JPH01226943A - Slip prevention of beam main-reinforcement at joint section of column and beam in reinforced concrete structure - Google Patents

Slip prevention of beam main-reinforcement at joint section of column and beam in reinforced concrete structure

Info

Publication number
JPH01226943A
JPH01226943A JP5261988A JP5261988A JPH01226943A JP H01226943 A JPH01226943 A JP H01226943A JP 5261988 A JP5261988 A JP 5261988A JP 5261988 A JP5261988 A JP 5261988A JP H01226943 A JPH01226943 A JP H01226943A
Authority
JP
Japan
Prior art keywords
column
reinforcement
main
concrete
joint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5261988A
Other languages
Japanese (ja)
Inventor
Kenzo Yoshioka
吉岡 研三
Masataka Sekine
関根 正孝
Katsumi Nagahara
永原 克巳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP5261988A priority Critical patent/JPH01226943A/en
Publication of JPH01226943A publication Critical patent/JPH01226943A/en
Pending legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

PURPOSE:To fit a one-piece main-reinforcement firmly on concrete by penetrating a column main-reinforcement through the penetrated slot at the connecting section of a column and a beam which are PC-formed, and by injecting grout into the slot. CONSTITUTION:The section of the one-piece main-reinforcement 3 of a beam is solidified with high-strength concrete, and is integrally combined as a PC member 4. With the PC member 4, a penetrated slot 6 for the column main- reinforcement 5 of a column 1 to pass through is also formed, and on the side surface 7, a rugged section is roughly formed. The PC member 4 is suspended by a crane or the like, and the column main-reinforcement 5 is penetrated through the penetrated slot 6, and after that, grout is injected into the penetrated slot 6, and the column main-reinforcement 5 and the PC member 4 are integrally formed.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は鉄筋コンクリート構造の柱・梁接合部における
梁主筋のスリップ防止方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for preventing slip of beam main reinforcements at column-beam joints in reinforced concrete structures.

(従来の技術) 鉄筋コンクリート骨組構造では一般的に中柱と梁の接合
部内の梁主筋は通し配筋される。そして、この梁の通し
主筋と柱主筋とが交差する部分にコンクリートを打設し
、柱・梁の接合を完了していた。
(Prior Art) In reinforced concrete frame structures, the main beam reinforcement in the joint between the center column and the beam is generally provided through-through. Then, concrete was poured at the intersection of the main reinforcement of the beam and the main reinforcement of the column, completing the connection of the column and beam.

しかし、梁主筋の定着長さが十分確保されない場合や、
隣接する梁部材の塑性変形能力に若干の不足を生じてい
る場合等において、同接合部からの梁主筋(梁の通し主
筋)の抜は出しが耐震上問題となっている。
However, there are cases where the anchorage length of the main beam reinforcement is not secured sufficiently, and
In cases where there is a slight deficiency in the plastic deformation capacity of adjacent beam members, the removal of the beam main reinforcement (the main reinforcement of the beam) from the joint becomes a seismic problem.

そこで、柱・梁接合部にスターラップを配する等の方法
、即ち特公昭58−42340号等が提案されている。
Therefore, methods such as arranging stirrups at the column-beam joints have been proposed, such as Japanese Patent Publication No. 58-42340.

(発明が解決しようとする課題) しかしながら、フープ筋を増大させる方法や定着板類を
使用する方法は柱主筋や梁主筋が複雑に錯綜している接
合部内に、さらに鉄筋や金具を挿入することになるため
、コンクリ−ト打設充填の障害になり接合部内に空隙を
作る結果、鉄筋使用量に応じた鉄筋性能を十分に発揮せ
ず、経済的効率が悪かった。
(Problem to be solved by the invention) However, the method of increasing the number of hoop reinforcements or the method of using fixing plates requires the insertion of additional reinforcing bars or metal fittings into the joint where the main reinforcement of the column or the main reinforcement of the beam is complicated. As a result, it becomes a hindrance to concrete pouring and filling, creating voids within the joint, and as a result, the reinforcing bars do not perform adequately in accordance with the amount of reinforcing bars used, resulting in poor economic efficiency.

上記空隙は、柱・梁接合部に圧縮強度の高いコンクリー
トを打ち込むために水セメント比の小さな堅練りの場合
特に顕著である。
The above-mentioned voids are particularly noticeable when concrete with a high compressive strength is poured into the column-beam joint and the water-cement ratio is hardened.

本発明は上記事情に鑑みてなされたものであって、その
目的は鉄筋コンクリートラーメン架構に強い地震力が作
用した場合に柱・梁接合部に大きな剪断力が働き、この
繰り返し加力が梁主筋と接合部コンクリートとの付着力
を劣化させて梁の通し主筋の抜は出しを増長する不具合
を解消した柱・梁接合部のスリップ防止方法を提供する
にある。
The present invention was made in view of the above circumstances, and its purpose is that when a strong earthquake force acts on a reinforced concrete rigid frame structure, a large shearing force acts on the column-beam joint, and this repeated applied force is applied to the beam main reinforcement. To provide a method for preventing slip at a column-beam joint, which solves the problem of increasing the pull-out of the main reinforcement of the beam due to the deterioration of the adhesion force with concrete at the joint.

(課題を解決するための手段) 上記目的を達成するために、本発明に係る鉄筋コンクリ
ート構造の柱・梁接合部における梁主筋のスリップ防止
方法は、柱・梁接合部において、柱主筋に直交する梁の
通し主筋部分゛については、柱主筋用の貫通孔を設けて
高強度コンクリートによるプレキャストコンクリート柱
・梁接合部を構成し、次に前記柱主筋をプレキャストコ
ンクリート柱・梁接合部の貫通孔に挿通した後、該貫通
孔にグラウトを注入して柱主筋と梁の通し主筋部分を固
めたプレキャストコンクリート柱・梁接合部とを一体化
するのである。
(Means for Solving the Problems) In order to achieve the above object, the method for preventing slip of the main beam reinforcement at the column-beam joint of a reinforced concrete structure according to the present invention provides a method for preventing slip of the main beam reinforcement at the column-beam joint. For the main reinforcement section of the beam, a through hole is provided for the main column reinforcement to form a precast concrete column/beam joint made of high-strength concrete, and then the column main reinforcement is inserted into the through hole of the precast concrete column/beam joint. After insertion, grout is injected into the through hole to integrate the column main reinforcement and the precast concrete column/beam joint where the main reinforcement section of the beam is solidified.

(作 用) 柱・梁接合部の梁通し主筋部分について予め高強度コン
クリートでプレキャスト化し、通し主筋とコンクリート
との定着を充分に確実なものとしている。
(Function) The main beam reinforcement at the column-beam joint is precast with high-strength concrete in advance to ensure that the main reinforcement and concrete are firmly anchored.

このことによって高強度コンクリートの付着力の強さと
相俟って剪断剛性が高まり、通し主筋の付着性能劣化が
防止される。
This increases the shear rigidity in combination with the strong adhesion of high-strength concrete, and prevents deterioration of the adhesion performance of the main reinforcement.

また、プレキャスト化した接合部は、その貫通孔に柱主
筋を通して柱と一体化する。それ故に接合部全体へのコ
ンクリートの充填作業を伴なわず簡易に充分な定着を得
、梁端塑性ヒンジ部分のエネルギ吸収能力は充分なので
、柱の鉛直方向荷重の作用と共にプレキャスト化した接
合部の靭性は高まっている。
Furthermore, the precast joint is integrated with the column by passing the column main reinforcement through the through hole. Therefore, sufficient anchorage can be easily obtained without the need for filling the entire joint with concrete, and the energy absorption capacity of the beam end plastic hinge part is sufficient, so the precast joint can be used in conjunction with the vertical load of the column. Toughness is increasing.

(実 施 例) 以下、本発明の好適な実施例について図面を参照にして
詳細に説明する。
(Embodiments) Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.

図は梁が梁間方向、桁行方向に交差する部分と柱との接
合部を示す。柱1の柱頂と十字形に交差する梁の交差部
分とが一体になる柱・梁接合部2を直線的に通る梁の通
し主筋3は夫々平行に配筋した梁主筋の一体的な延長部
分であり、この通し主筋3−3が交差する箇所をプレキ
ャスト(以下PCと略記)化している。
The figure shows the joints between the beams and the columns, where they intersect in the inter-beam and girder directions. The main reinforcing bars 3 of the beams that pass linearly through the column-beam joint 2, where the top of the column 1 and the intersection of the cross-shaped beams are integrated, are an integral extension of the main beam reinforcing bars arranged in parallel. The portion where the main through-bars 3-3 intersect is precast (hereinafter abbreviated as PC).

通し主筋3−3の交差角度と鉄筋の定着強度とを強固に
維持するため、PC部材4に使用するコンクリートは高
強度コンクリートとする。
The concrete used for the PC member 4 is high-strength concrete in order to firmly maintain the intersection angle of the through main reinforcements 3-3 and the anchoring strength of the reinforcing bars.

高強度コンクリートは水セメント比を小さくした普通セ
メントによる堅練りで得られるが、圧縮強度を極めて高
くする場合には減水剤を混合してもよいし、又は普通セ
メントに引張強度の強い炭素繊維、アラミド繊維、ポリ
エチレン繊維等の短繊維を混入したものを使用してもよ
い。
High-strength concrete can be obtained by hardening ordinary cement with a low water-to-cement ratio; however, if the compressive strength is to be extremely high, a water reducer may be mixed in, or carbon fibers with high tensile strength may be mixed with ordinary cement. A mixture of short fibers such as aramid fibers and polyethylene fibers may also be used.

すなわち、梁の通し主筋3部分を高強度コンクリートで
固め、PC部材4として一体的に結合する。そして、こ
のPC部材4には更に通し主筋3と直交する鉛直方向へ
柱1の柱主筋5が通る貫通孔6を形成するとともに側面
7に粗く凹凸を付しておく。
That is, the 3 portions of the main reinforcing bars of the beam are solidified with high-strength concrete and are integrally combined as the PC member 4. This PC member 4 is further provided with a through hole 6 through which the column main reinforcement 5 of the column 1 passes in a vertical direction orthogonal to the through main reinforcement 3, and the side surface 7 is roughened.

PC部材4の貫通孔6に挿通する柱主筋5は、柱・梁接
合部2を担持する途中迄を現場打柱1とし、その頂部上
に延出した部分である。
The main column reinforcement 5 inserted into the through-hole 6 of the PC member 4 is a cast-in-place column 1 up to the middle of supporting the column-beam joint 2, and is a portion extending above the top.

然して、PC部材4を揚重機(図示せず)等で吊り揚げ
、その貫通孔6に柱主筋5を通した後、貫通孔6内にグ
ラウトを注入して柱主筋5とPC部材4とを一体化する
ことにより、柱と梁との接合が完了する。グラウトには
膨張剤を混入してもよい。PC部材4の側面から四方へ
延出している梁主筋にスターラップを配筋し、スラブと
ともにコンクリートを現場打ちして梁が完成する。
After lifting the PC member 4 using a lifting machine (not shown) or the like and passing the column main reinforcement 5 through the through hole 6, grout is injected into the through hole 6 to connect the column main reinforcement 5 and the PC member 4. By integrating the columns and beams, the connection between the columns and beams is completed. Bulking agents may be mixed into the grout. Stirrups are arranged on the main beam reinforcement bars extending in all directions from the sides of the PC member 4, and concrete is poured on-site together with the slab to complete the beam.

(効 果) 本発明は叙述したようにして鉄筋コンクリート構造の柱
・梁接合部を施工するので、次のような効果を奏する。
(Effects) Since the present invention constructs a column-beam joint of a reinforced concrete structure as described above, the following effects are achieved.

梁の通し主筋部分は高強度コンクリートによるPC化が
なされているので、堅練りであっても十分に緻密なコン
クリートの打設がなされ、通し主筋とコンクリートとの
付着が密実で強力な鉄筋の定着が得られる。したがって
、梁端塑性ヒンジ部分のエネルギ吸収能力が十分に維持
され、梁主筋が接合部から抜は出す現象を防止する。し
たがって建物全体の骨組の復元力特性劣化が発生しにく
く耐震性に優れる。
The main reinforcement of the beam is made of high-strength concrete, so even if it is hard-mixed, the concrete is placed in a sufficiently dense manner, and the adhesion between the main reinforcement and the concrete is tight and strong. Retention is obtained. Therefore, the energy absorption capacity of the beam end plastic hinge portion is maintained sufficiently, and the phenomenon in which the beam main reinforcement is pulled out from the joint portion is prevented. Therefore, the restoring force characteristics of the entire building frame are less likely to deteriorate, resulting in excellent earthquake resistance.

また、PC化する際の通し鉄筋部分にはフープ筋やスタ
ーラップを使用しなくても接合部断面を大きくしなくて
すみ、自重の増大や空間喪失が少なくて、しかもコンク
リートを緻密に充填しやすく、経済効率も高い。
In addition, there is no need to use hoop reinforcements or stirrups for the through-reinforcement parts when converting to PC, and the cross section of the joint does not have to be made large, resulting in less increase in dead weight and loss of space, and moreover, it is possible to fill the concrete densely. Easy and economically efficient.

また、柱主筋をPC化した柱・梁接合部の貫通孔に通し
、この孔にグラウトを注入するだけなので、柱・梁接合
部にコンクリートを現場打ちする場合に較べ、この接合
部の施工時間は極めて短縮され、構造物全体の工期が短
くなる。
In addition, since the main column reinforcement is simply passed through the through hole of the PC column-beam joint and grout is injected into this hole, the construction time for this joint is shorter than when concrete is poured on-site at the column-beam joint. This will significantly shorten the construction period for the entire structure.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明方法を説明するための斜視図である。 1・・・・・・柱        2・・・・・・柱・
梁接合部3・・・・・・通し主筋     4・・・・
・・PC部材5・・・・・・柱主筋      6・・
・・・・貫通孔7・・・・・・側 面
FIG. 1 is a perspective view for explaining the method of the present invention. 1...Column 2...Column・
Beam joint 3...Through main bar 4...
...PC member 5...Column main reinforcement 6...
...Through hole 7...Side

Claims (1)

【特許請求の範囲】[Claims] (1)柱・梁接合部において、柱主筋に直交する梁の通
し主筋部分については、該柱主筋用の貫通孔を設けて高
強度コンクリートによるプレキャストコンクリート柱・
梁接合部を構成し、次に該柱主筋を該プレキャストコン
クリート柱・梁接合部の貫通孔に挿通した後、該貫通孔
にグラウトを注入して該柱主筋と梁の通し主筋部分を固
めた該プレキャストコンクリート柱・梁接合部とを一体
化することを特徴とする鉄筋コンクリート構造の柱・梁
接合部における梁主筋のスリップ防止方法。
(1) At the column-beam joint, for the main reinforcement of the beam that is perpendicular to the main reinforcement of the column, through-holes are provided for the main reinforcement of the column, and precast concrete columns made of high-strength concrete are installed.
A beam joint was constructed, and then the column main reinforcement was inserted into the through hole of the precast concrete column/beam joint, and then grout was injected into the through hole to solidify the column main reinforcement and the through main reinforcement part of the beam. A method for preventing slip of beam main reinforcement at a column/beam joint of a reinforced concrete structure, characterized by integrating the precast concrete column/beam joint.
JP5261988A 1988-03-08 1988-03-08 Slip prevention of beam main-reinforcement at joint section of column and beam in reinforced concrete structure Pending JPH01226943A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5261988A JPH01226943A (en) 1988-03-08 1988-03-08 Slip prevention of beam main-reinforcement at joint section of column and beam in reinforced concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5261988A JPH01226943A (en) 1988-03-08 1988-03-08 Slip prevention of beam main-reinforcement at joint section of column and beam in reinforced concrete structure

Publications (1)

Publication Number Publication Date
JPH01226943A true JPH01226943A (en) 1989-09-11

Family

ID=12919820

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5261988A Pending JPH01226943A (en) 1988-03-08 1988-03-08 Slip prevention of beam main-reinforcement at joint section of column and beam in reinforced concrete structure

Country Status (1)

Country Link
JP (1) JPH01226943A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05280150A (en) * 1992-03-31 1993-10-26 Kajima Corp Pc pole member and pc pole-girder joining member
JP2011080358A (en) * 2011-01-05 2011-04-21 Sumitomo Mitsui Construction Co Ltd Column-beam joint structure of building, building, and joining method
JP2014055517A (en) * 2013-12-25 2014-03-27 Takenaka Komuten Co Ltd Precast beam-column joint structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS626034A (en) * 1985-07-01 1987-01-13 株式会社大林組 Construction of concrete structure

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS626034A (en) * 1985-07-01 1987-01-13 株式会社大林組 Construction of concrete structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05280150A (en) * 1992-03-31 1993-10-26 Kajima Corp Pc pole member and pc pole-girder joining member
JP2011080358A (en) * 2011-01-05 2011-04-21 Sumitomo Mitsui Construction Co Ltd Column-beam joint structure of building, building, and joining method
JP2014055517A (en) * 2013-12-25 2014-03-27 Takenaka Komuten Co Ltd Precast beam-column joint structure

Similar Documents

Publication Publication Date Title
US6293063B2 (en) Cast-in-place hybrid building system
WO2005066419A1 (en) Method of applying prestress and connecting means used therein and prestressed concrete beam therefrom
KR100644745B1 (en) Pc column-beam joint system and construction method thereof
JP2004285738A (en) Box girder bridge structure and method of constructing the same
JP4094149B2 (en) Column and beam joint structure
Teran et al. Reinforced concrete jacketing of existing structures
JPH01226943A (en) Slip prevention of beam main-reinforcement at joint section of column and beam in reinforced concrete structure
JP2831934B2 (en) How to build substructure
JPH0882002A (en) Rc structure and its constructing method
JP2003138523A (en) Construction method for tension string girder bridge
KR102033052B1 (en) Method for constructing truss bridge support with infilled tube using src girder
JPH0657952A (en) Anchoring structure of main reinforcing bar
JPH02311640A (en) Construction of composite floor
CN211499175U (en) Novel take assembled beam column node that dismouting supported
JP3931635B2 (en) Composite box girder and its construction method
JPH02221535A (en) Connecting structure for pillar and beam
KR102673775B1 (en) Connecting Structure of beam and colum
JP3009582B2 (en) Construction method of continuous composite girder bridge between concrete slab and steel girder
KR102670768B1 (en) Steel composite ramen bridge reinforced with section steel supports and crossing rebars and its construction method
JP2620118B2 (en) Net formwork method for walls and floors
JP2762906B2 (en) RC frame
JP2001107373A (en) Joint structure of steel column base with foundation concrete
JPH0366878A (en) Construction method for precast column and beam and precast anti-seismic wall
JP2023097877A (en) Floor slab structure and bonding method
JPH0328547B2 (en)