KR102102593B1 - constructing level tunnel connecting part of vertical structure and apparatus thereof - Google Patents

constructing level tunnel connecting part of vertical structure and apparatus thereof Download PDF

Info

Publication number
KR102102593B1
KR102102593B1 KR1020180011719A KR20180011719A KR102102593B1 KR 102102593 B1 KR102102593 B1 KR 102102593B1 KR 1020180011719 A KR1020180011719 A KR 1020180011719A KR 20180011719 A KR20180011719 A KR 20180011719A KR 102102593 B1 KR102102593 B1 KR 102102593B1
Authority
KR
South Korea
Prior art keywords
formwork
descending
vertical
concrete
support
Prior art date
Application number
KR1020180011719A
Other languages
Korean (ko)
Other versions
KR20190092676A (en
Inventor
고엄식
김선우
Original Assignee
주식회사 네오시티
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 네오시티 filed Critical 주식회사 네오시티
Priority to KR1020180011719A priority Critical patent/KR102102593B1/en
Publication of KR20190092676A publication Critical patent/KR20190092676A/en
Application granted granted Critical
Publication of KR102102593B1 publication Critical patent/KR102102593B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

본 발명은 수직구의 굴착과 동시에 현장에서 콘크리트 타설을 통해 완성되는 일정높이의 수직구 벽체를 지상에서 수직구 하부로 하강시키는 하향식 공법에 적용되는 수직구 구조물의 수평터널 연결부 성형장치에 관한 것이다.
본 발명에 따른 수직구 구조물의 수평터널 연결부 성형장치는 바닥에 설치되는 가설구조물(100)과, 상기 가설구조물에 승강가능하게 설치되며 거푸집 패널(230)을 포함하는 콘크리트 거푸집(200)과, 상기 콘크리트 거푸집에 설치되어 콘크리트 거푸집을 통해 성형된 수직구 구조물의 벽체를 하강시키는 하강유도부재(230)와, 상기 가설구조물(100)과 콘크리트 거푸집(200) 사이에 설치되어 상기 거푸집 패널(230)을 포함한 콘크리트 거푸집(200)을 승강시키는 승강부재(300)와, 상기 콘크리트 거푸집(200)의 내부에 밀착되게 위치되는 수평터널 연결용 거푸집패널(400)과, 상기 하강유도부재(230)를 통해 콘크리트 거푸집(200)의 내부에 설치되어 상기 수평터널 연결용 거푸집패널(400)을 일정높이로 지지하는 지지대(270)를 포함하며; 상기 하강유도부재(230)는 가설구조물(100)에 수직상태로 지지되는 복수개의 외측수직지지대(210)와, 상기 각 외측수직지지대의 안쪽에 외측수직지지대와 연결되게 수직상태로 지지되는 복수개의 내측수직지지대(220)와, 상기 각 외측수직지지대(210)와 내측수직지지대(220) 사이에 수직상태로 고정된 하강유압잭(261)과, 상기 하강유압잭에 결합된 하강잭로드(262)와, 상기 하강잭로드의 하단에 고정된 하부브라켓(263)으로 구성되고; 상기 승강부재(300)는 상기 하강유도부재(230)의 구성요소인 각 외측수직지지대(210)의 외측부에 수직상태로 고정된 상승유압잭(310)과, 상기 승강유압잭에 하단이 가설구조물에 지지된 상태로 결합된 승강잭로드(320)로 구성됨을 특징으로 한다.
The present invention relates to an apparatus for forming a horizontal tunnel connection part of a vertical sphere structure applied to a top-down method of descending a vertical sphere wall of a predetermined height from the ground to a lower vertical sphere at the same time as excavation of the vertical sphere through concrete pouring in the field.
The apparatus for forming the horizontal tunnel connection part of the vertical sphere structure according to the present invention includes a temporary structure 100 installed on the floor, a concrete formwork 200 including a formwork panel 230 that is removably installed on the temporary structure, and the A falling induction member 230 installed in a concrete formwork and descending a wall of a vertical sphere structure formed through a concrete formwork, and installed between the temporary structure 100 and the concrete formwork 200 to install the formwork panel 230 The lifting member 300 for elevating the concrete formwork 200 included, the concrete panel 200 for the horizontal tunnel connection formwork located in close contact with the inside of the concrete formwork 200, and the concrete through the descending induction member 230 It is installed inside the formwork 200 and includes a support 270 to support the horizontal tunnel connection formwork panel 400 to a predetermined height; The descending induction member 230 includes a plurality of outer vertical supports 210 supported vertically on the temporary structure 100, and a plurality of supported vertically connected to the outer vertical supports inside each outer vertical support. An inner vertical support 220, a lower hydraulic jack 261 fixed in a vertical state between each outer vertical support 210 and an inner vertical support 220, and a falling jack rod 262 coupled to the descending hydraulic jack , Consisting of a lower bracket 263 fixed to the lower end of the descending jack rod; The elevating member 300 has a rising hydraulic jack 310 fixed vertically to an outer portion of each outer vertical support 210, which is a component of the descending induction member 230, and a lower structure supported by the lifting hydraulic jack on a temporary structure. It is characterized in that it consists of a lifting jack rod 320 coupled to the state.

Description

수직구 구조물의 수평터널 연결부 성형장치{constructing level tunnel connecting part of vertical structure and apparatus thereof}Forming device for horizontal tunnel connecting part of vertical sphere structure

본 발명은 수직구의 굴착과 동시에 현장에서 콘크리트 타설을 통해 완성되는 일정높이의 수직구 벽체를 지상에서 수직구 하부로 하강시키는 하향식 공법에 적용되는 수직구 구조물의 수평터널 연결부 성형장치에 관한 것이다.The present invention relates to a horizontal tunnel connecting part forming apparatus of a vertical sphere structure applied to a top-down method of descending a vertical sphere wall of a predetermined height from the ground to a lower vertical sphere at the same time as excavation of the vertical sphere through concrete pouring in the field.

일반적으로 지하철 선로 공사시 열차의 운행시 발생되는 바람에 포함된 각종 유해가스 및 미세먼지로 인하여 지하터널 및 승강장의 공기가 오염되는 것을 방지하기 위하여 각 전철역을 비롯하여 지하선로를 따라 일정구간 마다 지하터널 및 승강장내의 공기를 지상으로 배출시키거나 지상의 공기를 지하터널 및 승강장 내로 공급할 수 있는 통로역할을 하는 수직구 구조물을 필수적으로 갖추도록 되어 있다.In general, in order to prevent the air in the underground tunnel and the platform from being polluted by various harmful gases and fine dust contained in the wind generated during the operation of the train during the construction of the subway line, the underground tunnel is used for each section along each subway station and underground line. And a vertical sphere structure that essentially serves as a passage for discharging air from the platform to the ground or supplying ground air to the underground tunnel and platform.

이러한 수직구 구조물은 터파기 후 외곽부에 가설 흙막이벽을 설치하고, 가설 흙막이벽에 걸리는 하중을 버팀대로 지탱하면서 지하 맨 하부쪽에서부터 상부측으로 구축해 올라가는 전통적인인 공법을 통해 구조물을 시공하게 되나, 수시로 드나드는 공사차량의 정차로 인해 교통체증을 유발하고 인근 주변에 피해를 주기 때문에 대도시와 같이 건물이 부지경계선 가까이 근접하게 위치되어 있는 경우에 상기 공법을 적용하는데 많은 문제점이 있고, 가설흙막이 벽 설치시에 함께 설치되는 버팀대는 구조물 공사로 인한 공정의 복잡성과 작업의 위험성과 폐기물의 발생 등 여러가지 문제점들이 발생하기 때문에 최근에는 토지 이용효율을 높이면서 공기가 빠르고 경제적이며, 구조적으로 안전한 신개념의 지하구조물의 구축방법이 많이 제안되고 있다.These vertical sphere structures are constructed through a traditional method that builds and builds from the bottom to the top of the basement while installing a temporary barrier wall on the outer part after digging and supporting the load on the temporary barrier wall as a support, but often Because of the traffic jam caused by the stop of the construction vehicle and damage to the surrounding area, there are many problems in applying the above method when the building is located close to the site boundary, such as a large city, and when installing a temporary mud wall The props installed together in the construction process have many problems such as process complexity, work risk, and waste generation due to the construction of the structure, and recently, the air is fast, economical, and structurally safe. Many construction methods have been proposed.

이들 신공법들의 일예로서, 하향식 공법(Top-Down Method)이 알려져 있다.As an example of these new construction methods, a top-down method is known.

상기 하향식 공법은 굴착공사 이전에 지하외부 벽체(지중연속벽: 슬러리월(Slurry Wall))와 지하층 기둥(Bored Pile)을 선 시공한 후, 단계별로 지하층 슬래브와 토공사를 위해서 아래로 반복해 가면서 지하구조물을 형성하는 공법이다.The top-down method is to construct a basement outer wall (underground continuous wall: slurry wall) and a bored pile before excavation, and then repeat it downward for the basement slab and earthwork step by step. It is a method of forming structures.

이러한 하향식 공법은 하부로부터 상부측으로 구축해 올라가는 전통적인 시공과는 반대로 아래로 시공하므로 다운워드 공법(Downward Method), 역타(逆打)공법 또는 탑 다운공법(Top Down method)이라고도 한다. 상기 하향식 공법은 기존의오픈 컷(open cut) 공법으로 계획하기 어려운 대단면, 대심도 굴착에 안정적이며,1층 바닥이 선시공 되기 때문에 작업장의 조기확보가 가능하여 강우 및 강설시에도시공할 수 있는 전천후 공법이라는 측면에서 도심지의 공사에 적합한 공법으로 각광을 받고 있다. 특히, 지상과 지하가 동시에 진행될 수 있어 공기단축의 효과도 대할 수 있다.Such a top-down construction method is also called a downward method, a reverse method, or a top down method because it is constructed downward from the lower side to the traditional construction which is built up from the lower side. The top-down construction method is stable for excavation of large cross-sections and large depths that are difficult to plan with the existing open cut method, and since the floor on the first floor is pre-constructed, it is possible to secure an early work place, so that it can be constructed during rainfall and snowfall. In terms of all-weather construction method, it is spotlighted as a construction method suitable for downtown construction. In particular, the ground and the basement can be carried out at the same time, it can also treat the effect of air shortening.

본 출원인은 이러한 상기 하향식 공법을 이용한 수직구 구조물의 시공방법 및 장치를 특허출원 제10-2017-0041727호를 통해 제안한 바 있다.The applicant has proposed the construction method and apparatus of the vertical sphere structure using the above-described top-down method through patent application No. 10-2017-0041727.

상기 하향식 공법을 이용한 수직구 구조물의 시공방법 및 장치에 따르면, 지상에 가설구조물을 설치한 후에 상기 가설구조물에 콘크리트 거푸집을 설치한 상태에서 상기 가설구조물의 내부에서 수직구를 굴착함과 동시에 상기 콘크리트 거푸집을 통해 수직구 벽체를 성형하도록 되어 있으며, 상기 수직구 벽체를 상기 콘크리트 거푸집에 설치된 하강유도부재를 통해 수직구 내부로 일정 깊이 하강시킨 후에 상기 가설구조물에 고정된 승강부재를 이용하여 콘크리트 거푸집을 상승시켜 수평터널 연결용 수직구 벽체의 상단에 배근작업을 실시하도록 되어 있다.According to the construction method and apparatus of the vertical sphere structure using the top-down construction method, after installing the temporary structure on the ground, while the concrete formwork is installed in the temporary structure, the vertical sphere is excavated inside the temporary structure and at the same time, the concrete The vertical sphere wall is formed through a formwork, and after the vertical sphere wall is lowered to a certain depth inside the vertical sphere through a descending induction member installed in the concrete formwork, the concrete formwork is used by using a lifting member fixed to the temporary structure. It is designed to perform reinforcement work on the top of the vertical wall for connecting the horizontal tunnel by raising it.

그리고 다시 콘크리트 거푸집을 하강시켜 수직구 벽체의 상단에 상부수직구 벽체를 성형한 다음, 상기 상부수직구 벽체를 수직구와 함께 동반 하강시키는 과정을 반복하면서 시공이 이루어지도록 되어 있다.Then, the concrete formwork is lowered to form the upper vertical wall on the top of the vertical wall, and then the construction is performed while repeating the process of descending the upper vertical wall together with the vertical wall.

한편, 상기 수직구 구조물에는 지하시설물에 화재와 같은 긴급대피 상황이 발생할 경우 다수의 지하시설물 이용자들이 수직구 구조물을 통해 지상으로 탈출할 수 있도록 수평터널이 구비되는데, 이러한 수평터널은 수직구 구조물을 완성한 다음 수직구 구조물 내부로 굴착기를 내려보내 시공하는 방식으로 진행된다.On the other hand, the vertical structure is provided with a horizontal tunnel so that a number of underground facilities users can escape to the ground through the vertical structure when an emergency evacuation situation such as a fire occurs in the underground structure. After completion, the construction is carried out by sending the excavator down into the vertical structure.

그러나, 이와 같은 방식으로 수평터널을 시공하게 되면, 굴착기가 수평터널연결부를 형성시키기 위하여 이미 완성된 수직구 구조물의 벽면 일부를 파쇄하는 과정에서 수직구조물에 충격이 발생하게 되고, 이 충격으로 인하여 수직구조물의 구조적 안전성이 크게 저하되는 심각한 문제가 발생된다.However, when a horizontal tunnel is constructed in this way, an impact occurs on the vertical structure in the process of crushing a part of the wall of the vertical sphere structure that the excavator has already completed to form the horizontal tunnel connection. A serious problem arises in that the structural safety of the structure is significantly reduced.

아울러, 수평터널의 연결부에 대한 마감작업도 추가로 이루어져야 하므로 공기가 지연되는 문제도 발생된다.In addition, since the finishing work for the connection part of the horizontal tunnel has to be additionally performed, there is a problem in that air is delayed.

본 발명은 상기한 문제점들을 해결하기 위해 안출된 것으로서, 수직구조물의 구조적 안전성에 영향을 끼치지 않으면서 수평터널 연결부에 대한 일련의 작업과정을 신속하게 수행하여 작업능률이 향상되도록 하는 수직구 구조물의 수평터널 연결부 성형장치를 제공하는 데 그 목적이 있다.The present invention has been devised to solve the above-mentioned problems, and it is a vertical sphere structure that improves work efficiency by quickly performing a series of work processes for a horizontal tunnel connection without affecting the structural safety of the vertical structure. The aim is to provide a horizontal tunnel connection forming device.

상기 목적을 달성하기 위해, 본 발명의 수직구 구조물의 수평터널 연결부 성형장치는 바닥에 설치되는 가설구조물과, 상기 가설구조물에 승강가능하게 설치되며 거푸집 패널을 포함하는 콘크리트 거푸집과, 상기 콘크리트 거푸집에 설치되어 콘크리트 거푸집을 통해 성형된 수직구 구조물의 벽체를 하강시키는 하강유도부재와, 상기 가설구조물과 콘크리트 거푸집 사이에 설치되어 상기 거푸집 패널을 포함한 콘크리트 거푸집을 승강시키는 승강부재와, 상기 콘크리트 거푸집의 내부에 밀착되게 위치되는 수평터널 연결용 거푸집패널과, 상기 하강유도부재를 통해 콘크리트 거푸집의 내부에 설치되어 상기 수평터널 연결용 거푸집패널을 일정높이로 지지하는 지지대를 포함하며; 상기 하강유도부재는 가설구조물에 수직상태로 지지되는 복수개의 외측수직지지대와, 상기 외측수직지지대의 안쪽에 각 외측수직지지대와 연결되게 수직상태로 지지되는 복수개의 내측수직지지대와, 상기 각 외측수직지지대와 내측수직지지대 사이에 수직상태로 고정된 하강유압잭과, 상기 하강유압잭에 결합된 하강잭로드와, 상기 하강잭로드의 하단에 고정된 하부브라켓으로 구성되고; 상기 승강부재는 상기 하강유도부재의 구성요소인 각 외측수직지지대의 외측부에 수직상태로 고정된 승강유압잭과, 상기 승강유압잭에 하단이 가설구조물에 지지된 상태로 결합된 승강잭로드로 구성된다.In order to achieve the above object, the apparatus for forming the horizontal tunnel connection part of the vertical sphere structure of the present invention includes a temporary structure installed on the floor, a concrete formwork including a formwork panel, which is removably installed on the temporary structure, and the concrete formwork. A descending induction member installed to descend the wall of the vertical sphere structure formed through the concrete formwork, and a lifting member installed between the temporary structure and the concrete formwork to elevate the concrete formwork including the formwork panel, and the interior of the concrete formwork It includes a formwork panel for horizontal tunnel connection that is located in close contact with, and is installed inside the concrete formwork through the descending induction member to support the horizontal tunnel connection formwork panel to a predetermined height; The descending induction member includes a plurality of outer vertical supports supported vertically to the temporary structure, a plurality of inner vertical supports supported vertically to be connected to each outer vertical support inside the outer vertical supports, and each outer vertical It consists of a descending hydraulic jack fixed vertically between a support and an inner vertical support, a descending jack rod coupled to the descending hydraulic jack, and a lower bracket fixed to the lower end of the descending jack rod; The elevating member is composed of an elevating hydraulic jack fixed vertically to an outer portion of each outer vertical support, which is a component of the descending induction member, and an elevating jack rod coupled with the lower end of the elevating hydraulic jack supported on a temporary structure.

삭제delete

삭제delete

또한, 상기 수평터널 연결용 거푸집패널은 상하로 분할 형성되는데, 이 경우 상기 수평터널 연결용 거푸집패널의 내측에는 다수의 강도보강용 지지프레임이 설치되는 것이 바람직하다.In addition, the formwork panel for connecting the horizontal tunnel is formed to be divided up and down. In this case, it is preferable that a plurality of strength reinforcement support frames are installed inside the formwork panel for connecting the horizontal tunnel.

삭제delete

상기와 같이 구성된 본 발명은 콘크리트 거푸집 내부에 수평터널 연결용 거푸집패널을 안착시킨 다음 상기 콘크리트 거푸집과 수평터널 연결용 거푸집패널의 사이로 콘크리트를 타설하여 수평터널 연결용 수직구 벽체를 계속해서 반복적으로 성형시키기 때문에 수직구 구조물인 수평터널 벽체의 성형을 위한 콘크리트 양생과정 중 양생이 완료될 때까지 기다리지 않고 다음 벽체를 성형하는 작업을 연속해서 수행하게 되므로 작업성이 매우 우수하게 되고, 이에 따라 작업능률이 향상되어 수직구 구조물의 수평터널 연결부 작업을 포함한 전체적인 작업을 빠른시간 내에 완료할 수 있게되는 효과가 있다.The present invention configured as described above is to continuously form a vertical tunnel wall for horizontal tunnel connection by placing concrete in the formwork panel for horizontal tunnel connection inside the concrete formwork and then pouring concrete between the concrete formwork and the formwork panel for horizontal tunnel connection. Therefore, during the concrete curing process for forming the horizontal tunnel wall, which is a vertical sphere structure, the work of forming the next wall is continuously performed without waiting for curing to be completed. It has the effect of being able to complete the entire work in a short time, including the work of connecting the horizontal tunnel of the vertical sphere structure.

도 1은 본 발명에 따라 지상에 가설구조물과 콘크리트 거푸집이 설치된 상태를 나타내는 사시도.
도 2는 도 1의 단면사시도.
도 3a 및 3b는 각각 본 발명에 따라 수평터널 연결용 수직구 하부벽체가 성형되는 과정을 나타내는 단면사시도.
도 4a 및 4b는 각각 본 발명에 따라 수평터널 연결용 수직구 중앙벽체가 성형되는 과정을 나타내는 단면사시도.
도 5a 및 5b는 각각 본 발명에 따라 수평터널 연결용 수직구 상부벽체가 성형되는 과정을 나타내는 단면사시도.
도 6a 및 6b는 각각 본 발명에 따라 수평터널 연결용 수직구 벽체의 상단에 수직구 벽체가 일체로 성형되는 과정을 나타내는 단면사시도.
도 7은 본 발명에 따라 목표로 하는 깊이까지 수직구 벽체가 설치된 상태를 나타내는 단면도.
1 is a perspective view showing a temporary structure and a concrete formwork installed on the ground according to the present invention.
Figure 2 is a cross-sectional perspective view of Figure 1;
3A and 3B are cross-sectional perspective views respectively showing a process in which a vertical wall for vertical tunnel connection is formed according to the present invention.
4A and 4B are cross-sectional perspective views showing a process in which a central wall for vertical tunnel connection is formed according to the present invention, respectively.
5A and 5B are cross-sectional perspective views respectively showing a process in which the vertical wall for vertical tunnel connection is formed according to the present invention.
6A and 6B are cross-sectional perspective views showing a process in which a vertical sphere wall is integrally formed on the top of a vertical sphere wall for horizontal tunnel connection according to the present invention, respectively.
7 is to the target depth according to the invention A cross-sectional view showing a vertical sphere wall installed.

본 발명의 특징 및 이점들은 첨부도면에 의거한 다음의 바람직한 실시예에 대한 상세한 설명으로 더욱 명백해질 것이다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 발명자가 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.Features and advantages of the present invention will become more apparent from the detailed description of the following preferred embodiments based on the accompanying drawings. Prior to this, the terms or words used in the specification and claims are based on the principle that the inventor can appropriately define the concept of terms in order to best describe his or her invention in the technical spirit of the present invention. It must be interpreted as a match meaning and concept.

이하, 본 발명의 일 실시예를 도면을 참조하여 상세히 설명함에 있어, 동일한 구성에 대해서는 동일한 부호를 사용하며, 명료성을 위하여 가능한 중복되지 않게 상이한 부분만을 주로 설명한다.Hereinafter, an exemplary embodiment of the present invention will be described in detail with reference to the drawings. The same reference numerals are used for the same components, and only the different portions that are not duplicated as much as possible are mainly described for clarity.

본 발명에 따른 수직구 구조물의 수평터널 연결부 성형방법은 다음과 같은 순서에 따라 이루어진다.The method for forming a horizontal tunnel connection part of a vertical sphere structure according to the present invention is performed in the following order.

도 1 및 도 2에 도시된 바와 같이, 지상에 가설구조물(100)을 설치한 다음, 상기 가설구조물(100) 상부에 콘크리트 거푸집(200)을 설치한다.1 and 2, the temporary structure 100 is installed on the ground, and then the concrete formwork 200 is installed on the temporary structure 100.

상기 콘크리트 거푸집(200)은 가설구조물(100)의 상단에 설치되는 외측수직지지대(210)와, 상기 외측수직지지대(210)와 연결된 내측수직지지대(220)와, 상기 외측수직지지대(210)와 내측수직지지대(220)에 결합된 거푸집패널(230)을 구비하며, 수직구의 내부로의 승강이 가능한 안전작업대(240,250)를 더 구비할 수도 있다. 이와 같은 콘크리트 거푸집(200)은 종래와 대동소이하므로 상세한 설명은 생략한다.The concrete formwork 200 includes an outer vertical support 210 installed on the top of the temporary structure 100, an inner vertical support 220 connected to the outer vertical support 210, and the outer vertical support 210. It has a formwork panel 230 coupled to the inner vertical support 220, it may be further provided with a safety worktable (240,250) that can be elevated to the inside of the vertical sphere. Since the concrete formwork 200 is roughly the same as the conventional one, detailed description is omitted.

그리고 상기 콘크리트 거푸집(200)에는 성형된 수직구 벽체를 하강시키기 위한 하강유도부재(260)가 설치되며, 상기 가설구조물(100)에는 콘크리트 거푸집(200)을 승강시키기 위한 승강부재(300)가 설치된다.In addition, the concrete formwork 200 is provided with a descending induction member 260 for descending the molded vertical sphere wall, and the temporary structure 100 is provided with a lifting member 300 for elevating the concrete formwork 200. do.

상기 하강유도부재(260)는 콘크리트 거푸집(200)에 설치된 하강유압잭(261)과 상기 하강유압잭(261)에 결합된 하강잭로드(262)와 상기 하강잭로드(262)의 하단에 고정된 하부브라켓(263)으로 구성되고, 상기 승강부재(300)는 하강유도부재(260)와 같이 승강유압잭(310)과 상기 승강유압잭에 결합되어 하단이 가설구조물(100)에 지지된 승강잭로드(320)로 구성된다.The descending induction member 260 is fixed to the lower end of the descending jack rod 262 and the descending jack rod 262 coupled to the descending hydraulic jack 261 and the descending hydraulic jack 261 installed in the concrete formwork 200. Consists of a bracket 263, the lifting member 300 is coupled to the lifting hydraulic jack 310 and the lifting hydraulic jack as the descending induction member 260, the lower lifting jack rod 320 supported on the temporary structure 100 ).

도 3a에 도시된 바와 같이, 가설구조물(100)에 콘크리트 거푸집(200)의 설치가 완료되면, 승강부재(300)를 이용하여 콘크리트 거푸집(200)을 들어올린 상태에서 거푸집패널(230) 사이에 지지대(270)를 설치한다.As shown in Figure 3a, when the installation of the concrete formwork 200 to the temporary structure 100 is completed, between the formwork panel 230 in a state of lifting the concrete formwork 200 using the lifting member 300 The support 270 is installed.

상기 지지대(270)는 하강유도부재(260)의 하부브라켓(263)의 상단에 일정간격을 두고 수직으로 고정된 수직 및 수평부재로서, 이후 거푸집패널(230) 사이로 삽입되는 수평터널 연결용 거푸집패널(400)의 외측면을 지지한다. 따라서, 상기 지지대(270)들은 수평터널 연결용 거푸집패널(400)의 외측면을 따라 각기 다른 높이와 길이로 형성된다.The support 270 is a vertical and horizontal member fixed vertically at regular intervals on the upper end of the lower bracket 263 of the descending induction member 260, and then the formwork panel for horizontal tunnel connection inserted between the formwork panels 230 The outer surface of 400 is supported. Therefore, the support 270 is formed in different heights and lengths along the outer surface of the formwork panel 400 for horizontal tunnel connection.

아울러, 상기 지지대(270)들은 거푸집패널(230) 사이에는 수직구 벽체의 강도를 향상시키기 위하여 배근용 철근(A)이 설치될 수 있으며, 이 경우 상기 지지대(270)들은 배근용 철근(A)의 일부일 수 있다.In addition, the support 270 may be installed between the formwork panel 230 to improve the strength of the vertical sphere wall (A) reinforcement bar (A), in this case, the support 270 are reinforcement bar (A) It can be part of.

이와 같이, 지지대(270)의 설치가 완료되면 상기 지지대(270)에 수평터널 연결용 거푸집패널(400)을 안착시킨 다음, 승각부재(300)를 이용하여 상기 콘크리트 거푸집(200)을 원위치로 하강시킨다.As described above, when the installation of the support 270 is completed, the horizontal tunnel connection formwork panel 400 is seated on the support 270, and then the concrete formwork 200 is lowered to its original position using the elevation member 300. Order.

상기 수평터널 연결용 거푸집패널(400)은 수평터널 입구의 형상을 따라 원통형상으로 제작되는데, 수평터널의 입구 사이즈가 클 경우에는 상기 수평터널 연결용 거푸집패널(400)의 취급과 시공상의 어려움이 있기 때문에 도시된 바와 같이, 상하방향으로 분할형성하고 콘크리트 거푸집(200) 내부에 단계적으로 삽입시키면서 작업을 진행한다. 본 실시예에서는 상기 수평터널 연결용 거푸집패널(400)이 하부거푸집패널(400a)과 중간거푸집패널(400b)과 상부거푸집패널(400c)로 3분할된 것을 예를 들어 도시하고 설명한다.The horizontal tunnel connection formwork panel 400 is manufactured in a cylindrical shape along the shape of the horizontal tunnel entrance. When the entrance size of the horizontal tunnel is large, it is difficult to handle and construct the horizontal tunnel connection formwork panel 400. As it is shown, as shown in the figure, it is divided and formed in the vertical direction and the work is progressed while being inserted step by step inside the concrete formwork 200. In this embodiment, the horizontal tunnel connection formwork panel 400 is illustrated and described as an example in which the lower formwork panel 400a, the middle formwork panel 400b, and the upper formwork panel 400c are divided into three.

그리고 상기 하부거푸집패널(400a)과 중간거푸집패널(400b)과 상부거푸집패널(400c)의 내측에는 외부로부터 가해지는 하중을 견딜 수 있도록 강도보강용 지지프레임(410)들이 설치될 수 있다. 도시하지는 않았으나, 상기 지지프레임(410)들 사이에는 지지프레임(410)들끼리를 지지해 주는 보조프레임들이 더 설치될 수 있다. 이 경우, 상기 보조프레임들은 지지프레임(410)의 거리에 따라 지지높이를 가변시킬 수 있도록 실린더를 통해 신축가능하게 설치되는 것이 바람직하다.In addition, support frames 410 for strength reinforcement may be installed inside the lower formwork panel 400a, the middle formwork panel 400b, and the upper formwork panel 400c to withstand the load applied from the outside. Although not illustrated, auxiliary frames for supporting the support frames 410 between the support frames 410 may be further installed. In this case, the auxiliary frames are preferably installed to be stretchable through a cylinder so as to vary the support height according to the distance of the support frame 410.

상기 지지프레임(410)과 보조프레임들은 수평터널 연결용 거푸집패널(400)이 단계적으로 삽입될 때마다 해당 수평터널 연결용 거푸집패널(400a,400b,400c) 내부에 단계적으로 설치될 수도 있으나, 작업의 편의성과 공기단축을 위하여 해당 수평터널 연결용 거푸집패널(400a,400b,400c)에 미리 조립된 상태로 현장에 공급되도록 하는 것이 바람직하다.The support frame 410 and the auxiliary frames may be installed step-by-step inside the formwork panels 400a, 400b, 400c for horizontal tunnel connection whenever the formwork panels 400 for horizontal tunnel connection are inserted step by step. For convenience and shortening of the air, it is preferable to be supplied to the site in a pre-assembled state in the formwork panels 400a, 400b, 400c for connecting the horizontal tunnel.

도 3b에 도시된 바와 같이, 하부거푸집패널(400a)의 설치가 완료되면, 가설구조물(100)의 내부로 포크레인(미도시)과 같은 장비를 투입시켜 수직구의 굴착을 실시하는 동시에 콘크리트 거푸집(200)과 하부거푸집패널(400a) 사이로 콘크리트를 타설하여 현장에서 수평터널 연결용 수직구 하부벽체(B1)를 성형한다. 이와 같이, 본 발명은 수직구의 굴착이 진행되는 동안 콘크리트 타설 및 양생이 이루어지므로 공기를 크게 단축시킬 수 있다.As shown in Figure 3b, when the installation of the lower formwork panel (400a) is completed, by inserting equipment such as a fork lane (not shown) into the interior of the temporary structure 100, while performing the excavation of the vertical sphere at the same time the concrete formwork (200) ) And cast the concrete between the lower formwork panel (400a) to form a vertical sphere lower wall (B1) for horizontal tunnel connection in the field. As described above, the present invention can greatly shorten the air because concrete pouring and curing are performed during the excavation of the vertical sphere.

그리고, 도 4a에 도시된 바와 같이, 하부거푸집패널(400a)의 상부에 중간거푸집패널(400b)을 안착시킨 다음 중간거푸집패널(400b)과 하부거푸집패널(400a)을 견고하게 고정시키고 수평터널 연결용 수직구 하부벽체(B1)의 상부에 지지대(270)의 설치를 완료하면, 도 4b에 도시된 바와 같이, 하강유도부재(260)를 이용하여 거푸집패널(230) 사이로 지지대(270)와 중간거푸집패널(400b)을 동반하강시킨 다음 콘크리트 거푸집(200)과 중간거푸집패널(400b) 사이로 콘크리트를 타설하여 현장에서 수평터널 연결용 수직구 중간벽체(B2)를 성형한다.And, as shown in Figure 4a, the intermediate formwork panel 400b is seated on the upper part of the lower formwork panel 400a, and then the middle formwork panel 400b and the lower formwork panel 400a are securely fixed and connected to a horizontal tunnel. When the installation of the support 270 on the upper portion of the lower wall (B1) for the vertical installation is completed, as shown in FIG. 4B, the support 270 and the middle between the formwork panels 230 using the descending induction member 260. After accompanying the formwork panel 400b, concrete is poured between the concrete formwork 200 and the intermediate formwork panel 400b to form a vertical sphere intermediate wall B2 for horizontal tunnel connection in the field.

그리고, 도 5a에 도시된 바와 같이, 중간거푸집패널(400b)의 상부에 상부거푸집패널(400c)을 안착시킨 다음 상부거푸집패널(400c)과 중간거푸집패널(400b)을 견고하게 고정시키고 수평터널 연결용 수직구 중간 벽체(B2)의 상부에 지지대(270)의 설치를 완료하면, 도 5b에 도시된 바와 같이, 하강유도부재(260)를 이용하여 거푸집패널(230) 사이로 지지대(270)와 상부거푸집패널(400c)을 동반하강시킨 다음 콘크리트 거푸집(200)과 상부거푸집패널(400c) 사이로 콘크리트를 타설하여 현장에서 수평터널 연결용 수직구 상부벽체(B3)를 성형한다. 이렇게 하면 수직구의 수평터널 연결부가 성형된 수평터널 연결용 수직구 벽체가 완성된다.And, as shown in Figure 5a, the upper formwork panel 400c is seated on the upper side of the intermediate formwork panel 400b, and then the upper formwork panel 400c and the middle formwork panel 400b are securely fixed and connected to a horizontal tunnel. When the installation of the support 270 on the upper portion of the intermediate wall (B2) for the vertical sphere is completed, as shown in FIG. 5B, the support 270 and the upper part between the formwork panels 230 using the descending induction member 260. After descending the formwork panel (400c), concrete is poured between the concrete formwork (200) and the upper formwork panel (400c) to form a vertical sphere upper wall (B3) for horizontal tunnel connection in the field. This completes the vertical sphere wall for the horizontal tunnel connection where the horizontal tunnel connection portion of the vertical sphere is formed.

그리고, 도 6a에 도시된 바와 같이, 완성된 수평터널 연결용 수직구 벽체의 상부에 배근용 철근(A)을 설치하고, 도 6b에 도시된 바와 같이, 하강유도부재(260)를 이용하여 수평터널 연결용 수직구 벽체를 하강시킨 다음 콘크리트 거푸집(200)에 콘크리트를 타설하여 현장에서 수평터널 연결용 수직구 벽체의 상단에 수직구 벽체(B4)를 일체로 성형한다.And, as shown in Fig. 6a, the reinforcement (A) for the reinforcement is installed on the top of the vertical sphere wall for the completed horizontal tunnel connection, as shown in Fig. 6b, using a descending induction member 260 horizontal The vertical sphere wall for tunnel connection is lowered, and then concrete is poured into the concrete formwork 200 to form a vertical sphere wall (B4) integrally on the top of the vertical sphere wall for horizontal tunnel connection in the field.

한편, 수평터널 연결용 수직구 벽체 및 수직구 벽체(B4)의 성형이 이루어지는 동안 수직구의 굴착은 지속적으로 진행된다. 통상적으로 수직구의 굴착속도가 수평터널 연결용 수직구 벽체 및 수직구 벽체(B4)의 성형속도 보다 빠르므로 수평터널 연결용 수직구 벽체 및 수직구 벽체(B4)의 성형은 수직구의 굴착작업에 영향을 받지 않고 연속적으로 수행될 수 있다.On the other hand, while forming the vertical sphere wall and the vertical sphere wall (B4) for the horizontal tunnel connection, the excavation of the vertical sphere continues. Normally, the drilling speed of the vertical sphere is faster than the molding speed of the vertical sphere wall and vertical sphere wall (B4) for horizontal tunnel connection, so the molding of the vertical sphere wall and vertical sphere wall (B4) for horizontal tunnel connection affects the excavation of the vertical sphere. It can be performed continuously without receiving.

아울러, 수평터널 연결용 수직구 벽체가 하강하면 상부에 타설된 콘크리트가 양생되는 동안 수평터널 연결용 거푸집패널(400) 및 강도보강용 지지프레임(410)과 보조프레임을 해체하여 지상으로 반출한다.In addition, when the vertical sphere wall for the horizontal tunnel connection descends, the concrete panel for the horizontal tunnel connection is demolished and the support frame 410 for strength reinforcement and the auxiliary frame are dismantled and taken out to the ground while the concrete poured over the top is cured.

도 7에 도시된 바와 같이, 이러한 일련의 과정을 반복해 가면서 수평터널 연결용 수직구가 목표로 하는 깊이의 수직구의 바닥에 도달할 때까지 반복실시하면 수평터널 연결부(도 7의 A부분)가 성형된 수직구 구조물(도 7의 B부분)의 시공이 완료된다.As shown in FIG. 7, the horizontal tunnel connection part (part A of FIG. 7) is repeated until the vertical sphere for horizontal tunnel connection reaches the bottom of the target vertical depth while repeating this series of processes. Construction of the formed vertical sphere structure (part B in FIG. 7) is completed.

한편 수평터널 연결부가 성형된 수직구 구조물의 시공이 완료되면, 수직구의 바닥에 콘크리트를 타설하여 바닥면(D)을 시공한 다음 수직구 내부로 굴착기(미도시)를 투입하여 수평터널을 굴착한다.On the other hand, when the construction of the vertical sphere structure in which the horizontal tunnel connection is formed is completed, concrete is poured on the floor of the vertical sphere to construct the floor surface (D), and then an excavator (not shown) is inserted into the vertical sphere to excavate the horizontal tunnel. .

본 발명에 따르면, 수평터널 연결용 수직구 벽체에는 이미 수평터널 연결부가 형성되어 있기 때문에 상기 굴착기가 완성된 수직구 구조물(B)을 파쇄하지 않고 곧바로 수평터널 굴착을 수행할 수 있게 된다.According to the present invention, since the horizontal tunnel connection portion is already formed on the vertical sphere wall for horizontal tunnel connection, the horizontal tunnel excavation can be performed immediately without crushing the completed vertical sphere structure (B).

따라서, 본 발명의 의해 수직구 구조물의 작업이 완료된 상태에서 계속해서 수평터널 굴착과정을 수행하더라도 상기 수직구 구조물에 외력이 전혀 가해지지 않아 구조적 안정성에 영향이 전혀 없을 뿐만 아니라, 수평터널 연결부에 대한 마감작업도 전혀 요구되지 않아 공기를 크게 단축시킬 수 있게 된다.Therefore, even if the horizontal tunnel excavation process is continuously performed in the state in which the work of the vertical sphere structure is completed by the present invention, there is no external force applied to the vertical sphere structure, so there is no impact on structural stability, and the horizontal tunnel connection part No finishing is required at all, which significantly reduces air.

이와 같이, 도면을 참조하여 본 발명의 바람직한 실시예에 대해 상술하였으나 본 발명은 전술한 실시예에 한정되지 않으며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진자가 본 발명의 사상을 벗어나지 않고 변형 가능하며, 이러한 변형은 본 발명의 권리범위에 속할 것이다.As described above, preferred embodiments of the present invention have been described with reference to the drawings, but the present invention is not limited to the above-described embodiments, and those skilled in the art to which the present invention pertains deform without departing from the spirit of the present invention. It is possible, and such modifications will fall within the scope of the present invention.

100...가설구조물 200...콘크리트 거푸집
210...외측수직지지대 220...내측수직지지대
230...거푸집 패널 260...하강유도부재
261...하강유압잭 262...하강잭로드
263...하부부라켓 270...지지대
300...승강부재 310...승강유압잭
320...승강잭로드 400...수평터널 연결용 거푸집패널
400a...하부거푸집패널 400b...중간거푸집패널
400c...상부거푸집패널 410...강도보강용 지지프레임
A...배근용 철근
100 ... temporary structure 200 ... concrete formwork
210 ... outer vertical support 220 ... inner vertical support
230 ... formwork panel 260 ... descending induction member
261 ... Down hydraulic jack 262 ... Down jack rod
263 ... Lower racket 270 ... Support
300 ... Elevating member 310 ... Elevating hydraulic jack
320 ... lift jack rod 400 ... formwork panel for horizontal tunnel connection
400a ... lower formwork panel 400b ... middle formwork panel
400c ... Upper formwork panel 410 ... Support frame for strength reinforcement
A ... Reinforcing bar for reinforcement

Claims (5)

삭제delete 삭제delete 바닥에 설치되는 가설구조물과,
상기 가설구조물에 승강가능하게 설치되며 거푸집 패널을 포함하는 콘크리트 거푸집과,
상기 콘크리트 거푸집에 설치되어 콘크리트 거푸집을 통해 성형된 수직구 구조물의 벽체를 하강시키는 하강유도부재와,
상기 가설구조물과 콘크리트 거푸집 사이에 설치되어 상기 거푸집 패널을 포함한 콘크리트 거푸집을 승강시키는 승강부재와,
상기 콘크리트 거푸집의 내부에 밀착되게 위치되는 수평터널 연결용 거푸집패널과,
상기 하강유도부재를 통해 콘크리트 거푸집의 내부에 설치되어 상기 수평터널 연결용 거푸집패널을 일정높이로 지지하는 지지대를 포함하며;
상기 하강유도부재는 가설구조물에 수직상태로 지지되는 복수개의 외측수직지지대와, 상기 각 외측수직지지대의 안쪽에 외측수직지지대와 연결되게 수직상태로 지지되는 복수개의 내측수직지지대와, 상기 각 외측수직지지대와 내측수직지지대 사이에 수직상태로 고정된 하강유압잭과, 상기 하강유압잭에 결합된 하강잭로드와, 상기 하강잭로드의 하단에 고정된 하부브라켓으로 구성되고;
상기 승강부재는 상기 하강유도부재의 구성요소인 각 외측수직지지대의 외측부에 수직상태로 고정된 승강유압잭과, 상기 승강유압잭에 하단이 가설구조물에 지지된 상태로 결합된 승강잭로드로 구성됨을 특징으로 하는 수직구 구조물의 수평터널 연결부 성형장치.
The temporary structure installed on the floor,
A concrete formwork that is installed to be elevated on the temporary structure and includes a formwork panel,
A descending induction member installed on the concrete formwork and descending a wall of a vertical sphere structure formed through the concrete formwork;
A lifting member installed between the temporary structure and the concrete formwork to elevate the concrete formwork including the formwork panel;
A formwork panel for horizontal tunnel connection, which is located in close contact with the inside of the concrete formwork,
It is installed inside the concrete formwork through the descending induction member and includes a support for supporting the formwork panel for horizontal tunnel connection to a certain height;
The descending induction member includes a plurality of outer vertical supports supported vertically to the temporary structure, a plurality of inner vertical supports supported vertically to be connected to the outer vertical supports inside each outer vertical support, and each outer vertical It consists of a descending hydraulic jack fixed vertically between a support and an inner vertical support, a descending jack rod coupled to the descending hydraulic jack, and a lower bracket fixed to the lower end of the descending jack rod;
The elevating member is composed of an elevating hydraulic jack fixed vertically to an outer portion of each outer vertical support, which is a component of the descending induction member, and an elevating jack rod coupled with the lower end of the elevating hydraulic jack supported on a temporary structure. Forming device for horizontal tunnel connection of vertical sphere structure.
삭제delete 삭제delete
KR1020180011719A 2018-01-31 2018-01-31 constructing level tunnel connecting part of vertical structure and apparatus thereof KR102102593B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020180011719A KR102102593B1 (en) 2018-01-31 2018-01-31 constructing level tunnel connecting part of vertical structure and apparatus thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020180011719A KR102102593B1 (en) 2018-01-31 2018-01-31 constructing level tunnel connecting part of vertical structure and apparatus thereof

Publications (2)

Publication Number Publication Date
KR20190092676A KR20190092676A (en) 2019-08-08
KR102102593B1 true KR102102593B1 (en) 2020-04-22

Family

ID=67613089

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020180011719A KR102102593B1 (en) 2018-01-31 2018-01-31 constructing level tunnel connecting part of vertical structure and apparatus thereof

Country Status (1)

Country Link
KR (1) KR102102593B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102170998B1 (en) * 2020-06-12 2020-10-28 박서진 Excavation and lining concrete wall construction method of vertical tunnel using integral formwork and preceding excavation

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100902083B1 (en) * 2008-05-16 2009-06-10 장영미 System of casting a wall contruction and descending the same into teh groudnd, and a driving apparatus for stepwise descending the wall construction into teh groudnd

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200179986Y1 (en) * 1998-03-26 2000-05-01 염병대 F.r.p mould for cover circular type drain manhole with concrete

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100902083B1 (en) * 2008-05-16 2009-06-10 장영미 System of casting a wall contruction and descending the same into teh groudnd, and a driving apparatus for stepwise descending the wall construction into teh groudnd

Also Published As

Publication number Publication date
KR20190092676A (en) 2019-08-08

Similar Documents

Publication Publication Date Title
KR101859367B1 (en) Method for constructing vertical structure in vertical tunnel using top down method
KR101034398B1 (en) Land-side protection wall that use ground structure
KR102115380B1 (en) Hydraulic slipform safety locking device and virtical structure and slab construction method using the same
CN109577166B (en) Upper-span active highway door opening support and construction method
US7784231B2 (en) Multi-story building
KR102400229B1 (en) Method for demolishing underground building
CN102587659A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
CN110685459B (en) Breaking hammer dismantling construction method for dismantling hoist bent from lower part
CN110952995A (en) Construction method for external tunnel door post-cast ring beam
CN109024288B (en) Method for erecting steel truss girder by using precast concrete shoveling mat
KR102102593B1 (en) constructing level tunnel connecting part of vertical structure and apparatus thereof
KR100580225B1 (en) Upper structure raising method using bridge upper structure support and lift equipment and this
KR102079190B1 (en) weight down type perpendicular hole hive-cut press in mehthod of construction
CN113774972B (en) Reinforcing method for overload punching damage of independent foundation under column
KR101021945B1 (en) Steel form for forming lining wall of vertical tunnel
CN114541806A (en) Building displacement method used in project supervision construction
KR102171437B1 (en) Construction method of panel for pedestrian block
CN114016546A (en) Hole-pile method station steel pipe column hoisting and fixing device and construction method
KR102060692B1 (en) Construction method using road soundproof wall concrete retaining wall construction device
CN114293564A (en) Construction method for foundation pit slope pile foundation of building engineering on site
CN113653319A (en) Integrated formwork erecting method for multi-stair section and rest platform
JP2013155592A (en) Demolition method for border proximity underground concrete construction body
KR20120122790A (en) Apparatus for forming underground dome structure by oil pressure type lift and constructing method using the same
AU2016102393A4 (en) A Method of constructing a column, a tunnel, and a tunnel made from the method
GB2055130A (en) Method of raising buildings

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant