JPH1113141A - Constructing method of composite structure - Google Patents

Constructing method of composite structure

Info

Publication number
JPH1113141A
JPH1113141A JP16850397A JP16850397A JPH1113141A JP H1113141 A JPH1113141 A JP H1113141A JP 16850397 A JP16850397 A JP 16850397A JP 16850397 A JP16850397 A JP 16850397A JP H1113141 A JPH1113141 A JP H1113141A
Authority
JP
Japan
Prior art keywords
beams
steel
reinforced
column
temporary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP16850397A
Other languages
Japanese (ja)
Inventor
Hisanori Okura
久典 大倉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP16850397A priority Critical patent/JPH1113141A/en
Publication of JPH1113141A publication Critical patent/JPH1113141A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve workability by projecting a column steel frame, to which a reinforced beam in the inter-beam direction is built, in specified length from height, in which a beam in the girder direction is disposed, supporting a temporary beam at the upper ends of both column steel frames and constructing the reinforced beam under a suspended state. SOLUTION: In a composite structure 15, in which beams in the girder direction are formed in steel-framed beams 12 or steel-framed reinforced beams and a beam in the inter-beam direction 13 is formed in a reinforced beam 14, coin steel frames 16 are disposed in upright while the column steel frames 16 are projected in specified length from height, in which the steel-framed beams 12 in the girder direction are arranged. A temporary beam 17, from which the beforehand assembled reinforced beam 14 in the inter-beam direction 13 are hung down, is hung up and placed at the upper ends of both column steel frames 16 projected in specified length by a crane, and the reinforced beam 14 is built at a fixed place. Hanging jigs 18 supported to the temporary beam 17 consist of angle materials 19 installed to the temporary beam 17 and hang bolts 20 mounted at both ends of the angle material 19, and the upper end reinforcement of the reinforced beam 14 is supported. Accordingly, the erection works and removing works of supports need not be conducted, and workability and safety can be improved.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、桁行方向の梁が鉄
骨構造又は鉄骨鉄筋構造であり、梁間方向の梁が鉄筋構
造である複合構造物の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a composite structure in which a beam in a row direction has a steel structure or a steel frame structure, and a beam in a direction between beams has a steel structure.

【0002】[0002]

【従来の技術】従来、図10に示すように、桁行方向1
が鉄骨梁又は鉄骨鉄筋梁2で梁間方向3が鉄筋梁4であ
り、これらの梁が柱鉄骨5等に架設される複合構造物に
おいて、梁間方向3の鉄筋梁4は、梁型枠の組立が完了
するまで、鉄筋梁4の自重による撓み変形を防ぐために
該梁を支持する支保工が必要である。
2. Description of the Related Art Conventionally, as shown in FIG.
Is a steel beam or a steel reinforced beam 2 and the inter-beam direction 3 is a reinforced beam 4. In a composite structure in which these beams are erected on a column steel frame 5 or the like, the reinforced beam 4 in the inter-beam direction 3 is assembled with a beam formwork. Until the completion of the work, it is necessary to provide a supporting structure for supporting the rebar beam 4 in order to prevent the beam from being deformed by its own weight.

【0003】即ち、前記のような複合構造物において梁
間方向3の鉄筋梁4は、図11に示すように、アングル
等で形成した支柱6をコンクリート床面7の上に複数本
立設させて、この支柱6の上端に設けた支持アーム8で
鉄筋梁4の上端筋4aを支持する方法が取られている。
尚、図中符号9は、型枠を示す。
[0003] That is, in the composite structure as described above, as shown in FIG. 11, a plurality of pillars 6 formed by angles or the like are erected on a concrete floor surface 7 of the reinforcing beam 4 in the beam direction 3 by The upper arm 4a of the reinforcing bar 4 is supported by a support arm 8 provided at the upper end of the support column 6.
In addition, the code | symbol 9 in a figure shows a mold.

【0004】[0004]

【発明が解決しようとする課題】この従来例の方法にお
いては、支柱6の立設作業及び取り外し作業が煩雑であ
り、作業性が悪いという問題点を有していた。
However, the conventional method has a problem that the work for erecting and removing the support column 6 is complicated, and the workability is poor.

【0005】また、支柱6の立設状態が不安定であり、
安全性に欠けるという問題点もあった。
In addition, the standing condition of the column 6 is unstable,
There was also a problem of lack of safety.

【0006】更に、壁配筋した後コンクリート打設時
に、支柱6の取り外しができないので、そのまま壁筋と
一緒に埋め込むこととなり、コストが上昇するという欠
点も有していた。
[0006] Furthermore, since the pillar 6 cannot be removed at the time of concrete placement after wall arrangement, it has to be buried together with the wall reinforcement as it is, resulting in an increase in cost.

【0007】従って、従来例の方法においては、梁間方
向3における鉄筋梁4の架設を簡単に行い作業性を向上
させることと、安全性を向上させること、及び支柱6を
壁筋と一緒に埋め込んでしまう不都合を解消することに
解決しなければならない課題を有している。
Therefore, in the method of the prior art, the workability is improved by easily laying the reinforced beams 4 in the inter-beam direction 3, the safety is improved, and the columns 6 are embedded together with the wall bars. There is a problem that needs to be solved in order to solve the inconvenience.

【0008】[0008]

【課題を解決するための手段】前記従来例の課題を解決
する具体的手段として本発明は、桁行方向の梁が鉄骨構
造又は鉄骨鉄筋構造であり、梁間方向の梁が鉄筋構造で
ある複合構造物において、前記梁間方向の鉄筋梁が架設
される両端位置の柱鉄骨を前記桁行方向の梁が配設され
る高さよりも所定長さ突出させて形成し、該突出させた
両柱鉄骨の各々の上端に、予め先組した梁間方向の鉄筋
梁を垂下させた所定長さの仮梁を支持させ、垂下状態に
ある鉄筋梁を所定位置に架設することを特徴とする複合
構造物の構築方法を提供するものである。
As a specific means for solving the problems of the prior art, the present invention relates to a composite structure in which the beam in the row direction is a steel structure or a steel frame structure, and the beam in the direction between the beams is a steel structure. In the object, the column-shaped steel columns at both ends where the reinforcing beams in the inter-beam direction are erected are formed by projecting a predetermined length from the height at which the beams in the girder direction are provided, and each of the projecting double-column steel frames is formed. A method of constructing a composite structure, comprising: supporting a temporary beam of a predetermined length in which a pre-assembled inter-beam direction reinforcing steel beam is suspended at an upper end of the prefabricated beam; and suspending the suspended reinforcing steel beam at a predetermined position. Is provided.

【0009】また、前記梁間方向の鉄筋梁は、前記仮梁
に支持させた吊り治具を介して垂下させたものである。
Further, the reinforcing beam in the direction between the beams is suspended via a suspending jig supported by the temporary beam.

【0010】[0010]

【発明の実施の形態】次に、本発明を実施する一例につ
いて図面を参照しながら説明する。本発明は図1に示す
ように、桁行方向11の梁が鉄骨梁12又は鉄骨鉄筋梁
であり、梁間方向13の梁が鉄筋梁14である複合構造
物15において、前記梁間方向13の鉄筋梁14を柱鉄
骨16間の所定位置に架設する構築方法である。
Next, an embodiment of the present invention will be described with reference to the drawings. As shown in FIG. 1, the present invention relates to a composite structure 15 in which the beam in the beam direction 11 is a steel beam 12 or a steel reinforced beam and the beam in the interbeam direction 13 is a reinforced beam 14, This is a construction method in which the bridge 14 is installed at a predetermined position between the column steel frames 16.

【0011】まず、図1及び図2に示すように、柱設置
位置に複数本の柱鉄骨16を所定の方法で立設させる。
この場合、柱鉄骨16は、前記桁行方向11の鉄骨梁1
2が配設される高さよりも所定の長さ突出させて形成し
ておく。
First, as shown in FIGS. 1 and 2, a plurality of column steel frames 16 are erected at a column installation position by a predetermined method.
In this case, the column steel frame 16 is connected to the steel beam 1 in the row direction 11.
2 is formed so as to protrude by a predetermined length from the height at which it is disposed.

【0012】柱鉄骨16の上端16aは、図3に示すよ
うに、後述する仮梁17を安定した状態で支持できるよ
うに、例えばバネ式の位置決め用治具16bを予め取り
付けておくことが望ましい。尚、位置決め用治具16b
の替わりにキャッチクランプを用いても良いことは勿論
である。
As shown in FIG. 3, for example, a spring-type positioning jig 16b is desirably attached to the upper end 16a of the column steel frame 16 so that a temporary beam 17 described later can be supported in a stable state. . The positioning jig 16b
Of course, a catch clamp may be used in place of the above.

【0013】次に、所定の長さ突出させた両柱鉄骨16
の各々の上端16aに、予め先組した梁間方向13の鉄
筋梁14を垂下させた仮梁17をクレーン等で吊り上げ
て載置し、この垂下状態にある鉄筋梁14を所定の位置
に架設する。
Next, the steel columns 16 projecting a predetermined length are used.
On each upper end 16a, a temporary beam 17 in which a pre-assembled reinforcing beam 14 in the interbeam direction 13 is suspended is lifted by a crane or the like and placed, and the suspended reinforcing beam 14 is erected at a predetermined position. .

【0014】前記鉄筋梁14の垂下は、図4に示すよう
に、前記仮梁17に支持させた吊り治具18を介して垂
下させる。
As shown in FIG. 4, the rebar beam 14 is suspended via a suspending jig 18 supported by the temporary beam 17.

【0015】吊り治具18は、仮梁17の適宜の位置に
取り付けたアングル材19と、このアングル材19の両
端に設けた吊りボルト20と、両吊りボルト20の下部
に取り付けたアングル材21とからなり、このアングル
材21で鉄筋梁14の上端筋14aを支持すればよい。
The suspension jig 18 includes an angle member 19 attached to an appropriate position of the temporary beam 17, suspension bolts 20 provided at both ends of the angle member 19, and an angle member 21 attached to a lower portion of both suspension bolts 20. The upper end bar 14a of the reinforcing bar 14 may be supported by the angle member 21.

【0016】この時、吊りボルト20の長さは、鉄筋梁
14が所定の位置に架設できるように予め調整しておく
必要がある。尚、図4中の符号22は、ターンバックル
を示し、符号23は、鉄筋梁14のスターラップを示
す。
At this time, the length of the suspension bolt 20 must be adjusted in advance so that the reinforcing beam 14 can be installed at a predetermined position. In addition, the code | symbol 22 in FIG. 4 shows a turnbuckle, and the code | symbol 23 shows the stirrup of the rebar beam 14. FIG.

【0017】以上のように鉄筋梁14を架設することに
よって、梁間方向13の鉄筋梁14を支持するための支
柱を不要にすることができるのである。また、壁が梁に
配設される場合には、支柱を埋め込むことがないので経
済的である。
By arranging the reinforcing bars 14 as described above, it is possible to eliminate the need for supporting columns for supporting the reinforcing bars 14 in the inter-beam direction 13. In addition, when the wall is provided on the beam, it is economical because there is no need to embed the pillar.

【0018】次に、以上に説明した複合構造物の構築方
法の具体的な組み立て方について説明する。まず、図5
に示すように、地組ヤード24において桁行方向11の
鉄骨鉄筋梁25と、該鉄骨鉄筋梁25を架設する柱鉄骨
16とを予め陸組しておく。この時、前述のように、柱
鉄骨16の上端16aは、鉄骨鉄筋梁25よりも所定の
長さ突出させて形成しておく。尚、図5中符号26は、
地組用の足場を示す。
Next, a specific method of assembling the above-described method for constructing a composite structure will be described. First, FIG.
As shown in (1), the steel reinforced beams 25 in the girder direction 11 and the column steel frames 16 on which the steel reinforced beams 25 are erected are laid in advance in the ground yard 24. At this time, as described above, the upper end 16a of the column steel frame 16 is formed so as to protrude by a predetermined length from the steel frame beam 25. Incidentally, reference numeral 26 in FIG.
Show scaffolds for terrain.

【0019】また、図6に示すように、別の地組ヤード
27においては、枠組足場28を利用して梁間方向13
の鉄筋梁14を予め陸組しておく。
Further, as shown in FIG. 6, in another ground yard 27, the frame-to-beam direction 13 is
Reinforced beams 14 are laid in advance in advance.

【0020】そして、図7に示すように、所定のコンク
リートスラブ29形成後に、前記予め陸組した柱鉄骨1
6及び鉄骨鉄筋梁25をクレーン等で吊り上げて、柱鉄
骨16をコンクリートスラブ29に予め突出形成してお
いた柱鉄骨30に連結する。
Then, as shown in FIG. 7, after the formation of the predetermined concrete slab 29, the pre-landed column steel frame 1 is formed.
6 and the steel reinforced beam 25 are lifted by a crane or the like, and the column steel frame 16 is connected to the column steel frame 30 that has been formed in the concrete slab 29 in advance.

【0021】更に、柱鉄骨16の建入れ確認後に、所定
の連結部材31を本締めして柱鉄骨30と柱鉄骨16と
を強固に連結させる。尚、図7中符号32は、柱主筋を
示し、符号33は、柱帯筋を示す。
Further, after confirming the installation of the column steel frame 16, the predetermined connecting member 31 is fully tightened to firmly connect the column steel frame 30 and the column steel frame 16. In addition, the code | symbol 32 in FIG. 7 shows the pillar main bar, and the code | symbol 33 shows a columnar bar | burr.

【0022】前記のように桁行方向11の鉄骨鉄筋梁2
5と柱鉄骨16とを構築した後に、図8に示すように、
前記地組ヤード27で陸組した鉄筋梁14と、該鉄筋梁
14を垂下する仮梁17とをクレーン等で吊り上げて、
対向する柱鉄骨16、16の上端16a、16aに前記
仮梁17の両端を各々載置し、鉄筋梁14を所定の位置
に架設する。
As described above, the steel reinforced beam 2 in the row direction 11
After constructing 5 and column steel frame 16, as shown in FIG.
The reinforced beams 14 laid in the ground yard 27 and the temporary beams 17 hanging down the reinforced beams 14 are lifted by a crane or the like,
Both ends of the temporary beam 17 are placed on the upper ends 16a, 16a of the opposing columnar steel frames 16, 16, respectively, and the reinforcing beam 14 is erected at a predetermined position.

【0023】その後、図9に示すように、柱鉄骨16、
30に柱主筋32を配筋すると共に圧接を行う。更に、
鉄筋梁14及び鉄骨鉄筋梁25等に型枠を建て込み、P
Cスラブ、バルコニー、PC廊下を配設し、スラブ配筋
を行い、コンクリートを打設する。以上に説明した工程
を繰り返して行うことにより、複数階の複合構造物を構
築するものである。
Thereafter, as shown in FIG.
The column main reinforcement 32 is arranged at 30 and is pressed. Furthermore,
The formwork is erected on the reinforced beams 14 and the steel reinforced beams 25 and the like.
C slabs, balconies, PC corridors will be laid, slabs will be laid, and concrete will be cast. By repeating the steps described above, a multi-story composite structure is constructed.

【0024】[0024]

【発明の効果】以上説明したように本発明に係る複合構
造物の構築方法は、桁行方向の梁が鉄骨構造又は鉄骨鉄
筋構造であり、梁間方向の梁が鉄筋構造である複合構造
物において、前記梁間方向の鉄筋梁が架設される両端位
置の柱鉄骨を前記桁行方向の梁が配設される高さよりも
所定長さ突出させて形成し、該突出させた両柱鉄骨の各
々の上端に、予め先組した梁間方向の鉄筋梁を垂下させ
た所定長さの仮梁を支持させ、垂下状態にある鉄筋梁を
所定位置に架設することによって、従来例のように、梁
間方向の鉄筋梁を支持するための支柱が必要ないので、
支柱の立設作業及び取り外し作業を行う必要がなく、作
業性及び安全性が向上するという優れた効果を奏する。
As described above, the method for constructing a composite structure according to the present invention is directed to a composite structure in which the beams in the beam direction are steel structures or steel frame structures, and the beams in the direction between beams are steel structures. The column steel members at both ends where the reinforcing beams in the inter-beam direction are erected are formed by projecting a predetermined length from the height at which the beams in the girder direction are provided, and formed at the upper end of each of the protruding steel columns. By supporting a temporary beam of a predetermined length in which a pre-assembled reinforcing beam in the inter-beam direction is suspended, and reinforcing the suspended reinforcing beam at a predetermined position, a reinforcing beam in the inter-beam direction is provided as in the conventional example. Since there is no need for a support to support
There is no need to perform the work of erecting and removing the columns, and an excellent effect that workability and safety are improved is achieved.

【0025】また、吊り治具は、各階において再使用が
可能であり、作業コストの低減を図ることができるとい
う優れた効果を奏する。
Further, the hanging jig has an excellent effect that it can be reused on each floor and the working cost can be reduced.

【0026】更に、梁間方向の鉄筋梁は、前記仮梁に支
持させた吊り治具を介して垂下させたことによって、鉄
筋梁の垂下状態が安定するという優れた効果を奏する。
Further, since the reinforcing steel beams in the direction between the beams are suspended through the suspending jigs supported by the temporary beams, an excellent effect that the hanging state of the reinforcing steel beams is stabilized is exhibited.

【図面の簡単な説明】[Brief description of the drawings]

【図1】複合構造物の平面図である。FIG. 1 is a plan view of a composite structure.

【図2】梁間方向の鉄筋梁及び柱鉄骨を示す正面図であ
る。
FIG. 2 is a front view showing a reinforcing steel beam and a column steel frame in a direction between beams.

【図3】柱鉄骨の上端を示す斜視図である。FIG. 3 is a perspective view showing an upper end of a column steel frame.

【図4】図2のA−A線断面図である。FIG. 4 is a sectional view taken along line AA of FIG. 2;

【図5】桁行方向の鉄骨鉄筋梁と柱鉄骨とを予め陸組す
る状態を示す説明図である。
FIG. 5 is an explanatory view showing a state in which a steel reinforced beam in the girder direction and a column steel frame are preliminarily laid.

【図6】梁間方向の鉄筋梁を予め陸組する状態を示す説
明図である。
FIG. 6 is an explanatory diagram showing a state in which reinforcing beams in the direction between beams are laid in advance on a land.

【図7】柱鉄骨及び鉄骨鉄筋梁の構築状態を示す説明図
である。
FIG. 7 is an explanatory diagram showing a construction state of a column steel frame and a steel reinforced beam.

【図8】仮梁を柱鉄骨に載置して鉄筋梁を架設した状態
を示す説明図である。
FIG. 8 is an explanatory view showing a state in which a temporary beam is placed on a column steel frame and a reinforced beam is erected.

【図9】柱鉄骨に柱主筋を配筋した状態を示す説明図で
ある。
FIG. 9 is an explanatory view showing a state where a column main bar is arranged on a column steel frame.

【図10】従来例に係る複合構造物において桁行方向及
び梁間方向の梁を示す平面図である。
FIG. 10 is a plan view showing beams in a row direction and an inter-beam direction in a composite structure according to a conventional example.

【図11】従来例に係る複合構造物において梁間方向の
鉄筋梁の支持方法を示す断面図である。
FIG. 11 is a cross-sectional view showing a method of supporting a reinforcing beam in a direction between beams in a composite structure according to a conventional example.

【符号の説明】[Explanation of symbols]

1 桁行方向 2 鉄骨梁又は鉄骨鉄筋梁 3 梁間方向 4 鉄筋梁 4a 上端筋 5 柱鉄骨 6 支柱 7 コンクリート床面 8 支持アーム 9 型枠 11 桁行方向 12 鉄骨梁 13 梁間方向 14 鉄筋梁 14a上端筋 15 複合構造物 16 柱鉄骨 16a上端 16b位置決め用治具 17 仮梁 18 吊り治具 19 アングル材 20 吊りボルト 21 アングル材 22 ターンバックル 23 スターラップ 24 地組ヤード 25 鉄骨鉄筋梁 26 地組用の足場 27 地組ヤード 28 枠組足場 29 コンクリートスラブ 30 柱鉄骨 31 連結部材 32 柱主筋 33 柱帯筋 DESCRIPTION OF SYMBOLS 1 Girder direction 2 Steel beam or steel reinforced beam 3 Beam direction 4 Reinforced beam 4a Top reinforcement 5 Column steel 6 Support 7 Concrete floor 8 Support arm 9 Formwork 11 Girder direction 12 Steel beam 13 Beam direction 14 Reinforcement beam 14a top reinforcement 15 Composite structure 16 Column steel frame 16a Upper end 16b Positioning jig 17 Temporary beam 18 Hanging jig 19 Angle material 20 Hanging bolt 21 Angle material 22 Turnbuckle 23 Stirrup 24 Soil yard 25 Steel reinforced beam 26 Scaffolding for groundwork 27 Ground yard 28 Frame scaffolding 29 Concrete slab 30 Column steel 31 Connecting member 32 Column main bar 33 Column band bar

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 桁行方向の梁が鉄骨構造又は鉄骨鉄筋構
造であり、梁間方向の梁が鉄筋構造である複合構造物に
おいて、前記梁間方向の鉄筋梁が架設される両端位置の
柱鉄骨を前記桁行方向の梁が配設される高さよりも所定
長さ突出させて形成し、該突出させた両柱鉄骨の各々の
上端に、予め先組した梁間方向の鉄筋梁を垂下させた所
定長さの仮梁を支持させ、垂下状態にある鉄筋梁を所定
位置に架設することを特徴とする複合構造物の構築方
法。
1. A composite structure in which beams in the girder direction have a steel structure or a steel reinforced structure, and beams in the direction between beams have a reinforced structure. A beam of a predetermined length is formed by projecting a predetermined length from the height at which the beams in the girder direction are provided, and a pre-assembled inter-beam direction reinforcing steel beam is suspended at the upper end of each of the projecting steel columns. A method of constructing a composite structure, comprising: supporting a temporary beam of the above (1), and erected a reinforcing steel beam at a predetermined position.
【請求項2】 梁間方向の鉄筋梁は、前記仮梁に支持さ
せた吊り治具を介して垂下させたことを特徴とする請求
項1に記載の複合構造物の構築方法。
2. The method for constructing a composite structure according to claim 1, wherein the reinforcing beam in the direction between the beams is suspended via a suspending jig supported by the temporary beam.
JP16850397A 1997-06-25 1997-06-25 Constructing method of composite structure Pending JPH1113141A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16850397A JPH1113141A (en) 1997-06-25 1997-06-25 Constructing method of composite structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16850397A JPH1113141A (en) 1997-06-25 1997-06-25 Constructing method of composite structure

Publications (1)

Publication Number Publication Date
JPH1113141A true JPH1113141A (en) 1999-01-19

Family

ID=15869281

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16850397A Pending JPH1113141A (en) 1997-06-25 1997-06-25 Constructing method of composite structure

Country Status (1)

Country Link
JP (1) JPH1113141A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105432481A (en) * 2015-12-05 2016-03-30 余平 Quick animal house mounting method
CN109281395A (en) * 2018-08-20 2019-01-29 中民筑友科技投资有限公司 A kind of assembly method of assembly concrete truss building

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105432481A (en) * 2015-12-05 2016-03-30 余平 Quick animal house mounting method
CN109281395A (en) * 2018-08-20 2019-01-29 中民筑友科技投资有限公司 A kind of assembly method of assembly concrete truss building

Similar Documents

Publication Publication Date Title
AU2022204488A1 (en) Methods and apparatus for constructing multi-storey buildings
KR102269141B1 (en) Deck plate wall installation method using underground pavement
KR200383309Y1 (en) Form system for construction of underground slab
KR102296982B1 (en) Transfer Structure Construction Method Using U-shaped Steel Girder
JPH1113141A (en) Constructing method of composite structure
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JP2000160687A (en) Construction method for composite structure and precast concrete column
JP3408629B2 (en) Precast concrete foundation structure
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
JPH0988348A (en) Method for constructing foundation beam
KR102585526B1 (en) Composite frame with end-buried girder joint
JP3187618B2 (en) How to assemble beam reinforcement
JP2759361B2 (en) Pillar support members for building reinforced concrete buildings
JPH0881918A (en) Pipe and construction method thereof
JP3281421B2 (en) Construction method of horizontal beam erected on tower
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JP2959436B2 (en) How to build underground structures
JP2759131B2 (en) Foundation beam construction method for steel reinforced concrete columns
JP2759360B2 (en) Construction method of reinforced concrete building
JPS638260B2 (en)
JP2804219B2 (en) Reinforced steel pipe unit and building construction method using the same
JP2724891B2 (en) Construction method of pillar half PCa formwork
JPH0692669B2 (en) Frame method using shaped steel for beam with rebar concrete structure
JPH06287998A (en) Constructing method for preliminary assembling of reinforced concrete composite beam