JP2821933B2 - Underground structure construction method - Google Patents

Underground structure construction method

Info

Publication number
JP2821933B2
JP2821933B2 JP8376290A JP8376290A JP2821933B2 JP 2821933 B2 JP2821933 B2 JP 2821933B2 JP 8376290 A JP8376290 A JP 8376290A JP 8376290 A JP8376290 A JP 8376290A JP 2821933 B2 JP2821933 B2 JP 2821933B2
Authority
JP
Japan
Prior art keywords
excavation
underwater
excavator
room
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP8376290A
Other languages
Japanese (ja)
Other versions
JPH03281828A (en
Inventor
秀雄 大村
博 堀江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP8376290A priority Critical patent/JP2821933B2/en
Publication of JPH03281828A publication Critical patent/JPH03281828A/en
Application granted granted Critical
Publication of JP2821933B2 publication Critical patent/JP2821933B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、地下構造物あるいはその上に地上部建屋
を有する構造物などの地中構造物を構築する工法、特に
築造しようとする構造物を自重とその底部に充填した水
の圧力とをバランスさせながら下方を水中掘削すること
により、沈設する工法に関するものである。
The present invention relates to a method of constructing an underground structure such as an underground structure or a structure having an above-ground building thereon, particularly a structure to be constructed. Underwater excavation underwater while balancing its own weight and the pressure of the water filled into the bottom thereof.

「従来の技術、発明が解決せんとする問題点」 従来、地中に構造物を築造する工法として、山留支保
工による開削工法や、ニューマチックケーソンあるいは
オープンケーソンによる築造工法等が一般に知られてい
る。
"Conventional technologies and problems to be solved by the invention" Conventionally, as a method of constructing a structure underground, there are generally known methods such as a digging method using a stake, a pneumatic caisson or an open caisson. ing.

しかしながら、山留支保工による開削工法において
は、山留壁外部の地下水圧および土圧によって山留壁へ
荷重が加わるために、山留壁を強固なものとしなければ
ならず、それによって山留壁にかかわる工費がかさむと
いう問題があった。
However, in the open-cutting method using the shoring support, since the load is applied to the shoring due to groundwater pressure and earth pressure outside the shoring, the shoring must be strengthened. There was a problem that the construction cost related to the wall was increased.

また、ニューマチックケーソンによる築造工法におい
ては、圧気作業による作業者に対する安全性の問題、沈
設に伴って構造物へ偏荷重が作用するという施工の不安
定性、周辺摩擦による沈設不能、高度な掘削精度の要
求、さらには施工時の条件によって定まる作業室スラブ
としての下床板の過大設計など、地中構造物の構築に当
って種々の問題があった。
In the construction method using a pneumatic caisson, safety issues for workers due to pneumatic work, instability of construction due to the imbalanced load acting on the structure due to subsidence, inability to settle due to peripheral friction, high excavation precision There are various problems in the construction of the underground structure, such as the excessive design of the lower floor plate as a working room slab determined by the requirements of the construction and the conditions at the time of construction.

さらに、オープンケーソン工法においては、掘削時の
姿勢制御および位置制御が難しく、また地下水圧および
土圧などの問題から深い掘削は望めないなどの問題があ
った。
In addition, the open caisson method has problems that it is difficult to control the attitude and position during excavation, and that deep excavation cannot be expected due to problems such as groundwater pressure and earth pressure.

そこで、出願人らは地中構造物構築工法として、山留
壁の内部に水を溜めて築造しようとする構造物の下部を
その山留壁内部の水上に浮かべ、この構造物の下方の地
盤を掘削機によって水中掘削し、この掘削の進行と並行
して構造物の下部上に順次構造物の上部を一連に立ち上
げ、この構造物の重量あるいはこれに付加した荷重を均
衡させながら構造物の所定の位置に沈設する工法を提案
した(特願平1−132453号)。
Therefore, the applicants used an underground structure construction method in which the lower part of a structure to be built by storing water inside the retaining wall was floated on the water inside the retaining wall, and the ground below the structure was Is excavated underwater by an excavator, and the upper part of the structure is sequentially raised on the lower part of the structure in parallel with the progress of the excavation, and the weight of the structure or the load added thereto is balanced while the structure is (Japanese Patent Application No. 1-132453).

しかしながら、上記工法においては、山留支保工によ
る開削工法と比べては簡易ではあるが、山留壁を必要と
するので、そのための工期および工費がかかる等の問題
があった。
However, although the above-mentioned construction method is simpler than the open-cutting method using the shoring support, the shoring wall is required, and thus there is a problem that the construction period and the construction cost are required.

「問題点を解決するための手段」 この発明は前記従来の課題を解決するために、下方が
開放された掘削室を底部に設け、その掘削室上の床部に
連通開口を設けた構造物下部を予め地上で構築し、その
底部下方の地盤を掘削しながら所定位置まで沈設し、掘
削空室に水中自動掘削機を設置し、連通開口に接続して
上方に立ち上げた筒体から掘削室内に水を充填した後、
掘削室下方の地盤を水中自動掘削機によって水中掘削
し、構造物下部をその重量と掘削室の水の圧力をバラン
スさせながら沈設し、この沈設の進行と併行して構造物
下部上に順次構造物上部を一連に建ち上げ、順次同様に
水中自動掘削機によって水中掘削しながら構造物を所定
の位置に沈設し、沈設完了後掘削室および連通開口にコ
ンクリートを打設するようにした地中構造物の構築工法
を提案するものである。
"Means for Solving the Problems" In order to solve the above-mentioned conventional problems, the present invention provides a structure in which an excavation chamber with an open bottom is provided at the bottom, and a communication opening is provided on the floor above the excavation chamber. The lower part is constructed in advance on the ground, digging the ground below the bottom, sinking it to a predetermined position, installing an underwater automatic excavator in the excavation room, connecting to the communication opening, and excavating from the cylinder rising up After filling the room with water,
The ground under the excavation room is excavated underwater by an underwater automatic excavator, and the lower part of the structure is laid down while balancing its weight and the pressure of the water in the digging room. An underground structure in which the upper part of the structure is built in a series, and the structure is laid down at a predetermined position while digging underwater with the automatic underwater digger in the same way, and concrete is poured into the digging room and the communication opening after the digging is completed It proposes a construction method for objects.

「作用」 築造しようとする構造物の外壁を山留壁と兼用するこ
とによって山留壁の施工が省略されると共に、構造物下
部と下方の地盤に囲まれた空間内に水を注入充填し、自
動水中掘削機によって水中掘削するので、圧気作業がな
く安全かつ容易に掘削を行うことができ、また、この構
造物の重量および底部に充填した水の圧力、ならびにこ
の構造物と地盤との間に働く摩擦力とを均衡させること
により、構造物を掘削と併行させながら連続して確実に
所定の位置に沈設することが可能となる。
"Action" By using the outer wall of the structure to be built also as the retaining wall, construction of the retaining wall is omitted, and water is injected and filled into the space surrounded by the lower part of the structure and the lower ground. Underwater excavation by an automatic underwater excavator makes it possible to perform excavation safely and easily without pneumatic work.In addition, the weight of this structure and the pressure of water filled in the bottom, and the connection between this structure and the ground By balancing the frictional force acting therebetween, the structure can be reliably and continuously settled at a predetermined position while being concurrently excavated.

「実施例」 以下この発明を図面に示す実施例について説明する
と、第1図に示すように、構築計画地盤上において構築
しようとする構造物の下部部分である構造物下部1を築
造する。
"Example" Hereinafter, the present invention will be described with reference to an example shown in the drawings. As shown in FIG. 1, a structure lower part 1 which is a lower part of a structure to be constructed on a construction planning ground is constructed.

この構造物下部1は、周囲に下端が先鋭状の刃をなす
外壁1aが、また底部に下方が開放された掘削室1bが、さ
らに掘削室1b上の床部1cに連通開口1dを設けたコンクリ
ート構造体として構成されており、連通開口1dには筒体
2を接続して上方に立ち上げておく。
The lower part 1 of the structure has an outer wall 1a having a sharp edge at its lower end, a digging chamber 1b having a bottom opening at the bottom, and a communication opening 1d provided on a floor 1c on the digging chamber 1b. It is configured as a concrete structure, and a cylindrical body 2 is connected to the communication opening 1d and is raised upward.

次に、第2図に示すように、構造物下部1を設置した
下方の地盤を人力または掘削機等で地下水位付近まで掘
削しながら、構造物下部1を沈設する。
Next, as shown in FIG. 2, the lower part of the structure 1 is laid down while excavating the ground below the lower part 1 of the structure 1 to near the groundwater level with human power or an excavator.

そして、第3図に示すように、構造物下部1の掘削室
1b内においてカッター付き無人サンドポンプ掘削機等の
自動水中掘削機3を組立てて、床部1c底面に設置し、こ
れに掘削泥水の排泥管4を地上まで配管し、筒体2から
掘削室1b内に水を注入充填して構造物下部1の底部に所
要の水頭圧を作用させる。
Then, as shown in FIG.
In 1b, an automatic underwater excavator 3 such as an unmanned sand pump excavator with a cutter is assembled and installed on the bottom of the floor 1c. Water is injected and filled into 1b to apply a required head pressure to the bottom of the lower part 1 of the structure.

なお、水中自動掘削機3は、掘削室3の底部地盤上を
走行するものも用いることができる。
The underwater automatic excavator 3 that travels on the bottom ground of the excavation room 3 can also be used.

この状態で、自動水中掘削機3により掘削室1b下方の
地盤を水中掘削し、構造物下部1の重量(自重およびこ
れに付加した荷重を含む)および底部に調節充填した水
の圧力、ならびにこの構造物下部1と地山との間に働く
摩擦力とを適宜均衡させながら、構造物下部1を円滑に
沈設させる。
In this state, the ground under the excavation room 1b is excavated underwater by the automatic underwater excavator 3 to determine the weight of the lower portion 1 of the structure (including its own weight and the load added thereto) and the pressure of the water adjusted and filled at the bottom, and The lower part 1 of the structure is smoothly laid down while appropriately balancing the frictional force acting between the lower part 1 of the structure and the ground.

その後は第4図に示すように、構造物下部1の掘削の
進行と併行してその上に、順次構造物上部5,5′・・を
一連に建ち上げながら、上記同様に掘削と沈設を繰り返
して所要の地下構造物を沈設設置する。
Thereafter, as shown in FIG. 4, the excavation and subsidence are carried out in the same manner as described above while simultaneously constructing the upper parts 5, 5 ',. The required underground structures are repeatedly laid down and installed.

なお、このとき掘削した泥土は、排泥管4により外部
に排出処理する。
Note that the mud excavated at this time is discharged to the outside by the discharge pipe 4.

このようにして沈設完了後は、第5図に示すように掘
削室1b内の水を排水して自動水中掘削機3を解体撤去
し、掘削室1bおよび連通開口1d内に中理コンクリート6
を充填し、必要ならば構造物1の周囲に地盤固結材を注
入して施工を完了する。
After the submersion is completed in this manner, as shown in FIG. 5, the water in the excavation room 1b is drained, the automatic underwater excavator 3 is dismantled and removed, and the concrete 6 is placed in the excavation room 1b and the communication opening 1d.
And if necessary, a ground consolidation material is injected around the structure 1 to complete the construction.

なお、この発明で構築する構造物1は、第5図の地下
部に連続して地上部建屋を建ち上げた構造物を構築する
ことができることはいうまでもない。
It is needless to say that the structure 1 constructed according to the present invention can be constructed as a structure in which an above-ground building is continuously constructed underground in FIG.

「発明の効果」 以上の通りこの発明によれば、築造しようとする構造
物をその外壁自体を山留壁と兼用し、山留支保工による
開削を行うことなく直接所要位置まで沈設するので、山
留工費を不要として全体の工費を大巾に節減することが
できる。
[Effect of the Invention] As described above, according to the present invention, the structure to be built is used as the outer wall itself as a retaining wall, and is directly laid down to the required position without performing digging by retaining the pier. Eliminating the shoring work cost makes it possible to greatly reduce the entire work cost.

また、構造物底部の掘削室内に水を充填し、その下方
の地盤を自動水中掘削機によって水中掘削するので、構
造物の重量および水の圧力、ならびに構造物と地盤との
間に働く摩擦力とを適宜均衡させながら所定の位置に安
定してしかも安全に沈設することができると共に、掘削
の進行と併行して構造物下部上に順次構造物上部を一連
に建ち上げながら沈設するので、工期の短縮および工費
の削減が可能となる。
In addition, water is filled in the excavation room at the bottom of the structure, and the ground below is excavated underwater by an automatic underwater excavator, so that the weight of the structure and water pressure, and the frictional force acting between the structure and the ground Can be settled stably and safely at a predetermined position while appropriately balancing the above, and at the same time as the excavation progresses, the upper part of the structure is successively erected on the lower part of the structure while being erected. And work costs can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

第1〜5図はこの発明の施工工程を順に示す縦断側面図
である。 1……構造物下部、1a……外壁、 1b……掘削室、1c……床部、 1d……連通開口、2……筒体、 3……自動水中掘削機、4……排泥管、 5,5′……構造物上部、 6……中埋コンクリート。
1 to 5 are longitudinal side views sequentially showing the construction steps of the present invention. 1 ... lower part of structure, 1a ... outer wall, 1b ... excavation room, 1c ... floor, 1d ... communication opening, 2 ... cylinder, 3 ... automatic underwater excavator, 4 ... mud pipe , 5,5 ': Upper part of the structure, 6: Middle embedded concrete.

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】下方が開放された掘削室を底部に設け、そ
の掘削室上の床部に連通開口を設けた構造物下部を予め
地上で構築し、その底部下方の地盤を掘削しながら所定
位置まで沈設し、前記掘削室内に水中自動掘削機を設置
し、前記連通開口に接続して上方に立ち上げた筒体から
前記掘削室内に水を充填した後、掘削室下方の地盤を水
中自動掘削機によって水中掘削し、前記構造物下部をそ
の重量と掘削室の水の圧力をバランスさせながら沈設
し、この沈設の進行と併行して前記構造物下部上に順次
構造物上部を一連に建ち上げ、順次同様に水中自動掘削
機によって水中掘削しながら前記構造物を所定の位置に
沈設し、沈設完了後前記掘削室および連通開口にコンク
リートを打設することを特徴とする地中構造物の構築工
法。
An excavation chamber with an open bottom is provided at the bottom, and a lower portion of a structure having a communication opening in the floor above the excavation chamber is previously constructed on the ground, and a predetermined area is excavated while excavating the ground below the bottom. Submerged in the excavation room, an underwater automatic excavator is installed in the excavation room, and water is filled into the excavation room from a cylindrical body which is connected to the communication opening and rises upward. Underwater excavation is performed by an excavator, and the lower part of the structure is laid down while balancing the weight of the lower part and the pressure of the water in the digging chamber, and the upper part of the structure is sequentially built on the lower part of the structure in parallel with the progress of the laying. The underground structure is characterized in that the structure is submerged in a predetermined position while being excavated in the same manner by an underwater automatic excavator, and concrete is poured into the excavation chamber and the communication opening after the completion of the submersion. Construction method.
JP8376290A 1990-03-30 1990-03-30 Underground structure construction method Expired - Fee Related JP2821933B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8376290A JP2821933B2 (en) 1990-03-30 1990-03-30 Underground structure construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8376290A JP2821933B2 (en) 1990-03-30 1990-03-30 Underground structure construction method

Publications (2)

Publication Number Publication Date
JPH03281828A JPH03281828A (en) 1991-12-12
JP2821933B2 true JP2821933B2 (en) 1998-11-05

Family

ID=13811591

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8376290A Expired - Fee Related JP2821933B2 (en) 1990-03-30 1990-03-30 Underground structure construction method

Country Status (1)

Country Link
JP (1) JP2821933B2 (en)

Also Published As

Publication number Publication date
JPH03281828A (en) 1991-12-12

Similar Documents

Publication Publication Date Title
CN113818460A (en) Cofferdam construction method based on high-standard environmental protection requirement
Nonveiller Open caissons for deep foundations
JP2821934B2 (en) Underground structure construction method
JPH06146305A (en) Underwater foundation and installation method thereof
JP2876076B2 (en) Underground structure construction method
JP2821933B2 (en) Underground structure construction method
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
JP4498571B2 (en) Construction method of bottom enlarged structure
JP2809105B2 (en) How to build an underground tank
JPH0776845A (en) Method of settling open caisson
JPH0381422A (en) Caisson method
JPS62107115A (en) Method for sink laying underground sructural body
JPS5921831A (en) Reverse placement work
JPS6018769B2 (en) Construction method of underground structure
JP3350761B2 (en) Shaft excavation equipment and excavation method using the same
JPH059945A (en) Underground skeleton constructing method
JPS6357566B2 (en)
JP2536108B2 (en) Foundation construction method for offshore structures
CN116837884A (en) Open caisson method and open caisson structure
JP2581602B2 (en) Waste treatment method
JP2863698B2 (en) Submersion method for submerged body and supporting mechanism used for the method
JPH03295929A (en) Open caisson sinking construction method
JPS6352193B2 (en)
RU2059753C1 (en) Method for erecting underground storehouse
JPS5921822A (en) Mud-water excavation work

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070904

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080904

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees