JPH04169620A - Method of supporting multifunctional floor by sheathing wall in inverter-hammering process - Google Patents
Method of supporting multifunctional floor by sheathing wall in inverter-hammering processInfo
- Publication number
- JPH04169620A JPH04169620A JP2295230A JP29523090A JPH04169620A JP H04169620 A JPH04169620 A JP H04169620A JP 2295230 A JP2295230 A JP 2295230A JP 29523090 A JP29523090 A JP 29523090A JP H04169620 A JPH04169620 A JP H04169620A
- Authority
- JP
- Japan
- Prior art keywords
- floor
- retaining wall
- sheathing
- jack
- work
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 16
- 238000010276 construction Methods 0.000 claims abstract description 19
- 238000009412 basement excavation Methods 0.000 abstract description 9
- 239000002689 soil Substances 0.000 abstract description 3
- 238000004140 cleaning Methods 0.000 abstract description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 3
- 238000009415 formwork Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000003780 insertion Methods 0.000 description 1
- 230000037431 insertion Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000000630 rising effect Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は逆打工法における多機能床の山留壁への支持方
法に係るものである。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for supporting a multifunctional floor to a retaining wall in a reverse construction method.
(従来の技術)
逆打ち工法は地盤の掘削に伴って、本設用の地下のPC
a粱、床スラブを構築し、山留壁に作用している土圧、
水圧を支持しながら地下構造物を構築する工法である。(Conventional technology) With the reverse drilling method, when the ground is excavated, underground PC
a. Construction of the floor slab and earth pressure acting on the retaining wall,
This is a method of constructing underground structures while supporting water pressure.
しかしながら逆打ちには、下記に示す欠点がある。However, reverse hitting has the following drawbacks.
1)構築されたPCa梁が山留壁の土、水圧を支持する
までは次の掘削作業が進められない。そのため掘削作業
が一時中断する。1) The next excavation work cannot proceed until the constructed PCa beam supports the soil and water pressure of the mountain retaining wall. As a result, excavation work will be temporarily suspended.
2)掘削後、PCa梁を構築し、山留壁の土、水圧を
支持するまでに相当の時間を要する。この間に 山留壁
の変形が進行する可能性がある。2) After excavation, build PCa beams and reduce the soil and water pressure of the mountain retaining wall.
It takes a considerable amount of time to support it. During this time, deformation of the retaining wall may progress.
3)−船釣に、最下階の階高は大きくなるため、最下階
の掘削作業をするためには、中間に仮設の切梁を構築す
る必要がある。3) - For boat fishing, the height of the lowest floor is large, so in order to excavate the lowest floor, it is necessary to construct a temporary strut in the middle.
本出願人は前記逆打工法の欠点を除去し、省仮設、省労
務、工期短縮、安全性の向上を図った工法として、特願
平1−237216号において「構真柱に作業床を昇降
自在に装架し、同作業床を所定の位置まで下降して山留
壁に圧着せしめて同山留壁の切梁を兼用せしめ、前記作
業床上で地下躯体構築用型枠を組立て支持し、躯体コン
クリートを打設するとともに、前記作業床の下部を掘削
し、前記躯体の打設コンクリートの硬化をまって同作業
床上の型枠を撤去して同作業床を次位の地下躯体の構築
位置まで下降せしめ、以下前記の工程を反覆することを
特徴とする多機能作業床を用いた逆打ち工法。」を提案
した。The present applicant has proposed a construction method that eliminates the disadvantages of the above-mentioned reverse construction method, saves temporary construction, saves labor, shortens the construction period, and improves safety in Japanese Patent Application No. 1-237216. The work floor is freely mounted, lowered to a predetermined position and crimped to the mountain retaining wall so that it also serves as a strut of the mountain retaining wall, and the formwork for constructing the underground framework is assembled and supported on the work floor; At the same time as pouring the concrete for the framework, excavate the lower part of the working floor, wait for the cast concrete for the framework to harden, remove the formwork on the working floor, and use the same working floor as the construction site for the next underground framework. "This is a reverse construction method using a multi-functional work floor, which is characterized by lowering the work surface to a maximum height and then repeating the above steps."
(発明が解決しようとする課題)
前記工法においては、作業床は本設の梁、床スラブが架
設されるまでの期間、山留切梁部材として土圧を支持す
ることになり、前記作業床によって有効に土圧力を支持
するとともに、同作業床の新らたな下降位置において速
やかに、しかも確実に土圧を支持することができる作業
床の山留壁への支持方法の出現が要望されている。(Problems to be Solved by the Invention) In the above construction method, the working floor supports earth pressure as a retaining sill member until the permanent beams and floor slabs are erected, and the working floor There is a need for a method of supporting a work floor to a mountain retaining wall that can effectively support the earth pressure by the work floor, and can also quickly and reliably support the earth pressure at the new lowered position of the work bed. ing.
(課題を解決するための手段)
本発明に係る逆打工法における多機能床の山留壁への支
持方法は、このような要望に応えて提案されたもので、
構真柱に作業床を昇降自在に装架し、同作業床を所定の
位置まで下降して山留壁に圧着せしめて同山留壁の切梁
を兼用せしめ、前記作業床上で地下躯体部を施工すると
ともに、同作業床の下部を掘削し、同作業床を次位の地
下躯体構築位置まで下降せしめ、以下前記の工程を反覆
する逆打工法において、前記作業床と山留壁内側面に架
設された復起しとの間に油圧ジヤツキ群とスクリュージ
ヤツキ群とを介装し、油圧ジヤツキ群によって山留壁の
土圧を支持したのち、スクリュージヤツキ群を作動して
前記作業床と復起しを抑え、しかるのち油圧ジヤツキ群
を除去して下方位置における作業床の山留壁への支持作
業に転用することを特徴とするものである。(Means for Solving the Problems) The method of supporting a multifunctional floor to a retaining wall in the reverse construction method according to the present invention was proposed in response to such demands.
A working floor is attached to the structure pillar so that it can be raised and lowered freely, and the working floor is lowered to a predetermined position and crimped to the retaining wall so that it also serves as a strut for the retaining wall, and the underground frame section is installed on the working floor. At the same time, the lower part of the working floor is excavated and the working bed is lowered to the next underground structure construction position. In the reverse construction method, which repeats the above process, the working floor and the inner side of the retaining wall are A group of hydraulic jacks and a group of screw jacks are interposed between the restoring structure constructed at This method is characterized by suppressing the floor and rising, and then removing the hydraulic jack group and reusing it for supporting work on the mountain retaining wall of the working floor at the lower position.
〔作用)
本発明によれば前記したように、作業床が構真柱に沿っ
て所定位置までリフトダウンすると、直ちに山留壁内側
面に架設された復起しとの間に架設されたジヤツキ群の
うち、油圧ジヤツキ群を操作して速やかに山留壁の土圧
を支持する。[Function] According to the present invention, as described above, when the work floor is lifted down to a predetermined position along the main structure pillar, the jack installed between it and the lift installed on the inner side of the retaining wall is immediately lifted down to a predetermined position. Of the group, the hydraulic jack group is operated to quickly support the earth pressure of the mountain retaining wall.
この状態でスクリュージヤツキ群を操作し、伸長するこ
とによって作業床と復起しとを抑え、同作業床をリフト
ダウン位置に確固と固定し、同作業床上で所要の作業を
行なうとともに、作業床の下部の掘削を行なうことがで
きる。In this state, the screw jack group is operated and extended to prevent the work floor from lifting up, securely fix the work floor in the lift-down position, perform the required work on the work floor, and perform the work. Excavation of the lower part of the floor can be carried out.
このように前記スクリュージヤツキ群によって作業床を
固定したのち、油圧ジヤツキ群を取外し、下階部分にお
ける作業床の固定作業に転用するものである。After the work floor is fixed by the screw jack group in this way, the hydraulic jack group is removed and used for the work of fixing the work floor on the lower floor.
(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.
第1次掘削を終了したのち、本設床スラブとして構成さ
れた高剛性の作業床1を構築し、構真柱2に昇降自在に
装架する。After the first excavation is completed, a highly rigid working floor 1 configured as a permanent floor slab is constructed and mounted on the structure pillar 2 so as to be movable up and down.
図中3は作業床1に設けた作業床懸吊用pc鋼線4の挿
通孔、5及び6は夫々作業床1に設けた土砂搬出用ピッ
ト及びPC部材搬入用ピットである。In the figure, reference numeral 3 indicates an insertion hole for a PC steel wire 4 for suspending the work floor provided on the work floor 1, and 5 and 6 indicate a pit for transporting earth and sand and a pit for bringing in PC members provided on the work floor 1, respectively.
作業床1と山留壁7との間は、復起し材、ジヤツキ群取
付のため、1.0m程度の間隔を設ける。A distance of about 1.0 m is provided between the work floor 1 and the retaining wall 7 in order to attach the lifting material and the jack group.
次いで山留壁7の掘削面の清掃を行ったのち、復起し8
を架設する。Next, after cleaning the excavated surface of the mountain retaining wall 7, it was erected.
erect.
同復起し8と前記作業床1との間には、2台のスクリュ
ージヤツキ9と4台の加力能力100トン程度の油圧ジ
ヤツキ10を介装し、同油圧ジヤツキ10で山留壁7に
かかる土圧を支持し、この状態でスクリュージヤツキ9
を伸長して作業床1と復起し8を抑え、作業床1を固定
したのち、油圧ジヤツキ10を撤去する。Two screw jacks 9 and four hydraulic jacks 10 with a force application capacity of about 100 tons are interposed between the hoisting machine 8 and the work floor 1, and the hydraulic jacks 10 are used to create a retaining wall. Support the earth pressure applied to 7, and in this state screw jack 9
After the work floor 1 is extended and the work floor 1 and the work floor 8 are fixed, the hydraulic jack 10 is removed.
なお前記の作業は作業床1の相対する両端で行なう。Note that the above-mentioned work is performed at opposite ends of the work floor 1.
前記作業床1を固定したのち、本設の梁、スラブを架設
するとともに作業床1の下部を掘削し、しかるのちスク
リュージヤツキ9を撤去し、以下前記の工程を反覆する
。After fixing the working floor 1, the permanent beams and slabs are erected, and the lower part of the working floor 1 is excavated.Then, the screw jack 9 is removed, and the above steps are repeated.
(発明の効果)
本発明によれば前記したように逆打工法において、作業
床と山留壁内側面に架設された復起しとの間に、油圧ジ
ヤツキ群とスクリュージャ、キ群とを介装し、油圧ジヤ
ツキ群によって掘削を終了後、ただちに山留壁の土圧を
支持することが可能となるので、山留壁の変形を最小限
に抑えることができ、工事の安全性が向上するとともに
、前記スクリュージヤツキによって、リフトダウンされ
た作業床を山留壁内側面に架設された復起しに確実に固
定することができる。また同スクリュージヤツキによっ
て作業床を固定したのちは、前記油圧ジヤツキを取外し
て転用しうるものである。(Effects of the Invention) According to the present invention, in the reverse construction method as described above, a group of hydraulic jacks, a screwer, and a group of screws are installed between the work floor and the backing built on the inner surface of the retaining wall. As the earth pressure of the retaining wall can be supported immediately after excavation is completed using a group of hydraulic jacks, deformation of the retaining wall can be minimized, improving construction safety. At the same time, the screw jack can reliably fix the lifted-down work floor to the backrest installed on the inner surface of the retaining wall. Further, after the work floor is fixed with the same screw jack, the hydraulic jack can be removed and used for other purposes.
而してこの際、切梁材を兼用する作業床として最下階の
本設スラブ又は耐圧盤を用いることによって、剛性が高
く確実な山留支持が可能となる。At this time, by using a permanent slab or pressure platen on the lowest floor as a working floor that also serves as a strut material, it becomes possible to provide high rigidity and reliable support for the pile.
また本発明によればすべての作業が、作業床上での作業
となるため、安全性、作業の効率化を図ることができる
。Further, according to the present invention, all work is performed on the work floor, so safety and work efficiency can be improved.
第1図は本発明に係る逆打工法における多機能床の山留
壁への支持方法の一実施例の実施状況を示す平面図、第
2図及び第3図は夫々油圧ジャ。
キ及びスクリュージヤツキの設置部を示す側面図、第4
図及び第5図は夫々逆打工法の実施状況を示す緬断面図
並に平面図である。
1・・・作業床、 2・・・構真柱、7・・・山
留壁、 8・・・復起し、9・・・スクリュージ
ャ、キ、
10・・・油圧ジヤツキ。
代理人 弁理士 岡 本 重 文
外1名
第1図
第2図
第3図FIG. 1 is a plan view showing an embodiment of the method for supporting a multi-functional floor to a retaining wall in the reverse construction method according to the present invention, and FIGS. 2 and 3 are hydraulic jacks, respectively. Side view showing the installation part of the key and screw jack, No. 4
5 and 5 are a cross-sectional view and a plan view, respectively, showing the implementation status of the reverse pouring method. 1... Working floor, 2... Structural pillar, 7... Retaining wall, 8... Rearranging, 9... Screw jar, Ki, 10... Hydraulic jack. Agent: Patent attorney Shige Okamoto (1 person) Figure 1 Figure 2 Figure 3
Claims (1)
位置まで下降して山留壁に圧着せしめて同山留壁の切梁
を兼用せしめ、前記作業床上で地下躯体部を施工すると
ともに、同作業床の下部を掘削し、同作業床を次位の地
下躯体構築位置まで下降せしめ、以下前記の工程を反覆
する逆打工法において、前記作業床と山留壁内側面に架
設された腹起しとの間に油圧ジャッキ群とスクリュージ
ャッキ群とを介装し、油圧ジャッキ群によって山留壁の
土圧を支持したのち、スクリュージャッキ群を作動して
前記作業床と腹起しを抑え、しかるのち油圧ジャッキ群
を除去して下方位置における作業床の山留壁への支持作
業に転用することを特徴とする逆打工法における多機能
床の山留壁への支持方法。A working floor is attached to the structure pillar so that it can be raised and lowered freely, and the working floor is lowered to a predetermined position and crimped to the retaining wall so that it also serves as a strut for the retaining wall, and the underground frame section is installed on the working floor. At the same time, the lower part of the working floor is excavated and the working bed is lowered to the next underground structure construction position. In the reverse construction method, which repeats the above process, the working floor and the inner side of the retaining wall are A group of hydraulic jacks and a group of screw jacks are interposed between the work floor and the raised bed, and after the hydraulic jack group supports the earth pressure of the retaining wall, the screw jack group is operated to connect the work floor and the bed. A method for supporting a multi-functional floor to a retaining wall in a reverse hammering method, which is characterized by suppressing uplift, then removing a group of hydraulic jacks, and reusing the work floor for supporting the retaining wall at a lower position. .
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2295230A JPH04169620A (en) | 1990-11-02 | 1990-11-02 | Method of supporting multifunctional floor by sheathing wall in inverter-hammering process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2295230A JPH04169620A (en) | 1990-11-02 | 1990-11-02 | Method of supporting multifunctional floor by sheathing wall in inverter-hammering process |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH04169620A true JPH04169620A (en) | 1992-06-17 |
Family
ID=17817898
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2295230A Pending JPH04169620A (en) | 1990-11-02 | 1990-11-02 | Method of supporting multifunctional floor by sheathing wall in inverter-hammering process |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH04169620A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100753021B1 (en) * | 2006-11-13 | 2007-08-30 | 주식회사 시티기술단 | The subterranean soil flow wall construction method which formed the institution thing installation space part using main girder compression reaction |
JP2016223084A (en) * | 2015-05-28 | 2016-12-28 | 大成建設株式会社 | Construction method of underground structure by inverted construction method |
JP2017025602A (en) * | 2015-07-23 | 2017-02-02 | 株式会社竹中工務店 | Construction method of new construction object |
-
1990
- 1990-11-02 JP JP2295230A patent/JPH04169620A/en active Pending
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100753021B1 (en) * | 2006-11-13 | 2007-08-30 | 주식회사 시티기술단 | The subterranean soil flow wall construction method which formed the institution thing installation space part using main girder compression reaction |
JP2016223084A (en) * | 2015-05-28 | 2016-12-28 | 大成建設株式会社 | Construction method of underground structure by inverted construction method |
JP2017025602A (en) * | 2015-07-23 | 2017-02-02 | 株式会社竹中工務店 | Construction method of new construction object |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20090002344A (en) | Land-side protection wall that use ground structure | |
JP4069509B2 (en) | Construction method of reverse struts in the outer periphery of underground excavation space | |
JP2684155B2 (en) | Excavation method used for construction of underground structures | |
JP3850785B2 (en) | Caisson laying method using main foundation pile | |
JP2741259B2 (en) | Reverse construction method and multifunctional work floor using multifunctional work floor | |
JPH04169620A (en) | Method of supporting multifunctional floor by sheathing wall in inverter-hammering process | |
KR20210053497A (en) | Fileless-up wall demolition method | |
JP3248458B2 (en) | Shoring construction underground construction method | |
KR0179708B1 (en) | Working method for underground structure of a building | |
JPH09144049A (en) | Temporary holding method of construction | |
JP2004176434A (en) | Method for constructing structure and underground skeleton | |
JP3057466B2 (en) | How to build underground structures | |
JPH05179647A (en) | Supporting structure for earth retaining wall | |
JP2008255636A (en) | Construction method for rc girder | |
JPH11140892A (en) | Method for excavating ground and method for constructing underground structure using the same | |
JPH06341154A (en) | Construction of underground building frame | |
KR100593203B1 (en) | a deck supportframe and a construction methed | |
JPH04319121A (en) | Construction of underground base of building | |
JPH0730564B2 (en) | Construction method of underground structure | |
CN113529733B (en) | Deep foundation pit excavation supporting method | |
JP3234442B2 (en) | Building and scrap type building method | |
JP2829573B2 (en) | Segment press-fitting method | |
JPH04189922A (en) | Consturction method for underground structure using core section | |
JPS5921831A (en) | Reverse placement work | |
JPH03147926A (en) | construction method for basement |