition structure may be provided as a transition slab or transition beam, and the first horizontal connection part and the second horizontal connection part may be provided as a strut or a slab.

본 발명은 상기 가설용 전이구조물 상에 설치되는 지상골조를 더 포함할 수 있다.The present invention may further include a ground frame installed on the temporary transition structure.

본 발명에 따른 시공용 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법은, 시공영역의 둘레에서 흙막이를 수직으로 설치하는 흙막이 설치단계; 상기 흙막이의 내부에 복수의 메인포스트를 설치하는 단계; 상기 복수의 메인포스트 상의 일부에 지상 영역을 마련하도록 가설용 전이구조물을 수평하게 설치하는 단계; 상기 흙막이의 내부에서 상기 메인포스트를 따라 일정 깊이씩 순서대로 굴착하는 단계; 및 상기 메인포스트를 따른 굴착 깊이에 따라 상기 복수의 메인포스트의 일부를 제1 수평 연결부에 의해 수평 연결하는 단계; 및 상기 복수의 메인포스트의 일부와 흙막이를 제2 수평 연결부에 의해 수평 연결하는 단계;를 포함하며, 상기 흙막이, 복수의 메인포스트의 일부, 가설용 전이구조물, 및 제1, 2 수평 연결부는, 상기 메인포스트가 설치된 지반에 대해 지상구조물의 시공 하중을 지지하기 위한 구조체를 형성한다.In a building in which the underground structure for construction is a wall-type structure according to the present invention, the air-shortened reverse drilling method in which an early ground framing can be started using a temporary transition structure includes a retaining installation step of vertically installing a retaining wall around a construction area; Installing a plurality of main posts in the interior of the retaining wall; horizontally installing a temporary transition structure to provide a ground area on a part of the plurality of main posts; Excavating in order by a predetermined depth along the main post in the interior of the retaining wall; and horizontally connecting a portion of the plurality of main posts by a first horizontal connection unit according to the excavation depth along the main post; and horizontally connecting a portion of the plurality of main posts and the retaining unit by a second horizontal connection unit; including, the retaining wall, a portion of the plurality of main posts, a temporary transition structure, and the first and second horizontal connecting units, A structure for supporting the construction load of the above-ground structure is formed with respect to the ground on which the main post is installed.

본 발명은 상기 복수의 메인포스트의 각 층별로 상부에서 하부로 복수의 지하층 슬래브를 타설하는 단계; 및 상기 가설용 전이구조물에 대응하는 지하 영역 내에서 상기 지하층 슬래브와 함께 복수의 지하벽체를 타설하여 설치하는 단계;를 더 포함할 수 있다.The present invention comprises the steps of: pouring a plurality of basement slabs from the top to the bottom for each floor of the plurality of main posts; and pouring and installing a plurality of underground walls together with the basement slab in an underground area corresponding to the temporary transition structure.

본 발명은 상기 흙막이의 내부에서 상기 메인포스트가 매립되는 지반 상에 기초콘크리트를 타설하는 단계; 상기 기초콘크리트 상에서 상기 복수의 메인 포스트의 각 층별로 하부에서 상부로 복수의 지하층 슬래브를 타설하는 단계; 및 상기 가설용 전이구조물에 대응하는 지하영역 내에서 상기 지하층 슬래브와 함께 복수의 지하벽체를 타설하는 단계를 더 포함할 수 있다.The present invention comprises the steps of: pouring the foundation concrete on the ground in which the main post is buried in the interior of the retaining wall; pouring a plurality of basement slabs from the bottom to the top for each floor of the plurality of main posts on the foundation concrete; and pouring a plurality of underground walls together with the basement slab in an underground area corresponding to the temporary transition structure.

본 발명은 상기 가설용 전이구조물 상에 지상골조를 설치하는 단계;를 더 포함할 수 있다.The present invention may further include; installing a ground frame on the temporary transition structure.

본 발명은 지하구조물이 벽식구조로 되어 있는 건물에서 지하 최상층바닥(역타 시작층)에 UP-UP방식 또는 Top-Down방식으로 시공되는 지상골조의 하중을 고려하여 전이슬래브 또는 전이보와 같은 가설용 전이구조물을 설치함으로써 지하 시공 시에도 지상골조의 병행시공이 가능하여 공기를 단축시킬 수 있는, 공기단축형 역타공법구조 및 이를 이용한 시공방법을 제공할 수 있다.The present invention is for temporary use such as a transition slab or a transition beam in consideration of the load of the above-ground frame constructed in the UP-UP method or Top-Down method on the uppermost basement floor (reverse start floor) in a building in which the underground structure is a wall structure. By installing the transition structure, it is possible to provide parallel construction of the above-ground frame even in the case of underground construction, thereby reducing the construction period and providing a construction method using the same.

도 1 은 본 발명의 일 실시예에 따른 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법구조의 개략적인 평면도이다.
도 2는 도 1의 A-A'개략적인 단면도이다.
도 3은 도 1의 A-A'다른 개략적인 단면도이다.
도 4는 본 발명에 따른 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법의 순서도이다.
도 5는 본 발명의 일 실시예에 따른 가설전이구조물과 수평부재의 결합 구조 단면도이다.
도 6은 본 발명의 일 실시예에 따른 가설전이구조물과 수평부재의 다른 결합 구조 단면도이다.
1 is a schematic plan view of a shortened construction period in which an early ground frame construction is possible using a temporary transition structure in a building in which an underground structure is a wall structure according to an embodiment of the present invention.
FIG. 2 is a schematic cross-sectional view taken along line A-A' of FIG. 1 .
3 is a schematic cross-sectional view taken along line A-A' of FIG. 1 .
4 is a flowchart of a short-term reverse drilling method in which an early ground framing can be started using a temporary transition structure in a building in which the underground structure is a wall structure according to the present invention.
5 is a cross-sectional view of the coupling structure of the temporary transition structure and the horizontal member according to an embodiment of the present invention.
6 is a cross-sectional view of another coupling structure of a temporary transition structure and a horizontal member according to an embodiment of the present invention.

이하, 본 발명이 속하는 선호적인 실시예를 참고로 하여 더욱 상세하게 설명한다.Hereinafter, it will be described in more detail with reference to preferred embodiments to which the present invention pertains.

도 1 내지 도 3을 참조하면, 본 발명의 일 실시예에 따른 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법구조는, 지하외곽벽체를 마련하여 지하공간을 형성하기 위한 흙막이(100), 흙막이(100)의 내부 영역에 위치하며 흙막이(100)보다 깊게 직립 설치되는 복수의 메인포스트(110), 흙막이(100)의 내부에서 복수의 메인포스트(110) 상의 일부 영역에 탑재 설치되어 지상시공 영역을 마련하는 가설용 전이구조물(120), 복수의 메인포스트(110)를 연결하는 제1 수평 연결부(131) 및 복수의 메인포스트(110)와 흙막이(100)를 연결하는 제2 수평 연결부(132)를 포함한다.1 to 3, the construction of an air shortening type reverse perforation method in which an early ground framing can be started using a temporary transition structure in a building in which the underground structure is a wall structure according to an embodiment of the present invention, by providing an underground outer wall A retaining wall 100 for forming an underground space, a plurality of main posts 110 located in the inner area of the retaining wall 100 and installed upright deeper than the retaining wall 100, a plurality of main posts in the interior of the retaining wall 100 ( 110), a temporary transition structure 120 that is mounted and installed on a partial area to provide a ground construction area, a first horizontal connection part 131 that connects a plurality of main posts 110, and a plurality of main posts 110 and a retaining wall It includes a second horizontal connecting portion 132 for connecting (100).

본 실시예에서는 먼저, 흙막이(100)를 설치한 상태에서, 일부 영역의 메인포스트(110) 상에 가설용 전이구조물(120)를 지면에 수평하게 설치하고, 메인포스트(110)의 각 하부 층별로 제1 수평 연결부(131)에 의해 가설용 전이구조물(120)를 지지하는 메인포스트(110)들을 연결하며, 메인포스트(110)들을 제2 수평 연결부(132)에 의해 흙막이(100)에 연결함으로써 가설용 전이구조물(120) 상의 지상 건축물을 시공할 수 있는 주동부 위치에 대해 가설용 지지 구조체를 마련하는 작업을 수행한다.In this embodiment, first, in a state in which the retaining wall 100 is installed, the temporary transition structure 120 is installed horizontally on the ground on the main post 110 in some area, and each lower floor of the main post 110 is installed. to connect the main posts 110 supporting the temporary transition structure 120 by the first horizontal connection part 131, and connect the main posts 110 to the retaining wall 100 by the second horizontal connection part 132 By doing so, the task of providing a temporary support structure for the main eastern position where the above-ground building can be constructed on the temporary transition structure 120 is performed.

메인포스트(110)는 현장말뚝타설 또는 H빔과 같은 철골기둥조로서, 하단부가 PRD(Percussion rotary drill)공법 등에 의해 연직 방향으로 설치되며, 상단부가 가설용 전이구조물(120)의 내부를 통과하거나 내부에 매립되어 고정 설치된다.The main post 110 is a steel frame structure such as on-site pile casting or H-beam, and the lower end is installed in the vertical direction by a percussion rotary drill (PRD) method, etc., and the upper end passes through the inside of the temporary transition structure 120 or It is embedded inside and fixedly installed.

이러한 메인포스트(110)는 흙막이(100)가 설치된 시공영역에 설치되며, 가설용 전이구조물(120)가 설치되는 영역과 다른 영역에 순서대로 설치될 수 있다.This main post 110 is installed in the construction area where the retaining wall 100 is installed, and may be installed in an orderly area different from the area where the temporary transition structure 120 is installed.

가설용 전이구조물(120)는, 흙막이(100) 내부에 직립 설치된 메인포스트(110)들 중 지상 건축물의 지상골조를 지지하기 위한 일부의 메인포스트(110)들에 설치되는 것으로서, 지상하중의 시공에 따라 발생되는 하중을 메인포스트(110)를 통해 지하층의 하부에 있는 지반으로 전달하는 역할을 하게 된다. 이에 따라 가설용 전이구조물(120)에서 지상 하중은 메인포스트(110)들에 의해 충분히 지반 측으로 전달된다.The temporary transition structure 120 is to be installed on some of the main posts 110 for supporting the above-ground frame of the above-ground building among the main posts 110 installed upright inside the retaining wall 100, and the construction of ground load It serves to transfer the load generated according to the main post 110 to the ground under the basement floor. Accordingly, the ground load in the temporary transition structure 120 is sufficiently transmitted to the ground side by the main posts 110 .

이러한 가설용 전이구조물(120)는, 전체가 콘크리트 타설로 메워진 블록형상의 전이슬래브 또는 상호 연결된 프레임 구조의 개방 형상을 갖는 전이보로 마련되며, 지상골조(160)의 하중을 메인포스트(110)에 전달하면서 압축, 및 전단이나 굽힘에 충분히 견딜 수 있는 두께를 갖되, 하부 지하층의 층간 높이를 제한하지 않는, 바람직하게는 3m 이내의 적절한 두께로 제작된다.This temporary transition structure 120 is provided as a transition beam having an open shape of a block-shaped transition slab or an interconnected frame structure filled with concrete as a whole, and the load of the above-ground frame 160 is applied to the main post 110. It has a thickness that can sufficiently withstand compression, shear, or bending while delivering it, but does not limit the interlayer height of the lower basement, and is preferably manufactured to an appropriate thickness within 3 m.

가설용 전이구조물(120)는 메인포스트(110)의 상단부가 매립되도록 콘크리트가 타설되어 양생된 RC구조나 메인포스트(110)가 결합 가능한 프리캐스트 콘크리트로도 가능한 것으로서, 메인포스트(110)의 상단부에 탑재되어 안정적으로 위치 고정될 수 있는 구조이면 설치 가능하다.The temporary transition structure 120 is a RC structure in which concrete is poured and cured so that the upper end of the main post 110 is buried, or a precast concrete in which the main post 110 can be combined, and the upper end of the main post 110 is available. It can be installed if it has a structure that can be mounted to and fixed in a stable position.

이러한 가설용 전이구조물(120)는 시공되는 건축물의 배치 영역에 배치되는 것으로서, 복수 건물이 경우에는 건물 배치영역에 각각 대응하여 설치된다.The temporary transition structure 120 is disposed in an arrangement area of a building to be constructed, and in the case of a plurality of buildings, is installed corresponding to the building arrangement area.

일예로, 가설용 전이구조물(120)는 일정 두께를 갖는 평평한 콘크리트블록으로서, 건물 시공 작업이 기존 건물을 해체하고 굴착하여 건축하는 경우에, 기존 건물의 지상 바닥부에서 일정 깊이를 굴착한 지하 1층 바닥부에서 일정 높이를 성토한 후 미리 설치된 메인포스트(110) 상에 설치될 수 있다. 이때는 가설용 전이구조물(120)가 메인포스트(110) 상에 설치된 후, 가설용 전이구조물(120)의 하부에 있는 성토는 이후 바닥과 굴토 작업을 위해 제거된다.As an example, the temporary transition structure 120 is a flat concrete block having a certain thickness, and when the building construction work is to dismantle and excavate the existing building and construct it, the underground 1 is excavated to a certain depth from the ground floor of the existing building. It may be installed on the main post 110 installed in advance after filling a certain height at the bottom of the floor. In this case, after the temporary transition structure 120 is installed on the main post 110 , the fill in the lower portion of the temporary transition structure 120 is removed for the subsequent floor and excavation work.

가설용 전이구조물(120)가 설치되고 나서는, 지하 1층 깊이로 구건물의 잔여 구조와 지하토를 철거하고, 가설용 전이구조물(120)을 흙막이(100)와 일체로 고정시키는 구조를 만든다.After the temporary transition structure 120 is installed, the remaining structure and underground soil of the old building are removed to a depth of one floor underground, and the temporary transition structure 120 is integrally fixed with the retaining wall 100 .

가설용 전이구조물(120)의 하부와 측벽부에는 제1 수평 연결부(131)와 제2 수평 연결부(132)가 설치된다. 제1 수평 연결부(131)와 제2 수평 연결부(132)는, 스트럿 또는 슬래브 구조로 마련될 수 있다.A first horizontal connection part 131 and a second horizontal connection part 132 are installed in the lower part and the side wall part of the temporary transition structure 120 . The first horizontal connection part 131 and the second horizontal connection part 132 may be provided in a strut or slab structure.

상기에서 제1 수평 연결부(131)가 스트럿으로 마련되어 설치되는 경우에는, 상하 개방된 공간이 마련되며, 슬래브로 마련되는 경우에는, 지하 시공을 위한 개구부를 제외한 막힌 영역에 수평 슬래브가 지표 및 지하층 슬래브(150)로서 형성된다.In the above, when the first horizontal connection part 131 is provided as a strut and installed as a strut, an upper and lower open space is provided, and when it is provided as a slab, the horizontal slab is located in the blocked area except for the opening for underground construction. (150).

이러한 제1 수평 연결부(131)는 굴착에 따른 깊이 방향으로 지하 1층부터 더 깊은 층으로 굴착에 따라 순차적으로 설치되며, 제2 수평 연결부(132)는 제1 수평 연결부(131)와 함께 설치될 수 있다.The first horizontal connection part 131 is sequentially installed according to the excavation from the first basement level to a deeper layer in the depth direction according to the excavation, and the second horizontal connection part 132 is to be installed together with the first horizontal connection part 131. can

제1 수평 연결부(131)와 제2 수평 연결부(132)가 슬래브로 형성되는 경우에는, RC구조로 마련될 수 있으나, 이에 한정되지 않으며 데크 플레이트가 사용될 수도 있다.When the first horizontal connection part 131 and the second horizontal connection part 132 are formed of a slab, it may be provided in an RC structure, but is not limited thereto, and a deck plate may be used.

상기 제2 수평 연결부(132)는 흙막이(100)와 메인포스트(110) 사이의 하중을 전이시켜 흙막이(100)의 토압하중이나 메인포스트(110)에 가해지는 횡하중을 분산시킴으로써 안정적인 지하구조를 마련하는 역할을 하게 된다.The second horizontal connection part 132 transfers the load between the retainer 100 and the main post 110 to distribute the earth pressure load of the retainer 100 or the lateral load applied to the main post 110 to provide a stable underground structure. will play a role

상기와 같이, 본 실시예에 따르면, 흙막이(100), 메인포스트(110), 가설용 전이구조물(120), 및 제1, 2 수평연결부(131, 132)는 지하 굴착과 지상 시공의 하중을 지지하기 위한 "┏┳┓"와 같이 연결된 단면 형상을 형성하며, 지상골조(160)의 시공을 위한 축하중과 횡하중을 지지할 수 있는 구조체를 이루게 된다.As described above, according to this embodiment, the retaining wall 100, the main post 110, the temporary transition structure 120, and the first and second horizontal connection parts 131 and 132 are the loads of underground excavation and ground construction. It forms a cross-sectional shape connected like “┏┳┓” for supporting, and forms a structure capable of supporting axial and lateral loads for construction of the above-ground frame 160 .

상기에서 제2 수평 연결부(132)가 수평 슬래브로 타설되어 마련되는 경우에는, 층간을 지지하는 지하벽체(155)가 함께 형성될 수 있다. 이러한 지하벽체(155)는 수직, 수평 및 전단 방향으로 작용하는 하중을 지지하게 된다.In the case in which the second horizontal connection part 132 is provided by being poured into a horizontal slab, the basement wall 155 supporting the interlayer may be formed together. The underground wall 155 supports the load acting in the vertical, horizontal and shear directions.

제2 수평 연결부(132)가 층별로 상부에서 하부로 설치됨에 따라 지하벽체(155)가 함께 형성됨으로써 메인포스트(110)에 작용하는 하중이 지하벽체(155)로 전달되어 지지되며, 최하부에 기초콘크리트(140)가 타설되어 설치되는 경우에는 지하벽체(155)가 온전히 메인포스트(110)의 작용하는 하중을 기초콘크리트(140) 측으로 전달하는 역할을 하게 된다.As the second horizontal connection part 132 is installed from the top to the bottom for each floor, the underground wall 155 is formed together, so that the load acting on the main post 110 is transmitted to and supported by the underground wall 155, and the base is at the bottom. When the concrete 140 is poured and installed, the underground wall 155 serves to completely transfer the load acting on the main post 110 to the base concrete 140 side.

상기의 탑다운 시공에서는, 층간을 구성하는 제1 수평 연결부(131)들를 지지하는 수직이음구조인 지하벽체(155)와 지하층 슬래브(150)를 상부에서 하부로 굴착과 함께 설치함으로써 지하벽체(155)에 의한 견고한 지지구조를 굴착이 완료될 때까지 완성시킬 수 있다.In the top-down construction, the basement wall 155 and the basement slab 150, which are vertical joint structures supporting the first horizontal connection parts 131 constituting the floors, are installed together with excavation from the top to the bottom to provide the basement wall 155 ) can be completed until the excavation is completed.

상기와 같이, 본 실시예에 따르면, 메인포스트(110)들을 설치하고, 가설용 전이구조물(120), 및 제1, 2 수평 연결부(131, 132)를 층별로 상부에서 하부로 설치한 상태에서, 지상골조(160)을 가설용 전이구조물(120)에 설치하는 탑다운(Top-Down) 시공이 가능하게 된다.As described above, according to this embodiment, in a state in which the main posts 110 are installed, the temporary transition structure 120 , and the first and second horizontal connection parts 131 and 132 are installed from top to bottom for each floor. , It is possible to construct a top-down (Top-Down) installation of the above-ground frame 160 to the temporary transition structure (120).

본 실시예에 따른 지상골조(160)은, 탑다운과 업업 중 시공 방식의 선택에 따라 기초콘크리트(140)와 지하층 슬래브(150)의 타설 전이나 동시에 가설용 전이구조물(120) 상에 시공될 수 있으며, 기초콘크리트(140)의 타설과 함께 지하층 슬래브(150)가 형성되면서 시공될 수 있다.The above-ground frame 160 according to this embodiment is to be constructed on the transition structure 120 for temporary construction before or at the same time as the foundation concrete 140 and the basement slab 150 according to the selection of the construction method during top-down and up-up. It may be constructed while the basement slab 150 is formed along with the pouring of the foundation concrete 140 .

상기에서는 탑다운(Top-Down) 시공이 가능한 가설용 전이구조물(120)을 이용한 역타공법구조를 설명하였으며, 이하에서는 상기와 같이 지하층 슬래브(150)들과 지하벽체(155)가 완료된 상태에서 지하잔여골조 및 지상골조(160)를 설치하거나, 지하층 슬래브(150)들과 지하벽체(155)이 생략되어 지하굴착을 완료한 상태에서 지하층별로 하부에서 상부로 지하층 슬래브(150)들과 지하벽체(155)를 타설함과 동시에 지하잔여골조 및 지상골조(160)을 설치하는 업업(Up-Up)시공이 가능한 역타공법구조를 설명한다.In the above, the reverse perforation structure using the temporary transition structure 120 capable of top-down construction has been described. Hereinafter, the basement slab 150 and the basement wall 155 are completed in the state where the basement slab 150 and the basement wall 155 are completed as described above. In the state that the remaining and above-ground frames 160 are installed, or the underground slabs 150 and the underground walls 155 are omitted and the underground excavation is completed, the basement slabs 150 and the basement wall ( 155) and at the same time installing the remaining underground frame and the above-ground frame 160 will be described a reverse drilling method structure capable of up-up construction.

다른 실시예에서는, 업업 시공에 따라 지하굴착이 완료된 후, 흙막이(100)의 내부에서 메인포스트(110)가 매립된 지반 상에 타설되는 기초콘크리트(140), 기초콘크리트(140) 상에서 복수의 메인포스트(110)의 각 층별로 순차적으로 타설되는 복수의 지하층 슬래브(150), 및 지상하중 슬래브에 대응하는 지하 영역 내에서 지하층 슬래브(150)와 함께 순차적으로 타설되어 설치되는 복수의 지하벽체(155)가 더 포함된다.In another embodiment, after the underground excavation is completed according to the up-up construction, the main post 110 is poured on the ground in which the main post 110 is buried inside the retainer 100, a plurality of main concrete 140 on the foundation concrete 140. A plurality of basement slabs 150 that are sequentially poured for each floor of the post 110, and a plurality of basement walls 155 that are sequentially poured and installed together with the basement slab 150 in an underground area corresponding to the ground load slab ) is further included.

지하층 슬래브(150)는 제1, 2 수평 연결부(131, 132)가 스트럿으로 마련되는 경우에, 기초콘크리트(140) 상의 지하에서 지상 측으로 순차적으로 타설되어 설치될 수 있으며, 복수의 지하벽체(155)는 지하공간을 구획하거나 건축물의 지하에서 주동부를 지지하는 코어벽체를 형성하는 것으로서, 지하층 슬래브(150)의 타설과 함께 지하층 슬래브(150)에 수직으로 형성된다.When the first and second horizontal connection parts 131 and 132 are provided as struts, the basement slab 150 may be sequentially poured from the basement to the ground side on the foundation concrete 140 and installed, and a plurality of underground walls 155 ) is to form a core wall that partitions an underground space or supports the main body in the basement of a building, and is formed vertically on the basement slab 150 together with the pouring of the basement slab 150 .

이러한 지하벽체(155)는 가설용 전이구조물(120) 및 제1 수평 연결부(131)의 수직 축력을 기초콘크리트(140)에 지지하는 기둥 구조를 형성할 수 있으며, 지하 공간을 구획하게 되므로, 지하공간에서 벽체를 형성하기 위한 공정을 선행 작업으로 대체시킬 수 있다.The underground wall 155 can form a column structure that supports the vertical axial force of the temporary transition structure 120 and the first horizontal connection part 131 to the concrete foundation 140, and divides the underground space. The process for forming walls in a space can be replaced with a predecessor work.

상기와 같이, 본 실시예들에서는, 메인포스트(110) 상에 가설용 전이구조물(120)가 설치되고, 제1, 2 수평 연결부(131, 132)가 설치되어, 지상시공에 따른 지상골조(160)의 하중을 충분히 지지할 수 있는 지지구조를 확보한 상태에서, 가설용 전이구조물(120) 상에 지상벽체가 타설되며, 지상벽체 상에 지상 슬래브가 타설되어 지상골조(160)이 시공될 수 있다.As described above, in the present embodiments, the temporary transition structure 120 is installed on the main post 110, and the first and second horizontal connection parts 131 and 132 are installed, and the above-ground structure according to the above-ground construction ( 160), the above-ground wall is poured on the temporary transition structure 120, and the above-ground slab is poured on the above-ground wall to construct the above-ground frame 160. can

이하에서는, 본 발명의 일 실시예에 따른 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법에 설명한다.Hereinafter, an air shortening type reverse drilling method in which an early ground framing can be initiated using a temporary transition structure in a building in which the underground structure is a wall structure according to an embodiment of the present invention will be described.

도 1 내지 도 4를 참조하면, 본 발명의 일 실시예에 따른 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법은, 시공영역의 둘레에서 흙막이(100)를 수직으로 설치하는 흙막이(100) 설치단계, 흙막이(100)의 내부에 복수의 메인포스트(110)를 설치하는 단계, 복수의 메인포스트(110) 상의 일부에 지상 영역을 마련하도록 가설용 전이구조물(120)를 수평하게 설치하는 단계, 흙막이(100)의 내부에서 메인포스트(110)를 따라 일정 깊이씩 순서대로 굴착하는 단계, 및 메인포스트(110)를 따른 굴착 깊이에 따라 복수의 메인포스트(110)의 일부와 가설용 전이구조물(120)를 제1 수평 연결부(131)에 의해 수평 연결하는 단계, 및 복수의 메인포스트(110)의 일부와 흙막이(100)를 제2 수평 연결부(132)에 의해 수평 연결하는 단계를 포함한다.1 to 4, in the building in which the underground structure is a wall-type structure according to an embodiment of the present invention, the air shortening type reverse drilling method that enables early ground frame construction using a temporary transition structure is a retaining wall ( The retaining wall 100 installation step of vertically installing 100), the step of installing a plurality of main posts 110 in the interior of the retaining wall 100, the plurality of main posts 110 for temporary installation to provide a part of the ground area on the top A step of horizontally installing the transition structure 120, a step of sequentially excavating a predetermined depth along the main post 110 in the interior of the retaining wall 100, and a plurality of main steps according to the excavation depth along the main post 110 A step of horizontally connecting a part of the post 110 and the temporary transition structure 120 by a first horizontal connection part 131, and a part of the plurality of main posts 110 and the retaining wall 100 with a second horizontal connection part ( 132) by horizontal connection.

이러한 본 실시예는, 흙막이(100), 복수의 메인포스트(110)의 일부, 가설용 전이구조물(120), 및 제1, 2 수평 연결부(131, 132)는 메인포스트(110)가 설치된 지반에 대해 지상골조(160)의 시공 하중을 지지하기 위한 구조체를 형성한다.In this embodiment, the retaining wall 100, a portion of the plurality of main posts 110, the temporary transition structure 120, and the first and second horizontal connection parts 131 and 132 are the main posts 110 installed in the ground. To form a structure for supporting the construction load of the above-ground frame (160).

상기와 같은 본 실시예에 따르면, 지상골조(160)의 시공을 위한 지하지지 구조체가 확보되므로, 굴착과 함께 가설용 전이구조물(120) 상에 지상골조(160)을 시공하는 탑다운 시공과 굴착이 완료된 상태에서 지상골조(160)을 시공하는 업업 시공을 선택적으로 수행할 수 있게 된다.According to this embodiment as described above, since the underground support structure for the construction of the above-ground frame 160 is secured, the top-down construction and excavation of constructing the above-ground frame 160 on the temporary transition structure 120 together with excavation In this completed state, it is possible to selectively perform up-up construction for constructing the above-ground frame 160 .

상기와 같이 굴착과 지상골조(160)을 함께 시공하는 탑다운 시공에서는 지하벽체(155)를 RC구조로 설치하여 굴착이 완료됨과 동시에 가설용 전이구조물(120)의 지지와 크게 관계없이 지상골조(160)을 지하벽체(155)와 메인포스트(110)를 통해 지반에 충분히 지지할 수 있는 지지구조를 확보할 수 있다.In the top-down construction in which the excavation and the above-ground frame 160 are constructed together as described above, the underground wall 155 is installed as an RC structure to complete the excavation and at the same time to complete the excavation, regardless of the support of the temporary transition structure 120, the above-ground structure ( 160) through the underground wall 155 and the main post 110, it is possible to secure a support structure that can sufficiently support the ground.

한편, 본 실시예에 따른 공기단축형 역타공법에는, 업업 시공에 따라 지하굴착이 완료된 후, 흙막이(100)의 내부에서 메인포스트(110)가 매립되는 지반 상에 기초콘크리트(140)를 타설하는 단계, 기초콘크리트(140) 상에서 복수의 메인포스트(110)의 각 층별로 순차적으로 복수의 지하층 슬래브(150)를 타설하는 단계, 및 가설용 전이구조물(120)에 대응하는 지하영역 내에서 지하층 슬래브(150)와 함께 순차적으로 복수의 지하벽체(155)를 타설하는 단계가 더 포함될 수 있다.On the other hand, in the air shortening type reverse drilling method according to this embodiment, after the underground excavation is completed according to the up-up construction, pouring the foundation concrete 140 on the ground where the main post 110 is buried inside the retaining wall 100 , sequentially pouring a plurality of basement slabs 150 for each floor of the plurality of main posts 110 on the foundation concrete 140, and the basement slab in the underground area corresponding to the temporary transition structure 120 ( The step of sequentially pouring a plurality of underground walls 155 together with 150) may be further included.

이러한 업업 시공에서는 기초콘크리트(140), 및 지하벽체(155)와 함께 지하층 슬래브(150)가 지하바닥부터 상층부로 설치됨과 동시에 지상골조(160)이 가설용 전이구조물(120)에 상에 시공되는 작업이 진행된다.In this up-up construction, the basement slab 150 is installed from the basement floor to the upper floor together with the foundation concrete 140 and the basement wall 155, and at the same time, the above-ground frame 160 is constructed on the temporary transition structure 120. work is going on

상기와 같은 본 실시예들은, 지하구조물이 벽식구조로 되어 있는 건물에서 지하 최상층바닥(역타 시작층)에 UP-UP방식 또는 Top-Down방식으로 시공되는 지상골조의 하중을 고려하여 전이슬래브 또는 전이보와 같은 가설용 전이구조물(120)을 설치함으로써 지하 시공 시에도 지상골조의 병행시공이 가능하여 공기를 단축시킬 수 있는 장점을 제공한다.In the present embodiments as described above, in a building in which the underground structure is a wall-type structure, a transition slab or transition is taken in consideration of the load of the above-ground structure constructed in the UP-UP method or Top-Down method on the uppermost basement floor (reverse start floor). By installing the temporary transition structure 120 such as a beam, parallel construction of the above-ground frame is possible even during underground construction, thereby providing the advantage of shortening the construction period.

한편, 도 5를 참조하면, 상기 본 실시예들에는, 가설용 전이구조물(120)의 측벽에 설치되며 제2 수평 연결부(132)인 지층 슬래브가 거치되어 지지되는 "ㄱ"형상의 서포트 브라켓(170), 및 서포트 브라켓(170)의 하부를 가설용 전이구조물(120)의 측벽에 고정시키는 케미컬 앵커(171)가 더 포함된다.On the other hand, referring to FIG. 5 , in the present embodiments, a “L”-shaped support bracket installed on the sidewall of the temporary transition structure 120 and supported by a stratum slab that is the second horizontal connection part 132 is mounted on it ( 170), and a chemical anchor 171 for fixing the lower portion of the support bracket 170 to the sidewall of the temporary transition structure 120 is further included.

서포트 브라켓(170)은 가설용 전이구조물(120)에 연결되는 지층 슬래브를 지지하는 것으로서, 케미컬 앵커(171)에 의해 가설용 전이구조물(120)에 견고하게 고정된다. 케미컬 앵커(171)는 주입식 접착용 앵커로서, 앵커의 접착제로 에폭시 접착제를 사용할 수 있다.The support bracket 170 supports the stratum slab connected to the temporary transition structure 120 , and is firmly fixed to the temporary transition structure 120 by a chemical anchor 171 . The chemical anchor 171 is an anchor for injection-type adhesion, and an epoxy adhesive may be used as an adhesive of the anchor.

도 6을 참조하면, 본 실시예에는, 가설용 전이구조물(120)의 측벽에 매입 설치되는 매입 플레이트(180), 매입 플레이트(180)에서 연장되어 가설용 전이구조물(120)의 내부로 설치되는 "ㄱ" 갈고리 형상의 갈고리 보강 바(181), 매입 플레이트(180)를 가설용 전이구조물(120)에 측벽에 고정시키는 복수의 스터드 볼트(182), 및 매입 플레이트(180)에 연결되어 가설용 전이구조물(120)의 측벽에서 돌출 배치되는 가새 플레이트(183)가 더 포함된다.Referring to FIG. 6 , in this embodiment, an embedded plate 180 that is embedded in the sidewall of the temporary transition structure 120 , extends from the embedded plate 180 and is installed inside the temporary transition structure 120 . A hook reinforcing bar 181 in the shape of a "a" hook, a plurality of stud bolts 182 for fixing the embedded plate 180 to the side wall of the transition structure 120 for temporary construction, and the embedded plate 180 are connected to for temporary construction A brace plate 183 protruding from the sidewall of the transition structure 120 is further included.

매입 플레이트(180)는 가설용 전이구조물(120)의 측벽부에 매설되어 스터드 볼트(182)에 의해 고정됨으로써 가설용 전이구조물(120)의 측벽부에서 움직이지 않게 고정된다. 스터드 볼트(182)는 매입 플레이트(180)의 상하 방향을 따라 양측에 복수로 배치된다.The embedded plate 180 is embedded in the side wall of the temporary transition structure 120 and fixed by the stud bolts 182 so as not to move in the side wall of the temporary transition structure 120 . A plurality of stud bolts 182 are disposed on both sides along the vertical direction of the embedded plate 180 .

갈고리 보강바(181)는 제2 수평 연결부(132)로서 영구보로 사용 가능한 수평철골부재와 가설용 전이구조물(120)의 측벽부를 매입 플레이트(180)와 가새 플레이트(183)를 매개로 연결하는 것으로서, 가설용 전이구조물(120)의 측벽부 속으로 갈고리 형상으로 깊게 매설됨으로써 가설용 전이구조물(120)에서 이탈과 움직임을 견고하게 고정시키는 구조를 만들게 된다.The hook reinforcement bar 181 is a second horizontal connecting portion 132, which connects the side wall portion of the horizontal steel frame member usable as a permanent beam and the temporary transition structure 120 via the embedded plate 180 and the brace plate 183. As such, by being deeply buried in a hook shape into the side wall of the temporary transition structure 120 , a structure is made to firmly fix the deviation and movement from the temporary transition structure 120 .

가새 플레이트(183)는 매입 플레이트(180)와 수평철골부재를 결합시키도록 수평철골부재의 플랜지 사이에 있는 양측 벽부에 결합되는 한 쌍으로서, 매입 플레이트(180)에 한 쌍이 연결되어 있으며, 그 사이로 수평철골부재의 수직부재가 배치되는 것이다. 이러한 한 쌍의 가새 플레이트(183)는 수직부재를 사이에 두고 볼트로 체결된다.The brace plate 183 is a pair coupled to both side wall portions between the flanges of the horizontal steel frame member to couple the embedded plate 180 and the horizontal steel frame member, and a pair is connected to the embedded plate 180, between The vertical members of the horizontal steel frame members are arranged. The pair of brace plates 183 are fastened with bolts with a vertical member therebetween.

상기에서는 본 발명의 바람직한 실시예를 참조하여 설명하였지만, 해당 기술 분야의 숙련된 당업자는 하기의 특허 청구의 범위에 기재된 본 발명의 사상 및 영역으로부터 벗어나지 않는 범위 내에서 본 발명을 다양하게 수정 및 변경시킬 수 있음을 이행할 수 있을 것이다.Although the above has been described with reference to preferred embodiments of the present invention, those skilled in the art can variously modify and change the present invention within the scope without departing from the spirit and scope of the present invention as set forth in the claims below. You can do what you can do.

100 : 흙막이 110: 메인포스트
120: 가설용 전이구조물 131: 제1 수평 연결부
132: 제2 수평 연결부 140: 기초콘크리트
150: 지하층 슬래브 155: 지하벽체
160: 지상구조물 170: 서포트 브라켓
171: 케이컬 앵커 180: 매입 플레이트
181: 갈고리 보강 바 182: 스터드 볼트
183: 가세 플레이트
100: earth wall 110: main post
120: transition structure for temporary use 131: first horizontal connection part
132: second horizontal connection 140: concrete foundation
150: basement slab 155: basement wall
160: ground structure 170: support bracket
171: cable anchor 180: embedded plate
181: hook reinforcement bar 182: stud bolt
183: gas plate

Claims (6)

지하공간을 형성하기 위한 흙막이;
상기 흙막이의 내부에 위치하며, 상기 흙막이의 내부에서 지반에 직립 설치되는 복수의 메인포스트;
상기 흙막이의 내부에서 상기 복수의 메인포스트의 일부에 탑재되어 설치되며, 지상구조물의 지지를 위한 시공영역을 마련하도록 지면에 수평하게 설치되는 가설용 전이구조물;
상기 가설용 전이구조물에 대응하는 지하의 각층에서 상기 가설용 전이구조물을 지지하는 상기 복수의 메인포스트의 일부를 수평 연결하는 제1 수평 연결부; 및
상기 가설용 전이구조물의 외측에서 상기 흙막이와 가설용 전이구조물을 연결하는 제2 수평 연결부;를 포함하는 것을 특징으로 하는 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법구조.
retaining wall to form an underground space;
a plurality of main posts located inside the retaining wall and installed upright in the ground from the inside of the retaining wall;
a temporary transition structure mounted on a portion of the plurality of main posts in the retaining wall and installed horizontally on the ground to provide a construction area for supporting the above-ground structure;
a first horizontal connection unit horizontally connecting a portion of the plurality of main posts supporting the temporary transition structure in each basement level corresponding to the temporary transition structure; and
A second horizontal connection part connecting the retaining wall and the temporary transition structure from the outside of the temporary transition structure; Air shortened reverse punching structure.
제 1 항에 있어서,
상기 복수의 메인포스트의 각 층별로 상부에서 하부로 타설되는 복수의 지하층 슬래브; 및
상기 가설용 전이구조물에 대응하는 지하 영역 내에서 상기 지하층 슬래브와 함께 타설되어 설치되는 복수의 지하벽체;를 더 포함하는 것을 특징으로 하는 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법구조.
The method of claim 1,
a plurality of basement slabs poured from the top to the bottom for each floor of the plurality of main posts; and
A plurality of underground walls installed together with the basement slab in an underground area corresponding to the temporary transition structure; Reverse perforation structure with shortened construction period that can start the frame.
제 1 항에 있어서,
상기 흙막이의 내부에서 상기 메인포스트가 매립된 지반 상에 타설되는 기초콘크리트;
상기 기초콘크리트 상에서 상기 복수의 메인포스트의 각 층별로 하부에서 상부로 순차적으로 타설되는 복수의 지하층 슬래브; 및
상기 가설용 전이구조물에 대응하는 지하 영역 내에서 상기 지하층 슬래브와 함께 타설되어 설치되는 복수의 지하벽체;를 더 포함하는 것을 특징으로 하는 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법구조.
The method of claim 1,
Foundation concrete poured on the ground in which the main post is buried in the interior of the retaining wall;
a plurality of basement slabs sequentially poured from the bottom to the top for each floor of the plurality of main posts on the foundation concrete; and
A plurality of underground walls installed together with the basement slab in an underground area corresponding to the temporary transition structure; Reverse perforation structure with shortened construction period that can start the frame.
시공영역의 둘레에서 흙막이를 수직으로 설치하는 흙막이 설치단계;
상기 흙막이의 내부에 복수의 메인포스트를 설치하는 단계;
상기 복수의 메인포스트 상의 일부에 지상 영역을 마련하도록 가설용 전이구조물을 수평하게 설치하는 단계;
상기 흙막이의 내부에서 상기 메인포스트를 따라 일정 깊이씩 순서대로 굴착하는 단계; 및
상기 메인포스트를 따른 굴착 깊이에 따라 상기 복수의 메인포스트의 일부를 제1 수평 연결부에 의해 수평 연결하는 단계; 및
상기 복수의 메인포스트의 일부와 흙막이를 제2 수평 연결부에 의해 수평 연결하는 단계;를 포함하며,
상기 흙막이, 복수의 메인포스트의 일부, 가설용 전이구조물, 및 제1, 2 수평 연결부는, 상기 메인포스트가 설치된 지반에 대해 지상구조물의 시공 하중을 지지하기 위한 구조체를 형성하는 것을 특징으로 하는 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법.
A retaining wall installation step of vertically installing the retaining wall around the perimeter of the construction area;
Installing a plurality of main posts in the interior of the retaining wall;
horizontally installing a temporary transition structure to provide a ground area on a part of the plurality of main posts;
Excavating in order by a predetermined depth along the main post in the interior of the retaining wall; and
horizontally connecting a portion of the plurality of main posts by a first horizontal connection unit according to the excavation depth along the main post; and
Including; horizontally connecting a portion of the plurality of main posts and the retaining wall by a second horizontal connection unit;
The retaining wall, a portion of the plurality of main posts, the temporary transition structure, and the first and second horizontal connecting portions form a structure for supporting the construction load of the above-ground structure with respect to the ground on which the main post is installed. In a building with a wall-type structure, a shortened construction period type reverse drilling method that enables early ground framing using a temporary transition structure.
제 4 항에 있어서,
상기 복수의 메인포스트의 각 층별로 상부에서 하부로 복수의 지하층 슬래브를 타설하는 단계; 및
상기 가설용 전이구조물에 대응하는 지하 영역 내에서 상기 지하층 슬래브와 함께 복수의 지하벽체를 타설하여 설치하는 단계;를 더 포함하는 것을 특징으로 하는 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법.
5. The method of claim 4,
pouring a plurality of basement slabs from the top to the bottom for each floor of the plurality of main posts; and
Using a temporary transition structure in a building in which the underground structure is a wall-type structure, further comprising; pouring and installing a plurality of underground walls together with the basement slab in an underground area corresponding to the temporary transition structure Short-duration type reverse drilling method that enables early ground frame start-up.
제 4 항에 있어서,
상기 흙막이의 내부에서 상기 메인포스트가 매립되는 지반 상에 기초콘크리트를 타설하는 단계;
상기 기초콘크리트 상에서 상기 복수의 메인 포스트의 각 층별로 하부에서 상부로 복수의 지하층 슬래브를 타설하는 단계; 및
상기 가설용 전이구조물에 대응하는 지하영역 내에서 상기 지하층 슬래브와 함께 복수의 지하벽체를 타설하는 단계를 더 포함하는 특징으로 하는 지하구조물이 벽식구조인 건물에서 가설전이구조물을 이용하여 조기지상골조 착수가 가능한 공기단축형 역타공법.
5. The method of claim 4,
pouring the foundation concrete on the ground in which the main post is buried in the inside of the retaining wall;
pouring a plurality of basement slabs from the bottom to the top for each floor of the plurality of main posts on the foundation concrete; and
In a building in which the underground structure is a wall-type structure, the method further comprising the step of pouring a plurality of underground walls together with the basement slab in the underground area corresponding to the temporary transition structure Possible air shortening type reverse punching method.
KR1020210001429A 2020-01-08 2021-01-06 In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures KR20210090100A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1020200002593 2020-01-08
KR20200002593 2020-01-08

Publications (1)

Publication Number Publication Date
KR20210090100A true KR20210090100A (en) 2021-07-19

Family

ID=77125893

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210001429A KR20210090100A (en) 2020-01-08 2021-01-06 In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures

Country Status (1)

Country Link
KR (1) KR20210090100A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024037586A1 (en) * 2022-08-19 2024-02-22 中建三局集团(浙江)有限公司 Double-foundation-pit double-working-condition construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101632701B1 (en) 2014-04-29 2016-06-22 이승우 Circular prefabricated structure for column, Top down method and Construction method of frame using the same

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101632701B1 (en) 2014-04-29 2016-06-22 이승우 Circular prefabricated structure for column, Top down method and Construction method of frame using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024037586A1 (en) * 2022-08-19 2024-02-22 中建三局集团(浙江)有限公司 Double-foundation-pit double-working-condition construction method

Similar Documents

Publication Publication Date Title
KR101107567B1 (en) For top down methode of rc structure, the connecting devices between beam structure and vertical steel material, the supporting structures of exclusive use, and the construction method using these devices
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
CN114134931B (en) Reverse construction method for developing basement structure of existing building
KR20190022132A (en) Top-down method using precast-concrete colum
JP3799036B2 (en) Building basic structure and construction method
KR102396786B1 (en) Underground expansion and top-down method of new building using reinforcement of existing underground outer wall
RU2220258C1 (en) Process of erection of multilevel underground structure ( variants )
JP5865567B2 (en) Connecting slab and its construction method
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
KR20210090100A (en) In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
KR20100043161A (en) Pillar construction method by layer-built and frame construction method adapting the same
KR102409591B1 (en) Apartment remodeling construction method for construction duration reduction
JP4612422B2 (en) Construction method of structure and foundation structure used for it
JP2003003690A (en) Base isolation building and method for base isolation of exisiting building
KR20110043976A (en) Top-down method using precast column and building structure thereof
JP7106305B2 (en) Structural columns and seismically isolated buildings
JP3057466B2 (en) How to build underground structures
JP2736542B2 (en) Construction method of underground structure omitting temporary materials
WO2021149266A1 (en) Building construction method
KR102500803B1 (en) Method to Construction an underground tunnel in a Structure
JPH1130053A (en) Construction method of base isolation building
RU190322U1 (en) Device for the construction of multi-storey underground structures
KR102583537B1 (en) Top-down construction method for uneven-slope site
KR101255610B1 (en) Structure construction method and structure of use it
JP7275793B2 (en) Position adjusting device and method for adjusting position of structural column

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E601 Decision to refuse application