Large pipe jacking open caisson reverse construction method based on limited space
Technical Field
The invention relates to the technical field of underground engineering, in particular to a large-scale pipe jacking open caisson reverse construction method based on a limited space.
Background
In urban rail transit construction, a large number of municipal pipelines, gas, tap water and rain sewage pipelines need to be moved and modified due to construction requirements, wherein high-voltage cables such as 220KV, 110KV and 10KV with high risks, medium-voltage gas pipelines, high-voltage large-diameter tap water main pipelines and other large numbers of municipal pipelines need to be moved frequently. In actual construction, some pipelines are difficult to migrate and interfere with a station structure of rail transit, so that a lot of difficulties are brought to rail transit construction, and how to solve the construction problems needs to perform comparison and selection of multiple construction schemes and select an optimal scheme from the multiple construction schemes.
In some constructions, pipelines need to pass through a main trunk in the migration, and in order to ensure the smoothness of the main trunk, underground (high-pressure) pipelines are migrated by a multi-pass pipe jacking method, most of jacking pipes are less than 1.5m in diameter, and fewer jacking pipes with the pipe diameter of 3m are used. According to the technology of pipe-jacking construction, the open caisson must be constructed first, the depth of the open caisson is usually affected by various external factors, the existing underground obstacles can be avoided safely only by needing large burial depth, the burial depth of the open caisson is increased, and the difficulty and risk of construction are greatly increased.
Disclosure of Invention
The invention aims to provide a large pipe jacking open caisson reverse construction method based on limited space, which effectively controls the deformation of the earth surface and a retaining structure, the cross construction of foundation pit excavation and a main body structure, and the direct transmission of the self load of a reverse construction structure to a foundation through an upright column, reduces the influence of excavation unloading on a bearing stratum, improves the construction safety, is beneficial to protecting the environment, and meets the requirement of green construction.
In order to achieve the purpose, the invention provides a reverse construction method of a large pipe-jacking open caisson based on a limited space, which comprises the following steps:
A. leveling the field: leveling a pre-constructed field, removing foreign matters on the ground, and enclosing and sealing the construction field according to the requirement of green construction;
B. lofting for the first measurement: determining the ground position of the open caisson excavation according to design requirements;
C. constructing a steel sheet pile: constructing a fender post before the open caisson is excavated according to the measured setting-out position;
D. excavating the earth on the first layer: excavating earth surface soil bodies after the construction of the steel sheet piles is finished;
E. and (3) second measurement lofting: rechecking the space position of the excavation space after the first layer of excavation is finished;
F. construction of a first-section structure: constructing a first section of reinforced concrete structure of the open caisson;
G. and (5) excavating a second earth-saving side: after the construction of the first section of structure is completed, open caisson earthwork excavation construction is carried out;
H. the second section of north-south structure is inverted: constructing concrete structures on the north and south sides of the open caisson;
I. excavating east-west earthwork of a second section: excavating earthwork in the structural range of the second section of open caisson;
J. and (3) constructing a second east-west structure: constructing concrete structures on the two sides of the open caisson;
K. subsequent segment construction and bottom sealing: and constructing subsequent sections of the open caisson in sequence after the construction of the east-west structure of the second section, and finally performing open caisson bottom sealing construction.
Preferably, the fender pile adopts a Larsen sheet pile with a water stopping function, and the Larsen sheet pile forms connection by means of the connecting groove.
Preferably, the first layer of earthwork excavation is earth surface soil excavation performed after the construction of the steel sheet pile is finished, the excavation depth of the first layer of earthwork excavation meets the height of the first section of structure of the open caisson, and the supporting effect of the fender post on the soil body meets the requirement of soil body stability.
Preferably, the first section of structure construction is carried out after the first layer of earthwork excavation is finished and the excavation size is checked again through measurement, and then steel bar binding, concrete pouring and maintenance construction of the first section of open caisson structure are carried out.
Preferably, the excavation depth of the second section of earth excavation meets the requirement of the height of the second section of open caisson, soil bodies at the concrete bottom of the first sections of open caisson on the east and west sides are reserved in the excavation process, then soil bodies on the north and south sides are excavated, and the excavation size meets the requirement of the open caisson structure size.
Preferably, the second section of the south-north structure is reversely constructed by binding the reinforcing steel bars of the open caisson structure on the south and north sides and pouring concrete after the earth excavation on the south and north sides meets the design requirements.
Preferably, after the second east-west earth excavation is finished for the construction of the north-south concrete structure and reaches the strength required by the design, the east-west earth body is excavated and the design requirement is met.
Preferably, after the second east-west east soil body excavation meets the design requirements, reinforcement and concrete pouring construction of the open caisson structure is carried out.
Preferably, the subsequent segment construction and bottom sealing are the third segment open caisson structure construction according to the construction method of the second segment open caisson, the fourth segment open caisson structure can be continuously constructed according to the open caisson design, and the open caisson bottom sealing construction is carried out according to the design requirements after the structure meets the design requirements.
Therefore, the large pipe-jacking open caisson reverse construction method based on the limited space, which adopts the structure, effectively controls the deformation of the earth surface and the enclosure structure, the cross construction of the excavation of the foundation pit and the main structure, and the direct transmission of the self load of the reverse construction structure to the foundation by the upright post, simultaneously reduces the influence of excavation unloading on the bearing layer, improves the construction safety, is beneficial to protecting the environment, and meets the requirement of green construction.
The technical solution of the present invention is further described in detail by the accompanying drawings and embodiments.
Drawings
FIG. 1 is a flow chart of an embodiment of a large pipe jacking open caisson reverse construction method based on limited space.
Detailed Description
Examples
FIG. 1 is a flow chart of an embodiment of a large pipe jacking open caisson reverse construction method based on limited space. As shown in the figure, the invention provides a large pipe jacking open caisson reverse construction method based on a limited space, which comprises the following steps:
A. leveling the field: leveling a pre-constructed field, removing foreign matters on the ground, and enclosing and sealing the construction field according to the requirement of green construction;
B. lofting for the first measurement: determining the ground position of the open caisson excavation according to design requirements;
C. constructing a steel sheet pile: according to the measurement and setting-out position, carrying out guard pile construction before open caisson excavation, wherein the guard pile adopts Larsen sheet piles with water stopping functions, and the Larsen sheet piles form connection by means of connecting grooves;
D. excavating the earth on the first layer: excavating earth surface soil bodies after the construction of the steel sheet piles is finished, wherein the excavation depth meets the height of a first section structure of the open caisson, and the supporting effect of the fender piles on the soil bodies meets the requirement of soil body stability;
E. and (3) second measurement lofting: rechecking the space position of the excavation space after the first layer of excavation is finished;
F. construction of a first-section structure: constructing a first section of reinforced concrete structure of the open caisson, namely binding reinforcing steel bars of the first section of open caisson structure, pouring concrete and maintaining construction;
G. and (5) excavating a second earth-saving side: carrying out open caisson earthwork excavation construction after the construction of the first section of structure is finished, wherein the excavation depth of the second section of earthwork excavation meets the requirement of the height of the second section of open caisson, reserving soil bodies at the bottoms of the first sections of open caisson concrete on the east and west sides in the excavation process, excavating soil bodies on the south and north sides, and ensuring that the excavation size meets the requirement of the open caisson structure size so as to prevent the first section of open caisson structure from sinking due to dead weight;
H. the second section of north-south structure is inverted: constructing concrete structures on the south and north sides of the open caisson, and binding reinforcing steel bars and pouring concrete of the open caisson structure on the south and north sides after the earth excavation on the south and north sides meets the design requirements;
I. excavating east-west earthwork of a second section: excavating earthwork in the structural range of the second section of open caisson, excavating soil bodies on the east and west sides after construction for the north and south concrete structures is finished and the strength reaches the design requirement, and meeting the design requirement;
J. and (3) constructing a second east-west structure: constructing concrete structures on the east and west sides of the open caisson, and performing reinforcement binding and concrete pouring construction on the open caisson structure after the design requirements are met for soil excavation on the east and west sides;
K. subsequent segment construction and bottom sealing: and constructing subsequent sections of the open caisson in sequence after the construction of the second section of the structure, finally performing open caisson bottom sealing construction, constructing a third section of open caisson structure according to the construction method of the second section of the open caisson, continuously constructing a fourth section of open caisson structure according to the open caisson design, performing open caisson bottom sealing construction according to the design requirement until the structure meets the design requirement, ensuring the quality of construction joint concrete for chiseling hair, and ensuring the waterproof performance of the structure.
The invention solves the problem that the large buried depth pipe-jacking open caisson is constructed by adopting a reverse construction method in a composite stratum with soft upper stratum and narrow available ground space in the construction of the large pipe-jacking open caisson, is favorable for ensuring normal traffic order and is also favorable for quickly, safely and efficiently completing pipeline moving and modifying construction.
Therefore, the large pipe-jacking open caisson reverse construction method based on the limited space, which adopts the structure, effectively controls the deformation of the earth surface and the enclosure structure, the cross construction of the excavation of the foundation pit and the main structure, and the direct transmission of the self load of the reverse construction structure to the foundation by the upright post, simultaneously reduces the influence of excavation unloading on the bearing layer, improves the construction safety, is beneficial to protecting the environment, and meets the requirement of green construction.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting the same, and although the present invention is described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that: modifications and equivalents may be made to the invention without departing from the spirit and scope of the invention.