KR102146073B1 - Slip form for the construction of a vertical shaft with varying cross-section and the construction method - Google Patents

Slip form for the construction of a vertical shaft with varying cross-section and the construction method Download PDF

Info

Publication number
KR102146073B1
KR102146073B1 KR1020200047141A KR20200047141A KR102146073B1 KR 102146073 B1 KR102146073 B1 KR 102146073B1 KR 1020200047141 A KR1020200047141 A KR 1020200047141A KR 20200047141 A KR20200047141 A KR 20200047141A KR 102146073 B1 KR102146073 B1 KR 102146073B1
Authority
KR
South Korea
Prior art keywords
lifting
slip foam
main
section
excavation
Prior art date
Application number
KR1020200047141A
Other languages
Korean (ko)
Inventor
고엄식
Original Assignee
주식회사 네오시티
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 네오시티 filed Critical 주식회사 네오시티
Priority to KR1020200047141A priority Critical patent/KR102146073B1/en
Application granted granted Critical
Publication of KR102146073B1 publication Critical patent/KR102146073B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Abstract

The present invention relates to a slip form used in constructing a vertical shaft with a varying cross section having a planar cross section with a portion becoming smaller by forming a protruding unit on the inside of an inner wall, and a construction method of a vertical shaft with a varying cross section using the same. The slip form used in the present invention is formed in a planar shape corresponding to the cross section of a vertical shaft excluding the protruding unit, and includes a plurality of hydraulic jacks for lifting a slip form on a main surface unit coming in contact with an excavation surface, one or more lifting rings on an end other than the main surface unit coming in contact with the excavation surface to be connected to a lifting device above by a cable, and a coupling unit on the end other than the main surface unit coming in contact with the excavation surface to be coupled to an auxiliary slip form to simultaneously operate and lift the hydraulic jacks and the lifting device to maintain balance even when lifted. According to the present invention, the construction method of a vertical shaft comprises: (1) a step A of depositing bottom concrete on the lower surface of an excavation hole; (2) a step B of depositing on-site deposition concrete to construct a protruding unit after installing a form; (3) a step C of placing a main slip form formed in a planar shape corresponding to the cross section of a vertical shaft excluding the protruding unit and provided with a plurality of hydraulic jacks for lifting a slip form on a main surface unit coming in contact with an excavation surface and one or more lifting rings on an end other than the main surface unit coming in contact with the excavation surface on an upper portion of the bottom concrete; (4) a step D of coupling a cable to the lifting rings and connecting the lifting rings to a lifting device above; and (5) a step E of simultaneously operating the hydraulic jacks and the lifting device to form a vertical shaft with the protruding unit while ascending in a state in which the balance of the main slip form is maintained.

Description

변단면 수직구 시공을 위한 슬립폼 및 이를 이용한 변단면 수직구 시공방법{Slip form for the construction of a vertical shaft with varying cross-section and the construction method}Slip form for the construction of a vertical shaft with varying cross-section and the construction method}

본 발명은 내벽 안쪽에 돌출부가 형성되어 있어 평면단면이 작아지는 부분을 갖는 변단면 수직구 시공에 이용되는 슬립폼과 이를 이용한 변단면 수직구 시공방법에 관한 것이다.The present invention relates to a slip foam used for construction of a vertical vertical sphere having a portion having a small plane cross-section due to a protrusion formed inside the inner wall, and a method of constructing a vertical vertical sphere using the same.

최근 도시의 입체적인 개발을 위하여 도심지 지하공간을 활용한 대심도 터널이나 공공시설물을 수용하는 공동구 등의 시공이 증대됨에 따라, 시공 중 공사용 시공 후의 유지관리 통로 그리고 환기구 역할로서 수직구(vertical shaft) 시공사례가 증가하고 있다.In recent years, as the construction of deep tunnels using underground spaces in downtown areas or common areas to accommodate public facilities has increased for the three-dimensional development of cities, construction of a vertical shaft as a maintenance passage and ventilation port after construction during construction Cases are increasing.

이와 같은 수직구는 지상에서 수직방향의 굴착공을 굴착하고, 굴착공 저면에 바닥콘크리트를 타설하여 바닥면을 성형한 후, 굴착공의 바닥면에서부터 굴착공의 내주면을 따라 거푸집을 설치하고 콘크리트를 타설하는 공정을 반복하여 수직벽체를 형성하는 순서로 시공된다.Such a vertical hole excavates the excavation hole in the vertical direction from the ground, pours concrete on the bottom of the excavation hole to form the bottom surface, and then installs a formwork along the inner circumferential surface of the excavation hole from the bottom of the excavation hole and pours concrete. It is constructed in the order of forming a vertical wall by repeating the process.

수직구의 수직벽체를 형성함에 있어서, 과거에는 수직벽체의 형성위치에 거푸집을 설치하고 콘크리트를 타설한 후에 거푸집을 해체하고 다음 작업위치에 재조립하여 설치한 후 콘크리트를 타설하는 작업을 반복하는 거푸집 방식을 사용하였으나, 최근에는 슬립폼 공법이 많이 사용된다.In forming the vertical wall of the vertical sphere, in the past, the formwork was installed at the location where the vertical wall was formed, and after concrete was poured, the formwork was dismantled, reassembled and installed at the next working location, and then concrete was poured. Was used, but recently the slip foam method is widely used.

슬립폼은 콘크리트 타설 후에 콘크리트가 자립할 수 있는 강도 이상이 되면 거푸집을 상부 방향으로 상승시키면서 연속적으로 철근조립, 콘크리트 타설 등을 실시하여 구조물을 완성시키는 공법에 적용되는 거푸집을 말한다. 슬립폼은 일반적으로 상부작업대, 중간작업대, 하부작업대로 구성되며, 주면에 배치된 유압잭에 의하여 수직으로 이동하면서 수직벽체를 시공한다.Slip form refers to a form applied to the construction method of completing a structure by continuously assembling reinforcing bars and pouring concrete while raising the formwork upward when the strength of concrete becomes more than the strength that can stand on its own after pouring concrete. The slip foam is generally composed of an upper workbench, an intermediate workbench, and a lower workbench, and a vertical wall is constructed while moving vertically by a hydraulic jack arranged on the main surface.

슬립폼 공법은 단면이 일정한 수직구의 형성에는 유리하지만, 수직터널의 내부에 횡방향 수평터널이 연결되어 있어, 수평터널의 단부가 수직터널의 내부로 돌출되는 돌출부가 있는 경우에는, 수직구의 단면이 변하는 부분이 생기기 때문에 슬립폼 공법을 바로 적용하는데 어려움이 있다.The slip form method is advantageous for forming a vertical sphere with a constant cross section, but the horizontal tunnel is connected to the inside of the vertical tunnel, so if the end of the horizontal tunnel has a protrusion protruding into the vertical tunnel, the cross section of the vertical sphere is It is difficult to apply the slip foam method right away because there is a changeable part.

도 1a는 돌출부가 형성된 수직구의 절개 사시도이고, 도 1b는 내벽 안쪽에 돌출부가 형성된 수직구의 수직 단면도인데, 수직구(1)가 수평연결터널(2)과 연결되면서, 수평연결터널(2)의 단부가 수직구(1)의 내벽 안쪽에 위치하여 수직구 내부에 돌출부(21)가 형성되는 구조이다.1A is a cut-away perspective view of a vertical sphere with a protrusion, and FIG. 1B is a vertical cross-sectional view of a vertical sphere with a protrusion formed inside the inner wall. While the vertical sphere 1 is connected to the horizontal connection tunnel 2, the horizontal connection tunnel 2 The end portion is located inside the inner wall of the vertical sphere (1) is a structure in which the protrusion 21 is formed inside the vertical sphere.

돌출부가 형성된 구간에서는, 수직구의 단면에 대응되는 평면형상을 갖는 통상적인 슬립폼을 이용하여 수직구 벽체를 형성할 수 없기 때문에, 돌출부가 위치한 구간에는 전통적인 거푸집 방식을 이용하게 되므로, 슬립폼 공법을 선택함으로 인한 공기단축이나 비용절감효과가 줄어들게 된다.In the section where the protrusion is formed, since the vertical sphere wall cannot be formed using a normal slip foam having a planar shape corresponding to the cross section of the vertical sphere, the traditional formwork method is used in the section where the protrusion is located. The cost reduction effect or cost reduction effect due to the selection will be reduced.

또한 돌출부가 형성되는 구간에서, 돌출부 이외의 벽체 형성을 위하여 슬립폼 공법을 적용한다고 하더라도, 유압잭과 잭로드에 의해서 지지되지 않는 슬립폼 단부는 슬립폼의 자중과 슬립폼 작업대에 적재되는 각종 자재의 중량으로 인해서 처짐이 발생하게 되어 슬립폼이 수평상태를 유지하면서 상승하기가 어려운데, 이는 수직구의 수직도에도 영향을 주게 되어 시공품질을 저하시키는 요인이 된다.In addition, in the section where the protrusion is formed, even if the slip form method is applied to form walls other than the protrusion, the end of the slip foam that is not supported by the hydraulic jack and jack rod is the weight of the slip foam and various materials loaded on the slip foam work table. Due to the weight, sagging occurs and it is difficult for the slip form to rise while maintaining a horizontal state, which affects the verticality of the vertical sphere as well, which deteriorates the construction quality.

등록특허공보 제10-1679180호 수직환기구의 시공방법Registered Patent Publication No. 10-1679180 Construction method of vertical ventilation 등록특허공보 제10-1737193호 수직터널 구조물 및 그 시공방법Registered Patent Publication No. 10-1737193 Vertical tunnel structure and its construction method 등록특허공보 제10-0913381호 수직터널 구조물용 슬립폼 및 이를 이용한 지중수직터널 구조물의 시공방법Registered Patent Publication No. 10-0913381 Slip form for vertical tunnel structure and construction method of underground vertical tunnel structure using the same 등록특허공보 제10-2001526호 하향식 공법용 수직구 압입장치 및 이를 이용한 수직구 시공방법Registered Patent Publication No. 10-2001526 Vertical sphere press-in device for top-down construction method and vertical sphere construction method using the same

본 발명은 수직구 내벽 안쪽에 돌출부가 형성되어 있어, 수직구의 평면단면이 작아지는 부분이 있는 변단면 수직구에 있어서도, 연속적인 시공이 가능하도록 하기 위한 슬립폼과 이를 이용한 변단면 수직구 시공방법을 제공하기 위한 것이다.In the present invention, a protrusion is formed inside the inner wall of the vertical sphere, so that even in the side vertical sphere where the plane cross section of the vertical sphere is small, the slip foam for continuous construction and the construction method of the side vertical sphere using the same It is to provide.

본 발명은 슬립폼의 상승과정에서도 슬립폼의 평형을 유지하게 함으로써, 슬립폼에 의해 형성되는 수직구가 수직상태를 유지하도록 하는 것을 하나의 목적으로 한다. One object of the present invention is to maintain the vertical state of the vertical sphere formed by the slip foam by maintaining the balance of the slip foam even in the rising process of the slip foam.

또한 본 발명은 유압장치가 구비되지 않는 슬립폼의 단부를 다양한 방식으로 인양장치와 연결되게 함으로써, 시공현장의 상황에 따라 최적의 인양방식을 선택할 수 있게 하는 것을 하나의 목적으로 한다. 또한 인양브라켓의 길이를 조절함으로써 인양고리와 인양장치를 연결하는 케이블의 수직도를 조절할 수 있게 하는 것을 하나의 목적으로 한다. In addition, one object of the present invention is to allow the end of the slip foam not equipped with a hydraulic device to be connected to the lifting device in various ways, so that the optimal lifting method can be selected according to the situation of the construction site. In addition, one object is to be able to adjust the verticality of the cable connecting the lifting hook and the lifting device by adjusting the length of the lifting bracket.

그리고 본 발명은 돌출부의 상면에서는 슬립폼이 전체 수직구 평면단면에 대응하도록 슬립폼을 조립형성할 수 있게 함으로써, 수직구의 단면이 변화하는 경우에도 수직구의 연속적인 시공이 가능하도록 하는 것을 하나의 목적으로 한다.In addition, one object of the present invention is to make it possible to assemble the slip foam on the upper surface of the protrusion so that the slip foam corresponds to the plane cross section of the entire vertical sphere, thereby enabling continuous construction of the vertical sphere even when the cross section of the vertical sphere changes. To do.

본 발명의 이러한 목적은, 돌출부를 제외한 수직구 단면에 대응되는 평면형상으로 형성되며, 굴착면과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭이 구비되고, 굴착면과 접하는 주면부 이외의 단부에는 하나 또는 둘 이상의 인양고리가 구비되어 상부의 인양장치와 케이블에 의해 연결되며, 굴착면과 접하는 주면부 이외의 단부에는 수직구 평면단면이 확장되는 영역에서 부슬립폼과 결합할 수 있게 하기 위한 결합부가 구비되는 슬립폼에 의하여, 상기 유압잭과 인양장치가 동시에 작동하여 상승됨으로써 상승시에도 평형이 유지되게 한다.This object of the present invention is formed in a planar shape corresponding to the cross section of the vertical sphere excluding the protrusion, and a plurality of hydraulic jacks for lifting the slip foam are provided on the main surface part in contact with the excavation surface, and ends other than the main surface part in contact with the excavation surface Is provided with one or more lifting rings on the upper part and connected by cables, and at the ends other than the main surface part in contact with the excavation surface, the vertical ball can be combined with the sub-slip foam in the area where the plane cross section extends. By the slip foam provided with a coupling part, the hydraulic jack and the lifting device are simultaneously operated and lifted so that the balance is maintained even when ascending.

또한, 돌출부를 제외한 수직구 단면에 대응되는 평면형상으로 형성되며, 굴착면과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭이 구비되고, 굴착면과 접하는 주면부 이외의 단부에는 하나 또는 둘 이상의 인양고리가 구비되어 상부의 인양장치와 케이블에 의해 연결되며,굴착면과 접하는 주면부 이외의 단부에는 수직구 평면단면이 확장되는 영역에서 부슬립폼과 결합하기 위한 결합부가 구비되는 주슬립폼; 상기 돌출부에 대응되는 평면형상으로 형성되며, 굴착면과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭이 구비되고, 굴착면과 접하는 주면부 이외의 단부에서 주슬립폼의 결합부와 연결되어 조립되는 부슬립폼;으로 구성되어, 주슬립폼과 부슬립폼이 조립결합됨으로써 단면이 확장되는 부분에도 수직구의 연속적인 시공이 가능해진다.In addition, it is formed in a flat shape corresponding to the cross section of the vertical sphere excluding the protrusion, and a plurality of hydraulic jacks for lifting the slip foam are provided on the main surface in contact with the excavation surface, and one or two or more ends other than the main surface in contact with the excavation surface. A main slip foam provided with a lifting ring and connected by a lifting device and a cable at the top, and having a coupling portion for coupling with the sub slip foam in an area in which the vertical plane cross-section extends at an end other than the main surface portion in contact with the excavation surface; It is formed in a planar shape corresponding to the protrusion, and is provided with a plurality of hydraulic jacks for increasing the slip foam on the main surface in contact with the excavation surface, and is assembled by being connected to the coupling part of the main slip foam at the ends other than the main surface in contact with the excavation surface. Consisting of, the main slip foam and the sub slip foam are assembled and coupled to enable continuous construction of the vertical sphere even in the area where the cross section is expanded.

그리고, 인양장치가 굴착공 외부의 크레인, 굴착공 입구를 가로지르는 보, 굴착면에 고정된 인양브라켓 또는 돌출부 상부에 고정된 인양브라켓 중 어느 하나에 고정될 수 있기 때문에, 현장 상황에 따라 작업방식을 선택할 수 있다. 특히, 굴착면에 고정된 인양브라켓 또는 돌출부 상부에 고정된 인양브라켓은, 하나 또는 둘 이상의 조절공이 형성된 수평관체, 복수의 결합공이 형성되고 수평관체에 삽입되는 슬라이드체, 수평관체의 조절공 및 슬라이드체의 결합공을 관통 결합하여 수평관체와 슬라이드체를 고정하는 볼트 및 너트로 구성되어, 슬라이드체가 수평관체에 삽입되는 길이를 조절할 수 있기 때문에, 인양고리와 인양장치를 연결하는 케이블의 수직도를 쉽게 조절할 수 있다. And, since the lifting device can be fixed to any of the crane outside the drilling hole, the beam crossing the entrance of the drilling hole, the lifting bracket fixed to the drilling surface, or the lifting bracket fixed on the upper part of the protrusion, the working method according to the site situation You can choose. In particular, the lifting bracket fixed to the excavation surface or the lifting bracket fixed on the upper part of the protrusion includes a horizontal pipe body with one or more adjustment holes, a slide body having a plurality of coupling holes and inserted into the horizontal pipe body, and the adjustment hole and slide of the horizontal pipe body. It is composed of bolts and nuts to fix the horizontal pipe body and the slide body by penetrating through the coupling hole of the sieve, and because the length of the slide body inserted into the horizontal pipe body can be adjusted, the verticality of the cable connecting the lifting ring and the lifting device is reduced. Can be easily adjusted.

본 발명은 슬립폼의 상승과정에서도 슬립폼의 단부에 처짐이 발생하지 않고 평형을 유지할 수 있기 때문에, 슬립폼에 의해 형성되는 수직구의 수직도를 일정하게 유지할 수 있는 효과가 있다. The present invention has the effect of maintaining a constant verticality of a vertical sphere formed by the slip foam, since it is possible to maintain an equilibrium without sagging at the end of the slip foam even in the rising process of the slip foam.

또한 본 발명은 유압장치가 구비되지 않는 슬립폼의 단부를 굴착공 외부의 크레인, 굴착공 입구를 가로지르는 보, 굴착면에 고정된 인양브라켓 또는 돌출부 상부에 고정된 인양브라켓 중 어느 하나와 선택적으로 결합할 수 있기 때문에, 현장 상황에 따라 작업방식을 선택할 수 있는 장점이 있다. In addition, the present invention selectively connects the end of the slip foam not provided with a hydraulic device to one of a crane outside the drilling hole, a beam crossing the entrance of the drilling hole, a lifting bracket fixed to the drilling surface, or a lifting bracket fixed on the top of the protrusion. Because it can be combined, there is an advantage of being able to select a working method according to the site situation.

특히, 굴착면에 고정된 인양브라켓 또는 돌출부 상부에 고정된 인양브라켓은 수평관체와 슬라이드체로 구성되기 때문에, 인양고리와 인양장치를 연결하는 케이블의 수직도를 쉽게 조절할 수 있는 효과가 있다.In particular, since the lifting bracket fixed to the excavation surface or the lifting bracket fixed on the upper part of the protrusion is composed of a horizontal pipe body and a slide body, there is an effect that the verticality of the cable connecting the lifting hook and the lifting device can be easily adjusted.

그리고 수직구의 단면이 확장되는 구간에서는, 주슬립폼과 부슬립폼을 조립 결합하여 확장된 수직구 단면에 대응하는 슬립폼을 구성함으로써, 연속적인 수직구 시공이 가능하다는 장점이 있다. And in the section in which the cross section of the vertical sphere is extended, the main slip foam and the sub slip foam are assembled to form a slip foam corresponding to the expanded vertical sphere cross section, thereby enabling continuous vertical sphere construction.

도 1a 돌출부가 형성된 수직구의 절개 사시도
도 1b 돌출부가 형성된 수직구의 수직 단면도
도 2a 주슬립폼과 부슬립폼 분해 상태 중간작업대 평면도
도 2b 주슬립폼과 부슬립폼 분해 상태 단면도
도 3a 주슬립폼과 부슬립폼 결합 상태 중간작업대 평면도
도 3b 주슬립폼과 부슬립폼 결합 상태 단면도
도 4 주슬립폼과 부슬립폼 결합부분 상세도
도 5 굴착공 외부의 크레인에 인양장치를 고정한 실시예 단면도
도 6 굴착공 입구를 가로지는 보에 인양장치를 고정한 실시예 단면도
도 7 굴착면에 고정된 인양브라켓에 인양장치를 고정한 실시예에 따른 변단면 수직구 시공 순서도
도 8 돌출부 상부에 고정된 인양브라켓에 인양장치를 고정한 실시예에 따른 변단면 수직구 시공 순서도
도 9 굴착면에 고정된 인양브라켓 측면도
도 10 돌출부 상부에 고정된 인양브라켓 측면도
Fig. 1a a cutaway perspective view of a vertical sphere formed with a protrusion
Figure 1b vertical cross-sectional view of a vertical sphere formed with a protrusion
Fig. 2a A plan view of an intermediate working table in an exploded state of the main slip foam and the sub slip foam
Fig. 2b A cross-sectional view of the main slip foam and the sub slip foam in an exploded state
Fig. 3a A plan view of an intermediate working table in a state in which the main slip foam and the sub slip foam are combined
Figure 3b cross-sectional view of a state in which the main slip foam and the sub slip foam are combined
Fig. 4 Detailed view of the joint part of the main slip foam and the sub slip foam
Figure 5 Cross-sectional view of an embodiment in which a lifting device is fixed to a crane outside the excavation hole
Figure 6 A cross-sectional view of an embodiment in which the lifting device is fixed to the beam crossing the entrance of the excavation hole
Fig. 7 Flow chart of construction of a vertical tool on the side of a side according to an embodiment in which a lifting device is fixed to a lifting bracket fixed to the excavation surface
Fig. 8 Flow chart of construction of a vertical hole on the side of the side according to the embodiment in which the lifting device is fixed to the lifting bracket fixed on the upper part of the protrusion
Figure 9 Side view of a lifting bracket fixed to the excavation surface
Fig. 10 Side view of a lifting bracket fixed on the upper part of the protrusion

본 발명에 따른, 평면 단면이 작아지는 부분을 갖는 수직구 시공에 이용되는 슬립폼은, 도 2a 및 도 2b에 도시된 바와 같이, 크게 주슬립폼과 부슬립폼으로 구성할 수 있다. According to the present invention, the slip foam used in the construction of a vertical ball having a small plane cross-section may be largely composed of a main slip foam and a sub slip foam, as shown in FIGS. 2A and 2B.

주슬립폼(4)은 돌출부(21)를 제외한 수직구 단면에 대응되는 평면형상으로 형성되며; 굴착면(3)과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭(41)이 구비되고; 굴착면과 접하는 주면부 이외의 단부에는 하나 또는 둘 이상의 인양고리(42)가 구비되어 상부의 인양장치(44)와 케이블(45)에 의해 연결되며; 굴착면(3)과 접하는 주면부 이외의 단부에는 수직구 평면단면이 확장되는 영역에서 부슬립폼과 결합할 수 있게 하기 위한 결합부(43)가 구비된다. The main slip foam 4 is formed in a planar shape corresponding to a cross section of a vertical sphere excluding the protrusion 21; A plurality of hydraulic jacks 41 for increasing the slip foam are provided on the main surface portion in contact with the excavation surface 3; One or two or more lifting rings 42 are provided at ends other than the main surface portion in contact with the excavation surface, and are connected by the lifting device 44 and the cable 45 at the top; An end portion other than the main surface portion in contact with the excavation surface 3 is provided with a coupling portion 43 for engaging with the sub-slip foam in an area in which the vertical plane cross-section extends.

주슬립폼을 상승시킬 때에는 상기 유압잭(41)과 인양장치(44)를 동시에 작동시키기 때문에 상승시에도 슬립폼의 주면부 또는 단부에 처짐이 발생하지 않고 평형이 유지될 수 있다.When the main slip foam is raised, the hydraulic jack 41 and the lifting device 44 are simultaneously operated, so that even when the main slip foam is raised, the main surface portion or the end portion of the slip foam does not sag and the balance can be maintained.

부슬립폼(5)은 돌출부에 대응되는 평면형상으로 형성되며, 굴착면(3)과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭(51)이 구비되고, 굴착면과 접하는 주면부 이외의 단부에서 주슬립폼의 결합부(43)와 연결되어 조립될 수 있다.The sub-slip foam 5 is formed in a planar shape corresponding to the protrusion, and a plurality of hydraulic jacks 51 for lifting the slip foam are provided on the main surface portion in contact with the excavation surface 3, and other than the main surface portion in contact with the excavation surface. It can be assembled by being connected to the coupling portion 43 of the main slip foam at the end.

설명의 편의를 위하여 주슬립폼(4)과 부슬립폼(5)으로 구분하였지만, 주슬립폼(4)의 경우에는 부슬립폼(5)과 결합하지 않은 상태에서도 수직구 벽체 시공에 이용될 수 있기 때문에, 하나의 독립적인 슬립폼으로 시공현장에서 이용할 수 있다. 즉, 수직구 내부에 돌출부(21)가 형성되는 구간의 시공에 있어서는 부슬립폼(5)과 결합하지 않고, 돌출부 이외의 벽체를 상방향으로 연속적으로 시공할 수 있으므로, 부슬립폼은 하나의 독립적인 슬립폼으로 벽체의 시공에 이용할 수 있다.For convenience of explanation, it is divided into a main slip foam (4) and a sub slip foam (5), but in the case of the main slip foam (4), it can be used for vertical wall construction even when not combined with the sub slip foam (5). Because it can be used, it can be used at the construction site as an independent slip foam. That is, in the construction of the section in which the protrusion 21 is formed inside the vertical sphere, it is not combined with the sub-slip foam 5, and a wall other than the protrusion can be continuously constructed in the upward direction. As an independent slip foam, it can be used for wall construction.

또한, 일반적으로 슬립폼의 중간작업대가 슬립폼의 강성을 유지하기 때문에 슬립폼의 중간작업대에 인양고리와 결합부가 구비되는 것으로 도시하였지만, 인양고리와 결합부가 중간작업대에만 한정되어 구비될 수 있는 것은 아니다.In addition, in general, since the intermediate working table of the slip foam maintains the rigidity of the slip foam, it has been shown that the lifting hook and the coupling part are provided on the intermediate working table of the slip foam, but the lifting hook and the coupling part can be limited only to the intermediate working table. no.

도 3a 및 도 3b에는 주슬립폼과 부슬립폼이 조립되어 결합되어 있는 상태를 도시하고 있다. 3A and 3B show a state in which the main slip foam and the sub slip foam are assembled and combined.

수직구 내부에 돌출부(21)가 형성되는 구간의 시공이 완료된 후에는 부슬립폼(5)을 주슬립폼(4)과 조립하여 단면이 확장되는 구간의 벽체를 연속적으로 시공할 수 있다. After the construction of the section in which the protrusion 21 is formed in the vertical sphere is completed, the sub-slip foam 5 is assembled with the main slip-form 4 to continuously construct the wall of the section whose cross section is expanded.

도 4에는 주슬립폼과 부슬립폼의 결합부분이 도시되어 있다. 주슬립폼(4)의 결합부(43)는 주슬립폼의 단부에서 외주면 방향으로 구비되는 복수의 연결철물로 구성된다. 주슬립폼(4)의 결합부(43)에 부슬립폼(5)의 단부를 위치시킨 상태에서, 결합부에 부슬립폼 단부의 플랜지 또는 웹을 서로 고정한다. Figure 4 shows the coupling portion of the main slip foam and the sub slip foam. The coupling portion 43 of the main slip foam 4 is composed of a plurality of connecting hardware provided from the end of the main slip foam toward the outer circumferential surface. In a state where the end of the sub-slip form 5 is positioned on the coupling part 43 of the main slip form 4, the flange or the web at the end of the sub-slip form is fixed to each other in the coupling part.

도 4에서는 볼트와 너트에 의해서 체결하는 것으로 가정하여, 체결공이 형성되는 것으로 도시하였으나, 이 외에 용접이나 기타 체결수단을 활용할 수도 있다. 다만, 주슬립폼과 부슬립폼이 조립되고 나면 하나의 일체로 된 슬립폼으로 기능해야 하기 때문에, 주슬립폼(4)의 결합부(43)와 부슬립폼(5)의 단부가 조립 이후에도 그 조립부위에서 충분한 강성이 확보되도록 결합되어야 함은 당연하다. In FIG. 4, it is assumed that the bolt and the nut are fastened, and the fastening hole is formed. However, welding or other fastening means may be used in addition to this. However, after the main and sub-slip foams are assembled, they must function as a single integrated slip foam, so that the coupling portion 43 of the main slip-form 4 and the end of the sub-slip foam 5 remain even after assembly. It is natural that the assembly should be combined to ensure sufficient rigidity.

주슬립폼(4)과 부슬립폼(5)을 조립하여 일체로 한 후에는, 주슬립폼(4)의 인양고리(42)와 케이블(45)의 연결은 해제하고, 주슬립폼(4)의 주면부에 구비된 유압잭(41)과 부슬립폼(5)의 주면부에 구비된 유압잭(51)의 작동에 의해서 상승하면서 벽체를 시공한다.After assembling the main slip foam (4) and the sub slip foam (5) into one body, the connection between the lifting hook 42 and the cable 45 of the main slip foam 4 is released, and the main slip foam 4 A wall is constructed while rising by the operation of the hydraulic jack 41 provided on the main surface of the) and the hydraulic jack 51 provided on the main surface of the sub-slip form 5.

본 발명에서 주슬립폼(4)은 돌출부가 형성되어 있는 구간의 벽체를 시공할 때에는 유압잭(41)과 인양장치(44)에 의해서 상승되는데, 인양장치는 주슬립폼의 인양고리(42)와 케이블(45)에 의해서 연결된다. In the present invention, the main slip foam 4 is raised by the hydraulic jack 41 and the lifting device 44 when constructing the wall of the section in which the protrusion is formed, and the lifting device is the lifting ring 42 of the main slip foam and It is connected by a cable 45.

슬립폼의 수직 상태을 유지하면서 인양장치의 효율을 높이기 위해서는 인양장치(44)가 인양고리(42)의 수직 상부에 위치하는 것이 바람직하다.In order to increase the efficiency of the lifting device while maintaining the vertical state of the slip foam, it is preferable that the lifting device 44 is positioned vertically above the lifting ring 42.

인양장치(44)는 굴착공 외부의 크레인(6)에 설치될 수 있다. 도 5는 굴착공 외부에 위치하는 크레인 장비에 인양장치가 설치되는 실시예를 도시하고 있다.The lifting device 44 may be installed on the crane 6 outside the excavation hole. 5 shows an embodiment in which a lifting device is installed on a crane equipment located outside the excavation hole.

인양장치(44)는 굴착공 입구를 가로지르는 수평보(7)에 설치될 수 있다. 도 6은 굴착공 입구를 가로지는 수평보(7)에 인양장치를 설치한 실시예를 도시하고 있다.The lifting device 44 may be installed on the horizontal beam 7 crossing the entrance of the excavation hole. 6 shows an embodiment in which the lifting device is installed on the horizontal beam 7 crossing the entrance of the excavation hole.

인양장치(44)는 굴착면(3)에 고정된 인양브라켓(8)에 설치될 수 있다. 도 7a는 굴착면에 고정된 인양브라켓(8)에 인양장치를 설치한 실시예를 도시하고 있다.The lifting device 44 may be installed on the lifting bracket 8 fixed to the excavation surface 3. 7A shows an embodiment in which a lifting device is installed on a lifting bracket 8 fixed to an excavation surface.

인양장치(44)는 돌출부(21) 상부에 고정된 인양브라켓(9)에 설치될 수 있다. 도 8a는 돌출부 상부에 고정된 인양브라켓(9)에 인양장치를 설치한 실시예를 도시하고 있다.The lifting device 44 may be installed on the lifting bracket 9 fixed on the upper part of the protrusion 21. 8A shows an embodiment in which the lifting device is installed on the lifting bracket 9 fixed on the upper part of the protrusion.

인양장치를 크레인(6) 장비 또는 수평보(7)에 설치하는 경우에는, 인양장치와 인양고리를 연결하는 케이블의 길이가 길어지게 되므로, 유압잭과 인양장치를 동시에 작동하는 경우에도 슬립폼의 수평유지가 상대적으로 어려워질 수 있고, 슬립폼 작업대로 철근 및 자재를 운송하는 작업과 간섭이 발생할 수 있다. 따라서, 수직구의 깊이가 상대적으로 깊은 경우에는 굴착면(3) 또는 돌출부(21) 상부에 고정된 인양브라켓(8, 9)에 인양장치를 설치하는 것이 바람직하다.When the lifting device is installed on the crane (6) equipment or on the horizontal beam (7), the length of the cable connecting the lifting device and the lifting hook becomes longer. Therefore, even when operating the hydraulic jack and the lifting device at the same time, Maintenance can be relatively difficult, and interference with the transport of rebar and materials to the slip form workbench can occur. Therefore, when the depth of the vertical sphere is relatively deep, it is preferable to install the lifting device on the lifting brackets 8 and 9 fixed on the excavation surface 3 or the protrusion 21.

인양브라켓(8, 9)은 도 9 및 도 10에 도시되어 있다. 인양브라켓(8, 9)은, 하나 또는 둘 이상의 조절공(84, 94)이 형성된 수평관체(81, 91)와 복수의 결합공(85, 95)이 형성되고 수평관체(81, 91)에 삽입되는 슬라이드체(82, 92)를 포함하여 구성되는데, 슬라이드체(82, 92)가 수평관체(81, 91)에 삽입된 후에 조절공(84, 94)과 결합공(85, 95)를 관통하여 볼트가 체결된 후에 너트를 결합하여 고정된다. 슬라이드체(82, 92)에 길이방향으로 복수의 결합공이 형성되어 있기 때문에 인양장치(44)와 연결된 케이블의 수직도를 유지하기가 용이하다. 인양브라켓(8, 9)은 수평관체의 보강을 위해 사선 방향으로 지지대(83, 93)를 더 구비할 수 있으며, 수평관체의 하부에도 보강부재를 더 구비할 수 있다. 본 발명은 슬라이드체가 수평관체에 삽입되는 것으로 설명하였으나, 슬라이드체 없이 수평관체를 강봉 형태로 구성할 수도 있다.The lifting brackets 8 and 9 are shown in FIGS. 9 and 10. The lifting brackets (8, 9) are horizontal pipe bodies (81, 91) in which one or more adjustment holes (84, 94) are formed and a plurality of coupling holes (85, 95) are formed, and the horizontal pipe bodies (81, 91) are Consisting of including slide bodies (82, 92) to be inserted, after the slide bodies (82, 92) are inserted into the horizontal pipe bodies (81, 91), the adjustment holes (84, 94) and the coupling holes (85, 95) After the bolt is fastened through it, the nut is combined and fixed. Since a plurality of coupling holes are formed in the slide bodies 82 and 92 in the longitudinal direction, it is easy to maintain the verticality of the cable connected to the lifting device 44. The lifting brackets 8 and 9 may further include supports 83 and 93 in an oblique direction for reinforcing the horizontal pipe, and a reinforcing member may be further provided at a lower portion of the horizontal pipe. Although the present invention has been described as being inserted into the horizontal pipe body, the horizontal pipe body without the slide body may be configured in the form of a steel bar.

인양브라켓을 굴착면(3) 또는 돌출부(21)에 설치하는 경우에는, 굴착면(3) 또는 돌출부(21)에 삽입한 앵커와 결합함으로써, 인양장치를 작동해서 슬립폼을 상승시키는 경우에도 하중을 충분히 지지할 수 있게 한다.When the lifting bracket is installed on the excavation surface (3) or the protrusion (21), it is combined with the anchor inserted into the excavation surface (3) or the protrusion (21), so that even when the lifting device is operated to raise the slip foam, the load To be fully supported.

본 발명의 슬립폼을 이용하여 수직구의 평면단면이 작아지는 부분을 갖는 수직구 시공방법을 설명한다.A method of constructing a vertical sphere having a portion in which the plane cross-section of the vertical sphere is reduced by using the slip foam of the present invention will be described.

먼저, 굴착공의 굴착이 완료되면 굴착공 저면에 바닥콘크리트(10)를 타설한다.First, when the excavation of the excavation hole is completed, the floor concrete 10 is poured on the bottom of the excavation hole.

다음으로, 거푸집을 설치한 후 현장타설 콘크리트를 타설함으로써, 돌출부(21)를 시공한다.Next, the protrusion 21 is constructed by placing the cast-in-place concrete after installing the formwork.

그 다음에는, 상기 돌출부(21)를 제외한 수직구 단면에 대응되는 평면형상으로 형성되며, 굴착면과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭(41)이 구비되고, 굴착면과 접하는 주면부 이외의 단부에는 하나 또는 둘 이상의 인양고리(42)가 구비된 주슬립폼(4)을 바닥콘크리트(10)의 상부에 안치시킨다.Next, it is formed in a planar shape corresponding to the cross section of the vertical sphere excluding the protrusion 21, and a plurality of hydraulic jacks 41 for lifting the slip foam are provided on the main surface in contact with the excavation surface, and the main surface in contact with the excavation surface At the ends other than the part, the main slip foam 4 provided with one or more lifting rings 42 is placed on the top of the concrete floor 10.

이후에는, 인양고리(42)에 케이블(45)을 결합하고 케이블의 다른 단부는 상부의 인양장치(44)와 연결한다. 도 7a 및 도 8a에는 주슬립폼(4)의 인양고리(42)와 상부의 인양장치(44)가 케이블(43)에 의해 연결되어 있는 상태가 도시되어 있다. Thereafter, the cable 45 is connected to the lifting ring 42 and the other end of the cable is connected to the lifting device 44 on the upper part. 7A and 8A illustrate a state in which the lifting ring 42 of the main slip foam 4 and the lifting device 44 on the upper part are connected by a cable 43.

이 때, 인양장치(44)는 굴착공 외부의 크레인(6) 또는 굴착공 입구를 가로지르는 수평보(7)에 설치될 수 있다. 이뿐만 아니라, 인양장치(44)는 굴착면에 고정된 인양브라켓(8) 또는 돌출부 상부에 고정된 인양브라켓(9) 중 어느 하나에 설치될 수 있다. 인양브라켓(8, 9)을 하나 또는 둘 이상의 조절공이 형성된 수평관체(81, 91)와 복수의 결합공이 형성되고 수평관체에 삽입되는 슬라이드체(82, 92)를 포함하여 구성하는 경우에는, 슬라이드체가 수평관체에 삽입되는 길이를 조절함으로써 케이블의 수직도를 조절할 수 있다.At this time, the lifting device 44 may be installed on a crane 6 outside the excavation hole or a horizontal beam 7 crossing the entrance of the excavation hole. In addition, the lifting device 44 may be installed on either the lifting bracket 8 fixed to the excavation surface or the lifting bracket 9 fixed to the upper portion of the protrusion. When the lifting brackets (8, 9) include horizontal pipe bodies (81, 91) having one or more adjustment holes formed therein, and slide bodies (82, 92) having a plurality of coupling holes formed and inserted into the horizontal pipe body, the slide The verticality of the cable can be adjusted by adjusting the length of the sieve inserted into the horizontal tube.

인양고리(42)와 인양장치(44)를 케이블(45)로 연결하고 나면, 유압잭(41)과 인양장치(44)를 동시에 작동시켜 평형을 유지하면서 주슬립폼을 상승시킨다. 주슬립폼이 상승되면서 돌출부가 구비된 수직구 구간의 벽체가 시공된다. 도 7b 및 도 8b에는 주슬립폼이 유압잭(41)과 인양장치(44)에 의해서 상승되면서 벽체가 시공되는 상태가 도시되어 있다.After connecting the lifting hook 42 and the lifting device 44 with the cable 45, the hydraulic jack 41 and the lifting device 44 are simultaneously operated to raise the main slip form while maintaining the balance. As the main slip foam rises, the wall of the vertical sphere section with protrusions is constructed. 7B and 8B illustrate a state in which the wall is constructed while the main slip foam is raised by the hydraulic jack 41 and the lifting device 44.

돌출부가 구비된 수직구 구간의 벽체가 시공되고 나면, 돌출부의 상부에서, 상기 돌출부에 대응되는 평면형상으로 형성되며, 굴착면(3)과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭(51)이 구비된 부슬립폼(5)을 하강시켜, 주슬립폼과 부슬립폼을 일체로 조립한다.After the wall of the vertical sphere section provided with the protrusion is constructed, it is formed in a planar shape corresponding to the protrusion at the upper part of the protrusion, and a plurality of hydraulic jacks 51 for lifting the slip foam on the main surface part in contact with the excavation surface 3 ) By lowering the provided sub-slip foam (5), and assemble the main and sub-slip foam integrally.

주슬립폼(4)과 부슬립폼(5)을 조립한 후에는, 인양고리(42)에 결합된 케이블(45)을 연결해제한다.After assembling the main slip foam 4 and the sub slip foam 5, the cable 45 coupled to the lifting ring 42 is disconnected.

그 다음에는 일체로 조립된 슬립폼을, 주면부에 구비된 유압잭(41, 51)에 의하여 상승시키면서 수직구의 벽체를 연속 시공한다. 도 7c, 7d 및 도 8c, 8d에는 일체로 조립된 슬립폼이 유압잭(41, 51)에 의하여 상승되면서 수직구의 벽체를 연속 시공하는 상태가 도시되어 있다.After that, while the integrally assembled slip foam is raised by hydraulic jacks 41 and 51 provided on the main surface, the wall of the vertical sphere is continuously constructed. Figures 7c, 7d and 8c, 8d shows a state in which the integrally assembled slip foam is raised by the hydraulic jacks 41 and 51 and the wall of the vertical sphere is continuously constructed.

이와 같이, 도면을 참조하여 본 발명의 바람직한 실시예에 대해 상술하였으나, 본 발명은 전술한 실시예에 한정되지 않는다. 특히, 본 발명의 실시예에 있어서는 수직구의 수평단면이 원형인 경우로 설명하였으나, 사각형 등의 형태인 경우에도 이 기술분야에서 통상의 지식을 가진 자라면 본 발명을 적용할 수 있을 것이다. As described above, a preferred embodiment of the present invention has been described above with reference to the drawings, but the present invention is not limited to the above-described embodiment. In particular, in the embodiment of the present invention, it has been described that the horizontal cross section of the vertical sphere is circular, but even in the case of a rectangular shape, any person skilled in the art can apply the present invention.

이처럼, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 사람이 본 발명의 사상을 벗어나지 않는 범위 내에서 변형 가능하며, 이러한 변형도 본 발명의 권리범위에 속할 것이다.As such, a person having ordinary knowledge in the technical field to which the present invention pertains can be modified within the scope of the present invention, and such modifications will also fall within the scope of the present invention.

본 발명은 내벽 안쪽에 돌출부가 형성되어 있어 평면단면이 작아지는 부분을 갖는 변단면 수직구 시공에 이용된다.The present invention is used in the construction of a side vertical sphere having a portion with a smaller planar cross-section because a protrusion is formed inside the inner wall.

1: 수직구 2: 수평연결터널
3: 굴착면 4: 주슬립폼
5: 부슬립폼 6: 크레인
7: 수평보 8: 굴착면에 고정된 인양브라켓
9: 돌출부 상부에 고정된 인양브라켓 10: 바닥콘크리트
1: vertical hole 2: horizontal connection tunnel
3: Excavation surface 4: Main slip foam
5: sub-slip form 6: crane
7: Leveling beam 8: Lifting bracket fixed to the excavation surface
9: Lifting bracket fixed on the upper part of the protrusion 10: Concrete floor

Claims (10)

삭제delete 내벽 안쪽에 돌출부가 형성되어 있어 평면단면이 작아지는 부분을 갖는 수직구 시공에 이용되는 슬립폼으로서,
상기 돌출부를 제외한 수직구 단면에 대응되는 평면형상으로 형성되며, 굴착면과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭이 구비되고, 굴착면과 접하는 주면부 이외의 단부에는 하나 또는 둘 이상의 인양고리가 구비되어 상부의 인양장치와 케이블에 의해 연결되며, 굴착면과 접하는 주면부 이외의 단부에는 수직구 평면단면이 확장되는 영역에서 부슬립폼과 결합하기 위한 결합부가 구비되는 주슬립폼;
상기 돌출부에 대응되는 평면형상으로 형성되며, 굴착면과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭이 구비되고, 굴착면과 접하는 주면부 이외의 단부에서 주슬립폼의 결합부와 연결되어 조립되는 부슬립폼;으로 구성되어,
주슬립폼과 부슬립폼이 조립결합되어 이루어지는 변단면 수직구 시공을 위한 슬립폼.
It is a slip foam used in the construction of vertical spheres having a small plane cross section due to the protrusion formed inside the inner wall.
It is formed in a planar shape corresponding to the cross section of the vertical sphere excluding the protrusion, and a plurality of hydraulic jacks for lifting the slip foam are provided on the main surface in contact with the excavation surface, and one or more lifts at the ends other than the main surface in contact with the excavation surface. A main slip foam provided with a ring and connected by a cable to the lifting device above, and having a coupling portion for coupling with the sub slip foam at an end portion other than the main surface portion in contact with the excavation surface in an area in which the vertical plane cross-section is extended;
It is formed in a planar shape corresponding to the protrusion, and a plurality of hydraulic jacks for lifting the slip foam are provided on the main surface portion in contact with the excavation surface, and the assembly is connected to the coupling portion of the main slip foam at an end other than the main surface portion in contact with the excavation surface. It consists of;
Slip foam for construction of vertical holes on the side of the cross section formed by assembling and combining the main and sub slip foams.
청구항 2에 있어서,
상기 인양장치는 굴착공 외부의 크레인 또는 굴착공 입구를 가로지르는 수평보 중 어느 하나에 설치되는 것을 특징으로 하는 변단면 수직구 시공을 위한 슬립폼.
The method according to claim 2,
The lifting device is a slip foam for construction of a vertical cross section, characterized in that it is installed on either a crane outside the excavation hole or a horizontal beam crossing the entrance of the excavation hole.
청구항 2에 있어서,
상기 인양장치는 굴착면에 고정된 인양브라켓 또는 돌출부 상부에 고정된 인양브라켓 중 어느 하나에 설치되는 것을 특징으로 하는 변단면 수직구 시공을 위한 슬립폼.
The method according to claim 2,
The lifting device is a slip foam for construction of a vertical cross section, characterized in that it is installed in either a lifting bracket fixed to the excavation surface or a lifting bracket fixed to the upper portion of the protrusion.
청구항 4에 있어서,
상기 인양브라켓은 하나 또는 둘 이상의 조절공이 형성된 수평관체;
복수의 결합공이 형성되고 상기 수평관체에 삽입되는 슬라이드체;
상기 수평관체의 조절공 및 상기 슬라이드체의 결합공을 관통 결합하여 수평관체와 슬라이드체를 고정하는 볼트 및 너트로 구성되어,
슬라이드체가 수평관체에 삽입되는 길이를 조절할 수 있도록 하는 것을 특징으로 하는 변단면 수직구 시공을 위한 슬립폼.
The method of claim 4,
The lifting bracket includes a horizontal tube having one or two or more adjustment holes;
A slide body having a plurality of coupling holes formed therein and inserted into the horizontal tube body;
Consisting of a bolt and a nut for fixing the horizontal pipe body and the slide body by penetrating the adjusting hole of the horizontal pipe body and the coupling hole of the slide body,
A slip foam for construction of a vertical cross section, characterized in that the length of the slide body inserted into the horizontal pipe body can be adjusted.
내벽 안쪽에 돌출부가 형성되어 있어 평면단면이 작아지는 부분을 갖는 수직구 시공방법으로서,
(1) 굴착공 저면에 바닥콘크리트를 타설하는 a 단계;
(2) 거푸집을 설치한 후 현장타설 콘크리트를 타설하여 돌출부를 시공하는 b 단계;
(3) 상기 돌출부를 제외한 수직구 단면에 대응되는 평면형상으로 형성되며, 굴착면과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭이 구비되고, 굴착면과 접하는 주면부 이외의 단부에는 하나 또는 둘 이상의 인양고리가 구비된 주슬립폼을 바닥콘크리트의 상부에 안치하는 c 단계;
(4) 인양고리에 케이블을 결합하고 상부의 인양장치와 연결하는 d 단계;
(5) 상기 유압잭과 인양장치가 동시에 작동하여 주슬립폼의 평형이 유지된 상태로 상승하면서 돌출부가 구비된 수직구를 형성하는 e 단계;
(6) 상기 돌출부의 상부에서, 상기 돌출부에 대응되는 평면형상으로 형성되며, 굴착면과 접하는 주면부에는 슬립폼 상승을 위한 복수의 유압잭이 구비되고, 굴착면과 접하는 주면부 이외의 단부에서 주슬립폼의 결합부와 연결되어 조립되는 부슬립폼을 하강시켜, 주슬립폼과 부슬립폼을 일체로 조립하는 f 단계;
(7) 주슬립폼의 인양고리에 결합된 케이블을 연결해제하는 g 단계;
(8) 일체로 조립된 슬립폼을 주슬립폼과 부슬립폼의 주면부에 구비된 유압잭에 의하여 상승시키면서 수직구를 형성하는 h 단계;를 포함하는 것을 특징으로 하는 변단면 수직구 시공방법.
This is a vertical sphere construction method with a portion that has a small plane cross-section due to the protrusion formed inside the inner wall.
(1) a step of pouring concrete floor on the bottom of the excavation hole;
(2) b step of constructing the protrusion by placing on-site concrete after installing the formwork;
(3) It is formed in a planar shape corresponding to the cross section of the vertical sphere excluding the protruding part, and a plurality of hydraulic jacks for lifting the slip foam are provided on the main surface in contact with the excavation surface, and one or more at the ends other than the main surface in contact with the excavation surface. Step c of placing the main slip foam provided with two or more lifting rings on the top of the concrete floor;
(4) step d of coupling the cable to the lifting ring and connecting it to the lifting device above;
(5) e step of forming a vertical sphere provided with a protrusion while the hydraulic jack and the lifting device are simultaneously operated to maintain the balance of the main slip form;
(6) At the top of the protrusion, it is formed in a planar shape corresponding to the protrusion, and a plurality of hydraulic jacks for lifting the slip foam are provided on the main surface part in contact with the excavation surface, and the main surface at the ends other than the main surface part in contact with the excavation surface. F step of assembling the main slip foam and the sub slip foam integrally by lowering the sub slip foam to be assembled by being connected to the coupling portion of the slip foam;
(7) step g of disconnecting the cable coupled to the lifting ring of the main slip foam;
(8) step h of forming a vertical sphere while raising the integrally assembled slip foam by a hydraulic jack provided on the main surface of the main and sub-slip foams; a vertical vertical ball construction method comprising a.
청구항 6에 있어서,
상기 d 단계는, 인양장치가 굴착공 외부의 크레인 또는 굴착공 입구를 가로지르는 수평보에 설치되는 것을 특징으로 하는 변단면 수직구 시공방법.
The method of claim 6,
In the step d, the lifting device is installed on a crane outside the excavation hole or a horizontal beam crossing the entrance of the excavation hole.
청구항 6에 있어서,
상기 d 단계는, 인양장치가 굴착면에 고정된 인양브라켓 또는 돌출부 상부에 고정된 인양브라켓 중 어느 하나에 설치되는 것을 특징으로 하는 변단면 수직구 시공방법.
The method of claim 6,
In the step d, the lifting device is installed on either a lifting bracket fixed to the excavation surface or a lifting bracket fixed on the upper part of the protrusion.
청구항 8에 있어서,
상기 인양브라켓은, 하나 또는 둘 이상의 조절공이 형성된 수평관체;
복수의 결합공이 형성되고 상기 수평관체에 삽입되는 슬라이드체;
상기 수평관체의 조절공 및 상기 슬라이드체의 결합공을 관통 결합하여 수평관체와 슬라이드체를 고정하는 볼트 및 너트로 구성되어,
슬라이드체가 수평관체에 삽입되는 길이를 조절함으로써 케이블의 수직도를 조절하는 단계를 포함하는 것을 특징으로 하는 변단면 수직구 시공방법.
The method of claim 8,
The lifting bracket may include a horizontal tube having one or two or more adjustment holes;
A slide body having a plurality of coupling holes formed therein and inserted into the horizontal tube body;
Consisting of a bolt and a nut for fixing the horizontal pipe body and the slide body by penetrating the adjusting hole of the horizontal pipe body and the coupling hole of the slide body,
A method of constructing a vertical cross section comprising the step of adjusting the verticality of the cable by adjusting a length in which the slide body is inserted into the horizontal pipe body.
삭제delete
KR1020200047141A 2020-04-20 2020-04-20 Slip form for the construction of a vertical shaft with varying cross-section and the construction method KR102146073B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200047141A KR102146073B1 (en) 2020-04-20 2020-04-20 Slip form for the construction of a vertical shaft with varying cross-section and the construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200047141A KR102146073B1 (en) 2020-04-20 2020-04-20 Slip form for the construction of a vertical shaft with varying cross-section and the construction method

Publications (1)

Publication Number Publication Date
KR102146073B1 true KR102146073B1 (en) 2020-08-19

Family

ID=72291681

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200047141A KR102146073B1 (en) 2020-04-20 2020-04-20 Slip form for the construction of a vertical shaft with varying cross-section and the construction method

Country Status (1)

Country Link
KR (1) KR102146073B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102228679B1 (en) * 2020-11-18 2021-03-15 노오순 Vertical hole construction system

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001193382A (en) * 2000-01-14 2001-07-17 Kawatetsu Kizai Kogyo Co Ltd Constructing method for shaft having wall with varied thickness
KR100913381B1 (en) 2007-11-08 2009-08-26 주식회사 형주엔지니어링 Slip form for concrete lining of shaft tunnel and method constructing concrete lining of shaft tunnel
KR101679180B1 (en) 2016-04-28 2016-11-24 주식회사 네오시티 Method for constructing concrete lining of ventilation shaft tunnel
KR101737193B1 (en) 2015-01-02 2017-05-18 고엄식 Vertical tunnel construction and constructing method for the same
KR20180046064A (en) * 2016-10-27 2018-05-08 (주)세니츠코퍼레이션 Reinforcement and waterproof structure of vertical shafts-utility tunnels interface
KR200489266Y1 (en) * 2018-04-27 2019-05-23 김수학 Chain block mounting structure for opening and closing valve chamber
KR102001526B1 (en) 2018-11-06 2019-07-19 주식회사 네오시티 Vertical Ball Squeezing Device for Top-Down Method and Vertical Ball Squeezing Method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001193382A (en) * 2000-01-14 2001-07-17 Kawatetsu Kizai Kogyo Co Ltd Constructing method for shaft having wall with varied thickness
KR100913381B1 (en) 2007-11-08 2009-08-26 주식회사 형주엔지니어링 Slip form for concrete lining of shaft tunnel and method constructing concrete lining of shaft tunnel
KR101737193B1 (en) 2015-01-02 2017-05-18 고엄식 Vertical tunnel construction and constructing method for the same
KR101679180B1 (en) 2016-04-28 2016-11-24 주식회사 네오시티 Method for constructing concrete lining of ventilation shaft tunnel
KR20180046064A (en) * 2016-10-27 2018-05-08 (주)세니츠코퍼레이션 Reinforcement and waterproof structure of vertical shafts-utility tunnels interface
KR200489266Y1 (en) * 2018-04-27 2019-05-23 김수학 Chain block mounting structure for opening and closing valve chamber
KR102001526B1 (en) 2018-11-06 2019-07-19 주식회사 네오시티 Vertical Ball Squeezing Device for Top-Down Method and Vertical Ball Squeezing Method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102228679B1 (en) * 2020-11-18 2021-03-15 노오순 Vertical hole construction system

Similar Documents

Publication Publication Date Title
KR101034398B1 (en) Land-side protection wall that use ground structure
JP3644605B2 (en) Reverse driving method of underground structure under road surface.
KR20120096605A (en) Bracket support type downward construction system and method
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR102146073B1 (en) Slip form for the construction of a vertical shaft with varying cross-section and the construction method
KR101187170B1 (en) Application of under pinning method in remodeling
KR200388758Y1 (en) fixing anchor structure for tower crane
KR101383817B1 (en) Top down method
KR100650134B1 (en) Early remove support method
JP6387778B2 (en) Suspension jig used when building the core material of the underground continuous wall, the method of building the core material of the underground continuous wall, and the system for building the core material of the underground continuous wall
KR20210090100A (en) In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
JP5027752B2 (en) Construction method of underground floor pillar and underground floor pillar
JP3644606B2 (en) Installation method of formwork support in reverse placement method
RU2123091C1 (en) Foundation for metal column, method of foundation construction and alignment
JP4504747B2 (en) Building construction method using tower crane
JP2011089320A (en) Method for constructing precast basement column
EP1792019B1 (en) Method of raising a building structure, in particular a building structure subject to flooding
KR20210098162A (en) Under ground structure using column steel pipe wall and construction method thereof
KR100679986B1 (en) Structure for plastic slab deck system and Downward construction method using the same
JP7275793B2 (en) Position adjusting device and method for adjusting position of structural column
KR101239899B1 (en) Structures and production methods column mesh of slurry wall and construction method using a column mesh of slurry wall
KR100593203B1 (en) a deck supportframe and a construction methed
KR100227537B1 (en) Process for hanging concrete large slab forms
KR102330771B1 (en) Top-down construction method using bracket and double girder
KR102108622B1 (en) Support structure of temporary strut for construction period reduction

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant