KR100650134B1 - Early remove support method - Google Patents

Early remove support method Download PDF

Info

Publication number
KR100650134B1
KR100650134B1 KR1020050099142A KR20050099142A KR100650134B1 KR 100650134 B1 KR100650134 B1 KR 100650134B1 KR 1020050099142 A KR1020050099142 A KR 1020050099142A KR 20050099142 A KR20050099142 A KR 20050099142A KR 100650134 B1 KR100650134 B1 KR 100650134B1
Authority
KR
South Korea
Prior art keywords
concrete
concrete layer
formwork
support
dismantling
Prior art date
Application number
KR1020050099142A
Other languages
Korean (ko)
Inventor
이병영
Original Assignee
이병영
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이병영 filed Critical 이병영
Priority to KR1020050099142A priority Critical patent/KR100650134B1/en
Application granted granted Critical
Publication of KR100650134B1 publication Critical patent/KR100650134B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/18Devices for suspending or anchoring form elements to girders placed in ceilings, e.g. hangers
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/04Shores or struts; Chocks telescopic

Abstract

An early dismantling method of a support is provided to shorten a period of construction by supporting concrete layers strongly using a hanger rod and a timbering, preventing the deflection of a form using a timbering and executing pit excavation right after dismantling the timbering, and to improve workability and to cut down on expenses by making equipment simple and lightweight. An early dismantling method of a support comprises the steps of: constructing a primary concrete layer by assembling a hole pipe(30) to a form(40) and placing concrete; executing pit excavation under the primary concrete layer after the primary concrete layer is cured completely; installing timberings(50) on the lower part of the from to support the lower part of the form; constructing a secondary concrete layer(10) by assembling the hole pipe to the form and placing concrete; penetrating a hanger rod(20) to the hole pipe to make one end fixed to the lower part of the secondary concrete layer and the other end fixed to the upper part of the primary concrete layer; and dismantling the form and the timbering from the secondary concrete layer if the secondary concrete layer has the appointed strength and over. Hereon the hanger rod comprises a long bolt(21), a bearing plate(23) fixed to one end of the long bolt, a nut(22) coupled to one end of the long bolt to support the bearing plate and a coupling(24) coupled to the other end of the long bolt to be connected with the other long bolt.

Description

지지대 조기 해체 공법 { EARLY REMOVE SUPPORT METHOD }Early Dismantling Method of Supports {EARLY REMOVE SUPPORT METHOD}
도 1은 본 발명의 실시예에 따른 공정순서도,1 is a process flowchart according to an embodiment of the present invention,
도 2는 본 발명의 실시예에 따른 거푸집의 해체 전 상태를 간략하게 도시한 상태도,Figure 2 is a state diagram briefly showing a state before dismantling of the formwork according to an embodiment of the present invention,
도 3은 본 발명의 실시예에 따른 거푸집의 해체 후 상태를 간략하게 도시한 상태도.Figure 3 is a state diagram briefly showing the state after dismantling of the formwork according to the embodiment of the present invention.
<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>
S10 : 제1콘크리트타설단계, S20 : 터파기단계,S10: first concrete pouring step, S20: digging step,
S30 : 동바리설치단계, S40 : 제2콘트리트타설단계,S30: copper bar installation step, S40: second concrete pouring step,
S50 : 달대설치단계, S60 : 해체단계,S50: moon stand installation step, S60: dismantling step,
10 : 제2콘크리트층, 20 : 달대,10: second concrete layer, 20: moon stand,
21 : 장볼트, 22 : 너트,21: long bolt, 22: nut,
23 : 받침판, 24 : 커플링,23: support plate, 24: coupling,
30 : 홀파이프, 40 : 거푸집,30: hole pipe, 40: formwork,
50 : 동바리.50: Dong-bari.
본 발명은 지지대 조기 해체 공법 및 이에 사용되는 달대장치에 관한 것으로서, 특히 타설된 콘크리트층의 상부와 하부에 각각 지지대를 장착하여 콘크리트층을 지지하여 주되, 일정강도 이상이 되면 상기 하부지지대를 해체한 후 상기 콘크리트층의 하부에서 터파기작업을 수행하도록 함으로써 공사기간을 단축시킬 수 있고 장비를 단순화 및 경량화시켜 작업성을 향상시키며 비용을 절감시킬 수 있는 지지대 조기 해체 공법 및 이에 사용되는 달대장치에 관한 것이다.The present invention relates to an early dismantling method of the support and a device used for the same, in particular, to support the concrete layer by mounting the support on the upper and lower portions of the concrete layer, respectively, when the predetermined strength or more dismantle the lower support After the excavation work in the lower part of the concrete layer to reduce the construction period and to simplify and lighten the equipment to improve the workability and reduce the cost for the early dismantling method and support system will be.
콘크리트 구조물은 거푸집을 일정 형상으로 만들어 거푸집에 콘크리트를 채워 일정한 모양을 가진 부재를 형성시킨다. Concrete structures form the molds into a certain shape to fill the formwork with concrete to form a member having a certain shape.
콘크리트를 사용하여 건축물을 축조할 때에는 통상 아래쪽에서 위로 올라가면서 부재를 형성시키는 순서로 진행한다. When constructing a building using concrete, it is generally progressed from the bottom to the top in order to form the member.
땅 값이 비싼 도심지에 건물을 지으려 할 때에는 토지를 효율적으로 이용하기 위하여 여러 층의 지하층을 만들므로 점차 지하층은 깊어져 가는 추세이다.When building buildings in urban areas where the cost of land is expensive, underground floors are gradually becoming deeper because several layers of basements are created in order to use land efficiently.
통상 지하에 구조물을 축조할 경우 지하의 흙이나 암반을 파내고 지하 구조물이 완성될 때까지 오랜 기간 방치해야 하므로 주변 지반이 붕괴할 우려가 있고, 시각상 불안하며, 지하 토공사 중에 발생하는 소음, 분진 등 건설공해로 인해 민원이 발생하며, 도심지 공사에서 건설자재, 중장비를 위한 공간이 부족하며, 지하 구조물부터 축조하여 올라올 경우 공사기간이 긴 점 등의 문제점을 해결하기 위하여 지하층을 위에서 아래로 축조해 나가고 동시에 지상층 공사를 병행할 수 있는 역타 설 공법이 개발되어 적용되고 있다.In general, when constructing a structure underground, it is necessary to dig underground soil or rock and leave it for a long time until the underground structure is completed. Therefore, the surrounding ground may collapse, visually unstable, and noise and dust generated during underground earthwork Civil complaints are caused by construction pollution, and there is a lack of space for construction materials and heavy equipment in urban construction, and when building from underground structures, the basement floor is constructed from top to bottom to solve problems such as long construction period. Reverse casting method has been developed and applied to go out and at the same time ground floor construction.
역타설 공법은 Top down 공법으로 불리기도 하며, 선 시공한 강기둥을 묶는 슬래브와 보 콘크리트를 타설하고 이 구조체가 수평토압에 대응하는 수평지지대 역할을 하여 지상층을 위로 시공하면서 동시에 지하층은 아래로 구조물을 형성해 나가는 공법이다.The reverse casting method is also called top down method, and the slab and beam concrete that binds the pre-installed steel columns are cast and this structure acts as a horizontal support that corresponds to the horizontal earth pressure. It is a construction method to form.
역타설 공법은 지반을 정지한 상태에서 지반 위에 콘크리트 슬래브와 보를 타설하는 방법(concrete on grade)과, 지반을 파내고 지반을 고른 뒤 동바리를 세우고 거푸집을 설치한 다음 콘크리트를 타설하는 방법(form on supporting)을 통상 사용하고 있다. The reverse casting method is to place concrete slabs and beams on the ground with the ground stopped (concrete on grade), and to dig up the ground, select the ground, erect the club, install the formwork, and then form the concrete (form on). commonly used).
이런 방법들은 대개 콘크리트를 부어 넣은 뒤 충분한 양생기간을 거쳐 구조체가 제강도를 발현할 때까지 기다려야 하므로 작업대기 시간이 불가피하게 발생하여 공사기간이 장기화되는 문제가 있다.Since these methods usually have to wait until the structure develops steelmaking through sufficient curing period after pouring concrete, work waiting time is inevitably generated, resulting in a prolonged construction period.
이러한 문제점을 해결하기 위하여 등록특허공보 공고번호 제10-261775호에 기재된 무지주 역타설 거푸집 공법이 개발되었다.In order to solve this problem, the unsupported reverse casting form described in Korean Patent Publication No. 10-261775 has been developed.
이러한 무지주 역타설공법은 거푸집을 하부에서 동바리를 이용하여 지지하는 것이 아니라, 중량 및 대형의 거푸집지지틀을 상부에서 달대를 이용하여 매달아 놓고 콘크리트타설을 하는 방식으로 작업을 수행하는 공법이다.This unsupported reverse casting method is a method of supporting the formwork from the bottom using a copper bar, but a method of performing the work by placing the heavy and large formwork supporting frame suspended from the upper using the moon stand to cast concrete.
따라서, 콘크리트타설 후에 약간의 양생기간을 거친 후 바로 거푸집지지틀의 하부에서 터파기작업을 수행할 수 있어 공사기간을 단축시킬 수 있다.Therefore, it is possible to carry out the excavation work in the lower part of the formwork frame immediately after a little curing period after the concrete casting can shorten the construction period.
그러나, 이러한 무지주 역타설공법은 거푸집지지틀을 상기 달대를 이용하여 상부 구조물에 전부 매달아 놓아야 하므로, 달대와 상부 구조물에 많은 하중이 가해져 안전사고가 발생될 우려가 있고, 콘크리트 타설시 콘크리트가 하부로 배출되는 것을 방지하기 위하여 상기 거푸집지지틀을 튼튼하고 크게 제작되어야 하는바 그 제작비용이 많이 소모되며, 또한 상기 거푸집지지틀의 대형화 및 중량화에 의해 콘크리트타설시 그 하중이 더욱 증가하게 되어 상기 거푸집지지틀이 휘어지거나 처지게 되는 현상이 발생하여 결국 구조물에 하자가 발생하게 되는 문제가 있다. However, since the unsupported reverse casting method has to completely hang the formwork supporting frame on the upper structure by using the moon, there is a possibility that a heavy accident is applied to the moon and the upper structure, resulting in a safety accident. In order to prevent the discharge of the mold support frame to be made strong and large, the production cost is consumed a lot, and the load is increased further when the concrete is laid by the size and weight of the form support frame Forming support frame is bent or sagging occurs, there is a problem that eventually occurs in the structure.
또한, 상기 거푸집지지틀의 하중과 콘크리트의 하중을 지지하도록 하기 위하여 상기 달대를 상기 거푸집지지틀에 많이 장착하여야 하였는바, 철근작업이나 콘크리트 타설시 작업에 많은 장애가 되었다.In addition, in order to support the load of the formwork supporting frame and the load of the concrete was to be mounted on the formwork supporting frame a lot, bar has been a lot of obstacles in the work during reinforcement work or concrete pouring.
본 발명은 전술한 문제점을 해결하기 위하여 안출된 것으로서, 타설된 콘크리트층의 상부와 하부에 각각 지지대를 장착하여 콘크리트층을 지지하여 주되, 일정강도 이상이 되면 상기 하부지지대를 해체한 후 상기 콘크리트층의 하부에서 터파기작업을 수행하도록 함으로써 공사기간을 단축시킬 수 있고 장비를 단순화 및 경량화시켜 작업성을 향상시키며 장비 제작에 필요한 비용을 절감시킬 수 있는 지지대 조기 해체 공법 및 이에 사용되는 달대장치를 제공하는데 그 목적이 있다.The present invention has been made in order to solve the above-mentioned problems, but to support the concrete layer by mounting a support on the top and bottom of the poured concrete layer, respectively, if the concrete strength is above a certain strength after dismantling the lower support Providing early dismantling method and supporting device that can be used to reduce the construction period by simplifying and reducing the construction time by improving the workability and reducing the cost for the equipment production Its purpose is to.
상기 목적을 달성하기 위하여 본 발명의 지지대 조기 해체 공법은, 콘크리트 지하층을 축조하는 거푸집 공법에 있어서, 타설된 콘크리트층을 상부와 하부에서 각각 지지대에 의해 지지하여 주되, 일정강도 이상이 되면 상기 콘크리트층 하부를 지지하는 지지대를 해체한 후 상기 콘크리트층의 하부에서 터파기작업을 수행하도록 하는 것을 특징으로 한다.In order to achieve the above object, the early dismantling method of the present invention, in the formwork for constructing the concrete basement layer, the cast concrete layer is supported by the support from the upper and lower, respectively, when the concrete layer is above a certain strength, After dismantling the support for supporting the lower portion is characterized in that to carry out the digging operation in the lower portion of the concrete layer.
이러한 지지대 조기 해체 공법은, 거푸집에 홀파이프를 조립한 후에 콘크리트를 타설하여 제1콘크리트층을 축조하는 제1콘크리트타설단계; 상기 제1콘트리트층 아래를 굴착하는 터파기단계; 상기 거푸집을 하강시키고, 상기 거푸집의 하부를 지지하도록 상기 거푸집의 하부에 동바리를 세우는 동바리설치단계; 상기 거푸집에 홀파이프를 조립한 후에 콘크리트를 타설하여 제2콘크리트층을 축조하는 제2콘크리트타설단계; 상기 홀파이프에 달대를 관통시켜 일단이 상기 제2콘크리트층의 하부에 고정되고, 타단이 상기 제1콘크리트층 상부에 고정되도록 하는 달대설치단계; 상기 제2콘크리트층의 강도가 일정강도 이상이 되면 상기 거푸집과 동바리를 해체하는 해체단계로 이루어지되, 작업수행이 더 필요하면, 상기 해체단계 후에 상기 터파기단계로 이동하여 반복 수행하도록 한다.The early dismantling method of the support includes a first concrete placing step of constructing a first concrete layer by placing concrete after assembling a hole pipe in a formwork; Digging step to excavate under the first concrete layer; A copper bar installation step of lowering the formwork and establishing a clubb on the lower part of the formwork to support the lower part of the formwork; A second concrete placing step of constructing a second concrete layer by assembling concrete after assembling the hole pipe to the formwork; A month installation step of allowing the moon pipe to pass through the hole pipe so that one end is fixed to the lower portion of the second concrete layer and the other end is fixed to the upper portion of the first concrete layer; When the strength of the second concrete layer is above a certain strength, the formwork and the copper bar are dismantled to be dismantled, but if further work is required, after the dismantling step, the dismantling step may be performed repeatedly.
이때, 상기 거푸집에는 받침판이 조립되되, 상기 달대의 일단은 상기 받침판에 조립되어 상기 콘크리트층을 받치도록 한다.At this time, the support plate is assembled to the formwork, one end of the moon is assembled to the support plate to support the concrete layer.
또한 상기 터파기작업은, 축조될 콘크리트층보다 더 깊이 굴착하도록 한다.The excavation also allows excavation deeper than the concrete layer to be constructed.
그리고, 상기 목적을 달성하기 위하여 본 발명의 달대장치는, 긴 봉 형상을 가지는 장볼트와; 상기 장볼트의 일단에 관통되어 장착되는 판형상의 받침판과; 상기 장볼트의 일단에 체결되어 상기 받침판을 지지하는 너트와; 상기 장볼트의 타단에 체결되어 다른 장볼트와 연결되는 커플링으로 이루어진다.And, in order to achieve the above object, the device according to the present invention, the long bolt having a long rod shape; A plate-shaped support plate penetrated and mounted at one end of the long bolt; A nut fastened to one end of the long bolt to support the support plate; Is coupled to the other end of the long bolt is made of a coupling connected to the other long bolt.
이하에서는 첨부된 도면을 참조하여 본 발명의 바람직한 실시예에 대하여 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail a preferred embodiment of the present invention.
도 1은 본 발명의 실시예에 따른 공정순서도이고, 도 2는 본 발명의 실시예에 따른 거푸집의 해체 전 상태를 간략하게 도시한 상태도이며, 도 3은 본 발명의 실시예에 따른 거푸집의 해체 후 상태를 간략하게 도시한 상태도이다.1 is a process flow chart according to an embodiment of the present invention, Figure 2 is a state diagram briefly showing a state before disassembly of the formwork according to an embodiment of the present invention, Figure 3 is the disassembly of the formwork according to an embodiment of the present invention It is a state diagram which briefly shows a state after.
도 1에 도시된 바와 같이, 본 발명은 제1콘크리트타설단계(S10)와 터파기단계(S20)와 동바리설치단계(S30)와 제2콘크리트타설단계(S40)와 달대설치단계(S50)와 해체단계(S60)로 이루어진다.As shown in Figure 1, the present invention is the first concrete placing step (S10) and the excavation step (S20) and copper bar installation step (S30) and the second concrete placing step (S40) and moon stand installation step (S50) and Dismantling step (S60) is made.
상기 제1콘크리트타설단계(S10)는, 거푸집(40)에 홀파이프(30)를 조립한 후에 콘크리트를 타설하여 제1콘크리트층을 축조하는 단계이다.The first concrete placing step (S10), after assembling the hole pipe 30 in the formwork 40 is to cast the concrete to build the first concrete layer.
상기 홀파이프(30)란 도 2 및 도 3에 도시된 바와 같이, 콘크리트 타설시 관통공을 형성하기 위한 것으로써, 상기 홀파이프(30)에 후술하는 달대(20)를 관통시키게 된다.As shown in FIGS. 2 and 3, the hole pipe 30 is for forming a through hole when placing concrete, and passes through the moon stand 20 to be described later in the hole pipe 30.
상기 터파기단계(S20)는 상기 제1콘트리트층 아래를 굴착하는 단계로써, 이는 상기 제1콘크리트층이 완전히 양생되면 수행하게 된다.The excavation step (S20) is a step of excavating under the first concrete layer, which is performed when the first concrete layer is completely cured.
이때, 상기 터파기작업은 축조될 콘크리트층보다 더 깊이 굴착하도록 함이 바람직하다.At this time, the digging operation is preferably to be excavated deeper than the concrete layer to be built.
즉, 지하2층을 축조할 경우에는 지하2층을 형성할 콘크리트층보다 더 깊이 대략 3m정도 더 굴착하도록 하는데, 이는 후술하는 동바리(50)를 설치하기 위함이 다.That is, when constructing the basement 2 floors to be excavated about 3m deeper than the concrete layer to form the basement 2 floor, this is to install the copper bar (50) to be described later.
상기 동바리설치단계(S30)는, 상기 거푸집(40)을 하강시키고 상기 거푸집(40)의 하부를 지지하도록 상기 거푸집(40)의 하부에 동바리(50)를 세우는 단계이다.The copper bar installation step (S30), is the step of lowering the formwork 40 and erecting the copper club 50 in the lower portion of the formwork 40 to support the lower portion of the formwork (40).
따라서 이때에는 상기 동바리(50)에 의해 상기 거푸집(40)이 지지된다.Therefore, at this time, the formwork 40 is supported by the grouping (50).
상기 제2콘크리트타설단계(S40)는, 상기 거푸집(40)에 상기 홀파이프(30)를 조립한 후에 콘크리트를 타설하여 제2콘크리트층(10)을 축조하는 단계로서, 상기 콘크리트 타설에 의해 그 하중은 상기 동바리(50)가 받게 된다.The second concrete placing step (S40), after assembling the hole pipe 30 in the formwork 40 to cast concrete to build a second concrete layer 10, by the concrete pouring The load is received by the group 50.
상기 달대설치단계(S50)는, 상기 홀파이프(30)에 달대(20)를 관통시켜 일단이 상기 제2콘크리트층(10)의 하부에 고정되고, 타단이 상기 제1콘크리트층 상부에 고정되도록 하는 단계로서 이는 도 3에 도시되어 있는 상태와 같다.The moon stand installation step (S50), so that one end is fixed to the lower portion of the second concrete layer 10 through the moon stand 20 through the hole pipe 30, the other end is fixed to the upper portion of the first concrete layer This is the same as the state shown in FIG.
이로 인해, 상기 거푸집(40)은 상기 달대(20)와 상기 동바리(50)에 의해 지지된다.Thus, the formwork 40 is supported by the moon 20 and the grouping (50).
이때, 상기 달대설치단계(S50)는 상기 제2콘크리트타설단계(S40)에서 홀파이프(30) 조립 후 콘크리트타설 전에 이루어질 수도 있다.At this time, the installation step (S50) may be made before the concrete pouring after assembling the hole pipe 30 in the second concrete placing step (S40).
상기 달대(20)의 일단 즉 상기 제2콘크리트층(10)의 하부에 고정된 부위에는 넓은 평판형상의 받침판(23)이 조립되도록 함이 바람직하다.One end of the moon 20, that is, a portion fixed to the lower portion of the second concrete layer 10, it is preferable to allow the wide plate-shaped support plate 23 to be assembled.
이때, 상기 받침판(23)에는 상기 달대(20) 자세하게는 후술하는 장볼트(21)가 관통할 수 있도록 관통공을 형성하도록 한다.At this time, the support plate 23 is to form a through-hole so that the long bolt 21 to be described later in detail to the moon 20.
상기 받침판(23)은 상기 제2콘크리트타설단계(S40)에서 거푸집(40)에 함께 장착되도록 함이 바람직하고, 이러한 상기 받침판(23)에 의해 상기 달대(20)는 보다 넓은 면적의 제2콘크리트층(10)을 지지할 수 있다.The support plate 23 is preferably to be mounted together with the formwork 40 in the second concrete placing step (S40), by the support plate 23 the moon 20 is a second concrete of a larger area Layer 10 may be supported.
그리고, 상기 달대(20)는 도 2에 도시된 바와 같이, 상기 홀파이프(30)를 관통하는 장볼트(21)와, 상기 장볼트(21)의 일단을 체결하는 너트(22)로 이루어지도록 함이 바람직하고, 상기 달대(20)는 그 상부에 있는 달대(20) 자세하게는 장볼트(21)와 커플링(24)을 통하여 상호 체결되도록 함이 바람직하다.And, as shown in FIG. 2, the moon 20 is made of a long bolt 21 through the hole pipe 30 and a nut 22 for fastening one end of the long bolt 21. Preferably, the moon 20 is preferably to be fastened to each other through the long bolt 21 and the coupling 24 in detail the moon 20 in the upper portion.
상기 해체단계(S60)는, 도 3에 도시된 바와 같이 상기 거푸집(40)과 동바리(50)를 해체하는 단계로서, 이는 상기 제2콘크리트층(10)의 강도가 일정강도 이상이 되면 상기 거푸집(40)과 동바리(50)를 상기 제2콘크리트층(10)으로부터 해체하는 단계이다.The dismantling step (S60), as shown in Figure 3 is the step of dismantling the formwork 40 and the club 50, which is when the strength of the second concrete layer 10 is more than a certain strength of the formwork 40 and the group 50 is dismantled from the second concrete layer (10).
상기 거푸집(40)과 동바리(50)의 해체로 인해, 상기 제2콘크리트층(10)은 상기 달대(20) 자세하게는 상기 받침판(23)에 의해 하부가 받쳐져 상기 달대(20)에 의해 상기 제1콘크리트층에 매달리게 된다.Due to the disassembly of the formwork 40 and the grouping 50, the second concrete layer 10 is supported by the pedestal plate 23, in detail, by the pedestal plate 23. It hangs on the first concrete layer.
이때, 상기 제2콘크리트층(10)은 어느 정도의 강도를 가지고 있기 때문에 상기 달매만으로 충분히 지지될 수 있다.In this case, since the second concrete layer 10 has a certain strength, the second concrete layer 10 may be sufficiently supported only by the hanging.
그리고, 지하층을 더 구축할 필요가 있으면, 상기 해체단계(S60) 후에 상기 터파기단계(S20)로 이동하여 반복 수행하여 지하 구조물을 건축할 수 있다.And, if it is necessary to further build the basement, after the dismantling step (S60) it can be carried out by repeatedly moving to the trench step (S20) to build an underground structure.
그리고, 본 발명의 달대장치는 상술한 바와 같이, 긴 봉 형상을 가지는 장볼트(21)와, 상기 장볼트(21)의 일단에 관통되어 장착되는 판형상의 받침판(23)과, 상기 장볼트(21)의 일단에 체결되어 상기 받침판(23)을 지지하는 너트(22)와, 상기 장볼트(21)의 타단에 체결되어 다른 장볼트와 연결되는 커플링(24)으로 이루어지도록 한다.In addition, as described above, the moon stand device of the present invention, the long bolt 21 having a long rod shape, a plate-shaped support plate 23 which is mounted through one end of the long bolt 21 and the long bolt ( 21 is fastened to one end of the support plate 23 to support the support plate 23, and the other end of the long bolt 21 is coupled to the coupling 24 is connected to the other long bolt.
본 발명은, 상기 제1콘크리트층이 지상1층이고 제2콘크리트층(10)이 지하1층으로 하여 수행할 수도 있으나, 상기 제1콘크리트층이 지하1층 이하이고 제2콘크리트층(10)이 상기 제1콘크리트층보다 한층 낮은 즉 지하2층 이하로 하여 수행되도록 함이 바람직하다.The present invention may be performed by the first concrete layer being one ground level and the second concrete layer 10 being the first underground layer, but the first concrete layer is one or less underground levels and the second concrete layer 10 is used. It is preferable to be carried out to be lower than that of the first concrete layer, that is, the second basement floor or less.
이와 같은 본 발명의 공법에 의해, 상기 콘크리트층은 상기 달대(20)와 상기 동바리(50)에 의해 지지되는바 보다 견고하게 지지될 수 있고, 콘크리트 타설시 상기 동바리(50)에 의해 거푸집(40)하부에서 지지되는바 거푸집(40)이 처지거나 휘어지는 것을 방지할 수 있으며, 상기 동바리(50)를 해체하고 곧바로 터파기작업을 수행할 수 있어 공사기간을 단축시킬 수 있다.By the construction method of the present invention as described above, the concrete layer can be supported more firmly as supported by the moon 20 and the copper bar 50, the formwork 40 by the copper bar 50 when placing concrete Bar to be supported at the bottom formwork 40 can be prevented from sagging or bent, and can dismantle the copper bar 50 and immediately perform the digging work can shorten the construction period.
또한, 콘크리트층이 일정강도 이상이 되면 비로소 상기 동바리(50)를 해체하는바, 상기 달대(20)를 적게 설치하여도 충분히 콘크리트층을 지지할 수 있어, 달대(20) 설치에 따른 비용 및 작업량을 줄일 수 있으며, 달대(20)의 수가 적게 되어 상기 거푸집(40)에서 철근작업 및 콘크리트타설시 작업자가 보다 쉽게 작업을 수행할 수 있다.In addition, when the concrete layer reaches a certain strength or more, the copper bar 50 is dismantled, and even if the moon stand 20 is installed in a small amount, the concrete layer can be sufficiently supported, and the cost and work amount according to the moon stand 20 installation. It is possible to reduce the number of the moon 20, the worker in the reinforcement work and concrete pouring in the formwork 40 can be carried out more easily.
또한, 콘크리트타설후에 달대(20)를 설치함으로, 철근작업 및 콘크리트타설시 상기 달대(20)가 없어 작업자가 장애물없이 보다 쉽게 작업을 수행할 수 있다.In addition, by installing the moon 20 after the concrete is placed, when the reinforcement work and concrete placing, there is no moon 20, the operator can perform the operation more easily without obstacles.
또한, 콘크리트층을 상기 동바리(50)와 달대(20)가 지지하고 있는바, 상기 거푸집(40)의 하부에 상술한 종래의 중량 및 대형 거푸집지지틀과 같은 것을 장착 할 필요가 없어 장비의 경량화를 이룰 있어 자재비용을 절감시킬 수 있다.In addition, the concrete bar is supported by the club 50 and the stand 20, there is no need to mount the same as the conventional weight and the large formwork support frame described above in the lower portion of the form 40, the weight of the equipment Material cost can be reduced.
본 발명인 지지대 조기 해체 공법 및 이에 사용되는 달대장치는 전술한 실시예에 국한하지 않고, 본 발명의 기술 사상이 허용되는 범위 내에서 다양하게 변형하여 실시할 수 있다.The present invention support early dismantling method and the apparatus used for this is not limited to the above-described embodiment, it can be carried out in a variety of modifications within the scope of the technical idea of the present invention.
이상에서 설명한 바와 같은 본 발명의 지지대 조기 해체 공법 및 이에 사용되는 달대장치에 따르면 다음과 같은 효과가 있다.According to the early support dismantling method of the present invention as described above and the moon device used therein, the following effects are obtained.
이와 같은 본 발명의 공법에 의해, 상기 콘크리트층은 상기 달대와 상기 동바리에 의해 지지되는바 보다 견고하게 지지될 수 있고, 콘크리트 타설시 상기 동바리에 의해 거푸집하부에서 지지되는바 거푸집이 처지거나 휘어지는 것을 방지할 수 있으며, 상기 동바리를 해체하고 곧바로 터파기작업을 수행할 수 있어 공사기간을 단축시킬 수 있다.By the construction method of the present invention, the concrete layer can be more firmly supported by the dal and the copper bar, and when the concrete is placed in the formwork is bent or deflected by the bottom bar by the copper bar, It can be prevented, the dismantling of the copper bar can be carried out immediately to the excavation work can be shortened construction period.
또한, 콘크리트층이 일정강도 이상이 되면 비로소 상기 동바리를 해체하는바, 상기 달대를 적게 설치하여도 충분히 콘크리트층을 지지할 수 있어, 달대 설치에 따른 비용 및 작업량을 줄일 수 있으며, 달대의 수가 적게 되어 상기 거푸집에서 철근작업 및 콘크리트타설시 작업자가 보다 쉽게 작업을 수행할 수 있다.In addition, when the concrete layer reaches a certain strength or more, the copper bar is dismantled, and even if the moon stand is installed little, the concrete floor can be sufficiently supported, thereby reducing the cost and work load due to the moon stand, and the number of the moon stand is small. When the reinforcement work and concrete pouring in the formwork, the worker can perform the work more easily.
또한, 콘크리트타설후에 달대를 설치함으로, 철근작업 및 콘크리트타설시 상기 달대가 없어 작업자가 장애물없이 보다 쉽게 작업을 수행할 수 있다.In addition, by installing the moon after the concrete installation, there is no said moon during reinforcing work and concrete placement, the operator can perform the work more easily without obstacles.
또한, 콘크리트층을 상기 동바리와 달대가 지지하고 있는바, 상기 거푸집의 하부에 상술한 종래의 중량 및 대형 거푸집지지틀과 같은 것을 장착할 필요가 없어 장비의 경량화를 이룰 있어 자재비용을 절감시킬 수 있다.In addition, the concrete layer is supported by the copper bar and the stand, there is no need to install the above-described conventional weight and large formwork frame such as the lower portion of the formwork to achieve a lighter weight of the equipment can reduce the material cost have.
또한, 상기 받침판에 의해 상기 콘크리트층을 보다 넓은 면적으로 지지할 수 있다.In addition, the support plate may support the concrete layer in a larger area.
또한, 상기 터파기작업을 축조될 콘크리트층보다 더 깊이 굴착하도록 함으로써, 상기 동바리가 상기 콘크리트층의 하부에서 지지하도록 할 수 있다.In addition, the excavation work can be excavated deeper than the concrete layer to be built, so that the copper bar is supported at the bottom of the concrete layer.

Claims (5)

  1. 삭제delete
  2. 콘크리트 지하층을 축조하는 거푸집 공법에 있어서,In the formwork for constructing the concrete basement floor,
    거푸집에 홀파이프를 조립한 후에 콘크리트를 타설하여 제1콘크리트층을 축조하는 제1콘크리트타설단계와;A first concrete placing step of constructing a first concrete layer by assembling concrete after assembling the hole pipe in the formwork;
    상기 제1콘트리트층 아래를 굴착하는 터파기단계와;A trench for excavating under the first concrete layer;
    상기 거푸집을 하강시키고, 상기 거푸집의 하부를 지지하도록 상기 거푸집의 하부에 동바리를 세우는 동바리설치단계와;A copper bar installation step of lowering the formwork and establishing a clubb on the lower part of the formwork to support the lower part of the formwork;
    상기 거푸집에 홀파이프를 조립한 후에 콘크리트를 타설하여 제2콘크리트층을 축조하는 제2콘크리트타설단계와;A second concrete placing step of constructing a second concrete layer by assembling concrete after assembling the hole pipe in the formwork;
    상기 홀파이프에 달대를 관통시켜 일단이 상기 제2콘크리트층의 하부에 고정되고, 타단이 상기 제1콘크리트층 상부에 고정되도록 하는 달대설치단계와;A month installation step of allowing the moon pipe to pass through the hole pipe so that one end is fixed to the lower portion of the second concrete layer and the other end is fixed to the upper portion of the first concrete layer;
    상기 제2콘크리트층의 강도가 일정강도 이상이 되면 상기 거푸집과 동바리를 해체하는 해체단계로 이루어지되,When the strength of the second concrete layer is more than a certain strength is made of a dismantling step of dismantling the formwork and copper bar,
    작업수행이 더 필요하면, 상기 해체단계 후에 상기 터파기단계로 이동하여 반복 수행하고, If more work is needed, after the dismantling step, go to the digging step and repeat,
    상기 달대설치단계는, 상기 제2콘크리트타설단계 이후에 이루어지는 것을 특징으로 하는 지지대 조기 해체 공법.Wherein the installation step, the support early dismantling method, characterized in that made after the second concrete pouring step.
  3. 제 2항에 있어서,The method of claim 2,
    상기 거푸집에는 받침판이 조립되되,The base plate is assembled to the formwork,
    상기 달대의 일단은 상기 받침판에 조립되어 상기 콘크리트층을 받치도록 하는 것을 특징으로 하는 지지대 조기 해체 공법.One end of the moon is assembled to the support plate to support the early dismantling method, characterized in that to support the concrete layer.
  4. 제 2항 또는 제 3항에 있어서,The method of claim 2 or 3,
    상기 터파기작업은,The digging operation,
    축조될 콘크리트층보다 더 깊이 굴착하는 것을 특징으로 하는 지지대 조기 해체 공법.Early dismantling of the support, characterized in that the excavation deeper than the concrete layer to be constructed.
  5. 삭제delete
KR1020050099142A 2005-10-20 2005-10-20 Early remove support method KR100650134B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050099142A KR100650134B1 (en) 2005-10-20 2005-10-20 Early remove support method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050099142A KR100650134B1 (en) 2005-10-20 2005-10-20 Early remove support method

Publications (1)

Publication Number Publication Date
KR100650134B1 true KR100650134B1 (en) 2006-11-27

Family

ID=37713657

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050099142A KR100650134B1 (en) 2005-10-20 2005-10-20 Early remove support method

Country Status (1)

Country Link
KR (1) KR100650134B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121314A (en) * 2010-12-31 2011-07-13 李万山 Beam-slab framework early removal construction method
CN102787719A (en) * 2012-08-27 2012-11-21 泰博混凝土模板与支撑(陕西)有限公司 Formwork early removing mechanism and early removing formwork system
CN108560908A (en) * 2018-01-26 2018-09-21 东莞市九豪投资有限公司 A kind of support device of early stripping formwork system

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1701113A (en) * 1927-05-09 1929-02-05 Will E Keller Method of and apparatus for pouring concrete walls and floors of steel and concrete frame buildings
US5460499A (en) * 1993-08-27 1995-10-24 Franklin; James W. Concrete building frame construction apparatus
JPH08253946A (en) * 1995-03-17 1996-10-01 Fujita Corp Reverse placing method for concrete of underground structure under road
JPH09316900A (en) * 1996-05-31 1997-12-09 Hazama Gumi Ltd Top-down construction method
KR20000018037A (en) * 2000-01-05 2000-04-06 박정진 Hanging form system
KR200189795Y1 (en) * 1998-05-14 2000-09-01 형난옥 A game set comprising of seven blocks
JP2001107559A (en) * 1999-10-12 2001-04-17 Marui Sangyo Co Ltd Hanging fitting for concrete form
KR20040104218A (en) * 2003-06-03 2004-12-10 삼지건설(주) Construction method for Sub-terranean slab of Sink-down method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1701113A (en) * 1927-05-09 1929-02-05 Will E Keller Method of and apparatus for pouring concrete walls and floors of steel and concrete frame buildings
US5460499A (en) * 1993-08-27 1995-10-24 Franklin; James W. Concrete building frame construction apparatus
JPH08253946A (en) * 1995-03-17 1996-10-01 Fujita Corp Reverse placing method for concrete of underground structure under road
JPH09316900A (en) * 1996-05-31 1997-12-09 Hazama Gumi Ltd Top-down construction method
KR200189795Y1 (en) * 1998-05-14 2000-09-01 형난옥 A game set comprising of seven blocks
JP2001107559A (en) * 1999-10-12 2001-04-17 Marui Sangyo Co Ltd Hanging fitting for concrete form
KR20000018037A (en) * 2000-01-05 2000-04-06 박정진 Hanging form system
KR20040104218A (en) * 2003-06-03 2004-12-10 삼지건설(주) Construction method for Sub-terranean slab of Sink-down method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1020040104218

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102121314A (en) * 2010-12-31 2011-07-13 李万山 Beam-slab framework early removal construction method
CN102787719A (en) * 2012-08-27 2012-11-21 泰博混凝土模板与支撑(陕西)有限公司 Formwork early removing mechanism and early removing formwork system
CN108560908A (en) * 2018-01-26 2018-09-21 东莞市九豪投资有限公司 A kind of support device of early stripping formwork system

Similar Documents

Publication Publication Date Title
JP3644605B2 (en) Reverse driving method of underground structure under road surface.
KR100775767B1 (en) Top-down method using the vertical steel bar for the src column
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
KR100650134B1 (en) Early remove support method
KR20060096706A (en) Deck suspension top-down method of sub-structure
KR101401057B1 (en) Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed
KR100821663B1 (en) Construction method of Top-down concrete slab
KR100662524B1 (en) Double pipe girder struts as permanent system
JP4611113B2 (en) Integrated construction method of pile and column
KR101908943B1 (en) RC WALL STRUCTURE FOR TOP-DOWN AND METHOD FOR CONSTRUCTING THE STRUCTUREa
KR200390421Y1 (en) Top-down substructure by deck suspension
KR20120064833A (en) Construction method for reducing temporarily material in top-down method
KR20190022132A (en) Top-down method using precast-concrete colum
JP2001317217A (en) Base isolation building construction under foundation of exiting building
KR20050122763A (en) A deck supportframe and a construction methed
KR101687495B1 (en) Partial top-down construction method for building underground structures
JP2018066220A (en) Reconstruction method of underground skeleton
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
KR100615149B1 (en) A method of construction top-down for the ground fabric construction
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR101414155B1 (en) Self-supported shoring structure using shelf and construction method using the relieving platform
KR20160050516A (en) Downward construction method for hybrid structure system using a temporary bracket and a long span deck
JP5123967B2 (en) Seismic isolation method
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20091111

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20121204

Year of fee payment: 7

LAPS Lapse due to unpaid annual fee