KR102355446B1 - Vertical underground structure and method for constructing the same - Google Patents

Vertical underground structure and method for constructing the same Download PDF

Info

Publication number
KR102355446B1
KR102355446B1 KR1020190044774A KR20190044774A KR102355446B1 KR 102355446 B1 KR102355446 B1 KR 102355446B1 KR 1020190044774 A KR1020190044774 A KR 1020190044774A KR 20190044774 A KR20190044774 A KR 20190044774A KR 102355446 B1 KR102355446 B1 KR 102355446B1
Authority
KR
South Korea
Prior art keywords
wall
concrete
unit
concrete wall
constructing
Prior art date
Application number
KR1020190044774A
Other languages
Korean (ko)
Other versions
KR20200122029A (en
Inventor
이경미
Original Assignee
주식회사 티아이에스
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 티아이에스 filed Critical 주식회사 티아이에스
Priority to KR1020190044774A priority Critical patent/KR102355446B1/en
Publication of KR20200122029A publication Critical patent/KR20200122029A/en
Application granted granted Critical
Publication of KR102355446B1 publication Critical patent/KR102355446B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/10Prefabricated parts, e.g. composite sheet piles made of concrete or reinforced concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

본 발명은 지중수직구조물 및 그 시공방법에 관한 것으로, 본 발명은 다각형 또는 폐곡선 형태로 지반에 박혀 토벽을 지지하는 다수 개의 주열식 말뚝들을 포함하는 차수벽; 상기 차수벽에 접촉되도록 상기 차수벽에 수평방향과 수직 방향으로 배열되는 다수 개의 콘크리트패널들을 포함하는 내측콘크리트벽체; 상기 내측콘크리트벽체의 내측 지하바닥에 시공된 바닥체; 상기 내측콘크리트벽체에 설정된 두께로 형성되는 외측콘크리트벽체; 상기 내측콘크리트벽체와 외측콘크리트벽체 사이에 구비되는 방수층;을 포함한다. 본 발명에 따르면, 토벽의 압력을 견고하게 지지하면서 지중에 설치공간을 최소화하여 수직 방향으로 공간을 형성하고, 시공이 간단하면서 시공 기간을 단축시킨다.The present invention relates to an underground vertical structure and a construction method thereof, and the present invention relates to an order wall including a plurality of columnar piles that are embedded in the ground in a polygonal or closed curve shape to support a soil wall; an inner concrete wall including a plurality of concrete panels arranged in a horizontal direction and a vertical direction on the order wall so as to be in contact with the order wall; a floor body constructed on the inner basement floor of the inner concrete wall; an outer concrete wall formed to a thickness set on the inner concrete wall; and a waterproofing layer provided between the inner concrete wall and the outer concrete wall. According to the present invention, the space is formed in the vertical direction by minimizing the installation space in the ground while firmly supporting the pressure of the earth wall, and the construction period is shortened while the construction is simple.

Description

지중수직구조물 및 그 시공방법{VERTICAL UNDERGROUND STRUCTURE AND METHOD FOR CONSTRUCTING THE SAME}Underground vertical structure and its construction method

본 발명은 지중수직구조물 및 그 시공방법에 관한 것이다.The present invention relates to an underground vertical structure and a construction method thereof.

일반적으로, 지중에 설치되는 지하저장탱크, 수직터널 등의 지중수직구조물은 지반에 말뚝들을 설치한 후 지반을 굴착하면서 토류판들 및 띠장들을 설치하고 어스앵커들을 토벽에 설치하는 과정을 반복하면서 설정된 깊이까지 굴착하고 그 지하 바닥으로부터 합판이나 철판 등의 거푸집을 설치하고 콘크리트를 타설하여 구조물을 시공한다. 그러나 이와 같은 시공 방법은 지중수직구조물을 시공한 후 합판이나 철판 등의 거푸집을 철거하여야 하므로 시공이 복잡하고 비용이 많이 발생되는 단점이 있다.In general, underground vertical structures, such as underground storage tanks and vertical tunnels, installed underground, install piles in the ground and then excavate the ground to install earth plates and wales, and install earth anchors to the earth wall while repeating the process of installing the depth set The structure is constructed by excavating to the bottom, installing a form such as plywood or iron plate from the underground floor, and pouring concrete. However, such a construction method has disadvantages in that the construction is complicated and expensive because it is necessary to remove the form such as plywood or iron plate after constructing the underground vertical structure.

대한민국 등록특허 제10-1322089호(2013.10.28. 공고일)(이하, 선행기술이라 함)에는 흙막이벽체에 띠장을 설치하여 띠장과 PC벽체를 버팀보로 지지하여 설치하는 벽체 시공방법이 제시되어 있다. 그러나, 선행기술은 PC벽체 설치 순서가 복잡하며, 배면에 띠장이 설치되어 있어 되메우기 시공이 불가능하여 지하에 속빈공간이 발생되며, 이로 인하여, 도로의 안전 사고에 대한 중대한 문제가 되고 있는 씽크홀의 원인이 될 수 있다. 또한 수직파일에 띠장을 설치할 때 용접 및 볼트체결을 하게 되는데 PC벽체 배면에 접근할 수 있는 공간이 없어 띠장 해체를 못하여 가시설 강재를 해체 및 회수할 수 있는 방법이 없다. 따라서 경제성이 저하되는 단점이 있다.Republic of Korea Patent No. 10-1322089 (published on October 28, 2013) (hereinafter referred to as prior art) proposes a wall construction method in which a wale is installed on a retaining wall to support the wale and the PC wall with braces. However, in the prior art, the installation sequence of the PC wall is complicated, and the backfill construction is impossible because a wale is installed on the back side, so an empty space is generated in the basement. this can be Also, when installing a wale on a vertical pile, welding and bolting are performed, but there is no space to access the back side of the PC wall, so there is no way to dismantle and recover the temporary steel material. Therefore, there is a disadvantage in that economic efficiency is lowered.

본 발명의 목적은 토벽의 압력을 견고하게 지지하면서 지중에 설치공간을 최소화하여 수직 방향으로 공간을 형성하는 지중수직구조물 및 그 시공방법을 제공하는 것이다.An object of the present invention is to provide an underground vertical structure and a construction method thereof, which form a space in a vertical direction by minimizing the installation space in the ground while firmly supporting the pressure of the earth wall.

본 발명의 다른 목적은 시공이 간단하면서 시공 기간을 단축시키는 지중수직구조물 및 그 시공방법을 제공하는 것이다.Another object of the present invention is to provide an underground vertical structure that is simple to construct and shortens the construction period, and a construction method thereof.

상기한 바와 같은 본 발명의 목적을 달성하기 위하여, 다각형 또는 폐곡선 형태로 지반에 설치되어 토벽을 지지하는 다수 개의 주열식 말뚝들을 포함하는 차수벽; 상기 차수벽에 접촉되도록 상기 차수벽에 수평방향과 수직 방향으로 배열되는 다수 개의 콘크리트패널들을 포함하는 내측콘크리트벽체; 상기 내측콘크리트벽체의 내측 지하바닥에 시공된 바닥체; 상기 내측콘크리트벽체에 설정된 두께로 형성되는 외측콘크리트벽체; 상기 내측콘크리트벽체와 외측콘크리트벽체 사이에 구비되는 방수층;을 포함하는 지중수직구조물이 제공된다.In order to achieve the object of the present invention as described above, the order wall comprising a plurality of column-type piles installed in the ground in the form of a polygonal or closed curve to support the earth wall; an inner concrete wall including a plurality of concrete panels arranged in a horizontal direction and a vertical direction on the order wall so as to be in contact with the order wall; a floor body constructed on the inner basement floor of the inner concrete wall; an outer concrete wall formed to a thickness set on the inner concrete wall; An underground vertical structure comprising a; waterproof layer provided between the inner concrete wall and the outer concrete wall is provided.

상기 콘크리트패널은 지지수단에 의해 차수벽에 지지되며, 상기 지지수단은 상기 콘크리트패널에 다수 개의 관통구멍들과, 상기 콘크리트패널의 관통구멍에 관통 삽입되어 상기 차수벽에 박히는 앵커볼트 또는 고정핀을 포함하는 것이 바람직하다.The concrete panel is supported on the order wall by a support means, and the support means includes a plurality of through holes in the concrete panel, and an anchor bolt or fixing pin inserted through the through hole of the concrete panel and inserted into the order wall. it is preferable

상기 바닥체는, 지하 바닥에 타설된 버림콘크리트층과, 상기 버림콘크리트층 상면에 구비되는 방수층과, 상기 방수층 상면에 타설된 기초콘크리트층;을 포함하는 것이 바람직하다.Preferably, the flooring includes a concrete cast layer placed on the basement floor, a waterproof layer provided on the upper surface of the cast concrete layer, and a foundation concrete layer placed on the upper surface of the waterproof layer.

또한, 지중구조물을 시공할 지반에 다각형 또는 폐곡선 형태를 이루도록 주열식 말뚝들을 설치하여 차수벽을 시공하는 단계; 상기 주열식 말뚝들로 둘러 싸여진 지반 굴착영역을 단위 깊이로 굴착하고 상기 단위 깊이로 굴착되어 노출된 주열식 말뚝들에 접촉되도록 주열식 말뚝들을 따라 콘크리트패널들을 수평 방향으로 다각형 또는 폐곡선을 이루도록 배열시키고 상기 배열된 콘크리트패널들을 지지하도록 버팀보들을 설치하여 단위내측콘크리트벽체를 시공하는 단위내측벽체시공단계; 상기 단위내측벽체시공단계를 설정된 깊이까지 반복하여 폐곡선 형태의 내측콘크리트벽체를 시공하는 단계; 상기 내측콘크리트벽체의 내부 지하 바닥에 버림콘크리트를 타설하는 단계; 상기 내측콘크리트벽체와 버림콘크리트에 방수층을 시공하는 단계; 상기 버림콘크리트의 방수층에 기초콘크리트를 타설하는 단계; 상기 기초콘크리트의 상측으로 인접한 단위내측벽체시공단계로 설치된 버팀보들을 철거하는 단계; 상기 내측콘크리트벽체에 이어 단위외측콘크리트벽체를 타설하도록 상기 내측콘크리트벽체에 거푸집을 설치하는 단계; 상기 거푸집에 콘크리트를 타설하고 양생시켜 단위외측콘크리트벽체를 시공하는 단계; 상기 단위외측콘크리트벽체 바로 위에 위치하는 단위내측벽체시공단계로 설치된 버팀보들을 철거하고 상기 단위외측콘크리트벽체 위로 단위외측콘크리트벽체를 시공하는 단위외측벽체시공단계를 반복하여 외측콘크리트벽체를 시공하는 단계;를 포함하는 지중수직구조물 시공방법이 제공된다.In addition, the steps of constructing an order wall by installing column-type piles to form a polygonal or closed curve shape in the ground to construct the underground structure; The ground excavation area surrounded by the column-type piles is excavated to a unit depth, and the concrete panels are arranged to form a polygonal or closed curve in the horizontal direction along the column-type piles so as to be in contact with the exposed column-type piles excavated to the unit depth. a unit inner wall construction step of constructing a unit inner concrete wall by installing braces to support the arranged concrete panels; repeating the unit inner wall construction step to a set depth to construct an inner concrete wall in the form of a closed curve; pouring discarded concrete on the inner basement floor of the inner concrete wall; constructing a waterproofing layer on the inner concrete wall and the abandoned concrete; pouring the foundation concrete on the waterproof layer of the discarded concrete; dismantling the braces installed in the unit inner wall construction step adjacent to the upper side of the foundation concrete; installing a formwork on the inner concrete wall so as to pour a unit outer concrete wall following the inner concrete wall; constructing a unit outer concrete wall by pouring and curing concrete in the formwork; The steps of removing the braces installed in the unit inner wall construction step located directly above the unit outer concrete wall and repeating the unit outer wall construction step of constructing the unit outer concrete wall over the unit outer concrete wall to construct the outer concrete wall; A method of constructing an underground vertical structure comprising:

상기 단위내측벽시공단계에서, 상기 콘크리트패널을 차수벽에 지지한 다음 상기 콘크리트패널을 지지수단으로 차수벽에 지지하는 것을 더 포함하며, 상기 지지수단은 콘크리트패널에 구비되는 다수 개의 관통구멍들과, 상기 콘크리트패널의 관통구멍에 관통 삽입되어 상기 차수벽에 박는 앵커볼트 또는 고정핀을 포함하는 것이 바람직하다.In the unit inner wall construction step, the method further comprises supporting the concrete panel on the order wall and then supporting the concrete panel on the order wall as a support means, wherein the support means includes a plurality of through holes provided in the concrete panel; It is preferable to include an anchor bolt or a fixing pin which is inserted through the through hole of the concrete panel and driven into the order wall.

상기 거푸집은 내측콘크리트벽체와 간격을 두고 상기 기초콘크리트의 상면에 수평방향으로 배열된 거푸집용 콘크리트패널들과, 상기 거푸집용 콘크리트패널들을 각각 내측콘크리트벽체에 연결하는 연결유닛을 포함하는 것이 바람직하다.The formwork preferably includes concrete panels for formwork arranged in a horizontal direction on the upper surface of the foundation concrete at a distance from the inner concrete wall, and a connection unit for connecting the concrete panels for the formwork to the inner concrete wall, respectively.

상기 단위내측벽체시공단계에서, 상기 주열식 말뚝들을 따라 폐곡선을 이루도록 배열된 콘크리트패널들에 띠장을 설치하고 상기 띠장에 버팀보들을 설치하는 것이 바람직하다.In the unit inner wall construction step, it is preferable to install a wale on the concrete panels arranged to form a closed curve along the column-type piles, and install beams on the wale.

본 발명의 지중수직구조물은 지반에 다각형 또는 폐곡선 형태로 차수벽이 설치되어 토벽을 지지하고 차수벽에 접촉되도록 차수벽에 수평방향과 수직 방향으로 다수 개의 콘크리트패널들이 배열되어 내측콘크리트벽체를 구성하고 내측콘크리트벽체의 내측 지하바닥에 바닥체가 구비되고 내측콘크리트벽체에 설정된 두께로 외측콘크리트벽체가 구비되므로 토벽의 압력을 견고하게 지지하게 될 뿐만 아니라 수직 방향으로 공간을 형성하게 된다.In the underground vertical structure of the present invention, an order wall is installed in the ground in the form of a polygon or a closed curve to support the earth wall, and a plurality of concrete panels are arranged on the order wall in the horizontal and vertical directions so as to be in contact with the order wall to constitute the inner concrete wall and the inner concrete wall Since the floor is provided on the inner basement floor of the inner concrete wall and the outer concrete wall is provided with a thickness set on the inner concrete wall, the pressure of the earth wall is firmly supported and a space is formed in the vertical direction.

또한, 본 발명의 지중수직구조물 시공방법은 다각형 또는 폐곡선 형태를 이루도록 주열식 말뚝들을 설치하고 단위내측벽체시공단계를 반복하면서 설정된 깊이를 갖는 내측콘크리트벽체를 시공하고 내측콘크리트벽체의 내측 지하 바닥에 버림콘크리트를 타설하고 이어 방수층을 시공하고 이어 기초콘크리트를 타설한 후 내측콘크리트벽체에 단위외측벽체시공단계를 반복하면서 외측콘크리트벽체를 시공하게 되므로 토벽을 지지하면서 수직방향 내부 공간을 갖는 지중수직구조물을 간단하게 시공하게 되어 빠르고 견고하게 지중수직구조물을 시공하게 된다.In addition, the underground vertical structure construction method of the present invention installs column-type piles to form a polygonal or closed curve shape, constructs an inner concrete wall having a set depth while repeating the unit inner wall construction step, and discards it on the inner basement floor of the inner concrete wall After pouring concrete, then constructing the waterproofing layer, and then pouring the foundation concrete, the outer concrete wall is constructed while repeating the unit outer wall construction step on the inner concrete wall. The construction of underground vertical structures is quick and robust.

또한, 본 발명의 지중수직구조물은 내측콘크리트벽체를 지지하기 위한 별도의 어스앵커 등의 지보재 없이 내측콘크리트벽체를 지지하게 되므로 지중설치공간을 작게 차지하게 되어 건물들이 인접하게 되어도 구조물 시공이 자유롭게 된다.In addition, since the underground vertical structure of the present invention supports the inner concrete wall without a support material such as a separate earth anchor for supporting the inner concrete wall, it occupies a small underground installation space, and the construction of the structure becomes free even if the buildings are adjacent to it.

또한, 본 발명은 지중수직구조물 설치가 완료된 후 구조물 배면 되메우기를 하지 않아도 되므로 그만 큼 지하 굴착토량이 적어 경제성도 우수하게 되고, 강재를 이용한 흙막이 벽체에 띠장을 설치하지 않게 되어 강재를 손쉽에 인발하여 회수할 수 있게 된다.In addition, since the present invention does not require backfilling of the backside of the structure after installation of the underground vertical structure is completed, the amount of excavated soil is small, and the economical efficiency is excellent. be able to recover

도 1은 본 발명에 따른 지중수직구조물의 일실시예를 도시한 정단면도,
도 2는 본 발명에 따른 지중수직구조물의 일실시예를 도시한 평면도,
도 3은 본 발명에 따른 지중수직구조물의 다른 실시예를 도시한 평면도,
도 4는 본 발명에 따른 지중수직구조물의 일실시예를 구성하는 지지수단의 일예를 도시한 단면도,
도 5는 본 발명에 따른 지중수직구조물의 일실시예를 구성하는 지지수단의 다른 일예를 도시한 단면도,
도 6은 본 발명에 따른 지중수직구조물 시공방법의 일실시예를 도시한 순서도,
도 7a에서 7g는 본 발명에 따른 지중수직구조물 시공방법의 일실시예를 시공 단계별로 각각 도시한 측면도.
1 is a front sectional view showing an embodiment of an underground vertical structure according to the present invention;
2 is a plan view showing an embodiment of an underground vertical structure according to the present invention;
3 is a plan view showing another embodiment of the underground vertical structure according to the present invention;
Figure 4 is a cross-sectional view showing an example of the support means constituting an embodiment of the underground vertical structure according to the present invention,
5 is a cross-sectional view showing another example of the supporting means constituting an embodiment of the underground vertical structure according to the present invention;
Figure 6 is a flow chart showing an embodiment of the underground vertical structure construction method according to the present invention;
7a to 7g are side views each showing an embodiment of the underground vertical structure construction method according to the present invention in each construction stage.

이하, 본 발명에 따른 지중수직구조물 및 그 시공방법의 실시예를 첨부도면을 참조하여 설명한다.Hereinafter, an embodiment of the underground vertical structure and its construction method according to the present invention will be described with reference to the accompanying drawings.

도 1은 본 발명에 따른 지중수직구조물의 일실시예를 도시한 정단면도이다. 도 2는 본 발명에 따른 지중수직구조물의 일실시예를 도시한 평면도이다.1 is a front cross-sectional view showing an embodiment of an underground vertical structure according to the present invention. Figure 2 is a plan view showing an embodiment of the underground vertical structure according to the present invention.

도 1, 2에 도시한 바와 같이, 본 발명에 따른 지중수직구조물의 일실시예는, 차수벽(10), 내측콘크리트벽체(20), 바닥체(30), 외측콘크리트벽체(40), 방수층(50)을 포함한다.As shown in Figures 1 and 2, one embodiment of the underground vertical structure according to the present invention, the order wall 10, the inner concrete wall 20, the floor body 30, the outer concrete wall 40, the waterproofing layer ( 50).

차수벽(10)은 다각형이나 폐곡선 형태로 지반에 설치되어 토벽을 지지한다. 차수벽(10)은 다각형 또는 폐곡선을 따라 지반에 수직 방향으로 박힌 주열식 말뚝(11)들을 포함한다. 일예로, 주열식 말뚝(11)들은 위에서 볼 때 사각형 형태로 배열되어 차수벽(10)을 이루게 된다. 다른 일예로, 도 3에 도시한 바와 같이, 주열식 말뚝(11)들은 위에서 볼 때 원형 형태로 배열되어 차수벽(10)을 이루게 된다. 또다른 일예로, 주열식 말뚝(11)은 육각형 등 다각형 형태로 배열되어 차수벽(10)을 이루거나, 타원 형태로 배열되어 차수벽(10)을 이루게 된다. 이하에서, 주열식 말뚝(11)들이 위에서 볼 때 사각형 형태로 배열된 차수벽(10)에 대하여 설명한다.The order wall 10 is installed in the ground in the form of a polygonal or closed curve to support the earth wall. The order wall 10 includes columnar piles 11 embedded in a vertical direction in the ground along a polygonal or closed curve. As an example, the column-type piles 11 are arranged in a rectangular shape when viewed from above to form the order wall 10 . As another example, as shown in FIG. 3 , the columnar piles 11 are arranged in a circular shape when viewed from above to form the order wall 10 . As another example, the column-type piles 11 are arranged in a polygonal shape such as a hexagon to form the order wall 10 , or are arranged in an oval shape to form the order wall 10 . Hereinafter, the columnar piles 11 will be described with respect to the order wall 10 arranged in a rectangular shape when viewed from above.

내측콘크리트벽체(20)는 다각형 또는 폐곡선 형태의 차수벽(10)에 접촉되도록 차수벽(10)에 수평방향과 수직방향으로 배열되는 다수 개의 콘크리트패널(21)들을 포함한다. 즉, 내측콘크리트벽체(20)는 수직 방향으로 길이를 가지며, 횡단면 형상은 차수벽과 같이 다각형 또는 폐곡선 형태로 형성되며 균일한 두께를 갖는다. 즉, 차수벽(10)이, 위에서 볼 때, 사각형인 경우 내측콘크리트벽체(20) 또한 위에서 볼 때 사각형이 된다. 내측콘크리트벽체(20)가 위에서 볼 때 사각형인 경우 내측콘크리트벽체(20)를 구성하는 콘크리트패널(21)들은 각각 균일한 두께를 가지며 평면을 이루는 사각패널이나 육각패널로 형성된다. 내측콘크리트벽체(20)가 위에서 볼 때 원형인 경우 내측콘크리트벽체(20)를 구성하는 콘크리트패널(21)들은 각각 두께가 균일하며 곡률반경이 서로 같은 곡면패널로 형성된다. 내측콘크리트벽체(20)가 위에서 볼 때 타원형인 경우 내측콘크리트벽체(20)를 구성하는 콘크리트패널(21)은 곡면패널로 형성된다.The inner concrete wall 20 includes a plurality of concrete panels 21 arranged in horizontal and vertical directions on the order wall 10 so as to be in contact with the order wall 10 having a polygonal or closed curve shape. That is, the inner concrete wall 20 has a length in the vertical direction, and the cross-sectional shape is formed in a polygonal or closed curved shape like an order wall and has a uniform thickness. That is, when the order wall 10 is a rectangle when viewed from above, the inner concrete wall 20 also becomes a rectangle when viewed from above. When the inner concrete wall 20 has a rectangular shape when viewed from above, the concrete panels 21 constituting the inner concrete wall 20 have a uniform thickness, respectively, and are formed of a square panel or hexagonal panel forming a plane. When the inner concrete wall 20 is circular when viewed from above, the concrete panels 21 constituting the inner concrete wall 20 are each formed as curved panels having a uniform thickness and the same radius of curvature. When the inner concrete wall 20 is oval when viewed from above, the concrete panel 21 constituting the inner concrete wall 20 is formed as a curved panel.

콘크리트패널(21)은 지지수단(60)에 의해 차수벽(10)에 지지됨이 바람직하다. 지지수단(60)의 일예로, 도 4에 도시한 바와 같이, 지지수단(60)은 콘크리트패널(21)에 다수 개의 관통구멍(1)들과, 그 콘크리트패널(21)의 관통구멍(1)에 관통 삽입되어 차수벽(10)에 박히는 고정핀(2)(또는 앵커볼트)를 포함한다. 지지수단(60)의 다른 일예로, 도 5에 도시한 바와 같이, 지지수단(60)은 차수벽(10)의 주열식 말뚝(11)들에 결합된 걸림브라켓(3)들과, 콘크리트패널(21)의 배면에 구비되어 걸림브라켓(3)들을 걸리는 걸림홈(4)을 포함한다.The concrete panel 21 is preferably supported by the support means 60 on the order wall 10 . As an example of the support means 60 , as shown in FIG. 4 , the support means 60 has a plurality of through holes 1 in the concrete panel 21 , and the through holes 1 of the concrete panel 21 . ) is inserted through and includes a fixing pin 2 (or anchor bolt) that is inserted into the order wall 10 . As another example of the support means 60, as shown in FIG. 5, the support means 60 includes the locking brackets 3 coupled to the column-type piles 11 of the order wall 10, and a concrete panel ( It is provided on the rear surface of the 21) and includes a locking groove (4) for hooking the locking brackets (3).

바닥체(30)는 내측콘크리트벽체(20)의 내측 지하바닥에 시공된다. 바닥체(30)의 상면은 내측콘크리트벽체(20)의 하단 위에 위치하는 것이 바람직하다. 바닥체(30)의 일예로, 바닥체(30)는 내측콘크리트벽체(20)의 내부 지하 바닥에 타설된 버림콘크리트층(31)과, 그 버림콘크리트층(31) 상면에 구비되는 방수층(50)과, 그 방수층(50) 상면에 타설된 기초콘크리트층(32)을 포함하는 것이 바람직하다.The floor body 30 is constructed on the inner basement floor of the inner concrete wall 20 . The upper surface of the floor body 30 is preferably located above the lower end of the inner concrete wall (20). As an example of the floor body 30, the floor body 30 is a cast concrete layer 31 poured on the inner basement of the inner concrete wall 20, and a waterproof layer 50 provided on the upper surface of the cast concrete layer 31. ) and the waterproof layer 50, it is preferable to include a concrete base layer 32 poured on the upper surface.

외측콘크리트벽체(40)는 내측콘크리트벽체(20)에 설정된 두께로 형성된다. 외측콘크리트벽체(40)는 내측콘크리트벽체(20)의 횡단면 형상과 같은 횡단면 형상을 갖는다. 외측콘크리트벽체(40)의 하단은 바닥체(30)로부터 형성되고 상단은 내측콘크리트벽체(20)의 상단 높이와 상응하는 높이로 형성된다.The outer concrete wall 40 is formed to a thickness set in the inner concrete wall 20 . The outer concrete wall 40 has the same cross-sectional shape as the cross-sectional shape of the inner concrete wall 20 . The lower end of the outer concrete wall 40 is formed from the floor 30 and the upper end is formed to a height corresponding to the upper end of the inner concrete wall 20 .

방수층(50)은 내측콘크리트벽체(20)와 외측콘크리트벽체(40) 사이에 구비된다. 방수층(50)은 방수시트를 포함하는 것이 바람직하다. 방수층(50)은 바닥체(30)에 구비된 방수층(50)과 일체로 형성됨이 바람직하다.The waterproof layer 50 is provided between the inner concrete wall 20 and the outer concrete wall 40 . The waterproof layer 50 preferably includes a waterproof sheet. The waterproof layer 50 is preferably formed integrally with the waterproof layer 50 provided on the floor 30 .

도 6은 본 발명에 따른 지중수직구조물 시공방법의 일실시예를 도시한 순서도이다.6 is a flowchart showing an embodiment of the underground vertical structure construction method according to the present invention.

도 6에 도시한 바와 같이, 본 발명에 따른 지중수직구조물 시공방법의 일실시예는, 먼저, 지중수직구조물을 시공할 지반에 다각형 또는 폐곡선 형태를 이루도록 주열식 말뚝(11)들을 설치하여 차수벽을 시공하는 단계(S1)가 진행된다(도 7a 참조). 주열식 말뚝(11)들을 포함하는 차수벽(10)은 위에서 볼 때 다각형 또는 폐곡선 형태로, 사각형, 육각형, 원형, 타원형 중 한 개의 형상로 설치된다. 이하에서는 주열식 말뚝(11)들이 사각형으로 설치된 경우에 대하여 설명한다. 주열식 말뚝(11)들을 지반에 설치하는 기술은 일반적 기술이므로 구체적인 설명은 생략한다.As shown in Figure 6, an embodiment of the underground vertical structure construction method according to the present invention, first, to form a polygonal or closed curve shape in the ground to construct the underground vertical structure by installing the column-type piles 11 to install the order wall The construction step (S1) proceeds (see Fig. 7a). The order wall 10 including the column-type piles 11 is installed in a polygonal or closed curve shape when viewed from above, in one shape of a rectangle, a hexagon, a circle, and an oval. Hereinafter, a case in which the column-type piles 11 are installed in a rectangular shape will be described. Since the technology for installing the column-type piles 11 on the ground is a general technology, a detailed description thereof will be omitted.

주열식 말뚝(11)들을 설치한 다음 주열식 말뚝(11)들로 둘러 싸여진 지반 굴착영역을 단위 깊이로 굴착하고, 그 단위 깊이로 굴착되어 노출된 주열식 말뚝(11)들에 접촉되도록 주열식 말뚝(11)들을 따라 콘크리트패널(21)들을 수평 방향으로 다각형이나 폐곡선 형태를 이루도록 배열시키고, 그 수평으로 배열된 콘크리트패널(21)들을 지지하도록 버팀보(80)들을 설치하여 단위내측콘크리트벽체(W1)를 시공하는 단위내측벽체시공단계(S2)가 진행된다(도 7b 참조). 차수벽(10)이, 위에서 볼 때(횡단면 형상) 사각형인 경우 단위내측콘크리트벽체(W1) 또한 위에서 볼 때 사각형이 된다. 사각형인 단위내측콘크리트벽체(W1)를 구성하는 콘크리트패널(21)들은 각각 균일한 두께를 가지며 평면을 이루는 사각패널이며, 또한 육각패널, 또는 삼각패널이 될 수도 있다. 단위내측콘크리트벽체(W1)가 횡단면 형상이 원형인 경우 단위내측콘크리트벽체(W1)를 구성하는 콘크리트패널(21)들은 각각 두께가 균일하며 곡률반경이 서로 같은 곡면패널로 형성된다. 또한, 단위내측콘크리트벽체(W1)가 횡단면 형상이 타원형인 경우 단위내측콘크리트벽체(W1)를 구성하는 콘크리트패널(21)은 곡면패널로 형성된다. 콘크리트패널(21)들을 수평 방향으로 배열하되, 각각 수직 방향으로 세워 차수벽(10)에 지지하며, 수평 방향으로 일렬로 배열된 콘크리트패널(21)들은 버팀보(80)들로 지지한다. 콘크리트패널(21)은 지지수단(70)에 의해 차수벽(10)에 지지됨이 바람직하다. 지지수단(70)의 일예로, 도 4에 도시한 바와 같이, 지지수단(70)은 콘크리트패널(21)에 다수 개의 관통구멍(1)들과, 그 콘크리트패널(21)의 관통구멍(1)에 관통 삽입되어 차수벽(10)에 박히는 고정핀(또는 앵커볼트)(2)을 포함한다. 즉, 콘크리트패널(21)을 차수벽(10)에 지지한 상태에서 고정핀(2)을 콘크리트패널(21)의 관통구멍(1)을 통해 차수벽(10)에 박아 콘크리트패널(21)을 지지한다. 지지수단(70)의 다른 일예로, 도 5에 도시한 바와 같이, 지지수단(70)은 차수벽(10)의 주열식 말뚝(11)들에 결합된 걸림브라켓(3)들과, 콘크리트패널(21)의 배면에 구비되어 걸림브라켓(3)들이 걸리는 걸림홈(4)을 포함한다. 즉, 걸림브라켓(3)들을 차수벽(10)의 주열식 말뚝(11)에 결합시키고 콘크리트패널(21)을 차수벽(10)에 지지시 콘크리트패널(21)의 후면에 구비된 걸림홈(4)을 걸림브라켓(3)들에 걸어 지지하게 된다. 단위내측벽체시공단계(S2)에서, 주열식 말뚝(11)들을 따라 배열된 콘크리트패널(21)들에 띠장을 설치하고 그 띠장에 버팀보(80)들을 설치하여 콘크리트패널(21)들을 지지하는 것이 바람직하다.After installing the column-type piles 11, the ground excavation area surrounded by the column-type piles 11 is excavated to a unit depth, and the column-type pile is excavated to the unit depth to contact the exposed column-type piles 11. The concrete panels 21 are arranged along the piles 11 to form a polygonal or closed curve in the horizontal direction, and braces 80 are installed to support the horizontally arranged concrete panels 21, so that the unit inner concrete wall W1 ) of the unit inner wall construction step (S2) is in progress (see Fig. 7b). When the order wall 10 is rectangular when viewed from above (cross-sectional shape), the unit inner concrete wall W1 is also rectangular when viewed from above. Each of the concrete panels 21 constituting the rectangular unit inner concrete wall W1 has a uniform thickness and is a flat rectangular panel, and may also be a hexagonal panel or a triangular panel. When the unit inner concrete wall W1 has a circular cross-sectional shape, the concrete panels 21 constituting the unit inner concrete wall W1 are each formed as a curved panel having a uniform thickness and the same radius of curvature. In addition, when the unit inner concrete wall (W1) has an elliptical cross-sectional shape, the concrete panel 21 constituting the unit inner concrete wall (W1) is formed as a curved panel. The concrete panels 21 are arranged in a horizontal direction, each standing in a vertical direction and supported on the order wall 10 , and the concrete panels 21 arranged in a row in the horizontal direction are supported by braces 80 . The concrete panel 21 is preferably supported by the support means 70 on the order wall 10 . As an example of the support means 70 , as shown in FIG. 4 , the support means 70 includes a plurality of through holes 1 in the concrete panel 21 , and the through holes 1 of the concrete panel 21 . ) and a fixing pin (or anchor bolt) (2) inserted through and embedded in the order wall (10). That is, in a state in which the concrete panel 21 is supported on the order wall 10, the fixing pin 2 is driven into the order wall 10 through the through hole 1 of the concrete panel 21 to support the concrete panel 21. . As another example of the support means 70, as shown in FIG. 5, the support means 70 includes the locking brackets 3 coupled to the column-type piles 11 of the order wall 10, and a concrete panel ( It is provided on the rear surface of the 21) and includes a locking groove (4) to which the locking brackets (3) are caught. That is, when the locking brackets 3 are coupled to the column-type pile 11 of the order wall 10 and the concrete panel 21 is supported on the order wall 10, the locking groove 4 provided on the rear surface of the concrete panel 21 is supported by hanging on the locking brackets (3). In the unit inner wall construction step (S2), installing a wale on the concrete panels 21 arranged along the column-type piles 11 and installing braces 80 on the wale to support the concrete panels 21 desirable.

단위내측콘크리트벽체(W1)를 시공한 다음 단위내측벽체시공단계(S2)를 설정된 깊이까지 반복하여 횡단면이 다각형 또는 폐곡선 형태의 내측콘크리트벽체(20)를 시공하는 단계(S3)가 진행된다(도 7c 참조). 이와 같이 시공된 내측콘크리트벽체(20)는 횡단면이 사각형인 경우 사각형인 수직 방향의 내부 공간을 갖는다.After constructing the unit inner concrete wall (W1), repeat the unit inner wall construction step (S2) to a set depth to construct the inner concrete wall 20 having a polygonal or closed curved cross-section (S3) proceeds (Fig. see 7c). The inner concrete wall 20 constructed in this way has a rectangular vertical interior space when the cross section is rectangular.

내측콘크리트벽체(20)를 시공한 다음 내측콘크리트벽체(20)의 내부 지하 바닥에 버림콘크리트(31)를 타설하는 단계(S4)가 진행된다(도 7d 참조).After constructing the inner concrete wall 20, a step (S4) of pouring the discarded concrete 31 on the inner basement floor of the inner concrete wall 20 is performed (see FIG. 7d).

버림콘크리트(31)를 타설한 다음 그 버림콘크리트(31)가 양생된 후 내측콘크리트벽체(20)와 버림콘크리트(31)에 방수층(50)을 시공하는 단계(S5)가 진행된다(도 7d 참조).After pouring the discarded concrete 31, and after the discarded concrete 31 is cured, the step (S5) of constructing the waterproofing layer 50 on the inner concrete wall 20 and the discarded concrete 31 is performed (see Fig. 7d). ).

버림콘크리트(31)에 방수층(50)을 시공한 다음 버림콘크리트(31)의 방수층(50)에 기초콘크리트(32)를 타설하는 단계(S6)가 진행된다. 기초콘크리트(32)의 상면은 내측콘크리트벽체(20)의 하단 위에 위치하도록 타설하는 것이 바람직하다(도 7d 참조).After constructing the waterproofing layer 50 on the abandoned concrete 31, a step (S6) of pouring the foundation concrete 32 on the waterproofing layer 50 of the abandoned concrete 31 is performed. The upper surface of the foundation concrete 32 is preferably poured so as to be positioned above the lower end of the inner concrete wall 20 (see FIG. 7d).

기초콘크리트(32)를 타설한 다음 기초콘크리트(32)의 상측으로 인접한 단위내측벽체시공단계(S2)로 시공된 버팀보(80)들을 철거하는 단계(S7)가 진행된다.After pouring the foundation concrete 32, the step (S7) of dismantling the braces 80 constructed in the unit inner wall construction step (S2) adjacent to the upper side of the foundation concrete 32 is performed.

기초콘크리트(32)의 상측으로 인접한 버팀보(80)들을 철거한 다음 내측콘크리트벽체(20)에 이어 단위외측콘크리트벽체(40)를 타설하도록 내측콘크리트벽체(20)에 거푸집을 설치하는 단계(S8)가 진행된다. 거푸집은 기초콘크리트(32)에서 일정 높이를 가지며 내측콘크리트벽체(20)와 설정된 간격을 두고 설치된다. 거푸집의 일예로, 거푸집은 내측콘크리트벽체(20)와 간격을 두고 기초콘크리트(32)의 상면에 수평방향으로 배열된 거푸집용 콘크리트패널(21)들과, 그 거푸집용 콘크리트패널(21)들을 각각 내측콘크리트벽체(20)에 연결하는 연결유닛을 포함하는 것이 바람직하다. 연결유닛(22)의 일예로, 연결유닛(22)은 내측콘크리트벽체(20)에 매립되되, 수나사부가 외부로 노출된 내측볼트(6)와, 그 내측볼트(6)의 수나사부에 연결너트(7)에 의해 연결되는 거푸집용 콘크리트패널(21)에 관통 삽입되는 양쪽 볼트(8)와, 거푸집용 콘크리트패널(21)의 양쪽에 각각 위치하여 양쪽 볼트(8)의 한쪽 수나사산부에 체결되는 두 개의 고정너트(9)들을 포함한다. 이와 같이 거푸집을 콘크리트패널형 거푸집으로 설치할 경우 거푸집용 비계 등을 설치할 필요가 없어 시공이 매우 간단하게 된다.After removing the supporting beams 80 adjacent to the upper side of the foundation concrete 32, and then installing the formwork on the inner concrete wall 20 to pour the unit outer concrete wall 40 following the inner concrete wall 20 (S8) is going on The formwork has a predetermined height in the concrete foundation 32 and is installed at a set interval with the inner concrete wall 20 . As an example of the formwork, the formwork includes concrete panels 21 for formwork arranged in the horizontal direction on the upper surface of the foundation concrete 32 at a distance from the inner concrete wall 20, and the concrete panels 21 for the formwork, respectively. It is preferable to include a connection unit for connecting to the inner concrete wall (20). As an example of the connection unit 22 , the connection unit 22 is embedded in the inner concrete wall 20 , the inner bolt 6 with the male screw portion exposed to the outside, and the connection nut to the male screw portion of the inner bolt 6 . Both bolts 8 that are inserted through the concrete panel 21 for formwork connected by (7), respectively, are located on both sides of the concrete panel 21 for formwork and are fastened to one male thread part of both bolts 8 It includes two fixing nuts (9). In this way, when the formwork is installed as a concrete panel-type formwork, there is no need to install scaffolding for the formwork, so the construction is very simple.

거푸집을 설치한 다음 거푸집에 콘크리트를 타설하고 양생시켜 단위외측콘크리트벽체(W2)를 시공하는 단계(S9)가 진행된다(도 7e, 도 7f 참조).After the formwork is installed, concrete is poured into the formwork and cured to construct the unit outer concrete wall W2 (S9) (see FIGS. 7e and 7f).

단위외측콘크리트벽체(W2)를 시공한 다음 단위외측콘크리트벽체(W2) 바로 위에 위치하는 단위내측벽체시공단계(S2)로 설치된 버팀보(80)들을 철거하고 단위외측콘크리트벽체(W2) 위로 거푸집을 설치하고 콘크리트를 타설하여 단위외측콘크리트벽체(W2)를 시공하는 단위외측벽체시공단계를 반복하여 외측콘크리트벽체(40)를 시공하는 단계(S10)가 진행된다(도 7g 참조). 단위외측벽체시공단계에서 설치되는 거푸집은 기초콘크리트(32)에 이어 시공된 단위외측콘크리트벽체(W2)에 사용되는 거푸집과 같은 것이 바람직하다. 외측콘크리트벽체(40)의 상단은 내측콘크리트벽체(20)의 상단과 동일한 높이로 시공되며, 외측콘크리트벽체(40)의 단면 형상은 내측콘크리트벽체(20)의 단면 형상과 같다.After constructing the unit outer concrete wall (W2), remove the braces (80) installed in the unit inner wall construction step (S2) located just above the unit outer concrete wall (W2), and install the formwork over the unit outer concrete wall (W2) and repeating the unit outer wall construction step of constructing the unit outer concrete wall W2 by pouring concrete to construct the outer concrete wall 40 (S10) proceeds (see Fig. 7g). The formwork installed in the unit outer wall construction step is preferably the same as the formwork used for the unit outer concrete wall W2 constructed following the foundation concrete 32 . The upper end of the outer concrete wall 40 is constructed at the same height as the upper end of the inner concrete wall 20 , and the cross-sectional shape of the outer concrete wall 40 is the same as the cross-sectional shape of the inner concrete wall 20 .

이하, 본 발명에 따른 지중수직구조물 및 그 시공방법의 작용과 효과를 설명한다.Hereinafter, the operation and effect of the underground vertical structure and its construction method according to the present invention will be described.

본 발명의 지중수직구조물은 지반에 다각형 또는 폐곡선 형태로 차수벽(10)이 설치되어 토벽을 지지하고 차수벽(10)에 접촉되도록 차수벽(10)에 수평방향과 수직 방향으로 다수 개의 콘크리트패널(21)들이 배열되어 내측콘크리트벽체(20)를 구성하고 내측콘크리트벽체(20)의 내측 지하 바닥에 바닥체(30)가 구비되고 내측콘크리트벽체(20)에 설정된 두께로 외측콘크리트벽체(40)가 구비되므로 토벽의 압력을 견고하게 지지하며 수직 방향으로 공간을 형성하게 된다.The underground vertical structure of the present invention has a plurality of concrete panels 21 in the horizontal and vertical directions on the order wall 10 so that the order wall 10 is installed in the ground in the form of a polygon or a closed curve to support the earth wall and contact the order wall 10. These are arranged to constitute the inner concrete wall 20, the floor 30 is provided on the inner basement floor of the inner concrete wall 20, and the outer concrete wall 40 is provided with a thickness set in the inner concrete wall 20. It firmly supports the pressure of the soil wall and forms a space in the vertical direction.

또한, 본 발명의 지중수직구조물 시공방법은 다각형 또는 폐곡선 형태를 이루도록 주열식 말뚝(11)들을 설치하고, 단위내측벽체시공단계를 반복하면서 설정된 깊이를 갖는 내측콘크리트벽체(20)를 시공하고 내측콘크리트벽체(20)의 내측 지하 바닥에 버림콘크리트(31)를 타설하고 이어 방수층(50)을 시공하고 이어 기초콘크리트(32)를 타설한 후 내측콘크리트벽체(20)에 단위외측벽체시공단계를 반복하면서 외측콘크리트벽체(40)를 시공하게 되므로 토벽을 지지하면서 수직방향 내부 공간을 갖는 지중수직구조물을 간단하게 시공하게 되어 빠르고 견고하게 지중수직구조물을 시공하게 된다.In addition, the underground vertical structure construction method of the present invention installs the column-type piles 11 to form a polygonal or closed curve shape, and repeats the unit inner wall construction step while constructing the inner concrete wall 20 having a set depth and constructing the inner concrete After pouring discarded concrete 31 on the inner basement floor of the wall 20, then constructing the waterproofing layer 50, then pouring the foundation concrete 32, and repeating the unit outer wall construction step on the inner concrete wall 20 Since the outer concrete wall 40 is constructed, the underground vertical structure having a vertical interior space while supporting the earth wall is easily constructed, and the underground vertical structure is constructed quickly and firmly.

또한, 본 발명의 지중수직구조물은 내측콘크리트벽체(20)를 지지하기 위한 별도의 어스앵커 등의 지보재 없이 내측콘크리트벽체(20)를 지지하게 되므로 지중에 지중설치공간을 적게 차지하게 되어 건물들이 인접하게 되어도 설치가 자유롭게 된다.In addition, since the underground vertical structure of the present invention supports the inner concrete wall 20 without a support material such as a separate earth anchor for supporting the inner concrete wall 20, it occupies less underground installation space in the ground, so that the buildings are adjacent to each other. Even if you do, installation is free.

또한, 본 발명은 지중수직구조물 설치가 완료된 후 구조물 배면 되메우기를 하지 않아도 되므로 그만 큼 지하 굴착토량이 적어 경제성도 우수하게 되고, 강재를 이용한 흙막이 벽체에 띠장을 설치하지 않게 되어 강재를 손쉽에 인발하여 회수할 수 있게 된다.In addition, since the present invention does not require backfilling of the backside of the structure after installation of the underground vertical structure is completed, the amount of excavated soil is small, and the economical efficiency is excellent. be able to recover

10; 차수벽 20; 내측콘크리트벽체
30; 바닥체 40; 외측콘크리트벽체
50; 방수층
10; barrier 20; inner concrete wall
30; bottom 40; exterior concrete wall
50; waterproof layer

Claims (7)

삭제delete 삭제delete 삭제delete 지중구조물을 시공할 지반에 다각형 또는 폐곡선 형태를 이루도록 주열식 말뚝들을 설치하여 차수벽을 시공하는 단계;
상기 주열식 말뚝들로 둘러 싸여진 지반 굴착영역을 단위 깊이로 굴착하고 상기 단위 깊이로 굴착되어 노출된 주열식 말뚝들에 접촉되도록 주열식 말뚝들을 따라 콘크리트패널들을 수평 방향으로 다각형 또는 폐곡선을 이루도록 배열시키고 상기 배열된 콘크리트패널들을 지지하도록 버팀보들을 설치하여 단위내측콘크리트벽체를 시공하는 단위내측벽체시공단계;
상기 단위내측벽체시공단계를 설정된 깊이까지 반복하여 폐곡선 형태의 내측콘크리트벽체를 시공하는 단계;
상기 내측콘크리트벽체의 내부 지하 바닥에 버림콘크리트를 타설하는 단계;
상기 내측콘크리트벽체와 버림콘크리트에 방수층을 시공하는 단계;
상기 버림콘크리트의 방수층에 기초콘크리트를 타설하는 단계;
상기 기초콘크리트의 상측으로 인접한 단위내측벽체시공단계로 설치된 버팀보들을 철거하는 단계;
상기 내측콘크리트벽체에 이어 단위외측콘크리트벽체를 타설하도록 상기 내측콘크리트벽체에 거푸집을 설치하는 단계;
상기 거푸집에 콘크리트를 타설하고 양생시켜 단위외측콘크리트벽체를 시공하는 단계;
상기 단위외측콘크리트벽체 바로 위에 위치하는 단위내측벽체시공단계로 설치된 버팀보들을 철거하고 상기 단위외측콘크리트벽체 위로 단위외측콘크리트벽체를 시공하는 단위외측벽체시공단계를 반복하여 외측콘크리트벽체를 시공하는 단계;를 포함하며,
상기 거푸집은 내측콘크리트벽체와 간격을 두고 상기 기초콘크리트의 상면에 수평방향으로 배열된 거푸집용 콘크리트패널들과, 상기 거푸집용 콘크리트패널들을 각각 내측콘크리트벽체에 연결하는 연결유닛을 포함하며,
상기 단위내측벽시공단계에서, 상기 콘크리트패널은 균일한 두께를 가지며 평면을 이루며 다수 개의 관통구멍들이 구비되고, 상기 콘크리트패널을 차수벽에 지지한 다음 상기 콘크리트패널의 관통구멍들에 각각 앵커볼트 또는 고정핀을 관통 삽입하여 상기 차수벽에 박아 콘크리트패널을 지지하는 것을 특징으로 하는 지중수직구조물 시공방법.
constructing an order wall by installing column-type piles to form a polygonal or closed curve shape in the ground to construct the underground structure;
The ground excavation area surrounded by the column-type piles is excavated to a unit depth, and the concrete panels are horizontally polygonal along the column-type piles so that they are in contact with the exposed column-type piles excavated to the unit depth. or a unit inner wall construction step of constructing a unit inner concrete wall by arranging to form a closed curve and installing braces to support the arranged concrete panels;
repeating the unit inner wall construction step to a set depth to construct an inner concrete wall in a closed curve shape;
pouring discarded concrete on the inner basement floor of the inner concrete wall;
constructing a waterproofing layer on the inner concrete wall and the abandoned concrete;
pouring the foundation concrete on the waterproof layer of the discarded concrete;
dismantling the braces installed in the unit inner wall construction step adjacent to the upper side of the foundation concrete;
installing a formwork on the inner concrete wall so as to pour a unit outer concrete wall following the inner concrete wall;
constructing a unit outer concrete wall by pouring and curing concrete in the formwork;
The steps of removing the braces installed in the unit inner wall construction step located directly above the unit outer concrete wall and repeating the unit outer wall construction step of constructing the unit outer concrete wall over the unit outer concrete wall to construct the outer concrete wall; includes,
The formwork includes concrete panels for formwork arranged in a horizontal direction on the upper surface of the foundation concrete at a distance from the inner concrete wall, and a connecting unit for connecting the concrete panels for formwork to the inner concrete wall, respectively,
In the unit inner wall construction step, the concrete panel has a uniform thickness, forms a plane, is provided with a plurality of through-holes, supports the concrete panel on the order wall, and then anchors bolts or fixes to the through-holes of the concrete panel, respectively The underground vertical structure construction method, characterized in that by inserting a pin through and driving it into the order wall to support the concrete panel.
삭제delete 삭제delete 삭제delete
KR1020190044774A 2019-04-17 2019-04-17 Vertical underground structure and method for constructing the same KR102355446B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190044774A KR102355446B1 (en) 2019-04-17 2019-04-17 Vertical underground structure and method for constructing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190044774A KR102355446B1 (en) 2019-04-17 2019-04-17 Vertical underground structure and method for constructing the same

Publications (2)

Publication Number Publication Date
KR20200122029A KR20200122029A (en) 2020-10-27
KR102355446B1 true KR102355446B1 (en) 2022-01-26

Family

ID=73136078

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190044774A KR102355446B1 (en) 2019-04-17 2019-04-17 Vertical underground structure and method for constructing the same

Country Status (1)

Country Link
KR (1) KR102355446B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112609707A (en) * 2020-12-09 2021-04-06 中铁二十局集团第六工程有限公司 Foundation pit leakage water treatment method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011074727A (en) * 2009-10-01 2011-04-14 Ohbayashi Corp Earth retaining wall structure and construction method for earth retaining wall structure
KR101471058B1 (en) * 2014-09-15 2014-12-09 유한회사 강남이앤씨 Construction method of filling gap portion of earth retaining wall of temporary facility
KR101696916B1 (en) * 2016-02-29 2017-01-16 (주)한국리페어엔지니어링 Construction method of permanent wall with retaining wall combined PHC pile and steel pipe

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3312069B2 (en) * 1993-09-28 2002-08-05 帝都高速度交通営団 Waterproofing method for underground structures
KR101352429B1 (en) * 2011-12-29 2014-01-17 (주)엔코텍 Water-proofing type temporary soil sheathing construction method using crrugated steel plate segments

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011074727A (en) * 2009-10-01 2011-04-14 Ohbayashi Corp Earth retaining wall structure and construction method for earth retaining wall structure
KR101471058B1 (en) * 2014-09-15 2014-12-09 유한회사 강남이앤씨 Construction method of filling gap portion of earth retaining wall of temporary facility
KR101696916B1 (en) * 2016-02-29 2017-01-16 (주)한국리페어엔지니어링 Construction method of permanent wall with retaining wall combined PHC pile and steel pipe

Also Published As

Publication number Publication date
KR20200122029A (en) 2020-10-27

Similar Documents

Publication Publication Date Title
KR101341679B1 (en) Device for constructing an underground structure and method thereof
KR100967497B1 (en) Method for constructing an underground structure
KR20130006420A (en) Method of constructing underground structure to be newly built
KR101973565B1 (en) Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate
KR102234513B1 (en) Block type reinforcement retaining wall structure and constructing method for the same
JP4433066B2 (en) Wall structure with permanent anchor construction, wall construction method with permanent anchor construction,
KR100831332B1 (en) Underground retaining wall for public works and method for constructing the same
KR101169462B1 (en) Top-down construction method using post member
KR101262357B1 (en) Inclined Earth Retaining Structure Method
KR102355446B1 (en) Vertical underground structure and method for constructing the same
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR20170017199A (en) Retaining Wal1 Construction Method Using PHC Pile
KR20130021952A (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR20210119935A (en) Underground structure using strut and method construturing the same
KR102214872B1 (en) Structure using support beam and method for constructing the same
KR20120128345A (en) A Prevention Plate of the Ground Subsidence and Construction Method
KR100967496B1 (en) Device for constructing an underground structure
JP4997207B2 (en) Construction method for underground structures
KR200370135Y1 (en) Forms for edge girder construction
JP6083788B2 (en) Temporary support method for foundation
KR102312126B1 (en) Temporary retaining wall structure and method construturing the same
KR20210098162A (en) Under ground structure using column steel pipe wall and construction method thereof
JP5322214B2 (en) Foundation reinforcement method for existing wooden houses

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
AMND Amendment
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
X701 Decision to grant (after re-examination)