CN205024719U CN201520769847.6U CN201520769847U CN205024719U CN 205024719 U CN205024719 U CN 205024719U CN 201520769847 U CN201520769847 U CN 201520769847U CN 205024719 U CN205024719 U CN 205024719U
Authority
CN
China
Prior art keywords
pile foundation
diaphragm wall
integrated
vertical supporting
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201520769847.6U
Other languages
Chinese (zh)
Inventor
龙莉波
马跃强
刘龙
戚健文
李成
高伟
赵波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 2 Group Co Ltd
Original Assignee
Shanghai Construction No 2 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 2 Group Co Ltd filed Critical Shanghai Construction No 2 Group Co Ltd
Priority to CN201520769847.6U priority Critical patent/CN205024719U/en
Application granted granted Critical
Publication of CN205024719U publication Critical patent/CN205024719U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a pile foundation and integrated reverse construction vertical braces system of underground continuous wall, including reinforced concrete structure's underground continuous wall, and follow the reinforced concrete structure's of underground continuous wall's bottom downwardly extending setting pile foundation, underground continuous wall with as an organic wholeization of pile foundation reinforced concrete pours the completion. The utility model discloses can improve vertical bearing ability and holistic rigidity demand to can reduce the bulk settling of vertical braces system and inhomogeneous subsiding.

Description

The reverse construction vertical supporting system that pile foundation is integrated with diaphragm wall
Technical field
The utility model relates to technical field of building construction, is particularly a kind ofly applicable to the Pile Foundation reverse construction vertical supporting system integrated with diaphragm wall.
Background technology
Along with developing rapidly of China's building trade, highrise building, even super highrise building adopt the object of construction production of reverse construction to increase gradually.In reverse construction process, the load of underground beam slab and the vertical load of superstructure need vertical supporting System Take and are passed to basis, so the design and construction of vertical supporting system becomes the inverse important and difficult issues done in the design and construction stage of whole engineering in contrary working method engineering.The form of " one pile for one column " or " many, a post " that the general vertical supporting system of bearing structural beam slab load and construction load adopts structural column to combine with engineering pile usually.According to practical engineering experience, " one pile for one column " vertical supporting system that conventional angle splice joint lattice column and stand column pile form only can bear 2 ~ 3 layers of superstructure load.And the steel post that bearing capacity is higher " one pile for one column " bears 6 ~ 8 layers of superstructure load only.And the speed of application of superstructure is wanted far faster than the speed of underground structure adverse construction method, but due to conventional vertical supporting system bearing power restriction, superstructure is usually constructed to need to suspend to underground structure after the restriction number of plies and is completed, and vertical supporting system just can continue the construction of superstructure after can providing enough supporting capacity.Therefore, the routine " one pile for one column " that reverse construction adopts usually or " many, a post " vertical supporting system bearing power deficiency become the key affecting superstructure speed of application, this to a certain degree can delay Engineering Overall progress, reduces the advantage that the upper and lower synchronous construction of highrise building contrary sequence method shortens construction period.In addition, the vertical supporting system of " one pile for one column " or " many, a post " of prior art, due to its comparatively scattering device, when stress point is positioned at the corresponding position of stake, a sedimentation can be produced, and be uneven sedimentation, therefore had a strong impact on the supporting capacity of vertical supporting system and overall rigidity, the vertical supporting system particularly below Core Walls Structure position is more obvious.
Utility model content
Technical problem to be solved in the utility model is, the reverse construction vertical supporting system providing a kind of pile foundation integrated with diaphragm wall, to improve vertical bearing capacity and overall rigidity requirement, and the bulk settling of vertical supporting system and uneven sedimentation can be reduced.
In order to solve the problems of the technologies described above, the technical solution of the utility model is: the reverse construction vertical supporting system that a kind of pile foundation is integrated with diaphragm wall, comprise the diaphragm wall of reinforced concrete structure, and along the bottom of described diaphragm wall the pile foundation of reinforced concrete structure extended downwards, the integrated pouring construction of described diaphragm wall and described basis.
Further, the reverse construction vertical supporting system that the pile foundation that the utility model provides is integrated with diaphragm wall, described diaphragm wall, comprise the continuous wall trench underground being positioned at below ground location corresponding to core tube of high-rise building and arranging, be provided with diaphragm wall reinforcing cage in described continuous wall trench underground, described continuous wall trench underground and underground connection wall reinforcing cage have built concrete.
Further, the reverse construction vertical supporting system that the pile foundation that the utility model provides is integrated with diaphragm wall, described pile foundation, comprise and be positioned at described continuous wall trench underground several pile foundation pore-formings connected with described continuous wall trench underground are evenly set with downward-extension, be provided with pile foundation reinforcement cage in each described pile foundation pore-forming, described pile foundation pore-forming and pile foundation reinforcement cage have built concrete; Described continuous wall trench underground, diaphragm wall reinforcing cage and described pile foundation pore-forming, pile foundation reinforcement cage primary concreting concrete form diaphragm wall and the pile foundation of the integration of reinforced concrete structure.
Further, described pile foundation reinforcement cage is provided with reserved section reinforcing bar, and described reserved section reinforcing bar inserts in described diaphragm wall reinforcing cage.
Further, the reverse construction vertical supporting system that the pile foundation that the utility model provides is integrated with diaphragm wall, the periphery of described diaphragm wall is provided with auxiliary pile basis.
Further, the reverse construction vertical supporting system that the pile foundation that the utility model provides is integrated with diaphragm wall, described auxiliary pile basis, comprises engineering pile and structural column.
Further, the reverse construction vertical supporting system that the pile foundation that the utility model provides is integrated with diaphragm wall, described structural column is the lattice column of steel post or angle splice joint.
Compared with prior art, the reverse construction vertical supporting system that the utility model pile foundation is integrated with diaphragm wall, comprise the diaphragm wall of the reinforced concrete structure that integration is built, and the pile foundation of the reinforced concrete structure extended downwards along the bottom of described diaphragm wall.With the vertical supporting system of employing pile foundation structure pure in alternative prior art.That is, the upper/lower positions accordingly of the Core Walls Structure of highrise building adopts the integration diaphragm wall of building and pile foundation to constitute integrated reverse construction vertical supporting system by the utility model.Because diaphragm wall is reinforced concrete structure, its vertical bearing stress and integral rigidity are far longer than bearing stress and the rigidity of the vertical supporting system adopting separately pile foundation, in addition, the pile foundation extended bottom diaphragm wall has consolidated and strengthened again stability and the reliability of diaphragm wall, and namely pile foundation further improves bearing stress and the rigidity of diaphragm wall.In addition, reverse construction vertical supporting system of the present utility model, owing to have employed the diaphragm wall of reinforced concrete structure as support, compared with the vertical supporting system of " one pile for one column " in prior art or " many, a post ", the support system of its corresponding Core Walls Structure position is comparatively concentrated, therefore, it is possible to reduce the bulk settling of this support system and uneven sedimentation.In addition, after the reverse construction vertical supporting system adopting pile foundation of the present utility model integrated with diaphragm wall, in reverse construction process, without the need to waiting for that Underground Construction completes the construction that just can proceed superstructure, thus accelerate the construction speed of the superstructure of highrise building, there is raising efficiency of construction, shorten the effect of construction period.
Accompanying drawing explanation
Fig. 1 is the structural representation of the continuous wall trench underground of the utility model one embodiment;
Fig. 2 is the continuous wall trench underground of the utility model one embodiment and the structural representation of through pile foundation pore-forming thereof;
Fig. 3 is the structural representation of the utility model one embodiment pile foundation reverse construction vertical supporting system integrated with diaphragm wall;
Fig. 4 is the pile foundation of the utility model one embodiment and the cross-sectional view of ground, underground diaphragm wall.
Shown in figure: 110, diaphragm wall, 111, continuous wall trench underground, 112, diaphragm wall reinforcing cage, 120, pile foundation, 121 pile foundation pore-formings, 122, pile foundation reinforcement cage, 130, concrete, 140, auxiliary pile basis, 141, engineering pile, 142, structural column, 150, bracing of foundation pit wall, 200, ground.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model is described in detail:
Please refer to Fig. 1-4, the reverse construction vertical supporting system that present embodiment provides a kind of pile foundation integrated with diaphragm wall, comprise the diaphragm wall 110 of reinforced concrete structure, and along the bottom of described diaphragm wall 110 pile foundation 120 of reinforced concrete structure extended downwards, described diaphragm wall 110 has been built with the integrated steel concrete of described pile foundation 120.
The reverse construction vertical supporting system that the pile foundation that present embodiment provides is integrated with diaphragm wall, the diaphragm wall 110 of the reinforced concrete structure adopting integration to build and pile foundation 120, and the bottom that pile foundation 120 is positioned at diaphragm wall 110 is extended downwards.Because diaphragm wall 110 is reinforced concrete structure, its vertical bearing stress and integral rigidity are far longer than bearing stress and the rigidity of the vertical supporting system adopting separately pile foundation, in addition, pile foundation 120 extended bottom diaphragm wall 110 has consolidated and strengthened again stability and the reliability of diaphragm wall 110, and namely pile foundation 120 further improves bearing stress and the rigidity of diaphragm wall 110.Define the composite construction of diaphragm wall 110 and pile foundation 120.In addition, the reverse construction vertical supporting system of present embodiment, owing to have employed the diaphragm wall 110 of reinforced concrete structure as support, compared with the vertical supporting system of " one pile for one column " in prior art or " many, a post ", the support system of its corresponding Core Walls Structure position is comparatively concentrated, therefore, it is possible to reduce the bulk settling of this support system and uneven sedimentation.In addition, after the reverse construction vertical supporting system adopting the pile foundation of present embodiment integrated with diaphragm wall, in reverse construction process, without the need to waiting for that Underground Construction completes the construction that just can proceed superstructure, thus accelerate the construction speed of the superstructure of highrise building, there is raising efficiency of construction, shorten the effect of construction period.
Please refer to Fig. 1, Fig. 3, in present embodiment, diaphragm wall 110, comprise the continuous wall trench underground 111 being positioned at below position, core tube of high-rise building corresponding ground 200 and arranging, be provided with diaphragm wall reinforcing cage 112 in described continuous wall trench underground 111, described continuous wall trench underground 111 and underground connection wall reinforcing cage 112 have built concrete 130.This kind of structure, is conducive to forming Stability Analysis of Structures and the strong diaphragm wall 110 of vertical bearing capacity.The diaphragm wall 110 of reinforced concrete structure is firmer compared with the body of wall of brick structure or independent cement structures.
Please refer to Fig. 2, Fig. 3, in present embodiment, pile foundation 120, comprise and be positioned at described continuous wall trench underground 111 several pile foundation pore-formings 121 connected with described continuous wall trench underground 111 are evenly set with downward-extension, be provided with pile foundation reinforcement cage 122 in each described pile foundation pore-forming 121, described pile foundation pore-forming 121 and pile foundation reinforcement cage 122 have built concrete 130; Described continuous wall trench underground 111, diaphragm wall reinforcing cage 122 and pile foundation pore-forming 121, pile foundation reinforcement cage 122 primary concreting concrete form diaphragm wall 110 and the pile foundation 120 of the integration of reinforced concrete structure.Pile foundation pore-forming 121 and continuous wall trench underground 111 connect be convenient to synchronous in pile foundation pore-forming 121 and continuous wall trench underground 111 concreting 130, constructability.
Please refer to Fig. 4, in present embodiment, described pile foundation reinforcement cage 122 is provided with reserved section reinforcing bar 123, and described reserved section reinforcing bar 123 inserts in described diaphragm wall reinforcing cage 112.Reserved section reinforcing bar 123, make concrete in continuous wall trench underground 111 and pile foundation pore-forming 121 concreting and penetrate into pile foundation reinforcement cage 122 and diaphragm wall reinforcing cage 112 time, make the structure of the diaphragm wall 110 of the integration of formation and pile foundation 120 more stable, and form integrated support system.Namely after reserved section reinforcing bar 123 is inserted into diaphragm wall reinforcing cage 112, when concreting 130, concrete will penetrate into the junction of reserved section reinforcing bar 123 and diaphragm wall reinforcing cage 112, thus make diaphragm wall reinforcing cage 112 more stable with building of pile foundation reinforcement cage 122, shaping structures one.
Please refer to Fig. 1-3, the reverse construction vertical supporting system that the pile foundation that present embodiment provides is integrated with diaphragm wall, the periphery of described diaphragm wall 110 is provided with auxiliary pile basis 140.Wherein, described auxiliary pile basis 130, comprises engineering pile 141 and structural column 142.Wherein, described structural column 142 can be the lattice column of steel post or angle splice joint.Auxiliary pile basis 140 is for the bearing capacity of the superstructure outside supporting core cylinder.
Please refer to Fig. 1-3, present embodiment, bracing of foundation pit wall 150 can also be set on the border of foundation ditch, to prevent the situations such as Ji Fang border soil body landslide.
The utility model is not limited to above-mentioned detailed description of the invention, and all various changes done in the spirit and scope of claims of the present utility model, all within protection domain of the present utility model.

Claims (7)

1. the reverse construction vertical supporting system that a pile foundation is integrated with diaphragm wall, it is characterized in that, comprise the diaphragm wall of reinforced concrete structure, and along the bottom of described diaphragm wall the pile foundation of reinforced concrete structure extended downwards, described diaphragm wall and the integrated steel concrete of described pile foundation have been built.
2. the reverse construction vertical supporting system that pile foundation as claimed in claim 1 is integrated with diaphragm wall, it is characterized in that, described diaphragm wall, comprise the continuous wall trench underground being positioned at below ground location corresponding to core tube of high-rise building and arranging, be provided with diaphragm wall reinforcing cage in described continuous wall trench underground, described continuous wall trench underground and underground connection wall reinforcing cage have built concrete.
3. the reverse construction vertical supporting system that pile foundation as claimed in claim 2 is integrated with diaphragm wall, it is characterized in that, described pile foundation, comprise and be positioned at described continuous wall trench underground several pile foundation pore-formings connected with described continuous wall trench underground are evenly set with downward-extension, be provided with pile foundation reinforcement cage in each described pile foundation pore-forming, described pile foundation pore-forming and pile foundation reinforcement cage have built concrete; Described continuous wall trench underground, diaphragm wall reinforcing cage and described pile foundation pore-forming, pile foundation reinforcement cage primary concreting concrete form diaphragm wall and the pile foundation of the integration of reinforced concrete structure.
4. the reverse construction vertical supporting system that pile foundation as claimed in claim 3 is integrated with diaphragm wall, it is characterized in that, described pile foundation reinforcement cage is provided with reserved section reinforcing bar, and described reserved section reinforcing bar inserts in described diaphragm wall reinforcing cage.
5. the reverse construction vertical supporting system that pile foundation as claimed in claim 1 is integrated with diaphragm wall, it is characterized in that, the periphery of described diaphragm wall is provided with auxiliary pile basis.
6. the reverse construction vertical supporting system that pile foundation as claimed in claim 5 is integrated with diaphragm wall, is characterized in that, described auxiliary pile basis, comprises engineering pile and structural column.
7. the reverse construction vertical supporting system that pile foundation as claimed in claim 6 is integrated with diaphragm wall, it is characterized in that, described structural column is the lattice column of steel post or angle splice joint.
CN201520769847.6U 2015-09-30 2015-09-30 Pile foundation and integrated reverse construction vertical braces system of underground continuous wall Active CN205024719U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520769847.6U CN205024719U (en) 2015-09-30 2015-09-30 Pile foundation and integrated reverse construction vertical braces system of underground continuous wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520769847.6U CN205024719U (en) 2015-09-30 2015-09-30 Pile foundation and integrated reverse construction vertical braces system of underground continuous wall

Publications (1)

Publication Number Publication Date
CN205024719U true CN205024719U (en) 2016-02-10

Family

ID=55257264

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520769847.6U Active CN205024719U (en) 2015-09-30 2015-09-30 Pile foundation and integrated reverse construction vertical braces system of underground continuous wall

Country Status (1)

Country Link
CN (1) CN205024719U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105756075A (en) * 2016-02-29 2016-07-13 山东电力工程咨询院有限公司 Horizontal bearing combined foundation based on piles and underground continuous wall and method
CN107044132A (en) * 2017-02-22 2017-08-15 常熟建工建设集团有限公司 A kind of construction method of quake-resistant safety ground
CN109083128A (en) * 2018-09-10 2018-12-25 浙江吉通地空建筑科技有限公司 Fashioned iron column assembled underground continuous wall with high-bearing capacity

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105756075A (en) * 2016-02-29 2016-07-13 山东电力工程咨询院有限公司 Horizontal bearing combined foundation based on piles and underground continuous wall and method
CN107044132A (en) * 2017-02-22 2017-08-15 常熟建工建设集团有限公司 A kind of construction method of quake-resistant safety ground
CN107044132B (en) * 2017-02-22 2019-01-01 常熟建工建设集团有限公司 A kind of construction method of quake-resistant safety ground
CN109083128A (en) * 2018-09-10 2018-12-25 浙江吉通地空建筑科技有限公司 Fashioned iron column assembled underground continuous wall with high-bearing capacity

Similar Documents

Publication Publication Date Title
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN203239357U (en) Adjacent tunnel supporting structure suitable for collapsible loess
CN104746435A (en) Wide-angle Y-shaped pier column construction method
CN103334439A (en) Long-span reinforced concrete inner support structure of rectangular deep foundation pit and construction method of structure
CN103953114B (en) Steel frame-reinforced masonry shear wall combinative structure and construction method thereof
CN103556749A (en) Hanging flexible connection of precast concrete infill wall
CN203654294U (en) Foundation pit supporting structure used in reverse building method
CN105113537A (en) Vertical support system constructed through reverse construction method and method for vertical support system
CN103726586A (en) H-shaped steel and steel plate framework assembly shear wall with interfaces with grooves and manufacturing method
CN205024719U (en) Pile foundation and integrated reverse construction vertical braces system of underground continuous wall
CN203891087U (en) Gravity-type retaining wall reinforcement structure
CN103104102A (en) Construction method for underground storey-addition reconstruction
CN105714678B (en) A kind of combined type gravity anchorage
CN205676882U (en) A kind of novel supporting construction
CN107443550A (en) Prefabricated cushion cap template and its installation method
CN106988319A (en) A kind of rapid constructing method of large deep foundation pit agent structure side wall
CN207567784U (en) Deep basal pit combined type supporting
CN103911989B (en) A kind of underwater casting base type foundation with retaining wall and construction method thereof
CN103122642A (en) Construction method of vertical post support change
CN203530958U (en) Thin-wall prefabricated overlapped concrete underground diaphragm wall
CN204001705U (en) Outer wall of basement single surface formwork constructing structure based on earth anchor truss
CN103981799B (en) A kind of concrete filled steel tube opens string stiff beam and construction method thereof
CN203821248U (en) Steel pipe arch main arch assembling supporting system
CN203066083U (en) Supporting structure for two adjacent foundation pits