JPH06306853A - Construction of underground structure - Google Patents

Construction of underground structure

Info

Publication number
JPH06306853A
JPH06306853A JP5099289A JP9928993A JPH06306853A JP H06306853 A JPH06306853 A JP H06306853A JP 5099289 A JP5099289 A JP 5099289A JP 9928993 A JP9928993 A JP 9928993A JP H06306853 A JPH06306853 A JP H06306853A
Authority
JP
Japan
Prior art keywords
underground
wall body
concrete wall
concrete
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP5099289A
Other languages
Japanese (ja)
Other versions
JP2963972B2 (en
Inventor
Koichi Uemura
厚一 植村
Makoto Uemura
誠 植村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP5099289A priority Critical patent/JP2963972B2/en
Publication of JPH06306853A publication Critical patent/JPH06306853A/en
Application granted granted Critical
Publication of JP2963972B2 publication Critical patent/JP2963972B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To enable it to construct an underground continuous wall and a large sectional underground structure used with this wall simply in a short time, besides safely. CONSTITUTION:In use of an open type boring machine 1 installed with two digging jacks 2 in a machine body, where those of front, rear and upper faces are opened, in arranging them up and down toward the rear, earth and sand are digged and discharged out by a digging and discharging part 1d of this boring machine 1. In this case, these digging jacks 2 are extended and a concrete wall body 4 is used as a reaction, thereby advancing the boring machine 1 forward. A new concrete wall body 4 is hung down from the upside as a set in a tail part 1c of the boring machine 1, and it is connected to the existing concrete wall body 4. These operations are properly repeated and those of concrete wall bodies 4 are embedded in files, constructing an underground continuous wall body 5 in two rows at intervals. An interval between these underground continuous walls 5 is digged, and a concrete block 8 is installed on the bottom, connecting it to the underground continuous wall 5, and the whole body is formed into an H-type structure.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、地中連続壁体およびこ
の地中連続壁体を利用した大断面構造物としての地下構
造物の施工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a continuous underground wall and a method of constructing an underground structure as a large-section structure using the continuous underground wall.

【0002】[0002]

【従来の技術】従来、地下構造物を形成するための土留
め壁の形成としては、H形鋼などの親杭を計画された山
留め壁の中心線上に1m〜2m程度の間隔で打設し、掘
削の進行に伴い横矢板をはめ込んで構成する親杭横矢板
方式が代表的なものである。
2. Description of the Related Art Conventionally, as a retaining wall for forming an underground structure, parent piles such as H-section steel are laid on the center line of a planned retaining wall at intervals of about 1 m to 2 m. As the excavation progresses, the main pile side sheet pile method, which is configured by inserting the side sheet pile, is typical.

【0003】この親杭横矢板方式の他に、シートパイル
や鋼管等の矢板を一枚ずつ連続して打設して止水性のあ
る土留め壁を形成する鋼矢板もしくは鋼管矢板方式や、
場所打ちコンクリート(ソイルコンクリートも含む)を
連続して打設し、土留め壁を形成する柱列杭方式なども
ある。
In addition to the parent pile side sheet pile system, a steel sheet pile or steel pipe sheet pile system in which sheet piles, steel pipes, and other sheet piles are continuously struck one by one to form a water retaining wall.
There is also a column-column pile method in which cast-in-place concrete (including soil concrete) is continuously cast to form a retaining wall.

【0004】[0004]

【発明が解決しようとする課題】前記親杭横矢板方式
は、比較的経済的に土留め壁が形成でき、鋼矢板を打設
できないような硬い地盤にも適用できるが、止水性がな
いので地下水の多い地盤には不適当であり、横矢板挿入
時に余掘りが生じ易く周辺地盤の移動、沈下が起こり易
く、ヒービング現象の生じ易い地盤では根入れ部分の受
動土圧不足による移動が起こり易い。鋼矢板もしくは鋼
管矢板方式は種類が多いので使用条件に適合した断面の
ものを使用できるが、イニシャルコストが高くなること
があり、礫層などの硬い地盤を打抜くことができない。
また、矢板の剛性があまり高くないので、打込み長さが
制限される。
The above-mentioned horizontal pile pile method for parent piles can relatively economically form the earth retaining wall and can be applied to hard ground where steel sheet piles cannot be placed, but since it does not have water stopping ability. It is not suitable for the ground with a lot of groundwater, over-excavation is likely to occur when inserting a horizontal sheet pile, and the surrounding ground is likely to move or sink, and the heaving phenomenon is likely to occur. . Since there are many types of steel sheet piles or steel pipe sheet pile methods, it is possible to use those having a cross section that meets the usage conditions, but the initial cost may be high, and hard ground such as gravel layers cannot be punched.
Further, since the rigidity of the sheet pile is not so high, the driving length is limited.

【0005】柱列杭方式はたわみが少ないので、背面土
の移動がなく周辺地盤に対する影響が少ない。また、強
度寸法とも計画されたものを施工できるが、工期が長
く、工費もかさむ。
Since the column-row pile method has less deflection, the back soil does not move and the surrounding ground is less affected. Moreover, although the strength dimension can be planned, the construction period is long and the construction cost is high.

【0006】本発明の目的は前記従来例の不都合を解消
し、地中連続壁体やこれを利用した大断面地下構造物を
簡単かつ短時間で、安全に施工できる地下構造物の施工
法を提供することにある。
An object of the present invention is to solve the inconvenience of the above-mentioned conventional example, and to provide a method for constructing an underground structure which can construct a continuous underground wall body and a large-section underground structure using the same easily and safely in a short time. To provide.

【0007】[0007]

【課題を解決するための手段】本発明は前記目的を達成
するため、側壁板と底板とからなり、前面、後面及び上
面を開口した機体内に推進ジャッキを後方に向け上下に
並べて配設したオープンタイプの掘進機を使用し、この
掘進機の前面又は上面開口より前方の土砂を掘削排土す
る工程と、推進ジャッキを伸長してコンクリート壁体を
反力にして掘進機を前進させる工程と、掘進機のテール
部内で縮めた推進ジャッキの後方に新たなコンクリート
壁体を上方から吊り降してセットし、これを既設のコン
クリート壁体に接続する工程とを適宜繰り返して順次コ
ンクリート壁体を縦列に埋設して地中連続壁体を形成す
ること、および、この地中連続壁体を間隔を存して2列
構築し、この地中連続壁体間を掘削して、その底にコン
クリート床版を設けてこれを地中連続壁体と結合し、全
体をH型構造物とすることを要旨とするものである。
In order to achieve the above-mentioned object, the present invention comprises a side wall plate and a bottom plate, and the propulsion jacks are arranged vertically in a rearward direction in a fuselage having front, rear and upper faces opened. Using an open type excavator, a step of excavating and discharging earth and sand in front of the front or top opening of this excavator, and a step of extending the propulsion jack and making the concrete wall body a reaction force to advance the excavator. , A new concrete wall body is hung from above and set behind the propulsion jack contracted in the tail part of the excavator, and the process of connecting this to the existing concrete wall body is repeated as appropriate to sequentially construct the concrete wall body. Embedding in vertical rows to form an underground continuous wall, and constructing this underground continuous wall in two rows at intervals, excavating between the underground continuous walls, and concrete at the bottom Floor slab This was combined with the underground continuous wall Te, it is an gist that the entirety is taken as H-shaped structure.

【0008】[0008]

【作用】本発明によれば、地中連続壁体は開削工法(オ
ープンカット工法)とシールド工法の長所を生かした合
理性に富む工法で、迅速かつ簡単に施工でき、このよう
な地中連続壁体を利用するH型の大断面地下構造物も簡
単かつ安全に施工できることになる。
According to the present invention, the continuous underground wall can be quickly and easily constructed by a rational construction method utilizing the advantages of the open cut construction method (open cut construction method) and the shield construction method. An H-shaped large-section underground structure using walls can be easily and safely constructed.

【0009】[0009]

【実施例】以下、図面について本発明の実施例を詳細に
説明する。先に、本発明における地中連続壁体の施工法
を説明すると、図中1は掘進機で、これは左右の側壁板
1aとこれら側壁板1aに連結する底板1bとからなる
前面、後面及び上面を開口した機体を有するものであ
る。
Embodiments of the present invention will now be described in detail with reference to the drawings. First, the construction method of the underground continuous wall body in the present invention will be explained. In the figure, 1 is an excavator, which is a front surface, a rear surface and a left side wall plate 1a and a bottom plate 1b connected to these side wall plates 1a. It has a body with an open top.

【0010】この機体は前記側壁板1aと底板1bの先
端を刃口として形成し、また側壁板1aの中央に隔壁3
を設け、さらに、この隔壁3よりも後方に推進ジャッキ
2を後方に向け上下に多数段並べて配設する。このよう
にして、掘進機1は隔壁3よりも前方を掘削・排土部1
d、後方をコンクリート壁体の設置用のテール部1cと
する。
In this machine, the tips of the side wall plate 1a and the bottom plate 1b are formed as blade openings, and the partition wall 3 is formed at the center of the side wall plate 1a.
Further, the propulsion jacks 2 are arranged rearward of the partition wall 3 and arranged in multiple stages vertically facing rearward. In this way, the excavator 1 excavates and excavates in front of the bulkhead 3.
d, the rear part is a tail part 1c for installing a concrete wall.

【0011】図示は省略するが発進坑を構築し、この発
進坑にこの掘進機1を設置して推進ジャッキ2を伸長し
て発進坑内の反力壁に反力をとって掘進機1を前進さ
せ、後述の地中連続壁体5を形成する第1番目のコンク
リート壁体4を上方から吊り降し、掘進機1のテール部
1c内で縮めた推進ジャッキ2の後方にセットする。こ
のコンクリート壁体4はプレキャストコンクリート板か
らなる。
Although not shown, a starting pit is constructed, and the excavator 1 is installed in the starting pit, the propulsion jack 2 is extended, and a reaction force is applied to the reaction wall in the starting pit to advance the excavator 1 Then, the first concrete wall body 4 forming the below-mentioned underground continuous wall body 5 is hung from above and set behind the propulsion jack 2 compressed in the tail portion 1c of the excavator 1. The concrete wall body 4 is made of a precast concrete plate.

【0012】掘削機6で掘進機1の前面又は上面から土
砂を掘削しかつ排土する。掘進機1は縦に長いものであ
り、この掘削機6は地上にベースマシンを設置し、掘進
機1の長さに見合って掘削機構を掘進機1の刃口部に吊
り降ろして配置できるものがよく、一例としてスクリュ
ーオーガータイプの掘削機が利用し得る。なお、他の実
施例として掘削機6には、ドリリングバケットタイプの
ものやジェット水で掘削し、泥水を回収するタイプのも
のなど種々のものの利用が考えられる。
The excavator 6 excavates earth and sand from the front or upper surface of the excavator 1 and discharges it. The excavator 1 is a vertically long one, and this excavator 6 has a base machine installed on the ground, and the excavator can be arranged so as to be suspended from the cutting edge of the excavator 1 according to the length of the excavator 1. Well, as an example, a screw auger type excavator can be used. In addition, as other examples, various types of excavators 6, such as a drilling bucket type and a type of excavating with jet water to collect muddy water, can be considered.

【0013】かかる掘削機6での掘削・排土の後で、推
進ジャッキ2を伸長して掘進機1を前進させる。この前
進工程の際に前記第1番目のコンクリート壁体4の前に
第2番目のコンクリート壁体4を掘進機1のテール部1
c内に吊り降す。以下、同様の排土工程、前進工程、コ
ンクリート壁体4をセット工程を適宜繰返して、順次コ
ンクリート壁体4を掘進機1の前進に伴い縦列に地中に
残置する。
After excavation and soil removal by the excavator 6, the propulsion jack 2 is extended to advance the excavator 1. During this forward movement process, the second concrete wall body 4 is placed in front of the first concrete wall body 4 and the tail portion 1 of the excavator 1 is installed.
Suspend in c. Thereafter, the same earth discharging step, advancing step, and setting step of the concrete wall body 4 are appropriately repeated, and the concrete wall body 4 is sequentially left in the ground in a row along with the forward movement of the excavator 1.

【0014】前記隔壁3はこれがあると、掘進機1の掘
進時に土砂を圧密し、掘削機6での掘削・排土を容易と
することができる。なお、コンクリート壁体4は掘進機
1ののテール部1c内に吊り降す際には、既設のコンク
リート壁体4と相互に接続して一体化するが、この接続
は例えばコンクリート壁体4の内部に継手用の鉄筋等を
挿通させてこれをネジ継手、カップラー等で連結するも
のとする。
When the partition wall 3 is provided, it is possible to compact the earth and sand when the excavator 1 is excavating, and to facilitate excavation and earth removal by the excavator 6. When the concrete wall body 4 is suspended in the tail portion 1c of the excavator 1, the concrete wall body 4 is mutually connected and integrated with the existing concrete wall body 4. Reinforcing bars for joints shall be inserted inside and shall be connected by screw joints, couplers, etc.

【0015】このようにして掘進機1の前進に伴い縦列
に地中に残置されたコンクリート壁体4は地中連続壁体
5を形成するが、必要に応じて周囲の隙間を埋戻した
り、また、グラウトしたりする。最終的には掘進機1は
到達孔に導きここで撤去する。
In this way, the concrete wall bodies 4 left in the ground in a row along with the forward movement of the excavator 1 form a continuous underground wall body 5, but if necessary, the surrounding gaps may be backfilled. Also, grout. Finally, the excavator 1 leads to the reaching hole and is removed here.

【0016】以上が地中連続壁体5の施工であるが、本
発明はさらに、図4に示すようにこの地中連続壁体5は
間隔を存して2列構築し、図5に示すようにこの地中連
続壁体5間を掘削(根切り)する。その根切底は地中連
続壁体5の下端まで行かず、途中に位置し、地中連続壁
体5の下端付近は地盤に刺さったままとし、この部分で
支持力を得るものとする。
The above is the construction of the underground continuous wall body 5, but in the present invention, as shown in FIG. 4, the underground continuous wall body 5 is constructed in two rows at intervals, and is shown in FIG. Thus, the space between the underground continuous walls 5 is excavated (root cutting). The root cut bottom does not go to the lower end of the underground continuous wall body 5, but is located in the middle, and the vicinity of the lower end of the underground continuous wall body 5 is kept stuck in the ground, and the supporting force is obtained at this portion.

【0017】この地中連続壁体5は土留め壁として作用
するものであるが、なお、根切りの進行にともない、必
要の応じて地中連続壁体5にアースアンカー7を設け、
これで地中連続壁体5の支持力を増大させてもよい。
The underground continuous wall body 5 acts as an earth retaining wall. However, as the root cutting progresses, an earth anchor 7 is provided on the underground continuous wall body 5 if necessary.
This may increase the bearing capacity of the underground wall 5.

【0018】そして図6に示すように前記根切底に捨て
石や捨てコンを施し、その上に配筋したうえでコンクリ
ートを打設し、コンクリート床版8を設ける。このコン
クリート床版8は地中連続壁体5の壁面から突出させた
継手筋と配筋する鉄筋とを接続させて地中連続壁体5と
一体的に結合し、全体をH型構造物とする。
Then, as shown in FIG. 6, a gravel stone or a crushed concrete is applied to the root cutting bottom, and a concrete floor slab 8 is provided by placing concrete on the bar and reinforcing it. The concrete floor slab 8 connects the joint reinforcement protruding from the wall surface of the underground continuous wall body 5 and the reinforcing bar which is reinforced and is integrally connected to the underground continuous wall body 5 to form an H-shaped structure as a whole. To do.

【0019】このH型構造物は大断面地下構造物として
道路、水路、その他に利用し得る。
The H-shaped structure can be used as a large-section underground structure for roads, waterways and the like.

【0020】ところで、前記地中連続壁体5間の掘削
(根切り)及びコンクリート床版8の形成は、地中連続
壁体5の設計長をすべて施工した後で行うようにしても
よいが、地中連続壁体5の形成に応じて順次進行させる
ようにすることもできる。例えば数メートルもしくは十
数メートル地中連続壁体5を施工したならばその端より
数メートル短く遅れて掘削(根切り)及びコンクリート
床版8の形成を行い、次いで地中連続壁体5を延設し、
さらに掘削(根切り)及びコンクリート床版8の形成を
繰り返すというように順次H型構造物としての施工長を
延ばして行くような施工も可能である。
By the way, the excavation (root cutting) between the underground continuous wall bodies 5 and the formation of the concrete floor slab 8 may be performed after all the designed lengths of the underground continuous wall bodies 5 have been constructed. It is also possible to sequentially proceed according to the formation of the continuous underground wall 5. For example, if the underground continuous wall 5 is constructed for several meters or a dozen meters, excavation (root cutting) and formation of the concrete floor slab 8 are performed with a delay of several meters from the end, and then the underground continuous wall 5 is extended. Set up
Further, it is also possible to carry out a construction in which the construction length of the H-shaped structure is sequentially extended by repeating excavation (root cutting) and formation of the concrete floor slab 8.

【0021】[0021]

【発明の効果】以上述べたように本発明の地下構造物の
施工法は、地中連続壁体やこれを利用した大断面地下構
造物を簡単かつ短時間で、しかも安全に施工できるもの
である。
INDUSTRIAL APPLICABILITY As described above, the method for constructing an underground structure according to the present invention is capable of constructing an underground underground wall or a large-section underground structure using the underground structure easily, quickly and safely. is there.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の地下構造物の施工法の1実施例を示す
もので、地中連続壁体の施工を示す斜視図である。
FIG. 1 is a perspective view showing an embodiment of a method of constructing an underground structure of the present invention, showing construction of an underground continuous wall body.

【図2】本発明の地下構造物の施工法の1実施例を示す
もので、地中連続壁体の施工を示す縦断側面図である。
FIG. 2 shows one embodiment of the method for constructing an underground structure of the present invention, and is a vertical cross-sectional side view showing the construction of a continuous underground wall.

【図3】本発明の地下構造物の施工法でH型構造物を施
工する場合の平面図である。
FIG. 3 is a plan view in the case of constructing an H-shaped structure by the underground structure construction method of the present invention.

【図4】本発明の地下構造物の施工法でH型構造物を施
工する場合で、根切り前の工程を示す縦断正面図であ
る。
FIG. 4 is a vertical sectional front view showing a step before root cutting when an H-shaped structure is constructed by the underground structure construction method of the present invention.

【図5】本発明の地下構造物の施工法でH型構造物を施
工する場合で、根切り後の工程を示す縦断正面図であ
る。
FIG. 5 is a vertical sectional front view showing a step after root cutting in the case of constructing an H-shaped structure by the method for constructing an underground structure of the present invention.

【図6】本発明の地下構造物の施工法でH型構造物を施
工する場合で、根切り後のコンクリート床版の形成を示
す縦断正面図である。
FIG. 6 is a vertical cross-sectional front view showing formation of a concrete floor slab after root cutting in the case of constructing an H-shaped structure by the method for constructing an underground structure of the present invention.

【符号の説明】[Explanation of symbols]

1…掘進機 1a…側壁板 1b…底板 1c…テール部 1d…掘削・排土
部 2…推進ジャッキ 3…隔壁 4…コンクリート壁体 5…地中連続壁体 6…掘削機 7…アースアンカー 8…コンクリート
床版
DESCRIPTION OF SYMBOLS 1 ... Excavator 1a ... Side wall plate 1b ... Bottom plate 1c ... Tail part 1d ... Excavation / discharging part 2 ... Propulsion jack 3 ... Partition wall 4 ... Concrete wall body 5 ... Underground continuous wall body 6 ... Excavator 7 ... Earth anchor 8 … Concrete floor slabs

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 側壁板と底板とからなり、前面、後面及
び上面を開口した機体内に推進ジャッキを後方に向け上
下に並べて配設したオープンタイプの掘進機を使用し、
この掘進機の前面又は上面開口より前方の土砂を掘削排
土する工程と、推進ジャッキを伸長してコンクリート壁
体を反力にして掘進機を前進させる工程と、掘進機のテ
ール部内で縮めた推進ジャッキの後方に新たなコンクリ
ート壁体を上方から吊り降してセットし、これを既設の
コンクリート壁体に接続する工程とを適宜繰り返して順
次コンクリート壁体を縦列に埋設して地中連続壁体を形
成することを特徴とした地下構造物の施工法。
1. An open-type excavator, which is composed of a side wall plate and a bottom plate, and in which the propulsion jacks are arranged rearward in a vertical direction in a body having front, rear, and upper surfaces open,
The step of excavating and discharging earth and sand in front of the front or upper surface opening of the machine, the step of extending the propulsion jack to make the concrete wall body a reaction force to move the machine forward, and the contraction in the tail of the machine A new concrete wall body is hung from the top behind the propulsion jack and set, and the process of connecting this to the existing concrete wall body is repeated as appropriate to sequentially bury the concrete wall bodies in columns to form a continuous underground wall. A method of constructing an underground structure characterized by forming a body.
【請求項2】 側壁板と底板とからなり、前面、後面及
び上面を開口した機体内に推進ジャッキを後方に向け上
下に並べて配設したオープンタイプの掘進機を使用し、
この掘進機の前面又は上面開口より前方の土砂を掘削排
土する工程と、推進ジャッキを伸長してコンクリート壁
体を反力にして掘進機を前進させる工程と、掘進機のテ
ール部内で縮めた推進ジャッキの後方に新たなコンクリ
ート壁体を上方から吊り降してセットし、これを既設の
コンクリート壁体に接続する工程とを適宜繰り返して順
次コンクリート壁体を縦列に埋設して地中連続壁体を間
隔を存して2列構築し、この地中連続壁体間を掘削し
て、その底にコンクリート床版を設けてこれを地中連続
壁体と結合し、全体をH型構造物とすることを特徴とし
た地下構造物の施工法。
2. An open type excavator comprising a side wall plate and a bottom plate, the propulsion jacks facing rearward and arranged vertically in a body having front, rear and upper surfaces opened,
The step of excavating and discharging earth and sand in front of the front or upper surface opening of the machine, the step of extending the propulsion jack to make the concrete wall body a reaction force to move the machine forward, and the contraction in the tail of the machine A new concrete wall body is hung from the top behind the propulsion jack and set, and the process of connecting this to the existing concrete wall body is repeated as appropriate to sequentially bury the concrete wall bodies in columns to form a continuous underground wall. The body is constructed in two rows at intervals, excavation is performed between the underground continuous wall bodies, a concrete floor slab is provided at the bottom of the body, and this is connected to the underground continuous wall body, and the whole is an H-shaped structure. The construction method of the underground structure characterized by the following.
【請求項3】 地中連続壁体間の掘削およびコンクリー
ト床版の施工は、地中連続壁体の形成に応じて順次進行
させる請求項2記載の地下構造物の施工法。
3. The method for constructing an underground structure according to claim 2, wherein the excavation between the underground continuous walls and the construction of the concrete floor slab are sequentially performed according to the formation of the underground continuous walls.
JP5099289A 1993-04-26 1993-04-26 Construction method for underground structures Expired - Lifetime JP2963972B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5099289A JP2963972B2 (en) 1993-04-26 1993-04-26 Construction method for underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5099289A JP2963972B2 (en) 1993-04-26 1993-04-26 Construction method for underground structures

Publications (2)

Publication Number Publication Date
JPH06306853A true JPH06306853A (en) 1994-11-01
JP2963972B2 JP2963972B2 (en) 1999-10-18

Family

ID=14243492

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5099289A Expired - Lifetime JP2963972B2 (en) 1993-04-26 1993-04-26 Construction method for underground structures

Country Status (1)

Country Link
JP (1) JP2963972B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979123A (en) * 2012-12-03 2013-03-20 张永忠 Throwing and grappling impact grooving machine
CN106759425A (en) * 2017-03-23 2017-05-31 曹全忠 A kind of clamping plate connection stake manufacture machinery
CN106759261A (en) * 2016-12-07 2017-05-31 王德娟 A kind of wall forming machine
CN106869116A (en) * 2017-03-23 2017-06-20 曹全忠 Spigot-and-socket fender post arrangement and method for construction
CN106930310A (en) * 2017-04-26 2017-07-07 沈孝伦 One kind button connects stake scheme
CN107090824A (en) * 2017-05-13 2017-08-25 卢兴书 The arrangement and method for construction of jet-grouted anchor pile break adrift subterranean wall
CN107100131A (en) * 2017-04-25 2017-08-29 沈孝伦 Bend the method for construction of riverbank seepproof screen

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5277410A (en) * 1975-12-23 1977-06-29 Kazuyoshi Moroki Execution method of sheathing wall

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5277410A (en) * 1975-12-23 1977-06-29 Kazuyoshi Moroki Execution method of sheathing wall

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979123A (en) * 2012-12-03 2013-03-20 张永忠 Throwing and grappling impact grooving machine
CN106759261A (en) * 2016-12-07 2017-05-31 王德娟 A kind of wall forming machine
CN106759425A (en) * 2017-03-23 2017-05-31 曹全忠 A kind of clamping plate connection stake manufacture machinery
CN106869116A (en) * 2017-03-23 2017-06-20 曹全忠 Spigot-and-socket fender post arrangement and method for construction
CN107100131A (en) * 2017-04-25 2017-08-29 沈孝伦 Bend the method for construction of riverbank seepproof screen
CN106930310A (en) * 2017-04-26 2017-07-07 沈孝伦 One kind button connects stake scheme
CN107090824A (en) * 2017-05-13 2017-08-25 卢兴书 The arrangement and method for construction of jet-grouted anchor pile break adrift subterranean wall

Also Published As

Publication number Publication date
JP2963972B2 (en) 1999-10-18

Similar Documents

Publication Publication Date Title
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JPH06306853A (en) Construction of underground structure
JP3893056B2 (en) Construction method of underground structure
JP4303512B2 (en) Construction method of large section tunnel
JP3766423B2 (en) Retaining wall construction method
JP2668648B2 (en) Construction method of underground structure and starting pit used for it
JP5639213B2 (en) Open shield method
JPS6018769B2 (en) Construction method of underground structure
JP2587309B2 (en) Protective structure of concrete underground structure and its construction method
JPH02248521A (en) Open shield method
JP4279818B2 (en) Open shield method
JP3926818B2 (en) Installation method of concrete box
JP4279441B2 (en) Open shield machine and open shield method using this open shield machine
JP2673940B2 (en) How to build a horizontal plate-like structure in the ground
JP3302661B2 (en) Open shield machine and construction method of underground structure using it
JP2732014B2 (en) Construction method of large section underground structure by open shield method.
JP3333770B2 (en) Construction method for underground structures
JP2540440B2 (en) Open shield method
JP2002339691A (en) Earth retaining equipment and open-cut construction method using this equipment
JP2003027885A (en) Construction method for underground tunnel and underground tunnel
JP2003041896A (en) Concrete caisson for use in open shield tunneling method
JP3748152B2 (en) Tunnel digging method
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
JP2005030061A (en) Open shield construction method
JPH0428044B2 (en)

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080813

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090813

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100813

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100813

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110813

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130813

Year of fee payment: 14

EXPY Cancellation because of completion of term