KR100694493B1 - Downward construction method capable of using bracket support type temporary structure as working table - Google Patents

Downward construction method capable of using bracket support type temporary structure as working table Download PDF

Info

Publication number
KR100694493B1
KR100694493B1 KR1020050068193A KR20050068193A KR100694493B1 KR 100694493 B1 KR100694493 B1 KR 100694493B1 KR 1020050068193 A KR1020050068193 A KR 1020050068193A KR 20050068193 A KR20050068193 A KR 20050068193A KR 100694493 B1 KR100694493 B1 KR 100694493B1
Authority
KR
South Korea
Prior art keywords
support
temporary structure
beams
bracket
formwork
Prior art date
Application number
KR1020050068193A
Other languages
Korean (ko)
Other versions
KR20070013680A (en
Inventor
황기수
박무용
Original Assignee
황기수
박무용
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 황기수, 박무용 filed Critical 황기수
Priority to KR1020050068193A priority Critical patent/KR100694493B1/en
Publication of KR20070013680A publication Critical patent/KR20070013680A/en
Application granted granted Critical
Publication of KR100694493B1 publication Critical patent/KR100694493B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

본 발명은 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법에 관한 것으로서, 브라켓에 의해 고정 지지되는 가설구조체를 각 층 시공 중의 작업대로 활용할 수 있게 되면서 안전성 측면에서 향상되는 효과가 있고, 최하층 바닥 구조로 사용될 데크를 가설구조체 내에 포함시켜 사용하므로 작업대의 설치비용을 줄일 수 있는 등 활용성 및 경제성 측면에서 유리해지는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법에 관한 것이다.The present invention relates to a reverse casting method that can utilize a bracket-supported temporary structure as a workbench, while being able to utilize a temporary structure supported by a bracket as a workbench during construction of each floor, thereby improving safety in terms of safety. Since the deck to be used as a floor structure is included in the temporary structure to reduce the installation cost of the workbench, such as the reverse casting method that can utilize the bracket-supported temporary structure, which is advantageous in terms of utility and economics.

브라켓, 가설구조체, 역타설 공법, 트러스 데크, 딥 데크, 합판 거푸집, 지지거더, 보강보 Bracket, Temporary Structure, Reversal Method, Truss Deck, Deep Deck, Plywood Formwork, Support Girder, Reinforcement Beam

Description

브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법{Downward construction method capable of using bracket support type temporary structure as working table}Downward construction method capable of using bracket support type temporary structure as working table}

도 1은 본 발명에서 이용되는 브라켓 지지 타입 가설구조체의 제1실시예가 설치된 평면도, 1 is a plan view in which the first embodiment of the bracket support type temporary structure used in the present invention is installed;

도 2a와 도 2b는 도 1에 도시한 가설구조체의 제1실시예의 단면도, 2A and 2B are cross-sectional views of a first embodiment of the temporary structure shown in FIG. 1;

도 3은 도 1에 도시한 가설구조체의 제1실시예를 사용하는 경우에서 1층 및 지하층의 보 및 슬래브 구축 시스템을 도시한 단면도, 3 is a cross-sectional view showing the beam and slab construction system of the first floor and the basement floor in the case of using the first embodiment of the temporary structure shown in FIG.

도 4는 도 1에 도시한 가설구조체의 제1실시예를 사용하는 경우에서 최하층의 보 및 슬래브 구축 시스템을 도시한 단면도,4 is a cross-sectional view showing the lowest beam and slab construction system in the case of using the first embodiment of the temporary structure shown in FIG.

도 5a ~ 도 5h는 도 1에 도시한 가설구조체의 제1실시예를 작업대로 활용할 수 있는 지하층의 보 및 슬래브 역타 시공 전체 과정을 도시한 공정도,5a to 5h is a process diagram showing the entire process of construction of the beam and slab reverse construction of the basement floor that can utilize the first embodiment of the temporary structure shown in FIG.

도 6은 도 1에 도시한 가설구조체의 제1실시예를 사용하는 경우에서 지지거더 및 보강보 위에 트러스 데크가 고정된 상태를 도시한 확대단면도,6 is an enlarged cross-sectional view showing a state in which a truss deck is fixed on a support girder and a reinforcement beam in the case of using the first embodiment of the temporary structure shown in FIG.

도 7은 본 발명에서 이용되는 브라켓 지지 타입 가설구조체의 제2실시예가 설치된 평면도, 7 is a plan view in which the second embodiment of the bracket support type temporary structure used in the present invention is installed;

도 8a와 도 8b는 도 7에 도시한 가설구조체의 제2실시예의 단면도, 8A and 8B are cross-sectional views of a second embodiment of the temporary structure shown in FIG.

도 9는 도 7에 도시한 가설구조체의 제2실시예를 사용하는 경우에서 지지거더 및 보강보 위에 딥 데크가 고정된 상태를 도시한 확대단면도,9 is an enlarged cross-sectional view illustrating a state in which a deep deck is fixed on a support girder and a reinforcement beam in the case of using the second embodiment of the temporary structure shown in FIG. 7;

도 10은 도 7에 도시한 가설구조체의 제2실시예를 사용하는 경우에서 1층 및 지하층의 보 및 슬래브 구축 시스템을 도시한 단면도, FIG. 10 is a cross-sectional view showing a beam and slab construction system for the first floor and the basement floor when using the second embodiment of the temporary structure shown in FIG. 7; FIG.

도 11은 도 7에 도시한 가설구조체의 제2실시예를 사용하는 경우에서 최하층의 보 및 슬래브 구축 시스템을 도시한 단면도,FIG. 11 is a cross-sectional view showing the lowest beam and slab construction system in the case of using the second embodiment of the temporary structure shown in FIG. 7; FIG.

도 12는 본 발명에서 이용되는 브라켓 지지 타입 가설구조체의 제3실시예가 설치된 평면도, 12 is a plan view in which the third embodiment of the bracket support type temporary structure used in the present invention is installed;

도 13a와 도 13b는 도 12에 도시한 가설구조체의 제3실시예의 단면도, 13A and 13B are cross-sectional views of a third embodiment of the temporary structure shown in FIG. 12;

도 14는 도 12에 도시한 가설구조체의 제3실시예를 사용하는 경우에서 지하층의 보 및 슬래브 구축 시스템을 도시한 단면도, 14 is a cross-sectional view showing a beam and slab construction system of the basement floor in the case of using the third embodiment of the temporary structure shown in FIG.

도 15a ~ 도 15h는 도 12에 도시한 가설구조체의 제3실시예를 작업대로 활용할 수 있는 지하층의 보 및 슬래브 역타 시공 과정을 도시한 전체 공정도.15A to 15H are overall process diagrams illustrating a process of constructing a beam and slab reverse construction of the basement floor in which a third embodiment of the temporary structure shown in FIG. 12 can be used as a work bench.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

1 : 흙막이벽 2 : H-형강 기둥1: retaining wall 2: H-beam pillar

7 : 딥 데크 110 : 지지 브라켓7: deep deck 110: support bracket

120 : 지지거더 사각틀 121a, 121b : 지지거더120: support girders rectangular frame 121a, 121b: support girders

130 : 가설구조체 131 : 보강 지지틀130: temporary structure 131: reinforcement support frame

139 : 트러스 데크 140 : 가설지지틀139: truss deck 140: temporary frame

142 : 각재 145 : 딥 데크142: lumber 145: deep deck

149 : 합판 거푸집 150 : 보 거푸집149: plywood formwork 150: beam formwork

153 : 트러스 데크153: Truss Deck

본 발명은 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법에 관한 것으로서, 브라켓에 의해 고정 지지되는 가설구조체를 각 층 시공 중의 작업대로 활용할 수 있게 되면서 안전성 측면에서 향상되는 효과가 있고, 최하층 바닥 구조로 사용될 데크를 가설구조체 내에 포함시켜 사용하므로 작업대의 설치비용을 줄일 수 있는 등 활용성 및 경제성 측면에서 유리해지는 역타설 공법에 관한 것이다.The present invention relates to a reverse casting method that can utilize a bracket-supported temporary structure as a workbench, while being able to utilize a temporary structure supported by a bracket as a workbench during construction of each floor, thereby improving safety in terms of safety. Since the deck to be used as a floor structure is included in the temporary structure to reduce the installation cost of the workbench, such as the reverse casting method which is advantageous in terms of utilization and economics.

일반적으로 지하구조물을 구축하는 방법에는 두 가지가 있다.In general, there are two ways to build underground structures.

지하구조물이 축조되는 지반에 흙막이 공사를 한 다음 지반을 굴착하면서 흙막이를 지지할 수 있는 가시설물을 설치하고 토사를 전부 반출한 뒤 맨 아래층부터 구조물을 축조해 올라가는 순타설공법과, 흙막이를 시공하고 1층 구조물을 축조한 다음 그 구조물을 흙막이용 버팀부재로 이용하여 상부에서 하부로 지반을 굴착하면서 구조물을 축조해 내려가는 역타설공법이 그것이다.After constructing the earthquake on the ground where the underground structure is constructed, install the temporary facility to support the earthquake while excavating the ground, take out all the earth and sand, and build the structure from the bottom floor, After the construction of the first-floor structure, using the structure as a retaining member for the earthquake, the reverse casting method is to construct the structure while drilling the ground from the top to the bottom.

최근 토지 이용의 극대화 차원에서 지하공사가 점차 고심도화되고 있고, 특 히 순타설공법에 의한 시공시에는 흙막이 붕괴의 위험이나 주변 건물들 침하 등으로 인한 균열 발생은 물론, 시각적으로도 불안할 뿐만 아니라 공사기간이 길어지는 등 여러 문제가 있어서, 근래에는 역타설공법이 널리 적용되고 있다.In recent years, underground construction has been gradually intensified in order to maximize land use. Especially, when the construction is performed by the net pouring method, it is not only visually unstable as well as the occurrence of cracks due to the risk of earthquake collapse or settlement of surrounding buildings. Due to various problems such as lengthening of the construction period, the reverse casting method has been widely applied in recent years.

이 역타설공법은 흙막이벽 및 그 안쪽 지중의 골조용 기둥을 시공한 뒤 슬래브 및 보 등의 지하구조물을 지상 1층부터 지하층을 향하여 단계적으로 시공해 내려가는 방식이므로, 지하구조물과 지상구조물의 시공이 동시에 진행 가능하고, 지상 1층의 바닥을 작업장으로 활용할 수 있어 별도의 복공판이 필요하지 않으며, 무지보 거푸집 작업이 가능하다는 장점이 있다.In this reverse casting method, after constructing the retaining wall and the frame for the underground frame, the underground structures such as slabs and beams are constructed step by step from the ground floor to the underground floor. It can proceed at the same time, the floor of the ground floor can be utilized as a workshop, there is no need for a separate perforated plate, there is an advantage that the work can be plain.

이러한 역타설공법으로는 지반을 정지한 상태에서 지반 위에 콘크리트 슬래브와 보를 타설하는 방법(Concrete on Grade)과, 지반을 어느 정도 굴착하고 지반을 고른 뒤 동바리를 세우고 거푸집을 설치하여 콘크리트를 타설하는 방법(Form on Supporting)과, 거푸집 지지를 위한 동바리를 세우지 않는 대신에 선시공한 상층의 콘크리트 슬래브에 거푸집을 현수시켜 콘크리트를 타설하는 방법(무지보 역타설 현수 거푸집 공법) 등이 있다. Such a reverse casting method involves placing concrete slabs and beams on the ground while the ground is stopped (concrete on grade), and excaving the ground to some extent, selecting the ground, and then placing the clubs and installing the formwork to place the concrete. (Form on Supporting) and the method of placing concrete by suspending formwork on the concrete slab on the upper floor instead of establishing a ridge for supporting the formwork (inverted reversal suspension formwork).

이 중에서 동바리를 이용하는 공법은 상대밀도가 비교적 높은 지층에 적용하는 공법으로서, 지반을 선 굴착한 후 굴착된 지반 위에 버림 콘크리트를 타설하고, 이 버림 콘크리트를 지지기반으로 하여 동바리와 보 거푸집 및 슬래브 거푸집을 설치한 뒤, 보 및 슬래브의 콘크리트를 타설하는 공법이다.Among them, the method of using copper barley is a method applied to strata with relatively high relative density. After digging the ground, the discarded concrete is placed on the excavated ground, and the discarded concrete is used as the support base. After installing the concrete, the concrete of the beam and slab is poured.

여기서, 보 거푸집 및 슬래브 거푸집은 굴착 지반 위의 버림 콘크리트 상에서 동바리에 의해 지지되어진다.Here, the beam formwork and slab formwork are supported by clubbing on discarded concrete on the excavation ground.

그러나, 동바리의 이용시에는 연약지반 상에서의 지지가 불안정하고, 또한 콘크리트 강도가 일정 한도 이상으로 보양되지 않으면 해체가 불가하기 때문에 콘크리트 양생 중 동바리의 존치로 인하여 아래층의 굴토공사가 진행될 수 없다.However, when the copper barrier is used, support on the soft ground is unstable and dismantlement is impossible unless the concrete strength is maintained above a certain limit.

더구나, 거푸집, 동바리 등 가설자재를 굴토작업장 외부로 반출한 뒤 굴토 후 다시 아래층으로 이동하여 재설치해야 하고, 이를 각 층의 시공시마다 반복해야 하는 바, 이러한 작업을 반복 수행하는데 있어서 번잡한 문제점이 있게 된다.In addition, the temporary materials such as formwork, dongbari, etc. should be taken out of the Gulto workshop and moved back to the lower floor after reconstruction, and this should be repeated for each floor construction. do.

또한, 콘크리트를 부어 넣은 뒤 충분한 양생기간을 거쳐 구조체가 제강도를 발현할 때까지 기다려야 하므로 작업대기 시간이 불가피하게 발생하고, 동바리나 거푸집의 소운반 및 재조립에 소요되는 비용과 시간이 과다하여 비경제적일 뿐만 아니라 모든 작업이 인력에 의존하므로 노동집약적이어서 기능공의 인력 부족이 심화되는 현실에서 원가 절감이 어려워지는 등의 문제점이 있게 된다.In addition, after the concrete is poured, it is necessary to wait until the structure develops the steelmaking strength after sufficient curing period. Therefore, waiting time is inevitably generated, and the cost and time required for transporting and reassembling the copper bar or formwork are excessive. In addition to being economical, all work depends on manpower, which is labor intensive, which leads to problems such as difficulty in cost reduction in a situation in which labor force shortages intensify.

한편, 동바리 사용시의 문제점을 해결하기 위하여, 지하구조물을 축조할 때 지상 1층부터 지하 최저층을 향해 구축해 나가는 무지보 역타설 거푸집 공법(Non Supporting Formwork System for Top Down Construction)으로서, 거푸집 지지용 동바리를 설치하지 않는 대신, 선시공한 상층 콘크리트 슬래브에 거푸집을 현수시키는 무지보 역타설 현수 거푸집 공법이 제시된 바 있다.On the other hand, in order to solve the problem of using the grouping, as a non-supporting formwork system for top down construction that is constructed from the ground floor to the lowest basement when building underground structures, Instead of installing it, an unsupported reversal suspension formwork was proposed to suspend the formwork on the pre-installed upper concrete slab.

이 무지보 역타설 현수 거푸집 공법은 선시공한 상층의 슬래브에 현수재를 이용하여 거푸집을 현수시킨 상태에서 이 거푸집을 이용하여 하층의 슬래브를 시공하는 방법이다.This unsupported back-casting formwork is a method of constructing a lower slab by using the formwork with the formwork suspended from the upper slab.

이 방법을 이용하여 각 층의 지하구조물을 축조하기 위해서는, 거푸집에 콘 크리트를 타설하여 상층 슬래브를 시공하는 단계, 이 상층 슬래브의 시공시에 이용된 거푸집을 상층 슬래브 위의 유압 승강기를 이용하여 하강시키는 단계, 이 하강된 거푸집을 이용해 하층 슬래브를 시공하는 단계를 각 층마다 반복하게 된다.In order to build underground structures of each floor using this method, concrete is laid on the formwork to construct upper slabs, and the formwork used in the construction of the upper slab is lowered by using a hydraulic lift on the upper slab. The lowering slab is constructed by using the lowered formwork for each floor.

이러한 현수식 공법은, 슬래브 거푸집 및 보 거푸집 하부에 동바리를 설치하지 않고 거푸집을 상층의 슬래브에 매달아 설치하기 때문에, 작업장 확보 및 작업자의 안전 보장 측면에서 보다 유리하고, 거푸집 작업과 상관없이 지하 터파기를 연속적으로 진행할 수 있으며, 충분한 양생기간 확보로 우수한 콘크리트 품질을 얻을 수 있는 동시에 공기 단축 및 원가 절감이 가능해지는 장점이 있다.This suspension method is more advantageous in securing the workplace and ensuring the safety of the worker because it is installed by hanging the formwork on the upper slab without installing the copper bar at the bottom of the slab formwork and the beam formwork. It is possible to proceed continuously, it is possible to obtain excellent concrete quality by securing a sufficient curing period, and at the same time has the advantage that it is possible to shorten the air and reduce the cost.

특히, 현수식 공법을 적용하는 경우에는 상층 슬래브에 현수된 거푸집을 연속적으로 달아내리는 지하 골조공사, 하부에서의 굴토공사, 그리고 지상부 구조물 축조공사의 3단계 공정을 동시에 진행할 수 있게 된다.In particular, when the suspension method is applied, it is possible to simultaneously perform the three-stage process of underground frame construction, which continuously runs down the formwork suspended from the upper slab, the excavation work from the bottom, and the ground structure construction.

그러나, 무지보 공법으로 개발된 상기 현수식 공법에도 다음과 같은 문제점이 있다.However, the suspension method developed by the unsupported method has the following problems.

종래 현수재 지지방식의 공법에서는 유압 승강기 및 현수재가 모두 상층의 콘크리트 슬래브에 지지된 상태에서 하층 슬래브의 콘크리트 시공이 이루어진다. In the conventional suspension support method, the concrete construction of the lower slab is made while both the hydraulic elevator and the suspension are supported by the upper concrete slab.

즉, 하층 슬래브로 타설되는 콘크리트의 하중이 거푸집 및 현수재를 통해 전적으로 상층 슬래브에 지지되는 시스템으로 되어 있는 것이다. In other words, it is a system in which the load of concrete cast into the lower slab is entirely supported by the upper slab through formwork and suspension.

이와 같이 거푸집에 타설되는 하층 콘크리트의 하중이 전적으로 상층 슬래브에 작용하면서 상층 슬래브에 무리한 하중이 가해질 수 있고, 구조적 안정성을 최대한 확보하기 위해서는 하층 슬래브의 콘크리트 시공이 필연적으로 상층 슬래브의 시공이 완료된 후라야 가능하다.As the load of the lower concrete placed on the formwork acts entirely on the upper slab, the excessive load may be applied to the upper slab. It is possible.

결국, 선시공 슬래브의 완전 양생을 위하여 시간이 필요한 만큼 공기 지연의 문제가 불가피하게 발생하게 된다.As a result, the problem of air delay inevitably occurs as time is required for the complete curing of the pre-installed slab.

이러한 문제점을 해결하기 위하여, "역타설 시스템의 이동 조립식 지지 브라켓"이라는 명칭으로 출원되어 등록된 한국실용신안등록번호 제372315호에는 시공층의 보 거푸집 및 데크 플레이트에 콘크리트가 타설되는 동안 그 콘크리트 하중을 포함하여 보 거푸집, 데크 플레이트, 보 거푸집을 지지하는 철골보인 지지거더의 하중을 골조용 기둥 상에서 지지하는 브라켓이 개시되어 있다.In order to solve this problem, Korean Utility Model Registration No. 372315, filed and registered under the name of "Moving assembly support bracket of reversing system," loads concrete while it is being cast on the formwork and deck plate of the construction layer. Disclosed is a bracket for supporting the load of the beam formwork, the deck plate, the support girders, which is a steel frame beam supporting the formwork, on a frame pillar.

상기 지지 브라켓을 이용한 역타설 시스템에서는 각 골조용 기둥의 해당 층 높이에 지지 브라켓이 장착되어, 이 지지 브라켓 위에 지지거더가 지지되고, 이 지지거더 위에 보 거푸집이 지지되며, 보 거푸집에 데크 플레이트가 지지된다.In the reverse casting system using the support bracket, a support bracket is mounted at the height of the corresponding floor of each frame pillar, and a support girder is supported on the support bracket, and the formwork is supported on the support girder, and the deck plate is provided on the formwork. Supported.

그리고, 상기 지지 브라켓은 기둥 상에 쉽게 장착 및 해체가 가능하므로, 해당 층에 대해 보 및 슬래브의 콘크리트 타설 작업이 완료되면, 각 지지 브라켓들을 기둥 상의 아래층 높이로 내려 재설치한 뒤 동일 목적으로 사용하게 된다. In addition, since the support bracket can be easily mounted and dismantled on the column, when the concrete placing work of the beam and the slab is completed for the floor, the support brackets are lowered to the lower level on the column and reinstalled to be used for the same purpose. do.

이와 같이 지지 브라켓을 이용한 방법은, 종래와 같이 선시공한 상층 슬래브에 현수재를 이용하여 현수 및 지지시키는 방법이 아닌, 골조용 기둥에 지지 브라켓을 사용하여 보 및 슬래브의 거푸집 구조체를 지지시키는 방법으로서, 위에서 언급한 현수재 지지방식의 여러 문제점들을 해결할 수 있다.Thus, the method using the support bracket is a method of supporting the formwork of the beam and the slab by using the support bracket on the frame pillar rather than the method of suspending and supporting the upper slab pre-constructed using the suspension material. In other words, the above mentioned problems of suspension support can be solved.

또한, 역타설 공법에 사용되는 지지 브라켓에 대해서도 그 구성 및 구조를 보다 간단히 하고 경량화하는 동시에 제작단가를 낮춘 보다 개선된 지지 브라켓이 출원된 바 있다(한국특허출원번호 10-2005-0035022 및 한국실용신안출원번호 20-2005-0016621). In addition, the support bracket used in the reverse casting method has been filed with a more improved support bracket with a simpler, lighter weight and lower manufacturing cost. (Korean Patent Application No. 10-2005-0035022 and Korean Utility Sinan Application No. 20-2005-0016621).

그러나, 지지 브라켓을 이용하더라도 지하층의 시공시에 작업자가 올라가 작업하게 되는 작업대의 설치에 대해서는 특별히 개선된 바가 없으며, 통상 현수재 지지방식의 공법에서는 작업대를 현수재를 이용하여 현수시키므로, 작업대가 완전히 고정되지 못하고 흔들리는 등 안전성에서 매우 취약하고, 비용 및 활용성 측면에서도 불리한 문제점이 있었다. However, even if the support bracket is used, there is no particular improvement in the installation of the work platform where the worker climbs up during the construction of the basement floor, and in general, the suspension support method is used to suspend the work platform using the suspension material. It is very vulnerable in safety, such as unstable and rocking, and had disadvantages in terms of cost and usability.

따라서, 본 발명은 상기와 같은 문제점을 해결하기 위하여 발명한 것으로서, 브라켓에 의해 고정 지지되는 가설구조체를 각 층 시공 중의 작업대로 활용할 수 있게 되면서 안전성 측면에서 향상되는 효과가 있고, 최하층 바닥 구조로 사용될 데크를 가설구조체 내에 포함시켜 사용하므로 작업대의 설치비용을 줄일 수 있는 등 활용성 및 경제성 측면에서 유리해지는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법에 관한 것이다.Therefore, the present invention has been invented to solve the above problems, it is possible to utilize the temporary structure that is fixedly supported by the bracket as a workbench during the construction of each floor, there is an effect that is improved in terms of safety, and used as the bottom floor structure The present invention relates to a reverse casting method that can utilize a bracket-supported temporary structure that is advantageous in terms of utility and economics, such as reducing the installation cost of a workbench because the deck is included in the temporary structure.

이하, 첨부한 도면을 참조하여 본 발명을 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

본 발명은, 지하층의 보 및 슬래브를 역타 시공하는 역타설 공법에 있어서,The present invention, in the reverse casting method for reverse construction of the beam and the slab of the basement floor,

(a)흙막이벽 시공 후, 그 안쪽 지중에 H-형강 기둥을 시공하는 단계와; (b)1 차로 지반 굴토 후, 노출된 H-형강 기둥에 지지 브라켓을 고정 설치하고, 이웃한 H-형강 기둥의 두 지지 브라켓 사이 및 지지 브라켓과 흙막이벽 사이에 지지거더를 설치하는 단계와; (c)상기 지지거더에 가설구조체를 지지시켜 설치하는 단계와; (d)상기 가설구조체를 작업대로 활용하면서 그 위에 슬래브 거푸집과 보 거푸집을 설치한 후, 콘크리트 타설하여 1층 바닥 슬래브 및 보를 시공하는 단계와; (e)2차로 지반 굴토 후, 상기 각 지지 브라켓을 해체 및 하강시켜 추가 노출된 H-형강 기둥의 지하 1층 설치 높이에 맞추어 재설치하는 단계와; (f)상기 지지거더 및 가설구조체를 현수재로 하강시켜 상기 지지 브라켓 위에 재설치하는 단계와; (g)상기 가설구조체를 작업대로 활용하면서 그 위에 슬래브 거푸집과 보 거푸집을 설치한 후, 콘크리트 타설하여 지하 1층 바닥 슬래브 및 보를 시공하는 단계와; (h)상기 (e)~(g)단계를 반복하여 지하 2층 및 그 이하 지하층의 바닥 슬래브 및 보를 역타 시공해 내려가는 단계;를 포함하는 것을 특징으로 한다.(a) constructing an H-beam column in the inner ground after the construction of the retaining wall; (b) after the primary ground pit, the support bracket is fixed to the exposed H-beams and the support girder is installed between the two support brackets of neighboring H-beams and between the support bracket and the wall; (c) supporting and installing a temporary structure on the support girder; (d) installing slab formwork and beam formwork thereon while using the temporary structure as a workbench, and then placing concrete on the first floor floor slab and beam; (e) dismantling and lowering each of the support brackets after the second ground ground excavation and re-installing them according to the installation height of the first basement of the H-beams further exposed; (f) lowering the support girder and the temporary structure with a suspension material and reinstalling the support girder on the support bracket; (g) installing the slab formwork and beam formwork on the workbench while using the temporary structure as a workbench, and then constructing the basement floor slab and beam by placing concrete; (h) repeating the steps (e) to (g) to reverse construction of the bottom slab and beams of the basement 2 and the basement floor below.

특히, 상기 (c)단계의 가설구조체를 설치하기 전에 상기 (b)단계에서, 이웃한 H-형강 기둥의 두 지지 브라켓 사이에 2줄씩의 지지거더를 나란히 설치하고, 2줄씩의 지지거더를 각 H-형강 기둥을 중심으로 종과 횡으로 설치하되, 4개의 지지 브라켓에서 4각형 형태로 배치되는 4개의 지지거더들끼리 단부간에 접합 플레이트로 연결하여, 4개씩의 지지 브라켓을 한 단위로 하는 지지거더 사각틀을 구성하는 것을 특징으로 한다.In particular, before the installation of the temporary structure of step (c), in step (b), two support girders are installed side by side between two support brackets of adjacent H-beam columns, and two support girders are installed in each line. It is installed horizontally and vertically around the H-beam column, and four support girders arranged in a quadrilateral form from four support brackets are connected to each other by a joining plate between ends, so that four support brackets are used as a unit. Characterized by girder square frame.

또한, 상기 (c)단계에서 트러스 데크를 포함하는 가설구조체를 설치하고, 상기 각 층의 바닥 시공용 슬래브 거푸집으로서 트러스 데크를 사용하되, 상기 (h)단 계에서 지지 브라켓 및 지지거더를 이용하는 최하층 시공시에는 상기 가설구조체에 포함된 트러스 데크를 바닥 시공용 슬래브 거푸집으로 사용하는 것을 특징으로 한다.In addition, in the step (c), the temporary structure including the truss deck is installed, and the truss deck is used as the slab formwork for the floor construction of each layer, and in the step (h), the lowest layer using the support bracket and the support girder. In construction, the truss deck included in the temporary structure is used as a slab formwork for floor construction.

이때, 바람직한 제1실시예로서, 상기 (c)단계의 가설구조체를 설치하는 과정이,At this time, as a first preferred embodiment, the process of installing the temporary structure of the step (c),

상기 (b)단계에서 설치된 각 지지거더 사각틀의 지지거더 위에 길이방향을 따라 H-형강으로 된 테두리 보강보를 2층으로 적층시켜 고정하는 단계와; 상기 테두리 보강보들이 형성하는 사각공간 내측으로 테두리 보강보 사이에 H-형강으로 된 종방향 및 횡방향, 경사방향 보강보를 추가로 설치하여, 상기 보강보들로 이루어진 보강 지지틀을 각 지지거더 사각틀 위에 일체로 구성하는 단계와; 상기 각 보강 지지틀의 테두리 보강보 위에 각재를 개재시켜 트러스 데크들을 고정 설치하고, 이 트러스 데크 위에 복공용 합판을 고정 설치하여 가설구조체를 완성하는 단계;로 이루어짐을 특징으로 한다.Stacking and fixing the edge reinforcement beams made of H-shaped steel in two layers on the support girders of the respective square girders installed in the step (b); The longitudinal, transverse and inclined reinforcement beams made of H-shaped steel are additionally installed between the edge reinforcement beams inside the rectangular spaces formed by the edge reinforcement beams. Integrally configuring; And fixing the truss decks by interposing each of the truss decks on the edge reinforcing beams of the respective reinforcing support frames, and fixing the plywood for rehabilitation on the truss decks to complete the temporary structure.

또한, 상기 (c)단계에서 딥 데크를 포함하는 가설구조체를 설치하고, 상기 각 층의 바닥 시공용 슬래브 거푸집으로서 딥 데크를 사용하되, 상기 (h)단계에서 지지 브라켓 및 지지거더를 이용하는 최하층 시공시에는 상기 가설구조체에 포함된 딥 데크를 바닥 시공용 슬래브 거푸집으로 사용하는 것을 특징으로 한다.In addition, in step (c), a temporary structure including a deep deck is installed, and a deep deck is used as the slab formwork for floor construction of each layer, but in the step (h), the lowest floor construction using a support bracket and a support girder. At the time, the deep deck included in the temporary structure is characterized in that it is used as slab formwork for floor construction.

이때, 바람직한 제2실시예로서, 상기 (c)단계의 가설구조체를 설치하는 과정이,At this time, as a second preferred embodiment, the process of installing the temporary structure of the step (c),

상기 (b)단계에서 설치된 각 지지거더 사각틀에 사각공간 내측으로 H-형강으 로 된 종방향 및 횡방향 보강보를 추가로 설치하여, 상기 지지거더 사각틀과 보강보들로 이루어진 가설지지틀을 일체로 구성하는 단계와; 상기 각 가설지지틀의 보강보 위에 각재를 개재시켜 딥 데크들을 고정 설치하고, 이 딥 데크 위에 복공용 합판을 고정 설치하여 가설구조체를 완성하는 단계;로 이루어짐을 특징으로 한다.In addition, by installing the longitudinal and transverse reinforcement beams made of H-shaped steel in the rectangular space inside each support girder square frame installed in the step (b), the temporary support frame composed of the support girder square frame and the reinforcement beams is integrally formed. Making a step; It is characterized in that the step of fixing the deep decks by interposing the angular material on the reinforcement beams of each temporary supporting frame, and fixing the perforated plywood on the deep deck to complete the temporary structure.

한편, 본 발명은, 지하층의 보 및 슬래브를 역타 시공하는 역타설 공법에 있어서,On the other hand, the present invention, in the reverse casting method for reverse construction of the beam and the slab of the basement floor,

(a')흙막이벽 시공 후, 그 안쪽 지중에 H-형강 기둥을 시공하는 단계와; (b')1차로 지반 굴토 후, 노출된 H-형강 기둥에 지지 브라켓을 고정 설치하고, 이웃한 H-형강 기둥의 두 지지 브라켓 사이 및 지지 브라켓과 흙막이벽 사이에 지지거더를 설치하는 단계와; (c')상기 지지거더에 보강보 및 받침보, 장선들을 차례로 설치한 후, 이 장선들 위로 슬래브 및 보 시공용 합판 거푸집을 설치하여, 이들을 포함하는 가설구조체를 구성하는 단계와; (d')상기 합판 거푸집 내에 콘크리트 타설하여 1층 바닥 슬래브 및 보를 시공하는 단계와; (e')2차로 지반 굴토 후, 상기 각 지지 브라켓을 해체 및 하강시켜 추가 노출된 H-형강 기둥의 지하 1층 설치 높이에 맞추어 재설치하는 단계와; (f')상기 지지거더 및 합판 거푸집을 포함하는 가설구조체를 현수재로 하강시켜 상기 지지 브라켓 위에 재설치하는 단계와; (g')상기 가설구조체의 합판 거푸집 내에 콘크리트 타설하여 지하 1층 바닥 슬래브 및 보를 시공하는 단계와; (h')상기 (e')~(g')단계를 반복하여 지하 2층 및 그 이하 지하층의 바닥 슬래브 및 보를 역타 시공해 내려가는 단계;를 포함하는 것을 특징으로 한다.(a ') constructing the H-beam column in the inner ground after constructing the wall; (b ') the first step after ground excavation, fixing the support brackets to the exposed H-beams, and installing the support girder between the two support brackets of the neighboring H-beams and between the support brackets and the retaining walls; ; (c ') installing reinforcing beams and supporting beams and joists in order, and then installing slab and plywood formwork for beam construction on the joists, constructing a temporary structure comprising them; (d ') constructing concrete in the plywood formwork to construct the ground floor slab and beams; (e ') after the ground is excavated in a second step, dismantling and lowering each of the supporting brackets and reinstalling them according to the installation height of the first basement of the H-beams further exposed; (f ') lowering the temporary structure including the support girder and the plywood formwork with a suspension material and reinstalling it on the support bracket; (g ') constructing concrete in a plywood formwork of the temporary structure to construct a basement floor slab and beams; (h ') repeating the steps (e') to (g ') by stepping down the bottom slab and beams of the basement 2 and the basement floor below.

또한, 바람직한 제3실시예로서, 상기 (c')단계의 가설구조체를 설치하는 과정이,In addition, as a third preferred embodiment, the process of installing the temporary structure of the step (c '),

상기 (b')단계에서 설치된 각 지지거더 사각틀에 사각공간 내측으로 H-형강으로 된 종방향 및 횡방향 보강보를 추가로 설치하고, 상기 지지거더, 종방향 및 횡방향 보강보들 위에 H-형강으로 된 받침보를 2층으로 적층시켜, 상기 지지거더 사각틀과 보강보, 받침보들로 이루어진 가설지지틀을 일체로 구성하는 단계와; 상기 각 가설지지틀 위에 장선들을 받침보와 횡방향으로 설치한 뒤, 상기 장선들 위로 합판 거푸집을 고정 설치하여 가설구조체를 완성하는 단계;로 이루어짐을 특징으로 한다.The longitudinal and transverse reinforcement beams of H-shaped steel are additionally installed in the rectangular frame of each support girder installed in the step (b '), and the H-beams are supported on the support girder, longitudinal and transverse reinforcement beams. Stacking the supported support beams in two layers to integrally construct a temporary support frame consisting of the support girder square frame, the reinforcement beams and the support beams; And installing the joists on the temporary support frames in the transverse direction with the support beams, and then fixing the plywood formwork on the joists to complete the construction of the construction of the construction.

이하, 첨부한 도면을 참조하여 본 발명을 더욱 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in more detail with reference to the accompanying drawings.

본 발명은 지하층의 보 및 슬래브 시공시에 콘크리트 타설되는 보 및 슬래브 거푸집 구조체를 지지시키기 위하여 기둥 상에 고정 설치되는 지지 브라켓을 사용하는 역타설 공법에 관한 것으로서, 특히 각 층 시공시에 작업대로 활용할 수 있는 가설구조체를 지지 브라켓에 지지시켜 설치하는 것에 주안점이 있는 것이다. The present invention relates to a reverse casting method using a support bracket fixedly installed on a column to support a beam and slab formwork to be cast in concrete during the construction of a beam and a slab of a basement layer. The main point is to install the temporary structure to support the mounting bracket.

첨부한 도 1은 본 발명에서 이용되는 브라켓 지지 타입 가설구조체(작업대)의 제1실시예가 설치된 평면도이고, 도 2a와 도 2b는 도 1에 도시한 가설구조체의 제1실시예의 단면도로서, 도 2a는 도 1의 선 'A-A' 방향에서 취한 단면도이고, 도 2b는 도 1의 선 'B-B' 방향에서 취한 단면도이다.1 is a plan view in which the first embodiment of the bracket supporting type temporary structure (working table) used in the present invention is installed, and FIGS. 2A and 2B are cross-sectional views of the first embodiment of the temporary structure shown in FIG. Is a cross-sectional view taken in the direction 'AA' of FIG. 1, and FIG. 2B is a cross-sectional view taken in the direction 'BB' of FIG.

도 3은 도 1에 도시한 가설구조체의 제1실시예를 사용하는 경우에서 1층 및 지하층의 보 및 슬래브 구축 시스템을 도시한 단면도이고, 도 4는 도 1에 도시한 가설구조체의 제1실시예를 사용하는 경우에서 최하층의 보 및 슬래브 구축 시스템을 도시한 단면도이다.FIG. 3 is a cross-sectional view showing a beam and slab construction system of first and basement floors when the first embodiment of the temporary structure shown in FIG. 1 is used, and FIG. 4 is a first embodiment of the temporary structure shown in FIG. In the case of using the example, it is sectional drawing which shows the lowermost beam and slab construction system.

도 5a ~ 도 5h는 도 1에 도시한 가설구조체의 제1실시예를 작업대로 활용할 수 있는 지하층의 보 및 슬래브 역타 시공 전체 과정을 도시한 공정도이다.5a to 5h are process diagrams illustrating the entire process of construction of beam and slab reverse construction of the basement floor which can utilize the first embodiment of the temporary structure shown in FIG. 1 as a work bench.

도 1 내지 도 5h에서는 슬래브 거푸집 구조체로서 트러스 데크(truss deck)를 사용하는 경우에 대한 역타설 공법의 예가 도시되어 있으며, 1층 및 그 이하 지하층 시공에는 최하층의 본 구조물로 사용되는 트러스 데크가 포함된 가설구조체를 지지 브라켓에 지지시켜 설치한 후 작업대로 활용하고, 최하층의 시공시에는 가설구조체에 포함된 상기 트러스 데크를 슬래브 구축을 위한 본 구조물로 사용하는 것에 특징이 있는 것이다.1 to 5h show an example of the reverse casting method for the case of using a truss deck as a slab formwork structure, the first and lower basement construction includes the truss deck used as the lowermost main structure It is characterized by using the truss deck included in the temporary structure as a main structure for slab construction at the time of construction of the lowermost floor.

우선, 시공되는 건물의 경계선을 따라 흙막이벽(1)으로 CIP(Cast In-Place Pile)를 시공하며, 이 CIP에서는 엄지말뚝으로 통상 H-파일이 사용되어, 이 수직 시공된 H-파일이 배면의 토압 및 수압을 직접 지지하는 수직 휨부재의 역할을 하게 된다.First, CIP (Cast In-Place Pile) is constructed along the boundary line of the building to be constructed as a barrier wall (1). In this CIP, an H-pile is usually used as a thumb pile, and the vertically constructed H-pile is It acts as a vertical bending member that directly supports the earth pressure and water pressure.

이어, 흙막이벽(1)의 안쪽 지중에서 건물의 기둥에 상응하는 위치에 구멍을 천공한 후 H-형강 기둥(2)을 삽입하고, 각 H-형강 기둥(2)에 대하여 PRD 기초 콘크리트(3)를 타설하여 기둥 시공 작업을 완료한다. Subsequently, after drilling a hole at a position corresponding to the pillar of the building in the inner ground of the retaining wall (1), the H-beam column (2) is inserted, and the PRD foundation concrete (3) for each H-beam column (2) ) To finish the column construction.

다음, 1층 바닥 슬래브(S1) 및 보(G1)의 시공을 위하여, 1차로 지반을 굴토한 후 노출된 각 H-형강 기둥(2)의 소정 높이에 지지 브라켓(110)을 고정 설치하 며, 여기까지는 종래의 지지 브라켓을 이용한 시공 과정과 동일하다.Next, for the construction of the ground floor slab (S1) and the beam (G1), the support bracket 110 is fixed to a predetermined height of each exposed H-beam column (2) after first excavating the ground. Up to now, the construction process using the conventional support bracket is the same.

다만, 지지 브라켓(110) 위에 보 및 슬래브 거푸집 구조체를 지지하기 위한 철골보인 지지거더(121a,121b)가 설치되고, 특히 본 발명에서는 상기 지지거더(121a,121b) 위에 작업대로 사용하게 될 가설구조체(130)가 추가로 설치된 후, 이 가설구조체(130) 위에 보 및 슬래브 거푸집 구조체(150,153)가 설치되므로, 각 H-형강 기둥(2)에서 지지 브라켓(110)이 설치되는 높이는 종래와 비교하여 가설구조체(130)가 설치되는 높이 만큼 낮게 설치된다. However, the support girders 121a and 121b for supporting the beam and the slab formwork structure are installed on the support bracket 110, and in particular, in the present invention, a temporary structure to be used as a workbench on the support girders 121a and 121b. After the 130 is additionally installed, since the beam and slab formwork structures 150 and 153 are installed on the temporary structure 130, the height at which the support bracket 110 is installed in each H-beam column 2 is compared with the prior art. The temporary structure 130 is installed as low as the height is installed.

상기 지지 브라켓으로는 국내 실용신안등록번호 제372315호, 특허출원번호 10-2005-0035022, 실용신안출원번호 20-2005-0016621에 기재된 것들을 선택하여 사용할 수 있다. The support bracket may be selected and used in Korea Utility Model Registration No. 372315, Patent Application No. 10-2005-0035022, Utility Model Application No. 20-2005-0016621.

상기와 같이 지지 브라켓을(110) 설치한 후 지지 브라켓 위에 지지거더(121a,121b)를 설치하고, 이 지지거더(121a,121b) 위에는 작업대로 사용할 수 있는 가설구조체(130)를 설치하며, 이 가설구조체(130) 위에는 1층 바닥의 슬래브(S1) 및 보(G1)를 콘크리트 시공하기 위한 거푸집 구조체(150,153)를 설치한다.After the support bracket 110 is installed as described above, the support girders 121a and 121b are installed on the support bracket, and on the support girders 121a and 121b, a temporary structure 130 which can be used as a work bench is installed. On the temporary structure 130, formwork structures 150 and 153 for concrete construction of the slab S1 and the beam G1 of the first floor are installed.

상기 각 지지거더(121a,121b)는 양단부를 이웃한 두 기둥(2) 상의 지지 브라켓(110) 위에 지지시켜 설치하게 되며, 지지거더(121a,121b)가 기둥 상의 지지 브라켓(110)과 흙막이벽(1) 사이에 설치되는 경우에는 흙막이벽쪽의 단부를 흙막이벽(1) 내 H-파일에 설치된 별도 브라켓(4)이나 지지수단 또는 버림 콘크리트 위에 지지시킨다(도 5b 참조).Each of the support girders 121a and 121b is installed by supporting both ends of the support brackets 110 on two adjacent pillars 2, and the support girders 121a and 121b support the support brackets 110 and the soil wall on the columns. When installed between (1), the end of the retaining wall side is supported on a separate bracket (4) or supporting means or discarded concrete installed on the H-pile in the retaining wall (see Fig. 5b).

상기 지지거더(121a,121b)는 H-형강으로 실시될 수 있으며, 도 1에 도시된 바와 같이 지지거더(121a,121b)들이 각 H-형강 기둥(2)을 중심으로 사방 2줄씩 배치되어 설치된다.The support girders 121a and 121b may be implemented as H-shaped steels, and as shown in FIG. 1, the support girders 121a and 121b are disposed to be arranged in two rows each around the H-beams 2. do.

즉, 이웃한 H-형강 기둥(2)의 두 지지 브라켓(110) 사이에 2개의 지지거더(121a,121b)가 나란히 설치되는데, 2줄씩의 지지거더(121a,121b)들이 각 H-형강 기둥(2)을 중심으로 종과 횡, 사방으로 설치되므로, 지지거더(121a,121b)들은 H-형강 기둥(2)의 지지 브라켓(110)들을 연결하는 격자형 배치구조가 된다.That is, two support girders 121a and 121b are installed side by side between two support brackets 110 of the neighboring H-beam pillars 2, and two support girders 121a and 121b are formed by two rows of each H-beam pillar. Since it is installed in the longitudinal, transverse, and all directions about (2), the support girders (121a, 121b) is a lattice arrangement structure connecting the support brackets 110 of the H-beams (2).

도 1을 참조하면, 하나의 지지 브라켓(110)에 총 8개 지지거더(121a,121b)의 단부가 지지되고 있으며, 4개의 지지 브라켓(110)에 4각형 형태로 배치되는 4개의 지지거더(121a,121b)들은 단부가 접합 플레이트(122)로 연결 조립되어 일체화된다.Referring to FIG. 1, one end of eight support girders 121a and 121b is supported on one support bracket 110, and four support girders disposed in a quadrangular form on four support brackets 110 ( 121a and 121b are integrated by connecting the ends to the bonding plate 122.

도 1은 복공용 합판(원 안으로 표시함)(141)을 제외한 가설구조체(130)의 나머지 구성요소를 평면도로 도시한 것이므로, 실제로는 각 지지거더(121a,121b) 위에 길이방향을 따라 2층으로 적층되어 설치되는 보강보(132)만이 보이게 되나(위에서 본 도면이므로, 실제로는 위에 설치된 테두리 보강보만이 보임), 평면도 상에서 지지거더(121a,121b)가 그 위에 적층된 테두리 보강보(132)와 동일한 배치구조이기 때문에, 지지거더(121a,121b)의 배치구조가 상기와 같이 설명될 수 있다.FIG. 1 is a plan view showing the remaining components of the temporary structure 130 excluding the plywood plywood (shown in a circle) 141, and thus, in fact, two layers along the longitudinal direction on each support girder 121a and 121b. Only the reinforcement beams 132 stacked and installed are visible (as seen from above, in reality, only the edge reinforcement beams installed above are visible), and the support girders 121a and 121b are stacked on the edge reinforcement beams 132 stacked thereon. Since it is the same arrangement structure as that, the arrangement structure of the support girders 121a and 121b can be described as above.

상기 접합 플레이트는 도 2a에서 도면부호 122로 지시되고 있는데, 횡방향 배치된 지지거더(121b) 2개의 각 단부에 각각 접합 플레이트(122)가 용접 설치되고, 각 접합 플레이트(122)에 종방향 배치된 지지거더(121a)의 단부가 볼트(123)로 체결되어, 단부간에 연결된 4개의 지지거더(121a,121b)들이 전체적으로 사각틀 형태를 이루어 일체화된다.The joining plate is indicated by reference numeral 122 in FIG. 2A, in which the joining plate 122 is welded to each end of each of the two supporting girders 121b arranged in the lateral direction, and the joining plate 122 is longitudinally disposed. Ends of the supported girders 121a are fastened by bolts 123, and four support girders 121a and 121b connected between the ends are integrally formed in a rectangular frame shape as a whole.

상기 지지거더(121a,121b)들을 상층 시공 후 하층 시공을 위하여 하강시킬 때, 단부간에 연결 고정되어 사각틀을 이루고 있는 4개의 지지거더(121a,121b)들을 하나의 단위로 하여 하강시키게 된다.When the support girders 121a and 121b are lowered for lower construction after the upper layer construction, four support girders 121a and 121b which are connected and fixed between end portions to form a rectangular frame are lowered as one unit.

도 2a에서 도면부호 6은 지지거더(121a,121b)들을 하강시키기 위해 연결되는 현수재들을 나타내는데, 이 현수재(6)들은 각각 하단이 지지거더(121a,121b)의 재킹 포인트(도 1에도 표시함)에 연결되어, 지지 브라켓(110) 해체 후 지지거더(121a,121b) 및 가설구조체(130)를 하강시킬 때에만 이용되는 것들이다. In Fig. 2a, reference numeral 6 denotes suspensions which are connected to lower the support girders 121a and 121b, the suspensions 6 having lower ends of the jacking points of the support girders 121a and 121b respectively (also shown in Fig. 1). It is used only when the support girder (121a, 121b) and the temporary structure 130 is lowered after dismantling the support bracket (110).

한편, 본 발명에서 작업대로 활용되는 가설구조체(130)는, 상기와 같이 4개의 지지거더(121a,121b)로 구성되는 지지거더 사각틀(120)을 한 단위로 하여, 각 단위별로 구성되는데, 각 사각틀(120)을 구성하는 4개의 지지거더(121a,121b) 위에 H-형강으로 된 복수개의 보강보(132,133,134,135) 및 트러스 데크(139), 복공용 합판(141)을 조립하여 구성되며, 각 지지거더 사각틀(120)마다 동일하게 구성된다.On the other hand, the temporary structure 130 utilized in the workbench according to the present invention, the support girder square frame 120 composed of four support girders (121a, 121b) as described above, each unit is configured for each unit, each Consists of assembling a plurality of reinforcement beams (132, 133, 134, 135), truss deck (139), plywood plywood (141) made of H-shaped steel on the four support girders (121a, 121b) constituting the square frame 120, each support The girder square frame 120 is configured the same.

하나의 지지거더 사각틀(120) 위에 설치되는 가설구조체(130)의 구성에 대해서 구체적으로 설명하면 다음과 같다.The configuration of the temporary structure 130 installed on one support girder rectangular frame 120 will be described in detail as follows.

우선, 각 지지거더(121a,121b) 위에 테두리 보강보(132)를 2층으로 적층시킨 뒤, 이렇게 아래 위로 놓여져 있는 지지거더(121a,121b)와 테두리 보강보(132)의 서로 맞닿아 있는 플랜지 부분(H-빔의 플랜지 부분)을 볼트 및 너트(124)로 체결하여, 테두리 보강보(132)를 지지거더(121a,121b) 위에 고정한다. First, the edge reinforcement beams 132 are laminated in two layers on each of the support girders 121a and 121b, and the flanges which are in contact with each other of the support girders 121a and 121b and the edge reinforcement beams 132 thus placed up and down. The portion (flange portion of the H-beam) is fastened with bolts and nuts 124 to fix the rim reinforcement beam 132 on the support girders 121a and 121b.

상기 테두리 보강보(132)는 각 지지거더(121a,121b) 위에서 중앙에 1개, 그리고 그 양 측방으로 각 1씩 총 3개가 연이어 설치된다.The edge reinforcing beams 132 are installed in the center one on each support girder (121a, 121b), and a total of three each one in each side thereof.

또한, 하나의 지지거더 사각틀(120)에서 지지거더(121a,121b)들이 4각형 형 태로 배치되므로 그 위에 적층되는 테두리 보강보(132)들 또한 전체적으로는 4각형 형태로 배치되는데, 이 테두리 보강보(132)들이 형성하는 사각공간 내에는 또 다른 H-형강의 보강보(133,134,135)들을 적절히 배치하여 고정 설치한다.In addition, since the support girders 121a and 121b are arranged in a quadrangular shape in one support girder square frame 120, the edge reinforcement beams 132 stacked thereon are also arranged in a quadrangular shape as a whole. In the rectangular space formed by the 132, another H-shaped reinforcement beams 133, 134, 135 are properly arranged and fixed.

예컨대, 도 1에 도시한 바와 같이, 각 지지거더 사각틀(120)에서 양쪽 종방향 두 지지거더(121a) 위의 테두리 보강보(132) 사이에는 횡방향으로 연결되는 횡방향 보강보(133)를 설치하고, 이 횡방향 보강보(133)와 양쪽 횡방향 두 지지거더(121b) 위의 테두리 보강보(132) 사이에는 종방향으로 연결되는 종방향 보강보(134)를 설치한다.For example, as shown in Figure 1, in each support girder square frame 120 between the reinforcement beams 132 on the two longitudinal support girders (121a) in both longitudinal directions, the transverse reinforcement beams 133 connected in the transverse direction The longitudinal reinforcement beams 134 connected in the longitudinal direction are installed between the transverse reinforcement beams 133 and the edge reinforcement beams 132 on the two transverse support girders 121b.

또한, 두 변의 테두리 보강보(132) 사이에는 경사방향으로 경사방향 보강보(135)를 설치하는데, 각 방향으로 모두 설치하여 총 4개의 경사방향 보강보(135)를 설치한다.In addition, between the two side edge reinforcement beams 132 is installed in the inclined direction reinforcement beams 135 in the inclined direction, all in each direction to install a total of four inclined reinforcement beams 135.

상기 테두리 보강보(132)와 횡방향 보강보(133), 종방향 보강보(134), 경사방향 보강보(135)는 모두 H-형강을 적정 크기로 절단하여 사용한다. The edge reinforcement beam 132, the transverse reinforcement beam 133, the longitudinal reinforcement beam 134, the inclined reinforcement beam 135 are all used to cut the H-shaped steel to the appropriate size.

이하, 본 명세서에서는 명확한 설명을 위하여 4개의 지지거더(121a,121b)가 구성하는 사각틀(120)을 지지거더 사각틀로, 이 지지거더 사각틀(120) 위에 상기 보강보(132,133,134,135)들을 설치하여 구성되는 또 다른 틀을 보강 지지틀(131)로 칭하기로 한다.Hereinafter, in the present specification, for the sake of clarity, the rectangular frame 120 constituted by the four support girders 121a and 121b is a support girder square frame, and the reinforcement beams 132, 133, 134, and 135 are installed on the support girder square frame 120. Another frame will be referred to as a reinforcement support frame 131.

상기 보강 지지틀(131)을 구성하는 상기 보강보(132,133,134,135)들간에는 지지거더(121a,121b)와 마찬가지로 접합 플레이트를 사용하여 연결하게 되는데, 예컨대 지지거더(121a,121b) 위에 적층시켜 볼트 체결한 테두리 보강보(132) 내측으 로 접합 플레이트(137)가 측방 돌출되게 용접 설치되고, 이 측방 돌출된 접합 플레이트(137)에 경사방향 보강보(135)의 끝단을 접합시킨 상태에서 볼트 및 너트(138)로 체결하여 고정하게 된다.The reinforcing beams 132, 133, 134, and 135 constituting the reinforcing support frame 131 are connected to each other by using a joining plate similarly to the support girders 121a and 121b, for example, by being laminated on the support girders 121a and 121b and bolted together. The joint plate 137 is welded to the inner side of the edge reinforcement beam 132 so as to protrude laterally, and the bolt and nut (with the end of the inclined reinforcement beam 135 bonded to the side protruding joining plate 137). 138) to be fixed.

도 6은 직각 배치된 측방 테두리 보강보(132b)간의 결합구조를 보여주고 있으나, 이들과 마찬가지로 중앙 테두리 보강보(132a), 횡방향 보강보(133)와 종방향 보강보(134)간에도 모두 동일한 형태의 접합 플레이트를 사용하여 단부간에 연결 고정한다.FIG. 6 shows the coupling structure between the lateral reinforcement beams 132b disposed at right angles, but similarly, the same is applied between the center edge reinforcement beams 132a, the lateral reinforcement beams 133, and the longitudinal reinforcement beams 134. Secure the connection between the ends using a joining plate in the form.

한편, 상기와 같이 보강보(132,133,134,135)들로 구성되는 보강 지지틀(131) 위에는 트러스 데크(139)가 설치되며, 이 트러스 데크(139) 위에는 복공용 합판(141)이 깔리게 되는데, 결국 각 지지거더 사각틀(120) 위에 보강 지지틀(131), 트러스 데크(139), 복공용 합판(141)이 차례로 설치되어, 전체적으로는 각 지지거더 사각틀 단위별로 보강 지지틀(131), 트러스 데크(139), 복공용 합판(141)을 포함하여 구성되는 가설구조체(130)가 구성되고, 이 가설구조체(130)는 해당 층 시공시에 작업대로 활용하게 된다. On the other hand, the truss deck 139 is installed on the reinforcement support frame 131 composed of the reinforcement beams 132, 133, 134, 135 as described above, the plywood 141 for the perforation is laid on the truss deck 139, each end Reinforcement support frame 131, the truss deck 139, the plywood plywood 141 is installed in order on the support girder square frame 120, the overall support frame 131, truss deck (139) for each support girder square frame unit ), The temporary structure 130 is configured to include a plywood 141 for construction, the temporary structure 130 is utilized as a workbench at the time of construction of the floor.

상기 횡방향 보강보(133), 종방향 보강보(134), 경사방향 보강보(135)는 플랜지 상면의 높이가 모두 같은 높이가 되도록 하여 설치한 후, 그 위에 트러스 데크(139)를 직접 지지시킨다. The lateral reinforcement beams 133, the longitudinal reinforcement beams 134 and the inclined reinforcement beams 135 are installed so that the height of the flange upper surface is the same height, and directly supports the truss deck 139 thereon. Let's do it.

단, 테두리 보강보(132)의 경우, 트러스 데크(139)와의 사이에 각재(142)를 개재시켜, 이 각재(142)를 매개로 트러스 데크(139)를 지지시킨다.However, in the case of the edge reinforcement beam 132, the truss deck 139 is supported through the lumber 142 via the lumber 142 between the truss deck 139.

즉, 채널부재(143) 내에 각재(142)를 끼운 뒤 각재(142)를 채널부재(143)와 못(144a)으로 고정하고, 이와 같이 각재(142)가 고정된 채널부재(143)를 테두리 보강보(132)의 플랜지 상면에 용접하여 고정한다. That is, after inserting the horn 142 in the channel member 143, the horn 142 is fixed with the channel member 143 and the nail 144a, and thus the rim is fixed to the channel member 143 where the horn 142 is fixed. It is fixed by welding to the flange upper surface of the reinforcing beam 132.

이와 같이 테두리 보강보(132) 위에 채널부재(143)를 고정한 후에는 트러스 데크(139)와 각재(142)를 다시 못(144b)으로 고정하며, 이를 통해 결국 트러스 데크(139)가 각재(142)를 매개로 테두리 보강보(132)에 완전히 고정되도록 한다.After fixing the channel member 143 on the rim reinforcement beam 132 as described above, the truss deck 139 and the lumber 142 are fixed with nails 144b again, through which the truss deck 139 is the lumber 142. It is to be completely fixed to the edge reinforcement beam 132 through the).

상기와 같이 트러스 데크(139)가 고정된 상태에서 그 위에 복공용 합판(141)을 깐 후, 복공용 합판(141)과 트러스 데크(139)를 별도의 고정수단(141a)을 사용하여 완전히 고정시키며, 결국 지지거더 사각틀(120) 위에 보강 지지틀(131), 트러스 데크(139), 복공용 합판(141) 등으로 구성되는 가설구조체(130)가 일체로 고정되어 작업대로 쓰이게 된다.After the truss deck 139 is fixed as described above, after covering the plywood for rehabilitation thereon, the plywood 141 and truss deck 139 for rehabilitation are completely fixed using separate fixing means (141a). In the end, the temporary structure 130 composed of the reinforcement support frame 131, the truss deck 139, the plywood plywood 141, etc. is integrally fixed on the support girder square frame 120 to be used as a workbench.

상기 가설구조체(130), 즉 작업대 내의 트러스 데크(139)로는 최하층의 슬래브 구축을 위해 본 구조물로 사용되는 트러스 데크를 사용하는데, 이를 1층 및 그 이하 지하층의 시공시에는 가설구조체(130)에 포함시켜 사용하나, 최하층의 시공에는 그 내부에 직접 콘크리트를 타설 및 양생시켜 슬래브(S4)를 시공하는데 쓰이게 된다.As the truss deck 139 in the temporary structure 130, that is, the workbench, a truss deck used as the present structure is used for the construction of the slab of the lowermost floor. It is used to include, but the construction of the lowest floor is used to construct the slab (S4) by placing and curing concrete directly inside.

상기와 같이 각 기둥 상에 지지 브라켓(110)을 설치한 뒤 이 지지 브라켓(110)들을 이용하여 지지거더(121a,121b) 및 가설구조체(130)를 지지시킨 다음에는 1층 바닥 시공을 위한 보 및 슬래브 거푸집(150,153)을 설치한다.After the support brackets 110 are installed on each pillar as described above, the support girder 121a and 121b and the temporary structure 130 are supported using the support brackets 110, and then the beam for the first floor construction is performed. And install the slab formwork (150,153).

도 1 내지 도 5h는 플랫 슬래브(flat slab) 형태의 지하층 바닥 구조물을 구축하기 위한 거푸집 및 지지 시스템을 도시한 것으로, 플랫 슬래브 구조물에서는 주지된 바와 같이 각 H-형강 기둥과 슬래브 사이에 육면체 형태의 연결부, 즉 육면체 형태의 보가 하방 돌출되게 시공된다.1 to 5H illustrate formwork and support systems for building a basement floor structure in the form of a flat slab, in which a cube is placed between each H-beam column and slab, as is known in the flat slab structure. Connections, ie, hexahedral beams, are constructed to protrude downward.

1층 바닥 시공을 위한 보 및 슬래브 거푸집을 설치하는 과정을 설명하면, 상기와 같이 설치된 가설구조체(130) 위에 드롭 패널(151) 및 거푸집 받침(152)으로 이루어진 보 거푸집(150)을 설치하고, 이 거푸집 받침(152) 위로 슬래브 거푸집 구조체인 트러스 데크(153)를 지지시켜 설치한다. Referring to the process of installing the beam and slab formwork for the first floor construction, install the beam formwork 150 consisting of a drop panel 151 and the formwork 152 on the temporary structure 130 installed as described above, The truss deck 153, which is a slab formwork structure, is supported and installed on the formwork 152.

아울러, 트러스 데크(153)를 중간위치에서 지지할 수 있도록 이웃한 두 H-형강 기둥(2) 사이, 보다 명확히는 이웃한 H-형강 기둥(2)의 두 보 거푸집(150) 사이에도 가설구조체(130) 위로 적정 수의 거푸집 받침(152)을 설치한다(도시한 예에서는 1개만을 설치하고 있으나, 그 설치갯수는 적절히 변경 가능함).In addition, the temporary structure between the two neighboring H-beam pillars (2), more specifically between the two beam formwork 150 of the neighboring H-beam pillars (2) to support the truss deck (153) in an intermediate position 130, install the appropriate number of formwork 152 (only one is installed in the illustrated example, the number of installation can be changed appropriately).

상기와 같이 거푸집 작업을 마치고 나면, 보 거푸집(150) 및 트러스 데크(153)가 형성하는 보 및 슬래브 성형공간의 내측으로 보강철근을 설치하는 배근 작업을 한 후, 성형공간 내부에 콘크리트를 타설 및 양생하여 1층 바닥용 보(G1) 및 슬래브(S1)를 콘크리트 시공한다.After finishing the formwork as described above, after the reinforcement work to install the reinforcing bar to the inside of the beam and slab forming space formed by the beam formwork 150 and the truss deck 153, and placing concrete in the forming space and Curing and concrete construction of the first floor floor beam (G1) and slab (S1).

상기 거푸집 작업시에 보 거푸집(150)으로는 공지된 다양한 형태의 보 거푸집이 설치될 수 있으며, 보 거푸집이 도면으로 예시된 특정 형태로 한정되는 것은 아니다.The formwork 150 at the time of the formwork can be installed in various forms of known formwork, the formwork is not limited to the specific form illustrated in the drawings.

예를 들어, 플랫 슬래브 시공의 경우에는 가설구조체(130) 위에 각 H-형강 기둥(2)을 중심으로 육면체의 하방 돌출된 보를 성형할 수 있는 보 거푸집(드롭 패널 등 사용)을 설치하나, 2방향 보가 시공되는 경우(2-way wide girder system)에 는 두 H-형강 기둥 사이를 길게 연결하는 공지된 형태의 2방향 보 거푸집을 설치하게 된다.For example, in the case of flat slab construction, beam formwork (using a drop panel, etc.) can be formed on the temporary structure 130 to form beams protruding downward from a hexahedron around each H-beam column 2. In the case of directional beams (2-way wide girder system), a well-known two-way beam formwork is installed, which connects long between two H-beam columns.

상기와 같이 1층 바닥 시공이 완료된 후에는 지하 1층의 공사를 위하여 2차로 지반을 추가 굴착하고, 이후 각 지지 브라켓(110)을 분할 해체한 뒤 미리 정해놓은 지하 1층 설치 높이로 하강시켜 각 H-형강 기둥(2)에 고정 설치한다.After the ground floor construction is completed as described above, the ground is additionally excavated for the construction of the first floor underground, and then each support bracket 110 is divided and dismantled and then lowered to the predetermined first floor installation height. Fixed installation on H-beam column (2).

상기 지지 브라켓(110)을 하강시킬 때에는 하단이 지지거더(121a,121b)의 재킹 포인트에 연결된 현수재(6)를 이용하여 지지거더(121a,121b)를 가설구조체(130)와 함께 지지 브라켓 해체 전에 먼저 선시공된 1층 바닥에 지지시켜야 함은 물론이다.When the support bracket 110 is lowered, the support girder 121a and 121b are dismantled together with the temporary structure 130 by using the suspension material 6 connected to the jacking points of the support girders 121a and 121b. Of course, it must be supported on the first floor, which was previously constructed.

이때 상기 현수재(6)는 그 상단이 선시공된 1층 바닥 위에 배치된 현수하강장치(5)에 연결되어 지지거더(121a,121b) 및 가설구조체(130)를 지지하게 된다.In this case, the suspension material 6 is connected to the suspension lowering device 5 disposed on the floor of the first floor of which the top is pre-installed to support the support girders 121a and 121b and the temporary structure 130.

상기 현수재(6)는 지지 브라켓(110)이 분할 해체된 후 기둥(2)으로부터 분리된 상태에서 지지거더(121a,121b)와 가설구조체(130)를 임시로 지지하는 역할을 하고, 또한 지지거더(121a,121b)와 가설구조체(130)를 하층 높이에 재설치하기 위하여 현수 하강시키는데 이용된다.The suspension member 6 serves to temporarily support the support girders 121a and 121b and the temporary structure 130 in a state in which the support bracket 110 is divided and dismantled from the column 2. The girder (121a, 121b) and the temporary structure 130 is used to lower the suspension in order to reinstall the lower level.

이와 같이 각 지지 브라켓(110)의 하강 설치를 모두 완료한 후에는 지지거더(121a,121b) 및 가설구조체(130)를 현수재(6)를 이용해 하강시킨 뒤 1층 시공시와 동일하게 해당 지지 브라켓(110) 위에 지지시킨다.In this way, after completing the lower installation of each support bracket 110, the support girders (121a, 121b) and the temporary structure 130 is lowered using the suspension (6) and then the corresponding support as in the first floor construction Support on the bracket (110).

1층 바닥 시공시에 가설구조체(130) 위의 트러스 데크(153)는 슬래브 콘크리트와 일체화되어 1층 바닥 본 구조물을 구성하는 바, 이 트러스 데크(153)를 제외 하고 가설구조체(130) 및 지지거더(121a,121b)가 함께 현수 하강된다.The truss deck 153 on the temporary structure 130 during the construction of the first floor is integrated with the slab concrete to form the first floor floor structure, except for the truss deck 153 and the temporary structure 130 and the support. The girders 121a and 121b are suspended together.

하강시에는 지지거더(121a,121b)와 가설구조체(130)를 상호 조립된 상태로 현수 하강시키는데, 4개의 지지거더(121a,121b)들로 구성된 하나의 지지거더 사각틀(120) 및 그 위에 결합된 가설구조체(130)를 한 단위로 하여 각 단위별로 순차 하강시킨다.At the time of descending, the support girders 121a and 121b and the temporary structure 130 are suspended from each other in an assembled state, and one support girder square frame 120 composed of four support girders 121a and 121b is coupled thereto and The hypothesized structure 130 is descended for each unit sequentially.

물론, 상기 현수재(6)가 1층 바닥 슬래브 아래쪽에 위치된 지지거더(121a,121b)에 연결될 수 있도록, 바닥 슬래브(S1), 바닥 슬래브(S1)의 트러스 데크(153), 복공용 합판(141) 및 가설구조체(130)의 트러스 데크(139)에는 현수재(6)가 통과할 수 있는 통공(별도 도시하지 않음)을 시공하고, 이 통공을 통해 현수재(6)를 연결함이 마땅하다.Of course, the floor slab (S1), the truss deck 153 of the floor slab (S1), the plywood for plywood so that the suspension material 6 can be connected to the support girders (121a, 121b) located below the floor slab of the first floor. 141 and the truss deck 139 of the temporary structure 130, the through-hole (not shown) through which the suspension material 6 can pass, and connects the suspension material (6) through the through hole Right.

상기와 같이 지지 브라켓(110) 및 지지거더 사각틀(120), 가설구조체(130)를 지하 1층 설치 높이에 맞추어 모두 재설치한 후에는 지하 1층의 보(G2) 및 슬래브(S2)의 구축을 위하여 1층 시공시에 사용된 드롭 패널(151) 등의 보 거푸집(150)을 탈형시켜 가설구조체(130) 위에 재설치하고 거푸집 받침(152) 및 트러스 데크(153)를 설치하는 거푸집 작업을 실시한다.After re-installing the support bracket 110, the support girder square frame 120, and the temporary structure 130 in accordance with the installation height of the first basement level as described above, the construction of the beams G2 and the slab S2 of the first basement level is performed. In order to demolish the formwork 150, such as the drop panel 151 used during the construction of the first floor, reinstalled on the temporary structure 130, and performs the formwork to install the formwork 152 and the truss deck 153. .

상기 거푸집 작업을 마치고 나면, 보 및 슬래브 성형공간 내에 배근 작업을 하고, 이후 상기 성형공간 내에 콘크리트를 타설한다.After the formwork is finished, the reinforcement work in the beam and slab forming space, and then the concrete is poured into the forming space.

이와 같이 콘트리트 타설 후 양생 과정을 거쳐 지하 1층의 바닥 시공이 끝나면, 지하 2층의 바닥 시공을 위하여 지하 1층의 바닥 시공 과정을 반복한다.In this way, after the concrete is poured, after the curing of the ground floor on the first basement floor, the ground construction on the first floor is repeated for the second floor.

즉, 3차 지반 굴토 후 각 지지 브라켓(110)을 분할 해체하여 지하 2층 설치 높이로 하강 및 재설치하고, 이어 지지거더(121a,121b) 및 가설구조체(130)를 각 단위별로 하강시켜 지지 브라켓(110) 위에 지지시킨 뒤, 지지거더(121a,121b) 및 가설구조체(130)의 설치가 모두 끝나고 나면 거푸집 작업 및 배근 작업 후 성형공간 내에 콘크리트를 타설하여 지하 2층의 보(G3) 및 슬래브(S3)를 시공한다.That is, after the third ground excavation, each support bracket 110 is divided and dismantled and lowered and reinstalled to the basement level 2, and then the support girders 121a and 121b and the temporary structure 130 are lowered by each unit to support the bracket. After supporting on the (110), after the installation of the support girders (121a, 121b) and the temporary structure 130 is all finished, after placing the formwork and reinforcement work to cast concrete in the molding space beams (G3) and slabs of the second basement Construct (S3).

이와 같이 지하 2층의 바닥 시공이 완료되면, 지하 3층의 바닥 시공을 위하여 4차로 지반을 추가 굴토한 후, 지하 2층의 바닥 시공시와 동일하게 각 지지 브라켓(110)을 분할 해체하여 지하 3층 설치 높이로 하강 및 재설치한다.As described above, when the ground construction of the basement 2 floor is completed, the ground is additionally excavated in the fourth way for the ground construction of the basement 3 floor. Lower and reinstall to the third floor installation height.

이어 지지거더(121a,121b) 및 가설구조체(130) 역시 지하 2층의 바닥 시공시와 동일하게 하층으로 내려 지지 브라켓(110) 위에 지지시킨다.Subsequently, the support girders 121a and 121b and the temporary structure 130 are also supported on the support bracket 110 by being lowered to the lower floor in the same manner as when installing the basement 2 floors.

도 5a ~ 도 5h는 지하 4층의 건물을 시공하는 예를 도시하고 있으며, 지하 4층의 건물을 시공할 경우, 지하 3층의 바닥 시공은 지지 브라켓(110) 및 지지거더(121a,121b)를 이용하는 마지막 층(최하층)이 된다.5A to 5H illustrate an example of constructing a four-storey basement building, and in the case of constructing a four-storey basement building, the three-basement floor construction is performed by the support bracket 110 and the support girders 121a and 121b. Becomes the last layer (lowest layer).

이 경우, 지하 3층의 바닥 시공을 위해서는 가설구조체(130) 내에 포함된 트러스 데크(139)가 슬래브 구축용 거푸집으로 사용된다.In this case, the truss deck 139 included in the temporary structure 130 is used as the slab construction form for the floor construction of the basement 3 floors.

즉, 지지거더(121a,121b) 및 가설구조체(130)를 지하 3층 설치 높이에 맞추어 지지 브라켓(110) 위에 지지시킨 상태에서, 도 4에 도시한 바와 같이 가설구조체(130)의 복공용 합판(141)을 제거한 후, 그 하측의 트러스 데크(139)에서 보의 사각 영역에 해당하는 부분을 절단 제거한다.That is, in the state in which the support girders 121a and 121b and the temporary structure 130 are supported on the support bracket 110 in accordance with the installation level of the 3rd basement underground, the plywood for rehabilitation of the temporary structure 130 as shown in FIG. 4. After removing 141, the portion corresponding to the rectangular area of the beam is cut off and removed from the truss deck 139 below.

이어 지지거더(121a,121b) 위의 측방 테두리 보강보(132b)를 해체하여 제거한 뒤, 트러스 데크(139) 일부 및 측방 테두리 보강보(132b)가 제거된 H-형강 기둥 주변 공간에 드롭 패널(151) 등 보 거푸집(150)을 설치하고, 이후 트러스 데크(139) 및 보 거푸집(150)이 형성하는 성형공간 내에 보강철근 등을 설치하는 배근 작업을 한다.Next, after dismantling and removing the side rim reinforcement beams 132b on the support girders 121a and 121b, a drop panel (a part of the truss deck 139 and the side rim reinforcement beams 132b) is removed. 151) and the beam formwork 150 is installed, and then the reinforcement work for installing the reinforcing bars in the forming space formed by the truss deck (139) and the formwork 150.

이와 같이 최하층 시공시에 가설구조체(130) 내의 중앙 테두리 보강보(132a)는 본 구조물로 사용되는 트러스 데크(139)를 지지하지만, 양 측방의 테두리 보강보(132b)는 볼트 및 너트를 풀어 지지거더(121a,121b)로부터 해체시키게 된다.As described above, the bottom edge reinforcement beam 132a in the temporary structure 130 supports the truss deck 139 used as the present structure, but the edge reinforcement beams 132b on both sides are loosened bolts and nuts. It is disassembled from the girders 121a and 121b.

이와 같이 거푸집 작업 및 배근 작업이 완료되면 성형공간 내에 콘크리트를 타설하여 보(G4) 및 슬래브(S4)를 시공한다.When the formwork and reinforcement work is completed as described above, the concrete is poured into the molding space to construct the beams G4 and the slab S4.

이와 같이 지하 3층의 바닥 시공이 완료되면, 지하 4층 공간을 형성하기 위하여 최종 굴착 작업 후 기초 및 바닥을 시공하고, 이어 지하 3층의 바닥 시공시에 사용된 지지 브라켓(110), 지지거더(121a,121b), 보강보(132a,133,134,135) 및 보 거푸집(150) 등은 해체하여 외부 반출한다.When the floor construction of the basement 3 floors is completed as described above, the foundation and the floor are constructed after the final excavation work to form the space of the basement 4 floors, and then the support bracket 110 and the support girder used for the floor construction of the basement 3 floors. 121a, 121b, reinforcing beams 132a, 133, 134, 135, and the formwork 150 are dismantled and taken out outside.

상기와 같이 전 지하층의 보 및 슬래브 시공 과정을 모두 완료한 후에는 기초에서부터 미시공된 기둥 및 벽체 등의 수직재와 램프, 계단 등의 부위를 공사하여 지하공사를 완료하며, 지하층의 공사가 완료되기 전에 지상층을 동시에 공사할 수도 있다. After completing all the construction process of the beam and slab of the basement floor as above, the construction of the vertical materials such as pillars and walls, and the construction of lamps and stairs from the foundation is completed, and the underground construction is completed. The ground floor may be constructed at the same time before.

한편, 도 7은 본 발명에서 이용되는 브라켓 지지 타입 가설구조체(작업대)의 제2실시예가 설치된 평면도이고, 도 8a와 도 8b는 도 7에 도시한 가설구조체의 제2실시예의 단면도로서, 도 8a는 도 7의 선 'C-C' 방향에서 취한 단면도이고, 도 8b는 도 7의 선 'D-D' 방향에서 취한 단면도이다.7 is a plan view in which a second embodiment of a bracket support type temporary structure (working table) used in the present invention is installed, and FIGS. 8A and 8B are cross-sectional views of a second embodiment of the temporary structure shown in FIG. 7 is a cross-sectional view taken in the line 'CC' direction of FIG. 7, and FIG. 8B is a cross-sectional view taken in the line 'DD' direction of FIG. 7.

도 9는 도 7에 도시한 가설구조체의 제2실시예를 사용하는 경우에서 지지거더 및 보강보 위에 딥 데크가 고정된 상태를 도시한 확대단면도이다.FIG. 9 is an enlarged cross-sectional view illustrating a state in which a deep deck is fixed on a support girder and a reinforcement beam in the case of using the second embodiment of the temporary structure shown in FIG. 7.

도 10은 도 7에 도시한 가설구조체의 제2실시예를 사용하는 경우에서 1층 및 지하층의 보 및 슬래브 구축 시스템을 도시한 단면도이고, 도 11은 도 7에 도시한 가설구조체의 제2실시예를 사용하는 경우에서 최하층의 보 및 슬래브 구축 시스템을 도시한 단면도이다.FIG. 10 is a cross-sectional view illustrating a beam and slab construction system for the first floor and the basement floor when the second embodiment of the temporary structure shown in FIG. 7 is used, and FIG. 11 is a second embodiment of the temporary structure shown in FIG. In the case of using the example, it is sectional drawing which shows the lowermost beam and slab construction system.

도 7 내지 도 11에서는 슬래브 거푸집 구조체로서 딥 데크(deep deck)를 사용하는 경우에 대한 역타설 공법의 예가 도시되어 있으며, 1층 및 그 이하 지하층의 시공시에는 최하층의 본 구조물로 사용되는 딥 데크가 포함된 가설구조체를 지지 브라켓에 지지시켜 설치한 후 작업대로 활용하고, 최하층의 시공시에는 가설구조체에 포함된 상기 딥 데크를 슬래브 구축을 위한 본 구조물로 사용하는 것에 특징이 있는 것이다.7 to 11 show an example of a reverse casting method for the case of using a deep deck as a slab formwork, and the deep deck used as the main structure of the lowermost layer when constructing the first and lower basement floors. It is characterized by using a temporary structure including a supporting structure installed on the support bracket and then using the workbench, and when using the deep deck included in the temporary structure as the main structure for the slab construction.

상기 딥 데크는 예시한 바의 플랫 슬래브 시공뿐만이 아니라 1방향 보 및 슬래브(wide girder system)의 건물 시공을 위하여 널리 사용되는 슬래브 거푸집 구조체이다. The deep deck is a slab formwork structure widely used for the construction of unidirectional beams and slabs (wide girder system) as well as flat slab construction of the bar as illustrated.

도 7 내지 도 11에 도시된 가설구조체의 제2실시예는 딥 데크의 사용을 고려하여 변경 구성한 것으로, 도 1 내지 도 4에 도시된 제1실시예의 가설구조체와는 약간의 차이가 있다. The second embodiment of the temporary structure shown in FIGS. 7 to 11 is modified in consideration of the use of the deep deck, and is slightly different from the temporary structure of the first embodiment shown in FIGS. 1 to 4.

다만, 트러스 데크를 사용한 공법과 비교할 때, 딥 데크를 사용한 공법은 각 층의 보 및 슬래브 시공시에 작업대로 활용되는 가설구조체에만 차이가 있을 뿐, 전체적인 시공 과정은 동일하며, 따라서 시공 순서는 도 5a ~ 도 5h의 공정도를 참조하여 설명하기로 한다. However, compared with the truss deck method, the deep deck method differs only in the temporary structure used in the workbench for beam and slab construction of each floor, and the overall construction process is the same. It will be described with reference to the process diagram of 5a to 5h.

시공 과정을 설명하면, 흙막이벽 시공, H-형강 기둥 시공, 1차 굴토, 지지 브라켓 설치, 지지거더 설치 등은 앞서 설명한 제1실시예의 가설구조체를 사용할 경우와 동일하다.Referring to the construction process, the construction of the wall, H-beam column construction, primary pit, support bracket installation, support girder installation and the like is the same as the case of using the temporary structure of the first embodiment described above.

예를 들어, 지지거더(121a,121b)가 각 H-형강 기둥(2)을 중심으로 사방 2줄씩 배치되어 설치되고, 4개의 지지 브라켓(110)에 4각형 형태로 배치되는 4개의 지지거더(121a,121b)들은 단부가 접합 플레이트(122)로 연결 조립되어 일체화된다.For example, the support girders (121a, 121b) are installed in two rows on each side of each of the H-shaped steel pillars (2), four support girders arranged in a quadrilateral form on the four support brackets 110 ( 121a and 121b are integrated by connecting the ends to the bonding plate 122.

즉, 횡방향 배치된 지지거더(121b) 2개의 각 단부에 각각 접합 플레이트(122)가 용접 설치되고, 각 접합 플레이트(122)에 종방향 배치된 지지거더(121a)의 단부가 볼트로 체결되어, 단부간에 연결된 4개의 지지거더(121a,121b)들이 전체적으로 사각틀 형태를 이루어 일체화된다.That is, the joining plates 122 are welded to each of the two end portions of the supporting girders 121b arranged in the transverse direction, and the ends of the supporting girders 121a arranged in the longitudinal joining plates 122 are fastened with bolts. Four support girders 121a and 121b connected between the ends are integrated into a rectangular frame as a whole.

상층 시공 후 하층 시공을 위하여 하강시킬 때에는 단부간에 연결 고정되어 사각틀을 이루고 있는 4개의 지지거더(121a,121b)들을 하나의 단위로 하여 하강시키게 된다.When descending for lower construction after the upper construction, the four support girders (121a, 121b) connected to be fixed between the ends forming a rectangular frame is lowered as a unit.

한편, 작업대로 활용되는 가설구조체(130)는, 상기와 같이 4개의 지지거더(121a,121b)로 구성되는 지지거더 사각틀(120)을 한 단위로 하여, 각 단위별로 구성되는데, 사각틀(120)을 구성하는 4개의 지지거더(121a,121b)에 H-형강으로 된 복수개의 보강보(133,134,146)들을 설치하여 가설지지틀(140)을 구성하고 이와 같이 지지거더(121a,121b) 및 보강보(133,134,146)로 이루어진 가설지지틀(140) 위로 각 재(142)를 댄 뒤 그 위로 다시 딥 데크(145) 및 복공용 합판(141)을 차례로 조립하여 구성되며, 각 지지거더 사각틀(120)마다 동일하게 구성된다.On the other hand, the temporary structure 130 utilized as a workbench is configured by each unit by using the support girder square frame 120 composed of four support girders 121a and 121b as one unit, the rectangular frame 120 By installing a plurality of reinforcing beams 133, 134, 146 made of H-shaped steel in the four support girders (121a, 121b) constituting the temporary support frame 140 and thus support girders (121a, 121b) and reinforcing beams ( 133, 134, 146, each of the ashes 142 on the temporary support frame 140 composed of a combination of the deep deck 145 and the plywood 141 for the back and then sequentially configured, each support girder square frame 120 is the same Is configured.

하나의 지지거더 사각틀(120) 위에 설치되는 가설구조체(130)의 구성에 대해서 구체적으로 설명하면 다음과 같다.The configuration of the temporary structure 130 installed on one support girder rectangular frame 120 will be described in detail as follows.

우선, 사각형의 지지거더 사각틀(120)에서 지지거더(121a,121b)가 형성하는 사각공간 내에 보강보(133,134,146)들을 적절히 배치하여 고정설치한다.First, the reinforcement beams 133, 134, and 146 are appropriately disposed and fixed in the rectangular space formed by the support girders 121a and 121b in the rectangular support girder square frame 120.

예컨대, 도 7에 도시한 바와 같이, 각 지지거더 사각틀(120)에서 양쪽 종방향의 두 지지거더(121a) 사이에 접합 플레이트(미도시됨)를 매개로 횡방향으로 길게 연결되는 횡방향 보강보(133)를 설치하고, 이 횡방향 보강보(133)와 양쪽 횡방향 두 지지거더(121b) 사이에 역시 접합 플레이트(미도시됨)를 매개로 종방향으로 길게 연결되는 종방향 보강보(134)를 설치한다.For example, as shown in Figure 7, in each support girder square frame 120 between the two longitudinal support girders (121a) in both longitudinal directions, the transverse reinforcement beam is connected in the longitudinal direction through a bonding plate (not shown) A longitudinal reinforcement beam 134 which is installed and is connected in the longitudinal direction between the transverse reinforcement beams 133 and the two transverse support girders 121b in the longitudinal direction also through a bonding plate (not shown). Install).

또한, 종방향 보강보(134)와 양쪽 종방향 두 지지거더(121a) 사이에도 접합 플레이트(미도시됨)를 매개로 횡방향으로 길게 연결되는 횡방향 보강보(146)들을 추가로 설치한다.In addition, between the longitudinal reinforcing beams 134 and the two longitudinal support girders 121a, transverse reinforcing beams 146 that are connected in the transverse direction through the bonding plate (not shown) are further installed.

상기 보강보(133,134,146)들은 모두 H-형강을 적정 크기로 절단하여 사용한다. The reinforcing beams 133, 134, 146 are all used to cut the H-shaped steel to the appropriate size.

이하, 본 명세서에서는 명확한 설명을 위하여 4개의 지지거더(121a,121b)가 구성하는 사각틀(120)을 지지거더 사각틀로 칭하며, 이 지지거더 사각틀(120) 및 이에 일체로 조립된 보강보(133,134,146)들을 함께 묶어 가설지지틀(140)로 칭하기로 한다.Hereinafter, in the present specification, for the sake of clarity, the rectangular frame 120 formed by the four support girders 121a and 121b is referred to as a support girder square frame, and the support girder square frame 120 and the reinforcing beams 133, 134, and 146 integrally assembled thereto are provided. They will be referred to as a temporary supporting frame 140 together.

상기 가설지지틀(140)을 구성하는 지지거더(121a,121b)와 보강보(133,134,146)들은 단부간에 접합 플레이트를 사용하여 서로 결합되는데, 종방향 지지거더(121a)와 횡방향 지지거더(121b)의 단부간을 연결하는 접합 플레이트가 도 9에서 도면부호 122로 도시되고 있으며, 이와 유사하게 지지거더(121a,121b)와 보강보(133,134,146)간 접합 플레이트가 사용되므로 이는 별도 도면으로 나타내지는 않았다. The support girders 121a and 121b and the reinforcing beams 133, 134 and 146 constituting the temporary support frame 140 are coupled to each other by using a joining plate between the ends, the longitudinal support girders 121a and the transverse support girders 121b. The joint plate connecting the ends of the is shown by reference numeral 122 in Figure 9, and similarly because the junction plate between the support girders (121a, 121b) and the reinforcing beams (133, 134, 146) is used, which is not shown in the separate drawing.

한편, 상기 가설지지틀(140)을 구성하는 지지거더(121a,121b)와 보강보(133,134,146)들은 플랜지 상면의 높이가 모두 같은 높이가 되도록 하여 조립되며, 지지거더(121a,121b)와 보강보(133,134,146) 위에 각재(142)를 댄 후 이 각재(142) 위에 딥 데크(145)를 지지시킨다.On the other hand, the support girders (121a, 121b) and reinforcing beams (133, 134, 146) constituting the temporary support frame 140 are assembled so that the height of the upper surface of the flange all the same height, the support girders (121a, 121b) and reinforcement beams The horns 142 are mounted on the 133, 134, and 146 to support the deep deck 145 on the horns 142.

즉, 도 9에 도시한 바와 같이 채널부재(143) 내에 각재(142)를 끼운 뒤 각재(142)를 채널부재(143)와 못(144a)으로 고정하고, 이와 같이 각재(142)가 고정된 채널부재(143)를 보강보(133,134,146)의 플랜지 상면에 용접하여 고정한다. That is, as shown in FIG. 9, after inserting the horn 142 into the channel member 143, the horn 142 is fixed with the channel member 143 and the nail 144a, and thus the horn 142 is fixed. The channel member 143 is fixed to the upper surface of the flange of the reinforcing beams 133, 134, and 146 by welding.

상기와 같이 채널부재(143)를 고정한 후에는 딥 데크(145)와 각재(142)를 다시 못(144b)으로 고정하여, 결국 딥 데크(145)가 각재(142)를 매개로 가설지지틀(140)에 완전히 고정되도록 한다.After fixing the channel member 143 as described above, the deep deck 145 and the lumber 142 are fixed with the nail 144b again, so that the deep deck 145 is temporarily supported by the lumber 142. 140) to be fully secured.

여기서, 지지거더(121a,121b)와 딥 데크(145) 사이에는, 후술하는 바와 같이 최하층 시공시에 각재(142)가 쉽게 제거되어야 하므로, 채널부재를 사용하지 않고 각재(142)만을 개재시킨 후 각재(142)와 딥 데크(145) 사이를 못(144b)으로 고정시킨다(도 9 참조).Here, between the support girders (121a, 121b) and the deep deck (145), as described later, when the bottom layer construction must be easily removed, after interposing only the angular member 142 without using a channel member The nail 144b is fixed between the lumber 142 and the deep deck 145 (see FIG. 9).

상기와 같이 딥 데크(145)가 고정된 상태에서 그 위에 복공용 합판(141)을 깔게 된다.As described above, in the state where the deep deck 145 is fixed, the plywood 141 for rehabilitation is laid thereon.

이와 같이 가설구조체(130)는, 지지거더(121a,121b) 및 보강보(133,134,146)로 이루어지고 기둥(2) 상에 브라켓 지지되는 가설지지틀(140)과, 이 가설지지틀(140) 위로 설치되는 딥 데크(145)와, 이 딥 데크(145) 위로 설치되는 복공용 합판(141)을 포함하여 구성되며, 각 층의 시공 동안 작업대로 활용할 수 있게 된다. Thus, the temporary structure 130 is composed of a support girders (121a, 121b) and reinforcing beams (133, 134, 146) and the temporary support frame 140, which is bracket-supported on the pillar (2), and the temporary support frame 140 above It is configured to include a deep deck 145 is installed, and a multi-hole plywood 141 is installed above the deep deck 145, it is possible to utilize the workbench during the construction of each floor.

상기 가설구조체(130), 즉 작업대 내의 딥 데크(145)는 최하층 슬래브 구축시에 본 구조물 거푸집으로 사용되는 딥 데크를 사용하는데, 이를 1층 및 그 이하 지하층 시공시에는 가설구조체(130)에 포함시켜 사용하나, 최하층 시공시에는 그 내부에 직접 콘크리트를 타설 및 양생시켜 슬래브를 시공하는데 쓰이게 된다.The temporary structure 130, that is, the deep deck 145 in the workbench uses a deep deck used as the present formwork when constructing the lowermost slab, which is included in the temporary structure 130 during the construction of the first and lower basement floors. In the case of the lowest floor construction, it is used to construct slabs by placing and curing concrete directly inside.

상기와 같이 각 기둥(2) 상에 지지 브라켓(110)을 사용하여 가설구조체(130)를 지지시킨 다음에는 1층 바닥 시공을 위한 보 및 슬래브 거푸집(150,7)을 설치한다.After supporting the temporary structure 130 by using the support bracket 110 on each pillar 2 as described above, the beam and slab formwork (150, 7) for the first floor installation is installed.

1층 바닥 시공을 위한 보 및 슬래브 거푸집(150,7)을 설치하는 과정을 설명하면, 상기와 같이 설치된 가설구조체(130) 위에 드롭 패널(151) 및 거푸집 받침(152)으로 이루어진 보 거푸집(150)을 우선 설치하고, 거푸집 받침(152) 위로 슬래브 거푸집 구조체인 딥 데크(7)를 지지시켜 설치한다.Referring to the process of installing the beam and slab formwork (150, 7) for the construction of the first floor, beam formwork 150 consisting of a drop panel 151 and formwork 152 on the temporary structure 130 installed as described above ) Is installed first, and is installed by supporting the deep deck (7) of the slab formwork structure on the formwork 152.

또한, 상기 딥 데크(7)를 중간위치에서 지지할 수 있도록 이웃한 두 H-형강 기둥(2) 사이, 보다 명확히는 이웃한 H-형강 기둥(2)의 두 보 거푸집(150) 사이에도 가설구조체(130) 위로 적정 수의 거푸집 받침(152)을 설치한다(도시한 예에서는 1개만을 설치하고 있으나, 그 설치갯수는 적절히 변경 가능함).It is also hypothesized between two neighboring H-beam pillars 2, more specifically between two beam formwork 150 of neighboring H-beam pillars 2, to support the deep deck 7 in an intermediate position. An appropriate number of formwork 152 is installed on the structure 130 (only one is installed in the illustrated example, but the number of installation can be changed as appropriate).

상기와 같이 거푸집 작업을 마치고 나면, 보 거푸집(150) 및 딥 데크(7)가 형성하는 보 및 슬래브 성형공간의 내측으로 보강철근을 설치하는 배근 작업을 한 후, 성형공간 내부에 콘크리트를 타설 및 양생하여 1층 바닥용 보(G1) 및 슬래브(S1)를 콘크리트 시공한다.After finishing the formwork as described above, after the reinforcement work to install the reinforcing bar into the inside of the beam and slab forming space formed by the beam formwork 150 and the deep deck (7), and then placing concrete in the forming space and Curing and concrete construction of the first floor floor beam (G1) and slab (S1).

상기 거푸집 작업시에 보 거푸집(150)으로는 공지된 다양한 형태의 보 거푸집이 설치될 수 있으며, 보 거푸집이 도면으로 예시된 특정 형태로 한정되는 것은 아니다.The formwork 150 at the time of the formwork can be installed in various forms of known formwork, the formwork is not limited to the specific form illustrated in the drawings.

예를 들어, 플랫 슬래브 시공의 경우에는 가설구조체(130) 위에 각 H-형강 기둥(2)을 중심으로 육면체의 하방 돌출된 보를 성형할 수 있는 보 거푸집(드롭 패널 등 사용)을 설치하나, 1방향 보가 시공되는 경우(1-way wide girder system)에는 두 H-형강 기둥(2) 사이를 길게 연결하는 공지된 형태의 1방향 보 거푸집을 설치하게 된다.For example, in the case of flat slab construction, a beam formwork (using a drop panel, etc.) may be installed on the temporary structure 130 to form beams protruding downward from a hexahedron around each H-beam column 2. In the case of a directional beam construction (1-way wide girder system), a one-way beam formwork of a known type that connects long between two H-beam columns 2 is installed.

상기와 같이 1층 바닥 시공이 완료된 후에는 지하 1층의 공사를 위하여 2차로 지반을 추가 굴착하고, 이후 각 지지 브라켓(110)을 분할 해체한 뒤 미리 정해놓은 지하 1층 설치 높이로 하강시켜 각 H-형강 기둥(2)에 고정 설치한다.After the ground floor construction is completed as described above, the ground is additionally excavated for the construction of the first floor underground, and then each support bracket 110 is divided and dismantled and then lowered to the predetermined first floor installation height. Fixed installation on H-beam column (2).

상기 각 지지 브라켓(110)의 하강 설치를 모두 완료한 후에는 지지거더(121a,121b), 보강보(133,134,146), 딥 데크(145) 등을 포함하는 가설구조체(130)를 현수재(6)를 이용해 하강시킨 뒤 1층 시공시와 동일하게 해당 지지 브라켓(110) 위에 지지시킨다.After completing the lowering installation of each of the support brackets 110, the temporary structure 130 including support girders 121a and 121b, reinforcing beams 133, 134, 146, and deep deck 145, etc., is suspended. After descending using the support on the support bracket 110 in the same manner as the first floor construction.

상기 현수재(7)의 이용시에, 현수재(7)가 1층 바닥 슬래브(S1) 아래쪽에 위치된 지지거더(121a,121b)에 연결될 수 있도록, 바닥 슬래브(S1), 바닥 슬래브(S1)의 딥 데크(7), 복공용 합판(141) 및 가설구조체(130)의 딥 데크(145)에는 현수재(6)가 통과할 수 있는 통공(별도 도시하지 않음)을 시공하고, 이 통공을 통해 현수재(6)를 연결함이 마땅하다.At the time of use of the suspension material 7, the floor slab S1 and the floor slab S1 can be connected to the support girders 121a and 121b located below the first floor slab S1. In the deep deck 7, the plywood 141 for the hole and the deep deck 145 of the temporary structure 130, the through hole (not shown) through which the suspension material 6 can pass, and the through It is appropriate to connect the suspension (6) through.

상기와 같이 지지 브라켓(110) 및 가설구조체(130)를 지하 1층 설치 높이에 맞추어 모두 재설치한 후에는 지하 2층의 보(G2) 및 슬래브(S2)의 구축을 위하여 1층 시공시에 사용된 드롭 패널(151) 등의 보 거푸집(150)을 탈형시켜 가설구조체(130) 위에 재설치하고 거푸집 받침(152) 및 딥 데크(7)를 설치하는 거푸집 작업을 실시한다.After re-installing the support bracket 110 and the temporary structure 130 in accordance with the installation height of the first basement floor as described above, it is used during the construction of the first floor for the construction of the beam G2 and the slab S2 of the basement 2 floor. The formwork 150, such as the drop panel 151, is demolded and reinstalled on the temporary structure 130, and the formwork 152 and the deep deck 7 are installed.

상기 거푸집 작업을 마치고 나면, 보 및 슬래브 성형공간 내에 배근 작업을 하고, 이후 상기 성형공간 내에 콘크리트를 타설한다.After the formwork is finished, the reinforcement work in the beam and slab forming space, and then the concrete is poured into the forming space.

이와 같이 콘트리트 타설 후 양생 과정을 거쳐 지하 1층의 바닥 시공이 끝나면, 지하 2층의 바닥 시공을 위하여 지하 1층의 바닥 시공 과정을 반복한다.In this way, after the concrete is poured, after the curing of the ground floor on the first basement floor, the ground construction on the first floor is repeated for the second floor.

이후 지하 3층의 바닥 시공을 위하여 4차로 지반을 추가 굴토한 후, 지하 2층의 바닥 시공시와 동일하게 각 지지 브라켓(110)을 분할 해체하여 지하 3층 설치 높이로 하강 및 재설치한다.Thereafter, the ground is additionally excavated in the fourth order for the floor construction of the third basement, and then divided and dismantled each support bracket 110 in the same way as the construction of the basement of the second floor.

이어 가설구조체(130) 역시 지하 2층의 바닥 시공시와 동일하게 하층으로 내려 지지 브라켓(110) 위에 지지시킨다.Subsequently, the temporary structure 130 is also supported on the support bracket 110 by lowering to the lower floor as in the case of the floor construction of the basement 2 floor.

지하 3층의 바닥 시공을 위해서는 가설구조체(130) 내에 포함된 딥 데크 (145)가 슬래브 구축용 거푸집으로 사용된다.For the construction of the basement 3 floors, the deep deck 145 included in the temporary structure 130 is used as a slab construction formwork.

즉, 지지거더(121a,121b) 및 가설구조체(130)를 지하 3층 설치 높이에 맞추어 지지 브라켓(110) 위에 지지시킨 상태에서, 도 11에 도시한 바와 같이 가설구조체(130)의 복공용 합판(141)을 제거한 후, 그 하측의 딥 데크(145)에서 보의 사각 영역에 해당하는 부분을 절단 제거한다.That is, in the state in which the support girders 121a and 121b and the temporary structure 130 are supported on the support bracket 110 according to the installation height of the basement 3 floors, as shown in FIG. 11, the plywood for rehabilitation of the temporary structure 130 is shown. After removing 141, the portion of the lower deck deck 145 corresponding to the rectangular area of the beam is cut off.

이와 같이 딥 데크(145) 일부를 절단 제거하면 지지거더(121a,121b) 위 각재(142)도 함께 제거되며, 이후 딥 데크(145) 일부가 제거된 H-형강 기둥(2) 주변 공간에 드롭 패널(151) 등 보 거푸집(150)을 설치하고, 이후 딥 데크(145) 및 보 거푸집(150)이 형성하는 성형공간 내에 보강철근 등을 설치하는 배근 작업을 한다.When the part of the deep deck 145 is cut and removed as described above, the lumber 142 on the support girders 121a and 121b is also removed, and then a portion of the deep deck 145 is dropped into the space around the H-beam column 2 from which the part of the deep deck 145 is removed. The panel 151, such as the beam formwork 150 is installed, and then the reinforcement work for installing the reinforcing bar, etc. in the forming space formed by the deep deck 145 and the formwork 150.

이와 같이 거푸집 작업 및 배근 작업이 완료되면 성형공간 내에 콘크리트를 타설하여 보(G4) 및 슬래브(S4)를 시공한다.When the formwork and reinforcement work is completed as described above, the concrete is poured into the molding space to construct the beams G4 and the slab S4.

이와 같이 지하 3층의 바닥 시공이 완료되면, 지하 4층 공간을 형성하기 위하여 최종 굴착 작업 후 기초 및 바닥을 시공하고, 이어 지하 3층의 바닥 시공시에 사용된 지지 브라켓(110), 지지거더(121a,121b), 보강보(133,134,146) 및 보 거푸집(150) 등은 해체하여 외부 반출한다.When the floor construction of the basement 3 floors is completed as described above, the foundation and the floor are constructed after the final excavation work to form the space of the basement 4 floors, and then the support bracket 110 and the support girder used for the floor construction of the basement 3 floors. 121a, 121b, reinforcing beams 133, 134, 146, and the formwork 150 are dismantled and taken out.

상기와 같이 전 지하층의 보 및 슬래브 시공 과정을 모두 완료한 후에는 기초에서부터 미시공된 기둥 및 벽체 등의 수직재와 램프, 계단 등의 부위를 공사하여 지하공사를 완료하며, 지하층의 공사가 완료되기 전에 지상층을 동시에 공사할 수도 있다. After completing all the construction process of the beam and slab of the basement floor as above, the construction of the vertical materials such as pillars and walls, and the construction of lamps and stairs from the foundation is completed, and the underground construction is completed. The ground floor may be constructed at the same time before.

한편, 첨부한 도 12는 본 발명에서 이용되는 브라켓 지지 타입 가설구조체( 작업대)의 제3실시예가 설치된 평면도이고, 도 13a와 도 13b는 도 12에 도시한 가설구조체의 제3실시예의 단면도로서, 도 13a는 도 12의 선 'E-E' 방향에서 취한 단면도이고, 도 13b는 도 12의 선 'F-F' 방향에서 취한 단면도이다.12 is a plan view in which a third embodiment of the bracket supporting type temporary structure (working table) used in the present invention is installed, and FIGS. 13A and 13B are cross-sectional views of a third embodiment of the temporary structure shown in FIG. 12. FIG. 13A is a cross-sectional view taken along the line 'EE' of FIG. 12, and FIG. 13B is a cross-sectional view taken along the line 'FF' of FIG. 12.

도 14는 도 12에 도시한 가설구조체(작업대)의 제3실시예를 사용하는 경우에서 지하층의 보 및 슬래브 구축 시스템을 도시한 단면도이고, 도 15a ~ 도 15h는 도 12에 도시한 가설구조체의 제3실시예를 작업대로 활용할 수 있는 지하층의 보 및 슬래브 역타 시공 과정을 도시한 전체 공정도이다.14 is a cross-sectional view showing a beam and slab construction system of the basement floor in the case of using the third embodiment of the temporary structure (workbench) shown in Figure 12, Figures 15a to 15h is a view of the temporary structure shown in FIG. It is a whole process chart showing the process of construction of the beam and slab reverse erection of the basement floor can be used as a workbench of the third embodiment.

도 12 내지 도 15에서는 데크 플레이트가 아닌 일반 합판 거푸집을 사용하는 경우에 대한 역타설 공법의 예가 도시되어 있으며, 각 층의 시공시에 지지거더(121a,121b) 및 보강보(133,134,146), 받침보(147), 합판 거푸집(149) 등으로 구성된 가설구조체(130)를 지지 브라켓(110)에 지지시켜 설치한 후 작업대로 활용하는 것에 특징이 있는 것이다.12 to 15 show an example of the reverse casting method for the case of using a general plywood formwork instead of the deck plate, the support girders (121a, 121b) and reinforcement beams (133, 134, 146), support beams for the construction of each floor 147, the temporary structure 130 composed of plywood formwork 149 and the like is supported by the support bracket 110, and then installed to utilize the workbench.

제3실시예의 가설구조체(130)를 설치하는 역타설 공법은, 기둥(2) 상에 고정된 지지 브라켓(110)에 가설구조체(130)를 지지시켜 설치한 뒤 상층 보 및 슬래브의 시공을 완료하고, 이후 지지 브라켓(110) 및 가설구조체(130)를 하강시켜 재설치한 뒤 하층 보 및 슬래브의 시공을 완료하는 과정들을 하층으로 내려가면서 반복 실시하여 전체 지하층의 보 및 슬래브를 시공한다는 점에서 앞서 설명한 예들과 비교할 때 전체적인 시공 과정은 유사하다.In the reverse casting method for installing the temporary structure 130 of the third embodiment, the temporary structure 130 is supported by the support bracket 110 fixed on the pillar 2 and installed, and then the construction of the upper beam and the slab is completed. Then, after descending and re-installing the support bracket 110 and the temporary structure 130, the process of completing the construction of the lower beam and the slab is repeatedly carried out while descending to the lower floor to construct the beams and slabs of the entire basement floor. Compared with the examples described, the overall construction process is similar.

다만, 각 층의 보 및 슬래브를 구축하기 위한 합판 거푸집(149)을 가설구조체(130) 내에 포함시켜 작업대로 활용한다는 점에 차이가 있으며, 합판 거푸집 (149)을 지지하는 가설지지틀(140)의 구성에도 약간의 차이가 있다.However, there is a difference in that the plywood formwork 149 for constructing beams and slabs of each layer is included in the temporary structure 130 and used as a work bench, and the temporary support frame 140 supporting the plywood formwork 149 is used. There is also a slight difference in the configuration.

이하, 제3실시예의 가설구조체에 대하여 좀더 구체적으로 설명하면 다음과 같다.Hereinafter, the temporary structure of the third embodiment will be described in more detail.

지지 브라켓(110)과 지지거더(121a,121b)의 설치는 앞서 설명한 예들과 동일하다.Installation of the support bracket 110 and the support girders 121a and 121b is the same as the above-described examples.

그리고, 4개의 지지거더(121a,121b)가 4각형 형태로 결합된 각 지지거더 사각틀(120)에서, 양쪽 횡방향의 두 지지거더(121a) 사이에 접합 플레이트(미도시됨)를 매개로 종방향으로 길게 연결되는 종방향 보강보(133)를 설치하고, 종방향 보강보(133)와 양쪽 종방향 두 지지거더(121b) 사이에 역시 접합 플레이트(미도시됨)를 매개로 횡방향으로 길게 연결되는 횡횡향 보강보(134)를 설치한다.In addition, in each support girder square frame 120 in which four support girders 121a and 121b are coupled in a quadrangular shape, the support girders 121a and 121b are connected between two support girders 121a in both transverse directions through a bonding plate (not shown). The longitudinal reinforcing beams 133 connected in the longitudinal direction, and the longitudinal reinforcing beams 133 and the two longitudinal longitudinal support girders 121b are also extended in the transverse direction via a joining plate (not shown). Install the transverse reinforcing beams 134 connected.

또한, 횡방향 보강보(134)와 양쪽 횡방향 두 지지거더(121a) 사이에도 접합 플레이트(미도시됨)를 매개로 종방향으로 길게 연결되는 종방향 보강보(146)들을 추가로 설치한다.In addition, the longitudinal reinforcement beams 146 are further installed between the transverse reinforcement beams 134 and the two transverse support girders 121a in the longitudinal direction through a bonding plate (not shown).

상기 각 지지거더(121a,121b), 종방향 및 횡방향 보강보(133,134,146)들 위에는 시공될 보의 위치를 제외한 부분에 받침보(147)를 2층으로 적층시켜 볼트 및 너트(147a)로 고정한다.On each of the support girders 121a and 121b and the longitudinal and transverse reinforcement beams 133, 134 and 146, the support beams 147 are laminated in two layers except for the positions of the beams to be constructed and fixed with bolts and nuts 147a. do.

보강보(133,134,146)와 받침보(147)들은 모두 H-형강을 적정 크기로 절단하여 사용한다.The reinforcing beams 133, 134, 146 and the support beams 147 are used to cut the H-shaped steel to the appropriate size.

이하, 명확한 설명을 위하여 지지거더 사각틀(120) 및 이에 일체로 조립된 보강보(133,134,146), 받침보(147)들을 함께 묶어 가설지지틀(140)로 칭하기로 한 다.Hereinafter, for the sake of clarity, the support girder square frame 120 and the reinforcing beams 133, 134 and 146 integrally assembled thereto and the support beams 147 will be referred to as a temporary support frame 140.

한편, 상기 가설지지틀(140) 위에는 장선(148)들을 받침보(147)와는 횡방향 배치되게 하여 등간격으로 배치하며, 이 장선(148)들 위에는 합판 거푸집(149)을 설치한다.On the other hand, on the temporary support frame 140, the joists 148 are disposed at equal intervals so as to be arranged laterally with the support beam 147, and the plywood formwork 149 is installed on the joists 148.

상기 합판 거푸집(149)에서 슬래브 거푸집 부분은 받침보(147) 위에서 지지되며, 보 거푸집 부분은 하방 돌출되게 형성되어 지지거더(121a,121b) 위에서 지지된다.In the plywood formwork 149, the slab formwork portion is supported on the support beam 147, and the beam formwork portion is formed to protrude downward to be supported on the support girders 121a and 121b.

이와 같이 가설지지틀(140) 위에 장선(148)들을 배치한 후 그 위에 합판 거푸집(149)을 고정하여 가설구조체(130)를 완성한다. As such, after placing the joists 148 on the temporary support frame 140, the plywood formwork 149 is fixed thereon to complete the temporary structure 130.

이와 같이 설치되는 가설구조체(130)는 보 및 슬래브 시공 중에 작업대로 사용될 수 있으며, 동시에 가설구조체(130)의 합판 거푸집(149)은 보 및 슬래브 시공을 위한 거푸집으로도 사용되는데, 합판 거푸집(149) 내부에 보강철근을 설치하는 배근 작업을 한 후, 내부에 콘크리트를 타설하여 보 및 슬래브를 시공하게 된다. The temporary structure 130 installed as described above may be used as a workbench during beam and slab construction, and at the same time, the plywood formwork 149 of the temporary structure 130 is also used as formwork for beam and slab construction, and plywood formwork 149 ) After reinforcement work to install reinforcing steel bars inside, concrete and concrete will be placed inside to construct beams and slabs.

상기와 같이 콘크리트를 타설 및 양생하는 과정을 거쳐 상층 보 및 슬래브의 시공 과정이 모두 완료되면, 지지 브라켓(110) 및 가설구조체(130)를 하층으로 하강시켜 재설치한 후 배근 작업 및 콘크리트 타설 작업을 실시하여 하층 보 및 슬래브의 시공을 완료하게 되는데, 이러한 시공 과정을 전 지하층에 대해 동일하게 실시하여 시공해 내려간다. When the construction of the upper beams and slabs is completed through the process of placing and curing concrete as described above, the support bracket 110 and the temporary structure 130 are lowered and reinstalled after the reinforcement work and concrete placing work. After completing the construction of the lower beams and slabs, the construction process is carried out in the same way for all basement floors.

상층 시공 후 하층 시공을 위하여 가설구조체(130)를 하강시킬 때에는, 도 15에 도시한 바와 같이, 합판 거푸집(149)을 포함한 가설구조체(130)를, 시공된 상 층 슬래브 및 보로부터 분리시킨 뒤 조립상태에서 일체로 하강시키며, 이때 하나의 지지거더 사각틀(120) 및 이에 결합된 가설구조체(130)의 구성요소들을 한 단위로 하여 각 단위별로 순차 하강시킨다.When lowering the temporary structure 130 for lower construction after the upper layer construction, as shown in FIG. 15, the temporary structure 130 including the plywood formwork 149 is separated from the constructed upper slab and beam. It is lowered integrally in the assembled state, and in this case, one support girder square frame 120 and the components of the temporary structure 130 coupled thereto are sequentially lowered for each unit.

물론, 상기 합판 거푸집(149)은 순차 하강될 수 있게 각 단위별로 분리 구성되어야 하며, 가설구조체(130)의 현수 하강을 위해서 현수재(6)의 하단이 연결되는 지점은 지지거더(121a,121b) 또는 받침보(147)가 될 수 있다.Of course, the plywood formwork 149 should be separately configured for each unit to be sequentially lowered, the point where the lower end of the suspension material 6 is connected to the suspension lowering of the temporary structure 130 is supported girder 121a, 121b Or a support beam 147.

도 12에서 재킹 포인트는 현수재 하단이 연결되는 지점을 나타낸다.In FIG. 12, the jacking point indicates a point where the lower end of the suspension is connected.

도 15a ~ 15h를 참조하면, 흙막이벽(1) 및 H-형강 기둥(2)의 시공이 도 5a에서와 동일하며, 지반 굴토 후에 지지 브라켓(110) 및 가설구조체(130)를 설치하고, 해당 층에서 보 및 슬래브의 콘크리트 시공이 완료되면 다시 지반 굴토 후에 지지 브라켓(110) 및 가설구조체(130)를 하강시켜 재설치하는 전체적인 순서가 도 5a ~ 도 5h의 예와 동일하다.15A to 15H, the construction of the retaining wall 1 and the H-beam column 2 is the same as that of FIG. 5A, and after the ground excavation, the support bracket 110 and the temporary structure 130 are installed. When the concrete construction of the beam and the slab is completed in the floor, the overall order of lowering and reinstalling the support bracket 110 and the temporary structure 130 after ground excavation is the same as the example of FIGS. 5A to 5H.

다만 최하층에서도 보(G4) 및 슬래브(S4)의 콘크리트 시공을 위하여 가설구조체(130)의 합판 거푸집(149)을 상층에서와 동일하게 이용하며, 전 지하층의 보 및 슬래브 시공 과정을 모두 완료한 후에는 기초에서부터 미시공된 기둥 및 벽체 등의 수직재와 램프, 계단 등의 부위를 공사하여 지하공사를 완료한다.However, even in the lowermost floor, the plywood formwork 149 of the temporary structure 130 is used in the same way as in the upper layer for the concrete construction of the beam G4 and the slab S4. The underground construction is completed by constructing vertical materials such as pillars and walls, and lamps and stairs from the foundation.

이와 같이 하여, 본 발명은 브라켓 지지되는 가설구조체(130)를 구성하여 이를 작업대로 활용할 수 있도록 하는 역타설 공법으로서, 브라켓(110)에 의해 고정 지지되는 가설구조체(130)를 작업대로 활용할 수 있게 되면서 안전성 측면에서 향상되는 효과가 있고, 최하층 바닥 구조로 사용될 데크(139,145)를 가설구조체(130) 내에 포함시켜 시공 중의 작업대로 사용하는 경우 작업대의 설치비용을 줄일 수 있는 등 활용성 및 경제성 측면에서 유리해진다. In this way, the present invention is a reverse casting method for constructing the bracket-supported temporary structure 130 to use it as a workbench, it is possible to utilize the temporary structure 130 is fixed by the bracket 110 as a workbench In addition, it is effective in terms of safety, and includes decks (139,145) to be used as the bottom floor structure in the temporary structure 130 to reduce the installation cost of the workbench when used as a workbench during construction. Is advantageous.

이상에서 설명한 바와 같이, 본 발명에 따른 역타설 공법에 의하면, 브라켓에 의해 고정 지지되는 가설구조체를 각 층 시공 중의 작업대로 활용할 수 있게 되면서 안전성 측면에서 향상되는 효과가 있고, 최하층 바닥 구조로 사용될 데크를 가설구조체 내에 포함시켜 사용하는 경우 작업대의 설치비용을 줄일 수 있는 등 활용성 및 경제성 측면에서 유리해진다. As described above, according to the reverse casting method according to the present invention, the temporary structure that is fixedly supported by the bracket can be utilized as a workbench during the construction of each floor, while improving the safety aspect, deck to be used as the bottom floor structure When used in a temporary structure to reduce the installation cost of the workbench is advantageous in terms of utilization and economics.

Claims (12)

삭제delete 지하층의 보 및 슬래브를 역타 시공시, (a)흙막이벽 시공 후, 그 안쪽 지중에 H-형강 기둥을 시공하는 단계와, (b)1차로 지반 굴토 후, 노출된 H-형강 기둥에 지지 브라켓을 고정 설치하고, 이웃한 H-형강 기둥의 두 지지 브라켓 사이 및 지지 브라켓과 흙막이벽 사이에 지지거더를 설치하는 단계와, (c)상기 지지거더에 가설구조체를 지지시켜 설치하는 단계와, (d)상기 가설구조체를 작업대로 활용하면서 그 위에 슬래브 거푸집과 보 거푸집을 설치한 후, 콘크리트 타설하여 1층 바닥 슬래브 및 보를 시공하는 단계와, e)2차로 지반 굴토 후, 상기 각 지지 브라켓을 해체 및 하강시켜 추가 노출된 H-형강 기둥의 지하 1층 설치 높이에 맞추어 재설치하는 단계와, (f)상기 지지거더 및 가설구조체를 현수재로 하강시켜 상기 지지 브라켓 위에 재설치하는 단계와, (g)상기 가설구조체를 작업대로 활용하면서 그 위에 슬래브 거푸집과 보 거푸집을 설치한 후, 콘크리트 타설하여 지하 1층 바닥 슬래브 및 보를 시공하는 단계와, (h)상기 (e)~(g)단계를 반복하여 지하 2층 및 그 이하 지하층의 바닥 슬래브 및 보를 역타 시공해 내려가는 단계를 포함하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법에 있어서,In case of reversing the beam and slab of the basement, (a) After constructing the wall, construct the H-beam column in the inside of it, and (b) After the ground excavation, the support bracket is exposed to the exposed H-beam. And installing a support girder between the two support brackets of the adjacent H-beams and between the support bracket and the retaining wall, and (c) supporting and installing the temporary structure on the support girder; d) installing the slab formwork and the beam formwork on the workbench while using the temporary structure as a workbench, and constructing the ground floor slab and the beam by concrete placing; and e) dismantling each of the supporting brackets after the second ground excavation. And lowering and reinstalling according to the height of the first basement installation of the H-beam column further exposed, and (f) lowering the supporting girder and the temporary structure with a suspended material and reinstalling it on the supporting bracket, and (g) Prize After installing the slab formwork and beam formwork on the workbench using the temporary structure as a workbench, constructing the ground floor slabs and beams on the ground floor by placing concrete, and (h) repeating the above steps (e) to (g) In the reverse casting method that can utilize the bracket-supported temporary structure, including the step of backing down the floor slab and beams of the second and lower basement floor, 상기 (c)단계의 가설구조체를 설치하기 전에 상기 (b)단계에서, 이웃한 H-형강 기둥의 두 지지 브라켓 사이에 2줄씩의 지지거더를 나란히 설치하고, 2줄씩의 지지거더를 각 H-형강 기둥을 중심으로 종과 횡으로 설치하되, 4개의 지지 브라켓에서 4각형 형태로 배치되는 4개의 지지거더들끼리 단부간에 접합 플레이트로 연결하여, 4개씩의 지지 브라켓을 한 단위로 하는 지지거더 사각틀을 구성하는 것을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법.Before installing the temporary structure of step (c), in step (b), two rows of support girders are installed side by side between two support brackets of adjacent H-beam columns, and two rows of support girders are installed in each H- The support girder square frame is installed horizontally and vertically around the column pillars, and the four support girders arranged in a quadrilateral form from four support brackets are connected to each other by means of a joining plate between the ends. Reverse casting method that can utilize the bracket-supported temporary structure, characterized in that the workbench. 지하층의 보 및 슬래브를 역타 시공시, (a)흙막이벽 시공 후, 그 안쪽 지중에 H-형강 기둥을 시공하는 단계와, (b)1차로 지반 굴토 후, 노출된 H-형강 기둥에 지지 브라켓을 고정 설치하고, 이웃한 H-형강 기둥의 두 지지 브라켓 사이 및 지지 브라켓과 흙막이벽 사이에 지지거더를 설치하는 단계와, (c)상기 지지거더에 가설구조체를 지지시켜 설치하는 단계와, (d)상기 가설구조체를 작업대로 활용하면서 그 위에 슬래브 거푸집과 보 거푸집을 설치한 후, 콘크리트 타설하여 1층 바닥 슬래브 및 보를 시공하는 단계와, e)2차로 지반 굴토 후, 상기 각 지지 브라켓을 해체 및 하강시켜 추가 노출된 H-형강 기둥의 지하 1층 설치 높이에 맞추어 재설치하는 단계와, (f)상기 지지거더 및 가설구조체를 현수재로 하강시켜 상기 지지 브라켓 위에 재설치하는 단계와, (g)상기 가설구조체를 작업대로 활용하면서 그 위에 슬래브 거푸집과 보 거푸집을 설치한 후, 콘크리트 타설하여 지하 1층 바닥 슬래브 및 보를 시공하는 단계와, (h)상기 (e)~(g)단계를 반복하여 지하 2층 및 그 이하 지하층의 바닥 슬래브 및 보를 역타 시공해 내려가는 단계를 포함하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법에 있어서, In case of reversing the beam and slab of the basement, (a) After constructing the wall, construct the H-beam column in the inside of it, and (b) After the ground excavation, the support bracket is exposed to the exposed H-beam. And installing a support girder between the two support brackets of the adjacent H-beams and between the support bracket and the retaining wall, and (c) supporting and installing the temporary structure on the support girder; d) installing the slab formwork and the beam formwork on the workbench while using the temporary structure as a workbench, and constructing the ground floor slab and the beam by concrete placing; and e) dismantling each of the supporting brackets after the second ground excavation. And lowering and reinstalling according to the height of the first basement installation of the H-beam column further exposed, and (f) lowering the supporting girder and the temporary structure with a suspended material and reinstalling it on the supporting bracket, and (g) Prize After installing the slab formwork and beam formwork on the workbench using the temporary structure as a workbench, constructing the ground floor slabs and beams on the ground floor by placing concrete, and (h) repeating the above steps (e) to (g) In the reverse casting method that can utilize the bracket-supported temporary structure, including the step of backing down the floor slab and beams of the second and lower basement floor, 상기 (c)단계에서 트러스 데크를 포함하는 가설구조체를 설치하고, 상기 각 층의 바닥 시공용 슬래브 거푸집으로서 트러스 데크를 사용하되, 상기 (h)단계에서 지지 브라켓 및 지지거더를 이용하는 최하층 시공시에는 상기 가설구조체에 포함된 트러스 데크를 바닥 시공용 슬래브 거푸집으로 사용하는 것을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법. In the step (c), a temporary structure including a truss deck is installed, and a truss deck is used as the slab formwork for the floor construction of each layer, and in the step (h) during the lowest floor construction using the support bracket and the support girder Reverse casting method that can utilize the bracket-supported temporary structure, characterized in that using the truss deck included in the temporary structure as a slab formwork for floor construction. 청구항 2에 있어서,The method according to claim 2, 상기 (c)단계의 가설구조체를 설치하는 과정이,The process of installing the temporary structure of step (c), 상기 (b)단계에서 설치된 각 지지거더 사각틀의 지지거더 위에 길이방향을 따라 H-형강으로 된 테두리 보강보를 2층으로 적층시켜 고정하는 단계와;Stacking and fixing the edge reinforcement beams made of H-shaped steel in two layers on the support girders of the respective square girders installed in the step (b); 상기 테두리 보강보들이 형성하는 사각공간 내측으로 테두리 보강보 사이에 H-형강으로 된 종방향 및 횡방향, 경사방향 보강보를 추가로 설치하여, 상기 보강보들로 이루어진 보강 지지틀을 각 지지거더 사각틀 위에 일체로 구성하는 단계와;The longitudinal, transverse and inclined reinforcement beams made of H-shaped steel are additionally installed between the edge reinforcement beams inside the rectangular spaces formed by the edge reinforcement beams. Integrally configuring; 상기 각 보강 지지틀의 테두리 보강보 위에 각재를 개재시켜 트러스 데크들을 고정 설치하고, 이 트러스 데크 위에 복공용 합판을 고정 설치하여 가설구조체를 완성하는 단계;Fixing the truss decks by interposing a corner member on the rim reinforcement beams of the reinforcing support frames, and fixing the truss decks on the truss decks to complete the temporary structure; 로 이루어짐을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법.Reverse casting method that can be used as a workbench supported temporary bracket structure, characterized in that consisting of. 청구항 4에 있어서,The method according to claim 4, 상기 테두리 보강보들은 지지거더 상측에 적층시킨 상태에서 지지거더와 테두리 보강보의 서로 맞닿아 있는 플랜지 부분을 볼트 및 너트로 체결하여 고정하고, 상기 테두리 보강보, 종방향 및 횡방향 보강보, 경사방향 보강보들은 단부간에 접합 플레이트를 매개로 상호 연결하는 것을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법. The edge reinforcement beams are fastened by fastening the flange portions of the support girder and the edge reinforcement beams, which are in contact with each other, by bolts and nuts, and the edge reinforcement beams, longitudinal and transverse reinforcement beams, and inclined portions. Directional reinforcing beams are reverse casting method that can utilize the bracket-supported temporary structure as a workbench, characterized in that the interconnection between the ends via a bonding plate. 지하층의 보 및 슬래브를 역타 시공시, (a)흙막이벽 시공 후, 그 안쪽 지중에 H-형강 기둥을 시공하는 단계와, (b)1차로 지반 굴토 후, 노출된 H-형강 기둥에 지지 브라켓을 고정 설치하고, 이웃한 H-형강 기둥의 두 지지 브라켓 사이 및 지지 브라켓과 흙막이벽 사이에 지지거더를 설치하는 단계와, (c)상기 지지거더에 가설구조체를 지지시켜 설치하는 단계와, (d)상기 가설구조체를 작업대로 활용하면서 그 위에 슬래브 거푸집과 보 거푸집을 설치한 후, 콘크리트 타설하여 1층 바닥 슬래브 및 보를 시공하는 단계와, e)2차로 지반 굴토 후, 상기 각 지지 브라켓을 해체 및 하강시켜 추가 노출된 H-형강 기둥의 지하 1층 설치 높이에 맞추어 재설치하는 단계와, (f)상기 지지거더 및 가설구조체를 현수재로 하강시켜 상기 지지 브라켓 위에 재설치하는 단계와, (g)상기 가설구조체를 작업대로 활용하면서 그 위에 슬래브 거푸집과 보 거푸집을 설치한 후, 콘크리트 타설하여 지하 1층 바닥 슬래브 및 보를 시공하는 단계와, (h)상기 (e)~(g)단계를 반복하여 지하 2층 및 그 이하 지하층의 바닥 슬래브 및 보를 역타 시공해 내려가는 단계를 포함하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법에 있어서,In case of reversing the beam and slab of the basement, (a) After constructing the wall, construct the H-beam column in the inside of it, and (b) After the ground excavation, the support bracket is exposed to the exposed H-beam. And installing a support girder between the two support brackets of the adjacent H-beams and between the support bracket and the retaining wall, and (c) supporting and installing the temporary structure on the support girder; d) installing the slab formwork and the beam formwork on the workbench while using the temporary structure as a workbench, and constructing the ground floor slab and the beam by concrete placing; and e) dismantling each of the supporting brackets after the second ground excavation. And lowering and reinstalling according to the height of the first basement installation of the H-beam column further exposed, and (f) lowering the supporting girder and the temporary structure with a suspended material and reinstalling it on the supporting bracket, and (g) Prize After installing the slab formwork and beam formwork on the workbench using the temporary structure as a workbench, constructing the ground floor slabs and beams on the ground floor by placing concrete, and (h) repeating the above steps (e) to (g) In the reverse casting method that can utilize the bracket-supported temporary structure, including the step of backing down the floor slab and beams of the second and lower basement floor, 상기 (c)단계에서 딥 데크를 포함하는 가설구조체를 설치하고, 상기 각 층의 바닥 시공용 슬래브 거푸집으로서 딥 데크를 사용하되, 상기 (h)단계에서 지지 브라켓 및 지지거더를 이용하는 최하층 시공시에는 상기 가설구조체에 포함된 딥 데크를 바닥 시공용 슬래브 거푸집으로 사용하는 것을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법.In the step (c), the temporary structure including the deep deck is installed, and a deep deck is used as the slab formwork for the floor construction of each layer, but the construction of the lowermost layer using the support bracket and the support girder in the step (h) Reverse casting method that can utilize the bracket-supported temporary structure, characterized in that using the deep deck included in the temporary structure as a slab formwork for floor construction. 청구항 2에 있어서,The method according to claim 2, 상기 (c)단계의 가설구조체를 설치하는 과정이,The process of installing the temporary structure of step (c), 상기 (b)단계에서 설치된 각 지지거더 사각틀에 사각공간 내측으로 H-형강으로 된 종방향 및 횡방향 보강보를 추가로 설치하여, 상기 지지거더 사각틀과 보강보들로 이루어진 가설지지틀을 일체로 구성하는 단계와;In addition, by installing the longitudinal and transverse reinforcement beams made of H-shaped steel into the rectangular space inside each support girder square frame installed in the step (b), the temporary support frame composed of the support girder square frame and the reinforcement beams is integrally formed. Steps; 상기 각 가설지지틀의 보강보 위에 각재를 개재시켜 딥 데크들을 고정 설치하고, 이 딥 데크 위에 복공용 합판을 고정 설치하여 가설구조체를 완성하는 단계;A step of fixing the deep decks by interposing a lumber on the reinforcing beams of each temporary supporting frame, and fixing the perforated plywood on the deep deck to complete the temporary structure; 로 이루어짐을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법.Reverse casting method that can be used as a workbench supported temporary bracket structure, characterized in that consisting of. 청구항 7에 있어서, The method according to claim 7, 상기 지지거더, 종방향 보강보 및 횡방향 보강보들은 단부간에 접합 플레이트를 매개로 상호 연결하는 것을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법.The support girders, longitudinal reinforcement beams and transverse reinforcement beams can be used as a work station to the bracket-supported temporary structure, characterized in that the interconnection between the end via the joint plate. 삭제delete 지하층의 보 및 슬래브를 역타 시공시, (a')흙막이벽 시공 후, 그 안쪽 지중에 H-형강 기둥을 시공하는 단계와, (b')1차로 지반 굴토 후, 노출된 H-형강 기둥에 지지 브라켓을 고정 설치하고, 이웃한 H-형강 기둥의 두 지지 브라켓 사이 및 지지 브라켓과 흙막이벽 사이에 지지거더를 설치하는 단계와, (c')상기 지지거더에 보강보 및 받침보, 장선들을 차례로 설치한 후, 이 장선들 위로 슬래브 및 보 시공용 합판 거푸집을 설치하여, 이들을 포함하는 가설구조체를 구성하는 단계와, (d')상기 합판 거푸집 내에 콘크리트 타설하여 1층 바닥 슬래브 및 보를 시공하는 단계와, (e')2차로 지반 굴토 후, 상기 각 지지 브라켓을 해체 및 하강시켜 추가 노출된 H-형강 기둥의 지하 1층 설치 높이에 맞추어 재설치하는 단계와, (f')상기 지지거더 및 합판 거푸집을 포함하는 가설구조체를 현수재로 하강시켜 상기 지지 브라켓 위에 재설치하는 단계와, (g')상기 가설구조체의 합판 거푸집 내에 콘크리트 타설하여 지하 1층 바닥 슬래브 및 보를 시공하는 단계와, (h')상기 (e')~(g')단계를 반복하여 지하 2층 및 그 이하 지하층의 바닥 슬래브 및 보를 역타 시공해 내려가는 단계를 포함하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법에 있어서,When reversing the beams and slabs of the basement, (a ') after constructing the wall, construct the H-beam column in the inner ground, and (b') after the ground excavation, the exposed H-beam column Fixing the support brackets and installing support girders between two support brackets of neighboring H-beam columns and between the support brackets and the retaining walls, and (c ') the reinforcement beams, the support beams and the joists on the support girders. After the installation, the plywood formwork for slab and beam construction is installed on the joists, constructing a temporary structure including them, and (d ') concrete placing in the plywood formwork to construct the first floor slab and beam. Step (e ') after the second soil ground excavation, and dismantling and lowering each of the support brackets and reinstalled according to the installation height of the first basement of the H-beam column further exposed, (f') the support girder and Going to include plywood dies D) lowering the structure with a suspension material and reinstalling it on the support bracket; (g ') constructing concrete in the plywood formwork of the temporary structure to construct a basement floor slab and beam; and (h') the (e ' In the reverse casting method that can utilize the bracket-supported temporary structure, including the step of repeating the bottom slab and beams of the basement 2 and the basement floor by repeating the steps) to (g '), 상기 (c')단계의 가설구조체를 설치하기 전에 상기 (b')단계에서, 이웃한 H-형강 기둥의 두 지지 브라켓 사이에 2줄씩의 지지거더를 나란히 설치하고, 2줄씩의 지지거더를 각 H-형강 기둥을 중심으로 종과 횡으로 설치하되, 4개의 지지 브라켓에서 4각형 형태로 배치되는 4개의 지지거더들끼리 단부간에 접합 플레이트로 연결하여, 4개씩의 지지 브라켓을 한 단위로 하는 지지거더 사각틀을 구성하는 것을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법.Before installing the temporary structure of the step (c '), in the step (b'), two support girders are installed side by side between two support brackets of adjacent H-beam columns, and two support girders are installed in each line. It is installed horizontally and vertically around the H-beam column, and four support girders arranged in a quadrilateral form from four support brackets are connected to each other by a joining plate between ends, so that four support brackets are used as a unit. A reverse casting method that can utilize a bracket-supported temporary structure, which comprises a girder square frame, as a workbench. 청구항 10에 있어서,The method according to claim 10, 상기 (c')단계의 가설구조체를 설치하는 과정이,The process of installing the temporary structure of step (c '), 상기 (b')단계에서 설치된 각 지지거더 사각틀에 사각공간 내측으로 H-형강으로 된 종방향 및 횡방향 보강보를 추가로 설치하고, 상기 지지거더, 종방향 및 횡방향 보강보들 위에 H-형강으로 된 받침보를 2층으로 적층시켜, 상기 지지거더 사각틀과 보강보, 받침보들로 이루어진 가설지지틀을 일체로 구성하는 단계와;The longitudinal and transverse reinforcement beams of H-shaped steel are additionally installed in the rectangular frame of each support girder installed in the step (b '), and the H-beams are supported on the support girder, longitudinal and transverse reinforcement beams. Stacking the supported support beams in two layers to integrally construct a temporary support frame consisting of the support girder square frame, the reinforcement beams and the support beams; 상기 각 가설지지틀 위에 장선들을 받침보와 횡방향으로 설치한 뒤, 상기 장선들 위로 합판 거푸집을 고정 설치하여 가설구조체를 완성하는 단계;Installing the joists in the transverse direction with the support beams on each temporary support frame, and then fixing the plywood formwork over the joists to complete the construction of the construction of the construction of the construction; 로 이루어짐을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법.Reverse casting method that can be used as a workbench supported temporary bracket structure, characterized in that consisting of. 청구항 11에 있어서,The method according to claim 11, 상기 지지거더, 종방향 보강보 및 횡방향 보강보들은 단부간에 접합 플레이트를 매개로 상호 연결하고, 상기 받침보들은 지지거더 및 보강보 상측에 적층시킨 상태에서 서로 맞닿아 있는 위아래의 플랜지 부분을 볼트 및 너트로 체결하여 고정하는 것을 특징으로 하는 브라켓 지지되는 가설구조체를 작업대로 활용할 수 있는 역타설 공법.The support girders, longitudinal reinforcement beams and transverse reinforcement beams are interconnected by means of a joining plate between the ends, and the support beams are bolted to the upper and lower flange portions which are in contact with each other while being stacked on the upper side of the support girders and the reinforcement beams. And the reverse casting method that can utilize the bracket-supported temporary structure, characterized in that by fastening with a nut to the workbench.
KR1020050068193A 2005-07-27 2005-07-27 Downward construction method capable of using bracket support type temporary structure as working table KR100694493B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050068193A KR100694493B1 (en) 2005-07-27 2005-07-27 Downward construction method capable of using bracket support type temporary structure as working table

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050068193A KR100694493B1 (en) 2005-07-27 2005-07-27 Downward construction method capable of using bracket support type temporary structure as working table

Publications (2)

Publication Number Publication Date
KR20070013680A KR20070013680A (en) 2007-01-31
KR100694493B1 true KR100694493B1 (en) 2007-03-16

Family

ID=38013342

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050068193A KR100694493B1 (en) 2005-07-27 2005-07-27 Downward construction method capable of using bracket support type temporary structure as working table

Country Status (1)

Country Link
KR (1) KR100694493B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100856723B1 (en) * 2007-03-28 2008-09-04 박무용 System and method for underground downward construction using cantilever type steel frame
KR101250482B1 (en) * 2010-06-14 2013-04-03 (주)엠씨에스에스티기술사사무소 Underground slab construction method using wire rope and curing pannel flame
KR101335796B1 (en) 2012-05-03 2013-12-05 코오롱글로벌 주식회사 Apparatus for supporting form of underground building and method of constructing the underground building using the same
KR101341679B1 (en) * 2010-09-30 2013-12-16 (주)바로건설기술 Device for constructing an underground structure and method thereof
KR101409249B1 (en) 2014-05-13 2014-06-23 주식회사무영아멕스건축사사무소 Top Down Construction method Using Method Of Steel Hybrid Girder Construction
KR101627708B1 (en) 2015-06-25 2016-06-07 주식회사 거원에코텍 Apparatus and method for closing an opening of building slab formed by the interference with the temporary structure

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100775767B1 (en) * 2006-08-14 2007-11-12 깨뱉시스템주식회사 Top-down method using the vertical steel bar for the src column
KR102330771B1 (en) * 2020-01-07 2021-11-24 (주)한국건설공법 Top-down construction method using bracket and double girder

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200358247Y1 (en) * 2004-05-27 2004-08-05 박무용 Downward construction structure using bracket support type

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200358247Y1 (en) * 2004-05-27 2004-08-05 박무용 Downward construction structure using bracket support type

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100856723B1 (en) * 2007-03-28 2008-09-04 박무용 System and method for underground downward construction using cantilever type steel frame
KR101250482B1 (en) * 2010-06-14 2013-04-03 (주)엠씨에스에스티기술사사무소 Underground slab construction method using wire rope and curing pannel flame
KR101341679B1 (en) * 2010-09-30 2013-12-16 (주)바로건설기술 Device for constructing an underground structure and method thereof
KR101335796B1 (en) 2012-05-03 2013-12-05 코오롱글로벌 주식회사 Apparatus for supporting form of underground building and method of constructing the underground building using the same
KR101409249B1 (en) 2014-05-13 2014-06-23 주식회사무영아멕스건축사사무소 Top Down Construction method Using Method Of Steel Hybrid Girder Construction
KR101627708B1 (en) 2015-06-25 2016-06-07 주식회사 거원에코텍 Apparatus and method for closing an opening of building slab formed by the interference with the temporary structure

Also Published As

Publication number Publication date
KR20070013680A (en) 2007-01-31

Similar Documents

Publication Publication Date Title
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR100694503B1 (en) Downward construction system and method for 1-way girder and slab of underground structure
KR200417438Y1 (en) Bracket structure for girder and slab construction
KR20120096605A (en) Bracket support type downward construction system and method
JP4060323B2 (en) Bracket support type downward frame driving system and downward frame driving method using the same
KR101658648B1 (en) Beam-column joint and simultaneous construction method of upper and lower part of building using thereof
RU2220258C1 (en) Process of erection of multilevel underground structure ( variants )
KR100605514B1 (en) Bracket support type downward construction system and construction method using the same
KR200398231Y1 (en) 1way-supporting bracket for girder and slab construction
KR200385376Y1 (en) Form system for construction of underground slab
KR101071245B1 (en) Non support downward method using Steel-PC composite girder and the Steel-PC composite girder
KR101004747B1 (en) Pillar construction method by layer-built and frame construction method adapting the same
JP4550534B2 (en) Building basic structure
JP6855296B2 (en) Building foundation structure and its construction method
KR20200122037A (en) The construction method using a exterio wall of undergound structure
KR200370135Y1 (en) Forms for edge girder construction
JP5003253B2 (en) RC beam construction method
KR100695877B1 (en) Form with removable coner-form and method thereof
KR100620366B1 (en) Construction method of underground structures comprising composite reinforced concrete girders and beams using FRP
KR100593203B1 (en) a deck supportframe and a construction methed
KR100679986B1 (en) Structure for plastic slab deck system and Downward construction method using the same
JPH0657710A (en) Construction of concrete main tower
KR101707376B1 (en) Structure for constructing underground structure using composite beams and the construction method thereof
JP6682173B1 (en) How to build a building

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130326

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140307

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20150306

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160303

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170306

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20180305

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20190408

Year of fee payment: 13