JPS63312437A - Construction of underground structure - Google Patents
Construction of underground structureInfo
- Publication number
- JPS63312437A JPS63312437A JP62144039A JP14403987A JPS63312437A JP S63312437 A JPS63312437 A JP S63312437A JP 62144039 A JP62144039 A JP 62144039A JP 14403987 A JP14403987 A JP 14403987A JP S63312437 A JPS63312437 A JP S63312437A
- Authority
- JP
- Japan
- Prior art keywords
- underground
- beams
- floor
- stage
- root cutting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims description 22
- 238000000034 method Methods 0.000 claims description 10
- 238000009415 formwork Methods 0.000 description 11
- 239000000725 suspension Substances 0.000 description 5
- 238000009412 basement excavation Methods 0.000 description 2
- 238000005266 casting Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 206010039740 Screaming Diseases 0.000 description 1
- 229910000831 Steel Inorganic materials 0.000 description 1
- 210000000038 chest Anatomy 0.000 description 1
- 230000001934 delay Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Landscapes
- Foundations (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
(産業上の利用分野)
本発明は地下構造物の構築工法、特に逆打工法を採用す
る必要がある軟弱地盤、大規模、大深度の地下工事に適
用される地下構造物の構築工法に係るものである。[Detailed Description of the Invention] (Field of Industrial Application) The present invention is applicable to construction methods for underground structures, especially underground construction on soft ground, large scale, and deep underground that requires the adoption of the reverse construction method. This relates to construction methods for structures.
(従来の技術)
一般の地下構築物の構築工法においては、仮設土留壁に
仮設支保工を設け、仮設桟橋を設置して地下掘削を行っ
ている。(Prior Art) In the construction method of a general underground structure, temporary shoring is provided for a temporary earth retaining wall, a temporary pier is installed, and underground excavation is performed.
しかしながら、軟弱地盤における大規模、大深度の地下
掘削に関しては、従来の仮設一般山留工法では施工が困
難であり、安全性を確保するために全能逆打工法を採用
する場合が多く、従来の逆打工法では、地下部分各階躯
体工事については、七の都度、現場で型枠を組立て、鉄
筋を配筋し、コンクリートを打設し【いた。However, when it comes to large-scale, deep underground excavations in soft ground, it is difficult to carry out construction using the conventional temporary construction method, and in order to ensure safety, the omnipotent reverse method is often adopted. With the reverse casting method, formwork was assembled on-site, reinforcing bars were placed, and concrete was poured for each floor structure work in the underground section.
(発明が解決しようとする問題点)
このように前記従来の工法では、地下部分会躯体工事に
ついて、その都度、現場打型枠を組み立て、配筋、コン
クリート打設を行っているため、軟弱地盤よりの支持が
不安定であり、また上階コンクリートの強度が一定限以
上にならないと解体、及び下段根伐りができず、更にま
た解体型枠材を一旦上階に搬出、片付け、根伐り後、再
び下階に移動する等の作業が煩雑である。(Problems to be Solved by the Invention) As described above, in the conventional construction method, cast-on-site forms are assembled, reinforcement is arranged, and concrete is poured each time for underground sub-assembly construction work. The support of the upper floors is unstable, and unless the strength of the upper floor concrete exceeds a certain limit, demolition and root cutting of the lower level cannot be done, and furthermore, once the dismantled formwork materials have been carried to the upper floor, cleaned up, and the roots have been cut down. , the work of moving to the lower floor again is complicated.
その結果、逆打工事に非常に手間がかかり、工費が嵩み
、工程の遅れを招来している。As a result, reversing work is extremely time-consuming, increases construction costs, and causes delays in the process.
(問題点を解決するための手段)
本発明はこのような問題点を解決するために提案された
もので、地中に構築された垂直部材間に、第1次の根伐
りが完了したのち所要段数のPC梁を重合して下降自在
に懸吊し、同各PC梁を第1次の根伐り底まで吊り下ろ
し、最上部の第1段のPC梁を前記各垂直部材間に固定
して同各第1段のPC梁上に地上1階のスラブを施工し
、次いで第2次の根伐りを行ったのち、前記第2段以下
のPC梁を第2次の根伐り底まで吊り下ろし、第2段の
PC梁を前記各垂直部材間に固定して同第2段のPC梁
上に地下1階のスラブを施工し、以下前記同様の工程を
反覆することを特徴とする地下構造物の構築工法に係る
ものである。(Means for Solving the Problems) The present invention was proposed in order to solve the above problems. The required number of tiers of PC beams are overlapped and suspended so that they can descend freely, each of the same PC beams is lowered to the bottom of the first root cutting, and the first tier of PC beams at the top are fixed between each of the vertical members. The first floor slab was constructed on top of each of the first stage PC beams, and then the second root cutting was carried out, and the PC beams from the second stage onwards were suspended to the bottom of the second root cutting. lowering the second stage PC beam, fixing it between the respective vertical members, constructing a slab for the first basement floor on the second stage PC beam, and repeating the same process as described above. This relates to construction methods for structures.
(作 用)
本発明においては前記したように、地中に支持杭兼用の
外周連続地中壁や支持真柱等の如き垂直部材を構築した
のち、第1次の根伐りを行ない、前記各垂直部材間に、
地下階数に応じた段数のPC梁を重合して下降自在に懸
吊し、同各PC梁を重合状態のまま前記第1次の根伐り
底まで吊下ろし、重合状態にあるPC梁のうち最上部の
第1段のPC梁を前記各垂直部材に固定し、同第1段の
PC梁上にスラブ型枠を架設して地上1階のスラブコン
クリートを打設する。(Function) As described above, in the present invention, after constructing vertical members in the ground, such as an outer circumferential continuous underground wall that also serves as a support pile, a support pillar, etc., the first root cutting is performed, and each of the above-mentioned between the vertical members,
The number of PC beams corresponding to the number of underground floors are stacked and suspended so that they can descend freely, and each of the PC beams is suspended in a stacked state to the bottom of the first root cutting, and the highest of the stacked PC beams is suspended. The upper first-stage PC beam is fixed to each of the vertical members, a slab formwork is erected on the first-stage PC beam, and slab concrete for the first floor above ground is poured.
かくして地上1階のスラブの施工が完了したのち、第2
次の根伐りを行ない、前記第1段のPC梁以下に位置す
る第2段以下のPC梁を重合した状態で第2次の根伐り
底まで吊り下ろし、同重合状態にあるPC梁のうち最上
部に位置する第2段のPC梁を前記各垂直部材間に固定
したのち、同第2段のPC梁上に前記同様にし【地下1
階のスラブを施工し、以下前記同様の工程を必要階分、
反覆することによって、地下構造物を構築するものであ
る。After completing the construction of the first floor slab, the second floor
Perform the next root cutting, and suspend the PC beams of the second stage and below that are located below the first stage PC beam in a superimposed state to the bottom of the second root cutting, and among the PC beams in the same superposed state After fixing the second stage PC beam located at the top between each of the vertical members, do the same as above on the second stage PC beam [Underground 1
Construct the floor slab, and repeat the same process as above for the required floors.
By repeating the process, an underground structure is constructed.
(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.
地下構造物の外周に支持杭兼用の連続地中壁(1)を施
工するとともに、後述のPC梁を吊り下ろすための支持
真柱(2)を植立し第1次の根伐りを行なう。図中(3
)は第1次の根伐り底である。(第1図参照)
なお前記地中連続壁(1)には必要に応じて柱里及び梁
型な内蔵させる。また工期短縮のために地上躯体工事と
同時に地下階王手を行なう場合は、上部躯体支持用の耐
力のある支持真柱とする。更に前記根伐り底(3)には
地盤の硬軟によって作業用土間コンクリートを打設する
。Continuous underground walls (1) that also serve as support piles are constructed around the outer periphery of the underground structure, and support pillars (2) for suspending PC beams (described later) are erected and the first root cutting is performed. In the figure (3
) is the bottom of the first uprooting. (See Figure 1) The underground continuous wall (1) shall have pillar and beam-shaped built-in structures as necessary. In addition, if the basement floor construction is to be carried out at the same time as the above-ground structure work in order to shorten the construction period, strong support pillars will be used to support the upper structure. Furthermore, depending on the hardness or softness of the ground, concrete for working is placed at the bottom of the root cutting (3).
なお前記地中連続壁(1)及び支持真柱(2)が前述の
垂直部材を構成するものである。Note that the underground continuous wall (1) and the support pillar (2) constitute the above-mentioned vertical member.
次いで前記各垂直部材間において、根伐り底(3)上に
地下階数に応じた分だけのPC梁(4)を重合し、工事
用作業床(一般には1階の床梁)のPC梁(5)を支持
真柱(2)間に取付け、PC梁吊下ろし用の吊込架台(
6)を設置する。更に前記PC梁(5)に床付用の型枠
デツキ(力等を取付けてスラブコンクリートを打設する
。(第2図参照)な訃この際、適所に掘削用、躯体工事
用駄目穴を設けておく。Next, between each of the vertical members, PC beams (4) corresponding to the number of underground floors are superimposed on the cutting bottom (3), and the PC beams (4) of the construction work floor (generally the floor beam of the first floor) are superimposed on the root cutting bottom (3). 5) between the supporting pillars (2), and a suspension frame for hanging the PC beam (
6) Install. Furthermore, formwork decks for floor attachment (force etc. are attached to the PC beams (5) and slab concrete is cast. (See Figure 2) Set it up.
な訃型枠デツキ(7)は後述のように吊込架台(6)に
よって吊り下ろされるものである。The formwork deck (7) is suspended by a hanging frame (6) as described later.
第7図及び第8図は前記吊込架台(6)の詳細を示し、
前記1階のPC梁(5)が交叉する個所に、同各PC梁
(5)の軸線と45°の交角で交叉する方形枠状吊込枠
(@)の相隣る各辺間に、前記PG梁(5)上にこれと
直交して載架されるPC梁受材(60)が連結され、前
記吊込枠(6a)の相対する両辺間には同各辺と直交し
、且つ前記支持直往(2)を挟んで対向する一双の連結
片(6c)が連結され、同各連結片(60)間には更に
前記真柱(2)を挟む一双の連結片(メ)が連結され、
前記各連結片(6C) (6d)には前記真柱(2)に
沿って転勤するローラ(6e)が装着されている。FIG. 7 and FIG. 8 show details of the hanging frame (6),
At the point where the PC beams (5) on the first floor intersect, between each adjacent side of a rectangular frame-shaped hanging frame (@) that intersects the axis of each PC beam (5) at an angle of 45°, A PC beam support member (60) mounted perpendicularly on the PG beam (5) is connected, and between the opposite sides of the hanging frame (6a) there is a A pair of connecting pieces (6c) facing each other with the direct column (2) in between are connected, and a pair of connecting pieces (6c) sandwiching the true pillar (2) are further connected between each of the connecting pieces (60). ,
Each of the connecting pieces (6C) (6d) is equipped with a roller (6e) that moves along the true pillar (2).
また前記PC受梁材(6b)の両端部と前記吊込枠(6
a)との交叉部には、夫々前記各PC梁(4)の吊り下
ろし用PCストランド(pl)が貫挿され、同ストラン
ド(pl)は各PC梁(4)下端部に係止具(ql)を
介して係止される。また前記吊込枠(6a)の各辺中央
には型枠デツキ吊込用PCストランドω2〕が貫挿され
、型枠デツキ(力に係止具(g2)を介して係止されて
いる。In addition, both ends of the PC support beam material (6b) and the hanging frame (6b)
PC strands (pl) for hanging each of the PC beams (4) are inserted through the intersections with a), and the strands (pl) are attached to the lower end of each PC beam (4) with a locking tool ( ql). Further, a PC strand ω2 for hanging a formwork deck is inserted through the center of each side of the hanging frame (6a), and is locked to the formwork deck (force) via a locking tool (g2).
従って前記各ストランド■1)ω2)を操作することに
よって、前記PC梁(5)及び型枠デツキ(7)が吊り
下ろされるようになっている。Therefore, by operating each of the strands 1) and ω2), the PC beam (5) and formwork deck (7) are suspended.
図中(4a) (5a)は、前記各pc梁(4) (5
1に埋設され、前記真柱(2)の外周に突設されたブラ
ケツ) (2a)に接合されるように梁端部より突設さ
れた接続用鉄骨部、(40)は前記PC梁(4)に埋設
された肋筋の突出端部である。In the figure, (4a) and (5a) indicate the PC beams (4) and (5a).
(40) is a connecting steel frame part that is embedded in the PC beam (2a) and protrudes from the end of the beam so as to be connected to the bracket (2a) that is embedded in the PC beam (2a) and protrudes from the outer periphery of the PC beam (2a). This is the protruding end of the rib cage embedded in 4).
次いで前記吊込架台(6)によって前記第1次根伐り底
(3)上のPC梁(4)を、pcストランド(1)t)
を介して吊り上げ、第2次の根伐りを行なう。(8)は
同第2次の根伐り底である。(第3図参照)次いで前記
吊込架台(6)によって重合された下階用のPC梁(4
)を吊り下げ、同PC梁(4)中、最上部の地下1所用
PC梁(4A)を真柱(2)間、及び地中連続壁(1)
と真柱(2)との間に固定し、しかるのち前記吊込架台
(6)によって地下1階用のスラブ型枠デツキ(7A)
を地下1所用PC梁(4)上に吊り下げる。(第4図参
照)
次いで地下1階のスラブコンクリート(9)を打設し、
第3次根伐りを行なう。図中11αは第3次根伐り底で
ある。次いで吊込架台(6)によって第2段以下のPC
梁(4)を吊り下ろし、第2段の地下2階用pc梁(4
B)を真柱(2)間地中連続壁(1)と真柱(2)との
間に固定し、しかるのち前記吊込架台(6)によって地
下2階用スラブ型枠デツキ(7B)を前記PC梁(4B
)上に吊下げ、(第5図参照)地下2階のスラブコンク
’) −) (9)を打設し、以下前記同様の工程を地
下必要階分反覆し、第6図に示すように最終根伐りを行
ない、同最終根伐り底圓上に基礎コンクリートa’tを
打設したのち、後打柱部体a9工事及び打継処理を行な
って、全工程を完了する。Next, the PC beam (4) on the first root cutting bottom (3) is connected to the PC strand (1) by the suspension frame (6).
The tree is then hoisted up through the pipe and a second round of root cutting is carried out. (8) is the bottom of the second round of root cutting. (See Figure 3) Next, the lower floor PC beam (4) is superimposed by the suspension frame (6).
), and hang the PC beam (4A) at the top of the same PC beam (4) for one underground place between the true pillars (2) and the underground continuous wall (1).
and the true pillar (2), and then the slab formwork deck (7A) for the first basement floor is fixed using the hanging frame (6).
Suspend it on the PC beam (4) for one underground location. (See Figure 4) Next, concrete slab (9) for the first basement floor was poured.
The third round of root cutting will be carried out. In the figure, 11α is the bottom of the third cutting. Next, the PCs on the second stage and below are mounted on the suspension stand (6).
Suspend the beam (4) and attach it to the PC beam (4) for the second basement floor.
B) is fixed between the true pillar (2), the underground continuous wall (1) and the true pillar (2), and then the slab formwork deck for the second underground floor (7B) is installed using the suspension frame (6). The PC beam (4B
) above (see Figure 5), and pour the slab concrete ') -) (9) on the second basement floor, and repeat the same process as above for the required basement floors, and as shown in Figure 6, the final After cutting the roots and pouring the foundation concrete a't on the bottom circle of the final root cutting, the post-casting column body a9 construction and splicing treatment are performed to complete the entire process.
(発明の効果)
このように本発明によれば地中に垂直部材を構築し、同
各部材間において、所要段数のPC梁を重合して下降自
在に懸吊し、根伐りの進行に伴って前記所要段数のPC
梁を吊り下げ、上段より順次地下1階、地下2階丁・・
・・・部分において前記垂直部材間に固定するとともに
、地下各階のPC梁上に順次地下階スラブを施工するこ
とによって、地下工事を標準化された20部材によって
合理的に遂行し、現場作業を簡略化するとともに、作業
の安全性を向上し、地下工事の合理化とともに地上工事
も同時作業が可能となり、工期を縮減し、工費を節減し
うるものである。(Effects of the Invention) As described above, according to the present invention, vertical members are constructed in the ground, and a required number of PC beams are overlapped and suspended in a descending manner between the members, and as the root cutting progresses, the vertical members are constructed underground. PC of the above required number of stages
The beams are suspended, and from the top, the first basement floor, the second basement floor...
By fixing between the vertical members at the sections and sequentially constructing the basement floor slabs on the PC beams on each basement floor, underground construction can be carried out rationally using 20 standardized members, simplifying on-site work. This will improve work safety, streamline underground work, and allow above-ground work to be done simultaneously, shortening construction time and reducing construction costs.
第1図乃至第6図は本発明に係る地下構造物の構築工法
の一実施例の工程を示す縦断面図、第7図及び第8図は
夫々吊込架台の平面図釜に縦断面図である。
(1)・・・地中連続壁、(2)・・・支持真柱、(3
)・・・第1次根伐り底、(4)・・・PC梁、(5)
・・・工事用作業床のPC梁、(6)・・・吊込架台、
(7)・・・型枠デツキ、(8)・・・第2次根伐り底
、(9)・・・地下1階のスラブコンクリート、(6)
・・・地下2階のスラブコンクリート、叫・・・第3次
根伐り底。Figures 1 to 6 are longitudinal cross-sectional views showing the steps of an embodiment of the method for constructing an underground structure according to the present invention, and Figures 7 and 8 are a plan view of a hanging frame and a longitudinal cross-sectional view of the kettle. It is. (1)...Underground continuous wall, (2)...Support pillar, (3
)...First cutting bottom, (4)...PC beam, (5)
... PC beam for construction work floor, (6) ... hanging frame,
(7)...Formwork deck, (8)...Second root cutting bottom, (9)...Slab concrete for the first basement floor, (6)
...Slab concrete on the second basement floor, screaming...The bottom of the third round of root cutting.
Claims (1)
したのちに所要段数のPC梁を重合して下降自在に懸吊
し、同各PC梁を第1次の根伐り底まで吊り下ろし、最
上部の第1段のPC梁を前記各垂直部材間に固定して同
各第1段のPC梁上に地上1階のスラブを施工し、次い
で第2次の根伐りを行つたのち、前記第2段以下のPC
梁を第2次の根伐り底まで吊り下ろし、第2段のPC梁
を前記各垂直部材間に固定して同第2段のPC梁上に地
下1階のスラブを施工し、以下前記同様の工程を反覆す
ることを特徴とする地下構造物の構築工法。After the first root cutting is completed, the required number of PC beams are overlapped and suspended freely between the vertical members constructed underground, and each PC beam is placed at the bottom of the first root cutting. The first stage of PC beams at the top were fixed between the vertical members, and the first floor slab was constructed on top of each of the first stage PC beams, and then the second stage of root cutting was carried out. After that, the PC of the second stage and below
The beam is suspended to the bottom of the second root cutting, the second stage PC beam is fixed between each of the vertical members, and the slab for the first basement floor is constructed on the second stage PC beam, and the following is the same as above. A construction method for underground structures characterized by repeating the process of
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62144039A JPH0730564B2 (en) | 1987-06-11 | 1987-06-11 | Construction method of underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP62144039A JPH0730564B2 (en) | 1987-06-11 | 1987-06-11 | Construction method of underground structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS63312437A true JPS63312437A (en) | 1988-12-20 |
JPH0730564B2 JPH0730564B2 (en) | 1995-04-05 |
Family
ID=15352896
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP62144039A Expired - Lifetime JPH0730564B2 (en) | 1987-06-11 | 1987-06-11 | Construction method of underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0730564B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6417941A (en) * | 1987-07-13 | 1989-01-20 | Takenaka Komuten Co | Body constructing method |
JPH04293824A (en) * | 1991-03-20 | 1992-10-19 | Kajima Corp | Construction method for large span underground structure |
JPH07324343A (en) * | 1994-05-31 | 1995-12-12 | Toda Constr Co Ltd | Construction method for constructing underground skeleton |
KR100799336B1 (en) | 2006-06-23 | 2008-01-30 | 주식회사 하모니구조엔지니어링 | Non supporting form system for down ward construction and non supporting down ward construction method using the same |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6010063A (en) * | 1983-06-29 | 1985-01-19 | 株式会社間組 | Construction of underground stair beam material |
-
1987
- 1987-06-11 JP JP62144039A patent/JPH0730564B2/en not_active Expired - Lifetime
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6010063A (en) * | 1983-06-29 | 1985-01-19 | 株式会社間組 | Construction of underground stair beam material |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6417941A (en) * | 1987-07-13 | 1989-01-20 | Takenaka Komuten Co | Body constructing method |
JPH04293824A (en) * | 1991-03-20 | 1992-10-19 | Kajima Corp | Construction method for large span underground structure |
JPH07324343A (en) * | 1994-05-31 | 1995-12-12 | Toda Constr Co Ltd | Construction method for constructing underground skeleton |
KR100799336B1 (en) | 2006-06-23 | 2008-01-30 | 주식회사 하모니구조엔지니어링 | Non supporting form system for down ward construction and non supporting down ward construction method using the same |
Also Published As
Publication number | Publication date |
---|---|
JPH0730564B2 (en) | 1995-04-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100694493B1 (en) | Downward construction method capable of using bracket support type temporary structure as working table | |
JPS63312437A (en) | Construction of underground structure | |
JP3057466B2 (en) | How to build underground structures | |
JPH0684690B2 (en) | Building basement extension method | |
JPS61109827A (en) | Construction of basement | |
JP2736542B2 (en) | Construction method of underground structure omitting temporary materials | |
JPH11140892A (en) | Method for excavating ground and method for constructing underground structure using the same | |
JPH0673783A (en) | Construction of steel framed reinforced concrete column and steel beam | |
JP6682173B1 (en) | How to build a building | |
JPH08165662A (en) | Construction method of underground structure | |
JP2002038475A (en) | Construction method of caisson type pile | |
JP3187618B2 (en) | How to assemble beam reinforcement | |
JP2772397B2 (en) | Underground building construction method | |
JPS63312438A (en) | Construction of underground structure | |
KR200369485Y1 (en) | a deck supportframe | |
JPH0657769A (en) | Underground concrete structure and working method thereof | |
JPH10237886A (en) | Method for constructing underground tank | |
JPS6217233A (en) | Foundation base column | |
JPS63277342A (en) | Reverse execution of underground story | |
JPH0978836A (en) | Combined reinforcements for wall and beam and formation method of mold by use thereof | |
JPH03147926A (en) | construction method for basement | |
KR200167833Y1 (en) | Hanging semi down up system | |
JPH03132521A (en) | Strut construction method of basement floor excavation work | |
JPH1113141A (en) | Constructing method of composite structure | |
JPS63312439A (en) | Underground construction method |