JPS6018769B2 - Construction method of underground structure - Google Patents

Construction method of underground structure

Info

Publication number
JPS6018769B2
JPS6018769B2 JP10243478A JP10243478A JPS6018769B2 JP S6018769 B2 JPS6018769 B2 JP S6018769B2 JP 10243478 A JP10243478 A JP 10243478A JP 10243478 A JP10243478 A JP 10243478A JP S6018769 B2 JPS6018769 B2 JP S6018769B2
Authority
JP
Japan
Prior art keywords
underground
wall
continuous wall
underground continuous
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP10243478A
Other languages
Japanese (ja)
Other versions
JPS5530039A (en
Inventor
明美 野尻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP10243478A priority Critical patent/JPS6018769B2/en
Publication of JPS5530039A publication Critical patent/JPS5530039A/en
Publication of JPS6018769B2 publication Critical patent/JPS6018769B2/en
Expired legal-status Critical Current

Links

Description

【発明の詳細な説明】 この発明は地中に打設した杭とその上部の地中連続壁と
を一体化して、構造物地下部分の土留と上載荷重の支持
を行なうとともに地中連続壁を構造物本体壁として利用
する地下構造物の構築法に関するものである。
[Detailed Description of the Invention] This invention integrates a pile driven into the ground and an underground continuous wall above the pile to retain the earth in the underground part of a structure and support the overburden load. This relates to a method of constructing an underground structure to be used as the main wall of the structure.

従来、地中連続壁を構造物本体壁の一部分として利用す
る場合、地中連続壁自体の下部を支持杭の代わりとして
用いる方法等が探られているが、支持層への根入れ深さ
が十分なければならず、壁体を根入れするのでは不経済
となり、またその底面は応力集中を避けるためできるだ
け平坦にする必要がある他、種々の検討が必要となり、
必ずしも合理的と言えない。
Conventionally, when using an underground continuous wall as a part of the main wall of a structure, methods have been explored such as using the lower part of the underground continuous wall itself as a support pile, but the depth of penetration into the supporting layer is insufficient. It must be sufficient, and it would be uneconomical to embed the wall, and the bottom surface must be as flat as possible to avoid stress concentration, and various other considerations are required.
This cannot necessarily be said to be rational.

この発明はこのような事情に鑑み開発されたもので施工
手順の概略を述べると、まず構造物外周位置の柱部分に
掘削孔を設け、この掘削孔下部に場所打コンクリート杭
を打設し、その上部をソイルセメントあるいはセメント
バチルス等、掘削容易でかつ肌落ちのない材料で−旦埋
め戻し、孔壁の崩壊を防ぐとともに次に行なわれる所定
厚の地中連続壁部分の施工に備える。
This invention was developed in view of these circumstances, and to outline the construction procedure, first, an excavation hole is made in the column at the outer periphery of the structure, and a cast-in-place concrete pile is driven at the bottom of this excavation hole. The upper part is first backfilled with a material that is easy to excavate and does not fall off, such as soil cement or cement bacillus, to prevent collapse of the hole wall and to prepare for the subsequent construction of an underground wall of a predetermined thickness.

このとき、杭頭は構築する構造物本体の床付け面とほぼ
等しいか、若干上になる程度とする。次にこのコンクリ
ート杭で支持される地中連続壁部分を所要深さまでクラ
ムシェルその他の地盤長方形掘削機を用いて所定の幅で
掘削する。
At this time, the pile cap should be approximately equal to or slightly above the flooring surface of the structure to be constructed. Next, the section of the underground wall supported by the concrete piles is excavated to the required depth and width using a clamshell or other ground rectangular excavator.

なお前記コンクリート杭は固結遅延剤などを入れ、杭と
地中連続壁の一体化を図るために杭頭およびサイドはか
き落し装置で掘削する。次に表面にセン断鉄筋を突設し
た仕切鉄板を用いて、単位壁ごと鉄筋篭の蓮込みコンク
リートの打設を繰り返し、順次地中連続壁を構築する。
The concrete piles are filled with a consolidation retardant, and the pile heads and sides are excavated using a scraping device in order to integrate the piles with the underground wall. Next, using a partition steel plate with sheared reinforcing bars protruding from its surface, we repeat the pouring of reinforced concrete for each unit wall to construct a continuous underground wall.

このとき、構造物本体の柱および梁部分に対応する位置
には予め折り曲げ鉄筋を入れておく。地中連続壁が完成
したら、地中連続壁内部を床付け深さまで徐々に根切り
する。
At this time, bent reinforcing bars are placed in advance at positions corresponding to the pillars and beams of the structure body. Once the underground continuous wall is completed, gradually cut the roots inside the underground continuous wall to the flooring depth.

(この根切りはジャッキ等により切はりの軸力を変え、
地中連続壁に大きな曲げ応力が発生しないようにして行
なわれる。)所定深さまで掘削したら杭間さらい、杭頭
処理、折り曲げ鉄筋の立ておこし、洗浄等を行い構造物
本体の配筋、コンクIJート工事を行う。
(This root cutting is done by changing the axial force of the cutting beam using a jack etc.
This is done in such a way that large bending stresses are not generated on the diaphragm wall. ) After excavating to a specified depth, the piles will be cleaned, pile caps will be treated, bent reinforcing bars will be erected, and cleaning will be carried out, followed by reinforcing of the structure itself and concrete IJ construction.

次に図示した実施例について説明する。第1図および第
2図はコンクリート杭1の施工手順を示したもので、ま
ず鉄筋篭2を削孔Aの下部に蓮込み、次に固結時間を遅
延剤などで調整されたコンクリート3が打設され、その
上部はソィルセメントまたはセメントバチルス4によっ
て埋め戻される。
Next, the illustrated embodiment will be described. Figures 1 and 2 show the construction procedure for concrete pile 1. First, reinforcing bar cage 2 is inserted into the lower part of drilled hole A, and then concrete 3 whose setting time has been adjusted with a retarder etc. It is poured and the upper part is backfilled with soil cement or cement bacillus 4.

なおコンクリート杭1下面は必要に応じ拡底される(図
において破線で示す)。次に第3図に示すように掘削溝
Bの施工を行なう。図中7は構造物本体社を示したもの
で、地中連続肇9の施工後根切りを行ない、上述の杭1
上の埋め戻した部分に構築されることになる。第4図は
地中連続壁9部分の施工手順を示したもので、まず掘削
機8により掘削溝Bが設けられ鉄筋篭10および表面に
単位壁間をジョイントするセン断鉄筋13を突設した仕
切鉄板12の蓬込み、コンクリート11の打設を繰り返
し地中連続壁9が形成される。
Note that the bottom of the concrete pile 1 is expanded as necessary (indicated by a broken line in the figure). Next, as shown in FIG. 3, excavation trench B is constructed. 7 in the figure shows the main body of the structure, and after the construction of the underground continuous leg 9, root cutting is performed, and the above-mentioned pile 1
It will be built on the backfilled area above. Figure 4 shows the construction procedure for the 9 parts of the underground continuous wall. First, an excavation groove B is created using an excavator 8, and a reinforcing bar cage 10 and shear reinforcing bars 13 that connect the unit walls are protruded from the surface. The underground continuous wall 9 is formed by repeating the insertion of the partition iron plate 12 and the pouring of the concrete 11.

第5図はこのときの1−1断面を示したものである。そ
して、その後前述のように内部の根切りを行ない、構造
物本体の構築がなされる。
FIG. 5 shows a 1-1 cross section at this time. Thereafter, the internal roots are cut as described above, and the structure body is constructed.

この発明は以上の構成からなり、連続壁を杭に利用する
必要がなく、しかも杭は支持機構的には十分実績のある
ものであるため地中連続壁の深さも仮設的に必要な深さ
があれば良いことになり、地中連続壁を杭として利用す
るよりむしろ合理性の高い構造体となる。
This invention has the above-mentioned configuration, and there is no need to use continuous walls as piles.Moreover, since piles have a sufficiently proven support mechanism, the depth of the underground continuous wall can be set to a depth that is temporarily required. It would be a good thing if there was one, and the structure would be more rational than using underground walls as piles.

またコンクリート杭は地中連続壁の下部に設けられるの
で、地中連続壁施工時にも邪魔にならず十分士蟹および
止水効果を有する地中連続壁が施工できる。
In addition, since the concrete piles are installed at the bottom of the underground continuous wall, they do not get in the way during the construction of the underground continuous wall, allowing construction of a continuous underground wall that has a water-stopping effect.

さらに、コンクリート杭上部の削孔内は一旦、ソィルセ
メント等掘削容易な材料で埋め戻されるので、地中連続
壁の施工前、施工中の孔壁の崩壊が防止でき、杭位置の
確認も容易であり、また地中連続壁の施工にも支障はな
い。
Furthermore, since the inside of the drilled hole above the concrete pile is once backfilled with soil cement or other material that is easy to excavate, it is possible to prevent the hole wall from collapsing before and during the construction of the underground continuous wall, and it is easy to confirm the position of the pile. There is no problem with the construction of underground walls.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はコンクリート杭打設の手順を示す平面図、第2
図はその断面図、第3図は地中連続壁部分の掘削溝の平
面図、第4図は地中連続壁部分の施工手順を示す一部断
面図、第5図は第4図の1−1面にあたる断面図である
。 A……掘削孔、B……掘削溝、C……床付け面、D・・
・・・・地中連続壁下面、E・・…・支持層上面、1…
…コンクリート杭、2……鉄筋篭(杭の)、3・・・・
・・コンクリート(杭部分)、4・・・・・・ソィルセ
メントまたはセメントバチルス、5・・・…拡底部、6
・・・・・・ガイドウオール、7・・・・・・構造物本
体柱、8・・・・・・掘削機、9・・・・・・地中連続
壁、10・…・・鉄筋篭(地中連続壁の)、11・・・
・・・コンクリート(地中運碗墜部分)、12・・・・
・・仕切鉄板、13・・・・・・セン断鉄筋。 第1図 第3図 第5図 第2図 第4図
Figure 1 is a plan view showing the concrete pile driving procedure, Figure 2
The figure is a cross-sectional view, Figure 3 is a plan view of the excavation trench of the underground continuous wall part, Figure 4 is a partial cross-sectional view showing the construction procedure of the underground continuous wall part, and Figure 5 is 1 of Figure 4. It is a sectional view corresponding to the −1 plane. A...Drilling hole, B...Drilling groove, C...Flooring surface, D...
...Bottom surface of underground continuous wall, E...Top surface of support layer, 1...
...Concrete pile, 2...Reinforced cage (pile), 3...
... Concrete (pile part), 4 ... Soil cement or cement bacillus, 5 ... Expanded bottom part, 6
...Guide wall, 7 ... Structure main column, 8 ... Excavator, 9 ... Underground continuous wall, 10 ... Reinforced cage (of underground continuous wall), 11...
・・・Concrete (underground part of the ship), 12...
・・Partition iron plate, 13 ・・・・・Sensing reinforcing bar. Figure 1 Figure 3 Figure 5 Figure 2 Figure 4

Claims (1)

【特許請求の範囲】 1 構造物外周位置の柱部分に掘削孔を設け、この掘削
孔下部に場所打ちコンクリート杭を打設し、その上部を
掘削容易な材料で埋め戻した後、前記コンクリート杭に
より支持される所要深さの地中連続壁を構築し、その後
この地中連続壁内部を床付け深さまで掘削して構造物本
体の施工を行なうことを特徴とする地下構造物の構築法
。 2 コンクリート杭上部はソイルセメントまたはセメン
トバチルスで埋め戻しておく特許請求の範囲第1項記載
の地下構造物の構築法。
[Scope of Claims] 1. An excavation hole is provided in a column at the outer periphery of the structure, a cast-in-place concrete pile is driven in the lower part of the excavation hole, and the upper part is backfilled with a material that is easy to excavate. A method of constructing an underground structure characterized by constructing an underground continuous wall of a required depth to be supported by an underground continuous wall, and then excavating the inside of the underground continuous wall to the flooring depth to construct the structure itself. 2. The method for constructing an underground structure according to claim 1, wherein the upper part of the concrete pile is backfilled with soil cement or cement bacillus.
JP10243478A 1978-08-23 1978-08-23 Construction method of underground structure Expired JPS6018769B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10243478A JPS6018769B2 (en) 1978-08-23 1978-08-23 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10243478A JPS6018769B2 (en) 1978-08-23 1978-08-23 Construction method of underground structure

Publications (2)

Publication Number Publication Date
JPS5530039A JPS5530039A (en) 1980-03-03
JPS6018769B2 true JPS6018769B2 (en) 1985-05-13

Family

ID=14327351

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10243478A Expired JPS6018769B2 (en) 1978-08-23 1978-08-23 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JPS6018769B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS56159419A (en) * 1980-05-15 1981-12-08 Ohbayashigumi Ltd Continuous underground wall and construction thereof
JPS579924A (en) * 1980-06-20 1982-01-19 Takenaka Komuten Co Ltd Foundation structure for building
JP3687575B2 (en) * 2000-12-28 2005-08-24 コベルコクレーン株式会社 Construction support method and construction support system for underground continuous wall construction
CN105951712A (en) * 2016-05-31 2016-09-21 中铁第四勘察设计院集团有限公司 Underground diaphragm wall construction method for cutting through underground structure under ground limitation condition
CN106245625A (en) * 2016-07-28 2016-12-21 中国建筑第六工程局有限公司 Pass through the bored pile construction method of existing Large Underground space structure

Also Published As

Publication number Publication date
JPS5530039A (en) 1980-03-03

Similar Documents

Publication Publication Date Title
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JPH0960028A (en) Method for increasing strength of existing steel pipe pile
JPS6018769B2 (en) Construction method of underground structure
JP4485006B2 (en) Construction method for underground structures
JP2005002671A (en) Underpinning method and viaduct
JPS61191715A (en) Method of building underground continuous wall in pile support building having underground floor and cast-in-place concrete pile
JP6860895B2 (en) Retaining wall and its construction method
JP7115923B2 (en) Foundation structure reinforcement method and foundation structure reinforcement structure
JP3957607B2 (en) Pneumatic caisson and pneumatic caisson method
JPH0721196B2 (en) Reverse construction method of underground structure
JP2899668B2 (en) Simple underground construction
JP2599299B2 (en) Retaining wall and retaining method in soft ground
JPH11190024A (en) Earth retaining work
JP3101762B2 (en) Simple mountain retaining method
JP3012896B2 (en) Reverse cutting method combined with advance cutting
KR102570649B1 (en) Method of demolition of underground exterior walls
JPH0813494A (en) Fixing method of earth retaining wall and timbering
JPS5851092B2 (en) Earth retaining installation method using advance shoring frame
JPH0654016B2 (en) Underground space construction method
JP3809340B2 (en) Reverse strike method
JP3012895B2 (en) Simple underground construction method
JP6851180B2 (en) How to rebuild the building
JP2899669B2 (en) Simple mountain retaining method
JPS6233372B2 (en)
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing