WO2024037586A1 - Double-foundation-pit double-working-condition construction method - Google Patents

Double-foundation-pit double-working-condition construction method Download PDF

Info

Publication number
WO2024037586A1
WO2024037586A1 PCT/CN2023/113517 CN2023113517W WO2024037586A1 WO 2024037586 A1 WO2024037586 A1 WO 2024037586A1 CN 2023113517 W CN2023113517 W CN 2023113517W WO 2024037586 A1 WO2024037586 A1 WO 2024037586A1
Authority
WO
WIPO (PCT)
Prior art keywords
area
foundation pit
construction
support
foundation
Prior art date
Application number
PCT/CN2023/113517
Other languages
French (fr)
Chinese (zh)
Inventor
游鹏超
孙海伟
黄亚均
梅晓峰
史阳
李颖
林夏华
王艳惠
赵亮
陈凯
陈金豪
Original Assignee
中建三局集团(浙江)有限公司
中建三局第三建设工程有限责任公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中建三局集团(浙江)有限公司, 中建三局第三建设工程有限责任公司 filed Critical 中建三局集团(浙江)有限公司
Publication of WO2024037586A1 publication Critical patent/WO2024037586A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits

Definitions

  • This application relates to the field of foundation pit construction, and in particular to a rapid construction method for double foundation pits and dual working conditions.
  • a foundation pit is a soil pit excavated at the foundation design location according to the foundation elevation and foundation plane dimensions. Before excavation, the excavation plan should be determined based on geological and hydrological data and the conditions of buildings near the site, and waterproofing and drainage work should be carried out. Large foundation pits use methods such as underground continuous walls and column-type bored pile interlocking to prevent the outside soil from collapsing. Therefore, when constructing large foundation pits, for the sake of construction safety, a single foundation pit is often used. When the number of pits is large, the construction time and construction period tend to be longer.
  • this application provides a rapid construction method for double foundation pits and double working conditions.
  • a method for construction of double foundation pits and dual working conditions including the following steps: cleaning the surfaces of foundation pit A, foundation pit B and foundation pit D, and foundation pit D and foundation pit B are adjacent to foundation pit A;
  • Foundation pit D includes area D1 and area D2, foundation pit A includes area A1 and area A2, and foundation pit B includes area B1 and area B2.
  • Area B2 is adjacent to foundation pit A.
  • the order of earthwork excavation is area B1, B2.
  • the D foundation pit, A foundation pit and B foundation pit are arranged in a "7" shape, the D2 area is adjacent to the A foundation pit, and a first reinforcement structure is provided in the D2 area close to the A foundation pit;
  • Areas A1 and A2 are the north and south areas of foundation pit A respectively.
  • Area A1 is equipped with a second reinforcement structure;
  • the second layer of earth excavation and support construction will be carried out in the A1 area.
  • the first reinforcement structure and the second reinforcement structure provide construction conditions for the construction of foundation pit A, so that the inside of foundation pit A and foundation pit B can be constructed at the same time, shortening the construction period and increasing the construction speed.
  • the B2 area is divided into B2-1 area and B2-2 area from west to east.
  • the A2 area will undergo the second Excavation of layers of earth and support construction.
  • the interior of foundation pit A and foundation pit B can be constructed at the same time, shortening the construction period.
  • the A foundation pit, B foundation pit and D foundation pit all adopt the following method.
  • foundation pit A, foundation pit B and foundation pit D are constructed using the following construction method, which meets the land requirements and construction requirements.
  • the first reinforcement structure is a fixed structure composed of multiple first main columns and multiple first support columns.
  • the first main columns are stable inside the D foundation pit, and the first main columns are supported by the first The columns are fixedly connected to the original support structure, and the first reinforcement structure provides support to the northeast and southeast directions of the D2 area.
  • the first reinforcement structure provides support to the northeast and southeast directions of the D2 area, thereby achieving the stabilization of the edge of the foundation pit shared by the D2 area and the A foundation pit, and providing conditions for the construction of the A foundation pit.
  • the construction period is shortened.
  • the plurality of first main columns are divided into two groups.
  • the connection lines of the two groups of first main columns are parallel to the north-south direction.
  • the first main columns are connected by the first support column. Fixed connection with the original support structure through the first support column.
  • the stress-bearing area of the original support structure is increased, making the stress inside the D2 area more stable, and providing safety guarantee and construction for the construction of foundation pit A. condition.
  • the second reinforcement structure is a fixed structure composed of a plurality of second main columns and a plurality of secondary support columns.
  • the second main columns are stable inside the foundation pit A, and the second main columns are supported by the second The columns are connected to each other, and the second main column is fixedly connected to the original support structure through the second support column.
  • the second reinforcement structure provides northeastern support for area A1.
  • the original support structure inside the A foundation pit was reinforced, which provided conditions for the simultaneous construction of the A foundation pit.
  • connection lines of the plurality of second main columns are at an angle with the due east direction, and the second main columns are connected to the original support structure in the northeast direction of Area A1 through the second support column.
  • the construction speed is increased and the construction period is shortened.
  • Figure 1 is the location relationship diagram of D foundation pit, A foundation pit and B foundation pit;
  • Figure 2 is a partial structural schematic diagram intended to emphasize the first reinforcement structure
  • Figure 3 is a partial structural schematic diagram intended to emphasize the second reinforcing structure.
  • the embodiment of this application discloses a rapid construction method for double foundation pits and dual working conditions.
  • foundation pit D and foundation pit B are adjacent to foundation pit A.
  • Foundation pit D, foundation pit B, and foundation pit A all adopt the construction method of follow-up construction.
  • Foundation pit D, foundation pit A, and foundation pit B are in the same direction.
  • "7" shape arrangement D2 area is adjacent to A foundation pit, D foundation pit includes D1 area and D2 area, D1 area and D2 area are distributed from west to east, A foundation pit includes A1 area and A2 area, A1 area and Area A2 is the north and south areas of foundation pit A respectively.
  • Foundation pit B includes area B1 and area B2. Areas B1 and B2 are distributed from north to south.
  • D2 and area A are adjacent to each other, and area A2 and area B2 are adjacent to each other. Neighboring, there are basement structures at both foundation pit B and foundation pit A.
  • a rapid construction method for double foundation pits and double working conditions including the following steps:
  • foundation pit D During the excavation of foundation pit D, the first support construction in area B2 was completed, which realized the purpose of simultaneous construction of multiple foundation pits, shortened the construction period, and achieved the purpose of rapid construction; foundation pits D and B are both in line with A The foundation pits are adjacent, clean the surfaces of foundation pit A, foundation pit B and foundation pit D;
  • a first reinforcement structure 1 is provided in areas S3 and D2 close to foundation pit A.
  • the first reinforcement structure 1 provides support in the northeast and southeast directions to the edge of the foundation pit common to area D2 and foundation pit A;
  • the A1 area is provided with a second reinforcement structure 2.
  • the second reinforcement structure 2 provides northeastern support to the edge of the A1 area;
  • the second layer of earth excavation construction and the second support construction can be carried out in the A1 area, and the B2 area is from west to east. It is set as B2-1 area and B2-2 area.
  • the A2 area can carry out the second layer of earth excavation and the second support at the same time, further shortening the construction period and achieving the purpose of rapid construction. .
  • the user can only complete the construction of the B0 layer structure in the B2-2 area and the B0 layer structure in the D area. After completion, the second layer of earth excavation construction and the second support construction in the A2 area will be started. The engineering efficiency is low.
  • the first reinforcement structure 1 and the second reinforcement structure 2 of this application Both support trestles and three-layer concrete supports.
  • the first reinforcement structure 1 includes a fixed structure composed of a plurality of first main columns 11 and a plurality of first support columns 12.
  • the first main column 11 is The number is six.
  • the first main column 11 is firmly fixed inside the D foundation pit.
  • the first main column 11 is fixedly connected to the original support structure through the first support column 12 .
  • the plurality of first main columns 11 are divided into two groups.
  • connection lines of the two groups of first main columns 11 are parallel to the north-south direction.
  • the number of the first main columns in the group close to the foundation pit A is two, and the number of the first main columns 11 in the group far away from the foundation pit A is two.
  • the number of the first main columns 11 in the group is four.
  • the second reinforcement structure 2 is a fixed structure composed of a plurality of second main columns 21 and a plurality of second support columns 22.
  • the number of the second main columns 21 is three.
  • the second main columns 21 are stable inside the foundation pit A.
  • the second main columns 21 are connected to each other through the second support columns 22, and the second main columns 21 are fixedly connected to the original support structure through the second support columns 22.
  • Three second main columns 21 are connected to each other through the second support columns 22. There is an angle between the connection line of the main column 21 and the due east direction.
  • the second main column is connected to the original support structure in the northeast direction of the A1 area through the second support column 22, so that the second reinforcement structure 2 provides northeast support for the A1 area. force.
  • the original support structure, the first reinforcement structure 1 and the second reinforcement structure 2 are all connected by a support trestle, so that the first reinforcement structure 1 and the second reinforcement structure 2 can be connected in the same way as the original support structure. , improve the stability of fixation.

Abstract

The present application relates to the field of foundation pit construction, and in particular to a double-foundation-pit double-working-condition construction method. The method comprises the following steps: foundation pit D and foundation pit B are both adjacent to foundation pit A, and surfaces of foundation pit A, foundation pit B and foundation pit D are cleaned; foundation pit D comprises area D1 and area D2, foundation pit A comprises area A1 and area A2, and foundation pit B comprises area B1 and area B2, wherein area B2 is adjacent to foundation pit A, and the order of earthwork excavation is sequentially: area B1, area B2, foundation pit A and foundation pit D; foundation pit B is provided with a basement structure; when the earthwork excavation of area B2 is performed, the basement structure in area B1 has positive and negative zeroes; when the earthwork excavation of the foundation pit A is performed, the basement structure in area B2 is completed, and the construction of the floor of foundation pit D is completed; and when the earthwork excavation of foundation pit D is performed, first supporting construction of area B2 is completed. The present application has the effects of shortening a construction period and increasing construction speed.

Description

一种双基坑双工况建造方法A construction method for double foundation pits and double working conditions 技术领域Technical field
 本申请涉及基坑施工的领域,尤其是涉及一种双基坑双工况快速建造方法。This application relates to the field of foundation pit construction, and in particular to a rapid construction method for double foundation pits and dual working conditions.
背景技术Background technique
 基坑是在基础设计位置按基底标高和基础平面尺寸所开挖的土坑。开挖前应根据地质水文资料,结合现场附近建筑物情况,决定开挖方案,并作好防水排水工作。大型基坑采用地下连续墙和柱列式钻孔灌注桩连锁等方法,防止外侧土层坍入,所以在进行大型基坑施工时,为了施工安全,往往会采用单基坑的方式,当基坑的数量较多时,施工时间和施工周期往往较长。A foundation pit is a soil pit excavated at the foundation design location according to the foundation elevation and foundation plane dimensions. Before excavation, the excavation plan should be determined based on geological and hydrological data and the conditions of buildings near the site, and waterproofing and drainage work should be carried out. Large foundation pits use methods such as underground continuous walls and column-type bored pile interlocking to prevent the outside soil from collapsing. Therefore, when constructing large foundation pits, for the sake of construction safety, a single foundation pit is often used. When the number of pits is large, the construction time and construction period tend to be longer.
发明内容Contents of the invention
 为了缩短施工工期、提高建造速度,本申请提供一种双基坑双工况快速建造方法。In order to shorten the construction period and increase the construction speed, this application provides a rapid construction method for double foundation pits and double working conditions.
 本申请提供的一种双基坑双工况建造方法,采用如下的技术方案:This application provides a construction method for double foundation pits and double working conditions, which adopts the following technical solution:
一种双基坑双工况建造方法,包括如下步骤:将A基坑、B基坑以及D基坑的表面进行清理,D基坑和B基坑均与A基坑相邻;A method for construction of double foundation pits and dual working conditions, including the following steps: cleaning the surfaces of foundation pit A, foundation pit B and foundation pit D, and foundation pit D and foundation pit B are adjacent to foundation pit A;
D基坑包括D1区和D2区,A基坑包括A1区和A2区,B基坑包括B1区和B2区,其中B2区和A基坑相邻,土方开挖顺序依次为B1区、B2区、A基坑、D基坑;Foundation pit D includes area D1 and area D2, foundation pit A includes area A1 and area A2, and foundation pit B includes area B1 and area B2. Area B2 is adjacent to foundation pit A. The order of earthwork excavation is area B1, B2. Area, A foundation pit, D foundation pit;
B基坑设置有地下室结构;Pit B is equipped with a basement structure;
B2区土方开挖时,B1区地下室结构出正负零;During earth excavation in area B2, the basement structure in area B1 showed positive and negative zero;
A基坑土方开挖时,B2区地下室结构完成,D基坑底板施工完成;During the excavation of foundation pit A, the basement structure of area B2 is completed, and the construction of the floor of foundation pit D is completed;
D基坑土方开挖时,B2区第一道支撑施工完成。During the excavation of foundation pit D, the first support construction in area B2 was completed.
 通过采用上述技术方案,实现了多个基坑同步施工的目的,缩短了工期,实现了快速建造的目的。By adopting the above technical solution, the purpose of simultaneous construction of multiple foundation pits is achieved, the construction period is shortened, and the purpose of rapid construction is achieved.
 可选的,所述D基坑、A基坑和B基坑呈“7”字型排布,D2区与A基坑相邻,D2区靠近A基坑的位置设置有第一加固结构;Optionally, the D foundation pit, A foundation pit and B foundation pit are arranged in a "7" shape, the D2 area is adjacent to the A foundation pit, and a first reinforcement structure is provided in the D2 area close to the A foundation pit;
A1区和A2区分别为A基坑的北侧区域和南侧区域,A1区设置有第二加固结构;Areas A1 and A2 are the north and south areas of foundation pit A respectively. Area A1 is equipped with a second reinforcement structure;
B1区完成B1层结构施工后,A1区进行第二层土方开挖以及支撑施工。After the construction of the B1 layer structure is completed in the B1 area, the second layer of earth excavation and support construction will be carried out in the A1 area.
 通过采用上述技术方案,第一加固结构和第二加固结构为A基坑的施工提供了施工条件,使得A基坑内部可与B基坑同时施工,缩短了工期,提高了建造速度。By adopting the above technical solution, the first reinforcement structure and the second reinforcement structure provide construction conditions for the construction of foundation pit A, so that the inside of foundation pit A and foundation pit B can be constructed at the same time, shortening the construction period and increasing the construction speed.
 可选的,所述B2区自西到东依次为B2-1区、B2-2区,B2-1区施工至B1层并且D1区底板和D2区底板均施工完毕后,A2区进行第二层土方开挖以及支撑施工。Optionally, the B2 area is divided into B2-1 area and B2-2 area from west to east. After the construction of B2-1 area reaches the B1 floor and the construction of the D1 area floor and D2 area floor is completed, the A2 area will undergo the second Excavation of layers of earth and support construction.
 通过采用上述技术方案,实现了A基坑内部可与B基坑同时施工,缩短了工期。By adopting the above technical solution, the interior of foundation pit A and foundation pit B can be constructed at the same time, shortening the construction period.
 可选的,所述A基坑、B基坑以及D基坑均采用顺作法。Optionally, the A foundation pit, B foundation pit and D foundation pit all adopt the following method.
 通过采用上述技术方案,在第一加固结构和第二加固结构稳固后,A基坑、B基坑以及D基坑采用顺作法的施工方式进行施工,符合地块要求和施工要求。By adopting the above technical solution, after the first reinforcement structure and the second reinforcement structure are stabilized, foundation pit A, foundation pit B and foundation pit D are constructed using the following construction method, which meets the land requirements and construction requirements.
 可选的,所述第一加固结构为多根第一主立柱和多根第一次支撑柱组成的固定结构,第一主立柱稳固于D基坑内部,第一主立柱通过第一次支撑柱与原支撑结构固定连接,第一加固结构对D2区东北方向和东南方向提供支撑力。Optionally, the first reinforcement structure is a fixed structure composed of multiple first main columns and multiple first support columns. The first main columns are stable inside the D foundation pit, and the first main columns are supported by the first The columns are fixedly connected to the original support structure, and the first reinforcement structure provides support to the northeast and southeast directions of the D2 area.
 通过采用上述技术方案,通过第一加固结构对D2区东北方向和东南方向提供支撑力,实现了对D2区和A基坑共同使用的基坑边缘的稳固,为A基坑的施工提供条件,缩短了工期。By adopting the above technical solution, the first reinforcement structure provides support to the northeast and southeast directions of the D2 area, thereby achieving the stabilization of the edge of the foundation pit shared by the D2 area and the A foundation pit, and providing conditions for the construction of the A foundation pit. The construction period is shortened.
 可选的,多根所述第一主立柱分为两组,两组第一主立柱的连线均平行于南北方向,第一主立柱之间通过第一次支撑柱连接,第一主立柱与原支撑结构通过第一次支撑柱固定连接。Optionally, the plurality of first main columns are divided into two groups. The connection lines of the two groups of first main columns are parallel to the north-south direction. The first main columns are connected by the first support column. Fixed connection with the original support structure through the first support column.
 通过采用上述技术方案,通过两组第一主立柱与原支撑结构的固定,提高原支撑结构的受力面积,使得D2区内部的受力更加稳定,为A基坑的施工提供安全保障和施工条件。By adopting the above technical solution and fixing the two sets of first main columns with the original support structure, the stress-bearing area of the original support structure is increased, making the stress inside the D2 area more stable, and providing safety guarantee and construction for the construction of foundation pit A. condition.
 可选的,所述第二加固结构为多根第二主立柱和多根第二次支撑柱组成的固定结构,第二主立柱稳固于A基坑内部,第二主立柱通过第二次支撑柱相互连接,且第二主立柱通过第二次支撑柱固定连接于原支撑结构,第二加固结构为A1区提供东北方向的支撑力。Optionally, the second reinforcement structure is a fixed structure composed of a plurality of second main columns and a plurality of secondary support columns. The second main columns are stable inside the foundation pit A, and the second main columns are supported by the second The columns are connected to each other, and the second main column is fixedly connected to the original support structure through the second support column. The second reinforcement structure provides northeastern support for area A1.
 通过采用上述技术方案,实现了对A基坑内部原支撑结构的加固,为A基坑同时施工提供了条件。By adopting the above technical solution, the original support structure inside the A foundation pit was reinforced, which provided conditions for the simultaneous construction of the A foundation pit.
 可选的,多根所述第二主立柱的连线与正东方向存在夹角,第二主立柱通过第二次支撑柱连接于A1区东北方向的原支撑结构。Optionally, the connection lines of the plurality of second main columns are at an angle with the due east direction, and the second main columns are connected to the original support structure in the northeast direction of Area A1 through the second support column.
 通过采用上述技术方案,实现了A1区原支撑结构的加固。By adopting the above technical solution, the original support structure of Area A1 was reinforced.
 综上所述,本申请包括以下至少一种有益技术效果:To sum up, this application includes at least one of the following beneficial technical effects:
1.通过采用第一加固结构和第二加固结构的方式提高了施工速度,缩短了施工周期。1. By using the first reinforcement structure and the second reinforcement structure, the construction speed is increased and the construction period is shortened.
附图说明Description of drawings
 图1是D基坑、A基坑和B基坑的位置关系图;Figure 1 is the location relationship diagram of D foundation pit, A foundation pit and B foundation pit;
图2是旨在强调第一加固结构的局部结构示意图;Figure 2 is a partial structural schematic diagram intended to emphasize the first reinforcement structure;
图3是旨在强调第二加固结构的局部结构示意图。Figure 3 is a partial structural schematic diagram intended to emphasize the second reinforcing structure.
 附图标记说明:1、第一加固结构;11、第一主立柱;12、第一次支撑柱;2、第二加固结构;21、第二主立柱;22、第二次支撑柱。Explanation of reference signs: 1. First reinforcement structure; 11. First main column; 12. First support column; 2. Second reinforcement structure; 21. Second main column; 22. Second support column.
实施方式Implementation
 以下结合附图1-3对本申请作进一步详细说明。This application will be further described in detail below in conjunction with Figures 1-3.
 本申请实施例公开一种双基坑双工况快速建造方法。The embodiment of this application discloses a rapid construction method for double foundation pits and dual working conditions.
 参照图1,D基坑和B基坑均与A基坑相邻,D基坑、B基坑以及A基坑均采用顺作法的施工方式,D基坑、A基坑和B基坑呈“7”字型排布,D2区与A基坑相邻,D基坑包括D1区和D2区,D1区、D2区呈西东分布,A基坑包括A1区和A2区,A1区和A2区分别为A基坑的北侧区域和南侧区域,B基坑包括B1区和B2区,B1区和B2区呈南北分布,其中D2和A基坑相邻,A2区和B2区相邻,其中B基坑和A基坑处均设置有地下室结构。Referring to Figure 1, foundation pit D and foundation pit B are adjacent to foundation pit A. Foundation pit D, foundation pit B, and foundation pit A all adopt the construction method of follow-up construction. Foundation pit D, foundation pit A, and foundation pit B are in the same direction. "7" shape arrangement, D2 area is adjacent to A foundation pit, D foundation pit includes D1 area and D2 area, D1 area and D2 area are distributed from west to east, A foundation pit includes A1 area and A2 area, A1 area and Area A2 is the north and south areas of foundation pit A respectively. Foundation pit B includes area B1 and area B2. Areas B1 and B2 are distributed from north to south. D2 and area A are adjacent to each other, and area A2 and area B2 are adjacent to each other. Neighboring, there are basement structures at both foundation pit B and foundation pit A.
 B1区完成B1层结构施工后,A1区进行第二层土方开挖以及支撑施工。一种双基坑双工况快速建造方法,包括如下步骤:After the B1 layer structural construction is completed in B1 area, the second layer of earth excavation and support construction will be carried out in A1 area. A rapid construction method for double foundation pits and double working conditions, including the following steps:
S1、对A基坑、B基坑以及D基坑的表面进行清理;然后进行土方开挖施工,土方开挖顺序依次为B1区、A基坑、B2区、D基坑,完成首层土方开挖后,对首层进行支撑施工,并且进行栈桥施工;S1. Clean the surfaces of foundation pit A, foundation pit B and foundation pit D; then carry out earthwork excavation. The order of earthwork excavation is area B1, foundation pit A, area B2 and foundation pit D. The first layer of earthwork is completed. After excavation, support construction will be carried out on the first floor and trestle construction will be carried out;
S2、B2区土方开挖时,B1区地下室结构出正负零;During earth excavation in areas S2 and B2, positive and negative zeros were found in the basement structure of area B1;
A基坑土方开挖时,B2区地下室结构完成,D基坑底板施工完成;During the excavation of foundation pit A, the basement structure of area B2 is completed, and the construction of the floor of foundation pit D is completed;
D基坑土方开挖时,B2区第一道支撑施工完成,这实现了多个基坑同步施工的目的,缩短了工期,实现了快速建造的目的;D基坑和B基坑均与A基坑相邻,对A基坑、B基坑以及D基坑的表面进行清理;During the excavation of foundation pit D, the first support construction in area B2 was completed, which realized the purpose of simultaneous construction of multiple foundation pits, shortened the construction period, and achieved the purpose of rapid construction; foundation pits D and B are both in line with A The foundation pits are adjacent, clean the surfaces of foundation pit A, foundation pit B and foundation pit D;
S3、D2区靠近A基坑的位置设置有第一加固结构1,第一加固结构1对D2区和A基坑公用的基坑边缘提供东北方向和东南方向的支撑力;A first reinforcement structure 1 is provided in areas S3 and D2 close to foundation pit A. The first reinforcement structure 1 provides support in the northeast and southeast directions to the edge of the foundation pit common to area D2 and foundation pit A;
A1区设置有第二加固结构2,第二加固结构2对A1区的边缘提供东北方向的支撑力;The A1 area is provided with a second reinforcement structure 2. The second reinforcement structure 2 provides northeastern support to the edge of the A1 area;
通过第一加固结构1的加固和第二加固结构2的加固,当B2区B1层完成结构施工后,A1区可进行第二层土方开挖施工和第二道支撑施工,B2区自西向东设置为B2-1区和B2-2区,当B2-1区施工至B0层后,A2区可同时进行第二层土方开挖施工以及第二道支撑,进一步缩短工期,实现快速建造的目的。Through the reinforcement of the first reinforcement structure 1 and the reinforcement of the second reinforcement structure 2, after the structural construction of the B1 layer in the B2 area is completed, the second layer of earth excavation construction and the second support construction can be carried out in the A1 area, and the B2 area is from west to east. It is set as B2-1 area and B2-2 area. When the B2-1 area is constructed to the B0 layer, the A2 area can carry out the second layer of earth excavation and the second support at the same time, further shortening the construction period and achieving the purpose of rapid construction. .
 传统的施工方式中,由于缺少第一加固结构1和第二加固结构2的支撑,缺少受力支撑,使得用户只能在B2-2区的B0层结构施工完毕以及D区的B0层结构施工完毕后,再开始A2区的第二层土方开挖施工和第二道支撑施工,工程效率较低。In the traditional construction method, due to the lack of support from the first reinforcement structure 1 and the second reinforcement structure 2, and the lack of force support, the user can only complete the construction of the B0 layer structure in the B2-2 area and the B0 layer structure in the D area. After completion, the second layer of earth excavation construction and the second support construction in the A2 area will be started. The engineering efficiency is low.
 参照图2和图3,图2中E处虚线内的为第一加固结构1,图3中F处虚线内部的为第二加固结构2,本申请第一加固结构1和第二加固结构2均采用支撑栈桥、三层砼支撑的方式,第一加固结构1包括多根第一主立柱11和多根第一次支撑柱12组成的固定结构,本申请实施例中第一主立柱11的数量为六根,第一主立柱11稳固于D基坑内部,第一主立柱11通过第一次支撑柱12与原支撑结构固定连接。多根第一主立柱11分为两组,两组第一主立柱11的连线均平行于南北方向,靠近A基坑的一组第一主立柱数量为两根,远离A基坑的一组第一主立柱11数量为四根,通过两组第一主立柱11与原支撑结构的固定,提高原支撑结构的受力面积,第一主立柱11之间通过第一次支撑柱12连接,第一主立柱11与原支撑结构通过第一次支撑柱固定连接,使得D2区内部的受力更加稳定,为A基坑的施工提供安全保障和施工条件。Referring to Figures 2 and 3, what is within the dotted line at E in Figure 2 is the first reinforcement structure 1, and what is within the dotted line at F in Figure 3 is the second reinforcement structure 2. The first reinforcement structure 1 and the second reinforcement structure 2 of this application Both support trestles and three-layer concrete supports. The first reinforcement structure 1 includes a fixed structure composed of a plurality of first main columns 11 and a plurality of first support columns 12. In the embodiment of the present application, the first main column 11 is The number is six. The first main column 11 is firmly fixed inside the D foundation pit. The first main column 11 is fixedly connected to the original support structure through the first support column 12 . The plurality of first main columns 11 are divided into two groups. The connection lines of the two groups of first main columns 11 are parallel to the north-south direction. The number of the first main columns in the group close to the foundation pit A is two, and the number of the first main columns 11 in the group far away from the foundation pit A is two. The number of the first main columns 11 in the group is four. By fixing the two groups of first main columns 11 to the original support structure, the stress-bearing area of the original support structure is increased. The first main columns 11 are connected by the first support column 12 , the first main column 11 is fixedly connected to the original support structure through the first support column, which makes the stress inside the D2 area more stable and provides safety guarantee and construction conditions for the construction of foundation pit A.
 参照图2和图3,第二加固结构2为多根第二主立柱21和多根第二次支撑柱22组成的固定结构,本申请实施例中第二主立柱21的数量为三个,第二主立柱21稳固于A基坑内部,第二主立柱21通过第二次支撑柱22相互连接,且第二主立柱21通过第二次支撑柱22固定连接于原支撑结构,三根第二主立柱21的连线与正东方向存在夹角,第二主立柱通过第二次支撑柱22连接于A1区东北方向的原支撑结构,使得第二加固结构2为A1区提供东北方向的支撑力。Referring to Figures 2 and 3, the second reinforcement structure 2 is a fixed structure composed of a plurality of second main columns 21 and a plurality of second support columns 22. In the embodiment of the present application, the number of the second main columns 21 is three. The second main columns 21 are stable inside the foundation pit A. The second main columns 21 are connected to each other through the second support columns 22, and the second main columns 21 are fixedly connected to the original support structure through the second support columns 22. Three second main columns 21 are connected to each other through the second support columns 22. There is an angle between the connection line of the main column 21 and the due east direction. The second main column is connected to the original support structure in the northeast direction of the A1 area through the second support column 22, so that the second reinforcement structure 2 provides northeast support for the A1 area. force.
 进一步的,本申请中原支撑结构、第一加固结构1和第二加固结构2均采用支撑栈桥的方式连接,使得第一加固结构1和第二加固结构2可与原本的支撑结构的连接方式相同,提高固定的稳定性。Furthermore, in this application, the original support structure, the first reinforcement structure 1 and the second reinforcement structure 2 are all connected by a support trestle, so that the first reinforcement structure 1 and the second reinforcement structure 2 can be connected in the same way as the original support structure. , improve the stability of fixation.
 以上均为本申请的较佳实施例,并非依此限制本申请的保护范围,故:凡依本申请的结构、形状、原理所做的等效变化,均应涵盖于本申请的保护范围之内。The above are all preferred embodiments of the present application, and are not intended to limit the scope of protection of the present application. Therefore, any equivalent changes made based on the structure, shape, and principle of the present application shall be covered by the scope of protection of the present application. Inside.

Claims (3)

  1.   一种双基坑双工况建造方法,其特征在于:包括如下步骤:A method of construction of double foundation pits and double working conditions, which is characterized by: including the following steps:
    对A基坑、B基坑以及D基坑的表面进行清理,D基坑和B基坑均与A基坑相邻;Clean the surfaces of foundation pit A, foundation pit B and foundation pit D. Foundation pit D and foundation pit B are adjacent to foundation pit A;
    D基坑包括D1区和D2区,A基坑包括A1区和A2区,B基坑包括B1区和B2区,其中B2区和A基坑相邻,土方开挖顺序依次为B1区、B2区、A基坑、D基坑;Foundation pit D includes area D1 and area D2, foundation pit A includes area A1 and area A2, and foundation pit B includes area B1 and area B2. Area B2 is adjacent to foundation pit A. The order of earthwork excavation is area B1, B2. Area, A foundation pit, D foundation pit;
    B基坑设置有地下室结构;Pit B is equipped with a basement structure;
    B2区土方开挖时,B1区地下室结构出正负零;During earth excavation in area B2, the basement structure in area B1 showed positive and negative zero;
    A基坑土方开挖时,B2区地下室结构完成,D基坑底板施工完成;During the excavation of foundation pit A, the basement structure of area B2 is completed, and the construction of the floor of foundation pit D is completed;
    D基坑土方开挖时,B2区第一道支撑施工完成;During the excavation of foundation pit D, the first support construction in area B2 was completed;
    所述D基坑、A基坑和B基坑呈“7”字型排布,D2区与A基坑相邻,D2区靠近A基坑的位置设置有第一加固结构(1);The D foundation pit, A foundation pit and B foundation pit are arranged in a "7" shape, the D2 area is adjacent to the A foundation pit, and a first reinforcement structure (1) is provided in the D2 area close to the A foundation pit;
    A1区和A2区分别为A基坑的北侧区域和南侧区域,A1区设置有第二加固结构(2);Areas A1 and A2 are the north and south areas of foundation pit A respectively. Area A1 is equipped with a second reinforcement structure (2);
    B1区完成B1层结构施工后,A1区进行第二层土方开挖以及支撑施工;After the B1 layer structural construction is completed in B1 area, the second layer of earth excavation and support construction will be carried out in A1 area;
    所述B2区自西到东依次为B2-1区、B2-2区,B2-1区施工至B1层并且D1区底板和D2区底板均施工完毕后,A2区进行第二层土方开挖以及支撑施工;The B2 area is divided into B2-1 area and B2-2 area from west to east. The B2-1 area is constructed to the B1 layer and after the construction of the D1 area floor and the D2 area floor is completed, the second layer of earth excavation is carried out in the A2 area. and supporting construction;
    所述A基坑、B基坑以及D基坑均采用顺作法;The A foundation pit, B foundation pit and D foundation pit all adopt the following method;
    所述第一加固结构(1)为多根第一主立柱(11)和多根第一次支撑柱(12)组成的固定结构,第一主立柱(11)稳固于D基坑内部,第一主立柱(11)通过第一次支撑柱(12)与原支撑结构固定连接,第一加固结构(1)向D2区东北方向和东南方向提供支撑力;The first reinforcement structure (1) is a fixed structure composed of a plurality of first main columns (11) and a plurality of first support columns (12). The first main columns (11) are stable inside the D foundation pit. A main column (11) is fixedly connected to the original support structure through the first support column (12), and the first reinforcement structure (1) provides support force to the northeast and southeast of the D2 area;
    所述第二加固结构(2)为多根第二主立柱(21)和多根第二次支撑柱(22)组成的固定结构,第二主立柱(21)稳固于A基坑内部,第二主立柱(21)通过第二次支撑柱(22)相互连接,且第二主立柱(21)通过第二次支撑柱(22)固定连接于原支撑结构,第二加固结构(2)为A1区提供东北方向的支撑力。The second reinforcement structure (2) is a fixed structure composed of a plurality of second main columns (21) and a plurality of second support columns (22). The second main columns (21) are stable inside the foundation pit A. The two main columns (21) are connected to each other through the second support column (22), and the second main column (21) is fixedly connected to the original support structure through the second support column (22). The second reinforcement structure (2) is Zone A1 provides support in the northeast direction.
  2.   根据权利要求1所述的一种双基坑双工况建造方法,其特征在于:多根所述第一主立柱(11)分为两组,两组第一主立柱(11)的连线均平行于南北方向,第一主立柱(11)之间通过第一次支撑柱(12)连接,第一主立柱(11)与原支撑结构通过第一次支撑柱(12)固定连接。A method of construction of double foundation pits and double working conditions according to claim 1, characterized in that: the plurality of first main columns (11) are divided into two groups, and the connection lines of the two groups of first main columns (11) Both are parallel to the north-south direction, the first main columns (11) are connected through the first support column (12), and the first main column (11) is fixedly connected to the original support structure through the first support column (12).
  3.   根据权利要求1所述的一种双基坑双工况建造方法,其特征在于:多根所述第二主立柱(21)的连线与正东方向存在夹角,第二主立柱(21)通过第二次支撑柱(22)连接于A1区东北方向的原支撑结构。A method of construction of double foundation pits and double working conditions according to claim 1, characterized in that: the connection lines of the plurality of second main columns (21) have an angle with the due east direction, and the second main columns (21) ) is connected to the original support structure in the northeast direction of Area A1 through the second support column (22).
PCT/CN2023/113517 2022-08-19 2023-08-17 Double-foundation-pit double-working-condition construction method WO2024037586A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202211001529.6 2022-08-19
CN202211001529.6A CN115387344B (en) 2022-08-19 2022-08-19 Double-foundation pit double-working-condition rapid construction method

Publications (1)

Publication Number Publication Date
WO2024037586A1 true WO2024037586A1 (en) 2024-02-22

Family

ID=84119744

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2023/113517 WO2024037586A1 (en) 2022-08-19 2023-08-17 Double-foundation-pit double-working-condition construction method

Country Status (2)

Country Link
CN (1) CN115387344B (en)
WO (1) WO2024037586A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115387344B (en) * 2022-08-19 2023-09-12 中建三局第三建设工程有限责任公司 Double-foundation pit double-working-condition rapid construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2140603A1 (en) * 1971-08-13 1973-02-22 Aufschlaeger Kg Ferd PROCESS FOR THE PRODUCTION OF PIT ENCLOSURES, SLOPE AND BUILDING SECURING
CN203613544U (en) * 2013-11-29 2014-05-28 中船第九设计研究院工程有限公司 Envelop enclosure for deep foundation pit partition simultaneous excavation
CN109723085A (en) * 2019-01-17 2019-05-07 中建三局集团有限公司 A kind of deep basal pit point hole construction rib wall support changing structure for use and its construction method
CN112359839A (en) * 2020-11-17 2021-02-12 中建八局科技建设有限公司 Method for rapidly completing foundation pit earthwork and supporting flowing water construction by utilizing old diaphragm wall
KR20210090100A (en) * 2020-01-08 2021-07-19 임인식 In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
CN114703861A (en) * 2022-03-30 2022-07-05 中国建筑第八工程局有限公司 Double-foundation-pit construction method with shared supporting piles
CN115387344A (en) * 2022-08-19 2022-11-25 中建三局第三建设工程有限责任公司 Double-foundation-pit double-working-condition rapid construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103114594B (en) * 2013-03-06 2014-12-17 熊楚炎 Supporting structure of adjacent two foundation trenches and construction method thereof
CN204551487U (en) * 2015-03-30 2015-08-12 中国建筑第六工程局有限公司 A kind of steel support structure that can realize Adjacent Pit synchronous construction
CN110409454A (en) * 2019-08-07 2019-11-05 上海建工二建集团有限公司 Open foundation pit block construction system and method
CN114016513B (en) * 2021-10-26 2023-03-07 南京林业大学 Time-sequence-sharing excavation method of complex foundation pit group supporting system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2140603A1 (en) * 1971-08-13 1973-02-22 Aufschlaeger Kg Ferd PROCESS FOR THE PRODUCTION OF PIT ENCLOSURES, SLOPE AND BUILDING SECURING
CN203613544U (en) * 2013-11-29 2014-05-28 中船第九设计研究院工程有限公司 Envelop enclosure for deep foundation pit partition simultaneous excavation
CN109723085A (en) * 2019-01-17 2019-05-07 中建三局集团有限公司 A kind of deep basal pit point hole construction rib wall support changing structure for use and its construction method
KR20210090100A (en) * 2020-01-08 2021-07-19 임인식 In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
CN112359839A (en) * 2020-11-17 2021-02-12 中建八局科技建设有限公司 Method for rapidly completing foundation pit earthwork and supporting flowing water construction by utilizing old diaphragm wall
CN114703861A (en) * 2022-03-30 2022-07-05 中国建筑第八工程局有限公司 Double-foundation-pit construction method with shared supporting piles
CN115387344A (en) * 2022-08-19 2022-11-25 中建三局第三建设工程有限责任公司 Double-foundation-pit double-working-condition rapid construction method

Also Published As

Publication number Publication date
CN115387344A (en) 2022-11-25
CN115387344B (en) 2023-09-12

Similar Documents

Publication Publication Date Title
WO2024037586A1 (en) Double-foundation-pit double-working-condition construction method
CN103541364A (en) Design and construction method of large area foundation pit deformation control with roundabout method
CN109610466B (en) Unsynchronized construction method and structure of irregular deep foundation pits on two sides of built subway station
CN111155532A (en) Deep foundation pit supporting structure and construction method thereof
CN103321658A (en) Molded lining support structure and construction method for soft soil ground layer
CN110424411A (en) A kind of irregular foundation pit assembled steel support device and its construction and application method
CN111350513B (en) Underground excavation construction method for building subway station
CN104975606A (en) Method for handling high-low strides at adjacent parts of reverse building foundation pit and adjacent foundation pit
CN211500658U (en) Shallow tunnel supporting construction that nearly connects that buries suitable for sand ground
CN109594574B (en) Large pipe jacking open caisson reverse construction method based on limited space
CN111501771A (en) Application method of multi-elliptical-ring combined support in deep large-sludge foundation pit engineering
CN110685283B (en) Sandbar combined tile type foundation pit supporting structure and construction method thereof
CN112281861A (en) Support system for transfer node of urban rail transit transfer station and construction method
CN212270948U (en) Supporting structure capable of realizing cross implementation of adjacent foundation pits
CN109339510A (en) One kind being suitable for major diameter underground shaft type constructed parking garage structure and its construction method
CN105804086A (en) Construction method for support change joints in foundation trench reverse building method construction
CN211523226U (en) Inner support system for foundation pit
CN211257915U (en) Floor-adding structure of existing building underground space
CN203321539U (en) Moulded lining support structure
CN105155578A (en) Construction method for existing supporting system connected into subway in complex geology and environment
CN204780965U (en) Complicated geology and existing system construction structures that struts of environment access subway
CN217758840U (en) Multichannel multilayer self-stabilization type foundation pit supporting device
CN211690370U (en) Deep foundation pit supporting structure
CN218508442U (en) Deep foundation pit earth excavation structure for protecting existing structure
CN113718796B (en) Underground structure system with foundation pit supporting function and construction method

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 23854485

Country of ref document: EP

Kind code of ref document: A1