JP2004285738A - Box girder bridge structure and method of constructing the same - Google Patents
Box girder bridge structure and method of constructing the same Download PDFInfo
- Publication number
- JP2004285738A JP2004285738A JP2003080522A JP2003080522A JP2004285738A JP 2004285738 A JP2004285738 A JP 2004285738A JP 2003080522 A JP2003080522 A JP 2003080522A JP 2003080522 A JP2003080522 A JP 2003080522A JP 2004285738 A JP2004285738 A JP 2004285738A
- Authority
- JP
- Japan
- Prior art keywords
- girder
- bridge
- truss
- precast concrete
- box girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、箱桁橋構造およびその構築方法に関する。
【0002】
【従来の技術】
従来、コンクリート橋梁等において、比較的大型の橋梁を構築する場合、I形断面の桁に較べてねじり剛性が極めて大きく、曲線橋の主桁に有利であり、また桁高を低く設計できるので、長支間の橋や桁下空間の制限が大きい場合などに箱桁橋梁が採用されてきている。
【0003】
箱桁の構築にあたっては、▲1▼支保工を組み立てて、その上で場所打ち施工を行なう場合や、▲2▼押し出し工法のように、橋台背面で箱桁を構築する場合もある。また、▲3▼移動架設機を用いて1セグメントづつ箱桁を構築する場合もある(例えば、特許文献1参照)。
【0004】
しかし、前記▲1▼では、桁下空間が確保できない場合、適用できず、前記▲2▼▲3▼にあたっては、大規模な架設材または大型の架設装置が必要になり、工費が嵩むこととなる。
【0005】
【特許文献1】
特開2002−4225号公報
【0006】
これらの点を改善する工法として、桁を架設し、その後、上床版および必要に応じ下床版を現場打ちコンクリートで築造して一体化し、最後に外ケーブルを緊張定着する箱桁工法は、すでに本出願人により出願されている(特願2000−355038)。
【0007】
前記の発明は、ウェブ材としての桁が小スパンでは、箱桁構造は大きな架設設備を使わなくて大型の橋梁を施工できる形式として優れているが、ウェブ材としての桁が大スパン・大重量になると、やはり大型の架設設備を必要とする。また、ウェブ材としての桁が大スパンになると、施工ヤードが広く必要なる点およびコストが高くなる点から、更にウェブ材が軽量化された橋梁形式が求められている。
【0008】
【発明が解決しようとする課題】
本発明は、箱桁のウェブに当たる部分を軽量化された桁とすることにより、桁が大スパンでも軽量化可能な橋梁とすることができ、また、これを架設した後は、大規模な架設材または大型の架設装置を使用することなく、桁を利用して簡易の型枠支持装置により支持された型枠だけで上床版および必要に応じ下床版を容易に迅速に低コストで施工できる、構造が簡単な箱桁橋構造およびその構築方法を提供することを目的とする。
【0009】
【課題を解決するための手段】
前記の従来の問題点を有利に解決するために、第1発明の箱桁橋構造においては、箱桁橋において、箱桁でウェブとなる桁を、プレキャストコンクリート部材を備えたトラス構造の複数のプレキャストコンクリート製ウェブユニットを用いたトラス桁とし、複数の前記トラス桁を使用して、これらが橋軸方向に隣り合う橋脚または橋台にわたって架設され、橋軸方向と交差する方向に間隔をおいて隣り合う前記2つのトラス桁間に、上床版および必要に応じ下床版を現場打ちコンクリートで構築されて一体化され、かつ外ケーブルが配置されて、その外ケーブルが、前記トラス桁またはこれらの端部に渡って設けられた橋軸方向両端部の横桁に緊張定着され、緊張力が導入されていることを特徴とする。
【0010】
また、第2発明では、第1発明の箱桁橋構造において、前記プレキャストコンクリート製ウェブユニットは、PC鋼材が埋め込まれたプレキャストコンクリート製中空部材と、前記プレキャストコンクリート製中空部材に一体化された側部上床版と側部下床版を備えたユニット化された部材であって、前記PC鋼材で、前記側部上床版と側部下床版に定着されていることを特徴とする。
【0011】
また、第3発明では、第1または第2発明の箱桁橋構造において、前記トラス桁は、これを構成するブロック化された複数のプレキャストコンクリート製ウェブユニットが連結されて構成され、直列に隣り合うプレキャストコンクリート製ウェブユニット相互が、接着材およびPC鋼材で一体化されていることを特徴とする。
【0012】
また、第4発明では、第1〜第3発明のいずれかの箱桁橋構造において、前記トラス桁におけるウェブ部分に配置されたPC鋼材と、下弦材としての側部下床版に配置されたPC鋼材とにより、橋梁の自重を保持可能な構造とされ、かつ、外ケーブルで橋面荷重および活荷重を負担する構造とされていることを特徴とする。
【0013】
第5発明では、箱桁橋の構築方法において、箱桁でウェブとなる桁を、複数のプレキャストコンクリート製ウェブユニットを連結したトラス桁を使用して、これらを橋軸方向に隣り合う橋脚または橋台にわたって架設した後、橋軸方向と交差する方向に間隔をおいて隣り合う前記2つの桁間に、上床版および必要に応じ下床版を現場打ちコンクリートで構築して一体化し、かつ外ケーブルを配置して、その外ケーブルを桁またはこれらの端部に渡って設けられた橋軸方向両端部の横桁に緊張定着し、緊張力を導入することを特徴とする箱桁橋の構築方法である。
【0014】
【発明の実施の形態】
次に、この発明を図示の実施形態に基づいて詳細に説明する。
【0015】
図1および図2は、本発明の箱桁橋構造およびその構築方法において使用されるトラス桁を構成するための、プレキャストコンクリート部材1を使用したブロック化されたプレキャストコンクリート製ウェブユニット2を示すものであって、図1(a)は側面図、(b)は正面図、図2(a)は一部縦断側面図、(b)は平面図である。
【0016】
図1および図2に示すように、プレキャストコンクリート製ウェブユニット2は、トラスのウェブを構成するためのブロックされた1ユニットであり、橋梁完成時の上床版の一部を構成する側部上床版3と、山形(ほぼ逆V字状)に同一垂直面状に配置されたトラスを構成する斜材としての一対のプレキャストコンクリート部材1の上端部とが接合され、また、前記各プレキャストコンクリート部材1の下端部と、橋梁完成時の下床版の一部を構成する側部下床版4とが接合されている。前記のプレキャストコンクリート製ウェブユニット2は、正面ほぼH形で、側面から見てトラス構造の部材である。
【0017】
前記のプレキャストコンクリート部材1は、例えば、図11に示すように、PCパイル等の横断面円形等で、橋梁の軽量化を図るため、中空のプレキャストコンクリート部材であり、プレキャストコンクリート部材本体1aの環状周壁部5内に、PC鋼材6が周方向に間隔を置くと共に軸方向に延長するように埋め込み配置され、プレキャストコンクリート部材本体1aの両端部からPC鋼材6を突出するように配置された部材である。
【0018】
前記のプレキャストコンクリート部材1を製作する場合には、遠心成形等により製作し、全長または一部に緊張状態のPC鋼材(図示を省略)が埋め込み配置され、また端部側から張り出すように、接合用のPC鋼材6が設けられている。なお、プレキャストコンクリート部材1の内側に鋼管シース1bを埋め込み配置してもよい。
【0019】
前記の側部上床版3と側部下床版4とは、工場あるいは現場ヤード上において、プレキャストコンクリート部材1を所定の位置に配置すると共に側部上床版3側および側部下床版4側の配筋作業をした後、プレキャストコンクリート部材1の端部側を格点部コンクリート部分で埋め込むように、コンクリートを充填・硬化して製作され、プレキャストコンクリート部材1における各PC鋼材6を、コンクリート製側部上床版3と側部下床版4とに緊張定着して、各プレキャストコンクリート部材1と側部上床版3および側部下床版4とが一体化されたプレキャストコンクリート製ウェブユニット2が製作される。
【0020】
なお、側部上床版3と側部下床版4およびこれらに一体に形成された格点部鉄筋コンクリート部分における橋軸方向の端面、すなわち接合面には、図示を省略するが、適宜コッター(凹凸部)が設けられ、隣接するプレキャストコンクリート製ウェブユニット2との上下方向のずれ止めおよびせん断補強が図られる。
【0021】
前記の山形配置の各プレキャストコンクリート部材1を接合する部分となる頂点の上部格点部7は、上弦材となる側部上床版3に一体に設けられた上部格点部鉄筋コンクリート8により強固に、側部上床版3と一体化され、また、前記の山形配置の各プレキャストコンクリート部材1における下端部を接合する部分の下部格点部9は、下弦材となる側部下床版4に一体に設けられた下部格点部鉄筋コンクリート9aにより強固に、側部下床版4と一体化されている。前記の下部格点部鉄筋コンクリート9aには、橋梁軸方向(前後方向)に延長する透孔10が左右方向(橋軸方向と交差する方向)に間隔をおいて平行に予めシース等が埋め込み配置されて形成され、また前記各プレキャストコンクリート部材1の対向する内側の下部格点部鉄筋コンクリート9aには、前記透孔10の端部に鋼製等の支承部材11が埋め込み配置され、その外側は連結用のPC鋼材の支承縦壁12を備えた段部が形成されている。
【0022】
また、前記の側部下床版4には、橋軸方向両端部に貫通するPC鋼材挿通孔13が左右方向に間隔をおいて複数(図示の場合は、4つ)、橋軸方向に延長するように設けられ、また、図示を省略するが端部側に配置されるプレキャストコンクリート製ウェブユニット2の端部側には、定着部が設けられる。なお、前記の側部上床版3と側部下床版4には、橋軸直角方向に横締め用のシース等を予め埋め込み配置することにより、横締め用PC鋼材挿通孔14を設けることもできる。
【0023】
なお、プレキャストコンクリート部材1の両端部に、側部上床版3と側部下床版4を構築すべくコンクリートを打設した後、所定の強度が出た段階で、接合用のPC鋼材6を後から、側部上床版3と上部格点部コンクリート8とプレキャストコンクリート部材1と下部格点部コンクリート9aと側部下床版4とに予め埋め込み配置のシースにわたって挿入し緊張定着し、側部上床版3と側部下床版4の端部の凹部を跡埋めすることもできる。
【0024】
前記のように構成された、プレキャストコンクリート製ウェブユニット2相互を接合する場合には、現場において、桁接合用架台(図示を省略した)の上に複数のプレキャストコンクリート製ウェブユニット2をセットし、前後・左右・上下の3次元方向の位置調整を行い、プレキャストコンクリート製ウェブユニット2の橋軸方向の端部の縦端面に接着剤15を塗布し、他方のプレキャストコンクリート製ウェブユニット2を橋軸方向に移動して、プレキャストコンクリート製ウェブユニット2相互を、図3に示すように接着接合する。
【0025】
また、隣り合う下部格点部コンクリート9aをこれに挿通された接合用PC鋼材16を緊張してその端部を支承部材11で支承させると共に定着金具により定着し、プレキャストコンクリート製ウェブユニット2相互を接合し、このような工程を繰り返して、所定の長さのトラス桁17とし、かつ前記の側部下床版4における各PC鋼材挿通用孔13に、図5に示すように、PC鋼材18を挿通すると共に緊張して、トラス桁17の端部に定着する。
【0026】
前記と同様な一対のトラス桁17を構築し、これらのトラス桁17の端部には、図10に示すように支承20を取付けておくこともできる。前記のように構成されたトラス桁17は、側部下床版4に配置緊張された複数のPC鋼材18によりトラス桁17の自重を充分保持可能なトラス桁17とされている。本発明においては、前記のように構成されたトラス桁17を、箱桁におけるウェブ材として利用するものである。
【0027】
なお、前記の側部上床版3および側部下床版4の橋軸直角方向となる左右方向(図1bに示すプレキャストコンクリート製ウェブユニット2の右端部から右方向)には、側方に張り出す継手用の床版鉄筋があるが、図面上省略している。
【0028】
トラス桁17の橋軸方向からみた形状は倒T形あるいはI形でも良いが、側部上床版3間に後施工の上床版および側部下床版4間に後施工の下床版を現場で、構築することを考慮すると、H形の方が合理的であり、トラス桁を架設する場合も安定性がよい。なお、橋脚(または橋台)23に予め支承装置を設置しておいてもよい。
【0029】
<施工手順>
次に、前記のように予め製作されたトラス桁17を使用して、本発明の箱桁橋構造およびその構築方法の施工手順について説明する。
【0030】
まず、接合されたプレキャストコンクリート製のトラス桁17を、橋脚(または橋台)23に架設したガーダーあるいはレッカー(図示を省略した)を使って、橋軸直角方向(左右方向)に間隔をおいて橋脚(または橋台)23に架設する(図4参照)。なお、橋台(または橋台)23に取り付けられている下沓に合わせてトラス桁17を設置することにより、箱桁46におけるウェブ部分を架設する。トラス桁17の架設が終了したら、吊り足場(図示を省略した)を組む。
【0031】
橋軸方向と交差する方向に間隔をおいて隣り合うトラス桁17の上に渡って、スペーサ24として、多数のH形鋼を橋軸方向に並べる(図6参照)。このスペーサ4としてのH形鋼は、必ずしも必要ではなく、図示を省略するが、トラス桁17における側部上床版3(または側部下床版4)に、予め貫通孔を設け、吊りねじ杆からなる鋼棒を吊り下げ支持するように設置することによって、その吊り鋼棒で、型枠支持材およびこれに支持された型枠を吊り下げ支持してもよく、あるいは、図示を省略するが、側部上床版3(または側部下床版4)に、予め埋め込んだインサートに、型枠吊り鋼棒を螺合連結するようにして、型枠を支持するようにしてもよい。
【0032】
両方のプレキャストコンクリート製のトラス桁17上のH鋼からなるスペーサ24の上に、H鋼または型鋼等の型枠支持梁材28を支持部材として渡し、適宜ボルトあるいは適宜の仮止め金具により仮止めする。この型枠支持梁材28も前記のように、必ずしも必要なものではない。この実施形態では、前記型枠支持梁材28は、床版コンクリート34の重量に絶えられる間隔に並べるようにすればよい。このように、プレキャストコンクリート製のトラス桁17に渡した型枠支持梁材28に、型枠吊り材29の上部をナット43により係止するようにして、前記型枠吊り材29を吊り下げ支持する。
【0033】
前記の型枠支持梁材28に型枠吊り材29の上部を係止するために、型枠支持梁材28には、ボルト孔(図示の場合)あるいは、雌ねじ孔を設けるようにしておくか、型枠吊り材29の上部を係止フック状にしておく。
【0034】
前記吊り材29に支持させるようにして、型枠受け材30を並べ、上床版用および下床版用の型枠39を組む(図6または図7a参照)。また、端部横桁31、中間横桁32の型枠(図示を省略した)も組む。端部横桁31には、図示を省略するが、落橋防止装置、外ケーブル用の定着装置、シース、横締め用シース、鋼材などが配置される。また、中間横桁32にも横締め用シース、鋼材が配置される。
【0035】
各床版部、横桁部に鉄筋、横締め用シース(PC鋼材を挿入しておく)33を配置し、コンクリート34を打設する。
【0036】
コンクリート34が所定の強度に達したら、横締めPC鋼材35を緊張し、定着して、各側部上床版3,側部下床版4と一体化された上床版41および下床版40を構築する(図8参照)。
【0037】
次に外ケーブル36を配置する。中間横桁32のデビエータ部を貫通し傷がつかないように合成樹脂製または鋼製の保護管44を通す。端部横桁31の端部に楔式等の定着具37を取付け、外ケーブル36を緊張してプレストレスを導入し、定着する(図9、図12参照)。このように外ケーブル36を配置することにより、外ケーブルで橋面荷重および活荷重を負担できる構造とされている
【0038】
横締めPC鋼材35とシースとの間にグラウトを行う。その後、型枠、吊り下げ支持部材等の支保工を解体する。
【0039】
前記のように本発明においては、トラス桁17を橋脚(または橋台)3に架設した後は、トラス桁17に、型枠を支持するための部材を設置するだけで、大規模な架設材または大型の架設装置を使用することなく、トラス桁17を利用して簡易の型枠支持装置により支持された型枠だけで施工できるため、上下の床版(上床版および必要に応じ下床版)を容易に迅速に低コストで施工できる。また、施工も単純化されているので簡単であり、工程的にも単純であるので、迅速に施工でき、工期を短縮することができる。
【0040】
また、始めに架けるトラス桁17は、その自重とその後の床版を施工するときの荷重を負担できればよい。さらに、架設時に安定を良くするために上下の側部床版3,4を備えていれば、その後に現場打設される床版コンクリート34の打設量も少なくてすむ。
【0041】
本発明を実施する場合、下床版40を構築し、その次に上床版41を構築施工してもよい。そして、主に橋面荷重と、活荷重を外ケーブル36のプレストレスの導入で負担すればよい。
【0042】
前記のように、本発明では、前記トラス桁17におけるウェブ部分に配置されたPC鋼材16と、下弦材としての側部下床版4内に配置されたPC鋼材18とにより、橋梁の自重を保持可能な構造とされ、かつ、外ケーブル36で橋面荷重および活荷重を負担する構造とされている。
なお、箱桁46は、条件により、トラス桁17と、上床版41と外ケーブル36だけで成り立てば、下床版40を設けなくてもよい。したがって、下床版40は必要に応じ設ければよい。またトラス桁17の高さは適宜設定される。
【0043】
また、前記実施形態の場合、中間横桁32は、デビエータとして利用されている。なお、本発明を実施する場合、図示を省略するが、中間横桁32を設けないで、下床版40の上面に、デビエータを設けるようにしてもよい。
【0044】
また、本発明を実施する場合、図示を省略するが、トラス桁1の橋軸方向の端部側のみに、下床版40を設けるようにしてもよい。
【0045】
前記実施形態の場合は、トラス桁17の端部に渡って端部横桁31を構築し、外ケーブル36を端部横桁31に定着するようにしたが、予め、トラス桁17に横方向に突出する外ケーブル定着部を設けるようにして、外ケーブル36の両端部をトラス桁17に定着するようにしてもよい。
【0046】
本発明を実施する場合、図示を省略するが、下床版40または上床版41を構築する場合、プレキャストコンクリート製埋設板を埋め殺し型枠として使用してコンクリート34を打設するようにしてもよい。
【0047】
なお、前記各実施形態のように、2つのトラス桁17の上部に渡って支持梁材を多数架設し、それらの支持梁材を介して、下床版用の型枠または上床版用の型枠を支持したり、あるいは、2つの桁に多数の吊り下げ支持金具を設け、それらの吊り下げ支持金具により、下床版用の型枠または上床版用の型枠を支持すると、比較的大きな装置をプレキャストコンクリート製トラス桁上に配置する必要がないので、トラス桁を利用して簡易の型枠支持装置により支持された型枠だけで上下の床版を容易に迅速に低コストで施工できる。
【0048】
【発明の効果】
第1発明の箱桁橋構造によると、箱桁橋において、箱桁でウェブとなる桁を、プレキャストコンクリート部材を備えたトラス構造の複数のプレキャストコンクリート製ウェブユニットを用いたトラス桁とし、複数の前記トラス桁を使用して、これらが橋軸方向に隣り合う橋脚または橋台にわたって架設され、橋軸方向と交差する方向に間隔をおいて隣り合う前記2つのトラス桁間に、上床版および必要に応じ下床版を現場打ちコンクリートで構築されて一体化され、かつ外ケーブルが配置されて、その外ケーブルが、前記トラス桁またはこれらの端部に渡って設けられた橋軸方向両端部の横桁に緊張定着され、緊張力が導入されているので、比較的大スパンのトラス桁でも軽量なトラス桁を使用した、大スパンで軽量な箱桁とすることができ、また構造が簡単で、容易に迅速に低コストで施工できる箱桁橋とすることができる。
【0049】
特に本発明においては、プレキャストコンクリート部材を備えたトラス構造の複数のプレキャストコンクリート製ウェブユニットを用いたトラス桁を使用しているので、比較的狭い施工ヤードでも、短いスパンのプレキャストコンクリート製ウェブユニットを容易に低コストで製作することができる。
【0050】
また、第2発明のように、プレキャストコンクリート製ウェブユニットを、PC鋼材が埋め込まれたプレキャストコンクリート中空部材と、前記プレキャストコンクリート中空部材に一体化された側部上床版と側部下床版を備えたユニット化された部材とし、前記PC鋼材で、前記側部上床版と側部下床版に定着されていると、プレキャストコンクリート中空部材と、現場施工する場合の側部上床版または側部下床版との一体化を容易に行なうことができ、しかも、さらに材料費の少ない軽量なトラス桁とすることができるため、一層軽量な低コストな箱桁とすることができる。
【0051】
第3発明のように、トラス桁が、これを構成するブロック化された複数のプレキャストコンクリート製ウェブユニットが連結されて構成され、直列に隣り合うプレキャストコンクリート製ウェブユニット相互が、接着材およびPC鋼材で一体化されていると、プレキャストコンクリート製ウェブユニット相互の連結一体化を容易に行なうことができる。
【0052】
第4発明のように、トラス桁におけるウェブ部分に配置されたPC鋼材と、下弦材としての側部下床版に配置されたPC鋼材とにより、橋梁の自重を保持可能な構造とされ、かつ、外ケーブルで橋面荷重および活荷重を負担する構造とされていると、外ケーブルをトラス桁に配置することなく、トラス桁自身を保持可能なトラス桁とすることができるため、トラス桁間の床版の構築施工が容易であると共に、トラス桁内に配置されるPC鋼材と、外ケーブルとの分担が可能となるため、経済的な設計が可能となる。
【0053】
第5発明によると、箱桁でウェブとなる桁を、複数のプレキャストコンクリート製ウェブユニットを連結したトラス桁とし、これを架設した後は、大規模な架設材または大型の架設装置を使用することなく、トラス桁を利用して簡易の型枠支持装置により支持された型枠だけで上床版および必要に応じ下床版を容易に迅速に低コストで施工でき、また比較的大スパンの箱桁であっても軽量な箱桁とすることができる。また、外ケーブルを、トラス桁またはこれらの端部に渡って設けられた橋軸方向両端部の横桁に緊張定着し、緊張力を導入するだけで、外ケーブルを利用した軽量な箱桁橋を容易に構築することができる。
【図面の簡単な説明】
【図1】本発明において用いられるプレキャストコンクリート製ウェブユニットの一実施形態を示すものであって、(a)は側面図、(b)は正面図である。
【図2】(a)は、図1(a)の一部縦断側面図、(b)は平面図である。
【図3】プレキャストコンクリート製ウェブユニット端面相互の連結および下部格点部コンクリート相互の連結部を示す側面図である。
【図4】本発明を実施して箱桁橋を構築している状態を示すものであって、(a)は橋脚にトラス桁を架設した状態を示す概略縦断正面図、(b)は概略平面図である。
【図5】各プレキャストコンクリート製ウェブユニットにおける側部下床版の全長にわたって配置されると共に緊張定着されたPC鋼材を示す一部横断平面図である。
【図6】(a)は図4の状態からトラス桁上にスペーサを介在させて隣り合うトラス桁上に多数の型枠支持梁を設置し、下床版用型枠を支持している状態を示す概略縦断正面図、(b)は概略平面図である。
【図7】(a)は図6の状態から下床版を構築後、上床版を構築している状態を示す縦断正面図、(b)は(a)の状態から上床版を構築した状態を示す縦断正面図、(c)は外ケーブルの端部横桁定着部付近を示す縦断正面図である。
【図8】上床版および下床版を構築した後、左右のトラス桁と各床版とを横締めした状態を示す縦断正面図である。
【図9】(a)は完成した状態を示す概略側面図、(b)は(a)の概略平面図である。
【図10】本発明において使用されるトラス桁の一例を示す縦断正面図である。
【図11】プレキャストコンクリート製ウェブユニットにおけるトラス用斜材として用いられるプレキャストコンクリート部材を示す縦断正面図である。
【図12】(a)は端部横桁における外ケーブル定着部を示す縦断側面図、(b)は中間横桁と外ケーブルとの関係を示す縦断側面図である。
【符号の説明】
1 プレキャストコンクリート部材
1a プレキャストコンクリート部材本体
2 プレキャストコンクリート製ウェブユニット
3 側部上床版
4 側部下床版
5 環状周壁部
6 PC鋼材
7 上部格点部
8 上部格点部コンクリート
9 下部格点部
9a 下部格点部コンクリート
10 透孔
11 支承部材
12 支承縦壁
13 PC鋼材挿通孔
14 横締め用PC鋼材挿通孔
15 接着剤
16 接合用PC鋼材
17 トラス桁
18 PC鋼材
20 支承
23 橋脚(または橋台)
24 スペーサ
28 型枠支持梁材
29 型枠吊り材
30 型枠受け材
31 端部横桁
32 中間横桁
33 横締め用シース
34 コンクリート
35 横締めPC鋼材
36 外ケーブル
37 定着具
38 吊り鋼棒
39 型枠
40 下床版
41 上床版
43 ナット
44 保護管
46 箱桁[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a box girder bridge structure and a construction method thereof.
[0002]
[Prior art]
Conventionally, when constructing a relatively large bridge in a concrete bridge or the like, the torsional rigidity is extremely large as compared with the girder of the I-shaped cross section, which is advantageous for a main girder of a curved bridge, and the girder height can be designed low, Box girder bridges have been adopted for long span bridges and when the space under the girder is very limited.
[0003]
When constructing a box girder, (1) assembling the shoring and then performing cast-in-place construction on it, or (2) constructing a box girder on the back of the abutment, as in the extrusion method. (3) In some cases, a box girder is constructed one segment at a time using a mobile erection machine (for example, see Patent Document 1).
[0004]
However, in the above (1), if the space under the girder cannot be secured, it cannot be applied, and in the above (2) and (3), a large-scale erection material or a large-scale erection device is required, and the construction cost increases. Become.
[0005]
[Patent Document 1]
Japanese Patent Application Laid-Open No. 2002-4225
As a construction method to improve these points, the box girder method of erection of the girder, then building the upper slab and, if necessary, the lower slab with cast-in-place concrete and integrating it, and finally tensioning and fixing the outer cable, has already been implemented. It has been filed by the present applicant (Japanese Patent Application No. 2000-355038).
[0007]
In the above invention, when the girder as the web material is small span, the box girder structure is excellent as a form capable of constructing a large bridge without using large erection facilities, but the girder as the web material is large span and heavy weight In such cases, large erection facilities are required. In addition, when a girder as a web material has a large span, a bridge type in which the web material is further reduced in weight is demanded from the viewpoint that a large construction yard is required and the cost is increased.
[0008]
[Problems to be solved by the invention]
The present invention provides a bridge that can be reduced in weight even if the girder has a large span by making the portion of the box girder that corresponds to the web a lightweight girder. The upper floor slab and the lower slab can be constructed easily and quickly at low cost with only the formwork supported by the simple formwork supporting device using the girder, without using materials or large erection equipment. It is an object of the present invention to provide a box girder bridge structure having a simple structure and a construction method thereof.
[0009]
[Means for Solving the Problems]
In order to advantageously solve the above-mentioned conventional problems, in the box girder bridge structure of the first invention, in the box girder bridge, a girder to be a web by the box girder is replaced by a plurality of truss structures having a precast concrete member. A truss girder using a web unit made of precast concrete, and using a plurality of the truss girder, these are erected over piers or abutments adjacent in the bridge axis direction and are spaced apart in a direction intersecting with the bridge axis direction. Between the two truss girders, the upper slab and, if necessary, the lower slab are constructed from cast-in-place concrete and integrated, and an external cable is arranged, and the external cable is connected to the truss girder or their ends. It is characterized in that tension is fixed to the cross beams at both ends in the bridge axis direction provided over the portion, and tension is introduced.
[0010]
According to a second invention, in the box girder bridge structure of the first invention, the precast concrete web unit includes a precast concrete hollow member in which a PC steel material is embedded, and a side integrated with the precast concrete hollow member. A unitized member including a top floor slab and a side bottom slab, wherein the PC steel material is fixed to the side top slab and the side bottom slab.
[0011]
According to a third aspect of the present invention, in the box girder bridge structure of the first or second aspect, the truss girder is configured by connecting a plurality of precast concrete web units, which are blocks, constituting the truss girder. Matching precast concrete web units are characterized by being integrated with adhesive and PC steel.
[0012]
According to a fourth invention, in the box girder bridge structure according to any one of the first to third inventions, a PC steel material arranged on a web portion of the truss girder and a PC steel material arranged on a side lower slab as a lower chord material. It is characterized by having a structure capable of holding the bridge's own weight by using steel, and having a structure that bears a bridge surface load and a live load with an external cable.
[0013]
According to a fifth aspect of the present invention, in the method of constructing a box girder bridge, a girder forming a web by the box girder is formed by using a truss girder connecting a plurality of precast concrete web units, and connecting these with a pier or an abutment in the bridge axis direction. After erection, the upper slab and, if necessary, the lower slab are integrated with cast-in-place concrete between the two adjacent girders spaced apart in the direction intersecting with the bridge axis direction, and the outer cable is connected. A method of constructing a box girder bridge characterized by arranging the outer cable and tensioning and fixing the outer cable to the girder or the horizontal girder at both ends in the bridge axial direction provided across these ends, and introducing tension. is there.
[0014]
BEST MODE FOR CARRYING OUT THE INVENTION
Next, the present invention will be described in detail based on the illustrated embodiment.
[0015]
FIGS. 1 and 2 show a precast
[0016]
As shown in FIG. 1 and FIG. 2, the precast
[0017]
For example, as shown in FIG. 11, the
[0018]
When the above-mentioned
[0019]
The side
[0020]
Although not shown in the drawing, the end face in the bridge axis direction of the side
[0021]
The upper graded
[0022]
The side
[0023]
After the concrete is cast on both ends of the precast
[0024]
When joining the precast
[0025]
In addition, the adjacent lower
[0026]
A pair of
[0027]
The lateral
[0028]
The shape of the
[0029]
<Construction procedure>
Next, the construction procedure of the box girder bridge structure of the present invention and the construction method thereof will be described using the
[0030]
First, the joined precast
[0031]
A large number of H-shaped steels are arranged in the bridge axis direction as
[0032]
Form support beams 28 such as H steel or die steel are passed as support members on the
[0033]
In order to lock the upper part of the
[0034]
The
[0035]
Reinforcing bars and a sheath for horizontal tightening (PC steel material is inserted) 33 are arranged on each floor slab and horizontal beam, and concrete 34 is cast.
[0036]
When the concrete 34 reaches a predetermined strength, the laterally tightened
[0037]
Next, the
Grout is performed between the laterally tightened
[0039]
As described above, in the present invention, after the
[0040]
Further, the
[0041]
When implementing the present invention, the
[0042]
As described above, in the present invention, the weight of the bridge is maintained by the
The
[0043]
In the case of the above embodiment, the intermediate
[0044]
Further, when the present invention is carried out, although not shown, the
[0045]
In the case of the above-described embodiment, the
[0046]
In practicing the present invention, although not shown, when constructing the
[0047]
As in each of the above embodiments, a large number of support beams are erected over the upper portions of the two
[0048]
【The invention's effect】
According to the box girder bridge structure of the first invention, in the box girder bridge, the girder to be a web by the box girder is a truss girder using a plurality of precast concrete web units of a truss structure provided with a precast concrete member. Using the truss girders, these are erected over the piers or abutments adjacent in the bridge axis direction, and the upper deck and the necessary In response, the lower slab is constructed of cast-in-place concrete and integrated, and an outer cable is arranged, and the outer cable is provided next to the truss girder or both ends in the bridge axial direction provided over these ends. Since the girder is tensioned and tension is introduced, even a relatively large span truss girder can be used as a large span and lightweight box girder using a lightweight truss girder. The structure is simple, it can be a box girder bridge that can be applied by easily and quickly at low cost.
[0049]
Particularly, in the present invention, since a truss girder using a plurality of precast concrete web units having a truss structure provided with precast concrete members is used, even in a relatively narrow construction yard, a short span precast concrete web unit can be used. It can be easily manufactured at low cost.
[0050]
Further, as in the second invention, the precast concrete web unit includes a precast concrete hollow member in which a PC steel material is embedded, and a side upper deck and a side lower deck integrated with the precast concrete hollow member. As a unitized member, when the PC steel material is fixed to the side upper slab and the side lower slab, a precast concrete hollow member, and a side upper slab or a side lower slab for on-site construction. Can be easily integrated, and a light-weight truss girder can be further reduced in material cost, so that a lighter and lower-cost box girder can be obtained.
[0051]
As in the third invention, a truss girder is formed by connecting a plurality of precast concrete web units, which are block members, constituting the truss girder, and the precast concrete web units adjacent in series are bonded to each other by an adhesive and a PC steel material. When integrated, the precast concrete web units can be easily connected and integrated.
[0052]
As in the fourth invention, the PC steel material disposed on the web portion of the truss girder and the PC steel material disposed on the side lower slab as the lower chord have a structure capable of holding the weight of the bridge, and If the external cable is designed to bear the bridge surface load and live load, the truss girder can be held without holding the external cable on the truss girder. The construction and construction of the floor slab are easy, and the PC steel material arranged in the truss girder and the external cable can be shared, so that economical design is possible.
[0053]
According to the fifth invention, the girder which becomes the web by the box girder is a truss girder connecting a plurality of precast concrete web units, and after this is erected, a large-scale erection material or a larger erection device is used. The upper deck and the lower deck can be constructed easily and quickly at low cost using only the formwork supported by the simple form support device using the truss girder. However, a light box girder can be obtained. In addition, a lightweight box girder bridge that uses an external cable by simply fixing the external cable to the truss girder or the horizontal girder at both ends in the bridge axial direction provided across these ends and introducing tension. Can be easily constructed.
[Brief description of the drawings]
1 shows an embodiment of a web unit made of precast concrete used in the present invention, wherein (a) is a side view and (b) is a front view.
2 (a) is a partially longitudinal side view of FIG. 1 (a), and FIG. 2 (b) is a plan view.
FIG. 3 is a side view showing a connection between end faces of web units made of precast concrete and a connection between lower concrete points.
4A and 4B show a state in which a box girder bridge is constructed by implementing the present invention, wherein FIG. 4A is a schematic longitudinal sectional front view showing a state in which a truss girder is erected on a pier, and FIG. It is a top view.
FIG. 5 is a partial cross-sectional plan view showing a PC steel material that is disposed over the entire length of the side lower slab of each precast concrete web unit and is set and tensioned.
6 (a) shows a state in which a number of formwork supporting beams are installed on adjacent truss girders with spacers interposed on the truss girders from the state of FIG. 4 to support the formwork for the lower slab. FIG. 2B is a schematic plan view.
7A is a longitudinal sectional front view showing a state in which an upper slab is being constructed after the lower slab is constructed from the state of FIG. 6, and FIG. 7B is a state in which an upper slab is constructed from the state of FIG. And (c) is a longitudinal sectional front view showing the vicinity of an end portion of a lateral girder of the outer cable.
FIG. 8 is a vertical sectional front view showing a state where left and right truss girders and each floor slab are laterally tightened after an upper floor slab and a lower floor slab are constructed.
9A is a schematic side view showing a completed state, and FIG. 9B is a schematic plan view of FIG. 9A.
FIG. 10 is a vertical sectional front view showing an example of a truss girder used in the present invention.
FIG. 11 is a longitudinal sectional front view showing a precast concrete member used as a truss diagonal member in the precast concrete web unit.
12A is a vertical side view showing an outer cable fixing portion in an end horizontal girder, and FIG. 12B is a vertical side view showing a relationship between an intermediate horizontal girder and an outer cable.
[Explanation of symbols]
DESCRIPTION OF
24
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003080522A JP3844743B2 (en) | 2003-03-24 | 2003-03-24 | Box girder bridge structure and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003080522A JP3844743B2 (en) | 2003-03-24 | 2003-03-24 | Box girder bridge structure and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2004285738A true JP2004285738A (en) | 2004-10-14 |
JP3844743B2 JP3844743B2 (en) | 2006-11-15 |
Family
ID=33294349
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003080522A Expired - Fee Related JP3844743B2 (en) | 2003-03-24 | 2003-03-24 | Box girder bridge structure and its construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3844743B2 (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100794444B1 (en) | 2006-10-20 | 2008-01-16 | 원대연 | Construction Method of Composite Slab Bridge Using Composite Truss Girder |
CN102493349A (en) * | 2011-12-16 | 2012-06-13 | 中国建筑第六工程局有限公司 | Method for prefabricating and erecting box girders by using bailey beam |
CN104894977A (en) * | 2015-06-02 | 2015-09-09 | 中铁二十三局集团有限公司 | Three-dimensional adjustable jack device and method used for setting up maglev rail girders |
JP2017057684A (en) * | 2015-09-18 | 2017-03-23 | 国立大学法人 名古屋工業大学 | Bridge fall prevention device of truss bridge |
CN106638333A (en) * | 2016-12-12 | 2017-05-10 | 中铁山桥集团有限公司 | Truss integral hole compression reinforcing system and application method thereof |
CN107503278A (en) * | 2017-09-08 | 2017-12-22 | 上海市政工程设计研究总院(集团)有限公司 | A kind of truss-like steel box-girder diaphragm plate |
CN107905084A (en) * | 2017-12-12 | 2018-04-13 | 长沙市公路桥梁建设有限责任公司 | RPC steel truss combined bridge deck and continuous bridge |
CN109162158A (en) * | 2018-09-17 | 2019-01-08 | 中国建筑第八工程局有限公司 | The adjusting method and system of track girder assembly |
CN109797662A (en) * | 2019-03-29 | 2019-05-24 | 中铁建大桥工程局集团第四工程有限公司 | Long span cast-in-situ box girder crosses over high-grade highway bracket and construction method |
CN110512664A (en) * | 2019-09-27 | 2019-11-29 | 长沙理工大学 | Dynamic model device and test method for strengthening soil slope with hinged anchor cable frame beam |
CN111305079A (en) * | 2020-03-30 | 2020-06-19 | 河北省交通规划设计院 | Prefabricated assembled steel truss web concrete composite bridge and construction method |
CN111827079A (en) * | 2020-07-16 | 2020-10-27 | 中铁第四勘察设计院集团有限公司 | Road-rail dual-purpose box-truss composite girder bridge with cantilever arm |
CN112431112A (en) * | 2020-10-23 | 2021-03-02 | 浙江大学 | Assembled ground anchor through-type pedestrian cable bridge structure and construction method |
CN114319066A (en) * | 2021-12-01 | 2022-04-12 | 中国建筑土木建设有限公司 | Spliced steel truss box girder and mounting method thereof |
CN114837066A (en) * | 2022-05-19 | 2022-08-02 | 保利长大工程有限公司 | High-altitude cable tower beam construction bracket with external prestress and installation method |
CN115162358A (en) * | 2022-08-02 | 2022-10-11 | 中国建筑第七工程局有限公司 | Assembled steel-concrete combined support system for foundation pit engineering and construction method |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103981801B (en) * | 2014-01-27 | 2016-10-12 | 中铁宝桥集团有限公司 | Box beam truss-like endosternum composed structure and processing technology |
CN104999547A (en) * | 2015-06-30 | 2015-10-28 | 中铁二十三局集团有限公司 | Automatic template system for maglev curve track beam and use method of automatic template system |
-
2003
- 2003-03-24 JP JP2003080522A patent/JP3844743B2/en not_active Expired - Fee Related
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100794444B1 (en) | 2006-10-20 | 2008-01-16 | 원대연 | Construction Method of Composite Slab Bridge Using Composite Truss Girder |
CN102493349A (en) * | 2011-12-16 | 2012-06-13 | 中国建筑第六工程局有限公司 | Method for prefabricating and erecting box girders by using bailey beam |
CN104894977A (en) * | 2015-06-02 | 2015-09-09 | 中铁二十三局集团有限公司 | Three-dimensional adjustable jack device and method used for setting up maglev rail girders |
CN104894977B (en) * | 2015-06-02 | 2016-09-07 | 中铁二十三局集团有限公司 | A kind of method utilizing three-dimensional adjustable jack device to set up magnetic levitation track girder |
JP2017057684A (en) * | 2015-09-18 | 2017-03-23 | 国立大学法人 名古屋工業大学 | Bridge fall prevention device of truss bridge |
CN106638333A (en) * | 2016-12-12 | 2017-05-10 | 中铁山桥集团有限公司 | Truss integral hole compression reinforcing system and application method thereof |
CN107503278A (en) * | 2017-09-08 | 2017-12-22 | 上海市政工程设计研究总院(集团)有限公司 | A kind of truss-like steel box-girder diaphragm plate |
CN107905084B (en) * | 2017-12-12 | 2024-05-14 | 长沙市公路桥梁建设有限责任公司 | RPC steel truss combined bridge deck and continuous beam bridge |
CN107905084A (en) * | 2017-12-12 | 2018-04-13 | 长沙市公路桥梁建设有限责任公司 | RPC steel truss combined bridge deck and continuous bridge |
CN109162158A (en) * | 2018-09-17 | 2019-01-08 | 中国建筑第八工程局有限公司 | The adjusting method and system of track girder assembly |
CN109797662A (en) * | 2019-03-29 | 2019-05-24 | 中铁建大桥工程局集团第四工程有限公司 | Long span cast-in-situ box girder crosses over high-grade highway bracket and construction method |
CN110512664A (en) * | 2019-09-27 | 2019-11-29 | 长沙理工大学 | Dynamic model device and test method for strengthening soil slope with hinged anchor cable frame beam |
CN110512664B (en) * | 2019-09-27 | 2024-06-11 | 长沙理工大学 | Hinge type anchor rope frame beam soil slope reinforcement power model device and test method |
CN111305079A (en) * | 2020-03-30 | 2020-06-19 | 河北省交通规划设计院 | Prefabricated assembled steel truss web concrete composite bridge and construction method |
CN111827079A (en) * | 2020-07-16 | 2020-10-27 | 中铁第四勘察设计院集团有限公司 | Road-rail dual-purpose box-truss composite girder bridge with cantilever arm |
CN112431112A (en) * | 2020-10-23 | 2021-03-02 | 浙江大学 | Assembled ground anchor through-type pedestrian cable bridge structure and construction method |
CN114319066A (en) * | 2021-12-01 | 2022-04-12 | 中国建筑土木建设有限公司 | Spliced steel truss box girder and mounting method thereof |
CN114319066B (en) * | 2021-12-01 | 2024-05-10 | 中国建筑土木建设有限公司 | Spliced steel truss box girder and installation method thereof |
CN114837066A (en) * | 2022-05-19 | 2022-08-02 | 保利长大工程有限公司 | High-altitude cable tower beam construction bracket with external prestress and installation method |
CN115162358A (en) * | 2022-08-02 | 2022-10-11 | 中国建筑第七工程局有限公司 | Assembled steel-concrete combined support system for foundation pit engineering and construction method |
CN115162358B (en) * | 2022-08-02 | 2023-12-01 | 中国建筑第七工程局有限公司 | Assembled steel-concrete combined support system for foundation pit engineering and construction method |
Also Published As
Publication number | Publication date |
---|---|
JP3844743B2 (en) | 2006-11-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101630235B1 (en) | Precast truss wall structure and construction method of underground structure using thereof | |
KR100941066B1 (en) | Prestressed-precast-segmental open spendral concrete arch bridge and its constructing method | |
JP2004285738A (en) | Box girder bridge structure and method of constructing the same | |
KR101937680B1 (en) | Prefabricated Precast Structure and Construction Method Thereof | |
KR101652664B1 (en) | Precast deckplate and composite slab and concrete slab manufacturing method using the same | |
JP2004027516A (en) | Composite truss segment and truss bridge for simultaneously using suspension cable by using this truss segment and its construction method | |
KR101198812B1 (en) | composite rahmen bridge using a preflex girder | |
JP2006104747A (en) | Joint structure and joining method of pedestal | |
KR20140144035A (en) | The hybrid girder structures prestressed by using the external prestressing mechanism, and the construction method by rigid connection | |
JP2005256341A (en) | Corrugated steel-plate web u component bridge | |
JP2007077630A (en) | Continuous girder using precast main-girder segment, and its erection method | |
JP3737475B2 (en) | Box girder bridge structure and construction method | |
KR102269141B1 (en) | Deck plate wall installation method using underground pavement | |
JP5217428B2 (en) | Composite hollow structure of bridge column head or girder end | |
KR100785634B1 (en) | Continuous Structure of Prestressed Concrete Composite Beam Bridge and Its Method | |
KR101426155B1 (en) | The hybrid rahmen structure which can add prestress on steel girder of horizontal member by gap difference of connection face between vertical member and steel girder of horizontal member | |
KR20080111686A (en) | Bridge and slab integrated PHC composite girder using PHC girder | |
JP2000017613A (en) | Connection of corrugated steel plate web girder | |
JP2011157733A (en) | Method of constructing composite steel floor slab bridge, steel floor slab with rib, and composite steel floor slab bridge | |
JP3877995B2 (en) | How to build a string string bridge | |
KR101664997B1 (en) | Constructing method of precast T type modular composite rahmen bridge and composite rahmen bridge constructed by the same, and construction thing therefor | |
JP2002206209A (en) | Bridge having upper-lower section integral structure and its execution method | |
KR101824963B1 (en) | Hybrid composite girder and construction method therewith | |
KR20100138433A (en) | Prestressed steel composite girder with prestressed non-introduced portions at both ends of the lower flange casing concrete, its fabrication method, and its ramen structure and its construction method | |
KR102244029B1 (en) | Rahmen bridge without abuttment and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Effective date: 20060309 Free format text: JAPANESE INTERMEDIATE CODE: A971007 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060404 |
|
A521 | Written amendment |
Effective date: 20060524 Free format text: JAPANESE INTERMEDIATE CODE: A523 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Effective date: 20060815 Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060816 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 3 Free format text: PAYMENT UNTIL: 20090825 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090825 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 4 Free format text: PAYMENT UNTIL: 20100825 |
|
LAPS | Cancellation because of no payment of annual fees |