KR20190069910A - Installation structure and method of precast concrete culvert - Google Patents

Installation structure and method of precast concrete culvert Download PDF

Info

Publication number
KR20190069910A
KR20190069910A KR1020170170270A KR20170170270A KR20190069910A KR 20190069910 A KR20190069910 A KR 20190069910A KR 1020170170270 A KR1020170170270 A KR 1020170170270A KR 20170170270 A KR20170170270 A KR 20170170270A KR 20190069910 A KR20190069910 A KR 20190069910A
Authority
KR
South Korea
Prior art keywords
culvert
insertion groove
pile
along
concrete
Prior art date
Application number
KR1020170170270A
Other languages
Korean (ko)
Inventor
박광노
Original Assignee
박광노
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박광노 filed Critical 박광노
Priority to KR1020170170270A priority Critical patent/KR20190069910A/en
Publication of KR20190069910A publication Critical patent/KR20190069910A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2450/00Gaskets
    • E02D2450/10Membranes
    • E02D2450/105Membranes impermeable
    • E02D2450/106Membranes impermeable for liquids
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Sewage (AREA)

Abstract

The present invention relates to an installation structure for a precast concrete (PC) culvert and a method thereof, which are able to bond the PC culvert with a pile and to move at the same time. According to the present invention, the installation structure for the PC culvert comprises: a pile whose part protrudes towards an upper side of the ground; a leveling concrete placed along the ground where the pile is installed; the PC culvert formed in a square box, whose inside is formed as a space and whose a lower surface is formed as an opening unit, to have the head unit of the pile accommodated in the opening unit of the lower surface and settled on the leveling concrete; and a PC culvert floor surface formed on the opening unit of the lower surface of the PC culvert to be integrated with the head unit of the pile and both side surfaces of the PC culvert and to form a base slab of the PC culvert.

Description

프리캐스트 콘크리트 암거 설치구조 및 방법{INSTALLATION STRUCTURE AND METHOD OF PRECAST CONCRETE CULVERT}TECHNICAL FIELD [0001] The present invention relates to a precast concrete culvert construction method and a precast concrete culvert construction method,

본 발명은 프리캐스트 콘크리트 암거에 관한 것으로서, 보다 상세하게는 프리캐스트 콘크리트 암거와 파일이 일체로 접합되어 동시에 거동할 수 있도록 이루어진 프리캐스트 콘크리트 암거 설치구조 및 방법에 관한 것이다.The present invention relates to a precast concrete culvert, and more particularly, to a structure and a method for installing precast concrete culverts, in which precast concrete culverts and piles are integrally joined and can move at the same time.

일반적으로 도시의 도로 하부 등에는 전력구, 통신구, 수로 등과 같은 암거(Culvert) 구조물이 많이 설치되어 있다.Generally, there are many culvert structures such as electric power, communication and waterway in the lower part of the city.

이와 같은 암거는 지중을 굴착한 후 거푸집을 설치하고 콘크리트를 타설하는 방식으로 시공을 하거나, 또는 공장에서 프리캐스팅 공법으로 프리캐스트 콘크리트 암거(Precast Concrete Culvert: PC암거)를 단위부재로 제작하고 이를 운송수단으로 시공현장으로 운반하여 시공하고 있다.Such a culvert can be constructed by excavating the underground, installing the formwork and casting the concrete, or constructing the precast concrete culvert (PC culvert) as a unit member by pre-casting method at the factory. It is being transported to construction site by means.

PC암거는 시공성, 경제성, 품질 확보 면에서 유리하므로 대부분의 경우 PC암거를 이용한 사공방법으로 암거를 설치하고 있다.PC culvert is advantageous in terms of construction, economical efficiency and quality assurance, and in most cases, culvert is installed using PC culvert.

PC암거는 공장에서 일정한 크기의 블록형태로 제작하고 이를 시공현장으로 운반하여 연결하는 방식으로 설치한다. 이때 시공현장에서는 PC암거가 설치될 장소의 지반을 굴착하는 작업을 병행하게 된다.The PC culvert is manufactured in the form of a block of a certain size at the factory and transported to the construction site and connected. At this time, the construction site is used to excavate the ground in the place where the PC culvert is installed.

그리고 PC암거 설치를 위하여 지반을 굴착하면서 PC암거가 시공된 후 지반침하 등이 발생하여도 암거 구조물이 변위를 일으키지 않도록 지중에 파일을 설치할 수 있다.In addition, the pile can be installed in the ground so that the culvert structure does not cause displacement even if the PC pile is installed after excavating the pile for the installation of the PC culvert.

파일의 상부에는 철근이 노출되며, 이 노출철근에 구조용 철근을 배근한 후 레벨용 콘크리트 및 그 상부에 기초콘크리트를 타설하여 양생시킨 다음, 기초콘크리트 상부면을 따라서 PC암거를 연결하면서 거치하는 방식으로 PC암거를 설치하게 된다.The reinforcing bars are exposed at the upper part of the pile, the reinforced concrete structure is applied to the reinforced concrete, the concrete for level and the concrete are placed on the concrete for curing, and then the pile cement is fixed along the upper surface of the concrete. PC culvert will be installed.

그러나 이와 같이 설치된 PC암거는 기초콘크리트 상부면에 안착된 상태이므로 지진이나 차량 통행 등으로 인한 진동 및 외력에 의하여 측면방향으로 쉽게 유동하여 설치된 상태를 유지하지 못하고 변형될 수 있다. 그러면 PC암거들 사이의 연결부에 틈이 생겨 수밀성이 저하된다.However, since the PC culvert thus installed is placed on the upper surface of the foundation concrete, it can easily deform in the lateral direction due to vibration and external force due to earthquake or vehicle passing, and can be deformed without maintaining the installed state. This creates a gap in the connection between the PC culverts, resulting in poor watertightness.

즉, 파일로 인하여 PC암거는 수직 방향으로 침하되지는 않지만 측면방향으로는 충분히 유동될 가능성이 있다.In other words, due to the file, the PC cage is not submerged in the vertical direction but is likely to flow sufficiently in the lateral direction.

또한 파일의 상부에 레벨용 콘크리트 및 기초콘크리트를 타설하여 양생한 다음 PC암거를 설치하는 방식이므로 시공성이 좋지 않아 경제적이지 못하고, PC암거가 파일과 접합되지 않아 일체로 거동하지 못하므로 구조적으로 취약하다.In addition, since the level concrete and foundation concrete are laid on the upper part of the pile to cure and then the PC culvert is installed, the construction is not economical due to the poor workability, and the PC culvert is not bonded to the pile and is not structurally weak .

한국 실용신안등록 제20-0452669호Korean Utility Model Registration No. 20-0452669

본 발명은 상기한 바와 같은 종래의 문제점을 해결하기 위하여 제안된 것으로서, 본 발명의 목적은 PC암거와 파일이 일체로 접합되어 동시에 거동할 수 있도록 이루어진 PC암거 설치구조 및 방법을 제공하는데 있다.SUMMARY OF THE INVENTION It is an object of the present invention to provide a PC culvert installation structure and method in which a PC culvert and a file can be integrally joined and simultaneously moved.

본 발명이 제안하는 PC암거 설치구조는 지반의 상부 쪽으로 일부분이 돌출된 상태로 설치되는 파일; 상기 파일이 설치된 지반을 따라서 타설되는 버림 콘크리트; 내부가 공간으로 형성되고 하부면이 개방부로 이루어진 사각박스 형상으로 구성되면서 상기 하부면 개방부에 상기 파일의 두부가 수용된 상태로 상기 버림 콘크리트에 안착되는 PC암거; 상기 PC암거의 하부면 개방부에 형성되어 파일의 두부 및 PC암거의 양측면과 일체로 접합되면서 PC암거의 기초슬래브를 형성하는 PC암거 바닥면; 을 포함하는 PC암거 설치구조를 제공한다.The PC culvert installation structure proposed by the present invention is a file installed in a state where a portion is projected toward the upper side of the ground; Abandoned concrete paved along the ground where the piles are installed; A PC culvert having a rectangular box shape in which an interior is formed as a space and a lower surface is an open part and is seated on the abandoned concrete in a state where a head of the pile is housed in the lower surface opening part; A PC culvert bottom formed on the bottom opening of the PC culvert and forming a foundation slab of the PC culvert while being integrally joined to both sides of the pile and the PC culvert; The present invention provides a PC culvert mounting structure including:

상기 PC암거 하부면 개방부에는 바닥철근이 배근되고, 바닥철근에는 PC암거의 하부면 코너부분을 보강하기 위하여 우각부 보강철근이 더 배근된다.A bottom reinforcing bar is laid on the PC culvert lower opening and a bottom reinforcing bar is reinforced on the bottom reinforcing bar to reinforce the lower corner portion of the PC culvert.

상기 PC암거는 또 다른 PC암거와 접합되는 끝단부 접합면을 따라서 삽입홈이 형성되고, 이 삽입홈에는 지수판이 매립된다.The PC culvert has an insertion groove formed along an end joint surface joined with another PC culvert, and a waterproof plate is embedded in the insertion groove.

상기 PC암거는 인접된 또 다른 PC암거와 접합으로 연결한 후 삽입홈에 모르타르를 충진할 수 있도록 삽입홈과 연통되는 주입구가 형성되고, 이 주입구는 PC암거의 내측면을 따라서 복수개가 형성될 수 있다.The PC culvert is formed with an injection port communicating with the insertion groove so as to fill mortar with the insertion groove after being connected to another adjacent PC culvert, and a plurality of injection ports can be formed along the inner surface of the PC culvert have.

상기 PC암거는 삽입홈에 모르타르가 완전히 채워졌는지 확인할 수 있도록 배출구가 형성되고, PC암거는 삽입홈의 양쪽을 따라서 백업재가 제공될 수 있다.The PC culvert can be provided with a discharge port so that the mortar is completely filled in the insertion groove, and the PC culvert can be provided with a backup material along both sides of the insertion groove.

상기 PC암거의 코너부근 길이방향을 따라서 정착장치로 고정되는 긴장재가 더 설치될 수 있다. 또한 상기 PC암거의 외측면 하부 길이방향을 따라서 지수판이 설치될 수 있다.A tensional material fixed to the fixing device along the longitudinal direction in the vicinity of the corner of the PC culvert can be further installed. Further, a waterproof plate may be installed along the longitudinal direction of the lower portion of the outer side of the PC culvert.

또한 본 발명은 a) PC암거가 설치될 부분을 따라서 두부가 지반 외측으로 돌출되도록 파일을 설치하면서 파일이 설치된 지반을 따라서 버림 콘크리트를 타설하는 단계; b) 하부면이 제거되어 개방부로 이루어지고 또 다른 PC암거와 접합되는 접합면을 따라서 지수판이 매입되는 삽입홈이 형성된 PC암거를 상기 PC암거에 형성된 개방부가 상기 파일의 두부를 수용한 상태로 상기 버림 콘크리트에 안착시키는 PC암거 설치단계; c) 상기 b)단계를 연속적으로 진행하여 PC암거를 또 다른 PC암거와 접합으로 연결하면서 PC암거에 프리스트레스를 도입하기 위한 긴장재 설치단계; d) 상기 c)단계에서 버림 콘크리트에 안착된 PC암거의 하부 개방부에 콘크리트를 타설하여 파일의 두부와 일체로 결합된 PC암거 바닥면을 형성하는 단계; e) 상기 b)단계에서 설치된 PC암거의 접합면에 형성된 삽입홈에 주입구를 통하여 모르타르를 충진하는 단계; 를 포함하는 PC암거 설치방법을 제공한다.In addition, the present invention provides a method for constructing a culvert comprising the steps of: a) pouring abandoned concrete along a ground on which a pile is installed, while installing a file such that the toe protrudes outwardly from the ground along a portion where the culvert is to be installed; b) a PC culvert having an insertion groove in which a lower surface is removed to form an opening and which is joined to another PC culvert along a joint surface, the opening being formed in the culvert, PC culvert installation step to place on abandoned concrete; c) installing a prestressing material for introducing the prestress into the PC culvert while continuously connecting the PC culvert with another PC culvert in step b); d) placing concrete in the lower opening of the PC cowling which is seated on the abandoned concrete in step c), thereby forming a PC culvert floor integrally joined with the head of the pile; e) filling mortar through an injection port into an insertion groove formed in a joint surface of the PC culler installed in step b); The method comprising the steps of:

상기 b)단계를 행할 때 삽입홈의 양쪽을 따라서 삽입홈이 밀폐될 수 있도록 백업재 설치단계가 더 진행될 수 있다.The step of installing the backup material may be further performed so that the insertion groove may be sealed along both sides of the insertion groove when the step b) is performed.

상기 e)단계가 완료된 후 PC암거의 외측면 하부 길이방향을 따라서 수분이 침투하는 것을 방지하기 위한 지수판 설치단계가 더 행하여진다.After the step e) is completed, a waterproofing step for preventing water from penetrating along the lower longitudinal direction of the outer side of the PC culvert is further performed.

본 발명에 의한 PC암거 설치구조 및 방법은 PC암거의 바닥면을 구성하는 하부면이 파일과 일체로 결합되어 PC암거는 파일과 함께 일체로 거동할 수 있으므로 지반 침하 및 진동 등이 발생하여도 PC암거의 변위를 방지할 수 있다.In the PC culvert installation structure and method according to the present invention, since the bottom surface constituting the bottom surface of the PC culvert is integrally coupled with the pile and the PC culvert can be integrally moved together with the pile, even if ground settlement and vibration occur, The displacement of the culvert can be prevented.

또한 PC암거의 접합면에 주변에는 지수판이 삽입되는 삽입홈과 연통되는 주입구가 형성되어 PC암거를 접합으로 연결한 후, 주입구를 통하여 외부에서 삽입홈에 모르타르를 쉽게 채울 수 있다. 그러한 이유로 지수판이 설치된 상태를 고정하면서 접합부위로 수분이 침투하는 것을 저지시킬 수 있고, 아울러 접합부위의 결합력을 높일 수 있다.In addition, mortar can be easily filled into the insertion groove from the outside through the injection port after connecting the PC culvert to the joint by forming the injection hole communicating with the insertion groove into which the waterproof plate is inserted, on the joint surface of the PC culvert. For this reason, it is possible to prevent water from penetrating the joint portion while fixing the state where the waterproof plate is installed, and also to increase the bonding force of the joint portion.

도 1a 내지 도 1e는 본 발명의 PC암거 설치방법에 따라서 PC암거의 설치작업이 순차적으로 진행되는 과정을 설명하기 위한 도면이다.
도 2는 본 발명의 PC암거 설치방법에 따라서 블록단위로 제작된 PC암거들을 시공현장으로 운반하여 접합으로 연결하면서 설치하는 것을 나타내는 사시도이다.
도 3은 본 발명의 PC암거 설치방법에 따라서 PC암거들을 설치할 때 긴장재가 설치된 것을 나타내는 부분 확대도이다.
도 4는 본 발명에 제공되는 PC암거의 하부에 배치되는 철근배근을 설명하기 위한 부분 확대도이다.
도 5a 도 5b는 본 발명의 PC암거 설치방법에 따라서 PC암거들을 접합으로 연결한 후 접합부위에 형성된 지수판 삽입홈에 모르타르를 충진하는 것을 설명하기 위한 도면이다.
FIGS. 1A to 1E are views for explaining a process of sequentially installing a PC culvert according to the PC culvert installation method of the present invention.
Fig. 2 is a perspective view showing that the PC culverts, which are manufactured in block units according to the PC culvert installation method of the present invention, are transported to a construction site and are connected while being connected to each other.
Fig. 3 is an enlarged view showing that a tensional material is installed when the PC culver is installed according to the PC culvert installation method of the present invention.
Fig. 4 is a partially enlarged view for explaining a reinforcing steel arrangement disposed at a lower portion of the PC culver provided in the present invention. Fig.
FIGS. 5A and 5B are views for explaining filling mortar into a steel plate insertion groove formed on a joint after joining PC culverts according to the PC culvert installation method of the present invention.

이하, 본 발명의 바람직한 실시 예를 첨부한 도면을 참조하여 더욱 상세히 설명한다.Hereinafter, preferred embodiments of the present invention will be described in more detail with reference to the accompanying drawings.

도 1a 내지 도 1e는 본 발명의 PC암거 설치방법에 따라서 PC암거의 설치작업이 순차적으로 진행되는 과정을 설명하기 위한 도면이고, 도 2는 본 발명의 PC암거 설치방법에 따라서 블록단위로 제작된 PC암거들을 접합으로 연결하면서 설치하는 것을 나타내는 사시도이고, 도 3은 본 발명의 PC암거 설치방법에 따라서 PC암거들을 설치할 때 긴장재가 설치된 것을 나타내는 부분 확대도이고, 도 4는 본 발명에 제공되는 PC암거의 하부에 배치되는 철근배근을 설명하기 위한 도면으로서, 본 발명의 PC암거를 설치현장에 시공하기 위하여, 먼저 도 1a에서와 같이 PC암거(2)가 설치될 바닥면을 따라서 지중에 파일(4)을 설치하면서 파일(4)의 상부면 및 지반에 버림 콘크리트(6)를 타설한다.FIGS. 1A to 1E are views for explaining a process in which the installation work of the PC culvert is progressed according to the PC culvert installation method of the present invention, and FIG. 2 is a cross- FIG. 3 is a partially enlarged view showing that a tension member is installed when the PC culver is installed according to the PC culvert installation method of the present invention, and FIG. 4 is a perspective view of a PC In order to construct the PC culvert of the present invention at the site of installation, first, as shown in FIG. 1A, a pile (2) is installed along the floor where the PC culvert (2) 4, the abandoned concrete 6 is laid on the upper surface and the ground of the pile 4. [

파일(4)은 기초지반의 붕괴나 부등침하의 영향에 의해 PC암거(2)가 변위되는 것을 방지하는 역할을 수행하는 부재로서, 이러한 파일(4)은 일정 간격을 유지하며 타설 공법이나 압입공법 등과 같이 통상적인 방법을 이용하여 설치할 수 있으므로 상세한 설명은 생략한다.The pile 4 is a member which plays a role of preventing the PC culvert 2 from being displaced by the influence of the collapse of the foundation foundation or the uneven settlement. The pile 4 is kept at a constant interval, And the like, so that a detailed description thereof will be omitted.

파일(4)은 두부가 지표면과 동일 높이 또는 지표면보다 약간 높은 위치에 맞춰 설치하거나 또는 설치 후 돌출된 두부를 절단하여 정리하면 된다. 이때 파일(4)의 두부 외측으로 파일(4)에 매립된 철근의 일부분이 노출되도록 하면서 정리할 수도 있다.The pile 4 may be installed at the same height as the ground surface or at a position slightly higher than the ground surface, or may be arranged by cutting the protruding head portion after installation. At this time, a portion of the reinforcing bars embedded in the pile 4 may be exposed to the outside of the head of the pile 4 and arranged.

이러한 파일(4)은 내부가 공간부로 형성된 철근콘크리트 구조로 제작된 것이 사용될 수 있다.Such a pile 4 may be made of a reinforced concrete structure having a space formed therein.

이와 같이 지반에 파일(4)을 설치하면서 파일(4)의 상부면 및 지반에 버림 콘크리트(6)를 타설하여 양생한다.Thus, while installing the piles 4 on the ground, the abandoned concrete 6 is laid on the upper surface and the ground of the piles 4 to cure.

버림 콘크리트(6)는 PC암거(2)가 설치되는 바닥면의 높이를 설계높이로 맞추면서 PC암거(2)가 안정적으로 놓일 수 있도록 시공되는 부재이다. 버림 콘크리트(6)를 타설할 때 파일(4)의 두부는 매몰되지 않고 버림 콘크리트(6) 외부로 노출된 상태로 타설한다.The abandoned concrete 6 is a member to be installed so that the PC culter 2 can be stably placed while adjusting the height of the bottom surface on which the PC culter 2 is installed to the designed height. When the discarded concrete 6 is laid, the head of the pile 4 is poured without being buried and exposed to the outside of the discarded concrete 6.

이렇게 파일(4) 설치 및 버림 콘크리트(6)가 타설된 후, 소정의 시간이 경과하여 버림 콘크리트(6)가 양생되면 PC암거(2)의 설치를 위한 현장 준비 작업이 완료된다.After the file 4 is installed and the abandoned concrete 6 is laid, when the abandoned concrete 6 is cured after a predetermined time has elapsed, the site preparation work for installing the PC culter 2 is completed.

그 다음 도 1b와 같이 공장에서 제작된 PC암거(2)를 하부 개방부가 상기 파일(4)의 두부를 수용한 상태로 상기 버림 콘크리트(6)에 안착시키면서 또 다른 PC암거(2)를 접합으로 연결하면서 PC암거(2)를 길이방향으로 설치한다.Next, as shown in FIG. 1B, the PC culvert 2, which is manufactured in the factory, is placed on the abandoned concrete 6 with the lower opening portion receiving the head of the pile 4, Install the PC culvert (2) in the longitudinal direction while connecting.

상기 PC암거(2)는 양단부가 관통되고 내부가 공간으로 형성되면서 하부면이 개방부로 이루어진 사각박스 형상으로 구성된다.The PC culvert 2 is formed in a rectangular box shape having both ends thereof penetrated, an inner space formed as a space, and a lower surface as an opening.

PC암거(2)는 일정한 크기와 길이로 이루어진 블록단위로 제작되어 각각의 PC암거(2)를 서로 접합으로 연결하여 설치할 수 있도록 되어있다.The PC culter 2 is made up of block units each having a predetermined size and length, and each of the PC culver 2 can be connected and connected to each other.

PC암거(2)는 공장에서 제작할 때 하부면 개방부에는 PC암거(2)의 바닥부분을 구성하기 위하여 바닥부분의 주철근 역할을 하는 바닥철근(8)이 배근된다. 이 바닥철근(8)은 양단부가 PC암거(2)의 양측 벽면에 매입으로 고정한 상태로 설치된다.When the PC culter 2 is manufactured in a factory, a bottom reinforcing bar 8 serving as a main frame of the bottom part is disposed at the bottom opening of the PC culter 2 so as to constitute the bottom part of the PC culter 2. [ This bottom reinforcing bar 8 is installed in such a state that both end portions thereof are fixedly embedded in both side walls of the PC culvert 2.

그리고 바닥철근(8)의 양측단부에는 PC암거(2)의 하부면 코너부분을 보강하기 위하여 우각부 보강철근(10)이 더 배근될 수 있다.The right and left reinforcing bars 10 may be further provided at opposite ends of the bottom reinforcing bar 8 to reinforce the lower corner portions of the PC cage 2. [

이와 같이 본 발명에 제공된 PC암거(2)는 하부면이 개방부로 이루어지면서 이 개방부에는 바닥철근(8) 및 우각부 보강철근(10)을 배근한 상태로 공장에서 제작하고, 이를 운반하여 바닥철근(8)이 설치된 하부면을 시공현장의 지반에 설치된 파일(4)의 두부를 수용한 상태로 설치한다.As described above, the PC culter 2 provided in the present invention is manufactured in the factory with the bottom reinforcing bars 8 and the right reinforcing reinforcing bars 10 disposed in the open portion, The lower surface provided with the reinforcing bars (8) is installed in a state in which the head portion of the pile (4) installed on the ground in the construction site is accommodated.

이렇게 불록단위로 이루어진 PC암거(2)들을 끝단부를 서로 연결하면서 시공하게 되는데, PC암거(2)의 끝단 면에는 삽입홈(12)이 형성되고 이 삽입홈(12)에는 지수판(14)을 삽입하여 PC암거(2)의 접합면으로 수분이 침투하는 것을 방지할 수 있도록 구성된다.The PC culvert 2 is formed by connecting the end portions of the PC culver 2 to each other while being connected to each other. The PC culter 2 has an insertion groove 12 formed at an end surface thereof, So as to prevent moisture from penetrating into the joint surface of the PC culvert 2. [

또한 PC암거(2)를 설치하면서 도 1c와 같이 PC암거(2)의 코너부분을 관통하는 방향으로 긴장재(16) 설치단계를 실시하여 프리스트레스를 도입할 수도 있다. 긴장재(16)는 일측단을 PC암거(2)의 일측 끝단면에 형성된 오목부(18) 내부에 지지되는 정착장치(20)에 고정하고 PC암거(2)의 타측에서 인장기(22) 등을 이용하여 인장시킨 후, 또 다른 정착장치(20)에 고정시켜 구속하는 방법으로 설치할 수 있다.In addition, while installing the PC culvert 2, the prestress may be introduced by performing the step of installing the tension member 16 in a direction passing through the corner portion of the PC culvert 2 as shown in FIG. 1C. The tension member 16 has one end fixed to the fixing device 20 supported inside the concave portion 18 formed at one end surface of the PC culvert 2 and the tensioner 22 And then fixed to another fixing device 20 so as to be restrained.

긴장재(16)를 설치할 때 오목부(18) 일측면에는 지수재(24)를 제공하여 긴장재(16) 측으로 수분이 유입되는 것을 차단할 수 있다.An exponent 24 may be provided on one side surface of the recess 18 when the tension member 16 is installed to prevent moisture from flowing into the side of the stress member 16. [

긴장재(16)를 이용하여 프리스트레스를 도입한 후에는 바닥철근(8)과 직교하는 방향으로 배력철근(26)을 더욱 배근할 수도 있다.After introducing the prestress using the tensile member 16, the reinforcing bar 26 may be further routed in a direction orthogonal to the bottom reinforcing bar 8.

그리고 지수판(14)이 설치된 삽입홈(12)의 공간을 모르타르(Mortar)(28)로 채우기 위하여 PC암거(2)의 내측면에는 삽입홈(12)과 연결된 주입구(30)가 형성된다.An injection port 30 connected to the insertion groove 12 is formed on the inner surface of the PC cage 2 in order to fill the space of the insertion groove 12 in which the water resistance plate 14 is installed with a mortar 28.

모르타르(28)는 시멘트 모르타르 등이 사용될 수 있으며, 주입구(30)로 모르타르(28)을 주입하면 정착장치(20)가 설치된 오목부(18)에도 모르타르(28)이 충진되어 정착장치(20)가 모르타르(28) 속으로 매립되어 외기와의 접촉이 차단되므로 부식을 방지할 수 있고, 특히 긴장재(16) 간 연결에 따른 결속력과 PC암거(2)의 접합에 대한 전단 연결 강도를 더욱 강화하게 된다.When the mortar 28 is injected into the injection port 30, the mortar 28 is filled in the concave portion 18 provided with the fixing device 20 and the fixing device 20 is filled with the mortar 28. [ Since the contact with the outside air is blocked, corrosion can be prevented, and in particular, the binding force due to the connection between the tension members 16 and the shear connection strength with respect to the connection of the PC culvert 2 are further enhanced do.

주입구(30)는 공장에서 PC암거(2)를 제작할 때 그 선단부가 삽입홈(12)과 연결되는 파이프를 매입하는 방식으로 설치할 수 있으며, 이때 주입구(30)의 끝단부는 PC암거(2)의 측면 내측으로 일정길이가 노출되도록 설치할 수 있다.The injection port 30 can be installed in the factory in such a manner that the tip of the injection port 30 is connected to the insertion groove 12 when the PC culvert 2 is manufactured. A certain length may be exposed to the inside of the side surface.

이러한 주입구(30)는 PC암거(2)의 양쪽 측면에 각각 형성되어 복수개로 이루어질 수 있으며, 주입구(30)를 통하여 모르타르(28)을 주입할 경우, 삽입홈(12)에 모르타르(28)이 완전히 충진 되었는지 확인할 수 있도록, PC암거(2)의 상부면 내측으로는 배출구(32)가 형성된다. 즉, PC암거(2)의 측면에 각각 형성된 주입구(30)를 통하여 삽입홈(12)에 모르타르(28)을 주입하면, 주입구(30) 주변으로부터 모르타르(28)가 순차적으로 채워지고, 삽입홈(12) 전체에 모르타르(28)가 채워지면 배출구(32)로 여분의 모르타르(28)가 배출되어 이를 확인하는 것으로 삽입홈(12)에 모르타르(28)가 모두 채워졌는지 확인할 수 있다.When the mortar 28 is injected through the injection port 30, the mortar 28 is inserted into the insertion hole 12, and the mortar 28 is injected into the injection hole 12, A discharge port 32 is formed inside the upper surface of the PC culvert 2 so as to confirm whether it is completely filled. That is, when the mortar 28 is injected into the insertion groove 12 through the injection port 30 formed in the side surface of the PC culvert 2, the mortar 28 is sequentially filled from around the injection port 30, The excess mortar 28 is discharged to the discharge port 32 when the entire mortar 28 is filled in the discharge port 12 to confirm that the mortar 28 is completely filled in the insertion slot 12. [

이러한 주입구(30)로 인하여 PC암거(2)들을 연결하면서 설치한 다음, 미감작업을 행 때 주입구(30)를 통하여 삽입홈(12)의 공간에 모르타르(28)을 채워 지수판(14)이 설치된 상태를 고정하면서 수분이 침투를 완벽하게 저지시킬 수 있고, 이와 아울러 접합부위의 결합력을 높일 수 있다.The mortar 28 is filled in the space of the insertion groove 12 through the inlet 30 when the PC culver 2 is connected to the inlet port 30 to perform the aesthetic operation, The water can completely inhibit the penetration while fixing the state, and the bonding force of the bonding portion can be increased.

또한 주입구(30)를 통하여 삽입홈(12)으로 채워지는 모르타르(28)가 접합면 외측으로 유출되지 않도록 PC암거(2)들을 연결할 때 삽입홈(12)의 양쪽을 따라서 백업재(34)가 제공될 수 있다. 이 백업재(34)는 실리콘 등으로 이루어질 수 있다.A backup material 34 is formed along the both sides of the insertion groove 12 when the PC culver 2 is connected so that the mortar 28 filled in the insertion groove 12 through the injection port 30 does not flow out of the joint surface. Can be provided. The backup material 34 may be made of silicon or the like.

상기와 같이 PC암거(2)의 설치작업이 완료되면, 도 1d와 같이 버림 콘크리트(6)에 안착된 PC암거(2)의 하부 개방부에 현장콘크리트를 타설하여 PC암거(2)의 기초슬래브인 바닥면(36)을 형성하는 단계를 진행한다.When the installation work of the PC culvert 2 is completed as described above, the concrete concrete is placed in the lower opening of the PC culvert 2 which is seated on the fallen concrete 6 as shown in FIG. 1d, The process of forming the bottom surface 36 is continued.

이러한 공정이 완료되어 소정의 시간이 경과하여 타설된 현장콘크리트가 양생되면 바닥면(36)의 내부에는 바닥철근(8)과 배력철근(26) 및 우각부 보강철근(10)이 매립된 상태로 바닥면(36)의 양측면 끝단부는 PC암거(2)의 측면 하부에 접합으로 고정되면서 파일(4)의 두부와 일체로 결합된다.When the in-situ concrete is cured after a predetermined time has elapsed after completion of such a process, a bottom reinforcing bar 8, a reinforcing reinforcing bar 26 and a reinforcing reinforcing bar 10 are embedded in the bottom surface 36 Both side end portions of the bottom surface 36 are integrally joined to the head portion of the pile 4 while being fixed to the lower side of the side surface of the PC cage 2.

이에 따라 PC암거(2)는 파일(4)과 일체로 합성되어 PC암거(2)와 파일(4)은 일체로 거동할 수 있으므로, 예를 들어 지진이나 차량 통행 등으로 인한 지반 침하 및 진동 등이 발생하여도 시공이 완료된 PC암거(2)의 변위를 방지할 수 있다.As a result, the PC culter 2 can be integrally combined with the file 4 and the PC culter 2 and the pile 4 can be integrally moved. Therefore, for example, It is possible to prevent the displacement of the PC cage 2 whose construction has been completed.

이러한 공정이 완료되면 도 1e와 같이 PC암거(2)의 접합면에 형성된 삽입홈(12)에 주입구(30)를 통하여 모르타르(28)를 충진하는 공정을 행한다. 모르타르(28)는 무수축 모르타르를 사용하는 것이 바람직하다.When this process is completed, the mortar 28 is filled through the injection port 30 into the insertion groove 12 formed in the joint surface of the PC culvert 2 as shown in FIG. 1E. The mortar 28 is preferably a non-shrinkable mortar.

이렇게 삽입홈(12)의 공간에 모르타르(28)를 채우면 도 5a와 같이 지수판(14)이 설치된 상태를 고정하면서 삽입홈(12)의 비어있는 공간을 메워 외부에서 수분이 침투하는 것을 완벽하게 저지시킬 수 있고, 이와 아울러 접합부위의 결합력도 높이게 된다. 또 이때 정착장치(20)가 설치된 오목부(18)에도 모르타르(28)가 충진되어 정착장치(20)가 모르타르(28) 속으로 매립되어 외기와의 접촉을 차단시켜 정착장치(20)가 부식되는 것을 방지한다.When the mortar 28 is filled in the space of the insertion groove 12 as described above, the state in which the water resistance plate 14 is installed is fixed as shown in FIG. 5A, and the void space of the insertion groove 12 is filled, And the bonding strength of the joint portion is also increased. At this time, the recessed portion 18 provided with the fixing device 20 is also filled with the mortar 28 so that the fixing device 20 is embedded in the mortar 28 to block the contact with the outside air, .

주입구(30)를 통하여 모르타르(28)를 주입할 때, 도 5b에서와 같이 PC암거(2)의 상부면에 형성된 배출구(32)를 통하여 모르타르(28)의 배출 여부를 확인하면서 충진할 수 있는데, 배출구(32)로 모르타르(28)이 배출되면 삽입홈(12)에 모르타르(28)이 완충된 상태이므로 모르타르의 충진을 중지하면 된다,When the mortar 28 is injected through the injection port 30, it is possible to fill the mortar 28 by checking whether the mortar 28 is discharged through the discharge port 32 formed on the upper surface of the PC culvert 2 as shown in FIG. 5B The mortar 28 is completely filled in the insertion groove 12 when the mortar 28 is discharged to the discharge port 32. Therefore,

이와 같은 모르타르 충진 작업이 완료된 후, PC암거(2)의 접합면을 따라서 코킹작업이 진행될 수 있고, 또 이와 아울러 PC암거(2)의 외측면 하부 길이방향을 따라서 지수판(38)을 설치하는 작업이 더욱 진행될 수 있다.After the mortar filling operation is completed, the caulking operation can be performed along the joint surface of the PC culvert 2, and the operation of installing the watertight plate 38 along the longitudinal direction of the lower side of the outer side of the PC culvert 2 Can be further advanced.

이 지수판(38)으로 인하여 PC암거(2)의 하부에서 수분이 침투하는 것을 미연에 방지할 수 있다.It is possible to prevent moisture from penetrating from the lower portion of the PC culvert 2 due to the water level plate 38 in advance.

상기에서는 본 발명의 바람직한 실시예가 예시를 목적으로 설명되어 있으나 이에 제한되지는 않으며, 특허청구범위와 발명의 상세한 설명 및 첨부한 도면의 범위 내에서 여러 가지로 변형하여 실시하는 것도 가능하다.While the preferred embodiments of the present invention have been described for illustrative purposes, those skilled in the art will appreciate that various modifications, additions and substitutions are possible, without departing from the scope and spirit of the invention as disclosed in the accompanying claims.

2: PC암거 4: 파일
6: 버림 콘크리트 8: 바닥철근
10: 우각부 보강철근 12: 삽입홈
14: 지수판 16: 긴장재
18: 오목부 20: 정착장치
22: 인장기 24: 지수재
26: 배력철근 28: 모르타르
30: 주입구 32: 배출구
34: 백업재 36: 바닥면
38: 지수판
2: PC culvert 4: File
6: abandoned concrete 8: bottom steel
10: Rectangular rebar 12: Insert groove
14: Index plate 16: Tension material
18: recess 20: fixing device
22: Tensioner 24: Index material
26: Bracing reinforcement 28: Mortar
30: inlet 32: outlet
34: backup material 36: bottom surface
38:

Claims (13)

지반의 상부 쪽으로 일부분이 돌출된 상태로 설치되는 파일;
상기 파일이 설치된 지반을 따라서 타설되는 버림 콘크리트;
내부가 공간으로 형성되고 하부면이 개방부로 이루어진 사각박스 형상으로 구성되면서 상기 하부면 개방부에 상기 파일의 두부가 수용된 상태로 상기 버림 콘크리트에 안착되는 PC암거;
상기 PC암거의 하부면 개방부에 형성되어 파일의 두부 및 PC암거의 양측면과 일체로 접합되면서 PC암거의 기초슬래브를 형성하는 PC암거 바닥면;
을 포함하는 PC암거 설치구조.
A file which is installed with a part protruding toward the upper part of the ground;
Abandoned concrete paved along the ground where the piles are installed;
A PC culvert having a rectangular box shape in which an interior is formed as a space and a lower surface is an open part and is seated on the abandoned concrete in a state where a head of the pile is housed in the lower surface opening part;
A PC culvert bottom formed on the bottom opening of the PC culvert and forming a foundation slab of the PC culvert while being integrally joined to both sides of the pile and the PC culvert;
And a plurality of pcs.
청구항 1에 있어서,
상기 PC암거 하부면 개방부에는 바닥철근이 배근된 것을 특징으로 하는 PC암거 설치구조.
The method according to claim 1,
And a bottom reinforcing bar is laid on the PC culvert lower opening.
청구항 2에 있어서,
상기 바닥철근에는 PC암거의 하부면 코너부분을 보강하기 위하여 우각부 보강철근이 더 배근된 것을 특징으로 하는 PC암거 설치구조.
The method of claim 2,
Wherein the bottom reinforcing bars are further reinforced with right reinforcing bars to reinforce corner portions of the lower surface of the PC culvert.
청구항 1에 있어서,
상기 PC암거는 또 다른 PC암거와 접합되는 끝단부 접합면을 따라서 삽입홈이 형성되고, 이 삽입홈에는 지수판이 매립된 것을 특징으로 하는 PC암거 설치구조.
The method according to claim 1,
Wherein the PC culvert has an insertion groove formed along an end joint surface joined to another PC culvert, and a waterproof plate is embedded in the insertion groove.
청구항 4에 있어서,
상기 PC암거는 인접된 또 다른 PC암거와 접합으로 연결한 후 삽입홈에 모르타르를 충진할 수 있도록 삽입홈과 연통되는 주입구가 형성된 것을 특징으로 하는 PC암거 설치구조.
The method of claim 4,
Wherein the PC culvert is formed with an injection port communicating with the insertion groove so as to fill mortar with the insertion groove after being connected to another adjacent PC culvert.
청구항 6에 있어서,
상기 주입구는 PC암거의 내측면을 따라서 복수개가 형성된 것을 특징으로 하는 PC암거 설치구조.
The method of claim 6,
Wherein a plurality of the injection ports are formed along inner sides of the PC culvert.
청구항 5에 있어서,
상기 PC암거는 삽입홈에 모르타르가 완전히 채워졌는지 확인할 수 있도록 배출구가 형성된 것을 특징으로 하는 PC암거 설치구조.
The method of claim 5,
Wherein the PC culvert has a discharge port formed in the insertion groove to check whether the mortar is completely filled.
청구항 5에 있어서,
상기 PC암거는 삽입홈의 양쪽을 따라서 백업재가 제공된 것을 특징으로 하는 PC암거 설치구조.
The method of claim 5,
Wherein the PC culvert is provided with a backup material along both sides of the insertion groove.
청구항 1에 있어서,
상기 PC암거의 코너부근 길이방향을 따라서 정착장치로 고정되는 긴장재가 설치된 것을 특징으로 하는 PC암거 설치구조.
The method according to claim 1,
Wherein a tensional material fixed by a fixing device is installed along the longitudinal direction of the PC culvert near a corner.
청구항 1에 있어서,
상기 PC암거의 외측면 하부 길이방향을 따라서 지수판이 설치된 것을 특징으로 하는 PC암거 설치구조.
The method according to claim 1,
And a waterproof plate is installed along the longitudinal direction of the lower portion of the outer side of the PC culvert.
a) PC암거가 설치될 부분을 따라서 두부가 지반 외측으로 돌출되도록 파일을 설치하면서 파일이 설치된 지반을 따라서 버림 콘크리트를 타설하는 단계;
b) 하부면이 제거되어 개방부로 이루어지고 또 다른 PC암거와 접합되는 접합면을 따라서 지수판이 매입되는 삽입홈이 형성된 PC암거를 상기 PC암거에 형성된 개방부가 상기 파일의 두부를 수용한 상태로 상기 버림 콘크리트에 안착시키는 PC암거 설치단계;
c) 상기 b)단계를 연속적으로 진행하여 PC암거를 또 다른 PC암거와 접합으로 연결하면서 PC암거에 프리스트레스를 도입하기 위한 긴장재 설치단계;
d) 상기 c)단계에서 버림 콘크리트에 안착된 PC암거의 하부 개방부에 콘크리트를 타설하여 파일의 두부와 일체로 결합된 PC암거 바닥면을 형성하는 단계;
e) 상기 b)단계에서 설치된 PC암거의 접합면에 형성된 삽입홈에 주입구를 통하여 모르타르를 충진하는 단계;
를 포함하는 PC암거 설치방법.
a) pouring the abandoned concrete along the ground where the pile is installed, while installing the pile so that the tofu protrudes to the outside of the ground along the part where the PC culvert is to be installed;
b) a PC culvert having an insertion groove in which a lower surface is removed to form an opening and which is joined to another PC culvert along a joint surface, the opening being formed in the culvert, PC culvert installation step to place on abandoned concrete;
c) installing a prestressing material for introducing the prestress into the PC culvert while continuously connecting the PC culvert with another PC culvert in step b);
d) placing concrete in the lower opening of the PC cowling which is seated on the abandoned concrete in step c), thereby forming a PC culvert floor integrally joined with the head of the pile;
e) filling mortar through an injection port into an insertion groove formed in a joint surface of the PC culler installed in step b);
Wherein the PC is installed in a closed position.
청구항 11에 있어서,
상기 b)단계를 행할 때 삽입홈의 양쪽을 따라서 삽입홈이 밀폐될 수 있도록 백업재 설치단계가 더 진행되는 것을 특징으로 하는 PC암거 설치방법.
The method of claim 11,
Wherein the step of installing a backup material is further performed so that the insertion groove is sealed along both sides of the insertion groove when the step b) is performed.
청구항 11에 있어서,
상기 e)단계가 완료된 후 PC암거의 외측면 하부 길이방향을 따라서 수분이 침투하는 것을 방지하기 위한 지수판 설치단계가 더 행하여지는 것을 특징으로 하는 PC암거 설치방법.
The method of claim 11,
Further comprising a step of installing a waterproofing plate for preventing water from penetrating along the longitudinal direction of the bottom of the outer side of the PC culvert after the step (e) is completed.
KR1020170170270A 2017-12-12 2017-12-12 Installation structure and method of precast concrete culvert KR20190069910A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170170270A KR20190069910A (en) 2017-12-12 2017-12-12 Installation structure and method of precast concrete culvert

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170170270A KR20190069910A (en) 2017-12-12 2017-12-12 Installation structure and method of precast concrete culvert

Publications (1)

Publication Number Publication Date
KR20190069910A true KR20190069910A (en) 2019-06-20

Family

ID=67103796

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170170270A KR20190069910A (en) 2017-12-12 2017-12-12 Installation structure and method of precast concrete culvert

Country Status (1)

Country Link
KR (1) KR20190069910A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984226A (en) * 2019-11-19 2020-04-10 山东建固特种专业工程有限公司 Waterproof construction method for frame column in reverse construction method
CN112695807A (en) * 2020-12-11 2021-04-23 中国二十冶集团有限公司 Post-planting installation method for rubber water stop
KR102410140B1 (en) * 2022-05-04 2022-06-22 주식회사 부성건설 Culvert structure base plate repair and reinforcement method
KR102421097B1 (en) * 2022-02-10 2022-07-15 (주)추진건설 Precast concrete culvet structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200452669Y1 (en) 2008-11-06 2011-03-16 주식회사 케이씨산업개발 Assembling Structure of Precast Concrete Culvert

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200452669Y1 (en) 2008-11-06 2011-03-16 주식회사 케이씨산업개발 Assembling Structure of Precast Concrete Culvert

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984226A (en) * 2019-11-19 2020-04-10 山东建固特种专业工程有限公司 Waterproof construction method for frame column in reverse construction method
CN110984226B (en) * 2019-11-19 2021-08-03 山东建固特种专业工程有限公司 Waterproof construction method for frame column in reverse construction method
CN112695807A (en) * 2020-12-11 2021-04-23 中国二十冶集团有限公司 Post-planting installation method for rubber water stop
CN112695807B (en) * 2020-12-11 2022-07-01 中国二十冶集团有限公司 Post-planting installation method for rubber water stop
KR102421097B1 (en) * 2022-02-10 2022-07-15 (주)추진건설 Precast concrete culvet structure
KR102410140B1 (en) * 2022-05-04 2022-06-22 주식회사 부성건설 Culvert structure base plate repair and reinforcement method

Similar Documents

Publication Publication Date Title
KR101331261B1 (en) Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same
KR101131679B1 (en) Splicing Method of Embedded type Baseplate with Steel Column
KR100640716B1 (en) Precast concrete block for cantilever retaining wall and construction method using the same
KR20190069910A (en) Installation structure and method of precast concrete culvert
KR20140047118A (en) Foundation system for bridges
KR100788623B1 (en) Top-down method using precast-concrete colum
KR101713284B1 (en) Seismic retrofit PC wall panel for RC frame, Seismic retrofit structure of RC frame using PC wall panel and construction method thereof
KR101281070B1 (en) Wall structure for the water-storage tank and its constructing method
KR20100009802A (en) All precast concrete prefabricated water storage tank using precast concrete panel for retaining wall
KR20190022132A (en) Top-down method using precast-concrete colum
KR101183691B1 (en) Water-storage tank of assembly type and method for constructing the same
KR101561212B1 (en) Concrete precast wall and the construction method using the same
US20030033773A1 (en) Foundation construction
KR101211469B1 (en) Retaining wall structure having prefabricated block and method for constructing retaining wall using the same
KR20150043913A (en) Biased soil pressure reinforcement rigid-frame bridge and construction method of the same
AU2013366093B2 (en) Reinforced blockwork construction method
US10829924B2 (en) Composite wall and methods of constructing a composite wall
KR20210059485A (en) Installation structure of precast concrete vertical shaft
KR100880022B1 (en) Prefabricated precast concrete pumping plant manhole
KR102169270B1 (en) Fitting for forming concrete bracket, Concrete bracket for supporting slab of vertical shaft using the same, and construction method thereof
KR200420394Y1 (en) Precast concrete block for cantilever retaining wall
KR102120849B1 (en) Installation structure and method of precast concrete culvert
KR20090042395A (en) Retainning wall and its construction method
JP2964127B2 (en) How to build a basement
KR101389123B1 (en) Pile type protecting wall

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E601 Decision to refuse application