CN109594574B - Reverse construction method of large pipe jacking caisson based on limited space - Google Patents

Reverse construction method of large pipe jacking caisson based on limited space Download PDF

Info

Publication number
CN109594574B
CN109594574B CN201811515094.0A CN201811515094A CN109594574B CN 109594574 B CN109594574 B CN 109594574B CN 201811515094 A CN201811515094 A CN 201811515094A CN 109594574 B CN109594574 B CN 109594574B
Authority
CN
China
Prior art keywords
construction
caisson
section
excavation
east
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811515094.0A
Other languages
Chinese (zh)
Other versions
CN109594574A (en
Inventor
温法庆
孙连勇
王忠仁
门燕青
崔新壮
王磊
卢途
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
China Railway 18th Bureau Group Co Ltd
Jinan Rail Transit Group Co Ltd
Third Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
Shandong University
China Railway 18th Bureau Group Co Ltd
Jinan Rail Transit Group Co Ltd
Third Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University, China Railway 18th Bureau Group Co Ltd, Jinan Rail Transit Group Co Ltd, Third Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical Shandong University
Priority to CN201811515094.0A priority Critical patent/CN109594574B/en
Publication of CN109594574A publication Critical patent/CN109594574A/en
Application granted granted Critical
Publication of CN109594574B publication Critical patent/CN109594574B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种基于有限空间的大型顶管沉井逆作施工方法,对预施工的场地进行平整;根据设计要求,确定开挖沉井的地面位置;根据测量放线位置,进行沉围护桩施工;然后进行地表土体挖除;对开挖空间的空间位置进行复核;对沉井的第一节钢筋混凝土结构施工;首节结构施工完成后进行沉井土方开挖施工;对沉井南北两侧的混凝土结构施工;挖除第二节沉井结构范围内的土方;对沉井东西两侧的混凝土结构施工;第二节东西结构施工后施工沉井后续节段,进行沉井封底施工,有效的控制了地表及围护结构变形、基坑开挖与主体结构交叉施工、逆作结构的自身荷载由立柱直接传给地基,同时减小了开挖卸载对持力层的影响,提高了施工安全,同时利于保护环境。

Figure 201811515094

The invention discloses a large-scale pipe jacking caisson reverse construction method based on limited space. The pre-construction site is leveled; the ground position of the excavation caisson is determined according to design requirements; pile guard construction; then excavate the surface soil; review the spatial position of the excavation space; construct the reinforced concrete structure of the first section of the caisson; Construction of the concrete structures on the north and south sides of the well; excavation of the earthwork within the scope of the second section of the caisson structure; construction of the concrete structures on the east and west sides of the caisson; construction of the subsequent sections of the caisson after the construction of the second section of the east-west structure, and caisson The back cover construction effectively controls the deformation of the surface and the enclosure structure, the cross-construction of the foundation pit excavation and the main structure, and the self-load of the inverse structure is directly transmitted to the foundation from the column, and at the same time, the influence of excavation and unloading on the bearing layer is reduced. , improve the construction safety, and at the same time help to protect the environment.

Figure 201811515094

Description

Large pipe jacking open caisson reverse construction method based on limited space
Technical Field
The invention relates to the technical field of underground engineering, in particular to a large-scale pipe jacking open caisson reverse construction method based on a limited space.
Background
In urban rail transit construction, a large number of municipal pipelines, gas, tap water and rain sewage pipelines need to be moved and modified due to construction requirements, wherein high-voltage cables such as 220KV, 110KV and 10KV with high risks, medium-voltage gas pipelines, high-voltage large-diameter tap water main pipelines and other large numbers of municipal pipelines need to be moved frequently. In actual construction, some pipelines are difficult to migrate and interfere with a station structure of rail transit, so that a lot of difficulties are brought to rail transit construction, and how to solve the construction problems needs to perform comparison and selection of multiple construction schemes and select an optimal scheme from the multiple construction schemes.
In some constructions, pipelines need to pass through a main trunk in the migration, and in order to ensure the smoothness of the main trunk, underground (high-pressure) pipelines are migrated by a multi-pass pipe jacking method, most of jacking pipes are less than 1.5m in diameter, and fewer jacking pipes with the pipe diameter of 3m are used. According to the technology of pipe-jacking construction, the open caisson must be constructed first, the depth of the open caisson is usually affected by various external factors, the existing underground obstacles can be avoided safely only by needing large burial depth, the burial depth of the open caisson is increased, and the difficulty and risk of construction are greatly increased.
Disclosure of Invention
The invention aims to provide a large pipe jacking open caisson reverse construction method based on limited space, which effectively controls the deformation of the earth surface and a retaining structure, the cross construction of foundation pit excavation and a main body structure, and the direct transmission of the self load of a reverse construction structure to a foundation through an upright column, reduces the influence of excavation unloading on a bearing stratum, improves the construction safety, is beneficial to protecting the environment, and meets the requirement of green construction.
In order to achieve the purpose, the invention provides a reverse construction method of a large pipe-jacking open caisson based on a limited space, which comprises the following steps:
A. leveling the field: leveling a pre-constructed field, removing foreign matters on the ground, and enclosing and sealing the construction field according to the requirement of green construction;
B. lofting for the first measurement: determining the ground position of the open caisson excavation according to design requirements;
C. constructing a steel sheet pile: constructing a fender post before the open caisson is excavated according to the measured setting-out position;
D. excavating the earth on the first layer: excavating earth surface soil bodies after the construction of the steel sheet piles is finished;
E. and (3) second measurement lofting: rechecking the space position of the excavation space after the first layer of excavation is finished;
F. construction of a first-section structure: constructing a first section of reinforced concrete structure of the open caisson;
G. and (5) excavating a second earth-saving side: after the construction of the first section of structure is completed, open caisson earthwork excavation construction is carried out;
H. the second section of north-south structure is inverted: constructing concrete structures on the north and south sides of the open caisson;
I. excavating east-west earthwork of a second section: excavating earthwork in the structural range of the second section of open caisson;
J. and (3) constructing a second east-west structure: constructing concrete structures on the two sides of the open caisson;
K. subsequent segment construction and bottom sealing: and constructing subsequent sections of the open caisson in sequence after the construction of the east-west structure of the second section, and finally performing open caisson bottom sealing construction.
Preferably, the fender pile adopts a Larsen sheet pile with a water stopping function, and the Larsen sheet pile forms connection by means of the connecting groove.
Preferably, the first layer of earthwork excavation is earth surface soil excavation performed after the construction of the steel sheet pile is finished, the excavation depth of the first layer of earthwork excavation meets the height of the first section of structure of the open caisson, and the supporting effect of the fender post on the soil body meets the requirement of soil body stability.
Preferably, the first section of structure construction is carried out after the first layer of earthwork excavation is finished and the excavation size is checked again through measurement, and then steel bar binding, concrete pouring and maintenance construction of the first section of open caisson structure are carried out.
Preferably, the excavation depth of the second section of earth excavation meets the requirement of the height of the second section of open caisson, soil bodies at the concrete bottom of the first sections of open caisson on the east and west sides are reserved in the excavation process, then soil bodies on the north and south sides are excavated, and the excavation size meets the requirement of the open caisson structure size.
Preferably, the second section of the south-north structure is reversely constructed by binding the reinforcing steel bars of the open caisson structure on the south and north sides and pouring concrete after the earth excavation on the south and north sides meets the design requirements.
Preferably, after the second east-west earth excavation is finished for the construction of the north-south concrete structure and reaches the strength required by the design, the east-west earth body is excavated and the design requirement is met.
Preferably, after the second east-west east soil body excavation meets the design requirements, reinforcement and concrete pouring construction of the open caisson structure is carried out.
Preferably, the subsequent segment construction and bottom sealing are the third segment open caisson structure construction according to the construction method of the second segment open caisson, the fourth segment open caisson structure can be continuously constructed according to the open caisson design, and the open caisson bottom sealing construction is carried out according to the design requirements after the structure meets the design requirements.
Therefore, the large pipe-jacking open caisson reverse construction method based on the limited space, which adopts the structure, effectively controls the deformation of the earth surface and the enclosure structure, the cross construction of the excavation of the foundation pit and the main structure, and the direct transmission of the self load of the reverse construction structure to the foundation by the upright post, simultaneously reduces the influence of excavation unloading on the bearing layer, improves the construction safety, is beneficial to protecting the environment, and meets the requirement of green construction.
The technical solution of the present invention is further described in detail by the accompanying drawings and embodiments.
Drawings
FIG. 1 is a flow chart of an embodiment of a large pipe jacking open caisson reverse construction method based on limited space.
Detailed Description
Examples
FIG. 1 is a flow chart of an embodiment of a large pipe jacking open caisson reverse construction method based on limited space. As shown in the figure, the invention provides a large pipe jacking open caisson reverse construction method based on a limited space, which comprises the following steps:
A. leveling the field: leveling a pre-constructed field, removing foreign matters on the ground, and enclosing and sealing the construction field according to the requirement of green construction;
B. lofting for the first measurement: determining the ground position of the open caisson excavation according to design requirements;
C. constructing a steel sheet pile: according to the measurement and setting-out position, carrying out guard pile construction before open caisson excavation, wherein the guard pile adopts Larsen sheet piles with water stopping functions, and the Larsen sheet piles form connection by means of connecting grooves;
D. excavating the earth on the first layer: excavating earth surface soil bodies after the construction of the steel sheet piles is finished, wherein the excavation depth meets the height of a first section structure of the open caisson, and the supporting effect of the fender piles on the soil bodies meets the requirement of soil body stability;
E. and (3) second measurement lofting: rechecking the space position of the excavation space after the first layer of excavation is finished;
F. construction of a first-section structure: constructing a first section of reinforced concrete structure of the open caisson, namely binding reinforcing steel bars of the first section of open caisson structure, pouring concrete and maintaining construction;
G. and (5) excavating a second earth-saving side: carrying out open caisson earthwork excavation construction after the construction of the first section of structure is finished, wherein the excavation depth of the second section of earthwork excavation meets the requirement of the height of the second section of open caisson, reserving soil bodies at the bottoms of the first sections of open caisson concrete on the east and west sides in the excavation process, excavating soil bodies on the south and north sides, and ensuring that the excavation size meets the requirement of the open caisson structure size so as to prevent the first section of open caisson structure from sinking due to dead weight;
H. the second section of north-south structure is inverted: constructing concrete structures on the south and north sides of the open caisson, and binding reinforcing steel bars and pouring concrete of the open caisson structure on the south and north sides after the earth excavation on the south and north sides meets the design requirements;
I. excavating east-west earthwork of a second section: excavating earthwork in the structural range of the second section of open caisson, excavating soil bodies on the east and west sides after construction for the north and south concrete structures is finished and the strength reaches the design requirement, and meeting the design requirement;
J. and (3) constructing a second east-west structure: constructing concrete structures on the east and west sides of the open caisson, and performing reinforcement binding and concrete pouring construction on the open caisson structure after the design requirements are met for soil excavation on the east and west sides;
K. subsequent segment construction and bottom sealing: and constructing subsequent sections of the open caisson in sequence after the construction of the second section of the structure, finally performing open caisson bottom sealing construction, constructing a third section of open caisson structure according to the construction method of the second section of the open caisson, continuously constructing a fourth section of open caisson structure according to the open caisson design, performing open caisson bottom sealing construction according to the design requirement until the structure meets the design requirement, ensuring the quality of construction joint concrete for chiseling hair, and ensuring the waterproof performance of the structure.
The invention solves the problem that the large buried depth pipe-jacking open caisson is constructed by adopting a reverse construction method in a composite stratum with soft upper stratum and narrow available ground space in the construction of the large pipe-jacking open caisson, is favorable for ensuring normal traffic order and is also favorable for quickly, safely and efficiently completing pipeline moving and modifying construction.
Therefore, the large pipe-jacking open caisson reverse construction method based on the limited space, which adopts the structure, effectively controls the deformation of the earth surface and the enclosure structure, the cross construction of the excavation of the foundation pit and the main structure, and the direct transmission of the self load of the reverse construction structure to the foundation by the upright post, simultaneously reduces the influence of excavation unloading on the bearing layer, improves the construction safety, is beneficial to protecting the environment, and meets the requirement of green construction.
Finally, it should be noted that: the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting the same, and although the present invention is described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that: modifications and equivalents may be made to the invention without departing from the spirit and scope of the invention.

Claims (9)

1.一种基于有限空间的大型顶管沉井逆作施工方法,其特征在于,包括以下步骤:1. a large-scale pipe jacking caisson reverse construction method based on limited space, is characterized in that, comprises the following steps: A、平整场地:对预施工的场地进行平整,清除地面异物,根据绿色施工的要求进行施工场地的围挡及封闭;A. Leveling the site: leveling the pre-construction site, removing foreign objects on the ground, and enclosing and sealing the construction site according to the requirements of green construction; B、第一次测量放样:根据设计要求,确定开挖沉井的地面位置;B. The first measurement and stakeout: according to the design requirements, determine the ground position of the excavated caisson; C、钢板桩施工:根据测量放线位置,进行沉井开挖前的围护桩施工;C. Steel sheet pile construction: According to the measured lay-out position, carry out the construction of the enclosure piles before the caisson excavation; D、第一层土方开挖:钢板桩施工完毕后进行地表土体挖除;D. The first layer of earth excavation: excavate the surface soil after the steel sheet pile construction is completed; E、第二次测量放样:第一层开挖完成后对开挖空间的空间位置进行复核;E. The second measurement and stakeout: after the excavation of the first floor is completed, the spatial position of the excavation space shall be reviewed; F、首节结构施工:对沉井的第一节钢筋混凝土结构进行施工;F. Construction of the first section: construction of the first section of the reinforced concrete structure of the caisson; G、第二节土方开挖:首节结构施工完成后进行沉井土方开挖施工;G. The second section of earthwork excavation: after the first section of structural construction is completed, the earthwork excavation of the caisson shall be carried out; H、第二节南北结构逆作:对沉井南北两侧的混凝土结构进行施工;H. Section 2 North-South Structure Reverse Operation: Construct the concrete structures on the north and south sides of the caisson; I、第二节东西土方开挖:挖除第二节沉井结构范围内的土方;I. Section 2 East-West earthwork excavation: excavate the earthwork within the scope of the caisson structure in Section 2; J、第二节东西结构施工:对沉井东西两侧的混凝土结构进行施工;J. Section 2 East-West Structure Construction: Construction of the concrete structures on the east and west sides of the caisson; K、后续节段施工及封底:第二节东西结构施工后依次施工沉井后续节段,最后进行沉井封底施工。K. Subsequent section construction and back cover: After the construction of the second section of the east-west structure, the subsequent sections of the caisson are constructed in sequence, and finally the back cover construction of the caisson is carried out. 2.根据权利要求1所述的基于有限空间的大型顶管沉井逆作施工方法,其特征在于:所述围护桩采用具有止水功能的拉森板桩,所述拉森板桩依靠连接沟槽形成连接。2. The large-scale pipe jacking caisson reverse construction method based on limited space according to claim 1, characterized in that: the enclosure pile adopts a Larsen sheet pile with a water-stop function, and the Larsen sheet pile relies on The connection trench forms the connection. 3.根据权利要求1所述的基于有限空间的大型顶管沉井逆作施工方法,其特征在于:所述第一层土方开挖为钢板桩施工完毕后进行的地表土体挖除,其开挖深度满足沉井第一节结构的高度,且保证围护桩对土体的支护作用满足土体稳定性要求。3. The large-scale pipe jacking caisson reverse construction method based on limited space according to claim 1, characterized in that: the first layer of earth excavation is the surface soil excavation carried out after the steel sheet pile construction is completed, and the The excavation depth should meet the height of the structure of the first section of the caisson, and ensure that the supporting effect of the retaining piles on the soil meets the requirements of soil stability. 4.根据权利要求1所述的基于有限空间的大型顶管沉井逆作施工方法,其特征在于:首节结构施工在第一层土方开挖完毕后及经测量复核开挖尺寸后,进行第一节沉井结构的钢筋绑扎、混凝土浇筑及养护施工。4. The large-scale pipe jacking caisson reverse construction method based on limited space according to claim 1, is characterized in that: the construction of the first section is carried out after the excavation of the first layer of earthwork is completed and after the excavation size is checked and measured. The first section of the caisson structure is steel binding, concrete pouring and maintenance construction. 5.根据权利要求1所述的基于有限空间的大型顶管沉井逆作施工方法,其特征在于:第二节土方开挖的开挖深度满足第二节沉井高度要求,在开挖过程中预留东西两侧第一节沉井混凝土底部土体,然后开挖南北两侧土体,且开挖尺寸满足沉井结构尺寸要求。5. The large-scale pipe jacking caisson reverse construction method based on limited space according to claim 1 is characterized in that: the excavation depth of the second section of earthwork excavation meets the second section caisson height requirement, and in the excavation process The soil body at the bottom of the first section of the caisson concrete on the east and west sides is reserved, and then the soil body on the north and south sides is excavated, and the excavation size meets the structural size requirements of the caisson. 6.根据权利要求1所述的基于有限空间的大型顶管沉井逆作施工方法,其特征在于:第二节南北结构逆作是在南北侧土方开挖满足设计要求后,进行南北侧沉井结构的钢筋绑扎及混凝土浇筑。6. The large-scale pipe jacking caisson reverse construction method based on limited space according to claim 1, is characterized in that: the second section north-south structure reverse construction is to carry out north-south side sinking after the earth excavation on the north-south side meets the design requirements. Rebar binding and concrete pouring of well structure. 7.根据权利要求1所述的基于有限空间的大型顶管沉井逆作施工方法,其特征在于:第二节东西土方开挖为南北混凝土结构施工完毕并达到设计要求强度后,开挖东西侧土体,并满足设计要求。7. The large-scale pipe jacking caisson reverse construction method based on limited space according to claim 1, is characterized in that: the second section of east-west earthwork excavation is that after the north-south concrete structure construction is completed and reaches the required strength of the design, the east-west excavation is completed. side soil and meet the design requirements. 8.根据权利要求1所述的基于有限空间的大型顶管沉井逆作施工方法,其特征在于:第二节东西结构施工为东西侧土体开挖满足设计要求后,进行沉井结构的钢筋绑扎及混凝土浇筑施工。8. The large-scale pipe jacking caisson reverse construction method based on limited space according to claim 1, is characterized in that: the second section east-west structure construction is that after the soil excavation on the east and west sides meets the design requirements, the caisson structure is carried out. Reinforcement binding and concrete pouring construction. 9.根据权利要求1所述的基于有限空间的大型顶管沉井逆作施工方法,其特征在于:后续节段施工及封底是按照第二节沉井的施工方法施工第三节沉井结构施工,根据沉井设计继续施工第四节沉井结构,直到结构满足设计要求后,按设计要求进行沉井封底施工。9. the large-scale pipe jacking caisson reverse construction method based on limited space according to claim 1, is characterized in that: follow-up section construction and back cover are to construct the third section caisson structure according to the construction method of the second section caisson Construction, according to the caisson design, continue to construct the fourth section of the caisson structure until the structure meets the design requirements, and then carry out the caisson bottom sealing construction according to the design requirements.
CN201811515094.0A 2018-12-12 2018-12-12 Reverse construction method of large pipe jacking caisson based on limited space Active CN109594574B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811515094.0A CN109594574B (en) 2018-12-12 2018-12-12 Reverse construction method of large pipe jacking caisson based on limited space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811515094.0A CN109594574B (en) 2018-12-12 2018-12-12 Reverse construction method of large pipe jacking caisson based on limited space

Publications (2)

Publication Number Publication Date
CN109594574A CN109594574A (en) 2019-04-09
CN109594574B true CN109594574B (en) 2021-11-02

Family

ID=65961708

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811515094.0A Active CN109594574B (en) 2018-12-12 2018-12-12 Reverse construction method of large pipe jacking caisson based on limited space

Country Status (1)

Country Link
CN (1) CN109594574B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113216294B (en) * 2021-05-14 2022-02-15 南京工业大学 A kind of equipment and construction method for soil excavation in narrow area in reverse construction
CN113802608B (en) * 2021-10-22 2022-12-20 武汉市武昌市政建设(集团)有限公司 Open caisson structure applied to narrow zone and construction method thereof
CN114319405A (en) * 2021-12-10 2022-04-12 上海市基础工程集团有限公司 Construction method for micro-disturbance vertical press-in type thin-wall open caisson in complex environment
CN115453611B (en) * 2022-09-14 2025-04-04 广东电网有限责任公司 A method and probe rod for detecting electric pipe jacking

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4358040B2 (en) * 2004-06-17 2009-11-04 千葉窯業株式会社 Caisson etc.
CN102635124B (en) * 2012-04-23 2014-12-03 浙江省建工集团有限责任公司 Construction method aiming to large open caisson in weak soil area
CN103195158B (en) * 2013-04-03 2014-12-10 济南城建集团有限公司 Municipal drainage pipeline slurry balance pipe-jacking construction method
CN106369223B (en) * 2016-10-31 2018-04-10 中铁二十局集团第五工程有限公司 A kind of silt stratum pipe jacking construction method
JP6826914B2 (en) * 2017-03-03 2021-02-10 鹿島建設株式会社 Inclination suppression method when caisson is sunk
CN107975040A (en) * 2017-11-30 2018-05-01 上海宝冶集团有限公司 Circular top pipe working pit multiple material handling method of deep foundation pit construction method

Also Published As

Publication number Publication date
CN109594574A (en) 2019-04-09

Similar Documents

Publication Publication Date Title
CN109594574B (en) Reverse construction method of large pipe jacking caisson based on limited space
CN102127974B (en) Design and construction method of additional cellar under existing building
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN103321659A (en) Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method
CN100510281C (en) Semi-inverted construction method for storage tanks with super large diameter and super buried depth
CN109505611B (en) Construction method for realizing underground excavation and top-down construction by utilizing combined jacking pipes
Zheng et al. Field measurements and analysis of real-time capsule grouting to protect existing tunnel adjacent to excavation
CN104131565B (en) A kind of against making the construction method that the earthwork is just made to excavate
CN107489433B (en) Anti-leakage structure and anti-leakage method for tunnel CRD construction method
CN111255462B (en) Pipe curtain cover excavation top-down construction method for subway station construction
CN105756091A (en) Metro station foundation pit construction method for controlling deformation of neighboring buildings
CN111236241A (en) Reinforcement and excavation method of subway foundation pit in soft and water-rich stratum based on half-cover excavation method
CN104005414B (en) Large-size rebar cast in place concrete pile supports the constructional method of column
CN1070250C (en) Time-space effect method for excavation of foundation pit
CN105672351A (en) Construction method of buckling type prefabricated ribbed reinforced concrete comprehensive pipe gallery structure
CN209941754U (en) High-voltage power pipe culvert in-situ protection structure
CN115387344B (en) A rapid construction method for double foundation pits and double working conditions
CN111851508A (en) It is suitable for the structure of high-pressure circular deep foundation pit of water-rich sand egg layer and its construction method
CN113529830B (en) Shallow Buried Tunnel Adjacent Building Isolation-Underpinning Combination Reinforcement Structure and Its Construction Technology
CN202788876U (en) Superimposed bearing arched structure of large-span tunnel on stratum soft in upper layer and hard in lower layer
CN214363618U (en) Construction structure of concrete inverted hanging well suitable for mucky soil
CN205502070U (en) A dual -purpose underground gallery structure
Bai et al. Construction of shallow buried large-span metro stations using the small pipe roof-beam method
CN113279787A (en) Construction method for building pipe curtain supporting structure of ultra-shallow buried large-section underground excavation subway station
CN206845198U (en) A kind of tunnel CRD engineering method anti-leakage structures

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant