KR102272494B1 - Slope reinforcement structure using support and tension and Its Construction method - Google Patents

Slope reinforcement structure using support and tension and Its Construction method Download PDF

Info

Publication number
KR102272494B1
KR102272494B1 KR1020210017890A KR20210017890A KR102272494B1 KR 102272494 B1 KR102272494 B1 KR 102272494B1 KR 1020210017890 A KR1020210017890 A KR 1020210017890A KR 20210017890 A KR20210017890 A KR 20210017890A KR 102272494 B1 KR102272494 B1 KR 102272494B1
Authority
KR
South Korea
Prior art keywords
pile
sacrificial
support
piles
slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020210017890A
Other languages
Korean (ko)
Inventor
윤창걸
Original Assignee
주식회사 미강이엔씨
윤창걸
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 미강이엔씨, 윤창걸 filed Critical 주식회사 미강이엔씨
Priority to KR1020210017890A priority Critical patent/KR102272494B1/en
Application granted granted Critical
Publication of KR102272494B1 publication Critical patent/KR102272494B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0216Cribbing walls
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/207Securing of slopes or inclines with means incorporating sheet piles or piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Retaining Walls (AREA)

Abstract

The present invention relates to a slope reinforcement structure using bearing capacity and tensile strength, and a construction method thereof. An objective of the present invention is to effectively stabilize a slope. According to the present invention, the slope reinforcement structure using bearing capacity and tensile strength comprises a plurality of support piles (20), a composite wall (10), a tension material (30), and a manual earth rock unit.

Description

지지력과 긴장력을 이용한 사면 보강 구조물 및 이의 시공 방법{Slope reinforcement structure using support and tension and Its Construction method}Slope reinforcement structure using support and tension and Its Construction method

본 발명은 사면 보강 구조물에 관한 것으로, 더욱 상세하게는 흙막이 시설을 이용하여 절토를 최소화하고 흙막이 시설을 지지하여 안전한 시공이 가능하고 시공 후 구조적 강성도 우수한 지지력과 긴장력을 이용한 사면 보강 구조물 및 이의 시공 방법에 관한 것이다.The present invention relates to a slope reinforcement structure, and more particularly, a slope reinforcement structure using a retaining force and tension, which minimizes cutting by using a retaining facility, supports the retaining facility, enables safe construction, and has excellent structural rigidity after construction, and a construction method thereof is about

이 부분은 본 출원 내용과 관련된 배경 정보를 제공할 뿐 반드시 선행기술이 되는 것은 아니다.This section provides background information related to the subject matter of the present application and is not necessarily prior art.

옹벽과 지하구조물은 흙을 지지하는 벽체로서 제한된 용지를 최대한 확보하기 위한 목적으로 비탈면 하부에 설치된다. 현행 설치되고 있는 옹벽으로는 깎기 비탈면에 설치되는 콘크리트 옹벽 등이 있다. 콘크리트 옹벽은 자연 비탈면을 깎은 후 무근 또는 철근 콘크리트 구조물을 설치하여 비탈면의 횡방향 토압에 저항하는 구조의 옹벽이다.Retaining walls and underground structures are walls that support the soil, and are installed under the slope for the purpose of securing the limited land as much as possible. Retaining walls currently being installed include concrete retaining walls installed on cut slopes. A concrete retaining wall is a retaining wall of a structure that resists the lateral earth pressure of a slope by installing an unreinforced or reinforced concrete structure after cutting the natural slope.

이러한 옹벽은 토압에 저항하는 가장 일반적인 구조물로서, 도로, 철도, 하천, 교대 등 용지의 제한에 따른 토지의 최적 이용을 목적으로 사용되고 있다. These retaining walls are the most common structures that resist earth pressure, and are used for the purpose of optimal use of land due to site restrictions such as roads, railways, rivers, and bridges.

이와 같은 옹벽은 사면의 절토 작업을 필요로 하게 되는데, 이 절토 작업이 시간적, 비용적 측면에서 볼 때 비합리적이고 안정성도 좋지 못한 단점이 있으며, 이러한 단점을 해결하기 위하여 흙막이 가시설을 이용한 방법이 제안된 바 있다.Retaining walls like this require cutting work on the slope, and this cutting work is unreasonable in terms of time and cost and has poor stability. In order to solve this shortcoming, a method using temporary retaining facilities has been proposed. there is a bar

등록특허 제10-1465149호는 성토사면 또는 절토사면의 전면에 시공되어 횡방향 토압을 지지하는 합벽식 옹벽에 있어서, H-파일, 토류판 및 영구앵커로 구성되고, 상기 영구앵커의 두부에 띠장이 형성되며, 성토사면 또는 절토사면의 전면에 시공되는 흙막이 구조물; 상기 흙막이 구조물의 전면 하부에 타설되는 기초 콘크리트; 프리캐스트 제작되고, 상기 기초 콘크리트 상에 적층식으로 설치되는 적어도 하나 이상의 중력블록; 상기 흙막이 구조물의 띠장과 상기 중력블록을 횡방향으로 연결하는 후크형 연결부재; 및 상기 흙막이 구조물 및 상기 중력블록 사이의 공간에 타설되는 뒷채움 콘크리트를 포함하되, 상기 흙막이 구조물, 상기 중력블록 및 상기 뒷채움 콘크리트가 일체화되어 합벽식 옹벽을 형성하며, 상기 앵커 두부에 설치되는 H형강인 띠장은 H-파일과 토류판 배면에 수평방향으로 설치되어, 상기 띠장 전면에 앵커 두부가 지지되도록 설치되고, 상기 후크형 연결부재는, 흙막이 구조물의 앵커 두부가 지지되도록 설치된 띠장으로부터 연장 형성되는 정착 후크; 및 일단이 상기 중력블록 각각의 측면에 매립되고, 타단이 상기 흙막이 구조물 방향으로 돌출되도록 형성되어, 상기 정착 후크와 체결되는 블록 후크를 포함하되, 상기 정착 후크는 H 형강인 띠장의 플랜지 내측에 걸려져 정착(종방향 길이(d1))되도록 한 것이며, 뒷채움 콘크리트의 불필요한 공정을 수반하고, 영구앵커의 설치를 위한 천공 등 복잡하고 어려운 작업을 수반하는 등의 문제점이 있다.Registered Patent No. 10-1465149 discloses a combined wall retaining wall that is constructed on the entire surface of a fill slope or cut slope to support lateral earth pressure, and is composed of an H-pile, an earth plate and a permanent anchor, and a wale is placed on the head of the permanent anchor. a retaining structure that is formed and is constructed on the entire surface of the fill slope or the cut slope; Foundation concrete to be poured on the lower front of the retaining structure; At least one gravity block manufactured by precast and installed in a laminated manner on the foundation concrete; a hook-type connecting member connecting the wale of the retaining structure and the gravity block in the transverse direction; and backfilling concrete poured into the space between the retaining structure and the gravity block, wherein the retaining structure, the gravity block, and the backfilling concrete are integrated to form a junction-type retaining wall, and an H-shaped steel installed on the head of the anchor The wale is installed in the horizontal direction on the rear surface of the H-pillar and the earth plate, so that the anchor head is supported on the front of the wale, and the hook-type connecting member is formed extending from the wale installed so that the anchor head of the retaining structure is supported. ; and a block hook having one end embedded in each side of the gravity block, the other end protruding in the direction of the retaining structure, and fastened with the anchoring hook, wherein the anchoring hook is hung inside the flange of the H-shaped wale. It is designed to be fixed (longitudinal length (d1)), and it entails unnecessary processes of backfilling concrete, and there are problems such as complicated and difficult work such as drilling for installation of permanent anchors.

등록특허 제10-1465149호Registered Patent No. 10-1465149

본 발명은 전술한 바와 같은 문제점을 해결하기 위한 것으로, 절토 작업을 최소화하고 흙막이 시설의 설치 작업을 단순화하면서도 합성 벽체를 견고하고 안전하게 유지할 수 있는 지지력과 긴장력을 이용한 사면 보강 구조물 및 이의 시공 방법을 제공하려는데 그 목적이 있다. The present invention is to solve the problems as described above, and provides a slope reinforcement structure and a construction method thereof using the bearing capacity and tension that can keep the composite wall strong and safe while minimizing the cutting work and simplifying the installation work of the retaining facility. There is a purpose to do that.

본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물은, 상호 간에 일정 간격을 두고 사면의 지중에 삽입 설치되어 사면의 토사층에 의한 수동 토압을 받아 지지되는 다수의 지지말뚝과; 콘크리트의 벽체부와 흙막이 시설의 조합으로 이루어지며 상기 지지말뚝의 앞쪽에 일정 거리를 두고 시공되는 합성 벽체와; 상기 지지말뚝과 합성 벽체에 고정되어 상기 지지말뚝을 지지기반으로 하여 상기 합성 벽체를 지지하는 긴장재를 포함하며, 상기 합성 벽체는 상기 흙막이 시설이 상호 간에 일정 거리를 두고 지중에 삽입되는 다수의 희생말뚝, 상기 희생말뚝들의 사이에 횡방향으로 배열되면서 연결되는 띠장, 상기 희생말뚝들의 사이에 설치되는 토류판을 포함하고, 상기 벽체부는 상기 희생말뚝과 합성 시공되는 것을 특징으로 한다.The slope reinforcement structure using the bearing and tension forces according to the present invention comprises: a plurality of support piles inserted and installed in the ground of the slope at a predetermined distance from each other and supported by passive earth pressure by the soil layer of the slope; a composite wall made of a combination of a concrete wall part and a retaining facility and constructed at a predetermined distance in front of the support pile; A plurality of sacrificial piles fixed to the support pile and the composite wall to support the composite wall based on the support pile as a support base, wherein the composite wall is inserted into the ground at a predetermined distance between the retaining facilities. , a wale connected while being arranged in the transverse direction between the sacrificial piles, and an earth plate installed between the sacrificial piles, wherein the wall portion is compositely constructed with the sacrificial piles.

상기 희생말뚝은 경사면에 지지말뚝과 높이가 다르게 설치될 경우 경사로 설치가 용이한 경사쐐기와 경사긴장재를 포함하는 것을 특징으로 한다.The sacrificial pile is characterized in that it includes an inclined wedge and an inclined tension material that is easy to install on a ramp when the sacrificial pile is installed at a different height from the support pile.

본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물의 시공 방법은, 사면의 토사층에 다수의 지지말뚝을 삽입 설치하고 상기 지지말뚝의 앞에 희생말뚝을 설치하는 제1단계와; 상기 지지말뚝과 상기 흙막이 시설 사이의 토사층에 공간을 확보하고 긴장재를 거치한 후 길이방향의 양쪽을 상기 지지말뚝과 흙막이 시설의 희생말뚝에 각각 연결하여 설치하는 제2단계와; 상기 희생말뚝의 전면부를 터파기하고 띠장과 토류판을 설치하여 흙막이 시설을 시공하며, 상기 지지말뚝과 희생말뚝 사이의 토사층 위에 배수로 및 수동 토압부를 시공하는 제3단계와; 제3단계에서 설치한 흙막이 시설의 앞에 콘크리트의 벽체부를 시공하는 제4단계를 포함하는 것을 특징으로 한다.The construction method of the slope reinforcement structure using the bearing and tension force according to the present invention comprises: a first step of inserting and installing a plurality of supporting piles in the soil layer of the slope and installing the sacrificial piles in front of the supporting piles; a second step of securing a space in the soil layer between the support pile and the retaining facility, mounting a tension member, and then connecting both sides in the longitudinal direction to the support pile and the sacrificial pile of the retaining facility, respectively; a third step of excavating the front part of the sacrificial pile and installing a wale and earth plate to construct a retaining facility, and constructing a drainage channel and a manual earth pressure part on the soil layer between the support pile and the sacrificial pile; It is characterized in that it includes a fourth step of constructing a wall part of concrete in front of the retaining facility installed in the third step.

본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물 및 이의 시공 방법에 의하면, 사면의 토사층에 지지말뚝을 선 설치하고 지지말뚝의 앞에 흙막이 시설을 설치하면서 흙막이 시설에 의해 보호를 받는 상태에서 흙을 제거하는 것으로 시공이 이루어지므로 대형 장비없이 절토 작업이 가능하거나 대형 장비를 사용하여도 사용 시간이 짧아 시공비용을 대폭으로 절감하고 공기도 단축하는 효과가 있고, 지지말뚝을 통해 흙막이 시설을 지지하여 벽체부의 완성까지 흙막이 시설의 붕괴를 막고 작업자를 안전하게 보호하는 효과가 있다.According to the slope reinforcement structure using the bearing and tension force according to the present invention and the construction method thereof, the soil is removed in a state protected by the retaining facility while installing the support piles on the soil layer of the slope and installing the retaining facilities in front of the support piles. Because the construction is done by doing this, cutting work is possible without large equipment, or the use time is short even with large equipment, which greatly reduces construction costs and shortens the construction period. It has the effect of preventing the collapse of the retaining facility until completion and protecting the workers safely.

그리고, 긴장재를 통해 지지말뚝들을 일체로 합성하여 큰 지지력을 확보하게 되므로 장기간동안 사면 보강 구조물에 의한 사면의 안정화가 가능하고 사면의 붕괴를 막는 효과가 있다.In addition, since the support piles are integrally synthesized through the tension member to secure a large bearing capacity, the slope can be stabilized by the slope reinforcement structure for a long period of time, and there is an effect of preventing the collapse of the slope.

그리고, 지지말뚝을 지면에 대해 수직으로 설치하여 종래 앵커홀을 경사지게 설치하는 것보다 사면을 안정화할 수 있다.And, by installing the support piles perpendicular to the ground, it is possible to stabilize the slope rather than installing the conventional anchor hole inclined.

또한, 지지말뚝의 시공을 위한 부분만을 절토하고 이 절토 작업은 종래 절토 작업에 비해 적은 비용과 짧은 시간으로 가능하므로 시공성이 매우 우수하다.In addition, since only the part for the construction of the support pile is cut, and this cutting operation is possible at a low cost and a shorter time compared to the conventional cutting operation, the workability is very excellent.

도 1은 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물의 시공 상태 측면도.
도 2는 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물의 시공 상태 평면도로서, 긴장재를 보이기 위한 위치의 평면도.
도 3은 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물에 적용된 희생 말뚝과 띠장의 연결을 보인 평면도.
도 4는 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물에 적용된 희생 말뚝과 띠장의 연결을 보인 사시도.
도 5는 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물에 적용된 희생 말뚝과 띠장의 연결을 보인 측면도.
도 6은 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물에 적용된 희생 말뚝과 토류판의 설치 상태를 보인 평면도.
도 7은 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물에 적용된 희생 말뚝과 띠장 및 토류판을 보이기 위한 배면 사시도.
도 8은 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물에 적용된 긴장재가 지지말뚝에 고정되는 부분의 사시도.
도 9는 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물에 적용된 슬롯을 보이기 위한 측면도.
도 11 내지 도 15는 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물의 시공 공정도.
1 is a side view of the construction state of the slope reinforcement structure using the bearing force and tension force according to the present invention.
Figure 2 is a plan view of the construction state of the slope reinforcement structure using the bearing force and tension force according to the present invention, a plan view of the position for showing the tension material.
Figure 3 is a plan view showing the connection of the sacrificial pile and wale applied to the slope reinforcement structure using the bearing and tension according to the present invention.
Figure 4 is a perspective view showing the connection of the sacrificial pile and wale applied to the slope reinforcement structure using the bearing and tension force according to the present invention.
Figure 5 is a side view showing the connection of the sacrificial pile and the bandage applied to the slope reinforcement structure using the bearing and tension force according to the present invention.
Figure 6 is a plan view showing the installation state of the sacrificial pile and earth plate applied to the slope reinforcement structure using the bearing and tension force according to the present invention.
Figure 7 is a rear perspective view for showing the sacrificial pile, wale and earth plate applied to the slope reinforcement structure using the bearing and tension force according to the present invention.
8 is a perspective view of a portion in which the tension material applied to the slope reinforcement structure using the bearing force and tension force according to the present invention is fixed to the support pile.
Figure 9 is a side view for showing a slot applied to the slope reinforcement structure using the bearing force and tension according to the present invention.
11 to 15 are construction process diagrams of the slope reinforcement structure using the bearing force and tension force according to the present invention.

하기에서 본 발명을 설명함에 있어, 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략할 것이다. 그리고 후술되는 용어들은 본 발명에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있다. 그러므로 그 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.In the following description of the present invention, if it is determined that a detailed description of a related well-known function or configuration may unnecessarily obscure the gist of the present invention, the detailed description thereof will be omitted. In addition, the terms described below are terms defined in consideration of functions in the present invention, which may vary according to intentions or customs of users and operators. Therefore, the definition should be made based on the content throughout this specification.

도 1과 도 2에서 보이는 바와 같이, 본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물은, 콘크리트의 벽체부(11)와 흙막이 시설{강재의 희생말뚝(12)와 띠장(13)과 토류판(15)의 조합}이 합성된 합성 벽체(10), 합성 벽체(10)의 뒤쪽에 설치되는 지지말뚝(20), 지지말뚝(20)을 지지기반으로 하여 합성 벽체(10)를 지지하는 긴장재(30)를 포함하고, 긴장재(30)는 평면에서 볼 때 지그재그 형태로 설치되면서 연쇄적으로 연결되고 또한 측면에서 볼 때 지지말뚝(20)을 향해 상향 경사지게 설치되며, 사면 보강 구조물의 설명에서는 시공 후 상태를 기준으로 하여 본 발명의 구성 및 구성들의 유기적 결합관계에 대해서만 설명하고 그 후에 시공 방법을 구체적으로 설명한다.As shown in Figures 1 and 2, the slope reinforcement structure using the bearing and tension force according to the present invention is a concrete wall portion 11 and retaining facility {steel sacrificial pile 12 and wale 13 and earth plate ( Combination of 15)} is synthesized composite wall 10, support piles 20 installed at the back of the composite wall 10, and tension materials for supporting the composite wall 10 based on the support piles 20 ( 30), and the tension member 30 is connected in a chain while being installed in a zigzag form when viewed from the top, and is installed inclined upward toward the support pile 20 when viewed from the side, and in the description of the slope reinforcement structure, after construction Based on the state, only the configuration of the present invention and the organic coupling relationship of the configurations will be described, and then the construction method will be specifically described.

합성 벽체(10)는 콘크리트의 벽체부(11)와 강재의 희생 말뚝(12)이 합성된 구조체이며, 콘크리트의 벽체부(11)는 콘크리트의 특성을 이용하여 사면으로부터 전가되는 토압에 대한 버팀강성을 발휘하고, 희생 말뚝(12)은 예를 들어 H 빔의 기성품으로 벽체부(11)와 일체로 합성되면서 저부가 지중에 삽입 정착되어 지지력을 확보한다.The composite wall 10 is a structure in which a wall part 11 of concrete and a sacrificial pile 12 of steel are synthesized, and the wall part 11 of concrete uses the characteristics of concrete to withstand the earth pressure transmitted from the slope. and the sacrificial pile 12 is, for example, a ready-made product of the H-beam, and the bottom part is inserted and fixed in the ground while being integrally synthesized with the wall part 11 to secure the bearing capacity.

콘크리트의 벽체부(11)는 철근 콘크리트 구조물로서 상부에서 하부로 가면서 동일 내지 점진적으로 두꺼워지는 단면이고 저부에 더 넓은 단면의 저판부(11a)(말굽부)를 포함하는 구조이고 바람직하게 현장 타설로 시공되지만 동일한 구조의 프리캐스트 콘크리트 제품도 사용될 수 있다.The wall portion 11 of the concrete is a reinforced concrete structure with a cross-section that is the same to gradually thickening from the top to the bottom, and a structure including a bottom plate portion 11a (horseshoe portion) of a wider cross-section at the bottom, and is preferably cast in-situ. Precast concrete products of the same construction but constructed may also be used.

희생 말뚝(12)은 합성 벽체(10)의 지지력 확보를 위한 것으로 흙막이부(12-1) 및 지중에 벽체부(11)보다 더 깊은 지중에 삽입 정착되는 정착부(12-2)로 구분할 수 있다.The sacrificial pile 12 is for securing the bearing capacity of the composite wall 10 and can be divided into a retaining part 12-1 and a fixing part 12-2 that is inserted and fixed in the ground deeper than the wall part 11 in the ground. have.

희생 말뚝(12)은 벽체부(11)가 현장 타설형인 경우 합성력을 증대하기 위하여 다수개의 스터드가 포함될 수 있다.The sacrificial pile 12 may include a plurality of studs in order to increase the composite force when the wall portion 11 is cast-in-place.

이와 같은 구성의 희생 말뚝(12)은 사면 보강 구조물의 크기에 맞춰 상호 간에 일정 간격을 두고 이격되는 다수개가 사용되고, 이 때, 도 1과 도 3에서 보이는 것처럼, 이웃하는 희생 말뚝(12)은 띠장(13)으로 연결된다.A plurality of sacrificial piles 12 having such a configuration are used that are spaced apart from each other at regular intervals according to the size of the slope reinforcement structure, and at this time, as shown in FIGS. 1 and 3, the neighboring sacrificial piles 12 are wale (13) is connected.

띠장(13)은 도면에 예를 들어 H빔으로 도시하였을 뿐 길이방향의 양측 단부가 이웃하는 희생 말뚝(12)에 고정되어 견고하게 연결할 수 있는 모든 자재가 가능하다. 또한, 띠장(13)의 고정 방법으로 예컨대 도 4와 도 5에 도시된 것처럼, 희생 말뚝(12)에 띠장쐐기(14)를 고정(용접 등)하고 띠장쐐기(14)에 띠장(13)을 고정(볼팅 등)하는 방법이 가능하다.The wale 13 is, for example, only shown as an H-beam in the drawing, and both ends in the longitudinal direction are fixed to the adjacent sacrificial piles 12 and all materials that can be firmly connected are possible. In addition, as a fixing method of the wale 13, for example, as shown in FIGS. 4 and 5, the wale wedge 14 is fixed to the sacrificial pile 12 (welding, etc.), and the wale 13 is attached to the wale wedge 14. A method of fixing (bolting, etc.) is possible.

띠장(13)은 희생 말뚝(12)의 안에 삽입 즉 희생 말뚝(12)의 앞쪽으로 돌출되지 않아 벽체부(11)의 콘크리트 타설 공간을 침범하지 않으므로 돌출로 인한 벽체부(11)의 두께 증가를 막을 수 있다.The wale 13 is inserted into the sacrificial pile 12, that is, it does not protrude in front of the sacrificial pile 12 and does not invade the concrete pouring space of the wall part 11, so the increase in the thickness of the wall part 11 due to the protrusion can be stopped

띠장(13)은 사면 보강 구조물의 높이에 따라 1단 또는 2단 이상으로 설치되고 도면은 2단을 예로 들어 도시하였다.The wale 13 is installed in one stage or two or more stages depending on the height of the slope reinforcement structure, and the drawing shows two stages as an example.

띠장(13)도 희생 말뚝(12)과 동일한 목적으로 스터드를 포함할 수 있다.The wale 13 may also include studs for the same purpose as the sacrificial stake 12 .

띠장(13)을 통해 다수의 희생 말뚝(12)이 연결됨으로써 이 때 희생 말뚝(12)은 저부가 지중에 정착되어 있기 때문에 견고한 자립이 가능하다.By connecting a plurality of sacrificial stakes 12 through the wale 13, at this time, the sacrificial stakes 12 are firmly self-supporting because the bottom is fixed in the ground.

띠장쐐기(14)는 희생 말뚝 고정부(14-1)과 띠장 고정부(14-2)를 포함하는 구조이다. 희생 말뚝 고정부(14-1)는 H 빔 형태의 희생 말뚝(12) 안에 삽입되어 마주하는 2개의 플랜지에 각각 고정되는 2개의 수직형태이고 띠장 고정부(14-2)는 희생 말뚝 고정부(14-1)들을 연결하면서 띠장(13)의 웨브에 겹쳐져 고정되는 형태이다.The wale wedge 14 is a structure including a sacrificial pile fixing part 14-1 and a wale pole fixing part 14-2. The sacrificial pile fixing part 14-1 is inserted into the H-beam-shaped sacrificial pile 12 and is respectively fixed to two flanges facing each other, and the wale fixing part 14-2 is a sacrificial pile fixing part ( 14-1), it is superimposed on the web of the wale 13 and fixed while connecting them.

벽체부(11)의 현장 타설을 위하여 희생 말뚝(12)들의 사이에는 토류판(거푸집)(15)(도 1, 도 6, 도 7에 도시됨)을 설치할 수 있다. 토류판(15)은 뒤쪽에서 흙이 넘어오는 것을 막고 거푸집의 기능도 하도록 양쪽이 희생 말뚝(12)에 삽입되면서 고정구(15a)를 통해 고정된다.An earth plate (form) 15 (shown in FIGS. 1, 6 and 7) may be installed between the sacrificial piles 12 for on-site casting of the wall part 11 . The earth plate 15 is fixed through the fixture 15a while both sides are inserted into the sacrificial pile 12 so as to prevent the soil from coming over from the back and also function as a formwork.

지지말뚝(20)은 시공 상태를 기준으로 할 때 희생 말뚝(12)의 뒤쪽에 일정 거리를 두고 다수개가 일정 간격{바람직하게 희생 말뚝(12)들의 간격과 동일}으로 설치되고, 긴장재(30)가 경사지게 설치될 수 있도록 희생 말뚝(12)들 사이의 중앙을 설치 위치로 하며, 즉, 희생 말뚝(12)과 지지말뚝(20)은 지그재그 형태로 배열된다.A plurality of support piles 20 are installed at a predetermined distance (preferably the same as the spacing of the sacrificial piles 12) at a certain distance behind the sacrificial pile 12 based on the construction state, and the tension member 30 The center between the sacrificial piles 12 is the installation location so that the sacrificial piles 12 can be installed inclinedly, that is, the sacrificial piles 12 and the supporting piles 20 are arranged in a zigzag form.

지지말뚝(20)은 예를 들어 저부가 절토부의 지중에 삽입 정착된다.Support pile 20 is, for example, the bottom is inserted and fixed in the ground of the cut part.

긴장재(30)는 지지말뚝(20)을 지지기반으로 하여 합성 벽체(10)를 지지하며, 평철, 앵글, 케이블, 빔 등의 다양한 자재의 사용이 가능하면서 전후 양쪽이 각각 희생 말뚝(12)과 지지말뚝(20)에 고정된다.The tension member 30 supports the composite wall 10 based on the support pile 20 as a support base, and while various materials such as flat iron, angle, cable, and beam can be used, both sides of the sacrificial pile 12 and It is fixed to the support pile (20).

긴장재(30)는 지그재그 형태로 배열되는 희생 말뚝(12)과 지지말뚝(20)의 연결을 위하여 경사지게 설치되어야 하며 이를 위하여 경사 쐐기(31,32)가 사용된다.The tension member 30 should be installed inclinedly for the connection of the sacrificial pile 12 and the support pile 20 arranged in a zigzag shape, and for this, inclined wedges 31 and 32 are used.

경사 쐐기(31,32)는 희생 말뚝(12)쪽과 지지말뚝(20)쪽에 설치되지만 구성은 동일한 하나의 제품이며, 각각 일정 각도의 경사면(31a,32a)을 포함하여야 한다.Inclined wedges 31 and 32 are installed on the side of the sacrificial pile 12 and the support pile 20, but the configuration is the same as one product, and should include inclined surfaces 31a and 32a of a certain angle, respectively.

경사 쐐기(31,32)는 내부에 공간이 있으면서 일면에 경사면(31,32a)이 형성되는 박스(상하 개방 가능) 형태로서, 경사면(31a,32a)은 희생 말뚝(12)과 지지말뚝(20)의 바깥으로 돌출되어야 하며, 희생 말뚝(12)과 지지말뚝(20)에 각각 용접 등으로 고정되고, 경사면(31a,32a)에 긴장재(30)가 볼트와 너트 등으로 고정된다.Inclined wedges 31 and 32 are in the form of a box (top and bottom openable) in which inclined surfaces 31 and 32a are formed on one side while having a space therein, and inclined surfaces 31a and 32a are sacrificial piles 12 and support piles 20 ) and is fixed to the sacrificial pile 12 and the support pile 20 by welding, etc., respectively, and the tension member 30 is fixed to the inclined surfaces 31a and 32a with bolts and nuts.

도 1과 도 8에서 보이는 것처럼, 사면을 절토할 경우 배면에 물이 흡수 되어 토압이 증가하고 더욱 위험해 질 수 있어 서둘러 배수로를 설치하고 상면 마감이 필요하며, 지지말뚝(20) 전면에 배수로를 설치 할 경우 수동토압을 받아 전도방지에 효과적이다.As shown in Figures 1 and 8, when the slope is cut, water is absorbed on the back surface, increasing the earth pressure and making it more dangerous. When installed, it is effective to prevent overturning by receiving manual earth pressure.

또한, 배수로 설치와 경사면에 지지말뚝(20)을 설치할 경우 희생말뚝과 높이 차이가 있을 수 있어 긴장재(30)는 지지말뚝(20)으로 가면서 상향(또는 하향) 경사지게 설치될 수 있으며, 이 때의 경사 쐐기(31,32) 중 하나 이상은 긴장재(30)가 체결되는 경사 쐐기(31,32)의 체결공은 긴장재의 단부쪽은 원형으로 제작되고 내측 체결공은 각도 조절이 용이하게 체결장공(슬롯)으로 하며, 도 9는 지지말뚝(20)에 설치되는 경사 쐐기(32)에 체결장공(32b)이 형성된 것을 예로 들어 도시하였다. 긴장재(30)는 체결장공을 통해 각도를 조절할 수 있다. In addition, when installing the drainage channel and installing the support pile 20 on the inclined surface, there may be a difference in height from the sacrificial pile, so the tension member 30 may be installed to be inclined upward (or downward) while going to the support pile 20, at this time At least one of the inclined wedges (31, 32) is a fastening hole of the inclined wedge (31, 32) to which the tension material 30 is fastened, the end side of the tension material is made in a circular shape, and the inner fastening hole is a fastening hole ( slot), and FIG. 9 shows, for example, that the fastening hole 32b is formed in the inclined wedge 32 installed on the support pile 20 . The tension member 30 can adjust the angle through the fastening hole.

합성 벽체(10)와 지지말뚝(20) 사이의 토사층(40) 위에는 배수로(41)가 시공되고 배수로(41)의 높이에서부터 합성 벽체(10)로 가면서 하향 경사지는 전방 복구부(42) 및 배수로(41)의 뒤에서 절토사면까지 상향 경사지게 시공되는 후방 복구부(43)를 포함할 수 있다.A drainage passage 41 is constructed on the soil layer 40 between the composite wall 10 and the support pile 20, and the front restoration portion 42 and the drainage passage that slope downward from the height of the drainage passage 41 to the composite wall 10. It may include a rear recovery part 43 that is constructed to be inclined upward from the back of the 41 to the cut slope.

배수로(41)는 지지말뚝(20)의 두부를 지지기반으로 하며 지지말뚝(20)과 추가적인 고정(볼트와 너트, 앵커, 용접 등)되는 것도 가능하다.The drainage channel 41 is based on the support base of the head of the support pile 20 and it is also possible to be additionally fixed (bolts and nuts, anchors, welding, etc.) with the support piles 20 .

전방 복구부(42)와 후방 복구부(43)는 동일한 복구재료이며 토사 등이 사용된다.The front restoration part 42 and the rear restoration part 43 are the same restoration material, and earth and sand etc. are used.

배수로(41)의 앞에는 콘크리트에 의한 수동 토압부(44)가 시공될 수 있다. 수동 토압부(44)는 배수로(41)가 전방으로 밀리는 것을 막아주는 것으로 하부로 가면서 단면적이 넓어지는 형태가 바람직하다.A manual earth pressure part 44 made of concrete may be constructed in front of the drainage channel 41 . The passive earth pressure part 44 prevents the drainage passage 41 from being pushed forward, and it is preferable that the cross-sectional area increases as it goes downward.

도 10은 합성 벽체(10)의 변형 예를 도시한 것이며, 벽체부(11)의 저판부(11 a)에서 강성을 증대하기 위하여 저판 합성부(12a)가 포함된다. 10 shows a modified example of the composite wall 10, the bottom plate composite portion 12a is included in order to increase the rigidity in the bottom plate portion 11a of the wall portion 11.

저판 합성부(12a)는 희생 말뚝(12)과 동일한 자재(강재)로 저판부(11a)의 위치에 맞춰 캔틸레버 형태로 고정되어 벽체부(11)의 저판부(11a) 안에 매설됨으로써 벽체부(11)의 저판부(11a)가 연결되는 부분에서 균열과 파단을 막아준다.The bottom plate composite part 12a is fixed in the form of a cantilever according to the position of the bottom plate part 11a with the same material (steel material) as the sacrificial pile 12, and is embedded in the bottom plate part 11a of the wall part 11, so that the wall part ( 11) to prevent cracks and breakage in the portion where the bottom plate portion 11a is connected.

또한, 희생 말뚝(12)과 저판 합성부(12a)가 연결되는 우각부에 보강재(12b)가 포함될 수 있다. 보강재(12b)는 거셋판형, 채널형, 스트럿형 등이 가능하다.In addition, the reinforcing material 12b may be included in the right leg portion where the sacrificial pile 12 and the bottom plate composite portion 12a are connected. The reinforcing material 12b may be a gusset plate type, a channel type, a strut type, or the like.

본 발명에 의한 지지력과 긴장력을 이용한 사면 보강 구조물의 시공 방법은 크게 지지말뚝 설치 - 흙막이 시설 설치 - 긴장재 설치 - 벽체부 시공의 공정으로 이루어지고 바람직한 실시 예는 다음과 같다.The construction method of the slope reinforcement structure using the bearing capacity and tension force according to the present invention is largely composed of the following steps: support pile installation - retaining facility installation - tension material installation - wall part construction.

1. 절토 사면 정리(도 12 참고).1. Cut slope clearance (see Figure 12).

지지말뚝(20)의 설치를 위하여 사면의 일부를 절토하고 절토 사면을 정리하며, 이 때, 평평한 바닥의 작업레벨(1)은 대략 합성벽체(10)의 상단 높이이다. 즉, 합성벽체(10)의 높이에 맞춰 절토 사면을 정리한다.A part of the slope is cut for the installation of the support pile 20 and the cut slope is arranged, and at this time, the work level 1 of the flat floor is approximately the height of the upper end of the composite wall 10 . That is, the cut slope is arranged according to the height of the composite wall 10 .

2. 지지말뚝과 희생말뚝 설치(도 13 참고).2. Installation of supporting piles and sacrificial piles (refer to FIG. 13).

작업레벨(1)에서부터 사면 안쪽을 향해 대략 수직으로 지지말뚝(20)을 설치한다. 예를 들어 지지말뚝(20)을 항타로 설치하거나 사면에 말뚝공을 형성하여 지지말뚝(20)을 삽입 설치한 후 채움재의 채움으로 설치한다.Install the support piles (20) approximately vertically from the working level (1) toward the inside of the slope. For example, the support piles 20 are installed by driving, or pile holes are formed on the slopes to insert and install the support piles 20, and then install them by filling the filler material.

설치 방법에 상관없이 지지말뚝(20)의 두부는 작업레벨(1)보다 위쪽으로 돌출되며, 돌출된 부분은 배수로(41)를 지지하기 위한 높이이다.Regardless of the installation method, the head of the support pile 20 protrudes above the work level 1 , and the protruding portion is a height for supporting the drainage channel 41 .

그리고, 지지말뚝(20)의 앞쪽에 희생말뚝(12)을 설치한다. 희생말뚝(12)의 설치 방법도 지지말뚝(20)의 설치방법과 동일하며, 단 희생말뚝(12)은 두부가 작업레벨(1)보다 더 높게 돌출되지 않고 동일할 수 있다.Then, the sacrificial pile 12 is installed in front of the support pile 20 . The installation method of the sacrificial pile 12 is also the same as the installation method of the support pile 20 , but the sacrificial pile 12 may be the same without the head protruding higher than the work level (1).

희생말뚝(12)은 정착부(12-2)가 후속 공정에서 시공될 벽체부(11)의 저판부(11a) 보다 더 깊은 심도로 설치될 수 있도록 하는 레벨이다.The sacrificial pile 12 is a level so that the fixing part 12-2 can be installed at a deeper depth than the bottom plate part 11a of the wall part 11 to be constructed in a subsequent process.

3. 긴장재 설치(도 14 참고).3. Install the tension member (see Fig. 14).

희생말뚝(12)과 지지말뚝(20)에 경사 쐐기(31,32)를 각각 설치하고 긴장재(30)를 희생말뚝(12)의 뒤쪽 공간에 경사지게 배치하면서 전후 양측(도면 기준 좌우)을 경사 쐐기(31,32)에 각각 고정한다. 긴장재(30)를 설치한 후 흙을 되메우기 하여 긴장재(30)를 매설한다. 즉, 작업레벨(1)로 다시 복구를 한다.Inclined wedges 31 and 32 are installed on the sacrificial pile 12 and the support pile 20, respectively, and the tension member 30 is inclinedly disposed in the space behind the sacrificial pile 12, and the front and rear sides (left and right in the drawing) are inclined wedges. (31 and 32) are fixed respectively. After the tension material 30 is installed, the soil is backfilled to bury the tension material 30 . That is, it is restored to work level (1) again.

4. 흙막이 시설 완료(도 15 참고).4. Completion of retaining facilities (see Fig. 15).

희생말뚝(12)의 앞에 공간을 확보하기 위하여 터파기와 흙막이 시설의 시공을 완료하며, 희생말뚝(12)들을 띠장(13)으로 연결하고 희생말뚝(12)들 사이에 토류판(15)을 설치하는 작업과 터파기의 단계적 병행을 통해 흙막이 시설의 시공을 완료한다.In order to secure a space in front of the sacrificial piles 12, the construction of the excavation and retaining facilities is completed, the sacrificial piles 12 are connected with a wale 13, and the earth plate 15 is installed between the sacrificial piles 12. The construction of the earth retaining facility is completed through the phased parallel of work and excavation.

이어서, 토사층(40) 위에 배수로(41)를 시공한다.Next, a drainage channel 41 is constructed on the soil layer 40 .

배수로(41)는 프리캐스트 콘크리트 제품을 이용한 방식과 현장 타설을 이용한 방식 모두가 가능하고 각각의 방식에 맞춰 시공한다. 이 때, 배수로(41)를 지지말뚝(20)의 두부와 고정하는 것을 포함할 수 있으며 고정방법은 상기 방식에 따라 다양하게 실시 가능하다.The drainage channel 41 can be both a method using a precast concrete product and a method using an on-site casting, and is constructed according to each method. At this time, it may include fixing the drainage channel 41 to the head of the support pile 20, and the fixing method can be variously implemented according to the above method.

배수로(41)의 전면부에 거푸집을 설치하고 콘크리트를 타설하여 수동 토압부(44)를 시공하고 배면부를 복토한다.A formwork is installed in the front part of the drainage passage 41, concrete is poured, the manual earth pressure part 44 is constructed, and the rear part is covered.

6. 벽체부 시공(도 1 참고)6. Wall construction (refer to Fig. 1)

희생말뚝(12)을 포함하는 흙막이 시설 앞에 벽체부(11)를 시공하며, 현장 타설의 경우 희생말뚝(12)과 토류판(15)의 앞에 타설 공간을 두고 거푸집을 설치 및 철근을 배근하고 상기 타설 공간에 콘크리트를 타설하여 벽체부(11)를 시공한다. The wall part 11 is constructed in front of the retaining facility including the sacrificial pile 12, and in the case of on-site casting, a casting space is placed in front of the sacrificial pile 12 and the earth plate 15, the formwork is installed and the reinforcing bar is reinforced, and the casting is performed. Concrete is poured into the space to construct the wall part 11 .

벽체부(11)의 시공을 완료한 후 바닥부에 흙을 메우고 정리하여 마감한다.After completing the construction of the wall part 11, the bottom part is filled with soil, arranged and finished.

10 : 합성 벽체, 11 : 벽체부
12 : 희생 말뚝, 12-1 : 흙막이부
12-2 : 정착부,
13 : 띠장
14 : 띠장쐐기, 15 : 토류판
20 : 지지말뚝, 30 : 긴장재
31,32 : 경사 쐐기, 40 : 토사층
41 : 배수로, 42 : 전방 복구부
43 : 후방 복구부, 44 : 수동 토압부
10: composite wall, 11: wall part
12: sacrifice stake, 12-1: retaining part
12-2: fixing unit,
13 : belt
14: belt wedge, 15: earth plate
20: support pile, 30: tension material
31,32: inclined wedge, 40: soil layer
41: drainage, 42: front recovery part
43: rear recovery part, 44: manual earth pressure part

Claims (7)

상호 간에 일정 간격을 두고 사면의 지중에 삽입 설치되어 사면의 토사층에 의한 수동 토압을 받아 지지되는 다수의 지지말뚝과;
콘크리트의 벽체부와 흙막이 시설의 조합으로 이루어지며 상기 지지말뚝의 앞쪽에 일정 거리를 두고 시공되는 합성 벽체와;
상기 지지말뚝과 합성 벽체에 고정되어 상기 지지말뚝을 지지기반으로 하여 상기 합성 벽체를 지지하는 긴장재와;
상기 지지말뚝과 상기 합성 벽체 사이의 토사층 표면에 시공되는 배수로 및 상기 배수로의 전면부에 시공되는 수동 토압부를 포함하며,
상기 합성 벽체는 상기 흙막이 시설이 상호 간에 일정 거리를 두고 지중에 삽입되는 다수의 희생말뚝, 상기 희생말뚝들의 사이에 횡방향으로 배열되면서 연결되는 띠장, 상기 희생말뚝들의 사이에 설치되는 토류판을 포함하고, 상기 벽체부는 상기 희생말뚝과 합성 시공되며,
상기 지지말뚝은 상기 희생말뚝과 지그재그 형태로 설치되고, 상기 긴장재는 상기 합성 벽체와 지지말뚝의 지그재그 형태에 맞춰 경사지게 설치되어 상기 지지말뚝과 합성 벽체를 연쇄적으로 연결하고,
상기 배수로는 상기 토사층 표면보다 상부로 돌출되는 지지말뚝의 두부와 상기 수동 토압부에 의해 지지되면서 상기 합성 벽체로 가면서 하향 경사지는 전방 복구부 및 뒤쪽의 절토사면까지 상향 경사지게 시공되는 후방 복구부에 의해 지지되는 것을 특징으로 하는 영구적 흙막이 시설을 이용한 사면 보강 구조물.
a plurality of support piles inserted into the ground of the slope at a predetermined distance from each other and supported by passive earth pressure by the soil layer of the slope;
a composite wall made of a combination of a concrete wall part and a retaining facility and constructed at a predetermined distance in front of the support pile;
a tension member fixed to the support pile and the composite wall to support the composite wall based on the support pile;
A drainage channel constructed on the surface of the soil layer between the support pile and the composite wall and a passive earth pressure part constructed on the front part of the drain passage,
The composite wall includes a plurality of sacrificial piles in which the retaining facilities are inserted into the ground at a certain distance from each other, a wale connected in a transverse direction between the sacrificial piles, and a earth plate installed between the sacrificial piles and , The wall part is synthetically constructed with the sacrificial pile,
The support pile is installed in a zigzag form with the sacrificial pile, and the tension member is installed to be inclined according to the zigzag shape of the composite wall and the support pile to connect the support pile and the composite wall in a chain,
The drainage path is supported by the head of the support pile protruding above the surface of the soil layer and the passive earth pressure part, and a front recovery part that slopes downward as it goes to the composite wall and a rear recovery part that is constructed to be inclined upward to the cut slope at the back. A slope reinforcement structure using a permanent retaining facility, characterized in that it is supported.
삭제delete 삭제delete 청구항 1에 있어서, 상기 띠장은 상기 희생말뚝의 앞쪽으로 돌출되지 않도록 상기 희생말뚝에 연결되어 상기 벽체부는 그 두께가 상기 희생말뚝을 기준으로 하는 것을 특징으로 하는 영구적 흙막이 시설을 이용한 사면 보강 구조물.The slope reinforcement structure using a permanent retaining facility according to claim 1, wherein the wale is connected to the sacrificial pile so as not to protrude in front of the sacrificial pile, and the wall portion has a thickness based on the sacrificial pile. 청구항 1에 있어서, 상기 희생말뚝과 지지말뚝에 각각 고정되며 경사면을 포함하는 경사 쐐기를 포함하고, 상기 긴장재는 길이방향의 양쪽이 상기 경사 쐐기의 경사면에 각각 지지되면서 고정되는 것을 특징으로 하는 영구적 흙막이 시설을 이용한 사면 보강 구조물.The permanent retainer according to claim 1, wherein each of the sacrificial piles and the supporting piles includes an inclined wedge including an inclined surface, and the tension member is fixed while both sides of the longitudinal direction are respectively supported on the inclined surface of the inclined wedge. Slope reinforcement structures using facilities. 청구항 1에 의한 영구적 흙막이 시설을 이용한 사면 보강 구조물의 시공 방법으로서,
사면의 토사층에 다수의 지지말뚝을 삽입 설치하고 상기 지지말뚝의 앞에 희생말뚝을 설치하는 제1단계와;
상기 지지말뚝과 상기 희생말뚝 사이의 토사층에 공간을 확보하고 긴장재를 거치한 후 길이방향의 양쪽을 상기 지지말뚝과 흙막이 시설의 희생말뚝에 각각 연결하여 설치하는 제2단계와;
상기 희생말뚝의 전면부를 터파기하고 띠장과 토류판을 설치하여 흙막이 시설을 시공하며, 상기 지지말뚝과 희생말뚝 사이의 토사층 위에 배수로와 수동 토압부를 시공하고 전방 복구부와 후방 복구부를 시공하는 제3단계와;
제3단계에서 설치한 흙막이 시설의 앞에 콘크리트의 벽체부를 시공하는 제4단계를 포함하는 것을 특징으로 하는 영구적 흙막이 시설을 이용한 사면 보강 구조물의 시공 방법.
As a construction method of a slope reinforcement structure using the permanent retaining facility according to claim 1,
A first step of inserting a plurality of support piles in the soil layer of the slope and installing the sacrificial piles in front of the support piles;
a second step of securing a space in the soil layer between the support pile and the sacrificial pile and installing a tension member by connecting both sides of the longitudinal direction to the support pile and the sacrificial pile of the retaining facility, respectively;
The third step of excavating the front part of the sacrificial pile and installing a wale and earth plate to construct a retaining facility, constructing a drainage channel and a manual earth pressure part on the soil layer between the support pile and the sacrificial pile, and constructing a front restoration part and a rear restoration part Wow;
A construction method of a slope reinforcement structure using a permanent retaining facility, comprising a fourth step of constructing a wall part of concrete in front of the retaining facility installed in the third step.
청구항 6에 있어서, 상기 제4단계는 상기 흙막이 시설의 앞에 철근을 배근하고 거푸집을 설치함으로써 상기 토류판을 거푸집으로 하여 타설 공간을 형성하고 상기 타설 공간에 콘크리트를 타설하여 벽체부를 시공하는 것을 특징으로 하는 영구적 흙막이 시설을 이용한 사면 보강 구조물의 시공 방법.
The method according to claim 6, wherein the fourth step is to form a pouring space using the earth plate as a formwork by reinforcing reinforcing bars in front of the retaining facility and installing a formwork, and pouring concrete into the pouring space to construct a wall part. Construction method of slope reinforcement structure using permanent retaining system.
KR1020210017890A 2021-02-08 2021-02-08 Slope reinforcement structure using support and tension and Its Construction method Active KR102272494B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210017890A KR102272494B1 (en) 2021-02-08 2021-02-08 Slope reinforcement structure using support and tension and Its Construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210017890A KR102272494B1 (en) 2021-02-08 2021-02-08 Slope reinforcement structure using support and tension and Its Construction method

Publications (1)

Publication Number Publication Date
KR102272494B1 true KR102272494B1 (en) 2021-07-02

Family

ID=76896906

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210017890A Active KR102272494B1 (en) 2021-02-08 2021-02-08 Slope reinforcement structure using support and tension and Its Construction method

Country Status (1)

Country Link
KR (1) KR102272494B1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120048134A (en) * 2010-11-05 2012-05-15 한국도로공사 Retaining wall using corrugated steel plate and construction method thereof
KR20130062055A (en) * 2011-12-02 2013-06-12 이득근 Device for enhanced soil slope and how to install the device
KR101465149B1 (en) 2012-12-17 2014-11-25 한국철도기술연구원 Anchored retaining wall of gravity block type, and constructing method for the same
KR101949728B1 (en) * 2018-07-10 2019-02-19 강숙인 Retaining Wall having Truss Structure, and Constructing Method thereof
KR20190083466A (en) * 2018-01-04 2019-07-12 롯데건설 주식회사 Retaining wall and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20120048134A (en) * 2010-11-05 2012-05-15 한국도로공사 Retaining wall using corrugated steel plate and construction method thereof
KR20130062055A (en) * 2011-12-02 2013-06-12 이득근 Device for enhanced soil slope and how to install the device
KR101465149B1 (en) 2012-12-17 2014-11-25 한국철도기술연구원 Anchored retaining wall of gravity block type, and constructing method for the same
KR20190083466A (en) * 2018-01-04 2019-07-12 롯데건설 주식회사 Retaining wall and construction method thereof
KR101949728B1 (en) * 2018-07-10 2019-02-19 강숙인 Retaining Wall having Truss Structure, and Constructing Method thereof

Similar Documents

Publication Publication Date Title
KR101302743B1 (en) Phc pile and its using the same soil cement wall construction methode
KR101274974B1 (en) Earth retaining wall and construction method thereof
KR100866162B1 (en) Construction method of chair-type freestanding wall
WO2020021294A1 (en) Retaining engineering structure and design method for stabilizing deep excavations or earth slope instability near existing civil objects
EA037484B1 (en) Retaining wall method of precast block to prevent landslide
KR20200124949A (en) Anchor Tension way sheathing structure and sheathing method of construction
KR100831332B1 (en) Underground wall for civil engineering and construction method
US5356242A (en) System and method for adjustably connecting wall facing panels to the soldier beams of a tie-back or anchored wall
KR101206860B1 (en) Excavation tunnel constructing method using vertical side wall and arch ceiling
KR100562158B1 (en) Steel pipe loop method for constructing underground structure and its loop structure, and structure of steel pipe
JP2020070705A (en) Method for constructing lightweight fill retaining wall structure
US9951493B2 (en) Precast integral post and retaining wall and method for installing same
KR102272494B1 (en) Slope reinforcement structure using support and tension and Its Construction method
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
JP2000144769A (en) Method of landslide protection work for preparing housing lot
KR102150531B1 (en) Retaining wall structure using vertical underground insert and its construction method
KR102617795B1 (en) Retaining wall system combine H-piles with steel reinforcement structure
JP2004346729A (en) Widened road
KR100770159B1 (en) Steel pipe roof structure
KR100813910B1 (en) Steel pipe roof structure
US5558470A (en) System and method for adjustably anchoring traffic barriers and wall facing panels to the soldier beams of a wall
KR100488501B1 (en) Straight retaining wall having a shelf using H-shaped piles and constructing method thereof
KR100493516B1 (en) Micro pile and assembly foundation reinforcement structure member and its method for pier
KR100744972B1 (en) Prefabricated Earth Block Structure

Legal Events

Date Code Title Description
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20210208

PA0201 Request for examination
PA0302 Request for accelerated examination

Patent event date: 20210216

Patent event code: PA03022R01D

Comment text: Request for Accelerated Examination

Patent event date: 20210208

Patent event code: PA03021R01I

Comment text: Patent Application

PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20210312

Patent event code: PE09021S01D

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20210624

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20210628

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20210628

End annual number: 3

Start annual number: 1

PG1601 Publication of registration