KR20000003270A - Tunnel construction method at area of thin soil surface - Google Patents

Tunnel construction method at area of thin soil surface Download PDF

Info

Publication number
KR20000003270A
KR20000003270A KR1019980024476A KR19980024476A KR20000003270A KR 20000003270 A KR20000003270 A KR 20000003270A KR 1019980024476 A KR1019980024476 A KR 1019980024476A KR 19980024476 A KR19980024476 A KR 19980024476A KR 20000003270 A KR20000003270 A KR 20000003270A
Authority
KR
South Korea
Prior art keywords
tunnel
tunnel construction
ground
construction method
lining concrete
Prior art date
Application number
KR1019980024476A
Other languages
Korean (ko)
Other versions
KR100289256B1 (en
Inventor
유근무
Original Assignee
유근무
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 유근무 filed Critical 유근무
Priority to KR1019980024476A priority Critical patent/KR100289256B1/en
Publication of KR20000003270A publication Critical patent/KR20000003270A/en
Application granted granted Critical
Publication of KR100289256B1 publication Critical patent/KR100289256B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE: A tunnel construction method at the area of thin soil surface is provided to reduce the destruction of nature by minimizing the area cut by cutting only the necessary part of the ground. CONSTITUTION: A tunnel construction method at the area of thin soil surface comprises the steps of: sticking a H-beam(10) at left and right sides of a tunnel construction point at a regular interval; cutting the ground as ensuring a working space(40) to an appropriate depth while inserting bracing plates(30) for preventing soil collapse at the rear face of the H-beam; establishing the connecting beams(50) lengthwise to be supported by the H-beams(10) in a specific depth inside of the secured working space(40); installing a flexible mold(100) on the surface of a curved base ground and a packing body; forming a semi circle-shaped lining concrete(100) by pouring the concrete; removing of excavated soil of the inner base ground(20) and the packing body after hardening the lining concrete(100); releasing the inner and outer molding plates(70)(90).

Description

토피가 얕은 지역의 터널구축방법Tunnel construction method in shallow toffee area

본발명은 터널의 입출구나 계곡부 등의 토피가 얕은 지역에 구축되는 터널의 구축방법으로서, 특히 사면을 안정시키면서 터널시공에 따른 토공량을 대폭적으로 줄여 줄 뿐만 아니라, 가급적 자연환경을 훼손하지 아니하고 보존할 수 있게 하고, 또한 터널내부의 지반을 이용하여 터널을 시공할 수 있는 토피가 얕은 지역의 터널구축방법에 관한 것이다.The present invention is a tunnel construction method that is constructed in shallow toffee areas such as tunnel entry and exit, and in particular, while stabilizing slopes, it greatly reduces the amount of earthwork due to the construction of tunnels, and preserves the natural environment as much as possible without damaging it. In addition, the present invention relates to a tunnel construction method in a shallow toffee area in which a tunnel can be constructed using the ground inside the tunnel.

일반적으로 터널굴착공법의 선정기준으로서는 터널시공시 안전성, 구조적 안정성검토, 지질조건에 적합한 공법, 공사기간, 작업환경성, 주변시설물 저촉여부, 경제성 등을 고려하여 현장여건에 적합한 공법을 채택하여 시공을 하게 된다.In general, the selection criteria for the tunnel excavation method are the construction method considering the safety, structural stability review, construction method suitable for geological condition, construction period, working environment, enviroment of surrounding facilities, and economic feasibility. Done.

그런데, 터널굴착공법으로서는 폭약발파에 의한 굴착공법 또는 TBM 등의 기계식 굴착장비를 이용한 굴착공법등으로 대별되며, 이와 같은 공법을 통하여 점차적으로 터널의 심도깊이를 증가시켜 가면서 굴진하여 터널을 구축하게 된다.However, tunnel excavation methods are roughly classified into excavation methods using explosive blasting or excavation methods using mechanical excavation equipment such as TBM. Through such a method, tunnels are gradually constructed by increasing the depth of tunnels. .

통상 터널을 굴착하기 위해서는 터널상부의 토피층이 어느 정도 두께이상 되어야 아칭작용에 의해 붕괴되지 않고 터널을 구축할 수 있는데, 도1에서 도시된 바와 같이, 터널의 입출구(A)나 계곡부(B)에서는 토피가 얕은 지형조건을 갖게 되어, 지형조건상 토피가 얕은 구간에서도 불가피하게 터널(T)을 구축하여야 하는 경우가 발생한다.In general, in order to excavate a tunnel, the toffee layer on the upper part of the tunnel must be thicker than a certain thickness so that the tunnel can be constructed without collapsing by arching. As shown in FIG. 1, the entrance and exit of the tunnel (A) and the valley (B) are shown. ), The toffee has a shallow topographic condition, and it is inevitable that a tunnel (T) must be constructed even in a section where the toffee is shallow due to the topographical condition.

따라서, 토피가 얕은 지역은 지반자체가 견고하지 못하므로 아칭작용을 할 수 없기 때문에 이러한 경우 종래의 터널건설방법으로서는 도2에서 도시된 바와 같이 오픈컷방식으로 터널을 구축할 수 밖에 없었다.Therefore, since the ground itself is not strong in the shallow toffee can not be arching action in this case, as a conventional tunnel construction method was forced to build a tunnel in the open cut method as shown in FIG.

즉, 종래의 토피가 얕은 지역의 터널구축방법은 오픈컷방식의 공법으로서 도2에서 도시된 바와 같이, 터널의 전단면 라이닝콘크리트(3)가 구축될 수 있는 충분한 크기로 지반(1)을 굴착하되, 좌우측의 사면(2)이 붕괴되지 않게 안전한 기울기를 갖도록 큰 범위로 절토를 실시한 후, 라이닝콘크리트를 형성하기 위한 거푸집 및 지지대(미도시)등을 가설하는 동바리공정을 거쳐 상기 거푸집 내부에 콘크리트를 타설하여 라이닝콘크리트(3)를 구축하고, 상기 라이닝콘크리트가 경화된 후에 지지대 및 거푸집을 해체한 후, 라이닝콘크리트(3)의 상부에 다시 토사(4)를 되메우기 함으로써 터널을 구축하는 공법을 취할 수 밖에 없었다.That is, the tunnel construction method of the conventional toffee shallow region is an open-cut method, as shown in Figure 2, excavating the ground (1) to a sufficient size for the front end lining concrete (3) of the tunnel can be built However, after cutting to a large extent so as to have a safe inclination so that the left and right slopes (2) do not collapse, the concrete inside the formwork through a copper bar process to install a formwork and a support (not shown) for forming the lining concrete After constructing the lining concrete (3), and after the lining concrete is cured, the support and formwork are dismantled, and then take the method of building the tunnel by backfilling the soil (4) on top of the lining concrete (3) There was no choice but to.

이와 같은 종래의 터널구축공법은 토피가 얕은 지형조건을 갖는 터널의 입출구나 계곡부에 터널을 구축하기 위해서 사면의 안정과 작업소요공간의 확보등 안전을 고려하여 소요공간이 충분히 확보될 때까지 대절토공사를 수반하는 것이 필연적으로 뒤따르게 된다.In the conventional tunnel construction method, in order to construct a tunnel at the entrance or valley of a tunnel having a toffee topographical condition, it is necessary to consider the safety of the slope and secure the required working space until the required space is secured. Accompanied by earthwork will inevitably follow.

즉, 터널의 입출구나 계곡부에서는 도1에서 점선으로 도시된 부분과 같이, 산의 중턱을 거의 깎아 내려야 하는 절토작업이 큰 범위로 이루어져서, 사면이 급하게 형성되어지며, 또한 사면의 높이가 높아져서 제반작업들을 수행하기도 어려울 뿐만 아니라, 특히 공사후에는 안정된 기존 사면의 균형이 깨져 산사태의 위험이 나타나 안전상의 취약부가 되는 최대의 문제점이 되고 있다.That is, in the entrance and the valley of the tunnel, as shown by the dotted line in Fig. 1, the cutting work that almost needs to be cut down the mountain slope is made in a large range, so that the slope is formed rapidly, and the height of the slope is increased. Not only is it difficult to carry out the work, but especially after construction, the stable balance of the existing slopes is broken, causing the risk of landslides, which is the biggest problem of being a safety vulnerability.

이와 같이, 터널의 입출구나 계곡부가 설치되는 지역의 지반이 안정되어 있던 상태에서 터널구축작업의 안전성을 확보하기 위하여 충분한 소요공간확보시까지 넓은 범위의 절토가 이루어짐으로써 지반의 안정을 깨뜨리게 될 뿐만 아니라, 급경사를 형성하게 되어 갱구부의 주변사면이 불안정하게 되며, 상대적으로 토사면의 높이가 높게 형성됨으로써 결국 갱구부의 주변사면에 작용하는 토압의 증대를 가져오게 된다.As such, a wide range of cutting is made until sufficient space is secured to secure the safety of the tunnel construction work while the ground of the tunnel entrance / valley area is stabilized, thus destroying the stability of the ground. Rather, the steep slope is formed so that the peripheral slope of the shaft portion becomes unstable, and the height of the soil slope is formed to be relatively high, resulting in an increase in earth pressure acting on the peripheral slope of the shaft portion.

이때, 갱구부 주변사면에 작용되는 토압(PA)을 수식으로 나타내면 PA=1/2γH2KA로 나타낼 수 있는데, 여기에서 PA는 주동토압, γ는 흙의 단위중량, H는 옹벽높이, KA는 주동토압계수이다.At this time, if the earth pressure (P A ) acting on the peripheral surface of the shaft can be expressed by the formula P A = 1 / 2γH 2 K A , where P A is the main earth pressure, γ is the unit weight of the soil, H is the retaining wall The height, K A, is the main dynamic pressure coefficient.

따라서, 갱구부의 주변사면에 작용되는 토압(PA)은 토사면 높이(H)의 제곱에 비례하게 되므로 토사면의 높이가 높을수록 토압이 증가되어 사면의 붕괴위험도 그만큼 증가되는 문제점이 발생된다.Therefore, the earth pressure P A acting on the peripheral slope of the shaft portion is proportional to the square of the height of the soil slope H, so the soil pressure increases as the height of the soil slope increases, so that the risk of collapse of the slope increases.

또한, 충분한 작업공간확보를 위한 대규모의 절토가 이루어짐으로써, 대절토의 사면이 발생하게 되므로 많은 공사비가 소요되고, 공사가 장기화되며, 자연환경이 파괴되어 미관상 안좋을 뿐만 아니라, 터널구축후에는 사면처리에 막대한 비용이 소요되고, 사면이 크게 형성되어짐에 따라 갱구부의 위치가 상대적으로 깊게 형성되어 인위적인 계곡이 형성됨으로써 환기가 불량해지며, 갱구부 앞에 응달이 발생되어 동절기에는 노면결빙으로 사고발생율이 크게 증가되는 문제점들이 있다.In addition, large-scale cuts are made to secure sufficient working spaces, and the slopes of the large cuts are generated, which requires a lot of construction costs, prolongs the construction, destroys the natural environment, and not only looks aesthetically bad. The cost is enormous, and as the slope is made larger, the position of the shaft is formed relatively deep, and artificial valleys are formed, resulting in poor ventilation, and shading occurs in front of the shaft. There are problems.

또한, 터널단면을 구축하기 위한 시공면에 있어서도 동바리공등 복잡한 공종들을 거쳐야 하는데, 상부단면을 형성하기 위한 공정을 간단하게 할 수 없어 그만큼 공기가 길어지게 되는 시공상의 문제점도 여전히 있게 된다.In addition, even in the construction surface for the construction of the tunnel cross-section, such as the construction of the complex work, but the process for forming the upper cross-section can not be simplified, there is still a problem in the construction is that the air is longer.

결론적으로 상기 종래의 오픈컷공법에 의해 터널구조물을 구축하기 위해서는 작업에 지장을 주지 않는 범위까지 토사를 굴착하여야 하는데, 그에 따라 사면의 안정을 깨뜨리게 되고, 또한 많은 토공사가 수반되어 공사비가 많이 들어 비경제적이고, 작업기간이 더 소요되는 등 여러가지의 문제점들이 필연적으로 따르게 된다.In conclusion, in order to construct the tunnel structure by the conventional open cut method, it is necessary to excavate the soil to the extent that it does not interfere with the work, thereby breaking the stability of the slope, and also entails a lot of construction costs Many problems are inevitably followed, such as being uneconomical and taking longer to work.

따라서, 본발명의 목적은 토사를 파내고 되메우기하는 토공량을 대폭적으로 줄임으로써 공사기간을 단축시켜 주며, 사면을 안정하게 하고 자연을 보호할 수 있는 토피가 얕은 지역의 터널구축방법을 제공하는데 있다.Therefore, the purpose of the present invention is to shorten the construction period by drastically reducing the amount of earth excavation and refilling the soil, and to provide a tunnel construction method in a shallow toffee area that can stabilize the slope and protect nature.

본발명의 다른 목적은 라이닝콘크리트를 구축하기 위한 거푸집을 지지시켜 주는 지지대를 사용하지 아니함으로써 작업성과 안전성을 증대시켜 주는 토피가 얕은 지역의 터널구축방법을 제공하는데 있다.Another object of the present invention is to provide a tunnel construction method in a shallow toffee area that increases workability and safety by not using a support for supporting formwork for constructing lining concrete.

본발명의 또다른 목적은 필요한 부분만 절토하여 절토하는 면적을 최소한으로 줄임으로써 자연환경의 파괴를 줄여주는 토피가 얕은 지역의 터널구축방법을 제공하는데 있다.Another object of the present invention is to provide a tunnel construction method in a shallow toffee area that reduces the destruction of the natural environment by cutting only necessary parts and reducing the cut area to a minimum.

도1은 터널이 설치되는 구간의 지형조건을 나타내는 도면1 is a view showing the topographical conditions of the section in which the tunnel is installed

도2는 종래의 개착식공법에 따른 터널구축에 대한 단면도Figure 2 is a cross-sectional view of the tunnel construction according to the conventional detachable method

도3a 내지 도3f는 본발명의 터널구축에 대한 단면도로서,3a to 3f are cross-sectional views of the tunnel construction of the present invention,

도3a는 터널이 설치되는 단면 좌우측벽에 H-말뚝들을 박아 토류판을 설치하고, 터널의 상부단면 형태대로 지반을 일부 굴토한 상태의 단면도Figure 3a is a cross-sectional view of a state in which the earth plate is installed by driving the H-pegments on the left and right side walls of the cross section where the tunnel is installed, and in the form of an upper cross section of the tunnel.

도3b는 H-말뚝들사이에 연결빔을 설치한 후 터널의 상부단면과 동일한 형태로 작 업공간에 충진체를 채운 상태의 단면도Figure 3b is a cross-sectional view of the filling state in the working space in the same form as the upper end of the tunnel after installing the connecting beam between the H-piles

도3c는 바탕지반과 충진체의 상면으로 거푸집을 설치한 후, 콘크리트를 타설한 상태의 도면Figure 3c is a view of the state after pouring the formwork to the upper surface of the ground and the filling body poured concrete

도3d는 콘크리트성형후 내부지반을 굴토하여 충진체를 제거하고 거푸집을 제거한 상태의 도면Figure 3d is a state of removing the filling and removing the formwork by excavating the internal ground after concrete molding

도3e는 터널 상부라이닝콘크리트 상부로 스티로폴 및 토사를 되메운 상태의 도면Figure 3e is a view of the styropol and soil filling the upper portion of the tunnel upper lining concrete

도3f는 터널 내부의 2차라이닝콘크리트를 타설한 상태의 도면Figure 3f is a view of the state in which the secondary lining concrete in the tunnel

도4는 본발명의 터널상부단면을 구축한 상태의 사시도4 is a perspective view of a state in which the upper section of the tunnel of the present invention is constructed;

도5는 본발명의 터널상부단면 모서리부에서의 콘크리트를 타설한 상태의 단면도Figure 5 is a cross-sectional view of the state in which the concrete is poured in the corner of the upper section of the tunnel of the present invention

도6은 본발명의 터널하부단면에 기성콘크리트패널이 설치된 상태의 단면도Figure 6 is a cross-sectional view of the ready-made concrete panel is installed on the lower cross section of the tunnel of the present invention

도7a는 토류판이 H-말뚝의 배면에 설치되고, 연결빔이 H-말뚝사이에 설치된 상태 의 평면도Figure 7a is a plan view of the earth plate is installed on the back of the H-pile, the connecting beam is installed between the H-pile

도7b는 토류판이 설치된 상태의 측면도Figure 7b is a side view of the earth plate installed

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10:H-말뚝 11:T형받침판 20:바탕지반10: H-peg 11: T-shaped support plate 20: Base ground plate

30:토류판 40:작업공간 50:연결빔30: earth plate 40: working space 50: connecting beam

60:충진체 70:내부 거푸집판 80:공간부60: Filler 70: Internal formwork 80: Space

90:외부 거푸집판 91:지지대 100:라이닝콘크리트90: Outer formwork 91: Support 100: Lining concrete

a:폴리에칠렌스티로폴 b:토사 c:기성콘크리트패널a: Polyester styropole b: Soil c: Ready-made concrete panel

이하, 본발명의 기술적 구성을 설명하면 다음과 같다.Hereinafter, the technical configuration of the present invention will be described.

본발명의 토피가 얕은 지역의 터널구축방법은, 터널구축지점의 좌우측에 일정간격으로 H-말뚝(10)들을 박고, 상기 H-말뚝(10)들의 내측사이에 단면이 반원형상의 바탕지반(20)을 형성하도록 만곡지게 절토하되, 상기 H-말뚝의 배면에 토사붕괴방지용 토류판(30)들을 끼워가면서 적절한 깊이까지 작업공간(40)을 확보해 나가면서 절토하고, 상기 확보된 작업공간(40) 내부의 소정깊이에서 상기 H-말뚝(10)들에 지지되도록 연결빔(50)들을 길이방향으로 설치한 후, 터널의 외주면을 이루도록 작업공간을 충진체(60)로 채우고, 만곡진 바탕지반 및 충진체의 표면에는 유연성이 좋은 거푸집을 설치한 후, 콘크리트를 타설하여 반원아치형의 라이닝콘크리트(100)를 형성하고, 상기 라이닝콘크리트(100)가 경화된 후에 그 내부지반(20)의 굴토 및 충진체(60)를 제거하고 내,외부 거푸집판(70)(90)을 탈형해 냄으로써 터널이 구축됨을 특징으로 하는 것이다.In the tunnel construction method of the toffee shallow region of the present invention, the H-pegments 10 are driven at regular intervals on the left and right sides of the tunnel construction point, and the semi-circular base ground 20 is formed between the inner sides of the H-pegments 10. Cut to be curved to form a), while cutting the earth 40 while securing the work space 40 to an appropriate depth while sandwiching the earth plate for preventing soil disintegration on the back of the H-pile, the secured work space 40 After installing the connecting beams 50 in the longitudinal direction so as to support the H-peg 10 at a predetermined depth therein, the work space is filled with the filling body 60 to form the outer circumferential surface of the tunnel, and the curved base ground and After installing the formwork with good flexibility on the surface of the filling body, the concrete is poured to form a semi-circular arch type lining concrete 100, and after the lining concrete 100 is hardened, the excavation and filling of the internal ground 20 Remove the sieve (60) and inside and outside It is characterized in that the tunnel is built by demolding the second formwork plate (70, 90).

즉, 본발명은 토피가 얕은 장소에 구축될 터널의 단면 좌우측방에 수직으로 박은 H-말뚝들에 토류판들을 끼워서 좌우측의 지반붕괴를 방지하면서 터널상부단면 라이닝콘크리트를 구축한 후, 터널내부의 지반을 나중에 굴토하여 하부단면을 시공하는 방식으로서, 터널상부단면 선시공 하부단면 후시공의 특징을 갖는다.That is, the present invention is to install the ground concrete in the tunnel upper section, while preventing the ground collapse of the left and right by inserting the earth plate in the H-peg perpendicular to the left and right sides of the tunnel to be built in a shallow toffee As a method of constructing the lower cross section later, the tunnel has the characteristics of the upper cross section pre-construction lower cross section post-construction.

또한, 상부단면을 시공하기 위하여 바탕지반을 거푸집을 지지하는데 이용하는 특징을 갖는다.In addition, it has the feature of using the base ground to support the formwork in order to construct the upper cross-section.

따라서, 본발명은 H-말뚝들에 토류판들을 끼워서 토사의 붕괴를 방지하게 됨으로써 사면을 안정시키게 되고, 또한 토사를 파내고 되메우는 토공량이 대폭적으로 감소됨으로써 절토하는 면적이 대폭적으로 줄어 들어 자연환경의 파괴도 감소시킬 수 있으며, 또한 바탕지반(20)을 거푸집을 지지하는데 이용하게 됨으로써 콘크리트 타설에 필요한 지지대등 동바리공정이 전혀 필요없게 된다.Therefore, the present invention is to stabilize the slope by inserting the earth plate in the H-piles to prevent the collapse of the soil, and also drastically reduced the amount of earth cut by digging and refilling the soil to reduce the area of the natural environment Destruction can also be reduced, and since the base ground 20 is used to support the formwork, there is no need for a copper bar process such as a support for concrete placing.

이하, 첨부도면들에 도시되는 대표적인 실시예를 통하여 본발명을 보다 구체적으로 살펴보면 다음과 같다.Hereinafter, the present invention will be described in more detail with reference to exemplary embodiments shown in the accompanying drawings.

본발명의 실시예로서 도3a 내지 3f에서 도시하는 바와 같이, 터널구축지점의 좌우측에 일정간격으로 H-말뚝(10)들을 박고, 상기 H-말뚝(10) 내측사이의 지반을 단면이 반원형상의 바탕지반(20)을 형성하도록 그 표면을 만곡지게 절토하되, 상기 H-말뚝들의 배면에 H-말뚝(10) 사이로 토사붕괴방지용 토류판(30)들을 길이방향으로 끼워가면서 적절한 깊이까지 작업공간(40)을 확보해 나가면서 절토하고, 상기 확보된 작업공간(40) 내부의 소정깊이에서 상기 H-말뚝(10)에 지지되도록 연결빔(50)들을 길이방향으로 설치한 후, 상기 작업공간(40)을 다시 토사 및 모래주머니등의 충진체(60)로 채우되 그 외주면이 상기 반원형의 바탕지반(20)의 외주면과 동일 곡률을 이루도록 채우고, 상기 바탕지반(20) 및 그 좌우측의 충진체(60) 상부표면 전체면에 걸쳐서 반원아치형의 내측 거푸집판(70)을 만곡시켜서 깔되 그 내부 거푸집판의 좌우 하단부는 상기 연결빔(50)에 지지되도록 설치하고, 상기 내부 거푸집판(70)의 외부에 적절한 간격을 두고 공간부(80)를 이루며 동일한 곡률로 설치되는 외부 거푸집판(90)을 설치하고, 상기 연결빔(50)의 상면에 그 하단부가 지지되며 상기 내,외부 거푸집판(70)(90)사이의 공간부(80)에 미경화콘크리트를 타설하여 반원아치형의 라이닝콘크리트(100)를 형성하고, 상기 라이닝콘크리트(100)가 경화된 후에 그 내부의 바탕지반(20)의 굴토 및 충진체(60)를 제거하고 내,외부 거푸집판(70)(90)을 탈형해 냄으로써 터널상부단면을 시공하는 점에서 본발명의 기본적인 기술사상을 구현하는 것이다.As an embodiment of the present invention, as shown in Figures 3a to 3f, the H-pegments 10 are driven at regular intervals on the left and right sides of the tunnel construction point, and the ground between the inner sides of the H-peg 10 is semicircular. Cut the surface to be curved to form the base ground 20, the work space 40 to the appropriate depth while sandwiching the earth-to-earth decay earth plate 30 between the H-peg 10 on the back of the H-peg 10 in the longitudinal direction ) And cuts while securing the connecting beams 50 in the longitudinal direction so as to be supported by the H-pile 10 at a predetermined depth inside the secured working space 40, and then the working space 40. ) Is filled again with a filler 60 such as soil and sandbags, the outer peripheral surface of which is the same curvature as the outer peripheral surface of the semicircular base ground 20, and the base ground 20 and its left and right filling bodies ( 60) The inside of semi-circle arch type over the entire upper surface Curving the formwork plate 70, the left and right lower ends of the inner formwork is installed so as to be supported by the connecting beam 50, forming a space portion 80 at an appropriate interval on the outside of the inner formwork plate 70 The outer formwork plate 90 is installed with the same curvature, the lower end is supported on the upper surface of the connecting beam 50, and the space between the inner and outer formwork plates 70, 90 is not in the space 80. Placing the hardened concrete to form a semi-circular arch-shaped lining concrete 100, after the lining concrete 100 is cured to remove the piles and fillings 60 of the base ground 20 therein, the inner and outer formwork By demolding the plates 70 and 90, the basic technical concept of the present invention is realized in that the tunnel upper section is constructed.

도3a에서 도시한 바와 같이, 먼저 터널이 설치되는 좌우측 지반에 H-말뚝(10)들이 일정간격으로 평행하게 터널의 폭과 같은 간격으로 박혀 말뚝박기가 완료된 후, 라이닝콘크리트(100)가 설치될 상부 토피층의 지반을 굴토하면서 H-말뚝(10) 사이로 토류판(30)을 끼워가면서 소정깊이까지 원지반을 만곡지게 굴토하는데, 이때 원지반의 좌,우측에는 작업공간(40)을 확보하기 위하여 말뚝으로부터 소정의 공간이 확보되도록 굴토한다.As shown in FIG. 3a, first, after the piling is completed, the H-pegs 10 are parallelly spaced at the same interval as the width of the tunnel in the left and right ground where the tunnel is installed, and the lining concrete 100 is installed. While rolling up the ground of the upper toffee layer, while sandwiching the earth plate 30 between the H-stacks 10, the ground is curved to a predetermined depth. At this time, the left and right sides of the ground are piled up to secure a working space 40. Gut to secure a predetermined space.

이때 원지반을 만곡지게 굴토하여 형성되는 바탕지반(20)의 상부표면이 전체적으로 터널의 상부단면과 같은 형상의 반원형상을 이루도록 원지반을 굴토하고 정리하는 것이 중요하다.At this time, it is important to excavate and arrange the ground so that the upper surface of the ground ground 20 formed by flexing the ground is formed in a semi-circle shape with the same shape as the upper section of the tunnel.

이것은 그 바탕지반(20)의 외주면 형상이 터널상부단면의 외주면형상과 같게 하여 바탕지반(20)의 상면에 설치되는 내부 거푸집판(70)을 지지할 수 있도록 하기 위한 것으로서, 이는 바로 터널상부단면의 라이닝콘크리트(100)를 반원아치형으로 성형시키게 하는 이유때문이다.This is to make the outer circumferential surface shape of the base ground 20 to be the same as the outer circumferential surface shape of the upper end surface of the tunnel so as to support the inner form plate 70 installed on the upper surface of the base ground 20, which is the tunnel upper end surface. This is because of the reason that the lining concrete of the 100 is molded into a semi-circular arch type.

또한, 굴토시 바탕지반(20)의 좌우측에 작업공간(40)을 확보하는 이유는 H-말뚝 (10)사이에 연결빔(50)을 장비로 운반하여 설치하기 위한 공간을 확보하기 위해서이다.In addition, the reason for securing the working space 40 on the left and right sides of the base ground 20 in order to secure a space for transporting and installing the connecting beam 50 to the equipment between the H-pile 10.

따라서 좌우측의 작업공간(40)은 연결빔(50)이 설치되는 깊이까지 굴토하면 되고, 그이외의 원지반은 반원아치형으로 굴토를 하면 된다.Therefore, the work space 40 on the left and right sides may be excavated to the depth where the connecting beam 50 is installed, and the other base may be excavated in a semicircular arch type.

한편, 상기 좌우 H-말뚝(10)간의 폭은 구축될 터널의 폭과 같게 된다. 이러한 H-말뚝(10)은 터널구축이 완료된 후에 터널의 라이닝콘크리트(100)를 지지하게 되므로 그 전체가 지반에 매립되어지는 것이나, H-말뚝(10)의 상부가 돌출될 경우에는 상측의 일부를 절단하여 빼내고 하측부만 지반에 매립시킬 수 있다.On the other hand, the width between the left and right H-peg 10 is equal to the width of the tunnel to be built. Since the H-pile 10 supports the lining concrete 100 of the tunnel after the tunnel construction is completed, the whole is buried in the ground, but when the upper part of the H-peg 10 protrudes, a part of the upper side Can be cut out and buried only in the lower part in the ground.

한편, H-말뚝(10) 사이에 지지되는 토류판(30)은 도4에서 도시한 바와 같이, H-말뚝(10)의 플랜지와 플랜지 사이에 끼워질 수도 있으나, 도5·도6 또는 도7a에서 도시한 바와 같이 플랜지와 플랜지 사이에 연결빔(50)이 설치되므로 H-말뚝(10)의 배면에 지지되는 것이 바람직하다.Meanwhile, the earth plate 30 supported between the H piles 10 may be fitted between the flange and the flange of the H pile 10 as shown in FIG. 4, but FIG. 5, FIG. 6 or FIG. 7A. As shown in the connecting beam 50 is installed between the flange and the flange is preferably supported on the back of the H-peg 10.

H-말뚝들의 말뚝박기와 원지반의 굴토작업 및 토류판이 설치된 이후, 도3b에서와 같이 H-말뚝(10)들의 소정깊이의 위치에 H-말뚝(10)의 플랜지와 플랜지 사이에 T형받침판(11)들을 용착시키고, 전후 H-말뚝(10)사이의 T형받침판(11)상에 연결빔(50)을 설치하게 되며, 연결빔(50)들의 설치가 완료되면 바탕지반(20)의 좌우측 작업공간(40)상에 토사 및 모래주머니등의 충진체(60)로 채워지는데 바탕지반(20)과 함께 전체적으로 그 외주면이 반원아치형으로 형성되도록 설치한다.After the piling of the H-piles and the excavation work of the ground plate and the earth plate are installed, the T-shaped support plate between the flange and the flange of the H-peg 10 at the position of the predetermined depth of the H-peg 10 as shown in Figure 3b ( 11) are welded, and the connecting beam 50 is installed on the T-shaped support plate 11 between the front and rear H-pile 10, and when the installation of the connecting beam 50 is completed, the left and right sides of the ground ground 20 Filled with a filler 60, such as soil and sand bags on the work space 40 is installed so that the outer peripheral surface is formed in a semi-circular arch shape with the base ground 20 as a whole.

상기 연결빔(50)은 H-말뚝(10)간에 길이방향으로 설치되는 구조부로서 라이닝콘크리트(100)의 하중을 H-말뚝(10)으로 전달시켜 주는 역할을 하게 된다. 이러한 연결빔(50)은 도5a 내지 도7b에서와 같이, 그 양단부가 전후 H-말뚝(10)의 플랜지와 플랜지 사이에 용착된 T형받침판(11)들의 상부에 걸처져서 지지됨을 보여준다.The connecting beam 50 serves to transfer the load of the lining concrete 100 to the H-peg 10 as a structural part installed in the longitudinal direction between the H-peg 10. This connecting beam 50 shows that both ends are supported across the top of the T-shaped support plates 11 welded between the flange and the flange of the front-rear H-pile 10, as in FIGS. 5A-7B.

따라서, 연결빔(50)이 H-말뚝(10)의 플랜지와 플랜지 사이에 설치됨으로써 콘크리트로 타설시공될 라이닝콘크리트(100)의 하중을 H-말뚝(10)으로 확실하게 전달지지시키게 된다.Therefore, the connecting beam 50 is installed between the flange and the flange of the H-peg 10 to ensure that the load of the lining concrete 100 to be cast in concrete to be transmitted to the H-peg 10.

상기 연결빔(50)의 설치가 완료되면, 도3b 및 도5에서 도시한 바와 같이 작업공간(40)을 다시 충진체(60)로 채워주게 된다. 이때 충진체(60)는 토사 또는 모래주머니 등으로 채워지게 되는데, 그 외주면이 상기 반원아치형의 바탕지반(20)의 외주면과 동일한 곡률선상으로 채워지는 것이 중요하다.When the installation of the connecting beam 50 is completed, as shown in Figure 3b and 5 to fill the workspace 40 with the filler 60 again. At this time, the filling body 60 is filled with earth or sand bags, it is important that the outer peripheral surface is filled with the same curvature line as the outer peripheral surface of the semi-circular arch type base ground 20.

작업공간(40)에 충진체(60)를 채우는 이유는 반원아치형의 바탕지반(20)과 함께 그 상면에 내부 거푸집판(70)이 설치될 시 지지력을 갖게 하기 위해서이며, 상기 충진체(60)는 작업공간을 채워주는 형태로써 지지력을 확보할 수 있는 것으로 여러개로 분할하여 채워지거나 반원아치형의 외주면에 부분적으로 사용되어지는 것이면 본발명의 기술사상에 포함되는 것임을 밝혀 둔다.The reason for filling the filling body 60 in the work space 40 is to have a supporting force when the inner formwork plate 70 is installed on the upper surface together with the semicircular arch type base ground 20, and the filling body 60 is provided. ) Is a form that fills the working space, and it can be found that if it is divided into several parts or partially used on the outer circumference of the semicircle arch type, it is included in the technical idea of the present invention.

작업공간(40)의 채움작업이 완료되면, 도3c에서와 같이, 상기 바탕지반(20) 및 그 좌우측의 충진체(60) 상부표면 전체면에 걸쳐서 반원아치형으로 만곡되는 내부 거푸집판(70)을 일체로 깔게 된다.When the filling operation of the working space 40 is completed, as shown in Figure 3c, the base plate 20 and the inner formwork plate 70 that is curved in a semi-circular arch shape over the entire surface of the upper and lower surfaces of the filler 60 on the left and right sides thereof. Will be integrally laid.

이러한 내부 거푸집판(70)은 유연성의 재질로서 이루어져서 바탕지반(20)과 충진체(60)의 상면에 지지되고, 그 좌우 하단부는 상기 연결빔(50)의 내측끝단부에 지지되어, 라이닝콘크리트(100)를 타설하기 위한 거푸집의 내측패널 역할을 수행하게 된다.The inner formwork plate 70 is made of a flexible material and is supported on the upper surface of the base ground 20 and the filler 60, and the lower left and right ends thereof are supported at the inner end of the connecting beam 50, thereby lining concrete. To serve as an inner panel of the formwork for pouring 100.

한편, 내부 거푸집판(70)을 설치할 때 라이닝콘크리트용 철근배근도 함께 배근해 나가는 것이 바람직하다.On the other hand, when installing the inner formwork 70, it is preferable to also reinforce the reinforcement for lining concrete.

상기 내부 거푸집판(70)의 외부에 일정한 간격을 갖는 공간부(80)를 유지하면서 내부 거푸집판(70)과 동일한 곡률로 설치되는 외부 거푸집판(90)을 설치하는데, 이러한 외부 거푸집판(90)은 내부 거푸집판과 일정한 간격을 갖고 설치되어 그 사이로 콘크리트를 타설하게 되며, 그 좌우 하단부는 연결빔(50)의 외측 끝단부에 지지되고 가운데부분은 토류판(30)과의 사이에 지지대(91)를 설치하여 지지시켜서 라이닝콘크리트(100)를 타설시 반원형상으로 성형시키도록 하는 거푸집의 외측패널 역할을 수행하게 된다.While maintaining the space portion 80 having a predetermined interval on the outside of the inner formwork plate 70 to install the outer formwork plate 90 is installed with the same curvature as the inner formwork plate 70, such an outer formwork plate 90 ) Is installed at regular intervals with the inner formwork to pour concrete therebetween, the left and right lower ends are supported on the outer end of the connecting beam 50 and the middle portion is supported by the earth plate 30 (91) ) To support and to serve as the outer panel of the formwork to mold the lining concrete 100 in a semi-circular shape when placing.

이때 외부 거푸집판(90)의 좌우 하단부는 연결빔(50)의 외측 끝단부에 지지되고 가운데부분은 지지대(91)로 지지시켜 줌으로써, 종래에 좌우 경사면에 지지대를 설치하는 가설공사가 쉽지 않았던 것과는 달리, 간단하게 지지할 수 있게 된다.At this time, the left and right lower ends of the outer formwork plate 90 are supported at the outer end of the connecting beam 50 and the center part is supported by the support 91, which is not easy to install a support on the left and right slopes in the past. Otherwise, it can be simply supported.

한편, 상기 내,외부 거푸집판 사이의 공간부(80)는 결국 라이닝콘크리트(100)가 형성되는 공간이므로 공간부(80)의 두께를 현장에 따라 구조적인 강도에 알맞게 부여하는 것이 바람직하다. 즉, 터널상부에 되메우는 토피량에 따라서 하중이 무거우면 라이닝콘크리트(100)를 두껍게 시공할 필요가 있고 하중이 비교적 가벼우면 얇게 시공할 필요가 있다.On the other hand, since the space 80 between the inner and outer formwork is a space where the lining concrete 100 is eventually formed, it is preferable to give the thickness of the space 80 to the structural strength according to the site. In other words, when the load is heavy according to the amount of toppings on the upper part of the tunnel, the lining concrete 100 needs to be thickly constructed, and when the load is relatively light, it is necessary to thinly construct it.

이 공간부(80)의 소정위치에 일정한 소요두께의 콘크리트성형을 위하여 도시하지는 않았으나, 내부 거푸집판과 외부거푸집판의 사이에 스페이서들을 설치할 수 있음은 물론이다.Although not shown for concrete molding of a predetermined required thickness at a predetermined position of the space portion 80, it is a matter of course that spacers can be installed between the inner formwork plate and the outer formwork plate.

상기 내,외부 거푸집판으로 이루어지는 거푸집공사가 완료되면, 거푸집 내부 공간부(80)에 미경화콘크리트를 타설하여 반원아치형의 라이닝콘크리트(100)를 형성하게 된다.When the formwork consisting of the inner and outer formwork is completed, the non-hardened concrete is poured into the form inner space 80 to form a semi-circular arched lining concrete 100.

라이닝콘크리트를 형성하기 위한 콘크리트타설시 이 외부 거푸집판(90)은 여러개로 분할하여 설치할 수도 있으나, 중앙부를 제외한 좌우측 2개의 외부 거푸집판(90)을 사용하는 것이 바람직하며, 중앙부는 콘크리트를 채워넣어 바르는 작업형태로도 마무리가 가능하다.When laying concrete for forming lining concrete, the external formwork plate 90 may be divided into several pieces, but it is preferable to use two external formwork plates 90 on the left and right except the center part, and the center part is filled with concrete. It can be finished in the form of application.

이렇게 성형되어진 라이닝콘크리트(100)의 좌우 하단부는 연결빔(50)에 지지된다. 따라서 라이닝콘크리트(100)의 하중은 연결빔(50)과 H-말뚝(10)을 통하여 지반으로 전달된다.The left and right lower ends of the molded concrete lining 100 are supported by the connection beam 50. Therefore, the load of the lining concrete 100 is transmitted to the ground through the connecting beam 50 and the H-peg 10.

따라서, 내부 거푸집판(70)이 바탕지반(20)과 충진체(60)의 상면에 지지되기 때문에 종래에 지지대를 가설하였던 것과는 달리, 지지대를 가설할 필요가 없으므로 작업성을 증대할 수 있고 경제적이 된다.Therefore, since the inner formwork plate 70 is supported on the upper surface of the base ground 20 and the filling body 60, unlike the conventional support structure, there is no need to install the support structure, thereby increasing workability and economical efficiency. Becomes

상기 라이닝콘크리트(100)가 경화되면 도3d에서 도시한 바와 같이, 내부의 바탕지반(20)을 소정의 깊이로 굴토하는데, 내부 거푸집을 지지하고 있는 반원아치형의 바탕지반(20)을 굴토하고 좌우측 작업공간상에 채워져 있는 충진체(60)를 제거하고, 또한 내,외부 거푸집판(70)(90)을 탈형해 냄으로써 라이닝콘크리트(100)가 성형되어진다.When the lining concrete 100 is hardened, as shown in FIG. 3d, the inner base 20 is excavated to a predetermined depth, and the base ground 20 of the semicircular arch type supporting the inner form is excavated and left and right sides. The lining concrete 100 is molded by removing the filler 60 filled in the work space and demolding the inner and outer formwork plates 70 and 90.

그후, 라이닝콘크리트(100) 상부를 되메우기 할 때 도3e에서 도시한 바와 같이, 라이닝콘크리트(100)의 좌우측부에 폴리에칠렌 스티로폴(a)로 채우고, 그 상면에 토사(b)를 채워 되메우기를 한다.Thereafter, when filling the upper part of the lining concrete 100, as shown in Figure 3e, the left and right sides of the lining concrete 100 is filled with polyethylene styropole (a), and the soil (b) is filled on the upper surface of the back filling.

여기에서, 라이닝콘크리트(100)의 좌우측부에 폴리에칠렌 스티로폴(a)로 채워주는 이유는 가벼운 물질로 채워줌으로써 터널상면에 적재되는 하중을 덜어주기 위함이다.Here, the reason for filling the left and right sides of the lining concrete 100 with polyethylene styropol (a) is to reduce the load on the tunnel upper surface by filling with a light material.

한편, 필요에 따라서 H-말뚝(10) 상부를 잘라내고 토사를 되메우기 해 주는데, 이때 H-말뚝(10) 상부를 잘라내는 위치는 충진체(60)가 채워진 부분의 상측에서 이루어지는 것이 바람직하다. 이는 H-말뚝(10)의 바깥쪽에 굴토되지 않은 지반의 토압이 터널의 상부단면으로 영향을 주지 않게 하기 위해서이다.On the other hand, if necessary, cut the upper portion of the H-pile 10 and backfills the earth and sand, wherein the position to cut the upper portion of the H-pile 10 is preferably made on the upper side of the filling portion 60 is filled. This is to prevent the earth pressure of the ground that is not excavated outside of the H-pile 10 does not affect the upper section of the tunnel.

그후, 상기 라이닝콘크리트(100)의 하단부에는 도3f에서 도시한 바와 같이, 기존의 터널구축방법으로 시공하거나, 도6에서 도시한 바와 같이 기성콘크리트패널(c)을 적층하여 시멘트몰탈이나 숏크리트로 표면의 요철 및 공극을 정리한다.Thereafter, as shown in Figure 3f, the lower end portion of the lining concrete 100 is constructed by a conventional tunnel construction method, or as shown in Figure 6 by laminating a ready-made concrete panel (c) surface of cement mortar or shotcrete Clean up irregularities and voids.

이후 도3f에서 도시하는 바와 같이, 일반터널구축과 같은 공정으로서 시트방수처리를 한 후, 2차라이닝콘크리트공사를 하면서 터널구축에 따른 계속공사를 진행한다.Thereafter, as shown in FIG. 3F, after the sheet waterproofing is performed in the same manner as in the general tunnel construction, the secondary construction is performed while continuing the construction according to the tunnel construction.

이와 같이, 본발명은 터널이 구축되는 지점의 토피가 얕은 경우에 적용할 수 있는 공법으로서, 터널상부단면을 먼저 시공하고, 이후 내부지반을 굴착하여 터널하부단면을 후시공하는 공법을 통하여 터널을 구축하게 된다.As described above, the present invention is a method that can be applied when the toffee at the point where the tunnel is constructed is constructed, the tunnel upper section is first constructed, and then the inner ground is excavated to construct the tunnel through the tunnel construction section. To build.

따라서, 터널굴착공사시 토피가 얕은 장소에 구축될 터널의 단면 좌우측방에 수직지지빔을 설치하여 사전 상부라이닝공사를 본공사에 앞서 실시하는 것으로서, 토사를 많이 절토하지 않고서도 시공이 가능하다.Therefore, by installing vertical support beams in the left and right sides of the cross section of the tunnel to be constructed in a shallow toffee during tunnel excavation construction, the upper lining construction is performed in advance of the main construction, and the construction can be performed without cutting much soil.

이에 따라, 터널의 입출구나 계곡 등의 토피가 얕은 지역에서 사면이 안정되고, 산사태의 위험이 없어질 뿐만 아니라, 절토하는 범위를 크게 하지 않아도 되기 때문에 공기를 단축할 수 있고, 또한, 자연환경의 파괴를 최소한으로 할 수 있게 되며, 시공후에는 노면결빙으로 인한 사고가 예방된다.As a result, slopes are stabilized in areas with shallow toffees such as tunnel entrances and valleys, and there is no risk of landslides. Minimization of destruction is possible, and after construction, accidents caused by freezing of roads are prevented.

이와 같이 본발명은 첫째, 본발명은 터널을 구축하기 위한 대단위의 토공을 수반하지 않으므로 터널의 입출구나 계곡부 주위의 사면이 안정됨으로써 안전사고의 위험이 없어지며,Thus, the present invention, first, the present invention does not involve large-scale earthwork to build a tunnel, so that the slope of the entrance and exit of the tunnel is stabilized around the valley, and there is no risk of safety accidents.

둘째, 본발명은 좌우 H-말뚝(10)에 토류판(30)을 끼워서 지반의 붕괴를 방지한 상태에서 굴토 및 성토를 하기 때문에 토공량이 대폭적으로 감소되어 건설비용이 절감되고 전반적인 공사기간을 단축시켜 주는 효과가 있으며,Second, the present invention, because the soil plate 30 is inserted into the left and right H-pile 10 to prevent the collapse of the ground to excavate and fill the soil, the earthwork volume is drastically reduced, thereby reducing the construction cost and shortening the overall construction period. Giving effect,

셋째, 바탕지반(20)을 거푸집을 지지하는데 이용하고, 라이닝콘크리트(100)를 타설한 후에 바탕지반(20)을 굴착하는 것이므로, 종래 터널라이닝공사를 위하여 복잡한 동바리공, 지주대 등을 가설했던 것과는 달리, 지지대가 전혀 필요없게 되어 시공작업의 용이성과 시공비를 감축시키는 효과가 있으며,Third, since the ground ground 20 is used to support the formwork, and the ground ground 20 is excavated after the lining concrete 100 is poured, the conventional ground lining and the support base were hypothesized for the tunnel lining construction. Contrary to this, there is no need for support, which reduces the ease of construction and the cost of construction.

넷째, 절토하는 면적이 종래에 비하여 대폭적으로 줄여 들므로 자연환경의 파괴를 감소시킬 수 있는 효과가 있다.Fourth, since the cut area is drastically reduced compared to the prior art has the effect of reducing the destruction of the natural environment.

이상에서 살펴본 바와 같이, 본발명은 불필요한 절토 및 성토량을 줄임으로써 사면의 안정을 기할 수 있을 뿐만 아니라, 전체적으로 공사기간이 단축되고 공사비를 감소시킬 수 있으며, 또한 터널상부단면을 형성하기 위하여 터널내부의 지반을 거푸집을 지지하는데 이용함으로써 시공작업의 단순화를 기한 유용한 발명이다.As described above, the present invention can not only stabilize the slope by reducing unnecessary cut and fill amount, but also shorten the construction period and reduce the construction cost as a whole, and also to form the upper section of the tunnel. It is a useful invention to simplify the construction work by using the ground to support the formwork.

Claims (7)

터널구축지점의 좌우측에 일정간격으로 H-말뚝(10)들을 박고, 상기 H-말뚝(10)들의 내측사이에 단면이 반원형상의 바탕지반(20)을 형성하도록 만곡지게 절토하되, 상기 H-말뚝의 배면에 토사붕괴방지용 토류판(30)들을 끼워가면서 적절한 깊이까지 작업공간(40)을 확보해 나가면서 절토하고, 상기 확보된 작업공간(40) 내부의 소정깊이에서 상기 H-말뚝(10)들에 지지되도록 연결빔(50)들을 길이방향으로 설치한 후, 터널의 외주면을 이루도록 작업공간을 충진체(60)로 채우고, 만곡진 바탕지반 및 충진체의 표면에는 유연성이 좋은 거푸집을 설치한 후, 콘크리트를 타설하여 반원아치형의 라이닝콘크리트(100)를 형성하고, 상기 라이닝콘크리트(100)가 경화된 후에 그 내부지반(20)의 굴토 및 충진체(60)를 제거하고 내,외부 거푸집판(70)(90)을 탈형해 냄으로써 터널이 구축됨을 특징으로 하는 토피가 얕은 지역의 터널구축방법.H-piles 10 are driven to the left and right sides of the tunnel construction point at regular intervals, and the cuts are bent so as to form a semi-circular base ground 20 between the inner sides of the H-piles 10, the H-peg While cutting the work space 40 to the appropriate depth while inserting the earth and sand prevention earth plate 30 on the back of the, the H-peg 10 at a predetermined depth inside the secured work space 40 After installing the connecting beams 50 in the longitudinal direction to be supported in, fill the working space with the filler 60 to form the outer circumferential surface of the tunnel, and after installing a flexible formwork on the curved base ground and the surface of the filler After placing the concrete to form a semi-circular arch-shaped lining concrete 100, after the lining concrete 100 is cured, remove the piles and fillings 60 of the inner ground 20 and the inner and outer formwork plate ( Demolding 70) (90) Tunnel construction method of toffee shallow areas with features that axis. 제1항에 있어서, 충진체(60)는 토사 및 모래주머니로 이루어지는 것임을 특징으로 하는 토피가 얕은 지역의 터널구축방법.The tunnel construction method according to claim 1, wherein the filling body (60) is made of soil and sandbags. 제1항에 있어서, 상기 거푸집은 합판으로 이루어진 것임을 특징으로 하는 토피가 얕은 지역의 터널구축방법.The tunnel construction method of claim 1, wherein the formwork is made of plywood. 제1항에 있어서, 상기 연결빔(50)은 그 양단부를 상기 H-말뚝(10)의 플랜지와 플랜지 사이에 용착된 T형받침판(11) 상부에 설치되어 시공함을 특징으로 하는 토피가 얕은 지역의 터널구축방법.According to claim 1, wherein the connecting beam 50 is installed on the upper end of the T-shaped support plate 11 is welded between the flange and the flange of the H-pile 10, the toffee is shallow Local tunnel construction method. 제1항에 있어서, 상기 라이닝콘크리트(100)는 그 하단부가 연결빔(50)으로 하중이 전달지지되게 시공됨을 특징으로 하는 토피가 얕은 지역의 터널구축방법.The method of claim 1, wherein the lining concrete (100) is a tunnel construction method in the toffee shallow region, characterized in that the lower end is constructed so that the load is transmitted to the connection beam (50). 제1항에 있어서, 상기 라이닝콘크리트(100)의 상면 좌우측부에 폴리에칠렌 스티로폴(a)로 채운 후, 적절한 높이로 토사(b)를 되메우기하여 시공함을 특징으로 하는 토피가 얕은 지역의 터널구축방법.The tunnel construction method of claim 1, wherein after filling the upper and left sides of the lining concrete 100 with polystyrene styropol (a), the earth and sand (b) are refilled at an appropriate height. . 제1항에 있어서, 상기 라이닝콘크리트(100)의 하단부에는 기성콘크리트패널(c)을 H-말뚝(10)사이에 적층한 후, 시멘트몰탈로 요철 및 공극을 채워 시공함을 특징으로 하는 토피가 얕은 지역의 터널구축방법.According to claim 1, Topi is characterized in that the bottom of the lining concrete 100 is laminated with a ready-made concrete panel (c) between the H-pile 10, filling the irregularities and voids with cement mortar Tunnel construction in shallow areas.
KR1019980024476A 1998-06-26 1998-06-26 Tunnel construction method in shallow toffee area KR100289256B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1019980024476A KR100289256B1 (en) 1998-06-26 1998-06-26 Tunnel construction method in shallow toffee area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1019980024476A KR100289256B1 (en) 1998-06-26 1998-06-26 Tunnel construction method in shallow toffee area

Publications (2)

Publication Number Publication Date
KR20000003270A true KR20000003270A (en) 2000-01-15
KR100289256B1 KR100289256B1 (en) 2001-05-02

Family

ID=19541026

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1019980024476A KR100289256B1 (en) 1998-06-26 1998-06-26 Tunnel construction method in shallow toffee area

Country Status (1)

Country Link
KR (1) KR100289256B1 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030037086A (en) * 2001-11-02 2003-05-12 (주)청석엔지니어링 A Shallow Semi Cut and Cover Tunneling Method in Soft Ground and at Portal
KR100442690B1 (en) * 2000-11-10 2004-08-02 유근무 Tunnel Construction Method for using Wave Profile Type Steel Plate
KR100711576B1 (en) * 2005-11-08 2007-04-27 삼성물산 주식회사 Reinforcement structure for entrance of tunnel and construction method thereof
KR100890697B1 (en) * 2007-08-24 2009-03-26 허한구 Excavation-tunnel type Construction method of open tunnel-part
KR101640449B1 (en) * 2015-12-21 2016-07-18 우경기술주식회사 Construction method for open cutting in tunnel portal area
KR101655217B1 (en) * 2016-06-08 2016-09-07 우경기술주식회사 Construction method for open cutting in tunnel portal area
KR20190059533A (en) * 2017-11-23 2019-05-31 강원대학교산학협력단 Multiple-storied tunnel and construction method thereof
CN109869163A (en) * 2019-04-03 2019-06-11 北京市市政工程设计研究总院有限公司 A kind of construction method and structure of tunnel
CN110863515A (en) * 2019-12-17 2020-03-06 中铁二局集团有限公司 Bottom backfill structure of common-wall tunnel group and construction method thereof
CN111502691A (en) * 2020-05-15 2020-08-07 中铁二院工程集团有限责任公司 Anti-slip tunnel structure and construction method thereof

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101254608B1 (en) * 2010-08-19 2013-04-15 쌍용건설 주식회사 Tunnel construction method with support walls
KR101647074B1 (en) * 2016-06-07 2016-08-09 정진호 Apparatus for plating jig

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100442690B1 (en) * 2000-11-10 2004-08-02 유근무 Tunnel Construction Method for using Wave Profile Type Steel Plate
KR20030037086A (en) * 2001-11-02 2003-05-12 (주)청석엔지니어링 A Shallow Semi Cut and Cover Tunneling Method in Soft Ground and at Portal
KR100711576B1 (en) * 2005-11-08 2007-04-27 삼성물산 주식회사 Reinforcement structure for entrance of tunnel and construction method thereof
KR100890697B1 (en) * 2007-08-24 2009-03-26 허한구 Excavation-tunnel type Construction method of open tunnel-part
KR101640449B1 (en) * 2015-12-21 2016-07-18 우경기술주식회사 Construction method for open cutting in tunnel portal area
KR101655217B1 (en) * 2016-06-08 2016-09-07 우경기술주식회사 Construction method for open cutting in tunnel portal area
KR20190059533A (en) * 2017-11-23 2019-05-31 강원대학교산학협력단 Multiple-storied tunnel and construction method thereof
CN109869163A (en) * 2019-04-03 2019-06-11 北京市市政工程设计研究总院有限公司 A kind of construction method and structure of tunnel
CN110863515A (en) * 2019-12-17 2020-03-06 中铁二局集团有限公司 Bottom backfill structure of common-wall tunnel group and construction method thereof
CN111502691A (en) * 2020-05-15 2020-08-07 中铁二院工程集团有限责任公司 Anti-slip tunnel structure and construction method thereof

Also Published As

Publication number Publication date
KR100289256B1 (en) 2001-05-02

Similar Documents

Publication Publication Date Title
KR20210119861A (en) Slurry wall, construction method for the same and wire mesh assembly
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP7232714B2 (en) how to build a foundation
JP3893056B2 (en) Construction method of underground structure
JP2000352296A (en) Method o constructing passage just under underground structure
KR101884663B1 (en) Construction method for soil retaining wall using cap slab
JP3135826B2 (en) How to build an arch tunnel structure in embankment
JP6860895B2 (en) Retaining wall and its construction method
KR102289576B1 (en) Top-down type underground structure construction method using earth support plate
JPH06306853A (en) Construction of underground structure
KR100442690B1 (en) Tunnel Construction Method for using Wave Profile Type Steel Plate
JPS6117696A (en) Construction of underground head
KR100401330B1 (en) A method of construction for earth-protection walls of building
JP3234820B2 (en) Retaining wall construction method and construction of retaining wall for building residential land
JPS5851092B2 (en) Earth retaining installation method using advance shoring frame
KR200231108Y1 (en) Tunnel Construction Structure for using Wave Profile Type Steel Plate
JPH09184116A (en) Construction method of snowslide/falling stone guard fence and the fence
KR102371284B1 (en) Slurry wall, construction method for the same and wire mesh assembly
JPS6018769B2 (en) Construction method of underground structure
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
CN111648375B (en) Inner supporting structure based on shear wall as support
KR102272494B1 (en) Slope reinforcement structure using support and tension and Its Construction method
JPH0654016B2 (en) Underground space construction method
JP2004132124A (en) Pneumatic caisson and pneumatic caisson constructing method
JPS6016535B2 (en) How to form retaining walls and underground walls

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
N231 Notification of change of applicant
FPAY Annual fee payment

Payment date: 20040218

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee