KR102146077B1 - Construction method of top slab with opening for vertical shaft - Google Patents

Construction method of top slab with opening for vertical shaft Download PDF

Info

Publication number
KR102146077B1
KR102146077B1 KR1020200049134A KR20200049134A KR102146077B1 KR 102146077 B1 KR102146077 B1 KR 102146077B1 KR 1020200049134 A KR1020200049134 A KR 1020200049134A KR 20200049134 A KR20200049134 A KR 20200049134A KR 102146077 B1 KR102146077 B1 KR 102146077B1
Authority
KR
South Korea
Prior art keywords
support beam
wall
slab
vertical
opening
Prior art date
Application number
KR1020200049134A
Other languages
Korean (ko)
Inventor
고엄식
Original Assignee
주식회사 네오시티
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 네오시티 filed Critical 주식회사 네오시티
Priority to KR1020200049134A priority Critical patent/KR102146077B1/en
Application granted granted Critical
Publication of KR102146077B1 publication Critical patent/KR102146077B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/121Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to a construction method of a vertical shaft with an opening part on an uppermost slab which must have an opening part used for a purpose such as a vent on a slab installed on the upper most side of a vertical shaft. After a vertical shaft inner wall construction step of constructing an inner wall of a vertical shaft, while leaving an opening part after installing a support beam crossing an entrance of the vertical shaft on the upper end of the inner wall, a precast slab is mounted in a space between the support beam and the inner wall of the vertical shaft. A plurality of support beams can be used if the vertical shaft has a large cross section. The construction method includes a step of installing a first support beam crossing the entrance of the vertical shaft and a second support beam separated from the first support beam to cross the entrance of the vertical shaft on the upper end of the inner wall. A precast slab is mounted in a space between the first support beam and the inner wall of the vertical shaft and a space between the second support beam and the inner wall of the vertical shaft. While leaving the opening part, a precast slab is mounted between the first support beam and the second support beam.

Description

최상단 슬래브에 개구부를 구비한 수직구 시공방법{Construction method of top slab with opening for vertical shaft}Construction method of top slab with opening for vertical shaft}

수직구의 최상측에 설치되는 슬래브에, 환기구와 같은 용도로 사용되는 개구부를 구비하여야 하는 경우에 이용되는, 최상단 슬래브에 개구부를 구비한 수직구의 시공방법에 관한 것이다.The present invention relates to a method of constructing a vertical sphere having an opening in the uppermost slab, which is used when the slab installed on the uppermost side of the vertical hole must have an opening used for the same purpose as a ventilation hole.

최근 도시의 입체적인 개발을 위하여 도심지 지하공간을 활용한 대심도 터널이나 공공시설물을 수용하는 공동구 등의 시공이 증대됨에 따라 시공 중 공사용 통로, 시공 후의 유지관리 통로 그리고 환기구 역할로서 수직구(vertical shaft) 시공사례가 증가하고 있다.In recent years, as the construction of deep tunnels using urban underground spaces or common wards accommodating public facilities has been increasing for the three-dimensional development of cities, a vertical shaft is used as a construction passage during construction, a maintenance passage after construction, and a ventilation port. Construction cases are increasing.

이와 같은 수직구는 지상에서 수직방향의 굴착공을 굴착하고, 굴착공 저면에 바닥콘크리트를 타설하여 바닥면을 성형한 후, 굴착공의 바닥면에서부터 굴착공의 내주면을 따라 거푸집을 설치하고 콘크리트를 타설하는 공정을 반복하여 수직벽체를 형성하는 순서로 시공된다.Such a vertical hole excavates the excavation hole in the vertical direction from the ground, pours concrete on the bottom of the excavation hole to form the bottom surface, and then installs a formwork along the inner circumferential surface of the excavation hole from the bottom of the excavation hole and pours concrete. It is constructed in the order of forming a vertical wall by repeating the process.

수직구의 수직벽체를 형성함에 있어서, 과거에는 수직벽체의 형성위치에 거푸집을 설치하고 콘크리트를 타설한 후에 거푸집을 해체하고 다음 작업위치에 재조립하여 설치한 후 콘크리트를 타설하는 작업을 반복하는 거푸집 방식을 사용하였으나, 최근에는 슬립폼 공법이 많이 사용된다.In forming the vertical wall of the vertical sphere, in the past, the formwork was installed at the location where the vertical wall was formed, and after concrete was poured, the formwork was dismantled, reassembled and installed at the next working location, and then concrete was poured. Was used, but recently the slip foam method is widely used.

슬립폼은 콘크리트 타설 후에 콘크리트가 자립할 수 있는 강도 이상이 되면 거푸집을 상부 방향으로 상승시키면서 연속적으로 철근조립, 콘크리트 타설 등을 실시하여 구조물을 완성시키는 공법에 적용되는 거푸집을 말한다. 슬립폼은 일반적으로 상부작업대, 중간작업대, 하부작업대로 구성되며, 주면에 배치된 유압잭에 의하여 수직으로 이동하면서 수직벽체를 시공한다.Slip form refers to a form applied to the construction method of completing a structure by continuously assembling reinforcing bars and pouring concrete while raising the formwork upward when the strength of concrete becomes more than the strength that can stand on its own after pouring concrete. The slip foam is generally composed of an upper workbench, an intermediate workbench, and a lower workbench, and a vertical wall is constructed while moving vertically by a hydraulic jack arranged on the main surface.

이밖에도 등록특허공보 제10-2001526에는 하향식 수직구 시공장치와 방법이 개시되어 있는데, 이에 의하면 수직구 압입장치를 조립식으로 형성하여 수직구의 설치가 굴착이 진행됨과 동시에 수직구 벽체의 시공이 콘크리트 타설 또는 프리캐스트 콘크리트 벽을 이용하여 하향식으로 동시에 이루어지도록 하고 있다.In addition, Patent Publication No. 10-2001526 discloses a top-down vertical hole construction device and method. According to this, a vertical hole press-fitting device is prefabricated so that the installation of the vertical sphere is excavated and the construction of the vertical sphere wall is carried out by concrete pouring or Using precast concrete walls, it is done in a top-down manner at the same time.

이렇게 시공한 수직구의 최상단에는, 수직구를 덮는 슬래브 구조물이 시공되는데, 상기 최상단 슬래브에는 작업통로 또는 환기구로 이용되는 개구부가 마련된다. 도 1은 최상단 슬래브에 개구부를 구비한 수직구의 절개사시도이다. 이러한 슬래브 구조물은 거푸집을 설치하고 현장타설에 의해 시공하는 방법을 사용해 오고 있다. 그런데, 현장 타설에 의한 슬래브 시공은 수직구 내부에 거푸집 설치를 위해 비계, 동바리 등의 가시설물 설치, 거푸집 설치, 철근 배근, 철근 연결, 콘크리트 타설, 양생, 거푸집 및 가시설물 해체 등의 과정을 거쳐야 하므로 공사기간과 인력이 상대적으로 많이 소요되고, 현장타설에 소요되는 자재가 수직구 하부로 낙하될 수 있음에 따라 안전사고의 위험이 높아지는 문제가 있다.At the top of the vertical sphere constructed in this way, a slab structure covering the vertical sphere is constructed, and the uppermost slab is provided with an opening used as a working passage or a ventilation hole. 1 is a cutaway perspective view of a vertical sphere having an opening in an uppermost slab. Such slab structures have been constructed by installing formwork and placing them on site. However, slab construction by on-site casting has to go through the process of installing temporary facilities such as scaffolding and copper bars, installing formwork, reinforcing reinforcing bars, connecting rebars, placing concrete, curing, and dismantling formwork and temporary facilities to install the formwork inside the vertical hole. Therefore, there is a problem that the risk of safety accidents increases as the construction period and manpower are relatively large, and materials required for on-site placement may fall below the vertical hole.

등록특허공보 제10-1679180호 수직환기구의 시공방법Registered Patent Publication No. 10-1679180 Construction method of vertical ventilation 등록특허공보 제10-1584361호 지하공동구의 안전 유지관리용 환기 시설Registered Patent Publication No. 10-1584361 Ventilation facilities for safety maintenance of underground public areas 등록특허공보 제10-1262969호 터널 유지관리용 환기구의 접이식 안전 사다리Registered Patent Publication No. 10-1262969 Foldable safety ladder of ventilation port for tunnel maintenance 등록특허공보 제10-2026571호 수직구용 매입형 슬래브 브라켓 및 시공방법Registered Patent Publication No. 10-2026571 Embedded slab bracket for vertical sphere and construction method

본 발명은 수직구의 최상단을 덮는 슬래브 구조물을 지지보와 프리캐스트 슬래브에 의하여 시공함으로써 수직구 시공의 간편성과 신속성을 확보하기 위한 것이다.The present invention is to secure the simplicity and speed of construction of the vertical sphere by constructing the slab structure covering the uppermost end of the vertical sphere by means of a support beam and a precast slab.

특히 최상단 슬래브에 개구부를 형성하여야 하는 경우에도, 개구부를 제외한 부분은 사전에 미리 제작된 프리캐스트 슬래브를 이용하여 폐색함으로써, 수직구가 유지관리통로 또는 환기구로 기능하도록 하기 위한 것이다.In particular, even when an opening must be formed in the uppermost slab, the part except the opening is closed using a precast slab manufactured in advance, so that the vertical hole functions as a maintenance passage or ventilation hole.

또한 프리캐스트 슬래브를 거치하는 지지보가 수직구 내벽에 안정적으로 고정될 수 있게 하는 한편, 프리캐스트 슬래브가 지지보와 내벽 상부에 안치된 후에는 프리캐스트 슬래브의 움직임을 제한함으로써 구조물의 안정성을 향상시키고자 한다.In addition, the support beams on which the precast slab is mounted can be stably fixed to the inner wall of the vertical hole, while the movement of the precast slab is restricted after the precast slab is placed on the support beams and the inner wall, thereby improving the stability of the structure. Let's do it.

이와 함께 프리캐스트 슬래브의 상부에 현장 타설에 의해 마감 슬래브를 형성함으로써 수직구와 슬래브의 구조적 일체성을 꾀함과 함께 슬래브 구조물의 수밀성을 개선하고자 한다. In addition, by forming a finished slab on the top of the precast slab by casting on-site, it aims to improve the watertightness of the slab structure while seeking structural integrity between the vertical sphere and the slab.

또한 최상단 슬래브에 형성된 개구부의 주면에 단턱부를 구비함으로써, 개구부를 통해서 자재 또는 인력 등이 낙하하는 것을 방지하고자 한다.In addition, by providing a stepped portion on the main surface of the opening formed in the uppermost slab, it is intended to prevent material or manpower from falling through the opening.

본 발명의 이러한 목적은, 수직구의 내벽을 시공하는 수직구 내벽 시공 단계 이후에, 상기 내벽의 상단에 수직구의 입구를 가로지르는 지지보를 설치한 후, 개구부를 남겨둔 채 상기 지지보와 수직구의 내벽 사이 공간을 프리캐스트 슬래브로 폐색함으로써 달성된다. This object of the present invention is, after the vertical sphere inner wall construction step of constructing the inner wall of the vertical sphere, after installing a support beam crossing the entrance of the vertical sphere at the top of the inner wall, between the support beam and the inner wall of the vertical sphere while leaving an opening It is achieved by occluding the space with a precast slab.

수직구가 대단면인 경우에는 복수의 지지보를 사용할 수 있는데, 상기 내벽의 상단에 수직구의 입구를 가로지르는 제1 지지보와, 상기 제1 지지보와 이격되어 수직구의 입구를 가로지르는 제2 지지보를 설치하는 단계와, 상기 제1 지지보와 수직구의 내벽 사이 공간, 그리고 상기 제2 지지보와 수직구의 내벽 사이 공간을 폐색하는 프리캐스트 슬래브를 거치하고, 개구부를 남겨둔 채 제1 지지보와 제2 지지보의 사이에 프리캐스트 슬래브를 거치하는 단계를 포함함으로써 달성된다.When the vertical sphere has a large cross-section, a plurality of support beams can be used.A first support beam crossing the entrance of the vertical sphere at the upper end of the inner wall, and a second support crossing the entrance of the vertical sphere separated from the first support beam Installing a beam, mounting a precast slab that closes the space between the inner wall of the first support beam and the vertical sphere, and the space between the second support beam and the inner wall of the vertical sphere, and leaving the openings It is achieved by including the step of mounting a precast slab between the two support beams.

지지보를 수직구 내벽에 고정하는 방법으로는, 수직구 내벽 시공단계에서 상기 내벽의 최상측 단부에 지지보의 단부가 삽입되는 지지보 함입부를 형성하고, 지지보를 설치하는 단계에서 지지보의 단부를 내벽의 지지보 함입부에 삽입함으로써 지지보를 고정하거나, 수직구 내벽 시공단계에서 지지보의 단부가 거치될 수 있게 상기 내벽의 최상측 단부에 브라켓을 돌출되게 형성하고, 지지보를 설치하는 단계에서 지지보의 단부를 브라켓에 거치하고 고정함으로써 지지보를 설치할 수 있다. 지지보의 중앙 상부에 길이방향으로 돌출부가 구비됨으로써 이후에 안착되는 프리캐스트 슬래브의 움직임을 제한할 수 있다.As a method of fixing the support beam to the inner wall of the vertical sphere, in the vertical sphere inner wall construction step, a support beam recess is formed in which the end of the support beam is inserted into the uppermost end of the inner wall, and the end of the support beam is formed in the step of installing the support beam. The support beam is fixed by inserting it into the support beam recess of the inner wall, or a bracket is formed to protrude at the uppermost end of the inner wall so that the end of the support beam can be mounted in the vertical hole inner wall construction step, and supported in the step of installing the support beam Support beams can be installed by mounting and fixing the end of the beam to the bracket. By providing a protrusion in the longitudinal direction at the upper center of the support beam, it is possible to limit the movement of the precast slab to be seated later.

또한, 상기 프리캐스트 슬래브의 상부에 콘크리트를 현장타설하여 마감슬래브를 시공하는 단계를 더 포함함으로써, 수직구와 슬래브의 구조적 일체성을 확보하고 수밀성을 향상시킨다. In addition, by further comprising the step of constructing the finished slab by placing concrete on the top of the precast slab on-site, the structural integrity of the vertical sphere and the slab are secured and watertightness is improved.

그리고, 개구부의 주면에 단턱부를 구비하게 함으로써 개구부를 통하여 자재나 인력이 낙하하는 것을 방지할 수 있으므로 안전사고를 방지할 수 있다. In addition, by providing a stepped portion on the main surface of the opening, it is possible to prevent a material or manpower from falling through the opening, thereby preventing a safety accident.

본 발명은 수직구의 최상단을 덮는 슬래브 구조물을 지지보와 프리캐스트 슬래브에 의하여 시공함으로써 수직구 시공의 간편성과 신속성을 확보할 수 있다.The present invention can secure the simplicity and speed of construction of the vertical sphere by constructing the slab structure covering the uppermost end of the vertical sphere by means of a support beam and a precast slab.

특히 최상단 슬래브에 개구부를 형성하여야 하는 경우에도, 개구부를 제외한 부분은 사전에 미리 제작된 프리캐스트 슬래브를 이용하여 폐색함으로써, 수직구의 유지관리통로 또는 환기구를 쉽게 시공할 수 있다.In particular, even when an opening is to be formed in the uppermost slab, the part excluding the opening is closed using a precast slab prepared in advance, so that a maintenance passage or ventilation hole of the vertical hole can be easily constructed.

또한 프리캐스트 슬래브를 거치하는 지지보가 수직구 내벽에 안정적으로 고정될 뿐만 아니라, 프리캐스트 슬래브의 상부에 현장 타설에 의해 마감 슬래브를 형성함으로써 수직구와 슬래브의 구조적 일체성과 슬래브 구조물의 수밀성을 확보할 수 있다.In addition, not only the support beams for mounting the precast slab are stably fixed to the inner wall of the vertical hole, but also the structural integrity of the vertical sphere and the slab and the watertightness of the slab structure can be secured by forming the finished slab by casting on-site on the top of the precast slab. have.

또한 최상단 슬래브에 형성된 개구부의 주면에 단턱부를 구비함으로써, 개구부를 통해서 자재 또는 인력 등이 낙하하여 안전사고가 발생하는 것을 방지할 수 있는 효과가 있다.In addition, by providing a stepped portion on the main surface of the opening formed in the uppermost slab, there is an effect of preventing the occurrence of a safety accident by falling of materials or personnel through the opening.

도 1 최상단 슬래브에 개구부를 구비한 수직구의 절개 사시도
도 2 본 발명의 일 실시예에 따른 최상단 슬래브 시공 상태도
도 3 본 발명의 다른 실시예에 따른 최상단 슬래브 시공 상태도
도 4a 내벽 단부에 지지보 함입보를 형성한 상태 평면도 및 요부 사시도
도 4b 내벽 단부에 지지보 거치 브라켓을 형성한 상태 평면도 및 요부 사시도
도 5 본 발명에 따른 지지보 실시예 단면도
도 6 수직구 내벽, 프리캐스트 슬래브 및 마감 슬래브 결합관계 실시예 단면도
도 7 본 발명에 따른 시공순서 평면도
1 a cutaway perspective view of a vertical sphere having an opening in the uppermost slab
Figure 2 Construction state diagram of the top slab according to an embodiment of the present invention
Figure 3 Construction state diagram of the top slab according to another embodiment of the present invention
Fig. 4a A plan view and a perspective view of the main parts in a state in which the support beam is formed at the end of the inner wall
Fig. 4b a plan view and a perspective view of main parts in a state in which a support beam mounting bracket is formed at an end of an inner wall
Figure 5 A cross-sectional view of an embodiment of a support beam according to the present invention
Fig. 6 Cross-sectional view of an embodiment of a vertical hole inner wall, a precast slab and a finished slab coupling relationship
7 Construction sequence plan view according to the present invention

본 발명의 최상단 슬래브에 개구부를 구비한 수직구 시공방법은, 수직구의 내벽을 시공하는 수직구 내벽(11) 시공단계; 상기 내벽의 상단에 수직구의 입구를 가로지르는 지지보(100)를 설치하는 단계; 개구부를 남겨둔 채 상기 지지보와 수직구의 내벽 사이 공간을 폐색하는 프리캐스트 슬래브(200)를 거치하는 단계;를 포함하여 구성된다.The vertical sphere construction method having an opening in the uppermost slab of the present invention includes a vertical sphere inner wall 11 construction step of constructing the inner wall of the vertical sphere; Installing a support beam 100 crossing the entrance of the vertical sphere at the upper end of the inner wall; And mounting the precast slab 200 for closing the space between the support beam and the inner wall of the vertical sphere while leaving the opening.

도 2에는 수직구 내벽(11)이 시공된 후에, 하나의 지지보(100)가 수직구의 입구를 가로질러 설치되고, 개구부를 제외한 지지보와 수직구 사이의 공간은 프리캐스트 슬래브(200)를 거치하여 폐색한 상태가 도시되어 있다. 프리캐스트 슬래브(200)는 수직구 단면의 크기에 따라 제작 및 운반의 편리성을 고려하여 적절한 크기로 분할 제작된다. 도 2에서는 개구부가 형성되지 않는, 보(100)와 수직구 벽체(11) 사이 공간에 200a ~ 200e의 프리캐스트 슬래브를 거치하고, 개구부에 인접하여 200f ~ 200g의 프리캐스트 슬래브를 거치하는 것으로 도시하였으나, 프리캐스트 슬래브의 적정한 개수는 시공하고자 하는 수직구의 단면 크기 및 개구부의 크기를 고려하여 변경할 수 있다. 또한, 설명의 편의를 위해 프리캐스트 슬래브를 200a ~ 200g로 표기하였을 뿐이고, 이것이 프리캐스트 슬래브의 시공순서를 뜻하는 것은 아니다.In FIG. 2, after the vertical sphere inner wall 11 is constructed, one support beam 100 is installed across the entrance of the vertical sphere, and the space between the support beam and the vertical sphere excluding the opening is precast slab 200. Mounted and closed state is shown. The precast slab 200 is divided into appropriate sizes in consideration of the convenience of manufacturing and transportation according to the size of the vertical section. In FIG. 2, a precast slab of 200a to 200e is mounted in the space between the beam 100 and the vertical sphere wall 11 in which no opening is formed, and the precast slab of 200f to 200g is mounted adjacent to the opening. However, the appropriate number of precast slabs can be changed in consideration of the cross-sectional size of the vertical sphere to be constructed and the size of the opening. In addition, for convenience of explanation, precast slabs are only indicated as 200a ~ 200g, and this does not mean the construction order of the precast slabs.

한편 수직구의 단면이 상대적으로 큰 경우에는 복수 개의 지지보를 이용하여 시공하는 것이 시공성을 높이기에 유리하다. 본 발명의 다른 실시예에 따른 개구부를 구비한 수직구 시공방법은, 수직구의 입구를 가로지르는 복수개의 지지보를 이용하는 것으로서, 수직구의 내벽을 시공하는 수직구 내벽 시공단계; 상기 내벽의 상단에 수직구의 입구를 가로지르는 제1 지지보와 상기 제1 지지보와 이격되어 수직구의 입구를 가로지르는 제2 지지보를 설치하는 단계; 상기 제1 지지보와 수직구의 내벽 사이 공간, 그리고 상기 제2 지지보와 수직구의 내벽 사이 공간을 폐색하는 프리캐스트 슬래브를 거치하는 단계; 개구부를 남겨둔 채 제1 지지보와 제2 지지보의 사이에 프리캐스트 슬래브를 거치하는 단계;를 포함할 수 있다.On the other hand, when the cross section of the vertical sphere is relatively large, it is advantageous to increase workability to construct using a plurality of support beams. A vertical sphere construction method having an opening according to another embodiment of the present invention, as using a plurality of support beams crossing the entrance of the vertical sphere, the vertical sphere inner wall construction step of constructing the inner wall of the vertical sphere; Installing a first support beam crossing the entrance of the vertical sphere and a second support beam spaced apart from the first support beam and crossing the entrance of the vertical sphere at an upper end of the inner wall; Mounting a precast slab to block a space between the first support beam and the inner wall of the vertical sphere and the space between the second support beam and the inner wall of the vertical sphere; It may include; mounting the precast slab between the first support beam and the second support beam while leaving the opening.

상기 제1 지지보와 수직구의 내벽 사이 공간, 그리고 상기 제2 지지보와 수직구의 내벽 사이 공간을 폐색하는 프리캐스트 슬래브를 거치하는 단계와, 개구부를 남겨둔 채 제1 지지보와 제2 지지보의 사이에 프리캐스트 슬래브를 거치하는 단계는 병렬적인 구성으로서 순서를 바꾸거나 또는 동시에 진행할 수도 있다.Mounting a precast slab to block the space between the first support beam and the inner wall of the vertical sphere, and the space between the second support beam and the inner wall of the vertical sphere, and the first support beam and the second support beam while leaving openings. The step of passing the precast slabs between them is a parallel configuration, and the order may be changed or may be performed simultaneously.

도 3에는 수직구 내벽(11)이 시공된 후에, 수직구의 입구를 가로지르는 제1 지지보 및 상기 제1 지지보와 평행하게 이격되어 수직구의 입구를 가로지르는 제2 지지보가 설치되고 나서, 상기 제1 지지보와 수직구의 내벽 사이 공간, 그리고 상기 제2 지지보와 수직구의 내벽 사이 공간을 폐색하는 프리캐스트 슬래브를 거치하고, 또한 개구부를 남겨둔 채 제1 지지보와 제2 지지보의 사이에 프리캐스트 슬래브를 거치한 상태가 도시되어 있다. 3, after the vertical sphere inner wall 11 is constructed, a first support beam crossing the entrance of the vertical sphere and a second support beam spaced parallel to the first support beam and crossing the entrance of the vertical sphere are installed, A precast slab is mounted to block the space between the first support beam and the inner wall of the vertical sphere, and the space between the second support beam and the inner wall of the vertical sphere, and between the first support beam and the second support beam while leaving an opening. A state in which the precast slab is mounted is shown.

프리캐스트 슬래브(200)는 수직구 단면의 크기에 따라 제작 및 운반의 편리성을 고려하여 적절한 크기로 분할 제작된다. 도 3에서는 제1 지지보와 수직구 벽체 사이 공간을 200a ~ 200e의 프리캐스트 슬래브로 폐색하고, 제2 지지보와 수직구 벽체 사이 공간을 200f 내지 200j의 프리캐스트 슬래브로 폐색하는 것으로 도시하였으나, 프리캐스트 슬래브의 적정한 개수는 시공하고자 하는 수직구의 단면 크기와 시공성 등을 고려하여 변경할 수 있다. 또한 제1 지지보와 제2 지지보 사이 공간에 개구부(30)를 남겨둔 채, 200k ~ 200n의 프리캐스트 슬래브로 폐색하는 것으로 도시하였으나, 지지보 사이의 이격거리와 수직구의 단면크기를 고려하여 그 개수는 변경하여 구성할 수 있다. 또한, 설명의 편의를 위해 프리캐스트 슬래브를 200a ~ 200n으로 표기하였을 뿐이고, 이것이 프리캐스트 슬래브의 시공순서를 뜻하는 것은 아니다.The precast slab 200 is divided into appropriate sizes in consideration of the convenience of manufacturing and transportation according to the size of the vertical section. In FIG. 3, it is shown that the space between the first support beam and the vertical sphere wall is closed with a precast slab of 200a to 200e, and the space between the second support beam and the vertical sphere wall is closed with a precast slab of 200f to 200j. The appropriate number of precast slabs can be changed in consideration of the cross-sectional size and constructability of the vertical sphere to be constructed. In addition, it is shown that the opening 30 is left in the space between the first support beam and the second support beam, and is closed with a precast slab of 200k ~ 200n, but considering the separation distance between the support beams and the cross-sectional size of the vertical sphere, The number can be changed and configured. In addition, for convenience of explanation, precast slabs are only indicated as 200a to 200n, and this does not mean the construction order of the precast slabs.

본 발명에서는 수직구의 평면 단면이 원형인 경우를 예로 설명하지만, 이에 한정되는 것은 아니다. In the present invention, a case in which the plane cross section of the vertical sphere is circular is described as an example, but is not limited thereto.

내벽은 지지보(100)가 설치될 수 있게 지지보 지지수단을 구비한다. 지지보 지지수단은 지지보(100)와 접촉되어 지지보(100)의 단부를 고정하면서 지지보(100)로부터 전달받은 하중을 수직구 내벽(11)에 전달한다.The inner wall is provided with a support beam support means so that the support beam 100 can be installed. The support beam support means is in contact with the support beam 100 to fix the end of the support beam 100 and transmits the load received from the support beam 100 to the vertical sphere inner wall 11.

지지보 지지수단은 도 4a에 도시된 바와 같이, 수직구 내벽 시공단계에서 상기 내벽의 최상측 단부에 지지보의 단부가 삽입되도록 형성한 지지보 함입부(13)일 수 있다. 지지보를 설치하는 단계에서 지지보의 단부를 지지보 함입부(13)에 삽입함으로써 지지보 설치가 완료된다.As shown in FIG. 4A, the support beam support means may be a support beam depression 13 formed so that the end of the support beam is inserted into the uppermost end of the inner wall in the vertical hole inner wall construction step. In the step of installing the support beam, the support beam installation is completed by inserting the end of the support beam into the support beam recess 13.

지지보 지지수단은 도 4b에 도시된 바와 같이, 수직구 내벽 시공단계에서 지지보의 단부가 거치될 수 있게 상기 내벽의 최상측 단부에 설치한 브라켓(14)일 수 있다. 수직구 벽체에 브라켓을 매입하는 것에 대해서는 국내등록특허 제10-2047997호 개시되어 있으므로 자세한 설명은 생략한다. 다만, 지지보가 상부의 프리캐스트 슬래브(200) 및 마감슬래브(400)로부터 전달받은 하중을 수직구 벽체에 전달해야 하므로, 지지보가 거치되는 브라켓이 충분한 강도를 갖게 형성되어야 함은 이 기술분야에서 통상의 지식을 가진 사람에게 자명하다. 지지보의 단부를 브라켓(14)에 거치한 후에는 지지보가 움직이지 않게 지지보의 단부를 브라켓(14)에 고정한다.The support beam support means may be a bracket 14 installed at the uppermost end of the inner wall so that the end of the support beam can be mounted in the vertical hole inner wall construction step, as shown in FIG. 4B. As for the embedding of the bracket in the vertical sphere wall, a detailed description is omitted since it is disclosed in Korean Patent No. 10-2047997. However, since the support beam must transmit the load transmitted from the upper precast slab 200 and the finished slab 400 to the vertical sphere wall, it is common in this technical field that the bracket on which the support beam is mounted must be formed to have sufficient strength. It is self-evident to someone with knowledge of. After mounting the end of the support beam to the bracket 14, the end of the support beam is fixed to the bracket 14 so that the support beam does not move.

지지보(100)는 H형빔 또는 T형빔일수도 있고, 도 5a에 도시한 바와 같이, 그 중심에 H형빔 또는 T형빔이 위치하고 매설철근으로 강도를 보강한 프래캐스트빔일 수도 있다. 또한, 도 5b에 도시한 바와 같이, 단면의 외주면을 따라 철근으로 보강한 프리캐스트빔일 수도 있다.The support beam 100 may be an H-beam or a T-beam, and as shown in FIG. 5A, the H-beam or T-beam is positioned at the center thereof and may be a precast beam reinforced with a buried reinforcing bar. In addition, as shown in FIG. 5B, it may be a precast beam reinforced with reinforcement along the outer peripheral surface of the cross section.

지지보(100)는 도 5c에 도시한 바와 같이, 중앙 상부에 길이방향으로 돌출부(120)를 더 구비할 수 있는데, 돌출부(120)가 구비되면 프리캐스트 슬래브를 거치할 때 돌출부의 측면에 프리캐스트 슬래브의 단부가 접하게 되므로 작업이 편리해지고 프리캐스트 슬래브의 움직임을 제한할 수 있는 효과도 있다.As shown in FIG. 5C, the support beam 100 may further include a protrusion 120 in the longitudinal direction at the upper center. If the protrusion 120 is provided, the side of the protrusion is free when mounting the precast slab. Since the end of the cast slab comes into contact, the operation becomes convenient and there is an effect of limiting the movement of the precast slab.

도시하지는 않았지만, 복수의 지지보를 사용하는 경우에 있어서, 제1 지지보와 제2 지지보 사이의 이격거리가 긴 경우에는, 제1 지지보와 제2 지지보 사이에 수평보를 추가로 설치한 후 프리캐스트 슬래브를 거치할 수도 있다.Although not shown, in the case of using a plurality of support beams, if the separation distance between the first support beam and the second support beam is long, after installing additional horizontal beams between the first support beam and the second support beam Precast slabs can also be mounted.

도 6에는 수직구 벽체(11)와 지지보(100) 사이에 프리캐스트 슬래브(200)가 거치된 상태의 다양한 실시예가 도시되어 있다. 도 6(a)는 프리캐스트 슬래브(200)가 수직구 벽체 상단에 얹혀져 있는 상태를 도시한 것이다. 도 6(b)와 도 6(c)는 수직구 벽체의 상단 안쪽에 주면을 따라 프리캐스트 슬래브(200)가 안착할 수 있게 단턱이 형성되어, 프리캐스트 슬래브(200)의 일측은 보의 상단에 얹혀지고, 타단은 수직구 벽체의 상단 안쪽에 주면을 따라 형성된 단턱에 안착된 상태를 도시하고 있다. 도 6(d)는 수직구 벽체(11)의 안쪽에 프리캐스트 슬래브(200) 안착용 브라켓(15)을 설치하여, 프리캐스트 슬래브(200)의 일측은 보의 상단에 얹혀지고 타단은 수직구 벽체의 상단 안쪽에 구비된 브라켓(15)에 안착된 상태를 도시하고 있다.6 shows various embodiments of a state in which the precast slab 200 is mounted between the vertical sphere wall 11 and the support beam 100. 6(a) shows a state in which the precast slab 200 is placed on the top of the vertical sphere wall. 6(b) and 6(c) show that a stepped step is formed along the main surface inside the upper end of the vertical sphere wall so that the precast slab 200 can be seated, and one side of the precast slab 200 is the top of the beam. And the other end is seated on a stepped jaw formed along the main surface inside the upper end of the vertical sphere wall. 6(d) is a precast slab 200 mounting bracket 15 installed on the inside of the vertical sphere wall 11, so that one side of the precast slab 200 is placed on the top of the beam and the other end is a vertical sphere. It shows a state seated on the bracket 15 provided inside the upper end of the wall.

프리캐스트 슬래브(200)를 안착시킨 후에는, 프리캐스트 슬래브(200) 사이의 틈새, 프리캐스트 슬래브(200)와 수직구 벽체(11) 사이의 틈새, 및 프리캐스트 슬래브(200)와 지지보 사이의 틈새를 몰탈 등 충전재로 충전하여 수밀성을 향상시킨다. After seating the precast slab 200, the gap between the precast slab 200, the gap between the precast slab 200 and the vertical wall 11, and between the precast slab 200 and the support beam It improves watertightness by filling the gaps with a filler such as mortar.

본 발명에 의한 수직구 시공방법은, 프리캐스트 슬래브 위에 현장 콘크리트타설을 통해 마감슬래브(400)를 더 시공하는 단계를 포함할 수 있다. 마감슬래브(400)는 수직구 벽체와 프리캐스트 슬래브(200)가 커버되게 시공될 수 있다. The vertical sphere construction method according to the present invention may include the step of further constructing the finishing slab 400 through on-site concrete pouring on the precast slab. The finishing slab 400 may be constructed such that the vertical sphere wall and the precast slab 200 are covered.

마감슬래브(400)는, 수직구 벽체와 프리캐스트 슬래브 전체가 커버되도록 거푸집을 설치하고 거푸집 내에 콘크리트를 타설하여 시공할 수 있는데, 마감슬래브(400)의 보강을 위해 거푸집 내에 보강철근을 배치하고 수직구 벽체의 수직철근(미도시)과 고정한 후 콘크리트를 타설하게 되면, 수직구와 슬래브가 구조적으로 일체가 됨과 함께 슬래브 구조물의 수밀성을 확보할 수 있다. The finishing slab 400 can be constructed by installing a formwork so that the vertical sphere wall and the entire precast slab are covered and concrete is poured into the formwork.For reinforcement of the finishing slab 400, reinforcing reinforcing bars are placed in the formwork. If concrete is poured after fixing with the vertical reinforcing bars (not shown) of the direct ball wall, the vertical ball and the slab are structurally integrated and the watertightness of the slab structure can be secured.

또한 프리캐스트 슬래브(400)에도 상측으로 고정용 철근이 돌출되게 형성한 후 마감슬래브(400)의 시공을 위한 철근과 연결하면 보다 견고한 슬래브를 형성할 수 있다.In addition, a more robust slab can be formed by forming the precast slab 400 so that the fixing reinforcing bar protrudes upward and then connecting it to the reinforcing bar for construction of the finishing slab 400.

마감슬래브를 시공하는 단계에서는 개구부를 통한 낙하를 방지할 수 있게 개구부 주면에 단턱부를 구비할 수 있다. 단턱부는 개구부 주면에 프리캐스트 단턱블록(300)을 배치하여 조립 형성할 수 있다. In the step of constructing the finishing slab, a stepped portion may be provided on the main surface of the opening to prevent falling through the opening. The stepped portion may be assembled by disposing the precast stepped block 300 on the main surface of the opening.

단턱블록(300)은 마감슬래브를 시공할 때에 거푸집 역할을 할 수도 있으며, 도면에는 도시하지 않았지만, 블록외부로 철근을 돌출시켜 마감슬래브(400) 시공을 위한 보강철근과 연결함으로써 마감슬래브에 단턱부가 일체로 되게 형성할 수 있다.The stepped block 300 may serve as a formwork when constructing the finishing slab, and although not shown in the drawing, the stepped part on the finished slab is connected to the reinforcing bar for the construction of the finishing slab 400 by protruding the reinforcing bar outside the block. It can be formed integrally.

개구부의 주면에 단턱부가 구비되어 있기 때문에, 개구부의 존재를 작업자가 쉽게 인식할 수 있어서 추락사고 등이 방지될 뿐만 아니라, 슬래브 상부에 추가적인 작업을 하는 경우에도 자재 등이 단턱부를 쉽게 타고 넘어갈 수 없으므로 개구부를 통해 자재가 낙하하는 것도 방지할 수 있다.Since the stepped part is provided on the main surface of the opening, the existence of the opening can be easily recognized by the operator, preventing a fall accident, and even when additional work is performed on the upper part of the slab, materials, etc., cannot easily cross the stepped part. It can also prevent material from falling through the opening.

도 7에는 본 발명에 따른 수직구의 최상단 슬래브 시공순서가 도시되어 있다. 수직구 내벽 시공 단계에서, 지지보가 안착되는 지지보 지지수단을 마련한다(도 7a). 도 7a에서는 지지보 지지수단으로 내벽 상단에 지지보 함입부를 구비하는 것으로 도시하였지만, 앞에서 설명한 바와 같이, 지지보 지지수단은 지지보의 단부가 거치될 수 있게 상기 내벽의 최상측 단부에 설치한 브라켓(14)일 수도 있다. 다음으로, 지지보(100)가 지지보 지지수단에 안착된다(도 7b). 도 7b에서는 2개의 지지보를 설치하는 것으로 도시하였지만, 수직구 단면의 크기에 따라 하나의 지지보를 설치하거나 또는 2개 이상의 지지보를 설치하는 것도 가능하다. 그 다음에는, 개구부를 제외한 공간을, 복수개로 분할 제작된 프리캐스트 슬래브를 거치함으로써 폐색한다(도 7c). 프리캐스트 슬래브의 분할 개수는 작업의 편리성과 시공성을 고려하여 조절할 수 있음은 위에서 설명한 바이다. 개구부의 주면에 단턱부를 형성하는 경우에는, 개구부의 주면에 따라 미리 제작된 프리캐스트 단턱블록을 조립 설치한다(도 7d). 마지막으로, 프리캐스트 슬래브 위에 현장 콘크리트타설을 통해 마감슬래브를 더 시공함으로써 슬래브의 시공을 완료한다(도 7e). 7 shows the construction sequence of the uppermost slab of the vertical sphere according to the present invention. In the step of constructing the inner wall of the vertical sphere, a support beam support means on which the support beam is seated is provided (FIG. 7A). In Fig. 7a, it is shown that the support beam has a recess at the upper end of the inner wall as the support beam support means, but as described above, the support beam support means is a bracket installed at the uppermost end of the inner wall so that the end of the support beam can be mounted. It may be (14). Next, the support beam 100 is seated on the support beam support means (Fig. 7b). In Fig. 7b, it is shown that two support beams are installed, but it is possible to install one support beam or two or more support beams according to the size of the vertical section. Then, the space excluding the openings is closed by placing precast slabs divided into a plurality of pieces (Fig. 7C). It is described above that the number of divisions of the precast slab can be adjusted in consideration of the convenience and constructability of work. In the case of forming a stepped portion on the main surface of the opening, a precast stepped block is assembled and installed along the main surface of the opening (Fig. 7D). Finally, the construction of the slab is completed by further constructing the finished slab through on-site concrete pouring on the precast slab (FIG. 7e).

이와 같이, 도면을 참조하여 본 발명의 바람직한 실시예에 대해 상술하였으나 본 발명은 전술한 실시예에 한정되지 않으며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 사람이 본 발명의 사상을 벗어나지 않는 범위 내에서 변형 가능하고, 이러한 변형도 본 발명의 권리범위에 속할 것이다.Thus, although the preferred embodiment of the present invention has been described above with reference to the drawings, the present invention is not limited to the above-described embodiment, and those of ordinary skill in the art to which the present invention pertains do not depart from the spirit of the present invention. It can be modified within the scope, and such modifications will also belong to the scope of the present invention.

수직구의 최상측에 설치되는 슬래브에, 환기구와 같은 용도로 사용되는 개구부를 구비하여야 하는 수직구의 시공에 이용될 수 있다.It can be used for construction of a vertical hole that must have an opening used for the same purpose as a ventilation hole in the slab installed at the top of the vertical hole.

10: 수직구 11: 수직구 내벽
13: 함입부 14: 지지보 지지 브라켓
15: 프래캐스트 슬래브 지지 브라켓 20: 슬래브
30: 개구부 100: 지지보
110: 본체부 120: 돌출부
200: 프리캐스트 슬래브 300: 단턱블록
400: 마감슬래브
10: vertical sphere 11: vertical sphere inner wall
13: depression 14: support beam support bracket
15: precast slab support bracket 20: slab
30: opening 100: support beam
110: main body 120: protrusion
200: precast slab 300: stepped block
400: finishing slab

Claims (10)

수직구의 내벽을 시공하는 수직구 내벽 시공단계;
상기 내벽의 상단에 수직구의 입구를 가로지르는 지지보를 설치하는 단계;
개구부를 남겨둔 채 상기 지지보와 수직구의 내벽 사이 공간을 프리캐스트 슬래브로 폐색하는 단계;
상기 프리캐스트 슬래브의 상부에 콘크리트를 현장타설하여 마감슬래브를 시공하는 단계를 포함하는 것을 특징으로 하는, 최상단 슬래브에 개구부를 형성하는 수직구 시공방법.
Vertical sphere inner wall construction step of constructing the inner wall of the vertical sphere;
Installing a support beam crossing the entrance of the vertical sphere at the upper end of the inner wall;
Closing the space between the support beam and the inner wall of the vertical sphere with a precast slab while leaving an opening;
A vertical sphere construction method for forming an opening in the uppermost slab, comprising the step of constructing a finished slab by placing concrete on-site on the top of the precast slab.
수직구의 내벽을 시공하는 수직구 내벽 시공단계;
상기 내벽의 상단에 수직구의 입구를 가로지르는 제1 지지보와 상기 제1 지지보와 이격되어 수직구의 입구를 가로지르는 제2 지지보를 설치하는 단계;
상기 제1 지지보와 수직구의 내벽 사이 공간, 그리고 상기 제2 지지보와 수직구의 내벽 사이 공간을 프리캐스트 슬래브를 거치하여 폐색하는 단계;
개구부를 남겨둔 채 제1 지지보와 제2 지지보의 사이에 프리캐스트 슬래브를 거치하는 단계;
상기 프리캐스트 슬래브의 상부에 콘크리트를 현장타설하여 마감슬래브를 시공하는 단계를 포함하는 것을 특징으로 하는, 최상단 슬래브에 개구부를 형성하는 수직구 시공방법.
Vertical sphere inner wall construction step of constructing the inner wall of the vertical sphere;
Installing a first support beam crossing the entrance of the vertical sphere and a second support beam spaced apart from the first support beam and crossing the entrance of the vertical sphere at an upper end of the inner wall;
Closing the space between the first support beam and the inner wall of the vertical sphere, and the space between the second support beam and the inner wall of the vertical sphere through a precast slab;
Mounting a precast slab between the first support beam and the second support beam while leaving an opening;
A vertical sphere construction method for forming an opening in the uppermost slab, comprising the step of constructing a finished slab by placing concrete on-site on the top of the precast slab.
수직구의 내벽을 시공하는 수직구 내벽 시공단계;
상기 내벽의 상단에 수직구의 입구를 가로지르는 제1 지지보와 상기 제1 지지보와 이격되어 수직구의 입구를 가로지르는 제2 지지보를 설치하는 단계;
개구부를 남겨둔 채 제1 지지보와 제2 지지보의 사이에 프리캐스트 슬래브를 거치하는 단계;
상기 제1 지지보와 수직구의 내벽 사이 공간, 그리고 상기 제2 지지보와 수직구의 내벽 사이 공간에 프리캐스트 슬래브를 거치하여 폐색하는 단계;
상기 프리캐스트 슬래브의 상부에 콘크리트를 현장타설하여 마감슬래브를 시공하는 단계를 포함하는 것을 특징으로 하는, 최상단 슬래브에 개구부를 형성하는 수직구 시공방법.
Vertical sphere inner wall construction step of constructing the inner wall of the vertical sphere;
Installing a first support beam crossing the entrance of the vertical sphere and a second support beam spaced apart from the first support beam and crossing the entrance of the vertical sphere at an upper end of the inner wall;
Mounting a precast slab between the first support beam and the second support beam while leaving an opening;
Blocking the space between the first support beam and the inner wall of the vertical sphere, and the space between the second support beam and the inner wall of the vertical sphere by mounting a precast slab;
A vertical sphere construction method for forming an opening in the uppermost slab, comprising the step of constructing a finished slab by placing concrete on-site on the top of the precast slab.
청구항 1 내지 3 중 어느 하나에 있어서,
수직구 내벽 시공단계에서 상기 내벽의 최상측 단부에 지지보의 단부가 삽입되는 지지보 함입부를 형성하고, 지지보를 설치하는 단계에서 지지보의 단부를 내벽의 지지보 함입부에 삽입함으로써 지지보를 설치하는 것을 특징으로 하는, 최상단 슬래브에 개구부를 구비한 수직구 시공방법.
The method according to any one of claims 1 to 3,
The support beam is installed by forming a support beam recess into which the end of the support beam is inserted into the uppermost end of the inner wall in the construction of the vertical wall inner wall, and inserting the end of the support beam into the support beam recess of the inner wall in the step of installing the support beam. A vertical sphere construction method having an opening in the uppermost slab, characterized in that.
청구항 1 내지 3 중 어느 하나에 있어서,
수직구 내벽 시공단계에서 지지보의 단부가 거치될 수 있게 상기 내벽의 최상측 단부에 브라켓을 돌출되게 형성하고, 지지보를 설치하는 단계에서 지지보의 단부를 브라켓에 거치하고 고정함으로써 지지보를 설치하는 것을 특징으로 하는, 최상단 슬래브에 개구부를 구비한 수직구 시공방법.
The method according to any one of claims 1 to 3,
In the vertical hole inner wall construction step, a bracket is formed to protrude from the uppermost end of the inner wall so that the end of the support beam can be mounted, and in the step of installing the support beam, the support beam is installed by mounting and fixing the end of the support beam to the bracket. Characterized in that, vertical ball construction method having an opening in the uppermost slab.
청구항 1 내지 3 중 어느 하나에 있어서,
상기 지지보는 중앙 상부에 길이방향으로 상기 프리캐스트 슬래브의 움직임을 제한하는 돌출부가 구비되어 있는 것을 특징으로 하는, 최상단 슬래브에 개구부를 구비한 수직구 시공방법.
The method according to any one of claims 1 to 3,
The vertical ball construction method having an opening in the uppermost slab, characterized in that the support beam is provided with a protrusion for restricting the movement of the precast slab in a longitudinal direction at an upper center of the support beam.
청구항 1 내지 3 중 어느 하나에 있어서,
상기 프리캐스트 슬래브는 하나 또는 둘 이상으로 분할 제작하여 거치하는 것을 특징으로 하는, 최상단 슬래브에 개구부를 구비한 수직구 시공방법.
The method according to any one of claims 1 to 3,
The precast slab is a vertical ball construction method having an opening in the uppermost slab, characterized in that divided into one or two or more for mounting.
삭제delete 청구항 1 내지 3 중 어느 하나에 있어서,
상기 마감슬래브는 프리캐스트 슬래브와 상기 벽체의 단부를 일체화하는 것을 특징으로 하는, 최상단 슬래브에 개구부를 구비한 수직구 시공방법.
The method according to any one of claims 1 to 3,
The finishing slab is a vertical ball construction method having an opening in the uppermost slab, characterized in that the precast slab and the end of the wall are integrated.
청구항 1 내지 3 중 어느 하나에 있어서,
개구부의 주면에 단턱부를 더 구비하여 개구부를 통하여 자재나 인력이 낙하하는 것을 방지하는 것을 특징으로 하는, 최상단 슬래브에 개구부를 구비한 수직구 시공방법.
The method according to any one of claims 1 to 3,
A vertical ball construction method having an opening in the uppermost slab, characterized in that the stepped portion is further provided on the main surface of the opening to prevent material or personnel from falling through the opening.
KR1020200049134A 2020-04-23 2020-04-23 Construction method of top slab with opening for vertical shaft KR102146077B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200049134A KR102146077B1 (en) 2020-04-23 2020-04-23 Construction method of top slab with opening for vertical shaft

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200049134A KR102146077B1 (en) 2020-04-23 2020-04-23 Construction method of top slab with opening for vertical shaft

Publications (1)

Publication Number Publication Date
KR102146077B1 true KR102146077B1 (en) 2020-08-19

Family

ID=72291654

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200049134A KR102146077B1 (en) 2020-04-23 2020-04-23 Construction method of top slab with opening for vertical shaft

Country Status (1)

Country Link
KR (1) KR102146077B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102293968B1 (en) 2021-04-17 2021-08-26 주식회사 네오시티 A device for supporting the lower part of a wall for an aerial wall construction and a method for constructing an aerial wall using the same
KR102687730B1 (en) * 2023-12-05 2024-07-23 주식회사 네오시티 Vertical structure including precast elevator pit and construction method thereof
KR102714426B1 (en) * 2024-01-23 2024-10-11 노오순 Temporary slab constructed at the top of a vertical sphere and construction method of ground concrete structure using the same

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020073985A (en) * 2001-03-19 2002-09-28 주식회사 케이티 Vertical shaft construction method and precast structures used for the method
KR101262969B1 (en) 2013-03-06 2013-05-09 창전이앤시 주식회사 Folder ladder for repairing tunnel
JP2015074910A (en) * 2013-10-08 2015-04-20 Jfe建材株式会社 Mounting structure and mounting method of canopy for vertical shaft
KR101584361B1 (en) 2015-06-12 2016-01-13 주식회사 탑이엔씨 Ventilation facilities for easy maintenance of common duct
KR101679180B1 (en) 2016-04-28 2016-11-24 주식회사 네오시티 Method for constructing concrete lining of ventilation shaft tunnel
KR102026571B1 (en) 2018-08-16 2019-11-04 고엄식 Embankment type slab bracket for vertical structure and construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020073985A (en) * 2001-03-19 2002-09-28 주식회사 케이티 Vertical shaft construction method and precast structures used for the method
KR101262969B1 (en) 2013-03-06 2013-05-09 창전이앤시 주식회사 Folder ladder for repairing tunnel
JP2015074910A (en) * 2013-10-08 2015-04-20 Jfe建材株式会社 Mounting structure and mounting method of canopy for vertical shaft
KR101584361B1 (en) 2015-06-12 2016-01-13 주식회사 탑이엔씨 Ventilation facilities for easy maintenance of common duct
KR101679180B1 (en) 2016-04-28 2016-11-24 주식회사 네오시티 Method for constructing concrete lining of ventilation shaft tunnel
KR102026571B1 (en) 2018-08-16 2019-11-04 고엄식 Embankment type slab bracket for vertical structure and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102293968B1 (en) 2021-04-17 2021-08-26 주식회사 네오시티 A device for supporting the lower part of a wall for an aerial wall construction and a method for constructing an aerial wall using the same
KR102687730B1 (en) * 2023-12-05 2024-07-23 주식회사 네오시티 Vertical structure including precast elevator pit and construction method thereof
KR102714426B1 (en) * 2024-01-23 2024-10-11 노오순 Temporary slab constructed at the top of a vertical sphere and construction method of ground concrete structure using the same

Similar Documents

Publication Publication Date Title
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
CN110268124B (en) Precast reinforced heavy concrete retaining wall
JP3644605B2 (en) Reverse driving method of underground structure under road surface.
KR102146077B1 (en) Construction method of top slab with opening for vertical shaft
KR200417438Y1 (en) Bracket structure for girder and slab construction
KR101687495B1 (en) Partial top-down construction method for building underground structures
JP2001241053A (en) Method for constructing underground structure
KR102227414B1 (en) Joint structure of underground exterior wall and slab
KR100775767B1 (en) Top-down method using the vertical steel bar for the src column
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR102298436B1 (en) Vertical concrete structure and method for constructing the same
KR102396786B1 (en) Underground expansion and top-down method of new building using reinforcement of existing underground outer wall
CN112921986A (en) Assembled underground structure and integrated construction method of assembled underground structure and foundation pit
JP5865567B2 (en) Connecting slab and its construction method
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
KR101049949B1 (en) Vertical sphere structure using reverse punching method and its construction method
US20230068973A1 (en) Construction of a building
JP3760304B2 (en) Building foundation construction method
KR0179708B1 (en) Working method for underground structure of a building
KR102115352B1 (en) Construction method of slurrry wall using prefabrecated reinforcing bar cage
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
KR101253841B1 (en) Vertically Inserting Column into the Eccentrically Bored Hole & the Method Thereof
KR101482523B1 (en) Nodular Box Girder, and Nodular Box Girder Bridge and Constructing Method thereof
KR20210090100A (en) In a building where the underground structure is a wall structure, the shortened construction type top down construction method and structure that enables early ground frame start using temporary transfer structures
JP3644606B2 (en) Installation method of formwork support in reverse placement method

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant