JPS6233372B2 - - Google Patents
Info
- Publication number
- JPS6233372B2 JPS6233372B2 JP10491883A JP10491883A JPS6233372B2 JP S6233372 B2 JPS6233372 B2 JP S6233372B2 JP 10491883 A JP10491883 A JP 10491883A JP 10491883 A JP10491883 A JP 10491883A JP S6233372 B2 JPS6233372 B2 JP S6233372B2
- Authority
- JP
- Japan
- Prior art keywords
- piles
- retaining wall
- retaining
- underground
- walls
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 238000010276 construction Methods 0.000 claims description 7
- 238000005520 cutting process Methods 0.000 claims description 3
- 239000002689 soil Substances 0.000 description 5
- 229910000831 Steel Inorganic materials 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 238000009415 formwork Methods 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 235000008331 Pinus X rigitaeda Nutrition 0.000 description 1
- 235000011613 Pinus brutia Nutrition 0.000 description 1
- 241000018646 Pinus brutia Species 0.000 description 1
- 238000005056 compaction Methods 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Retaining Walls (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【発明の詳細な説明】
本発明は傾斜地を階段状の宅地に造成する工法
に関する。従来、傾斜地における宅地造成には、
第1図に示すように、L型コンクリート擁壁1を
構築しているが、この擁壁1の構築には、シート
パイルの打設等による所要の山止め壁2を仮設
し、必要に応じこれをアースアンカ3により支持
させたのち、床付け掘削を行うとともに、多数の
基礎杭4を打設して、その上に上記擁壁1を構築
し、しかるのち上記掘削の埋戻しをしている。こ
のため、比較的広い床付け面積を必要とし掘削土
量が多くなり、その搬出、搬入(埋戻し)に重機
械を使用しなければならないとともに手間がかか
り、また、埋戻し工における転圧によつても地山
と同じ程度に締め固めすることが難しく、そのう
え、法面掘削が多く、高さもあるので地山の崩壊
防止に充分な配慮を必要とし、かつ山止め壁の支
保工あるいは埋戻し土の一時預け等のために近隣
地の使用を余儀なくされる等諸々の欠点があつ
た。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for creating a stepped residential lot on a slope. Conventionally, when developing residential land on sloped land,
As shown in Figure 1, an L-shaped concrete retaining wall 1 is being constructed.In order to construct this retaining wall 1, the required retaining wall 2 is temporarily constructed by placing sheet piles, etc., and as needed. After supporting this with earth anchors 3, the floor is excavated, a large number of foundation piles 4 are driven, and the retaining wall 1 is constructed on top of it, and then the excavation is backfilled. There is. For this reason, a relatively large floor area is required, and a large amount of excavated soil is required.It is necessary to use heavy machinery to carry it out and carry it in (backfilling), which is time-consuming. However, it is difficult to compact the ground to the same degree as the ground, and in addition, there is a lot of slope excavation and the height is high, so sufficient consideration must be taken to prevent the ground from collapsing. There were various disadvantages such as having to use neighboring land for temporary storage of returned soil.
本発明は、かかる欠点を解消し、かつ宅地盤と
して地山を広範囲に残すことを目的とするもの
で、傾斜地に親杭を所定の間隔で自立列設すると
ともに、その列設した親杭の両側に所定の間隔を
おいて山止め壁を築造し、その山止め壁の杭と上
記親杭との間に適宜の支保工を架設したのち、上
記親杭相互間に地中梁と壁体を形成して地中擁壁
として、所要の切土工、盛土工を行うことを特徴
とする傾斜地における宅地造成工法に係るもので
ある。 The purpose of the present invention is to eliminate such drawbacks and to leave a large area of ground as the ground for a building. After constructing retaining walls at a predetermined interval on both sides and erecting appropriate shoring between the piles of the retaining walls and the above-mentioned main piles, underground beams and walls are installed between the above-mentioned main piles. This relates to a construction method for building land on a slope, which is characterized by forming an underground retaining wall and performing the necessary cutting and embankment work.
以下これを図示の実施例について詳述する。 This will be explained in detail below with reference to the illustrated embodiment.
5は地中擁壁構築計画線上に所要の間隔をおい
て自立列設した親杭で、地中所定深さまで掘削し
た削孔6に親杭5を挿入し、その基礎部にコンク
リート7を打設して自立させたもので、この親杭
としては図示のH形鋼のほかI形鋼、鋼管等であ
つてもよい。 Reference numeral 5 indicates parent piles that are arranged in a free-standing row at required intervals on the planned line for constructing an underground retaining wall.The parent piles 5 are inserted into holes 6 that have been excavated to a predetermined depth underground, and concrete 7 is poured into their foundations. The main pile may be made of I-beams, steel pipes, etc. in addition to the H-beams shown in the figure.
8,8′は列設した上記親杭5の両側に所要の
間隔をおいて築造した山止め壁で、この山止め壁
8,8′は、各親杭5の前後に対向させて山止め
杭9,9′を列設したのち、親杭5と山止め杭
9,9′との間を下方へ逆掘りしつつ、対向する
親杭と山止め杭9,9′との間に支保工10,1
0′を、また山止め杭9相互、及び9′相互間には
壁材11,11′を、それぞれ順次下方に向つて
架設することにより構築したものであつて、各山
止め壁8,8′は少なくとも傾斜地表面から親杭
5のコンクリート基礎部上端対向位置に達する高
さを有する。 Reference numerals 8 and 8' refer to retaining walls constructed at a required interval on both sides of the main piles 5 arranged in a row. After installing the piles 9, 9' in a row, while digging backwards downward between the main pile 5 and the retaining piles 9, 9', add support between the opposing parent pile and the retaining piles 9, 9'. Engineering 10,1
0', and wall materials 11 and 11' between each of the retaining piles 9 and between each of the retaining piles 9 and 9', respectively, in a downward direction. ' has a height that reaches at least from the sloping ground surface to a position facing the upper end of the concrete foundation of the parent pile 5.
上記において、山止め杭として図示のH形鋼の
ほかI形鋼、角パイプ、鋼管等を採用し、また支
保工として図示のジヤツキのほか腹起し、切り梁
等を採用し、さらに壁材としては、同じく図示の
松矢板のほか所要断面形状のパイプ、H形鋼、C
形鋼等を採用してもよい。 In the above, in addition to the H-beams shown in the figure, I-beams, square pipes, steel pipes, etc. are used as the retaining piles, and in addition to the shown jacks, braces, cut beams, etc. are used as supporting materials, and wall materials are also used. In addition to the pine pile sheets shown in the figure, pipes with the required cross-sectional shape, H-beam steel, and C
Shaped steel or the like may also be used.
次に、親杭5相互間であつて、上記コンクリー
ト基礎部の直上位置に梁用鉄筋12を、またその
上方には壁用鉄筋13を配筋し、かつこれらの外
側を所定の型枠で囲繞したのち、そこにコンクリ
ートを打設して地中梁14及び壁体15を形成す
ることによつて地中擁壁16を構築する。 Next, between the parent piles 5, beam reinforcing bars 12 are arranged directly above the concrete foundation, and above them, wall reinforcing bars 13 are arranged, and the outside of these bars is placed in a predetermined formwork. After enclosing it, concrete is placed there to form underground beams 14 and walls 15, thereby constructing an underground retaining wall 16.
次に、所定養生期間経過後、型枠及び山止め壁
8,8′解体、撤去するとともに、埋戻し工1
7、背面裏込め工18、切土工19、盛土工20
を施工して宅地の造成を完了する。 Next, after a predetermined curing period, the formwork and retaining walls 8, 8' are dismantled and removed, and backfilling work 1
7. Rear backfilling 18, cutting 19, embankment 20
construction to complete the development of the residential land.
なお、第4,5図の21は親杭5に取外し可能
に固定した架台で、図示のようにジヤツキを載置
する。第3,5図の22は壁体15に貫通させた
水抜きパイプである。 In addition, 21 in FIGS. 4 and 5 is a frame removably fixed to the main pile 5, on which a jack is placed as shown. Reference numeral 22 in FIGS. 3 and 5 is a drain pipe penetrated through the wall 15.
第7図イ,ロは山止め壁を構成する壁材として
所要断面形状のパイプを使用した他の例を示し、
イは山止め杭のH形鋼23に円形パイプ24の端
部を挿入し、それを止め金25で係止したもので
あり、また、ロは山止め杭に角パイプ26を採用
し、これに上下方向に列設した受入口26′に円
形パイプ27の端部を挿入し、止め金28で係止
したものである。 Figures 7A and 7B show other examples in which pipes with the desired cross-sectional shape are used as the wall material constituting the retaining wall.
In A, the end of the circular pipe 24 is inserted into the H-beam 23 of the pile and is locked with a stopper 25. In B, a square pipe 26 is used as the pile. The ends of the circular pipes 27 are inserted into the receiving ports 26' arranged in the vertical direction, and are locked with the stoppers 28.
以上に詳述したとおり、本発明によれば、床付
け面積が狭く、したがつて掘削面積及び土量も少
ないため、掘削土の搬出、搬入(埋戻し)は小型
機械で充分で、特に、地山の大部分をそのまま残
すことができるので、従来の埋戻し転圧する場合
にくらべ強固な宅地盤を造成できる。また、法面
掘削が少ないため崩壊の危険も少ない。さらに、
上記のように親杭を利用して山止め壁を支持でき
るので、階段状をなして上下左右に隣接する全ブ
ロツクにおいて同時に着工し重複作業を行うこと
ができ、従来に比し工期を著しく短縮することが
可能である。そのうえ、山止め壁の支保を隣地に
とる必要がなく、埋戻し土も少ないためこれを隣
地等に一時預ける必要がない等隣地への影響も最
小限にできる。 As detailed above, according to the present invention, since the floor area is small, and therefore the excavated area and soil volume are also small, a small machine is sufficient for carrying out and carrying in (backfilling) the excavated soil, and in particular, Since most of the ground can be left intact, a stronger housing ground can be created compared to conventional backfilling and compaction. Also, because there is little excavation on the slope, there is less risk of collapse. moreover,
As mentioned above, the retaining wall can be supported using the parent piles, making it possible to start construction at the same time on all blocks that are adjacent to each other vertically and horizontally in a stair-like manner, and to perform redundant work, significantly shortening the construction period compared to conventional methods. It is possible to do so. Furthermore, there is no need to provide support for the retaining wall on adjacent land, and since there is little backfilling soil, there is no need to temporarily deposit it on adjacent land, etc., and the impact on adjacent land can be minimized.
図面第1図は従来の宅地造成工法の説明図、第
2〜6図は本発明による宅地造成工法の実施例を
示すもので、第2図は山止め壁を築造した状態の
概略平面図、第3図イ,ロは地中擁壁を構築した
状態の概略平面図及び断面図、第4,5図は地中
擁壁の構築状況の断面図及び平面図、第6図は地
中梁の配筋状況の平面図、第7図イ,ロは山止め
壁の他の例を示す要部の断面図である。
5…親杭、8,8′…山止め壁、10,10′…
支保工、14…地中梁、15…壁体、16…地中
擁壁。
Figure 1 is an explanatory diagram of the conventional residential land preparation method, Figures 2 to 6 show examples of the housing land preparation method according to the present invention, and Figure 2 is a schematic plan view of a state in which a retaining wall has been constructed; Figure 3 A and B are a schematic plan view and cross-sectional view of the underground retaining wall constructed, Figures 4 and 5 are cross-sectional views and plan views of the underground retaining wall construction status, and Figure 6 is an underground retaining wall. Fig. 7A and Fig. 7B are cross-sectional views of main parts showing other examples of retaining walls. 5... Main pile, 8, 8'... Mounting wall, 10, 10'...
Shoring, 14... Underground beam, 15... Wall, 16... Underground retaining wall.
Claims (1)
ともに、その列設した親杭の両側に所定の間隔を
おいて山止め壁を築造し、その山止め壁の杭と上
記親杭との間に適宜の支保工を架設したのち、上
記親杭相互間に地中梁と壁体を形成して地中擁壁
として、所要の切土工、盛土工を行うことを特徴
とする傾斜地における宅地造成工法。1. Install parent piles in a self-supporting row at a predetermined interval on a slope, and construct retaining walls at a prescribed interval on both sides of the row of parent piles, and make sure that the stakes in the retaining wall and the above-mentioned parent piles are connected to each other. A residential land on a slope where, after erecting appropriate shoring between the main piles, underground beams and walls are formed between the above-mentioned parent piles, and necessary cutting and embankment work is performed to form an underground retaining wall. Construction method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10491883A JPS59233028A (en) | 1983-06-14 | 1983-06-14 | Residential land formation work on sloped ground |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP10491883A JPS59233028A (en) | 1983-06-14 | 1983-06-14 | Residential land formation work on sloped ground |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS59233028A JPS59233028A (en) | 1984-12-27 |
JPS6233372B2 true JPS6233372B2 (en) | 1987-07-21 |
Family
ID=14393479
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP10491883A Granted JPS59233028A (en) | 1983-06-14 | 1983-06-14 | Residential land formation work on sloped ground |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS59233028A (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5046742B2 (en) * | 2005-07-19 | 2012-10-10 | 有限会社カヌカデザイン | Retaining wall and its supporting method |
JP4532435B2 (en) * | 2006-05-16 | 2010-08-25 | 有限会社カヌカデザイン | Retaining wall and its construction method |
JP5943202B2 (en) * | 2012-12-27 | 2016-06-29 | 株式会社カヌカデザイン | Composite retaining wall and its construction method |
-
1983
- 1983-06-14 JP JP10491883A patent/JPS59233028A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS59233028A (en) | 1984-12-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100884289B1 (en) | Composite type steel temporary construction and construction method thereof | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
KR20000003270A (en) | Tunnel construction method at area of thin soil surface | |
JPH07145625A (en) | Method of constructing earth retaining wall | |
JP2000144769A (en) | Method of landslide protection work for preparing housing lot | |
KR102617795B1 (en) | Retaining wall system combine H-piles with steel reinforcement structure | |
JPS6233372B2 (en) | ||
US4056154A (en) | Squaring off and reaming tool for deep elongated trench excavations | |
JPS62288269A (en) | Method for extending underground stair of building | |
JPS63280153A (en) | Underground inverted lining method | |
JPH11190024A (en) | Earth retaining work | |
JP3109038B2 (en) | Underground skeleton structure and construction method | |
CN111648375B (en) | Inner supporting structure based on shear wall as support | |
JPS6018769B2 (en) | Construction method of underground structure | |
JPS638249B2 (en) | ||
CN217840090U (en) | Full-height inverted filter frame for pile-plate type retaining wall | |
JPH0739666B2 (en) | Permeable temporary earth retaining material, permeable frame structure and concrete wall construction method | |
CN115262568B (en) | Deepening support and excavation construction method based on zero-field deep foundation pit | |
JPH02266016A (en) | Structural process of underground concrete body of building | |
JPH04115016A (en) | Earth retaining wall in weak foundation and method of retaining earth | |
JP3809340B2 (en) | Reverse strike method | |
CN115094948A (en) | Pile-plate type retaining wall combined frame and construction method | |
JPS6350491B2 (en) | ||
KR20010048073A (en) | The construction method of a concrete retaining wall | |
JP2001336151A (en) | Ground excavation method using shore strut type earth retaining timbering |