KR20090042395A - Retaining Wall and Construction Method - Google Patents

Retaining Wall and Construction Method Download PDF

Info

Publication number
KR20090042395A
KR20090042395A KR1020070108120A KR20070108120A KR20090042395A KR 20090042395 A KR20090042395 A KR 20090042395A KR 1020070108120 A KR1020070108120 A KR 1020070108120A KR 20070108120 A KR20070108120 A KR 20070108120A KR 20090042395 A KR20090042395 A KR 20090042395A
Authority
KR
South Korea
Prior art keywords
wall
pile
bottom plate
protrusion
tension member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
KR1020070108120A
Other languages
Korean (ko)
Inventor
김동립
Original Assignee
김동립
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김동립 filed Critical 김동립
Priority to KR1020070108120A priority Critical patent/KR20090042395A/en
Publication of KR20090042395A publication Critical patent/KR20090042395A/en
Ceased legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0266Retaining or protecting walls characterised by constructional features made up of preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Retaining Walls (AREA)

Abstract

A retaining wall and a construction method thereof are provided to reduce the size of a bottom door installed at the retaining wall construction by connecting a tensile member. A retaining wall construction method comprises: a step of poring the lean concrete(1) into an upper part with specific depth; a step of placing a bottom plate(2) manufactured in advance with the precast concrete on the upper part of the concrete; a step of forming a protrusion(31) in which the upper side part of a pile(3) is protruded on the bottom plate; a step of setting a wall(4) manufactured on the opposite side of the pile on the bottom plate; a step of connecting one or more tensile member(5) between a connection part(41) of the wall and the protrusion of the pile; and a step for poling the cap concrete(6) on the protrusion of the pile; and a step of hardening and refilling the wall front side and real side with the rubble.

Description

옹벽과 이의 시공방법{Retainning wall and its construction method} Retaining wall and its construction method

본 발명은 전체적으로 옹벽에 관한 것으로, 특히 옹벽 구축을 위해 설치되는 지지용 저판(底板)의 크기를 줄이면서 전도 및 활동에 대한 저항을 높임과 동시에 옹벽의 두께도 경제적으로 줄일 수 있는 옹벽과 이의 시공방법에 관한 것이다.The present invention relates to a retaining wall as a whole. In particular, the retaining wall and its construction can reduce the size of the retaining plate installed for the building of the retaining wall while increasing the resistance to conduction and activity and at the same time economically reducing the thickness of the retaining wall. It is about a method.

옹벽의 구축을 위해 사용되는 지지용 저판은, 절토 또는 성토 등의 비탈면 토사의 붕괴를 막기 위해 시공되는 옹벽을 고정하기 위한 것이다.The support base plate used for the construction of the retaining wall is for fixing the retaining wall constructed to prevent the collapse of sloped soil such as cut or fill.

여기서, 옹벽은 벽돌 또는 콘크리트 등으로 구축되는데, 규모 및 시공의 편리성을 고려하여 근래에는 콘크리트를 이용한 구조물이 널리 시공되고 있다. 이러한 콘크리트 구조물은, 설치대상이 되는 경사지 또는 암반 등의 형태에 따라 지지기반의 확보를 위해 설치대상으로부터 비교적 멀리 떨어져 설치되어야 하고, 옹벽의 전체 높이가 높게 되는 경우에는 이에 대응하여 옹벽을 지지하기 위한 저판이 크게 형성됨과 더불어, 옹벽의 두께도 두껍게 되어야 한다. Here, the retaining wall is constructed of brick or concrete, etc., in consideration of scale and convenience of construction, recently, structures using concrete have been widely constructed. Such concrete structures should be installed relatively far from the installation object to secure the support base according to the shape of the slope or rock to be installed, and in case the overall height of the retaining wall becomes high, In addition to the large base plate, the retaining wall must be thick.

이에 따라 작업공간이 많이 필요하게 되고, 콘크리트 구조물의 설치 후 되메우기 작업이 많아지게 되어 공사기간이 연장되며, 이에 수반하여 공사비용이 상승되는 문제점이 있었다.Accordingly, the work space is required a lot, the backfill work is increased after the installation of the concrete structure, the construction period is extended, and there was a problem that the construction cost increases.

한편, 옹벽의 설치대상 주변에 공교롭게도 어떠한 장애물이 위치하는 경우에는, 지지기반을 확보하지 못해서 옹벽을 설치하기가 곤란하게 되고, 이에 따라 보다 복잡하고 시간 및 비용이 많이 소요되는 방식의 구조물을 사용하고 있는 실정에 있다. On the other hand, if any obstacle is located around the installation target of the retaining wall, it is difficult to install the retaining wall due to the failure of securing a support base, and thus, a structure of a more complicated and time-consuming method is used. There is a situation.

이에 본 발명은 상기와 같은 종래기술의 문제점을 감안하여 안출한 것으로, 옹벽 구축을 위해 지반에 놓이는 지지용 저판과 결합되는 말뚝을 설치하고서 이 말뚝 및 콘크리트 구조물로 된 벽체 사이에 인장력을 가할 수 있는 인장부재를 연결함으로써, 옹벽 구축을 위해 설치되는 상기 저판의 크기를 줄이면서 전도 및 활동에 대한 저항을 높임과 동시에 옹벽의 두께도 경제적으로 줄일 수 있도록 된 옹벽을 제공하는 데에 그 목적이 있다. The present invention has been made in view of the problems of the prior art as described above, by installing a pile coupled to the support base plate placed on the ground for building the retaining wall can be applied a tensile force between the pile and the wall of the concrete structure It is an object of the present invention to provide a retaining wall that can reduce the size of the bottom plate installed for building the retaining wall while increasing the resistance to conduction and activity while economically reducing the thickness of the retaining wall.

또한 본 발명의 다른 목적은, 상기한 옹벽을 비교적 짧은 공사기간 내에 비용도 경제적으로 시공할 수 있는 시공방법을 제공하는 것으로, 프리캐스트 콘크리트를 이용한 조립식 시공방법과, 설치대상에다 직접 시공하는 현장타설식 시공방법을 제안하고자 한다.In addition, another object of the present invention is to provide a construction method in which the retaining wall can be cost-effectively constructed within a relatively short construction period, and includes a prefabricated construction method using precast concrete, and on-site construction directly on the installation target. The formula construction method is proposed.

상기한 목적을 달성하기 위해, 본 발명에 따른 옹벽은, 지반 상에 설치되는 저판과; 이 저판의 일측 밑 지반 속에 설치되되, 그 일부가 저판 위로 돌출된 돌출부를 형성한 채로 저판과 결합되는 말뚝과; 상기 저판 상에서 말뚝의 맞은편에 세워지는 벽체 및; 이 벽체와 상기 말뚝의 돌출부 사이에 인장력을 가하도록 연결되는 적어도 하나의 인장부재;를 구비하는 것을 특징으로 한다. In order to achieve the above object, the retaining wall according to the present invention comprises: a bottom plate installed on the ground; A pile which is installed in one side of the bottom plate of the bottom plate, the part being coupled to the bottom plate while forming a protrusion protruding from the bottom plate; A wall erected opposite the pile on the bottom plate; And at least one tension member connected between the wall and the protrusion of the pile to apply a tension force.

또, 본 발명의 한 실시예에 따른 옹벽의 시공방법은, 지반에 터파기 및 버림 콘크리트를 타설하는 단계와; 그 위에 저판을 놓는 단계와; 이 저판에 미리 형성된 구멍을 통해 지반 속으로 말뚝을 설치하되, 말뚝의 일부가 저판 위로 돌출된 돌출부를 형성하도록 설치하는 단계와; 상기 저판 상에서 말뚝의 맞은편에 벽체를 세우 는 단계와; 이 벽체와 상기 말뚝의 돌출부 사이에 적어도 하나의 인장부재를 연결하는 단계와; 상기 말뚝의 돌출부 상에 캡 콘크리트를 타설하는 단계와; 옹벽의 길이만큼 위의 단계들을 되풀이하는 단계 및; 벽체의 이면(裏面) 쪽 저판 위로 되메우기하는 단계;를 포함하는 것을 특징으로 한다. In addition, the construction method of the retaining wall according to an embodiment of the present invention, the step of pouring excavation and discarded concrete on the ground; Placing a bottom plate thereon; Installing a pile into the ground through a hole previously formed in the bottom plate, wherein a portion of the pile is formed to form a protrusion protruding onto the bottom plate; Erecting walls on opposite sides of the pile on the bottom plate; Connecting at least one tension member between the wall and the protrusion of the pile; Placing cap concrete on the protrusion of the pile; Repeating the above steps by the length of the retaining wall; And backfilling the bottom plate toward the rear surface of the wall.

본 발명의 다른 실시예에 따른 옹벽의 시공방법은, 지반에 터파기하는 단계와; 지반 속으로 말뚝을 설치하는 단계와; 이 말뚝이 설치된 지반 주변으로 버림 콘크리트를 타설하는 단계와; 그 위에다 저판 및 벽체를 만들되, 상기 말뚝의 일부가 저판 위로 돌출된 돌출부를 형성하도록 하는 한편, 상기 벽체는 저판 상에서 말뚝의 맞은편에 위치하도록 만드는 단계와; 상기 벽체와 상기 말뚝의 돌출부 사이에 적어도 하나의 인장부재를 연결하는 단계와; 상기 말뚝의 돌출부 상에 캡 콘크리트를 타설하는 단계 및; 벽체의 이면 쪽 저판 위로 되메우기하는 단계;를 포함하는 것을 특징으로 한다. Construction method of the retaining wall according to another embodiment of the present invention, the step of digging in the ground; Installing a pile into the ground; Placing discarded concrete around the ground on which the pile is installed; Making a bottom plate and a wall thereon, such that a portion of the pile forms a protrusion protruding above the bottom plate, while the wall is positioned opposite the pile on the bottom plate; Connecting at least one tension member between the wall and the protrusion of the pile; Placing cap concrete on the protrusion of the pile; And backfilling the bottom plate on the back side of the wall.

이하 본 발명을 첨부도면에 의거하여 보다 상세히 설명한다. Hereinafter, the present invention will be described in more detail with reference to the accompanying drawings.

도 1은 본 발명의 한 실시예에 따른 옹벽의 시공방법을 설명하기 위해 단계별로 간략하게 나타낸 도면으로서, 이 실시예에서는 프리캐스트 콘크리트를 이용한 조립식 시공방법에 대해 설명하기로 한다. 1 is a view briefly illustrated step by step to explain the construction method of the retaining wall according to an embodiment of the present invention, in this embodiment will be described the prefabricated construction method using precast concrete.

먼저, 통상적으로 토목 공사에서 기초를 형성하는 방법으로, 설치대상이 되는 지지기반에 소정 깊이만큼 터파기를 하고서, 그 위에 버림 콘크리트(1)를 타설한다. First, as a method of forming a foundation in civil engineering, first, a trench is drilled by a predetermined depth on a support base to be installed, and the discarded concrete 1 is poured thereon.

이어서 버림 콘크리트(1)의 위에다 프리캐스트 콘크리트로 미리 제작된 저판(2)을 놓는다. 이 저판(2)은 예컨대 2 ~ 3m의 폭을 갖도록 대략 사각형 형상으로 만들어지며, 필요에 따라 도 1에 도시된 바와 같이 단차진 지지턱(21)이 형성되거나 지지홈이 형성되어, 나중에 설명되는 벽체(4)의 밑부분을 지지하게 되는데, 즉 이는 벽체(4)의 전도 및 활동에 대한 저항부로 작용하게 된다. 또, 이 지지턱(21) 또는 지지홈의 반대측에는 아래에 설명되는 말뚝(3)을 설치하기 위한 구멍(22)이 형성되어 있다. Subsequently, a bottom plate 2 made of precast concrete is placed on the discarded concrete 1. The bottom plate 2 is made into a substantially rectangular shape, for example, to have a width of 2 to 3 m, and as shown in FIG. 1, as shown in FIG. 1, a stepped support jaw 21 is formed or a support groove is formed, which will be described later. The bottom of the wall 4 is supported, that is, it acts as a resistance to the conduction and activity of the wall 4. Moreover, the hole 22 for attaching the pile 3 demonstrated below is formed in the opposite side to this support jaw 21 or the support groove.

다음으로, 저판(2)에 미리 형성된 구멍(22)을 통해 지반 속으로 말뚝(3)을 설치하는데, 이 말뚝(3)은 현장타설말뚝(C.I.P:Cast In Place Pile)으로서, 당해분야의 숙련자들이 잘 알고 있듯이 드릴을 이용하여 지반을 천공하고 시멘트 몰탈과 보강형 H-파일 등을 삽입하여 조성된 콘크리트 말뚝이다. 이러한 말뚝(3)은 내구성이 충분히 보장된다면, 전술된 현장타설말뚝에 한정되지 않고, 다른 재료 및 다른 형태로 된 말뚝이 사용될 수 있다. Next, the pile 3 is installed into the ground through a hole 22 formed in the bottom plate 2, which is a cast in place pile (CIP), and is suitable for those skilled in the art. As they are well aware, it is a concrete pile made by drilling the ground using a drill and inserting cement mortar and reinforced H-pile. Such piles 3 are not limited to the above-described cast-in-place piles, if the durability is sufficiently secured, and other materials and different-shaped piles may be used.

한편, 말뚝(3)의 설치시, 이 말뚝(3)의 상부측 일부가 저판(2) 위로 돌출될 수 있게 설치되어, 돌출부(31)를 형성할 수 있어야 한다. 또, 이 돌출부(31)에는 핀이음이나 볼트연결 등을 위한 연결공(32)이 형성되어야 한다.On the other hand, during the installation of the pile 3, a portion of the upper side of the pile 3 should be installed so as to protrude above the bottom plate 2, it should be able to form a protrusion (31). In addition, the protruding portion 31 should be formed with a connection hole 32 for pin joint or bolt connection.

그 후에, 상기 저판(2) 상에서 말뚝(3)의 맞은편에는, 원하는 높이 및 예컨대 2 ~ 3m의 폭을 갖도록 대략 사각형 형상으로 미리 프리캐스트 콘크리트로 제작된 벽체(4)를 세우게 된다. 이 벽체(4)와 상기 저판(2)은 원하는 옹벽의 길이만큼 다수개를 연속으로 이어붙일 수 있게 되어 있다. Thereafter, opposite the pile 3 on the bottom plate 2, a wall 4 made of precast concrete in a substantially rectangular shape is erected so as to have a desired height and a width of, for example, 2-3 m. The wall 4 and the bottom plate 2 can be joined in series by a desired length of the retaining wall.

더욱 상세히 설명하자면, 각 벽체(4)는 그 수직한 한쪽 측단면에 높이방향으로 대략 30 ~ 50cm의 간격을 두고 아이볼트(43)가 장착되어 있고, 반대쪽 측단면에는 높이방향으로 길게 형성된 홈부(44)가 형성되어 있되, 이 홈부(44)의 안에는 상기 아이볼트(43)와 동일한 간격으로 연결고리(45)가 설치되어 있다. 따라서, 원하는 옹벽의 길이만큼 저판(2)과 함께 벽체(4)를 이어붙일 때에는, 벽체(4)의 아이볼트(43)가 다른 벽체(4)의 인접한 측단면의 홈부(44) 내에 삽입되게 하고서 그 안에 있는 연결고리(45)가 아이볼트(45)에 걸림고정되어 이어지게 함과 더불어, 이들 이음부의 강성을 보강하기 위해 상기 홈부(44) 안을 그라우팅 처리하면 된다. 도 2에는, 상기 벽체(4)들의 이음부의 한 예가 잘 나타나 있다. More specifically, each wall 4 has an eye bolt 43 mounted on one vertical side surface thereof at intervals of about 30 to 50 cm in the height direction, and a groove portion formed in the height side on the opposite side surface thereof. 44 is formed, but in the groove 44, the connecting ring 45 is provided at the same interval as the eye bolt 43. Thus, when joining the wall 4 together with the bottom plate 2 by the desired retaining wall length, the eye bolt 43 of the wall 4 is inserted into the groove 44 of the adjacent side end surface of the other wall 4. Then, the connecting ring 45 therein is fixed to the eye bolts 45, and the grouting process is performed in the groove 44 to reinforce the rigidity of these joints. 2 shows an example of the joint of the walls 4.

또한, 상기 벽체(4)의 이면(말뚝 쪽)에는, 나중에 설명되는 인장부재(5)를 연결하기 위한 적어도 하나의 연결부(41)가 높이방향으로 소정의 간격을 두고 벽체(4)의 폭방향으로 길게 형성되어 있는데, 이들 연결부(41)의 중간부분에는 연결홈(42a)이 각각 형성되어 있고, 이 연결홈(42a)을 가로질러 연결홈(42a)의 양측벽 속으로 뻗어 있는 철심(42b)이 벽체(4)의 이면과는 떨어진 채로 설치되어 있다. In addition, on the rear surface (pile side) of the wall 4, at least one connecting portion 41 for connecting the tension member 5 described later is a width direction of the wall 4 at a predetermined interval in the height direction. In the middle portion of the connecting portion 41, connecting grooves 42a are formed respectively, and the iron cores 42b extend across the connecting grooves 42a into both side walls of the connecting grooves 42a. ) Is provided away from the back surface of the wall 4.

여기서, 벽체(4)를 세울 때에는 크레인(도시되지 않음)을 이용하여서, 저판(2) 상의 지지턱(21) 또는 지지홈에 의해 그 밑부분이 지지될 수 있도록 벽체(4)를 맞추어 세워 둔다. 이 상태에서, 이 벽체(4)의 이면에 형성된 적어도 하나의 연결부(41)와 말뚝(3)의 돌출부(31) 사이에 적어도 하나의 인장부재(5)를 연결하여, 벽체(40)를 지탱하게 된다. Here, when the wall 4 is erected, the wall 4 is erected so that its bottom can be supported by the support jaw 21 or the support groove on the bottom plate 2 using a crane (not shown). . In this state, at least one tension member 5 is connected between the at least one connecting portion 41 formed on the rear surface of the wall 4 and the protrusion 31 of the pile 3 to support the wall 40. Done.

상기 인장부재(5)는 예컨대 스테인리스 강이나 내부식성이 우수한 재료로 된 관이나 봉의 형태로 될 수 있으며, 그 한쪽 끝에는 벽체(4)의 연결부(41)에 설치된 철심(42b)에 걸어맞춰지는 연결고리(53)가 구비되어 있고, 반대쪽 끝에는 말뚝(3)의 돌출부(31)에 형성된 연결공(32)에 맞춰져, 핀이나, 볼트 및 너트 등으로 연결될 수 있게 형성된 관통공(52)이 구비되어 있다. 도 2에는, 상기 인장부재(5)와 상기 벽체(4)의 연결관계가 도시되어 있다. The tension member 5 may be, for example, in the form of a tube or rod made of stainless steel or a material having excellent corrosion resistance, and one end thereof is connected to an iron core 42b installed at the connection portion 41 of the wall 4. Ring 53 is provided, and the opposite end is provided with a through hole 52 that is connected to the connection hole 32 formed in the projection 31 of the pile 3, so that it can be connected by pins, bolts, nuts, etc. have. In Fig. 2, the connection between the tension member 5 and the wall 4 is shown.

또한, 각 인장부재(5)는 벽체(4) 및 말뚝(3)의 사이에서 서로 상이한 각도로 대략 일직선으로 정렬되어 연결된다. In addition, each tension member 5 is connected between the wall 4 and the pile 3 aligned in a substantially straight line at different angles from each other.

이어서, 상기 말뚝(3)의 돌출부(31)에다 캡 콘크리트(6)를 타설하여, 부식이 급격히 이루어지지 않도록 보호한다.Subsequently, the cap concrete 6 is poured into the protruding portion 31 of the pile 3 to protect it from corrosion.

한편, 소정의 길이를 갖는 옹벽을 시공하기 위해서는, 위의 공정을 상기 길이에 맞춰 여러 번 되풀이하여, 전술한 바와 같이 다수의 저판(2)과 다수의 벽체(4)를 연속되게 옆으로 이어붙인다. On the other hand, in order to construct a retaining wall having a predetermined length, the above process is repeated several times in accordance with the length, and the plurality of bottom plates 2 and the plurality of walls 4 are continuously connected sideways as described above. .

끝으로, 모든 프리캐스트 콘크리트로 된 구조물의 조립이 완료되면, 벽체(4)의 이면 쪽 저판(2) 위로 잡석 등을 이용해서 성토를 하고 다짐공정을 시행하여 되메우기 함으로써, 옹벽의 시공을 완료하게 된다. Finally, when the assembly of all the precast concrete structures is completed, the rubble is piled up on the bottom plate 2 on the back side of the wall 4 by using rubble, and the compacting process is performed to refill, thereby completing the construction of the retaining wall. do.

이상과 같이, 지지용 저판과 결합되게 말뚝을 설치하고서 이 말뚝 및 벽체 사이에 인장력을 가할 수 있는 인장부재를 연결시킴으로써, 통상 옹벽의 구축을 위해 설치되는 저판의 크기를 줄이면서도 전도 및 활동에 대한 저항을 높임과 동시에 옹벽의 두께도 경제적으로 줄일 수 있게 된다. As described above, by installing a pile to be coupled to the support base plate and connecting a tension member capable of applying a tensile force between the pile and the wall, while reducing the size of the bottom plate that is usually installed for the construction of the retaining wall, In addition to increasing resistance, the retaining wall thickness can be reduced economically.

또한, 장애물의 유무에 상관없이 옹벽을 비교적 짧은 공사기간 내에 비용도 저렴하게 간단히 시공할 수 있는 효과가 있게 된다. In addition, regardless of the presence or absence of obstacles, the retaining wall can be easily and inexpensively constructed in a relatively short construction period.

도 3은 본 발명의 다른 실시예에 따른 옹벽의 시공방법을 설명하기 위해 단계별로 간략하게 나타낸 도면으로서, 이 실시예에서는 설치대상에다 직접 시공하는 현장타설식 시공방법에 대해 설명하기로 한다. 3 is a view briefly illustrated step by step in order to explain the construction method of the retaining wall according to another embodiment of the present invention, in this embodiment will be described in the field-pouring construction method to be installed directly on the installation target.

먼저, 통상적으로 토목 공사에서 기초를 형성하는 방법으로 설치대상이 되는 지지기반에 소정 깊이만큼 터파기를 한다. First, the excavation by a predetermined depth to the support base to be installed by the method of forming the foundation in civil engineering in general.

이어서 상기 지지기반의 일측에서 지반 속으로 말뚝(3)을 설치하는데, 이 말뚝(3)은 현장타설말뚝이 바람직하지만, 내구성이 충분히 보장된다면 현장타설말뚝에만 한정되지 않고, 다른 재료 및 다른 형태로 된 말뚝이 사용될 수 있다. Subsequently, the pile 3 is installed into the ground at one side of the support base, which is preferably cast in place, but is not limited to the cast in place if the durability is sufficiently secured, and is made of other materials and other forms. Piles can be used.

한편, 말뚝(3)의 설치시, 이 말뚝(3)의 상부측 일부가 나중에 설명되는 저판(2) 위로 돌출될 수 있게 여유길이를 두고 설치되어, 돌출부(31)를 형성할 수 있어야 한다. 또, 이 돌출부(31)에는 핀이음이나 볼트연결 등을 위한 연결공(32)이 형성되어야 한다. On the other hand, in the installation of the pile (3), it should be provided with an allowable length so that a part of the upper side of the pile (3) can be projected onto the bottom plate (2), which will be described later, to form a projection (31). In addition, the protruding portion 31 should be formed with a connection hole 32 for pin joint or bolt connection.

상기 말뚝(3)의 설치가 완료되면, 그 지반 주변으로 버림 콘크리트(1)를 타설한다. When the installation of the pile 3 is completed, the discarded concrete 1 is poured around the ground.

다음으로, 버림 콘크리트(1)의 위에다 거푸집(도시되지 않음)을 설치하고 콘크리트로 저판(2) 및 벽체(4)를 일체로 하여 만들게 되는데, 벽체(4)는 저판(2) 상에서 말뚝(3)의 맞은편에 소정의 높이를 갖도록 직립되게 형성되고, 예컨대 아이볼트와 같은 연결부(41)가 이 벽체(4)의 이면에 다수열로 배치되게 된다. Next, a formwork (not shown) is installed on the discarded concrete 1 and the bottom plate 2 and the wall 4 are made of concrete, and the wall 4 is piled on the bottom plate 2. It is formed so as to be upright to have a predetermined height opposite the (), for example, the connecting portion 41 such as an eye bolt is arranged in a plurality of rows on the back surface of the wall (4).

더욱 상세히 설명하자면, 원하는 높이를 갖는 벽체(4)는 그 이면에 나중에 설명되는 인장부재(5)를 연결하기 위한 적어도 하나의 연결부(41)가 높이방향으로 소정의 간격을 두고 정렬되어 다수열로 배치되는데, 이들 연결부(41)에는 핀이음이나 볼트연결 등을 위한 연결공(42)이 각각 형성되어 있어야 한다. More specifically, the wall 4 having a desired height has a plurality of rows in which at least one connecting portion 41 for connecting the tensioning member 5 described later is arranged at predetermined intervals in the height direction. Is arranged, these connection portion 41, the connection hole 42 for pin joint or bolt connection, etc. should be formed respectively.

벽체(4) 및 저판(2)이 성형된 후에는, 벽체(4)의 이면에 있는 연결부(41)와 말뚝(3)의 돌출부(31) 사이에 적어도 하나의 인장부재(5)를 연결하여, 벽체(4) 및 저판(2) 또는 말뚝(3) 사이에 인장력을 가하게 한다. After the wall 4 and the bottom plate 2 are formed, at least one tension member 5 is connected between the connecting portion 41 on the rear surface of the wall 4 and the protrusion 31 of the pile 3. A tension force is applied between the wall 4 and the bottom plate 2 or the pile 3.

상기 인장부재(5)는 예컨대 스테인리스 강이나 내부식성이 우수한 재료로 된 관이나 봉의 형태로 될 수 있으며, 그 양끝에는 벽체(4)의 각 연결부(41)에 있는 연결공(42) 및 말뚝(3)의 돌출부(31)에 형성된 연결공(32)에 맞춰져, 핀이나, 볼트 및 너트 등으로 연결될 수 있게 형성된 관통공(52:도 1 참조)이 구비되어 있다. The tension member 5 may be, for example, in the form of a tube or rod made of stainless steel or a material having excellent corrosion resistance, and at both ends thereof, a connection hole 42 and a pile (at each connection portion 41 of the wall 4). 3 is provided with a through hole 52 (see FIG. 1) formed to fit the connecting hole 32 formed in the protrusion 31 of the present invention so as to be connected with a pin, a bolt, a nut, or the like.

특히, 이 실시예에서는 도 3에 도시된 바와 같이, 인장부재(5)가 부식방지를 위해 코팅된 와이어의 형태로 될 수 있는바, 그 양끝이 연결고리를 갖추어 각 연결공(32,42)에 연결되거나, 와이어가 직접 각 연결공(32,42)에 끼워져 연결되어도 된다. 더구나, 인장력을 조절할 수 있도록 와이어로 된 인장부재(5)의 중간에 턴버클(51)을 개재시키는 것도 좋다. In particular, in this embodiment, as shown in Figure 3, the tension member (5) can be in the form of a coated wire to prevent corrosion, both ends are provided with a connecting ring each connecting hole (32, 42) Or wires may be directly inserted into and connected to the respective connecting holes 32 and 42. In addition, the turnbuckle 51 may be interposed in the middle of the tension member 5 made of a wire so as to adjust the tension force.

또한, 각 인장부재(5)는 벽체(4) 및 말뚝(3)의 사이에서 서로 상이한 각도로 대략 일직선으로 정렬되어 연결된다. In addition, each tension member 5 is connected between the wall 4 and the pile 3 aligned in a substantially straight line at different angles from each other.

이어서, 상기 말뚝(3)의 돌출부(31)에다 캡 콘크리트(6)를 타설하여, 부식이 급격히 이루어지지 않도록 보호한다.Subsequently, the cap concrete 6 is poured into the protruding portion 31 of the pile 3 to protect it from corrosion.

끝으로, 상기 벽체(4)의 이면 쪽 저판(2) 위로 잡석 등을 이용해서 성토를 하고 다짐공정을 시행하여 되메우기 함으로써, 옹벽의 시공을 완료하게 된다. Finally, the back surface of the wall 4 is filled with rubble or the like using a rubble, followed by a compaction process to fill the back wall, thereby completing the construction of the retaining wall.

이상과 같이, 지지용 저판과 결합되게 말뚝을 설치하고서 이 말뚝 및 벽체 사이에 인장력을 가할 수 있는 인장부재를 연결시킴으로써, 통상 옹벽의 구축을 위해 설치되는 저판의 크기를 줄이면서도 전도 및 활동에 대한 저항을 높임과 동시에 옹벽의 두께도 경제적으로 줄일 수 있게 된다. As described above, by installing a pile to be coupled to the support base plate and connecting a tension member capable of applying a tensile force between the pile and the wall, while reducing the size of the bottom plate that is usually installed for the construction of the retaining wall, In addition to increasing resistance, the retaining wall thickness can be reduced economically.

또한, 장애물의 유무에 상관없이 옹벽을 비교적 짧은 공사기간 내에 비용도 저렴하게 간단히 시공할 수 있는 효과가 있게 된다. In addition, regardless of the presence or absence of obstacles, the retaining wall can be easily and inexpensively constructed in a relatively short construction period.

이상에서는 본 발명을 특정한 실시예들을 예로 들어 도시하고 설명하였으나, 본 발명은 상기한 실시예들에 한정되지 않고 본 발명의 정신을 벗어나지 않는 한 당해분야의 숙련자들에 의해 다양하게 변경 및 수정될 수 있다. The present invention has been illustrated and described with reference to specific embodiments, but the present invention is not limited to the above embodiments and may be variously modified and modified by those skilled in the art without departing from the spirit of the present invention. have.

도 1은 본 발명의 한 실시예에 따른 옹벽의 시공방법을 설명하기 위해 단계별로 간략하게 나타낸 도면이다.1 is a view briefly shown step by step to explain a construction method of a retaining wall according to an embodiment of the present invention.

도 2는 도 1에 도시된 벽체의 분할부 및 인장부재 사이의 연결관계를 나타낸 평단면도이다.FIG. 2 is a cross-sectional plan view illustrating a connection relationship between the partition and the tension member of the wall illustrated in FIG. 1.

도 3은 본 발명의 다른 실시예에 따른 옹벽의 시공방법을 설명하기 위해 단계별로 간략하게 나타낸 도면이다.Figure 3 is a simplified view showing step by step to explain the construction of the retaining wall according to another embodiment of the present invention.

Claims (8)

지반 상에 설치되는 저판(2)과; 이 저판(2)의 일측 밑 지반 속에 설치되되, 그 일부가 저판(2) 위로 돌출된 돌출부(31)를 형성한 채로 저판(2)과 결합되는 말뚝(3)과; 상기 저판(2) 상에서 말뚝(3)의 맞은편에 세워지는 벽체(4) 및; 이 벽체(4)와 상기 말뚝(3)의 돌출부(31) 사이에 인장력을 가하도록 연결되는 적어도 하나의 인장부재(5);를 구비하는 것을 특징으로 하는 옹벽. A bottom plate 2 installed on the ground; A pile 3 which is installed in the lower ground of one side of the bottom plate 2, and part of which is coupled to the bottom plate 2 while forming a protrusion 31 protruding above the bottom plate 2; A wall (4) erected opposite the pile (3) on the bottom plate (2); And at least one tension member (5) connected to exert a tensile force between the wall (4) and the protrusion (31) of the pile (3). 지반에 터파기 및 버림 콘크리트(1)를 타설하는 단계와; 그 위에 미리 제작된 저판(2)을 놓는 단계와; 이 저판(2)에 미리 형성된 구멍(22)을 통해 지반 속으로 말뚝(3)을 설치하되, 말뚝(3)의 일부가 저판 위로 돌출된 돌출부(31)를 형성하도록 설치하는 단계와; 상기 저판(2) 상에서 말뚝(3)의 맞은편에 미리 제작된 벽체(4)를 세우는 단계와; 이 벽체(4)와 상기 말뚝(3)의 돌출부(31) 사이에 적어도 하나의 인장부재(5)를 연결하는 단계와; 상기 말뚝(3)의 돌출부(31) 상에 캡 콘크리트(6)를 타설하는 단계와; 옹벽의 길이만큼 위의 단계들을 되풀이하는 단계 및; 벽체(4)의 이면 쪽 저판(2) 위로 되메우기하는 단계;를 포함하는 것을 특징으로 하는 옹벽의 시공방법. Pouring digging and discarding concrete (1) into the ground; Placing a prefabricated bottom plate 2 thereon; Installing a pile (3) into the ground through a hole (22) preformed in the bottom plate (2), wherein a portion of the pile (3) is formed to form a protrusion (31) protruding onto the bottom plate; Erecting a prefabricated wall (4) on the bottom plate (2) opposite the pile (3); Connecting at least one tension member (5) between the wall (4) and the protrusion (31) of the pile (3); Placing cap concrete (6) on the protrusion (31) of the pile (3); Repeating the above steps by the length of the retaining wall; And backfilling the bottom plate (2) on the back side of the wall (4). 제2항에 있어서, 상기 되풀이하는 단계에서는, 옹벽의 길이만큼 저판(2)과 벽체(4)를 연속되게 옆으로 이어붙이되, 각 벽체(4)의 수직한 한쪽 측단면에는 높 이방향으로 간격을 두고 다수의 아이볼트(43)가 장착되어 있고, 반대쪽 측단면에는 높이방향으로 길게 형성된 홈부(44)가 형성되어 있되, 이 홈부(44)의 안에는 상기 아이볼트(43)와 동일한 간격으로 연결고리(45)가 설치되어 있어서, 한 벽체(4)의 아이볼트(43)가 다른 벽체(4)의 인접한 측단면의 홈부(44) 내에 삽입되게 하고서 그 안에 있는 연결고리(45)가 아이볼트(45)에 걸림고정되어 이어지게 한 후, 상기 홈부(44) 안을 그라우팅 처리하는 것을 특징으로 하는 옹벽의 시공방법.The method of claim 2, wherein in the step of repeating, the bottom plate 2 and the wall 4 are successively connected sideways by the length of the retaining wall, and in one vertical side surface of each wall 4 in the height direction. A plurality of eye bolts 43 are mounted at intervals, and groove portions 44 that are formed long in the height direction are formed on opposite side cross-sections, and inside the groove portions 44 at the same interval as the eye bolts 43. The connecting ring 45 is provided so that the eye bolt 43 of one wall 4 is inserted into the groove 44 of the adjacent side surface of the other wall 4 and the connecting ring 45 therein is inserted into the eye. The retaining wall construction method of the retaining wall, characterized in that the grouting process in the groove portion 44 after being fixed to the bolt (45). 제2항에 있어서, 상기 적어도 하나의 인장부재(5)를 연결하는 단계에서는, 인장부재(5)의 한 끝에 구비된 연결고리(53)를 벽체(4)의 연결부(41)의 중간에 형성된 연결홈(42a) 안에 설치된 철심(42b)에 걸어맞추는 한편, 인장부재(5)의 반대쪽 끝에 형성된 관통공(52)을 말뚝(3)의 돌출부(31)에 형성된 연결공(32)에 맞추고서 핀이나 볼트 및 너트로 연결하는 것을 특징으로 하는 옹벽의 시공방법.The method of claim 2, wherein in the step of connecting the at least one tension member 5, the connecting ring 53 provided at one end of the tension member 5 is formed in the middle of the connection portion 41 of the wall (4) While engaging with the iron core 42b installed in the connecting groove 42a, the through hole 52 formed at the opposite end of the tension member 5 is aligned with the connecting hole 32 formed in the protrusion 31 of the pile 3, A method of constructing a retaining wall, which is connected by pins, bolts, and nuts. 지반에 터파기하는 단계와; 지반 속으로 말뚝(3)을 설치하는 단계와; 이 말뚝(3)이 설치된 지반 주변으로 버림 콘크리트(1)를 타설하는 단계와; 그 위에다 저판(2) 및 벽체(4)를 만들되, 상기 말뚝(3)의 일부가 저판(2) 위로 돌출된 돌출부(31)를 형성하도록 하는 한편, 상기 벽체(4)는 저판(2) 상에서 말뚝(3)의 맞은편에 직립되게 위치하도록 만드는 단계와; 상기 벽체(4)와 상기 말뚝(3)의 돌출부(31) 사이에 적어도 하나의 인장부재(5)를 연결하는 단계와; 상기 말뚝(3)의 돌출부(31) 상에 캡 콘크리트(6)를 타설하는 단계 및; 벽체(4)의 이면 쪽 저판(2) 위 로 되메우기하는 단계;를 포함하는 것을 특징으로 하는 옹벽의 시공방법. Digging in the ground; Installing the pile 3 into the ground; Placing the discarded concrete 1 around the ground on which the pile 3 is installed; On top of which the bottom plate 2 and the wall 4 are made, a part of the pile 3 forms a projection 31 protruding above the bottom plate 2, while the wall 4 is placed on the bottom plate 2. Making an upright position opposite the pile 3; Connecting at least one tension member (5) between the wall (4) and the protrusion (31) of the pile (3); Placing cap concrete (6) on the protrusion (31) of the pile (3); And backfilling the bottom plate (2) on the back side of the wall (4). 제5항에 있어서, 상기 적어도 하나의 인장부재(5)를 연결하는 단계에서는, 벽체(4)의 연결부(41)에 형성된 연결공(42) 및 말뚝(3)의 돌출부(31)에 형성된 연결공(32)에다, 와이어로 된 인장부재(5)를 직접 연결하는 것을 특징으로 하는 옹벽의 시공방법. The method of claim 5, wherein in the step of connecting the at least one tension member 5, the connection hole 42 formed in the connection portion 41 of the wall 4 and the connection formed in the protrusion 31 of the pile 3 A method of constructing a retaining wall, characterized in that to directly connect a tension member (5) made of wire to a ball (32). 제6항에 있어서, 상기 인장부재(5)의 인장력을 조절할 수 있도록 그 중간에 턴버클(51)을 추가로 설치하는 것을 특징으로 하는 옹벽의 시공방법. 7. A method according to claim 6, characterized in that a turnbuckle (51) is further installed in the middle of the tension member (5) so as to adjust the tensile force of the tension member (5). 제2항 또는 제5항에 있어서, 상기 인장부재(5)들은 벽체(4) 및 말뚝(3)의 사이에서 서로 상이한 각도로 연결되는 것을 특징으로 하는 옹벽.Retaining wall according to claim 2 or 5, characterized in that the tension members (5) are connected at different angles between the wall (4) and the pile (3).
KR1020070108120A 2007-10-26 2007-10-26 Retaining Wall and Construction Method Ceased KR20090042395A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070108120A KR20090042395A (en) 2007-10-26 2007-10-26 Retaining Wall and Construction Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070108120A KR20090042395A (en) 2007-10-26 2007-10-26 Retaining Wall and Construction Method

Publications (1)

Publication Number Publication Date
KR20090042395A true KR20090042395A (en) 2009-04-30

Family

ID=40765127

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070108120A Ceased KR20090042395A (en) 2007-10-26 2007-10-26 Retaining Wall and Construction Method

Country Status (1)

Country Link
KR (1) KR20090042395A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049528A (en) * 2016-04-18 2016-10-26 单发成 Casting method for material saving anti-slip retaining wall
CN107366302A (en) * 2017-06-27 2017-11-21 华恒建设集团有限公司 A kind of construction technology of reinforced concrete retaining wall
KR102091127B1 (en) * 2019-07-05 2020-03-19 동아이엔지(주) Joint structure for baseplate-pile and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049528A (en) * 2016-04-18 2016-10-26 单发成 Casting method for material saving anti-slip retaining wall
CN107366302A (en) * 2017-06-27 2017-11-21 华恒建设集团有限公司 A kind of construction technology of reinforced concrete retaining wall
CN107366302B (en) * 2017-06-27 2019-02-05 华恒建设集团有限公司 A kind of construction technology of reinforced concrete retaining wall
KR102091127B1 (en) * 2019-07-05 2020-03-19 동아이엔지(주) Joint structure for baseplate-pile and construction method thereof

Similar Documents

Publication Publication Date Title
KR101058520B1 (en) A retaining wall composed of PA piles and its construction method
KR102208793B1 (en) Under ground structure using column wall and construction method thereof
KR101973565B1 (en) Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate
CN101939492B (en) Precast temporary facility structure and construction method for the same
KR100640716B1 (en) Inverted tee type precast concrete retaining wall block and construction method using the same
KR101167511B1 (en) Underpass using precast concrete pile and method for constructing the same
KR101182704B1 (en) Construction method of undergroud structure using PHC pile
JP4812324B2 (en) Retaining wall and its construction method
JP2000265458A (en) PCa pile underground wall slab connection structure for underground structures
JP6703816B2 (en) Footing foundation structure
KR20070108741A (en) Top-down method using the PC column
KR20090042395A (en) Retaining Wall and Construction Method
KR101222348B1 (en) The Supporting Structure and Pressing device of Underground Structure
KR100919921B1 (en) Retaining wall using panel and construction method
JP6860895B2 (en) Retaining wall and its construction method
KR102216972B1 (en) Construction method for building concrete foundation which piles are supposed to be exposed because of nearby excavation
JP3768220B2 (en) Pier structure and pier
JP2012031678A (en) Foundation for structure and method for constructing the same
KR100673475B1 (en) PC girder member for base frame frame, assembly structure and method of construction
JP3963326B2 (en) Seismic reinforcement structure for bridge pier and its construction method
KR100562686B1 (en) Underground structure using steel sheet pile and cast-in-place concrete and construction method
JP7269197B2 (en) ROAD STRUCTURE AND METHOD FOR MANUFACTURING ROAD STRUCTURE
KR200194424Y1 (en) Precast retaining wall using high strength micro pile
KR102110080B1 (en) H-type steel wall And Open cut method for constructing an underground structure using H-type steel wall
JP5201719B2 (en) Column construction method and column structure

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20071026

PA0201 Request for examination
E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20090413

Patent event code: PE09021S01D

PG1501 Laying open of application
E601 Decision to refuse application
PE0601 Decision on rejection of patent

Patent event date: 20090828

Comment text: Decision to Refuse Application

Patent event code: PE06012S01D

Patent event date: 20090413

Comment text: Notification of reason for refusal

Patent event code: PE06011S01I