JPS59233028A - Residential land formation work on sloped ground - Google Patents

Residential land formation work on sloped ground

Info

Publication number
JPS59233028A
JPS59233028A JP10491883A JP10491883A JPS59233028A JP S59233028 A JPS59233028 A JP S59233028A JP 10491883 A JP10491883 A JP 10491883A JP 10491883 A JP10491883 A JP 10491883A JP S59233028 A JPS59233028 A JP S59233028A
Authority
JP
Japan
Prior art keywords
piles
walls
work
master
underground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10491883A
Other languages
Japanese (ja)
Other versions
JPS6233372B2 (en
Inventor
Katsuo Oshima
大島 勝夫
Masanori Nakayama
中山 昌典
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Seishin Kogyo KK
Hazama Ando Corp
Original Assignee
Hazama Gumi Ltd
Seishin Kogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hazama Gumi Ltd, Seishin Kogyo KK filed Critical Hazama Gumi Ltd
Priority to JP10491883A priority Critical patent/JPS59233028A/en
Publication of JPS59233028A publication Critical patent/JPS59233028A/en
Publication of JPS6233372B2 publication Critical patent/JPS6233372B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines

Abstract

PURPOSE:To form a strong residential ground by a method in which sheathing walls are constructed on both sides of master piles driven at given intervals, a timbering work is provided between the piles of sheathing walls and the master piles, and underground beams and walls are formed between the master piles, followed by cutting and banking works. CONSTITUTION:Master piles 5 are penetrated into pits 6 provided at given intervals, and sheathing walls 8 and 8' are constructed at a given interval on both sides of the master piles 5. Timbering works 10 and 10' are provided between the piles 9 and 9' of the sheathing walls 8 and 8' and the master piles 5, and underground beams 14 and walls are formed between the master piles 5 to construct an underground retaining wall 16, followed by embedding work, back-filling work 18, cutting work 19, and banking work 20. Since the amount of area to be excavated and also of soil to be excavated is small, the construction work can be attained by small-size working machine. Also, since the majority of the natural ground can be left behind, strong residential ground can be formed.

Description

【発明の詳細な説明】 本発明は傾斜地を階段状の宅地に造成する工法に関する
。従来、傾斜地における宅地造成KFi、第1図に示す
ように、L型コンクリート擁壁1を構築しているが、こ
の擁m1の構築には、シートパイルの打設等による所要
の山止めm2を仮設し、必要に応じこれをアースアンカ
3により支持はせたのち、床付は掘削を行うとともに、
多数の基礎杭4を打設して、その上に上記tAf壁1を
構築し、しかるのち上記掘削の埋戻しをしている。この
ため、比較的広い床付は面積を必要とし掘削出量が多く
なり、その搬出、搬入(g。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a construction method for creating a stepped residential lot on a slope. Conventionally, in residential development KFi on sloped land, as shown in Figure 1, an L-shaped concrete retaining wall 1 is constructed, but in order to construct this retaining wall m1, the required retaining wall m2 is required by placing sheet piles, etc. After constructing a temporary structure and supporting it with earth anchors 3 as necessary, the flooring will be excavated and
A large number of foundation piles 4 are driven, the tAf wall 1 is constructed thereon, and the excavation is then backfilled. For this reason, a relatively wide floor requires a large area and requires a large amount of excavation, and the removal and loading (g.

戻し)に重機板を使用しなければならないとともに手間
がかかり、また、埋戻し工における転圧によっても地山
と同じ程度に締め固めすることが難しく、そのうえ、法
面掘削が多く、高さもあるので地山の崩壌防止に充分な
配慮を必要とし、かつ出止め壁の支保工あるいけ埋戻し
土の一時預は等のために近隣地の使用を余儀なくされる
勢銘々の欠点があった。
It is time-consuming and requires the use of heavy machinery for backfilling (backfilling), and it is difficult to compact the ground to the same level as the ground through compaction during backfilling.In addition, there is a lot of slope excavation and the height is high. Therefore, sufficient consideration had to be taken to prevent the ground from collapsing, and there were disadvantages in that they were forced to use nearby land for shoring of the stopping wall, temporary storage of backfilling soil, etc. .

本発明は、かかる欠一点を解消し、かつ宅地盤として地
山を広範囲に残すことを目的とするもので、傾斜地に親
杭を所定の間隔で自立列設するとともに1その列設した
親杭の両側に所定の間隔をおいて山止め壁を築造し、そ
の山止め壁の杭と上記親杭との間に適宜の支保工を架設
したのち、上記親杭相互間に地中梁と壁体を形成して地
中擁壁として、所要の切土工、盛土工を行うことを特徴
とする傾斜地における宅地造成工法に係るものである。
The purpose of the present invention is to eliminate such drawbacks and to leave a large area of ground as a building ground.The present invention aims to solve this problem and to leave a large area of ground as the ground for housing. After constructing retaining walls at a predetermined interval on both sides of the retaining wall, and erecting appropriate shoring between the piles of the retaining wall and the above-mentioned main piles, install underground beams and walls between the above-mentioned main piles. This relates to a construction method for building land on a slope, which is characterized by forming a wall as an underground retaining wall and performing necessary cutting and embankment work.

以下これを図示の実施例について詳述する。This will be explained in detail below with reference to the illustrated embodiment.

5は地中擁壁構築計画紗上に所要の間隔をおいて自立列
設した親杭で、地中所定深さまで掘削した削孔6に親杭
5を挿入し、その基礎部にコンクリート7を打設して自
立させたもので、との親杭としてI″ii図示形−の(
窟か工形鋼、鋼管等であってもよい。
Reference numeral 5 denotes parent piles that are arranged in a self-supporting row at required intervals on the underground retaining wall construction plan. It was driven and made to stand on its own, and was used as a parent pile with I″ii diagram-shaped (
It may also be made of hollow shaped steel, steel pipes, etc.

8.8′は列設した上記親杭5の両側に所要の間隔をお
いて築造した山止め壁で、この山土メ壁8,8′は、各
親杭5の前後に対向させて山止め杭9,9′を列設した
のち、親杭5と山止め杭9.9′との間を下方へ逆掘り
しつつ、対向する親杭と山止め杭9,9′との間に支保
工10.10’を、また出止め杭9相互、及び9′相互
間には壁材11.11’を、それぞれ順次下方に向って
架設することにより構築したものであって、各山止め壁
8,8′は少なくとも傾斜地表面から親杭5のコンクリ
ート基礎部上端対向位置に達する高さを有する。
Reference numeral 8.8' denotes a pile retaining wall built at a required interval on both sides of the main piles 5 arranged in a row. After installing the retaining piles 9 and 9' in a row, while digging backwards downward between the main pile 5 and the retaining piles 9 and 9', dig between the opposing parent pile and the retaining piles 9 and 9'. It is constructed by sequentially erecting shoring 10.10', and wall materials 11.11' between the retaining piles 9 and 9' downwards, and each retaining pile is The walls 8, 8' have a height that reaches at least from the slope surface to a position facing the upper end of the concrete foundation of the parent pile 5.

上記において、出止め杭として図示のH形C!々のにか
工形鋼、角パイプ、鋼管等を採用し、また支保工として
図示のジヤツキのにか腹起し、切り菜活を採用し、さら
に壁材としては、同じく図示の松矢板のほか所要断面形
状のパイプ、H形鋼、C形鋼等を採用してもよい。
In the above, the H-shaped C! For the walls, we used shaped steel, square pipes, steel pipes, etc., and for the shoring, we used the shown jacks, and we used cut-and-cut wood for the walls. In addition, pipes, H-shaped steel, C-shaped steel, etc. with the desired cross-sectional shape may be used.

次に、親核5相互間であって、上記コンクリート基礎部
の直上位6′に梁用鉄筋12を、またその上方には壁用
鉄筋13を配筋し、かつこれらの外側を所定の型枠で囲
続したのち、そこにコンクリートを打設して地中梁14
及び壁体15を形成することによって地中擁壁16を構
築する0 次に、所定養生期間経過後、型枠及び山止め壁8.8/
を解体、撤去するとともに、埋戻し工17、背面裏込め
工18、切土工19、盛土工20を施工して宅地の造成
を完了する。
Next, between the parent cores 5, beam reinforcing bars 12 are arranged directly above the concrete foundation 6', and above them, wall reinforcing bars 13 are arranged, and the outside of these bars is shaped into a predetermined shape. After surrounding it with a frame, concrete is poured there and underground beam 14
Then, after a predetermined curing period, formwork and retaining wall 8.8/
will be dismantled and removed, and backfilling work 17, rear backfilling work 18, cutting work 19, and embankment work 20 will be carried out to complete the development of the residential land.

なお、第4,5図の21は親杭5に取外し可能に固定し
た架台で、図示のようにジヤツキを(3) 載餘する。第3,5図の22は壁体15に貫通させた水
抜きパイプである。
In addition, 21 in FIGS. 4 and 5 is a frame removably fixed to the main pile 5, on which a jack (3) is mounted as shown. Reference numeral 22 in FIGS. 3 and 5 is a drain pipe penetrated through the wall 15.

第7図(イ)(ロ)は山止め壁を権威する壁材として所
要断面形状のパイプを使用した他の例を示し、(イ)は
山止め杭のH形鋼23に円形パイプ24の端部を挿入し
、それを止め金25で係止したものであり、また、(ロ
)は出止め杭に角パイプ26を採用し、これに上下方向
に列設した受入口26′に円形バイブ27の端部を挿入
し、止め金28で係止したものである。
Figures 7(a) and 7(b) show other examples in which pipes with the desired cross-sectional shape are used as wall materials for the retaining wall, and (a) shows a circular pipe 24 attached to the H-shaped steel 23 of the retaining pile. The end is inserted and locked with a stopper 25, and in (b) a square pipe 26 is used as the stopper, and a circular pipe is inserted into the receiving opening 26' arranged vertically. The end of the vibrator 27 is inserted and locked with a stopper 28.

以上に詳述したとおり、本発明によれば、床付は面積が
狭く、したがって掘削面積及び出量も少ないため、掘削
土の搬出、搬入(埋戻し)は小型機械で充分で、製に、
地山の大部分をそのまま残すことができるので、従来の
埋戻し転圧する場合にくらべ強固な宅地盤を造成で色る
As detailed above, according to the present invention, since the floor area is small, and therefore the excavation area and amount of excavation are also small, a small machine is sufficient for carrying out and carrying in (backfilling) the excavated soil.
Since most of the ground can be left intact, a stronger housing ground can be created compared to conventional backfilling and compaction.

また、法面掘削が少ないため崩壊の危険も少ない。さら
に、上記のように親杭を利用して山止め壁を支持できる
ので、階段状をなして上下左右に隣接する全ブロックに
おいて同時に着工しく4) 1M ’4fi作業を行うことができ、従来に比し工期
を著しく短縮することが可能である。そのうえ、山止め
壁の支保を隣地にとる必要がなく、埋戻し土も少ないた
めこれをC地等に一時預ける必要がない等隣地への影G
も最小限にできる。
Also, because there is little excavation on the slope, there is less risk of collapse. Furthermore, as mentioned above, the retaining wall can be supported using the parent piles, so construction can be started simultaneously on all blocks adjacent to each other vertically and horizontally in a stair-like manner. In comparison, it is possible to significantly shorten the construction period. In addition, there is no need to support the retaining wall on the adjacent land, and since there is little backfilling soil, there is no need to temporarily store it in land C, etc., and there is no impact on the neighboring land G.
can also be minimized.

【図面の簡単な説明】[Brief explanation of drawings]

図面第1図は従来の宅地造成工法の説明図、第2〜6図
は本発明による宅地造成工法の実施例を示すもので、第
2図は山止め壁を築造した状態の概略平面図、第3図(
イ)(ロ)は地中擁壁を構築した状態の概略平面図及び
断面図、第4,5図は地中擁壁の構築状況の断面図及び
平面図、第6図は地中梁の配筋状況の平面図、第7図(
イ)(ロ)は出止め壁の他の例を示す要部の断面図であ
る。 5・・・親杭、 8.81・・・山止め壁、  10.
10’・・・支保工、 14・・・地中梁、 15・・
・壁体、16・・・地中擁壁。 N 〜 針 ( 166− 特開口H59−233028(6)
Drawings Figure 1 is an explanatory diagram of the conventional housing land preparation method, Figures 2 to 6 show examples of the housing land preparation method according to the present invention, and Figure 2 is a schematic plan view of a state in which a retaining wall has been constructed. Figure 3 (
b) (b) is a schematic plan view and cross-sectional view of the underground retaining wall as constructed, Figures 4 and 5 are cross-sectional views and plan views of the underground retaining wall construction status, and Figure 6 is a schematic plan view of the underground retaining wall. Plan view of reinforcement situation, Figure 7 (
(a) and (b) are sectional views of main parts showing other examples of the stopper wall. 5... Main pile, 8.81... Mountain retaining wall, 10.
10'...Shoring, 14...Underground beam, 15...
・Wall body, 16... Underground retaining wall. N ~ Needle (166- Special opening H59-233028 (6)

Claims (1)

【特許請求の範囲】[Claims] 1、傾斜地に親杭な所定の間隔で自立列設するとともに
、その列設した親杭の両側に所定の間隔をおいて山止め
壁を築造し、その山止め壁の杭と上記親杭との間に適宜
の支保工を架設したのち、上記親杭相互間に地中梁と壁
体を形成して地中擁壁として、所要の切土工、盛土工を
行うことを特徴とする傾斜地における宅地造成工法。
1. Set up free-standing rows of parent piles at predetermined intervals on the slope, and construct retaining walls at predetermined intervals on both sides of the row of parent piles. After erecting appropriate shoring between the above-mentioned main piles, underground beams and walls are formed between the above-mentioned parent piles to form an underground retaining wall, and the necessary cutting and embankment work is carried out. Housing land preparation method.
JP10491883A 1983-06-14 1983-06-14 Residential land formation work on sloped ground Granted JPS59233028A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10491883A JPS59233028A (en) 1983-06-14 1983-06-14 Residential land formation work on sloped ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10491883A JPS59233028A (en) 1983-06-14 1983-06-14 Residential land formation work on sloped ground

Publications (2)

Publication Number Publication Date
JPS59233028A true JPS59233028A (en) 1984-12-27
JPS6233372B2 JPS6233372B2 (en) 1987-07-21

Family

ID=14393479

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10491883A Granted JPS59233028A (en) 1983-06-14 1983-06-14 Residential land formation work on sloped ground

Country Status (1)

Country Link
JP (1) JPS59233028A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007205161A (en) * 2005-07-19 2007-08-16 Kanuka Design:Kk Retaining wall and its construction method
JP2007308876A (en) * 2006-05-16 2007-11-29 Kanuka Design:Kk Retaining wall and its construction method
JP2014125797A (en) * 2012-12-27 2014-07-07 Kanukadesign Ltd Composite retaining wall and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007205161A (en) * 2005-07-19 2007-08-16 Kanuka Design:Kk Retaining wall and its construction method
JP2007308876A (en) * 2006-05-16 2007-11-29 Kanuka Design:Kk Retaining wall and its construction method
JP2014125797A (en) * 2012-12-27 2014-07-07 Kanukadesign Ltd Composite retaining wall and construction method thereof

Also Published As

Publication number Publication date
JPS6233372B2 (en) 1987-07-21

Similar Documents

Publication Publication Date Title
US3184893A (en) Contact foundation method
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
CN110777802A (en) Deep foundation pit high-low span supporting structure and construction method thereof
JP2000352296A (en) Method o constructing passage just under underground structure
JP4115095B2 (en) Reverse strike method
JP2868651B2 (en) Earth retaining method above existing underground structure
JPS59233028A (en) Residential land formation work on sloped ground
JP2000144769A (en) Method of landslide protection work for preparing housing lot
JPS62288269A (en) Method for extending underground stair of building
JPH11190024A (en) Earth retaining work
JPS63280153A (en) Underground inverted lining method
JPS6018769B2 (en) Construction method of underground structure
CN111648375B (en) Inner supporting structure based on shear wall as support
CN115262568B (en) Deepening support and excavation construction method based on zero-field deep foundation pit
JP3809340B2 (en) Reverse strike method
KR102579002B1 (en) Method of demolition of underground exterior walls
JPH02266016A (en) Structural process of underground concrete body of building
JPH03147926A (en) construction method for basement
JPS59177422A (en) Construction work of underground continuous wall using disposable formwork
JPH0849248A (en) Construction method for sheathing aining wall
JPH04368519A (en) Anchor retaining wall
JPH0238627A (en) Rebuilding of existing building
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
JPH0649982B2 (en) Construction method of underground structure
JP2005307688A (en) Construction method for earth retaining wall for newly built underground skeleton and construction method for newly built skeleton by use of its method