KR100938918B1 - Top-down construction method using steel frame by channel - Google Patents

Top-down construction method using steel frame by channel Download PDF

Info

Publication number
KR100938918B1
KR100938918B1 KR1020090068810A KR20090068810A KR100938918B1 KR 100938918 B1 KR100938918 B1 KR 100938918B1 KR 1020090068810 A KR1020090068810 A KR 1020090068810A KR 20090068810 A KR20090068810 A KR 20090068810A KR 100938918 B1 KR100938918 B1 KR 100938918B1
Authority
KR
South Korea
Prior art keywords
channel
wall
steel frame
twig
shaped steel
Prior art date
Application number
KR1020090068810A
Other languages
Korean (ko)
Inventor
서정호
신동규
Original Assignee
(주)씨엠파트너스건축사사무소
쌍용건설 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=41810290&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=KR100938918(B1) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by (주)씨엠파트너스건축사사무소, 쌍용건설 주식회사 filed Critical (주)씨엠파트너스건축사사무소
Application granted granted Critical
Publication of KR100938918B1 publication Critical patent/KR100938918B1/en
Priority to PCT/KR2010/003108 priority Critical patent/WO2010134731A2/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Hydrology & Water Resources (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE: A Top-down construction method using a twig type steel frame by a channel for continuous construction of a basement outer wall is provided to facilitate application in a field by using a twig type steel frame assembled simply by a channel. CONSTITUTION: A Top-down construction method using a twig type steel frame by a channel for continuous construction of a basement outer wall comprises the steps for installing a twig type steel frame assembled simply by a channel between a retaining wall(110) and a slab to transmit earth pressure; and successively constructing the basement outer wall after securing the continuous construction space of the basement outer wall.

Description

지하외벽의 연속시공을 위해 채널에 의한 나뭇가지형 스틸프레임을 이용한 역타공법{Top-down construction method using steel frame by channel}Top-down construction method using steel frame by channel for continuous construction of underground walls

본 발명은 건물의 지하부분(보, 슬래브)으로 직접 토압을 지지해가면서 굴착하여 건물의 지하부분을 시공하는 역타공법에 관한 것으로서, 더욱 상세하게는 채널에 의한 나뭇가지형 스틸프레임을 이용하면서 전반적인 건물 지하부분은 역순으로 시공하는 한편 지하외벽은 순차적으로 연속 시공하는 방법에 관한 것이다.The present invention relates to a reverse drilling method for constructing the underground part of a building by excavating while supporting the earth pressure directly to the underground part of the building (beam, slab), and more specifically, using a twig-shaped steel frame by a channel. The underground part of the building is constructed in reverse order, while the underground exterior wall is sequentially constructed.

일반적으로 건물의 지하부분을 시공하는 방법은 시공방향에 따라 크게 순타공법과 역타공법으로 구분할 수 있다. 순타공법은 흙막이벽을 시공한 후 가설지지체(수평버팀대, 레이커, 어스앵커 락볼트 등)로 흙막이벽을 지지하면서 지하 최하층까지 굴토한 다음 지하 최하층에서부터 한층 한층 올라가면서 구조물을 순차적으로 시공하는 방법이다. 역타공법은 흙막이벽을 시공한 후 굴토와 구조체 공사를 한층 한층 내려가면서 역순으로 시공하는 방법으로, 일명 탑다운(Top-down)공법이라고 한다. 역타공법은 터파기와 지상공사의 병행으로 공기단축이 가능하고, 영구 구조물을 흙막이벽 지지체로 사용하여 구조적 안정성을 확보할 수 있으며, 소음과 진동이 적기 때문에, 현재 도심지 공사에 유리하게 적용되고 있다.In general, the method of constructing the underground part of a building can be divided into the forward and reverse method according to the construction direction. The netting method is a method of constructing a sequential wall, supporting it with a temporary support (horizontal brace, raker, earth anchor rock bolt, etc.), tacking to the bottom of the basement, and then constructing the structure sequentially from the basement to the bottom. . The reverse drilling method is a method of constructing a wall of clay and constructing a structure in the reverse order while further down the pit and structure work. It is called a top-down method. The reverse drilling method is possible to shorten the air by the combination of the trench and the ground work, and to secure the structural stability by using the permanent structure as the support wall of the earth wall, and it is advantageously applied to the construction of the downtown because of the low noise and vibration.

한편, 일반적으로 지하 건물은 H-Beam+토류판, CIP(Cast in-Place Pile), SCW(Soil Cement Wall) 등과 같은 주열식 흙막이벽을 시공한 후 흙막이벽 내측을 굴착하여 구조체를 구축하는 방법으로 진행되는데, 굴착과정에는 흙막이벽을 통해 전달되는 토압 등 외력을 지지하기 위한 버팀공사가 수반된다. 통상 흙막이벽의 버팀공법으로는 가설Strut나 Ground Anchor 또는 영구구조물을 이용하는 방법 등이 있으며, 이 중 도심지 인접공사에는 영구구조물을 이용한 버팀공법이 굴착 공사시의 구조적 안정성 확보와 공기단축, 그리고 민원 발생 소지 억제 등의 측면을 고려할 때 가장 유리하다.On the other hand, underground buildings generally proceed with a method of constructing a structure by excavating the inner wall of the retaining wall after constructing a heat-retaining retaining wall such as H-Beam + earth plate, CIP (Cast in-Place Pile), SCW (Soil Cement Wall), etc. Excavation process is accompanied by a bracing work to support external forces, such as earth pressure transmitted through the wall. Generally, temporary wall struts, ground anchors, or permanent structures are used for the construction of the retaining walls. Among these, adjacent structures in the city center use the permanent structures to secure structural stability, shorten the air, and generate civil complaints. It is the most advantageous when considering aspects, such as possession inhibition.

영구구조물을 이용한 버팀공법은 역타공법과 맞물려 역타지지공법이 되는데, 역타지지공법은 건물 지하부분의 층간 수평구조체인 보와 슬래브가 흙막이벽을 지지하는 영구구조물로 역할하도록 시공하는 과정을 지하 최하층까지 역순으로 반복적으로 수행한 후에 지하외벽을 시공하는 방식으로 진행된다. 이와 같은 역타지지공법에서 지하외벽은 그 일부분이 테두리보와 슬래브의 형태로 흙막이벽을 지지하고 위한 구성으로 먼저 시공되고 그 나머지가 나중에 시공된다. 즉 지하외벽은 분리 시공되는 것이다. 지하외벽의 분리 시공은 벽체철근의 연속배근과 벽체콘크리트의 연속타설을 어렵게 하여 전반적으로 지하외벽의 구조적인 성능을 저하시키는 원인이 되며, 나아가 시공줄눈을 통한 누수문제를 일으켜 철근의 부식, 콘크리트 열화 등 구조물의 내구성을 저하시키는 원인이 되기도 한다.Reinforcement method using permanent structure is a reverse support method combined with reverse punching method. Reverse punching method is the process of constructing beam and slab, which is a horizontal structure between floors in the basement part of the building, to serve as a permanent structure to support the wall. After repeatedly performing in reverse order, it proceeds by constructing the outer wall. In the reverse support method, the basement outer wall is first constructed as a part for supporting the retaining wall in the form of a rim beam and slab, and the rest is later constructed. In other words, the basement outer wall is to be separated. Separation of the basement outer walls makes continuous reinforcement of wall reinforcement and continuous construction of wall concrete difficult, which in turn degrades the structural performance of the basement walls.In addition, it causes leakage problems through construction joints, causing corrosion of reinforcing bars and deterioration of concrete. It may also cause the durability of the back structure.

본 발명은 상기한 종래 역타공법에 있어 지하외벽 시공에 관련한 문제를 동시에 해결하고자 개발된 것으로서, 다음과 같은 기술적 과제가 있다.The present invention was developed in order to solve the problems related to the construction of the basement outer wall at the same time in the conventional reverse drilling method, there are the following technical problems.

첫째, 건물 지하부분을 역타공법으로 시공함에 있어 다른 부분은 역순으로 시공하되 지하외벽만은 순차적으로 연속 시공함으로써 시공줄눈을 최소화할 수 있는 방법을 제공하고자 한다.First, in constructing the underground part of the building by reverse drilling method, the other parts should be constructed in reverse order, but only underground exterior walls are sequentially installed to provide a method of minimizing construction joints.

둘째, 건물 지하부분을 역타공법으로 시공함에 있어 가설작업을 최소화하여 시공성을 향상시킴은 물론 일정의 시공품질과 경제성을 확보할 수 있는 방법을 제공하고자 한다.Second, in constructing the underground part of the building by reverse drilling method, it is intended to provide a method to minimize construction work and improve construction, as well as to secure a certain construction quality and economic feasibility.

상기한 기술적 과제를 해결하기 위해, 본 발명은 건물의 지하부분을 역타공법으로 시공함에 있어 채널로 조립된 나뭇가지형 스틸프레임을 흙막이벽과 슬래브 사이에 설치 시공함으로써 나뭇가지형 스틸프레임에 의해 토압전달을 유효하게 실현하는 한편 지하외벽의 연속시공 공간을 확보한 후에 지하외벽을 순차적으로 연속 시공하는 방법을 제공한다. In order to solve the above technical problem, the present invention in the construction of the underground part of the building by reverse drilling method by installing a branched steel frame assembled with channels between the retaining wall and the slab earth pressure by the branched steel frame The present invention provides a method of sequentially constructing an underground exterior wall while effectively realizing transmission and securing a continuous construction space of the underground exterior wall.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

첫째, 지하외벽을 하부층에서부터 순차적으로 연속 시공할 수 있기 때문에 지하외벽의 시공줄눈 발생을 최소화할 수 있으며, 이에 따라 시공줄눈에 의한 누수 등을 차단하면서 지하외벽의 시공품질을 개선할 수 있다.First, since the basement outer wall can be sequentially installed from the lower layer, it is possible to minimize the occurrence of construction joints of the basement outer wall, thereby improving the construction quality of the basement outer wall while blocking leakage caused by the construction joint.

둘째, 흙막이벽을 지지하기 위한 지지체의 시공에서 형틀, 철근 등의 가설작업을 최소화할 수 있으며, 이에 따라 역타공법에서 전반적으로 시공성과 경제성을 향상시킬 수 있다.Second, in the construction of the support to support the retaining wall can minimize the construction work, such as mold, reinforcing bars, thereby improving the overall construction and economic efficiency in the reverse drilling method.

셋째, 채널 부재로 간단하게 조립한 나뭇가지형 스틸프레임을 이용하기 때문에 현장에 용이하게 적용할 수 있다. 또한 나뭇가지형 스틸프레임은 그 일부분을 규격화하여 제작할 수 있기 때문에 현장 작업량을 최소화하면서 적용할 수 있다.Third, since it uses a branched steel frame that is simply assembled as a channel member, it can be easily applied to the field. In addition, since the branched steel frame can be manufactured by standardizing a part of it, it can be applied while minimizing the amount of field work.

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다. Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.

본 발명에 따른 역타공법은 건물의 지하부분(보, 슬래브)으로 직접 토압을 지지해가면서 굴착하여 건물의 지하부분을 시공하는 역타방법에 관한 것으로서, 건물의 지하부분을 역타공법으로 시공함에 있어 채널로 조립된 나뭇가지형 스틸프레임(200)을 흙막이벽(110)과 슬래브(160) 사이에 설치 시공함으로써 나뭇가지형 스틸프레임(200)에 의해 토압전달을 유효하게 실현하는 한편 지하외벽의 연속시공 공 간을 확보한 후에 지하외벽(180)을 순차적으로 연속 시공한다는데 기술적 특징이 있다. 도 1a 내지 도 1h는 본 발명에 따른 역타공법의 시공순서를 도시하며, 이를 참고하여 본 발명을 단계적으로 설명한다.The reverse drilling method according to the present invention relates to a reverse drilling method for constructing the underground part of a building by excavating while supporting the earth pressure directly to the underground part of the building (beams, slabs), and in constructing the underground part of the building by the reverse drilling method. By installing and installing the branched steel frame 200 assembled between the retaining wall 110 and the slab 160, the earthquake pressure transmission is effectively realized by the branched steel frame 200, while the continuous construction of the basement outer wall. After securing the space there is a technical feature to sequentially build the basement outer wall 180 sequentially. 1A to 1H show the construction procedure of the reverse drilling method according to the present invention, the present invention will be described step by step with reference to this.

(a)단계 : 흙막이벽 및 내부기둥 시공- 도 1a(a) step: construction of the retaining wall and the inner pillar- Figure 1a

건축선에 맞춰 흙막이벽(110)을 시공한다. 흙막이벽(110)은 H말뚝과 토류판, CIP, SCW, 시트파일 등은 물론 지하연속벽(슬러리월)으로 시공 가능하다. 본 발명에서는 실시예를 통해 H형강에 의한 엄지말뚝(110a)과 철근콘크리트 기둥을 주열식으로 시공하여 완성한 흙막이벽(110)을 확인할 수 있다.Construct the earth wall 110 according to the construction line. Soil wall 110 can be installed as a H continuous pile, earth plate, CIP, SCW, sheet pile, as well as underground continuous wall (slurry wall). In the present invention can be confirmed through the embodiment the thumb pile (110a) by the H-beam and reinforced concrete pillars to construct the main wall wall 110 completed by the main heating method.

흙막이벽(110)을 시공한 후에는 흙막이벽(110) 내부로 내부기둥(120)을 시공한다. 본 단계에서 내부기둥(120)은 건물 지하부분의 구조체를 구성하는 영구 기둥이 된다. 내부기둥(120)은 철골 또는 PC로 시공할 수 있다.After constructing the retaining wall 110, the inner pillar 120 is constructed into the retaining wall 110. In this step, the inner pillar 120 is a permanent column constituting the structure of the basement of the building. The inner column 120 may be constructed of steel or PC.

(b)단계 : 굴토 및 브라켓- 도 1b(b) step: gulting and brackets-Figure 1b

흙막이벽(110) 내측 지반을 굴토한다. 굴토깊이는 흙막이벽(110)의 안정적인 지지상태를 고려하면서 실시한다. The ground wall 110 excavates the ground. The pit depth is carried out while considering the stable support state of the retaining wall (110).

굴토한 후에는 흙막이벽(110)에 브라켓(130)을 고정 설치한다. 브라켓(130)은 (c)단계에서 설치되는 거치보(140)와 함께 (d)단계에서 설치되는 외곽수평보(150b)를 안정적으로 지지하기 위한 구성이므로, 외곽수평보(150b)의 설계 계획에 따라 적절한 위치에만 설치하면 된다. 브라켓(130)은 (c)단계에서 설치되는 거 치보(140)와 함께 (h)단계에서 시공되는 지하외벽(180)에 영구적으로 묻히며, 이를 감안하면 브라켓(130)은 지하외벽(180)에서 돌출되지 않게 설치하도록 한다.After the excavation, the bracket 130 is fixed to the earth wall 110. Since the bracket 130 is configured to stably support the outer horizontal beam 150b installed in the step (d) together with the mounting beam 140 installed in the step (c), the design plan of the outer horizontal beam 150b You only need to install it at the appropriate location. The bracket 130 is permanently buried in the basement outer wall 180 constructed in step (h) together with the mounting beam 140 installed in step (c), and in view of this, the bracket 130 is the basement outer wall 180. Do not protrude from the

(c)단계 : 거치보 설치- 도 1c(c) step: mounting bracket-Figure 1c

브라켓(130) 상호 간을 연결하는 거치보(140)를 브라켓(130) 위에 거치하면서 설치한다. 이때 거치보(140)는 (h)단계에서 시공할 지하외벽(180) 내부에 위치하도록 설치해야 한다. 그래야 거치보(140)가 지하외벽(180)에서 돌출되지 않게 매입되어 건물 지하부분의 공간 활용이 자유로워진다. 나아가 거치보(140)는 지하외벽(180)의 중앙에 위치하도록 설치하는 것이 더욱 바람직한데, 이는 (h)단계를 진행하는 과정에서 거치보(140)의 방해를 받지 않으면서 거치보(140)를 사이에 두고 벽체철근(181)을 연속 배근할 수 있기 때문이다.Bracket 130 is installed while mounting on the bracket 130 to connect the bracket 140 to each other. At this time, the mounting beam 140 should be installed to be located inside the basement outer wall 180 to be constructed in step (h). Thus, the mounting beam 140 is embedded so as not to protrude from the basement outer wall 180 frees the space utilization of the basement of the building. Furthermore, the mounting beam 140 is more preferably installed to be located in the center of the basement outer wall 180, which is the mounting beam 140 without being disturbed by the mounting beam 140 in the process of (h). This is because the wall reinforcement 181 can be continuously arranged with the gap therebetween.

(d)단계 : 수평보 설치- 도 1dStep (d): horizontal beam installation-FIG. 1d

내부기둥(120) 상호 간을 연결하는 내부수평보(150a)를 설치하고, 흙막이벽(110)을 향하는 외곽수평보(150b)를 내부기둥(120)에 연결하고 거치보(140)에 거치하면서 설치한다. 본 단계에서 내부수평보(150a)와 외곽수평보(150b)는 건물 지하부분의 구조체를 구성하는 영구 보가 된다.While installing the inner horizontal beams 150a connecting the inner pillars 120 to each other, and connecting the outer horizontal beams 150b facing the retaining wall 110 to the inner pillars 120 and mounting them on the mounting beam 140. Install. In this step, the inner horizontal beam 150a and the outer horizontal beam 150b become permanent beams that constitute the structure of the basement of the building.

내부수평보(150a)와 외곽수평보(150b)는 철골부재, PC부재, 철골과 PC 또는 RC의 복합부재 등으로 설치할 수 있으며, 다만 철골과 RC의 복합부재로 설치하는 경우에는 철골부분만 본 단계에서 설치하고 RC부분은 (f)단계에서 슬래브(160) 시 공과 함께 시공할 수 있다. 나아가 내부수평보(150a)와 외곽수평보(150b)는 모멘트에 대응하여 단부가 보강되는 형태로 설치 시공할 수 있다. 본 발명의 실시예에서는 H형강의 외곽수평보(150b)를 확인할 수 있다.The inner horizontal beam 150a and the outer horizontal beam 150b may be installed as a steel member, a PC member, a steel member and a composite member of a PC or RC, etc., but only when the steel member is installed as a composite member of steel and RC. The RC part can be installed at the stage and can be installed with the slab 160 construction in the step (f). Furthermore, the inner horizontal beam 150a and the outer horizontal beam 150b may be installed in a form in which an end portion is reinforced in response to a moment. In the embodiment of the present invention can check the outer horizontal beam (150b) of the H-beam.

(e)단계: 나뭇가지형 스틸프레임 설치- 도 1eStep (e): Installing a Twig Type Steel Frame-FIG. 1E

나뭇가지형 스틸프레임(200)을 외곽수평보(150b) 위에 거치하면서 설치한다. 나뭇가지형 스틸프레임(200)은 중앙에 위치한 중앙채널(210)과, 중앙채널(210)에서 양쪽으로 뻗어 나온 연결채널(220) 및 내민채널(230)을 기본 구성으로 하며, 중앙채널(210)이 큰 나무줄기가 되고 연결채널(220)과 내민채널(230)이 중앙채널(210)에서 양쪽으로 뻗어 나온 작은 나뭇가지가 됨에 따라 나뭇가지형 스틸프레임(200)이라 명명하고 있다. 다만 나뭇가지형 스틸프레임(200)은 양 측면판과 바닥판을 구비한 채널 부재를 기본 부재로 하여 조립되는 것인데, 양 측면판과 바닥판을 구비한 채널 부재는 기본적인 ㄷ자형 단면의 부재(통상의 채널 부재)는 물론 H형의 단면 부재(양 플랜지가 양 측면판이 되고 웨브가 바닥판이 됨)도 포괄하며, 형강, 철판 절곡, 철판 용접 등의 다양한 방법으로 제작하여 입수할 수 있다. 나뭇가지형 스틸프레임(200)은 각 구성부재들을 외곽수평보(150b) 위에서 직접 조립하면서 설치하는 것은 물론, 각 구성부재의 일부 또는 전부를 조립한 상태로 준비하여 설치할 수도 있다.It installs while mounting the twig-shaped steel frame 200 on the outer horizontal beam (150b). The twig-shaped steel frame 200 has a central channel 210 located in the center, a connection channel 220 and an imine channel 230 extending from both sides from the central channel 210 as a basic configuration, and the central channel 210. As the tree trunk is large and the connecting channel 220 and the inner channel 230 become small branches extending from both sides of the central channel 210, the tree-shaped steel frame 200 is named. However, the twig-shaped steel frame 200 is assembled by using a channel member having both side plates and a bottom plate as a base member, and the channel member having both side plates and a bottom plate is a member having a basic U-shaped cross section (usually Channel member), as well as H-shaped cross-section member (both flanges are both side plates and webs are bottom plates), and can be produced and obtained by various methods such as bending steel, sheet bending, and welding of steel sheets. The twig-shaped steel frame 200 may be installed while assembling each component directly on the outer horizontal beam 150b, and may be prepared and installed in a state in which some or all of the components are assembled.

나뭇가지형 스틸프레임(200)은 직접적으로는 흙막이벽(110)에서 (f)단계에서 시공할 슬래브(160)로 토압을 전달하는 토압전달체로서 역할하며, 간접적으로는 나 뭇가지와 나뭇가지 사이(곧 연결채널 사이와 내민채널 사이)의 빈 공간을 (h)단계에서 시공할 벽체철근(181)의 연속 배근공간과 벽체콘크리트(182)의 타설공간으로 제공하는 역할을 한다.Twig-type steel frame 200 directly serves as a earth pressure carrier for transmitting earth pressure to the slab 160 to be constructed in step (f) from the earth wall 110, indirectly between the branches and branches It serves to provide an empty space (between the connection channel and the imminent channel) to the continuous reinforcement space of the wall reinforcement 181 to be constructed in step (h) and the placing space of the wall concrete 182.

한편, 나뭇가지형 스틸프레임(200)은 안정적인 토압전달체가 되어야 하는데, 본 발명에서는 나뭇가지형 스틸프레임(200)이 안정적인 토압전달체가 되기 위한 구체적인 실현방안으로 세 가지 실시예를 제안하며, 이에 대한 자세한 사항은 후술한다(2a 내지 도 4d 참고).On the other hand, the twig-shaped steel frame 200 should be a stable earth pressure carrier, the present invention proposes three embodiments as a concrete implementation plan for the twig-shaped steel frame 200 to be a stable earth pressure carrier, for this Details will be described later (see 2a to 4d).

(f)단계 : 슬래브 시공- 도 1fStep (f): Slab Construction- Fig. 1f

내부수평보(150a)와 외곽수평보(150b) 위로 슬래브콘크리트(162)를 타설하면서 슬래브(160)를 시공한다. 이때 슬래브(160)는 나뭇가지형 스틸프레임(200)에서 연속적으로 이어져 일체화되도록 시공해야 한다. 그래야 슬래브(160)는 나뭇가지형 스틸프레임(200)과 함께 흙막이벽(110)을 지지하는 수평버팀대가 된다. 나뭇가지형 스틸프레임(200)과 슬래브(160)의 일체화 방식은 후술한다(2a 내지 도 4d 참고).The slab 160 is constructed while placing the slab concrete 162 on the inner horizontal beam 150a and the outer horizontal beam 150b. At this time, the slab 160 should be constructed so as to be continuously integrated in the tree-shaped steel frame 200 to be integrated. Thus, the slab 160 is a horizontal brace supporting the retaining wall 110 together with the twig-shaped steel frame 200. The integration method of the twig-shaped steel frame 200 and the slab 160 will be described later (see 2a to 4d).

슬래브(160)는 데크를 설치한 후 슬래브콘크리트(162)를 타설하거나 슬래브거푸집을 설치한 후 슬래브콘크리트(162)를 타설하는 방식으로 시공할 수 있으며, 구조계산에 따라 슬래브철근(161)을 적절히 배근하는 것은 물론이다. 슬래브거푸집은 슬래브(160)를 완성한 후 제거한다.The slab 160 can be constructed by placing the slab concrete 162 after installing the deck or by installing the slab concrete 162 and then placing the slab concrete 162, according to the structural calculation, the slab reinforcement (161) appropriately Of course, I'm going back. The slab formwork is removed after completing the slab 160.

(g)단계 : 반복 실시- 도 1g(g) step: repeated execution- FIG. 1g

상기 (b)단계 내지 (f)단계를 반복 실시한다. 최하층 바닥은 매트기초로 시공한다. 본 단계의 진행으로 지하외벽(180)을 제외한 지하부분의 골조가 완성된다. 즉, 건물 지하부분의 내부기둥(120)과 층간 보 및 층간 슬래브(160)가 완성되는 것이다.Steps (b) to (f) are repeated. The bottom floor is constructed with a mat base. By the progress of this step, the base frame is completed except for the basement outer wall 180. That is, the inner pillar 120 and the interlayer beam and the interlayer slab 160 of the basement of the building are completed.

(h)단계 : 지하외벽 시공- 도 1h(h) step: underground exterior wall construction- Fig. 1h

나뭇가지형 스틸프레임(200)에서 연결채널(220) 사이와 내민채널(230) 사이의 빈 공간을 통해 벽체철근(181)을 연속 배근하고 벽체콘크리트(182)를 타설하면서 지하외벽(180)을 시공한다. 본 단계의 진행으로 지하외벽(180)이 완성되며, 나뭇가지형 스틸프레임(200)은 벽체콘크리트(182)에 매입되어 일체화된다. 이로써 건물 지하부분의 모든 골조가 완성된다.In the twig-shaped steel frame 200, the reinforcement of the wall reinforcement 181 through the empty space between the connection channel 220 and the inner channel 230, and placing the concrete wall 182 while placing the outer concrete wall 180 Construct. Under the progress of this step, the basement outer wall 180 is completed, the twig-shaped steel frame 200 is embedded in the wall concrete 182 is integrated. This completes all the frames in the basement of the building.

도 2a 내지 도 2d는 본 발명에 따른 역타공법의 제1실시예를 도시하며, 제1실시예는 나뭇가지형 스틸프레임(200)만으로 토압을 전달하도록 구성한 방식이다.2a to 2d show a first embodiment of the reverse drilling method according to the present invention, the first embodiment is configured to transmit the earth pressure to the twig-shaped steel frame 200 only.

도 2a는 본 발명의 제1실시예에서 이용하는 나뭇가지형 스틸프레임(200)을 도시하는데, 보는 바와 같이 중앙채널(210), 연결채널(220), 내민채널(230), 연결스티프너(240), 엔드플레이트(250), 제1스터드(260)로 구성되며, 이와 같은 구성에 의해 나뭇가지형 스틸프레임(200)은 그 자체만으로 토압전달체로서 역할한다. 나뭇가지형 스틸프레임(200)은 설치장소에서의 요구내력에 맞게 구조설계하면서 적합 하게 각 구성부재의 단면과 강성을 설계하도록 하며, 다만 나뭇가지형 스틸프레임(200) 만으로 토압을 전달해야 하기 때문에 충분한 단면성능을 가지도록 설계한다. 가령 각 구성부재를 ㄷ형강 내지 H형강으로 구성하는 것이다.Figure 2a shows a twig-shaped steel frame 200 used in the first embodiment of the present invention, the center channel 210, the connection channel 220, the inner channel 230, the connection stiffener 240 as shown And, the end plate 250, the first stud 260 is composed of, by this configuration the twig-shaped steel frame 200 serves as a earth pressure carrier by itself. The twig-shaped steel frame 200 is designed to suit the required strength at the installation site, while properly designing the cross-section and rigidity of each component, but only because the twig-shaped steel frame 200 must deliver earth pressure Design to have sufficient cross section performance. For example, each constituent member is composed of c-beams or H-beams.

중앙채널(210)은 외곽수평보(150b) 위에 거치함으로써 설치되며, 지하외벽(180) 단면 내부에 위치시키면서 흙막이벽(110)을 따라 연속적으로 이어지게 배치되다. 연결채널(220)은 중앙채널(210)의 일 측면판과 흙막이벽(110)을 연결하도록 설치되며, 연결채널(220) 상호 간은 띄엄띄엄 배치된다. 내민채널(230)은 중앙채널(210)의 타 측면판에서 뻗어 나오도록 설치되며, 내민채널(230) 상호 간 띄엄띄엄 배치된다. 중앙채널(210), 연결채널(220), 내민채널(230)은 서로 용접 접합되는데, 중앙채널(210)과 내민채널(230)은 일정한 규격으로 준비하여 현장 또는 공장에서 용접하면 되며, 연결채널(220, 고정채널)은 균일하게 시공하지 못한 흙막이벽(110)의 시공오차를 유연하게 흡수할 수 있도록 현장에서 적절하게 재단하면서 용접하면 된다.The central channel 210 is installed by mounting on the outer horizontal beam 150b, and is disposed to be continuously connected along the retaining wall 110 while being positioned inside the cross section of the basement outer wall 180. The connection channel 220 is installed to connect one side plate and the retaining wall 110 of the central channel 210, and the connection channels 220 are spaced apart from each other. The inner channel 230 is installed so as to extend from the other side plate of the central channel 210, the inner channel 230 is spaced apart from each other. The central channel 210, the connection channel 220, the mining channel 230 is welded to each other, the central channel 210 and the mining channel 230 is prepared in a predetermined standard and welded in the field or factory, the connection channel 220, the fixed channel may be welded while cutting appropriately in the field so as to flexibly absorb the construction error of the earth wall 110 is not uniformly constructed.

연결스티프너(240)는 연결채널(220)의 측면판에서 내민채널(230)의 측면판으로 연속적으로 이어지게 위치시키면서 중앙채널(210)의 양 측면판 상호 간을 연결하도록 설치되는 구성으로, 연결스티프너(240)에 의해 연결채널(220)에서 중앙채널(210)을 거쳐 내민채널(230)로 안정적인 응력흐름이 형성된다. 연결스티프너(240)는 플레이트, 앵글 등 다양한 형태의 부재로 수평 또는 수직으로 설치될 수 있다. 엔드플레이트(250)는 내민채널(230)의 단부와 동일하거나 더 넓은 판면으로 마련되어 내민채널(230)의 단부를 폐쇄하도록 설치되는 구성이며, 엔드플레이 트(250)는 슬래브콘크리트(162) 타설과정에서 슬래브콘크리트(162)가 나뭇가지형 스틸프레임(200) 내부에 채워지는 것을 차단하는 역할을 함과 아울러 토압지지력을 슬래브(160)에서 나뭇가지형 스틸프레임(200)으로 안정적으로 전달하는 지압판으로 역할한다. 제1스터드(260)는 엔드플레이트(250)에 돌출 접합되는 구성으로, 제1스터드(260)에 의해 슬래브(160) 시공과정에서 나뭇가지형 스틸프레임(200)과 슬래브(160)가 일체화되며, 도 2a에서는 볼트 타입의 제1스터드(260)를 확인할 수 있다. 연결스티프너(240), 엔드플레이트(250), 제1스터드(260)도 용접하여 설치한다.The connection stiffener 240 is configured to connect the two side plates of the central channel 210 while continuously connecting to the side plate of the inner channel 230 from the side plate of the connection channel 220, the connection stiffener A stable stress flow is formed from the connection channel 220 through the central channel 210 by the 240 to the inner channel 230. The connection stiffener 240 may be installed horizontally or vertically with various types of members such as plates and angles. The end plate 250 is configured to be provided with the same or wider plate surface than the end of the inner channel 230 and is installed to close the end of the inner channel 230, and the end plate 250 is disposed of the slab concrete 162. At the slab concrete 162 serves to block the filling inside the twig-shaped steel frame 200, as well as acupressure plate to stably transfer earth pressure bearing force from the slab (160) to the twig-shaped steel frame (200) Role. The first stud 260 is configured to protrude and bond to the end plate 250, the twig-shaped steel frame 200 and the slab 160 is integrated in the construction process of the slab 160 by the first stud 260, In FIG. 2A, the first stud 260 of the bolt type may be confirmed. The connecting stiffener 240, the end plate 250, and the first stud 260 are also welded and installed.

도 2b는 도 2a의 나뭇가지형 스틸프레임(200)을 설치한 상태를 도시한다. 보는 바와 같이 나뭇가지형 스틸프레임(200)은 연결채널(220)을 흙막이벽(110)에 연결 설치하고, 중앙채널(210)을 외곽수평보(150b)에 거치하여 설치한다. 나아가 도 2b에서 보는 바와 같이 나뭇가지형 스틸프레임(200)에 제2스터드(270)를 더 접합할 수 있다. 제2스터드(270)는 중앙채널(210)의 내부 또는 외부에 돌출되게 접합 설치될 수 있으며, 제2스터드(270)에 의해 지하외벽(180) 시공과정에서 나뭇가지형 스틸프레임(200)과 지하외벽(180)이 일체화된다. 제2스터드(270)는 볼트, 플레이트, 라스 등 그 형태에 제한이 없으며, 도 2b에서는 볼트 타입의 제2스터드(270)가 중앙채널(210) 내부에 돌출 접합된 경우를 확인할 수 있다.2B illustrates a state in which the twig-shaped steel frame 200 of FIG. 2A is installed. As shown, the twig-shaped steel frame 200 is installed by connecting the connecting channel 220 to the retaining wall 110, and is installed by mounting the central channel 210 on the outer horizontal beam (150b). Furthermore, as shown in FIG. 2B, the second stud 270 may be further bonded to the twig-shaped steel frame 200. The second stud 270 may be installed to protrude to the inside or the outside of the central channel 210, the second steel stud 270 and the twig-shaped steel frame 200 during the construction of the basement outer wall 180 The basement outer wall 180 is integrated. The second stud 270 is not limited in the form of bolts, plates, laths, etc. In FIG. 2B, a case in which the bolt-type second studs 270 protrude and join the inside of the central channel 210 may be confirmed.

한편, 내민채널(230)은 도 2b에서와 같이 그 단부가 지하외벽선과 일치하도 록 설치할 수 있을 뿐만 아니라, 도시하지 않았지만 지하외벽선 내부는 물론 외부에 위치하도록 설치하는 것도 가능하다. 다만 내민채널(230)의 단부가 지하외벽선 내부에 위치한다면 슬래브(160)는 그 일부가 지하외벽(180) 시공 전에 지하외벽선 내부에까지 연장 시공될 것이고, 내민채널(230)의 단부가 지하외벽선 외부에 위치한다면 내민채널(230)은 슬래브(160) 시공으로 슬래브(160)에 매입될 것이다.On the other hand, the inner channel 230, as shown in Figure 2b not only can be installed so that its end coincides with the subterranean outer wall line, although not shown, it is also possible to be installed so as to be located in the outer and outer subterranean wall line as well. However, if the end of the inner channel 230 is located in the basement outer wall line, the slab 160 will be a part of the extension to the inside of the outer wall line before the construction of the basement outer wall 180, the end of the end channel 230 is underground If it is located outside the outer wall line, the internal channel 230 will be embedded in the slab 160 by the slab 160 construction.

도 2c는 도 2b에서와 같이 나뭇가지형 스틸프레임(200)을 설치한 후에 슬래브(160)를 시공한 상태를 도시한다. 보는 바와 같이 나뭇가지형 스틸프레임(200)의 엔드플레이트(250)를 경계로 슬래브콘크리트(162)를 타설하면, 나뭇가지형 스틸프레임(200)의 제1스터드(260)가 슬래브콘크리트(162)에 매입되면서 나뭇가지형 스틸프레임(200)과 슬래브(160)는 일체화된다. 이로써 나뭇가지형 스틸프레임(200)과 슬래브(160)의 합성에 의해 흙막이벽(110)의 지지구조가 완성된다.FIG. 2C illustrates a state in which the slab 160 is constructed after installing the twig-shaped steel frame 200 as shown in FIG. 2B. As shown, when the slab concrete 162 is poured around the end plate 250 of the twig-shaped steel frame 200, the first stud 260 of the twig-shaped steel frame 200 is slab concrete 162. While being embedded in the twig-shaped steel frame 200 and the slab 160 is integrated. As a result, the supporting structure of the retaining wall 110 is completed by synthesizing the twig-shaped steel frame 200 and the slab 160.

도 2d는 도 2c에서와 같은 슬래브(160) 시공을 역타로 지하 최하층까지 반복 실시한 후에 지하외벽(180)을 시공한 상태를 도시한다. 보는 바와 같이 나뭇가지형 스틸프레임의 연결채널(220) 사이와 내민채널(230) 사이의 빈 공간을 통해 벽체철근(181)을 연속 배근하고 벽체콘크리트(182)를 타설한다. 벽체콘크리트(182)는 나뭇가지형 스틸프레임(200) 내부에도 타설되며, 이로써 나뭇가지형 스틸프레임(200)은 지하외벽(180)에 매입되어 지하외벽(180)과 일체화된다. 특히 나뭇가지형 스틸프레임(200)에 제2스터드(270)가 마련되었다면 나뭇가지형 스틸프레임(200)과 지하외벽(180)의 일체화는 강화된다.FIG. 2D illustrates a state in which the basement outer wall 180 is constructed after repeating the construction of the slab 160 as shown in FIG. 2C to the basement lower floor. As shown, the wall reinforcement 181 is continuously reinforced and the wall concrete 182 is poured through the empty space between the connection channel 220 of the twig-shaped steel frame and the inner channel 230. The wall concrete 182 is also placed inside the twig-shaped steel frame 200, whereby the twig-shaped steel frame 200 is embedded in the basement outer wall 180 is integrated with the basement outer wall 180. In particular, if the second stud 270 is provided in the twig-shaped steel frame 200, the integration of the twig-shaped steel frame 200 and the basement outer wall 180 is strengthened.

도 3a 내지 도 3d는 본 발명에 따른 역타공법의 제2실시예를 도시하며, 제2실시예는 나뭇가지형 스틸프레임(200)과 슬래브콘크리트(162)의 합성으로 토압을 전달하도록 구성한 방식이다.3a to 3d show a second embodiment of the reverse drilling method according to the present invention, the second embodiment is configured to deliver the earth pressure by the combination of the twig-shaped steel frame 200 and the slab concrete 162 .

도 3a는 본 발명의 제2실시예에서 이용하는 나뭇가지형 스틸프레임(200)을 도시하는데, 보는 바와 같이 중앙채널(210), 연결채널(220), 내민채널(230)로 구성되며, 이와 같은 구성의 나뭇가지형 스틸프레임(200) 내부에 슬래브콘크리트(162)가 채워짐에 따라 토압전달체로서 안정적으로 역할하게 된다. 중앙채널(210), 연결채널(220), 내민채널(230)은 앞서 제1실시예에서 설명한 바와 동일하다. 다만 제2실시예는 나뭇가지형 스틸프레임(200)과 슬래브콘크리트(162)의 합성에 의해 토압전달체로서 역할하게 되므로, 제1실시예에 비해 나뭇가지형 스틸프레임(200)의 단면 성능을 줄여 적용할 수 있다. 가령 나뭇가지형 스틸프레임(200)에서 슬래브콘크리트와 합성되는 채널 부재를 플레이트 절곡형 ㄷ채널로 절곡한 것으로 구성하는 것이다. 도 3a의 나뭇가지형 스틸프레임(200)은 연결채널(220)을 H형강으로 구성하면서 중앙채널(210)과 내민채널(230)을 플레이트 절곡형 ㄷ채널로 구성한 예인데, 중앙채널(210)과 내민채널(230)에만 슬래브콘크리트가 타설되어 합성되도록 제안된 형태이며, 플레이트 절곡형 ㄷ채널로 구성한 내민채널(230)이 H형강으로 구성한 연결채널(220)에 비해 단면성능이 작으므로 내민채널(230)이 더 많이 마련되고 있다. 도 3a의 나뭇가지형 스틸프레임(200)은 연결채널(220)에도 슬래브콘크리트(162)가 타설되는 형태로 적절하게 변형할 수 있음은 물론이다.Figure 3a shows a twig-shaped steel frame 200 used in the second embodiment of the present invention, as shown is composed of a central channel 210, a connection channel 220, the inner channel 230, such as As the slab concrete 162 is filled in the twig-shaped steel frame 200 of the configuration, it serves as a stable earth pressure carrier. The central channel 210, the connection channel 220, and the mining channel 230 are the same as described in the first embodiment. However, since the second embodiment serves as a earth pressure carrier by synthesizing the twig-shaped steel frame 200 and the slab concrete 162, the cross-sectional performance of the twig-shaped steel frame 200 is reduced compared to the first embodiment. Applicable For example, the channel member synthesized with the slab concrete in the twig-shaped steel frame 200 is configured to be bent into a plate bent c-channel. The twig-shaped steel frame 200 of FIG. 3A is an example in which the central channel 210 and the internal channel 230 are formed of a plate bent type c channel while the connecting channel 220 is formed of an H-beam, and the center channel 210 is formed. Slab concrete is poured and synthesized only in the endogenous channel 230 and the endogenous channel because the cross-sectional performance is smaller than that of the connecting channel 220 composed of H-shaped steel. More is being prepared. The twig-shaped steel frame 200 of FIG. 3a may be appropriately modified in a form in which the slab concrete 162 is poured into the connection channel 220.

한편, 제2실시예에서 나뭇가지형 스틸프레임(200)은 도 3a에서와 같이 폼타이(280)와 제2스터드(270)를 더 포함하여 구성할 수 있다. 폼타이(280)는 중앙채널(210)의 바닥판에서 떠 있게 위치시키면서 중앙채널(210)의 양 측면판을 연결하도록 설치되는 부재인데, 중앙채널(210) 내부에 슬래브콘크리트(162)를 채우는 과정에서 슬래브콘크리트(162)의 채움을 원활하게 함과 동시에 중앙채널(210)의 변형을 억제한다. 폼타이(280)는 볼트, 플레이트 등 다양한 형태로 설치할 수 있으며, 도 3a에서는 플레이트를 수직으로 용접하여 설치한 상태를 확인할 수 있다. 제2스터드(270)는 제1실시예에서와 마찬가지로 지하외벽(180) 시공과정에서 나뭇가지형 스틸프레임(200)과 지하외벽(180)을 일체화하기 위해 마련되는 부재인데, 도 3a에서는 플레이트 타입의 제2스터드(270)가 중앙채널(210) 하부에 외부로 돌출 접합된 경우를 확인할 수 있다.Meanwhile, in the second embodiment, the twig type steel frame 200 may further include a form tie 280 and a second stud 270 as shown in FIG. 3A. The form tie 280 is a member which is installed to connect both side plates of the central channel 210 while floating in the bottom plate of the central channel 210, filling the slab concrete 162 inside the central channel 210. While smoothing the filling of the slab concrete 162 in the process and suppresses the deformation of the central channel (210). The form tie 280 may be installed in various forms such as a bolt and a plate, and in FIG. 3A, the form tie 280 may be checked by vertically welding the plate. As in the first embodiment, the second stud 270 is a member provided to integrate the twig-shaped steel frame 200 and the basement outer wall 180 in the process of constructing the basement outer wall 180, and in FIG. 3A, a plate type. The second stud 270 of the protruding outwardly bonded to the lower center channel 210 can be confirmed.

나아가 제2실시예에서 나뭇가지형 스틸프레임(200)은 도 3a에서와 같이 중앙채널(210)의 타 측면판이 일 측면판보다 낮은 높이로 마련할 수도 있다. 이는 슬래브철근(161)의 정착을 고려한 것이다(도 3c 참조).Furthermore, in the second embodiment, the twig-shaped steel frame 200 may have another side plate of the central channel 210 at a height lower than that of one side plate as shown in FIG. 3A. This is to consider the fixing of the slab reinforcing bars 161 (see Fig. 3c).

도 3b는 도 3a의 나뭇가지형 스틸프레임(200)을 설치한 상태를 도시한다. 보는 바와 같이 나뭇가지형 스틸프레임(200)에서 연결채널(220)을 흙막이벽(110)에 연결 설치하고, 중앙채널(210)을 외곽수평보(150b)에 거치하여 설치한다.3B illustrates a state in which the twig-shaped steel frame 200 of FIG. 3A is installed. As shown, the twig-shaped steel frame 200 is installed by connecting the connection channel 220 to the retaining wall 110, and is mounted by mounting the central channel 210 on the outer horizontal beam (150b).

도 3c는 도 3b에서와 같이 나뭇가지형 스틸프레임(200)을 설치한 후에 슬래브(160)를 시공한 상태를 도시한다. 보는 바와 같이 나뭇가지형 스틸프레임(200) 의 내부를 포함하여 슬래브콘크리트(162)를 타설한다. 도 3c에서는 도 3a의 나뭇가지형 스틸프레임(200)을 적용한 결과 중앙채널(210)과 내민채널(230)에만 슬래브콘크리트가 타설된 상태를 확인할 수 있다. 이로써 슬래브(160)가 흙막이벽(110)에서부터 연속적으로 이어지도록 형성되며, 결국 흙막이벽(110)의 지지구조가 완성된다. 특히 나뭇가지형 스틸프레임(200)에서 중앙채널(210)의 타 측면판이 낮은 높이로 마련되었다면, 슬래브(160) 시공과정에서 슬래브철근(161)을 배근함에 있어 나뭇가지형 스틸프레임 중앙채널(210)의 타 측면판을 넘어 중앙채널(210) 내부에까지 도달하도록 배근한다. 이는 슬래브철근(161)의 정착을 위함이다.FIG. 3c illustrates a state in which the slab 160 is constructed after the twig-shaped steel frame 200 is installed as in FIG. 3b. As shown, the slab concrete 162, including the inside of the twig-shaped steel frame 200 is poured. In FIG. 3C, as a result of applying the twig type steel frame 200 of FIG. 3A, the slab concrete is poured into only the central channel 210 and the imminent channel 230. As a result, the slab 160 is continuously formed from the retaining wall 110, and thus, the supporting structure of the retaining wall 110 is completed. In particular, if the other side plate of the central channel 210 in the twig-shaped steel frame 200 is provided at a low height, in the slab 160 construction process in the reinforcement of the slab reinforcing bars 161, the central steel channel of the twig-type steel frame 210 Beyond the other side plate of) to reach inside the central channel 210. This is for the settlement of the slab reinforcement (161).

도 3d는 도 3c에서와 같은 슬래브(160) 시공을 역타로 지하 최하층까지 반복 실시한 후에 지하외벽(180)을 시공한 상태를 도시한다. 보는 바와 같이 나뭇가지형 스틸프레임(200)의 연결채널(220) 사이와 내민채널(230) 사이의 빈 공간을 통해 벽체철근(181)을 연속 배근하고 벽체콘크리트(182)를 타설한다. 이로써 나뭇가지형 스틸프레임(200)은 지하외벽(180)에 매입되어 지하외벽(180)과 일체화된다. 특히 나뭇가지형 스틸프레임(200)에 제2스터드(270)가 마련되었다면 나뭇가지형 스틸프레임(200)과 지하외벽(180)의 일체화는 강화된다.FIG. 3d illustrates a state in which the basement outer wall 180 is constructed after repeating the construction of the slab 160 as shown in FIG. As shown, the reinforcement of the wall reinforcement 181 is continuously placed through the empty space between the connection channel 220 of the tree-shaped steel frame 200 and the internal channel 230, and the wall concrete 182 is poured. Thus, the twig-shaped steel frame 200 is embedded in the basement outer wall 180 is integrated with the basement outer wall 180. In particular, if the second stud 270 is provided in the twig-shaped steel frame 200, the integration of the twig-shaped steel frame 200 and the basement outer wall 180 is strengthened.

도 4a 내지 도 4d는 본 발명에 따른 역타공법의 제3실시예를 도시하며, 앞서 살펴본 제2실시예를 변형한 방식이다.4A to 4D show a third embodiment of the reverse punching method according to the present invention, which is a modification of the second embodiment described above.

도 4a는 본 발명의 제3실시예에서 이용하는 나뭇가지형 스틸프레임(200)을 도시하는데, 연결스티프너(240)가 없다는 점에서 차이가 있을 뿐 전체적으로 제1실 시예에서 이용하는 나뭇가지형 스틸프레임과 동일하다. 다시 말해, 제3실시예에서 나뭇가지형 스틸프레임(200)은, 중앙채널(210), 연결채널(220), 내민채널(230), 엔드플레이트(250), 제1스터드(260)를 포함하여 구성된다. 이와 같은 구성의 나뭇가지형 스틸프레임(200)은 중앙채널(210)과 연결채널(220)에만 슬래브콘크리트(162)가 타설되어 합성되도록 제안된 형태이며, 도 3a의 나뭇가지형 스틸프레임(200)과 유사하게 연결채널(220)에 슬래브콘크리트(162)가 타설되지 않는 형태로 적절하게 변형할 수 있음은 물론이다. 나아가 제3실시예의 나뭇가지형 스틸프레임(200)은 제2스터드(270)와 폼타이(280)를 더 포함하여 구성될 수 있으며, 제2스터드(270)와 폼타이(280)는 앞서 제2실시예에서 설명한 바와 동일한 구성이다.Figure 4a shows the twig-shaped steel frame 200 used in the third embodiment of the present invention, there is a difference in that there is no connection stiffener 240, and the twig-type steel frame used in the first embodiment as a whole same. In other words, in the third embodiment, the twig-shaped steel frame 200 includes a central channel 210, a connection channel 220, an inner channel 230, an end plate 250, and a first stud 260. It is configured by. The twig-shaped steel frame 200 of such a configuration is a form proposed to be synthesized by pouring the slab concrete 162 only in the central channel 210 and the connection channel 220, the twig-shaped steel frame 200 of Figure 3a Similarly, the slab concrete 162 in the connection channel 220 can be appropriately modified in a form that is not poured. Furthermore, the twig-shaped steel frame 200 of the third embodiment may further include a second stud 270 and a form tie 280, and the second stud 270 and the form tie 280 may be formed of the first stud 270. The configuration is the same as described in the second embodiment.

도 4b는 도 4a의 나뭇가지형 스틸프레임(200)을 설치한 상태를 도시한다. 보는 바와 같이 나뭇가지형 스틸프레임(200)에서 연결채널(220)을 흙막이벽(110)에 연결 설치하고, 중앙채널(210)을 외곽수평보(150b)에 거치하여 설치한다.4B illustrates a state in which the twig-shaped steel frame 200 of FIG. 4A is installed. As shown, the twig-shaped steel frame 200 is installed by connecting the connection channel 220 to the retaining wall 110, and is mounted by mounting the central channel 210 on the outer horizontal beam (150b).

도 4c는 도 4b에서와 같이 나뭇가지형 스틸프레임(200)을 설치한 후에 슬래브(160)를 시공한 상태를 도시한다. 보는 바와 같이 나뭇가지형 스틸프레임(200)의 내부를 포함하여 슬래브콘크리트(162)를 타설한다. 도 4c에서는 도 4a의 나뭇가지형 스틸프레임(200)을 적용한 결과 중앙채널(210)과 연결채널(220)에만 슬래브콘크리트(162)가 타설된 상태를 확인할 수 있다. 이로써 슬래브(160)가 흙막이벽(110)에서부터 연속적으로 이어지도록 형성되며, 결국 흙막이벽(110)의 지지구조가 완성된다. 4C illustrates a state in which the slab 160 is constructed after installing the twig-shaped steel frame 200 as in FIG. 4B. As shown, the slab concrete 162, including the inside of the twig-shaped steel frame 200 is poured. In FIG. 4C, as a result of applying the twig type steel frame 200 of FIG. 4A, the slab concrete 162 may be placed only on the center channel 210 and the connection channel 220. As a result, the slab 160 is continuously formed from the retaining wall 110, and thus, the supporting structure of the retaining wall 110 is completed.

도 4d는 도 4c에서와 같은 슬래브(160) 시공을 역타로 지하 최하층까지 반복 실시한 후에 지하외벽(180)을 시공한 상태를 도시한다. 지하외벽(180)은 앞서 살펴본 제2실시예의 경우와 동일한 방식으로 완성된다.FIG. 4D illustrates a state in which the basement outer wall 180 is constructed after repeating the construction of the slab 160 as shown in FIG. 4C to the lowest basement floor. The basement outer wall 180 is completed in the same manner as in the case of the second embodiment described above.

이상에서 본 발명은 구체적인 실시예를 참조하여 상세히 설명되었으나, 실시예는 본 발명을 예시하기 위한 것일 뿐이므로, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 치환, 부가 및 변형된 실시 형태들 역시 아래에 첨부한 특허청구범위에 의하여 정하여지는 본 발명의 보호범위에 속한다고 할 것이다.The present invention has been described in detail above with reference to specific embodiments, but the embodiments are only for illustrating the present invention, and thus the embodiments substituted, added, and modified within the scope without departing from the spirit of the present invention are also described below. It will be said to belong to the protection scope of the present invention as defined by the claims appended hereto.

도 1a 내지 도 1h는 본 발명에 따른 역타공법의 시공순서를 도시한다.1A to 1H show the construction sequence of the reverse punching method according to the present invention.

도 2a 내지 도 2d는 본 발명에 따른 역타공법의 제1실시예를 도시하는데, 채널에 의한 나뭇가지형 스틸프레임을 도시한 사시도(2a), 나뭇가지형 스틸프레임이 설치된 상태를 도시한 상세도(2b), 슬래브 시공 후의 상태를 도시한 상세도(2c), 지하외벽 시공 후의 상태를 도시한 상세도(2d)이다. Figures 2a to 2d shows a first embodiment of the reverse drilling method according to the present invention, a perspective view (2a) showing a twig-shaped steel frame by the channel, a detailed view showing a state in which the twig-shaped steel frame is installed (2b), detailed drawing (2c) which shows the state after slab construction, and detailed drawing (2d) which shows the state after construction of an underground outer wall.

도 3a 내지 도 3d는 본 발명에 따른 역타공법의 제2실시예를 도시하는데, 채널에 의한 나뭇가지형 스틸프레임을 도시한 사시도(3a), 나뭇가지형 스틸프레임이 설치된 상태를 도시한 상세도(3b), 슬래브 시공 후의 상태를 도시한 상세도(3c), 지하외벽 시공 후의 상태를 도시한 상세도(3d)이다. Figure 3a to 3d shows a second embodiment of the reverse drilling method according to the present invention, a perspective view (3a) showing a twig-shaped steel frame by the channel, a detailed view showing a state where the twig-shaped steel frame is installed (3b), detailed drawing (3c) which shows the state after slab construction, and detailed drawing (3d) which shows the state after construction of an underground outer wall.

도 4a 내지 도 4d는 본 발명에 따른 역타공법의 제3실시예를 도시하는데, 채널에 의한 나뭇가지형 스틸프레임을 도시한 사시도(4a), 나뭇가지형 스틸프레임이 설치된 상태를 도시한 상세도(4b), 슬래브 시공 후의 상태를 도시한 상세도(4c), 지하외벽 시공 후의 상태를 도시한 상세도(4d)이다. Figures 4a to 4d shows a third embodiment of the reverse punching method according to the present invention, a perspective view (4a) showing a twig-shaped steel frame by the channel, a detailed view showing a state where the twig-shaped steel frame is installed (4b), detailed drawing (4c) which shows the state after slab construction, and detailed drawing (4d) which shows the state after construction of an underground outer wall.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

110: 흙막이벽 110a: 엄지말뚝110: retaining wall 110a: thumb pile

120: 내부기둥120: inner pillar

130: 브라켓130: bracket

140: 거치보 140: pedestal

150a: 내부수평보 150b: 외곽수평보150a: horizontal level beam 150b: horizontal level beam

160: 슬래브160: slab

180: 지하외벽180: outer wall

200: 나뭇가지형 스틸프레임200: twig steel frame

210: 중앙채널 220: 연결채널210: center channel 220: connection channel

230: 내민채널 240: 연결스티프너230: Immunization channel 240: Connection stiffener

250: 엔드플레이트 260: 제1스터드250: end plate 260: first stud

270: 제2스터드 280: 폼타이270: second stud 280: form tie

Claims (7)

건물의 지하부분으로 직접 토압을 지지해가면서 굴착하여 건물의 지하부분을 시공하는 역타공법으로서, It is a reverse drilling method that constructs the underground part of the building by excavating while supporting the earth pressure directly to the underground part of the building. (a)흙막이벽(110)을 시공하고, 흙막이벽(110) 내부로 내부기둥(120)을 시공하는 단계;(a) constructing the mud wall 110, and constructing the inner pillar 120 into the mud wall 110; (b)흙막이벽(110) 내측 지반을 굴착하고, 흙막이벽(110)에 브라켓(130)을 고정 설치하는 단계;(b) excavating the inner ground of the retaining wall 110 and fixing the bracket 130 to the retaining wall 110; (c)브라켓(130) 상호 간을 연결하는 거치보(140)를 브라켓(130) 위에 거치하면서 설치하되, 거치보(140)가 하기 (h)단계에서 시공할 지하외벽(180)의 내부에 위치하도록 설치하는 단계;(c) the bracket 130 is installed while mounting on the bracket 130 to connect the mounting beam 140 to each other, the mounting beam 140 to the inside of the basement outer wall 180 to be constructed in the following (h) step Installing to locate; (d)내부기둥(120) 상호 간을 연결하는 내부수평보(150a)를 설치하고, 흙막이벽(110)을 향하는 외곽수평보(150b)를 내부기둥(120)에 연결하고 거치보(140)에 거치하면서 설치하는 단계;(d) Installing the inner horizontal beam (150a) to connect the inner column (120) with each other, connect the outer horizontal beam (150b) facing the earth wall 110 to the inner column (120) and mounting beam 140 Installing while mounting on; (e)양 측면판과 바닥판을 구비한 채널 부재로 조립되는 나뭇가지형 스틸프레임(200)을 외곽수평보(150b) 위에 거치하면서 설치하는 단계;(e) installing the twig-shaped steel frame 200 assembled with a channel member having both side plates and a bottom plate on the outer horizontal beam 150b; (f)내부수평보(150a)와 외곽수평보(150b) 위로 슬래브콘크리트(162)를 타설하면서 슬래브(160)를 시공하되, 나뭇가지형 스틸프레임(200)에서 슬래브(160)로 연속적으로 이어지도록 시공하는 단계;(f) Constructing the slab 160 while placing the slab concrete 162 on the inner horizontal beam 150a and the outer horizontal beam 150b, but continuously from the twig steel frame 200 to the slab 160 Constructing to carry; (g)상기 (b)단계 내지 (f)단계를 반복 실시하는 단계;(g) repeating steps (b) to (f); (h)나뭇가지형 스틸프레임(200) 사이의 빈 공간을 통해 벽체철근(181)을 배근하고 벽체콘크리트(182)를 타설하면서 지하외벽(180)을 시공하는 단계;를 포함하여 이루어지되,(h) reinforcing the wall reinforcement 181 through the empty space between the tree-shaped steel frame 200 and constructing the outer wall 180 while pouring the wall concrete 182; 상기 (e)단계는, 외곽수평보(150b) 위에 거치하여 설치되며 (h)단계에서 시공할 지하외벽(180) 단면 내부에 위치시키면서 흙막이벽(110)을 따라 연속적으로 이어지게 배치되는 중앙채널(210); 중앙채널(210)의 일 측면판과 흙막이벽(110)을 연결하도록 설치되며 상호 간 띄엄띄엄 배치되는 연결채널(220); 중앙채널(210)의 타 측면판에서 뻗어 나오도록 설치되며 상호 간 띄엄띄엄 배치되는 내민채널(230); 연결채널(220)의 측면판에서 내민채널(230)의 측면판으로 연속적으로 이어지게 위치시키면서 중앙채널(210)의 양 측면판 상호 간을 연결하도록 설치되는 연결스티프너(240); 내민채널(230)의 단부와 동일하거나 더 넓은 판면으로 마련되어 내민채널(230)의 단부를 폐쇄하도록 설치되는 엔드플레이트(250); 엔드플레이드(250)에 돌출 접합되는 제1스터드(260);로 구성되는 나뭇가지형 스틸프레임(200)을 설치하면서 이루어지며,The step (e) is mounted on the outer horizontal beam (150b) is installed in the center channel (12) while being located in the cross section of the underground wall (180) to be constructed in step (h) to be continuously connected along the retaining wall (110) 210); A connection channel 220 installed to connect one side plate and the retaining wall 110 of the central channel 210 and spaced apart from each other; An internal channel 230 installed to extend from the other side plate of the central channel 210 and spaced apart from each other; A connection stiffener 240 which is installed to connect both side plates of the central channel 210 while being continuously connected to the side plate of the channel 23 in the side plate of the connection channel 220; An end plate 250 provided with a plate surface that is the same as or wider than the end of the inner channel 230 and installed to close the end of the inner channel 230; The first stud 260 is protruded and bonded to the end plate 250; is made while installing a twig-shaped steel frame 200 consisting of, 상기 (f)단계는, 나뭇가지형 스틸프레임의 제1스터드(260)가 매입되도록 나뭇가지형 스틸프레임의 엔드플레이트(250)를 경계로 슬래브콘크리트(162)를 타설하면서 이루어지며,The step (f) is made while placing the slab concrete 162 around the end plate 250 of the branched steel frame so that the first stud 260 of the branched steel frame is embedded, 상기 (h)단계는, 나뭇가지형 스틸프레임의 연결채널(220) 사이와 내민채널(230) 사이의 빈 공간을 통해 벽체철근(181)을 연속 배근하고 벽체콘크리트(182)를 타설하면서 이루어지는 것을 특징으로 하는 채널에 의한 나뭇가지형 스틸프레임을 이용한 역타공법.The step (h) is made by continuously reinforcing the wall reinforcement 181 through the empty space between the connection channel 220 and the inner channel 230 of the twig-shaped steel frame and pouring the wall concrete 182 Reverse punching method using twig-shaped steel frame by the channel. 건물의 지하부분으로 직접 토압을 지지해가면서 굴착하여 건물의 지하부분을 시공하는 역타공법으로서, It is a reverse drilling method that constructs the underground part of the building by excavating while supporting the earth pressure directly to the underground part of the building. (a)흙막이벽(110)을 시공하고, 흙막이벽(110) 내부로 내부기둥(120)을 시공하는 단계;(a) constructing the mud wall 110, and constructing the inner pillar 120 into the mud wall 110; (b)흙막이벽(110) 내측 지반을 굴착하고, 흙막이벽(110)에 브라켓(130)을 고정 설치하는 단계;(b) excavating the inner ground of the retaining wall 110 and fixing the bracket 130 to the retaining wall 110; (c)브라켓(130) 상호 간을 연결하는 거치보(140)를 브라켓(130) 위에 거치하면서 설치하되, 거치보(140)가 하기 (h)단계에서 시공할 지하외벽(180) 내부에 위치하도록 설치하는 단계;(c) the bracket 130 is installed while mounting the bracket 140 to connect with each other on the bracket 130, the mounting beam 140 is located inside the basement outer wall 180 to be constructed in the following (h) step Installing to enable; (d)내부기둥(120) 상호 간을 연결하는 내부수평보(150a)를 설치하고, 흙막이벽(110)을 향하는 외곽수평보(150b)를 내부기둥(120)에 연결하고 거치보(140)에 거치하면서 설치하는 단계;(d) Installing the inner horizontal beam (150a) to connect the inner column (120) with each other, connect the outer horizontal beam (150b) facing the earth wall 110 to the inner column (120) and mounting beam 140 Installing while mounting on; (e)양 측면판과 바닥판을 구비한 채널 부재로 조립되는 나뭇가지형 스틸프레임(200)을 외곽수평보(150b) 위에 거치하면서 설치하는 단계;(e) installing the twig-shaped steel frame 200 assembled with a channel member having both side plates and a bottom plate on the outer horizontal beam 150b; (f)내부수평보(150a)와 외곽수평보(150b) 위로 슬래브콘크리트(162)를 타설하면서 슬래브(160)를 시공하되, 나뭇가지형 스틸프레임(200)에서 슬래브(160)로 연속적으로 이어지도록 시공하는 단계;(f) Constructing the slab 160 while placing the slab concrete 162 on the inner horizontal beam 150a and the outer horizontal beam 150b, but continuously from the twig steel frame 200 to the slab 160 Constructing to carry; (g)상기 (b)단계 내지 (f)단계를 반복 실시하는 단계;(g) repeating steps (b) to (f); (h)나뭇가지형 스틸프레임(200) 사이의 빈 공간을 통해 벽체철근(181)을 배근하고 벽체콘크리트(182)를 타설하면서 지하외벽(180)을 시공하는 단계;를 포함하여 이루어지되,(h) reinforcing the wall reinforcement 181 through the empty space between the tree-shaped steel frame 200 and constructing the outer wall 180 while pouring the wall concrete 182; 상기 (e)단계는, 외곽수평보(150b) 위에 거치하여 설치되며 (h)단계에서 시공할 지하외벽(180) 단면 내부에 위치시키면서 흙막이벽(110)을 따라 연속적으로 이어지게 배치되는 중앙채널(210); 중앙채널(210)의 일 측면판과 흙막이벽(110)을 연결하도록 설치되며 상호 간 띄엄띄엄 배치되는 연결채널(220); 중앙채널(210)의 타 측면판에서 뻗어 나오도록 설치되며 상호 간 띄엄띄엄 배치되는 내민채널(230);로 구성되는 나뭇가지형 스틸프레임(200)을 설치하면서 이루어지며,The step (e) is mounted on the outer horizontal beam (150b) is installed in the center channel (12) while being located in the cross section of the underground wall (180) to be constructed in step (h) to be continuously connected along the retaining wall 110 ( 210); A connection channel 220 installed to connect one side plate and the retaining wall 110 of the central channel 210 and spaced apart from each other; It is installed while extending from the other side plate of the central channel (210) and the internal channel (230) spaced apart from each other; is made while installing a twig-shaped steel frame 200, 상기 (f)단계는, 나뭇가지형 스틸프레임(200)에서 중앙채널(210)과 내민채널(230) 내부에 필수적으로 슬래브콘크리트(162)를 타설하는 한편 연결채널(220) 내부에 선택적으로 슬래브콘크리트(162)를 타설하면서 이루어지며,In the step (f), the slab concrete 162 is poured into the central channel 210 and the inner channel 230 in the twig-shaped steel frame 200, and the slab is selectively disposed in the connection channel 220. Is made while pouring concrete 162, 상기 (h)단계는, 나뭇가지형 스틸프레임의 연결채널(220) 사이와 내민채널(230) 사이의 빈 공간을 통해 벽체철근(181)을 연속 배근하고 벽체콘크리트(182)를 타설하면서 이루어지는 것을 특징으로 하는 채널에 의한 나뭇가지형 스틸프레임을 이용한 역타공법.The step (h) is made by continuously reinforcing the wall reinforcement 181 through the empty space between the connection channel 220 and the inner channel 230 of the twig-shaped steel frame and pouring the wall concrete 182 Reverse punching method using twig-shaped steel frame by the channel. 건물의 지하부분으로 직접 토압을 지지해가면서 굴착하여 건물의 지하부분을 시공하는 역타공법으로서, It is a reverse drilling method that constructs the underground part of the building by excavating while supporting the earth pressure directly to the underground part of the building. (a)흙막이벽(110)을 시공하고, 흙막이벽(110) 내부로 내부기둥(120)을 시공하는 단계;(a) constructing the mud wall 110, and constructing the inner pillar 120 into the mud wall 110; (b)흙막이벽(110) 내측 지반을 굴착하고, 흙막이벽(110)에 브라켓(130)을 고정 설치하는 단계;(b) excavating the inner ground of the retaining wall 110 and fixing the bracket 130 to the retaining wall 110; (c)브라켓(130) 상호 간을 연결하는 거치보(140)를 브라켓(130) 위에 거치하면서 설치하되, 거치보(140)가 하기 (h)단계에서 시공할 지하외벽(180) 내부에 위치하도록 설치하는 단계;(c) the bracket 130 is installed while mounting the bracket 140 to connect with each other on the bracket 130, the mounting beam 140 is located inside the basement outer wall 180 to be constructed in the following (h) step Installing to enable; (d)내부기둥(120) 상호 간을 연결하는 내부수평보(150a)를 설치하고, 흙막이벽(110)을 향하는 외곽수평보(150b)를 내부기둥(120)에 연결하고 거치보(140)에 거치하면서 설치하는 단계;(d) Installing the inner horizontal beam (150a) to connect the inner column (120) with each other, connect the outer horizontal beam (150b) facing the earth wall 110 to the inner column (120) and mounting beam 140 Installing while mounting on; (e)양 측면판과 바닥판을 구비한 채널 부재로 조립되는 나뭇가지형 스틸프레임(200)을 외곽수평보(150b) 위에 거치하면서 설치하는 단계;(e) installing the twig-shaped steel frame 200 assembled with a channel member having both side plates and a bottom plate on the outer horizontal beam 150b; (f)내부수평보(150a)와 외곽수평보(150b) 위로 슬래브콘크리트(162)를 타설하면서 슬래브(160)를 시공하되, 나뭇가지형 스틸프레임(200)에서 슬래브(160)로 연속적으로 이어지도록 시공하는 단계;(f) Constructing the slab 160 while placing the slab concrete 162 on the inner horizontal beam 150a and the outer horizontal beam 150b, but continuously from the twig steel frame 200 to the slab 160 Constructing to carry; (g)상기 (b)단계 내지 (f)단계를 반복 실시하는 단계;(g) repeating steps (b) to (f); (h)나뭇가지형 스틸프레임(200) 사이의 빈 공간을 통해 벽체철근(181)을 배근하고 벽체콘크리트(182)를 타설하면서 지하외벽(180)을 시공하는 단계;를 포함하여 이루어지되,(h) reinforcing the wall reinforcement 181 through the empty space between the tree-shaped steel frame 200 and constructing the outer wall 180 while pouring the wall concrete 182; 상기 (e)단계는, 외곽수평보(150b) 위에 거치하여 설치되며 (h)단계에서 시공할 지하외벽(180) 단면 내부에 위치시키면서 흙막이벽(110)을 따라 연속적으로 이어지게 배치되는 중앙채널(210); 중앙채널(210)의 일 측면판과 흙막이벽(110)을 연결하도록 설치되며 상호 간 띄엄띄엄 배치되는 연결채널(220); 중앙채널(210)의 타 측면판에서 뻗어 나오도록 설치되며 상호 간 띄엄띄엄 배치되는 내민채널(230); 내민채널(230)의 단부와 동일하거나 더 넓은 판면으로 마련되어 내민채널(230)의 단부를 폐쇄하도록 설치되는 엔드플레이트(250); 엔드플레이드(250)에 돌출 접합되는 제1스터드(260);로 구성되는 나뭇가지형 스틸프레임(200)을 설치하면서 이루어지며,The step (e) is mounted on the outer horizontal beam (150b) is installed in the center channel (12) while being located in the cross section of the underground wall (180) to be constructed in step (h) to be continuously connected along the retaining wall (110) 210); A connection channel 220 installed to connect one side plate and the retaining wall 110 of the central channel 210 and spaced apart from each other; An internal channel 230 installed to extend from the other side plate of the central channel 210 and spaced apart from each other; An end plate 250 provided with a plate surface that is the same as or wider than the end of the inner channel 230 and installed to close the end of the inner channel 230; The first stud 260 is protruded and bonded to the end plate 250; is made while installing a twig-shaped steel frame 200 consisting of, 상기 (f)단계는, 나뭇가지형 스틸프레임(200)에서 중앙채널(210) 내부에 필수적으로 슬래브콘크리트(162)를 타설하는 한편 연결채널(220) 내부에 선택적으로 슬래브콘크리트(162)를 타설함과 아울러 제1스터드(260)가 매입되도록 나뭇가지형 스틸프레임의 엔드플레이트(250)를 경계로 슬래브콘크리트(162)를 타설하면서 이루어지며,In the step (f), the slab concrete 162 is poured into the central channel 210 in the tree-shaped steel frame 200, and the slab concrete 162 is selectively poured into the connection channel 220. In addition, the first stud 260 is embedded while placing the slab concrete 162 to the border of the end plate 250 of the twig-shaped steel frame, 상기 (h)단계는, 나뭇가지형 스틸프레임의 연결채널(220) 사이와 내민채널(230) 사이의 빈 공간을 통해 벽체철근(181)을 연속 배근하고 벽체콘크리트(182)를 타설하면서 이루어지는 것을 특징으로 하는 채널에 의한 나뭇가지형 스틸프레임을 이용한 역타공법.The step (h) is made by continuously reinforcing the wall reinforcement 181 through the empty space between the connection channel 220 and the inner channel 230 of the twig-shaped steel frame and pouring the wall concrete 182 Reverse punching method using twig-shaped steel frame by the channel. 제2항 또는 제3항에서,The method of claim 2 or 3, 상기 (e)단계는, 중앙채널(210)의 바닥판에서 떠 있게 위치시키면서 중앙채널(210)의 양 측면판을 연결하도록 설치되는 폼타이(280);가 더 포함되어 구성되는 나뭇가지형 스틸프레임(200)을 설치하면서 이루어지며,The step (e), the form-tied 280 is installed to connect both side plates of the central channel 210 while floating in the bottom plate of the central channel 210; It is made while installing the frame 200, 상기 (f)단계는, 상기 나뭇가지형 스틸프레임의 폼타이(280)가 매입되도록 슬래브콘크리트(162)를 타설하면서 이루어지는 것을 특징으로 하는 채널에 의한 나뭇가지형 스틸프레임을 이용한 역타공법.The step (f) is a reverse punching method using a twig-shaped steel frame by the channel, characterized in that the slab concrete 162 is poured so that the form tie 280 of the twig-shaped steel frame is embedded. 제1항 내지 제3항 중 어느 한 항에서,The method according to any one of claims 1 to 3, 상기 (e)단계는, 중앙채널(210)의 내부 또는 외부에 돌출되게 접합 설치되는 제2스터드(270);가 더 포함되어 구성되는 나뭇가지형 스틸프레임(200)을 설치하면서 이루어지되, The step (e) is made while installing the twig-shaped steel frame 200 further comprises; a second stud 270 that is bonded to protrude in or out of the central channel 210, 상기 (h)단계는, 상기 나뭇가지형 스틸프레임의 제2스터드(270)가 매입되도록 벽체콘크리트(182)를 타설하면서 이루어지는 것을 특징으로 하는 채널에 의한 나뭇가지형 스틸프레임을 이용한 역타공법.The step (h) is a reverse punching method using a twig-shaped steel frame by the channel, characterized in that the wall concrete 182 is poured so that the second stud 270 of the twig-shaped steel frame is embedded. 제5항에서,In claim 5, 상기 나뭇가지형 스틸프레임의 제2스터드(270)는, 볼트 타입, 플레이트 타 입, 라스 타입으로 마련되는 것을 특징으로 하는 채널에 의한 나뭇가지형 스틸프레임을 이용한 역타공법.The second stud 270 of the twig-type steel frame, bolt type, plate type, lath type, the reverse drilling method using a twig-type steel frame by the channel, characterized in that provided. 제1항 내지 제3항 중 어느 한 항에서,The method according to any one of claims 1 to 3, 상기 (e)단계는, 중앙채널(210)의 타 측면판이 일 측면판보다 낮은 높이로 마련되는 나뭇가지형 스틸프레임(200)을 설치하면서 이루어지며,In the step (e), the other side plate of the central channel 210 is made while installing a twig-shaped steel frame 200 is provided at a lower height than one side plate, 상기 (f)단계는, 슬래브철근(161)이 나뭇가지형 스틸프레임의 중앙채널(210)의 타 측면판을 넘어 중앙채널(210) 내부에 도달하도록 배근하면서 이루어지는 것을 특징으로 하는 채널에 의한 나뭇가지형 스틸프레임을 이용한 역타공법.Step (f), the slab reinforcing bar 161 is made through the channel, characterized in that the reinforcement to reach the inside of the central channel 210 beyond the other side plate of the central channel 210 of the twig-shaped steel frame Reverse punching method using branched steel frame.
KR1020090068810A 2009-05-18 2009-07-28 Top-down construction method using steel frame by channel KR100938918B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
PCT/KR2010/003108 WO2010134731A2 (en) 2009-05-18 2010-05-17 Top-down construction method using a branch-type steel frame with channels for the continuous construction of an underground retaining wall

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
KR1020090042901 2009-05-18
KR20090042901 2009-05-18
KR20090056504 2009-06-24
KR1020090056504 2009-06-24

Publications (1)

Publication Number Publication Date
KR100938918B1 true KR100938918B1 (en) 2010-01-27

Family

ID=41810290

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090068810A KR100938918B1 (en) 2009-05-18 2009-07-28 Top-down construction method using steel frame by channel

Country Status (2)

Country Link
KR (1) KR100938918B1 (en)
WO (1) WO2010134731A2 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101034853B1 (en) 2010-06-22 2011-05-17 (주)씨엠파트너스건축사사무소 Top-down construction method by whole support of retaining wall and form corresponding to uneven surface for using in the same
KR101169462B1 (en) 2012-03-08 2012-07-30 (주)엠씨에스에스티기술사사무소 Top-down construction method using post member
KR101198286B1 (en) 2010-09-15 2012-11-07 주식회사 액트파트너 Non-wale strut system for top-down construction and top-down construction method thereby
KR200470708Y1 (en) 2012-08-09 2014-01-07 주식회사 씨엠파트너스건축사사무소 A steel frame having water stop for transferring earth pressure on retaining wall
KR101421648B1 (en) * 2012-09-25 2014-07-22 (주)바로건설기술 Underground retaining wall supporting structure and construction method thereof
KR20200122037A (en) 2019-04-17 2020-10-27 에스케이건설주식회사 The construction method using a exterio wall of undergound structure
KR20210088850A (en) * 2020-01-07 2021-07-15 (주)한국건설공법 Top-down construction method
KR20220014113A (en) 2020-07-28 2022-02-04 에스케이에코플랜트(주) The construction method of underground structure using foundation of existing undergound structure

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102561390B (en) * 2010-12-17 2016-01-27 上海市电力公司 The application of contrary sequence method technique in the structure construction of underground substation
CN103882868B (en) * 2014-03-11 2017-09-12 中国建筑第八工程局有限公司 Bored concrete pile encloses the unilateral formwork supporting structure and construction method of purlin in going along with sb. to guard him
CN110670598A (en) 2019-07-24 2020-01-10 青岛理工大学 Cold joint treatment structure and method for secant pile construction
CN110409460A (en) * 2019-08-07 2019-11-05 上海建工二建集团有限公司 Temporary plugging device and method applied to foundation pit engineering support structure leakage emergency
CN110670632B (en) * 2019-10-06 2021-07-09 湖北工业大学 Construction method for horizontal construction joint of side wall of underground structure reverse construction method
CN111764397A (en) * 2020-05-28 2020-10-13 浙江土工岩土科技有限公司 Underground diaphragm wall plugging device and method
CN114635430B (en) * 2022-03-28 2023-12-26 广州一建建设集团有限公司 Construction process for large-depth half-reverse excavation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09235741A (en) * 1996-03-01 1997-09-09 Fujita Corp Construction method of underground external wall
KR20080098262A (en) * 2007-05-04 2008-11-07 (주)씨.에스 구조 엔지니어링 Non-support construction method using the deckplate for wall girder
KR20080100740A (en) * 2007-05-14 2008-11-19 (주) 씨엠파트너스 건축사사무소 Strut system of temporary plate with opening supporting temporary retaining wall and subgrade external wall construction method utilizing the same
KR20090029993A (en) * 2007-09-19 2009-03-24 주식회사 한미파슨스건축사사무소 Underground structure and its construction method with retaining wall supported by rigid diaphragm

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09235741A (en) * 1996-03-01 1997-09-09 Fujita Corp Construction method of underground external wall
KR20080098262A (en) * 2007-05-04 2008-11-07 (주)씨.에스 구조 엔지니어링 Non-support construction method using the deckplate for wall girder
KR20080100740A (en) * 2007-05-14 2008-11-19 (주) 씨엠파트너스 건축사사무소 Strut system of temporary plate with opening supporting temporary retaining wall and subgrade external wall construction method utilizing the same
KR20090029993A (en) * 2007-09-19 2009-03-24 주식회사 한미파슨스건축사사무소 Underground structure and its construction method with retaining wall supported by rigid diaphragm

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101034853B1 (en) 2010-06-22 2011-05-17 (주)씨엠파트너스건축사사무소 Top-down construction method by whole support of retaining wall and form corresponding to uneven surface for using in the same
KR101198286B1 (en) 2010-09-15 2012-11-07 주식회사 액트파트너 Non-wale strut system for top-down construction and top-down construction method thereby
KR101169462B1 (en) 2012-03-08 2012-07-30 (주)엠씨에스에스티기술사사무소 Top-down construction method using post member
KR200470708Y1 (en) 2012-08-09 2014-01-07 주식회사 씨엠파트너스건축사사무소 A steel frame having water stop for transferring earth pressure on retaining wall
KR101421648B1 (en) * 2012-09-25 2014-07-22 (주)바로건설기술 Underground retaining wall supporting structure and construction method thereof
KR20200122037A (en) 2019-04-17 2020-10-27 에스케이건설주식회사 The construction method using a exterio wall of undergound structure
KR20210088850A (en) * 2020-01-07 2021-07-15 (주)한국건설공법 Top-down construction method
KR102362257B1 (en) * 2020-01-07 2022-02-11 (주)한국건설공법 Top-down construction method
KR20220014113A (en) 2020-07-28 2022-02-04 에스케이에코플랜트(주) The construction method of underground structure using foundation of existing undergound structure

Also Published As

Publication number Publication date
WO2010134731A3 (en) 2011-01-27
WO2010134731A2 (en) 2010-11-25
WO2010134731A9 (en) 2011-03-24

Similar Documents

Publication Publication Date Title
KR100938918B1 (en) Top-down construction method using steel frame by channel
KR100788623B1 (en) Top-down method using precast-concrete colum
KR101331261B1 (en) Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
KR100531385B1 (en) Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
KR101687495B1 (en) Partial top-down construction method for building underground structures
KR20090094971A (en) Under ground top-down method
KR100831332B1 (en) Underground retaining wall for public works and method for constructing the same
KR100313720B1 (en) Composite Underground Structure Construction Method
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR101051978B1 (en) Basement structure construction method using PC member
KR20210088850A (en) Top-down construction method
KR101182704B1 (en) Construction method of undergroud structure using PHC pile
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR20060107638A (en) Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same
KR101631447B1 (en) Top-Down method of underground structure using the CFT and the Composite Beam
KR101198286B1 (en) Non-wale strut system for top-down construction and top-down construction method thereby
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR20110052360A (en) Downward construction method of underground structure that enables continuous basement wall using non-wale and diaphragm action of concrete slab
KR20100113957A (en) Joint structure and method for constructing slab of underground structures using the same
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
KR20080103260A (en) Reinforcing bar assembly for separate concrete pours and strut system method utilizing the same
KR101485563B1 (en) The horizontal structural frame
JP2018168561A (en) Underground structure and method of constructing underground structure

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
N231 Notification of change of applicant
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
J204 Request for invalidation trial [patent]
J204 Request for invalidation trial [patent]
J204 Request for invalidation trial [patent]
J301 Trial decision

Free format text: TRIAL DECISION FOR INVALIDATION REQUESTED 20100324

Effective date: 20111007

Free format text: TRIAL DECISION FOR INVALIDATION REQUESTED 20100427

Effective date: 20111007

Free format text: TRIAL DECISION FOR INVALIDATION REQUESTED 20100227

Effective date: 20111007

Free format text: TRIAL NUMBER: 2010100000503; TRIAL DECISION FOR INVALIDATION REQUESTED 20100227

Effective date: 20111007

Free format text: TRIAL NUMBER: 2010100001044; TRIAL DECISION FOR INVALIDATION REQUESTED 20100427

Effective date: 20111007

Free format text: TRIAL NUMBER: 2010100000733; TRIAL DECISION FOR INVALIDATION REQUESTED 20100324

Effective date: 20111007

FPAY Annual fee payment

Payment date: 20130109

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20131224

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20150116

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20160112

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170117

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20180209

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20191021

Year of fee payment: 10

R401 Registration of restoration