JPH0730564B2 - Construction method of underground structure - Google Patents

Construction method of underground structure

Info

Publication number
JPH0730564B2
JPH0730564B2 JP62144039A JP14403987A JPH0730564B2 JP H0730564 B2 JPH0730564 B2 JP H0730564B2 JP 62144039 A JP62144039 A JP 62144039A JP 14403987 A JP14403987 A JP 14403987A JP H0730564 B2 JPH0730564 B2 JP H0730564B2
Authority
JP
Japan
Prior art keywords
floor
slab
beams
formwork
suspension frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP62144039A
Other languages
Japanese (ja)
Other versions
JPS63312437A (en
Inventor
惇平 間瀬
長英 可児
邦夫 絹川
澄男 前沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP62144039A priority Critical patent/JPH0730564B2/en
Publication of JPS63312437A publication Critical patent/JPS63312437A/en
Publication of JPH0730564B2 publication Critical patent/JPH0730564B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は地下構造物の構築工法、特に逆打工法を採用す
る必要がある軟弱地盤、大規模、大深度の地下工事に適
用される地下構造物の構築工法に係るものである。
DETAILED DESCRIPTION OF THE INVENTION (Industrial field of application) The present invention is applied to the underground construction method for construction of underground structures, especially for the soft ground, large scale, and deep underground where the reverse construction method is required. It relates to the construction method of structures.

(従来の技術) 一般の地下構造物の構築工法においては、仮設土留壁に
仮設支保工を設け、仮設桟橋を設置して地下掘削を行っ
ている。
(Prior Art) In a general construction method for an underground structure, temporary shoring is installed on a temporary earth retaining wall, and a temporary pier is installed to perform underground excavation.

しかしながら、軟弱地盤における大規模、大深度の地下
掘削に関しては、従来の仮設一般山留工法では施工が困
難であり、安全性を確保するために全館逆打工法を採用
する場合が多く、従来の逆打工法では、地下部分各階躯
体工事については、その都度、現場で側枠を組立て、鉄
筋を配筋し、コンクリートを打設していた。
However, for large-scale and deep underground excavation on soft ground, it is difficult to construct with the conventional temporary general mountain retaining method, and in many cases the whole building reverse driving method is adopted to ensure safety. In the reverse construction method, for each basement floor construction work, side frames were assembled on site, reinforcing bars were laid and concrete was placed each time.

(発明が解決しようとする問題点) このように前記従来の工法では、地下部分各躯体工事に
ついて、その都度、現場打型枠を組み立て、配筋、コン
クリート打設を行っているため、軟弱地盤よりの支持が
不安定であり、また上階コンクリートの強度が一定限以
上にならないと解体、及び下段根伐りができず、更にま
た解体型枠材を一旦上階に搬出、片付け、根伐り後、再
び下階に移動する等の作業が煩雑である。
(Problems to be solved by the invention) As described above, in the conventional construction method, as for each substructure work of the underground part, the on-site casting form is assembled, the bar arrangement and the concrete placement are performed each time. Support is unstable, and if the strength of the upper floor concrete does not exceed a certain limit, dismantling and lower level root cutting cannot be performed.Furthermore, the demolished formwork material is once transported to the upper floor, tidyed up, and after root cutting. The work of moving to the lower floor again is complicated.

その結果、逆打工事に非常に手間がかかり、工費が嵩
み、工程の遅れを招来している。
As a result, the reverse striking work is extremely troublesome, the construction cost is high, and the process is delayed.

(問題点を解決するための手段) 本発明はこのような問題点を解決するために提案された
もので地中に構築された垂直真柱間の第1次根伐り底に
地下階の全PC梁を仮置きし、前記垂直真柱に装架された
吊込架台を反力として全PC梁を吊上げ、1階PC梁を前記
垂直真柱間に固定した後、スラブ型枠を吊込架台を支持
材として1階PC梁間に架設し、1階床コンクリートを打
設し、同打設コンクリートの硬化後スラブ型枠を剥離
し、下階のPC梁とスラブ型枠を別々に吊下ろし、以下前
記工程を反覆して地下階PC梁とスラブを順次施工するこ
とを特徴とする地下構造物の構築工法に係るものであ
る。
(Means for Solving Problems) The present invention has been proposed to solve such problems, and the entire basement floor is provided at the first root cutting bottom between vertical true pillars constructed underground. Temporarily place the PC beams, hang all the PC beams by using the suspension frame mounted on the vertical true columns as a reaction force, fix the first floor PC beams between the vertical true columns, and then hang the slab formwork. The pedestal is used as a support material between the first-floor PC beams, the first-floor concrete is placed, the slab formwork is peeled off after hardening of the placed concrete, and the lower-level PC beams and slab formwork are suspended separately. The present invention relates to a construction method for an underground structure, which is characterized by sequentially constructing a basement floor PC beam and a slab by reversing the above steps.

(作用) 本発明においては前記したように、地中に支持真柱を構
築したのち、第1次の根伐りを行ない、前記各垂直真柱
間の第1次根伐り底に地下階の全PC梁を仮置きし、前記
垂直真柱に架設した吊込架台を反力支持材として全PC梁
を吊上げ重合状態にある同PC梁のうち最上部の第1段の
1階PC梁を前記各垂直真柱に固定し、同1段のPC梁上に
スラブ型枠を架設して1階床コンクリートを打設する。
同打設コンクリートの硬化後、スラブ型枠を剥離し、下
階のPC梁とスラブ型枠を別々に吊下ろす。
(Operation) In the present invention, as described above, after constructing the supporting true pillars in the ground, the first root cutting is performed, and all the basement floors are formed at the first root cutting bottom between the vertical true pillars. The PC beam is temporarily placed, and all the PC beams are hoisted by using the suspension frame erected on the vertical true pillar as a reaction force support material. It is fixed to each vertical true pillar, slab formwork is erected on the PC beam of the same step, and the first floor concrete is placed.
After hardening of the cast concrete, the slab formwork is peeled off and the PC beam and slab formwork on the lower floor are hung separately.

かくして地上1階のスラブの施工が完了したのち、第2
次の根伐りを行ない、前記第1段のPC梁以下に位置する
第2段以下のPC梁を重合した状態で第2次の根伐り底ま
で吊り下ろし、同重合状態にあるPC梁のうち最上部に位
置する第2段のPC梁を前記各垂直真柱間に固定したに
ち、同第2段のPC梁上に前記同様にして地下1階のスラ
ブを施工し、以下前記同様の工程を必要階分、反覆する
ことによって、地下構造物を構築するものである。
After the construction of the slab on the first floor above the ground is completed, the second
Of the PC beams in the same superposed state, the following root cutting was carried out, and the PC beams of the second stage and below located below the first stage PC beams were suspended in the state of being piled up to the second root cutting bottom. After fixing the second-stage PC beam located at the top between the vertical columns, a slab on the first basement floor was constructed on the second-stage PC beam in the same manner as above, and the same as above. Underground structures are constructed by repeating the steps for the required floors.

(実施例) 以下本発明を図示の実施例について説明する。(Examples) The present invention will be described below with reference to illustrated examples.

地下構造物の外周に支持杭兼用の連続地中壁(1)を施
工するとともに、後述のPC梁を吊り下ろすための支持真
柱(2)を植立し第1次の根伐りを行なう。図中(3)
は第1次の根伐り底である。(第1図参照) なお前記地中連続壁(1)には必要に応じて柱型及び梁
型を内蔵させる。更に前記根伐り底(3)には地盤の硬
質によって作業要土間コンクリートを打設する。
A continuous underground wall (1) that also serves as a support pile will be constructed on the outer periphery of the underground structure, and a supporting true pillar (2) will be planted for hanging the PC beam, which will be described later, for the first root cutting. (3) in the figure
Is the first root cutting bottom. (See FIG. 1) In addition, a pillar type and a beam type are incorporated in the underground continuous wall (1) as needed. Further, concrete for working soil is placed on the root cutting bottom (3) due to the hardness of the ground.

次いで前記各垂直真柱間において、根伐り底(3)上に
地下階数に応じた分だけのPC梁(4)を仮置きし、工事
要作業床(一般には1階の床梁)のPC梁(5)を支持真
柱(2)間に取付け、PC梁及び型枠デッキ吊下ろし要の
吊込架台(6)を設置する。更に前記PC梁上端と同一レ
ベルに床形成要型枠デッキ(7)等を前記吊込架台にワ
イヤーを介して吊込み取付けてスラブコンクリートを打
設する。(第2図参照)なおこの際、適所に掘削用、躯
体工事用駄目穴を設けておく。
Next, between the above vertical true pillars, PC beams (4) corresponding to the number of basements are temporarily placed on the root-cutting bottom (3), and PCs for the work floors requiring construction (generally floor beams) The beam (5) is installed between the supporting true pillars (2), and the suspension frame (6) for hanging the PC beam and the form deck is installed. Further, the floor forming required formwork deck (7) and the like are attached to the suspension frame via wires at the same level as the upper end of the PC beam, and slab concrete is poured. (See Fig. 2) At this time, use holes for excavation and building work at appropriate places.

なお型枠デッチ(7)は後述のように吊込架台(6)に
よって吊り下ろされるものである。
The formwork ditch (7) is hung by the suspension frame (6) as described later.

第7図及び第8図は前記吊込架台(6)の詳細を示し、
前記1階のPC梁(5)が交叉する個所に、同各PC梁
(5)の軸線と45°の交角で交叉する方形枠状吊込枠
(6a)の相隣る各辺間に、前記PC梁(5)下にこれと直
交して支持するPC梁受材(g1)が連結され、前記吊込
材(6a)の相対する両辺間には同各辺と直交し、且つ前
記支持直柱(2)を挟んで対向する一双の連結片(6c)
が連結され、同各連結片(6c)間には更に前記真柱
(2)を挟む一双の連結片(6d)が連結され、前記各連
結片(6c)(6d)には前記支持真柱(2)隅角に当接し
て吊込枠の水平位置を規制する規制片(6e)が装着され
ている。
7 and 8 show the details of the suspension frame (6),
At the location where the PC beams (5) on the first floor intersect, between the adjacent sides of the rectangular frame-shaped suspension frame (6a) that intersects with the axis of each PC beam (5) at an angle of 45 °, A PC beam receiving member (g 1 ) which is supported orthogonally to the PC beam (5) is connected under the PC beam (5), and is orthogonal between the opposite sides of the suspending member (6a) and is directly connected to the supporting line A pair of connecting pieces (6c) facing each other across the pillar (2)
And a pair of connecting pieces (6d) sandwiching the true pillar (2) are further connected between the connecting pieces (6c), and the supporting true pillars are connected to the connecting pieces (6c) (6d). (2) A restricting piece (6e) that is in contact with the corner and restricts the horizontal position of the hanging frame is attached.

また前記PC受梁材(g1)の両端部と前記吊込枠(6e)
との交叉部には、夫々前記PC梁(4)の吊り下ろし用PC
ストランド(p1)が貫挿され、同ストランド(p1)は
各PC梁(4)下端部に係止具(q1)を介して係止され
る。また前記吊込枠(6a)の各辺中央には型枠デッキ吊
込用PCストランド(p2)が貫挿され、型枠デッキ
(7)に係止具(q2)を介して係止されている。
Both ends of the PC beam member (g 1 ) and the suspension frame (6e)
PCs for hanging the PC beams (4) at the intersections with
The strand (p 1 ) is inserted, and the strand (p 1 ) is locked to the lower end of each PC beam (4) via a locking tool (q 1 ). Further, a PC strand (p 2 ) for suspending the formwork deck is inserted through the center of each side of the suspension frame (6a) and locked to the formwork deck (7) via a locking tool (q 2 ). Has been done.

従って前記各ストランド(p1)(p2)を操作すること
によって、前記PC梁(5)及び型枠デッキ(7)が別々
に吊り下ろされるようになっている。
Therefore, by operating the strands (p 1 ) and (p 2 ), the PC beam (5) and the form deck (7) can be hung separately.

図中(4a)(5a)は、前記PC梁(4)(5)に埋設さ
れ、前記真柱(2)の外周に突設されたブラケット(2
a)に接合されるように梁端部より突設された接続用鉄
骨部、(4b)は前記PC梁(4)に埋設された肋筋の突出
端部である。
In the figure, (4a) and (5a) are embedded in the PC beams (4) and (5), and the brackets (2) projecting from the outer periphery of the true column (2).
The connecting steel frame projecting from the beam end so as to be joined to a), (4b) is the projecting end of the rib that is embedded in the PC beam (4).

次いで前記吊込架台(6)によって前記第1次根伐り底
(3)上のPC梁(4)を、PCストランド(p1)を介し
て吊り上げ、第2次の根伐りを行なう。(8)は同第2
次の根伐り底である。(第3図参照) 次いで前記吊込架台(6)によって重合された下階用の
PC梁(4)を吊り下げ、同PC梁(4)中、最上部の地下
1階用PC梁(4A)を垂直真柱(2)間、及び地中連続壁
(1)と垂直真柱(2)との間に固定し、しかるのち前
記吊込架台(6)によってスラブ型枠デッキ(7)を地
下1階用PC梁(4A)に吊り上げる。(第4図参照) 対で地下1階のスラブコンクリート(9)を打設し、第
3次根伐りを行なう。図中(10)は第3次根伐り底であ
る。対で吊込架台(6)によって第2段以下のPC梁
(4)を吊り下ろし、第2段の地下2階用PC梁(4)を
前記垂直柱(2)間、又は地中連続壁(1)と垂直真柱
(2)との間に固定し、しかるのち前記吊込架台(6)
によってスラブ型枠デッキ(7)を前記PC梁(4B)上に
吊下げ、(第5図参照)地下2階のスラブコンクリート
(9′)を打設し、以下前記同様の工程を地下必要階分
反覆し、第6図に示すように最終根伐りを行ない、同最
終根伐り底(11)上に基礎コンクリート(12)を打設し
たのち、後打柱躯体(13)工事及び打継処理を行って、
全工程を完了する。
Next, the PC beam (4) on the first root cutting bottom (3) is lifted by the suspension base (6) through the PC strand (p 1 ) to perform the second root cutting. (8) is the second
It is the next root cut. (See FIG. 3) Then, for the lower floor, which was polymerized by the suspension frame (6).
Suspend the PC beam (4), among the PC beam (4), the uppermost PC beam (4A) for the first basement floor between the vertical true pillars (2) and between the underground continuous wall (1) and the vertical true pillar It is fixed to (2), and then the slab formwork deck (7) is hung up on the PC beam (4A) for the first basement floor by the suspension frame (6). (Refer to Fig. 4) Slab concrete (9) on the first basement floor is placed in pairs and the third root cutting is performed. (10) in the figure is the third root cutting bottom. PC beams (4) below the second stage are hung by a suspension frame (6) in pairs, and the PC beams (2) for the second basement floor of the second stage are connected between the vertical columns (2) or the underground wall. It is fixed between (1) and the vertical true pillar (2), and then the suspension frame (6).
Suspend the slab formwork deck (7) on the PC beam (4B) and place the slab concrete (9 ') on the second basement floor (see Fig. 5). After overturning, the final root cutting is performed as shown in Fig. 6, and the basic concrete (12) is placed on the final root cutting bottom (11), and then the post strut body (13) construction and jointing treatment. Go to
Complete all steps.

(発明の効果) 本発明によれば前記垂直真柱に装架した吊込架台によっ
て地下部の施工を行ない、垂直真柱における吊込架台よ
り上部は上階の鉄骨躯体の施工に利用されるので、地上
部と地下部とが同時施工されるものであり、また前記吊
込架台はPC梁用とスラブ型枠用とを兼用できることとも
相俟って施工性が向上される。
(Effects of the Invention) According to the present invention, the construction of the underground portion is performed by the suspension frame mounted on the vertical true pillar, and the portion above the suspension frame of the vertical true pillar is used for the construction of the steel frame on the upper floor. Therefore, the above-ground part and the underground part are simultaneously constructed, and the workability is improved in combination with the fact that the suspension base can be used for both the PC beam and the slab formwork.

【図面の簡単な説明】[Brief description of drawings]

第1図乃至第6図は本発明に係る地下構造物の構築工法
の一実施例の工程を示す縦断面図、第7図及び第8図は
夫々吊込架台の平面図並に縦断面図である。 (1)……地下連続壁、(2)……支持真柱、(3)…
…第1次根伐り底、(4)……PC梁、(5)……工事用
作業床のPC梁、(6)……吊込架台、(7)……型枠デ
ッキ、(8)……第2次根伐り底、(9)……地下1階
のスラブコンクリート、(9′)……地下2階のスラブ
コンクリート、(10)……第3次根伐り底。
1 to 6 are vertical cross-sectional views showing the steps of an embodiment of a method for constructing an underground structure according to the present invention, and FIGS. 7 and 8 are plan views and vertical cross-sectional views of a suspension frame, respectively. Is. (1) …… Continuous underground wall, (2) …… Supporting true pillar, (3)…
… Primary deforestation bottom, (4) …… PC beams, (5) …… PC floor beams for construction work, (6) …… Suspended frame, (7) …… Formwork deck, (8) …… The second root cut bottom, (9) …… Slab concrete on the first basement floor, (9 ′) …… Slab concrete on the second basement floor, (10) …… Third root cut bottom.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】地中に構築された垂直真柱間の第1次根伐
り底に地下階の全PC梁を仮置きし、前記垂直真柱に装架
された吊込架台を反力支持材として全PC梁を吊上げ、1
階PC梁を前記垂直真柱間に固定した後、スラブ型枠を吊
込架台を支持材として1階PC梁間に架設し、1階床コン
クリートを打設し、同打設コンクリートの硬化後スラブ
型枠を剥離し、下階のPC梁とスラブ型枠を別々に吊下ろ
し、以下前記工程を反覆して地下階PC梁とスラブを順次
施工することを特徴とする地下構造物の構築工法。
[Claim 1] All the PC beams of the basement floor are temporarily placed on the first root cutting bottom between the vertical true pillars constructed in the ground, and the suspension frame mounted on the vertical true pillars is supported by reaction force. Hoist all PC beams as materials, 1
After fixing the floor PC beam between the vertical true pillars, the slab formwork is installed between the first floor PC beams using the suspension frame as a supporting material, the first floor concrete is cast, and the slab after hardening of the cast concrete is slab A construction method for an underground structure, characterized in that the formwork is peeled off, the PC beam and the slab formwork on the lower floor are hung separately, and then the above steps are repeated to successively construct the PC beam and the slab on the basement floor.
JP62144039A 1987-06-11 1987-06-11 Construction method of underground structure Expired - Lifetime JPH0730564B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62144039A JPH0730564B2 (en) 1987-06-11 1987-06-11 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62144039A JPH0730564B2 (en) 1987-06-11 1987-06-11 Construction method of underground structure

Publications (2)

Publication Number Publication Date
JPS63312437A JPS63312437A (en) 1988-12-20
JPH0730564B2 true JPH0730564B2 (en) 1995-04-05

Family

ID=15352896

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62144039A Expired - Lifetime JPH0730564B2 (en) 1987-06-11 1987-06-11 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JPH0730564B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0788699B2 (en) * 1987-07-13 1995-09-27 株式会社竹中工務店 Body construction method
JPH07103583B2 (en) * 1991-03-20 1995-11-08 鹿島建設株式会社 Construction method for large span underground structure
JPH07324343A (en) * 1994-05-31 1995-12-12 Toda Constr Co Ltd Construction method for constructing underground skeleton
KR100799336B1 (en) 2006-06-23 2008-01-30 주식회사 하모니구조엔지니어링 Non supporting form system for down ward construction and non supporting down ward construction method using the same

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6010063A (en) * 1983-06-29 1985-01-19 株式会社間組 Construction of underground stair beam material

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6010063A (en) * 1983-06-29 1985-01-19 株式会社間組 Construction of underground stair beam material

Also Published As

Publication number Publication date
JPS63312437A (en) 1988-12-20

Similar Documents

Publication Publication Date Title
KR100694493B1 (en) Downward construction method capable of using bracket support type temporary structure as working table
JPH0730564B2 (en) Construction method of underground structure
JP5003253B2 (en) RC beam construction method
JP2897663B2 (en) How to build underground structures
JP3057466B2 (en) How to build underground structures
JP2002038475A (en) Construction method of caisson type pile
JPH0657710A (en) Construction of concrete main tower
JPS61109827A (en) Construction of basement
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam
JP6682173B1 (en) How to build a building
JPH0657769A (en) Underground concrete structure and working method thereof
JP3187618B2 (en) How to assemble beam reinforcement
JPH0730565B2 (en) Construction method of underground structure
JPH0470424A (en) Lift-down underground building body construction
JPH08177068A (en) Construction of underground structure
JPS6010063A (en) Construction of underground stair beam material
JPH07324343A (en) Construction method for constructing underground skeleton
JPH0978836A (en) Combined reinforcements for wall and beam and formation method of mold by use thereof
JP2023022563A (en) Concrete wall construction method
JPH0967824A (en) Double slab construction method
KR200369485Y1 (en) a deck supportframe
JP2508931B2 (en) Lift slab method
JPH1113141A (en) Constructing method of composite structure
JPH0381456A (en) Work scaffold in deep foundation method
JPH03287923A (en) Method for constructing underground story of building