JP2759131B2 - Foundation beam construction method for steel reinforced concrete columns - Google Patents
Foundation beam construction method for steel reinforced concrete columnsInfo
- Publication number
- JP2759131B2 JP2759131B2 JP34429089A JP34429089A JP2759131B2 JP 2759131 B2 JP2759131 B2 JP 2759131B2 JP 34429089 A JP34429089 A JP 34429089A JP 34429089 A JP34429089 A JP 34429089A JP 2759131 B2 JP2759131 B2 JP 2759131B2
- Authority
- JP
- Japan
- Prior art keywords
- foundation beam
- foundation
- main
- reinforcement
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims description 24
- 239000010959 steel Substances 0.000 title claims description 24
- 239000011150 reinforced concrete Substances 0.000 title claims description 6
- 238000010276 construction Methods 0.000 title description 18
- 230000002787 reinforcement Effects 0.000 claims description 14
- 239000004567 concrete Substances 0.000 claims description 10
- 230000003014 reinforcing effect Effects 0.000 description 10
- 238000000034 method Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 3
- 238000009434 installation Methods 0.000 description 2
- 230000009897 systematic effect Effects 0.000 description 2
- 241000282376 Panthera tigris Species 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009415 formwork Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Foundations (AREA)
Description
【発明の詳細な説明】 産業上の利用分野 この発明は、建築の基礎構造部分、特に鉄骨鉄筋コン
クリート造(以下SRC造と云う)の基礎梁を構築する分
野で実施される基礎梁構築工法に関する。Description: BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a foundation beam construction method implemented in the field of constructing a foundation beam of a building, particularly a steel reinforced concrete (hereinafter referred to as SRC) foundation beam.
従来の技術 従来、SRC造の基礎梁を構築するにあたっては、近年
の建設工事量の増大に伴う鉄骨事情の逼迫で鉄骨部材断
面はできるだけ小さくしてコストダウンを図るという目
的があり、このためSRC造柱の柱脚部鉄骨部分(O節部
分)は基礎梁中に埋設し強度の不足を補うことが一般的
に行なわれている。そして、各柱脚部鉄骨部分は、隣合
うもの同士の相互間に繋ぎ梁(仮設梁)を入れるか、又
は個々の柱脚部鉄骨毎に丸綱ワイヤーによる虎綱を張っ
て建方精度を確保する事が行なわれている。Conventional technology Conventionally, when constructing a foundation beam of SRC structure, the purpose is to reduce the cross section of the steel frame member as much as possible due to the tightness of the steel frame due to the increase in the amount of construction work in recent years. It is common practice to embed a steel column portion (O-node portion) of a column base into a foundation beam to compensate for insufficient strength. For each column-base steel frame, a connecting beam (temporary beam) is inserted between adjacent ones, or a tiger rope with a round rope wire is stretched for each column-base steel frame to improve the construction accuracy. It is being ensured.
また、基礎梁上端主筋の仮受けに関しては、市販品又
は注文製作品である梁主筋受け馬を設置するか、あるい
は基礎梁の両側位置に設置された鉄筋足場の間に単管を
架け渡して現場施工する方法などが実施されている。Regarding temporary support of the upper main bar of the foundation beam, a beam main bar receiving horse, which is a commercially available or custom-made product, is installed, or a single pipe is laid between reinforcing bar scaffolds installed on both sides of the foundation beam. Methods for on-site construction are being implemented.
さらに鉄筋組立用の足場及びコンクリート打設用の足
場は、枠組み足場又は単管による足場を仮設することが
一般的に実施されている。Further, as a scaffold for assembling reinforcing bars and a scaffold for placing concrete, it is generally practiced to temporarily provide a framework scaffold or a single-pipe scaffold.
本発明が解決しようとする課題 上記従来の基礎梁構築工法の場合は、柱脚部鉄骨の建
方精度の確保と、基礎梁上端主筋の仮受け、及び作業用
足場の仮設が、夫々個別的に独立の構造、工程として行
なわれている。従って、仮設材が多く必要であることは
勿論のこと、工数と手間が多くかかって省力化、省人化
に甚だ不利であるほか、工期の短縮も図り難いという欠
点があり、解決するべき課題になっている。Problems to be Solved by the Present Invention In the case of the above-mentioned conventional foundation beam construction method, securing of the column base steel frame construction accuracy, provisional support of the foundation beam upper main reinforcement, and provisional installation of the work scaffold are individually performed. Are performed as independent structures and processes. Therefore, it requires not only a large number of temporary materials, but also a lot of man-hours and labor, which is extremely disadvantageous for labor saving and labor saving, and it is difficult to shorten the construction period. It has become.
従って、本発明の目的は、柱脚部鉄骨部分の建方精度
の確保と、基礎梁上端主筋の仮受け、及び作業用足場の
確保をシステム的に関連づけて合理化、複合化して実施
出来るように改良した基礎梁構築工法を提供することで
ある。Therefore, an object of the present invention is to rationalize and secure the securing of the construction accuracy of the column base steel frame portion, the provisional support of the main reinforcement at the upper end of the foundation beam, and the securing of the work scaffolding in a systematic manner. It is to provide an improved foundation beam construction method.
課題を解決するための手段 上記従来技術の課題を解決するための手段として、こ
の発明に係る鉄骨鉄筋コンクリート造の基礎構築工法
は、図面に好適な実施例を示したとおり、 鉄骨鉄筋コンクリート造柱2′の基礎梁1中に埋設さ
れる柱脚部鉄骨部分2の相互間に所定高さ位置に繋ぎ梁
3が配置し、前記繋ぎ梁3の上には基礎梁上端主筋4を
仮受けする棒状の梁主筋受け5を側方へ十分な長さ突き
出すものとして設置した。この梁主筋受け5の上に主筋
4を支持せしめて基礎梁鉄筋6が組み立て、前記梁主筋
受け5の側方部分には鉄筋足場用及びコンクリート足場
用の足場板7が架設したことを特徴とする。Means for Solving the Problems As means for solving the problems of the prior art, a steel reinforced concrete foundation foundation construction method according to the present invention is, as shown in the preferred embodiment in the drawings, a steel reinforced concrete column 2 ′. A connecting beam 3 is arranged at a predetermined height between the column-base steel frame portions 2 buried in the foundation beam 1, and a bar-like member for temporarily receiving the main reinforcement 4 at the upper end of the foundation beam is provided on the connecting beam 3. The beam main bar receiver 5 was installed as one protruding a sufficient length to the side. The main reinforcing bar 4 is supported on the beam reinforcing bar receiver 5 to assemble the foundation beam reinforcing bar 6, and a scaffold plate 7 for reinforcing bar scaffolding and concrete scaffolding is provided on a side portion of the beam reinforcing bar receiver 5. I do.
作用 柱脚部鉄骨2の建方精度は、繋ぎ梁3との繋ぎ作業に
おいて十分に確保される。The construction accuracy of the column base steel frame 2 is sufficiently ensured in the connection work with the connection beam 3.
繋ぎ梁3の高さ位置を予め適正に設定することによ
り、該繋ぎ梁3の上に設置した梁主筋受け5の高さを丁
度基礎梁上端主筋4の高さ位置とすることが出来る。従
って、直ちに梁主筋受け5の上に基礎梁上端主筋4を載
置して、基礎梁鉄筋6の組立てが行なえる。By appropriately setting the height position of the connecting beam 3 in advance, the height of the beam main bar receiver 5 installed on the connecting beam 3 can be set as the height position of the upper main beam 4 of the foundation beam. Therefore, the main beam 4 at the upper end of the foundation beam is immediately placed on the beam main bar receiver 5, and the foundation beam reinforcement 6 can be assembled.
また、梁主筋受け5の側方部分の上に足場板7を架設
することで直ちに作業用足場として利用することが出来
るのである。Further, by laying the scaffold plate 7 on the side portion of the main beam support 5, it can be used immediately as a work scaffold.
実 施 例 次に、図示した本発明の実施例を説明する。Embodiment Next, the illustrated embodiment of the present invention will be described.
第1図と第2図は、本発明に係る基礎梁構築工法の実
施概況を示したもので、SRC造基礎梁1が捨てコンクリ
ート(ベースコンクリート)8の上に構築される場合を
示している。図中10はスラブである。このSRC造基礎梁
1の上に立設されるSRC造柱2′の特に基礎梁1の中に
埋設される柱脚部鉄骨部分2は、その柱脚プレート2aが
捨てコンクリート8中のアンカーボルト9に固定されて
いる。この柱脚部鉄骨部分2は、通常は鉄骨断面を出来
るだけ小さくする目的で横断面を十字形とし、かつ各先
端部にフランジプレートを溶接した十字鉄骨が使用され
ている。この柱脚部鉄骨部分2の建方精度は、相互間に
配置した繋ぎ梁3との接合作業において十分に調整して
確保される。FIGS. 1 and 2 show the outline of the implementation of the foundation beam construction method according to the present invention, in which the SRC foundation beam 1 is constructed on a discarded concrete (base concrete) 8. . In the figure, reference numeral 10 denotes a slab. The steel base portion 2 of the SRC column 2 ′ erected on the SRC foundation beam 1, particularly the column base portion 2 buried in the foundation beam 1, has the column base plate 2 a discarded and anchor bolts in the concrete 8. 9 is fixed. The column-base steel frame portion 2 is usually a cross-shaped steel frame having a cross-shaped cross section and a flange plate welded to each end portion in order to make the steel frame cross-section as small as possible. The construction accuracy of the column base steel frame portion 2 is sufficiently adjusted and secured in the joining work with the connecting beams 3 arranged between each other.
繋ぎ梁3は断面の大きさが100×50mm位の軽量溝形鋼
(又はその他の形鋼でも可)であり、その長手方向に等
配された数本の支柱11によって捨てコンクリート8の上
に水平に支持されている。特にこの繋ぎ梁3は、梁主筋
受け5を基礎梁上端主筋4の高さ位置に設置する必要
上、各支柱11の下端に設けられたレベル調整ボルト12を
操作して適正な高さ位置に配置される。しかる後に繋ぎ
梁3は柱脚部鉄骨部分2と接合し、その建方精度の確保
に寄与せしめることが行なわれている。繋ぎ梁3は、基
礎梁断面のほぼ中央部位に配置されている(第2図)。
この繋ぎ梁3には、長手方向のところどころの位置に、
後に打設するコンクリートの充填性を良好ならしめる孔
3a…が設けられている。The connecting beam 3 is a lightweight channel (or other shaped steel) having a cross section of about 100 × 50 mm, and is disposed on the concrete 8 discarded by several columns 11 equally arranged in the longitudinal direction. Supported horizontally. In particular, the connecting beam 3 is required to be installed at the height position of the main reinforcing bar 4 at the upper end of the foundation beam, so that the level adjusting bolts 12 provided at the lower ends of the columns 11 are operated to set the connecting beam 3 at the appropriate height position. Be placed. Thereafter, the connecting beam 3 is joined to the column base steel frame portion 2 to contribute to ensuring the accuracy of its construction. The connecting beam 3 is arranged substantially at the center of the cross section of the foundation beam (FIG. 2).
In this connecting beam 3, at some position in the longitudinal direction,
Holes to improve the filling of concrete to be cast later
3a ... are provided.
上記の繋ぎ梁3の上面には、長手方向に数m位の間隔
をあけて、アングル等を利用した梁主筋受け5が水平方
向に、かつ基礎梁1の幅方向に十分長く突き出るものと
して設置されている。この梁主筋受け5は通常繋ぎ梁3
に溶接して固定されている。この梁主筋受け5の上面は
丁度基礎梁上端主筋4の高さ位置に等しいものとされて
おり、この梁主筋受け5…の上に直接基礎梁上端主筋4
を支持せしめて基礎梁鉄筋6が組み立てられている。On the upper surface of the connecting beam 3, a beam main bar receiver 5 using an angle or the like is installed at a distance of about several meters in the longitudinal direction so as to protrude sufficiently long in the horizontal direction and in the width direction of the foundation beam 1. Have been. The main beam support 5 is usually a connecting beam 3
It is fixed by welding. The upper surface of the main beam support 5 is exactly equal to the height of the upper main bar 4 of the foundation beam.
Are supported, and the foundation beam reinforcing bar 6 is assembled.
なお、梁主筋受け5のうち基礎梁断面の幅方向の両側
方(又は片側方)に例えば25cm位長く突き出た部分は、
まずその先端部を捨てコンクリート8の上に立てた単管
支柱13とクランプ14で強固に連結して両端支持の形とさ
れ、当該突き出し部分の上に足場板7が架設されてい
る。従って、前記基礎梁鉄筋6の組立足場用として使用
でき、また、その後に側型枠15を設置して行なわれるSR
C造基礎梁1のコンクリート打設用の足場が確保される
のである。In addition, the portion of the beam main reinforcement receiver 5 that protrudes, for example, about 25 cm long on both sides (or one side) in the width direction of the foundation beam cross section,
First, the tip is discarded and solidly connected by a clamp 14 to a single pipe column 13 standing on concrete 8 to form a support at both ends, and a scaffold plate 7 is erected on the protruding portion. Accordingly, it can be used as a scaffold for assembling the foundation beam reinforcing bar 6, and thereafter, the SR is performed by installing the side formwork 15.
A scaffold for concrete placement of the C-structure foundation beam 1 is secured.
繋ぎ梁3は、上述した用途、機能の仮設材であるか
ら、第2図又は第3図に示した如く溝形鋼を下向きの態
様で実施する場合のほか、第3図Bのように上向きの態
様で実施する場合、あるいは第3図Cのように横向きの
態様で実施する場合もあり、いずれの態様でも同様な作
用効果を奏する。Since the connecting beam 3 is a temporary material having the above-mentioned use and function, it is not limited to the case where the channel steel is embodied in the downward direction as shown in FIG. 2 or FIG. 3 or upward as shown in FIG. 3B. In some cases, the present invention may be implemented in a horizontal orientation as shown in FIG. 3C.
本発明が奏する効果 以上に実施例と併せて詳述したとおりであって、この
発明に係る鉄骨鉄筋コンクリート造の基礎梁構築工法に
よれば、基礎梁1の中に埋設される柱脚部鉄骨部分2の
建方及びその精度の確保から梁主筋受け5の設置、並び
に作業用足場の確保までを、システム的に関連づけて合
理化、複合化した構成で実施できるので、仮設資材を大
幅に節約でき、工数及び手間を省略して省力化、省人化
が図れ、大幅なコストダウンと、合理化作業による工期
の短縮に大きな利益が得られるのである。作業の安全性
と品質の向上にも寄与するところが大である。Advantageous Effects of the Present Invention As described in detail in conjunction with the embodiments above, according to the method for constructing a steel-frame reinforced concrete foundation beam according to the present invention, a column-base steel frame portion embedded in the foundation beam 1 From the construction of 2 and securing its accuracy to the installation of the main beam support 5 and the securing of work scaffolding, it can be implemented in a systematic and rationalized, compounded configuration, so that temporary materials can be greatly saved, Labor saving and labor saving can be achieved by omitting man-hours and labor, and significant benefits can be obtained in drastic cost reduction and shortening of construction period by rationalization work. It greatly contributes to the improvement of work safety and quality.
第1図はこの発明に係る基礎梁構築工法の実施要領を正
面方向から簡単に示した説明図、第2図は第1図のII−
II線矢視の構造を拡大して詳細に示した断面図、第3図
A,B,Cは繋ぎ梁の異なる実施態様を示した立面図であ
る。 2′……SRC造柱、1……SRC造基礎梁 2……柱脚鉄骨、3……繋ぎ梁 4……基礎梁上端主筋、5……梁主筋受け 6……基礎梁鉄筋、7……足場板FIG. 1 is an explanatory view simply showing from a front direction the procedure for carrying out a foundation beam construction method according to the present invention, and FIG. 2 is II- in FIG.
FIG. 3 is an enlarged sectional view of the structure taken along line II, and FIG.
A, B and C are elevation views showing different embodiments of the connecting beam. 2 '... SRC column, 1 ... SRC foundation beam 2 ... steel column base, 3 ... connecting beam 4 ... foundation beam upper main reinforcement, 5 ... beam reinforcement reinforcement 6 ... foundation beam reinforcement, 7 ... … Scaffold board
Claims (1)
設される柱脚部鉄骨部分の相互間に所定高さ位置に繋ぎ
梁が配置され、前記繋ぎ梁の上に基礎梁上端主筋を仮受
けする梁主筋受けが側方へ十分な長さ突き出したものと
して設置され、この梁主筋受けの上に主筋を支持せしめ
て基礎梁鉄筋が組み立てられ、前記梁主筋受けの側方部
分に鉄筋足場用及びコンクリート足場用の足場板が架設
されていることを特徴とする鉄骨鉄筋コンクリート造の
基礎梁工法。1. A connecting beam is disposed at a predetermined height position between column-base steel frames buried in a foundation beam of a steel-framed reinforced concrete column, and a top main reinforcement of a foundation beam is temporarily supported on the connecting beam. The main beam reinforcement to be installed is set as one that protrudes sufficiently long to the side, the main reinforcement is supported on this main beam reinforcement, and the foundation beam reinforcement is assembled. And a scaffold plate for a concrete scaffold is erected.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP34429089A JP2759131B2 (en) | 1989-12-27 | 1989-12-27 | Foundation beam construction method for steel reinforced concrete columns |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP34429089A JP2759131B2 (en) | 1989-12-27 | 1989-12-27 | Foundation beam construction method for steel reinforced concrete columns |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH03199574A JPH03199574A (en) | 1991-08-30 |
JP2759131B2 true JP2759131B2 (en) | 1998-05-28 |
Family
ID=18368096
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP34429089A Expired - Fee Related JP2759131B2 (en) | 1989-12-27 | 1989-12-27 | Foundation beam construction method for steel reinforced concrete columns |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2759131B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112144660A (en) * | 2020-10-15 | 2020-12-29 | 中国建筑第八工程局有限公司 | Herringbone stiff column base structure and construction method thereof |
-
1989
- 1989-12-27 JP JP34429089A patent/JP2759131B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH03199574A (en) | 1991-08-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
AU2025200281A1 (en) | Methods and apparatus for constructing multi-storey buildings | |
KR20110053831A (en) | Reinforced concrete composite column with vertical connection means and construction method using the same | |
KR102585526B1 (en) | Composite frame with end-buried girder joint | |
JPS627344B2 (en) | ||
EP1561874A1 (en) | Connecting device and node for buildings with prefabricated elements | |
JP2759131B2 (en) | Foundation beam construction method for steel reinforced concrete columns | |
JP2654935B2 (en) | Construction method of ribbed slab and spacer for rib reinforcement | |
JP2000160687A (en) | Construction method for composite structure and precast concrete column | |
KR102634379B1 (en) | Prefabricated bracket assembly integrated with prefabricated column assembly for connecting PC beams | |
JP3319709B2 (en) | Construction method of prestressed concrete steel beam | |
JP3244102U (en) | Steel house foundation structure and anchor set used therein | |
US20250109588A1 (en) | Prefabricated bracket assembly integrated to prefabricated column assembly for connecting pc beams | |
JPH0380946B2 (en) | ||
KR102585732B1 (en) | Prestressed precast module with integrated girder and column and construction method using the same | |
JP2614000B2 (en) | Basics of steel frame | |
JP2784450B2 (en) | Reinforced concrete foundation | |
JP3066711B2 (en) | Formwork equipment for fabric foundation construction | |
JPH11269893A (en) | Working method for continuous footing foundation | |
JPH1113141A (en) | Construction method of composite structure | |
JP2782111B2 (en) | Steel framing construction method | |
JP2811211B2 (en) | Flat slab construction method | |
JP3284383B2 (en) | Support hardware for SRC beam construction | |
JP2004027647A (en) | Steel structure of house, and its construction method | |
JPH084029A (en) | Precast concrete foundation structure | |
JP2001011942A (en) | How to build a steel frame standing from the foundation after completion of foundation work |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
LAPS | Cancellation because of no payment of annual fees |