JPH0788699B2 - Body construction method - Google Patents

Body construction method

Info

Publication number
JPH0788699B2
JPH0788699B2 JP62174202A JP17420287A JPH0788699B2 JP H0788699 B2 JPH0788699 B2 JP H0788699B2 JP 62174202 A JP62174202 A JP 62174202A JP 17420287 A JP17420287 A JP 17420287A JP H0788699 B2 JPH0788699 B2 JP H0788699B2
Authority
JP
Japan
Prior art keywords
floor
construction
ground
underground
skeleton
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP62174202A
Other languages
Japanese (ja)
Other versions
JPS6417941A (en
Inventor
繁夫 飯沼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP62174202A priority Critical patent/JPH0788699B2/en
Publication of JPS6417941A publication Critical patent/JPS6417941A/en
Publication of JPH0788699B2 publication Critical patent/JPH0788699B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、地下階を有する鉄骨鉄筋コンクリート造の建
物における躯体構築法、特に、地下階外殻先行工法に関
するものである。
TECHNICAL FIELD The present invention relates to a skeleton construction method for a steel-framed reinforced concrete building having a basement floor, and more particularly to a basement floor outer shell preceding construction method.

「従来の技術と発明が解決しようとする課題」 最近、建物の建設工期につき短工期の要望が高まってお
り、地下階を有する建物についても例外ではない。
“Problems to be solved by conventional techniques and inventions” Recently, there is an increasing demand for a short construction period for the construction period of a building, and a building having a basement floor is no exception.

この要望を満たすためには、施工法の改良が不可欠であ
り、特に、大規模又は大深度掘削を伴う高層又は超高層
の建物の施工法には十分な検討が必要となる。
In order to meet this demand, improvement of the construction method is indispensable, and in particular, sufficient examination is required for the construction method of a high-rise or super-high-rise building accompanied by large-scale or deep-depth excavation.

従来、この種の建物における短工期施工工法として、安
全性向上を含めて、逆打工法、セミ逆打工法(改良逆打
工法)が採用されているが、いずれも構真柱の建込みが
必要である。
Conventionally, the reverse construction method and the semi-reverse construction method (improved reverse construction method) have been adopted as the short-term construction method for this type of building, including the improvement of safety. is necessary.

また、この構真柱は、基礎形式を杭基礎とする場合には
比較的問題は少ないが、直接基礎のときには、構真柱建
込み用杭が必要となり、コスト、工期、基礎の納まり等
において不利な面が発生するため、是非とも直接基礎形
式を活かした短工期工法を確立するよう望まれている。
In addition, this structure column has relatively few problems when the foundation type is a pile foundation, but when it is a direct foundation, a structure column stake is required, which is cost, construction period, and foundation settlement. Since there are disadvantages, it is desirable to establish a short-term construction method that directly utilizes the basic form.

本発明は、かかる要求に応えようとするものである。The present invention seeks to meet this need.

「課題を解決するための手段」 上記目的達成のため、特許請求の範囲第1項の発明は、
地下鉄骨の組立後、地下躯体の外殻を先行施工し、次い
で、地下階の躯体工事と地上階の鉄骨組立及び躯体工事
とを並行させることを特徴とする。
"Means for Solving the Problems" In order to achieve the above-mentioned object, the invention of claim 1 is
After assembling the subway bones, the outer shell of the underground skeleton is pre-constructed, and then the skeleton construction of the underground floor and the steel skeleton assembly and skeleton construction of the ground floor are performed in parallel.

また、特許請求の範囲第2項の発明は、地下鉄骨の組立
後、地下躯体の外殻たる外周部柱・梁・壁及び地上一階
の床・梁を先行施工し、次いで、その地上一階の床を作
業床に利用して、地下階の躯体工場と地上階の鉄骨組立
及び躯体工事とを並行させることを特徴とする。
In addition, the invention of claim 2 is that, after the subway bone is assembled, the outer peripheral pillars / beams / walls and the floors / beams on the first floor above the outer shell of the underground structure are constructed first, and then It is characterized by using the floor of the floor as a work floor and paralleling the skeleton factory on the basement floor with the steel frame assembly and skeleton construction on the ground floor.

「作用」 特許請求の範囲第1項及び第2項のいずれ発明にあって
も、先行施工した地下躯体の外殻は、地上階と地下階と
の複層並行工事を可能にし、また、施工中の地上階に加
わる風、地震等の水平力を山止め壁を通じて地盤へと伝
達して、複層並行工事であっても安定かつ安全な状態を
確保する。
"Operation" In any of the inventions of Claims 1 and 2, the outer shell of the underground skeleton that has been constructed in advance enables the multi-story parallel construction of the ground floor and the basement, and the construction Horizontal force of wind, earthquake, etc. applied to the ground floor inside is transmitted to the ground through the cliff wall to ensure a stable and safe condition even in the case of multi-story parallel construction.

更に、特許請求の範囲第2項の発明にあっては、外殻と
して先行施工した地上一階の床は、作業床としての利用
を可能にする。
Further, in the invention according to claim 2, the floor on the first floor above the ground, which was previously constructed as the outer shell, can be used as a working floor.

「実施例」 第1図は、特許請求の範囲第1項及び第2項の発明に係
る躯体構築法の実施例を示している。
"Embodiment" FIG. 1 shows an embodiment of the body construction method according to the inventions of claims 1 and 2.

以下、図示のI〜Vの工程に従い順に説明する。Hereinafter, the steps I to V will be sequentially described.

I山止め壁の施工 地中に、建物の地下外壁に適合する山止め壁1を施工す
る。
I Construction of a retaining wall In the ground, a retaining wall 1 that fits the underground outer wall of the building is constructed.

山止め壁1の種類は、地盤条件、支保工条件に見合うも
のでよい。連続壁等の剛性の高いものでもよいし、ソイ
ル柱列壁やH形鋼横矢板等の比較的剛性の低いものでも
よい。特に、比較的剛性の小さい山止め壁の場合には、
外殻を先行させる効果が高い。
The type of the mountain retaining wall 1 may be suitable for the ground condition and the support work condition. It may be one having a high rigidity such as a continuous wall, or one having a relatively low rigidity such as a soil column wall or a horizontal H-shaped steel sheet pile. In particular, in the case of a mountain stop wall with relatively small rigidity,
Highly effective in leading the outer shell.

II掘削−支保工の繰り返し 山止め壁1の内側において、掘削しては支保工を施し
て、基礎地盤まで順次に掘り下げ、根切を完了する。
II Repetition of excavation and support work Excavation and support work are performed on the inside of the retaining wall 1, and the foundation ground is sequentially dug down to complete root cutting.

支保工には、図示のアースアンカー工法又は切梁工法を
採用する。アースアンカー工法の場合、複数のアンカー
2を適宜に地中へ貫入させればよいので、施工性が高
い。
For the support work, the earth anchor method or the beam method shown in the figure is used. In the case of the earth anchor construction method, since a plurality of anchors 2 may be appropriately penetrated into the ground, workability is high.

腹起し3は、本設の地下外壁を利用したRC(鉄筋コンク
リート)腹起しとし、そのまま本設に活用する。
The uprising 3 is an RC (reinforced concrete) upholstery that uses the underground wall of the main construction, and is used for the main construction as it is.

本設の地下外壁の柱・梁・壁がRCの場合には、掘削と並
行した先行逆打ちも可能である。
If the pillars, beams, and walls of the basement outer wall of the permanent construction are RC, it is also possible to perform reverse strike in parallel with excavation.

また、所要の乗入構台4を仮設する。In addition, the required entry platform 4 is temporarily installed.

III基礎打設−地下鉄骨組立−地上一階床・梁先行打設 基礎5を打設し、最下段の支保工を解体し、地下鉄骨6
の建方・本締めし、これと並行して地下外壁の柱・梁・
壁7を先行打設し(地上一階床・梁打設後でも可)、地
上一階の床・梁8を先行打設する。
III Foundation Casting-Subway Bone Assembly-First Floor Floor, Beam Leading Casting Foundation 5 is cast, the bottom support structure is dismantled, and subway bone 6
The erection and final tightening of the
The wall 7 is placed in advance (it is possible even after the first floor above the floor and the beam is placed), and the floor and beam 8 on the first floor above is placed in advance.

而して、地上一階にて、広い作業スペースの確保と早期
の乗入構台4の解体を得る。
Thus, on the first floor above the ground, a large work space is secured and the dismantling of the entrance gantry 4 is obtained at an early stage.

IV地下外殻完了と地上・地下複層並行作業 地下外殻、すなわち、基礎5、地上一階の床・梁8、地
下外周の柱・梁・壁7が完成して後、地下躯体9と地上
鉄骨10の複層並行作業を行う。
IV Completion of Underground Outer Shell and Parallel Work of Aboveground and Underground Layers Underground outer shell, namely foundation 5, floor / beam 8 on the first floor above ground, pillars / beams / walls 7 on the outer periphery of the underground, and then underground skeleton 9 Performs multi-layer parallel work on the above ground steel frame 10.

この際、地上鉄骨10には、風、地震等による水平力が加
わることとなるが、この水平力は、地上一階の床・梁
8、地下外周の柱・梁・壁7、山止め壁1を通じて地盤
へと伝達され、したがって、施工途中における水平力に
対して安定した架構となる。
At this time, horizontal force due to wind, earthquake, etc. will be applied to the above-ground steel frame 10, but this horizontal force is the floor / beam 8 on the first floor above the ground, pillars / beams / walls 7 on the outer perimeter of the ground, and retaining walls. It is transmitted to the ground through No. 1 and, therefore, the frame becomes stable against horizontal force during construction.

V地上・地下躯体複層並行作業 地下躯体9及び地上躯体11の複層並行作業を行い、特
に、高層部が鉄骨造の場合には、この高層部にてPca
(プレキャストコンクリート)版12を建込み、3段階複
層並行作業を行う。
V Parallel work on the ground / underground structure Multi-layer work on the underground structure 9 and the ground structure 11 is performed. Especially when the high-rise part is a steel frame structure, Pca
(Precast concrete) A slab 12 is built and a three-step parallel work is performed.

高層部が鉄骨造の場合は、地上階の施工スピードが早く
なり、水平力も大きく作用することとなるが、上述のよ
うにして地盤へと伝達されるため、安定性を確保でき
る。
If the high-rise part is made of steel frame, the construction speed on the ground floor will be faster, and the horizontal force will also be large, but since it is transmitted to the ground as described above, stability can be secured.

「発明の効果」 特許請求の範囲第1項及び第2項の発明によれば、構真
柱も構真柱建込み用杭も必要なく、直接基礎形式の利点
を活かした短工期施工が可能となり、而して、その地下
躯体の外殻の先行施工により、後の地下途中階の躯体工
事と地上階の鉄骨組立及び躯体工事とを支障なく並行さ
せることができて、工期を大幅に短縮でき、コストを低
減できる。
"Effect of the invention" According to the inventions of claims 1 and 2, neither the construction column nor the pile for erection of the construction column is required, and the construction work can be done in a short period of time by taking advantage of the direct foundation type. Therefore, by the preceding construction of the outer shell of the underground skeleton, the skeleton construction of the later underground intermediate floor and the steel frame assembly and skeleton construction of the ground floor can be performed in parallel without any trouble, and the construction period is greatly shortened. The cost can be reduced.

また、その地下躯体の外殻の先行施工により、施工中の
地上階に加わる風、地震等の水平力を、該外殻から山止
め壁を通じて地盤へと適正に伝達させることができて、
そのような複層並行工事であっても施工中の安定性、安
全性を確保できる。
In addition, by preceding construction of the outer shell of the underground structure, horizontal force such as wind and earthquake applied to the ground floor under construction can be appropriately transmitted from the outer shell to the ground through the mountain retaining wall,
Even in such multi-story parallel construction, stability and safety during construction can be secured.

更に、特許請求の範囲第2項の発明によれば、外殻とし
て地上一階の床を先行施工するので、該床を作業床とし
て利用できて、早期に乗入構台を解体でき、より一層の
工期の短縮を可能にすることができ、施工を容易にする
ことができる。
Further, according to the invention of claim 2, since the first floor above the ground is constructed as the outer shell in advance, the floor can be used as a work floor, and the entry gantry can be disassembled at an early stage, and further The construction period can be shortened and the construction can be facilitated.

【図面の簡単な説明】[Brief description of drawings]

第1図は、本発明の実施例に係る施工手順を示す説明図
である。 1……山止め壁、2……アースアンカー 3……腹起し、4……乗入構台 5……基礎、6……地下鉄骨 7……地下外周の柱・梁・壁 8……地上一階の床・梁 9……地下躯体、10……地上鉄骨 11……地上躯体、12……Pca版
FIG. 1 is an explanatory view showing a construction procedure according to an embodiment of the present invention. 1 ... Mountain stop wall, 2 ... Earth anchor 3 ... Raised, 4 ... Entry pedestal 5 ... Foundation, 6 ... Subway bone 7 ... Pillars / beams / walls around underground 8 ... Ground Floors and beams on the first floor 9 …… Underground structure, 10 …… Overground steel frame 11 …… Overground structure, 12 …… Pca version

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】地下鉄骨の組立後、地下躯体の外殻を先行
施工し、次いで、地下階の躯体工事と地上階の鉄骨組立
及び躯体工事とを並行させることを特徴とする躯体構築
法。
1. A skeleton construction method, characterized in that after assembling a subway bone, an outer shell of an underground skeleton is pre-constructed, and then a skeleton construction on the basement floor and a steel frame assembly and skeleton construction on the ground floor are performed in parallel.
【請求項2】地下鉄骨の組立後、地下躯体の外殻たる外
周部柱・梁・壁及び地上一階の床・梁を先行施工し、次
いで、その地上一階の床を作業床に利用して、地下階の
躯体工事と地上階の鉄骨組立及び躯体工事とを並行させ
ることを特徴とする躯体構築法。
2. After assembling the subway bone, the outer peripheral columns / beams / walls of the underground structure and the floors / beams on the first floor above ground are pre-constructed, and then the floor on the first floor above is used as a work floor. Then, the skeleton construction method is characterized in that the skeleton construction on the basement floor and the steel frame assembly and skeleton construction on the ground floor are performed in parallel.
JP62174202A 1987-07-13 1987-07-13 Body construction method Expired - Fee Related JPH0788699B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62174202A JPH0788699B2 (en) 1987-07-13 1987-07-13 Body construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62174202A JPH0788699B2 (en) 1987-07-13 1987-07-13 Body construction method

Publications (2)

Publication Number Publication Date
JPS6417941A JPS6417941A (en) 1989-01-20
JPH0788699B2 true JPH0788699B2 (en) 1995-09-27

Family

ID=15974507

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62174202A Expired - Fee Related JPH0788699B2 (en) 1987-07-13 1987-07-13 Body construction method

Country Status (1)

Country Link
JP (1) JPH0788699B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0497014U (en) * 1991-01-22 1992-08-21
JP2016199957A (en) * 2015-04-14 2016-12-01 戸田建設株式会社 Floor preceding method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0730564B2 (en) * 1987-06-11 1995-04-05 大成建設株式会社 Construction method of underground structure

Also Published As

Publication number Publication date
JPS6417941A (en) 1989-01-20

Similar Documents

Publication Publication Date Title
JP2001262595A (en) Building construction method of underground building frame
JPH102126A (en) Base isolated building
JP2001349065A (en) Underground base isolating construction method for existing building
JPH0220767A (en) Earthquake-proofing method for existing building
JPH0788699B2 (en) Body construction method
JP3641227B2 (en) Construction method of underground structure
JP2001271497A (en) Temporary bearing construction method for existing building
JP2950325B1 (en) Construction method of seismic isolation building
JP3053938B2 (en) Double striking method
JP2003003690A (en) Base isolation building and method for base isolation of exisiting building
JPH1130053A (en) Construction method of base isolation building
JPH05179647A (en) Supporting structure for earth retaining wall
JP2897663B2 (en) How to build underground structures
JPH09228398A (en) Construction method for pile support type multistoried building
JP3077099B2 (en) Basement construction method in a narrow site
JP2004060310A (en) Wooden earthquake-proof construction using earthquake-proof core
JPH0742179A (en) Modified inversion placing construction method
JP2926151B2 (en) Building structure and construction method
JP2004244982A (en) Construction method of building
JP2819008B2 (en) Existing building seismic isolation method
JPH08291529A (en) Underground floor construction method
JP2002174051A (en) Construction method for base isolation
RU24225U1 (en) CONSTRUCTIVE-ARCHITECTURAL SOLUTION OF RECONSTRUCTION OF A SMALL BUILDING
JPH0696918B2 (en) Building dismantling method
JPH09195526A (en) Structure and its construction

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees