KR101335796B1 - Apparatus for supporting form of underground building and method of constructing the underground building using the same - Google Patents

Apparatus for supporting form of underground building and method of constructing the underground building using the same Download PDF

Info

Publication number
KR101335796B1
KR101335796B1 KR1020120047022A KR20120047022A KR101335796B1 KR 101335796 B1 KR101335796 B1 KR 101335796B1 KR 1020120047022 A KR1020120047022 A KR 1020120047022A KR 20120047022 A KR20120047022 A KR 20120047022A KR 101335796 B1 KR101335796 B1 KR 101335796B1
Authority
KR
South Korea
Prior art keywords
basement
formwork
suspension
underground
ground
Prior art date
Application number
KR1020120047022A
Other languages
Korean (ko)
Other versions
KR20130123697A (en
Inventor
권순철
김일호
석재원
Original Assignee
코오롱글로벌 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 코오롱글로벌 주식회사 filed Critical 코오롱글로벌 주식회사
Priority to KR1020120047022A priority Critical patent/KR101335796B1/en
Publication of KR20130123697A publication Critical patent/KR20130123697A/en
Application granted granted Critical
Publication of KR101335796B1 publication Critical patent/KR101335796B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/38Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings for plane ceilings of concrete
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L3/00Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

본 발명은 구조적의 단순화 및 경량화를 통해 그 설치 및 하강작업이 매우 간편하여 무지보 역타설 지하구조물의 구축작업을 효율적으로 진행할 수 있는 지하구조물의 현수식 거푸집 지지장치 및 이를 이용한 무지보 역타설 지하구조물의 구축방법에 관한 것이다.
본 발명에 의한 지하구조물의 현수식 거푸집 지지장치는 지하층 구조물의 골조기둥의 좌우 양측에 대칭적으로 배치된 복수의 지지브라켓; 상기 복수의 지지브라켓의 길이방향에 대해 직교하는 방향으로 가로질러 설치되는 복수의 크로스부재; 및 상기 복수의 지지브라켓을 현수지지하는 현수재가 연결된 현수유닛;을 포함한다.
The present invention is a simple support structure for the suspended formwork of the underground structure that can be efficiently carried out the construction work of the non-reinforced underground structure through the installation and descent work very simple and light weight, and the non-reversed basement underground using the same It relates to a construction method of the structure.
Suspended formwork supporting device of the underground structure according to the present invention comprises a plurality of support brackets symmetrically disposed on both left and right sides of the frame pillar of the basement structure; A plurality of cross members installed in a direction orthogonal to a longitudinal direction of the plurality of support brackets; And a suspension unit to which suspension materials for suspending the plurality of support brackets are connected.

Description

지하구조물의 현수식 거푸집 지지장치 및 이를 이용한 무지보 역타설 지하구조물의 구축방법{APPARATUS FOR SUPPORTING FORM OF UNDERGROUND BUILDING AND METHOD OF CONSTRUCTING THE UNDERGROUND BUILDING USING THE SAME} Suspended formwork supporting device for underground structures and construction method for unsupported reverse casting underground structure using the same {APPARATUS FOR SUPPORTING FORM OF UNDERGROUND BUILDING AND METHOD OF CONSTRUCTING THE UNDERGROUND BUILDING USING THE SAME}

본 발명은 지하구조물에 관한 것으로, 보다 상세하게는 구조적의 단순화 및 경량화를 통해 그 설치 및 하강작업이 매우 간편하여 무지보 역타설 지하구조물의 구축작업을 효율적으로 진행할 수 있는 지하구조물의 현수식 거푸집 지지장치 및 이를 이용한 무지보 역타설 지하구조물의 구축방법에 관한 것이다. The present invention relates to an underground structure, and more particularly, the installation and descent work is very simple through the structural simplification and light weight, so that the suspended formwork of the underground structure that can efficiently proceed the construction work of the unsupported underground placing structure The present invention relates to a support device and a method for constructing a non-supported reverse casting underground structure using the same.

일반적으로 지하구조물을 구축하는 방법으로는 순타설공법과 역타설공법 등이 있다. In general, there are methods for constructing underground structures such as forward pouring and reverse pouring.

순타설공법은 지하구조물이 축조되는 지반에 흙막이 공사를 한 다음 지반을 굴착하면서 흙막이를 지지할 수 있는 가시설물을 설치하고, 토사를 전부 반출한 뒤 맨 아래층부터 구조물을 축조해 올라가는 공법이고, 역타설공법은 흙막이를 시공하고 1층 구조물을 축조한 다음 그 구조물을 흙막이용 버팀부재로 이용하여 상부에서 하부로 지반을 굴착하면서 구조물을 축조해 내려가는 공법이다. The net pouring method is a method of constructing a structure on the ground where underground structures are constructed, then installing a temporary facility to support the soil wall while excavating the ground, and after lifting up all the soil, constructing the structure from the bottom floor. The pour method is a method of constructing a structure and constructing a one-story structure, and then constructing the structure while digging the ground from the top to the bottom using the structure as a support member for the barrier.

최근 토지 이용의 극대화 차원에서 지하공사가 점차 고심도화되고 있고, 특히 순타설공법에 의한 시공시에는 흙막이 붕괴의 위험이나 주변 건물들 침하 등으로 인한 균열 발생은 물론, 시각적으로도 불안할 뿐만 아니라 공사기간이 길어지는 등 여러 문제가 있어서, 근래에는 역타설공법이 널리 적용되고 있다.In recent years, underground construction has been increasingly intensified in order to maximize land use. In particular, when the construction is carried out by the net pouring method, not only the construction of cracks due to the risk of earthquake collapse or the settlement of nearby buildings, but also visually unstable construction Due to various problems such as long periods of time, the reverse casting method has been widely applied in recent years.

이 역타설공법은 흙막이벽 및 그 안쪽 지중의 골조용 기둥을 시공한 뒤 슬래브 및 보 등의 지하구조물을 지상 1층부터 지하층을 향하여 단계적으로 시공해 내려가는 방식이므로, 지하구조물과 지상구조물의 시공이 동시에 진행 가능하고, 지상 1층의 바닥을 작업장으로 활용할 수 있어 별도의 복공판이 필요하지 않으며, 무지보 거푸집 작업이 가능하다는 장점이 있다.In this reverse casting method, after constructing the retaining wall and the frame for the underground frame, the underground structures such as slabs and beams are constructed step by step from the ground floor to the underground floor. It can proceed at the same time, the floor of the ground floor can be utilized as a workshop, there is no need for a separate perforated plate, there is an advantage that the work can be plain.

이러한 역타설공법으로는 지반을 정지한 상태에서 지반 위에 콘크리트 슬래브와 보를 타설하는 방법(Concrete on Grade)과, 지반을 어느 정도 굴착하고 지반을 고른 뒤 동바리(staging, floor post)를 세우고 거푸집을 설치하여 콘크리트를 타설하는 방법(Form on Supporting)과, 거푸집 지지를 위한 동바리를 세우지 않는 대신에 선 시공한 상층 콘크리트 슬래브에 거푸집을 현수시켜 콘크리트를 타설하는 방법(무지보 역타설 현수 거푸집 공법) 등이 있다.Such a reverse casting method involves placing concrete slabs and beams on the ground while the ground is stopped (Concrete on Grade), excaving the ground to some extent, selecting the ground, then setting up staging (floor posts) and installing the formwork. Form on Supporting, and the method of placing concrete by suspending formwork on the upper concrete slab, instead of setting up a ridge for supporting formwork (unsupported reversal suspension formwork). have.

이중에서 동바리를 이용하는 공법은 상대밀도가 비교적 높은 지층에 적용하는 공법으로서, 지반을 선 굴착한 후 굴착된 지반 위에 버림 콘크리트를 타설하고, 이 버림 콘크리트를 지지기반으로 하여 동바리와 보 거푸집 및 슬래브 거푸집을 설치한 뒤, 보 및 슬래브의 콘크리트를 타설하는 공법이다.여기서, 보 거푸집 및 슬래브 거푸집은 굴착 지반 위의 버림 콘크리트상에서 동바리에 의해 지지되어진다.The method of using copper barley is a method applied to strata with relatively high relative density. After drilling the ground, the cast concrete is placed on the excavated ground, and the cast concrete is used as the support base for the copper bar, the formwork and the slab formwork. After the installation, the concrete of the beam and slab is poured. Here, the beam formwork and the slab formwork are supported by copper bars on the discarded concrete on the excavation ground.

그러나, 동바리의 이용시에는 연약지반상에서의 지지가 불안정하고, 또한 콘크리트 강도가 일정 한도 이상으로 보양되지 않으면 해체가 불가하기 때문에 콘크리트 양생 중 동바리의 존치로 인하여 아래층의 굴토공사가 진행될 수 없다.However, when the copper barrier is used, support on the soft ground is unstable and dismantlement is impossible unless the concrete strength is maintained above a certain limit.

더구나, 거푸집, 동바리 등 가설자재를 굴토작업장 외부로 반출한 뒤 굴토 후 다시 아래층으로 이동하여 재설치해야 하고, 이를 각 층의 시공시마다 반복해야 하는 바, 이러한 작업을 반복 수행하는데 있어서 번잡한 문제점이 있게 된다.In addition, the temporary materials such as formwork, dongbari, etc. should be taken out of the Gulto workshop and moved back to the lower floor after reconstruction, and this should be repeated for each floor construction. do.

또한, 콘크리트를 부어 넣은 뒤 충분한 양생기간을 거쳐 구조체가 제강도를 발현할 때까지 기다려야 하므로 작업대기 시간이 불가피하게 발생하고, 동바리나 거푸집의 소운반 및 재조립에 소요되는 비용과 시간이 과다하여 비경제적일 뿐만 아니라 모든 작업이 인력에 의존하므로 노동집약적이어서 기능공의 인력 부족이 심화되는 현실에서 원가 절감이 어려워지는 등의 문제점이 있게 된다.In addition, after the concrete is poured, it is necessary to wait until the structure develops the steelmaking strength after sufficient curing period. Therefore, waiting time is inevitably generated, and the cost and time required for transporting and reassembling the copper bar or formwork are excessive. In addition to being economical, all work depends on manpower, which is labor intensive, which leads to problems such as difficulty in cost reduction in a situation in which labor force shortages intensify.

한편, 동바리 사용시의 문제점을 해결하기 위하여, 지하구조물을 축조할 때 지상 1층부터 지하 최저층을 향해 구축해 나가는 무지보 역타설 거푸집 공법(Non Supporting Formwork System for Top Down Construction)으로서, 거푸집 지지용 동바리를 설치하지 않는 대신, 선 시공한 상층 슬래브 측에 거푸집을 현수시키는 무지보 역타설 현수 거푸집 공법이 제시된 바 있다.On the other hand, in order to solve the problem of using the grouping, as a non-supporting formwork system for top down construction that is constructed from the ground floor to the lowest basement when building underground structures, Instead of installing it, an unsupported reversal suspension formwork was proposed to suspend formwork on the upper slab side.

이 무지보 역타설 현수 거푸집 공법은 선 시공한 상층 슬래브에 와이어 등과 같은 현수재를 이용하여 거푸집을 현수시킨 상태에서 이 거푸집을 이용하여 하층의 슬래브를 시공하는 방법이다.This unsupported back-casting formwork is a method of constructing a lower slab using the formwork, while the formwork is suspended by using a suspension material such as wire to the upper slab pre-installed.

이 방법을 이용하여 각 층의 지하구조물을 축조하기 위해서는, 거푸집에 콘크리트를 타설하여 상층 슬래브를 시공하는 단계, 이 상층 슬래브의 시공시에 이용된 거푸집을 상층 슬래브 위의 유압식 현수장치를 이용하여 하강시키는 단계, 이 하강된 거푸집을 이용해 하층 슬래브를 시공하는 단계를 각 층마다 반복하게 된다.In order to build the underground structure of each floor by using this method, concrete is laid on the formwork to construct upper slab, and the formwork used in the construction of the upper slab is lowered by using hydraulic suspension device on the upper slab. The lowering slab is constructed by using the lowered formwork for each floor.

이러한 현수식 공법은, 슬래브 거푸집 및 보 거푸집 하부에 동바리를 설치하지 않고 거푸집을 상층 슬래브에 매달아 설치하기 때문에, 작업장 확보 및 작업자의 안전보장 측면에서 보다 유리하고, 거푸집 작업과 상관없이 지하 터파기를 연속적으로 진행할 수 있으며, 충분한 양생기간 확보로 우수한 콘크리트 품질을 얻을 수 있는 동시에 공기 단축 및 원가 절감이 가능해지는 장점이 있다.This suspension method is more advantageous in terms of securing the workplace and safety of the worker, because it is installed in the upper slab without installing the copper bar at the bottom of the slab formwork and the beam formwork. It is possible to proceed to, and by obtaining a sufficient curing period can be obtained excellent concrete quality at the same time has the advantage of shortening the air and reducing the cost.

특히, 현수식 공법을 적용하는 경우에는 상층 슬래브에 현수된 거푸집을 연속적으로 달아내리는 지하 골조공사, 하부에서의 굴토공사, 그리고 지상부 구조물 축조공사의 3단계 공정을 동시에 진행할 수 있게 된다.In particular, when the suspension method is applied, it is possible to simultaneously perform the three-stage process of underground frame construction, which continuously runs down the formwork suspended from the upper slab, the excavation work from the bottom, and the ground structure construction.

이러한 현수식 공법은 유압식 현수장치 및 현수재가 모두 상층 슬래브 측에 지지된 상태에서 하층 슬래브의 콘크리트 시공이 이루어진다. 즉, 하층 슬래브로 타설되는 콘크리트의 하중이 거푸집 및 현수재를 통해 전적으로 상층 슬래브에 지지되는 시스템으로 되어 있다.In this suspension method, the concrete construction of the lower slab is performed while both the hydraulic suspension device and the suspension material are supported on the upper slab side. In other words, it is a system in which the load of concrete poured into the lower slab is entirely supported by the upper slab through formwork and suspension.

또한, 종래의 현수식 공법은 유압식 현수장치의 설치 및 전용에 따른 비용부담이 높아지고, 또한 거푸집을 지지하기 위한 구조물이 복잡하게 구성될 뿐만 아니라 그 중량이 상대적으로 무거워 인력에 의한 작업이 불가능한 단점이 있었다. In addition, the conventional suspension method has a high cost burden due to the installation and conversion of the hydraulic suspension device, and the structure for supporting the formwork is not only complicated structure, but also the weight is relatively heavy, which is impossible to work by manpower there was.

또한, 종래의 현수식 공법은 거푸집에 타설되는 하층 구조물의 하중이 전적으로 바로 위(직상)의 상층 구조물에 작용하면서 상층 슬래브에 무리한 하중이 가해질 수 있고, 구조적 안정성을 최대한 확보하기 위해서는 하층 슬래브의 콘크리트 시공이 필연적으로 상층 슬래브의 시공이 완료된 후라야 가능하다. 결국, 선 시공된 상측 슬래브의 완전 양생을 위해 시간이 필요한 만큼 공기 지연의 문제가 불가피하게 발생하게 된다.In addition, in the conventional suspension method, while the load of the lower layer structure placed in the formwork acts on the upper structure directly above (directly), an excessive load may be applied to the upper slab, and in order to secure the structural stability to the maximum, the lower slab concrete Construction is inevitable only after the construction of the upper slab is completed. As a result, the problem of air delay inevitably occurs as time is required for the complete curing of the pre-installed upper slab.

본 발명은 상기와 같은 점을 감안하여 안출한 것으로, 구조적의 단순화 및 경량화를 통해 그 설치 및 하강작업이 매우 간편하여 무지보 역타설 지하구조물의 구축작업을 효율적으로 진행할 수 있는 지하구조물의 현수식 거푸집 지지장치 및 이를 이용한 무지보 역타설 지하구조물의 구축방법을 제공하는 데 그 목적이 있다. The present invention has been made in view of the above points, the installation and descending work is very easy through the simplified and lightweight structure of the suspension structure of the underground structure that can efficiently proceed the construction work of the unsupported underground placing structure The purpose of the present invention is to provide a formwork supporting device and a method for constructing a non-supported retrocast underground structure.

상기와 같은 목적을 달성하기 위한 본 발명의 일측면은 지상 1층 구조물로부터 지하층을 향하여 복수의 지하층 구조물을 단계적으로 시공하는 무지보 역타설 지하구조물의 콘크리트 타설을 위한 거푸집을 지지하기 위한 지하구조물의 현수식 거푸집 지지장치로서, One aspect of the present invention for achieving the above object is an underground structure for supporting the formwork for the concrete casting of the unsupported inverse placing underground structure for constructing a plurality of basement structure step by step from the ground one-story structure to the basement floor As a suspension formwork,

지하층 구조물의 골조기둥의 좌우 양측에 대칭적으로 배치된 복수의 지지브라켓; 상기 복수의 지지브라켓의 길이방향에 대해 직교하는 방향으로 가로질러 설치되는 복수의 크로스부재; 및 상기 복수의 지지브라켓을 지상 1층 구조물 측에서 현수지지하는 현수재를 가진 현수유닛;을 포함하고, A plurality of support brackets symmetrically disposed on both left and right sides of the frame pillar of the basement structure; A plurality of cross members installed in a direction orthogonal to a longitudinal direction of the plurality of support brackets; And a suspension unit having a suspension material for supporting the plurality of support brackets on the ground floor structure side.

상기 복수의 지지브라켓은 상기 골조기둥의 폭방향에서 좌우 양측에 2열의 지지브라켓이 대칭적으로 배치되며, 각 열의 지지브라켓들은 지하층 구조물의 보를 따라 길이방향으로 인접하여 배치되고, 상기 각 열의 지지브라켓들의 서로 마주보는 단부들은 연결브라켓을 매개로 서로 연결되며, 상기 복수의 크로스부재는 2열로 배치된 지지브라켓들을 가로질러 설치되고, 상기 골조기둥의 전면 및 후면 각각에는 스톱플레이트가 대칭적으로 설치되며, 각 스톱플레이트의 좌우 양측은 골조기둥의 좌우 측에서 돌출하고, 상기 복수의 지지브라켓 중에서 골조기둥에 인접한 지지브라켓들은 상기 스톱플레이트의 상면에 대칭적으로 지지되며, 상기 현수유닛의 현수재는 지상 1층 구조물의 보 및 지하층 구조물의 보를 수직방향으로 관통하여 그 하단이 현재 타설 진행 중인 지하층 구조물의 보에 인접한 지지브라켓 측에 고정되는 것을 특징으로 한다. The plurality of support brackets are symmetrically arranged in two rows of support brackets on the left and right sides in the width direction of the frame pillar, the support brackets in each row are disposed adjacent in the longitudinal direction along the beam of the basement structure, the support brackets in each row End of each other is connected to each other via a connecting bracket, the plurality of cross members are installed across the support brackets arranged in two rows, the stop plate is symmetrically installed on each of the front and rear of the frame pillar The left and right sides of each stop plate protrude from the left and right sides of the frame pillar, and support brackets adjacent to the frame pillars of the plurality of support brackets are symmetrically supported on the top surface of the stop plate, and the suspension of the suspension unit is ground 1. Vertically penetrates the beams of the layer structure and the beams of the basement structure Installation characterized in that fixed to the adjacent side of the support bracket to the beam structure of the basement that is in progress.

상기 지지브라켓은 웨브 및 상기 웨브의 양측에 상기 웨브에 대해 직교하는 방향으로 연결된 플랜지를 가진 H빔 구조로 구성되고, 연결브라켓은 상기 지지브라켓의 웨브 측에 결합되는 것을 특징으로 한다. The support bracket is composed of an H beam structure having a web and a flange connected in a direction orthogonal to the web on both sides of the web, and the connection bracket is coupled to the web side of the support bracket.

상기 현수유닛은 지상 1층 구조물의 상면에 배치되고, 상기 현수유닛의 현수재는 지하층 구조물의 보에 인접한 지지브라켓의 상단에 고정되는 것을 특징으로 한다. The suspension unit is disposed on the upper surface of the ground-floor structure, the suspension of the suspension unit is characterized in that it is fixed to the upper end of the support bracket adjacent to the beam of the underground structure.

지하층 구조물의 보에 인접한 지지브라켓의 상단에는 고리부가 형성되고, 상기 고리부에는 상기 현수재의 하단이 고정되는 것을 특징으로 한다. The upper end of the support bracket adjacent to the beam of the basement structure is formed with a ring, characterized in that the lower end of the suspension is fixed to the ring.

지상 1층 구조물의 보 및 지하층 구조물의 보에는 수직방향으로 관통하는 관통공이 형성되고, 상기 현수재는 지상 1층 구조물 및 상기 지하층 구조물들의 관통공들을 관통하여 수직방향으로 설치되는 것을 특징으로 한다. The beams of the ground level structure and the beams of the basement layer structure are formed through holes penetrating in the vertical direction, the suspension is characterized in that installed in the vertical direction through the through holes of the ground layer structure and the underground layer structures.

상기 지하층 구조물의 관통공에 인접하여 하중 분산유닛이 설치되고, 상기 하중 분산유닛은 현재 타설이 진행 중인 지하층 구조물의 하중을 지상 1층 구조물 및 그 직상의 지하층 구조물 측으로 분산하도록 구성되는 것을 특징으로 한다. A load dispersing unit is installed adjacent to the through hole of the basement structure, and the load distributing unit is configured to distribute the load of the basement structure currently being poured to the ground aboveground structure and the basement structure directly above. .

본 발명의 다른 측면은 상술한 지하구조물의 현수식 거푸집 지지장치를 이용한 무지보 역타설 지하구조물의 구축방법으로,Another aspect of the present invention is a method for constructing an unsupported retro-casting underground structure using the suspension formwork supporting device of the above-described underground structure,

지상 1층 구조물을 시공하는 지상 1층 구조물 시공단계; 및 상기 지상 1층 구조물의 지하에 층단위로 배치되는 복수의 지하층 구조물을 단계적으로 시공하는 지하층 구조물 시공단계;로 이루어지고, A first floor structure construction step of constructing a first floor structure; And an underground floor structure construction step of constructing a plurality of underground floor structures disposed in units of floors in the basement of the ground floor structure;

상기 지하층 구조물 시공단계는, 지하층 구조물의 콘크리트 타설을 위한 거푸집 및 상기 거푸집을 지지하기 위한 거푸집 지지장치를 설치하며, 상기 거푸집 지지장치는 복수의 지지브라켓에 의해 상향으로 지지됨과 더불어 지상 1층 구조물의 상면에 설치된 현수유닛으로부터 연결된 현수재에 의해 현수지지되게 설치되고, 상기 거푸집 측에 콘크리트를 타설함으로써 복수의 지하층 구조물을 시공하는 것을 특징으로 한다. In the construction of the basement layer structure, the formwork for concrete placing of the basement structure and the formwork support device for supporting the formwork are installed, and the formwork support device is supported upward by a plurality of support brackets, It is installed to be suspended by a suspension material connected from a suspension unit installed on the upper surface, it characterized in that the construction of a plurality of basement floor structure by pouring concrete on the formwork side.

본 발명에 의하면, 거푸집을 지지하는 구성요소의 간소화 및 경량화 등을 통해 유압식 현수장치의 설치가 필요하지 않아 그 시공비용이 절감되고, 또한 타설되는 하층 구조물 및 거푸집에 대한 하중을 지상 1층 구조물 및 그 직상측의 지하층 구조물 측에서 분산하여 지지함으로써 하중 분산을 효과적으로 구현함과 더불어 직상의 상층 지하구조물의 양생조건에 영향을 받지 않으므로 공사진행 시에 대기시간을 대폭 줄여 시공기간의 확보가 유리한 장점이 있다. According to the present invention, since the installation of the hydraulic suspension device is not necessary through the simplification and the weight reduction of the components supporting the formwork, the construction cost is reduced, and the load on the lower layer structure and the formwork to be poured is placed on the ground floor 1 layer structure and By distributing and supporting at the basement structure on the upper side, the load distribution is effectively realized and it is not affected by the curing conditions of the upper structure on the upper layer. have.

도 1은 본 발명에 의한 거푸집 지지장치에 의해 무지보 역타설 지하구조물이 구축되는 상태를 도시한 도면이다.
도 2는 도 1의 화살표 A부분을 확대한 도면이다.
도 3은 도 2의 B-B선을 따라 도시한 도면이다.
도 4는 도 3의 C-C선을 따라 도시한 도면이다.
도 5는 도 1의 화살표 D부분을 확대한 도면이다.
도 6은 본 발명의 거푸집 지지장치의 일 실시예에 따른 하중 분산유닛을 도시한 사시도이다.
도 7은 본 발명의 거푸집 지지장치의 다른 실시예에 따른 하중 분산유닛을 도시한 정면도이다.
도 8은 도 7의 화살표 E방향에서 바라본 평면도이다.
도 9는 본 발명에 의한 거푸집 지지장치를 이용한 무지보 역타설 지하구조물의 구축방법을 도시한 공정도이다.
1 is a view showing a state in which the non-reinforced inverse underground structure is constructed by the formwork supporting apparatus according to the present invention.
FIG. 2 is an enlarged view of a portion A of FIG. 1.
Fig. 3 is a view along the line BB in Fig.
FIG. 4 is a view along the line CC of FIG. 3.
5 is an enlarged view of a portion D of FIG. 1.
6 is a perspective view showing a load distribution unit according to an embodiment of the formwork supporting apparatus of the present invention.
7 is a front view showing a load distribution unit according to another embodiment of the formwork supporting apparatus of the present invention.
FIG. 8 is a plan view viewed from the arrow E direction of FIG. 7.
9 is a process chart showing a method for constructing a non-supported reinforcement underground structure using a formwork supporting device according to the present invention.

이하, 본 발명의 바람직한 실시예를 첨부된 도면을 참조하여 상세히 설명한다. 참고로, 본 발명을 설명하는 데 참조하는 도면에 도시된 구성요소의 크기, 선의 두께 등은 이해의 편의상 다소 과장되게 표현되어 있을 수 있다. 또, 본 발명의 설명에 사용되는 용어들은 본 발명에서의 기능을 고려하여 정의한 것이므로 사용자, 운용자 의도, 관례 등에 따라 달라질 수 있다. 따라서, 이 용어에 대한 정의는 본 명세서의 전반에 걸친 내용을 토대로 내리는 것이 마땅하겠다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. For the sake of convenience, the size, line thickness, and the like of the components shown in the drawings referenced in the description of the present invention may be exaggerated somewhat. The terms used in the description of the present invention are defined in consideration of the functions of the present invention, and thus may be changed depending on the user, the intention of the operator, customs, and the like. Therefore, the definition of this term should be based on the contents of this specification as a whole.

도 1에 도시된 바와 같이, 지하구조물은 지상 1층 구조물(10)의 지하 측에 지하를 향해 복수층의 지하층 구조물(11, 12)이 층단위로 시공되고, 복수의 지하층 구조물(11, 12)은 지하 1층 구조물(11), 지하 2층 구조물(12) 등으로 이루어진다. 한편, 도 1에서는 지하 2층 구조물(12)까지만 도시되어 있지만, 본 발명은 이에 한정되지 않고, 지하 2층 구조물(12)의 하측에 지하 3층 구조물, 지하 4층 구조물, 지하 5층 구조물 등이 연속적으로 더 배치될 수 있다. 이에 본 명세서에서는 지상 1층 구조물(10)의 하측에 배치되는 지하 1층 구조물, 지하 2층 구조물, 지하 3층 구조물 등을 통칭하여 "지하층 구조물"이라 정의한다. 이하에서는 "지하층 구조물"을 지하 1층 구조물, 지하 2층 구조물, 지하 3층 구조물, 지하 4층 구조물, 지하 5층 구조물 등을 의미한다. As shown in FIG. 1, in the underground structure, a plurality of basement layer structures 11 and 12 are constructed in units of layers toward the basement on the basement side of the ground layer 1 structure 10, and the plurality of basement layer structures 11 and 12. ) Is composed of the first basement structure 11, the second underground structure 12 and the like. Meanwhile, in FIG. 1, only up to the two-story underground structure 12 is illustrated, but the present invention is not limited thereto. The three-story underground structure, the four-story underground structure, the five-story underground structure, etc., are located below the two-story underground structure 12. This may be further arranged continuously. Thus, in the present specification, the basement 1 floor structure, the basement 2 floor structure, and the basement 3 floor structure, which are disposed below the ground 1 floor structure 10, are collectively defined as "underground structure". Hereinafter, the "underground structure" refers to a basement 1 floor structure, a basement 2 floor structure, a basement 3 floor structure, a basement 4 floor structure, a basement 5 floor structure, and the like.

지상 1층 구조물(10) 및 각 지하층 구조물(11, 12)은 슬래브(14) 및 보(15)로 이루어지며, 보(15)는 슬래브(14)의 일측에 길이방향으로 연장되어 슬래브(14)의 강성을 보강하도록 시공된다. 한편, 지상 1층 구조물(10)로부터 지하측으로 수직방향으로 복수의 골조기둥(20)이 미리 설치되고, 각 골조기둥(20)은 복수의 지하층 구조물(11, 12)들의 시공이 완료된 후에 골조기둥(20)의 외면에 철근의 배근 및 콘크리트 타설이 이루어져 수직구조물로 시공된다. 이러한 골조기둥(20)은 지상 1층 구조물(10) 및 지하층 구조물(11, 12)들의 수직방향으로 인접한 보(15)들을 관통하여 수직방향으로 배치된다. The ground-floor structure 10 and each subterranean structure 11 and 12 are composed of a slab 14 and a beam 15, the beam 15 is longitudinally extended to one side of the slab 14 to the slab 14 It is constructed to reinforce rigidity of). On the other hand, a plurality of frame pillars 20 are installed in the vertical direction from the ground first floor structure 10 to the basement side in advance, and each frame pillar 20 is a frame pillar after the construction of the plurality of basement layer structures 11 and 12 is completed Reinforcement of reinforcement and concrete is made on the outer surface of (20) and is constructed as a vertical structure. The frame pillar 20 is disposed in the vertical direction through the beams 15 adjacent to each other in the vertical direction of the ground-floor structure 10 and the basement structures 11 and 12.

본 발명에 의한 무지보 역타설 지하구조물의 구축방법은 도 9에 도시된 바와 같이, 지상 1층 구조물(10)을 시공하는 지상 1층 구조물 시공단계(S1), 현수지지공법을 이용하여 지상 1층 구조물(10)의 하부에 배치되는 하층 구조물(12, 13)들을 연속하여 시공하는 지하층 구조물 시공단계(S2)로 이루어진다. As shown in FIG. 9, the method for constructing the unsupported retro-casting underground structure according to the present invention is a ground one-story structure construction step (S1) for constructing the ground one-story structure 10 (S1) by using a suspension support method. Base layer structure construction step (S2) of successively constructing the lower layer structures (12, 13) disposed in the lower portion of the layer structure (10).

지상 1층 구조물 시공단계(S1)는 흙막이벽체의 시공 및 터파기를 진행한 후에 지상 1층 구조물(10)을 시공한다. 이러한 지상 1층 구조물(10)의 시공 시에는 지상 1층 구조물(10)의 슬래브(14) 및 보(15) 등을 타설하기 위한 거푸집을 지지하는 서포트(미도시)를 설치할 수도 있다. In the ground floor construction step (S1), after the construction and excavation of the retaining wall, the ground ground floor structure 10 is constructed. At the time of construction of the above ground ground structure 10, a support (not shown) for supporting the formwork for placing the slab 14 and the beam 15 of the above ground ground structure 10 may be installed.

지하층 구조물 시공단계(S2)는 지상 1층 구조물(10)의 하부에 배치되는 지하 1층 구조물(11), 지하 2층 구조물(12), 그 이하 층의 지하층 구조물 등을 하향으로 순차적이고 연속적으로 시공한다. 한편, 도 1에서는 지하 1층 구조물(11), 지하 2층 구조물(12)이 시공된 지하구조물이 예시되어 있으나, 본 발명은 지하 2층 구조물(12)의 하측에 지하 3층 구조물, 지하 4층 구조물, 지하 5층 구조물 등이 더 시공될 수도 있다. Underground structure construction step (S2) sequentially and continuously downward to the basement 1 floor structure 11, the basement 2 floor structure 12, the basement floor structure of the lower floor, etc. disposed below the ground 1 floor structure (10). Construct. Meanwhile, although FIG. 1 illustrates an underground structure in which the basement 1 story structure 11 and the basement 2 story structure 12 are constructed, the present invention provides a basement 3 story structure below the basement 2 story structure 12 and the basement 4. Floor structures, underground five-story structures, etc. may be further constructed.

지하층 구조물 시공단계(S2)에서는 지하 1층 구조물(11), 지하 2층 구조물(12) 등과 같은 하중 구조물을 위한 거푸집(200)을 거푸집 지지장치(100)를 이용하여 현수지지하면서 콘크리트 타설 및 양생 등을 진행하다. In the construction step (S2) of the basement structure, concrete pouring and curing while suspending the formwork 200 for the load structure such as the basement layer 1 structure, the basement layer 2 structure 12, etc. using the formwork support device 100 Proceed.

이를 구체적으로 살펴보면, 지상 1층 구조물(10)의 하측에 대해 터파기가 진행되면, 지하 1층 구조물(11), 지하 2층 구조물(12) 등과 같은 지하층 구조물(11, 12)들의 콘크리트 타설 및 양생을 위한 거푸집(200)을 설치하고, 이러한 거푸집(200)을 거푸집 지지장치(100)에 의해 현수지지시킨다. Specifically, when the trench proceeds to the lower side of the ground one story structure 10, concrete pouring and curing of the underground story structures 11 and 12, such as the first story underground structure 11 and the second story underground structure 12, is described. Install the formwork for 200, the formwork 200 is suspended by the formwork support device (100).

거푸집(200)은 지하층 구조물(11, 12)의 보(15)를 타설하기 위한 보 거푸집(210) 및 지하층 구조물(11, 12)의 슬래브(14)를 타설하기 위한 슬래브 거푸집(220)으로 이루어진다. Formwork 200 is composed of beam formwork 210 for placing beams 15 of basement structures 11 and 12 and slab formwork 220 for casting slab 14 of basement structures 11 and 12. .

보 거푸집(210)은 측판(210) 및 바닥판(212)으로 이루어지고, 바닥판(212)은 거푸집 지지장치(100)에 의해 지지된다. Beam formwork 210 is made of a side plate 210 and the bottom plate 212, the bottom plate 212 is supported by the formwork support device (100).

슬래브 거푸집(220)은 딥 데크, 데크 플레이트 등과 같이 복수의 엠보싱이 연속적으로 형성된 플레이트 구조로 구성될 수 있다. The slab formwork 220 may be configured as a plate structure in which a plurality of embossings are continuously formed, such as a deep deck and a deck plate.

도 2 내지 도 4에 도시된 바와 같이, 본 발명에 의한 거푸집 지지장치(100)는 골조기둥(20)의 좌우 양측에 대칭적으로 배치된 복수의 지지브라켓(110), 복수의 지지브라켓(110)의 길이방향에 대해 직교하는 방향으로 가로질러 설치된 복수의 크로스부재(120), 복수의 지지브라켓(110)을 현수지지하는 현수유닛(150)을 포함한다. As shown in Figures 2 to 4, the formwork supporting apparatus 100 according to the present invention is a plurality of support brackets 110, a plurality of support brackets 110 symmetrically arranged on both left and right sides of the frame pillar (20) It includes a plurality of cross members 120 installed in a direction perpendicular to the longitudinal direction of the cross-section, the suspension unit 150 for suspension support of the plurality of support brackets (110).

도 2에 도시된 바와 같이, 2열의 지지브라켓(110)들이 골조기둥(20)의 폭방향에서 좌우 양측에 대칭적으로 배치되고, 각 열의 지지브라켓(110)들은 도 3에 도시된 바와 같이 보(15)의 길이방향을 따라 인접하여 배치된다. As shown in FIG. 2, two rows of support brackets 110 are symmetrically disposed on both left and right sides in the width direction of the frame pillar 20, and the support brackets 110 of each row are beamed as shown in FIG. 3. It is arrange | positioned adjacently along the longitudinal direction of (15).

특히, 도 3 및 도 4에 도시된 바와 같이 보(15)의 길이방향을 따라 배치된 지지브라켓(110)들의 서로 마주보는 단부들은 연결브라켓(105)을 매개로 서로 연결된다. 연결브라켓(105)은 지지브라켓(110)들의 인접한 단부 측에 체결구 또는 용접 등을 통해 결합된다. 이에, 지지브라켓(110)은 지하층 구조물(11, 12)의 보(15)의 길이방향을 따라 서로 연결됨에 따라 거푸집(200)의 안정적인 지지구조가 효과적으로 구현될 수 있다. In particular, as shown in FIGS. 3 and 4, the opposite ends of the support brackets 110 disposed along the longitudinal direction of the beam 15 are connected to each other via a connecting bracket 105. The connection bracket 105 is coupled to the adjacent end side of the support brackets 110 through fasteners or welding. Thus, as the support bracket 110 is connected to each other along the longitudinal direction of the beams 15 of the basement layer structures 11 and 12, the stable support structure of the formwork 200 can be effectively implemented.

한편, 지지브라켓(110)은 웨브(111) 및 웨브(111)의 양측에 웨브(111)에 대해 직교하는 방향으로 연결된 플랜지(112)를 가진 H빔 구조로 구성되고, 이에 도 4의 확대도와 같이 연결브라켓(115)은 지지브라켓(110)의 웨브(111)측에 결합되며, 특히 지지브라켓(110)의 웨브(111) 양측에 한 쌍의 연결브라켓(115)이 체결구 또는 용접 등을 통해 대칭적으로 결합됨으로써 지지브라켓(110)들의 길이방향 결합력이 보다 견고하게 이루어질 수 있다. On the other hand, the support bracket 110 is composed of an H-beam structure having a web 111 and a flange 112 connected to both sides of the web 111 in a direction orthogonal to the web 111, and thus, an enlarged view of FIG. 4. Likewise, the connection bracket 115 is coupled to the web 111 side of the support bracket 110, and in particular, a pair of connection brackets 115 are connected to both sides of the web 111 of the support bracket 110 to fasten or weld, or the like. By being coupled symmetrically through the longitudinal coupling force of the support brackets 110 can be made more robust.

도 3에 도시된 바와 같이 골조기둥(20)의 전면 및 후면 각각에는 스톱플레이트(130)가 대칭적으로 설치되고, 각 스톱플레이트(130)의 좌우 양측은 골조기둥(20)의 좌우 측에서 돌출하도록 구성된다. 각 스톱플레이트(130)의 상면은 평탄하게 형성되고, 이에 도 2와 같이 각 스톱플레이트(130)의 상면에는 보(15)에 인접한 한 쌍의 지지브라켓(110)들이 지지된다. As shown in FIG. 3, stop plates 130 are symmetrically installed on each of the front and rear surfaces of the frame pillar 20, and both left and right sides of each stop plate 130 protrude from the left and right sides of the frame pillar 20. It is configured to. The top surface of each stop plate 130 is formed flat, so that a pair of support brackets 110 adjacent to the beam 15 are supported on the top surface of each stop plate 130 as shown in FIG. 2.

복수의 크로스부재(120)는 2열로 배치된 지지브라켓(110)들을 가로질러 설치되고, 즉 지지브라켓(110)들의 길이방향에 대해 직교하는 방향으로 설치된다. 이에 2열의 지지브라켓(110)들 사이는 복수의 크로스부재(120)를 통해 서로 견고하게 연결될 수 있고, 복수의 크로스부재(120)들의 상면에 보 거푸집(210)의 바닥판(212)이 안정적으로 안치될 수 있다. The plurality of cross members 120 are installed across the support brackets 110 arranged in two rows, that is, installed in a direction perpendicular to the longitudinal direction of the support brackets 110. Accordingly, between the two rows of support brackets 110 may be firmly connected to each other through a plurality of cross members 120, and the bottom plate 212 of the formwork 210 is stable on the upper surfaces of the plurality of cross members 120. Can be enshrined.

현수유닛(150)은 지상 1층 구조물(10)의 상면에 배치되고, 현수유닛(150)은 삼발이 등과 같은 현수지지대 및 체인블록 등으로 이루어지며, 이 현수유닛(150)에는 와이어 등과 같은 현수재(151)가 연결된다. 현수재(151)의 하단은 지하층 구조물(11, 12)의 보(15)에 인접한 지지브라켓(110)의 상단에 고정되고, 지하층 구조물(11, 12)의 보(15)에 인접한 지지브라켓(110)의 상단에는 고리부(106)가 형성되며, 이 고리부(106)에는 현수재(151)의 하단이 고정된다. Suspension unit 150 is disposed on the upper surface of the ground-floor structure 10, the suspension unit 150 is made of a suspension support and chain block, such as trivet, etc., Suspension unit 150, such as wire 151 is connected. The lower end of the suspension material 151 is fixed to the top of the support bracket 110 adjacent to the beams 15 of the basement structures 11 and 12, and the support brackets adjacent to the beams 15 of the basement structures 11 and 12 ( A ring portion 106 is formed at an upper end of the 110, and a lower end of the suspension material 151 is fixed to the ring portion 106.

한편, 현수재(151)는 지상 1층 구조물(10) 및 지하층 구조물(11, 12)들의 보(15)를 관통하여 수직방향으로 긴장되고, 지상 1층의 구조물(10) 및 지하층 구조물(11, 12)의 보(15)에는 수직방향으로 관통하는 관통공(18)이 형성된다. 이러한 관통공(18)은 도 5에 도시된 바와 같이 관통공(18)을 가진 파이프부재(19)가 매립됨으로써 형성될 수도 있다. 이에, 현수재(151)는 지상 1층 구조물(10) 및 지하층 구조물(11, 12)의 보(15)를 관통한 후에 거푸집(200)을 현수지지하도록 시공됨에 따라 지하 1층 구조물(10) 및 지하층 구조물(11, 12)들은 관통공(18)으로 인한 강도 저하 문제를 최소화할 수 있는 장점이 있다. Meanwhile, the suspension material 151 is tensioned in the vertical direction by penetrating through the beams 15 of the ground-floor structure 10 and the basement structures 11 and 12, and the structure 10 and the basement structure 11 of the ground layer 1. The through-hole 18 penetrating in the vertical direction is formed in the beam 15 of 12. The through hole 18 may be formed by embedding the pipe member 19 having the through hole 18 as shown in FIG. 5. Accordingly, the suspension material 151 is constructed so as to suspend the formwork 200 after passing through the beams 15 of the ground-floor structure 10 and the basement structures 11 and 12. And basement structure (11, 12) has the advantage that can minimize the problem of strength degradation due to the through-holes (18).

이와 같은 본 발명의 거푸집 지지장치(100)는 지지브라켓(110) 및 크로스부재(120)들이 스톱플레이트(130)에 의해 상향으로 지지됨과 더불어 현수유닛(150)의 현수재(151)에 의해 현수지지되는 구조로 구성됨으로써 전체 구조가 간소화됨과 더불어 거푸집(200) 및 그 거푸집(200)에 의해 타설되는 지하층 구조물의 안정적인 지지가 용이하게 구현될 수 있는 장점이 있다. Such a formwork supporting device 100 of the present invention is supported by the support bracket 110 and the cross member 120 upward by the stop plate 130 and suspended by the suspension material 151 of the suspension unit 150 As the structure is supported, the overall structure is simplified, and there is an advantage that the stable support of the formwork 200 and the underground layer structure cast by the formwork 200 can be easily implemented.

또한, 본 발명의 거푸집 지지장치(100)는 지지브라켓(110)이 보(15)의 길이방향을 따라 일렬로 연결되는 구조로 구성됨에 따라 각 지지브라켓(110)의 사이즈 및 중량을 종래에 비해 대폭 감소할 수 있고, 이에 인력에 의한 거푸집 지지장치(100)의 설치 및 하강을 용이하게 실시할 수 있는 장점이 있다. In addition, the formwork supporting apparatus 100 of the present invention is configured in a structure in which the support bracket 110 is connected in a line along the longitudinal direction of the beam 15, compared to the size and weight of each support bracket 110 compared to the prior art Can be greatly reduced, there is an advantage that can be easily carried out installation and descent of the formwork supporting apparatus 100 by the manpower.

도 5에 도시된 바와 같이, 지하층 구조물(도 1에서는 지하 1층 구조물(11), 지하 2층 구조물(12) 등에 해당)의 관통공(18)에 인접하여 하중 분산유닛(160)이 설치될 수 있다. As shown in FIG. 5, the load distribution unit 160 may be installed adjacent to the through hole 18 of the basement structure (in FIG. 1, corresponding to the basement 1 layer structure 11, the basement 2 layer structure 12, etc.). Can be.

이러한 하중 분산유닛(160)은 현재 타설이 진행 중인 지하층 구조물(13)의 하중을 지상 1층 구조물(10) 뿐만 아니라 그 직상층 구조물(12) 측으로도 하중을 전달함으로써 하중 분산효과를 높일 수 있다. The load distribution unit 160 may increase the load distribution effect by transferring the load of the basement layer structure 13 that is currently being poured not only to the ground layer structure 10 but also to the upper layer structure 12. .

예컨대, 도 1에 예시된 바와 같이 지하 2층 구조물(12)의 타설이 진행 중일 경우, 지하 2층 구조물(12)의 하중은 하중 분산유닛(160)을 통해 지하 1층 구조물(11) 측으로 전달됨으로써 지하 2층 구조물(12)의 하중이 지상 1층 구조물(10) 및 지하 1층 구조물(11) 측으로 적절히 분산될 수 있고, 이를 통해 거푸집 지지장치(100)의 보다 안정적이고 견고한 지지를 구현할 수 있다. For example, as shown in FIG. 1, when placing the underground two story structure 12 is in progress, the load of the underground two story structure 12 is transferred to the basement one story structure 11 through the load distribution unit 160. By doing so, the load of the underground two-story structure 12 can be properly distributed to the ground one-story structure 10 and the underground one-story structure 11, thereby realizing more stable and robust support of the formwork supporting device 100. have.

또한, 지하 3층 구조물(미도시)의 타설이 진행될 경우, 지하 3층 구조물의 하중은 하중 분산유닛(160)을 통해 지하 1층 구조물(11) 및 지하 2층 구조물(12) 측으로 전달됨으로써 지하 3층 구조물의 하중이 지상 1층 구조물(10), 지하 1층 구조물(11), 지하 2층 구조물(12) 측으로 적절히 분산될 수도 있다. In addition, when the underground three-story structure (not shown) proceeds, the load of the three-story underground structure is transmitted to the basement 1 floor structure 11 and the basement 2 floor structure 12 through the load distribution unit 160, thereby underground The load of the three-story structure may be properly distributed to the ground one-story structure 10, the underground one-story structure 11, and the underground two-story structure 12.

이와 같이, 본 발명은 하중 분산유닛(160)을 통해 지하층 구조물을 타설할 경우 그 하중을 지상 1층 구조물 뿐만 아니라 그 직상측의 지하층 구조물 측에도 전달할 수 있으므로 하중 분산효과를 높일 수 있고, 이에 지지브라켓(110) 및 크로스부재(120)의 경량화를 용이하게 달성할 수 있을 뿐만 아니라 지하층 구조물의 콘크리트 타설 시에 그 직상층 구조물의 양생 조건에 영향을 받지 않으므로 공사 진행 시의 대기시간을 줄여 시공기간의 확보를 유리하게 할 수 있는 장점이 있다.As such, when the basement structure is placed through the load distribution unit 160, the load can be transferred not only to the ground floor structure but also to the basement structure side on the upper side thereof, thereby increasing the load distribution effect, thereby supporting the bracket. Light weight of the 110 and the cross member 120 can be easily achieved, and when the concrete is placed in the basement structure, it is not affected by the curing conditions of the upper layer structure, thereby reducing the waiting time during construction. There is an advantage that can be advantageous to secure.

일 실시예에 따른 하중 분산유닛(160)은 도 5 및 도 6에 도시된 바와 같이 그 내부에 현수재(151)가 끼워지는 끼움공(161)이 형성되며, 그 외측면에 경사면(163)이 형성되며, 그 일측에는 개구(162)가 형성된 원추형 구조로 이루어진다. 도 6에 도시된 바와 같이, 하중 분산유닛(160)은 지지브라켓(110) 및 거푸집(200)의 하중에 의해 현수재(151)가 긴장될 경우 하중 분산유닛(160)은 현수재(151)와 함께 하향 이동하면서 하중 분산유닛(160)이 관통공(18) 측에서 오무려져 쐐기결합된다. 이에, 하중이 구조물 측으로 효과적으로 전달된다. As shown in FIGS. 5 and 6, the load dispersing unit 160 according to the exemplary embodiment is provided with a fitting hole 161 into which the suspension member 151 is fitted, and an inclined surface 163 on an outer surface thereof. It is formed, and one side is made of a conical structure in which the opening 162 is formed. As shown in FIG. 6, when the suspension member 151 is tensioned due to the load of the support bracket 110 and the formwork 200, the load distribution unit 160 is suspended. While moving downward with the load distribution unit 160 is pinched in the through hole 18 side is wedge coupled. Thus, the load is effectively transmitted to the structure side.

다른 실시예에 따른 하중 분산유닛(170)은 도 7 및 도 8에 도시된 바와 같이, 관통공(18)에 인접하여 설치된 마찰롤러(171)로 구성되고, 이 마찰롤러(171)는 브라켓(172)을 매개로 관통공(18)에 인접하여 설치된다. As shown in FIGS. 7 and 8, the load distributing unit 170 according to another embodiment includes a friction roller 171 provided adjacent to the through hole 18, and the friction roller 171 includes a bracket ( 172 is installed adjacent to the through-hole 18 via a medium.

현수재(151)가 긴장될 경우 마찰롤러(171)의 외주면에 현수재(151)가 감겨지고, 이에 현수재(151)는 마찰롤러(171)의 외주면과 마찰접촉함에 따라 현수재(151) 측에 걸리는 하중이 구조물 측으로 효과적으로 전달될 수 있다. When the suspension material 151 is tensioned, the suspension material 151 is wound on the outer circumferential surface of the friction roller 171, and the suspension material 151 is in friction contact with the outer circumferential surface of the friction roller 171. The load on the side can be effectively transmitted to the structure side.

한편, 마찰롤러(171)들은 도 8에 도시된 바와 같이, 보(15) 측에 일렬로 배치된 관통공(18)들에 대해 대칭적으로 배치되고, 이에 현수재(151)의 하중을 구조물 측으로 효과적으로 전달할 수 있다. Meanwhile, as shown in FIG. 8, the friction rollers 171 are symmetrically arranged with respect to the through holes 18 arranged in a line on the beam 15 side, thereby applying a load of the suspension material 151 to the structure. Can be effectively delivered to the side.

이상과 같은 본 발명은 거푸집 지지장치(100)의 지지브라켓(110)이 스톱플레이트(130)을 통해 하측이 안정적으로 지지되면서 현수유닛(150)의 현수재(151)에 의해 상향으로 현수지지될 수 있고, 2열의 지지브라켓(110)들은 보(15)의 길이방향을 따라 연결됨에 따라 보(15)를 타설하기 위한 보 거푸집(210)을 견고하게 지지할 수 있는 장점이 있다. The present invention as described above is supported by the support bracket 110 of the formwork support device 100 is supported by the suspension 151 of the suspension unit 150 while the lower side is stably supported by the stop plate 130. And, the support brackets 110 of the two rows are connected along the longitudinal direction of the beam 15, there is an advantage that can firmly support the beam formwork 210 for placing the beam 15.

이상, 본 발명의 구체적인 실시예를 설명하였으나, 본 발명은 이 명세서에 개시된 실시예 및 첨부된 도면에 의하여 한정되지 않으며 본 발명의 기술적 사상을 벗어나지 않는 범위 이내에서 당업자에 의하여 다양하게 변형될 수 있다.While the present invention has been described in connection with what is presently considered to be practical exemplary embodiments, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the appended claims. .

10: 지상 1층 구조물 12: 지하 2층 구조물
13: 지하 3층 구조물 14: 슬래브
15: 보 20: 골조기둥
100: 거푸집 지지장치 100: 지지브라켓
120: 크로스부재 130: 스톱플레이트
150: 현수유닛 151: 현수재
160, 170: 하중 분산유닛 200: 거푸집
210: 보 거푸집 220: 슬래브 거푸집
10: ground level 1 structure 12: underground 2 level structure
13: 3 underground structure 14: slab
15: see 20: skeleton
100: formwork support device 100: support bracket
120: cross member 130: stop plate
150: suspension unit 151: suspension
160, 170: load distribution unit 200: formwork
210: see formwork 220: slab formwork

Claims (7)

지상 1층 구조물로부터 지하층을 향하여 복수의 지하층 구조물을 단계적으로 시공하는 무지보 역타설 지하구조물의 콘크리트 타설을 위한 거푸집을 지지하기 위한 지하구조물의 현수식 거푸집 지지장치로서,
지하층 구조물의 골조기둥의 좌우 양측에 대칭적으로 배치된 복수의 지지브라켓과, 상기 복수의 지지브라켓의 길이방향에 대해 직교하는 방향으로 가로질러 설치되는 복수의 크로스부재와, 상기 복수의 지지브라켓을 지상 1층 구조물 측에서 현수지지하는 현수재를 가진 현수유닛을 포함하고,
상기 골조기둥의 전면 및 후면 각각에는 스톱플레이트가 대칭적으로 설치되며, 각 스톱플레이트의 좌우 양측은 골조기둥의 좌우 측에서 돌출하고, 상기 복수의 지지브라켓 중에서 골조기둥에 인접한 지지브라켓들은 상기 스톱플레이트의 상면에 대칭적으로 지지되며,
상기 현수유닛은 지상 1층 구조물의 상면에 배치되고, 상기 현수유닛의 현수재는 그 하단이 현재 타설 진행 중인 지하층 구조물의 보에 인접한 지지브라켓의 상단에 고정되며,
상기 지상 1층 구조물의 보 및 상기 지하층 구조물의 보에는 수직방향으로 관통하는 관통공이 형성되고, 상기 현수재는 상기 관통공을 관통하여 수직방향으로 설치되며,
상기 지하층 구조물의 관통공에는 현재 타설이 진행 중인 지하층 구조물의 하중을 지상 1층 구조물 및 그 직상의 지하층 구조물 측으로 분산하는 하중 분산유닛이 설치되고,
상기 하중 분산유닛은 상기 관통공에 인접하여 설치된 마찰롤러로 이루어지고, 상기 마찰롤러의 외주면에는 상기 현수재가 감겨짐에 따라 현수재는 마찰롤러의 외주면과 마찰접촉함에 따라 현수재에 걸리는 하중이 구조물에 전달되도록 구성되는 것을 특징으로 하는 지하구조물의 현수식 거푸집 지지장치.
As a suspended formwork supporting device for underground structures for supporting the formwork for concrete placing of unsupported retro-casting underground structures for constructing a plurality of underground structures in stages from the ground-level structure to the basement,
A plurality of support brackets symmetrically disposed on both the left and right sides of the frame pillar of the basement structure, a plurality of cross members installed in a direction orthogonal to a longitudinal direction of the plurality of support brackets, and the plurality of support brackets It includes a suspension unit having a suspension material suspended from the ground floor structure side,
A stop plate is symmetrically installed on each of the front and rear sides of the frame pillar, and both left and right sides of each stop plate protrude from the left and right sides of the frame pillar, and among the plurality of support brackets, the support brackets adjacent to the frame pillar are the stop plate. Symmetrically supported on the top of
The suspension unit is disposed on the upper surface of the ground-floor structure, the suspension of the suspension unit is fixed to the upper end of the support bracket adjacent the beam of the basement structure, the lower end of which is currently being poured,
The beams of the ground one-story structure and the beams of the basement structure are formed through holes penetrating in the vertical direction, the suspension is installed in the vertical direction through the through holes,
The through hole of the basement structure is provided with a load distribution unit for distributing the load of the basement structure currently being poured to the ground above-ground structure and the basement structure directly above,
The load distributing unit includes a friction roller installed adjacent to the through hole. As the suspension material is wound around the outer circumferential surface of the friction roller, the suspension material is in contact with the outer circumferential surface of the friction roller, and the load applied to the suspension material is applied to the structure. Suspended formwork support device for underground structures, characterized in that configured to be delivered.
청구항 1에 있어서,
상기 지지브라켓은 웨브 및 상기 웨브의 양측에 상기 웨브에 대해 직교하는 방향으로 연결된 플랜지를 가진 H빔 구조로 구성되고, 연결브라켓은 상기 지지브라켓의 웨브 측에 결합되는 것을 특징으로 하는 지하구조물의 현수식 거푸집 지지장치.
The method according to claim 1,
The support bracket is composed of an H beam structure having a web and a flange connected in a direction orthogonal to the web on both sides of the web, and the connection bracket is coupled to the web side of the support bracket. Modular formwork support.
삭제delete 청구항 1에 있어서,
상기 지하층 구조물의 보에 인접한 지지브라켓의 상단에는 고리부가 형성되고, 상기 고리부에는 상기 현수재의 하단이 고정되는 것을 특징으로 하는 지하구조물의 현수식 거푸집 지지장치.
The method according to claim 1,
Suspension formwork supporting device of the underground structure, characterized in that the upper end of the support bracket adjacent to the beam of the basement structure is formed, the lower end of the suspension is fixed to the ring.
삭제delete 삭제delete 청구항 1, 2, 4 중 어느 한 항에 따른 지하구조물의 현수식 거푸집 지지장치를 이용한 무지보 역타설 지하구조물의 구축방법으로,
지상 1층 구조물을 시공하는 지상 1층 구조물 시공단계; 및
상기 지상 1층 구조물의 지하에 층단위로 배치되는 복수의 지하층 구조물을 단계적으로 시공하는 지하층 구조물 시공단계;로 이루어지고,
상기 지하층 구조물 시공단계는, 지하층 구조물의 콘크리트 타설을 위한 거푸집 및 상기 거푸집을 지지하기 위한 거푸집 지지장치를 설치하며, 상기 거푸집 지지장치는 복수의 지지브라켓에 의해 상향으로 지지됨과 더불어 지상 1층 구조물의 상면에 설치된 현수유닛으로부터 연결된 현수재에 의해 현수지지되게 설치되고,
상기 거푸집 측에 콘크리트를 타설함으로써 복수의 지하층 구조물을 시공하는 것을 특징으로 하는 무지보 역타설 지하구조물의 구축방법.





Claims 1, 2, 4 as a method for constructing the unsupported retro-casting underground structure using a suspension formwork supporting device of the underground structure,
A first floor structure construction step of constructing a first floor structure; And
A basement layer construction step of constructing a plurality of basement layer structures disposed in units of floors in the basement of the ground layer structure;
In the construction of the basement structure, a formwork for placing concrete and a formwork supporting device for supporting the formwork are installed, and the formwork support device is supported upward by a plurality of support brackets, It is installed to be suspended by the suspension material connected from the suspension unit installed on the upper surface,
The construction method of the non-supporting reinforcement underground structure, characterized in that for constructing a plurality of basement structure by pouring concrete on the formwork side.





KR1020120047022A 2012-05-03 2012-05-03 Apparatus for supporting form of underground building and method of constructing the underground building using the same KR101335796B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120047022A KR101335796B1 (en) 2012-05-03 2012-05-03 Apparatus for supporting form of underground building and method of constructing the underground building using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120047022A KR101335796B1 (en) 2012-05-03 2012-05-03 Apparatus for supporting form of underground building and method of constructing the underground building using the same

Publications (2)

Publication Number Publication Date
KR20130123697A KR20130123697A (en) 2013-11-13
KR101335796B1 true KR101335796B1 (en) 2013-12-05

Family

ID=49852864

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120047022A KR101335796B1 (en) 2012-05-03 2012-05-03 Apparatus for supporting form of underground building and method of constructing the underground building using the same

Country Status (1)

Country Link
KR (1) KR101335796B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112211223B (en) * 2020-10-20 2021-09-24 福建中设工程咨询有限公司 Municipal pipe gallery structure and construction method
KR102579166B1 (en) * 2023-06-02 2023-09-14 홍승대 Top-down Structures Using Suspended rebar
KR102579169B1 (en) * 2023-06-02 2023-09-14 홍승대 Top-down method using suspended rebar

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100261775B1 (en) * 1997-07-31 2000-07-15 박형국 Method for non-supporting formwork for top_down construction and anchorage, coupler, supporting frame and hydraulic lift
KR200417438Y1 (en) 2006-03-14 2006-05-26 박무용 Bracket structure for girder and slab construction
KR100694503B1 (en) * 2005-04-27 2007-03-13 (주)한국건설공법 Downward construction system and method for 1-way girder and slab of underground structure
KR100694493B1 (en) 2005-07-27 2007-03-16 황기수 Downward construction method capable of using bracket support type temporary structure as working table

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100261775B1 (en) * 1997-07-31 2000-07-15 박형국 Method for non-supporting formwork for top_down construction and anchorage, coupler, supporting frame and hydraulic lift
KR100694503B1 (en) * 2005-04-27 2007-03-13 (주)한국건설공법 Downward construction system and method for 1-way girder and slab of underground structure
KR100694493B1 (en) 2005-07-27 2007-03-16 황기수 Downward construction method capable of using bracket support type temporary structure as working table
KR200417438Y1 (en) 2006-03-14 2006-05-26 박무용 Bracket structure for girder and slab construction

Also Published As

Publication number Publication date
KR20130123697A (en) 2013-11-13

Similar Documents

Publication Publication Date Title
KR100694503B1 (en) Downward construction system and method for 1-way girder and slab of underground structure
KR200417438Y1 (en) Bracket structure for girder and slab construction
KR101341679B1 (en) Device for constructing an underground structure and method thereof
KR101107567B1 (en) For top down methode of rc structure, the connecting devices between beam structure and vertical steel material, the supporting structures of exclusive use, and the construction method using these devices
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
CN207003723U (en) High-rise assembled single row of holes precast shear wall and its assembling structure
KR101335796B1 (en) Apparatus for supporting form of underground building and method of constructing the underground building using the same
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR200398231Y1 (en) 1way-supporting bracket for girder and slab construction
JP4362824B2 (en) Reverse strike method
KR20100043161A (en) Pillar construction method by layer-built and frame construction method adapting the same
KR20110136138A (en) Underground slab construction method using wire rope and curing pannel flame
KR100967496B1 (en) Device for constructing an underground structure
JP3644606B2 (en) Installation method of formwork support in reverse placement method
CN209779679U (en) Displacement system of pipe gallery segment
JP6387778B2 (en) Suspension jig used when building the core material of the underground continuous wall, the method of building the core material of the underground continuous wall, and the system for building the core material of the underground continuous wall
KR100757710B1 (en) Dowel bar construction method for downward construction of underground structures
KR20140092629A (en) A temporary skeleton system used in constructuring a underground structure of a building and a top down underground construction method using a temporary skeleton system
KR100679986B1 (en) Structure for plastic slab deck system and Downward construction method using the same
KR20120088929A (en) Structure of Temporary Retaning wall
KR200358247Y1 (en) Downward construction structure using bracket support type
KR200402363Y1 (en) Structure for concreting work of column
JP3208100U (en) Scaffolding device for construction of underground structures
KR100227537B1 (en) Process for hanging concrete large slab forms
KR100593203B1 (en) a deck supportframe and a construction methed

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170426

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20180910

Year of fee payment: 6