KR100757710B1 - Dowel bar construction method for downward construction of underground structures - Google Patents

Dowel bar construction method for downward construction of underground structures Download PDF

Info

Publication number
KR100757710B1
KR100757710B1 KR1020060084491A KR20060084491A KR100757710B1 KR 100757710 B1 KR100757710 B1 KR 100757710B1 KR 1020060084491 A KR1020060084491 A KR 1020060084491A KR 20060084491 A KR20060084491 A KR 20060084491A KR 100757710 B1 KR100757710 B1 KR 100757710B1
Authority
KR
South Korea
Prior art keywords
formwork
dowel
concrete
construction
pipe
Prior art date
Application number
KR1020060084491A
Other languages
Korean (ko)
Inventor
박무용
황기수
최창식
Original Assignee
박무용
황기수
최창식
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 박무용, 황기수, 최창식 filed Critical 박무용
Priority to KR1020060084491A priority Critical patent/KR100757710B1/en
Application granted granted Critical
Publication of KR100757710B1 publication Critical patent/KR100757710B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

A method for laying dowel bars of an underground structure constructed downward is provided to reduce the number of used couplers by reducing the number of joints, and to improve workability through integrated construction after downward construction of a beam and a slab. A plurality of pipes are vertically fixed and installed in a beam mold of each layer in the process of downward constructing a beam and a slab by casting concrete after a mold is installed. Upper and lower layers are connected to each other by allowing dowel bars to pass through the pipe that vertically penetrates a beam of each layer if the concrete is casted and then the mold is disassembled, so that the downward construction of the beam and slab is completed. A pillar and a wall structure are constructed by installing the mold and casting concrete, so that dowel bars are buried in the concrete of the pillar and the wall structure.

Description

역타설 시공되는 지하구조물의 다월 철근 시공방법{Dowel bar construction method for downward construction of underground structures}Dowel bar construction method for downward construction of underground structures

도 1a는 종래기술에 따른 다월 철근의 설치상태를 나타낸 단면도,Figure 1a is a cross-sectional view showing the installation state of the dowel rebar according to the prior art,

도 1b는 도 1a의 선 'F-F'를 따라 취한 단면도,FIG. 1B is a cross-sectional view taken along the line 'F-F' of FIG. 1A,

도 2는 보 거푸집을 해체한 상태의 단면도,2 is a sectional view of a state in which the beam formwork is disassembled;

도 3과 도 4는 종래기술에 따른 다월 철근의 층간 연결 시공상태를 나타낸 단면도,3 and 4 is a cross-sectional view showing the construction of the interlayer connection of the dowel rebar according to the prior art,

도 5a와 도 5b는 종래기술에 따른 문제점을 설명하기 위한 도면,5a and 5b is a view for explaining a problem according to the prior art,

도 6a와 도 6b는 본 발명에 따른 다월 철근 시공과정에서 보 거푸집 내부에 파이프가 시공된 상태의 예를 나타낸 단면도, Figure 6a and 6b is a cross-sectional view showing an example of a state in which the pipe construction inside the formwork in the dowel reinforcement construction process according to the present invention,

도 7은 도 6a에서 콘크리트 시공 후 보 거푸집이 해체된 상태의 단면도, Figure 7 is a cross-sectional view of the formwork dismantled after the concrete construction in Figure 6a,

도 8은 도 7의 선 'A-A'를 따라 취한 단면도, 8 is a cross-sectional view taken along the line 'A-A' of FIG. 7,

도 9는 도 7에서 'B' 부분을 확대하여 나타낸 단면도,FIG. 9 is an enlarged cross-sectional view of a portion 'B' in FIG. 7;

도 10a와 도 10b는 본 발명에 따른 다월 철근 시공과정에서 보 및 슬래브 시공 후 다월 철근이 배근된 상태의 예를 나타낸 단면도, Figure 10a and Figure 10b is a cross-sectional view showing an example of the reinforcement state of the dowel reinforcement after the beam and slab construction in the dowel reinforcement construction process according to the present invention,

도 11은 도 10a에서 'C' 부분을 확대하여 나타낸 단면도,FIG. 11 is an enlarged cross-sectional view of a portion 'C' in FIG. 10A;

도 12는 본 발명에 따른 내력벽체에서의 다월 철근 시공방법을 순서대로 도시한 단면도, 12 is a cross-sectional view showing in sequence the method of construction of the dowel rebar in the bearing wall according to the present invention,

도 13은 도 12의 선 'D-D'를 따라 취한 단면도,FIG. 13 is a cross-sectional view taken along the line 'D-D' of FIG. 12,

도 14는 본 발명에 따른 비내력벽체에서의 다월 철근 시공방법을 순서대로 도시한 단면도, 14 is a cross-sectional view showing in sequence the method of construction of the dowel rebar in the non-bearing wall according to the present invention,

도 15는 도 14의 선 'E-E'를 따라 취한 단면도.15 is a cross-sectional view taken along the line 'E-E' in FIG.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for main parts of the drawings>

1 : H-형강 기둥 2 : 보 거푸집1: H-beam column 2: beam formwork

5 : 충전 플레이트 6 : 다월 철근5: filling plate 6: dowel rebar

7 : 커플러 11 : 파이프7: coupler 11: pipe

12 : 마개 13 : 보강철근12: stopper 13: rebar

14 : 와이어 15 : 정착제 14 wire 15 fixing agent

본 발명은 역타설 시공되는 지하구조물의 다월 철근 시공방법에 관한 것으로서, 더욱 상세하게는 역타 시공되는 지하구조물에서 상하 층간의 연결을 위하여 기둥 및 벽체 부분의 콘크리트 내부에 수직으로 매입 및 층간 연결 설치되는 다월 철근의 시공방법에 관한 것이다.The present invention relates to a method for constructing a multi-bar reinforcement of underground structures to be built in reverse, and more specifically, to be connected to each other and installed vertically inside the concrete of columns and wall parts for connection between upper and lower layers in underground structures to be installed in reverse. It is about construction method of dowel rebar.

일반적으로 지하구조물을 구축하는 방법에는 두 가지가 있다.In general, there are two ways to build underground structures.

지하구조물이 축조되는 지반에 흙막이 공사를 한 다음 지반을 굴착하면서 흙막이를 지지할 수 있는 가시설물을 설치하고 토사를 전부 반출한 뒤 맨 아래층부터 구조물을 축조해 올라가는 순타설공법과, 흙막이를 시공하고 1층 구조물을 축조한 다음 그 구조물을 흙막이용 버팀부재로 이용하여 상부에서 하부로 지반을 굴착하면서 구조물을 축조해 내려가는 역타설공법이 그것이다.After constructing the earthquake on the ground where the underground structure is constructed, install the temporary facility to support the earthquake while excavating the ground, take out all the earth and sand, and build the structure from the bottom floor, After the construction of the first-floor structure, using the structure as a retaining member for the earthquake, the reverse casting method is to construct the structure while drilling the ground from the top to the bottom.

최근 토지 이용의 극대화 차원에서 지하공사가 점차 고심도화되고 있고, 특히 순타설공법에 의한 시공시에는 흙막이 붕괴의 위험이나 주변 건물들 침하 등으로 인한 균열 발생은 물론, 시각적으로도 불안할 뿐만 아니라 공사기간이 길어지는 등 여러 문제가 있어서, 근래에는 역타설공법이 널리 적용되고 있다.In recent years, underground construction has been increasingly intensified in order to maximize land use. In particular, when the construction is carried out by the net pouring method, not only the construction of cracks due to the risk of earthquake collapse or the settlement of nearby buildings, but also visually unstable construction Due to various problems such as long periods of time, the reverse casting method has been widely applied in recent years.

이 역타설공법은 흙막이벽 및 그 안쪽 지중의 골조용 기둥을 시공한 뒤 슬래브 및 보 등의 지하구조물을 지상 1층부터 지하층을 향하여 단계적으로 시공해 내려가는 방식이므로, 지하구조물과 지상구조물의 시공이 동시에 진행 가능하고, 지상 1층의 바닥을 작업장으로 활용할 수 있어 별도의 복공판이 필요하지 않으며, 무지보 거푸집 작업이 가능하다는 장점이 있다.In this reverse casting method, after constructing the retaining wall and the frame for the underground frame, the underground structures such as slabs and beams are constructed step by step from the ground floor to the underground floor. It can proceed at the same time, the floor of the ground floor can be utilized as a workshop, there is no need for a separate perforated plate, there is an advantage that the work can be plain.

이러한 역타설공법으로는 지반을 정지한 상태에서 지반 위에 콘크리트 슬래브와 보를 타설하는 방법(Concrete on Grade)과, 지반을 어느 정도 굴착하고 지반을 고른 뒤 동바리를 세우고 거푸집을 설치하여 콘크리트를 타설하는 방법(Form on Supporting)과, 거푸집 지지를 위한 동바리를 세우지 않는 대신에 선시공한 상층의 콘크리트 슬래브에 거푸집을 현수시켜 콘크리트를 타설하는 방법(무지보 역타설 현 수 거푸집 공법) 등이 있다. Such a reverse casting method involves placing concrete slabs and beams on the ground while the ground is stopped (concrete on grade), and excaving the ground to some extent, selecting the ground, and then placing the clubs and installing the formwork to place the concrete. (Form on Supporting) and the method of placing concrete by suspending formwork on the concrete slab on the upper floor instead of establishing a swivel for supporting the formwork.

이 중에서 동바리를 이용하는 공법은 상대밀도가 비교적 높은 지층에 적용하는 공법으로서, 지반을 선 굴착한 후 굴착된 지반 위에 버림 콘크리트를 타설하고, 이 버림 콘크리트를 지지기반으로 하여 동바리와 보 거푸집 및 슬래브 거푸집을 설치한 뒤, 보 및 슬래브의 콘크리트를 타설하는 공법이다.Among them, the method of using copper barley is a method applied to strata with relatively high relative density. After digging the ground, the discarded concrete is placed on the excavated ground, and the discarded concrete is used as the support base. After installing the concrete, the concrete of the beam and slab is poured.

여기서, 보 거푸집 및 슬래브 거푸집은 굴착 지반 위의 버림 콘크리트상에서 동바리에 의해 지지되어진다.Here, beam formwork and slab formwork are supported by clubs on discarded concrete on the excavation ground.

최근 동바리의 사용을 줄이기 위하여 무지보 시공의 장점을 가진 데크 플레이트(Deck Plate)가 개발되어 그 사용이 점차 늘고 있는 바, 흙막이벽과 그 안쪽 지중의 골조용 기둥이 시공된 상태에서, 시공될 보를 따라 그 하측으로 보 거푸집을 버림 콘크리트 위 동바리로 지지시켜 설치하고, 보 거푸집과 보 거푸집 사이에 데크 플레이트를 지지시켜 설치한 다음, 보 거푸집과 데크 플레이트에 콘크리트를 동시 타설하여 보와 슬래브(데크 슬래브)를 완성한다. Recently, deck plate, which has the advantage of unsupported construction, has been developed to reduce the use of copper bar, and its use is gradually increasing. Underneath it, the beam formwork is installed by supporting the slab on the discarded concrete, and the deck plate is supported by the deck formwork between the formwork and the formwork.The concrete is then cast on the formwork and the deck plate to form the beam and slab (deck slab). To complete).

이때, 역타설공법이 이용되므로, 우선 보 거푸집 및 데크 플레이트에 콘크리트를 타설하여 상층 슬래브 및 보를 선시공하고, 상층 시공시에 이용된 보 거푸집을 하층 높이에 맞게 하강시켜 재설치한 후 동일하게 콘크리트를 타설하여 하층 슬래브 및 보를 시공하게 된다.In this case, since the reverse casting method is used, first, the concrete is placed on the formwork and the deck plate, and the upper slab and the beam are pre-installed. Thus, the lower slabs and beams will be constructed.

이러한 방법으로 보 거푸집 하강 및 데크 플레이트 설치, 슬래브 및 보의 콘크리트 타설 작업을 각 층의 시공과정에서 반복하여, 지하구조물을 지하층을 향해 단계적으로 시공해 내려가게 된다.In this way, the beam formwork and deck plate installation, slab and concrete placement of the slab are repeated in the construction process of each floor, and the underground structure is constructed step by step toward the basement floor.

한편, 동바리 사용시의 문제점을 해결하기 위하여, 지하구조물을 축조할 때 지상 1층부터 지하 최저층을 향해 구축해 나가는 무지보 역타설 거푸집 공법(Non Supporting Formwork System for Top Down Construction)으로서, 거푸집 지지용 동바리를 설치하지 않는 대신, 선시공한 상층 콘크리트 슬래브에 거푸집을 현수시키는 무지보 역타설 현수 거푸집 공법이 제시된 바 있다.On the other hand, in order to solve the problem of using the grouping, as a non-supporting formwork system for top down construction that is constructed from the ground floor to the lowest basement when building underground structures, Instead of installing it, an unsupported reversal suspension formwork was proposed to suspend the formwork on the pre-installed upper concrete slab.

이 무지보 역타설 현수 거푸집 공법은 선시공한 상층의 슬래브에 현수재를 이용하여 거푸집을 현수시킨 상태에서 이 거푸집을 이용하여 하층의 슬래브를 시공하는 방법이다.This unsupported back-casting formwork is a method of constructing a lower slab by using the formwork with the formwork suspended from the upper slab.

이 방법을 이용하여 각 층의 지하구조물을 축조하기 위해서는, 거푸집에 콘크리트를 타설하여 상층 슬래브를 시공하는 단계, 이 상층 슬래브의 시공시에 이용된 거푸집을 상층 슬래브 위의 유압 승강기를 이용하여 하강시키는 단계, 이 하강된 거푸집을 이용해 하층 슬래브를 시공하는 단계를 각 층마다 반복하게 된다.In order to build underground structures of each floor using this method, concrete is laid on the formwork to construct the upper slab, and the formwork used in the construction of the upper slab is lowered by using a hydraulic lift on the upper slab. The construction of the lower slab using the lowered formwork is repeated for each floor.

이러한 현수식 공법은, 슬래브 거푸집 및 보 거푸집 하부에 동바리를 설치하지 않고 거푸집을 상층의 슬래브에 매달아 설치하기 때문에, 작업장 확보 및 작업자의 안전 보장 측면에서 보다 유리하고, 거푸집 작업과 상관없이 지하 터파기를 연속적으로 진행할 수 있으며, 충분한 양생기간 확보로 우수한 콘크리트 품질을 얻을 수 있는 동시에 공기 단축 및 원가 절감이 가능해지는 장점이 있다.This suspension method is more advantageous in securing the workplace and ensuring the safety of the worker because it is installed by hanging the formwork on the upper slab without installing the copper bar at the bottom of the slab formwork and the beam formwork. It is possible to proceed continuously, it is possible to obtain excellent concrete quality by securing a sufficient curing period, and at the same time has the advantage that it is possible to shorten the air and reduce the cost.

특히, 현수식 공법을 적용하는 경우에는 상층 슬래브에 현수된 거푸집을 연속적으로 달아내리는 지하 골조공사, 하부에서의 굴토공사, 그리고 지상부 구조물 축조공사의 3단계 공정을 동시에 진행할 수 있게 된다.In particular, when the suspension method is applied, it is possible to simultaneously perform the three-stage process of underground frame construction, which continuously runs down the formwork suspended from the upper slab, the excavation work from the bottom, and the ground structure construction.

또한 좀더 개량된 공법으로서, 시공층의 보 거푸집 및 데크 플레이트에 콘크리트가 타설되는 동안, 그 콘크리트 하중을 포함하여 보 거푸집, 데크 플레이트, 보 거푸집을 지지하는 철골보인 지지거더의 하중을, 골조용 기둥상에 설치된 브라켓으로 하여금 지지하도록 하는 공법이 제시된 바 있다.In addition, as a more improved method, while concrete is being laid on the beam formwork and deck plate of the construction layer, the load of the steel frame supporting girder supporting the beam formwork, deck plate, and formwork, including the concrete load, A method of supporting the bracket installed on the support has been proposed.

상기 지지 브라켓을 이용한 역타설 시스템에서는 각 골조용 기둥의 해당 층 높이에 지지 브라켓이 장착되어, 이 지지 브라켓 위에 지지거더가 지지되고, 이 지지거더 위에 보 거푸집이 지지되며, 보 거푸집에 데크 플레이트가 지지된다.In the reverse casting system using the support bracket, a support bracket is mounted at the height of the corresponding floor of each frame pillar, and a support girder is supported on the support bracket, and the formwork is supported on the support girder, and the deck plate is provided on the formwork. Supported.

그리고, 상기 지지 브라켓은 기둥상에 쉽게 장착 및 해체가 가능하므로, 해당 층에 대해 보 및 슬래브의 콘크리트 타설 작업이 완료되면, 각 지지 브라켓들을 기둥상의 아래층 높이로 내려 재설치한 뒤 동일 목적으로 사용하게 된다. In addition, since the support bracket can be easily mounted and dismantled on the column, when the concrete and the concrete placing work of the beam and the slab is completed for the floor, each support bracket is lowered down to the height of the column and reinstalled to be used for the same purpose. do.

이와 같이 지지 브라켓을 이용한 방법은, 종래와 같이 선시공한 상층 슬래브에 현수재를 이용하여 현수 및 지지시키는 방법이 아닌, 지지 브라켓을 통해 골조용 기둥에 지지시키는 방법으로서, 기존의 현수재 지지방식에서 지적되어 왔던 여러 문제점을 해결할 수 있다.As such, the method using the support bracket is not a method of suspending and supporting the upper slab pre-constructed as in the prior art by using a suspension material, but a method of supporting the frame pillar through the support bracket. Many problems that have been pointed out can be solved.

한편, 전 층의 보 및 슬래브의 역타설 시공을 모두 완료하면, 골조용 기둥, 예컨대 골조용 기둥으로 시공된 H-형강 기둥의 주변으로 기둥 거푸집을 설치한 뒤 그 내부에 콘크리트를 타설하여 기둥을 시공하는 작업을 실시한다. On the other hand, when the reinforcement construction of the beams and slabs of the entire floor is completed, the pillar formwork is installed around the H-beam column constructed as a frame pillar, for example, a frame pillar, and then concrete is poured into the pillar. Carry out construction work.

상기 기둥 거푸집을 설치하는 과정에서 기둥 내부에 매입되는 상, 하부의 다월 철근(dowel bar)은 커플러(coupler)를 이용하여 서로 연결하게 되며, 이렇게 연결된 다월 철근은 상하 층간을 연결하는 역할을 하게 된다. In the process of installing the pillar formwork, the upper and lower dowel bars embedded in the pillars are connected to each other by using a coupler, and the connected dowel bars serve to connect the upper and lower layers. .

이러한 기둥 콘크리트 타설 작업은 맨 아래층부터 실시하되, 각 층에 대하여 H-형강 기둥 주변에 기둥 거푸집을 설치하고, 기둥 거푸집 내에 콘크리트를 타설할 수 있도록 충전 파이프를 설치한 다음, 이 충전 파이프를 통해 상기 기둥 거푸집 내부로 콘크리트를 타설하게 된다.This pillar concrete pouring work should be carried out from the bottom floor, and for each floor, a pillar formwork is installed around the H-beam pillar, and a filling pipe is installed so that concrete can be poured into the pillar formwork. Concrete is poured into the column formwork.

기둥 콘크리트의 타설을 위하여 충전 파이프를 설치하는 방법으로는 기둥 내부 매입 방식과 기둥 외부 매입 방식을 들 수 있다. Filling pipes for the installation of pillar concrete can be installed in the column and the column.

그러나, 기둥 내부 매입 방식의 경우, 충전 파이프를 H-형강 기둥 주변으로 미리 매설시켜 보를 시공해야 하므로, 보 시공시에 충전 파이프를 매설하는 작업에 어려움이 있고, 충전 파이프가 보를 관통하는 형태가 되어 보가 구조적으로 취약해질 수 있는 문제가 있게 된다.However, in the case of the pillar-filling method, since the filling pipe must be buried in advance around the H-beam column, it is difficult to embed the filling pipe during the construction of the beam, and the filling pipe penetrates the beam. There is a problem that the beam can be structurally vulnerable.

또한 기둥 외부 매입 방식의 경우, 충전 파이프를 경사방향으로 배치하여 기둥 외부에 설치하는 동시에 충전 파이프의 하단 투입구가 기둥 거푸집 내부로 연결되게 하는 구조이나, 이 또한 충전 파이프가 슬래브를 관통하는 형태로 설치되어야 하며, 기둥에서 콘크리트가 충전 파이프의 하단 투입구 하측으로만 충전될 수 있으므로 하단 투입구 상측 기둥 부분은 별도로 콘크리트가 선 타설되어야 하는 문제가 있게 된다. In addition, in the case of the pillar external filling method, the filling pipe is disposed in an inclined direction and installed outside the pillar, and at the same time, the lower opening of the filling pipe is connected to the inside of the pillar formwork, but also the filling pipe is installed through the slab. In the column, since the concrete can be filled only below the lower inlet of the filling pipe, the upper portion of the lower inlet has a problem in that concrete is pre-poured separately.

이러한 문제점을 해결하기 위하여, "기둥 콘크리트 타설 구조"라는 명칭으로 본 발명자에 의해 출원되어 등록된 실용신안등록번호 제402363호(2005.11.23)에는 H-형강 기둥을 따라 두 플랜지 양 끝단 사이에 충전 플레이트를 설치하는 기술이 개시되어 있다.In order to solve this problem, Utility Model Registration No. 403663 (filed on November 23, 2005) filed and filed by the inventor under the name "column concrete pouring structure" is filled between both ends of two flanges along an H-beam column. A technique for installing a plate is disclosed.

여기서는 각 층의 보 및 슬래브를 역타 시공한 후에 맨 아래층부터 SRC 합성기둥을 순타 시공하는데, 기둥 콘크리트 타설 구조로서, 종래와 같이 충전 파이프를 설치하는 대신, H-형강 기둥의 양쪽 플랜지 내부공간을 폐단면 형태로 밀폐하는 동시에 그 상, 하단이 개방될 수 있게, H-형강 기둥을 따라 두 플랜지 양 끝단 사이에 충전 플레이트를 길게 용접 설치한다.In this case, after reversing the beams and slabs of each floor, the SRC composite columns are smoothly constructed from the bottom layer. As a concrete concrete casting structure, instead of installing a filling pipe as in the prior art, the inner spaces of both flanges of the H-beam columns are closed. The filling plate is long welded between the two flange ends along the H-beam, so that it can be sealed in the form of a face and the top and bottom can be opened.

상기 충전 플레이트에 의해 형성되는 플랜지 내부공간은 보 및 슬래브의 콘크리트 시공 후에 보를 상하로 관통하면서 상층 및 하층의 기둥 공간을 연결하는 콘크리트 타설 통로 역할을 하게 되며, 플랜지 내부공간의 상단 개구부는 곧 콘크리트 투입구가 되고, 이 플랜지 내부공간을 통해 콘크리트가 투입되도록 되어 있다.The flange inner space formed by the filling plate serves as a concrete pouring passage connecting the upper and lower column spaces through the beam up and down after concrete construction of the beam and slab, and the upper opening of the flange inner space is concrete inlet. The concrete is to be introduced through this flange inner space.

한편, 종래기술에 따른 다월 철근 시공방법을 설명하면 다음과 같다.On the other hand, when explaining the dowel rebar construction method according to the prior art.

우선, 지하구조물의 역타 시공 과정에서, 특정 층의 보 거푸집 및 슬래브 거푸집을 설치한 후, 도 1a에 나타낸 바와 같이 보 거푸집을 상하로 관통하도록 다월 철근을 설치하는 바, 이때 다월 철근은 도 1b에 나타낸 바와 같이 골조기둥인 H-형강 기둥 주변으로 소정 간격으로 배열하여 설치하며, 보 거푸집 내부에 배근되는 보강철근들에 철사로 엮어 고정한다.First, in the process of reverse construction of the underground structure, after installing the formwork and slab formwork of a specific layer, as shown in Figure 1a to install the dowel rebar to penetrate the formwork up and down, the dowel reinforcement is shown in Figure 1b As shown, it is installed by arranging at predetermined intervals around the frame pillar H-beam, and is fixed by weaving with wire to the reinforcing bars are reinforced inside the formwork.

그리고, 보 및 슬래브의 콘크리트를 타설한 후, 도 2에 나타낸 바와 같이 보 거푸집을 해체하게 된다.Then, after pouring the concrete of the beams and slabs, as shown in Figure 2, the formwork is dismantled.

이러한 보 및 슬래브 시공 과정을 하층으로 내려가면서 반복 실시하며, 전 층의 시공이 완료되면, 맨 아래층부터 SRC 합성기둥을 순타 시공하는데, 골조기둥 인 H-형강 기둥에 충전 플레이트를 설치하고(도 1b 참조), 도 3에 나타낸 바와 같이 이미 선 시공된 상층의 다월 철근과 하층의 다월 철근 사이에 중간 다월 철근을 연결한다.This beam and slab construction process is repeatedly performed while going down to the lower floor, and when the construction of the entire floor is completed, the SRC composite column is smoothly constructed from the bottom layer, and the filling plate is installed on the H-beam column which is a frame pillar (FIG. 1B). 3), as shown in FIG. 3, the intermediate dowel bars are connected between the upper dowel bars and the lower dowel bars.

이때, 다월 철근의 연결은 커플러(철금이음장치)를 사용하여 연결하게 된다.At this time, the connection of the dowel rebar is connected using a coupler (metal fittings).

이후, 해당 층의 기둥 거푸집을 설치하고, 이어 충전 플레이트를 통해 콘크리트를 타설하여 기둥 거푸집(도면의 기둥 콘크리트 타설 라인을 따라 설치되는 것임) 내부에 콘크리트가 채워지도록 하며, 콘크리트가 양생되고 난 뒤 기둥 거푸집을 해체하고 나면 도 4에 나타낸 바와 같이 콘크리트 내부에 매입된 상태에서 상하 층간을 연결하는 철근으로서 다월 철근의 시공이 완료된다. Thereafter, the pillar formwork of the floor is installed, and then concrete is poured through the filling plate so that the concrete is filled inside the pillar formwork (which is installed along the pillar concrete placing line in the drawing), and after the concrete is cured, the pillar After dismantling the formwork, construction of the dowel rebar is completed as the reinforcing bar connecting the upper and lower floors in the state embedded in the concrete as shown in FIG.

도 4는 3개 층에서 다월 철근의 연결상태를 보여주는 단면도이다.4 is a cross-sectional view showing the connection state of the dowel rebar in three layers.

그러나, 상기와 같이 종래기술에 따른 다월 철근의 시공방법에 따르면 다음과 같은 문제점이 있었다.However, according to the construction method of the dowel rebar according to the prior art as described above had the following problems.

우선, 도 4에 나타낸 바와 같이 각 층별로 이음 개소가 지나치게 많아진다(통상 1개층 2개소 이음).First, as shown in FIG. 4, the number of joint parts becomes too many for each layer (normally two joints of one layer).

즉, 보 및 슬래브 시공시에 보 거푸집을 관통하는 다월 철근을 설치한 후 보 및 슬래브의 콘크리트를 타설하고, 기둥 시공시에 상층과 하층의 다월 철근(상기 보 거푸집을 관통하는 다월 철근임)을 중간 다월 철근으로 서로 연결한 후 기둥 거푸집 설치 및 기둥 콘크리트를 타설하는 바, 상층과 하층의 다월 철근을 중간 다월 철근으로 연결하기 위하여 각 층별로 적어도 2개소의 철근 이음이 필수적이다.That is, after installing the dowel reinforcing bar through the formwork for beam and slab construction, the concrete of the beam and the slab is poured, and the dowel reinforcing bar through the upper and lower layers (which is the dowel reinforcing bar through the formwork) during the column construction. After linking each other with intermediate dowel bars and installing pillar formwork and pouring concrete, it is essential to connect at least two reinforcing bars in each floor to connect the upper and lower dowel bars with middle dowel bars.

이와 같이 철근의 이음 개소가 많아짐에 따라 커플러의 사용개수가 불필요하 게 많아지고, 특히 보 콘크리트 타설 전에 보 거푸집을 관통하는 다월 철근 설치 및 기둥 콘크리트 타설 전에 중간 다월 철근 설치 등 여러 단계로 다월 철근의 시공이 나누어져 실시되는 바, 작업 효율의 저하, 작업 공정 및 작업 인력의 증가, 비용 및 시간 증가 등 여러 문제점이 있게 된다. As the number of joints of reinforcing bars increases, the number of use of couplers becomes unnecessary. Especially, the installation of dowel rebars in several stages, such as the installation of dowel reinforcing bars through the formwork and the installation of intermediate dowel bars before column concrete As the construction is divided and carried out, there are various problems such as a decrease in work efficiency, an increase in work process and workforce, and an increase in cost and time.

특히, 보 거푸집을 관통하는 다월 철근을 설치하게 됨에 따라 보 거푸집에는 다월 철근이 관통하도록 된 구멍이 만들어지므로 보 거푸집을 재활용하는 것이 구멍으로 인해 거의 어렵게 된다. In particular, as the dowel reinforcing bars are installed through the formwork, holes are formed in the formwork so that the dowel reinforcing bars become difficult to recycle the formwork.

또한 보 거푸집을 관통하는 다월 철근을 설치하고 보 거푸집 내부에 콘크리트를 타설하여 보의 시공이 완료된 후에는 보 거푸집을 해체해야 하는 바, 이때 수직 관통하도록 설치된 다월 철근은 그 존재 자체가 보 거푸집의 해체를 어렵게 한다.In addition, after the construction of the beam is completed by installing a dowel reinforcing bar penetrating through the formwork and placing concrete inside the formwork, the dowel reinforcing bar installed to penetrate vertically is dismantled. Makes it difficult.

즉, 도 5a에 나타낸 바와 같이 보의 시공이 완료된 후 보 거푸집을 해체하고자 할 경우 커플러의 간섭으로 보 거푸집을 하방으로 해체하는 것이 어렵게 된다.That is, as shown in FIG. 5a, when the beam formwork is to be dismantled after the construction of the beam is completed, it becomes difficult to dismantle the formwork downward due to the interference of the coupler.

또한 도 5b에 나타낸 바와 같이 커플러를 미리 설치하지 않더라도 보 거푸집 내부에 타설되는 콘크리트에 의해 하중이 가해지면서 다월 철근에 약간의 휨이라도 발생하게 되면, 즉 철근 절곡이 발생한다면 이 또한 간섭을 초래하여 보 거푸집을 하방으로 해체하는데 많은 어려움이 있게 된다.In addition, as shown in FIG. 5B, even if the coupler is not installed in advance, if a load is applied by concrete placed inside the formwork, even if a slight bending occurs in the rebar, that is, the bending of the reinforcing bar may also cause interference. There are many difficulties in dismantling the formwork downwards.

따라서, 본 발명은 상기와 같은 문제점을 해결하기 위하여 발명한 것으로서, 다월 철근을 보 및 슬래브의 역타 시공 후 파이프 내부에 삽입하여 일괄적으로 연결 시공함으로써, 다월 철근의 이음 개소 및 커플러 사용개수 축소, 작업 효율의 향상, 작업 공정 및 작업 인력의 축소, 비용 및 시간의 절감 등 효과를 가지는 역타설 시공되는 지하구조물의 다월 철근 시공방법을 제공하는데 그 목적이 있다. Therefore, the present invention was invented to solve the above problems, by inserting the dowel reinforcement of the reinforcement of the reinforcement of the beam and slab into the inside of the pipe in a batch connection, reducing the number of joints and coupler use of the dowel rebar, The purpose of the present invention is to provide a method for constructing the reinforcing bars of underground structures to be constructed in reverse, which has the effect of improving work efficiency, reducing work process and workforce, and reducing costs and time.

또한 보 거푸집 해체 후 다월 철근을 파이프를 통해 일괄 시공함에 따라 보 거푸집에 다월 철근 관통을 위한 구멍 가공이 필요 없게 되고, 따라서 보 거푸집의 재활용성을 향상시킬 수 있으며, 보 거푸집의 해체가 용이해지는 다월 철근 시공방법을 제공하는데 그 목적이 있다. In addition, since the dowel reinforcement is carried out through pipes after dismantling the formwork, it is not necessary to make holes for the penetration of the reinforcement in the formwork, thereby improving the recyclability of the formwork, and making it easier to dismantle the formwork. The purpose is to provide rebar construction methods.

이하, 첨부한 도면을 참조하여 본 발명을 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

상기한 목적을 위해, 본 발명은, 역타 시공되는 지하구조물에서 상하 층간의 연결을 위하여 기둥 및 벽체 부분의 콘크리트 내부에 수직으로 매입 및 층간 연결 설치되는 다월 철근의 시공방법에 있어서,In order to achieve the above object, the present invention, in the construction method of the dowel reinforcement is installed vertically embedded and interlayer connection in the concrete interior of the column and the wall for the connection between the upper and lower layers in the reverse construction underground construction,

거푸집을 설치한 후 콘크리트를 타설하여 보 및 슬래브를 역타 시공해 내려가는 과정에서 각 층의 보 거푸집 내부에 다수개의 파이프를 수직으로 고정 설치한 후 콘크리트를 타설하는 단계와;Placing concrete after installing the formwork and fixing a plurality of pipes vertically inside the beam formwork on each floor in the process of laying down the beams and slabs;

콘크리트를 타설한 후 거푸집을 해체하여 보 및 슬래브의 역타 시공이 모두 완료되면 각 층의 보를 상하로 관통하는 상기 파이프의 내부에 다월 철근을 통과시켜 상하 층간을 연결 시공하는 단계와; When the concrete is finished by dismantling the formwork after the concrete is laid, passing the dowel reinforcing bars through the pipes vertically through the beams of each floor to connect the upper and lower floors;

거푸집을 설치하고 콘크리트를 타설하여 기둥 및 벽체를 시공함으로써 시공된 기둥 및 벽체 부분의 콘크리트 내부에 다월 철근을 매입시키는 단계;Installing a formwork and placing concrete to construct pillars and walls to purchase dowel reinforcing bars within the concrete of the constructed pillars and wall portions;

를 포함하는 것을 특징으로 하는 역타설 시공되는 지하구조물의 다월 철근 시공방법을 제공한다.Provides a method for constructing the rebar reinforcement of the underground structure to be constructed in reverse, comprising a.

여기서, 상기 각 파이프는, 이후 콘크리트 시공되는 보 상측으로 일부가 노출될 수 있도록 상단부가 보 콘크리트 타설면보다 높게 설치되고, 하단부 끝단은 보 거푸집 내부 저면에 밀착되도록 설치되는 것을 특징으로 한다.Here, each of the pipes, the upper end is installed higher than the beam concrete placing surface so that a portion to be exposed to the side of the concrete to be constructed later, the lower end is characterized in that it is installed to be in close contact with the inner bottom surface of the formwork.

또한 상기 각 파이프의 보 상측으로 노출되는 상단부에 콘크리트 유입을 방지하기 위한 마개가 설치되는 것을 특징으로 한다.In addition, a stopper for preventing the inflow of concrete is installed on the upper end exposed to the complementary side of each pipe.

또한 상기 각 파이프는 보 거푸집 내부에 설치되는 보강철근에 철사로 묶어 고정하거나 용접하여 고정하는 것을 특징으로 한다.In addition, each of the pipes is characterized in that it is fixed to the reinforcing bar is installed in the formwork by fixing the wire or welded.

또한 상기 보 거푸집 내부에 파이프의 열을 따르면서 파이프와 인접될 수 있게 보강철근을 상, 하 높이에 각각 추가로 설치한 후, 이렇게 설치된 보강철근에 파이프를 철사로 묶어 고정하거나 용접하여 고정하는 것을 특징으로 한다.In addition, after installing the reinforcing bars in each of the upper and lower heights so as to be adjacent to the pipe while following the row of pipes in the formwork, it is characterized by fixing or welding by fixing the pipes to the reinforcing bars so installed. It is done.

또한 상기 파이프의 내부에 다월 철근을 통과시킨 후 파이프의 내부공간에 정착제를 주입하여 파이프와 다월 철근을 일체화시키는 것을 특징으로 한다.In addition, after passing the dowel reinforcement inside the pipe is characterized in that the pipe and the dowel reinforcement is integrated by injecting a fixing agent into the inner space of the pipe.

또한 상기 정착제에 의한 일체성을 향상시키기 위하여 내주면에 요철 구조를 가지는 파이프를 사용하는 것을 특징으로 한다.In addition, it is characterized in that to use a pipe having an uneven structure on the inner peripheral surface in order to improve the integrity by the fixing agent.

또한 상기 요철 구조는 파이프의 내주면을 나사산 가공하여 형성한 것임을 특징으로 한다.In addition, the uneven structure is characterized in that formed by threading the inner peripheral surface of the pipe.

이하, 첨부한 도면을 참조하여 본 발명에 대해 더욱 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in more detail with reference to the accompanying drawings.

도 6a와 도 6b는 본 발명에 따른 다월 철근 시공과정에서 보 거푸집 내부에 파이프가 시공된 상태의 예를 나타낸 단면도이고, 도 7은 도 6a에서 콘크리트 시공 후 보 거푸집이 해체된 상태의 단면도이다. 6a and 6b is a cross-sectional view showing an example of a state in which the pipe construction inside the formwork in the reinforcing bar construction process according to the present invention, Figure 7 is a cross-sectional view of the formwork is dismantled after the concrete construction in Figure 6a.

또한 도 8은 도 7의 선 'A-A'를 따라 취한 단면도이고, 도 9는 'B' 부분을 확대하여 나타낸 단면도이다.8 is a cross-sectional view taken along a line 'A-A' of FIG. 7, and FIG. 9 is an enlarged cross-sectional view of a portion 'B'.

또한 도 10a와 도 10b는 본 발명에 따른 다월 철근 시공과정에서 보 및 슬래브 시공 후 다월 철근이 배근된 상태의 예를 나타낸 단면도이며, 도 11은 도 10a에서 'C' 부분을 확대하여 나타낸 단면도이다.10A and 10B are cross-sectional views illustrating examples of a state in which a dowel rebar is disposed after beam and slab construction in a dowel rebar construction process according to the present invention, and FIG. 11 is an enlarged cross-sectional view of a portion 'C' in FIG. 10A. .

본 발명은 역타 시공되는 지하구조물에서 상하 층간의 연결을 위하여 기둥 및 벽체 부분의 콘크리트 내부에 수직으로 매입 및 층간 연결 설치되는 다월 철근의 시공방법에 관한 것이다. The present invention relates to a construction method of a dowel reinforcing bar installed vertically embedded and interlayer connection in the concrete of the pillars and the wall portion for the connection between the upper and lower floors in the reverse construction underground structure.

우선, 역타설 공법이 적용되는 지하구조물의 시공은 상층에서 하층으로 내려가면서 보(G) 및 슬래브(S)를 역타 시공하게 되는 바, 각 층의 보(G) 및 슬래브(S)는 보 거푸집(2) 및 슬래브 거푸집(3)을 설치한 뒤 내부에 보강철근(4)을 배근하고 이어 거푸집 내부에 콘크리트를 타설한 뒤 보 거푸집(2)을 해체하는 과정으로 진행된다.First of all, the construction of underground structures to which the reverse casting method is applied will reverse the construction of beams (G) and slabs (S) while descending from the upper floor to the lower floor, and the beams (G) and slabs (S) of each floor will be formed in the beam formwork. (2) After installing the slab formwork (3) and reinforce the reinforcing bar (4) inside, and then cast concrete inside the formwork proceeds to dismantle the formwork (2).

이와 같이 각 층의 보(G) 및 슬래브(S)를 시공하기 위하여 보 거푸집(2)과 슬래브 거푸집(3)을 설치한 뒤 내부에 보강철근(4)을 배근하고 나면, 종래에는 콘 크리트 타설 전에 보 거푸집(2)을 관통하도록 다수개의 다월 철근을 수직으로 설치하였는 바, 본 발명에서는, 보 거푸집(2)을 관통하는 다월 철근의 설치 과정이 삭제되고 그 대신, 보 거푸집(2) 내부에 보(G)의 수직 관통 통로를 형성하기 위한 다수개의 파이프(11)를 수직으로 고정 설치하게 된다.In this way, after installing the beam formwork (2) and the slab formwork (3) to construct the beam (G) and slab (S) of each layer, and after reinforcing reinforcing bars (4) in the interior, conventionally placed concrete Previously, a plurality of dowel bars were vertically installed so as to penetrate the formwork 2, and in the present invention, the installation process of the dowel bars penetrating the formwork 2 is eliminated, and instead, the inside of the formwork 2 is removed. A plurality of pipes 11 for forming the vertical through passage of the beam G is fixed vertically.

즉, 도 6a 또는 도 6b에 나타낸 바와 같이, 보 거푸집(2) 내부에 상하로 길게 파이프(11)를 수직 설치하며, 이때 파이프(11)는 그 상단부가, 이후 콘크리트 시공되는 보(G) 상측으로 일부가 노출될 수 있도록, 보 콘크리트 타설면보다 소정 높이 만큼 높게 돌출 설치된다.That is, as shown in Fig. 6a or 6b, the pipe 11 is vertically installed vertically in the beam formwork 2, the upper end of the pipe 11, the upper side of the beam (G), which is then concrete construction In order to be able to expose a part, it is installed to protrude by a predetermined height than the beam concrete placing surface.

또한 이때 파이프(11)의 하단부 끝단이 보 거푸집(2) 내부 저면에 밀착되도록 설치된다. In addition, at this time, the lower end of the pipe 11 is installed to be in close contact with the inner bottom surface of the formwork (2).

상기 파이프(11)는 후술하는 바와 같이 기둥 시공 전, 즉 기둥 거푸집 설치 및 콘크리트 타설 전에 다월 철근(6)이 삽입되어 통과하도록 설치되는 파이프(11)로서, 본 발명에서는 다수개의 파이프(11)를 보 거푸집(2) 내부에서도 다월 철근(6)이 배치되는 각 위치에 각각 수직 설치하게 된다. The pipe 11 is a pipe 11 which is installed so that the dowel reinforcement 6 is inserted and passed through before the column construction, that is, the pillar formwork and concrete pouring, as described later, in the present invention, a plurality of pipes 11 Even inside the formwork (2) is installed vertically at each position where the dowel reinforcement (6) is arranged.

상기 파이프(11)가 설치되는 위치는 도 8에 나타낸 바와 같이 보 거푸집(2) 내부에서 골조용 기둥인 H-형강 기둥(1) 주변으로 기존 다월 철근이 배치되는 각 위치가 되며, 보 거푸집(2) 내부의 H-형강 기둥(1) 주변으로 사각형 배열을 이루도록 소정 간격으로 배치되어 설치된다.As shown in FIG. 8, the pipe 11 is installed at each position in which existing dowel reinforcing bars are disposed around the H-beam pillar 1, which is a frame pillar within the beam formwork 2. 2) It is disposed and arranged at a predetermined interval to form a rectangular array around the H-beam pillar (1) inside.

상기와 같이 보 거푸집(2) 내부에 미리 파이프(11)를 설치한 상태에서 콘크리트를 타설하게 되면, 이후 보 거푸집(2)을 해체할 경우 파이프(11)는 보(G)의 상 측과 하측을 수직 연결하는 통로를 형성하게 되며, 이러한 파이프(11)에 의해 보(G)에는 다월 철근(6)이 수직으로 관통할 수 있는 통로가 형성되게 된다.When the concrete is poured in the state in which the pipe 11 is installed in the inside of the beam formwork 2 as described above, the pipe 11 is the upper side and the lower side of the beam G when dismantling the formwork 2 later. To form a passage connecting the vertical, the pipe (11) by the pipe (G) is to form a passage through which the dowel reinforcement (6) can vertically penetrate.

결국, 보(G) 시공 후 기둥 콘크리트 타설 전에 후술하는 바와 같이 다월 철근(6)을 각 파이프(11) 내부에 삽입시켜 통과시킴으로써 다월 철근(6)은 보(G)를 상하로 관통하도록 설치가 가능해지며, 이와 같이 파이프(11)는 콘크리트 시공된 보(G)에 다월 철근(6)이 상하로 관통할 수 있는 통로를 형성하기 위한 것이다.As a result, the dowel reinforcement 6 is installed so as to penetrate the beam G up and down by inserting the dowel reinforcement 6 into each pipe 11 and passing it as described below before the post-beam concrete pouring after the beam G construction. In this way, the pipe 11 is to form a passage through which the reinforcing bars 6 can penetrate up and down in the concrete constructed beam G.

즉, 본 발명의 시공방법에서는 보 거푸집(2) 내부에 상하로 파이프(11)를 설치한 후 콘크리트를 타설하여, 시공되는 보(G)에 파이프(11)에 의해 형성되는 수직 관통 통로를 만들고, 이 수직 관통 통로를 통해 다월 철근(6)을 삽입하여 층간 연결 시공하는 것에 주된 특징이 있는 것이다.That is, in the construction method of the present invention after installing the pipe (11) up and down inside the beam formwork (2), the concrete is poured, to create a vertical through passage formed by the pipe (11) in the beam (G) to be constructed In addition, the main feature is to insert the dowel reinforcement (6) through the vertical through passage to connect the layers.

상기 파이프(11)로는 PVC 재질의 파이프나 강관을 사용할 수 있으며, 보 거푸집(2) 내부에 기존 설치되는 보강철근(4)에 철사(14)로 묶어 고정하거나 강관의 경우 용접하여 고정하는 것이 가능하다.The pipe 11 may be a pipe or steel pipe made of PVC, can be fixed to the reinforcing steel reinforcement (4) existing in the formwork (2) by tying with a wire 14 or fixed by welding in the case of steel pipes. Do.

더욱 바람직하기로는, 도 6a와 도 6b, 그리고 도 7 및 도 8에 나타낸 바와 같이, H-형강 기둥(1) 주변으로 다수개의 파이프(11)를 설치하되, 보 거푸집(2) 내부에 파이프(11)의 열을 따르는 별도의 보강철근(13)을 상, 하 높이에 각각 추가로 설치한 후, 이렇게 설치된 보강철근(13)에 각 파이프(11)를 철사(14)로 묶어 고정하거나 용접하여 고정하는 것도 가능하다.More preferably, as shown in Figs. 6A and 6B, and Figs. 7 and 8, a plurality of pipes 11 are installed around the H-beams 1, but the pipes (2) inside the formwork (2). After installing additional reinforcing bars 13, respectively, in the upper and lower heights along the row of 11), the pipes 11 are tied to the reinforcing bars 13, and the wires 14 are fixed or welded. It is also possible to fix.

상기 보강철근(13)은 도 8에 나타낸 바와 같이 파이프(11)의 외곽(도 6a 참조) 또는 내곽(도 6b 참조)을 따라 인접될 수 있게 사각형 모양으로 배근되며, 도 6a 및 도 6b, 도 7에 나타낸 바와 같이 상하로 두 위치에 각각 설치된다.As shown in FIG. 8, the reinforcing bars 13 are arranged in a rectangular shape so as to be adjacent along the outer side (see FIG. 6A) or the inner side (see FIG. 6B) of the pipe 11, and FIGS. 6A and 6B and FIG. As shown in Fig. 7, they are installed in two positions up and down respectively.

상기 보강철근(13)은 파이프(11) 열을 따라 발생할 수 있는 균열을 방지하는 보강의 역할과 함께 파이프(11)의 위치를 고정하는 역할을 하게 된다. The reinforcing bar 13 serves to fix the position of the pipe 11 together with the role of reinforcing to prevent cracking that may occur along the pipe 11 row.

그리고, 도 11에 나타낸 바와 같이 파이프(11)의 내주면에는 단면상에서 볼 때 요철이 형성될 수 있도록 나사산(11a) 가공을 할 수도 있으며, 이러한 구조는 후술하는 바와 같이 다월 철근(6) 삽입 후 정착제(15)를 주입한 상태에서 파이프(11)와 다월 철근(6)의 일체성을 보다 향상시킨다. In addition, as shown in FIG. 11, the inner circumferential surface of the pipe 11 may be machined with a thread 11a so that irregularities can be formed when viewed in cross section. Such a structure may be fixed after insertion of the dowel rebar 6 as described below. In the state in which the agent (15) is injected, the unity between the pipe 11 and the dowel rebar 6 is further improved.

즉, 다월 철근(6) 삽입 후 파이프(11) 내부공간에 시멘트 밀크와 같은 정착제(15)를 주입하게 되는데, 이때 정착제(15)가 경화되고 나면 파이프(11)의 내측면과 다월 철근(6)의 외주면이 정착제(15)에 의해 일체 고정되는 바, 파이프(11) 내주면에 나사산(11a) 가공을 하게 되면, 파이프(11)의 나사골(11b) 부분과 다월 철근(6)의 돌기(6a) 사이에 정착제(15)가 채워지면서 파이프(11)와 다월 철근(6)을 더욱 확실히 일체화시킬 수가 있게 되는 것이다(파이프 내주면과 정착제, 다월 철근 표면과 정착제 사이의 슬립이 완전히 방지됨). That is, after inserting the dowel reinforcement (6), the fixing agent (15), such as cement milk, is injected into the inner space of the pipe (11). At this time, after the fixing agent (15) is cured, the inner surface of the pipe (11) and the dowel reinforcement are inserted. The outer circumferential surface of (6) is integrally fixed by the fixing agent 15, and when the thread 11a is processed on the inner circumferential surface of the pipe 11, the threaded bone 11b portion of the pipe 11 and the dowel reinforcement 6 As the fixing agent 15 is filled between the projections 6a, the pipe 11 and the dowel reinforcing bars 6 can be more reliably integrated (slip between the pipe inner circumferential surface and the fixing agent, the dowel reinforcing bar surface and the fixing agent Completely prevented).

상기와 같이 보 거푸집(2) 내부에 파이프(11)를 설치한 상태에서 보 거푸집(2) 내부에 콘크리트를 타설하고 이후 콘크리트가 양생되고 나면 보 거푸집(2)을 해체하는 바, 이와 같이 보 거푸집(2)이 해체된 상태를 도 7에 도시하였으며, 보 거푸집(2) 내부에 콘크리트가 타설될 때 파이프(11)의 상단부를 통해 파이프(11) 내부로 콘크리트가 유입되는 것을 막기 위하여, 도 9에 나타낸 바와 같이 보(G) 상측으로 노출되는 파이프(11)의 상단부에 콘크리트 유입을 막기 위한 마개(12)를 설 치하는 것이 바람직하다.As the above, in the state in which the pipe 11 is installed in the formwork (2), the concrete is placed inside the formwork (2), and after the concrete is cured, the formwork (2) is dismantled. 7 shows the dismantled state, and in order to prevent the concrete from flowing into the pipe 11 through the upper end of the pipe 11 when concrete is poured into the inside of the formwork 2, FIG. 9. As shown in, it is preferable to install a stopper 12 to prevent the inflow of concrete at the upper end of the pipe 11 exposed to the upper beam (G).

본 발명의 시공방법에서는, 보 거푸집(2) 내부에 파이프(11)를 설치하는 것일 뿐, 종래와 같이 보 거푸집(2)을 관통하도록 다월 철근(6)을 설치하는 것이 아니기 때문에, 보 거푸집(2)에 어떠한 구멍도 가공할 필요가 없으며, 또한 보 거푸집(2)의 해체도 종래와 같이 미리 설치한 다월 철근(6)에 의해 간섭되는 일이 근본적으로 발생하지 않으므로 매우 용이해진다.In the construction method of the present invention, since only the pipe 11 is installed inside the formwork 2, the dowel reinforcement 6 is not provided so as to penetrate the formwork 2 as in the prior art. It is not necessary to process any holes in 2), and the dismantling of the formwork 2 is also very easy since the interference by the dowel bars 6 installed in advance as in the past does not occur fundamentally.

한편, 보 거푸집(2) 내부에 파이프(11)를 설치하고 콘크리트를 타설하여 전 층의 보(G) 및 슬래브(S)를 역타 시공한 후에는 기존과 마찬가지로 기둥 시공을 하는 바, 기둥 시공은 맨 아래층부터 순타 시공한다. On the other hand, after installing the pipe (11) in the beam formwork (2) and re-installing the beam (G) and slab (S) of the entire floor by installing concrete, the column construction is performed as before. Construct the net from the bottom floor.

각 층의 기둥 시공에서, H-형강 기둥(1)의 양쪽 플랜지 내부공간을 폐단면 형태로 밀폐하는 충전 플레이트(5)를 길게 용접 설치하고, 파이프(11)의 내부에는 다월 철근(6)을 삽입시켜 상하로 보(G)를 관통시킨 뒤 층간 연결 시공을 한 후, 마지막으로 기둥 거푸집을 설치(기둥 콘크리트 타설 라인을 따라 설치하는 것임)하여 기둥 콘크리트를 타설하게 된다.In the column construction of each layer, the filling plate 5 which seals the inner space of both flanges of the H-beam column 1 in the form of a closed cross section is welded, and the dowel reinforcement 6 is installed inside the pipe 11. After inserting the beam (G) up and down through the interlayer connection construction, and finally to install the column formwork (to be installed along the pillar concrete placing line) to pour the pillar concrete.

이와 같이 하층에서 상층으로 올라가면서 기둥을 시공하는 과정에서, 기둥 거푸집 설치 전에 다월 철근(6)을 보(G) 내부에 매입된 파이프(11) 내부로 통과시켜 상하로 연결하게 된다.As such, in the process of constructing the column while going up from the lower layer to the upper layer, the dowel reinforcing bar 6 passes through the pipe 11 embedded in the beam G before installation of the column formwork and is connected up and down.

이때, 상하의 다월 철근(6)을 연결하기 위하여 커플러(7)를 사용하는 것은 종래와 같으나, 도 10a 및 도 10b에 나타낸 바와 같이 다월 철근(6)은 파이프(11) 내부로 통과시켜 연결하며, 또한 파이프(11)의 내부에는 다월 철근(6)과의 사이 공 간에 도 11에 나타낸 바와 같이 정착제(15)를 주입하여 일체화시킨다. At this time, the coupler 7 is used to connect the upper and lower dowel bars 6 as in the related art, but as shown in FIGS. 10A and 10B, the dowel bars 6 are connected to each other by passing through the pipe 11. In addition, as shown in FIG. 11, the fixing agent 15 is injected into the space between the pipe 11 and the dowel rebar 6 to be integrated.

도 10a는 다월 철근(6)을 1개층 1개소 이음이 되도록 연결한 예를 도시한 것이며, 도 10b는 다월 철근(6)을 2개층 1개소 이음이 되도록 연결한 예를 도시한 것이다.FIG. 10A illustrates an example in which the dowel bars 6 are connected to one layer in one layer, and FIG. 10B illustrates an example in which the dowel bars 6 are connected to one layer in two layers.

이와 같이 본 발명의 시공방법에 따르면, 다월 철근(6)을 보(G) 및 슬래브(S)의 역타 시공 후 일괄적으로 파이프(11) 내부에 삽입하여 시공하므로, 종래와 같이 1개층 2개소 이음에 비해 이음 개소가 축소된 1개층 1개소 또는 2개층 1개소의 이음 시공이 가능해진다. As described above, according to the construction method of the present invention, since the dowel reinforcing bars 6 are collectively inserted into the pipe 11 after the reverse construction of the beams G and the slabs S, two places of one floor as in the prior art. Compared with a joint, the joint construction of one place of one floor or one place of two floors with which a joint site was reduced is attained.

물론, 경우에 따라서는 3개 층 이상마다 다월 철근(6)의 이음 시공을 할 수도 있다. Of course, in some cases, the joint construction of the dowel rebar 6 may be performed every three or more layers.

상기와 같이 다월 철근(6)을 설치한 후에는 종래와 같이 층별로 기둥 거푸집을 설치하고 이어 충전 플레이트(5)에 의해 형성되는 플랜지 내부공간을 통해 콘크리트를 타설하는 기둥 순타 시공을 하게 된다.After installing the dowel reinforcement 6 as described above, the pillar formwork is installed per floor as in the prior art, and then the pillar netting construction for placing concrete through the flange inner space formed by the filling plate 5 is performed.

충전 플레이트 설치 및 이를 이용한 기둥 콘크리트 타설은 실용신안등록번호 제402363호(2005.11.23)에 개시된 바와 같다.Filling plate installation and pillar concrete pouring using the same is as disclosed in Utility Model Registration No. 403363 (Nov. 23, 2005).

도 10a 및 도 10b를 참조하면, 최하단의 다월 철근(6)은 종래와 같이 하부를 기초 콘크리트 내부로 매입되도록 하여 고정하고, 이는 그 상단부에 설치된 커플러(7)를 통해 상측의 또 다른 다월 철근(6)과 연결하게 된다.10A and 10B, the bottom dowel reinforcement 6 is fixed to be embedded in the lower part of the base concrete as in the prior art, which is fixed to another upper dowel reinforcement bar (7) through the coupler 7 installed at the upper end thereof. 6).

한편, 이러한 기둥 내 다월 철근(6)의 시공방법은 내력벽체 또는 비내력벽체에 들어가는 다월 철근(6)의 시공에도 적용이 가능하다.On the other hand, the construction method of the dowel rebar 6 in the column can be applied to the construction of the dowel reinforcement (6) to enter the bearing wall or non-bearing wall.

도 12는 내력벽체에서의 다월 철근 시공방법을 순서대로 도시한 단면도이고, 도 13은 도 12의 선 'D-D'를 따라 취한 단면도이다.FIG. 12 is a cross-sectional view sequentially illustrating a method for constructing a dowel rebar in a bearing wall, and FIG. 13 is a cross-sectional view taken along the line 'D-D' of FIG. 12.

또한 도 14는 비내력벽체에서의 다월 철근 시공방법을 순서대로 도시한 단면도이고, 도 15는 도 14의 선 'E-E'를 따라 취한 단면도이다.FIG. 14 is a cross-sectional view sequentially illustrating a method for constructing a dowel rebar in a non-bearing wall, and FIG. 15 is a cross-sectional view taken along the line 'E-E' of FIG. 14.

도시한 바와 같이, 상층의 보(G)와 하층의 보 사이에 기둥 부분이 아닌 벽체 부분에도 다월 철근(6)이 매입 시공되는 바, 이때 다월 철근(6)의 시공은 각 층의 보(G) 및 슬래브(S) 시공시에 파이프(11)를 보 거푸집(2) 내부에 설치한 후 콘크리트 타설 및 거푸집 해체하여 해당 층에서의 보(G) 및 슬래브(S) 시공을 완료하고, 이후 전 층의 보(G) 및 슬래브(S) 역타 시공을 완료한 뒤에는 파이프(11) 내부에 다월 철근(6)을 삽입하여 연결 시공한 후 벽체 순타 시공을 한다.As shown, the dowel reinforcement 6 is embedded between the upper beam G and the lower beam in the wall portion, not the column portion, wherein the construction of the dowel reinforcement 6 is performed in the beam G of each layer. ) And the slab (S) during the construction of the pipe (11) inside the beam formwork (2), after the concrete is laid and dismantled to complete the construction of the beam (G) and slab (S) in the floor, and then After finishing the beam (G) and slab (S) construction of the floor, insert the dowel reinforcement (6) into the pipe (11) and connect the construction and then wall smooth construction.

이러한 다월 철근(6)의 시공방법은 기둥 부분에서의 시공 방법 및 과정 자체는 동일하나 다월 철근(6)의 배치가 기둥 부분과는 차이가 있으므로 보 거푸집(2) 내부에 시공되는 파이프(11)의 배치에도 차이가 있다.The construction method of the dowel reinforcement (6) is the same construction method and the process itself in the column portion, but the arrangement of the dowel reinforcement (6) is different from the pillar portion, so the pipe (11) to be constructed inside the formwork (2) There is also a difference.

도 13과 도 15를 참조하면, 내력벽체의 경우 보 거푸집(2) 내부에 보 거푸집(2)을 따라 2열로 파이프(11)가 배치되며, 비내력벽체의 경우 보 거푸집(2)을 따라 중앙 1열로 파이프(11)가 배치된다.13 and 15, in the case of the bearing wall, pipes 11 are arranged in two rows along the formwork 2, and in the case of the non-bearing wall, the pipes 11 are arranged along the center of the formwork 2. The pipes 11 are arranged in one row.

그리고, 파이프(11)의 고정을 위하여 벽체 내부에 별도의 보강철근(13)을 파이프(11)와 인접될 수 있도록 파이프(11) 열을 따라 길게 설치하고, 상기 보강철근(13)에 각 파이프(11)를 철사(14)로 엮거나 용접하여 고정하게 된다.In addition, a separate reinforcing bar 13 is installed in the wall so as to be adjacent to the pipe 11 so as to be adjacent to the pipe 11 so as to fix the pipe 11, and each pipe is installed in the reinforcing bar 13. (11) is fixed by weaving or welding the wire (14).

물론, 상기 보강철근(13)은 상측과 하측으로 각각 설치하며, 이와 같이 설치 된 보강철근(13)은 파이프(11) 열을 따라 발생할 수 있는 균열을 방지하는 보강의 역할과 함께 파이프(11)를 보 거푸집(2) 내부에서 위치 고정하는 역할을 하게 된다.Of course, the reinforcing bar 13 is installed to the upper side and the lower side, respectively, the reinforcing bar 13 is installed in this way with the role of reinforcement to prevent cracks that may occur along the pipe (11) heat It serves to fix the position inside the formwork (2).

내력벽체에서는 다월 철근(6)을 좌우 2열로 배열된 각 파이프(11)의 내부로 통과시켜 각 열 별로 상측의 다월 철근(6)과 하측의 다월 철근(6)을 겹이음 연결 처리한 후 벽체 시공을 하며, 비내력벽체에서는 다월 철근(6)을 중앙 1열로 배열된 각 파이프(11)의 내부로 통과시킨 뒤 중앙의 다월 철근(6)과 좌우 양측의 두 다월 철근(6)을 겹이음 연결 처리한 후 벽체 시공을 한다. In the bearing wall, the dowel bars 6 are passed through the inside of each pipe 11 arranged in two rows of left and right, and the upper dowel bars 6 and the lower dowel bars 6 are connected to each other in a row, and then the walls are connected. In the non-bearing wall, the dowel reinforcement 6 is passed through each of the pipes 11 arranged in a single row in the center, and the dowel reinforcement 6 in the center and the two dowel reinforcements 6 on both sides are stacked. After connection, wall construction is done.

요약하면, 기둥 부분과 마찬가지로 보(G) 내부에 파이프(11)를 시공하고, 이후 파이프(11) 내부에 다월 철근(6)을 삽입하여 층간 연결 시공을 한 후, 벽체 순타 시공을 진행한다.In summary, the pipe 11 is constructed inside the beam G as in the column portion, and after the dowel reinforcement 6 is inserted into the pipe 11 to perform the interlayer connection construction, the wall smooth construction is performed.

이와 같이 하여, 본 발명에 따른 다월 철근 시공방법에 따르면, 지하구조물에서 다월 철근(6)의 이음 개소를 축소할 수 있고, 보 거푸집(2) 해체가 용이해지며, 보 거푸집(2)의 재활용성이 향상되는 효과가 있다. In this way, according to the dowel reinforcement method according to the present invention, it is possible to reduce the joint portion of the dowel reinforcement (6) in the underground structure, easy disassembly of the formwork (2), recycling the formwork (2) There is an effect of improving the sex.

이하, 본 발명에 따른 역타설 시공되는 지하구조물의 다월 철근 시공방법에 의하면, 다음과 같은 효과가 있다.Hereinafter, according to the dowel reinforcement method of the underground structure to be constructed in the reverse casting according to the present invention, the following effects.

1) 다월 철근을 보 및 슬래브의 역타 시공 후 파이프 내부에 삽입하여 일괄적으로 연결 시공하므로, 종래와 같이 1개층 2개소 이음에 비해 이음 개소가 축소 된 1개층 1개소 또는 2개층(그 이상 층 가능) 1개소의 이음 시공이 가능해지며, 이와 같이 지하구조물에서 다월 철근의 이음 개소 축소가 가능해진다. 1) Dowel reinforcing bars and slabs are inserted into the inside of the pipe after the re-installation of the beams and slabs, so that the joints are collectively connected. Possible) Construction of one joint is possible, and in this way, it is possible to reduce the joint position of the dowel rebar in the underground structure.

2) 이음 개소 축소에 따라 커플러의 사용개수를 줄일 수 있고, 보 및 슬래브의 역타 시공 후 일괄 시공으로 작업 효율의 향상, 작업 공정 및 작업 인력의 축소, 비용 및 시간의 절감 등 효과가 있게 된다. 2) The use of couplers can be reduced by reducing the number of joints, and the batch construction after the reverse construction of beams and slabs will improve the work efficiency, reduce the work process and workforce, and reduce costs and time.

3) 보 거푸집 해체 후 다월 철근을 파이프를 통해 일괄 시공함에 따라 보 거푸집에 다월 철근 관통을 위한 구멍 가공이 필요 없게 되고, 따라서 보 거푸집의 재활용성이 향상된다.3) After dismantling the formwork, the dowel reinforcing bars will be installed through the pipe, thus eliminating the need for the hole processing for penetrating the reinforcing bar into the formwork, thus improving the recyclability of the formwork.

4) 보 거푸집 해체 후 다월 철근을 파이프를 통해 일괄 시공함에 따라 보 거푸집 해체시에 다월 철근과의 간섭이 근본적으로 발생하지 않으며, 따라서 보 거푸집의 해체가 용이해진다.4) After dismantling the formwork, the dowel reinforcing bar is installed through the pipe, so the interference with the dowel does not occur when the formwork is dismantled. Therefore, the formwork is easy to dismantle.

Claims (8)

역타 시공되는 지하구조물에서 상하 층간의 연결을 위하여 기둥 및 벽체 부분의 콘크리트 내부에 수직으로 매입 및 층간 연결 설치되는 다월 철근의 시공방법에 있어서,In the construction method of the dowel reinforcing bar is installed in the vertical structure in the concrete of the column and the wall for the connection between the upper and lower floors in the reverse construction, 거푸집을 설치한 후 콘크리트를 타설하여 보 및 슬래브를 역타 시공해 내려가는 과정에서 각 층의 보 거푸집 내부에 다수개의 파이프를 수직으로 고정 설치한 후 콘크리트를 타설하는 단계와;Placing concrete after installing the formwork and fixing a plurality of pipes vertically inside the beam formwork on each floor in the process of laying down the beams and slabs; 콘크리트를 타설한 후 거푸집을 해체하여 보 및 슬래브의 역타 시공이 모두 완료되면 각 층의 보를 상하로 관통하는 상기 파이프의 내부에 다월 철근을 통과시켜 상하 층간을 연결 시공하는 단계와; When the concrete is finished by dismantling the formwork after the concrete is laid, passing the dowel reinforcing bars through the pipes vertically through the beams of each floor to connect the upper and lower floors; 거푸집을 설치하고 콘크리트를 타설하여 기둥 및 벽체를 시공함으로써 시공된 기둥 및 벽체 부분의 콘크리트 내부에 다월 철근을 매입시키는 단계;Installing a formwork and placing concrete to construct pillars and walls to purchase dowel reinforcing bars within the concrete of the constructed pillars and wall portions; 를 포함하는 것을 특징으로 하는 역타설 시공되는 지하구조물의 다월 철근 시공방법.Dowel reinforcement construction method of the underground structure to be constructed in reverse, comprising a. 청구항 1에 있어서,The method according to claim 1, 상기 각 파이프는, 이후 콘크리트 시공되는 보 상측으로 일부가 노출될 수 있도록 상단부가 보 콘크리트 타설면보다 높게 설치되고, 하단부 끝단은 보 거푸집 내부 저면에 밀착되도록 설치되는 것을 특징으로 하는 역타설 시공되는 지하구조물의 다월 철근 시공방법. The pipes, the underground structure to be installed in reverse construction, characterized in that the upper part is installed higher than the beam concrete pour surface so that a portion is exposed to the complementary side of the concrete construction afterwards, and the bottom end is in close contact with the inner bottom surface of the formwork Dowel rebar construction method. 청구항 2에 있어서,The method according to claim 2, 상기 각 파이프의 보 상측으로 노출되는 상단부에 콘크리트 유입을 방지하기 위한 마개가 설치되는 것을 특징으로 하는 역타설 시공되는 지하구조물의 다월 철근 시공방법.Dowel reinforcement construction method of the underground structure to be installed in reverse pouring characterized in that a stopper is installed to prevent the inflow of concrete at the upper end exposed to the complementary side of each pipe. 청구항 1에 있어서, The method according to claim 1, 상기 각 파이프는 보 거푸집 내부에 설치되는 보강철근에 철사로 묶어 고정하거나 용접하여 고정하는 것을 특징으로 하는 역타설 시공되는 지하구조물의 다월 철근 시공방법.Wherein each pipe is a reinforcing bar construction method of reinforcement underground construction, characterized in that the fastening or welding by fixing to the reinforcing steel bar is installed inside the formwork. 청구항 4에 있어서,The method according to claim 4, 상기 보 거푸집 내부에 파이프의 열을 따르면서 파이프와 인접될 수 있게 보강철근을 상, 하 높이에 각각 추가로 설치한 후, 이렇게 설치된 보강철근에 파이프를 철사로 묶어 고정하거나 용접하여 고정하는 것을 특징으로 하는 역타설 시공되 는 지하구조물의 다월 철근 시공방법. After installing the reinforcing bars in the upper and lower heights so as to be adjacent to the pipes while following the row of pipes in the formwork, the pipes are fixed to the reinforcing bars thus installed or fixed by welding. Dowel reinforcement method of underground structures to be constructed in reverse. 청구항 1에 있어서, The method according to claim 1, 상기 파이프의 내부에 다월 철근을 통과시킨 후 파이프의 내부공간에 정착제를 주입하여 파이프와 다월 철근을 일체화시키는 것을 특징으로 하는 역타설 시공되는 지하구조물의 다월 철근 시공방법.Dowel reinforcement construction method of the underground structure to be installed in the reverse casting structure characterized in that the pipe and the dowel reinforcement is integrated by passing the dowel reinforcement inside the pipe and then injecting a fixing agent into the inner space of the pipe. 청구항 6에 있어서,The method according to claim 6, 상기 정착제에 의한 일체성을 향상시키기 위하여 내주면에 요철 구조를 가지는 파이프를 사용하는 것을 특징으로 하는 역타설 시공되는 지하구조물의 다월 철근 시공방법.Dowel reinforcement construction method of the underground structure to be built in reverse casting, characterized in that to use the pipe having an uneven structure on the inner peripheral surface in order to improve the integrity by the fixing agent. 청구항 7에 있어서,The method according to claim 7, 상기 요철 구조는 파이프의 내주면을 나사산 가공하여 형성한 것임을 특징으로 하는 역타설 시공되는 지하구조물의 다월 철근 시공방법. The uneven structure is a dowel reinforcement construction method of the underground structure to be constructed by reverse casting, characterized in that formed by threading the inner peripheral surface of the pipe.
KR1020060084491A 2006-09-04 2006-09-04 Dowel bar construction method for downward construction of underground structures KR100757710B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060084491A KR100757710B1 (en) 2006-09-04 2006-09-04 Dowel bar construction method for downward construction of underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060084491A KR100757710B1 (en) 2006-09-04 2006-09-04 Dowel bar construction method for downward construction of underground structures

Publications (1)

Publication Number Publication Date
KR100757710B1 true KR100757710B1 (en) 2007-09-13

Family

ID=38737402

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060084491A KR100757710B1 (en) 2006-09-04 2006-09-04 Dowel bar construction method for downward construction of underground structures

Country Status (1)

Country Link
KR (1) KR100757710B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107401182A (en) * 2017-08-29 2017-11-28 广州宏途设备工程有限公司 One kind wears dividing wall support changing structure for use and its application method
CN115198806A (en) * 2022-07-18 2022-10-18 中国二十二冶集团有限公司 Underground wall post-cast strip template reinforcing and installing construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4330970A (en) 1979-10-23 1982-05-25 Copreal S.A. Building structure and steel parts for same
JPH04176944A (en) * 1990-11-09 1992-06-24 Nippon Splice Sleeve Kk Precast concrete column member
JPH08135087A (en) * 1994-11-04 1996-05-28 Ohbayashi Corp Precast concrete column member and joint method thereof
JP2000352108A (en) 1999-06-10 2000-12-19 Kajima Corp Precast block construction
KR20010091696A (en) * 2000-03-17 2001-10-23 배종렬 PC member connection method with steel reinforcing connection Sleeve
JP2005139811A (en) 2003-11-10 2005-06-02 Kawada Construction Co Ltd Joining structure of precast concrete member
KR200402363Y1 (en) 2005-09-22 2005-11-29 박무용 Structure for concreting work of column

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4330970A (en) 1979-10-23 1982-05-25 Copreal S.A. Building structure and steel parts for same
JPH04176944A (en) * 1990-11-09 1992-06-24 Nippon Splice Sleeve Kk Precast concrete column member
JPH08135087A (en) * 1994-11-04 1996-05-28 Ohbayashi Corp Precast concrete column member and joint method thereof
JP2000352108A (en) 1999-06-10 2000-12-19 Kajima Corp Precast block construction
KR20010091696A (en) * 2000-03-17 2001-10-23 배종렬 PC member connection method with steel reinforcing connection Sleeve
JP2005139811A (en) 2003-11-10 2005-06-02 Kawada Construction Co Ltd Joining structure of precast concrete member
KR200402363Y1 (en) 2005-09-22 2005-11-29 박무용 Structure for concreting work of column

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107401182A (en) * 2017-08-29 2017-11-28 广州宏途设备工程有限公司 One kind wears dividing wall support changing structure for use and its application method
CN115198806A (en) * 2022-07-18 2022-10-18 中国二十二冶集团有限公司 Underground wall post-cast strip template reinforcing and installing construction method

Similar Documents

Publication Publication Date Title
KR100951097B1 (en) Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR100694503B1 (en) Downward construction system and method for 1-way girder and slab of underground structure
KR100634726B1 (en) Form system for construction of underground slab and method for constructing underground slab and breast wall using the same
KR101903628B1 (en) Precast Double Wall Structure with Enhanced Seismic Performance and Construction method thereof
KR100741431B1 (en) Mold assembly, composite crossbeam and construction method using the same
KR20090094971A (en) Under ground top-down method
KR20120096605A (en) Bracket support type downward construction system and method
CN107859206A (en) Pre-manufactured steel structure overlapped shear wall and its construction method
KR200417438Y1 (en) Bracket structure for girder and slab construction
KR100775767B1 (en) Top-down method using the vertical steel bar for the src column
KR100313720B1 (en) Composite Underground Structure Construction Method
KR101051978B1 (en) Basement structure construction method using PC member
JP2750368B2 (en) Construction method of reactor containment top slab
KR200398231Y1 (en) 1way-supporting bracket for girder and slab construction
KR100757710B1 (en) Dowel bar construction method for downward construction of underground structures
KR101267565B1 (en) Construction method of under-ground core part structure in top-down construction procedure
CN111877626A (en) Overhead laminated slab construction structure and construction method
KR101908943B1 (en) RC WALL STRUCTURE FOR TOP-DOWN AND METHOD FOR CONSTRUCTING THE STRUCTUREa
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
JP6855296B2 (en) Building foundation structure and its construction method
CN214195056U (en) Prefabricated shear wall with assembling holes arranged in staggered mode reserved in assembling mode and assembling structure of prefabricated shear wall
CN113403936A (en) Bracket-free rapid construction method for hollow pier partition plate of bridge
KR200402363Y1 (en) Structure for concreting work of column
KR100679986B1 (en) Structure for plastic slab deck system and Downward construction method using the same
KR102579169B1 (en) Top-down method using suspended rebar

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120904

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20131205

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140904

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20150904

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160905

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170904

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20180905

Year of fee payment: 12