JP2831934B2 - How to build substructure - Google Patents

How to build substructure

Info

Publication number
JP2831934B2
JP2831934B2 JP13595994A JP13595994A JP2831934B2 JP 2831934 B2 JP2831934 B2 JP 2831934B2 JP 13595994 A JP13595994 A JP 13595994A JP 13595994 A JP13595994 A JP 13595994A JP 2831934 B2 JP2831934 B2 JP 2831934B2
Authority
JP
Japan
Prior art keywords
steel
block
insertion hole
precast
precast block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP13595994A
Other languages
Japanese (ja)
Other versions
JPH084031A (en
Inventor
宗人 阿部
将博 中井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PII ESU KK
Original Assignee
PII ESU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PII ESU KK filed Critical PII ESU KK
Priority to JP13595994A priority Critical patent/JP2831934B2/en
Publication of JPH084031A publication Critical patent/JPH084031A/en
Application granted granted Critical
Publication of JP2831934B2 publication Critical patent/JP2831934B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、例えば橋脚等のいわゆ
る下部構造物を構築する方法に関し、さらに詳しくは、
プレキャストコンクリートブロック(以下プレキャスト
ブロックという)を用いてプレストレスト鉄筋コンクリ
ート(PRC)構造で橋脚等を施工する構築方法に関す
る。この技術は高さ30〜50m程度の橋脚等の施工に
好適に利用することができる。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a so-called substructure such as a pier,
The present invention relates to a construction method for constructing a pier or the like in a prestressed reinforced concrete (PRC) structure using a precast concrete block (hereinafter, referred to as a precast block). This technology can be suitably used for construction of a pier or the like having a height of about 30 to 50 m.

【0002】[0002]

【従来の技術】図14、15に本発明が適用されるコン
クリート橋100の1例を示した。基礎杭101等の上
に構築されたフーチング102から立ち上がる橋脚10
3からなるいわゆる下部構造の上部に橋体104(上部
構造)が支持されている。図15は下部構造の断面図
(図14のA−A矢視断面図)を示している。
2. Description of the Related Art FIGS. 14 and 15 show an example of a concrete bridge 100 to which the present invention is applied. A pier 10 rising from a footing 102 constructed on a foundation pile 101 or the like.
The bridge body 104 (upper structure) is supported on the upper part of the so-called lower structure composed of 3. FIG. 15 is a sectional view of the lower structure (a sectional view taken along the line AA in FIG. 14).

【0003】従来、橋脚等のような、構造物を構築する
場合、場所打ちコンクリート工法によるRC(鉄筋コン
クリート)構造の場合は、一般に全型枠を取付けて施工
する全型枠工法又はスライド式型枠を用いて施工するス
ライデング工法によって施工されていた。また、プレキ
ャストブロックを用いるRC構造の構築工法やPC(プ
レストレストコンクリート)構造の構築方法も知られて
おり、場所打ちコンクリート工法に比し、現場で型枠を
必要とせず、品質の優れたブロックを使用することがで
きる利点がある。
Conventionally, in the case of constructing a structure such as a pier, etc., in the case of an RC (reinforced concrete) structure by a cast-in-place concrete method, generally, a full formwork method in which all formworks are attached and constructed or a sliding formwork is used. It was constructed by a sliding method of construction. Construction methods of RC structures using precast blocks and construction methods of PC (prestressed concrete) structures are also known. Compared with cast-in-place concrete methods, high-quality blocks that do not require formwork on site are required. There are advantages that can be used.

【0004】プレキャストブロックを用いるRC構造で
は、各プレキャストブロックにブロック長さにほぼ等し
い鉄筋を埋め込んでおき、プレキャストブロック1段ご
とにこの鉄筋を結合しながら順次積み上げてゆくもので
ある。従って、継手の数が多く、煩雑となり、工期が長
くなる等の問題がある。また、プレキャストブロックの
接合面に継手があるので、継手の剪断に対して補強を要
し、剪断キー等を設ける必要がある。工期短縮のため
に、ブロックを多段に積重し、多段に亘る通し鉄筋を挿
通して結合する技術も、例えば、『土木施工』8巻8号
25〜32頁『東北本線第8馬淵川橋りょう工事におけ
るRCプレキャストブロック式橋脚の施工』に紹介され
ているが、依然としてRC構造であるため、多数の鉄筋
を必要とし根本的な対策になっていない。
In the RC structure using a precast block, reinforcing bars having a length substantially equal to the block length are embedded in each precast block, and the reinforcing bars are sequentially stacked while being connected to each precast block. Therefore, there are problems that the number of joints is large, complicated, and the construction period becomes long. In addition, since there is a joint on the joint surface of the precast block, it is necessary to provide reinforcement for shearing of the joint and to provide a shear key or the like. In order to shorten the construction period, the technique of stacking blocks in multiple stages and inserting and connecting through-the-bar reinforcing bars in multiple stages is also described in, for example, "Civil Engineering Construction" Vol. 8, No. 8, pp. 25-32, "Tohoku Main Line No. 8 Mabuchigawa Bridge Ryo" Construction of RC Precast Block Type Bridge Pier in Construction ", but because it is still RC structure, it requires many reinforcing bars and is not a fundamental measure.

【0005】一方、プレキャストブロックを用いてPC
(プレストレストコンクリート)構造の橋脚等を構築す
る技術もあるが、この場合は、プレキャストブロックの
相互の接合面にフルプレストレスが作用し、プレキャス
トブロックの接合面に凹凸があると、凸部に大きな局部
応力が生じ縦ひび割れ等が発生する問題がある。従っ
て、プレキャストブロックの接合面は高い平坦精度が要
求され、例えば鏡面仕上げを行って施工するか、又はマ
ッチキャストでプレキャストブロックを製作しなければ
ならない。
On the other hand, using a precast block
(Prestressed concrete) There is also a technology for constructing bridge piers and the like, but in this case, full prestress acts on the mutual joining surfaces of the precast blocks, and if the joining surfaces of the precast blocks have irregularities, large local There is a problem that stress is generated and vertical cracks and the like occur. Therefore, the joining surface of the precast block is required to have a high flatness accuracy. For example, the precast block must be mirror-finished or manufactured by match casting.

【0006】プレキャストブロックを用い、フーチング
に定着したPCストランドをJ字状に配設した施工例が
『PCIジャーナル:1985年9月』に記載されてい
る。また、『W.ポルドニー、J.ミューラー著:PC
橋の設計と施工:九州橋梁工学研究会訳、1992.
2.20発行』には、プレキャスト橋脚として杭、杭キ
ャップ、躯体上方部及びピアキャップがプレキャストセ
グメントであり、躯体の下部とフーチング上部が場所打
ちされ、PCストランドをプレキャスト躯体を通ってU
字状に場所打ちフーチングに挿通した例が記載されてい
る。これらはいずれもPC構造である。
A construction example in which PC strands fixed to a footing are arranged in a J shape using a precast block is described in "PCI Journal: September 1985". Also, "W. Poldonie, J.M. By Mueller: PC
Bridge Design and Construction: Translated by Kyushu Bridge Engineering Society, 1992.
2.20 issuance ”, the precast pier includes a pile, a pile cap, an upper part of the skeleton and a pier cap as precast segments. The lower part of the skeleton and the upper part of the footing are cast in place.
An example is described in which the device is inserted into a character-shaped place-in-place footing. These are all PC structures.

【0007】[0007]

【発明が解決しようとする課題】本発明は、プレキャス
トブロックを用いて橋脚等を構築する場合の上記問題点
を解決し、短工期で構造物の構築ができる構築方法を提
供しようとするものである。すなわち、構造物をプレキ
ャストブロックを用いたプレストレスト鉄筋コンクリー
ト(PRC)構造とし、その新規な構築方法を提供する
ことを目的とするものである。
SUMMARY OF THE INVENTION The present invention solves the above-mentioned problems in the case of constructing a pier or the like using a precast block, and provides a construction method capable of constructing a structure in a short construction period. is there. That is, an object of the present invention is to provide a novel construction method of a prestressed reinforced concrete (PRC) structure using a precast block.

【0008】本発明の課題は次のとおりである。 (a)プレキャストブロック製作時に鉄筋継手をプレキ
ャストブロック内にあらかじめ設けておく煩雑さをなく
する。 (b)鉄筋継手の数を可及的に少くなくする。 (c)プレキャストブロックの接合面に鉄筋継手が集中
しないようにする。
The objects of the present invention are as follows. (A) Eliminate the trouble of providing a reinforcing joint in the precast block in advance when manufacturing the precast block. (B) Reducing the number of rebar joints as much as possible. (C) Prevent the rebar joint from concentrating on the joint surface of the precast block.

【0009】(d)プレキャストブロックの接合面の製
作精度の高度化(鏡面仕上げなど)を不必要にする。 (e)設計上の接合面での剪断の問題を解消する。 (f)鋼材総量を減らし、かつ、経済性、施工性を高め
る。
(D) It is not necessary to improve the production accuracy (mirror finish or the like) of the joint surface of the precast block. (E) Eliminates the problem of shear at the joint surface in design. (F) Reduce the total amount of steel materials, and increase the economy and workability.

【0010】[0010]

【課題を解決するための手段】本発明は、上記問題点を
解決するために、次の技術手段を講じたことを特徴とす
る。すなわち、本発明は、フーチング内にU字状さや管
を埋設し、主鉄筋挿通孔及びPC鋼より線挿通孔を備え
たプレキャストブロックを前記フーチング上に積重し、
積重したブロックの主鉄筋挿通孔に通し主鉄筋を上方か
ら挿通すると共に、前記PC鋼より線挿通孔及び前記U
字状さや管を通ってPC鋼より線を上方から挿通し、該
PC鋼より線を最上ブロック上端にて緊張して前記積重
したブロックに軽度の縦方向プレストレスを導入した
後、主鉄筋挿通孔及びPC鋼より線挿通孔にグラウトを
注入してブロックと付着させPRC構造物を形成するこ
とを特徴とする下部構造物の構築方法である。
The present invention is characterized by taking the following technical means in order to solve the above problems. That is, the present invention embeds a U-shaped sheath tube in the footing, stacks a precast block having a main reinforcing bar insertion hole and a PC steel wire insertion hole on the footing,
The main rebar is inserted from above through the main rebar insertion holes of the stacked blocks, and the PC stranded wire insertion hole and the U
After penetrating the PC steel stranded wire from above through the shape and tube, and tensioning the PC steel stranded wire at the upper end of the uppermost block to introduce a slight longitudinal prestress into the stacked blocks, A method for constructing a substructure, comprising: injecting grout into an insertion hole and a PC steel wire insertion hole and attaching the grout to a block to form a PRC structure.

【0011】上記方法において、前記通し鉄筋は長尺鉄
筋を用いると共に、継手位置を互いに異なる高さ位置に
設けて鉄筋の弱点を分散させ、地震荷重に対して安全性
を高めるようにすると好適である。本発明において、
「軽度の」プレストレスとは、コンクリートに導入する
プレストレスの値を通常のフルストレスの値より低いレ
ベルの値とすることを言う。
In the above method, it is preferable that a long reinforcing bar is used as the through reinforcing bar, and that joints are provided at different heights to disperse weak points of the reinforcing bar, thereby enhancing safety against an earthquake load. is there. In the present invention,
"Mild" pre-stress refers to a level of pre-stress introduced into concrete at a lower level than normal full stress.

【0012】例えば、プレストレス導入量を10〜15
kgf/cm2 とする。
For example, the prestress introduction amount is set to 10 to 15
kgf / cm 2 .

【0013】[0013]

【作用】本発明は上記構成により次の作用を生ずる。 (イ)本発明に係る構造物は、PRC構造である。この
構造物の力学的構成は、主は鉄筋による補強であり、P
C鋼より線によるものは従である。PC鋼より線の緊張
によるプレストレス導入量は「軽度の」小さい値とす
る。例えば、10〜15kgf/cm2 とした。これは
プレキャストブロック相互間の接着剤の接着効果等を十
分なものとするものである。本発明では、PRC構造と
し、PC鋼材の緊張により導入するプレストレスは小さ
い値とするため、プレキャストブロックは接合面の高い
平坦精度が要求されない。従って、プレキャストブロッ
ク接合面を鏡面仕上処理するとか、接合面をマッチキャ
ストとすることを要しない。このことにより、本発明で
は、プレキャストブロックを単体製作とすることが可能
で、製作順序を考慮する必要がないから、プレキャスト
ブロックの製造工程が簡易化される。
According to the present invention, the following effects are produced by the above configuration. (A) The structure according to the present invention has a PRC structure. The mechanical structure of this structure is mainly reinforced by rebar,
The one with C steel strand is secondary. The amount of prestress introduced due to the tension of the PC steel strand is a "mild" small value. For example, it was set to 10 to 15 kgf / cm 2 . This makes the adhesive effect of the adhesive between the precast blocks sufficient. In the present invention, since the prestress introduced by the tension of the PC steel has a small value in the PRC structure, the precast block does not require a high flatness of the joint surface. Therefore, it is not necessary to perform a mirror-finish treatment on the joint surface of the precast block or make the joint surface a match cast. As a result, in the present invention, the precast block can be manufactured as a single unit, and it is not necessary to consider the manufacturing order, so that the manufacturing process of the precast block is simplified.

【0014】(ロ)主鉄筋の配置はプレキャストブロッ
ク製作時に行わず、コンクリート打設時にはシース等に
よって挿通孔を形成しておき、プレキャストブロック積
重後、それらの挿通孔に通し鉄筋を挿入するものであ
る。主鉄筋とブロックとの固定はグラウチングにより行
う。主鉄筋を後挿入することによって継手の減少を図る
ことができ、接合面への継手の集中を排除し、継手作業
を簡略化し、製作時の煩雑さの改善を図ることができ
る。また通し鉄筋のグラウトをPC鋼より線の緊張後に
行うため、プレストレスが鉄筋の拘束を受けずにプレキ
ャストブロックの全断面に有効に導入される。
(B) The arrangement of the main reinforcing bars is not performed at the time of manufacturing the precast block, but the insertion holes are formed by a sheath or the like at the time of concrete casting, and after the precast blocks are stacked, the reinforcing bars are inserted through the insertion holes. It is. The main reinforcement and the block are fixed by grouting. The number of joints can be reduced by rear-inserting the main reinforcing bar, the concentration of the joints on the joint surface can be eliminated, the joint work can be simplified, and the complexity of manufacturing can be improved. In addition, since the through-rebar is grouted after the tension of the PC steel strand, prestress is effectively introduced to the entire cross section of the precast block without being restricted by the rebar.

【0015】(ハ)PC鋼より線は、プレキャストブロ
ック積重完了後に、U字形の片側からガイドワイヤによ
り引き込み、フーチング内のさや管を通って反対側より
引き出されるU字形配設とする。PC鋼材の緊張定着を
最上部のブロックで一括して行うため、定着具の数を低
減することができ、施工が簡単である。 (ニ)プレキャストブロック同士の接合面は、通し鉄筋
が横断しているため、RC構造のプレキャストブロック
のような特別の配慮、例えば剪断キーを設けるなどの対
策が不要である。
(C) After completion of stacking of the precast block, the PC steel strand is drawn in from one side of the U-shape with a guide wire, passed through a sheath in the footing, and drawn out from the other side. Since the tension fixing of the PC steel material is performed collectively by the uppermost block, the number of fixing tools can be reduced, and the construction is simple. (D) Since the through-bar reinforces the joint surface between the precast blocks, special considerations such as a precast block having an RC structure, for example, a measure such as providing a shear key is not required.

【0016】(ホ)以上の結果、工期の短縮を図ること
ができる。
(E) As a result, the construction period can be shortened.

【0017】[0017]

【実施例】図1に本発明の構築方法により施工された橋
脚の一例を示した。フーチング1上に基準ブロック2a
を介して多数のプレキャストブロック2が積重され、断
面矩形6m×4mで、高さ31mの橋脚(下部構造物)
が構築されている。主鉄筋3は35mmφ×160本、
組立仮締め用PC鋼棒13は32mmφ×24本、PC
鋼より線4は12.4mmφ×12本×7ケーブルであ
る。図2はプレキャストブロックの平面図で、図1に示
される主鉄筋3、PC鋼より線4、組立仮締め用PC鋼
棒13の配設位置を示している。
1 shows an example of a pier constructed by the construction method of the present invention. Reference block 2a on footing 1
A large number of precast blocks 2 are stacked via a bridge, and a pier (substructure) with a rectangular section of 6m x 4m and a height of 31m
Has been built. Main rebar 3 is 35mmφ × 160,
PC steel rod 13 for temporary fastening of assembly is 32mmφ × 24, PC
The steel strand 4 is a 12.4 mmφ × 12 × 7 cable. FIG. 2 is a plan view of the precast block, and shows the arrangement positions of the main reinforcing bar 3, the PC steel strand 4, and the PC steel rod 13 for temporarily fastening the assembly shown in FIG.

【0018】以下、実施例の構造物の構築方法を図3〜
13に従って説明する。 (1)フーチング1のコンクリート打設に先立ち、図3
に示すように、主鉄筋挿入用鋼管11、U字状さや管1
2、組立仮締め用PC鋼棒13を固定した鋼製フレーム
14を組み立て、図4、図5に示すように基礎鉄筋15
に固着設置する。次いで、基準ブロック2aをフーチン
グ1中に半分ほど埋設できるように設置する。
The construction method of the structure of the embodiment will be described below with reference to FIGS.
13 will be described. (1) Prior to placing footing 1 in concrete, Fig. 3
As shown in the figure, the steel tube 11 for inserting the main reinforcing bar, the U-shaped sheath tube 1
2. Assemble a steel frame 14 to which a PC steel bar 13 for temporarily fastening the assembly is fixed, and as shown in FIGS.
To be fixedly installed. Next, the reference block 2a is installed in the footing 1 so that it can be embedded about half.

【0019】(2)上記鋼製フレーム14及び基準ブロ
ック2aがずれないように慎重にフーチング1のコンク
リートを打設する。(図6) (3)フーチング1のコンクリートの強度発現を待っ
て、図7に示すように、プレキャストブロック2をクレ
ーン21を用いて積重する。プレキャストブロック2は
端面にエポキシ樹脂接着剤を塗布し、基準ブロック2a
から立設されている組立仮締め用PC鋼棒13をガイド
にして、4ブロック積重し、PC鋼棒13を仮緊張し仮
止めする。次いで、図8に示すように、次工程4ブロッ
ク分の組立仮締め用PC鋼棒13をカップラ16を用い
て接続する。
(2) The footing 1 concrete is carefully poured in so that the steel frame 14 and the reference block 2a do not shift. (FIG. 6) (3) After the concrete strength of the footing 1 has developed, the precast blocks 2 are stacked using the crane 21 as shown in FIG. An epoxy resin adhesive is applied to the end face of the precast block 2, and the reference block 2a
The PC steel rods 13 for temporary tightening, which are erected from above, are used as a guide to stack four blocks, and the PC steel rods 13 are temporarily tensioned and temporarily fixed. Next, as shown in FIG. 8, the PC steel rods 13 for temporary assembling for four blocks in the next process are connected using the coupler 16.

【0020】(4)次いで、前工程最終ブロックの上に
次のブロック2の当接端面にエポキシ樹脂接着剤を塗布
しながら4ブロック積重し、PC鋼棒13を仮緊張し仮
止めする。これを、所定の高さまで繰り返す。 (5)所定の高さまでプレキャストブロック2の積重が
完了したら、図9に示すように、主鉄筋3をクレーン2
1を用いて、ブロックの上端より落し込み挿入する。な
おこのとき、図10に示すように、主鉄筋3をカップラ
16を用いて接続する。この主鉄筋3の長手方向の接続
位置が同一レベル位置に集中しないように、主鉄筋3は
定尺長さの異なるものを組み合わせる。挿入は多数の主
鉄筋3を吊り治具22に櫛状に吊下して同時に挿入する
ことにより効率化を図った。
(4) Next, four blocks are stacked while applying an epoxy resin adhesive to the contact end surface of the next block 2 on the last block of the previous process, and the PC steel rod 13 is temporarily tensioned and temporarily fixed. This is repeated up to a predetermined height. (5) When the stacking of the precast block 2 is completed to a predetermined height, as shown in FIG.
1 and insert it from the upper end of the block. At this time, as shown in FIG. 10, the main reinforcing bar 3 is connected using the coupler 16. The main reinforcing bars 3 are combined with different lengths so that the connecting positions in the longitudinal direction of the main reinforcing bars 3 do not concentrate on the same level position. The efficiency was improved by inserting a large number of main reinforcing bars 3 into the hanging jig 22 in a comb shape and inserting them at the same time.

【0021】(6)主鉄筋3の挿入が完了したら、図1
1に示すように、PC鋼より線4をプレキャストブロッ
クの上端のシースの開放端よりプッシングマシーン25
を用いて押込み挿入し、フーチング1内を通って反転
し、シースの開放他端からPC鋼より線が上方に突出し
緊張代が出るまで押込む。本例ではプッシングマシーン
によって押込挿入したがPC鋼より線挿入に先立ちあら
かじめガイドワイヤをU字形挿通孔より挿入しておいて
そのワイヤにより一括引き込み挿入することも可能であ
る。
(6) When the insertion of the main reinforcing bar 3 is completed, FIG.
As shown in FIG. 1, a PC steel stranded wire 4 was pushed from the open end of the sheath at the upper end of the precast block to a pushing machine 25.
Then, the wire is inverted through the footing 1 and pushed until the PC stranded wire protrudes upward from the open other end of the sheath and a tension allowance appears. In this embodiment, the guide wire is pushed and inserted by a pushing machine. However, it is also possible to insert a guide wire from a U-shaped insertion hole in advance before inserting a strand of PC steel, and to collectively insert the guide wire with the wire.

【0022】(7)所定の本数のPC鋼より線4の挿入
が完了したら、図12に示すようにU字状PC鋼より線
4の両端に定着具26を装着して緊張ジャッキ27をセ
ットし、PC鋼より線4を緊張してプレキャストブロッ
クに10〜15kgf/cm 2 程度のプレストレスを導
入する。主鉄筋3はコンクリートと付着していないため
軸力を拘束しない。従って、少ない量のPC鋼より線4
で有効にプレストレスを導入することができる。
(7) Inserting a predetermined number of PC stranded wires 4
Is completed, U-shaped PC steel strand as shown in FIG.
Attach the fixing device 26 to both ends of the
And tension the PC steel strand 4 to pre-cast block.
10-15kgf / cm Two Inducing a degree of prestress
Enter. Because the main reinforcing bar 3 does not adhere to concrete
Do not restrain axial force. Therefore, a small amount of PC steel strand 4
Thus, prestress can be effectively introduced.

【0023】(8)すべてのPC鋼より線4の緊張が完
了したら、PC鋼より線4、主鉄筋3、PC鋼棒13の
ダクトにグラウトを注入し、プレキャストブロックを一
体化する。 (9)このようにして構築した橋脚上に鉄筋、型枠を組
み立てて横梁を構築し、橋体を施工する。
(8) When the tension of all the PC steel strands 4 is completed, grout is injected into the ducts of the PC steel strands 4, the main reinforcing bars 3, and the PC steel rods 13 to integrate the precast block. (9) Reinforcing bars and formwork are assembled on the pier thus constructed to construct a cross beam, and a bridge body is constructed.

【0024】上記実施例の橋脚の施工は、従来約5か月
を要していたが、本発明方法によれば、1.5か月に短
縮することができた。また、鉄筋量は従来の約2/3と
なった。さらに、橋脚の靭性が向上し、プレキャストブ
ロックの主鉄筋継手の弱点が解消された。また、部材の
厚さも薄くすることができ、軽量化すると共に、主鉄筋
継手が分散し、プレキャストブロックの接合部に集中し
ないので高さの高い橋脚等の下部構造物を容易に施工す
ることが可能となった。
The construction of the bridge pier of the above embodiment conventionally required about 5 months, but according to the method of the present invention, it could be reduced to 1.5 months. Moreover, the amount of rebar became about 2/3 of the conventional one. In addition, the toughness of the pier was improved, and the weakness of the main rebar joint of the precast block was eliminated. In addition, the thickness of the members can be reduced, and the weight can be reduced, and the main reinforcing joints are dispersed and not concentrated at the joints of the precast blocks, so that it is easy to construct lower structures such as tall piers. It has become possible.

【0025】図13は組立仮締め用PC鋼棒の結合部を
示すもので、下方のプレキャストブロック2のPC鋼棒
13は頂面の定着板33に定着用ナット32により定着
されている。上方のプレキャストブロック2にPC鋼棒
13を挿通し、カップラ31によって上下のPC鋼材1
3,13を連結する。本発明の工法では、PC鋼より線
を緊張して接着剤が硬化するに必要な圧力、すなわち1
0〜15kg/cm2 程度となるように応力導入し、そ
の後、主鉄筋をグラウチングして、プレキャストブロッ
クのコンクリートと一体化させる。従って、プレキャス
トブロックの接合面を鏡面仕上げする必要がなく、プレ
キャストブロックの継目に弱点がなく、総合的に鉄筋量
を減少することができ、構造体が剛性及び靭性に富み、
プレキャストブロックの製造工程も簡単になり、下部構
造物の構築を安全、安価、短工期に施工することができ
る。
FIG. 13 shows a connecting portion of a PC steel rod for provisional tightening. The PC steel rod 13 of the lower precast block 2 is fixed to a fixing plate 33 on the top surface by a fixing nut 32. The PC steel bar 13 is inserted into the upper precast block 2 and the upper and lower PC steel materials 1 are
3 and 13 are connected. In the method of the present invention, the pressure required to cure the adhesive by tensioning the strand of PC steel, ie, 1
Stress is introduced so as to be about 0 to 15 kg / cm 2 , and then the main reinforcing bar is grouted to be integrated with the concrete of the precast block. Therefore, it is not necessary to mirror-finish the joint surface of the precast block, there is no weak point at the seam of the precast block, the amount of rebar can be reduced comprehensively, the structure is rich in rigidity and toughness,
The manufacturing process of the precast block is also simplified, and the construction of the substructure can be performed safely, at low cost, and in a short construction period.

【0026】[0026]

【発明の効果】本発明の下部構造物の構築方法は、主鉄
筋を後挿入としたこととPRC構造とすることで、接合
面の製作精度を通常のものにでき、マッチキャストや、
鏡面仕上げ等を必要としなくなり、ブロックの製作順序
も自由となる。また、高品質の構造物を安全、高能率、
短工期に施工することができるという優れた効果を奏す
る。
According to the method of constructing a substructure of the present invention, since the main reinforcing bars are inserted in the back and the PRC structure is used, the manufacturing accuracy of the joint surface can be made normal, and match casting,
There is no need for a mirror finish or the like, and the production order of the blocks is also free. In addition, high-quality structures are safe, efficient,
It has an excellent effect that it can be constructed in a short construction period.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例の構造物の全体図である。FIG. 1 is an overall view of a structure according to an embodiment of the present invention.

【図2】実施例の構造物のプレキャストブロックの鋼材
配置を示す平面図である。
FIG. 2 is a plan view showing a steel material arrangement of a precast block of a structure according to an example.

【図3】本発明の工程説明図である。FIG. 3 is an explanatory view of a process of the present invention.

【図4】本発明の工程説明図である。FIG. 4 is a process explanatory view of the present invention.

【図5】本発明の工程説明図である。FIG. 5 is a process explanatory view of the present invention.

【図6】本発明の工程説明図である。FIG. 6 is a process explanatory view of the present invention.

【図7】本発明の工程説明図である。FIG. 7 is a process explanatory view of the present invention.

【図8】本発明の工程説明図である。FIG. 8 is a process explanatory view of the present invention.

【図9】本発明の工程説明図である。FIG. 9 is an explanatory view of a process of the present invention.

【図10】本発明の工程説明図である。FIG. 10 is a process explanatory view of the present invention.

【図11】本発明の工程説明図である。FIG. 11 is a process explanatory view of the present invention.

【図12】本発明の工程説明図である。FIG. 12 is a process explanatory view of the present invention.

【図13】実施例の組立仮締め用PC鋼棒の接続詳細図
である。
FIG. 13 is a detailed connection diagram of a PC steel rod for temporary assembly in the embodiment.

【図14】本発明方法が適用される実施例の構造物の例
を示す説明図である。
FIG. 14 is an explanatory view showing an example of a structure according to an embodiment to which the method of the present invention is applied.

【図15】図14のA−A矢視図である。FIG. 15 is a view taken in the direction of arrows AA in FIG. 14;

【符号の説明】[Explanation of symbols]

1 フーチング 2 プレキャス
トブロック 3 主鉄筋 4 PC鋼より
線 11 鉄筋用鋼管 12 さや管 13 PC鋼棒 14 フレーム 15 鉄筋 16 カップラ 21 クレーン 22 吊り治具 23 足場 25 プッシング
マシーン 31 カップラ 32 定着ナット 33 定着板 35 面 36 グラウト注入孔
DESCRIPTION OF SYMBOLS 1 Footing 2 Precast block 3 Main reinforcing bar 4 PC steel strand 11 Steel tube for reinforcing bar 12 Sheath tube 13 PC steel rod 14 Frame 15 Reinforcing bar 16 Coupler 21 Crane 22 Suspension jig 23 Scaffold 25 Pushing machine 31 Coupler 32 Fixing nut 33 Fixing plate 35 Surface 36 grout injection hole

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 フーチング内にU字状さや管を埋設し、
主鉄筋挿通孔及びPC鋼より線挿通孔を備えたプレキャ
ストブロックを前記フーチング上に積重し、積重したブ
ロックの主鉄筋挿通孔に通し主鉄筋を上方から挿通する
と共に、前記PC鋼より線挿通孔及び前記U字状さや管
を通ってPC鋼より線を上方から挿通し、該PC鋼より
線を最上ブロック上端にて緊張して前記積重したブロッ
クに軽度の縦方向プレストレスを導入した後、主鉄筋挿
通孔及びPC鋼より線挿通孔にグラウトを注入してブロ
ックと付着させPRC構造物を形成することを特徴とす
る下部構造の構築方法。
1. A U-shaped sheath is embedded in a footing,
A precast block having a main reinforcing bar insertion hole and a PC steel stranded wire insertion hole is stacked on the footing, the main reinforcing bar is inserted from above through the main reinforcing bar insertion hole of the stacked block, and the PC steel stranded wire is inserted. A PC steel strand is inserted from above through the insertion hole and the U-shaped sheath, and the PC strand is tensioned at the upper end of the uppermost block to introduce mild longitudinal prestress into the stacked blocks. After that, a grout is injected into the main rebar insertion hole and the PC steel wire insertion hole and adhered to the block to form a PRC structure.
【請求項2】 前記通し鉄筋は継手位置を互いに異なる
高さ位置に設けることを特徴とする請求項1記載の下部
構造の構築方法。
2. The method for constructing a lower structure according to claim 1, wherein the through-bars are provided with joint positions at different heights.
JP13595994A 1994-06-17 1994-06-17 How to build substructure Expired - Lifetime JP2831934B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13595994A JP2831934B2 (en) 1994-06-17 1994-06-17 How to build substructure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13595994A JP2831934B2 (en) 1994-06-17 1994-06-17 How to build substructure

Publications (2)

Publication Number Publication Date
JPH084031A JPH084031A (en) 1996-01-09
JP2831934B2 true JP2831934B2 (en) 1998-12-02

Family

ID=15163851

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13595994A Expired - Lifetime JP2831934B2 (en) 1994-06-17 1994-06-17 How to build substructure

Country Status (1)

Country Link
JP (1) JP2831934B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100949597B1 (en) * 2008-03-13 2010-03-25 구일건설(주) Method for enhancing bearing power of existing bridges using the a pile
KR101017127B1 (en) * 2008-05-06 2011-02-25 진성토건 주식회사 Connecting Structure between Foundation and Pier, and Construction Method thereof
KR100920204B1 (en) * 2008-09-12 2009-10-06 (주)대우건설 Constructing method of precast pier footing for bridge
CN106013618B (en) * 2016-07-25 2018-01-16 佳木斯大学 A kind of prestress steel ledges for building
CN106758786B (en) * 2016-11-11 2018-08-21 重庆大学 A kind of prefabricated assembled concrete-filled double skin steel tube lattice bridge pier
KR102418610B1 (en) * 2020-10-23 2022-07-06 현대건설주식회사 Pillar construction method based on segment plug-in and pillar structure constructed by the same

Also Published As

Publication number Publication date
JPH084031A (en) 1996-01-09

Similar Documents

Publication Publication Date Title
JP3537706B2 (en) Precast block method
KR20020011706A (en) Fabricated pier and Fabricated pier construction method
JP2831934B2 (en) How to build substructure
JP3660647B2 (en) Girder construction method using concrete receiving beams
JP2001303584A (en) Structure for connecting head of foundation pile with footing
JPH05340031A (en) Prestressed concrete girder and its manufacture
JP3708874B2 (en) Columnar structure and its construction method
JPH06158716A (en) Construction method of building with precast concrete member
KR101576865B1 (en) Construction method of slab for bridge without support bar using converse T-type beams
JP3590561B2 (en) Precast concrete block joining method
JPH0270850A (en) Pc coupled beam and execution of construction using same
JP6340467B1 (en) Ramen structure using sleeve wall and joining method thereof
JP2579944Y2 (en) Load-bearing wall assembly structure
JPH11181807A (en) Construction method for underground story
JPH01226943A (en) Slip prevention of beam main-reinforcement at joint section of column and beam in reinforced concrete structure
JPH116162A (en) Construction method for reinforced concrete underground external wall
JPH057381Y2 (en)
JPH0469268B2 (en)
JPH07197420A (en) Construction method of continuous composite girder bridge of concrete floor slab and steel girder
JP2023118410A (en) Rigid connection structure of upper and lower joints, bridge pier, and method for constructing rigid connection structure of upper and lower joints
JPS63277332A (en) Construction of reinforced concrete structure
JPH11117265A (en) Permanent form for dam levee body, and raising method of dam levee body
JPH08260484A (en) Connecting structure for top board footing
JPH011836A (en) Construction method for prestressed steel reinforced concrete beams
JPH05112947A (en) Execution method of foundation

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980908

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100925

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140925

Year of fee payment: 16

EXPY Cancellation because of completion of term