KR100539829B1 - 형강을 이용한 거푸집용 갱폼 인양방법 - Google Patents
형강을 이용한 거푸집용 갱폼 인양방법 Download PDFInfo
- Publication number
- KR100539829B1 KR100539829B1 KR10-2003-0052796A KR20030052796A KR100539829B1 KR 100539829 B1 KR100539829 B1 KR 100539829B1 KR 20030052796 A KR20030052796 A KR 20030052796A KR 100539829 B1 KR100539829 B1 KR 100539829B1
- Authority
- KR
- South Korea
- Prior art keywords
- gangform
- retaining wall
- lifting
- building
- formwork
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
- E04G11/20—Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
- E04G11/28—Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
Claims (1)
- 골조용 프레임(11)으로서 일정한 높이를 가지는 골조구조물로 형성되고 그 상단 후방면에는 거푸집(20)이 설치되는 거푸집용 갱폼(10)을 건물의 외벽을 따라 인양시켜 콘크리트 옹벽(14)을 시공하도록 한 것에 있어서,상기 콘크리트 옹벽(14)상에 2 ~ 3단으로 분리되는 한 쌍의 H형강을 연결 고정시킨 상태에서 각각의 H형강 사이로 갱폼(10)을 삽입하여 콘크리트 옹벽(14)상에 고정시키는 갱폼설치단계(A)와,상기 갱폼설치단계(A)를 거친 후, 갱폼(10)의 상단에 설치된 상기 거푸집(20)으로서 1개층에 해당하는 콘크리트 옹벽(14)을 타설하여 양생시키는 옹벽시공단계(B)와,상기 옹벽시공단계(B)를 거친 후, 갱폼(10)의 양측에 설치된 H형강 중 하부형강(23)을 분리하여 그 상부형강(21)의 상단부에 하부형강(23)을 조립 고정시키는 형강분해 및 조립단계(C)와,상기 형강분해 및 조립단계(C)를 거친 후, 그 하부형강(23)의 상단부에 인양기(17)를 설치하여 상기 인양기(17)로서 H형강을 따라 갱폼(10)을 인양시키는 갱폼인양단계(D)를 거치게 되며,상기 옹벽시공단계(B)로부터 갱폼인양단계(D)로 이루어지는 일련의 공정단계를 시공하고자 하는 건물의 높이에 맞추어 반복적으로 행하는 것을 특징으로 하는 형강을 이용한 거푸집용 갱폼 인양방법.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2003-0052796A KR100539829B1 (ko) | 2003-07-30 | 2003-07-30 | 형강을 이용한 거푸집용 갱폼 인양방법 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2003-0052796A KR100539829B1 (ko) | 2003-07-30 | 2003-07-30 | 형강을 이용한 거푸집용 갱폼 인양방법 |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20050014244A KR20050014244A (ko) | 2005-02-07 |
KR100539829B1 true KR100539829B1 (ko) | 2005-12-28 |
Family
ID=37225409
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR10-2003-0052796A KR100539829B1 (ko) | 2003-07-30 | 2003-07-30 | 형강을 이용한 거푸집용 갱폼 인양방법 |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100539829B1 (ko) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100892615B1 (ko) | 2008-07-28 | 2009-04-08 | 최재주 | 갱폼 안전 인양 시스템 |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102140841A (zh) * | 2010-12-31 | 2011-08-03 | 青岛一建集团有限公司 | 高层钢-混凝土混合结构建筑楼盖少支撑模板施工方法 |
KR102096548B1 (ko) * | 2018-08-31 | 2020-04-02 | 호서대학교 산학협력단 | 자동 거푸집 인양 장치 및 이를 이용한 자동 거푸집 인양 방법 |
-
2003
- 2003-07-30 KR KR10-2003-0052796A patent/KR100539829B1/ko active IP Right Grant
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100892615B1 (ko) | 2008-07-28 | 2009-04-08 | 최재주 | 갱폼 안전 인양 시스템 |
WO2010013901A2 (ko) * | 2008-07-28 | 2010-02-04 | 최재주 | 갱폼 안전 인양 시스템 |
WO2010013901A3 (ko) * | 2008-07-28 | 2010-06-10 | 최재주 | 갱폼 안전 인양 시스템 |
Also Published As
Publication number | Publication date |
---|---|
KR20050014244A (ko) | 2005-02-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103635643B (zh) | 高层钢结构建筑钢筋砼筒体的施工方法 | |
CN112458918A (zh) | 一种高墩液压顶升整体式钢架平台翻模施工系统及施工方法 | |
JP3196043B2 (ja) | 階段と階段室の構築方法及び階段の構築方法並びに階段部材 | |
JP2010133084A (ja) | 中空式高構造物の施工方法 | |
KR100539829B1 (ko) | 형강을 이용한 거푸집용 갱폼 인양방법 | |
JPH09317183A (ja) | 建造物構築方法 | |
JP5075398B2 (ja) | 塔状pc構造物の施工方法および緊張システム装置 | |
CN113338537A (zh) | 一种超高、大截面的混凝土框架柱的施工方法 | |
JP7369090B2 (ja) | シャフト壁ユニット | |
JP4027170B2 (ja) | 外部足場装置及び外部足場装置の施工方法 | |
CN112627543A (zh) | 核心筒电梯井钢梁安装用井道内提升架及钢梁施工方法 | |
JP3543246B2 (ja) | 仮設養生体 | |
JPH03125755A (ja) | 筒状高層構造物の施工方法 | |
CN217151146U (zh) | 一种超5米悬挑混凝土模板支撑体系的悬挑钢梁组件 | |
JPH05171809A (ja) | 鉄骨造建物におけるエレベータシャフトの施工法 | |
JP3543247B2 (ja) | 仮設養生体の支持ブラケット | |
JP2001329689A (ja) | 建物の構築方法 | |
JP3281421B2 (ja) | 塔状体に架設される水平梁の構築方法 | |
JPH09296610A (ja) | 外部養生ユニット | |
JPH0642184A (ja) | ハーフpc床板を用いた躯体の構築方法 | |
JP2843042B2 (ja) | 鉄骨建方ユニット足場工法 | |
JPH08199595A (ja) | 擁壁工事用移動足場 | |
JPH11287040A (ja) | 吊り階段 | |
JP3098107B2 (ja) | 地中梁の構築工法 | |
JP3224152B2 (ja) | コンクリート建造物における横梁の築造方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20121010 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20131015 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20141210 Year of fee payment: 10 |
|
FPAY | Annual fee payment |
Payment date: 20161221 Year of fee payment: 12 |
|
FPAY | Annual fee payment |
Payment date: 20171220 Year of fee payment: 13 |
|
FPAY | Annual fee payment |
Payment date: 20191217 Year of fee payment: 15 |