KR102298436B1 - Vertical concrete structure and method for constructing the same - Google Patents

Vertical concrete structure and method for constructing the same Download PDF

Info

Publication number
KR102298436B1
KR102298436B1 KR1020210010948A KR20210010948A KR102298436B1 KR 102298436 B1 KR102298436 B1 KR 102298436B1 KR 1020210010948 A KR1020210010948 A KR 1020210010948A KR 20210010948 A KR20210010948 A KR 20210010948A KR 102298436 B1 KR102298436 B1 KR 102298436B1
Authority
KR
South Korea
Prior art keywords
slab
vertical wall
concrete
vertical
width direction
Prior art date
Application number
KR1020210010948A
Other languages
Korean (ko)
Inventor
한녹희
Original Assignee
주식회사 효명이씨에스
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 효명이씨에스 filed Critical 주식회사 효명이씨에스
Priority to KR1020210010948A priority Critical patent/KR102298436B1/en
Application granted granted Critical
Publication of KR102298436B1 publication Critical patent/KR102298436B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

Disclosed are a concrete vertical structure and a construction method thereof, which enable a PC slab to be strongly coupled to a vertical wall to improve anti-vibration stability, improve constructability by use of a temporary fixing device and application of a slip form method for holding the PC slab without installation of an additional bracket, reduce a construction period, and improve economic efficiency. The concrete vertical structure comprises: a vertical wall installed in a vertical direction on the ground or the underground; and the PC slab installed on an inner circumferential surface of the vertical wall in a horizontal direction. A connection space unit for post-application of concrete is formed between the PC slab and the vertical wall, a rebar for a connection unit is installed in the connection space unit, and the concrete is applied to enable the PC slab and the vertical wall to be strongly coupled.

Description

콘크리트 수직구조물 및 이의 시공방법{VERTICAL CONCRETE STRUCTURE AND METHOD FOR CONSTRUCTING THE SAME}Concrete vertical structure and its construction method

본 발명은 콘크리트 수직구조물 및 이의 시공방법에 관한 것으로서, 더욱 상세하게는 지중 전력구, 통신구, 지하철의 수직출입구, 연결통로 및 환기구 등의 콘크리트 수직구조물 및 이의 시공방법에 관한 것이다.The present invention relates to a concrete vertical structure and a construction method thereof, and more particularly, to a concrete vertical structure such as an underground power outlet, a communication port, a vertical entrance of a subway, a connecting passage and a ventilation opening, and a construction method thereof.

일반적으로, 지중 전력구, 통신구, 지하철의 수직출입구, 연결통로 및 환기구, 지하 저장시설 등에 있어서 다양한 콘크리트 수직구조물이 시공된다. 예를 들어, 지하철 선로 공사시 발생하는 각종 유해가스 및 미세먼지로 인한 오염을 방지하기 위하여 일정 구간마다 공기가 순환되도록 지상과 지하를 연결하는 통로를 의무적으로 갖추어야 한다.In general, various concrete vertical structures are constructed in underground power outlets, communication ports, vertical entrances and exits of subways, connecting passages and ventilation ports, underground storage facilities, and the like. For example, in order to prevent pollution due to various harmful gases and fine dust generated during subway line construction, it is mandatory to have a passage connecting the ground and the basement so that air is circulated at every predetermined section.

이러한 콘크리트 수직구조물의 시공방법을 일례로 설명하면, 먼저 지상에서 지하로 수직공을 굴착하고, 수직공의 내주면에 철구조물을 설치하거나 콘크리트 몰탈을 타설하여 수직터널 구조물이 붕괴하지 않도록 한 후에, 수직공의 바닥에서부터 철근을 배열하여 거푸집을 설치하고 기초콘크리트를 타설한 후에 기초콘크리트의 양생이 완료되면 거푸집을 해체하고 지상으로부터 폐자재를 수거하여 그 시공을 완료한다.To explain the construction method of such a concrete vertical structure as an example, first excavate a vertical hole from the ground to the basement, install a steel structure on the inner circumferential surface of the vertical hole, or pour concrete mortar to prevent the vertical tunnel structure from collapsing. After installing the formwork by arranging the reinforcing bars from the bottom of the craftsman and pouring the base concrete, when the base concrete is cured, the formwork is dismantled and the waste materials are collected from the ground to complete the construction.

한편, 선 출원된 대한민국 공개특허공보 제10-2009-0047575호(2009.05.13)에는 지중 수직터널 구조물용 슬립폼 및 이를 이용한 지중수직터널 구조물의 시공방법이 개시된 바 있다. 하지만, 종래의 콘크리트 수직구조물 및 이의 시공방법은 PC슬래브를 지지하기 위한 브라켓이 수직벽체에 추가 설치되어야 하므로 시공성이 좋지 못하고 공사기간이 오래 걸리며 경제성이 낮을 뿐 아니라 수직벽체와 PC슬래브가 강결접합되어 있지 않아서 내진 안전성이 떨어지는 문제점이 있다.Meanwhile, Korean Patent Laid-Open Publication No. 10-2009-0047575 (2009.05.13), which was previously applied for, discloses a slip form for an underground vertical tunnel structure and a construction method for an underground vertical tunnel structure using the same. However, in the conventional concrete vertical structure and its construction method, since a bracket for supporting the PC slab must be additionally installed on the vertical wall, the workability is poor, the construction period is long, the economic feasibility is low, and the vertical wall and the PC slab are rigidly joined. There is a problem that seismic safety is deteriorated because there is no seismic safety.

특허문헌 : 대한민국 공개특허공보 제10-2009-0047575호(2009.05.13)Patent Literature: Republic of Korea Patent Publication No. 10-2009-0047575 (2009.05.13)

이와 같은 종래의 문제점을 해결하기 위하여, 본 발명에서는 PC슬래브를 수직벽과 강결시킴으로써 내진 안전성을 개선하고 PC슬래브를 지지하는 별도의 브라켓 설치없이 PC슬래브를 거치하기 위한 임시고정장치 사용 및 슬립폼 공법 적용 등으로 시공성을 개선하며 공기단축 및 경제성을 향상시킬 수 있는 콘크리트 수직구조물 및 이의 시공방법을 제공한다.In order to solve the conventional problems, in the present invention, the seismic safety is improved by strengthening the PC slab with a vertical wall, and a temporary fixing device for mounting the PC slab without installing a separate bracket to support the PC slab is used and the slip form method To provide a concrete vertical structure that can improve constructability by application, etc., shorten construction period and improve economic feasibility, and a construction method thereof.

본 발명에 따른 콘크리트 수직구조물은 지상 또는 지하에 수직 방향으로 설치된 수직벽체와, 상기 수직벽체의 내주면에 수평 방향으로 설치되는 PC슬래브를 포함하는 콘크리트 수직구조물에 있어서, 상기 PC슬래브와 수직벽체 사이에 콘크리트 후타설을 위한 연결공간부가 형성되고, 상기 연결공간부에 연결부 보강근을 설치하고 콘크리트를 타설하여 PC슬래브와 수직벽체 사이를 강결한다.The concrete vertical structure according to the present invention is a concrete vertical structure including a vertical wall installed on the ground or underground in a vertical direction, and a PC slab installed in a horizontal direction on an inner circumferential surface of the vertical wall, between the PC slab and the vertical wall. A connection space is formed for concrete post-casting, and a connection reinforcing bar is installed in the connection space, and concrete is poured to strengthen the connection between the PC slab and the vertical wall.

상기 수직벽체에 커플러가 선매입되고, 상기 커플러에 헤디드바가 후설치되어 수직벽체와 PC슬래브가 강결된다.A coupler is pre-buried in the vertical wall, and a headed bar is installed in the coupler later, so that the vertical wall and the PC slab are rigidly connected.

상기 수직벽체에 커플러가 선매입되고, 상기 커플러에 연결부 보강근을 설치한 후 상기 연결부 보강근을 용접이음하거나 겹침이음하여 수직벽체와 PC슬래브가 강결된다.A coupler is pre-buried in the vertical wall, and after installing a connecting reinforcing bar in the coupler, the connecting reinforcing bar is welded or overlapped to strengthen the vertical wall and the PC slab.

상기 PC슬래브에 커플러가 선매입되고, 상기 PC슬래브의 커플러에 연결부 보강근을 설치하여 수직벽체에 설치된 연결부 보강근과 결합된다.A coupler is pre-buried in the PC slab, and a connection reinforcing bar is installed in the coupler of the PC slab to be coupled with the connecting reinforcing bar installed in the vertical wall.

또한, 수직벽체의 내주면과 마주하는 PC슬래브의 단부에 브라켓부가 돌출 형성되어, 상기 브라켓부가 연결공간부의 하부를 커버한다.In addition, a bracket portion is formed to protrude from the end of the PC slab facing the inner circumferential surface of the vertical wall, and the bracket portion covers the lower portion of the connection space portion.

상기 브라켓부의 단부에 경사지도록 모따기부가 형성되고, 상기 브라켓부의 단부와 수직벽체의 내벽면 사이에 이격부가 형성되며, 상기 이격부에 콘크리트의 유실을 방지하는 실링재가 삽입되되, 상기 실링재의 단면 형상은 상기 모따기부에 대응되도록 쐐기 형상으로 이루어진다.A chamfer is formed at the end of the bracket to be inclined, and a spacer is formed between the end of the bracket and the inner wall surface of the vertical wall, and a sealing material for preventing the loss of concrete is inserted into the spacer, the cross-sectional shape of the sealing material is It is made in a wedge shape to correspond to the chamfer.

상기 브라켓부에는, PC슬래브의 단면 및 브라켓부의 바닥면으로부터 수직하게 연장 형성된 하나 또는 복수개의 리브가 더 구비될 수 있다.The bracket part may further include one or a plurality of ribs extending vertically from the end surface of the PC slab and the bottom surface of the bracket part.

상기 PC슬래브와 수직벽체에 아이바 형태의 고정장치가 매입되어 구성되고, 상기 PC슬래브와 수직벽체의 고정장치에 길이조절이 가능한 봉부재가 연결되어 PC슬래브와 수직벽체 사이가 임시 고정된다.A fixing device in the form of an eye bar is embedded in the PC slab and the vertical wall, and a length-adjustable bar member is connected to the fixing device of the PC slab and the vertical wall to temporarily fix the PC slab and the vertical wall.

상기 PC슬래브는 폭 방향으로 복수개의 단위패널이 연결되어 폭 방향 양측에 위치하는 외측패널과 상기 외측패널 사이에 위치하는 내측패널로 구성되며, 상기 내측패널은 길이 방향으로 주철근이 1방향 배근되고, 상기 외측패널은, 내측패널과 마주하는 일부 구간에 길이 방향 및 폭 방향으로 주철근이 2방향 배근되며, 폭 방향 양측에 위치하는 다른 구간에 폭 방향으로 주철근이 1방향 배근된다.The PC slab is composed of an outer panel positioned on both sides in the width direction by connecting a plurality of unit panels in the width direction and an inner panel positioned between the outer panel, and the inner panel has main reinforcing bars reinforced in one direction in the longitudinal direction, In the outer panel, the main reinforcing bars are reinforced in two directions in the longitudinal direction and the width direction in some sections facing the inner panel, and the main reinforcing bars are reinforced in one direction in the width direction in other sections located on both sides in the width direction.

상기 PC슬래브는 폭 방향으로 복수개의 단위패널이 연결되어 폭 방향 양측에 위치하는 외측패널과 상기 외측패널 사이에 위치하는 내측패널로 구성되며, 내측패널 연결부의 수직벽체에는 길이 방향으로 연결부 보강근이 설치되고, 외측패널 연결부의 수직벽체에는, 내측패널과 마주하는 일부 구간에 길이 방향으로 연결부 보강근이 설치되며, 폭 방향 양측에 위치하는 다른 구간에 폭 방향으로 연결부 보강근이 설치된다.The PC slab is composed of an outer panel positioned on both sides in the width direction by connecting a plurality of unit panels in the width direction, and an inner panel positioned between the outer panel, and a connecting reinforcing bar is installed in the vertical wall of the inner panel connecting part in the longitudinal direction. And, on the vertical wall of the outer panel connection part, the connecting part reinforcing bar is installed in some sections facing the inner panel in the longitudinal direction, and the connecting part reinforcing bar is installed in the other section located on both sides in the width direction in the width direction.

상기 수직벽체의 내측에 하나 또는 복수개의 중간벽체를 더 구비할 수 있다.One or a plurality of intermediate walls may be further provided on the inside of the vertical wall.

상기 수직벽체 내측에 수직벽체와 수평 방향으로 연결되는 거더를 더 구비하고, 상기 거더는 PC슬래브를 지지한다.A girder connected to the vertical wall in a horizontal direction is further provided inside the vertical wall, and the girder supports the PC slab.

상기 PC슬래브의 단면은, 내부가 채워진 충실형, 내부에 공간부가 형성된 중공형, 상부가 요철 형태인 상향리브형, 하부가 요철 형태인 하향리브형 중 하나로 또는 이들의 조합으로 구성된다.The cross section of the PC slab is composed of one of a solid type with a filling inside, a hollow type with a space formed therein, an upward rib type with an uneven top, and a downward rib type with an uneven bottom, or a combination thereof.

한편, 본 발명에 따른 콘크리트 수직구조물의 시공방법은 수직벽체와 PC슬래브에 연결부 보강근을 설치하는 단계; 수직벽체와 PC슬래브 사이에 길이조절이 가능한 봉부재를 설치하여 PC슬래브를 수직벽체에 임시 거치하는 단계; 수직벽체의 내벽면과 PC슬래브의 브라켓부의 단부 사이는 일정 간격 이격시켜 실링재를 삽입하는 단계; 및 수직벽체와 PC슬래브 간의 연결공간부에 콘크리트를 후타설하여 강결하는 단계를 포함한다.On the other hand, the construction method of the concrete vertical structure according to the present invention comprises the steps of installing a connecting portion reinforcement to the vertical wall and the PC slab; Temporarily mounting the PC slab to the vertical wall by installing a length-adjustable bar member between the vertical wall and the PC slab; inserting a sealing material by spaced apart a predetermined distance between the inner wall surface of the vertical wall and the end of the bracket portion of the PC slab; And it includes the step of hardening by pouring concrete after the connection space between the vertical wall and the PC slab.

본 발명에 따른 콘크리트 수직구조물 및 이의 시공방법은 수직벽체와 PC슬래브를 강결접합하여 내진안전성을 개선하고 현장작업을 최소화하여 시공성을 개선하며 공기단축 및 경제성을 향상시킬 수 있을 뿐 아니라, 작업의 용이성 측면에서 유리하며 수직벽체와 PC슬래브 간의 고정상태를 안정적으로 구현할 수 있는 매우 유용한 발명이다.The concrete vertical structure and its construction method according to the present invention can improve seismic safety by rigidly bonding a vertical wall and a PC slab, minimize on-site work, improve workability, shorten construction period and improve economic feasibility, as well as ease of operation It is advantageous in terms of aspect and is a very useful invention that can stably implement the fixed state between the vertical wall and the PC slab.

또한, 본 발명에 따른 콘크리트 수직구조물 및 이의 시공방법은 PC슬래브와 수직벽체간 강결에 따른 힘의 흐름을 고려하여 PC슬래브 및 수직벽체와의 연결부 보강방향을 최적화 결정함으로써 구조안전성을 개선할 수 있다.In addition, the concrete vertical structure and its construction method according to the present invention can improve structural safety by optimizing and determining the reinforcement direction of the connection part between the PC slab and the vertical wall in consideration of the flow of force due to the rigidity between the PC slab and the vertical wall. .

도 1은 본 발명의 일 실시 예에 따른 콘크리트 수직구조물을 도시한 부분 절개 사시도이고,
도 2 및 도 3은 본 발명의 일 실시 예에 따른 수직벽체와 PC슬래브의 연결구조를 확대 도시한 단면도이며,
도 4 내지 도 6은 도 3의 변형 예에 따른 수직벽체와 PC슬래브의 연결구조를 확대 도시한 단면도이고,
도 7은 본 발명의 일 실시 예에 따른 실링재를 도시한 사시도이며,
도 8은 본 발명의 변형 예에 따른 PC슬래브를 도시한 사시도이고,
도 9는 본 발명의 변형 예에 따른 PC슬래브 단면을 도시한 것이며,
도 10은 본 발명의 일 실시 예에 따른 콘크리트 수직구조물의 평면도이며,
도 11은 본 발명의 일 실시 예에 따른 콘크리트 수직구조물의 PC슬래브 배근도 및 연결부를 도시한 평면도이고,
도 12는 본 발명의 일 실시 예에 따른 수직벽체와 PC슬래브 연결부 상세를 도시한 평면도이며,
도 13은 본 발명의 일 실시 예에 따른 PC슬래브의 배근도를 일부 도시한 평면도이고,
도 14는 도 1의 변형 예에 따른 콘크리트 수직구조물을 도시한 부분 절개 사시도이며,
도 15는 다른 변형 예에 따른 거더가 설치된 콘크리트 수직구조물의 사시도이고,
도 16은 또 다른 변형 예에 따른 거더가 설치된 콘크리트 수직구조물의 평면도이며,
도 17은 본 발명의 일 실시 예에 따른 PC슬래브간 전단연결을 도시한 단면도이고,
도 18은 본 발명의 변형 예에 따른 토핑콘크리트 타설을 통한 PC슬래브간 연결방법을 도시한 단면도이며,
도 19는 본 발명의 일 실시 예에 따른 콘크리트 수직구조물의 시공방법을 도시한 흐름도이다.
1 is a partially cut-away perspective view showing a concrete vertical structure according to an embodiment of the present invention;
2 and 3 are enlarged cross-sectional views illustrating a connection structure between a vertical wall and a PC slab according to an embodiment of the present invention;
4 to 6 are enlarged cross-sectional views illustrating the connection structure of the vertical wall and the PC slab according to the modified example of FIG. 3,
7 is a perspective view showing a sealing material according to an embodiment of the present invention,
8 is a perspective view showing a PC slab according to a modified example of the present invention;
9 shows a cross-section of a PC slab according to a modified example of the present invention,
10 is a plan view of a vertical concrete structure according to an embodiment of the present invention;
11 is a plan view showing a PC slab reinforcement and a connection part of a vertical concrete structure according to an embodiment of the present invention;
12 is a plan view showing details of a vertical wall and a PC slab connection part according to an embodiment of the present invention;
13 is a plan view partially showing a rearrangement view of a PC slab according to an embodiment of the present invention;
14 is a partially cut-away perspective view showing a vertical concrete structure according to a modification of FIG. 1;
15 is a perspective view of a concrete vertical structure provided with a girder according to another modified example;
16 is a plan view of a concrete vertical structure provided with a girder according to another modified example;
17 is a cross-sectional view showing a shear connection between PC slabs according to an embodiment of the present invention;
18 is a cross-sectional view showing a connection method between PC slabs through pouring topping concrete according to a modified example of the present invention;
19 is a flowchart illustrating a method of constructing a vertical concrete structure according to an embodiment of the present invention.

이하 첨부된 도면에 따라서 콘크리트 수직구조물 및 이의 시공방법의 기술적 구성을 상세히 설명하면 다음과 같다.Hereinafter, the technical configuration of the concrete vertical structure and its construction method will be described in detail according to the accompanying drawings.

도 1 내지 도 13을 참조하면, 본 발명의 일 실시 예에 따른 콘크리트 수직구조물은 수직벽체(10)와 PC슬래브(20)를 포함하여 이루어진다. 이하의 설명에서, 도 10의 좌우 방향이 길이 방향이며, 상하 방향이 폭 방향이다. 방향은 설명의 편의를 위해 임의로 설정한 것이다.1 to 13 , a concrete vertical structure according to an embodiment of the present invention includes a vertical wall 10 and a PC slab 20 . In the following description, the left-right direction in FIG. 10 is the longitudinal direction, and the up-down direction is the width direction. The direction is arbitrarily set for convenience of explanation.

수직벽체(10)는 지상 또는 지하에 수직 방향으로 설치되는 것으로서, 지하에 설치할 경우 지중에 수직터널공간을 굴착하여 형성하고 소정의 벽두께로 콘크리트를 타설하고 경화하여 형성할 수 있다. 바람직하게는, 수직벽체(10)는 슬립폼 공법을 적용하여 공기를 단축하고 시공성을 확보할 수 있다.The vertical wall 10 is installed on the ground or underground in a vertical direction, and when installed underground, it can be formed by excavating a vertical tunnel space in the ground, pouring concrete to a predetermined wall thickness, and hardening. Preferably, the vertical wall 10 can shorten the air and secure the workability by applying the slip-form method.

한편, 수직벽체(10)는 도 14에 도시된 것처럼 내측에 하나 또는 복수개의 중간벽체(19)를 더 포함할 수 있으며, 슬립폼 공법에만 한정받지 않고 그 밖의 다양한 공법으로 형성할 수 있다.On the other hand, the vertical wall 10 may further include one or a plurality of intermediate walls 19 on the inside as shown in FIG. 14 , and may be formed by various other methods without being limited only to the slip form method.

수직벽체(10)의 내부에는 미리 커플러(35) 및 아이바 형태의 고정장치(50)가 선매입된다. 커플러(35)는 높이 방향으로 단층 또는 복수개의 층으로 형성 가능하다. 고정장치(50)는 커플러(35)와 인접하게 배치되되, 커플러(35)보다 소정 높이 상부에 위치하도록 배치한다. A coupler 35 and a fixing device 50 in the form of an eye bar are pre-embedded in the vertical wall 10 in advance. The coupler 35 may be formed in a single layer or a plurality of layers in the height direction. The fixing device 50 is disposed adjacent to the coupler 35 , and disposed so as to be positioned above the coupler 35 by a predetermined height.

수직벽체(10)의 커플러(35)는 PC슬래브(20)에 매입된 커플러(30)와 함께 연결부 보강근(40)을 후설치하기 위한 것이며, 수직벽체(10)에 매입된 고정장치(50)는 길이조절이 가능한 봉부재(60)를 연결하기 위한 것이다. 예를 들어, 봉부재(60)는 턴버클로 구현될 수 있다. 수직벽체(10)의 고정장치(50)를 커플러(35)보다 상부에 위치시키고 적절히 그 이격거리를 조절하여 수직벽체(10)와 PC슬래브(20) 간의 임시 고정상태를 안정적으로 제어할 수 있다.The coupler 35 of the vertical wall 10 is for post-installation of the connector reinforcement 40 together with the coupler 30 embedded in the PC slab 20, and the fixing device 50 embedded in the vertical wall 10 is for connecting the length-adjustable rod member (60). For example, the rod member 60 may be implemented as a turnbuckle. The temporary fixing state between the vertical wall 10 and the PC slab 20 can be stably controlled by positioning the fixing device 50 of the vertical wall 10 above the coupler 35 and appropriately adjusting the separation distance therebetween. .

PC슬래브(20)는 수직벽체(10)의 내주면에 수평 방향으로 설치되는 것으로서, 전체적으로는 원판 형상이며 폭 방향으로 복수개의 단위패널이 연결되어 이루어진다. 즉, PC슬래브(20)는 폭 방향 양측에 위치하는 외측패널(22)과 외측패널(22) 사이에 위치하는 복수개의 내측패널(23)로 구성된다.The PC slab 20 is installed on the inner circumferential surface of the vertical wall 10 in the horizontal direction, and has a disk shape as a whole and a plurality of unit panels are connected in the width direction. That is, the PC slab 20 is composed of an outer panel 22 positioned on both sides in the width direction and a plurality of inner panels 23 positioned between the outer panel 22 .

PC슬래브(20)의 내부에도 수직벽체(10)에 선매입된 커플러(35) 및 고정장치(50)에 대응되도록 커플러(30) 및 고정장치가 선매입될 수 있다. 이와 같이, PC슬래브(20)와 수직벽체(10)에는 커플러가 선매입되고, 연결부 보강근(40)이 후설치되어 연결된다.The coupler 30 and the fixing device may be pre-buried in the PC slab 20 so as to correspond to the coupler 35 and the fixing device 50 pre-embedded in the vertical wall 10 . In this way, the coupler is pre-buried in the PC slab 20 and the vertical wall 10, and the connecting part reinforcing bar 40 is installed and connected afterwards.

이 경우, PC슬래브(20)와 수직벽체(10) 사이에 연결공간부(72)가 형성된다. 연결공간부(72)는 콘크리트 후타설을 위한 공간이다. 수직벽체(10)의 내주면과 마주하는 PC슬래브(20)의 단부에 브라켓부(25)가 돌출 형성된다. 즉, 브라켓부(25)는 내민받침부로서, PC슬래브(20)의 하측 단부에서 수직벽체(10)를 향해 연장 형성되어, 연결공간부(72)의 하부를 커버한다.In this case, the connection space 72 is formed between the PC slab 20 and the vertical wall 10 . The connection space 72 is a space for concrete post-casting. A bracket portion 25 is formed to protrude from the end of the PC slab 20 facing the inner circumferential surface of the vertical wall 10 . That is, the bracket part 25 is a push-resistant support part, and extends from the lower end of the PC slab 20 toward the vertical wall 10 to cover the lower part of the connection space part 72 .

브라켓부(25)의 길이 방향 단부에는 경사진 형상의 모따기부(26)가 형성된다. 아울러, 브라켓부(25)의 단부와 수직벽체(10)의 내벽면 사이에 소정 간격을 띄워 공간을 형성한 이격부(71)가 형성된다. 이와 같이, 브라켓부(25)의 단부와 수직벽체(10)의 내벽면 사이에 이격부(71)를 형성함에 따라, 시공성을 향상시킬 수 있다.An inclined chamfer 26 is formed at an end of the bracket part 25 in the longitudinal direction. In addition, a spaced portion 71 is formed with a predetermined distance between the end of the bracket portion 25 and the inner wall surface of the vertical wall 10 to form a space. In this way, by forming the spaced portion 71 between the end of the bracket portion 25 and the inner wall surface of the vertical wall 10, it is possible to improve the workability.

또한, 이격부(71)에는 실링재(80)가 삽입된다. 실링재(80)는 콘크리트의 유실을 방지하는 것으로서, 선제작되어 브라켓부(25)의 단부와 수직벽체(10)의 내벽면 사이의 틈을 메워 콘크리트를 타설하기 위한 사전 준비를 마무리한다. 실링재(80)의 단면 형상은 브라켓부(25)의 모따기부(26)에 대응되도록 쐐기 형상으로 이루어진 쐐기부(81)를 갖는다.In addition, the sealing material 80 is inserted into the separation portion 71 . The sealing material 80 is to prevent the loss of concrete, and is pre-fabricated to fill the gap between the end of the bracket part 25 and the inner wall surface of the vertical wall 10 to complete the preliminary preparation for pouring concrete. The cross-sectional shape of the sealing material 80 has a wedge portion 81 formed in a wedge shape to correspond to the chamfer portion 26 of the bracket portion 25 .

실링재(80)의 쐐기부(81)는 브라켓부(25)의 모따기부(26)에 걸려 실링재(80)가 브라켓부(25)의 하부로 이탈하지 않고 결합이 이루어진다. 한편, 수직벽체(10)와 PC슬래브(20) 사이에 형성된 연결공간부(72)에 콘크리트를 타설하여 PC슬래브(20)와 수직벽체(10) 사이를 강결한다. 이와 같이, PC슬래브(20)와 수직벽체(10) 사이에 강결부(90)를 형성함에 따라, 내진안전성을 개선하고 시공성을 개선하며 공기단축 및 경제성을 향상시킬 수 있다.The wedge portion 81 of the sealing material 80 is caught by the chamfer 26 of the bracket portion 25 , and the sealing material 80 is coupled without leaving the lower portion of the bracket portion 25 . On the other hand, concrete is poured into the connection space 72 formed between the vertical wall 10 and the PC slab 20 to strengthen the connection between the PC slab 20 and the vertical wall 10 . In this way, by forming the rigid portion 90 between the PC slab 20 and the vertical wall 10, it is possible to improve seismic safety, improve workability, shorten construction period, and improve economic efficiency.

또한, 전술한 바와 같이, PC슬래브(20)와 수직벽체(10)에 고정장치(50)가 매입되어 구성된다. 아울러, PC슬래브(20)와 수직벽체(10)의 고정장치(50)에 봉부재(60)가 연결되어 PC슬래브(20)와 수직벽체(10) 사이가 임시 고정된다. 봉부재(60)는 PC슬래브(20)와 수직벽체(10) 간의 콘크리트 강결이 완료되면 제거된다. 이와 같이 PC슬래브(20)와 수직벽체(10) 간의 임시 고정 및 해체를 선매입된 고정장치(50) 및 봉부재(60)를 통해 구현함으로써, 시공의 용이성을 제공하고 공기 단축에 일조하게 된다.In addition, as described above, the fixing device 50 is embedded in the PC slab 20 and the vertical wall 10 . In addition, the bar member 60 is connected to the fixing device 50 of the PC slab 20 and the vertical wall 10 to temporarily fix the PC slab 20 and the vertical wall 10 . The bar member 60 is removed when the concrete hardening between the PC slab 20 and the vertical wall 10 is completed. As such, by implementing the temporary fixing and dismantling between the PC slab 20 and the vertical wall 10 through the pre-buried fixing device 50 and the rod member 60, it provides ease of construction and contributes to shortening the construction period. .

한편, 수직벽체(10)와 PC슬래브(20)의 사이에 형성되는 연결공간부(72)에 연결부 보강근(40)을 설치하고 콘크리트를 타설하여 PC슬래브(20)와 수직벽체(10) 사이가 강결된다. 이 경우, 연결부 보강근(40)의 결합구조는 헤디드바 결합구조, 용접이음, 겹침이음 등의 방법으로 구현될 수 있다.On the other hand, the connection part reinforcement 40 is installed in the connection space 72 formed between the vertical wall 10 and the PC slab 20, and concrete is poured, so that there is a gap between the PC slab 20 and the vertical wall 10. is hardened In this case, the coupling structure of the connecting part reinforcing bar 40 may be implemented by a method such as a headed bar coupling structure, a welding joint, or an overlapping joint.

즉, 도 3에 도시된 것처럼, 수직벽체(10)에 커플러(35)가 선매입되고 커플러(35)에 헤디드바 등으로 구성된 연결부 보강근(40)이 후설치되며, PC슬래브(20)에도 커플러(30)가 선매입되고 커플러(30)에 헤디드바 등으로 구성된 연결부 보강근(40)이 설치되어, 수직벽체(10)와 PC슬래브(20)에 각각 설치된 헤디드바 등의 연결부 보강근(40)의 결합을 통해 수직벽체(10)와 PC슬래브(20)가 연결된다.That is, as shown in FIG. 3 , the coupler 35 is pre-buried in the vertical wall 10 , and the connection part reinforcing bar 40 composed of a headed bar or the like is installed in the coupler 35 afterward, and also in the PC slab 20 . The coupler 30 is pre-buried and the connection part reinforcement 40 composed of a headed bar is installed in the coupler 30, and the connection part reinforcement such as a headed bar installed in the vertical wall 10 and the PC slab 20, respectively ( 40), the vertical wall 10 and the PC slab 20 are connected.

또한, 도 4에 도시된 것처럼, 수직벽체(10)에 커플러(35)가 선매입되고 커플러(35)에 헤디드바 등으로 구성된 연결부 보강근(40)이 후설치되며, PC슬래브(20)에는 커플러를 선매입하지 않고 PC슬래브(20)에 형성된 헤디드바 등으로 구성된 연결부 보강근(40)의 결합을 통해 수직벽체(10)와 PC슬래브(20)가 연결되는 것도 가능하다.In addition, as shown in Fig. 4, the coupler 35 is pre-buried in the vertical wall 10, and the connection part reinforcing bar 40 composed of a headed bar, etc. is installed in the coupler 35 afterward, and the PC slab 20 has It is also possible to connect the vertical wall 10 and the PC slab 20 through the coupling of the connecting part reinforcing bar 40 composed of a headed bar formed on the PC slab 20 without pre-buying the coupler.

아울러, 도 5에 도시된 것처럼, 수직벽체(10)에 커플러(35)가 선매입되고, 커플러(35)에 연결부 보강근(40)을 설치한 후 연결부 보강근(40)을 용접이음하여 용접이음부(45)를 형성함으로써 수직벽체(10)와 PC슬래브(20)가 연결되는 것도 가능하다.In addition, as shown in FIG. 5 , the coupler 35 is pre-buried in the vertical wall 10 , and after installing the connector reinforcing bar 40 in the coupler 35 , the connecting reinforcing bar 40 is welded to the welded joint. It is also possible to connect the vertical wall 10 and the PC slab 20 by forming (45).

또한, 도 6에 도시된 것처럼, 수직벽체(10)에 커플러(35)가 선매입되고, 커플러(35)에 연결부 보강근(40)을 설치한 후 연결부 보강근(40)을 겹침이음하여 겹침이음부(46)를 형성함으로써 수직벽체(10)와 PC슬래브(20)가 연결되는 것도 가능하다.In addition, as shown in FIG. 6 , the coupler 35 is pre-embedded in the vertical wall 10 , and after installing the connecting portion reinforcing bar 40 in the coupler 35 , the connecting reinforcing bar 40 is overlapped to overlap the joint. It is also possible to connect the vertical wall 10 and the PC slab 20 by forming (46).

한편, 도 8에 도시된 것처럼, 브라켓부(25)에는 하나 또는 복수개의 리브(27)가 더 구비될 수 있다. 리브(27)는 도시된 것처럼, PC슬래브(20)의 조건에 따라 적절히 그 개수를 가감할 수 있다. 리브(27)는 PC슬래브(20)의 단면 및 브라켓부(25)의 바닥면으로부터 수직하게 연장 형성된다. 리브(27)는 브라켓부(25)의 강성을 보강하고 파손을 방지하는 기능을 한다.Meanwhile, as shown in FIG. 8 , one or a plurality of ribs 27 may be further provided in the bracket unit 25 . As shown, the number of ribs 27 may be appropriately increased or decreased according to the conditions of the PC slab 20 . The rib 27 is formed to extend vertically from the end surface of the PC slab 20 and the bottom surface of the bracket part 25 . The rib 27 serves to reinforce the rigidity of the bracket part 25 and prevent damage.

또한, 도 9에 도시된 것처럼, PC슬래브(20)의 단면은, 내부가 채워진 충실형, 내부에 공간부가 형성된 중공형, 상부가 요철 형태인 상향리브형, 하부가 요철 형태인 하향리브형 중 하나로 또는 이들의 조합으로 구성될 수 있다.In addition, as shown in FIG. 9 , the cross section of the PC slab 20 is of a solid type with a filling inside, a hollow type with a space formed therein, an upward rib type with an uneven top, and a downward rib type with an uneven shape at the bottom. It may consist of one or a combination thereof.

한편, 내측패널(23)은 수직벽체와의 강결에 따른 응력 흐름을 고려하여, 길이 방향으로 주철근(21)이 1방향 배근된다. 아울러, 외측패널(22)은, 수직벽체와의 강결에 따른 응력 흐름을 고려하여, 내측패널(23)과 마주하는 일부 구간(S2)에 길이 방향 및 폭 방향으로 주철근(21)이 2방향 배근되며, 폭 방향 양측에 위치하는 다른 구간(S1)에 폭 방향으로 주철근(21)이 1방향 배근된다.On the other hand, in the inner panel 23, the main reinforcing bars 21 are reinforced in one direction in the longitudinal direction in consideration of the stress flow due to the rigidity with the vertical wall. In addition, in the outer panel 22, in consideration of the stress flow due to the rigidity with the vertical wall, the main reinforcing bars 21 are reinforced in two directions in the longitudinal and width directions in some section S2 facing the inner panel 23. and the main reinforcing bars 21 are reinforced in one direction in the width direction in another section S1 located on both sides in the width direction.

또한, 내측패널(23) 연결부의 수직벽체(10)는 수직벽체와의 강결에 따른 응력 흐름을 고려하여, 길이 방향으로 연결부 보강근(40)이 설치된다. 아울러, 외측패널(22) 연결부의 수직벽체(10)는, 수직벽체와의 강결에 따른 응력 흐름을 고려하여, 내측패널(23)과 마주하는 일부 구간(S2)에 길이 방향으로 연결부 보강근(40)이 설치되며, 폭 방향 양측에 위치하는 다른 구간(S1)에 폭 방향으로 연결부 보강근(40)이 설치된다.In addition, in the vertical wall 10 of the connecting portion of the inner panel 23, the connecting reinforcing bar 40 is installed in the longitudinal direction in consideration of the stress flow due to the rigidity with the vertical wall. In addition, the vertical wall 10 of the connection part of the outer panel 22 is longitudinally connected to the reinforcing bar 40 in a partial section S2 facing the inner panel 23 in consideration of the stress flow due to rigidity with the vertical wall. ) is installed, and the connecting part reinforcing bar 40 is installed in the other section (S1) located on both sides in the width direction in the width direction.

이 경우, 폭 방향 양측에 위치하는 다른 구간(S1)은 수직벽체(10)의 내경(D)의 대략 10분의 1인 0.1D의 직경으로 구간 범위를 설정할 수 있다. 상기 S1 구간의 직경 범위는 적절히 설계 변경 가능하다. 상기 S2 구간은 응력의 흐름이 양방향으로 발생한다. 즉, 내측패널(23)과 마주하는 일부 구간(S2)에서는 길이 방향 및 폭 방향으로 응력이 발생한다.In this case, the other sections S1 located on both sides in the width direction may set the section range to a diameter of 0.1D, which is approximately 1/10 of the inner diameter D of the vertical wall 10 . The diameter range of the S1 section can be appropriately changed in design. In the S2 section, the flow of stress occurs in both directions. That is, in the partial section S2 facing the inner panel 23, stress is generated in the longitudinal direction and the width direction.

한편, PC슬래브(20)에 작용하는 힘을 해석해보면, PC슬래브(20)와 수직벽체(10) 간의 콘크리트 강결 후에 내측패널(23)은 길이 방향으로 힘을 크게 받으며, 외측패널(22)은 캔틸레버처럼 작용을 하여 폭 방향으로 힘을 크게 받는다. 외측패널(22) 중 S1 구간에는 기본적으로 폭 방향으로 주철근이 촘촘하게 배근된다. 아울러, 외측패널(22)의 S2 구간은 길이 방향으로 크게 힘이 작용하는 구간으로서, 연결부 보강근(40)도 길이 방향으로 설치되며, 주철근도 길이 방향으로 촘촘하게 배근된다.On the other hand, if the force acting on the PC slab 20 is analyzed, the inner panel 23 receives a large force in the longitudinal direction after concrete hardening between the PC slab 20 and the vertical wall 10, and the outer panel 22 is It acts like a cantilever and receives a large force in the width direction. In the S1 section of the outer panel 22, the main reinforcing bars are densely reinforced in the width direction. In addition, the section S2 of the outer panel 22 is a section in which a large force is applied in the longitudinal direction, and the connecting reinforcing bars 40 are also installed in the longitudinal direction, and the main reinforcing bars are also densely reinforced in the longitudinal direction.

또한, 도 15 및 도 16을 더 참조하면, 수직벽체(10) 내측에 수직벽체(10)와 수평 방향으로 연결되는 거더(99)를 더 구비할 수 있다. 거더(99)는 PC슬래브(20)를 지지하는 것으로, 계단 또는 환기덕트 등의 설치로 인해 PC슬래브(20) 내부에 개구부(98)가 필요할 경우 개구부(98) 주변으로 거더(99)를 수직벽체(10)와 연결 설치하여, PC슬래브(20)를 지지하도록 함으로써 개구부(98) 주변 PC슬래브(20)의 구조안전성을 확보할 수 있다.In addition, referring further to FIGS. 15 and 16 , a girder 99 connected to the vertical wall 10 in the horizontal direction may be further provided inside the vertical wall 10 . The girder 99 supports the PC slab 20, and when the opening 98 is required inside the PC slab 20 due to the installation of stairs or ventilation ducts, the girder 99 is vertically installed around the opening 98. By connecting and installing the wall 10 to support the PC slab 20, the structural safety of the PC slab 20 around the opening 98 can be secured.

아울러, 도 17에 도시된 것처럼, PC슬래브(20) 간의 연결은 PC슬래브(20) 간의 마주하는 단면부에 요입 형성된 홈을 형성하고, PC슬래브(20) 사이에 시멘트밀크 그라우팅 등을 통해 전단연결부(97)를 형성하여 이루어질 수 있다. 한편, 도 18에 도시된 것처럼, PC슬래브(20)의 다양한 단면 구조에 있어서 PC슬래브(20) 간의 연결시 PC슬래브(20)의 상부에 토핑콘크리트(28)가 타설되는 것도 가능하다. 또한, 전술한 PC슬래브(20)의 구조와는 별개로, PC슬래브(20)에 프리스트레스를 도입하는 것도 가능하다.In addition, as shown in FIG. 17 , the connection between the PC slabs 20 forms a recess formed in the cross-section facing the PC slabs 20, and the shear connection part through cement milk grouting, etc. between the PC slabs 20 (97) may be formed. On the other hand, as shown in FIG. 18 , in various cross-sectional structures of the PC slab 20 , it is also possible that the topping concrete 28 is poured on the PC slab 20 when the PC slabs 20 are connected. In addition, it is also possible to introduce a prestress to the PC slab 20 separately from the structure of the PC slab 20 described above.

도 19를 더 참조하면, 본 발명의 일 실시 예에 따른 콘크리트 수직구조물의 시공방법은 수직벽체(10)와 PC슬래브(20)에 연결부 보강근(40)을 설치하는 단계와, 길이조절이 가능한 봉부재(60)를 이용해 PC슬래브(20)를 수직벽체(10) 내부에 임시 거치하는 단계와, 실링재(80) 삽입 단계와, 연결공간부(72)에 콘크리트를 타설해 강결하는 단계와, PC슬래브간의 연결 단계를 포함하여 이루어진다.Referring further to FIG. 19 , the construction method of a concrete vertical structure according to an embodiment of the present invention includes the steps of installing a connecting part reinforcing bar 40 on the vertical wall 10 and the PC slab 20 , and a rod with adjustable length. The step of temporarily mounting the PC slab 20 in the vertical wall 10 using the member 60, the step of inserting the sealing material 80, the step of pouring concrete into the connection space 72, and the PC It is made including the step of connecting the slabs.

먼저, 수직벽체(10)와 PC슬래브(20)에 커플러(35,30)를 매입한 후에, 연결부 보강근(40)을 후설치하는 단계를 수행한다. 이후에, 수직벽체(10)와 PC슬래브(20) 사이에 봉부재(60)을 설치하여, PC슬래브(20)를 수직벽체(10)에 임시 거치한다. 이후에, 수직벽체(10)의 내벽면과 PC슬래브(20)의 브라켓부(25)의 단부 사이는 일정 간격 이격시켜 실링재(80)를 삽입한다.First, after embedding the couplers 35 and 30 in the vertical wall 10 and the PC slab 20, a step of post-installing the connecting reinforcing bar 40 is performed. Thereafter, the bar member 60 is installed between the vertical wall 10 and the PC slab 20 , and the PC slab 20 is temporarily mounted on the vertical wall 10 . Thereafter, the sealing material 80 is inserted between the inner wall surface of the vertical wall 10 and the end of the bracket portion 25 of the PC slab 20 by a predetermined interval.

이후에, 수직벽체(10)와 PC슬래브(20) 간의 연결부를 콘크리트로 후타설하여 강결한다. 이후에, 외측패널(22)과 내측패널(23)들을 서로 전단 연결하는 단계를 수행한다. 상기에서, 수직벽체(10)의 시공은 슬립폼 공법을 적용하여 공기를 단축하고 시공성을 확보할 수 있다.Thereafter, the connection portion between the vertical wall 10 and the PC slab 20 is reinforced by pouring concrete afterward. Thereafter, a step of shear connecting the outer panel 22 and the inner panel 23 to each other is performed. In the above, the construction of the vertical wall 10 can be performed by applying the slip-form method to shorten the air and secure the workability.

지금까지 본 발명에 따른 콘크리트 수직구조물 및 이의 시공방법은 도면에 도시된 실시 예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 당업자라면 누구든지 이로부터 다양한 변형 및 균등한 다른 실시 예가 가능하다는 점을 이해할 것이다. 따라서, 진정한 기술적 보호 범위는 첨부된 특허청구범위의 기술적 사상에 의하여 정해져야 할 것이다.Up to now, the concrete vertical structure and its construction method according to the present invention have been described with reference to the embodiments shown in the drawings, but these are merely exemplary, and it is understood that various modifications and equivalent other embodiments are possible by anyone skilled in the art. will understand Accordingly, the true technical protection scope should be determined by the technical spirit of the appended claims.

10: 수직벽체 20: PC슬래브
21: 주철근 22: 외측패널
23: 내측패널 25: 브라켓부
26: 모따기부 27: 리브
28: 토핑콘크리트 30,35: 커플러
40: 연결부 보강근 45: 용접이음부
46: 겹침이음부 50: 고정장치
60: 봉부재 71: 이격부
72: 연결공간부 80: 실링재
81: 쐐기부 90: 강결부
10: vertical wall 20: PC slab
21: main reinforcing bar 22: outer panel
23: inner panel 25: bracket part
26: chamfer 27: rib
28: topping concrete 30,35: coupler
40: connection reinforcing bar 45: welded joint
46: overlap joint 50: fixing device
60: bar member 71: spaced part
72: connection space 80: sealing material
81: wedge portion 90: rigid portion

Claims (14)

지상 또는 지하에 수직 방향으로 설치된 수직벽체와, 상기 수직벽체의 내주면에 수평 방향으로 설치되는 PC슬래브를 포함하는 콘크리트 수직구조물에 있어서,
상기 PC슬래브와 수직벽체 사이에 콘크리트 후타설을 위한 연결공간부가 형성되고, 상기 연결공간부에 연결부 보강근을 설치하고 콘크리트를 타설하여 PC슬래브와 수직벽체 사이를 강결하며,
수직벽체의 내주면과 마주하는 PC슬래브의 단부에 브라켓부가 돌출 형성되어, 상기 브라켓부가 연결공간부의 하부를 커버하며,
상기 브라켓부의 단부에 경사지도록 모따기부가 형성되고, 상기 브라켓부의 단부와 수직벽체의 내벽면 사이에 이격부가 형성되며, 상기 이격부에 콘크리트의 유실을 방지하는 실링재가 삽입되되, 상기 실링재의 단면 형상은 상기 모따기부에 대응되도록 쐐기 형상으로 이루어지는 콘크리트 수직구조물.
In the concrete vertical structure comprising a vertical wall installed in the vertical direction on the ground or underground, and a PC slab installed in the horizontal direction on the inner circumferential surface of the vertical wall,
A connection space for concrete post-casting is formed between the PC slab and the vertical wall, and a connection reinforcing bar is installed in the connection space and concrete is poured to strengthen the connection between the PC slab and the vertical wall,
A bracket part is formed to protrude from the end of the PC slab facing the inner circumferential surface of the vertical wall, and the bracket part covers the lower part of the connection space,
A chamfer is formed at the end of the bracket to be inclined, and a spacer is formed between the end of the bracket and the inner wall surface of the vertical wall, and a sealing material for preventing the loss of concrete is inserted into the spacer, the cross-sectional shape of the sealing material is A concrete vertical structure formed in a wedge shape to correspond to the chamfer.
제1 항에 있어서,
상기 수직벽체에 커플러가 선매입되고, 상기 커플러에 헤디드바가 후설치되어 수직벽체와 PC슬래브가 강결되는 콘크리트 수직구조물.
The method of claim 1,
A concrete vertical structure in which a coupler is pre-buried in the vertical wall, and a headed bar is installed in the coupler after the vertical wall and the PC slab are rigidly connected.
제1 항에 있어서,
상기 수직벽체에 커플러가 선매입되고, 상기 커플러에 연결부 보강근을 설치한 후 상기 연결부 보강근을 용접이음하거나 겹침이음하여 수직벽체와 PC슬래브가 강결되는 콘크리트 수직구조물.
The method of claim 1,
A concrete vertical structure in which a coupler is pre-buried in the vertical wall, and a connection reinforcing bar is installed in the coupler, and then the connection reinforcing bar is welded or overlapped to strengthen the vertical wall and the PC slab.
제2 항 또는 제3 항에 있어서,
상기 PC슬래브에 커플러가 선매입되고, 상기 PC슬래브의 커플러에 연결부 보강근을 설치하여 수직벽체에 설치된 연결부 보강근과 결합되는 콘크리트 수직구조물.
4. The method of claim 2 or 3,
A concrete vertical structure in which a coupler is pre-buried in the PC slab, and a connection reinforcing bar is installed in the coupler of the PC slab to be combined with a connecting reinforcing bar installed in a vertical wall.
삭제delete 삭제delete 제1 항에 있어서,
상기 브라켓부에는,
PC슬래브의 단면 및 브라켓부의 바닥면으로부터 수직하게 연장 형성된 하나 또는 복수개의 리브가 더 구비되는 콘크리트 수직구조물.
The method of claim 1,
In the bracket part,
A concrete vertical structure further comprising one or a plurality of ribs extending vertically from the cross-section of the PC slab and the bottom surface of the bracket.
제1 항 내지 제3 항 중 어느 한 항에 있어서,
상기 PC슬래브와 수직벽체에 아이바 형태의 고정장치가 매입되어 구성되고, 상기 PC슬래브와 수직벽체의 고정장치에 길이조절이 가능한 봉부재가 연결되어 PC슬래브와 수직벽체 사이가 임시 고정되는 콘크리트 수직구조물.
4. The method according to any one of claims 1 to 3,
A concrete vertical structure in which a fixing device in the form of an eye bar is embedded in the PC slab and the vertical wall, and a rod member capable of adjusting the length is connected to the fixing device of the PC slab and the vertical wall to temporarily fix the PC slab and the vertical wall .
제1 항 내지 제3 항 중 어느 한 항에 있어서,
상기 PC슬래브는 폭 방향으로 복수개의 단위패널이 연결되어 폭 방향 양측에 위치하는 외측패널과 상기 외측패널 사이에 위치하는 내측패널로 구성되며,
상기 내측패널은 길이 방향으로 주철근이 1방향 배근되고,
상기 외측패널은, 내측패널과 마주하는 일부 구간에 길이 방향 및 폭 방향으로 주철근이 2방향 배근되며, 폭 방향 양측에 위치하는 다른 구간에 폭 방향으로 주철근이 1방향 배근되는 콘크리트 수직구조물.
4. The method according to any one of claims 1 to 3,
The PC slab is composed of an outer panel located on both sides in the width direction by connecting a plurality of unit panels in the width direction, and an inner panel located between the outer panel,
In the inner panel, main reinforcing bars are reinforced in one direction in the longitudinal direction,
The outer panel is a concrete vertical structure in which the main reinforcing bars are reinforced in two directions in the longitudinal direction and the width direction in some sections facing the inner panel, and the main rebars are reinforced in one direction in the width direction in other sections located on both sides in the width direction.
제1 항 내지 제3 항 중 어느 한 항에 있어서,
상기 PC슬래브는 폭 방향으로 복수개의 단위패널이 연결되어 폭 방향 양측에 위치하는 외측패널과 상기 외측패널 사이에 위치하는 내측패널로 구성되며,
내측패널 연결부의 수직벽체에는 길이 방향으로 연결부 보강근이 설치되고,
외측패널 연결부의 수직벽체에는, 내측패널과 마주하는 일부 구간에 길이 방향으로 연결부 보강근이 설치되며, 폭 방향 양측에 위치하는 다른 구간에 폭 방향으로 연결부 보강근이 설치되는 콘크리트 수직구조물.
4. The method according to any one of claims 1 to 3,
The PC slab is composed of an outer panel located on both sides in the width direction by connecting a plurality of unit panels in the width direction, and an inner panel located between the outer panel,
On the vertical wall of the inner panel connection part, the connection part reinforcing bar is installed in the longitudinal direction,
In the vertical wall of the outer panel connection part, the connecting part reinforcing bars are installed in some sections facing the inner panel in the longitudinal direction, and the connecting part reinforcing bars are installed in the other sections located on both sides in the width direction in the width direction.
제1 항 내지 제3 항 중 어느 한 항에 있어서,
상기 수직벽체의 내측에 하나 또는 복수개의 중간벽체를 더 구비하는 콘크리트 수직구조물.
4. The method according to any one of claims 1 to 3,
Concrete vertical structure further comprising one or a plurality of intermediate walls on the inside of the vertical wall.
제1 항 내지 제3 항 중 어느 한 항에 있어서,
상기 수직벽체 내측에 수직벽체와 수평 방향으로 연결되는 거더를 더 구비하고, 상기 거더는 PC슬래브를 지지하는 콘크리트 수직구조물.
4. The method according to any one of claims 1 to 3,
A concrete vertical structure further comprising a girder connected to the vertical wall in a horizontal direction inside the vertical wall, wherein the girder supports the PC slab.
제1 항 내지 제3 항 중 어느 한 항에 있어서,
상기 PC슬래브의 단면은,
내부가 채워진 충실형, 내부에 공간부가 형성된 중공형, 상부가 요철 형태인 상향리브형, 하부가 요철 형태인 하향리브형 중 하나로 또는 이들의 조합으로 구성되는 콘크리트 수직구조물.
4. The method according to any one of claims 1 to 3,
The cross section of the PC slab is
A concrete vertical structure composed of one of a solid type with a filling inside, a hollow type with a space formed inside, an upward rib type with an uneven top, and a downward rib type with an uneven bottom, or a combination thereof.
삭제delete
KR1020210010948A 2021-01-26 2021-01-26 Vertical concrete structure and method for constructing the same KR102298436B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210010948A KR102298436B1 (en) 2021-01-26 2021-01-26 Vertical concrete structure and method for constructing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210010948A KR102298436B1 (en) 2021-01-26 2021-01-26 Vertical concrete structure and method for constructing the same

Publications (1)

Publication Number Publication Date
KR102298436B1 true KR102298436B1 (en) 2021-09-06

Family

ID=77782289

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210010948A KR102298436B1 (en) 2021-01-26 2021-01-26 Vertical concrete structure and method for constructing the same

Country Status (1)

Country Link
KR (1) KR102298436B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115163924A (en) * 2022-08-05 2022-10-11 福州轨道交通设计院有限公司 Integrated support combined with subway assembled wallboard body system and anti-seismic support
KR20230077254A (en) * 2021-11-25 2023-06-01 디엘이앤씨 주식회사 Construction method of underground structure using large form

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060117746A (en) * 2005-05-13 2006-11-17 삼성중공업 주식회사 A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR20090047575A (en) 2007-11-08 2009-05-13 주식회사 형주엔지니어링 Slip form for concrete lining of shaft tunnel and method constructing concrete lining of shaft tunnel
KR20110132910A (en) * 2010-06-03 2011-12-09 김원근 Underpass using precast concrete pile and bottom slab and method for constructing the same
KR20160083659A (en) * 2015-01-02 2016-07-12 고엄식 Vertical tunnel construction and constructing method for the same
KR101703946B1 (en) * 2016-01-15 2017-02-23 (주)골든엔지니어링 Girdir support structure and top down construction method using the same
KR101899442B1 (en) * 2018-02-05 2018-09-17 정도건설산업 (주) PC slab with inclined end plate
KR102182536B1 (en) * 2019-10-10 2020-11-24 동서 피, 씨, 씨 주식회사 Combined structure of precast columns and beams for construction of warehouse, precast beams used for the same

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060117746A (en) * 2005-05-13 2006-11-17 삼성중공업 주식회사 A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR20090047575A (en) 2007-11-08 2009-05-13 주식회사 형주엔지니어링 Slip form for concrete lining of shaft tunnel and method constructing concrete lining of shaft tunnel
KR20110132910A (en) * 2010-06-03 2011-12-09 김원근 Underpass using precast concrete pile and bottom slab and method for constructing the same
KR20160083659A (en) * 2015-01-02 2016-07-12 고엄식 Vertical tunnel construction and constructing method for the same
KR101703946B1 (en) * 2016-01-15 2017-02-23 (주)골든엔지니어링 Girdir support structure and top down construction method using the same
KR101899442B1 (en) * 2018-02-05 2018-09-17 정도건설산업 (주) PC slab with inclined end plate
KR102182536B1 (en) * 2019-10-10 2020-11-24 동서 피, 씨, 씨 주식회사 Combined structure of precast columns and beams for construction of warehouse, precast beams used for the same

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20230077254A (en) * 2021-11-25 2023-06-01 디엘이앤씨 주식회사 Construction method of underground structure using large form
KR102546703B1 (en) 2021-11-25 2023-06-21 디엘이앤씨 주식회사 Construction method of underground structure using large form
CN115163924A (en) * 2022-08-05 2022-10-11 福州轨道交通设计院有限公司 Integrated support combined with subway assembled wallboard body system and anti-seismic support
CN115163924B (en) * 2022-08-05 2024-05-28 福州轨道交通设计院有限公司 Comprehensive support combined with subway assembled wallboard system and anti-seismic support

Similar Documents

Publication Publication Date Title
KR101331261B1 (en) Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same
KR100634726B1 (en) Form system for construction of underground slab and method for constructing underground slab and breast wall using the same
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
KR102298436B1 (en) Vertical concrete structure and method for constructing the same
KR101687495B1 (en) Partial top-down construction method for building underground structures
JP5619646B2 (en) Construction method of underground structure and underground structure
KR100938395B1 (en) The Construction Method of Underpass using Steel-Concrete Composite Wall Pile
KR102269141B1 (en) Deck plate wall installation method using underground pavement
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR20190069910A (en) Installation structure and method of precast concrete culvert
JP5764245B2 (en) Construction method of underground structure and underground structure
CA2892704C (en) Reinforced blockwork construction method
KR101735077B1 (en) Bridge deck using precast concrete panel
KR20020007521A (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
JP5875651B2 (en) Underground structure and construction method of underground structure
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
KR101415867B1 (en) Precast concrete structure construction method for downward construction of underground structures
KR102331979B1 (en) Modularized monolithic joint pc wall and basement outer wall pc construction method
KR20030010407A (en) A fiber reinforced earth retaining wall, a constructing method thereof, and a composite underground wall structure using thereof
KR20080103260A (en) Reinforcing bar assembly for separate concrete pours and strut system method utilizing the same
JP7213154B2 (en) Top slab construction method for shaft and top slab structure
KR101483865B1 (en) Construction Method of Underground Structure using Composite Wale
JP2001032409A (en) Joining method and joining structure of precast reinforced concrete aseismatic wall

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant