JP2000352108A - Precast block construction - Google Patents

Precast block construction

Info

Publication number
JP2000352108A
JP2000352108A JP11163511A JP16351199A JP2000352108A JP 2000352108 A JP2000352108 A JP 2000352108A JP 11163511 A JP11163511 A JP 11163511A JP 16351199 A JP16351199 A JP 16351199A JP 2000352108 A JP2000352108 A JP 2000352108A
Authority
JP
Japan
Prior art keywords
steel pipe
tubular steel
precast
segments
outer tubular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11163511A
Other languages
Japanese (ja)
Other versions
JP3537706B2 (en
Inventor
Kumiko Suda
久美子 須田
Takahiro Arai
崇裕 新井
Takeyoshi Hishiki
剛啓 日紫喜
Takumi Onabe
卓巳 尾鍋
Hiroshi Shinpo
弘 新保
Seiichiro Takizawa
清一郎 滝沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP16351199A priority Critical patent/JP3537706B2/en
Publication of JP2000352108A publication Critical patent/JP2000352108A/en
Application granted granted Critical
Publication of JP3537706B2 publication Critical patent/JP3537706B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To positively connect segments together, and to enhance the strength of the same, by embedding an external steel pipe in the piling direction, inserting an internal steel pipe into the external steel pipe in the piled segments, and injecting a filler in a gap between the steel pipes and the in internal steel pipe, to thereby connect the segments to each other. SOLUTION: A plurality of precast blocks as segments 2a, 2b,... constituting a structural skeleton are produced, and a plurality of external steel pipes 6 which are each penetrated through the segments in a piling direction to form sleeves are embedded in the segments at suitable intervals. When these segments 2a, 2b,... are sequentially piled up in the construction field to construct the structural skeleton, an internal steel pipe 7 to be a dowel pipe is inserted into each external steel pipe 6 in the piled segments 2a, 2b,.... Further, a filler 11 is injected in a gap between the internal steel pipe 7 and the external steel pipe 6 and in the internal steel pipe 7, to thereby connect the segments 2a, 2b,... to each other by the internal steel pipe 7. Thus, without complicating the structure, shearing transfer can be achieved with a means other than fraction between the segments.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、橋脚などの構造躯
体の構築方法として最適なプレキャストブロック工法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a precast block construction method most suitable as a method for constructing a structural body such as a bridge pier.

【0002】[0002]

【従来の技術】橋梁の橋桁、橋脚や、タンク、サイロお
よび煙突などの構造躯体を構築する工法のひとつにプレ
キャストブロック工法がある。
2. Description of the Related Art A precast block method is one of the methods for constructing a structural body such as a bridge girder, a pier, a tank, a silo, and a chimney.

【0003】このプレキャストブロック工法は、現場で
のコンクリート打設による構造躯体の構築が困難な場合
などに用いられ、構造躯体(例えば橋脚)を分割して、
プレキャストブロックをセグメントとして工場もしく
は、現場付近の製作アードなどで製作しておき、これを
現場に搬入して組み立て、最後にプレストレッシングに
より一体化を図って構築するものである。
[0003] This precast block method is used when it is difficult to construct a structural skeleton by casting concrete on site, for example, by dividing a structural skeleton (for example, a pier).
The precast block is manufactured as a segment at a factory or a production yard near the site, and then carried into the site to assemble and finally integrated by prestressing.

【0004】図25はその一例を示すもので、基礎であ
るフーチング3のみを場所打ちコンクリートまたはプレ
キャストブロックで構築し、その中に端部を固定して建
て込んだPC鋼棒4上に上から工場製作によるプレキャ
ストブロックによるセグメント2a,2b,2c,2
d,2e…をクレーンなどで吊り上げ、順次落とし込ん
で積み重ねる。
[0004] Fig. 25 shows an example of this. Only the footing 3 as a foundation is constructed from cast-in-place concrete or precast block, and a PC steel bar 4 is fixed from above onto a PC steel bar 4 having an end fixed therein. Segments 2a, 2b, 2c, 2 of precast blocks manufactured by factory
are lifted by a crane or the like, dropped and stacked one by one.

【0005】セグメント2a,2b,2c,2d,2e
…間には必要に応じてモルタルやエポキシ樹脂による目
地材5を充填して相互に接合し、目地材5が硬化した時
期にPC鋼棒4を緊張してセグメント2a,2b,2
c,2d,2e…間にプレストレスを導入してこれらを
一体化し橋脚1を構築する。
[0005] Segments 2a, 2b, 2c, 2d, 2e
... Between them, a filler material 5 made of mortar or epoxy resin is filled if necessary and joined together, and when the filler material 5 is hardened, the PC steel rod 4 is tensioned and the segments 2a, 2b, 2
A prestress is introduced between c, 2d, 2e, etc., and these are integrated to construct the pier 1.

【0006】[0006]

【発明が解決しようとする課題】このような従来のプレ
キャストブロック工法は、積み重ねて相互に接合された
複数のセグメント2a,2b,2c,2d,2e…の接
合面には、目地材5が介在するだけであるため、剪断伝
達はセグメント2a,2b,2c,2d,2e…間の摩
擦によっており、構造体全体を見れば耐震の面で強度的
に十分なものとはいえなかった。
In such a conventional precast block construction method, the joint material 5 is interposed at the joining surface of the plurality of segments 2a, 2b, 2c, 2d, 2e,. , The shear transmission is due to the friction between the segments 2a, 2b, 2c, 2d, 2e,..., And the strength of the structure as a whole is not sufficient in terms of earthquake resistance.

【0007】本発明の目的は前記従来例の不都合を解消
し、複数のプレキャストブロックをセグメントとして積
み重ねて構造躯体を構築するプレキャストブロック工法
において、積み重ねたセグメント間の接合を確実にする
とともに、セグメント間の摩擦以外の手段でも剪断伝達
が行われるようにして強度の向上を図り、また、そのた
めに構造が特に複雑になることもないプレキャストブロ
ック工法を提供することにある。
SUMMARY OF THE INVENTION An object of the present invention is to solve the above-mentioned disadvantages of the prior art, and in a precast block construction method in which a plurality of precast blocks are stacked as segments to construct a structural frame, joining between the stacked segments is ensured, Another object of the present invention is to provide a precast block construction method in which the shear is transmitted by means other than friction to improve the strength and the structure is not particularly complicated.

【0008】[0008]

【課題を解決するための手段】本発明は前記目的を達成
するため、第1に、構造躯体を構成するセグメントとし
て複数のプレキャストブロックを製作し、該プレキャス
トブロックを施工現場で順次積み重ね、構造躯体を構築
するブロック工法において、前記プレキャストブロック
には、これを積み重ね方向に貫通させて鞘管となる外筒
鋼管を埋設しておき、積み重ねたプレキャストブロック
の外筒鋼管内にダボ管となる内筒鋼管を挿通し、内筒鋼
管と外筒鋼管との隙間および内筒鋼管内に充填材を注入
し、該内筒鋼管でプレキャストブロックを相互に結合す
ることを要旨とするものである。
According to the present invention, in order to achieve the above object, firstly, a plurality of precast blocks are manufactured as segments constituting a structural frame, and the precast blocks are sequentially stacked at a construction site to form a structural frame. In the block construction method for constructing the precast block, the outer cylinder steel pipe serving as a sheath pipe is buried in the precast block by penetrating the precast block in the stacking direction, and the inner cylinder serving as a dowel pipe in the outer cylinder steel pipe of the stacked precast block. The gist of the present invention is to insert a filler into a gap between an inner tubular steel pipe and an outer tubular steel pipe and to insert a filler into the inner tubular steel pipe, and connect the precast blocks to each other with the inner tubular steel pipe.

【0009】第2に、外筒鋼管は積み重ねる全てのプレ
キャストブロックに設け、全てのプレキャストブロック
の積み重ね終了後に、1本もので構成する内筒鋼管を全
ての外筒鋼管を貫通するように挿入することを要旨とす
るものである。
Second, the outer tubular steel pipes are provided on all the precast blocks to be stacked, and after the completion of the stacking of all the precast blocks, the inner tubular steel pipe constituted by one piece is inserted so as to penetrate all the outer tubular steel pipes. The gist is that.

【0010】第3に、外筒鋼管は積み重ねる全てのプレ
キャストブロックに設け、内筒鋼管を複数の分割管で構
成して、全てのプレキャストブロックの積み重ね終了後
に、または一段ずつプレキャストブロックを積み重ねる
毎に、分割された内筒鋼管を1本ずつ外筒鋼管内に挿入
することを要旨とするものである。
Third, the outer tubular steel pipes are provided on all the precast blocks to be stacked, and the inner tubular steel pipes are composed of a plurality of divided pipes. The gist of the invention is to insert the divided inner tubular steel pipes one by one into the outer tubular steel pipe.

【0011】第4に、外筒鋼管は積み重ねる全てのプレ
キャストブロックに設け、内筒鋼管を複数の分割管で構
成して、一段ずつプレキャストブロックを積み重ねる毎
に、上下のプレキャストブロックの接合箇所に位置させ
て分割された内筒鋼管を1本ずつ外筒鋼管内に挿入し、
上下の内筒鋼管の間には隙間を設けることを要旨とする
ものである。
Fourth, the outer tubular steel pipe is provided on all the precast blocks to be stacked, and the inner tubular steel pipe is constituted by a plurality of divided pipes. Insert the split inner steel pipes one by one into the outer steel pipes,
The gist is to provide a gap between the upper and lower inner tubular steel pipes.

【0012】第5に、構造躯体を構成するセグメントと
して複数のプレキャストブロックを製作し、該プレキャ
ストブロックを施工現場で順次積み重ね、構造躯体を構
築するプレキャストリート)ブロック工法において、前
記プレキャスト)ブロックは、これを貫通して鞘管とな
る外筒鋼管を埋設したものと、この外筒鋼管内に挿入さ
れるダボ管となる内筒鋼管を上下に突出させて貫通させ
たものとで構成し、外筒鋼管を設けたプレキャストブロ
ックと内筒鋼管を設けたプレキャストブロックとを交互
に積み重ね、上下のプレキャストブロックの接合箇所の
外筒鋼管内に内筒鋼管の突出部を挿入して、内筒鋼管と
外筒鋼管との隙間および内筒鋼管内に充填材を注入し、
上下のプレキャストブロックを相互に結合することを要
旨とするものである。
Fifth, a plurality of precast blocks are manufactured as segments constituting a structural frame, and the precast blocks are sequentially stacked at a construction site to construct a structural frame. An outer tubular steel pipe that becomes a sheath pipe through this is buried, and an inner tubular steel pipe that becomes a dowel pipe inserted into this outer tubular steel pipe is formed by vertically projecting and penetrating it. The precast block provided with the tubular steel pipe and the precast block provided with the inner tubular steel pipe are alternately stacked, and the protrusion of the inner tubular steel pipe is inserted into the outer tubular steel pipe at the joint of the upper and lower precast blocks, and the inner tubular steel pipe and Inject the filler into the gap between the outer tube and the inner tube,
The gist is to connect upper and lower precast blocks to each other.

【0013】請求項1記載の本発明によれば、積み重ね
たプレキャストブロックの外筒鋼管内に挿入した内筒鋼
管がダボ管となるから、この内筒鋼管でプレキャストブ
ロックが相互に結合され、プレキャストブロック間の摩
擦だけでなく、内筒鋼管によっても剪断伝達が行われ、
強度が向上する。さらに、内筒鋼管と外筒鋼管との隙間
および内筒鋼管内に充填材を注入することで、より一層
の一体化が図れる。
According to the first aspect of the present invention, since the inner tubular steel pipe inserted into the outer tubular steel pipe of the stacked precast blocks becomes the dowel pipe, the precast blocks are connected to each other by the inner tubular steel pipe, and the precast blocks are joined together. Shear transmission is performed not only by friction between the blocks but also by the inner steel pipe,
Strength is improved. Further, by injecting the filler into the gap between the inner tubular steel pipe and the outer tubular steel pipe and into the inner tubular steel pipe, further integration can be achieved.

【0014】請求項2記載の本発明によれば、前記作用
に加えて、内筒鋼管を1本もので構成することで、該内
筒鋼管を外筒鋼管内に挿入する作業が1回ですみ施工性
がよいだけでなく、内筒鋼管の加工工程も少なくてす
む。
According to the second aspect of the present invention, in addition to the above-described operation, the operation of inserting the inner tubular steel pipe into the outer tubular steel pipe is performed once by configuring the inner tubular steel pipe by one. Not only is the workability good, but the number of processing steps for the inner tube is also small.

【0015】請求項3記載の本発明によれば、請求項1
記載の本発明の作用に加えて、内筒鋼管を分割した短尺
なものとしたから、取扱いが容易となり、外筒鋼管内へ
の挿入のためのセットや挿入が容易になる。また、組み
立てが終了したセグメントから内筒鋼管を順次挿入して
いけるから、1日の工程でセグメントの組み立てを完了
しなくてもすみ、施工性がよい。
According to the third aspect of the present invention, a first aspect is provided.
In addition to the operation of the present invention described above, since the inner tubular steel pipe is divided into a short length, handling becomes easy, and setting and insertion for insertion into the outer tubular steel pipe become easy. Further, since the inner tubular steel pipes can be sequentially inserted from the assembled segments, it is not necessary to complete the assembly of the segments in one day, and the workability is good.

【0016】請求項4記載の本発明によれば、請求項1
記載の本発明の作用に加えて、上下のプレキャストブロ
ックの接合箇所に位置させて分割された内筒鋼管を1本
ずつ外筒鋼管内に挿入し、上下の内筒鋼管の間には隙間
を設けるようにしたから、内筒鋼管のダボ管としての機
能は確保しつつ、隙間を設けることで充填材の充填空間
を大きく確保でき、積み重ねたセグメントの接合強度を
向上できる。
According to the fourth aspect of the present invention, a first aspect is provided.
In addition to the operation of the present invention described above, the divided inner tubular steel pipes positioned at the joints of the upper and lower precast blocks are inserted one by one into the outer tubular steel pipe, and a gap is formed between the upper and lower inner tubular steel pipes. Since the inner tube is provided, the space as the filling space for the filler can be ensured by providing the gap while the function as the dowel tube of the inner tubular steel tube is secured, and the joining strength of the stacked segments can be improved.

【0017】請求項5記載の本発明によれば、外筒鋼管
のみを設けたプレキャストブロックと内筒鋼管のみを設
けたプレキャストブロックとの2種類を用意し、これら
を交互に積み重ねることで、セグメントの積み重ね時に
外筒鋼管内への内筒鋼管の挿入が同時に行えて、セグメ
ントの積み重ね後に内筒鋼管を挿入する作業を別途格別
に行う必要がなく、施工性がよく、作業時間も短縮でき
る。
According to the fifth aspect of the present invention, a precast block provided with only an outer tubular steel pipe and a precast block provided with only an inner tubular steel pipe are prepared, and these are alternately stacked to form a segment. During stacking, the inner tube can be inserted into the outer tube at the same time, and the work of inserting the inner tube after stacking the segments does not need to be performed separately, so that the workability is good and the working time can be shortened.

【0018】[0018]

【発明の実施の形態】以下、図面について本発明の実施
の形態を詳細に説明する。図1は本発明のプレキャスト
ブロック工法で使用するプレキャストブロックによるセ
グメント2a(2b,2c,2d,2e…)の一例を示
す斜視図で、例えば構造躯体として橋脚に使用するもの
として、工場製作により中央の縦方向に空所を設けた直
方体形状に形成し、鞘管となる外筒鋼管6を適宜間隔で
複数個埋設した。この外筒鋼管6はセグメント2a(2
b,2c,2d,2e…)製作時に同時に埋設する。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a perspective view showing an example of a segment 2a (2b, 2c, 2d, 2e...) Formed by a precast block used in the precast block method according to the present invention. Was formed in a rectangular parallelepiped shape having a space in the vertical direction, and a plurality of outer tubular steel pipes 6 serving as sheath tubes were embedded at appropriate intervals. This outer tubular steel pipe 6 has a segment 2a (2
b, 2c, 2d, 2e ...).

【0019】図2は前記外筒鋼管6内に挿入されてダボ
管となる内筒鋼管7を示し、外径を外筒鋼管6の内径よ
り小さく形成したもので、第1実施形態では積み重ねた
複数のセグメント2a(2b,2c,2d,2e…)に
貫通するような長尺な一本もので形成する。
FIG. 2 shows an inner tubular steel pipe 7 which is inserted into the outer tubular steel pipe 6 to be a dowel pipe. The inner diameter of the inner tubular steel pipe 7 is smaller than the inner diameter of the outer tubular steel pipe 6. In the first embodiment, the inner tubular steel pipe 7 is stacked. It is formed of a single long piece penetrating through the plurality of segments 2a (2b, 2c, 2d, 2e ...).

【0020】次にかかる外筒鋼管6と内筒鋼管7を使用
して複数のセグメント2a(2b,2c,2d,2e
…)を積み重ねて構造躯体を構築する方法を図3〜図17
について説明する。図3は、構造躯体として例えば橋脚
1を構築する場合で、図中、17は昇降階段を示し、工法
の基本構成は図25について既に説明したプレキャストブ
ロック工法と同様であり、まず、第1工程として場所打
ちコンクリートまたはプレキャストブロックでフーチン
グ3を構築する。
Next, using the outer tubular steel pipe 6 and the inner tubular steel pipe 7, a plurality of segments 2a (2b, 2c, 2d, 2e) are used.
…)) To build a structural frame by stacking
Will be described. FIG. 3 shows a case in which, for example, a pier 1 is constructed as a structural skeleton. In the figure, reference numeral 17 denotes an ascending and descending stair. The basic configuration of the method is the same as that of the precast block method described above with reference to FIG. Build footing 3 with cast-in-place concrete or precast blocks.

【0021】このフーチング3の上に第1番目の最下段
のセグメント2aをセットするが、該セグメント2aの
据え付けはフーチング3上に打設する現場打ちコンクリ
ートによるコンクリートダボ8による。この第1番目の
最下段のセグメント2aの設置およびコンクリートダボ
8の構築は、吊り具やジャッキを使用して図6に示すよ
うにセグメント2aをフーチング3上方に間隔を存して
セットし、セグメント2aの内部に型枠を組んで、この
型枠内に逆打ちによりコンクリートを打設すれば、図4
に示すように、セグメント2aとフーチング3との間の
隙間およびセグメント2aの下方内部にコンクリートが
充填してコンクリートダボ8が構築される。
A first lowermost segment 2a is set on the footing 3, and the segment 2a is installed by a concrete dowel 8 made of cast-in-place concrete cast on the footing 3. The installation of the first lowermost segment 2a and the construction of the concrete dowel 8 are performed by setting the segment 2a above the footing 3 with a space as shown in FIG. When a formwork is assembled inside 2a and concrete is poured into the formwork by back-hitting, FIG.
As shown in (1), concrete fills the gap between the segment 2a and the footing 3 and the lower inside of the segment 2a to form the concrete dowel 8.

【0022】あるいは、フーチング3に箱抜き3aを設
けた場合は、図5に示すようにこの箱抜き3aの内部に
セグメント2aの下部を挿入してこれを設置し、この状
態で場所打ちコンクリートを箱抜き3aの内部に打設す
れば、セグメント2aの下部が打設したコンクリートに
よるコンクリートダボ8内に埋設された状態でフーチン
グ3の上に設置される。この場合は、図4に示した場合
のような型枠を組む必要がない。
Alternatively, when the box 3a is provided in the footing 3, the lower portion of the segment 2a is inserted into the box 3a as shown in FIG. When the segment 2a is cast into the inside of the box blank 3a, the segment 2a is placed on the footing 3 while being buried in the concrete dowel 8 made of cast concrete. In this case, there is no need to form a mold as in the case shown in FIG.

【0023】このようにして図7に示すようにフーチン
グ3上に形成された打設コンクリートによるコンクリー
トダボ8を介して第1番目の最下段のセグメント2aが
設置される。次に第2工程として必要に応じて図8に示
すようにこのセグメント2aの上面の接合面にエポキシ
樹脂またはモルタルによる接着剤9を塗布する。
In this way, as shown in FIG. 7, the first lowermost segment 2a is installed via the concrete dowel 8 made of cast concrete formed on the footing 3. Next, as a second step, an adhesive 9 made of epoxy resin or mortar is applied to the joining surface on the upper surface of the segment 2a as necessary as shown in FIG.

【0024】次に第3工程として図9に示すように下か
ら2段目の第2番目のセグメント2bを第1番目のセグ
メント2aの上に設置する。設置方法は、例えば第1番
目のセグメント2aをフーチング3上にセットした場合
と同様にして図3にも示すようにクレーン18や吊り具19
を使用する。また、図示は省略するが第1と第1のセグ
メント2a,2bの接合箇所にガイドキーを設けておけ
ば、ガイドキーを合致することで対応する正しい位置で
両セグメント2a,2bを接合できる。
Next, as a third step, as shown in FIG. 9, the second segment 2b of the second stage from the bottom is set on the first segment 2a. The installation method is, for example, similar to the case where the first segment 2a is set on the footing 3, as shown in FIG.
Use Although not shown, if a guide key is provided at the joint between the first and second segments 2a and 2b, the two segments 2a and 2b can be joined at the corresponding correct positions by matching the guide keys.

【0025】次に第4工程として図10に示すように必要
に応じて仮止め用または本緊張用となるPC鋼材10を第
1と第2のセグメント2a,2bとの間に緊張して第1
のセグメント2aに対して第2のセグメント2bを仮止
めする。
Next, as shown in FIG. 10, as a fourth step, a PC steel material 10 for temporary fixing or final tension is tensioned between the first and second segments 2a and 2b as necessary, as shown in FIG. 1
The second segment 2b is temporarily fixed to the segment 2a.

【0026】かかる工程を繰り返して、第5工程として
図11に示すように第3番目以降のセグメント2c,2
d,2e…を上部に順次積み重ねて設置する。この状態
で図12に示すように上下位置のセグメント2a〜2e…
では、それぞれに設けてある外筒鋼管6が連通して一本
の長い孔が形成される。
The above steps are repeated to form a fifth step as shown in FIG.
.. are sequentially stacked on the upper part. In this state, as shown in FIG.
In this case, one long hole is formed by communicating the outer tubular steel pipes 6 provided respectively.

【0027】所定位置までセグメント2a…を積み重ね
たならば、第6工程として図13に示すように外筒鋼管6
による鞘管の内部にダボ管となる内筒鋼管7を上方から
挿入する。この内筒鋼管7は図14に示すように長尺な一
本物で構成してあり、連通する複数の外筒鋼管6への挿
入作業は1回ですむ。
When the segments 2a are stacked up to a predetermined position, as a sixth step, as shown in FIG.
An inner cylindrical steel pipe 7 serving as a dowel pipe is inserted into the inside of the sheath pipe from above. As shown in FIG. 14, the inner tubular steel pipe 7 is formed of a single long piece, and the operation of inserting the plurality of communicating outer tubular steel pipes 6 only once.

【0028】次に第7工程として図15に示すように内筒
鋼管7内にPC鋼材10を挿入し、下端をフーチング3
に、上端を最上段のセグメント2eに定着して緊張し、
プレストレスを導入して積み重ねたセグメント2a〜2
e…を一体化する。このPC鋼材10のフーチング3への
定着は、フーチング3の底部に限定されるものではな
く、後施工できるようフーチング3の側部や上部とする
こともできる。また、このPC鋼材10の挿入は、全ての
セグメント2a…の積み重ねが完了した後ではなく、セ
グメント2a…を1段ずつ積み上げるごとに行ってもよ
い。
Next, as a seventh step, a PC steel material 10 is inserted into the inner tubular steel pipe 7 as shown in FIG.
Then, the upper end is fixed to the uppermost segment 2e and tensed,
Segments 2a-2 stacked by introducing prestress
e ... are integrated. The fixing of the PC steel material 10 to the footing 3 is not limited to the bottom portion of the footing 3 but may be at the side portion or the upper portion of the footing 3 so that post-processing can be performed. Further, the insertion of the PC steel material 10 may be performed not after the completion of the stacking of all the segments 2a but every time the segments 2a are stacked one by one.

【0029】最後に第8工程として図16、図17に示すよ
うにセグメント2a〜2e内に上方もしくは下方の開口
からセメントペーストによる充填材11を注入し、内筒鋼
管7と外筒鋼管6との隙間、および内筒鋼管7の内部に
充填して一体化を図る。
Finally, as an eighth step, as shown in FIGS. 16 and 17, a filler 11 made of cement paste is injected into the segments 2a to 2e from the upper or lower opening, and the inner tubular steel pipe 7 and the outer tubular steel pipe 6 are formed. And the inside of the inner tubular steel pipe 7 to be integrated.

【0030】これにより外筒鋼管6を鞘管としその内部
に挿入した内筒鋼管7がダボ管として機能し、積み重ね
た複数のセグメント2a〜2eが一体化する。そして、
複数のセグメント2a〜2e間には内筒鋼管7がダボ管
とし介在することでセグメント2a〜2e間の剪断伝達
がセグメント2a〜2e同士の摩擦以外の方法でも行え
ることになり強度が向上する。また、この内筒鋼管7は
PC鋼材10のシースとして使用されるから、施工性もよ
くなる。
As a result, the outer tubular steel pipe 6 serves as a sheath pipe, and the inner tubular steel pipe 7 inserted therein functions as a dowel pipe, and the plurality of stacked segments 2a to 2e are integrated. And
Since the inner tubular steel pipe 7 is provided as a dowel pipe between the plurality of segments 2a to 2e, shear transmission between the segments 2a to 2e can be performed by a method other than friction between the segments 2a to 2e, and the strength is improved. Further, since the inner tubular steel pipe 7 is used as a sheath of the PC steel material 10, workability is improved.

【0031】図18は第2実施形態を示し、内筒鋼管7を
長尺な一本物とせずに、長さ方向を複数に分割した分割
管7a,7b,7c,7d…で構成した。これにより、
セグメント2a,2b…を1段ずつ積み重ねる毎に上下
のセグメント2a,2b…の接合箇所に位置させて分割
管7a…による内筒鋼管を1本ずつ挿入することが可能
となる。この場合、複数の分割体7a…は上下に位置す
るものが相互に接合して連続し全体として1本物となる
ような長さとする。
FIG. 18 shows a second embodiment, in which the inner tubular steel pipe 7 is not made into a single long piece, but is constituted by divided pipes 7a, 7b, 7c, 7d,... This allows
Each time the segments 2a, 2b are stacked one by one, it becomes possible to insert the inner tubular steel pipes one by one by placing them at the joint of the upper and lower segments 2a, 2b. In this case, the plurality of divided bodies 7a have a length such that those positioned at the top and bottom are joined to each other to be continuous and one whole as a whole.

【0032】よって、長尺な内筒鋼管7を取り扱わずに
すみ、セグメント2a,2b…へのセットや挿入の作業
が容易になる。また、組み上げが完了したセグメント2
a,2b…から分割管7a,7b…を順次挿入していく
ことができるから、1日のうちの工程で全てのセグメン
ト2a,2b…の積み重ねを完了しなくてもすみ、作業
工程を柔軟に決定できる。
Therefore, it is not necessary to handle the long inner tubular steel pipe 7, and the work of setting and inserting into the segments 2a, 2b... Becomes easy. In addition, the completed segment 2
can be sequentially inserted from a, 2b..., so that it is not necessary to complete the stacking of all the segments 2a, 2b. Can be determined.

【0033】図19、図20は第3実施形態を示し、第2実
施形態と同様に内筒鋼管7を分割管7a、7b,7c,
7d…で構成する場合、各分割管7a…を積み重ねたセ
グメント2a,2b…の少なくとも接合箇所に位置する
ような短尺なものに形成し、積み重ねが完了したセグメ
ント2a,2b…から分割管7a…を順次挿入してい
く。
FIGS. 19 and 20 show a third embodiment. Similar to the second embodiment, the inner tubular steel pipe 7 is divided into divided pipes 7a, 7b, 7c, and 7c.
7d, each divided pipe 7a is formed into a short piece which is located at least at the joint of the stacked segments 2a, 2b, and the divided pipes 7a, 2b,. Are sequentially inserted.

【0034】この場合は、上下位置の分割管7a…相互
間には隙間が生じて分割管7a…は不連続に配設される
が、この隙間は図19に示すような僅かなものであっても
よいが、図20に示すように分割管7a…にはダボ管とし
ての機能を付与させるものとして、図19に示した例の場
合に比較してさらに短尺に形成し、分割管7a…相互の
間の間隔を大きくとることもできる。
In this case, a gap is formed between the divided pipes 7a at the upper and lower positions and the divided pipes 7a are arranged discontinuously, but this gap is small as shown in FIG. However, as shown in FIG. 20, the divided pipes 7a are provided with a function as dowel pipes, and are formed to be shorter than those in the example shown in FIG. The spacing between them can be large.

【0035】そして、いずれの場合も、第2実施形態と
同様、長尺な内筒鋼管7を取り扱わずにすみ、セグメン
ト2a,2b…へのセットや挿入の作業が容易になる。
また、組み上げが完了したセグメント2a,2b…から
分割管7a,7b…を順次挿入していくことができるか
ら、1日のうちの工程で全てのセグメント2a,2b…
の積み重ねを完了しなくてもすみ、作業工程を柔軟に決
定でき、さらに、内筒鋼管7に要する材料を節減でき
る。
In any case, as in the second embodiment, it is not necessary to handle the long inner tubular steel pipe 7, and the work of setting and inserting into the segments 2a, 2b.
.. Can be sequentially inserted from the assembled segments 2a, 2b..., So that all the segments 2a, 2b.
Need not be completed, the working process can be determined flexibly, and the material required for the inner tubular steel pipe 7 can be saved.

【0036】この第3実施形態の場合は前記のように上
下の分割管7a…の間には隙間が生じるから、分割管7
a…をセットするときにこの分割管7a…が下方に落下
する。そこでこれを防止すべく図21に示すように分割管
7a…の下部外周面に突起状のスペーサ12を放射方向に
突設するとともに、中間部の外周面にも同様の形状のス
トッパー13を突設し、一方、外筒鋼管6の内周面には前
記ストッパー13の受け部となる突起14を突設した。
In the case of the third embodiment, as described above, there is a gap between the upper and lower divided pipes 7a.
are set downward, the divided tubes 7a fall downward. In order to prevent this, as shown in FIG. 21, a projecting spacer 12 is radially provided on the outer peripheral surface of the lower part of the divided pipes 7a, and a stopper 13 of the same shape is also projected on the outer peripheral surface of the intermediate portion. On the other hand, a projection 14 serving as a receiving portion for the stopper 13 is provided on the inner peripheral surface of the outer tubular steel pipe 6.

【0037】これにより、分割管7a…を外筒鋼管6の
内部に挿入したとき、スペーサ12が外筒鋼管6の内壁に
圧着し、また、ストッパー13の下部が突起14の上部に当
接することで、分割管7a…が外筒鋼管6の内部の所定
位置に係止され下方に落下することが防止される。
When the divided pipes 7a are inserted into the outer tubular steel pipe 6, the spacer 12 is pressed against the inner wall of the outer tubular steel pipe 6, and the lower part of the stopper 13 contacts the upper part of the projection 14. Are locked at a predetermined position inside the outer tubular steel pipe 6 and are prevented from falling downward.

【0038】また、図22に示すように、内筒鋼管7の周
壁にスリット15による開口を適宜形成することもでき
る。このスリット15は例えば縦長の細長孔状に形成した
ものを適宜間隔で複数設けたもので、これにより、外筒
鋼管6や内筒鋼管7の内部に充填材11を注入したとき
に、この充填材11が外筒鋼管6および内筒鋼管7相互間
をスムーズに流動して充填材11の充填が確実なものとな
る。
Further, as shown in FIG. 22, an opening by a slit 15 can be appropriately formed in the peripheral wall of the inner tubular steel pipe 7. The slit 15 is formed, for example, in the form of a vertically elongated slot with a plurality of slits provided at appropriate intervals, so that when the filler 11 is injected into the outer tubular steel pipe 6 or the inner tubular steel pipe 7, The material 11 flows smoothly between the outer tubular steel pipe 6 and the inner tubular steel pipe 7, and the filling of the filler 11 is ensured.

【0039】図23、図24は第4実施形態を示し、前記し
た第1〜第3実施形態と同様に鞘管となる外筒鋼管6を
適宜間隔で複数個埋設したセグメント2a…と、これと
は別個に外筒鋼管6は埋設せずに、ダボ管となる内筒鋼
管7を埋設したセグメント16a…を使用する。この内筒
鋼管7を埋設したセグメント16aでは、前記内筒鋼管7
は、その上下端部をセグメント16aから上下に突出させ
ておく。
FIGS. 23 and 24 show a fourth embodiment, similar to the first to third embodiments, in which a plurality of outer tubular steel tubes 6 serving as a sheath tube are buried at appropriate intervals. Separately, the outer tubular steel pipe 6 is not buried, but the segments 16a in which the inner tubular steel pipe 7 serving as the dowel pipe is buried are used. In the segment 16a in which the inner tubular steel pipe 7 is embedded, the inner tubular steel pipe 7
Has its upper and lower ends projecting vertically from the segment 16a.

【0040】この場合は、外筒鋼管6を埋設したセグメ
ント2a…と内筒鋼管7を埋設したセグメント16aとを
交互に積み重ねれば、内筒鋼管7を埋設したセグメント
16aから下方に突出する内筒鋼管7が下段の外筒鋼管6
を埋設したセグメント2aの外筒鋼管6内に挿入し、上
方に突出する内筒鋼管7が上段の外筒鋼管6を埋設した
セグメント2bの外筒鋼管6内に挿入する。
In this case, if the segments 2a in which the outer tubular steel pipes 6 are embedded and the segments 16a in which the inner tubular steel pipes 7 are embedded are alternately stacked, the segments in which the inner tubular steel pipes 7 are embedded are obtained.
The inner tubular steel pipe 7 projecting downward from 16a is the lower outer tubular steel pipe 6
Is inserted into the outer tubular steel pipe 6 of the embedded segment 2a, and the inner tubular steel pipe 7 projecting upward is inserted into the outer tubular steel pipe 6 of the segment 2b in which the upper outer tubular steel pipe 6 is embedded.

【0041】よって、外筒鋼管6を埋設したセグメント
2a…と内筒鋼管7を埋設したセグメント16aとを交互
に積み重ねるだけで、積み重ねと同時に外筒鋼管6内に
内筒鋼管7が挿入され、施工性がよく、作業時間も短縮
する。
Therefore, the segments 2a, in which the outer tube 6 is embedded, and the segments 16a, in which the inner tube 7 is embedded, are alternately stacked, and the inner tube 7 is inserted into the outer tube 6 simultaneously with the stacking. Good workability and shortens work time.

【0042】[0042]

【発明の効果】以上述べたように本発明のプレキャスト
ブロック工法は、複数のプレキャストブロックをセグメ
ントとして積み重ねて構造躯体を構築するプレキャスト
ブロック工法において、積み重ねたセグメント間の接合
を内筒鋼管をダボ管として使用したから、接合を容易か
つ確実にするとともに、セグメント間の摩擦以外の手段
でも剪断伝達が行われるようになり強度の向上を図るこ
とができ、また、そのために構造が特に複雑になること
もなく、施工性も向上するものである。
As described above, according to the precast block method of the present invention, in the precast block method in which a plurality of precast blocks are stacked as segments to construct a structural frame, the joint between the stacked segments is formed by using a dowel pipe. Since it is used as a joint, it is easy and reliable to join, and shear transmission is performed by means other than friction between segments, so that strength can be improved, and the structure is particularly complicated because of this. No workability is improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明のプレキャストブロック工法の実施形態
で使用するセグメントの斜視図である。
FIG. 1 is a perspective view of a segment used in an embodiment of a precast block method according to the present invention.

【図2】本発明のプレキャストブロック工法の実施形態
で使用する内筒鋼管の正面図である。
FIG. 2 is a front view of the inner tubular steel pipe used in the embodiment of the precast block method according to the present invention.

【図3】本発明のプレキャストブロック工法の実施形態
を示す全体斜視図である。
FIG. 3 is an overall perspective view showing an embodiment of a precast block method according to the present invention.

【図4】本発明のプレキャストブロック工法の第1実施
形態の第1工程の一例を示す縦断正面図である。
FIG. 4 is a longitudinal sectional front view showing an example of a first step of the first embodiment of the precast block method according to the present invention.

【図5】本発明のプレキャストブロック工法の第1実施
形態の第1工程の他の例を示す縦断正面図である。
FIG. 5 is a longitudinal sectional front view showing another example of the first step of the first embodiment of the precast block method according to the present invention.

【図6】本発明のプレキャストブロック工法の第1実施
形態の第1工程を示す説明図である。
FIG. 6 is an explanatory view showing a first step of the first embodiment of the precast block method according to the present invention.

【図7】本発明のプレキャストブロック工法の第1実施
形態の第1工程のダボ構築後を示す正面図である。
FIG. 7 is a front view of the precast block method according to the first embodiment of the present invention after the dowel is formed in the first step.

【図8】本発明のプレキャストブロック工法の第1実施
形態の第2工程を示す正面面である。
FIG. 8 is a front view showing a second step of the first embodiment of the precast block method according to the present invention.

【図9】本発明のプレキャストブロック工法の第1実施
形態の第3工程を示す正面面である。
FIG. 9 is a front view showing a third step of the first embodiment of the precast block method of the present invention.

【図10】本発明のプレキャストブロック工法の第1実
施形態の第4工程を示す正面面である。
FIG. 10 is a front view showing a fourth step of the first embodiment of the precast block method of the present invention.

【図11】本発明のプレキャストブロック工法の第1実
施形態の第5工程を示す正面面である。
FIG. 11 is a front view showing a fifth step of the first embodiment of the precast block method of the present invention.

【図12】本発明のプレキャストブロック工法の第1実
施形態の第5工程を示す説明面である。
FIG. 12 is an explanatory view showing a fifth step of the first embodiment of the precast block method of the present invention.

【図13】本発明のプレキャストブロック工法の第1実
施形態の第6工程を示す縦断正面面である。
FIG. 13 is a longitudinal sectional front view showing a sixth step of the first embodiment of the precast block method of the present invention.

【図14】本発明のプレキャストブロック工法の第1実
施形態の第6工程を示す要部の縦断正面面である。
FIG. 14 is a vertical sectional front view of a main part showing a sixth step of the first embodiment of the precast block method of the present invention.

【図15】本発明のプレキャストブロック工法の第1実
施形態の第7工程を示す縦断正面面である。
FIG. 15 is a vertical sectional front view showing a seventh step of the first embodiment of the precast block method of the present invention.

【図16】本発明のプレキャストブロック工法の第1実
施形態の第8工程を示す縦断正面面である。
FIG. 16 is a vertical sectional front view showing an eighth step of the first embodiment of the precast block method of the present invention.

【図17】本発明のプレキャストブロック工法の第1実
施形態の第8工程を示す要部の横断平面面である。
FIG. 17 is a cross-sectional plan view of a main part showing an eighth step of the first embodiment of the precast block method of the present invention.

【図18】本発明のプレキャストブロック工法の第2実
施形態の要部を示す縦断正面面である。
FIG. 18 is a longitudinal sectional front view showing a main part of a second embodiment of the precast block method according to the present invention.

【図19】本発明のプレキャストブロック工法の第3実
施形態の要部を示す縦断正面面である。
FIG. 19 is a longitudinal sectional front view showing a main part of a third embodiment of the precast block method according to the present invention.

【図20】本発明のプレキャストブロック工法の第3実
施形態の要部を示す他の例の縦断正面面である。
FIG. 20 is a longitudinal sectional front view of another example showing a main part of the third embodiment of the precast block method of the present invention.

【図21】本発明のプレキャストブロック工法の第3実
施形態の要部を示すさらに他の例の縦断正面面である。
FIG. 21 is a longitudinal sectional front view of still another example showing a main part of the third embodiment of the precast block method of the present invention.

【図22】本発明のプレキャストブロック工法の第1〜
第3実施形態の要部を示す縦断正面面である。
FIG. 22 shows the first to first precast block construction methods of the present invention.
It is a vertical front view showing a main part of the third embodiment.

【図23】本発明のプレキャストブロック工法の第4実
施形態のセグメントの斜視図である。
FIG. 23 is a perspective view of a segment of a fourth embodiment of the precast block method according to the present invention.

【図24】本発明のプレキャストブロック工法の第4実
施形態の要部を示す縦断正面面である。
FIG. 24 is a longitudinal sectional front view showing a main part of a fourth embodiment of the precast block method according to the present invention.

【図25】プレキャストブロック工法を示す縦断正面図
である。
FIG. 25 is a vertical sectional front view showing a precast block method.

【符号の説明】[Explanation of symbols]

1…橋脚 2a,2b,2c,2d,2e… …セグメント 3…フーチング 3a…箱抜き 4…PC鋼棒 5…目地材 6…外筒鋼管 7…内筒鋼管 7a,7b,7c,7d… …分割管 8…コンクリートダボ 9…接着剤 10…PC鋼材 11…充填材 12…スペーサ 13…ストッパー 14…突起 15…スリット 16a…セグメント 17…昇降階段 18…クレーン 19…吊り具 DESCRIPTION OF SYMBOLS 1 ... Bridge pier 2a, 2b, 2c, 2d, 2e ... Segment 3 ... Footing 3a ... Box removal 4 ... PC steel bar 5 ... Joint material 6 ... Outer tube steel tube 7 ... Inner tube steel tube 7a, 7b, 7c, 7d ... Split pipe 8 Concrete dowel 9 Adhesive 10 PC steel 11 Filler 12 Spacer 13 Stopper 14 Protrusion 15 Slit 16a Segment 17 Lifting stairs 18 Crane 19 Hanging tool

───────────────────────────────────────────────────── フロントページの続き (72)発明者 日紫喜 剛啓 東京都調布市飛田給二丁目19番1号 鹿島 建設株式会社技術研究所内 (72)発明者 尾鍋 卓巳 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 (72)発明者 新保 弘 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 (72)発明者 滝沢 清一郎 東京都港区元赤坂一丁目2番7号 鹿島建 設株式会社内 Fターム(参考) 2D059 AA03 AA05 CC03 GG55  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Takehiro Nishiko 2-19-1, Tobita-Shi, Chofu-shi, Tokyo Kashima Construction Co., Ltd. (72) Inventor Takumi Onabe 1-2-1, Moto-Akasaka, Minato-ku, Tokyo No. 7 Inside Kashima Construction Co., Ltd. (72) Hiroshi Shinbo Inventor 1-2-7 Moto Akasaka, Minato-ku, Tokyo Kashima Construction Co., Ltd. (72) Seiichiro Takizawa 1-2-2 Moto-Akasaka, Minato-ku, Tokyo No. 7 F-term in Kashima Construction Co., Ltd. (reference) 2D059 AA03 AA05 CC03 GG55

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 構造躯体を構成するセグメントとして複
数のプレキャストブロックを製作し、該プレキャストブ
ロックを施工現場で順次積み重ね、構造躯体を構築する
ブロック工法において、前記プレキャストブロックに
は、これを積み重ね方向に貫通させて鞘管となる外筒鋼
管を埋設しておき、積み重ねたプレキャストブロックの
外筒鋼管内にダボ管となる内筒鋼管を挿通し、内筒鋼管
と外筒鋼管との隙間および内筒鋼管内に充填材を注入
し、該内筒鋼管でプレキャストブロックを相互に結合す
ることを特徴としたプレキャストブロック工法。
1. A block construction method for manufacturing a plurality of precast blocks as segments constituting a structural skeleton, sequentially stacking the precast blocks at a construction site, and constructing a structural skeleton. The outer tubular steel pipe that becomes the sheath pipe by being penetrated is buried, and the inner tubular steel pipe that becomes the dowel pipe is inserted into the outer tubular steel pipe of the stacked precast block, and the gap between the inner tubular steel pipe and the outer tubular steel pipe and the inner pipe A precast block construction method comprising injecting a filler into a steel pipe and connecting the precast blocks to each other with the inner cylindrical steel pipe.
【請求項2】 外筒鋼管は積み重ねる全てのプレキャス
トブロックに設け、全てのプレキャストブロックの積み
重ね終了後に、1本もので構成する内筒鋼管を全ての外
筒鋼管を貫通するように挿入する請求項1記載のプレキ
ャストブロック工法。
2. An outer tubular steel pipe is provided on all the precast blocks to be stacked, and after completion of stacking of all the precast blocks, an inner tubular steel pipe constituted by one piece is inserted so as to penetrate all the outer tubular steel pipes. 1. The precast block method according to 1.
【請求項3】 外筒鋼管は積み重ねる全てのプレキャス
トブロックに設け、内筒鋼管を複数の分割管で構成し
て、全てのプレキャストブロックの積み重ね終了後に、
または一段ずつプレキャストブロックを積み重ねる毎
に、分割された内筒鋼管を1本ずつ外筒鋼管内に挿入す
る請求項1記載のプレキャストブロック工法。
3. The outer tubular steel pipe is provided on all the precast blocks to be stacked, and the inner tubular steel pipe is constituted by a plurality of divided pipes, and after all the precast blocks have been stacked,
2. The precast block method according to claim 1, wherein each time the precast blocks are stacked one by one, the divided inner tubular steel pipes are inserted one by one into the outer tubular steel pipe.
【請求項4】 外筒鋼管は積み重ねる全てのプレキャス
トブロックに設け、内筒鋼管を複数の分割管で構成し
て、一段ずつプレキャストブロックを積み重ねる毎に、
上下のプレキャストブロックの接合箇所に位置させて分
割された内筒鋼管を1本ずつ外筒鋼管内に挿入し、上下
の内筒鋼管の間には隙間を設ける請求項1記載のプレキ
ャストブロック工法。
4. The outer tubular steel pipe is provided on all the precast blocks to be stacked, and the inner tubular steel pipe is constituted by a plurality of divided pipes. Each time the precast blocks are stacked one by one,
The precast block construction method according to claim 1, wherein the divided inner cylindrical steel pipes positioned at the joints of the upper and lower precast blocks are inserted one by one into the outer cylindrical steel pipe, and a gap is provided between the upper and lower inner cylindrical steel pipes.
【請求項5】 構造躯体を構成するセグメントとして複
数のプレキャストブロックを製作し、該プレキャストブ
ロックを施工現場で順次積み重ね、構造躯体を構築する
プレキャストブロック工法において、前記プレキャスト
ブロックは、これを貫通して鞘管となる外筒鋼管を埋設
したものと、この外筒鋼管内に挿入されるダボ管となる
内筒鋼管を上下に突出させて貫通させたものとで構成
し、外筒鋼管を設けたプレキャストブロックと内筒鋼管
を設けたプレキャストブロックとを交互に積み重ね、上
下のプレキャストブロックの接合箇所の外筒鋼管内に内
筒鋼管の突出部を挿入して、内筒鋼管と外筒鋼管との隙
間および内筒鋼管内に充填材を注入し、上下のプレキャ
ストブロックを相互に結合することを特徴としたプレキ
ャストブロック工法。
5. A precast block method for producing a plurality of precast blocks as segments constituting a structural frame, sequentially stacking the precast blocks at a construction site, and constructing a structural frame, wherein the precast block penetrates through the precast blocks. An outer tubular steel pipe was provided in which an outer tubular steel pipe serving as a sheath pipe was buried, and an inner tubular steel pipe serving as a dowel pipe inserted into the outer tubular steel pipe was vertically projected and penetrated. The precast block and the precast block provided with the inner tubular steel pipe are alternately stacked, and the protrusion of the inner tubular steel pipe is inserted into the outer tubular steel pipe at the joint of the upper and lower precast blocks. A precast block method characterized by injecting a filler into the gap and the inner tubular steel pipe, and connecting the upper and lower precast blocks to each other.
JP16351199A 1999-06-10 1999-06-10 Precast block method Expired - Fee Related JP3537706B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16351199A JP3537706B2 (en) 1999-06-10 1999-06-10 Precast block method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16351199A JP3537706B2 (en) 1999-06-10 1999-06-10 Precast block method

Publications (2)

Publication Number Publication Date
JP2000352108A true JP2000352108A (en) 2000-12-19
JP3537706B2 JP3537706B2 (en) 2004-06-14

Family

ID=15775263

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16351199A Expired - Fee Related JP3537706B2 (en) 1999-06-10 1999-06-10 Precast block method

Country Status (1)

Country Link
JP (1) JP3537706B2 (en)

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100549649B1 (en) * 2002-11-28 2006-02-08 동양종합건업 주식회사 Precast Tall Pier for Bridge
WO2006073319A2 (en) * 2005-01-06 2006-07-13 Crisologo Ferdinand D Precast concrete wall form block
KR100625782B1 (en) * 2004-04-06 2006-09-20 정재용 Pier Structure having Precast Concrete Form and Constructing Method therefor
KR100704874B1 (en) 2005-12-15 2007-04-09 주식회사 포스코건설 Structures of prefabricated concrete pier strengthened in shear by steel pipe
KR100738999B1 (en) * 2006-06-15 2007-07-25 (주)대우건설 Precast concrete segment having connecting structure using steel duct, and connecting structure thereof
KR100757710B1 (en) 2006-09-04 2007-09-13 박무용 Dowel bar construction method for downward construction of underground structures
WO2007117116A2 (en) * 2006-04-11 2007-10-18 Jung Byung Noeh Steel house welding join multi panel bolting method
WO2008007863A1 (en) * 2006-07-10 2008-01-17 Daewoo Engineering & Construction Co., Ltd Method for constructing precast concrete pier segment having connecting structure using steel duct
KR100860591B1 (en) 2007-06-19 2008-09-26 삼성물산 주식회사 Vertical structure building method using precast concreat block
KR100862005B1 (en) 2007-07-16 2008-10-07 아주대학교산학협력단 Manufacturing method of segmental internally confined hollow concrete filled tube
KR100868557B1 (en) 2007-08-13 2008-11-13 삼성물산 주식회사 Temporary system for vertical structure using precast concreat block and vertical structure building method using precat concreat
JP2011080240A (en) * 2009-10-06 2011-04-21 Jr Soken Engineering:Kk Concrete structure and construction method for the same
JP2015040440A (en) * 2013-08-22 2015-03-02 Jfeエンジニアリング株式会社 Dam body
JP2015040441A (en) * 2013-08-22 2015-03-02 Jfeエンジニアリング株式会社 Foundation structure
CN104790291A (en) * 2015-04-22 2015-07-22 上海市城市建设设计研究总院 Prefabricated type bridge pier column and connecting method thereof
JP2016156233A (en) * 2015-02-26 2016-09-01 新日鐵住金株式会社 Steel pipe joint structure and concrete construction reinforcement structure
CN108360370A (en) * 2018-05-11 2018-08-03 重庆大学 A kind of prefabricated steel tube confinement reinforced concrete bridge pier and cushion cap connecting node
CN108505406A (en) * 2018-05-18 2018-09-07 中铁二院工程集团有限责任公司 A kind of full-prefabricated assembled concrete shipping suspension type monorail structure
CN109137721A (en) * 2018-09-17 2019-01-04 中国二十冶集团有限公司 A kind of prefabricated assembled suspension bridge bridge pier
KR101954403B1 (en) 2017-08-28 2019-03-05 중앙대학교 산학협력단 Construction method of precast concrete column
KR20190023352A (en) * 2017-08-28 2019-03-08 중앙대학교 산학협력단 Construction method of precast concrete column
CN110468691A (en) * 2019-07-23 2019-11-19 北京工业大学 Replaceable assembly concrete is anti-after a kind of calamity waves bridge pier system
JP2021507148A (en) * 2017-12-16 2021-02-22 エヌエックスティ アイピー プロプライエタリー リミテッドNxt Ip Pty Ltd Building system
CN112609565A (en) * 2021-01-13 2021-04-06 安徽六安公路桥梁工程有限公司 Steel pipe concrete prefabricated bridge pier
CN113106848A (en) * 2020-01-10 2021-07-13 中国国家铁路集团有限公司 Steel bar sleeve connecting structure, segment prefabricated assembly type pier and construction method
KR102385958B1 (en) * 2021-11-15 2022-04-22 주식회사 케이씨산업 Bridge pier and the construction method using maintained concrete mold

Cited By (34)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100549649B1 (en) * 2002-11-28 2006-02-08 동양종합건업 주식회사 Precast Tall Pier for Bridge
KR100625782B1 (en) * 2004-04-06 2006-09-20 정재용 Pier Structure having Precast Concrete Form and Constructing Method therefor
WO2006073319A2 (en) * 2005-01-06 2006-07-13 Crisologo Ferdinand D Precast concrete wall form block
WO2006073319A3 (en) * 2005-01-06 2006-10-19 Ferdinand D Crisologo Precast concrete wall form block
KR100704874B1 (en) 2005-12-15 2007-04-09 주식회사 포스코건설 Structures of prefabricated concrete pier strengthened in shear by steel pipe
WO2007117116A3 (en) * 2006-04-11 2007-12-06 Jung Byung Noeh Steel house welding join multi panel bolting method
WO2007117116A2 (en) * 2006-04-11 2007-10-18 Jung Byung Noeh Steel house welding join multi panel bolting method
KR100738999B1 (en) * 2006-06-15 2007-07-25 (주)대우건설 Precast concrete segment having connecting structure using steel duct, and connecting structure thereof
WO2007145477A1 (en) * 2006-06-15 2007-12-21 Daewoo Engineering & Construction Co., Ltd Precast concrete segment having connecting structure using steel duct, and connecting structure thereof
WO2008007863A1 (en) * 2006-07-10 2008-01-17 Daewoo Engineering & Construction Co., Ltd Method for constructing precast concrete pier segment having connecting structure using steel duct
CN101356317B (en) * 2006-07-10 2011-01-19 株式会社大宇建设 Method for constructing precast concrete pier segment having connecting structure using steel duct
KR100757710B1 (en) 2006-09-04 2007-09-13 박무용 Dowel bar construction method for downward construction of underground structures
KR100860591B1 (en) 2007-06-19 2008-09-26 삼성물산 주식회사 Vertical structure building method using precast concreat block
KR100862005B1 (en) 2007-07-16 2008-10-07 아주대학교산학협력단 Manufacturing method of segmental internally confined hollow concrete filled tube
KR100868557B1 (en) 2007-08-13 2008-11-13 삼성물산 주식회사 Temporary system for vertical structure using precast concreat block and vertical structure building method using precat concreat
JP2011080240A (en) * 2009-10-06 2011-04-21 Jr Soken Engineering:Kk Concrete structure and construction method for the same
JP2015040440A (en) * 2013-08-22 2015-03-02 Jfeエンジニアリング株式会社 Dam body
JP2015040441A (en) * 2013-08-22 2015-03-02 Jfeエンジニアリング株式会社 Foundation structure
JP2016156233A (en) * 2015-02-26 2016-09-01 新日鐵住金株式会社 Steel pipe joint structure and concrete construction reinforcement structure
CN104790291A (en) * 2015-04-22 2015-07-22 上海市城市建设设计研究总院 Prefabricated type bridge pier column and connecting method thereof
KR101954403B1 (en) 2017-08-28 2019-03-05 중앙대학교 산학협력단 Construction method of precast concrete column
KR20190023352A (en) * 2017-08-28 2019-03-08 중앙대학교 산학협력단 Construction method of precast concrete column
KR101980656B1 (en) 2017-08-28 2019-05-22 중앙대학교 산학협력단 Construction method of precast concrete column
JP2021507148A (en) * 2017-12-16 2021-02-22 エヌエックスティ アイピー プロプライエタリー リミテッドNxt Ip Pty Ltd Building system
JP7325835B2 (en) 2017-12-16 2023-08-15 エヌエックスティ ビルディング システム プロプライエタリー リミテッド building system
CN108360370A (en) * 2018-05-11 2018-08-03 重庆大学 A kind of prefabricated steel tube confinement reinforced concrete bridge pier and cushion cap connecting node
CN108360370B (en) * 2018-05-11 2019-11-12 重庆大学 A kind of prefabricated steel tube confinement reinforced concrete bridge pier and cushion cap connecting node
CN108505406A (en) * 2018-05-18 2018-09-07 中铁二院工程集团有限责任公司 A kind of full-prefabricated assembled concrete shipping suspension type monorail structure
CN109137721A (en) * 2018-09-17 2019-01-04 中国二十冶集团有限公司 A kind of prefabricated assembled suspension bridge bridge pier
CN110468691A (en) * 2019-07-23 2019-11-19 北京工业大学 Replaceable assembly concrete is anti-after a kind of calamity waves bridge pier system
CN110468691B (en) * 2019-07-23 2021-02-26 北京工业大学 Replaceable assembled concrete anti-swing pier system after disaster
CN113106848A (en) * 2020-01-10 2021-07-13 中国国家铁路集团有限公司 Steel bar sleeve connecting structure, segment prefabricated assembly type pier and construction method
CN112609565A (en) * 2021-01-13 2021-04-06 安徽六安公路桥梁工程有限公司 Steel pipe concrete prefabricated bridge pier
KR102385958B1 (en) * 2021-11-15 2022-04-22 주식회사 케이씨산업 Bridge pier and the construction method using maintained concrete mold

Also Published As

Publication number Publication date
JP3537706B2 (en) 2004-06-14

Similar Documents

Publication Publication Date Title
JP3537706B2 (en) Precast block method
KR101478131B1 (en) Construction Method of Precast Pier
JP4675950B2 (en) Precast concrete column and its joining method
KR100396583B1 (en) The construction method of rc structure using improved precast wall members
JP2896988B2 (en) Construction method of prestressed masonry structure
JP2831934B2 (en) How to build substructure
JP2003328369A (en) Precast concrete member, caisson construction method using the same, and tunnel construction method
CN211229041U (en) Assembled concrete structure wall-column concrete filled steel tube key connecting structure
JP2017095915A (en) Junction structure between column-beam joint part and column, rigid-frame viaduct, construction method for junction structure between column-beam joint part and column, and precast concrete member
JPH0315605Y2 (en)
JPH0314483Y2 (en)
JP2019100087A (en) Pile head isolation structure and construction method thereof
KR100517373B1 (en) Wall Structure Using Tapered Hollow Precast Concrete Pannel and Constructing Method thereof
JPH08100432A (en) Footing device
JPH11181807A (en) Construction method for underground story
JPH038954A (en) Concrete panel for wall, and constructing method for wall using concrete panel
JP2922731B2 (en) How to connect slabs and concrete columns
JP2579944Y2 (en) Load-bearing wall assembly structure
JPH07268867A (en) Cast-in-place concrete pile and method for fabricating the same
KR200317090Y1 (en) Tapered Hollow Precast Concrete Pannel
JP2023103756A (en) Base structure of concrete block structure
JP5889050B2 (en) Main column made of reinforced concrete
JPH05112948A (en) Permanent form and foundation execution method using it
JPH11293764A (en) Precast embedded formwork for column
JPS6311734A (en) Construction method for bonding pillar and concrete slab

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040316

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040317

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 3537706

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130326

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130326

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160326

Year of fee payment: 12

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees