JPS5921831A - Reverse placement work - Google Patents

Reverse placement work

Info

Publication number
JPS5921831A
JPS5921831A JP57131548A JP13154882A JPS5921831A JP S5921831 A JPS5921831 A JP S5921831A JP 57131548 A JP57131548 A JP 57131548A JP 13154882 A JP13154882 A JP 13154882A JP S5921831 A JPS5921831 A JP S5921831A
Authority
JP
Japan
Prior art keywords
mud
raft
water
ground
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP57131548A
Other languages
Japanese (ja)
Inventor
Shiro Kawatani
史郎 河谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP57131548A priority Critical patent/JPS5921831A/en
Publication of JPS5921831A publication Critical patent/JPS5921831A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Abstract

PURPOSE:To raise the efficiency and safety of construction work by a method in which the height of a raft floated on mud water is adjusted by varying the amount of mud water to a given height, and a mud-water excavator is set below the raft and operated. CONSTITUTION:A sheathing wall 1 and plural reversely placed pillars 2 are constructed under the ground E, and the ground F is excavated to a depth that a mud-water excavator 10 can reach by an excavator (not illustrated). Mud water 12 is charged through a hose 11 into the inside of the sheathing wall 1 and float a raft 13 on the mud water. Under the condition, the ground F is further excavated by the mud-water excavator 10, the height of the raft 13 is adjusted by the amount of the mud water 12, and cut beams 5, floor and ceilings 8, and side walls 9 are constructed on the raft 13 by workers M to complete a given structure. The needs for complicated temporary scaffolds can be eliminated, the working efficiency can be raised, and the safety of the work can also be raised because the mud-water excavator 10 is located away from workers.

Description

【発明の詳細な説明】 本発明は、地下ないし地下から地上Kかけて建造物を構
築するための逆打ち工法に関し、特に、作業が容易で安
全性が高くなるようにした逆打ち工法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a reverse construction method for constructing a building underground or from underground to above ground, and particularly to a reverse construction method that facilitates work and improves safety.

従来の逆打ち工法を第1〜2図に基づいて説明する。The conventional reverse pouring method will be explained based on FIGS. 1 and 2.

従来の施工方法によると、第1図に示すように、先ず山
留め壁1および該山留め壁1の内側に位置される複数の
逆打ち柱2を地中Eに構築する。尚、山留め壁1け既知
の地下連続壁の工法等と同じ方法で造られる。また、逆
打ち柱2は一般にH型鋼等からなり、下端部はビアー3
により固定されている。
According to the conventional construction method, as shown in FIG. 1, first, a retaining wall 1 and a plurality of reverse pillars 2 located inside the retaining wall 1 are constructed underground E. The retaining wall will be constructed using the same method as the known construction method for underground continuous walls. In addition, the reverse column 2 is generally made of H-shaped steel, etc., and the lower end has a via 3.
Fixed by

次に、パックホウやユンr等の掘削機4により山留め壁
1の内側の地盤Fを掘り下げて行き、同時に地上に近い
側から逆打ち柱2間に切梁5を架設する作業を進めて行
く。尚、一般に地上でも逆打ち柱2に並通の柱6を継ぎ
足して、該柱6間に通常の梁7が架設され、地上部分の
建造物の構築が進められる。
Next, the ground F inside the retaining wall 1 is dug using an excavator 4 such as a pack hoe or a yun r, and at the same time, the work of constructing the struts 5 between the reverse pillars 2 is proceeded from the side close to the ground. Generally, even on the ground, parallel columns 6 are added to the reverse columns 2, and normal beams 7 are erected between the columns 6 to proceed with the construction of the above-ground portion of the building.

」二記切梁5の作り方としては、一般に逆打ち柱2間に
■型鋼等の鉄骨(図示せず)を架設して、該鉄骨周囲に
鉄筋を巻き、その周囲に型枠を組んでコンクリートを打
設する方法が採られている。
The general method for making the sill 5 is to erect a steel frame (not shown), such as a type steel, between the reverse-strength columns 2, wrap reinforcing bars around the steel frame, and construct a formwork around it to form concrete. A method of pouring is used.

切梁5は山留め壁1にかかる土庄を支持する作用もする
The struts 5 also function to support the earthen wall placed on the retaining wall 1.

次に、第2図に示すように、掘削機4により更に掘削を
進めると同時に、地上に近い切梁5周囲には、床兼天井
材8と側壁9等をコンクリート等により構築し、以下、
地下側に向けて同様の作業を繰り返して行き、所要の建
造物を完成する。尚、前記側壁9としては、出留め壁1
とは別体のものにする場合と、出留め壁1をそのまま利
用する場合とがある。また、出留め壁1にかかる土庄を
支える方法としては、前記切梁5以外に図示しないアン
カー等を用いる方法もある。工事が完了した後は、ダメ
穴等を通して掘削機4等が引き上げられる。
Next, as shown in FIG. 2, while further excavation is carried out by the excavator 4, a floor/ceiling material 8, side walls 9, etc. are constructed of concrete etc. around the strut 5 near the ground.
Repeat the same work towards the underground side to complete the required structure. In addition, as the side wall 9, the retaining wall 1
There are cases where it is made separate from the wall 1, and cases where the retaining wall 1 is used as is. Further, as a method of supporting the earthen wall on the retaining wall 1, there is also a method of using an anchor or the like (not shown) in addition to the strut 5. After the construction is completed, the excavator 4, etc. is pulled up through the damaged hole.

しかし、上記した従来の逆打ち工法によると、切梁5等
を構築する労働者Mが掘削機4の近くで作業する者と並
行して作業をすることになるので危険性が高くなる問題
がある。また、掘り下げられた地盤F lから施工中の
切梁5捷での高さが高くなるので、相応の作業台や足場
を作るいわゆる仮設作業が必要となり、作業が難しくな
る問題がある。
However, according to the conventional reverse construction method described above, the worker M who constructs the struts 5 etc. has to work in parallel with the person working near the excavator 4, which increases the risk of danger. be. In addition, since the height of the five struts under construction from the excavated ground Fl will be higher, so-called temporary construction work will be required to construct appropriate work platforms and scaffolding, making the work difficult.

本発明は、このような従来の問題を解消するためになさ
れたもので、安全性が高く目一つ作業能率が向上する逆
打ち工法を提供することを目的とする。
The present invention was made to solve these conventional problems, and an object of the present invention is to provide a reverse pouring method that is highly safe and significantly improves work efficiency.

本発明の要旨は、山留め壁および該山留め壁の内側に位
置される逆打ち柱を地中に構築する工程と、前記山留め
壁の内側の地盤をほぼ泥水掘削機械が入る深さまで掘り
下げる工程と、前記出留め壁の内側に泥水を注入する工
程と、前記山留め壁の内側の泥水上に筏を浮べる工程と
、前記泥水掘削機械により泥水掘削を行ないながら泥水
量を調整して前記後の高さを順次降下させ、該筏の上方
で山留め壁の内側に逆打ち躯体な構築する工程とを具備
する逆打ち工法にある。
The gist of the present invention is a step of constructing a retaining wall and a reverse pillar located inside the retaining wall in the ground, a step of digging the ground inside the retaining wall to a depth that a mud excavation machine can enter, A step of injecting muddy water into the inside of the retaining wall, a step of floating the raft on the muddy water inside the retaining wall, and a step of adjusting the amount of muddy water while excavating the muddy water with the muddy water excavation machine to increase the height after the above-mentioned height. The method includes the steps of lowering the raft one after another and constructing an inverse structure inside the retaining wall above the raft.

以下、第3図〜第4図に示す−・実施例により本発明を
説明する。尚、従来と同一の物には同一・の符号を用い
て説明する。
Hereinafter, the present invention will be explained with reference to examples shown in FIGS. 3 and 4. Incidentally, the same reference numerals are used in the explanation for the same parts as in the prior art.

本実施例の工法では、第3図に示すように先ず従来と同
様の方法で出留め壁1、および該山留め壁1の内側に位
置される複数の逆打ち柱2を地中Eに構築する。
In the construction method of this embodiment, as shown in FIG. 3, first, a retaining wall 1 and a plurality of reverse pillars 2 located inside the retaining wall 1 are constructed underground E using a method similar to the conventional method. .

次に、バックホウのような掘削機4 (第1〜2図参照
)を地上に置いて、山留め壁1の内側の地盤Fをほぼ泥
水掘削機10が入る深さく約地下1階分位の深さ)まで
掘り下げる。
Next, an excavator 4 such as a backhoe (see Figures 1 and 2) is placed on the ground, and the ground F inside the retaining wall 1 is dug to a depth that is approximately the same as the depth of one basement floor into which the mud excavator 10 can fit. Dig down to ).

次いで、山留め壁1の内・側にホース11から泥水12
を注入し、該泥水12上に作業用足場となる筏13を浮
べる。
Next, muddy water 12 is poured from the hose 11 onto the inside/side of the retaining wall 1.
is injected into the muddy water 12, and a raft 13 serving as a scaffold for work is floated on top of the muddy water 12.

この状態で、前記泥水掘削機械10により地盤Fの泥水
掘削を進め、筏13の高さは泥水12の量により調節す
る。筏13上では、労働者Mが前記した切梁5等の逆打
ち躯体な構築する作業を行なう。尚、前記泥水掘削機1
0により掘削された土砂はホース14を介してポンプ1
5により吸引され、沈砂槽16に送られる。該沈砂槽1
6で土砂から分離された泥水が前記ホース11により前
記地盤F上に注入される。また、沈砂槽16で泥水から
分離された土砂は水分離装置17に送られ、ここから所
定の場所へ連ばれ廃棄される。尚、地」二では柱6及び
梁7等の構築作業が行なわれている0 次に、第4図に示すように、地盤Fの泥水掘削を進める
と同時に、切梁5周辺に従来と同様の床兼天井材8と側
壁9等の逆打ち躯体を構築して行き、所望の建造物を完
成する。
In this state, the muddy water excavation of the ground F is carried out by the muddy water excavation machine 10, and the height of the raft 13 is adjusted according to the amount of muddy water 12. On the raft 13, the worker M performs the work of constructing the above-mentioned inverted structure of the struts 5 and the like. In addition, the muddy water excavator 1
The earth and sand excavated by 0 is sent to pump 1 via hose 14.
5 and sent to the sand settling tank 16. The sand settling tank 1
The muddy water separated from the earth and sand in step 6 is injected onto the ground F through the hose 11. Further, the earth and sand separated from the muddy water in the sand settling tank 16 is sent to a water separator 17, from where it is taken to a predetermined location and disposed of. Construction work for pillars 6, beams 7, etc. is being carried out on ground 2.Next, as shown in Figure 4, muddy excavation of ground F is proceeding, and at the same time, construction work is being carried out around struts 5 in the same way as before. The floor/ceiling material 8, side walls 9, etc., are constructed to complete the desired building.

工事が完了した後は、エレベータ、階段、ダメ孔等を通
して泥水掘削機械10を引き上げ、筏13は分解して引
き上げる。
After the construction is completed, the mud excavation machine 10 is pulled up through an elevator, stairs, a damaged hole, etc., and the raft 13 is disassembled and pulled up.

上記泥水掘削機械10は、筏13の下面に変向レールや
リフトを設けてこれらにより移動させたり、水中ブルド
ーザ−の如き車両に積んで移動させることができ、また
リモートコントロール装置により地上や筏13上から遠
隔操作することも可能である。このように、泥水掘削機
械10は作業員が直接操作する必要がないので、無人化
工法が可能となり、特に作業が遅れがちな掘削作業は−
昼夜作業が可能となり躯体構築作業との平準化が容易と
なる。
The muddy water excavation machine 10 can be moved by installing a direction changing rail or a lift on the underside of the raft 13, or by being loaded onto a vehicle such as an underwater bulldozer, or can be moved on the ground or on the raft 13 by a remote control device. It can also be controlled remotely from above. In this way, since the mud water excavation machine 10 does not require direct operation by a worker, unmanned construction methods are possible, especially for excavation work that tends to be delayed.
It is possible to work day and night, making it easier to level the work with the framework construction work.

以上説明してきたように本発明では、泥水上に浮べた筏
の高を最適な高さに容易に調整して作業台とすることが
できるので、従来の如き複雑な仮設の足場が不要となり
作業能率が向上する利点がある。また、泥水掘削機械が
労働者や作業員とは完全に離れて筏の下方に位置される
ので、安全性が高くなる長所もある。更に、泥水掘削を
行なうので、無振動、無騒音工法が可能になる利点も得
られる。
As explained above, according to the present invention, the height of the raft floating on muddy water can be easily adjusted to the optimal height and used as a work platform, eliminating the need for complicated temporary scaffolding as in the past. This has the advantage of improving efficiency. Another advantage is that the mud drilling machine is located below the raft, completely away from the workers and workers, which increases safety. Furthermore, since muddy water excavation is carried out, there is also the advantage that vibration-free and noise-free construction methods are possible.

【図面の簡単な説明】[Brief explanation of drawings]

第1図及び第2図は夫々従来の逆打ち工法の工程を示す
断面説明図、第3図及び第4図は夫々本発明の一実施例
に係る逆打ち工法の工程を示す断面説明図である。 1・・・山留め壁     2・・・逆打ち柱5・・・
切梁(逆打ち躯体)8・・・床兼天井材(逆打ち躯体)
9・・・側壁(逆打ち躯体)10・・・泥水掘削機械1
2・・・泥水      13・・・筏E・・・地中 
      F・・・地盤。 特許出願人 三井建設株式会社 第3図 第4図 手続補正書 昭和58年2月8日 特許庁長官  若 杉 和 夫  殿 1、事件の表示   特願昭57−131548号2、
発明の名称   逆打ち工法 3、補正をする者 事件との関係  特許出願人 東京都 千代田区 岩本町 3丁目10番1号三 井 
建 設 株式会社 代表取締役社長 町 1)良 治 4、代理人 東京都港区新橋1丁目18番19号キムラヤ大塚ヒル6
階第1図 第2図 第3図 第4図 に0−
FIGS. 1 and 2 are cross-sectional explanatory diagrams showing the steps of the conventional reverse pouring method, respectively, and FIGS. 3 and 4 are cross-sectional explanatory diagrams showing the steps of the reverse pouring method according to an embodiment of the present invention, respectively. be. 1... Mountain retaining wall 2... Reverse pillar 5...
Stray beam (reverse-build frame) 8...Floor and ceiling material (reverse-build frame)
9... Side wall (reverse hammered frame) 10... Mud water excavation machine 1
2...Muddy water 13...Raft E...Underground
F...Ground. Patent applicant Mitsui Construction Co., Ltd. Figure 3 Figure 4 Procedural amendment February 8, 1980 Director of the Patent Office Kazuo Wakasugi 1, Indication of case Patent application No. 131548-1982 2,
Title of the invention: Reverse pouring method 3, relationship with the amended case Patent applicant: Mitsui, 3-10-1 Iwamoto-cho, Chiyoda-ku, Tokyo
Construction Representative Director and President Town Co., Ltd. 1) Ryoji 4, Agent Kimraya Otsuka Hill 6, 1-18-19 Shinbashi, Minato-ku, Tokyo
0- on floor 1, 2, 3, 4

Claims (2)

【特許請求の範囲】[Claims] (1)  出留め壁および該山留め壁の内側に位置され
る逆打ち柱を地中に構築する工程と、前記山留め壁の内
側の地盤をほぼ泥水掘削機械が入る深さまで掘り下げる
工程と、前記山留め壁の内側に泥水を注入する工程と、
前記山留め壁の内側の泥水上に筏を浮べる工程と、前記
泥水掘削機械により泥水掘削を行ないながら泥水量を調
整して前記後の高さを順次降下させ、該筏の上方で山留
め壁の内側に逆打ち躯体を構築する工程とを具備する逆
打ち工法。
(1) A step of constructing a retaining wall and a reverse pillar located inside the retaining wall in the ground, a step of digging the ground inside the retaining wall to a depth that a mud excavation machine can enter, and a step of constructing the retaining wall. The process of injecting muddy water into the inside of the wall,
A step of floating the raft on the muddy water inside the retaining wall, and adjusting the amount of muddy water while excavating muddy water with the muddy water excavation machine to sequentially lower the height above the raft and inside the retaining wall. A reverse construction method comprising the steps of constructing a reverse concrete structure.
(2)前記泥水掘削機械はリモートコントロール装置に
より操作されることを特徴とする特許請求の範囲第1項
記載の逆打ち工法。
(2) The reverse drilling method according to claim 1, wherein the muddy water excavation machine is operated by a remote control device.
JP57131548A 1982-07-28 1982-07-28 Reverse placement work Pending JPS5921831A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP57131548A JPS5921831A (en) 1982-07-28 1982-07-28 Reverse placement work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP57131548A JPS5921831A (en) 1982-07-28 1982-07-28 Reverse placement work

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP588183A Division JPS5921822A (en) 1983-01-19 1983-01-19 Mud-water excavation work

Publications (1)

Publication Number Publication Date
JPS5921831A true JPS5921831A (en) 1984-02-03

Family

ID=15060646

Family Applications (1)

Application Number Title Priority Date Filing Date
JP57131548A Pending JPS5921831A (en) 1982-07-28 1982-07-28 Reverse placement work

Country Status (1)

Country Link
JP (1) JPS5921831A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104481030A (en) * 2013-06-14 2015-04-01 孔志坚 Synchronous construction method of basement with underground continuous wall and main body
CN104612161A (en) * 2013-06-14 2015-05-13 孔志坚 Method for reversed construction of foundation pit with underground diaphragm wall
CN105756067A (en) * 2016-03-11 2016-07-13 天津市建工工程总承包有限公司 Method for horizontally and temporarily supporting and changing support in deep foundation pit

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104481030A (en) * 2013-06-14 2015-04-01 孔志坚 Synchronous construction method of basement with underground continuous wall and main body
CN104612161A (en) * 2013-06-14 2015-05-13 孔志坚 Method for reversed construction of foundation pit with underground diaphragm wall
CN105756067A (en) * 2016-03-11 2016-07-13 天津市建工工程总承包有限公司 Method for horizontally and temporarily supporting and changing support in deep foundation pit

Similar Documents

Publication Publication Date Title
US3226933A (en) Sheeting wall system and method of constructing same
KR100877974B1 (en) Reverse removing method of underground retaining wall using bottom-up cut and gradual land infilling with struts
KR20210053497A (en) Fileless-up wall demolition method
JPS5921831A (en) Reverse placement work
JPH0559728A (en) Sheathing work above underground structure
JPH0684690B2 (en) Building basement extension method
JPH09144049A (en) Temporary holding method of construction
JP3133598B2 (en) Construction method of small and medium-sized building with basement floor
JPH06341154A (en) Construction of underground building frame
JPH0721196B2 (en) Reverse construction method of underground structure
KR102500013B1 (en) Method for constructing underground structure
JP2996113B2 (en) How to build a shaft
CN216689436U (en) Prefabricated wallboard convenient to installation
CN114875925B (en) Construction method of oversized deep foundation pit of subway tunnel adjacent to sea-filling stratum
JP2963802B2 (en) How to build an underground parking
JPH07138972A (en) Construction method for underground skeleton
JPH04189922A (en) Consturction method for underground structure using core section
JP2821933B2 (en) Underground structure construction method
JPH03147926A (en) construction method for basement
Enami et al. Demolition Method for Reinforced Concrete Underground Structures in Japan (Part 3, Practical Examples of Demolition Procedure)
JPS5921822A (en) Mud-water excavation work
JP2838019B2 (en) Caisson blade framing method
JPH0742179A (en) Modified inversion placing construction method
CN115369916A (en) Underground building construction method
JPS63277342A (en) Reverse execution of underground story