KR102396786B1 - Underground expansion and top-down method of new building using reinforcement of existing underground outer wall - Google Patents
Underground expansion and top-down method of new building using reinforcement of existing underground outer wall Download PDFInfo
- Publication number
- KR102396786B1 KR102396786B1 KR1020200099675A KR20200099675A KR102396786B1 KR 102396786 B1 KR102396786 B1 KR 102396786B1 KR 1020200099675 A KR1020200099675 A KR 1020200099675A KR 20200099675 A KR20200099675 A KR 20200099675A KR 102396786 B1 KR102396786 B1 KR 102396786B1
- Authority
- KR
- South Korea
- Prior art keywords
- wall
- underground
- construction
- reinforcing plate
- existing
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
- E02D29/055—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0007—Production methods using a mold
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
본 발명은 기존 지하 외벽의 두께와 대지가 협소하고 인접 건물로 인하여 흙막이 벽체 시공이 불가한 상태에서 기존 지하 외벽의 보강을 통해 신설 건물의 지하 증축 공사 중에는 기존 지하 외벽을 가설 흙막이 벽체로 활용하고 공사 완료 후에는 지하 층축(신축) 구조물의 외벽을 형성하기 위한 영구거푸집으로 활용할 수 있도록 한 신설 건물의 지하 증축 및 역타 공법을 제공한다.
본 발명에 따른 기존 지하 외벽의 보강을 통한 신설 건물의 지하 증축 및 역타 공법은, 지하에 기존 건축물의 지하 외벽이 있는 경우 신설 건물을 증축하는 공법에 있어서, 기존 지하 외벽의 현황을 파악하며 콘크리트 강도와 두께를 필수 조건으로 확인하는 1단계와; 1단계에서 확인된 조건을 기준으로 시공 단계의 토압에 대응하도록 1차 보강판을 준비한 후, 지하 외벽에 1차 보강판을 수직방향으로 부착시켜 지하 외벽을 지하 전층에 걸쳐 1차 보강판으로 보강한 후, 지하 외벽을 갖는 지하 전층에 지하골조의 공사를 수행하는 2단계와; 지하골조의 공사가 완료되면, 1차 보강판이 설치된 지하 외벽측에 철근을 배근하는 3단계와; 1차 보강판이 설치된 지하 외벽측에 2차 보강판의 시공을 위한 고정앵커를 설치하는 4단계와; 지하 외벽에 맞도록 보강 및 거푸집 기능을 하는 2차 보강판을 상기 고정앵커를 사용하여 설치하는 5단계와; 상기 1차 보강판과 2차 보강판의 사이에 콘크리트를 충진하여 기존 지하 외벽에 합성되는 신축 합벽을 형성하는 6단계;를 포함하는 것을 특징으로 한다.The present invention uses the existing underground outer wall as a temporary retaining wall during the underground extension of a new building through reinforcement of the existing underground outer wall in a state where the thickness and site of the existing underground outer wall are narrow and the retaining wall construction is impossible due to the adjacent building. After completion, the underground extension and reverse drilling method of the new building will be provided so that it can be used as a permanent form to form the outer wall of the underground storey (new construction) structure.
The underground extension and reverse drilling method of a new building through reinforcement of an existing underground outer wall according to the present invention is a method of extending a new building when there is an underground outer wall of an existing building in the basement. and the first step of confirming the thickness as essential conditions; After preparing the primary reinforcing plate to respond to the earth pressure of the construction stage based on the conditions confirmed in step 1, attach the primary reinforcing plate to the underground outer wall in the vertical direction to reinforce the underground outer wall with the primary reinforcing plate over the entire basement floor After that, the second step of performing the construction of an underground frame on the entire basement level having an underground outer wall; When the construction of the underground frame is completed, the third step of reinforcing reinforcing bars on the side of the underground outer wall where the primary reinforcing plate is installed; A fourth step of installing a fixed anchor for the construction of the secondary reinforcement plate on the side of the underground outer wall where the primary reinforcement plate is installed; a fifth step of installing a secondary reinforcing plate serving as reinforcement and formwork to fit the underground outer wall using the fixed anchor; and a sixth step of filling concrete between the first reinforcing plate and the second reinforcing plate to form an expansive composite wall synthesized in an existing underground outer wall.
Description
본 발명은 신설 건물의 지하 증축 및 역타 공법에 관한 것으로, 특히 기존 지하 외벽의 두께와 대지가 협소하고 인접 건물로 인하여 흙막이 벽체 시공이 불가한 상태에서 기존 지하 외벽의 보강을 통해 신설 건물의 지하를 증축할 수 있도록 한 신설 건물의 지하 증축 및 역타 공법에 관한 것이다.The present invention relates to an underground extension and reverse construction method of a new building. In particular, the thickness and site of the existing underground external wall are narrow, and the construction of a retaining wall is impossible due to an adjacent building. It is about the underground extension and reverse construction method of a new building that can be extended.
기존 지하 N층 건축물을 철거하거나 신축을 위해서는 기존지하 외벽 외부에 있는 기존 흙막이 벽체 외측으로 흙막이 벽체를 신설해야 한다. 그러나, 기존 지하외벽 두께와 대지의 협소, 인접 건물로 인하여 흙막이 벽체 시공이 불가한 경우가 있다. In order to demolish or build a new basement N-story building, a new retaining wall must be built outside the existing retaining wall outside the existing underground outer wall. However, there are cases where it is impossible to construct a retaining wall due to the existing underground outer wall thickness, the narrow site, and adjacent buildings.
일 예로, 검토 현장의 기존 건축물은 지하 5층, 지상 5층 건물이며, 신축 계획은 지하 3층 지상 17층 규모 건축물인 경우, 본 검토 현장의 특징은 대지의 단변의 폭이 약 20.1m이고, 기존 지하외벽 내측 폭이 17m로, 지하구조물이 대지의 면적을 거의 차지하고 있는 상태이다. 신축건물은 오피스텔로 인하여 주차장 확보를 위하여 기계식 주차장을 설계되었으나, 기계식 주차장의 철골 프레임으로 인하여 지하외벽 내측 폭으로 16.3m 이상 필요하다.For example, if the existing building at the review site is a building with 5 stories below ground and 5 stories above the ground, and the new construction plan is a building with 3 stories below the ground and 17 stories above the ground, the feature of this review site is that the width of the short side of the site is about 20.1 m, The inner width of the existing underground outer wall is 17m, and the underground structure occupies almost the area of the site. For the new building, a mechanical parking lot was designed to secure a parking lot due to the officetel.
이같이 신축 공사가 필요한 현장에 기존 건축물이 들어서 있는 경우, 신축 지하 외벽의 내측 폭이 기존 지하 외벽의 내측 폭보다 작지만 크게 1M 이내로 차이가 나지 않는 경우 흙막이 벽체 시공이 불가능하다. 또한 레이커 방식을 이용하여 기존 지하구조물을 철거 할 수도 있으나, 시공이 거의 불가한 임시 흙막이 벽체 시공과, 철거하면서 되메우고 다시 굴토하는 공정으로 인하여 공기 증가와 공사비 증가와 같은 문제점이 발생하게 된다. 예로, 지하 5층 규모를 레이커 방식으로 철거 하는 것은 현실적으로 어렵다.When an existing building is located at a site requiring new construction, it is impossible to construct a retaining wall if the inner width of the new underground outer wall is smaller than the inner width of the existing underground outer wall but does not differ significantly within 1M. In addition, existing underground structures can be demolished using the raker method, but problems such as increase in construction period and construction cost occur due to the construction of temporary retaining walls, which is almost impossible to construct, and the process of backfilling and excavating during demolition. For example, it is realistically difficult to demolish the 5th basement floor using the raker method.
따라서 기존 건축물의 지하 증축이 필요한 경우 인접 건물의 영향을 받지 않고, 또한 별도의 CIP 공법을 사용하지 않으므로 경제성을 가지며, 신설 지하 외벽을 합벽으로 형성시켜 넓은 공간 확보가 유리한 새로운 공법이 요구된다.Therefore, when an underground extension of an existing building is required, a new construction method is required that is not affected by adjacent buildings, has economical efficiency because it does not use a separate CIP method, and is advantageous in securing a large space by forming a new underground outer wall with a composite wall.
본 발명의 배경이 되는 기술로는 한국 등록특허 등록번호 제10-1612521호로서, '변형억제 및 합벽식 지하구조물 시공방법'이 제안되어 있다. 이는 상측은 지하 흙막이구조물을 선행 시공하고, 하측은 탑다운공법으로 시공함으로써, 굴착된 인접 지반을 안전하게 지지하면서 지하구조물을 안전하고 경제적으로 시공하도록 한 것이다. 그러나 상기 배경기술은 지반 굴착 과정이 필요하고, 지반 보강을 위해 인접한 건물의 하부로 소일네일링의 설치 등으로 인해 기존 건축물의 지하 증축을 시공하는 공법에는 적용하기가 어렵다.As the background technology of the present invention, as Korean Patent Registration No. 10-1612521, 'deformation suppression and construction method of a junction wall type underground structure' is proposed. This is to construct the underground structure safely and economically while safely supporting the excavated adjacent ground by prior construction of the underground retaining structure on the upper side and the top-down method on the lower side. However, the above background technology requires a ground excavation process, and is difficult to apply to a method of constructing an underground extension of an existing building due to the installation of nail nailing to the lower part of an adjacent building for ground reinforcement.
본 발명의 배경이 되는 다른 기술로는 한국 등록특허 등록번호 제10-1296856호로서, '지하 구조물의 벽체 보강 구조체 및 이를 이용한 지하 구조물의 구축방법'이 제안되어 있다. 이는 지하 구조물의 벽체를 감소시키더라도 토압 지지구조를 강화하고 슬라브의 하중을 견딜 수 있으며, 지하구조물의 공간 활용도를 향상시키도록 한 것이다. 그러나 이 배경기술을 기존 지하구조물에 적용하는 경우 흙막이벽을 새로 구축해야 함으로 지하공간의 폭이 좁아지고 경제성이 떨어지는 문제가 발생된다.As another technology that is the background of the present invention, as Korean Patent Registration No. 10-1296856, 'a wall reinforcement structure of an underground structure and a method of constructing an underground structure using the same' are proposed. Even if the wall of the underground structure is reduced, the earth pressure support structure can be strengthened, the slab load can be endured, and the space utilization of the underground structure is improved. However, when this background technology is applied to an existing underground structure, a new retaining wall must be built, which causes a narrow width of the underground space and lowers economic efficiency.
본 발명은 기존 지하 외벽의 두께와 대지가 협소하고 인접 건물로 인하여 흙막이 벽체 시공이 불가한 상태에서 기존 지하 외벽의 보강을 통해 신설 건물의 지하 증축 공사 중에는 기존 지하 외벽을 가설 흙막이 벽체로 활용하고 공사 완료 후에는 지하 층축(신축) 구조물의 외벽을 형성하기 위한 영구거푸집으로 활용할 수 있도록 한 신설 건물의 지하 증축 및 역타 공법을 제공함에 그 목적이 있다.The present invention uses the existing underground outer wall as a temporary retaining wall during the underground extension of a new building through reinforcement of the existing underground outer wall in a state where the thickness and site of the existing underground outer wall are narrow and the retaining wall construction is impossible due to the adjacent building. After completion, the purpose of this is to provide an underground extension and reverse drilling method for a new building that can be used as a permanent form to form the outer wall of an underground storey (new construction) structure.
본 발명에 따른 기존 지하 외벽의 보강을 통한 신설 건물의 지하 증축 및 역타 공법은, 지하에 기존 건축물의 지하 외벽이 있는 경우 신설 건물을 증축하는 공법에 있어서, 기존 지하 외벽의 현황을 파악하며 콘크리트 강도와 두께를 필수 조건으로 확인하는 1단계와; 1단계에서 확인된 조건을 기준으로 시공 단계의 토압에 대응하도록 1차 보강판을 준비한 후, 지하 각층의 슬래브에 부분적으로 두께 방향으로 형성시킨 개구부를 통과하여 지하 외벽에 1차 보강판을 수직방향으로 연속적으로 부착시켜 지하 외벽을 지하 전층에 걸쳐 1차 보강판으로 보강한 후, 지하 외벽을 갖는 지하 전층에 지하골조의 공사를 수행하는 2단계와; 지하골조의 공사가 완료되면, 1차 보강판이 설치된 지하 외벽측에 철근을 배근하는 3단계와; 1차 보강판이 설치된 지하 외벽측에 2차 보강판의 시공을 위한 고정앵커를 설치하는 4단계와; 지하 외벽에 맞도록 보강 및 거푸집 기능을 하는 2차 보강판을 상기 고정앵커를 사용하여 설치하는 5단계와; 상기 1차 보강판과 2차 보강판의 사이에 콘크리트를 충진하여 기존 지하 외벽에 합성되는 신축 합벽을 형성하는 6단계;를 포함하는 것을 특징으로 한다.The underground extension and reverse drilling method of a new building through reinforcement of an existing underground outer wall according to the present invention is a method of extending a new building when there is an underground outer wall of an existing building in the basement. and the first step of confirming the thickness as essential conditions; After preparing the first reinforcing plate to respond to the earth pressure of the construction stage based on the conditions confirmed in step 1, it passes through the opening partially formed in the slab of each basement level in the thickness direction and attaches the first reinforcing plate to the basement wall in the vertical direction a second step of continuously attaching the basement wall with a primary reinforcing plate over the entire basement level, and then performing the construction of an underground frame on the entire basement floor having the basement exterior wall; When the construction of the underground frame is completed, the third step of reinforcing reinforcing bars on the side of the underground outer wall where the primary reinforcing plate is installed; A fourth step of installing a fixed anchor for the construction of the secondary reinforcement plate on the side of the underground outer wall where the primary reinforcement plate is installed; a fifth step of installing a secondary reinforcing plate serving as reinforcement and formwork to fit the underground outer wall using the fixed anchor; and a sixth step of filling concrete between the first reinforcing plate and the second reinforcing plate to form an expansive composite wall synthesized in an existing underground outer wall.
삭제delete
또한, 1차 보강판은 일정하게 이격된 유간을 가지고 배열되어져 설치된 것을 특징으로 한다.In addition, the primary reinforcing plate is characterized in that it is arranged and installed with intervals that are regularly spaced apart.
여기서, 지하골조의 공사는 지하 각층에 PRD(Percussion Rotary Drill) 시공을 위해 PRD장비의 하중을 고려하여 PRD장비 지지용 잭 서포트를 설치하는 단계와; PRD 시공을 위하여 신축구조물의 기둥이 시공될 위치를 선택하여 지상 1층과 지하 각층의 슬래브 및 기존 기초에 열려진 개구부를 형성시킨 후 PRD 공사로 신설 말뚝을 설치하는 단계와; 기존 구조물의 1층 슬래브를 포함한 보 및 기둥을 철거하고, 지상1층 신설 슬래브를 시공하는 단계와; 지하 각층의 슬래브를 포함한 보 및 기둥의 순차적인 하향식 철거 그리고 해당 철거 층에서의 신설 슬래브를 신축하는 공사를 반복하는 단계;를 포함하는 것을 특징으로 한다.Here, the construction of the underground frame includes the steps of installing a jack support for supporting the PRD equipment in consideration of the load of the PRD equipment for the construction of a percussion rotary drill (PRD) on each basement floor; For PRD construction, the steps of selecting a location where the columns of the new structure will be constructed, forming an opening in the slabs and existing foundations of the first and basement floors above the ground, and installing new piles by PRD construction; Demolition of beams and columns including the first-floor slab of the existing structure, and constructing a new first-floor slab; and repeating the sequential top-down demolition of beams and columns, including the slabs of each basement floor, and the construction of new slabs on the corresponding demolished floor.
본 발명의 기존 지하 외벽의 보강을 통한 신설 건물의 지하 증축 및 역타 공법에 따르면, 신축 합벽의 형성으로 기존 지하 외벽의 보강이 이루어지기 때문에 기존 지하외벽 두께와 대지 협소, 인접 건물로 인하여 흙막이 벽체 시공이 불가한 상태에서 적용이 유리하다. According to the underground extension and reverse drilling method of a new building through reinforcement of the existing underground exterior wall of the present invention, the existing basement exterior wall is reinforced by the formation of a new composite wall, so the existing basement exterior wall thickness and site narrow, and the retaining wall construction due to the adjacent building Application in this impossible state is advantageous.
또한, 임시 흙막이 벽체의 시공과 철거, 되메우기 및 굴토 공정이 제거되어져 공기가 단축되고, 2차 보강판이 보강과 함께 거푸집의 역할을 수행하게 되어 경제성 시공이 가능해진다.In addition, the construction and demolition of the temporary retaining wall, backfilling and excavation processes are eliminated to shorten the construction period, and the secondary reinforcing plate serves as a formwork together with reinforcement, making economical construction possible.
또한, 기존 지하 외벽의 보강을 통해 신설 건물의 지하를 증축할 수 있어 기존 지하 외벽의 두께와 대지가 협소하고 인접 건물로 인하여 흙막이 벽체 시공이 불가한 상태에서 유용하다.In addition, it is possible to extend the basement of a new building by reinforcing the existing underground wall, so it is useful when the thickness of the existing underground wall and the site are narrow and it is impossible to construct a retaining wall due to an adjacent building.
또한, 기존 외벽(옹벽)에 보강판이 설치되어 보강 뿐만 아니라 가설 흙막이 벽체(CIP)의 역할을 수행할 수 있고, 굴착 깊이를 깊게할 수 있어 시공성이 향상된다.In addition, a reinforcing plate is installed on the existing outer wall (retaining wall) to perform the role of not only reinforcement but also a temporary retaining wall (CIP), and the excavation depth can be deepened, thereby improving workability.
본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1 내지 도 5는 본 발명에 따른 신설 건물의 지하 증축을 위한 기존 지하 외벽의 보강 순서도로서,
도 1의 (A),(B)는 1차 보강판으로 지하 외벽을 보강하는 사시도 및 일측면도이고,
도 2의 (A),(B)는 1차 보강판의 전면에 철근을 배근한 사시도 및 일측면도이고,
도 3의 (A),(B)는 1차 보강판의 전면에 고정앵커를 설치한 사시도 및 일측면도이고,
도 4의 (A),(B)는 2차 보강판을 고정앵커를 통해 설치한 사시도 및 일측면 확대도이고,
도 5는 1차 보강판과 2차 보강판의 사이에 콘크리트를 타설하여 신축 합벽을 형성시킨 측면도이다.
도 6 내지 도 23은 본 발명에 따른 신설 건물의 지하 증축을 위한 역타 공법의 순서도이다.The following drawings attached to this specification illustrate preferred embodiments of the present invention, and serve to further understand the technical spirit of the present invention together with the detailed description of the present invention, so the present invention is limited to the matters described in the accompanying drawings It should not be construed as being limited.
1 to 5 are a reinforcement flow chart of an existing underground outer wall for an underground extension of a new building according to the present invention,
1 (A), (B) is a perspective view and one side view of reinforcing the basement outer wall with a primary reinforcing plate,
2 (A), (B) is a perspective view and a side view of reinforcing reinforcing bars on the front surface of the primary reinforcing plate,
3 (A), (B) is a perspective view and a side view in which a fixed anchor is installed on the front surface of the primary reinforcing plate,
4 (A) and (B) are a perspective view and an enlarged view of one side in which the secondary reinforcing plate is installed through a fixed anchor,
5 is a side view illustrating a new construction wall formed by pouring concrete between a primary reinforcing plate and a secondary reinforcing plate.
6 to 23 are flowcharts of a reverse punching method for underground extension of a new building according to the present invention.
아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다.Hereinafter, the present invention will be described in detail with reference to the embodiments shown in the accompanying drawings, but the presented embodiments are illustrative for a clear understanding of the present invention, and the present invention is not limited thereto.
본 발명은 지하에 기존 건축물(10)의 지하 외벽(12)이 있는 경우 신설 건물을 증축하는 공법에 적용된다.The present invention is applied to a construction method of extending a new building when there is an underground
먼저, 1단계로 도 1 및 도 6에 도시된 기존 지하 외벽(12)의 현황을 파악하며, 콘크리트 강도와 두께를 필수 조건으로 확인한다. 설계도서가 없는 경우에는 코아 시험을 통하여 콘크리트 강도 및 두께를 확인 할 수 있다. 여기에서 철근 배근은 지하 층고 변경으로 인하여 기존 배근의 상태와 구조해석에 의해 필요 구간이 변경되므로 안전측으로 최소 철근비로 철근 배근을 정한다.First, as a first step, the current status of the existing underground
그 다음, 2단계로 도 1과 같이 지하 외벽(12)의 콘크리트 강도와 두께를 고려하여 보강될 1차 보강판(21)을 준비한다. 1차 보강판(21)은 일정한 두께와 폭(w)을 갖는다. 대부분 토압은 수직 방향으로 작용하므로, 1차 보강판(21)의 보강은 수직 방향으로 설치한 후 지하 수평 골조를 시공한다. 도 2와 같이 기존 지하 슬래브(13)에 간섭이 발생하는 경우에는 외벽으로 일정 간격으로 부분적으로 슬래브에 개방(OPEN)된 개구부(13a)를 형성시켜서 1차 보강판(21)을 연속하여 보강할 수 있다.Next, in the second step, as shown in FIG. 1 , the
그 다음, 도 1 및 도 7과 같이 지하 외벽(12)에 1차 보강판(21)을 수직방향으로 부착시켜 지하 외벽(12)을 1차 보강판(21)으로 보강하는 단계를 갖는다. 본 실시 예에서 1차 보강판(21)은 복열의 앵커볼트(25)를 통해 지하 외벽(12)에 설치되어 있다.Next, as shown in FIGS. 1 and 7 , the
이때 보강영역의 불연속이 발생되지 않도록 1차 보강판(21)은 지하 각층(B1F~B5F)의 슬래브(13)에 부분적으로 두께 방향으로 형성시킨 개구부(13a)를 통과하여 연속적으로 설치될 수 있다. 또한 1차 보강판(21)은 시공의 경제성과 용의성을 고려하여 일정하게 이격된 유간(G)을 가지고 배열되어져 설치됨이 바람직하다.At this time, the
그 다음, 도 8 내지 도 19와 같이 지하 외벽(12)을 갖는 지하 전층(B1F~B5F)에 지하골조의 공사를 수행하는 단계를 갖는다. 지하골조에 대한 공사는 후에 별도로 기술한다.Then, as shown in FIGS. 8 to 19 , it has a step of performing the construction of an underground frame on the entire basement floor (B1F to B5F) having an underground
그 다음, 지하골조의 공사가 완료되면, 도 2와 같이 1차 보강판(21)이 설치된 지하 외벽(12)측에 철근(30)을 배근하는 단계를 갖는다. 본 실시 예에서 철근(30)은 압축력을 분담하는 수직철근(31)과 수직철근(31)의 위치를 고정하고 좌굴을 방지하는 띠철근(32)을 포함한다. 띠철근(32)은 수직철근(31)에 대해 직각을 이루어 배치된다.Next, when the construction of the underground frame is completed, as shown in FIG. 2 , there is a step of reinforcing the reinforcing
그 다음, 도 3과 같이 1차 보강판(21)이 설치된 지하 외벽(12)측에 2차 보강판(22)의 시공을 위한 고정앵커(40)를 설치하는 단계를 갖는다. 고정앵커(40)는 본 실시 예와 같이 1차 보강판(21)측에 고정 설치될 수도 있지만 지하 외벽(12)측에 더 설치될 수도 있다. 고정앵커(40)는 앵커볼트, 세트앵커볼트, 케미컬 앵커 등등이 될 수 있다.Next, as shown in FIG. 3 , there is a step of installing a
그 다음, 도 4와 같이 고정앵커(40)를 사용하여 보강 및 거푸집 기능을 하는 2차 보강판(22)을 설치한다. 따라서 1차 보강판(21)과 2차 보강판(22)의 사이에는 배근된 철근(30)과 함께 타설될 콘크리트의 충전 공간이 형성된다.Next, as shown in FIG. 4, a
그 다음, 도 5와 같이 1차 보강판(21)과 2차 보강판(22)의 사이에 콘크리트를 타설 충진하여 기존 지하 외벽(12)에 합성되는 신축 합벽(14)을 형성하는 단계를 갖는다. 신축 합벽(14)을 형성하는 과정은 도 20 내지 도 22에 나타나 있다. 도 20은 신설된 지하 3층에 신축 합벽(14)이 시공된 상태이고, 도 21은 신설된 지하 2층에까지 신축 합벽(14)이 추가적으로 시공된 상태이고, 도 22는 신설된 지하 1층에까지 신축 합벽(14)이 추가적으로 더 시공된 상태이다.Then, as shown in FIG. 5, pouring and filling concrete between the primary reinforcing
여기서, 외벽용 강판 즉 1차 보강판(21)과 2차 보강판(22)은 신축구조물의 영구상태 외벽용으로 사용된다. 특히, 2차 보강판(22)은 시공단계에서는 거푸집용으로 사용되므로, 일반 거푸집이 불필요하여 시공성과 경제성이 유리해지는 특징을 갖는다.Here, the steel plate for the outer wall, that is, the primary reinforcing
이같이 지하골조 공사가 완료되면, 이후 도 23과 같이 상층 골조 공사를 진행하게 된다.When the basement frame construction is completed in this way, the upper floor frame construction is proceeded as shown in FIG.
이와 같이 본 발명에 따른 기존 지하 외벽의 보강을 통한 신설 건물의 지하 증축 및 역타 공법은 신축 합벽(14)의 형성으로 기존 지하 외벽(12)의 보강이 이루어지기 때문에 기존 지하 외벽 두께와 대지 협소, 인접 건물로 인하여 흙막이 벽체 시공이 불가한 상태에서 적용이 유용하다. As described above, in the underground extension and reverse drilling method of a new building through reinforcement of the existing underground exterior wall according to the present invention, the existing underground
물론, 레이커 방식을 이용하여 기존 지하구조물을 철거 할 수도 있으나, 시공이 거의 불가한 임시 흙막이 벽체 시공, 철거하면서 되메우고, 다시 굴토하는 공정으로 인하여 공기 증가와 공사비 증가와 같은 문제점의 발생이 없어지는 이점을 갖는다.Of course, existing underground structures can be demolished using the raker method, but problems such as increase in construction cost and increase in construction cost are eliminated due to the construction of a temporary retaining wall that is almost impossible to construct, backfilling while dismantling, and excavating again. have an advantage
한편, 상기 과정에서 이루어지는 지하골조의 공사 방법을 설명한다.On the other hand, the construction method of the underground frame made in the above process will be described.
먼저, 지하골조의 공사는 도 8과 같이 지하 각층(B1F~B5F)에 PRD(Percussion Rotary Drill) 시공을 위해 PRD장비의 하중을 고려하여 PRD장비 지지용 잭 서포트(110)를 설치한다.First, in the construction of the underground frame, the
그 다음, 도 9와 같이 PRD 시공을 위하여 신축구조물의 기둥이 시공될 위치를 선택하여 지상 1층(1F)과 지하 각층(B1F~B5F)의 슬래브(13) 및 기존 기초(11)에 열려진 개구부(13a)를 형성시킨 후, 도 10과 같이 알려진 PRD(Percussion Rotary Drill) 공법을 통해 신설 말뚝(120)을 설치한다.Next, for PRD construction, as shown in FIG. 9, select the location where the columns of the new structure will be constructed, After forming (13a), a
그 다음, 도 11과 같이 기존 구조물(10)의 1층 슬래브(13)를 포함한 보 및 기둥을 철거한 후, 도 12와 같이 지상1층 신설 슬래브(130)를 시공한다.Next, as shown in FIG. 11 , the beams and columns including the first-
그 다음, 도 13 내지 도 18에 나타난 순서데로 지하 각층(B1F~B5F)의 슬래브(13)를 포함한 보 및 기둥의 순차적인 하향식 철거 그리고 해당 철거 층에서의 신설 슬래브(130)를 신축하는 공사를 반복하여서 진행된다. 여기서 기존 지하 최하층의 슬래브와 기초를 철거한 후에는 도 19와 같이 새로운 기초를 시공하게 된다.Then, in the order shown in FIGS. 13 to 18, the sequential top-down demolition of beams and columns including the
물론, 지하구조물이 완성되면 도 20 및 도 21과 같이 신설 말뚝(120)에 철근콘크리트로 피복하여 철골철근 콘크리트구조로 기둥(150)이 완성된다Of course, when the underground structure is completed, the
이와 같이 본 공법에 따르면, 기존 외벽(옹벽)에 보강판이 설치되어 보강 뿐만 아니라 가설 흙막이 벽체(CIP)의 역할을 수행할 수 있고, 굴착 깊이를 깊게 할 수 있어 시공성이 향상된다.As described above, according to this construction method, a reinforcing plate is installed on the existing outer wall (retaining wall) to perform the role of not only reinforcement but also a temporary retaining wall (CIP), and the excavation depth can be deepened, thereby improving workability.
또한, 합성옹벽으로 신설 지하 외벽을 시공하게 되고, 두게가 얇아지므로 신설 지하 건축물의 공가 확보에 유리하고, CIP 공사가 불필요해지는 경제적 이점을 갖는다.In addition, the new underground outer wall is constructed with a synthetic retaining wall, and since the thickness becomes thinner, it is advantageous to secure a space for a new underground building, and has the economic advantage of not requiring CIP construction.
또한, 2차 보강판이 보강과 함께 거푸집의 역할을 수행하게 되어 경제성 시공이 가능해진다.In addition, the secondary reinforcing plate serves as a formwork together with reinforcement, making economical construction possible.
지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. So far, the present invention has been described in detail with reference to the presented embodiment, but those skilled in the art can make various modifications and variations of the invention without departing from the technical spirit of the present invention with reference to the presented embodiment. will be. The present invention is not limited by such variations and modifications, but only by the claims appended hereto.
12: 지하 외벽
14: 신축 합벽
21: 1차 보강판
22: 2차 보강판
30: 철근
40: 고정앵커12: basement outer wall
14: expansion and contraction wall
21: primary reinforcement plate
22: secondary reinforcement plate
30: rebar
40: fixed anchor
Claims (4)
기존 지하 외벽(12)의 현황을 파악하며 콘크리트 강도와 두께를 필수 조건으로 확인하는 1단계와;
1단계에서 확인된 조건을 기준으로 시공 단계의 토압에 대응하도록 1차 보강판(21)을 준비한 후, 지하 각층의 슬래브(13)에 부분적으로 두께 방향으로 형성시킨 개구부(13a)를 통과하여 지하 외벽(12)에 1차 보강판(21)을 수직방향으로 연속적으로 부착시켜 지하 외벽(12)을 지하 전층에 걸쳐 1차 보강판(21)으로 보강한 후, 지하 외벽(12)을 갖는 지하 전층에 지하골조의 공사를 수행하는 2단계와;
지하골조의 공사가 완료되면, 1차 보강판(21)이 설치된 지하 외벽(12)측에 철근(30)을 배근하는 3단계와;
1차 보강판(21)이 설치된 지하 외벽(12)측에 2차 보강판(22)의 시공을 위한 고정앵커(40)를 설치하는 4단계와;
지하 외벽(12)에 맞도록 보강 및 거푸집 기능을 하는 2차 보강판(22)을 상기 고정앵커(40)를 사용하여 설치하는 5단계와;
상기 1차 보강판(21)과 2차 보강판(22)의 사이에 콘크리트를 충진하여 기존 지하 외벽(12)에 합성되는 신축 합벽(14)을 형성하는 6단계;를 포함하는 것을 특징으로 하는 기존 지하 외벽의 보강을 통한 신설 건물의 지하 증축 및 역타 공법.In the construction method of extending a new building when there is an underground outer wall 12 of an existing building in the basement,
Step 1 of identifying the current status of the existing underground outer wall 12 and confirming the concrete strength and thickness as essential conditions;
After preparing the first reinforcing plate 21 to respond to the earth pressure of the construction stage based on the conditions confirmed in step 1, it passes through the openings 13a partially formed in the thickness direction in the slabs 13 of each basement level and passes through the basement. After the primary reinforcing plate 21 is continuously attached to the outer wall 12 in the vertical direction to reinforce the underground outer wall 12 with the primary reinforcing plate 21 over the entire basement level, the basement having the underground outer wall 12 The second stage of performing the construction of an underground frame on the entire floor;
When the construction of the underground frame is completed, the third step of reinforcing the reinforcing bar 30 on the side of the underground outer wall 12 where the primary reinforcing plate 21 is installed;
A fourth step of installing a fixed anchor 40 for the construction of the secondary reinforcement plate 22 on the side of the underground outer wall 12 where the primary reinforcement plate 21 is installed;
a fifth step of installing a secondary reinforcing plate 22 having a reinforcing and formwork function to fit the underground outer wall 12 using the fixed anchor 40;
A sixth step of filling concrete between the first reinforcing plate 21 and the second reinforcing plate 22 to form an expansion-contracted composite wall 14 synthesized in the existing underground outer wall 12; characterized in that it comprises a The underground extension and reverse drilling method of a new building through reinforcement of the existing underground outer wall.
1차 보강판(21)은 일정하게 이격된 유간(G)을 가지고 배열되어져 설치된 것을 특징으로 하는 기존 지하 외벽의 보강을 통한 신설 건물의 지하 증축 및 역타 공법.The method of claim 1,
The first reinforcing plate 21 is an underground extension and reverse drilling method of a new building through reinforcement of an existing underground outer wall, characterized in that it is arranged and installed with intervals G at regular intervals.
지하골조의 공사는
지하 각층에 PRD(Percussion Rotary Drill) 시공을 위해 PRD장비의 하중을 고려하여 PRD장비 지지용 잭 서포트(110)를 설치하는 단계와;
PRD 시공을 위하여 신축구조물의 기둥이 시공될 위치를 선택하여 지상 1층(1F)과 지하 각층의 슬래브(13) 및 기존 기초(11)에 열려진 개구부(13a)를 형성시킨 후 PRD 공사로 신설 말뚝(120)을 설치하는 단계와;
기존 구조물(10)의 1층 슬래브(13)를 포함한 보 및 기둥을 철거하고, 지상1층 신설 슬래브(130)를 시공하는 단계와;
지하 각층의 슬래브(13)를 포함한 보 및 기둥의 순차적인 하향식 철거 그리고 해당 철거 층에서의 신설 슬래브(130)를 신축하는 공사를 반복하는 단계;를 포함하는 것을 특징으로 하는 기존 지하 외벽의 보강을 통한 신설 건물의 지하 증축 및 역타 공법.The method of claim 1,
Underground structure construction
Installing a jack support 110 for PRD equipment support in consideration of the load of the PRD equipment for PRD (Percussion Rotary Drill) construction on each basement floor;
For PRD construction, select the location where the columns of the new structure will be constructed, form the openings 13a on the first floor (1F) above the ground, the slabs 13 on each basement level, and the existing foundation 11, and then build new piles for PRD construction installing (120);
Demolition of beams and columns including the first-floor slab 13 of the existing structure 10, and constructing a new first-floor slab 130 above the ground;
Reinforcement of an existing underground outer wall, comprising a; sequential top-down demolition of beams and columns including the slab 13 of each basement floor, and repeating the construction of a new slab 130 in the corresponding demolished floor. Underground extension and reverse construction method of new buildings through
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020200099675A KR102396786B1 (en) | 2020-08-10 | 2020-08-10 | Underground expansion and top-down method of new building using reinforcement of existing underground outer wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020200099675A KR102396786B1 (en) | 2020-08-10 | 2020-08-10 | Underground expansion and top-down method of new building using reinforcement of existing underground outer wall |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20220019346A KR20220019346A (en) | 2022-02-17 |
KR102396786B1 true KR102396786B1 (en) | 2022-05-12 |
Family
ID=80493241
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020200099675A KR102396786B1 (en) | 2020-08-10 | 2020-08-10 | Underground expansion and top-down method of new building using reinforcement of existing underground outer wall |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR102396786B1 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114582219B (en) * | 2022-02-23 | 2023-08-11 | 山东高速工程建设集团有限公司 | Foundation pit adjacent building construction simulation device |
KR102632253B1 (en) * | 2022-12-06 | 2024-02-01 | 맹기섭 | An Extended Structure |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011017188A (en) * | 2009-07-09 | 2011-01-27 | Toda Constr Co Ltd | Demolition method of existing building |
JP2016121511A (en) * | 2014-12-25 | 2016-07-07 | 大成建設株式会社 | Underground structure |
KR101994069B1 (en) * | 2019-01-31 | 2019-06-27 | 김은영 | the method of reconstruction of underground building |
JP2020084580A (en) * | 2018-11-26 | 2020-06-04 | 株式会社竹中工務店 | Construction method of earth retaining wall structure in inverted construction method |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH09273317A (en) * | 1996-04-05 | 1997-10-21 | Taisei Corp | Vibration-resistant reinforcing method of existing concrete structure |
KR101296856B1 (en) | 2011-08-24 | 2013-08-14 | 주식회사 세진에스씨엠 | Reinforcement structure for wall of underground structure and construction method of underground structure using the same |
KR101612521B1 (en) | 2015-10-12 | 2016-04-14 | 우경기술주식회사 | Method for constructing underground structures restraining transformation and using external wall |
-
2020
- 2020-08-10 KR KR1020200099675A patent/KR102396786B1/en active IP Right Grant
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2011017188A (en) * | 2009-07-09 | 2011-01-27 | Toda Constr Co Ltd | Demolition method of existing building |
JP2016121511A (en) * | 2014-12-25 | 2016-07-07 | 大成建設株式会社 | Underground structure |
JP2020084580A (en) * | 2018-11-26 | 2020-06-04 | 株式会社竹中工務店 | Construction method of earth retaining wall structure in inverted construction method |
KR101994069B1 (en) * | 2019-01-31 | 2019-06-27 | 김은영 | the method of reconstruction of underground building |
Also Published As
Publication number | Publication date |
---|---|
KR20220019346A (en) | 2022-02-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106088650B (en) | A kind of method and building suitable for building with brick-concrete structure underground increasing layer | |
CN109944250B (en) | Foundation pit forward and backward combined construction method of non-permanent vertical supporting system | |
KR100967497B1 (en) | Method for constructing an underground structure | |
WO2011114507A1 (en) | Method of constructing underground structure to be newly built | |
JP2001303599A (en) | Building demolishing and constructing method and building | |
JP2012107479A (en) | Method for constructing underground and aboveground structure | |
KR102396786B1 (en) | Underground expansion and top-down method of new building using reinforcement of existing underground outer wall | |
JP6855296B2 (en) | Building foundation structure and its construction method | |
KR20200029079A (en) | Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method | |
KR100313720B1 (en) | Composite Underground Structure Construction Method | |
JP4914062B2 (en) | Two-tiered retaining wall and its construction method | |
KR102290076B1 (en) | The construction method using a exterio wall of undergound structure | |
KR101267565B1 (en) | Construction method of under-ground core part structure in top-down construction procedure | |
KR20200104534A (en) | Method for constructing underground structure busing PC integrating method without support | |
KR20070052109A (en) | Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
KR20200029080A (en) | Construction method for earth self-retaining wall using reinforcing member and PHC pile | |
KR101296856B1 (en) | Reinforcement structure for wall of underground structure and construction method of underground structure using the same | |
CN113404054A (en) | Cement mixing pile type, cast-in-place pile type crown beam construction method and crown beam system | |
KR100625115B1 (en) | downward reinforced-concrete underground structure using temporary assistant columns | |
KR100662524B1 (en) | Double pipe girder struts as permanent system | |
JP6768477B2 (en) | How to build an underground structure | |
KR100615149B1 (en) | A method of construction top-down for the ground fabric construction | |
KR20210090100A (en) | In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures | |
KR20210098162A (en) | Under ground structure using column steel pipe wall and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right |