CN109137721A - A kind of prefabricated assembled suspension bridge bridge pier - Google Patents
A kind of prefabricated assembled suspension bridge bridge pier Download PDFInfo
- Publication number
- CN109137721A CN109137721A CN201811082981.3A CN201811082981A CN109137721A CN 109137721 A CN109137721 A CN 109137721A CN 201811082981 A CN201811082981 A CN 201811082981A CN 109137721 A CN109137721 A CN 109137721A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- prefabricated section
- hole
- bridge pier
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The present invention provides a kind of prefabricated assembled suspension bridge bridge piers, it include: the multiple basic units being stacked up, each described basic unit includes two prefabricated sections, each described prefabricated section is rectangular shape, and there are parallel, planar upper and lower surfaces, one end of the prefabricated section is provided with the step of rectangular shape, the height of the step is the half of the prefabricated section thickness, and two prefabricated sections mutually overlap the basic unit formed with the consistency of thickness of the prefabricated section by the step.Prefabricated assembled suspension bridge bridge pier provided by the invention, prefabricated section completed in factory it is prefabricated, the scene that is transported to carry out it is assembled, to engineering after remove, and can be transported to and reuse elsewhere, greatly increase utilization rate, and solve the problems of the prior art.
Description
Technical field
The present invention relates to technical field of bridge construction, especially a kind of prefabricated assembled suspension bridge bridge pier.
Background technique
In bridges in highway engineering work progress, the top priority that builder's road is the construction stage is built, sidewalk uses
Also extend through all stage in construction.In sidewalk work progress, across river at need to set up make-shift bridge, make-shift bridge
Setting up speed is the key that entire sidewalk construction speed.It is also a key factor for influencing entire project construction progress.
Traditional make-shift bridge bridge pier generallys use cast-in-situ steel reinforced concrete, and the method has the following problems: first is that when construction
It needs to build island cofferdam, accumulates a large amount of sandstone and other materials, removed after to be onstructed, expend a large amount of manpower and material resources,
And river is caused to block, it is very fast or water larger area is difficult to realize in flow velocity;Second is that foundation pit needs to drain before bridge pier pours,
But if river water head is larger, and water electrode easily enters from the sand material gap in loose cofferdam, causes draining difficulty big, and easily induce pipe
The safety accidents such as gush, topple over;Third is that being not thorough for draining causes river water to penetrate into foundation pit, when concrete is not pre-hardening to concrete table
Face generates impact, and bridge pier cannot be guaranteed at pier quality;Fourth is that the mountable floor system of ability after concrete reaches design strength,
Leverage suspension bridge construction speed;Fifth is that this construction method expends a large amount of manpower and material resources and mechanical, cost increase;Sixth is that work
After completion of works, bridge pier is removed difficult, also becomes waste material a pile after dismounting, cannot reuse, for 10m or so only have one across
Suspension bridge applicability is poor.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of prefabricated assembled suspension bridge bridge piers, solve the above problems.
The present invention provides a kind of prefabricated assembled suspension bridge bridge piers, comprising: the multiple basic units being stacked up, each
The basic unit includes two prefabricated sections, each described prefabricated section is rectangular shape, and is had parallel, planar
Upper and lower surfaces are provided with the step of rectangular shape in one end of the prefabricated section, and the height of the step is the prefabricated section
The half of thickness, two prefabricated sections mutually overlaps the described of formation and the consistency of thickness of the prefabricated section by the step
Basic unit.
Further, to enhance overall stability, at least one is provided between the outer edge and inward flange of the step
First mounting hole of a perforation prefabricated section, multiple first mounting holes are vertically forming the first hole, one first rod piece
It is set in first hole, shape matches with first hole.
Further, be additionally provided at remaining position in addition to the step at least one penetrate through the prefabricated section
Two mounting holes, multiple second mounting holes are set in second hole in vertically the second hole of formation, one second rod piece,
Its shape matches with second hole.
Further, first mounting hole and second mounting hole are cylinder, and diameter is identical.
Further, multiple hoisting structures are additionally provided on the prefabricated section, for installing when prefabricated section described in handling
Suspension hook.
Further, multiple hoisting structures are distributed on the upper surface and the lower surface, and each described
The U-shaped reinforcing bar that structure includes pit He is set in the pit is hung, two free ends of the U-shaped reinforcing bar are anchored in described prefabricated
In block.
It further, further include blotter, the blotter is layed in river bed, and the bridge pier is set to the rubble
Above bed course.
Prefabricated assembled suspension bridge bridge pier provided by the invention, prefabricated section is prefabricated in factory's completion, is transported to scene and carries out assembly,
It is removed after to engineering, and can be transported to and reuse elsewhere, greatly increase utilization rate, and solve the prior art
The problems in.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of prefabricated section in the prefabricated assembled suspension bridge bridge pier of the present invention;
Fig. 2 is the A-A cross-sectional view of Fig. 1;
Fig. 3 is the structural schematic diagram of the prefabricated assembled suspension bridge bridge pier of the present invention.
In figure, 1. prefabricated sections, 101. steps, 102. first mounting holes, 103. second mounting holes, 104. hoisting structures,
100. basic unit, 200. first holes, 300. first rod pieces, 400. second holes, 500. second rod pieces, 600. rubble pads
Layer.
Specific embodiment
The present invention will be further explained below with reference to the attached drawings and specific examples, so that those skilled in the art can be with
It more fully understands the present invention and can be practiced, but illustrated embodiment is not as a limitation of the invention.
A kind of prefabricated assembled suspension bridge bridge pier, as shown in Fig. 1 ~ 3, comprising: the multiple basic units 100 being stacked up, often
One basic unit 100 includes two prefabricated sections 2, each prefabricated section 2 is rectangular shape, and is had parallel, planar
Upper and lower surfaces, one end of prefabricated section 1 is provided with the step 101 of rectangular shape, the height of step 101 is that prefabricated section 1 is thick
The half of degree, two prefabricated sections 1 form the basic unit 100 with the consistency of thickness of prefabricated section 1 by the mutually overlap joint of step 101.
In one optional embodiment of the present embodiment, to guarantee that two blocks of prefabricated sections 1 connect secured in basic unit 100
Property, (position of center line P in Fig. 1) is provided at least one perforation prefabricated section 1 between the outer edge and inward flange of step 101
First mounting hole 102(Fig. 2), after two prefabricated sections 1 are by step 101 mutually overlap joint, two the first mounting holes 102 are vertical
Direction position is corresponding.Multiple 100 heap poststacks of basic unit form the first hole 200(and see Fig. 3), it is set in the first hole 200
It is equipped with the first rod piece 300 to match with its shape.It is by the first rod piece 300 that two in a basic unit 100 are prefabricated
Block is connected as one, meanwhile, and be an entirety by multiple basic units 100 concatenation, it ensure that the fastness and stabilization of bridge pier
Property.The cross-sectional shape of first mounting hole 102 can be round, rectangle and other polygons, preferably justify in the present embodiment
Shape facilitates manufacture.For example, the hollow circular-tube that a nominal diameter is 200mm is arranged in mold, by the open circles when prefabricated
Pipe build-in is in prefabricated section 1, and after the completion of manufacture, the inner cavity of the hollow circular-tube is the first mounting hole 102.Multiple first mounting holes
102 are formed by the first hole 200 as cylinder, and correspondingly, it is 170mm that the first rod piece 300, which can select nominal diameter,
Hollow circular-tube can concrete perfusion in cavity for the intensity for guaranteeing the first rod piece 300.In addition, in present embodiment,
The position of center line P is only provided with first mounting hole 102, can also be as needed, along the direction of center line P setting multiple the
One mounting hole 102.
In the above-described embodiment, prefabricated at each to further strengthen the fastness between multiple basic units 100
On block 1, the second mounting hole 103(figure of at least one perforation prefabricated section 1 is additionally provided at remaining position in addition to step 101
2), multiple second mounting holes 103 are shown in Fig. 3 in vertically the second hole 400(of formation), one second rod piece 500 is set to the second hole
In 400, shape matches with the second hole 400.The manufacturing method of second mounting hole 103 and the second rod piece 500 can join
Examine the first mounting hole 102 and the first rod piece 300.
For convenience of manufacture, unified specifications of raw materials, the first mounting hole 102 and the second mounting hole 103 are cylinder, and
Diameter is identical.
In one optional embodiment of the present embodiment, as illustrated in fig. 1 and 2, multiple hoisting structures are additionally provided on prefabricated section 1
104, for installing hook when handling prefabricated section 1.Specifically, multiple hoisting structures 104 are distributed in upper and lower surfaces,
Each hoisting structure 104 includes pit and the U-shaped reinforcing bar being set in pit, and two free ends of U-shaped reinforcing bar are anchored in prefabricated
In block 1.
It further include blotter 600 in one optional embodiment of the present embodiment, blotter 600 is layed in river bed, bridge
Pier is set to 600 top of blotter.600 construction method of blotter: after river bed excavation pit, packing sedimentation by throwing stones, upper surface
It is laid with rubble, to prevent pier slope, 600 surface of blotter is answered smooth, is located in the same horizontal plane.
The present invention possessed advantage, benefit compared with existing conventional techniques include at least:
1, speed of application is fast.Bridge pier can shift to an earlier date in the prefabricated completion of pre-fabricated factory, once can prefabricated muti-piece, efficiency is higher, to be installed
When be transported to again construction site assembly, effectively accelerate speed of application.
2, difficulty is small.The complicated procedures of forming in cofferdam, drainage of foundation pit is avoided, difficulty of construction is decreased obviously.
3, quality is guaranteed.The factorial production, avoid early stage river water infiltration wash away concrete, improve bridge pier at pier matter
Amount.
4, project amount is small.It eliminates and builds island cofferdam, material is removed, and project amount is considerably reduced.
5, applied widely.
6, convenient disassembly.After completion of works, it is convenient that bridge pier is removed, and can be transported to again after disassembly and carry out repeating benefit elsewhere
With.
The scope of protection of the present invention is not limited to this.Those skilled in the art are made equivalent on the basis of the present invention
Substitution or transformation, it is within the scope of the present invention.Protection scope of the present invention is subject to claims.
Claims (7)
1. a kind of prefabricated assembled suspension bridge bridge pier characterized by comprising the multiple basic units being stacked up, each institute
Stating basic unit includes two prefabricated sections, each described prefabricated section is rectangular shape, and is had parallel, planar
Upper and lower surfaces are provided with the step of rectangular shape in one end of the prefabricated section, and the height of the step is the prefabricated section
The half of thickness, two prefabricated sections mutually overlaps the described of formation and the consistency of thickness of the prefabricated section by the step
Basic unit.
2. prefabricated assembled suspension bridge bridge pier as described in claim 1, which is characterized in that in the outer edge and inner edge of the step
It is provided at least one first mounting hole for penetrating through the prefabricated section between edge, multiple first mounting holes form the vertical
One hole, one first rod piece are set in first hole, and shape matches with first hole.
3. prefabricated assembled suspension bridge bridge pier as claimed in claim 2, which is characterized in that remaining position in addition to the step
Place is additionally provided at least one second mounting hole for penetrating through the prefabricated section, and multiple second mounting holes form second vertical
Hole, one second rod piece are set in second hole, and shape matches with second hole.
4. prefabricated assembled suspension bridge bridge pier as claimed in claim 3, which is characterized in that first mounting hole and described second
Mounting hole is cylinder, and diameter is identical.
5. prefabricated assembled suspension bridge bridge pier as described in claim 1, which is characterized in that be additionally provided on the prefabricated section multiple
Hoisting structure, for installing hook described in handling when prefabricated section.
6. prefabricated assembled suspension bridge bridge pier as claimed in claim 5, which is characterized in that multiple hoisting structures are distributed in institute
It states on upper surface and the lower surface, each described hoisting structure includes pit and the U-shaped reinforcing bar that is set in the pit,
Two free ends of the U-shaped reinforcing bar are anchored in the prefabricated section.
7. prefabricated assembled suspension bridge bridge pier as described in claim 1, which is characterized in that it further include blotter, the rubble
In river bed, the bridge pier is set to above the blotter setting cushion.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811082981.3A CN109137721A (en) | 2018-09-17 | 2018-09-17 | A kind of prefabricated assembled suspension bridge bridge pier |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811082981.3A CN109137721A (en) | 2018-09-17 | 2018-09-17 | A kind of prefabricated assembled suspension bridge bridge pier |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109137721A true CN109137721A (en) | 2019-01-04 |
Family
ID=64814489
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811082981.3A Pending CN109137721A (en) | 2018-09-17 | 2018-09-17 | A kind of prefabricated assembled suspension bridge bridge pier |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109137721A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109778681A (en) * | 2019-03-04 | 2019-05-21 | 北京工业大学 | A kind of modularization Precast Concrete Segmental Bridges railway solid pier |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08333714A (en) * | 1995-06-09 | 1996-12-17 | P S Co Ltd | Constructing method of columnar structure used with hybrid prefabricated segments |
JP2000352108A (en) * | 1999-06-10 | 2000-12-19 | Kajima Corp | Precast block construction |
JP4428304B2 (en) * | 2005-06-29 | 2010-03-10 | 鹿島建設株式会社 | Plastic hinge part of RC structure |
CN202000251U (en) * | 2010-06-09 | 2011-10-05 | 中交第一公路勘察设计研究院有限公司 | Cylindrical hollow prefabricated prestressed concrete pier structure |
CN202611082U (en) * | 2012-05-18 | 2012-12-19 | 周玉 | Z-shaped porous stone face wall brick and lapping structure thereof |
CN104790291A (en) * | 2015-04-22 | 2015-07-22 | 上海市城市建设设计研究总院 | Prefabricated type bridge pier column and connecting method thereof |
CN204825619U (en) * | 2015-08-10 | 2015-12-02 | 江苏建筑职业技术学院 | Assembled concrete bridge mound |
CN107938499A (en) * | 2018-01-11 | 2018-04-20 | 西南科技大学 | A kind of prefabricated assembled bridge pier |
CN108005332A (en) * | 2017-11-28 | 2018-05-08 | 盐城荣平建设工程有限公司 | A kind of reinforced concrete prefabricated board |
CN108385512A (en) * | 2018-03-22 | 2018-08-10 | 北京工业大学 | One kind being based on bolted modular assembly formula Hollow High Pier splicing structure and its practice |
CN108396640A (en) * | 2018-04-23 | 2018-08-14 | 南昌大学 | A kind of assembly concrete pier column structure |
-
2018
- 2018-09-17 CN CN201811082981.3A patent/CN109137721A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08333714A (en) * | 1995-06-09 | 1996-12-17 | P S Co Ltd | Constructing method of columnar structure used with hybrid prefabricated segments |
JP2000352108A (en) * | 1999-06-10 | 2000-12-19 | Kajima Corp | Precast block construction |
JP4428304B2 (en) * | 2005-06-29 | 2010-03-10 | 鹿島建設株式会社 | Plastic hinge part of RC structure |
CN202000251U (en) * | 2010-06-09 | 2011-10-05 | 中交第一公路勘察设计研究院有限公司 | Cylindrical hollow prefabricated prestressed concrete pier structure |
CN202611082U (en) * | 2012-05-18 | 2012-12-19 | 周玉 | Z-shaped porous stone face wall brick and lapping structure thereof |
CN104790291A (en) * | 2015-04-22 | 2015-07-22 | 上海市城市建设设计研究总院 | Prefabricated type bridge pier column and connecting method thereof |
CN204825619U (en) * | 2015-08-10 | 2015-12-02 | 江苏建筑职业技术学院 | Assembled concrete bridge mound |
CN108005332A (en) * | 2017-11-28 | 2018-05-08 | 盐城荣平建设工程有限公司 | A kind of reinforced concrete prefabricated board |
CN107938499A (en) * | 2018-01-11 | 2018-04-20 | 西南科技大学 | A kind of prefabricated assembled bridge pier |
CN108385512A (en) * | 2018-03-22 | 2018-08-10 | 北京工业大学 | One kind being based on bolted modular assembly formula Hollow High Pier splicing structure and its practice |
CN108396640A (en) * | 2018-04-23 | 2018-08-14 | 南昌大学 | A kind of assembly concrete pier column structure |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109778681A (en) * | 2019-03-04 | 2019-05-21 | 北京工业大学 | A kind of modularization Precast Concrete Segmental Bridges railway solid pier |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107313517B (en) | Connecting node for laminated wall and laminated floor slab in middle layer | |
CN105951612B (en) | Stake head bug repairing and reinforcement structure and its construction method under active service bridge water | |
CN104652417A (en) | High-performance concrete corrugated sheet pile, forming die and production method for high-performance concrete corrugated sheet pile | |
CN108035379B (en) | Comprehensive pipe gallery and construction method thereof | |
KR100898945B1 (en) | Concrete arch bridge having water flow path and construction method thereof | |
CN108643133B (en) | Detachable arch dam and construction and dismantling method thereof | |
CN108277750B (en) | Construction method of high-fill deep-thick soft foundation pile-supported large-section porous cast-in-place box culvert | |
CN207327274U (en) | A kind of water channel engineering system | |
CN213508795U (en) | Concrete module type inspection well shaft structure and concrete module brick | |
CN109137721A (en) | A kind of prefabricated assembled suspension bridge bridge pier | |
CN105064500A (en) | Balcony beam slab inner side filling wall body and main body structure integral casting construction method | |
CN210117716U (en) | Trapezoidal foundation ditch lateral wall concrete typical forms of elevartor shaft | |
CN205669211U (en) | A kind of prefabricated Gravity Retaining Wall | |
CN103882883A (en) | Method for constructing foundation shared by tower crane and garage frame column | |
CN110468744A (en) | A kind of channel bridge reinforced construction method | |
CN110438859A (en) | A kind of the precast concrete road and its construction method of draining of catchmenting | |
CN108130889B (en) | Manufacturing method of stepped construction joint between main bottom plate of pump brake and side wall of runner layer | |
CN107288153A (en) | A kind of prefabricated Gravity Retaining Wall | |
CN206220537U (en) | A kind of assembly type truss frame platform | |
CN114718245A (en) | Recycled block/aggregate concrete prefabricated superposed beam and construction method thereof | |
CN211815250U (en) | Road widening roadbed splicing structure | |
CN208201614U (en) | A kind of steel corrugated plating assembling combination bridge | |
CN105970838A (en) | Deck type arch bridge vault padding unloading and reinforcing construction method and application | |
CN204875689U (en) | River levee crown brick and embankment protective structure | |
CN206219996U (en) | Stake head bug repairing and reinforcement structure under active service bridge water |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190104 |
|
RJ01 | Rejection of invention patent application after publication |