JP3319709B2 - Construction method of prestressed concrete steel beam - Google Patents

Construction method of prestressed concrete steel beam

Info

Publication number
JP3319709B2
JP3319709B2 JP26999497A JP26999497A JP3319709B2 JP 3319709 B2 JP3319709 B2 JP 3319709B2 JP 26999497 A JP26999497 A JP 26999497A JP 26999497 A JP26999497 A JP 26999497A JP 3319709 B2 JP3319709 B2 JP 3319709B2
Authority
JP
Japan
Prior art keywords
steel pipe
steel
concrete
prestressed concrete
pipe beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP26999497A
Other languages
Japanese (ja)
Other versions
JPH11107443A (en
Inventor
雅司 大平
Original Assignee
ドーピー建設工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ドーピー建設工業株式会社 filed Critical ドーピー建設工業株式会社
Priority to JP26999497A priority Critical patent/JP3319709B2/en
Publication of JPH11107443A publication Critical patent/JPH11107443A/en
Application granted granted Critical
Publication of JP3319709B2 publication Critical patent/JP3319709B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は建築構造物の屋根
架構や土木構造物の橋梁のような大スパン構造物に適用
されるプレストレストコンクリート鋼管梁の施工方法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a prestressed concrete steel pipe applied to a large span structure such as a roof frame of a building structure or a bridge of a civil engineering structure.

【0002】[0002]

【従来の技術及び発明が解決しようとする課題】大スパ
ン構造物の梁にはプレストレスを導入したプレキャスト
コンクリートやSRC造の梁部材が使用されるが、中実
断面でプレキャスト化される場合は梁部材1本当たりの
重量が大きいことから、支間の大きさによってはその全
長に亘る長さを持つ梁部材として一括して下部構造間に
架設することができない。
2. Description of the Related Art Precast concrete or SRC beam members with prestress are used for beams of large span structures, but when precast in solid sections, Since the weight per beam member is large, depending on the size of the span, it cannot be installed as a beam member having a length over its entire length between the lower structures.

【0003】このため、現場では各梁部材を吊り込む毎
に互いに接合することにより、あるいは一方の下部構造
から梁部材を接合しながら送り出すことにより梁部材を
下部構造間に架設することになるが、いずれの方法でも
梁部材の本数分の吊り込みや送り出しの作業を必要とす
るため、架設作業の効率が悪い。また各梁部材の接合部
分にはサポートや足場を必要とし、仮設工事にも時間が
割かれるため、工期が長期化する傾向がある。
[0003] For this reason, at the site, the beam members are erected between the lower structures by joining the beam members each time they are suspended or by sending out the beam members while joining them from one lower structure. However, any of the methods requires the work of hanging and sending out the beam members, so that the efficiency of the erection work is low. In addition, a support and a scaffold are required at a joint portion of each beam member, and time is required for temporary construction, so that the construction period tends to be longer.

【0004】この発明は上記背景より、吊り込み後の梁
部材同士の接合を不要にする施工方法を提案するもので
ある。
The present invention proposes a construction method that eliminates the need for joining beam members after suspension from the above background.

【0005】[0005]

【課題を解決するための手段】本発明では梁部材をプレ
ストレスを導入した鋼管コンクリート造で構成し、下部
構造間へは複数本の鋼管を、支間に応じた長さを持つ鋼
管梁部材として一本化させた形で先行して架設し、架設
後にコンクリートを充填して鋼管コンクリート梁にプレ
ストレスを導入したプレストレストコンクリート鋼管梁
を完成させることにより、吊り込み後の梁部材同士の接
合を不要にし、架設作業の効率を上げ、工期の短縮を図
る。
According to the present invention, a beam member is formed of a steel pipe concrete structure in which a prestress is introduced, and a plurality of steel pipes are provided between lower structures as steel pipe beam members having a length corresponding to the span. Pre-stressed concrete steel pipe beams with pre-stress introduced into steel pipe concrete beams by filling concrete after construction and pre-installed in a unified form, eliminating the need to join beam members after suspension To increase the efficiency of installation work and shorten the construction period.

【0006】鋼管は支間を複数の区間に区分した長さで
製作され、予め内部に組立鉄筋とシースが配置される。
この複数個の鋼管は互いに接合されて一本化され、一本
化された鋼管梁部材が一括して下部構造間に架設され
る。
[0006] The steel pipe is manufactured to have a length in which the span is divided into a plurality of sections, and an assembled reinforcing bar and a sheath are previously disposed inside.
The plurality of steel pipes are joined together to be unified, and the unified steel pipe beam members are collectively installed between the lower structures.

【0007】鋼管梁部材の架設後、その内部にコンクリ
ートが充填されると共に、シース内にPC鋼材が挿通さ
せられる。コンクリートの強度発現後、PC鋼材が緊張
され、コンクリートにプレストレスが与えられることに
よりプレストレストコンクリート鋼管梁が完成する。
[0007] After the steel pipe beam member is erected, concrete is filled into the steel pipe beam member, and a PC steel material is inserted into the sheath. After the strength of the concrete is developed, the PC steel material is tensioned and prestress is applied to the concrete, thereby completing the prestressed concrete steel pipe.

【0008】鋼管梁部材内部へのコンクリートの充填が
下部構造間への架設後であることにより、鋼管梁部材は
実質的に中空であるため、支間の大きさに関係なく、鋼
管梁部材を一括して吊り込み、架設することが可能にな
る。
Since the inside of the steel pipe beam member is filled with concrete after the erection between the substructures, the steel pipe beam member is substantially hollow. It can be suspended and erected.

【0009】下部構造間への架設が一括して行えること
で、架設作業が単純化され、鋼管単位で架設する場合よ
り架設の効率が格段に向上する。また現場での鋼管梁部
材同士の接合の必要がなくなることで、施工性が向上
し、それに伴い、鋼管梁部材を支持するためのサポート
の設置も不要になるため、仮設工事が大幅に簡略化さ
れ、工期の短縮が図られる。
The erection work can be simplified because the erection between the lower structures can be performed at once, and the erection efficiency is remarkably improved as compared with the case where the erection is performed in units of steel pipes. Eliminating the necessity of joining steel pipe beam members at the site eliminates the need for installation work, and as a result, eliminates the need to install supports to support steel pipe beam members, greatly simplifying temporary construction work. The construction period is shortened.

【0010】プレストレストコンクリート鋼管梁が建築
構造物の屋根架構の梁を構成する場合は上記したPC鋼
材の緊張によって施工が終了するが、橋梁を構成する場
合は請求項2に記載のように、鋼管の内部への組立鉄筋
とシースの配置と共に、鋼管の上面にスタッドボルトが
固定され、一本化された複数本の鋼管梁部材がそれぞれ
一括して下部構造間に並列して架設させられる。
In the case where the prestressed concrete steel pipe beam constitutes a beam of a roof frame of a building structure, the construction is terminated by the above-mentioned tension of the PC steel material, but in the case of constituting a bridge, the steel pipe is constituted as described in claim 2. The stud bolt is fixed to the upper surface of the steel pipe together with the arrangement of the reinforcing steel bar and the sheath inside the steel pipe, and a plurality of unified steel pipe beam members are collectively laid in parallel between the lower structures.

【0011】この場合も、各鋼管梁部材の内部にコンク
リートを充填すると共に、シース内にPC鋼材を挿通
し、コンクリートの強度発現後、PC鋼材を緊張してプ
レストレストコンクリート鋼管梁が完成する。
Also in this case, concrete is filled into each steel pipe beam member, a PC steel material is inserted into the sheath, and after the strength of the concrete is developed, the PC steel material is tensioned to complete a prestressed concrete steel beam.

【0012】プレストレストコンクリート鋼管梁が橋梁
を構成する場合、特に請求項3に記載のように、互いに
隣接する鋼管梁部材のいずれか一方に他方の鋼管梁部材
との間に跨るプレートを固定しておくことにより、各鋼
管梁部材の架設時の位置決めと間隔保持が行える。
In the case where the prestressed concrete steel beam constitutes a bridge, a plate straddling between one of the steel beam members adjacent to each other and the other is fixed to one of the steel beam members adjacent to each other. By doing so, positioning and spacing can be maintained when each steel pipe beam member is erected.

【0013】プレートはまた、床版用の鉄筋配筋時の足
場の役目を持つ他、床版コンクリートの打設時の床型枠
を兼ねるため、請求項3では足場や型枠の設置も不要に
なり、支保工が一切不要になる。
The plate also serves as a scaffold when arranging reinforcing bars for floor slabs, and also serves as a floor formwork when placing concrete slabs. And no support work is required.

【0014】請求項4では各鋼管の接合される端面を下
から上へかけてその鋼管側から接合される相手の鋼管側
へ傾斜させ、鋼管梁部材を上に凸の状態で一本化するこ
とにより、プレストレストコンクリート鋼管梁が活荷重
により下に凸に撓むことを防止する。
According to a fourth aspect of the present invention, the joined end faces of the steel pipes are inclined from the bottom to the top to the steel pipe side to be joined from the steel pipe side, and the steel pipe beam members are united in a state protruding upward. This prevents the prestressed concrete steel pipe beam from bending downward due to the live load.

【0015】[0015]

【発明の実施の形態】この発明は内部に組立鉄筋2とシ
ース3が配置された複数個の鋼管1を接合して一本化し
た鋼管梁部材4を一括して下部構造8,8間に架設し、
鋼管梁部材4の内部へのコンクリート5の充填と、シー
ス3内へのPC鋼材6の挿通と緊張によりプレストレス
トコンクリート鋼管梁7を完成させる方法である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention relates to a steel pipe beam member 4 in which a plurality of steel pipes 1 in each of which an assembled reinforcing bar 2 and a sheath 3 are arranged are joined to form a single steel pipe beam member 4 between lower structures 8, 8. Erection,
This is a method of completing a prestressed concrete steel beam 7 by filling concrete 5 into the inside of the steel tube beam member 4 and inserting and tensioning the PC steel material 6 into the sheath 3.

【0016】橋梁の施工要領を示す図5〜図13により施
工手順を説明する。図5〜図13は図1,図2に示すよう
に鋼管1が角形鋼管である場合の例である。
The construction procedure will be described with reference to FIGS. FIGS. 5 to 13 show an example in which the steel pipe 1 is a square steel pipe as shown in FIGS.

【0017】図5に示すように鋼管1は下部構造8,8
間距離である支間を複数の区間に区分した長さで製作さ
れ、具体的には支間分の長さを持つ鋼管の製作後にその
鋼管を複数の区間に区分した長さに切断することで製作
される。
As shown in FIG. 5, the steel pipe 1 has a lower structure 8,8.
It is manufactured by dividing the span, which is the distance, into a plurality of sections.Specifically, after manufacturing a steel pipe with the length of the span, it is manufactured by cutting the steel pipe into the length divided into a plurality of sections. Is done.

【0018】各鋼管1の内部には図6に示すように組立
鉄筋2とそれに一体化したシース3が挿入される。図
3,図4に組立鉄筋2を示す。鋼管1内部への組立鉄筋
2とシース3の配置までの作業は工場で行われ、鋼管1
は組立鉄筋2とシース3を内蔵した状態で現場へ搬入さ
れる。
As shown in FIG. 6, an assembled reinforcing bar 2 and a sheath 3 integrated therewith are inserted into each steel tube 1. 3 and 4 show the assembled reinforcing bar 2. The work up to the placement of the assembling rebar 2 and the sheath 3 inside the steel pipe 1 is performed in a factory.
Is transported to the site with the built-in rebar 2 and sheath 3 built-in.

【0019】各鋼管1の接合される端面は、図7に示す
ように一本化された鋼管梁部材4が上に凸の状態で下部
構造8,8間に架設されるよう、図5に示すように下か
ら上へかけてその鋼管1側から接合される相手の鋼管1
側へ傾斜する。
The joined end faces of the steel pipes 1 are connected to each other in the manner shown in FIG. 5 so that the unified steel pipe beam member 4 is erected between the lower structures 8 and 8 in a state of projecting upward as shown in FIG. As shown, from the bottom to the top, the steel pipe 1 to be joined from the steel pipe 1 side
Tilt to the side.

【0020】組立鉄筋2とシース3を内蔵した鋼管1は
図7に示すように互いに接合されて一本化され、一本化
された鋼管梁部材4は図8に示すように一括して下部構
造8,8間に吊り込まれ、架設される。鋼管1,1同士
の接合は溶接により、もしくは端面にフランジを固定し
て、あるいは図18に示すように鋼管1,1間にスプライ
スプレート14を渡してボルトにより行われる。
As shown in FIG. 7, the steel pipes 1 containing the assembled reinforcing bars 2 and the sheaths 3 are joined together to be unified, and the unified steel pipe beam members 4 are collectively lower as shown in FIG. It is suspended between the structures 8, 8 and is erected. The joining of the steel pipes 1 and 1 is performed by welding, by fixing a flange to the end face, or by passing a splice plate 14 between the steel pipes 1 and 1 as shown in FIG.

【0021】図9に示すように鋼管梁部材4の架設終了
後、鋼管梁部材4の内部にコンクリート5を充填すると
共に、シース3内にPC鋼材6を挿通し、コンクリート
5の強度発現後、図10に示すようにPC鋼材6を緊張し
てコンクリート鋼管梁にプレストレスが与えられたプレ
ストレストコンクリート鋼管梁7が完成する。
As shown in FIG. 9, after the steel pipe beam member 4 is erected, concrete 5 is filled into the steel pipe beam member 4 and a PC steel material 6 is inserted into the sheath 3 so that the strength of the concrete 5 is developed. As shown in FIG. 10, the prestressed concrete steel pipe beam 7 in which the prestress is applied to the concrete steel pipe beam by tensioning the PC steel material 6 is completed.

【0022】プレストレストコンクリート鋼管梁7が屋
根架構の梁を構成する場合は図10の段階で施工は終了す
る。
When the prestressed concrete steel pipe beam 7 constitutes the beam of the roof frame, the construction is completed at the stage shown in FIG.

【0023】図11〜図13は梁が橋梁の場合のその後の施
工要領を示すが、梁が橋梁の場合は図1,図11に示すよ
うに組立鉄筋2とシース3を挿入する図6の段階で、ま
たは複数本の鋼管1を一本化する図7の段階で鋼管1の
上面に床版コンクリートとの一体性を確保するスタッド
ボルト9が固定される。
FIGS. 11 to 13 show the subsequent construction procedure when the beam is a bridge. When the beam is a bridge, as shown in FIGS. 1 and 11, the assembled reinforcing bar 2 and the sheath 3 are inserted as shown in FIGS. At the stage or in the stage of FIG. 7 in which the plurality of steel tubes 1 are unified, stud bolts 9 for securing the integrity with the floor slab concrete are fixed to the upper surface of the steel tubes 1.

【0024】図1,図11に示すように隣接するプレスト
レストコンクリート鋼管梁7,7間の間隔はその幅方向
に跨設されるプレート10によって保持される。プレート
10はプレストレストコンクリート鋼管梁7の完成後に隣
接するプレストレストコンクリート鋼管梁7,7間に設
置されて接合される他、予めスタッドボルト9の固定時
に鋼管1に固定される。
As shown in FIGS. 1 and 11, the interval between adjacent prestressed concrete steel beams 7, 7 is held by a plate 10 laid in the width direction thereof. plate
After the prestressed concrete steel pipe beam 7 is completed, the prestressed concrete steel pipe beams 7 are installed between the adjacent prestressed concrete steel pipe beams 7, 7 and joined. In addition, the stud bolts 9 are fixed to the steel pipe 1 in advance.

【0025】プレート10は隣接するプレストレストコン
クリート鋼管梁7,7間に跨るため、互いに隣接するプ
レストレストコンクリート鋼管梁7,7のいずれか一方
に固定されれば足り、1本おきに配置されるプレストレ
ストコンクリート鋼管梁7の両側にプレート10,10を固
定し、その間に配置されるプレストレストコンクリート
鋼管梁7にプレート10を固定しない場合もある。
Since the plate 10 is straddled between the adjacent prestressed concrete steel pipes 7, 7, it is sufficient if the plate 10 is fixed to one of the adjacent prestressed concrete steel pipes 7, 7. In some cases, the plates 10 and 10 are fixed on both sides of the steel pipe beam 7, and the plate 10 is not fixed to the prestressed concrete steel pipe beam 7 disposed therebetween.

【0026】いずれか一方のプレストレストコンクリー
ト鋼管梁7に接合されているプレート10を隣接するプレ
ストレストコンクリート鋼管梁7に接合した後、図12に
示すようにプレストレストコンクリート鋼管梁7とプレ
ート10上に床版用の鉄筋11を配筋する。配筋作業は隣接
するプレストレストコンクリート鋼管梁7,7間に跨設
されているプレート10を利用して行えるため、格別の足
場や支保工を設置する必要はない。
After the plate 10 joined to one of the prestressed concrete steel pipes 7 is joined to the adjacent prestressed concrete steel pipe 7, the floor slab is placed on the prestressed concrete steel pipe 7 and the plate 10 as shown in FIG. Reinforcing bar 11 is arranged. Since the bar arrangement work can be performed using the plate 10 laid between the adjacent prestressed concrete steel pipe beams 7, 7, it is not necessary to install a special scaffolding or support.

【0027】配筋終了後、図13に示すようにプレストレ
ストコンクリート鋼管梁7とプレート10上にコンクリー
トを打設して床版12を構築し、橋梁の施工が完了する。
プレート10は床版12の捨て型枠になるため、コンクリー
トの打設時に別途型枠を設置する必要はない。
After the rebar arrangement, as shown in FIG. 13, concrete is cast on the prestressed concrete steel pipe 7 and the plate 10 to construct the floor slab 12, and the construction of the bridge is completed.
Since the plate 10 becomes a discarded formwork of the floor slab 12, there is no need to separately provide a formwork when placing concrete.

【0028】図14,図15は鋼管1が2本のH形鋼を幅方
向に組み合わせて溶接した形である場合のプレストレス
トコンクリート鋼管梁7の断面を示す。この場合の施工
要領を図16〜図21により説明する。
FIGS. 14 and 15 show cross sections of a prestressed concrete steel pipe beam 7 in a case where the steel pipe 1 is formed by welding two H-shaped steel pieces in the width direction. The construction procedure in this case will be described with reference to FIGS.

【0029】この場合も図16に示すように各鋼管1の内
部に組立鉄筋2とシース3が配置されるが、2本のH形
鋼を溶接する以前に図17−(a) に示すように一方のH形
鋼の内部に組立鉄筋2とシース3が配置され、その後に
他方のH形鋼が一方のH形鋼に溶接され、(b) に示すよ
うに組立鉄筋2とシース4を内蔵した鋼管1が製作され
る。この例ではH形鋼の溶接により鋼管1が構成される
ことから、鋼管1の内周面となるH形鋼の片面に、充填
されるコンクリート5との付着を確保するためのスタッ
ドボルト13を突設しておくことができる。図17までは工
場での作業となる。
Also in this case, as shown in FIG. 16, an assembled reinforcing bar 2 and a sheath 3 are arranged inside each steel pipe 1, but before welding two H-shaped steels, as shown in FIG. 17- (a). The assembled rebar 2 and the sheath 3 are arranged inside one H-shaped steel, and then the other H-shaped steel is welded to the one H-shaped steel, and as shown in FIG. The built-in steel pipe 1 is manufactured. In this example, since the steel pipe 1 is formed by welding the H-shaped steel, the stud bolt 13 for securing adhesion to the concrete 5 to be filled is provided on one side of the H-shaped steel which is the inner peripheral surface of the steel pipe 1. Can be protruded. Up to Fig. 17, the work is performed at the factory.

【0030】組立鉄筋2とシース3を内蔵した鋼管1は
図18に示すように互いに接合されて一本化され、一本化
された鋼管梁部材4は図8に示すように一括して下部構
造8,8間に架設される。鋼管1,1同士の接合は溶接
により、もしくは端面にフランジを固定して、あるいは
スプライスプレート14を渡してボルトにより行われる。
As shown in FIG. 18, the steel pipes 1 containing the assembled reinforcing bars 2 and the sheaths 3 are joined together to be unified, and the unified steel pipe beam members 4 are collectively lower as shown in FIG. It is erected between the structures 8,8. The joining of the steel pipes 1 and 1 is performed by welding, or by fixing a flange to an end face, or by bolts across a splice plate 14.

【0031】鋼管梁部材4の架設後、鋼管梁部材4の内
部にコンクリート5を充填すると共に、シース3内にP
C鋼材6を挿通し、コンクリート5の強度発現後、PC
鋼材6を緊張してプレストレストコンクリート鋼管梁7
を完成させることは図9,図10と同様である。
After the steel pipe beam member 4 is erected, concrete 5 is filled into the steel pipe beam member 4 and P
After inserting the C steel material 6 and developing the strength of the concrete 5, PC
Prestressed concrete steel pipe beam 7 by tensioning steel 6
Is the same as in FIGS. 9 and 10.

【0032】更に図19に示すように隣接するプレストレ
ストコンクリート鋼管梁7,7間の間隔をプレート10に
よって保持し、プレート10を隣接するプレストレストコ
ンクリート鋼管梁7に接合した後、図20に示すようにプ
レストレストコンクリート鋼管梁7とプレート10上に床
版用の鉄筋11を配筋し、図21に示すようにプレストレス
トコンクリート鋼管梁7とプレート10上にコンクリート
を打設して床版12を構築し、橋梁の施工が完了する。
Further, as shown in FIG. 19, the gap between the adjacent prestressed concrete steel pipes 7, 7 is maintained by the plate 10, and the plate 10 is joined to the adjacent prestressed concrete steel pipe 7, and as shown in FIG. Reinforcing bars 11 for floor slabs are arranged on the prestressed concrete steel tube 7 and the plate 10, and concrete is poured on the prestressed concrete steel tube 7 and the plate 10 as shown in FIG. Construction of the bridge is completed.

【0033】[0033]

【発明の効果】複数本の鋼管を、支間に応じた長さを持
つ鋼管梁部材として一本化した形で下部構造間に架設
し、架設後に鋼管梁部材内にコンクリートを充填し、プ
レストレスを導入してプレストレストコンクリート鋼管
梁を完成させるため、鋼管梁部材を支間の大きさに関係
なく、支間の全長に亘る長さを持つ梁部材として一括し
て架設することが可能になり、架設作業が単純化され、
架設効率が向上する。
According to the present invention, a plurality of steel pipes are erected between lower structures in the form of a single steel pipe beam member having a length corresponding to the span, and after the erection, concrete is filled in the steel pipe beam member and prestressing is performed. In order to complete the prestressed concrete steel pipe beam by introducing the steel pipe beam member, it is possible to install the steel pipe beam member as a beam member having the length of the entire length of the span regardless of the size of the span. Is simplified,
Construction efficiency is improved.

【0034】また現場での鋼管梁部材同士の接合の必要
がなくなるため、施工性が向上し、それに伴い、鋼管梁
部材を支持するためのサポートの設置も不要になるた
め、仮設工事が簡略化され、工期の短縮が図られる。
Further, since there is no need to join the steel pipe beam members at the site, the workability is improved, and accordingly, it is not necessary to install a support for supporting the steel pipe beam members. The construction period is shortened.

【0035】請求項3では互いに隣接する鋼管梁部材の
いずれか一方に他方の鋼管梁部材との間に跨るプレート
を固定しておくため、プレストレストコンクリート鋼管
梁が橋梁を構成する場合、各鋼管梁部材の架設時の位置
決めと間隔保持が行える。
According to a third aspect of the present invention, a plate straddling between one of the steel pipe beam members adjacent to each other and the other steel pipe beam member is fixed. Positioning and spacing at the time of erection of members can be performed.

【0036】またプレートが床版用の鉄筋配筋時の足場
の役目を果たし、床版コンクリートの打設時の床型枠を
兼ねるため、足場や型枠の設置も不要になり、支保工が
一切不要になる。
Further, since the plate serves as a scaffold when arranging reinforcing bars for floor slabs and also serves as a floor formwork for placing concrete slabs, it is not necessary to install scaffolds and formwork, and the shoring works. It becomes completely unnecessary.

【0037】請求項4では鋼管梁部材を上に凸の状態で
一本化するため、プレストレストコンクリート鋼管梁が
活荷重により下に凸に撓むことが防止できる。
According to the fourth aspect, since the steel pipe beam members are unified in the state of being raised upward, the prestressed concrete steel pipe beam can be prevented from being bent downward by a live load.

【図面の簡単な説明】[Brief description of the drawings]

【図1】鋼管が角形鋼管である場合のプレストレストコ
ンクリート鋼管梁を示した断面図である。
FIG. 1 is a cross-sectional view showing a prestressed concrete steel pipe beam when the steel pipe is a square steel pipe.

【図2】図1のプレストレストコンクリート鋼管梁から
なる橋梁を示した断面図である。
FIG. 2 is a sectional view showing a bridge made of the prestressed concrete steel pipe of FIG. 1;

【図3】組立鉄筋を示した断面図である。FIG. 3 is a sectional view showing an assembled reinforcing bar.

【図4】組立鉄筋を示した側面図である。FIG. 4 is a side view showing an assembled reinforcing bar.

【図5】鋼管が角形鋼管である場合の鋼管の製作時の様
子を示した側面図である。
FIG. 5 is a side view showing a state when the steel pipe is manufactured when the steel pipe is a square steel pipe.

【図6】鋼管内への組立鉄筋とシースの挿入時の様子を
示した側面図である。
FIG. 6 is a side view showing a state in which an assembled reinforcing bar and a sheath are inserted into a steel pipe.

【図7】鋼管梁部材の製作時の様子を示した側面図であ
る。
FIG. 7 is a side view showing a state when a steel pipe beam member is manufactured.

【図8】鋼管梁部材の架設時の様子を示した側面図であ
る。
FIG. 8 is a side view showing a state when the steel pipe beam member is erected.

【図9】鋼管梁部材の架設終了時の様子を示した側面図
である。
FIG. 9 is a side view showing a state at the end of the installation of the steel pipe beam member.

【図10】PC鋼材の緊張時の様子を示した側面図であ
る。
FIG. 10 is a side view showing a state in which a PC steel material is tensioned.

【図11】プレストレストコンクリート鋼管梁が橋梁を
構成する場合の図10の断面図である。
11 is a cross-sectional view of FIG. 10 when a prestressed concrete steel pipe forms a bridge.

【図12】プレストレストコンクリート鋼管梁上に鉄筋
を配筋した様子を示した断面図である。
FIG. 12 is a cross-sectional view showing a state where reinforcing bars are arranged on a prestressed concrete steel pipe beam.

【図13】プレストレストコンクリート鋼管梁上にコン
クリートを打設した様子を示した断面図である。
FIG. 13 is a sectional view showing a state where concrete is cast on a prestressed concrete steel pipe beam.

【図14】鋼管がH形鋼からなる場合のプレストレスト
コンクリート鋼管梁を示した断面図である。
FIG. 14 is a cross-sectional view showing a prestressed concrete steel pipe beam when the steel pipe is made of H-section steel.

【図15】図14のプレストレストコンクリート鋼管梁か
らなる橋梁を示した断面図である。
FIG. 15 is a cross-sectional view showing a bridge made of the prestressed concrete steel pipe of FIG.

【図16】鋼管内への組立鉄筋とシースの挿入時の様子
を示した側面図である。
FIG. 16 is a side view showing a state at the time of inserting the assembled rebar and the sheath into the steel pipe.

【図17】(a) は組立鉄筋とシースを内蔵した鋼管の製
作時の様子を示した断面図、(b)は完成時の様子を示し
た断面図である。
17 (a) is a cross-sectional view showing a state of a steel pipe having a built-in rebar and a sheath built therein, and FIG. 17 (b) is a cross-sectional view showing a state of completion.

【図18】鋼管梁部材の製作時の様子を示した側面図で
ある。
FIG. 18 is a side view showing a state when the steel pipe beam member is manufactured.

【図19】プレストレストコンクリート鋼管梁が橋梁を
構成する場合の図10の断面図である。
FIG. 19 is a cross-sectional view of FIG. 10 when a prestressed concrete steel pipe forms a bridge.

【図20】プレストレストコンクリート鋼管梁上に鉄筋
を配筋した様子を示した断面図である。
FIG. 20 is a cross-sectional view showing a state where reinforcing bars are arranged on a prestressed concrete steel pipe beam.

【図21】プレストレストコンクリート鋼管梁上にコン
クリートを打設した様子を示した断面図である。
FIG. 21 is a sectional view showing a state where concrete is cast on a prestressed concrete steel pipe beam.

【符号の説明】[Explanation of symbols]

1……鋼管、2……組立鉄筋、3……シース、4……鋼
管梁部材、5……コンクリート、6……PC鋼材、7…
…プレストレストコンクリート鋼管梁、8……下部構
造、9……スタッドボルト、10……プレート、11……鉄
筋、12……床版、13……スタッドボルト、14……スプラ
イスプレート。
1 ... steel pipe, 2 ... assembled rebar, 3 ... sheath, 4 ... steel pipe beam member, 5 ... concrete, 6 ... PC steel, 7 ...
... prestressed concrete steel tube beam, 8 ... substructure, 9 ... stud bolt, 10 ... plate, 11 ... rebar, 12 ... floor slab, 13 ... stud bolt, 14 ... splice plate.

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E04C 3/26 E01D 21/00 ──────────────────────────────────────────────────続 き Continued on the front page (58) Fields surveyed (Int.Cl. 7 , DB name) E04C 3/26 E01D 21/00

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 支間を複数の区間に区分した長さで製作
され、予め内部に組立鉄筋とシースが配置された複数個
の鋼管を接合して一本化し、一本化された鋼管梁部材を
一括して下部構造間に架設した後、鋼管梁部材の内部に
コンクリートを充填すると共に、シース内にPC鋼材を
挿通し、コンクリートの強度発現後、PC鋼材を緊張し
てコンクリートにプレストレスを与え、プレストレスト
コンクリート鋼管梁を完成させるプレストレストコンク
リート鋼管梁の施工方法。
1. A steel pipe beam member which is manufactured by joining a plurality of steel pipes each having a span divided into a plurality of sections, and in which a plurality of steel pipes in which an assembling reinforcing bar and a sheath are arranged in advance are joined to form a single piece. After the construction is completed, the concrete is filled into the steel pipe beam member, the PC steel is inserted into the sheath, and after the strength of the concrete is developed, the PC steel is tensioned to pre-stress the concrete. Construction method of prestressed concrete steel tube beam to give and complete prestressed concrete steel tube beam.
【請求項2】 支間を複数の区間に区分した長さで製作
され、予め内部に組立鉄筋とシースが配置されると共
に、上面にスタッドボルトが固定された複数個の鋼管を
接合して一本化し、一本化された複数本の鋼管梁部材を
それぞれ一括して下部構造間に鋼管梁部材の幅方向に並
列させて架設した後、各鋼管梁部材の内部にコンクリー
トを充填すると共に、シース内にPC鋼材を挿通し、コ
ンクリートの強度発現後、PC鋼材を緊張してコンクリ
ートにプレストレスを与え、プレストレストコンクリー
ト鋼管梁を完成させるプレストレストコンクリート鋼管
梁の施工方法。
2. A plurality of steel pipes each having a span divided into a plurality of sections and having a reinforcing bar and a sheath disposed therein in advance and joining a plurality of steel pipes having stud bolts fixed to the upper surface thereof. After a plurality of unified steel pipe beam members are collectively installed in parallel in the width direction of the steel pipe beam members between the lower structures, concrete is filled into each steel pipe beam member, and the sheath is filled. A method of constructing a prestressed concrete steel pipe beam in which a PC steel material is inserted into the steel pipe, and after the strength of the concrete is developed, the PC steel material is tensioned to give prestress to the concrete and complete the prestressed concrete steel pipe beam.
【請求項3】 互いに隣接する鋼管梁部材のいずれか一
方に、他方の鋼管梁部材との間に跨るプレートを固定す
る請求項2記載のプレストレストコンクリート鋼管梁の
施工方法。
3. The method for constructing a prestressed concrete steel pipe beam according to claim 2, wherein a plate straddling between the steel pipe beam members adjacent to each other is fixed to one of the steel pipe beam members adjacent to each other.
【請求項4】 各鋼管の接合される端面は下から上へか
けてその鋼管側から接合される相手の鋼管側へ傾斜し、
鋼管梁部材は上に凸の状態で一本化される請求項1乃至
請求項3のいずれかに記載のプレストレストコンクリー
ト鋼管梁の施工方法。
4. An end face to be joined of each steel pipe is inclined from the bottom to the top from the steel pipe side to a mating steel pipe side to be joined,
The method for constructing a prestressed concrete steel beam according to any one of claims 1 to 3, wherein the steel tube beam member is integrated in an upwardly convex state.
JP26999497A 1997-10-02 1997-10-02 Construction method of prestressed concrete steel beam Expired - Fee Related JP3319709B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP26999497A JP3319709B2 (en) 1997-10-02 1997-10-02 Construction method of prestressed concrete steel beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP26999497A JP3319709B2 (en) 1997-10-02 1997-10-02 Construction method of prestressed concrete steel beam

Publications (2)

Publication Number Publication Date
JPH11107443A JPH11107443A (en) 1999-04-20
JP3319709B2 true JP3319709B2 (en) 2002-09-03

Family

ID=17480089

Family Applications (1)

Application Number Title Priority Date Filing Date
JP26999497A Expired - Fee Related JP3319709B2 (en) 1997-10-02 1997-10-02 Construction method of prestressed concrete steel beam

Country Status (1)

Country Link
JP (1) JP3319709B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113006373A (en) * 2021-01-29 2021-06-22 中铁十六局集团第二工程有限公司 Segmental beam additionally provided with steel pipe and horizontally distributed steel bars

Also Published As

Publication number Publication date
JPH11107443A (en) 1999-04-20

Similar Documents

Publication Publication Date Title
KR102187993B1 (en) Prefabricated Bridge Structure and Construction Method
KR100926140B1 (en) Structure for using precast members and construction method thereof
KR100927344B1 (en) Construction method for connecting underground structure and underground structure using connection structure for underground construction
KR101011252B1 (en) Rigid-frame bridge frame for reinforcing negative moment part and rigid-frame bridge having it
KR101242395B1 (en) Construction method for rhamen bridge
KR200381303Y1 (en) Form system for joint between retaining wall and slab of basement floor
JP2005256341A (en) Corrugated steel-plate web u component bridge
JP6266246B2 (en) Steel column and footing joint structure and construction method
KR102269141B1 (en) Deck plate wall installation method using underground pavement
CN111270685A (en) Recyclable support truss, foundation pit support system and subway station construction method
JP2011149265A (en) Beam member and building structure
JP4472726B2 (en) Base-isolated building structure
JP2003336213A (en) Concrete receiving beam and method for building girder by using it
JP3319709B2 (en) Construction method of prestressed concrete steel beam
CN212316934U (en) Supporting member and foundation pit supporting system
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JPH07292683A (en) Anchor frame and foundation construction method using the frame
JPH0673203U (en) Beam-column joint structure
KR102634379B1 (en) Prefabricated bracket assembly integrated with prefabricated column assembly for connecting PC beams
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
KR20010095899A (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
JP2706431B2 (en) Column and beam connection and connection method
JPH0332586Y2 (en)
JP3060195B2 (en) Construction method of steel basement reinforced concrete continuous underground wall
JP2005220688A (en) Wall-type reinforced concrete structure and constructing method of of the same

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20020604

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080621

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090621

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100621

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100621

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110621

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120621

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120621

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130621

Year of fee payment: 11

LAPS Cancellation because of no payment of annual fees