KR101331261B1 - Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same - Google Patents

Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same Download PDF

Info

Publication number
KR101331261B1
KR101331261B1 KR1020130037717A KR20130037717A KR101331261B1 KR 101331261 B1 KR101331261 B1 KR 101331261B1 KR 1020130037717 A KR1020130037717 A KR 1020130037717A KR 20130037717 A KR20130037717 A KR 20130037717A KR 101331261 B1 KR101331261 B1 KR 101331261B1
Authority
KR
South Korea
Prior art keywords
panel
wall
concrete
installing
underground
Prior art date
Application number
KR1020130037717A
Other languages
Korean (ko)
Inventor
윤영수
엄영호
심상준
김영준
Original Assignee
주식회사 아라엔텍
주식회사 한국종합기술
김영준
엄영호
심상준
윤영수
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 아라엔텍, 주식회사 한국종합기술, 김영준, 엄영호, 심상준, 윤영수 filed Critical 주식회사 아라엔텍
Priority to KR1020130037717A priority Critical patent/KR101331261B1/en
Application granted granted Critical
Publication of KR101331261B1 publication Critical patent/KR101331261B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B11/00Arrangements or adaptations of tanks for water supply
    • E03B11/10Arrangements or adaptations of tanks for water supply for public or like main water supply
    • E03B11/14Arrangements or adaptations of tanks for water supply for public or like main water supply of underground tanks

Abstract

The present invention relates to an underground prefabricated precast concrete (PC) rainwater recycling facility for a strut or earth anchor structure using an underground PC continuous wall which has excellent waterstop and reinforcement effects for the edge part where the underground PC continuous wall meets a bottom slab and a construction method for the same to use a temporary facility wall as a permanent structure and to install the temporary facility wall and a structure wall on the same line. A construction method for a PC rainwater recycling facility according to a proper embodiment of the present invention comprises a step of installing a guiding wall on the top of an underground continuous wall to be constructed; a step of trench-excavating a space between the guiding walls facing each other using excavation equipment, injecting a stabilizer liquid into the excavation hole, and maintaining a hollow wall; a step of installing a PC panel to be connected to the excavation hole, installing a grouting water stop between neighboring PC panels, performing joint grouting, and sealing an outer wall part with high density cement-bentonite in order to build the underground continuous wall; a step of excavating the ground of an area surrounded by the PC panels and supporting the excavated area with struts; a step of placing lean concrete onto the bottom surface of the excavated area and placing foundation concrete on the top of the lean concrete placement to build the bottom slab; a step of setting up a plurality of PC columns on the top of the bottom slab and installing a PC beam at the top of each PC column so that the PC beam supported in the PC panel is placed at the groove on the top of the PC panel; and installing a PC slab on the top of the PC beam and placing topping concrete.

Description

피씨 지중연속벽을 활용하여 스트럿구조나 어스앙카 구조에서 시공가능한 지하조립식 피씨 저류조 및 이의 시공 방법{Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same}Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same}

본 발명은 피씨 저류조 및 이의 시공 방법에 관한 것으로, 특히 벽체를 가시설 벽체로 사용 후 영구구조물로 사용할 수 있고, 가시설 벽체와 구조물 벽체가 같은 라인 상에 시공되며, 피씨 지중연속벽과 바닥슬래브가 만나는 모서리부에서의 지수 및 보강효과가 뛰어난 피씨 지중연속벽을 활용하여 스트럿구조나 어스앙카 구조에서 시공가능한 지하조립식 피씨 저류조 및 이의 시공 방법에 관한 것이다.The present invention relates to a PC storage tank and a construction method thereof, and in particular, the wall can be used as a permanent structure after using the wall as a temporary wall, and the temporary wall and the structural wall are constructed on the same line, where the PC underground wall and the floor slab meet. The present invention relates to an underground PC storage tank and a construction method thereof that can be constructed in strut structures or earth anchor structures by using PC underground continuous walls having excellent index and reinforcement effects at edges.

저류조는 물 부족과 침수 피해에 대처하기 위해 비가 올 때나 홍수 시에 빗물을 모아서 생활용수, 청소용수, 소방용수, 조경용수 등으로 사용할 수 있는 시설물이다.Reservoir is a facility that can collect rainwater during rain or flood to cope with water shortage and flood damage, and can be used as living water, cleaning water, fire water, landscaping water.

저류조는 콘크리트형 저류조와 플라스틱형 저류조가 있으며, 콘크리트형 저류조의 경우 시공 현장에서 콘크리트를 타설하여 구조물을 형성하는 현장타설식 콘크리트 저류조와 공장에서 목적에 따라 미리 만든 각 부재를 현장으로 운반하여 조립 시공하는 방식의 프리캐스트 콘크리트(Precast Concrete, PC 또는 피씨) 저류조가 있다.There are concrete storage tanks and plastic storage tanks.In the case of concrete storage tanks, on-site concrete-type storage tanks in which concrete is formed by placing concrete at the construction site and each component made in advance in the factory are transported and assembled. There is a precast concrete (PC or PC) storage tank.

현장타설식 콘크리트 저류조의 경우 가장 오래된 방식의 저류 공법인데 반해 시공(양생) 기간이 길고, 품질확보가 어렵다는 단점을 갖는다. 피씨 저류조의 경우 양생 기간이 필요없이 조립만으로 시공이 완료되는 이점을 갖는다.In the case of cast-in-place concrete storage tank, it is the oldest storage method, but it has a long construction period and it is difficult to secure quality. In the case of PC storage tank, there is an advantage that the construction is completed only by the assembly without the curing period.

본 발명의 배경이 되는 기술로는 한국 등록특허 등록번호 제10-0802994호에 대형 우수 저류조 및 이의 시공 방법이 제시되어 있다. 이 배경 기술에서는 기초지반을 굴착하고, 고른 후 기초잡석층을 포설하고 다지는 제1단계; 상기 기초잡석층상에 정밀한 위치와 레벨을 유지하기 위한 레일 또는 H형강을 기초콘크리트 상에 설치하는 제2단계; 상기 레일 또는 H형강 위에 전후방향으로 좌우측벽 및 중앙벽 들을 연속해서 설치하고, PS강봉을 사용하여 긴장 및 정착시켜 조립하는 제3단계; 저판부개구부를 폐쇄하기 위해 현장타설콘크리트 또는 PC부재로 마감하여 바닥슬래브를 완성시키는 제4단계; 연속해서 설치되는 문형 좌우측 천정슬래브 및 중앙벽들간의 상부공간을 폐쇄하기 위한 문형 중앙부 천정슬래브들을 조립 설치하는 제5단계; 상기 순서에 의해 조립 설치된 평평한 박스형상의 블록군의 전후개방구 등을 폐쇄하기 위해 전후방 마감벽들을 조립 설치하는 제6단계; 조립 완료된 부재들의 이음부 내면에는 탄성실링재를 설치하고, 저류조 외벽에는 저류조의 목적에 따라 차수시트 또는 투수시트를 설치한 후, 고운 모래층으로 되메우기를 하고 저류조 상부에 점검구와 환기공을 설치하는 제7단계; 유입구와 유출구 접합시설을 완료한 후, 저류조 상부를 복토하고 필요한 시설을 설치하는 제8단계를 순차적으로 시행하여 저류조를 시공한다.As a background technology of the present invention, a large storm storage tank and a construction method thereof are proposed in Korean Patent Registration No. 10-0802994. In the background art, the first step of excavating, selecting and laying foundation rubble layer after excavation; A second step of installing a rail or H-shaped steel on the foundation concrete to maintain a precise position and level on the foundation rubble layer; A third step of continuously installing the left and right side walls and the center walls in the front and rear directions on the rail or the H-shaped steel, and assembling by tensioning and fixing using a PS steel bar; A fourth step of finishing the floor slab by finishing with site-cast concrete or PC member to close the bottom plate opening; A fifth step of assembling and installing the door-shaped left and right ceiling slabs continuously installed and the door-shaped center ceiling slabs for closing the upper space between the center walls; A sixth step of assembling and installing the front and rear finishing walls in order to close the front and rear openings and the like of the flat box-shaped block group installed in the above order; An elastic sealing material is installed on the inner surface of the joints of the assembled members, and on the outer wall of the storage tank, a seat sheet or a permeation sheet is installed according to the purpose of the storage tank, and then the backfill is filled with a fine sand layer, and a check hole and a ventilation hole are installed on the storage tank. step; After completing the inlet and outlet connection facilities, the storage tank is constructed by sequentially performing the eighth step of covering the upper part of the reservoir and installing the necessary facilities.

상기 배경기술은 벽체에 모서리부가 일체로 형성되어져 있어 보강이나 지수구조가 필요치 않다는 장점이 있지만 저판부개구부를 폐쇄하기 위해 현장타설콘크리트 또는 PC부재로 마감하여 바닥슬래브를 완성시키게 되면, 저판부개구부와 바닥슬래브간에 물리적인 접합 경계면이 생기게 된다. 따라서 이 접합 경계면은 지수구조에 취약하게 되고, 물리적인 균열면이 발생될 소지를 가지게 된다.The background art has the advantage that the edges are integrally formed on the wall, so that no reinforcement or index structure is required, but when the floor slab is completed by finishing the cast-in-place concrete or PC member to close the bottom plate opening, the bottom plate opening and There will be a physical interface between floor slabs. Therefore, this junction interface becomes vulnerable to the exponential structure, and has a possibility of generating a physical crack surface.

한국 공개특허 공개번호 제10-2010-0130354호Korean Laid-Open Patent Publication No. 10-2010-0130354 한국 공개특허 공개번호 제10-2012-0066802호Korean Laid-Open Patent Publication No. 10-2012-0066802 한국 등록특허 등록번호 제10-0988806호Korea Patent Registration No. 10-0988806

본 발명은 피씨 지중연속벽과 바닥슬래브가 만나는 모서리부에서의 지수 및 보강효과가 뛰어난 피씨 지중연속벽을 활용한 피씨 저류조의 시공방법을 제공함에 그 목적이 있다.It is an object of the present invention to provide a method of constructing a PC storage tank using a PC underground continuous wall having excellent index and reinforcement effects at an edge portion where a PC underground continuous wall and a floor slab meet.

본 발명의 적절한 실시 형태에 따른 피씨 저류조의 시공방법은,The construction method of PC storage tank which concerns on appropriate embodiment of this invention,

지중연속벽이 구축될 상부 부분에 안내벽을 설치하는 단계와;Installing a guide wall on an upper portion of the underground continuous wall;

서로 마주하는 안내벽의 사이를 굴착 장비를 이용하여 트렌치 굴착하면서 굴착공 내로 안정액을 투입하여 공벽을 유지하는 단계와;Maintaining a hollow wall by injecting a stabilizer into the excavation hole while trenching trenches between the guide walls facing each other using the excavating equipment;

굴착공에 피씨 판넬을 연접되게 설치한 후 이웃한 피씨 판넬의 사이에 그라우팅 지수판을 설치하고 조인트 그라우팅을 실시하며 외벽부에 고비중의 시멘트-벤토나이트로 씰링을 실시하여 지중연속벽을 구축하는 단계와;After installing the PC panel in the excavation hole, install the grouting index plate between neighboring PC panels, perform joint grouting, and seal the outer wall with high-weight cement-bentonite to build underground continuous walls. ;

피씨 판넬로 에워싸진 내부 영역의 지반을 굴착한 후 지보공으로 지지시켜 놓는 단계와;Excavating the ground of the inner region enclosed with the PC panel and supporting it with the support;

굴착 바닥면에 버림콘크리트를 타설하고, 버림콘크리트 상면에 기초콘크리트를 타설하여 바닥슬래브를 시공하는 단계와;Casting the discarded concrete on the excavated bottom surface, and constructing the bottom slab by pouring the foundation concrete on the discarded concrete upper surface;

바닥슬래브의 상면에 다수의 피씨 기둥을 세우고, 각 피씨 기둥의 상단에 피씨 보를 설치하되, 피씨 판넬에 지지되는 피씨 보를 피씨 판넬의 상면에 함몰된 홈턱에 위치시키면서 설치하는 단계와;Erecting a plurality of PC pillars on an upper surface of the floor slab, and installing PC beams on the top of each PC pillar, while installing the PC beams supported by the PC panels on the recesses recessed in the upper surface of the PC panels;

피씨 보의 상면에 상부 피씨 슬래브를 시공한 후 토핑큰크리트를 타설하는 단계를 포함하는 것을 특징으로 한다.After constructing the upper PC slab on the upper surface of the PC beam, characterized in that it comprises the step of pouring topping large concrete.

또한, 지수 시공을 위해 기초콘크리트 타설시 상기 피씨 판넬의 하부에 설치된 판상형 지수판이 접합되는 단계가 더 포함되어 시공되는 것을 특징으로 한다.In addition, it characterized in that the construction further comprises the step of bonding the plate-shaped index plate installed in the lower portion of the PC panel when placing the concrete for the exponential construction.

또한, 지수 시공을 위해 피씨 판넬과 바닥슬래브가 만나는 모서리 부분에 고무재로 제작된 앵글형 지수판이 위치되고, 앵글형 지수판은 앵커 볼트의 고정력으로 덮개판에 의해 피씨 판넬과 바닥슬래브가 접하는 모서리에 설치된 내측판에 밀착되어 시공된 것을 특징으로 한다.In addition, an angle type index plate made of rubber material is positioned at the corner where the PC panel and the floor slab meet for index construction, and the angle type index plate is installed at the corner where the PC panel and the floor slab contact by the cover plate with the fixing force of the anchor bolt. It is characterized in that the construction is in close contact with the plate.

또한, 피씨 판넬과 바닥슬래브가 만나는 모서리 부분의 보강 결합을 위해, 피씨 판넬의 하부측에 매설된 쉬스관에 바닥슬래브에 매설시킨 강선을 인입시킨 후 기초콘크리트의 양생 후 피씨 판넬측에 정착시키는 단계가 더 포함되어 시공되는 것을 특징으로 한다.In addition, for reinforcing coupling of the corner portion where the PC panel and the floor slab meet, a steel wire embedded in the bottom slab is introduced into a sheath tube embedded at the bottom side of the PC panel, and then fixed on the PC panel side after curing of the foundation concrete. It is characterized in that the construction is further included.

또한, 기초콘크리트 타설시 상기 피씨 판넬의 하부에 설치된 지수판이 접합되거나, 피씨 판넬과 바닥슬래브가 만나는 모서리 부분에 접합된 L자형 내측판과 고무판 및 덮개판이 순차적으로 적층되어져 앵커 볼트로 피씨 판넬과 바닥슬래브에 접합되는 단계와; 피씨 판넬과 바닥슬래브가 만나는 모서리 부분의 보강 결합을 위해, 피씨 판넬의 하부측에 매설된 쉬스관에 바닥슬래브에 매설시킨 강선을 인입시킨 후 기초콘크리트의 양생 후 피씨 판넬측에 정착시키는 단계가 더 포함되어 시공되는 것을 특징으로 한다.In addition, when laying the foundation concrete, the index plate installed at the lower part of the PC panel is bonded, or the L-shaped inner plate, the rubber plate and the cover plate, which are bonded to the corner portion where the PC panel and the bottom slab meet, are sequentially stacked so that the PC panel and the floor are anchor bolts. Bonding to the slab; For reinforcing coupling of the corner part where the PC panel and the floor slab meet, the steel wire embedded in the bottom slab is introduced into the sheath pipe embedded at the bottom side of the PC panel, and then the curing is performed on the PC panel side after curing of the foundation concrete. It is characterized by being included.

또한, 피씨 판넬에 높이 방향으로 어스앵커를 설치한 후 피씨 판넬의 전면에 일정 간격을 두고 제2 피씨 판넬을 수직으로 하여 단계적으로 적층하면서 해당 위치에 존재하는 어스앵커를 제거한 후 매 단계마다 현장 콘크리트를 타설하여 합벽을 시공하는 단계가 더 포함된 것을 특징으로 한다.In addition, after installing the earth anchors in the height direction in the PC panel, and the second PC panel vertically stacked at a predetermined interval on the front of the PC panel, and stepped to remove the earth anchor existing in the corresponding position after each step concrete It is characterized in that it further comprises the step of constructing the plywood by pouring.

또한, 스트러트로 지지된 피씨 판넬의 전면에 일정 간격을 두고 제3 피씨 판넬, 강판, 합판 거푸집 중의 어느 하나를 수직으로 적층 한 후 현장 콘크리트를 타설하고 스트러트를 제거하면서 다시 제3 피씨 판넬, 강판, 합판 거푸집 중의 어느 하나를 수직으로 적층 한 후 현장 콘크리트를 타설하는 단계를 반복하여 합벽을 시공하는 단계가 더 포함된 것을 특징으로 한다.In addition, vertically stack any one of the third PC panel, the steel sheet, and the plywood formwork at a predetermined interval on the front side of the PC panel supported by the strut, and then cast the site concrete and remove the strut, and again the third PC panel, steel sheet, After repeating any one of the plywood formwork stacked vertically, the step of placing the concrete concrete is characterized in that it further comprises the step of constructing the plywood wall.

본 발명의 피씨 지중연속벽을 활용한 피씨 저류조 및 이의 시공 방법에 따르면, 기초콘크리트 타설시 지중연속벽을 구성하는 피씨 판넬의 하부에 설치된 판상형 지수판이 접합되거나, 피씨 판넬과 바닥슬래브가 만나는 모서리 부분에 내측판과 고무판 및 덮개판으로 이루어지는 지수모듈이 설치되어져 피씨 판넬과 바닥슬래브와의 접합 모서리부에 지수구조를 갖게 된다.According to the PC storage tank utilizing the PC underground continuous wall of the present invention and its construction method, the edge portion where the plate-shaped index plate is installed in the lower part of the PC panel constituting the underground continuous wall when the foundation concrete is placed, or the PC panel and the floor slab meet An index module composed of an inner plate, a rubber plate and a cover plate is installed at the bottom to have an index structure at the joining edge portion of the PC panel and the bottom slab.

또한, 피씨 판넬과 바닥슬래브와의 모서리부에 강연선이 긴장 정착되어져 보강 구조를 얻을 수 있다.In addition, the strands are tension-fixed at the corners of the PC panel and the floor slab to obtain a reinforcing structure.

또한, 벽체를 가시설 벽체로 사용 후 영구구조물로 사용할 수 있어 가시설 비용을 감소시킬 수 있다.In addition, the wall can be used as a permanent structure after using the wall as a temporary wall can reduce the cost of the facility.

또한, 가시설 벽체와 구조물 벽체가 같은 라인 상에 시공되어 토공량 감소에 따른 공기 및 비용을 절감시킬 수 있다.In addition, the temporary wall and the structural wall can be constructed on the same line to reduce the air and cost of reducing the amount of earthwork.

따라서 본 발명은 지하조립 피씨 저류조, 초기 우수처리시설 저류조, 주차장, 지하차도, 하수 관거 등등에 적용될 수 있다.Therefore, the present invention can be applied to the underground assembly PC storage tank, the initial stormwater treatment facility storage tank, parking lot, underground roadway, sewage pipes and the like.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1은 본 발명에 따른 지하조립식 피씨 저류조의 시공 상태도.
도 2a는 본 발명에 적용되는 피씨 판넬의 예시도.
도 2b은 본 발명에 적용되는 피씨 판넬의 다양한 단면 상태도.
도 3은 본 발명에 적용되는 코너 판넬의 다양한 단면도.
도 4는 본 발명에 적용되는 보의 사시도.
도 5a는 본 발명에 적용되는 기둥의 사시도.
도 5b는 본 발명에 적용되는 상부 슬래브의 다양한 형태를 각기 사시도로 나타낸 도면.
도 6은 지반에 안내벽이 시공된 모습을 나타내는 예시도.
도 7은 안내벽의 사이로 트렌치 굴착을 시공한 상태도.
도 8은 굴착공에 지중연속벽을 구성하는 피씨 판넬을 시공하는 상태를 나타낸 예시도.
도 9는 피씨 판넬로 둘러싸여진 부분을 굴착한 후 버림콘크리트와 기초슬래브가 시공된 상태를 나타내는 예시도.
도 10은 기둥과 보를 시공한 상태를 나타내는 예시도.
도 11은 상부 피씨 슬래브의 설치 상태를 나타내는 시공상태도.
도 12a 및 도 12b는 토핑큰크리트를 타설하여 피씨 판넬과 상부 피씨 슬래브를 일체화한 모습을 나타내는 예시도.
도 12c는 상부 슬래브와 토핑콘크리트가 연결되는 피씨 판넬 부분을 도시한 도면.
도 12d는 보, 상부 슬래브 및 토핑콘크리트가 연결되는 피씨 판넬 부분을 도시한 도면.
도 13은 피씨 판넬과 바닥슬래브간 접합부에 판상형 지수판을 이용하여 시공한 상태를 나타내는 예시도.
도 14a는 피씨 판넬과 바닥슬래브간 접합부에 앵글형 지수판을 이용하여 시공한 상태를 나타내는 예시도.
도 14b는 도 14a의 요부단면도.
도 15a는 피씨 판넬과 바닥슬래브간 접합부를 강선을 이용하여 보강한 시공상태도.
도 15b는 도 15a의 요부단면도.
도 16은 판상형 지수판, 앵글형 지수판 및 강연선을 모두 설치하여 저류조의 모서리부를 지수 및 보강한 예시도.
도 17은 합벽 시공의 공정 및 완성된 사시도를 나타낸 도면.
도 18은 벽체가 높은 경우 합벽 시공의 공정 및 완성된 사시도를 나타낸 도면.
The following drawings, which are attached in this specification, illustrate the preferred embodiments of the present invention, and together with the detailed description thereof, serve to further understand the technical spirit of the present invention. It should not be construed as limited.
1 is a state diagram of the construction of the underground assembled PC storage tank according to the present invention.
Figure 2a is an illustration of a PC panel applied to the present invention.
Figure 2b is a various cross-sectional state diagram of the PC panel applied to the present invention.
Figure 3 is a cross-sectional view of a corner panel applied to the present invention.
4 is a perspective view of a beam applied to the present invention.
Figure 5a is a perspective view of a column applied to the present invention.
Figure 5b is a perspective view of each of the various forms of the upper slab applied to the present invention.
6 is an exemplary view showing a state in which the guide wall is constructed on the ground.
7 is a state in which trench excavation is constructed between guide walls.
8 is an exemplary view showing a state of constructing a PC panel constituting the underground continuous wall in the excavation hole.
9 is an exemplary view showing a state in which cast concrete and foundation slab are constructed after excavating a portion surrounded by a PC panel.
10 is an exemplary view showing a state in which pillars and beams are constructed.
11 is a construction state diagram showing an installation state of the upper PC slab;
12A and 12B are exemplary views showing a state in which a PC panel and an upper PC slab are integrated by pouring topping large concrete;
Figure 12c is a view showing a part of the PC panel that the upper slab and the topping concrete is connected.
FIG. 12D illustrates a part of a PC panel to which beams, upper slabs, and topping concrete are connected. FIG.
FIG. 13 is an exemplary view showing a state of construction using a plate-shaped index plate at a joint portion between a PC panel and a bottom slab. FIG.
14A is an exemplary view showing a state of construction using an angled index plate in the junction between the PC panel and the bottom slab.
Fig. 14B is a sectional view of the main parts of Fig. 14A;
Figure 15a is a construction state reinforcement using a steel wire junction between the PC panel and the floor slab.
Fig. 15B is a sectional view of the main parts of Fig. 15A;
FIG. 16 is an exemplary view in which all of the plate-shaped index plate, the angle-type index plate, and the strand are installed to index and reinforce the corner portion of the storage tank. FIG.
17 is a view showing a process and a completed perspective view of the construction of the plywood wall.
18 is a view showing a process and a completed perspective view of the plywood construction when the wall is high.

아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in detail below with reference to the embodiments shown in the accompanying drawings, but the present invention is not limited thereto.

먼저, 도 1, 도 3 및 도 11에서와 같이 본 발명의 조립식 피씨 저류조는 벽체(가시설 벽체)를 구성하는 피씨 판넬(20) 및 코너 판넬(21)과, 저류조의 바닥층을 이루는 버림콘크리트(30)와 바닥슬래브(32), 저류조의 상부 구조물을 이루는 보(36), 상부 피씨 슬래브(38)와 토핑콘크리트(39), 그리고 상부 구조물을 지지하는 기둥(34)을 포함한다.First, the prefabricated PC storage tank of the present invention, as shown in Figures 1, 3 and 11, the PC panel 20 and the corner panel 21 constituting the wall (temporary wall) and the discarded concrete 30 forming the bottom layer of the storage tank ) And a bottom slab 32, a beam 36 constituting the upper structure of the storage tank, the upper PC slab 38 and the topping concrete 39, and a pillar 34 for supporting the upper structure.

피씨 판넬(20)은 도 2a와 같이 폭, 높이, 두께를 갖는 육면체 형태로서 공장에서 프리캐스트 콘크리트로 제작된다. 이때 강도를 보강하기 위해 PS강선, PS강연선, 강봉 등이 설치되며 도 2b(가)에 도시된 바와 같이 단면이 솔리드형이거나 도 2b(나)와 같이 중공 구멍(20a)을 갖는 중공형이 될 수 있다.The PC panel 20 is made of precast concrete in a factory in the form of a cube having a width, a height, and a thickness as shown in FIG. 2A. At this time, PS steel wire, PS steel wire, steel rods, etc. are installed to reinforce the strength, and the cross section is solid as shown in FIG. Can be.

코너 판넬(21)은 저류조(1)의 벽체 모서리부에 배치되는 것으로, 도 3과 같이 다양한 단면 형태를 가질 수 있다. 즉 코너 판넬(21)은 도3(가),(나)와 같이 L자형 단면이 되거나 도3(다),(라)와 같이 일자형 단면이 될 수 있다. 코너 판넬(21)은 피씨 판넬(20)과 동일한 프리캐스트 콘크리트로 제작된다. 이때 코너 판넬(21)의 양쪽에는 지수재를 설치하기 위해 상하방향으로 요홈이 형성될 수 있다. 이때 양쪽 요홈간의 방향은 직각을 이룬다.The corner panel 21 is disposed at the edge of the wall of the storage tank 1 and may have various cross-sectional shapes as shown in FIG. 3. That is, the corner panel 21 may have an L-shaped cross section as shown in FIGS. 3 (a) and 3 (b) or a straight cross section as shown in FIG. 3 (c) and (d). The corner panel 21 is made of the same precast concrete as the PC panel 20. In this case, grooves may be formed on both sides of the corner panel 21 in the vertical direction to install the water repellent material. At this time, the direction between both grooves forms a right angle.

버림콘크리트(30)는 저류조의 최하위 바닥층을 이루는 부분으로 현장 콘크리트로 타설된다. 버림콘크리트(30)는 벽체 내부의 토공을 실시한 후 이루어진다. 바닥슬래브(32)는 버림콘크리트(30)의 상면에 설치된다. 바닥슬래브(32)는 철근이 배근되고, 배근된 철근은 현장 타설된 콘크리트와 합성된다.The discarded concrete 30 is poured into the site concrete as a part forming the bottom floor of the storage tank. The discarded concrete 30 is made after earthwork is carried out inside the wall. The bottom slab 32 is installed on the upper surface of the discarded concrete 30. The bottom slab 32 is reinforced with reinforcement, the reinforced reinforcement is composited with the site-cast concrete.

보(36)는 도 4와 같이 프리캐스트 콘크리트로 제작되어 길이 방향으로 사각단면을 갖는다. 이때 보(36)의 상면 및 양단으로 돌출된 합성용 철근을 갖는다. 본 실시 예에 제시된 보(36)는 일 형태로서 본 발명은 예시된 형태에 한정되는 것은 아니다.The beam 36 is made of precast concrete as shown in FIG. 4 and has a rectangular cross section in the longitudinal direction. At this time, it has a synthetic reinforcing bar projecting to the upper surface and both ends of the beam (36). The beam 36 shown in this embodiment is one form, and the present invention is not limited to the illustrated form.

기둥(34)은 도 5a와 같이 높이 방향으로 사각 단면을 가지며 상부와 하부에 헌치부를 갖는다. 또한 기둥(34)은 상단에 슬래브와의 합성을 위해 합성철근이 설치되어져 있다.The pillar 34 has a rectangular cross section in the height direction as shown in FIG. 5A and has haunches at the top and the bottom. In addition, the pillar 34 is a synthetic reinforcing bar is installed on the top for the synthesis with the slab.

상부 피씨 슬래브(38)는 도 5b의 (가)와 같이 하프 슬래브, (나)의 중공형 슬래브, (다)의 더블티 슬래브, (라)의 역리브 슬래브 등 본 발명이 속하는 기술분야에서 공지된 임의의 피씨 슬래브가 사용될 수 있다.The upper PC slab 38 is well known in the art to which the present invention belongs, such as a half slab, a hollow slab of (B), a double tee slab of (C), and an inverted rib slab of (D) as shown in FIG. Any PC slab can be used.

이와 같이 이루어진 지중조립식 저류조의 시공 방법을 설명한다.The construction method of the underground assembly storage tank made in this way is demonstrated.

먼저, 도 6과 같이 지중연속벽이 구축될 지면(11)의 상부 부분에 안내벽(12)을 설치한다. 이때, 안내벽(12)은 피씨 판넬(20)이 인입될 위치에 거푸집을 설치한 후 거푸집의 외부로 콘크리트를 타설하여 시공되거나 H형강을 설치하여 시공될 수 있다. 안내벽(12)은 지반 굴착시 가이드라인이 되며 피씨 판넬의 거치대 역활과 표토의 안전성을 제공하게 된다.First, as shown in FIG. 6, the guide wall 12 is installed in an upper portion of the ground 11 on which the underground continuous wall is to be constructed. In this case, the guide wall 12 may be installed by installing the formwork at the position where the PC panel 20 is to be drawn, and then installing concrete to the outside of the formwork or installing the H-shaped steel. The guide wall 12 serves as a guideline when excavating the ground and provides the role of the cradle of the PC panel and the safety of the topsoil.

다음, 도 7과 같이 서로 마주하는 안내벽(12)(12) 사이를 수직으로 굴착 장비를 이용하여 트렌치 굴착을 수행하고, 굴착공 내로 안정액을 투입하여 공벽의 붕괴를 방지한다. 안정액은 예로 시멘트-베토나이트가 될 수 있다. 트렌치 굴착은 안내벽(12)(12)을 따라 이루어진다. 안내벽(12)(12)을 따라 굴착이 이루어지면 굴착공(13)이 형성된다. 이때 굴착 장비에 경사계 또는 음파측정기를 설치하여 수직도를 맞추고 굴착 심도를 확보한다. 굴착 중에는 피씨 판넬의 보호를 위한 측면보호판과 판넬 밀착을 위한 판넬 가이드가 설치될 수 있다.Next, trench excavation is performed using the excavation equipment vertically between the guide walls 12 and 12 facing each other as shown in FIG. 7, and a stabilizer is introduced into the excavation hole to prevent the collapse of the hollow walls. The stabilizer can be, for example, cement-betonite. Trench excavation takes place along the guide walls 12, 12. When excavation is made along the guide walls 12 and 12, an excavation hole 13 is formed. At this time, install the inclinometer or sonic measuring equipment in the excavation equipment to adjust the verticality and secure the depth of excavation. During excavation, a side guard plate for protecting the PC panel and a panel guide for panel contact may be installed.

그 다음, 도 8과 같이 굴착공(13)에 피씨 판넬(20)을 연접되게 설치한다. 피씨 판넬(20)은 도 2b(가)에 도시된 바와 같이 단면이 솔리드형이거나 (나)와 같이 중공 구멍(20a)을 갖는 중공형이 될 수 있다. 이때 도 8과 같이 이웃한 피씨 판넬(20)(20)의 사이에 그라우팅 지수판(22)을 설치하고 조인트 그라우팅을 실시하며 외벽부에 고비중의 시멘트-벤토나이트로 씰링을 실시한다. 그라우팅 지수판(22)은 내부에 패커, 그라우팅 호스가 설치되어, 그라우팅 호스를 통해 주입된 그라우트재가 그라우팅 지수판(22)의 홀(22a)을 통해 배출되어 그라우팅 차수막을 형성한다. 이에 따라 지중에는 연속된 벽체 즉, 지중연속벽이 구축된다. 이 지중연속벽은 굴착작업 중에는 흙막이 벽체가 되고 굴착이 완료된 후에는 저류조의 벽체를 구성한다. 따라서 본 발명에 따르면, 가설 흙막이 벽체를 별도로 구축할 필요가 없고 또한 가설 흙막이 벽체가 저류조의 벽체를 구성하므로 굴착 완료 후 저류조의 벽체를 별도로 구축할 필요가 없게 된다.Next, the PC panel 20 is installed to be connected to the excavation hole 13 as shown in FIG. 8. The PC panel 20 may be solid as shown in FIG. 2B (A), or may be hollow having a hollow hole 20a as shown in (B). In this case, as shown in FIG. 8, a grouting index plate 22 is installed between neighboring PC panels 20 and 20, and joint grouting is performed to seal the outer wall portion with a high specific weight of cement-bentonite. The grouting index plate 22 is provided with a packer and a grouting hose therein, and the grout material injected through the grouting hose is discharged through the holes 22a of the grouting index plate 22 to form a grouting lining film. As a result, continuous walls, that is, underground continuous walls, are constructed in the ground. This underground continuous wall becomes an earth wall during the excavation work and forms a wall of the storage tank after the excavation is completed. Therefore, according to the present invention, it is not necessary to separately build the temporary barrier wall, and since the temporary barrier wall constitutes the wall of the storage tank, there is no need to separately construct the wall of the storage tank after the excavation is completed.

여기서 벽체의 모서리부는 도 3과 같은 다양한 단면 형태를 갖는 코너 판넬(21) 중 어느 하나가 될 수 있다.Here, the edge portion of the wall may be any one of the corner panels 21 having various cross-sectional shapes as shown in FIG. 3.

이때 도 9와 같이 피씨 판넬(20)과 굴착공(13)과의 사이에는 시멘트 벤토나이드(19)가 충진됨이 바람직하다.At this time, it is preferable that the cement bentonide 19 is filled between the PC panel 20 and the excavation hole 13 as shown in FIG. 9.

그 다음, 도 9와 같이 피씨 판넬(20)들로 에워싸진 내부 영역의 지반을 굴착한 후 지보공(25)으로 지지시켜 놓는다. 여기서 지보공(25)이란 굴착 중 피씨 판넬(20)로 이루어지는 지중연속벽의 전도를 방지하기 위해 설치되는 버팀보 및 그 부속물을 의미한다. 이때 굴착 깊이에 따라 버티보의 설치는 반복된다.Next, as shown in FIG. 9, the ground of the inner region surrounded by the PC panels 20 is excavated and supported by the support holes 25. Here, the support ball 25 refers to a brace and its accessories installed to prevent the ground continuous wall made of the PC panel 20 during excavation. At this time, the installation of the vertical beam is repeated according to the excavation depth.

이후, 도 10과 같이 굴착된 굴착공의 바닥면에 버림콘크리트(30)를 타설하고, 버림콘크리트 상면에 기초콘크리트를 타설하여 일정 두께 바닥슬래브(32)를 시공한다. 바닥슬래브(32) 내에는 철근이 배근되어 질 수 있다. 이때 바닥슬래브(32)는 모서리를 따라 헌치를 형성시킴이 바람직하다.Then, cast concrete 30 on the bottom surface of the excavated excavation hole as shown in Figure 10, and the foundation concrete is poured on the discarded concrete upper surface to construct a floor slab 32 of a predetermined thickness. Reinforcing bars may be arranged in the bottom slab 32. At this time, the bottom slab 32 is preferably to form a haunch along the corner.

그 다음, 도 11과 같이 바닥슬래브(32)의 상면에 설정된 위치마다 피씨 기둥(34)을 세우고, 피씨 기둥(34)의 상단에 피씨 보(36)를 설치한다. 피씨 기둥(34)과 바닥슬래브(32)간의 접합 그리고 피씨 기둥(34)과 피씨 보(36)의 접합은 이 분야에서 주지의 기술이므로 상세한 설명은 생략한다. 이때 피씨 판넬(20)에 지지되는 피씨 보(36)를 도 12a 내지 도 12d와 같이 피씨 판넬(20)의 상면에 함몰되어 형성된 홈턱(20b)에 위치시키면서 설치함이 바람직하다. 따라서 피씨 보(36)는 확고하고 안정된 설치 구조를 갖게 된다.Then, the PC pillar 34 is erected at each position set on the upper surface of the floor slab 32 as shown in FIG. 11, and the PC beam 36 is installed on the top of the PC pillar 34. Since the joint between the PC pillar 34 and the bottom slab 32 and the PC pillar 34 and the PC beam 36 are well known in the art, detailed description thereof will be omitted. At this time, it is preferable to install the PC beam 36 supported by the PC panel 20 while being located in the grooved jaw 20b formed by recessing the upper surface of the PC panel 20 as shown in FIGS. 12A to 12D. Therefore, the PC beam 36 has a firm and stable installation structure.

그 다음, 피씨 보(36)의 상면에 상부 피씨 슬래브(38)를 시공한 후 도 12a 및 도 12b와 같이 토핑콘크리트(39)를 타설한다. 이때 토핑콘크리트(39)의 두께 층에 피씨 판넬(20)의 상부에 일정 구간 노출시킨 이형철근(27)을 매입되게 하여 시공될 수 있다. 도 12a는 상부 피씨 슬래브(38)가 피씨 판넬(20)의 상단에 지지되어 있는 상태에서 토핑콘크리트(39)가 타설되어 있는 상태를 나타내고, 도 12b는 피씨 보(36)의 단부가 피씨 판넬(20)의 상면에 함몰되어 형성된 홈턱(20b)에 지지되어 있는 상태에서 이형철근(27)이 피씨 보(36)의 단부를 삽통하여 토핑콘크리트(39)에 합성되어 있는 상태를 나타낸다. 이 경우 토핑콘크리트(39)층은 이형철근(27)을 매개로 피씨 판넬(20)에 합성되고, 이로 인해 상부 피씨 슬래브(38)는 토핑콘크리트(39)와 피씨 보(36)의 사이에서 안정되게 설치된다.Next, after the upper PC slab 38 is constructed on the upper surface of the PC beam 36, the topping concrete 39 is poured as shown in FIGS. 12A and 12B. At this time, it can be constructed by embedding the deformed reinforcing bar 27 exposed to the upper portion of the PC panel 20 in the thickness layer of the topping concrete 39 to be embedded. FIG. 12A illustrates a state in which the topping concrete 39 is poured while the upper PC slab 38 is supported on the upper end of the PC panel 20. FIG. 12B shows that the end of the PC beam 36 has a PC panel ( The deformed reinforcing bar 27 is inserted into the topping concrete 39 by inserting the end portion of the PC beam 36 in a state of being supported by the grooved jaw 20b formed by being recessed on the upper surface of 20). In this case, the topping concrete 39 layer is synthesized in the PC panel 20 through the deformed reinforcing bar 27, so that the upper PC slab 38 is stable between the topping concrete 39 and the PC beam 36. It is installed.

여기서, 지수 시공을 위해 기초콘크리트 타설시 도 13과 같이 상기 피씨 판넬(20)의 하부에 설치된 판상형 지수판(31)이 접합되는 단계가 더 포함될 수 있다. 이때 판상형 지수판(31)은 도 13에서와 같이 일부가 피씨 판넬(20)에 타부가 바닥슬래브(32)에 매설되도록 한다. 따라서 피씨 판넬(20)과 바닥슬래브(32)가 접하게 되는 모서리부분에 판상형 지수판(31)에 의한 수밀 구조를 갖게 된다. 이때 판상형 지수판(31)은 판상형으로 금속, 합성수지, 복합소재 등으로 제작된 것이 될 수 있다.Here, the step of bonding the plate-shaped index plate 31 installed in the lower portion of the PC panel 20 as shown in Figure 13 when the foundation concrete for the exponential construction may be further included. At this time, the plate-shaped index plate 31, as shown in Figure 13 so that the other part is embedded in the bottom panel 32 in the PC panel 20. Therefore, it has a watertight structure by the plate-shaped index plate 31 at the corner portion where the PC panel 20 and the bottom slab 32 are in contact with each other. At this time, the plate-shaped index plate 31 may be made of a plate-like metal, synthetic resin, composite material.

또 다른 방법으로 지수 시공을 위해 도 14a 및 도 14b에서와 같이 피씨 판넬(20)과 바닥슬래브(32)가 만나는 모서리 부분에 고무재로 제작된 앵글형 지수판(42)이 설치될 수 있다. 이때 앵글형 지수판(42)은 피씨 판넬(20)과 바닥슬래브(32)가 접하는 모서리에 설치된 내측판(40)(40)에 밀착된 후 덮개판(44)에 의해 설치된다. 내측판(40)(40)과 덮개판(44)의 대형면에는 각각 돌기(44a)가 형성되어 앵글형 지수판(42)를 가압한다. 이때 덮개판(44)은 L자형으로 피씨 판넬(20)과 바닥슬래브(32)에 고정되어 있는 앵커 볼트(46)에 의해 앵글형 지수판(42)을 모서리부에 밀착시킨다. 내측판(40)과 덮개판(44)은 강재로 제작된 것이 사용될 수 있다. As another method, an angle type index plate 42 made of rubber may be installed at an edge portion where the PC panel 20 and the bottom slab 32 meet as shown in FIGS. 14A and 14B. At this time, the angle type index plate 42 is installed by the cover plate 44 after being in close contact with the inner plate 40, 40 is installed in the corner that the PC panel 20 and the bottom slab 32 contact. Protrusions 44a are formed on the large surfaces of the inner plates 40 and 40 and the cover plate 44 to press the angled index plates 42, respectively. At this time, the cover plate 44 is L-shaped in close contact with the angle-shaped index plate 42 by the anchor bolt 46 fixed to the PC panel 20 and the bottom slab 32. The inner plate 40 and the cover plate 44 may be made of steel.

한편, 피씨 판넬(20)과 바닥슬래브(32)가 만나는 모서리 부분의 보강 결합을 위해, 도 15a 및 도 15b에 도시된 바와 같이 피씨 판넬(20)의 하부측에 매설된 쉬스관(24)에 바닥슬래브(32)에 매설시킨 강선(33)을 인입시킨 후 기초콘크리트의 양생 후 피씨 판넬(20)측에 정착시키는 단계가 더 포함되어 시공될 수 있다. 이때 쉬스관(24)은 피씨 판넬(20) 내부에 매설된 상태에서 하단이 바닥슬래브(32)와 연결되는 접합용 홈부(201)에 위치되고 상단은 피씨 판넬(20)의 정착홈(202)에 위치된다.On the other hand, for the reinforcement coupling of the corner portion where the PC panel 20 and the bottom slab 32, in the sheath tube 24 embedded in the lower side of the PC panel 20, as shown in Figure 15a and 15b After the steel wire 33 embedded in the bottom slab 32 is drawn in, the curing of the foundation concrete may be further included and the step of fixing the PC panel 20 side. At this time, the sheath tube 24 is located in the joining groove 201 connected to the bottom slab 32 in the state embedded in the PC panel 20, the upper end of the fixing groove 202 of the PC panel 20 Is located in.

이같이 피씨 판넬(20)과 바닥슬래브(32)가 만나는 모서리 부분에 강선(33)을 긴장시켜 설치하는 경우 강선(33)에 의해 바닥슬래브(32)의 단부에 압축력을 발생시켜 보강이 이루어진다.As such, when the steel wire 33 is tensioned and installed at the corner portion where the PC panel 20 and the bottom slab 32 meet, the steel wire 33 generates a compressive force at an end portion of the bottom slab 32, thereby making reinforcement.

한편, 본 발명은 도 16과 같이 위에서 예시된 2가지의 지수 방법 및 보강 방법을 모두 적용하여 구현될 수 있다. 따라서 저류조의 바닥 모서리부의 지수력은 배가되고 보강력은 증대된다.On the other hand, the present invention can be implemented by applying both the exponential method and the reinforcement method illustrated above as shown in FIG. Therefore, the exponential force at the bottom edge of the reservoir is doubled and the reinforcement is increased.

다른 한편, 본 발명은 도 17과 같이 같이 피씨 판넬(20)에 높이 방향으로 어스앵커(61)(62)를 설치한 후 피씨 판넬(20)의 전면에 일정 간격을 두고 제2 피씨 판넬(71)(72)(73)을 수직으로 하여 단계적으로 적층한 후 해당 위치에 존재하는 어스앵커(61)(62)를 순차적으로 제거하면서 매 제거 단계마다 현장 콘크리트(81)를 타설하여 합벽이 시공될 수 있다.On the other hand, the present invention, after installing the earth anchors 61, 62 in the height direction in the PC panel 20 as shown in Figure 17, the second PC panel 71 at a predetermined interval on the front surface of the PC panel 20. ) 72 and 73 are stacked vertically and then the earth anchors 61 and 62 existing at the corresponding positions are sequentially removed while the concrete concrete 81 is poured in each removal step to construct the plywood wall. Can be.

즉, 1단계에서 제2 피씨 판넬(71)을 설치한 후 현장 콘크리트를 타설하고 첫 번째 어스앵커(61)를 제거한다. 다음, 2단계에서 제2 피씨 판넬(72)을 설치한 후 현장 콘크리트를 타설하고 두 번째 어스앵커(62)를 제거한다. 그 다음, 3단계에서 제2피씨 판넬(72)을 설치한 후 현장 콘크리트를 타설하여 이루어지는 방법이다.That is, after installing the second PC panel 71 in the first step, the site concrete is poured and the first earth anchor 61 is removed. Next, after installing the second PC panel 72 in the second step, the site concrete is poured and the second earth anchor 62 is removed. Then, after installing the second PC panel 72 in the third step is a method made by pouring the site concrete.

또한 합벽 시공의 다른 방법으로 높이가 높은 경우에, 도 18과 같이 스트러트(88)로 지지된 피씨 판넬(72)의 전면에 일정 간격을 두고 제3 피씨 판넬(73)을 수직으로 적층 한 후 현장 콘크리트(81)를 타설하고 스트러트를 제거하면서 제3 피씨 판넬(73)을 수직으로 적층 한 후 현장 콘크리트(81)를 타설하는 단계를 반복하여 합벽을 시공할 수 있다. 이때 제3 피씨 판넬(73)에 대체하여 강판 또는 합판 거푸집이 사용될 수도 있다.In addition, when the height is high by another method of plywood construction, the third PC panel 73 is vertically laminated at a predetermined interval on the front surface of the PC panel 72 supported by the strut 88 as shown in FIG. After placing the concrete 81 and removing the struts, the third PC panel 73 is vertically stacked, and then the step of pouring the field concrete 81 may be repeated to construct the plywood wall. In this case, a steel plate or plywood formwork may be used in place of the third PC panel 73.

지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is evident that many alternatives, modifications and variations will be apparent to those skilled in the art in light of the above teachings. will be. The invention is not limited by these variations and modifications, but is limited only by the claims appended hereto.

12: 안내벽
13: 굴착공
20: 피씨 판넬
24: 쉬스관
27: 이형철근
30: 버림콘크리트
31: 판상형 지수판
32: 바닥슬래브
33: 강선
38: 상부 피씨 슬래브
39: 토핑콘크리트
42: 앵글형 지수판
12: guide wall
13: excavator
20: PC panel
24: Sheath tube
27: deformed rebar
30: cast concrete
31: plate-shaped index plate
32: floor slab
33: liner
38: Upper PC Slab
39: topping concrete
42: angled index plate

Claims (8)

삭제delete 지중연속벽이 구축될 상부 부분에 안내벽을 설치하는 단계와;
서로 마주하는 안내벽의 사이를 굴착 장비를 이용하여 트렌치 굴착하면서 굴착공 내로 안정액을 투입하여 공벽을 유지하는 단계와;
굴착공에 피씨 판넬을 연접되게 설치한 후 이웃한 피씨 판넬의 사이에 그라우팅 지수판을 설치하고 조인트 그라우팅을 실시하며 외벽부에 고비중의 시멘트-벤토나이트로 씰링을 실시하여 지중연속벽을 구축하는 단계와;
피씨 판넬로 에워싸진 내부 영역의 지반을 굴착한 후 지보공으로 지지시켜 놓는 단계와;
굴착 바닥면에 버림콘크리트를 타설하고, 버림콘크리트 상면에 기초콘크리트를 타설하여 바닥슬래브를 시공하는 단계와;
바닥슬래브의 상면에 다수의 피씨 기둥을 세우고, 각 피씨 기둥의 상단에 피씨 보를 설치하되, 피씨 판넬에 지지되는 피씨 보를 피씨 판넬의 상면에 함몰된 홈턱에 위치시키면서 설치하는 단계와;
피씨 보의 상면에 상부 피씨 슬래브를 시공한 후 토핑큰크리트를 타설하는 단계를 포함하고,
지수 시공을 위해 기초콘크리트 타설시 상기 피씨 판넬의 하부에 설치된 판상형 지수판이 접합되는 단계가 더 포함되어 시공되는 것을 특징으로 하는 피씨 지중연속벽을 활용하여 스트럿구조나 어스앙카 구조에서 시공가능한 지하조립식 피씨 저류조의 시공 방법.
Installing a guide wall on an upper portion of the underground continuous wall;
Maintaining a hollow wall by injecting a stabilizer into the excavation hole while trenching trenches between the guide walls facing each other using the excavating equipment;
After installing the PC panel in the excavation hole, install the grouting index plate between neighboring PC panels, perform joint grouting, and seal the outer wall with high-weight cement-bentonite to build underground continuous walls. ;
Excavating the ground of the inner region enclosed with the PC panel and supporting it with the support;
Casting the discarded concrete on the excavated bottom surface, and constructing the bottom slab by pouring the foundation concrete on the discarded concrete upper surface;
Erecting a plurality of PC pillars on an upper surface of the floor slab, and installing PC beams on the top of each PC pillar, while installing the PC beams supported by the PC panels on the recesses recessed in the upper surface of the PC panels;
Constructing an upper PC slab on the upper surface of the PC beam, and then pouring the topping large concrete,
Underground concrete for construction of exponential construction, the plate-like exponential plate installed in the lower part of the PC panel is further included, the step of using the underground continuous wall, characterized in that the construction is possible to install in the strut structure or earth anchor structure Construction method of storage tank.
지중연속벽이 구축될 상부 부분에 안내벽을 설치하는 단계와;
서로 마주하는 안내벽의 사이를 굴착 장비를 이용하여 트렌치 굴착하면서 굴착공 내로 안정액을 투입하여 공벽을 유지하는 단계와;
굴착공에 피씨 판넬을 연접되게 설치한 후 이웃한 피씨 판넬의 사이에 그라우팅 지수판을 설치하고 조인트 그라우팅을 실시하며 외벽부에 고비중의 시멘트-벤토나이트로 씰링을 실시하여 지중연속벽을 구축하는 단계와;
피씨 판넬로 에워싸진 내부 영역의 지반을 굴착한 후 지보공으로 지지시켜 놓는 단계와;
굴착 바닥면에 버림콘크리트를 타설하고, 버림콘크리트 상면에 기초콘크리트를 타설하여 바닥슬래브를 시공하는 단계와;
바닥슬래브의 상면에 다수의 피씨 기둥을 세우고, 각 피씨 기둥의 상단에 피씨 보를 설치하되, 피씨 판넬에 지지되는 피씨 보를 피씨 판넬의 상면에 함몰된 홈턱에 위치시키면서 설치하는 단계와;
피씨 보의 상면에 상부 피씨 슬래브를 시공한 후 토핑큰크리트를 타설하는 단계를 포함하고,
지수 시공을 위해 피씨 판넬과 바닥슬래브가 만나는 모서리 부분에 고무재로 제작된 앵글형 지수판이 위치되고, 앵글형 지수판은 앵커 볼트의 고정력으로 덮개판에 의해 피씨 판넬과 바닥슬래브가 접하는 모서리에 설치된 내측판에 밀착되어 시공된 것을 특징으로 하는 피씨 지중연속벽을 활용하여 스트럿구조나 어스앙카 구조에서 시공가능한 지하조립식 피씨 저류조의 시공 방법.
Installing a guide wall on an upper portion of the underground continuous wall;
Maintaining a hollow wall by injecting a stabilizer into the excavation hole while trenching trenches between the guide walls facing each other using the excavating equipment;
After installing the PC panel in the excavation hole, install the grouting index plate between neighboring PC panels, perform joint grouting, and seal the outer wall with high-weight cement-bentonite to build underground continuous walls. ;
Excavating the ground of the inner region enclosed with the PC panel and supporting it with the support;
Casting the discarded concrete on the excavated bottom surface, and constructing the bottom slab by pouring the foundation concrete on the discarded concrete upper surface;
Erecting a plurality of PC pillars on an upper surface of the floor slab, and installing PC beams on the top of each PC pillar, while installing the PC beams supported by the PC panels on the recesses recessed in the upper surface of the PC panels;
Constructing an upper PC slab on the upper surface of the PC beam, and then pouring the topping large concrete,
An angled index plate made of rubber is placed at the corner where the PC panel and the bottom slab meet for index construction, and the angle type index plate is mounted on the inner plate installed at the corner where the PC panel and the bottom slab are contacted by the cover plate with the fixing force of the anchor bolt. Construction method of underground assembly type PC storage tank which can be constructed in strut structure or earth anchor structure by using PC underground continuous wall characterized in that it is constructed in close contact.
제3항에 있어서,
피씨 판넬과 바닥슬래브가 만나는 모서리 부분의 보강 결합을 위해, 피씨 판넬의 하부측에 매설된 쉬스관에 바닥슬래브에 매설시킨 강선을 인입시킨 후 기초콘크리트의 양생 후 피씨 판넬측에 정착시키는 단계가 더 포함되어 시공되는 것을 특징으로 하는 피씨 지중연속벽을 활용하여 스트럿구조나 어스앙카 구조에서 시공가능한 지하조립식 피씨 저류조의 시공 방법.
The method of claim 3,
For reinforcing coupling of the corner part where the PC panel and the floor slab meet, the steel wire embedded in the bottom slab is introduced into the sheath pipe embedded at the bottom side of the PC panel, and then the curing is performed on the PC panel side after curing of the foundation concrete. Construction method of underground assembly type PC storage tank that can be constructed in strut structure or earth anchor structure by using PC underground continuous wall, characterized in that the construction is included.
삭제delete 청구항 제2항 또는 제3항에 있어서,
피씨 판넬에 높이 방향으로 어스앵커를 설치한 후 피씨 판넬의 전면에 일정 간격을 두고 제2 피씨 판넬을 수직으로 하여 단계적으로 적층하면서 해당 위치에 존재하는 어스앵커를 제거한 후 매 단계마다 현장 콘크리트를 타설하여 합벽을 시공하는 단계가 더 포함된 것을 특징으로 하는 피씨 지중연속벽을 활용하여 스트럿구조나 어스앙카 구조에서 시공가능한 지하조립식 피씨 저류조의 시공 방법.
The method according to claim 2 or 3,
After installing the earth anchors in the PC panel in the height direction, lay the second PC panels vertically with a certain distance on the front of the PC panel, and remove the earth anchors in the corresponding position, and then install the site concrete at every step. Construction method of underground assembly type PC storage tank can be constructed in a strut structure or earth anchor structure using the PC underground continuous wall, characterized in that further comprising the step of constructing the plywood wall.
청구항 제2항 또는 제3항에 있어서,
스트러트로 지지된 피씨 판넬의 전면에 일정 간격을 두고 제3 피씨 판넬, 강판, 합판 거푸집 중의 어느 하나를 수직으로 적층 한 후 현장 콘크리트를 타설하고 스트러트를 제거하면서 다시 제3 피씨 판넬, 강판, 합판 거푸집 중의 어느 하나를 수직으로 적층 한 후 현장 콘크리트를 타설하는 단계를 반복하여 합벽을 시공하는 단계가 더 포함된 것을 특징으로 하는 피씨 지중연속벽을 활용하여 스트럿구조나 어스앙카 구조에서 시공가능한 지하조립식 피씨 저류조의 시공 방법.
The method according to claim 2 or 3,
Lay out vertically one of the third PC panel, steel plate, and plywood formwork at regular intervals on the front side of the PC panel supported by strut. Lay out any one of the vertically stacked and then cast concrete on the site by repeating the step of constructing the plywood using the underground continuous wall PC underground construction available in the strut structure or earth anchor structure Construction method of storage tank.
청구항 제2항 또는 제3항의 시공방법으로 제작된 것을 특징으로 하는 피씨 지중연속벽을 활용하여 스트럿구조나 어스앙카 구조에서 시공가능한 지하조립식 피씨 저류조.An underground assembly type PC storage tank that can be constructed in a strut structure or an earth structure using a PC underground continuous wall, which is manufactured by the method of claim 2.
KR1020130037717A 2013-04-05 2013-04-05 Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same KR101331261B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130037717A KR101331261B1 (en) 2013-04-05 2013-04-05 Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130037717A KR101331261B1 (en) 2013-04-05 2013-04-05 Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same

Publications (1)

Publication Number Publication Date
KR101331261B1 true KR101331261B1 (en) 2013-11-20

Family

ID=49858108

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130037717A KR101331261B1 (en) 2013-04-05 2013-04-05 Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same

Country Status (1)

Country Link
KR (1) KR101331261B1 (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103614998A (en) * 2013-11-26 2014-03-05 中冶天工集团有限公司 Lining wall concrete placement top-down method based on underground diaphragm wall
KR101779739B1 (en) * 2017-01-10 2017-09-19 아이앤티엔지니어링(주) Connection Structure Of Elevator Pit Under Structure And Steel Form
WO2018177305A1 (en) * 2017-03-29 2018-10-04 王燏斌 Groove pile for fabricated underground building and construction method thereof
WO2018177308A1 (en) * 2017-03-29 2018-10-04 王燏斌 Fabricated underground building interface structure and construction method thereof
CN108755968A (en) * 2018-07-17 2018-11-06 有利华建筑预制件(深圳)有限公司 Assembling synthesis building and its construction method
CN109235639A (en) * 2018-11-15 2019-01-18 福建工程学院 Prestressing without bondn assembling type node and construction method with energy-consuming device
KR101971554B1 (en) * 2018-09-18 2019-09-03 주식회사 티아이에스 Method constructuring an underground structure using a temporary structure
KR20190110713A (en) * 2018-03-21 2019-10-01 유기선 Underground structure wall and underground structure and method construturing the same
CN110453675A (en) * 2019-08-27 2019-11-15 中煤第三建设(集团)有限责任公司 One kind is folded to pour formula diaphram wall and its construction method
KR20210035663A (en) * 2019-09-24 2021-04-01 주식회사 제영이엔씨 the underground undercurrent space structure by the caisson assembly and this construction method
CN113981948A (en) * 2021-12-06 2022-01-28 上海建工一建集团有限公司 Reverse construction method adopting prefabricated underground continuous wall

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55161117A (en) * 1979-06-02 1980-12-15 Ohbayashigumi Ltd Constructing method for underground continuous wall by precast concrete member
JPH10331153A (en) * 1997-05-29 1998-12-15 Tone Chika Gijutsu Kk Multi-functional underground continuous wall and method for constructing the same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS55161117A (en) * 1979-06-02 1980-12-15 Ohbayashigumi Ltd Constructing method for underground continuous wall by precast concrete member
JPH10331153A (en) * 1997-05-29 1998-12-15 Tone Chika Gijutsu Kk Multi-functional underground continuous wall and method for constructing the same

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103614998A (en) * 2013-11-26 2014-03-05 中冶天工集团有限公司 Lining wall concrete placement top-down method based on underground diaphragm wall
KR101779739B1 (en) * 2017-01-10 2017-09-19 아이앤티엔지니어링(주) Connection Structure Of Elevator Pit Under Structure And Steel Form
WO2018177305A1 (en) * 2017-03-29 2018-10-04 王燏斌 Groove pile for fabricated underground building and construction method thereof
WO2018177308A1 (en) * 2017-03-29 2018-10-04 王燏斌 Fabricated underground building interface structure and construction method thereof
KR102197091B1 (en) 2018-03-21 2020-12-30 유기선 Underground structure wall and underground structure and method construturing the same
KR20190110713A (en) * 2018-03-21 2019-10-01 유기선 Underground structure wall and underground structure and method construturing the same
CN108755968A (en) * 2018-07-17 2018-11-06 有利华建筑预制件(深圳)有限公司 Assembling synthesis building and its construction method
KR101971554B1 (en) * 2018-09-18 2019-09-03 주식회사 티아이에스 Method constructuring an underground structure using a temporary structure
CN109235639A (en) * 2018-11-15 2019-01-18 福建工程学院 Prestressing without bondn assembling type node and construction method with energy-consuming device
CN110453675A (en) * 2019-08-27 2019-11-15 中煤第三建设(集团)有限责任公司 One kind is folded to pour formula diaphram wall and its construction method
KR20210035663A (en) * 2019-09-24 2021-04-01 주식회사 제영이엔씨 the underground undercurrent space structure by the caisson assembly and this construction method
KR102345516B1 (en) * 2019-09-24 2022-01-03 주식회사 제영이엔씨 the underground undercurrent space structure by the caisson assembly and this construction method
CN113981948A (en) * 2021-12-06 2022-01-28 上海建工一建集团有限公司 Reverse construction method adopting prefabricated underground continuous wall

Similar Documents

Publication Publication Date Title
KR101331261B1 (en) Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same
KR100938918B1 (en) Top-down construction method using steel frame by channel
US7500807B2 (en) Method of construction using sheet piling sections
KR102153902B1 (en) Slurry wall, construction method for the same and wire mesh assembly
KR102208793B1 (en) Under ground structure using column wall and construction method thereof
KR101173045B1 (en) Earth retaining-cum-retaining wall, and construction method thereof
KR101161332B1 (en) Construction method of the underground tunnel
KR102276610B1 (en) Precast Structure for Straigt Retaining Wall using Temporary Sheating Wall after Constructing Temporary Sheating Wall and Construction Method using Thereof
KR20160131410A (en) Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method
KR102431393B1 (en) Construction Method of Underground Structures
KR20100009802A (en) All precast concrete prefabricated water storage tank using precast concrete panel for retaining wall
KR20210090101A (en) Integrated slurry wall construction structure and method using pouring blocking device and extension rebar, and construction device thereof
KR101288601B1 (en) Underpass using precast concrete pile and bottom slab and method for constructing the same
KR20190069910A (en) Installation structure and method of precast concrete culvert
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
US10829924B2 (en) Composite wall and methods of constructing a composite wall
KR20080025219A (en) Underground outer wall construction method using deck-plate and deck-plate for constructing underground outer wall
KR20210055980A (en) Underground roadway by top-down method using steel continuous wall in the earth without traffic control and temporary road and method for constructing the same
KR20060106159A (en) The engineering-works structure using composite pile and steel sheet pile, and it's construction method
KR102617795B1 (en) Retaining wall system combine H-piles with steel reinforcement structure
JP2000212979A (en) Underground structure having arch roof and construction method therefor
JP2012251292A (en) Pile foundation structure of outdoor facility and construction method for the same
KR101219451B1 (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same
KR200428941Y1 (en) Strut system of temporary retaining wall

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20161110

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20171109

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20181113

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20191113

Year of fee payment: 7