KR101737193B1 - Vertical tunnel construction and constructing method for the same - Google Patents

Vertical tunnel construction and constructing method for the same Download PDF

Info

Publication number
KR101737193B1
KR101737193B1 KR1020150000024A KR20150000024A KR101737193B1 KR 101737193 B1 KR101737193 B1 KR 101737193B1 KR 1020150000024 A KR1020150000024 A KR 1020150000024A KR 20150000024 A KR20150000024 A KR 20150000024A KR 101737193 B1 KR101737193 B1 KR 101737193B1
Authority
KR
South Korea
Prior art keywords
vertical
wall
passage
installing
vertical passage
Prior art date
Application number
KR1020150000024A
Other languages
Korean (ko)
Other versions
KR20160083659A (en
Inventor
고엄식
Original Assignee
고엄식
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 고엄식 filed Critical 고엄식
Priority to KR1020150000024A priority Critical patent/KR101737193B1/en
Publication of KR20160083659A publication Critical patent/KR20160083659A/en
Application granted granted Critical
Publication of KR101737193B1 publication Critical patent/KR101737193B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D3/00Wind motors with rotation axis substantially perpendicular to the air flow entering the rotor 
    • F03D3/06Rotors
    • F03D3/061Rotors characterised by their aerodynamic shape, e.g. aerofoil profiles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D3/00Wind motors with rotation axis substantially perpendicular to the air flow entering the rotor 
    • F03D3/06Rotors
    • F03D3/062Rotors characterised by their construction elements
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/20Rotors
    • F05B2240/21Rotors for wind turbines
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/20Rotors
    • F05B2240/21Rotors for wind turbines
    • F05B2240/221Rotors for wind turbines with horizontal axis
    • F05B2240/2212Rotors for wind turbines with horizontal axis perpendicular to wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/74Wind turbines with rotation axis perpendicular to the wind direction

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Sustainable Development (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Combustion & Propulsion (AREA)
  • Sustainable Energy (AREA)
  • Architecture (AREA)
  • Fluid Mechanics (AREA)
  • Physics & Mathematics (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

본 발명은 지하에 건설되는 수직터널 구조물 및 그 시공방법에 관한 것으로서, 보다 상세하게는 환풍로와 대피로 시설이 구비된 수직터널 구조물 및 그 시공방법에 관한 것이다.
본 발명의 수직터널 구조물은 지하시설물의 연결터널(4)과 연결되도록 굴착된 수직공(1)의 내벽면을 이루는 원형벽체(10)와, 상기 원형벽체를 수직의 대피로(3)와 환기로(2)로 구획하는 수직벽체(20)와, 상기 대피로의 내부에 수직벽체(20)를 이용하여 수직공의 바닥에서 지상까지 형성된 수직통로(30)와, 상기 수직통로의 내부에 설치된 대피용 계단(40)과, 수직벽체의 하단에 형성된 수직통로 출입구(50)와, 상기 수직공에서 발생되는 지하수를 저장할 수 있도록 수직공의 바닥과 최하층의 프리캐스트 슬라브와의 사이에 형성된 공간부로 이루어진 집수조(90)를 포함하여 구성된다.
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a vertical tunnel structure constructed in a basement and a construction method thereof, and more particularly, to a vertical tunnel structure including an air passage and an escape route, and a construction method thereof.
The vertical tunnel structure of the present invention comprises a circular wall 10 constituting an inner wall surface of a straight hole 1 excavated so as to be connected to a connection tunnel 4 of an underground facility, A vertical passage 30 formed in the inside of the evacuation passage to the ground from the bottom of the vertical hole by using the vertical wall body 20; A vertical passage entrance 50 formed at the lower end of the vertical wall, and a space formed between the bottom of the horizontal hole and the precast slab in the lowermost layer so as to store groundwater generated in the vertical hole, And a water collecting tank (90).

Description

수직터널 구조물 및 그 시공방법{Vertical tunnel construction and constructing method for the same}TECHNICAL FIELD [0001] The present invention relates to a vertical tunnel structure and a construction method thereof,

본 발명은 지하에 건설되는 수직터널 구조물 및 그 시공방법에 관한 것으로서, 보다 상세하게는 환풍로와 대피로 시설이 구비된 수직터널 구조물 및 그 시공방법에 관한 것이다.BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a vertical tunnel structure constructed in a basement and a construction method thereof, and more particularly, to a vertical tunnel structure including an air passage and an escape route, and a construction method thereof.

일반적으로 지하철 선로 공사시 열차의 운행시 발생되는 바람에 포함된 각종 유해가스 및 미세먼지로 인하여 지하터널 및 승강장의 공기가 오염되는 것을 방지하기 위하여 각 전철역을 비롯하여 지하선로를 따라 일정구간 마다 지하터널 및 승강장내의 공기를 지상으로 배출시키거나 지상의 공기를 지하터널 및 승강장 내로 공급할 수 있는 통로역할을 하는 수직터널 구조물을 필수적으로 갖추도록 되어 있다.Generally, in order to prevent pollution of air in underground tunnels and platforms due to various harmful gases and fine dust contained in wind generated when a train is operated on subway lines, underground tunnels And a vertical tunnel structure serving as a passage for discharging the air in the platform to the ground or supplying the ground air into the underground tunnel and the platform.

이와 같은 수직터널 구조물의 시공은 지상에서 지하로 수직공을 굴착하고 수직공의 내주면에 철구조물을 설치하거나 콘크리트 몰탈을 타설하여 수직터널 구조물가 붕괴되지 않도록 한 다음, 수직공의 바닥에서부터 철근을 배열하여 거푸집을 설치하고 기초콘크리트를 타설한 후에 기초콘크리트의 양생이 완료되면 거푸집을 해체한 후에 지상으로부터 폐자재를 수거하여 그 시공을 완료한다.The construction of such a vertical tunnel structure is carried out by excavating a horizontal tunnel from the ground to the ground, installing a steel structure on the inner surface of the tunnel, or preventing the vertical tunnel structure from collapsing by placing a concrete mortar, After the mold is laid and the foundation concrete is cured, once the curing of the foundation concrete is completed, the mold is dismantled and the waste material is collected from the ground and the construction is completed.

그러나, 종래와 같은 수직터널 구조물의 시공방법은 거푸집이 지지할 수 있는 기초콘크리트의 무게에 한계가 있기 때문에 1회 시공할 수 있는 높이가 일정높이(4m 내지 5m 정도) 이하로 제한된다.However, since the conventional concrete tunnel construction method has a limitation on the weight of the foundation concrete that can be supported by the form, the height at which the concrete can be constructed once is limited to a certain height (about 4m to 5m).

따라서, 수직터널 구조물의 바닥에서 출구까지 다수 회에 걸쳐 거푸집의 설치, 기초콘크리트의 타설/양생 및 거푸집의 해체를 반복해야 하므로 시공 기간과 비용이 과다하게 소요될 뿐만 아니라 이음부의 발생으로 누수와 같은 위험성이 상존한다는 문제가 있다.Therefore, it is necessary to repeat the installation of the formwork from the bottom to the exit of the vertical tunnel structure, the installation / curing of the foundation concrete, and the dismantling of the formwork, so that the construction period and cost are excessively required, There is a problem that it exists.

최근에는 상기와 같은 수직터널 구조물 내부에 화재와 같은 재난발생시 이용객들의 수직터널 구조물를 이용하여 신속하게 대피할 수 있도록 수직터널 구조물 내부에 대피용 계단을 설치하여 기능성을 부여한 형태로의 시공도 이루어지고 있으나, 상기 대피용 계단이 개방된 구조이므로 화재 대피시 대피자들이 지상까지 도달하는 장시간 동안 수직터널 구조물를 통해 외부로 배출되는 연기와 유독가스들에 그대로 노출되어 실질적인 대피로로서의 기능을 수행할 수 없는 실정이다.In recent years, in order to quickly evacuate a vertical tunnel structure of a user in the event of a disaster such as a fire in the above-mentioned vertical tunnel structure, a step for evacuation has been installed inside the vertical tunnel structure to impart functionality to the tunnel structure , Because the stairway for evacuation is open, it is exposed to the smoke and toxic gases discharged to the outside through the vertical tunnel structure for a long time when the evacuees reach the ground when evacuating the fire, so that they can not function as a practical evacuation route. to be.

본 발명은 상기한 문제점들을 해결하기 위해 안출된 것으로서, 시공기간과 예산을 적게 소요하면서 재난 발생시 승객들의 안전한 대피로로서의 기능을 수행할 수 있는 수직터널 구조물 및 그 시공방법을 제공하는데 그 목적이 있다.SUMMARY OF THE INVENTION It is an object of the present invention to provide a vertical tunnel structure and a method of constructing the same that can perform a function as a safe evacuation route for passengers in the event of a disaster, .

상기 목적을 달성하기 위해, 본 발명의 수직터널 구조물은 지하시설물의 연결터널과 연결되도록 굴착된 수직공의 내벽면을 이루는 원형벽체와, 상기 원형벽체를 수직의 대피로와 환기로로 구획하는 수직벽체와, 상기 대피로 내부에 수직벽체를 이용하여 수직공의 바닥에서 지상까지 형성된 수직통로와, 상기 수직통로 내부에 설치된 대피용 계단과, 수직벽체의 하단에 형성된 수직통로 출입구와, 상기 수직공에서 발생되는 지하수를 저장할 수 있도록 수직공의 바닥과 최하층의 프리캐스트 슬라브와의 사이에 형성된 공간부로 이루어진 집수조를 포함하여 구성됨을 특징으로 한다.In order to achieve the above object, the vertical tunnel structure of the present invention comprises a circular wall constituting an inner wall surface of a through hole excavated to be connected to a connection tunnel of an underground facility, and a vertical wall separating the circular wall into a vertical evacuation path and a vent path A vertical passage formed from the floor to the ground using a vertical wall inside the evacuation passage; a step for evacuation provided inside the vertical passage; a vertical passage entrance formed at the lower end of the vertical wall; And a space formed between the floor of the watercraft and the lowest precast slab so as to store groundwater generated in the watercourse.

또한, 상기 대피로에는 각각의 층을 이루도록 수직통로가 관통하는 프리캐스트 슬라브가 일정 높이 간격으로 설치될 수 있다.In addition, the pre-cast slabs through which the vertical passages penetrate to form the respective layers may be installed at predetermined intervals.

이 경우, 상기 수직통로의 외측에는 상기 프리캐스트 슬라브들을 차례로 관통하면서 대피로의 바닥에서 지상까지를 연결하는 엘리베이터 설치통로가 설치되며, 상기 수직통로와 상기 엘리베이터 설치통로에는 각층마다 대피로로 통하는 출입구가 형성되는 것이 바람직하다.In this case, an elevator installation passage is formed on the outer side of the vertical passage for connecting the pre-cast slabs sequentially from the floor to the ground of the evacuation route, and the vertical passage and the elevator installation passage are provided with an entrance Is formed.

또한, 상기 집수조와 최하층 슬라브 사이에 기계실로 활용할 수 있는 공간부를 형성하는 보조슬라브가 더 설치될 수 있다.Further, auxiliary slabs may be further provided between the water collecting tank and the lowermost slab to form a space that can be used as a machine room.

삭제delete

한편, 상기 지하시설물의 연결터널을 상하로 구획하는 수평벽체와 수직벽체를 연결하는 연결벽체를 더 구비할 수도 있다.It is also possible to further include a connection wall connecting the vertical wall and the horizontal wall separating the connection tunnel of the underground facility.

그리고, 본 발명의 수직터널 구조물의 시공방법은 수직공 굴착단계와, 수직공의 바닥에 기초 콘크리트가 타설되는 단계와, 수직공의 내부에 슬립폼 작업대가 가설되는 단계와, 굴착된 수직공의 내벽면을 이루는 원형벽체와 상기 수직공을 수직의 대피로와 환기로로 구획하는 수직벽체와 수직벽체로부터 대피로를 향해 일정간격을 두고 연장되는 수직통로의 측벽체를 이루는 철근 콘크리트 구조물들이 설치되는 단계와, 상기 슬립폼 작업대가 상승하면서 상기 철근 콘크리트 구조물들에 원형벽체와 수직벽체와 수직통로의 측벽체들이 연속적으로 타설되는 단계와, 프리캐스트로 제작된 수직통로 전면벽체가 완성된 수직통로의 측벽체에 조립되면서 수직통로가 완성되는 단계와, 완성된 수직통로 내부에 대피용 계단이 조립되는 단계를 포함하여 구성됨을 특징으로 한다.The method for constructing the vertical tunnel structure according to the present invention includes a step of drilling a vertical hole, a step of placing a foundation concrete on the floor of the horizontal hole, a step of installing a slip foam workbench in the interior of the horizontal hole, A reinforced concrete structure constituting a sidewall of a circular wall constituting an inner wall of the vertical wall, a vertical wall partitioning the vertical wall into a vertical escape route and a ventilation passage, and a vertical passage extending from the vertical wall at a predetermined interval toward the escape route are installed A step of continuously inserting the sidewalls of the vertical walls and the vertical passages into the reinforced concrete structures while the slipform workbench is elevated; A step of completing the vertical passage while being assembled to the side wall, and a step of assembling the step for escape inside the completed vertical passage, The features.

삭제delete

그리고 본 발명의 수직터널 구조물의 시공방법은 수직공 굴착단계와, 수직공의 바닥에 기초 콘크리트가 타설되는 단계와, 수직공의 내부에 슬립폼 작업대가 가설되는 단계와, 굴착된 수직공의 내벽면을 이루는 원형벽체와 상기 수직공을 수직의 대피로와 환기로로 구획하는 수직벽체를 이루는 철근 콘크리트 구조물들이 설치되는 단계와, 상기 슬립폼 작업대가 상승하면서 상기 철근 콘크리트 구조물들에 원형벽체와 수직벽체가 연속적으로 타설되는 단계와, 프리캐스트로 제작된 수직통로가 완성된 수직벽체에 조립되는 단계와, 완성된 수직통로 내부에 대피용 계단이 조립되는 단계를 포함하여 구성됨을 특징으로 한다.The method for constructing the vertical tunnel structure according to the present invention comprises the steps of drilling a vertical hole, placing the base concrete on the floor of the horizontal hole, installing a slip foam workbench in the interior of the horizontal hole, A step of installing reinforced concrete structures constituting a vertical wall constituting a vertical wall and a circular wall wall constituting the wall and a vertical escape route and a ventilating passage of the horizontal wall; A step in which the wall is continuously inserted; a step of assembling the pre-cast vertical passageway into the completed vertical wall; and a step of assembling a step for evacuation in the completed vertical passageway.

이 경우, 상기 수직공의 내부에 슬립폼 작업대가 가설되는 단계 이후에 수직공 바닥에 집수조가 설치되는 단계를 더 거치며, 상기 집수조가 설치되는 단계는 굴착된 수직공의 바닥에 수직공의 내벽면을 이루는 원형벽체를 이루는 철근 콘크리트 구조물들이 설치되는 단계와 상기 슬립폼 작업대가 상승하면서 상기 철근 콘크리트 구조물들에 원형벽체가 연속적으로 타설되는 단계와 상기 원형벽체에 일정 높이로 프리캐스트 슬라브 지지용 브라켓들이 설치되는 단계와, 프리캐스트 슬라브가 상기 프리캐스트 슬라브 지지용 브라켓들을 통해 조립되는 단계로 구성될 수 있다.In this case, the step of installing the slip-foam workbench in the inside of the through hole may further include a step of installing a water collecting tank on the bottom of the water hole, wherein the step of installing the water collecting tank includes: Wherein the reinforcing concrete structures are continuously installed while the slip foam workbench is elevated and the reinforcing concrete structures are continuously installed in the reinforcing concrete structures, and a step in which the pre-cast slab supporting brackets And a step in which the precast slab is assembled through the precast slab supporting brackets.

또한, 상기 원형벽체와 수직벽체와 수직통로에는 일정 높이 간격마다 프리캐스트 슬라브 지지용 브라켓들이 설치되고, 완성된 수직통로 내부에 대피용 계단이 설치되는 단계 이전에 프리캐스트 슬라브가 상기 프리캐스트 슬라브 지지용 브라켓들을 통해 조립될 수도 있다.In addition, the pre-cast slab supporting brackets are installed at a predetermined height interval in the circular wall, the vertical wall, and the vertical passage, and the pre-cast slab is installed in the pre- And may be assembled through the brackets.

아울러, 수직통로의 내측에는 대피용 계단 지지용 브라켓들이 설치되며, 상기 완성된 수직통로 내부에 대피용 계단이 설치되는 단계에서 상기 대피용 계단은 상기 대피용 계단 지지용 브라켓에 조립되는 프리캐스트로 제작된 슬라브형 조립식 계단일 수 있다.In addition, the step for supporting the step for supporting the escape is provided on the inner side of the vertical passage, and the step for escape is installed in the completed vertical passage, It may be a slab-type prefabricated staircase manufactured.

또한, 수직통로의 내측에는 대피용 계단 지지용 브라켓들이 설치되며, 상기 완성된 수직통로 내부에 대피용 계단이 설치되는 단계에서 상기 대피용 계단은 상기 대피용 계단 지지용 브라켓에 조립되는 조립식 철재 계단일 수도 있다.In addition, in the step of installing the step for escape inside the completed vertical passage, the step for escape is provided on the inner side of the vertical passage, the step for supporting the step for supporting the escape is provided, Lt; / RTI >

한편, 상기 완성된 수직통로 내부에 대피용 계단이 조립되는 단계 이전에 수직통로의 외측에 일정높이 단위로 제작된 프리캐스트로 제작된 엘리베이터 설치통로가 조립될 수도 있다.Meanwhile, the pre-cast elevator installation passageway may be assembled at a predetermined height unit outside the vertical passageway before the step of assembling the escape step inside the completed vertical passageway.

아울러, 상기 철근 콘크리트 구조물들이 설치되는 단계에서 엘리베이터 설치통로를 이루는 철근 콘크리트 구조물이 함께 설치되고, 슬립폼 작업대가 상승하면서 엘리베이터 설치통로도 함께 타설되도록 할 수도 있다.In addition, when the reinforced concrete structures are installed, a reinforced concrete structure constituting an elevator installation passage is installed together, and the elevator installation passage may be installed together with the slip foam work platform.

한편, 상기 원형벽체를 이루는 철근 콘크리트 구조물들이 설치되는 단계에서, 상기 수직공의 바닥에는 슬립폼 작업대를 승강시키기 위한 잭로드가 내벽면을 따라 일정간격으로 설치되며, 지하시설물의 연결터널 전면에 설치되는 잭로드들에 한하여 외측에 수직강도 보강용 지지관이 결합되는 것이 바람직하다.Meanwhile, at the stage where the reinforced concrete structures constituting the circular wall are installed, jack rods for lifting and lowering the slip foam workbench are installed at the bottom of the through holes at regular intervals along the inner wall surface, It is preferable that the vertical strength reinforcing supporting pipe is coupled to the outer side of the jack rods.

또한, 수직공의 내부에 슬립폼 작업대가 가설되는 단계에서 상기 슬립폼 작업대의 상단에 설치된 보조작업대를 통해 수직공에 가설된 철골구조물들의 해체작업 및 방수포 부착작업이 수행될 수 있다.Further, in the step of installing the slip foam workbench in the inside of the weir, the disassembly operation of the steel structure and the work of attaching the waterproof foam can be performed through the auxiliary workbench provided at the upper end of the slip foam workbench.

상기와 같이 구성된 본 발명은 평상시에는 환기로를 통해 지하시설물에 대한 환기가 이루어지게 되며, 지하시설물에 화재와 같은 긴급대피 상황이 발생할 경우 다수의 지하시설물 이용자들은 연결터널을 통해 대피로로 이동한 후에 수직통로 내에 마련된 슬라브계단을 타고 지상으로 신속하고 안전하게 대피할 수 있게 된다. 이때, 화재로 발생되는 대부분의 연기와 유독가스는 연결터널의 상부로 모이면서 환기로를 통해 지상으로 배출되며, 슬라브계단은 수직통로 내부에 설치되어 외부와 격리되어 있기 때문에 대피중인 지하시설물 이용자들은 연기와 유독가스에 노출되지 않고 신속하고 안전하게 지상으로 대피할 수 있게 되는 효과가 있다.According to the present invention configured as described above, the underground facility is ventilated through a ventilation path at a normal time, and when an emergency evacuation situation occurs such as a fire in an underground facility, a large number of underground facility users move to the escape route through a connection tunnel It is possible to quickly and safely evacuate to the ground on the slab step provided in the vertical passage. Most of the smoke and toxic gases generated by the fire are collected at the top of the connecting tunnel and discharged to the ground through the ventilation duct. Since the slab staircase is installed inside the vertical passage and isolated from the outside, It is possible to quickly and safely evacuate to the ground without being exposed to smoke and toxic gas.

또한, 본 발명은 수직터널 구조물의 시공이 슬립폼 작업대를 통해 연속적으로 이루어질 뿐 아니라, 수직통로의 전면벽체나 슬라브 또는 대피용 계단과 같은 구조물들을 프리캐스트 조립방식으로 설치하므로 시공기간과 비용을 크게 절감할 수 있는 효과가 있다.In addition, since the construction of the vertical tunnel structure is continuously performed through the slipform workbench, and the structures such as the front wall, the slab, and the escape staircase of the vertical passage are installed by the precast assembly method, There is an effect that can be saved.

도 1은 본 발명에 따른 수직터널 구조물의 평면도.
도 2는 도 1의 Ⅱ-Ⅱ선에 따른 수직터널 구조물의 정단면도.
도 3은 도 1의 Ⅲ-Ⅲ선에 따른 수직터널 구조물의 측단면도.
도 4는 도 1의 Ⅲ-Ⅲ선에 따른 단면도로서 집수조가 설치된 상태를 나타내는 도면.
도 5 내지 도 7은 본 발명에 따른 수직터널 구조물의 시공방법을 순서대로 나타내는 도면.
도 8은 본 발명의 지하시설물의 연결터널 전면에 설치되는 잭로드들에 한하여 외측에 수직강도 보강용 지지관이 결합된 상태를 나타내는 도면.
도 9는 본 발명의 프리캐스트 수직통로 전면벽체가 수직통로의 측벽체에 조립된 상태를 나타내는 평면도
도 10은 도 9의 Ⅹ-Ⅹ선에 따른 단면도.
도 11은 본 발명의 수직통로 전면벽체의 외측에 엘리베이터 설치통로가 설치된 상태를 나타내는 평면도.
도 12는 도 11의 XII-XII선에 따른 단면도.
1 is a plan view of a vertical tunnel structure according to the present invention;
2 is a front cross-sectional view of a vertical tunnel structure taken along the line II-II in FIG.
3 is a side cross-sectional view of a vertical tunnel structure taken along the line III-III in FIG.
Fig. 4 is a sectional view taken along the line III-III in Fig. 1, showing a state in which a water collecting tank is installed. Fig.
FIGS. 5 to 7 are views sequentially illustrating a method of constructing a vertical tunnel structure according to the present invention. FIG.
8 is a view showing a state in which a vertical strength reinforcing supporting pipe is coupled to an outer side only of jack rods installed on the entire connection tunnel of an underground facility of the present invention.
9 is a plan view showing a state in which the precast vertical passage front wall of the present invention is assembled to a side wall of a vertical passage;
10 is a cross-sectional view taken along the line X-X in Fig.
11 is a plan view showing a state in which an elevator installation passage is installed outside the vertical passage front wall of the present invention.
12 is a sectional view taken along the line XII-XII in Fig.

본 발명의 특징 및 이점들은 첨부도면에 의거한 다음의 바람직한 실시예에 대한 상세한 설명으로 더욱 명백해질 것이다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 발명자가 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.The features and advantages of the present invention will become more apparent from the following detailed description of preferred embodiments with reference to the accompanying drawings. Prior to this, terms and words used in the present specification and claims are to be interpreted in accordance with the technical idea of the present invention based on the principle that the inventor can properly define the concept of the term in order to explain his invention in the best way. It must be interpreted in terms of meaning and concept.

이하, 본 발명의 일 실시예를 도면을 참조하여 상세히 설명함에 있어, 동일한 구성에 대해서는 동일한 부호를 사용하며, 명료성을 위하여 가능한 중복되지 않게 상이한 부분만을 주로 설명한다.Hereinafter, one embodiment of the present invention will be described in detail with reference to the drawings. The same reference numerals are used for the same components, and only the different portions are described for the sake of clarity.

도 1 내지 도 3에 도시된 바와 같이, 본 발명의 수직터널 구조물은 지하시설물의 연결터널(4)과 연결되도록 굴착된 수직공(1)의 내벽면을 이루는 원형벽체(10)와, 상기 원형벽체(10)를 수직의 대피로(3)와 환기로(2)로 구획하는 수직벽체(20)와, 상기 대피로(3) 내부에 수직벽체(20)를 이용하여 수직공(1)의 바닥에서 지상까지 형성된 수직통로(30)와, 상기 수직통로(30) 내부에 설치된 대피용 계단(40)과, 수직벽체(20)의 하단에 형성된 수직통로 출입구(50)를 포함하여 구성된다.1 to 3, the vertical tunnel structure according to the present invention includes a circular wall 10 constituting an inner wall surface of a straight hole 1 excavated to be connected to a connection tunnel 4 of an underground facility, A vertical wall body 20 for partitioning the wall 10 into a vertical escape path 3 and a ventilation path 2 and a vertical wall body 20 in which the vertical wall 20 is used inside the escape path 3, A vertical passage 30 formed from the floor to the ground, a step 40 for escape provided inside the vertical passage 30 and a vertical passage entrance 50 formed at the lower end of the vertical wall 20.

상기 지하시설물의 연결터널(4)을 상하로 구획하는 수평벽체(4a)와 수직벽체(20)를 연결하는 연결벽체(60)를 설치하여 대피로(3)와 환기로(2)가 연결터널(4)에서부터 각각 분리된 유로를 형성하도록 하는 것이 바람직하다.A horizontal wall 4a for vertically dividing the connection tunnel 4 of the underground facility and a connection wall 60 for connecting the vertical wall 20 are provided so that the escape route 3 and the ventilation route 2 are connected to each other by a connection tunnel It is preferable to form the flow paths separately from the flow paths 4.

그리고 상기 대피로(3)에는 각각의 층을 이루도록 수직통로(30)가 관통하는 슬라브(70)가 일정 높이 간격으로 설치될 수 있다.The slabs 70, through which the vertical passages 30 pass, may be installed at the predetermined intervals in the evacuation route 3.

아울러, 도 11 및 도 12에 도시된 바와 같이, 상기 수직통로(30)의 외측에는 상기 슬라브(70)들을 차례로 관통하면서 대피로(3)의 바닥에서 지상까지를 연결하는 엘리베이터 설치통로(80)가 설치될 수도 있다. 상기 엘리베이터 설치통로(80)에 설치되는 엘리베이터는 평상시에는 관리자의 이동수단으로 이용되며 지하시설물에 화재와 같은 긴급대피 상황이 발생한 경우 다수의 지하시설물 이용자들이 지상으로 탈출할 수 있는 수단으로 활용된다. 이 경우, 상기 수직통로(30) 및 엘리베이터 설치통로(80)에는 각 층마다 대피로(3)로 통하는 출입구가 형성되어야 함은 물론이다.11 and 12, an elevator installation passage 80 is formed on the outer side of the vertical passage 30 to sequentially connect the slabs 70 and connect the floor of the escape route 3 to the ground, May be installed. The elevator installed in the elevator installation passage 80 is normally used as a moving means of an administrator. When an emergency evacuation situation such as a fire occurs in an underground facility, a plurality of users of the underground facility can utilize it as a means of escaping to the ground. In this case, it is needless to say that the vertical passage 30 and the elevator installation passage 80 are provided with entrances through the escape route 3 for each floor.

한편, 도 4에 도시된 바와 같이, 상기 수직공(1)의 바닥에는 수직공(1)으로부터 발생되는 지하수를 저장할 수 있는 집수조(90)가 설치될 수도 있다. 이 경우 상기 집수조(90)는 수직공(1)의 바닥과 최하층의 슬라브(71)와의 사이에 형성된 공간부가 된다.Meanwhile, as shown in FIG. 4, a water collecting tank 90, which can store groundwater generated from the water hole 1, may be installed on the bottom of the water hole 1. In this case, the water collecting tank (90) is a space formed between the bottom of the water hole (1) and the slab (71) of the lowest layer.

아울러, 집수조(90)와 최하층 슬라브(71) 사이에 보조 슬라브(72)를 더 설치하여 보조 슬라브(72)와 집수조(90) 사이의 공간을 기계실(91)로 활용할 수도 있다.The auxiliary slab 72 may be further provided between the water collecting tank 90 and the lowermost slab 71 to utilize the space between the auxiliary slab 72 and the water collecting tank 90 as the machine room 91.

이와 같이 수직터널 구조물은 평상시에는 환기로(2)를 통해 지하시설물에 대한 환기가 이루어지게 되며, 지하시설물에 화재와 같은 긴급대피 상황이 발생할 경우 다수의 지하시설물 이용자들은 연결터널(4)을 통해 대피로(3)로 이동한 후에 수직통로(30) 내에 마련된 대피용 계단(40)을 타고 지상으로 신속하고 안전하게 대피할 수 있게 된다. 이때, 화재로 발생되는 대부분의 연기와 유독가스는 연결터널(4)의 상부로 모이면서 환기로(2)를 통해 지상으로 배출되며, 대피용 계단(40)은 수직통로(30) 내부에 설치되어 외부와 격리되어 있기 때문에 대피용 계단(40)을 이용 중인 대피중인 지하시설물 이용자들은 연기와 유독가스에 노출되지 않고 신속하고 안전하게 지상으로 대피할 수 있게 된다.As such, the vertical tunnel structure is normally ventilated to the underground facility through the ventilation path 2. When an emergency evacuation situation occurs such as a fire in the underground facility, a large number of users of the underground facility pass through the connection tunnel 4 It is possible to quickly and safely evacuate to the ground on the escape stairway 40 provided in the vertical passage 30 after moving to the escape route 3. At this time, most of the smoke and noxious gas generated in the fire are collected on the upper part of the connection tunnel 4 and discharged to the ground through the ventilation path 2. The escape step 40 is installed inside the vertical passage 30 The user is able to evacuate to the ground quickly and safely without being exposed to smoke and toxic gases.

이하, 본 발명에 따른 수직터널 구조물의 시공방법을 첨부도면에 도시한 실시예에 따라서 상세히 설명한다.Hereinafter, a method of constructing a vertical tunnel structure according to the present invention will be described in detail with reference to the embodiments shown in the accompanying drawings.

도 5에 도시된 바와 같이, 먼저 지하시설물의 연결터널(4)과 연결되도록 지상으로부터 수직공(1)을 굴착한다.As shown in FIG. 5, first, the digger 1 is excavated from the ground so as to be connected to the connection tunnel 4 of an underground facility.

도시하지는 않았으나 굴착된 수직공(1)의 내주면에 콘크리트 몰탈을 타설하여 수직공(1)이 붕괴되지 않도록 한 다음 방수포를 부착한다. 만일, 수직공(1)의 굴착과정에서 지반이 약한 부분이 있다면 수직공(1) 내측면에 철구조물(1a)을 설치하는 보강작업이 추가될 수 있다.Although not shown, a concrete mortar is placed on the inner circumferential surface of the excavated swivel (1) so that the swivel (1) is not collapsed, and then a deflector is attached. If there is a weak portion in the excavation process of the swivel (1), reinforcement work for installing the steel structure (1a) in the swivel (1) may be added.

수직공(1)의 굴착이 완료되면 굴착된 수직공(1)의 바닥에 기초 콘크리트를 타설하고 그 위에 철근을 배근한 다음 본체 콘크리트를 타설하여 수직공(1)의 바닥을 견고하게 시공한다.After completion of excavation of the weir 1, the foundation concrete is laid on the bottom of the excavated weir 1, the reinforcing bars are laid on the foundation concrete, and then the main body concrete is laid on the bottom of the weir 1 to securely construct the bottom.

도 6 및 도 7에 도시된 바와 같이, 수직공(1)의 바닥시공이 완료되면, 슬립폼 작업대(100)를 설치한 다음 슬립폼 작업대(100)를 이용하여 벽체가 설치될 위치에 수직철근과 수평철근으로 이루어진 철근 콘크리트 구조물(200)들을 설치한다.6 and 7, when the floor construction of the straight hole 1 is completed, the slip-form workbench 100 is installed, and then the slab- And reinforced concrete structures 200 made of horizontal reinforcing bars are installed.

상기 철근 콘크리트 구조물(200)들은 굴착된 수직공(1)의 내벽면을 이루는 원형벽체(10)와, 상기 수직공(1)을 수직의 대피로(3)와 환기로(2)로 구획하는 수직벽체(20)와, 수직벽체(20)로부터 대피로(3)를 향해 일정간격을 두고 연장되는 수직통로(30)의 측벽체(31)의 위치와 형태에 맞추어 일정 높이만큼만 설치된다.The reinforced concrete structures 200 are divided into a circular wall 10 constituting the inner wall surface of the diggered through hole 1 and a vertical wall 3 partitioned by the vertical wall 3 and the ventilation passage 2 The vertical wall 20 and the vertical wall 30 extending from the vertical wall 20 to the escape route 3 at regular intervals.

그리고 슬립폼 작업대(100)를 상승시켜 원형벽체(10)와 수직벽체(20)와 수직통로(30)의 측벽체(31)들의 타설을 연속적으로 수행한다.Then, the slipform workbench 100 is elevated to continuously carry out the placement of the circular wall 10, the vertical wall 20, and the side walls 31 of the vertical passage 30.

도시하지는 않았으나, 수직벽체(20)를 이루는 철근 콘크리트 구조물(200)을 설치할 때, 수직벽체(20)와 대피로(3)를 연결하는 출입구 설치용 철골 및 거푸집이 설치되며, 상기 출입구 설치용 거푸집이 설치된 이후에는 지하시설물의 연결터널(4)을 상하로 구획하면서 상기 출입구와 연결되는 연결벽체(60) 설치용 거푸집도 설치된다.Although not shown, a steel frame and a formwork for installing a doorway are provided for connecting the vertical wall 20 and the escape route 3 when the reinforced concrete structure 200 constituting the vertical wall 20 is installed, and the doorway installation formwork is installed Thereafter, a mold for installing a connection wall body 60, which is connected to the entrance, is installed, while vertically dividing the connection tunnel 4 of the underground facility.

상기 슬립폼 작업대(100)는 굴착된 수직공(1)의 내주면에서 각 철근 콘크리트 구조물(200)들로부터 일정거리 이격된 위치에서 수직으로 설치되는 복수의 폼프레임(110)과, 상기 폼프레임(110)의 하단부 외측에 결합되는 폼패널(120)과, 상기 폼프레임(110)의 외측에 결합되는 유압잭(130)과, 상기 유압잭(130)에 결합되는 잭로드(140)와, 상기 폼프레임(110)의 상단 내측에 결합되는 상단데크(150)와 상기 폼프레임(110)의 중단 내측에 결합되는 중단데크(160)와, 상기 중단데크(160)의 하부에 높이조절가능하게 설치되는 승강식 하단데크(170)로 구성된다.The slipform workbench 100 includes a plurality of foam frames 110 vertically installed at a predetermined distance from the reinforcing concrete structures 200 on the inner circumferential surface of the excavated through hole 1, A hydraulic jack 130 coupled to the outside of the foam frame 110; a jack rod 140 coupled to the hydraulic jack 130; An upper deck 150 coupled to an inside of an upper end of the ceiling 110 and an intermediate deck 160 coupled to an inner side of the break of the foam frame 110, And a lower expression deck 170.

상기 상단데크(150)에는 미경화 콘크리트를 주입하기 위한 콘크리트 호퍼(180)가 설치된다. 상기 콘크리트 호퍼(180)는 가장 효율적으로 미경화 콘크리트를 주입할 수 있도록 주입 위치를 고려하여 복수로 구비되어도 무방하다. 또한 상기 콘크리트 호퍼(180)는 상단데크(150)에 직접 고정되는 방식으로 설치되지 아니하고 지상에서 크레인으로 매달아 상단데크(150)의 상단으로부터 일정거리 이격되게 설치하여도 무방하다. 이 경우 지상으로부터 미경화 콘크리트를 콘크리트 호퍼(180)로 공급하기가 매우 용이해지고 작업상황에 따라서 콘크리트 호퍼(180)의 위치를 자유자재로 변경할 수 있다는 이점이 있다.The upper deck 150 is provided with a concrete hopper 180 for injecting unhardened concrete. The concrete hopper 180 may be provided in plurality in consideration of the injection position so as to inject the uncured concrete most efficiently. Also, the concrete hopper 180 may not be installed in a manner directly fixed to the upper deck 150, but may be installed at a distance from the upper end of the upper deck 150 by hanging from the ground with a crane. In this case, it is very easy to supply the uncured concrete from the ground to the concrete hopper 180, and the position of the concrete hopper 180 can be freely changed according to the operation conditions.

상기 콘크리트 호퍼(180)의 하단에는 상단 콘크리트 주입관(190)이 하향경사지게 연장된다. 그리고 상단데크(150)의 데크패널에는 상기 상단 콘크리트 주입관(190)의 하단과 연결되어 상단 콘크리트 주입관(190)으로부터 공급받은 콘크리트를 중단데크(160)로 통과시키기 위한 상단 콘크리트 주입공(151)들이 형성되어 있으며, 상기 중단데크(160)에는 상단 콘크리트 주입공(151)과 연결된 중단 콘크리트 주입관(190)이 설치된다. 상기 중단 콘크리트 주입관(190)은 수평으로 360°회전가능하게 설치하는 것이 바람직하다.At the lower end of the concrete hopper 180, the upper concrete injection pipe 190 extends downwardly. The deck panel of the upper deck 150 is connected to the lower end of the upper concrete injection pipe 190 and is connected to the upper concrete injection hole 151 for passing the concrete supplied from the upper concrete injection pipe 190 to the stop deck 160 The suspended concrete injection pipe 190 connected to the upper concrete injection hole 151 is installed in the suspended deck 160. It is preferable that the suspended concrete injection pipe 190 is rotatably installed 360 ° horizontally.

한편, 중단데크(160)의 데크패널에는 상기 중단 콘크리트 주입관(190)의 하단과 연결되어 중단 콘크리트 주입관(190)으로부터 공급받은 콘크리트를 하단데크(170)로 통과시키기 위한 중단 콘크리트 주입공(161)들이 형성될 수 있다. 이 경우 상기 하단데크(170)에는 중단 콘크리트 주입공(161)과 연결된 콘크리트 주입호스(192)가 설치된다. 상기 콘크리트 주입호스(192)는 후술할 프리캐스트 슬라브(70)의 설치를 위하여 원형벽체(10)와 수직벽체(20)와 수직통로(30)에 설치되는 프리캐스트 슬라브 지지용 브라켓(210)에 콘크리트를 주입한다.The deck panel of the suspended deck 160 is connected to the lower end of the suspended concrete injection pipe 190 and connected to the suspended concrete injection hole 190 for passing the concrete supplied from the suspended concrete injection pipe 190 to the lower deck 170 161 may be formed. In this case, the lower deck 170 is provided with a concrete injection hose 192 connected to the interrupted concrete injection hole 161. The concrete injection hose 192 has a circular wall 10, a vertical wall 20 and a precast slab supporting bracket 210 installed in the vertical passage 30 for installing a precast slab 70 to be described later Concrete is injected.

아울러, 상기 콘크리트 호퍼(180)의 하단에도 콘크리트 주입호스(192)가 연결될 수 있다. 이 경우, 상기 콘크리트 주입호스(192)는 상단콘크리트 주입관(190)과 연결되어 상단콘크리트 주입관(190)으로부터 콘크리트를 공급받기 힘든 수직벽체(20) 및 수직통로(30)측에 콘크리트를 주입한다.Also, a concrete injection hose 192 may be connected to the lower end of the concrete hopper 180. In this case, the concrete injection hose 192 is connected to the upper concrete injection pipe 190 and injects concrete into the vertical wall 20 and the vertical passage 30 which are difficult to receive concrete from the upper concrete injection pipe 190 do.

한편, 중단데크(160)의 하부에는 승강식 하단데크(170)를 승강시키기 위한 윈치(171)가 설치되는 것이 바람직하다.On the other hand, it is preferable that a winch 171 for raising and lowering the elevating lower deck 170 is installed below the suspended deck 160.

아울러, 상기 슬립폼 작업대(100)의 상단데크(150)의 상단 가장자리에는 슬립폼 설치시 가설된 철골 구조물(1a)들의 해체작업 및 해체된 철골구조물(1a)의 자리에 방수포를 부착하는 작업을 수행할 수 있는 보조작업대(155)가 더 구비될 수 있다.At the upper edge of the upper deck 150 of the slipform workbench 100, a work for dismantling the steel structures 1a installed at the time of installing the slip foam and attaching the tarpaulins to the disassembled steel structure 1a It is possible to further include the auxiliary workbench 155 that can be performed.

이와 같이 구성된 슬립폼 작업대(100)는 상단데크(150)에서 수평 및 수직철근의 조립 및 자재적재 그리고 잭로드(140)의 연장 조립과 콘크리트의 공급이 지속적으로 이루어지고, 중단데크(160)에서 수평 및 수직 철근조립과 콘크리트의 타설이 이루어지며, 상기 승강식 하단데크(170)에서 프리캐스트 슬라브 지지용 브라켓(210)을 설치하는 작업이 이루어진다.The slipform workbench 100 configured as described above is constructed such that horizontal and vertical rebar assemblies and materials are stacked in the upper deck 150 and the jack rod 140 is extended and assembled, Horizontal and vertical rebar assemblies and pouring of concrete are performed, and the precast slab supporting bracket 210 is installed in the elevating lower deck 170.

아울러, 상단데크(150)에는 수직철근과 수평철근 및 이들의 조립을 위한 잡자재가 적재되고, 중단데크(160)에는 프리캐스트 슬라브 지지용 브라켓의 설치를 위한 철근과 매립박스와 거푸집 및 이들을 설치하는 데 필요한 잡자재들이 적재된다.In addition, the upper deck 150 is provided with a vertical reinforcing bar, a horizontal reinforcing bar, and a handy material for assembling the reinforcing bar, the reinforcing bar, the embedding box and the mold for installing the precast slab supporting bracket, The necessary job items are loaded.

한편, 상기 수직철근과 수평철근 및 프리캐스트 슬라브 지지용 브라켓(210)의 설치를 위한 각종 자재들은 상,중,하단데크(170)에 형성된 통과공을 통하여 필요한 위치로 공급된다.Various materials for installing the vertical reinforcing bars, the horizontal reinforcing bars, and the precast slab supporting brackets 210 are supplied to the required positions through the through holes formed in the upper, middle, and lower decks 170.

이와 같은 슬립폼 작업대(100)의 설치가 완료되면, 작업자는 미리 설치된 잭로드(140)를 이용하여 각 철근 콘크리트 구조물(200)을 따라 폼패널(120)을 설치한 다음, 콘크리트 호퍼(180)와 콘크리트 주입관(190) 및 콘크리트 주입호스(192)를 이용하여 폼패널(120)의 외주면과 수직공(1)의 내주면 사이에 콘크리트를 주입하여 일정높이로 타설한다.When the installation of the slip-form workbench 100 is completed, the operator installs the foam panel 120 along the reinforcing concrete structures 200 using the jack rod 140 installed in advance, Concrete is injected between the outer circumferential surface of the foam panel 120 and the inner circumferential surface of the through hole 1 by using the concrete injection pipe 190 and the concrete injection hose 192 to pour the concrete at a predetermined height.

슬립폼 작업대(100)를 상승시켜 원형벽체(10)와 수직벽체(20)와 수직통로(30)의 측벽체(31)들의 타설을 연속적으로 수행할 때, 상기 원형벽체(10)와 수직벽체(20)와 수직통로(30)의 양측벽의 외측에 일정 높이 간격마다 프리캐스트 슬라브 지지용 브라켓(210)의 설치도 함께 이루어진다. 즉, 중단데크(160)에서 프리캐스트 슬라브(70)가 설치될 위치에 브라켓용 철근을 상기 수직철근 및 수평철근에 연결하여 설치한 다음, 상기 브라켓용 철근을 절곡하여 미리 준비한 브라켓용 매립박스 내에 수용되도록 한 후에, 원형벽체(10)의 타설이 완료되면 상기 매립박스를 제거하고 브라켓용 거푸집을 설치한 다음, 중단 콘크리트 주입공(161)으로 콘크리트를 주입하여 콘크리트 주입호스(192)를 통해 브라켓용 거푸집에 콘크리트를 타설하면 상기 프리캐스트 슬라브 지지용 브라켓(210)의 설치가 완료되는 것이다.When the slip foam workbench 100 is raised to continuously carry out the insertion of the circular wall 10, the vertical wall 20 and the side walls 31 of the vertical passage 30, the circular wall 10 and the vertical wall 30, The precast slab supporting bracket 210 is also installed outside the side walls of the vertical passage 30 and the vertical passage 30 at predetermined intervals. That is, a bracket reinforcing bar is connected to the vertical reinforcing bar and the horizontal reinforcing bar at a position where the precast slab 70 is to be installed in the halt deck 160, and then the reinforcing bar for bracket is bent, The concrete is injected into the concrete pouring hole 161 through the concrete pouring hose 192 and then the concrete is injected through the concrete pouring hose 192 into the pouring hole of the bracket, When the concrete is laid on the formwork, the installation of the precast slab supporting bracket 210 is completed.

그리고, 상기 프리캐스트 슬라브 지지용 브라켓(210)이 설치될 때, 수직통로(30)의 양측벽의 내측에 대피용 계단 지지용 브라켓(41)들도 설치된다. 상기 대피용 계단 지지용 브라켓(41)의 설치방법은 프리캐스트 슬라브 지지용 브라켓(210)과 대동소이하므로 여기서의 상세한 설명은 생략하기로 한다.When the precast slab supporting bracket 210 is installed, stair support brackets 41 for escape are also installed inside the side walls of the vertical passage 30. [ Since the method of installing the step brackets for escape 41 is similar to that of the precast slab supporting bracket 210, detailed description thereof will be omitted.

한편, 도 8에 도시된 바와 같이, 지하시설물의 연결터널(4) 전면에는 원형벽체를 형성시킬 필요가 없으므로 이곳에는 철근 콘크리트 구조물을 설치하지 않고 오로지 잭로드(140)만 설치되는데, 이곳에 설치되는 잭로드(140)들은 다른 곳에 설치되는 잭로드(140)들과 비교할 때 상부로부터 큰 수직하중을 받게 되므로 이곳에 설치되는 잭로드(140)의 외측에만 수직강도 보강용 지지관(141)이 결합된다.As shown in FIG. 8, since it is not necessary to form a circular wall on the front surface of the connection tunnel 4 of the underground facility, only the jack rod 140 is installed therein without installing a reinforced concrete structure. Since the jack rods 140 are subjected to a large vertical load from the top in comparison with the jack rods 140 installed at other places, the vertical strength reinforcing supporting tube 141 is provided only on the outer side of the jack rod 140 installed there .

상기 수직강도 보강용 지지관(141)은 좌우 한 쌍(141a,141b)으로 이루어져 합치되는 철재구조물로서, 일정 높이를 갖도록 복수로 구비되어 잭로드(140)를 따라 수직공(1)의 바닥에서부터 연결터널(4)의 상부까지 연속적으로 적층 결합하여 사용된다.The vertical strength reinforcing supporting pipe 141 is composed of a pair of right and left pairs of steel structures 141a and 141b and is made up of a plurality of steel structures having a predetermined height from the bottom of the through hole 1 along the jack rod 140 To the upper part of the connection tunnel 4, and is used.

이와 같은 과정을 거쳐 지상까지 원형벽체(10)와 수직벽체(20)와 수직통로(30)의 측벽체(31)의 시공이 완료되면 슬립폼 작업대(100)는 완전히 상승하게 되며 이후 해체된다.After completion of the construction of the circular wall 10, the vertical wall 20 and the side wall 31 of the vertical passage 30 to the ground through the above process, the slipform workbench 100 is completely raised and then disassembled.

그리고, 도 9 및 도 10에 도시된 바와 같이, 프리캐스트 수직통로(30)의 전면벽체(32)를 수직통로(30)의 측벽체(31)에 조립하여 수직통로(30)를 완성한다. 이때, 프리캐스트 수직통로(30)의 전면벽체(32)는 지상에 설치된 크레인에 매달아서 필요한 위치로 공급된다.9 and 10, the front wall 32 of the precast vertical passage 30 is assembled to the side wall body 31 of the vertical passage 30 to complete the vertical passage 30. As shown in Fig. At this time, the front wall 32 of the precast vertical passage 30 is hung from a crane installed on the ground and supplied to a necessary position.

그리고 프리캐스트 슬라브 지지용 브라켓(210) 상부에 지지되도록 프리캐스트 슬라브(70)가 설치하는 것이 바람직하다. 상기 프리캐스트 슬라브(70)는 지상에 설치된 크레인에 매달아서 필요한 위치로 공급된다. 상기 프리캐스트 슬라브(70)는 세그먼트 형태로 조각내어 제작되므로 운송 및 운반이 쉽고 작은 출력의 크레인을 이용할 수 있어서 작업공기 및 비용적인 측면에서 매우 유리하다. 이 경우, 수직통로(30)는 프리캐스트 슬라브(70)를 통해 각 층으로 구획되며, 상기 프리캐스트 수직통로(30)의 전면벽체(32)에는 각층마다 대피로(3)로 통하는 출입구가 형성된다.The precast slab 70 is preferably installed to be supported on the precast slab supporting bracket 210. The precast slab 70 is suspended from a crane installed on the ground and supplied to a required position. Since the precast slab 70 is manufactured in the form of a segment, it is easy to transport and transport, and a crane with a small output can be used, which is very advantageous in terms of work air and cost. In this case, the vertical passage 30 is partitioned into the respective layers through the precast slabs 70, and the front wall 32 of the precast vertical passage 30 is provided with an entrance for passing through the escape route 3 for each layer do.

상기와 같이 수직통로(30)와 슬라브(70)층이 완성되면, 도 1 내지 도 3에 도시된 바와 같이, 완성된 수직통로(30) 내부에 대피용 계단(40)을 설치한다. 상기 대피용 계단(40)은 도시된 바와 같이 상기 대피용 계단 지지용 브라켓(41)에 조립되는 프리캐스트로 제작된 슬라브형 조립식 계단일 수도 있고, 도시되지는 않았으나 상기 대피용 계단 지지용 브라켓(41)에 조립되는 조립식 철재 계단일 수도 있다. 이때, 슬라브형 조립식 계단 또는 조립식 철재 계단은 지상에 설치된 크레인에 매달아서 필요한 위치로 공급된다. 상기 슬라브형 조립식 계단 또는 조립식 철재 계단은 세그먼트 형태로 조각내어 조립되므로 운송 및 운반이 쉽고 작은 출력의 크레인을 이용할 수 있어서 작업공기 및 비용적인 측면에서 매우 유리하다.When the vertical passages 30 and the slabs 70 are completed as described above, a step 40 for escape is provided in the completed vertical passage 30 as shown in FIGS. The shelf step 40 may be a slab-type prefabricated staircase that is assembled to the shelf-supporting bracket 41 as shown in the figure. Although not shown, the shelf- 41). ≪ / RTI > At this time, the slab-type assembled staircase or the prefabricated steel staircase is hung from a ground-mounted crane and supplied to a necessary position. Since the slab-type prefabricated staircase or the prefabricated steel staircase is sliced and assembled in a segment form, it is easy to transport and transport, and a crane with a small output can be used, which is very advantageous in terms of working air and cost.

수직통로(30) 내부로 공급된 슬라브형 조립식 계단과 조립식 철재 계단은 대피용 계단 지지용 브라켓(41)에 단부가 지지된 상태에서 볼트를 이용하여 상호 체결을 통해 견고하게 조립되도록 한다.The slab-type assembly step and the prefabricated steel staircase supplied to the inside of the vertical passage 30 are assembled firmly by using bolts in a state in which the ends are supported by the step-supporting bracket 41 for escape.

본 발명의 다른 실시예로서, 수직공(1)의 내부에 슬립폼 작업대(100)가 가설되는 단계 이후에 철근 콘크리트 구조물(200)을 설치할 때, 수직통로(30) 전체를 이루는 철근 콘크리트 구조물을 설치할 수도 있다.When the reinforced concrete structure 200 is installed after the slip form workbench 100 is installed in the inside of the through hole 1, the reinforcing concrete structure constituting the entirety of the vertical path 30 It can also be installed.

이 경우, 수직통로(30)의 측벽체(31)를 이루는 철근 콘크리트 구조물들만 설치하는 경우와는 달리 프리캐스트로 제작된 수직통로(30)의 전면벽체(32)가 수직통로(30)의 측벽체(31)에 조립되는 단계를 거치지 않아도 되므로 작업속도가 빨라지는 이점이 있다.In this case, unlike the case where only the reinforced concrete structures constituting the sidewall 31 of the vertical passage 30 are provided, the front wall 32 of the vertical passage 30 made of precast is connected to the side of the vertical passage 30 There is no need to pass the step of assembling to the wall 31, which is advantageous in that the operation speed is increased.

본 발명의 또 다른 실시예로서, 도 11 및 도 12에 도시된 바와 같이, 수직통로(30)의 전면벽체(32)의 외측에 엘리베이터 설치통로(80)가 설치될 수도 있다.As another embodiment of the present invention, an elevator installation passage 80 may be provided outside the front wall 32 of the vertical passage 30, as shown in FIGS.

이 경우, 상기 엘리베이터 설치통로(80)는 일정높이 단위로 프리캐스트로 제작되어 수직통로(30)의 설치가 완료된 이후에 수직통로(30)의 전면벽체(32)의 외측에 조립된다. 이때, 수직통로(30)의 전면벽체(32)의 외측에 엘리베이터 설치통로용 브라켓(미도시)이 미리 설치되어 있어야 함은 물론이다.In this case, the elevator installation passage 80 is precast in units of a predetermined height, and is assembled to the outside of the front wall 32 of the vertical passage 30 after the installation of the vertical passage 30 is completed. Needless to say, an elevator installation passage bracket (not shown) must be installed outside the front wall 32 of the vertical passage 30.

한편, 본 발명의 엘리베이터 설치통로(80)는 본 발명의 다른 실시예에서와 같이 수직통로(30) 전체를 이루는 철근 콘크리트 구조물이 설치될 때 엘리베이터 설치통로(80)를 이루는 철근 콘크리트 구조물도 함께 설치되도록 한 다음 슬립폼 작업대(100)를 이용하여 수직통로(30)와 함께 일괄 타설하여 제작되도록 할 수도 있다.In the elevator installation passage 80 of the present invention, when a reinforced concrete structure constituting the entire vertical passage 30 is installed as in the other embodiments of the present invention, a reinforced concrete structure constituting the elevator installation passage 80 is also installed So that it can be assembled together with the vertical passage 30 by using the slip foam workbench 100.

상기 엘리베이터 설치통로(80)는 상기 프리캐스트 슬라브(70)들을 차례로 관통하면서 수직공(1)의 바닥에서 지상까지 설치된다. 이때, 상기 프리캐스트 슬라브(70)에는 엘리베이터 설치공이 미리 형성되어 있어야 함은 물론이다. 그리고 엘리베이터 장비의 설치는 대피용 계단(40)이 설치될 때 함께 이루어진다.The elevator installation passage 80 is installed from the bottom of the straight hole 1 to the ground while sequentially passing through the precast slabs 70. In this case, it is needless to say that an elevator installation hole must be formed in the precast slab 70 in advance. And the installation of the elevator equipment is done together when the escape stairs 40 are installed.

본 발명의 또 다른 실시예로서, 도 4에 도시된 바와 같이, 상기 수직공(1)의 내부에 슬립폼 작업대(100)가 가설되는 단계 이후에 집수공 바닥에 집수조(90)가 설치되는 단계를 더 거치도록 할 수도 있다.4, the step of installing the slip foam workbench 100 in the interior of the weir hole 1 and then installing the water collecting vessel 90 on the bottom of the flocculent pouring floor (step < RTI ID = 0.0 > May be added.

이 경우, 상기 집수조(90)가 설치되는 단계는 수직공(1)의 바닥에 굴착된 수직공(1)의 내벽면을 이루는 원형벽체(10)를 이루는 철근 콘크리트 구조물(200)들이 설치되는 단계와, 상기 슬립폼 작업대(100)가 상승하면서 상기 철근 콘크리트 구조물(200)들에 원형벽체(10)가 연속적으로 타설되는 단계와, 상기 원형벽체(10)에 일정 높이로 프리캐스트 슬라브 지지용 브라켓(210)들이 설치되는 단계와, 프리캐스트 슬라브(70)가 상기 프리캐스트 슬라브 지지용 브라켓(210)들을 통해 조립되는 단계를 거친다.In this case, in the step of installing the water collecting tank 90, the reinforcing concrete structures 200 constituting the circular wall 10 constituting the inner wall surface of the through hole 1 excavated on the bottom of the through hole 1 are installed (10) is continuously inserted into the reinforced concrete structures (200) while the slip foam workbench (100) is elevated, and a step of placing the circular wall (10) The pre-cast slab supporting brackets 210 are installed on the pre-cast slab supporting brackets 210, and the pre-cast slabs 70 are assembled through the pre-cast slab supporting brackets 210.

그리고, 상기 프리캐스트 슬라브(70)는 수직공(1) 전체로 볼 때 최하층의 프리캐스트 슬라브(71)가 되며, 상기 집수조(90)는 수직공(1)의 바닥과 최하층의 프리캐스트 슬라브(70)와의 사이에 형성된 공간부가 된다. 이 경우 최하층의 프리캐스트 슬라브(70) 상면에 수직벽체(20)와 수직통로(30)가 시공된다.The precast slab 70 becomes the lowest precast slab 71 when viewed from the whole of the through hole 1 and the collecting vessel 90 is connected to the bottom of the through hole 1 and the lowest precast slab 70). In this case, the vertical wall 20 and the vertical passage 30 are formed on the upper surface of the lowest precast slab 70.

또한, 최하층의 프리캐스트 슬라브(70)를 형성시킨 다음 최하층의 프리캐스트 슬라브(70)의 상부에 프리캐스트 보조 슬라브(72)를 더 설치할 수도 있다. 이 경우, 보조 슬라브(72)와 최하층 슬라브(71) 사이에 형성되는 공간부를 기계실(91)로 활용할 수도 있다.Further, a precast slab 70 may be formed and then a precast auxiliary slab 72 may be further provided on the top of the lowest precast slab 70. In this case, a space formed between the auxiliary slab 72 and the lowermost slab 71 may be utilized as the machine room 91. [

상기 최하층의 프리캐스트 슬라브(70)와 보조 슬라브(72)는 세그먼트 형태로 조각내어 제작되므로 운송 및 운반이 쉽고 작은 출력의 크레인을 이용할 수 있어서 작업공기 및 비용적인 측면에서 매우 유리하다.Since the lowermost precast slab 70 and the auxiliary slab 72 are manufactured in the form of a segment, they can be easily transported and transported, and a crane with a small output can be used, which is very advantageous in terms of working air and cost.

이와 같이 집수조(90) 및 기계실(91)의 설치가 완료되면 최하층의 프리캐스트 슬라브(71) 또는 보조 슬라브(72)의 상면에 굴착된 수직공(1)의 내벽면을 이루는 원형벽체(10)와 상기 수직공(1)을 수직의 대피로(3)와 환기로(2)로 구획하는 수직벽체(20)와 수직벽체(20)로부터 대피로(3)를 향해 일정간격을 두고 연장되는 수직통로(30)를 이루는 철근 콘크리트 구조물(200)들이 설치되며 이후의 시공단계는 상술한 바와 동일하다.When the installation of the water collecting tank 90 and the machine room 91 is completed, the circular wall body 10 constituting the inner wall surface of the straight hole 1, which is excavated on the top surface of the lowest precast slab 71 or the auxiliary slab 72, And a vertical wall 20 partitioning the vertical wall 1 into a vertical escape path 3 and a ventilation path 2 and a vertical wall 20 extending from the vertical wall 20 toward the escape path 3 at regular intervals The reinforced concrete structures 200 constituting the passages 30 are installed and the subsequent construction steps are the same as described above.

이와 같이 집수조(90)와 기계실(91)의 설치가 원형벽체(10)의 시공과 동시에 이루어지고, 최하층의 프리캐스트 슬라브(71)와 보조 슬라브(72)가 세그먼트 형태로 조각내어 제작되므로 시공기간과 비용을 크게 절감할 수 있다.Since the water collecting tank 90 and the machine room 91 are installed simultaneously with the construction of the circular wall 10 and the lowermost precast slab 71 and the auxiliary slab 72 are cut out in the form of segments, And the cost can be greatly reduced.

본 발명의 또 다른 실시예로서, 원형벽체(10)와 수직벽체(20)만 슬립폼 작업대(100)를 이용하여 설치하고 수직통로(30)를 비롯한 나머지는 대피용 계단(40) 및 엘리베이터 설치통로(80)를 모두 프리캐스트 방식으로 조립하여 시공하는 방법도 가능하다. 이 경우, 프리캐스트로 조립되는 구조물들이 다른 실시예들에 비하여 가장 많기 때문에 시공기간과 비용을 가장 크게 절감할 수 있다.In another embodiment of the present invention, only the circular wall 10 and the vertical wall 20 are installed using the slipform workbench 100, and the rest including the vertical passage 30 is used for the escape step 40 and the elevator installation And the passages 80 may be all assembled in a precast manner. In this case, since the structures to be assembled by precast are the largest in comparison with the other embodiments, the construction period and cost can be saved most greatly.

이와 같이, 도면을 참조하여 본 발명의 바람직한 실시예에 대해 상술하였으나 본 발명은 전술한 실시예에 한정되지 않으며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진자가 본 발명의 사상을 벗어나지 않고 변형 가능하며, 이러한 변형은 본 발명의 권리범위에 속할 것이다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is clearly understood that the same is by way of illustration and example only and is not to be takeners of ordinary skill in the art, And such variations are within the scope of the present invention.

1...수직공 2...환기로
3...대피로 4...연결터널
4a...수평벽체 10...원형벽체
20...수직벽체 30...수직통로
31...측벽체 32...전면벽체
40...대피용 계단 41...대피용 계단 지지용 브라켓
50...출입구 60...연결벽체
70...프리캐스트 슬라브 71...최하층 슬라브
72...보조 슬라브 80...엘리베이터 설치통로
90...집수조 91...기계실
100...슬립폼 작업대 141...수직강도 보강용 지지관
155...보조작업대 200...철근 콘크리트 구조물
210...프리캐스트 슬라브 지지용 브라켓
1 ... handicraft 2 ... ventilation furnace
3 ... evacuation route 4 ... connection tunnel
4a ... horizontal wall 10 ... circular wall
20 ... vertical wall 30 ... vertical passage
31 ... side wall 32 ... front wall
40 ... escape stairs 41 ... escape stair support brackets
50 ... doorway 60 ... connection wall
70 ... Precast slab 71 ... Lowermost slab
72 ... auxiliary slab 80 ... elevator installation passage
90 ... Sewer tank 91 ... Machine room
100 ... Slipform workbench 141 ... Support pipe for vertical strength reinforcement
155 ... Secondary workbench 200 ... Reinforced concrete structure
210 ... Precast slab support bracket

Claims (17)

지하시설물의 연결터널과 연결되도록 굴착된 수직공의 내벽면을 이루는 원형벽체;
상기 원형벽체를 수직의 대피로와 환기로로 구획하는 수직벽체;
상기 대피로의 내부에 수직벽체를 이용하여 수직공의 바닥에서 지상까지 형성된 수직통로;
상기 수직통로의 내부에 설치된 대피용 계단;
수직벽체의 하단에 형성된 수직통로 출입구; 및
상기 수직공에서 발생되는 지하수를 저장할 수 있도록 수직공의 바닥과 최하층의 프리캐스트 슬라브와의 사이에 형성된 공간부로 이루어진 집수조를 포함하여 구성됨을 특징으로 하는 수직터널 구조물.
A circular wall constituting an inner wall surface of a through hole excavated to be connected to a connection tunnel of an underground facility;
A vertical wall for partitioning the circular wall into a vertical escape path and a ventilation path;
A vertical passage formed from the bottom of the weir to the ground using a vertical wall inside the evacuation passage;
A step for escaping provided inside the vertical passage;
A vertical passage entrance formed at the lower end of the vertical wall; And
And a water collecting tank having a space formed between the bottom of the water hole and the lowest precast slab so as to store groundwater generated in the water hole.
제 1항에 있어서,
상기 대피로에는 각각의 층을 이루도록 수직통로가 관통하는 프리캐스트 슬라브가 일정 높이 간격으로 설치된 것을 특징으로 하는 수직터널 구조물.
The method according to claim 1,
Wherein the pre-cast slabs through which the vertical passages pass to form the respective layers are installed at predetermined intervals.
제 2항에 있어서,
상기 수직통로의 외측에는 상기 프리캐스트 슬라브들을 차례로 관통하면서 대피로의 바닥에서 지상까지를 연결하는 엘리베이터 설치통로가 설치되며,
상기 수직통로와 상기 엘리베이터 설치통로에는 각층마다 대피로로 통하는 출입구가 형성된 것을 특징으로 하는 수직터널 구조물.
3. The method of claim 2,
An elevator installation passage for connecting the pre-cast slabs from the bottom to the ground is provided at the outside of the vertical passage,
Wherein the vertical passage and the elevator installation passage are provided with an entrance through which the escape route passes for each layer.
삭제delete 제 1항에 있어서,
상기 집수조와 최하층 슬라브 사이에 기계실로 활용할 수 있는 공간부를 형성하는 보조 슬라브가 더 설치된 것을 특징으로 하는 수직터널 구조물.
The method according to claim 1,
Further comprising a secondary slab formed between the water collecting tank and the lowermost slab to form a space that can be utilized as a machine room.
제 1항에 있어서,
상기 지하시설물의 연결터널을 상하로 구획하는 수평벽체와 수직벽체를 연결하는 연결벽체를 더 구비한 것을 특징으로 하는 수직터널 구조물.
The method according to claim 1,
Further comprising a connection wall connecting the vertical wall and the horizontal wall separating the connection tunnel of the underground facility.
삭제delete 수직공 굴착단계;
수직공의 바닥에 기초 콘크리트가 타설되는 단계;
수직공의 내부에 슬립폼 작업대가 가설되는 단계;
굴착된 수직공의 내벽면을 이루는 원형벽체와 상기 수직공을 수직의 대피로와 환기로로 구획하는 수직벽체와 수직벽체로부터 대피로를 향해 일정간격을 두고 연장되는 수직통로의 측벽체를 이루는 철근 콘크리트 구조물들이 설치되는 단계;
상기 슬립폼 작업대가 상승하면서 상기 철근 콘크리트 구조물들에 원형벽체와 수직벽체와 수직통로의 측벽체들이 연속적으로 타설되는 단계;
프리캐스트로 제작된 수직통로의 전면벽체가 완성된 수직통로의 측벽체에 조립되면서 수직통로가 완성되는 단계; 및
완성된 수직통로 내부에 대피용 계단이 조립되는 단계를 포함하여 구성됨을 특징으로 하는 수직터널 구조물의 시공방법.
A hydraulic drilling step;
Placing a base concrete on the bottom of the weir;
A slip foam workbench is installed in the interior of the weir;
A vertical wall constituting the inner wall surface of the excavated swivel and a vertical wall separating the horizontal wall into a vertical escape route and a ventilating route and a reinforcing wall constituting a side wall of a vertical passage extending from the vertical wall at regular intervals toward the escape route Installing concrete structures;
The sidewall bodies of the vertical wall and vertical wall are continuously inserted into the reinforced concrete structures while the slip foam workbench is raised;
A step of completing the vertical passage while the front wall of the pre-cast vertical passage is assembled to the side wall of the completed vertical passage; And
And assembling a step for evacuation into the completed vertical passage. ≪ RTI ID = 0.0 > 18. < / RTI >
수직공 굴착단계;
수직공의 바닥에 기초 콘크리트가 타설되는 단계;
수직공의 내부에 슬립폼 작업대가 가설되는 단계;
굴착된 수직공의 내벽면을 이루는 원형벽체와 상기 수직공을 수직의 대피로와 환기로로 구획하는 수직벽체를 이루는 철근 콘크리트 구조물들이 설치되는 단계;
상기 슬립폼 작업대가 상승하면서 상기 철근 콘크리트 구조물들에 원형벽체와 수직벽체가 연속적으로 타설되는 단계;
프리캐스트로 제작된 수직통로가 완성된 수직벽체에 조립되는 단계; 및
완성된 수직통로 내부에 대피용 계단이 조립되는 단계를 포함하여 구성됨을 특징으로 하는 수직터널 구조물의 시공방법.
A hydraulic drilling step;
Placing a base concrete on the bottom of the weir;
A slip foam workbench is installed in the interior of the weir;
Installing a reinforced concrete structure constituting a circular wall constituting an inner wall surface of the excavated swivel and a vertical wall partitioning the swivel passage into a vertical evacuation route and a ventilating route;
The slab-form workbench rises and the circular wall and the vertical wall are continuously inserted into the reinforced concrete structures;
Assembling a pre-cast vertical passage into a finished vertical wall; And
And assembling a step for evacuation into the completed vertical passage. ≪ RTI ID = 0.0 > 18. < / RTI >
제 8항 또는 제 9항에 있어서,
상기 수직공의 내부에 슬립폼 작업대가 가설되는 단계 이후에 수직공의 바닥에 집수조가 설치되는 단계를 더 거치며,
상기 집수조가 설치되는 단계는 굴착된 수직공의 바닥에 수직공의 내벽면을 이루는 원형벽체를 이루는 철근 콘크리트 구조물들이 설치되는 단계와, 상기 슬립폼 작업대가 상승하면서 상기 철근 콘크리트 구조물들에 원형벽체가 연속적으로 타설되는 단계와, 상기 원형벽체에 일정 높이로 프리캐스트 슬라브 지지용 브라켓들이 설치되는 단계와, 프리캐스트 슬라브가 상기 프리캐스트 슬라브 지지용 브라켓들을 통해 조립되는 단계로 구성된 것을 특징으로 하는 수직터널 구조물의 시공방법.
10. The method according to claim 8 or 9,
Further comprising the step of installing a water collecting tank on the bottom of the water hole after the slip foam workbench is installed in the water hole,
The step of installing the water collecting tank includes the steps of installing reinforced concrete structures constituting a circular wall constituting the inner wall surface of the water hole on the bottom of the excavated water hole and forming a circular wall on the reinforced concrete structures, Wherein the precast slab supporting brackets are installed at a predetermined height on the circular wall, and the precast slab supporting brackets are assembled through the precast slab supporting brackets. Construction method of structure.
제 8항 또는 제 9항에 있어서,
상기 원형벽체와 수직벽체와 수직통로에는 일정 높이 간격마다 프리캐스트 슬라브 지지용 브라켓들이 설치되고,
완성된 수직통로의 내부에 대피용 계단이 설치되는 단계 이전에 프리캐스트 슬라브가 상기 프리캐스트 슬라브 지지용 브라켓들을 통해 조립되는 것을 특징으로 하는 수직터널 구조물의 시공방법.
10. The method according to claim 8 or 9,
The pre-cast slab supporting brackets are installed at the predetermined height intervals in the circular wall, the vertical wall, and the vertical passage,
Wherein the precast slabs are assembled through the precast slab support brackets prior to the step of installing the escape stairs inside the completed vertical passageways.
제 8항 또는 제 9항에 있어서,
수직통로의 내측에는 대피용 계단 지지용 브라켓들이 설치되며,
상기 완성된 수직통로의 내부에 대피용 계단이 설치되는 단계에서 상기 대피용 계단은 상기 대피용 계단 지지용 브라켓에 조립되는 프리캐스트로 제작된 슬라브형 조립식 계단인 것을 특징으로 하는 수직터널 구조물의 시공방법.
10. The method according to claim 8 or 9,
Stairs supporting brackets for escape are provided inside the vertical passage,
Wherein the step of installing the vertical tunnel is a prefabricated slab-type assembly step that is assembled to the step-support bracket for evacuation in the step of installing the step for evacuation inside the completed vertical pathway. Way.
제 8항 또는 제 9항에 있어서,
수직통로의 내측에는 대피용 계단 지지용 브라켓들이 설치되며,
상기 완성된 수직통로 내부에 대피용 계단이 설치되는 단계에서 상기 대피용 계단은 상기 대피용 계단 지지용 브라켓에 조립되는 조립식 철재 계단인 것을 특징으로 하는 수직터널 구조물의 시공방법.
10. The method according to claim 8 or 9,
Stairs supporting brackets for escape are provided inside the vertical passage,
Wherein the step for evacuation is a prefabricated steel step to be assembled to the bracket for supporting the step for evacuation in the step of installing the step for evacuation inside the completed vertical passage.
제 8항 또는 제 9항에 있어서,
상기 완성된 수직통로의 내부에 대피용 계단이 조립되는 단계 이전에 수직통로의 외측에 일정높이 단위로 제작된 프리캐스트로 제작된 엘리베이터 설치통로가 조립되는 것을 특징으로 하는 수직터널 구조물의 시공방법.
10. The method according to claim 8 or 9,
Wherein a pre-cast elevator installation passage is assembled on the outside of the vertical passage in a unit of a predetermined height before the step of assembling the escape step inside the completed vertical passage.
제 8항 또는 제 9항에 있어서,
상기 철근 콘크리트 구조물들이 설치되는 단계에서 엘리베이터 설치통로를 이루는 철근 콘크리트 구조물이 함께 설치되고,
슬립폼 작업대가 상승하면서 엘리베이터 설치통로도 함께 타설되도록 한 것을 특징으로 하는 수직터널 구조물의 시공방법.
10. The method according to claim 8 or 9,
A reinforcing concrete structure constituting an elevator installation passage is installed together with the reinforcing concrete structures,
And the elevator installation passage is also installed while the slip-form worktable is elevated.
제 8항 또는 제 9항에 있어서,
상기 원형벽체를 이루는 철근 콘크리트 구조물들이 설치되는 단계에서,
상기 수직공의 바닥에는 슬립폼 작업대를 승강시키기 위한 잭로드가 내벽면을 따라 일정간격으로 설치되며,
지하시설물의 연결터널의 전면에 설치되는 잭로드들에 한하여 외측에 수직강도 보강용 지지관이 결합되는 것을 특징으로 하는 수직터널 구조물의 시공방법.
10. The method according to claim 8 or 9,
In the step of installing the reinforced concrete structures constituting the circular wall,
Jack rods for raising and lowering the slip foam workbench are installed at the bottom of the weir holes at regular intervals along the inner wall surface,
Wherein a vertical strength reinforcing support pipe is coupled to the outer side of the jack rods provided on the front surface of the connection tunnel of the underground facility.
제 8항 또는 제 9항에 있어서,
수직공의 내부에 슬립폼 작업대가 가설되는 단계에서
상기 슬립폼 작업대의 상단에 설치된 보조작업대를 통해 수직공에 가설된 철골 구조물들의 해체작업 및 방수포 부착작업이 수행되는 것을 특징으로 하는 수직터널 구조물의 시공방법.
10. The method according to claim 8 or 9,
At the stage where the slipform workbench is installed in the inside of the weir
Wherein the disassembly operation of the steel structures and the work of attaching the tarpaulins are performed through the auxiliary workbench provided at the upper end of the slip foam workbench.
KR1020150000024A 2015-01-02 2015-01-02 Vertical tunnel construction and constructing method for the same KR101737193B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020150000024A KR101737193B1 (en) 2015-01-02 2015-01-02 Vertical tunnel construction and constructing method for the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020150000024A KR101737193B1 (en) 2015-01-02 2015-01-02 Vertical tunnel construction and constructing method for the same

Publications (2)

Publication Number Publication Date
KR20160083659A KR20160083659A (en) 2016-07-12
KR101737193B1 true KR101737193B1 (en) 2017-05-18

Family

ID=56505170

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020150000024A KR101737193B1 (en) 2015-01-02 2015-01-02 Vertical tunnel construction and constructing method for the same

Country Status (1)

Country Link
KR (1) KR101737193B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102146073B1 (en) 2020-04-20 2020-08-19 주식회사 네오시티 Slip form for the construction of a vertical shaft with varying cross-section and the construction method
KR102169270B1 (en) 2020-06-12 2020-10-23 주식회사 네오시티 Fitting for forming concrete bracket, Concrete bracket for supporting slab of vertical shaft using the same, and construction method thereof
KR102169272B1 (en) 2020-06-12 2020-10-23 주식회사 네오시티 Fitting for forming concrete bracket, Concrete bracket for supporting slab of vertical shaft using the same, and construction method thereof
KR102169279B1 (en) 2020-06-12 2020-10-23 주식회사 네오시티 Inside hardware for forming concrete bracket, Concrete bracket using the same, and construction method thereof
KR102293968B1 (en) 2021-04-17 2021-08-26 주식회사 네오시티 A device for supporting the lower part of a wall for an aerial wall construction and a method for constructing an aerial wall using the same

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102214779B1 (en) * 2019-08-19 2021-02-10 (주)이안텍 Precast vertical core structureand construction method therewith
KR102228679B1 (en) * 2020-11-18 2021-03-15 노오순 Vertical hole construction system
KR102298436B1 (en) * 2021-01-26 2021-09-06 주식회사 효명이씨에스 Vertical concrete structure and method for constructing the same
KR102645179B1 (en) * 2022-07-19 2024-03-07 윤준섭 Precast type vertical tunnel
KR102687730B1 (en) * 2023-12-05 2024-07-23 주식회사 네오시티 Vertical structure including precast elevator pit and construction method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102146073B1 (en) 2020-04-20 2020-08-19 주식회사 네오시티 Slip form for the construction of a vertical shaft with varying cross-section and the construction method
KR102169270B1 (en) 2020-06-12 2020-10-23 주식회사 네오시티 Fitting for forming concrete bracket, Concrete bracket for supporting slab of vertical shaft using the same, and construction method thereof
KR102169272B1 (en) 2020-06-12 2020-10-23 주식회사 네오시티 Fitting for forming concrete bracket, Concrete bracket for supporting slab of vertical shaft using the same, and construction method thereof
KR102169279B1 (en) 2020-06-12 2020-10-23 주식회사 네오시티 Inside hardware for forming concrete bracket, Concrete bracket using the same, and construction method thereof
KR102293968B1 (en) 2021-04-17 2021-08-26 주식회사 네오시티 A device for supporting the lower part of a wall for an aerial wall construction and a method for constructing an aerial wall using the same

Also Published As

Publication number Publication date
KR20160083659A (en) 2016-07-12

Similar Documents

Publication Publication Date Title
KR101737193B1 (en) Vertical tunnel construction and constructing method for the same
RU2519321C2 (en) Method to erect underground structure
AU2019400693B2 (en) Method for operating a construction site device, and construction site device
US3275719A (en) Method of building in situ construction using sequential molding techniques
US7784231B2 (en) Multi-story building
CN109356167B (en) Deep foundation pit support dismantling system and construction method
CN108386004B (en) Elevator landing is registered one's residence building and method of construction
KR101679180B1 (en) Method for constructing concrete lining of ventilation shaft tunnel
US3239990A (en) Multi-storey buildings
JP2021514437A (en) Shaft slip foam device and method
CN115298400A (en) Construction method
JP5417018B2 (en) How to install an elevator in an existing building
CN107178184A (en) Cantilever stair and its installation method
CN112012197A (en) Manual hole digging pile and construction method thereof
AU2019316713A1 (en) Method of erecting a multi-storey structure and facade
CN107100361A (en) Inner support aluminum dipping form device and its installation method are climbed outside a kind of
CN109610842B (en) Jacking concrete pumping construction method
CN114961335A (en) Demolition construction method for large-span reinforced concrete supporting beam
JP2014111891A (en) Building construction method, and underground skeleton of new building
JP6318382B2 (en) Evacuation device
KR102102593B1 (en) constructing level tunnel connecting part of vertical structure and apparatus thereof
KR20210141194A (en) Construction Method and Device of Wall and Floor Structure in Elevator's Machine Room in Apartment Building and Office Using Hanging Structural Method by Steel and Deck Plate in Top-down Structure
CN109208936B (en) Existing building elevator shaft structure additional construction structure and construction method thereof
CN207829329U (en) Cantilever stair
JP5150313B2 (en) Three-dimensional parking device in void and its construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right