JP3850785B2 - Caisson laying method using main foundation pile - Google Patents

Caisson laying method using main foundation pile Download PDF

Info

Publication number
JP3850785B2
JP3850785B2 JP2002300844A JP2002300844A JP3850785B2 JP 3850785 B2 JP3850785 B2 JP 3850785B2 JP 2002300844 A JP2002300844 A JP 2002300844A JP 2002300844 A JP2002300844 A JP 2002300844A JP 3850785 B2 JP3850785 B2 JP 3850785B2
Authority
JP
Japan
Prior art keywords
caisson
foundation pile
pile
jack
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002300844A
Other languages
Japanese (ja)
Other versions
JP2004137685A (en
Inventor
啓一 齋藤
義廣 鈴木
茂 菅野
勝俊 田中
▲こう▼一 藤野
明尚 藤本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JR East Consultants Co
East Japan Railway Co
Original Assignee
JR East Consultants Co
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JR East Consultants Co, East Japan Railway Co filed Critical JR East Consultants Co
Priority to JP2002300844A priority Critical patent/JP3850785B2/en
Publication of JP2004137685A publication Critical patent/JP2004137685A/en
Application granted granted Critical
Publication of JP3850785B2 publication Critical patent/JP3850785B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

【0001】
【発明の属する技術分野】
本発明は、土木工事分野におけるオープンケーソンの施工方法において、特に、本設基礎杭を利用したケーソン沈設方法および支持方法に関するものである。
【0002】
【従来の技術】
従来、杭基礎工法による下部工躯体(フーチング)の構築方法は、はじめに本設となる所要の基礎杭を設置し、次に仮設土留め工を行って本設基礎杭の天端まで開削工法により掘削した後、下部工躯体を構築するという手順が一般的である。
【0003】
また、従来のオープンケーソンの沈設技術は、グランドアンカーに代表される地盤定着材料をケーソン躯体からわずかに離れた外周に所要数量設置し、該アンカーを地盤反力とすることでケーソンを沈設施工する方法が一般的に用いられている。
【0004】
さらに、ケーソンの側方移動を抑止する方法としては、該ケーソンの近傍に別途に側方移動用に専用の杭などを設置し、これを不動部材としてケーソン沈設時のガイドとする技術がある。
【0005】
従来技術における杭基礎工法によれば、下部工躯体を構築するための仮設土留め工に一定期間の工期を必要とし、さらに、下部工躯体の構築後も仮設土留め工に用いられた仮設材料を撤去するための工期を必要とするばかりか、該仮設材料の完全な撤去も難しいという問題があった。
【0006】
また、オープンケーソン施工に関する従来技術は、グランドアンカーなどの定着材料を予め設置することを前提としたものであり、工事箇所の土質条件やケーソン躯体の重量などによって左右されるものの、オープンケーソン施工の場合は、補助工法としての圧入の併用または、ケーソン躯体上部に重錘などを設置して見掛けのケーソン躯体重量を増加させることなどが、ケーソン躯体の沈下力の増大および施工精度の向上を得やすいとして必要条件となっている。
【0007】
前述のことから、グランドアンカーなどの定着材料の設置に要する工期や相応の占用する施工範囲ばかりでなく、定着材料や重錘に要する費用などが負担になるほか、建設事業の環境問題が取りざたされている中で、グランドアンカーは定着部分を完全に撤去することが難しく、完全撤去にはさらに所要の工期と費用を必要とすることが問題となっている。
【0008】
前記の諸問題を解決する改良技術として、特開平6−341154号に開示の地下躯体構築工法が知られている。この先行技術は、それ以前に行われていた、アースアンカー(グランドアンカー)を、基礎杭とは別に設置したアンカー体に連設する工法に代えて、前記アースアンカーをケーソンを沈設する領域に打ち込まれた基礎杭に一体連結するもので、これにより基礎杭で得られる緊張力をケーソン躯体の沈設の際にも得ることができるようにすると共に、工期短縮を可能とするというものである。
【0009】
【特許文献1】
特開平6−341154号公報
【0010】
【発明が解決しようとする課題】
しかし、特開平6−341154号に開示の従来技術では、基礎杭に一体連結したアースアンカーによりジャッキ反力を採ってケーソン躯体を沈設することはできるが、このアースアンカーは、通常、PC鋼線または細径棒体等からなるものであって、それ自体剛性を有していないことから、ケーソン躯体の沈設作業の際の水平方向移動を抑制する反力部材として機能させたり、さらに、ケーソン沈設後、着底地盤の支持力の不均衡などによるケーソン躯体の傾斜等の抑止のため、ケーソン底盤構築の際のケーソンの仮支持反力材として機能させることはできず、これらのためケーソン躯体の高精度の沈設が難しく、また圧入作業の不安定さなどの問題が依然として残されていた。
【0011】
さらに、従来のオープンケーソン工法では、ケーソン躯体沈設終了段階において、着底地盤の支持力の不均衡などから、ケーソン着底後も多少のケーソン躯体の傾斜や沈下が発生する場合があり、この対応策としてケーソン躯体を支持するため、アースアンカーとは別途に支持杭を必要とするようなケーソン支持装置を設置したり、ケーソン仕切り壁の下部に支台(サンドル)を設置するなどの面倒な手間のかかる方法が採られている。
【0012】
本発明は、前記の問題点を解決したもので、本設基礎杭を利用したケーソン沈設方法および、支持方法を提供することを目的とする。
【0013】
【課題を解決するための手段】
前記の目的を達成するため、本発明は、次のように構成する。
【0014】
第1の発明は、ジャッキにより圧力を加えてオープンケーソンを所定位置にて所定深度まで沈設する過程において、ケーソンを沈設する領域に打込まれた本設基礎杭に立設する剛性支持部材を前記ジャッキに連結することで、前記剛性支持部材および本設基礎杭を前記ケーソン沈設のための圧入反力材として利用し、前記剛性支持部材にストラッドを固着し、ストラッドに設けたガイドローラをケーソンの内側壁と仕切り壁に接触させることで、前記ケーソンの移動を鉛直方向のみに拘束させることを特徴とする。
【0015】
第2の発明は、ジャッキにより圧力を加えてオープンケーソンを所定位置にて所定深度まで沈設する過程において、ケーソンを沈設する領域に打込まれた本設基礎杭に立設する剛性支持部材を前記ジャッキに連結することで、前記剛性支持部材および本設基礎杭を前記ケーソン沈設のための圧入反力材として利用し、前記ジャッキにより圧力を加えてオープンケーソンを所定位置および所定深度まで沈設完了した後、前記剛性支持部材と本設基礎杭をケーソンの吊り持ち反力材として利用し、配置変えをした前記ジャッキにより前記ケーソンに吊上げ力を加えてケーソンの過沈下(自沈)防止を図り、ケーソン底盤を構築することを特徴とする。
【0016】
第3の発明は、第2の発明におけるケーソン底盤を構築するに際し、ケーソンの刃口と略同じ厚さに下地コンクリートを打設し、下地コンクリートの上面と切断面が略揃うように本設基礎杭を切断し、その後、前記ケーソン底盤を打設することで本設基礎杭とケーソン躯体を一体化することを特徴とする。
【0017】
【作用】
第1の発明では、基礎杭などが下部工躯体を支持するような構造物である場合において、下部工躯体をケーソンとして地上にて予め構築しておき、オープンケーソン工法により沈設する際、ケーソンを沈設する領域に打設された基礎杭および、当該基礎杭に立設する剛性支持部材に圧入反力を取ってケーソンを沈設するものであるから、従来のグランドアンカーや本設基礎杭と別途の圧入専用の基礎杭などが不要であるのは勿論、基礎杭と剛性支持部材は何れも剛体であるから水平方向反力材として機能させることができ、したがって、ケーソンの圧入作業をより高精度で、かつ円滑に行うことが出来る。また、剛性支持部材に固着したガイドローラ付きストラッドの前記ガイドローラをケーソンの内側壁と仕切り壁に接触させることで、ケーソンの移動を鉛直成分に確実に拘束でき、したがって、ケーソンを高精度でかつ円滑に沈設することができる。
【0018】
第2および第3の発明では、所定位置および所定深度までケーソンの沈設を完了(着底)した後に、ケーソン底盤を構築することでその過沈下(自沈)を抑制するので、従来のように別途にケーソン躯体吊り支持杭を必要とせず、また、支台(サンドル)手間のかかる方法なども不要となり、さらに、ケーソン底盤を構築するに際して、予め設置された本設基礎杭から立設する中間接続杭を利用してケーソンを確実に吊り持ち支持させることができ、その作業が容易となる。
【0019】
【発明の実施の形態】
以下、本発明の実施形態を図を参照して説明する。図1〜図4は、本発明のケーソン沈設過程の工程図、図5〜図8は圧入装置の図、図9〜図11は吊り下げ装置の図であり、図1〜図11は相互に対応する図として示している。図12〜図16は他の実施形態に係るケーソン圧入装置の図である。
【0020】
まず、図1〜図4を参照して、本発明のケーソン沈設の施工順を次の(1)〜(9)工程に分けて概要的に説明する。
【0021】
(1)第1工程では、本設基礎杭・中間接続杭を設置する。
(2)第2工程では、ケーソン刃口部を設置する。
(3)第3工程では、第nリフトのケーソン躯体を構築する。
(4)第4工程では、ケーソン圧入設備を設置する。
(5)第5工程では、ケーソン沈下のため地盤掘削する。
(6)第6工程では、ケーソン沈下を完了する。
(7)第7工程では、ケーソン支持部材を設置する。
(8)第8工程では、最終掘削(床付け)を行う。
(9)第9工程では、ケーソン工を完了する。
【0022】
以下、(1)〜(9)の各施工段階(ステップ)の詳細を説明する。
【0023】
(1)本設基礎杭・中間接続杭設置段階(ステップ)
削孔工法やオールケーシング工法などの既存の技術により、ケーソンを沈設する所定の領域に本設基礎杭1として所要の場所打ち杭を必要本数施工すると共に、多数の本設基礎杭1のうち、必要な本設基礎杭1に、剛性支持部材の1例としてH形鋼材などの中間接続杭(反力杭)2を、施工基面(地表面)3にその杭頭2aが突出するように立設状態に施工する。(図1A参照)
【0024】
中間接続杭2は、本設基礎杭1の杭コンクリート1aに点線で示すようにコンクリート1aに埋設しておき、接続杭頭2aを施工基面(地表面)3において、本設基礎杭1の上端から突出させておき、本設基礎杭1を所定深さ打設するのに対応して、本設基礎杭1の上部から杭コンクリート1aを順次ハツルことによりH形鋼製の中間接続杭2を露出させることで構成してもよい。
【0025】
(2)ケーソン刃口部設置段階(ステップ)
ケーソン(躯体)4の刃口4aを施工基面3に設置する。(図1A参照)
【0026】
(3)ケーソン躯体第nリフト構築段階(ステップ)
第nリフトのケーソン躯体4の構築を行う。(n=1、2、3、4…・)
【0027】
(4)ケーソン圧入設備設置段階(ステップ)
構築したケーソン躯体4上に支圧盤5を設置し、該支圧盤5上に反力桁6を仮設し、該反力桁6の上部にセンターホールジャッキからなる液圧(油圧)ジャッキ7を設置し、該液圧ジャッキ7にはテンションロッド(グリッパーロッド)8を挿設させて本設基礎杭1に立設する中間接続杭2の杭頭2aと連結し、液圧ジャッキ7を緊張することで圧入効果を得る圧入設備10の設置工を行う。(図1B参照)
【0028】
(5)ケーソン沈下掘削段階(ステップ)
ケーソン4の圧入を行うと共にケーソンの内側の地盤3aを掘削し、該ケーソン4を沈下させる。(図1C参照)
【0029】
なお、このとき、同時に、中間接続杭2と中間接続杭2の間隙ならびに、中間接続杭2とケーソン躯体内壁(またはケーソン躯体仕切り壁)との間隙にストラッドを横設し、さらに、ケーソン躯体内壁(またはケーソン躯体仕切り壁)に位置する該ストラッドには隔壁ローラを設置する一連の作業を、ケーソンの掘削深度に伴い順次設備し、これら手段によってケーソン躯体の可動範囲を鉛直方向のみに拘束し、つまり、側方移動を防止する措置を講じることで、ケーソン沈設精度の向上を図る。(中間接続杭2にストラッドを横設する構成については、図12〜図16に示す他の実施形態で説明する)
【0030】
(6)ケーソン沈下完了段階(ステップ)
ケーソン4の沈下と、内側地盤3aの掘削を停止し、圧入設備10を一旦撤去
する。(図2A参照)
【0031】
(3)〜(5)の各段階(ステップ)を所定深度まで繰返し実施することで、ケーソン4の圧入沈下を完了させる。(図2B、図2C参照)
【0032】
なお、ケーソン躯体4の最終リフト構築においては、ケーソン吊り支持部材11(図2Cでは、ケーソン吊り支持部材を図示省略し、図3B、Cに示す)をケーソン躯体4から上方に突設させる。その際の掘削工は、ケーソン躯体4の過沈下(自沈)を防止できる以上の必要根入れ長の地山を掘り残して、ケーソン内側の地盤3aの掘削を終了する。その後、圧入設備10を一旦撤去する。(図3A参照)
【0033】
(7)ケーソン支持部材設置段階(ステップ)
中間接続杭2の杭頭部2aに支圧桁12を設置し、該支圧桁12の上部に反力桁6を架設し、液圧ジャッキ(センターホールジャッキ)7を該反力桁6の上部に設置し、吊り筋(ケーソン吊り支持部材)21を該液圧ジャッキ7に挿設することで、吊り下げ設備13の設置工を行う。そして、液圧ジャッキ7を緊張させることで本設基礎杭1および、該本設基礎杭1に立設する中間接続杭2を支持反力材とするケーソン躯体4の沈下防止措置を行う。(図3B参照)
【0034】
(8)最終掘削(床付け)段階(ステップ)
ケーソン躯体4の沈下防止措置が完了した後、ケーソン内側の地盤3aを掘削し、必要根入れ長を掘り残した地山を掘削し(図3C参照)、刃口4aと略同じ厚みコンクリート15を打設して床付けする。(図4A参照)
【0035】
(9)ケーソン工完了段階(ステップ)
本設基礎杭1の杭頭処理を行い、床付けコンクリート15の上に配筋を行い、その後コンクリートを打設し、床付けコンクリート15の上にケーソン底盤14を構築する。ケーソン底盤14とケーソン躯体4とは機械継手(図示省略)で一体化され、したがって、ケーソン底盤14を介して、本設基礎杭1とケーソン躯体4とを一体化でき、その後、液圧ジャッキ7をジャッキダウンする。さらに、その後、ケーソン吊り下げ設備13を撤去し、ケーソン底盤14から突出状態にある中間接続杭2を該ケーソン底盤14面にて切断撤去し、ケーソン工の完了となる。(図4B参照)
【0036】
次に、図5〜図8を参照して、圧入設備の詳細を説明する。
【0037】
図5は、第2リフトのケーソン躯体4を構築した上、これに圧入設備10を設置した平面図、図6、図7は、図5のa−a、b−b断面図、図8は、図6のc部の詳細図である。
【0038】
各図に示すように、ケーソン4は平面から見て例えば、田の字状に仕切り壁が構築されていて、ケーソン4の上面でかつ両側付近に離れて左右それぞれ複数のブロック状の支圧盤5が設置されていて、各支圧盤5の上に間隙をあけて設けられる2本1組の反力桁6が、平行にかつ左右2組設けられていて、各反力桁6の両端部にセンターホールジャッキからなる液圧ジャッキ7が支持されていて、液圧ジャッキ7の中心を挿通するグリッパーロッド8が、2本1組の反力桁6の間隙16を挿通して立上がっている。
【0039】
液圧ジャッキ7を構成するセンターホールジャッキとグリッパーロッド8とは公知であり、液圧ジャッキ7を作動させることで、センターホールジャッキに内蔵の上下のストッパー部材が交互に拡縮しながら、グリッパーロッド8のテーパ部をスライドすると共に、係合段部に係合することで、段階的にグリッパーロッド8を引上げることができ、グリッパーロッド8の下端が連結される中間接続杭2に相対的に引張反力を伝達できる。
【0040】
グリッパーロッド8と中間接続杭2との連結は図8のようになされている。グリッパーロッド8の下端にはアジャストロッド17が連結され、アジャストロッド17にアンカーカプラー18が取り付けられ、中間接続杭2の上端に設けられた取り付けブラケット19とアンカーカプラー18の間がPC鋼棒20やPC鋼線などで連結されている。グリッパーロッド8と中間接続杭2の連結構造はその他公知の構造であってよい。
【0041】
前述のようにして、ケーソン4上面の略四隅部に配置される4台の液圧ジャッキ7を同期して作動させることで、剛性体である中間接続杭2を介して数センチ(2cm)以下の誤差でケーソン4を圧入できる。なお、液圧ジャッキ7の圧入力を取り出すため、中間接続杭2の上端にグリッパーロッド8が連結されるが、このグリッパーロッド8はある程度の硬直性を有すると共に、液圧ジャッキ7の圧入力を取り出すのに必要な最短長であるので、剛性体である中間接続杭2にケーソン4を高精度で沈下させるための反力材として機能を発揮でさせる上で不具合はない。
【0042】
なお、中間接続杭2は、ケーソン圧入時の反力材としてより大きな剛性を付与するのが望ましく、既述のように、本設基礎杭1の杭コンクリート1aを施工基面(地表面)3まで伸ばし、中間接続杭2を杭コンクリート1aに埋設しておき、本設基礎杭1を所定深さ打設するのに対応して、杭コンクリートaを順次ハツって中間接続杭2を露出させるのがよい。
【0043】
次に、図9は、第2リフトのケーソン躯体4の沈設が完了した後、これに吊り下げ設備13を設置した平面図、図10(A)、(B)は、図9のd−d、e−e断面図、図11は、図10(B)のf部の詳細図である。
【0044】
本発明では、ケーソン躯体4内の地盤3aの掘削を一部残して第nリフトのケーソン躯体4の沈設が完了した後、該ケーソン躯体4を吊り下げ設備13にて吊り下げ支持した状態で前記の掘り残した一部を最終掘削し、床付けを行うと共に、ケーソン底盤14を構築することについては既述した。ケーソン吊り下げ設備13はこの作業に必要となる。
【0045】
本発明に係る吊り下げ設備13の詳細は次のように構成されている。
【0046】
ケーソン4の内側に立設される複数の中間接続杭2のうち、所定位置の中間接続杭2の杭頭2aを利用して支圧桁23が所定間隔離れて平行に設けられており、各支圧桁23のうえに支圧盤5が間隔をあけて複数設けられており、各支圧盤5の上に間隙をあけて設けられる2本1組の反力桁6が平行にかつ左右2組設けられていている。そして、各反力桁6の両端部には、ケーソン沈設時とは配置変えを行ったセンターホールジャッキからなる液圧ジャッキ7が支持されていて、液圧ジャッキ7の中心を挿通するグリッパーロッド8が、2本1組の反力桁6の間隙16を挿通して立上がっている
【0047】
また、図に示すように、平面から見て田の字状に仕切壁が構築された複数段のケーソン4のうち、最上段のケーソン4の4隅部の近傍に吊り筋21を埋設し、吊り筋21の上部を該ケーソン4の上面から所定長突出させており、吊り筋21とグリッパーロッド8が連結されている。
【0048】
グリッパーロッド8と吊り筋21との連結は次のようになされている。すなわち、グリッパーロッド8の下端にはアジャストロッド17が連結され、アジャストロッド17にアンカーカプラー18が取り付けられ、吊り筋21の上端に設けられた取り付けブラケット19とアンカーカプラー18の間がPC鋼棒20やPC鋼線などで連結されている。グリッパーロッド8と吊り筋21の連結構造は、前記のほか公知の構造であってよい。
【0049】
液圧ジャッキ(センターホールジャッキ)7とグリッパーロッド8は、既述のとおり公知である。簡単に説明すると、グリッパーロッド8は係合段部とテーパー部が交互に連続した軸体であり、センターホールジャッキは、拡縮自在、かつ上下動自在の上下一対をなすストッパー部材を内蔵している。そして、センターホールジャッキを作動させるとき、上下のストッパー部材が交互に拡縮しながら上下動し、各ストッパー部材が拡径しながらグリッパーロッド8のテーパー部をスライドして下動すると共に、縮径し係合段部に係合して上動することとを繰返すことで、段階的にグリッパーロッド8を引上げることができ、グリッパーロッド8の下端が連結される吊り筋21を介して、かつ剛体である中間接続杭2に支持反力をとってケーソン4を吊り下げ支持できる。
【0050】
この吊り下げ設備13でケーソン4を吊り下げ支持した状態(沈下防止措置が完了した状態)で、ケーソン内側の地盤3aを掘削し、必要根入れ長を掘り残した地山を掘削し床付けコンクリートを打設するものである。(これについては既述した)
【0051】
次に、図12〜図16は、他の実施形態を示し、図12は、第2リフトのケーソン躯体4の上部に圧入設備10を設置すると共に、圧入設備10と中間接続杭2の間隙に先端にガイドローラ23を有するストラッド22を設置した平面図、図13は、図12のg−g断面図、図14(A)は、図12のh−h断面図、図14(B)は、図13のi部の詳細図である。
【0052】
この実施形態では、H形鋼製の中間接続杭(反力杭)2の両フランジに、長さが長短異なるH形鋼製の複数のストラッド22がボルトナット24により着脱自在に設けられ、端部に位置するストラッド22の先端にガイドローラ23が取り付けられ、このガイドローラ23がケーソン躯体4の側壁に回転自在に圧接している。図12〜図16におけるその他の構成は、図5〜図8の圧入設備10と同じであるので、同一要素には同一符号を付して説明を省略する。
【0053】
この実施形態においては、中間接続杭2と中間接続杭2の間隙ならびに、中間接続杭2とケーソン躯体内壁4bまたは、ケーソン躯体仕切り壁4cとの間隙にストラッド22を横設する一連の作業は、ケーソン4の掘削深度に伴い順次設備する。具体的には、本設基礎杭1の杭コンクリート1aを剥離することで剥き出しになった中間接続杭2に順次ストラッド22をボルト接合で横設していく。さらに、ストラッド22の先端に設けたガイドローラ23は、ケーソン躯体内壁4bおよび仕切り壁4cと圧接して回転しながら上下動する。
【0054】
前記のガイドローラ付きストラッド22によってケーソン躯体4は、その可動範囲を鉛直方向のみに拘束されて円滑に下動する。こうして、ストラッド22が取り付けられた剛性体である中間接続杭(反力杭)2を反力材として、ケーソン躯体4の側方移動を防止する措置を講じることで、ケーソン沈設精度の向上を図ることができる。
【0055】
以上、実施形態について説明したが、本発明はこの図示例に限定されず、適宜、設計変更の範囲で変更実施してよく、これらは本発明の範囲に属する。
【0056】
【発明の効果】
本発明に係る本設基礎杭を利用したケーソン沈設方法および支持方法によると、開削工法における仮設土留めの作業を省略することができる。また、圧入工法併用時のオープンケーソン工法におけるケーソン圧入用グランドアンカーなどの使用および、設置作業を省略できることから、撤去が不可能または難しい該グランドアンカーの設置・撤去作業、および仮設工である土留めに要する工期の短縮や、工費の低減が可能となる。さらに、従来技術と同等の沈設精度を確保してオープンケーソンの圧入沈設施工が可能となり、ケーソン躯体を杭基礎工法における下部工躯体とすることが可能となるため、省力的施工に繋がる効果を有する。
【0057】
さらに本発明によると、所定位置および所定深度までケーソンの沈設を完了(着底)した後に、過沈下(自沈)を抑制しケーソン底盤を構築するので、従来のように別途にケーソン躯体吊り支持杭を必要とせず、また、支台(サンドル)などの手間のかかる方法なども不要となり、さらに、ケーソン底盤を構築するに際して、予め設置された本設基礎杭から立設する中間接続杭を利用してケーソンを確実に吊り持ち支持させることができ、施工の省力化に寄与できる。
【0058】
また、河川工事に代表されるような高水位下において、従来技術では、例えば橋台を築造する際、仮締切としてコルゲート管などを使用してドライ環境とした後、築造作業を行っていたが、本発明によればケーソンにより仮締切などを必要としないため、前述同様に工期短縮や工費低減に対して有効である。
【0059】
さらにまた、グランドアンカーなどを用いるケーソンの圧入工法に比し、予め設置される本設基礎杭から例えば、H形鋼などを反力部材として介在させ圧入装置を作用させることにより、グランドアンカー使用時に発現するアンカー部の伸びを抑制することが可能となるため、ケーソン躯体構築時にジャッキダウンして圧入設備を一時撤去する際などには確実に施工性が向上する。
【0060】
【図面の簡単な説明】
【図1】 本発明のケーソン沈設過程の第1工程図である。
【図2】 本発明のケーソン沈設過程の第2工程図である。
【図3】 本発明のケーソン沈設過程の第3工程図である。
【図4】 本発明のケーソン沈設過程の第4工程図である。
【図5】 第2リフトのケーソン躯体を構築した上、これに圧入設備を設置した平面図 である。
【図6】 図5のa−a断面図である。
【図7】 図5のb−b断面図である。
【図8】 図6のc部の詳細図である。
【図9】 第2リフトのケーソン躯体の沈設が完了した後、これに吊り下げ設備を設置 した平面図である。
【図10】 (A)、(B)は、図9のd−d、e−e断面図である。
【図11】 図11は、図10(B)のf部の詳細図である。
【図12】 他の実施形態を示し、第2リフトのケーソン躯体の上部に圧入設備を設置すると共に、圧入設備と中間接続杭の間隙にガイドローラ付きストラッドを設置した平面図である。
【図13】 図12のg−g断面図で、かつ中央部から左右のケーソンの沈設深さを変えて表示する図である。
【図14】 (A)は、図12のh−h断面図、(B)は、図13のi部の詳細図である。
【図15】 ローラ付きストラッドと反力杭とケーソン側壁の関係を示す平面拡大図である。
【図16】 ローラ付きストラッドと反力杭とケーソン側壁の関係を示す側面拡大図である。
【符号の説明】
【0061】
1 本設基礎杭
1a杭コンクリート
2 中間接続杭
2a 杭頭
3 施工基礎面(地表面)
4 ケーソン躯体
4a 刃口
4b ケーソン躯体内壁
4c ケーソン躯体仕切り壁
5 支圧盤
6 反力桁
7 液圧ジャッキ
8 グリッパーロッド(テンションロッド)
10 圧入設備
12 支圧桁
13 吊り下げ設備
14 ケーソン底盤
15 床付けコンクリート
16 間隙
17 アジャストロッド
18 アンカーカプラー
19 取り付けブラケット
20 PC鋼材
21 吊り筋(ケーソン吊り支持部材)
22 ストラッド
23 ガイドローラ
24 ボルトナット
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an open caisson construction method in the field of civil engineering work, and more particularly to a caisson laying method and a support method using a main foundation pile.
[0002]
[Prior art]
Conventionally, the construction method of the lower structure (footing) by the pile foundation method is to install the required foundation pile first, and then perform temporary earth retaining work to the top edge of the foundation pile by open-cut method After excavation, the general procedure is to construct the substructure.
[0003]
In addition, the conventional open caisson laying technique is to install a required amount of ground fixing material represented by a ground anchor on the outer periphery slightly away from the caisson housing, and lay the caisson by using the anchor as a ground reaction force. The method is commonly used.
[0004]
Furthermore, as a method of suppressing the lateral movement of the caisson, there is a technique in which a dedicated pile or the like is separately installed in the vicinity of the caisson and used as a guide when the caisson is set as a stationary member.
[0005]
According to the pile foundation method in the prior art, the temporary earth retaining work for constructing the substructure requires a certain period of time, and the temporary material used for the temporary earth retaining work after the construction of the substructure In addition to requiring a construction period for removing the temporary material, it was difficult to completely remove the temporary material.
[0006]
In addition, the conventional technology related to open caisson construction is based on the premise that fixing materials such as ground anchors are installed in advance, and it depends on the soil conditions of the construction site and the weight of the caisson housing, but the open caisson construction In this case, it is easy to obtain an increase in caisson housing subsidence and improvement in construction accuracy by using press-fitting as an auxiliary method or by installing a weight on the upper part of the caisson housing to increase the apparent caisson housing weight. As a prerequisite.
[0007]
From the above, not only the construction period required for the installation of fixing materials such as ground anchors and the corresponding construction scope, but also the costs required for fixing materials and weights are borne, and environmental problems in the construction business have been addressed. However, it is difficult for the ground anchor to completely remove the anchoring portion, and the complete removal requires a further work period and cost.
[0008]
As an improved technique for solving the above problems, an underground building construction method disclosed in JP-A-6-341154 is known. In this prior art, instead of the construction method of connecting an earth anchor (ground anchor) to an anchor body installed separately from the foundation pile, the earth anchor was driven into the area where the caisson was submerged. In this way, the tension force obtained by the foundation pile can be obtained even when the caisson frame is set, and the construction period can be shortened.
[0009]
[Patent Document 1]
JP-A-6-341154
[Problems to be solved by the invention]
However, in the prior art disclosed in Japanese Patent Laid-Open No. 6-341154, the caisson housing can be sunk by using the reaction force of the jack by the ground anchor integrally connected to the foundation pile. Alternatively, it is made of a thin rod or the like and does not have its own rigidity, so that it can function as a reaction member that suppresses horizontal movement during the caisson housing installation work, or caisson installation Later, in order to prevent the inclination of the caisson frame due to imbalance in the support capacity of the ground, it is not possible to function as a temporary support material for the caisson when building the caisson base. It was difficult to set up with high precision, and problems such as instability of press-fitting work remained.
[0011]
Furthermore, in the conventional open caisson method, at the end of caisson frame installation, there may be some tilting or settlement of the caisson frame even after the caisson has settled due to imbalance in the bearing capacity of the landing ground. In order to support the caisson housing as a measure, it is troublesome to install a caisson support device that requires a support pile separately from the earth anchor, or to install a support (sanddle) under the caisson partition wall. This method is adopted.
[0012]
The present invention solves the above-described problems, and an object thereof is to provide a caisson laying method and a support method using a main foundation pile.
[0013]
[Means for Solving the Problems]
In order to achieve the above object, the present invention is configured as follows.
[0014]
According to a first aspect of the present invention, in the process of laying an open caisson to a predetermined depth at a predetermined position by applying pressure with a jack, the rigid support member erected on the main foundation pile driven into the area where the caisson is laid By connecting to the jack, the rigid support member and the main foundation pile are used as a press-fitting reaction force material for caisson deposition, the straddle is fixed to the rigid support member, and the guide roller provided on the straddle is connected to the caisson. The movement of the caisson is restricted only in the vertical direction by contacting the inner wall and the partition wall.
[0015]
According to a second aspect of the present invention, in the process of laying an open caisson to a predetermined depth at a predetermined position by applying pressure with a jack, the rigid support member standing on the main foundation pile driven into the area where the caisson is laid is By connecting to a jack, the rigid support member and the foundation foundation pile were used as a press-fitting reaction force material for caisson deposition, and the open caisson was completed to a predetermined position and a predetermined depth by applying pressure with the jack. Then, the rigid support member and the main foundation pile are used as a caisson suspension reaction force material, and the caisson is prevented from being oversunk (self-sinking) by applying a lifting force to the caisson with the rearranged jack. It is characterized by building a bottom board.
[0016]
In constructing the caisson bottom plate in the second invention, the third invention is that the foundation concrete is cast so that the foundation concrete is cast to approximately the same thickness as the edge of the caisson, and the top surface and the cut surface of the foundation concrete are substantially aligned. The pile is cut, and then the caisson bottom plate is placed to integrate the main foundation pile and the caisson frame.
[0017]
[Action]
In the first invention, when the foundation pile or the like is a structure that supports the lower construction body, the lower construction body is pre-constructed on the ground as a caisson, and when the caisson is set by the open caisson method, Since the caisson is laid down by taking the press-fitting reaction force on the foundation pile placed in the area to be laid and the rigid support member standing on the foundation pile, it is separate from the conventional ground anchor and main foundation pile. Needless to say, a foundation pile dedicated to press-fitting is not necessary, and both the foundation pile and the rigid support member are rigid bodies, so that they can function as a horizontal reaction force material. And can be performed smoothly. Further, by bringing the guide roller of the straddled guide roller fixed to the rigid support member into contact with the inner wall and the partition wall of the caisson, the movement of the caisson can be reliably restrained to the vertical component. It can be laid down smoothly.
[0018]
In the second and third inventions, after the caisson has been laid down to the predetermined position and the predetermined depth (bottomed), the caisson bottom plate is constructed to suppress the oversinking (self-sinking). In addition, no caisson frame suspension support pile is required, and there is no need for a laborious method (sanddle), and in addition, when constructing the caisson bottom plate, an intermediate connection is erected from the pre-installed main foundation pile. The caisson can be reliably lifted and supported using the pile, and the work becomes easy.
[0019]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments of the present invention will be described below with reference to the drawings. 1 to 4 are process diagrams of the caisson laying process of the present invention, FIGS. 5 to 8 are diagrams of a press-fitting device, FIGS. 9 to 11 are diagrams of a suspension device, and FIGS. It is shown as a corresponding figure. 12 to 16 are views of a caisson press-fitting device according to another embodiment.
[0020]
First, with reference to FIGS. 1-4, the construction order of caisson installation of this invention is divided into the following (1)-(9) processes, and is demonstrated roughly.
[0021]
(1) In the first step, a permanent foundation pile and an intermediate connection pile are installed.
(2) In the second step, a caisson blade portion is installed.
(3) In the third step, an nth lift caisson housing is constructed.
(4) In the fourth step, caisson press-fitting equipment is installed.
(5) In the fifth step, ground excavation is performed for caisson settlement.
(6) In the sixth step, the caisson settlement is completed.
(7) In the seventh step, a caisson support member is installed.
(8) In the eighth step, final excavation (flooring) is performed.
(9) In the ninth step, the caisson work is completed.
[0022]
Hereinafter, the details of each construction stage (step) of (1) to (9) will be described.
[0023]
(1) Main foundation pile and intermediate connection pile installation stage (step)
The required number of cast-in-place piles are constructed as the required foundation pile 1 in the predetermined area where the caisson is sunk by existing technologies such as the drilling method and all-casing method. As an example of a rigid support member, an intermediate connection pile (reaction force pile) 2 such as an H-shaped steel material is placed on a permanent foundation pile 1 such that the pile head 2a protrudes from the construction base surface (ground surface) 3. Install in the installed condition. (See Figure 1A)
[0024]
The intermediate connection pile 2 is embedded in the concrete 1a as indicated by the dotted line in the pile concrete 1a of the permanent foundation pile 1, and the connection pile head 2a is placed on the construction base surface (ground surface) 3 of the permanent foundation pile 1 The intermediate connection pile 2 made of H-shaped steel is made to protrude from the upper end, and the pile concrete 1a is crushed sequentially from the upper part of the permanent foundation pile 1 corresponding to driving the permanent foundation pile 1 to a predetermined depth. You may comprise by exposing.
[0025]
(2) Caisson blade edge installation stage (step)
The cutting edge 4 a of the caisson (frame) 4 is installed on the construction base surface 3. (See Figure 1A)
[0026]
(3) Caisson body n-th lift construction stage (step)
The caisson housing 4 of the nth lift is constructed. (N = 1, 2, 3, 4 ...)
[0027]
(4) Caisson press-fitting equipment installation stage (step)
A bearing plate 5 is installed on the constructed caisson housing 4, a reaction force girder 6 is temporarily installed on the bearing plate 5, and a hydraulic (hydraulic) jack 7 including a center hole jack is installed on the reaction force girder 6. Then, a tension rod (gripper rod) 8 is inserted into the hydraulic jack 7 and connected to the pile head 2 a of the intermediate connection pile 2 erected on the main foundation pile 1 to tension the hydraulic jack 7. The installation work of the press-fitting equipment 10 to obtain the press-fitting effect is performed. (See Figure 1B)
[0028]
(5) Caisson subsidence excavation stage
The caisson 4 is press-fitted and the ground 3a inside the caisson is excavated to sink the caisson 4. (See Figure 1C)
[0029]
At the same time, a straddle is installed in the gap between the intermediate connection pile 2 and the intermediate connection pile 2 and the gap between the intermediate connection pile 2 and the caisson enclosure wall (or the caisson enclosure partition wall). (Or the caisson enclosure partition wall) The straddle that is located on the straddle is equipped with a series of operations to install the bulkhead roller in accordance with the caisson excavation depth, and the movable range of the caisson enclosure is restricted only in the vertical direction by these means, In other words, the caisson laying accuracy is improved by taking measures to prevent lateral movement. (The configuration in which the straddle is installed on the intermediate connection pile 2 will be described in other embodiments shown in FIGS. 12 to 16).
[0030]
(6) Caisson settlement completion stage (step)
The settlement of the caisson 4 and the excavation of the inner ground 3a are stopped, and the press-fitting equipment 10 is temporarily removed. (See Figure 2A)
[0031]
By repeating the steps (3) to (5) to a predetermined depth, the caisson 4 is completely pressed and settled. (See FIGS. 2B and 2C)
[0032]
In the final lift construction of the caisson housing 4, the caisson suspension support member 11 (the caisson suspension support member is omitted in FIG. 2C and shown in FIGS. 3B and 3C) is projected upward from the caisson housing 4. The excavator at that time ends the excavation of the ground 3a inside the caisson, leaving a ground having a necessary depth longer than the caisson housing 4 can be prevented from being oversunk (self-sinking). Thereafter, the press-fitting equipment 10 is once removed. (See Figure 3A)
[0033]
(7) Caisson support member installation stage (step)
A supporting girder 12 is installed on the pile head 2 a of the intermediate connection pile 2, a reaction force girder 6 is installed on top of the supporting girder 12, and a hydraulic jack (center hole jack) 7 is attached to the reaction force girder 6. By installing the suspension bar (caisson suspension support member) 21 on the hydraulic jack 7 and installing the suspension facility 13 on the upper part. Then, the hydraulic jack 7 is tensed to prevent the caisson housing 4 from sinking using the main foundation pile 1 and the intermediate connection pile 2 erected on the main foundation pile 1 as a supporting reaction material. (See Figure 3B)
[0034]
(8) Final excavation (flooring) stage
After the caisson enclosure 4 settlement prevention measures are completed, the ground 3a inside the caisson is excavated, and the ground that has left the necessary penetration length is excavated (see FIG. 3C). Place and floor. (See Figure 4A)
[0035]
(9) Caisson construction completion stage (step)
Pile head processing of the foundation foundation pile 1 is performed, reinforcement is placed on the flooring concrete 15, and then the concrete is placed, and the caisson bottom 14 is constructed on the flooring concrete 15. The caisson bottom plate 14 and the caisson housing 4 are integrated by a mechanical joint (not shown). Therefore, the main foundation pile 1 and the caisson housing 4 can be integrated via the caisson bottom plate 14, and then the hydraulic jack 7 Jack down. Further, after that, the caisson suspension equipment 13 is removed, and the intermediate connection pile 2 protruding from the caisson bottom board 14 is cut and removed on the surface of the caisson bottom board 14 to complete the caisson work. (See Figure 4B)
[0036]
Next, the details of the press-fitting equipment will be described with reference to FIGS.
[0037]
FIG. 5 is a plan view in which the caisson housing 4 of the second lift is constructed and the press-fitting equipment 10 is installed thereon, FIGS. 6 and 7 are cross-sectional views taken along lines aa and bb in FIG. 5, and FIG. FIG. 7 is a detailed view of part c in FIG. 6.
[0038]
As shown in each figure, the caisson 4 has a partition wall constructed in, for example, a square shape when viewed from the plane, and a plurality of block-shaped bearing plates 5 on the left and right sides of the upper surface of the caisson 4 are separated from both sides. Are installed, and a pair of reaction force girders 6 are provided in parallel and on the left and right sides of each reaction force beam 6 at both ends of each reaction force girder 6. A hydraulic jack 7 composed of a center hole jack is supported, and a gripper rod 8 inserted through the center of the hydraulic jack 7 is inserted through a gap 16 between a pair of reaction force beams 6 and rises.
[0039]
The center hole jack and the gripper rod 8 constituting the hydraulic jack 7 are well known. By operating the hydraulic jack 7, the upper and lower stopper members built in the center hole jack are alternately expanded and contracted, and the gripper rod 8 The gripper rod 8 can be pulled up step by step by sliding the taper portion of the gripper and engaging with the engagement step portion, and is pulled relatively to the intermediate connection pile 2 to which the lower end of the gripper rod 8 is coupled. Can transmit reaction force.
[0040]
The connection between the gripper rod 8 and the intermediate connection pile 2 is as shown in FIG. An adjusting rod 17 is connected to the lower end of the gripper rod 8, an anchor coupler 18 is attached to the adjusting rod 17, and a PC steel rod 20 or the like is provided between the mounting bracket 19 provided at the upper end of the intermediate connection pile 2 and the anchor coupler 18. It is connected with PC steel wire. The connection structure of the gripper rod 8 and the intermediate connection pile 2 may be other known structures.
[0041]
As described above, by operating the four hydraulic jacks 7 arranged at substantially the four corners of the upper surface of the caisson 4 in synchronization, a few centimeters (2 cm) or less via the intermediate connection pile 2 which is a rigid body. Caisson 4 can be press-fitted with an error of. In addition, in order to take out the pressure input of the hydraulic jack 7, the gripper rod 8 is connected to the upper end of the intermediate connection pile 2. The gripper rod 8 has a certain degree of rigidity and the pressure input of the hydraulic jack 7. Since it is the shortest length required for taking out, there is no problem in making the intermediate connection pile 2 which is a rigid body function as a reaction force material for sinking the caisson 4 with high accuracy.
[0042]
The intermediate connection pile 2 desirably has greater rigidity as a reaction material during caisson press-fitting. As described above, the pile concrete 1a of the foundation foundation pile 1 is applied to the construction base surface (ground surface) 3. The intermediate connection pile 2 is buried in the pile concrete 1a, and the pile concrete a is sequentially released to expose the intermediate connection pile 2 in response to placing the main foundation pile 1 to a predetermined depth. It is good.
[0043]
Next, FIG. 9 is a plan view in which the hanging equipment 13 is installed after the caisson housing 4 of the second lift is completed, and FIGS. 10A and 10B are views of FIG. FIG. 11 is a detailed view of a portion f in FIG.
[0044]
In the present invention, after the caisson housing 4 of the n-th lift is completed while leaving a part of excavation of the ground 3 a in the caisson housing 4, the caisson housing 4 is suspended and supported by the suspension equipment 13. As described above, a part of the left digging is finally excavated and floored, and the caisson bottom 14 is constructed. The caisson suspension facility 13 is required for this work.
[0045]
The details of the hanging equipment 13 according to the present invention are configured as follows.
[0046]
Of the plurality of intermediate connection piles 2 erected on the inner side of the caisson 4, the supporting girders 23 are provided in parallel at predetermined intervals using the pile heads 2a of the intermediate connection piles 2 at predetermined positions. A plurality of support plates 5 are provided on the support girders 23 at intervals, and one set of two reaction force girders 6 provided with a gap on each of the support plates 5 in parallel and in two sets on the left and right. It is provided. At both ends of each reaction force beam 6, a hydraulic jack 7 made up of a center hole jack that has been repositioned when caisson is installed is supported, and gripper rods 8 that pass through the center of the hydraulic jack 7 are supported. Are standing up through the gap 16 between the two pairs of reaction force beams 6.
Also, as shown in the figure, hanging bars 21 are embedded in the vicinity of the four corners of the uppermost caisson 4 among the multi-stage caissons 4 in which the partition walls are constructed in a U-shape when viewed from above. The upper part of the suspension bar 21 protrudes from the upper surface of the caisson 4 for a predetermined length, and the suspension bar 21 and the gripper rod 8 are connected.
[0048]
The gripper rod 8 and the suspension bar 21 are connected as follows. That is, an adjustment rod 17 is connected to the lower end of the gripper rod 8, an anchor coupler 18 is attached to the adjustment rod 17, and a PC steel rod 20 is provided between the mounting bracket 19 provided at the upper end of the suspension bar 21 and the anchor coupler 18. And PC steel wire. In addition to the above, the connection structure of the gripper rod 8 and the suspension bar 21 may be a known structure.
[0049]
The hydraulic jack (center hole jack) 7 and the gripper rod 8 are known as described above. Briefly, the gripper rod 8 is a shaft body in which engagement step portions and taper portions are alternately continued, and the center hole jack incorporates a pair of stopper members that can expand and contract and can move up and down. . When the center hole jack is operated, the upper and lower stopper members move up and down alternately, and each stopper member expands and slides the tapered portion of the gripper rod 8 while moving down. The gripper rod 8 can be pulled up step by step by repeatedly engaging with the engaging step and moving upward, and the rigid body is connected to the lower end of the gripper rod 8 via the suspension bar 21. The caisson 4 can be suspended and supported by the intermediate reaction pile 2 that is the support reaction force.
[0050]
In the state where the caisson 4 is suspended and supported by the suspension equipment 13 (when the settlement prevention measures have been completed), the ground 3a inside the caisson is excavated, and the ground where the necessary penetration length has been dug is excavated, and flooring concrete is provided. Is to be placed. (This has already been described)
[0051]
Next, FIG. 12 to FIG. 16 show another embodiment, and FIG. 12 shows that the press-fitting equipment 10 is installed on the upper part of the caisson housing 4 of the second lift, and in the gap between the press-fitting equipment 10 and the intermediate connection pile 2. FIG. 13 is a cross-sectional view taken along the line gg in FIG. 12, FIG. 14A is a cross-sectional view taken along the line hh in FIG. 12, and FIG. 14B is a plan view in which the straddle 22 having the guide roller 23 is installed. FIG. 14 is a detailed view of a part i in FIG. 13.
[0052]
In this embodiment, a plurality of H-shaped steel straddles 22 having different lengths are detachably provided by bolts and nuts 24 on both flanges of an H-shaped steel intermediate connection pile (reaction force pile) 2. A guide roller 23 is attached to the front end of the straddle 22 positioned at this portion, and this guide roller 23 is in pressure contact with the side wall of the caisson housing 4 so as to be rotatable. Other configurations in FIGS. 12 to 16 are the same as those of the press-fitting equipment 10 in FIGS. 5 to 8, and thus the same elements are denoted by the same reference numerals and description thereof is omitted.
[0053]
In this embodiment, a series of operations for laterally setting the straddle 22 in the gap between the intermediate connection pile 2 and the intermediate connection pile 2 and the gap between the intermediate connection pile 2 and the caisson enclosure wall 4b or the caisson enclosure partition wall 4c, The facilities will be installed in sequence with the caisson 4 drilling depth. Specifically, the straddles 22 are sequentially installed by bolt joints on the intermediate connection pile 2 that is exposed by peeling off the pile concrete 1a of the main foundation pile 1. Further, the guide roller 23 provided at the tip of the straddle 22 moves up and down while rotating in pressure contact with the caisson housing wall 4b and the partition wall 4c.
[0054]
The caisson housing 4 is smoothly moved downward by restraining its movable range only in the vertical direction by the straddle 22 with guide rollers. Thus, the intermediate connection pile (reaction force pile) 2 which is a rigid body to which the straddle 22 is attached is used as a reaction material, and measures for preventing lateral movement of the caisson housing 4 are taken, thereby improving caisson installation accuracy. be able to.
[0055]
Although the embodiment has been described above, the present invention is not limited to this illustrated example, and may be modified as appropriate within the scope of design changes, and these belong to the scope of the present invention.
[0056]
【The invention's effect】
According to the caisson laying method and the supporting method using the permanent foundation pile according to the present invention, the temporary earth retaining work in the open-cut method can be omitted. In addition, the use of caisson press-fitting ground anchors in the open caisson method when using the press-fitting method and the installation work can be omitted, so it is impossible or difficult to remove and install the ground anchor, which is temporary work. It is possible to shorten the construction period required for the construction and to reduce the construction cost. Furthermore, the installation accuracy of open caisson can be secured with the same accuracy as that of the conventional technology, and the caisson frame can be used as the lower frame in the pile foundation method, resulting in labor-saving construction. .
[0057]
Furthermore, according to the present invention, after the caisson has been laid down to the predetermined position and the predetermined depth (bottomed down), the caisson bottom plate is constructed by suppressing the oversinking (self-sinking). In addition, a laborious method such as a stand (sanddle) is not required, and in addition, when constructing the caisson bottom plate, an intermediate connection pile standing up from a pre-installed foundation foundation pile is used. The caisson can be securely held and supported, which can contribute to labor saving in construction.
[0058]
Also, under the high water level represented by river construction, in the prior art, for example, when building an abutment, a corrugated pipe or the like was used as a temporary deadline, and then the building work was performed. According to the present invention, the caisson does not require a temporary deadline and the like, which is effective for shortening the construction period and reducing the construction cost as described above.
[0059]
Furthermore, compared to the caisson press-in method using a ground anchor, etc., by using a press-fitting device by interposing, for example, H-shaped steel as a reaction force member from a pre-installed foundation foundation pile, when using the ground anchor Since it becomes possible to suppress the elongation of the anchor part that appears, workability is reliably improved when jacking down at the time of caisson housing construction and temporarily removing the press-fitting equipment.
[0060]
[Brief description of the drawings]
FIG. 1 is a first process diagram of a caisson laying process of the present invention.
FIG. 2 is a second process diagram of the caisson setting process of the present invention.
FIG. 3 is a third process diagram of the caisson laying process of the present invention.
FIG. 4 is a fourth process diagram of the caisson laying process of the present invention.
FIG. 5 is a plan view in which a caisson housing for a second lift is constructed and press-fitting equipment is installed on the second caisson housing.
6 is a cross-sectional view taken along the line aa in FIG.
7 is a cross-sectional view taken along the line bb of FIG.
FIG. 8 is a detailed view of part c in FIG. 6;
FIG. 9 is a plan view in which a suspension facility is installed after the caisson housing of the second lift is completed.
10A and 10B are sectional views taken along line dd and ee in FIG.
FIG. 11 is a detailed view of a part f in FIG. 10 (B).
FIG. 12 is a plan view showing another embodiment, in which a press-fit facility is installed on the upper part of the caisson housing of the second lift, and a straddle with guide rollers is installed in the gap between the press-fit facility and the intermediate connection pile.
13 is a cross-sectional view taken along the line gg of FIG. 12 and is displayed by changing the set depth of the left and right caissons from the center.
14A is a cross-sectional view taken along the line hh in FIG. 12, and FIG. 14B is a detailed view of a portion i in FIG.
FIG. 15 is an enlarged plan view showing the relationship between the straddled roller, the reaction force pile, and the caisson side wall.
FIG. 16 is an enlarged side view showing the relationship between the straddled roller, the reaction force pile and the caisson side wall.
[Explanation of symbols]
[0061]
1 foundation foundation pile 1a pile concrete 2 intermediate connection pile 2a pile head 3 construction foundation surface (ground surface)
4 Caisson housing 4a Cutting edge 4b Caisson housing body wall 4c Caisson housing partition wall 5 Supporting plate 6 Reaction force girder 7 Hydraulic jack 8 Gripper rod (tension rod)
DESCRIPTION OF SYMBOLS 10 Press-fit equipment 12 Supporting girder 13 Suspension equipment 14 Caisson bottom board 15 Flooring concrete 16 Gap 17 Adjustment rod 18 Anchor coupler 19 Mounting bracket 20 PC steel material 21 Suspension reinforcement (caisson suspension support member)
22 Strud 23 Guide roller 24 Bolt nut

Claims (3)

ジャッキにより圧力を加えてオープンケーソンを所定位置にて所定深度まで沈設する過程において、ケーソンを沈設する領域に打込まれた本設基礎杭に立設する剛性支持部材を前記ジャッキに連結することで、前記剛性支持部材および本設基礎杭を前記ケーソン沈設のための圧入反力材として利用し、前記剛性支持部材にストラッドを固着し、ストラッドに設けたガイドローラをケーソンの内側壁と仕切り壁に接触させることで、前記ケーソンの移動を鉛直方向のみに拘束させることを特徴とする本設基礎杭を利用したケーソン沈設方法。 In the process of laying open caisson to a predetermined depth at a predetermined position by applying pressure with a jack, by connecting to the jack a rigid support member standing on the foundation foundation pile driven into the caisson sunk area The rigid support member and the main foundation pile are used as a press-fitting reaction force material for caisson deposition , a strad is fixed to the rigid support member, and guide rollers provided on the straddle are used as inner walls and partition walls of the caisson. A caisson laying method using a main foundation pile, wherein the caisson movement is restricted only in a vertical direction by contacting. ジャッキにより圧力を加えてオープンケーソンを所定位置にて所定深度まで沈設する過程において、ケーソンを沈設する領域に打込まれた本設基礎杭に立設する剛性支持部材を前記ジャッキに連結することで、前記剛性支持部材および本設基礎杭を前記ケーソン沈設のための圧入反力材として利用し、前記ジャッキにより圧力を加えてオープンケーソンを所定位置および所定深度まで沈設完了した後、前記剛性支持部材と本設基礎杭をケーソンの吊り持ち反力材として利用し、配置変えをした前記ジャッキにより前記ケーソンに吊上げ力を加えてケーソンの過沈下(自沈)防止を図り、ケーソン底盤を構築することを特徴とする本設基礎杭を利用したケーソン支持方法。 In the process of laying open caisson to a predetermined depth at a predetermined position by applying pressure with a jack, by connecting to the jack a rigid support member standing on the foundation foundation pile driven into the caisson sunk area The rigid support member and the main foundation pile are used as a press-fitting reaction force material for caisson deposition, and after the open caisson is completed to a predetermined position and a predetermined depth by applying pressure by the jack, the rigid support member And using the foundation pile as a caisson suspension reaction force material, applying the lifting force to the caisson with the rearranged jack to prevent the caisson from over-sinking (self-sinking), and building the caisson base A caisson support method using the characteristic foundation pile. 請求項2記載のケーソン底盤を構築するに際し、ケーソンの刃口と略同じ厚さに下地コンクリートを打設し、下地コンクリートの上面と切断面が略揃うように本設基礎杭を切断し、その後、前記ケーソン底盤を打設することで本設基礎杭とケーソン躯体を一体化することを特徴とする本設基礎杭を利用したケーソン支持方法。 In constructing the caisson bottom plate according to claim 2 , the foundation concrete is cast to a thickness substantially the same as that of the caisson blade, and the main foundation pile is cut so that the top surface and the cut surface of the foundation concrete are substantially aligned. A caisson support method using a permanent foundation pile, wherein the permanent foundation pile and the caisson frame are integrated by driving the caisson bottom plate.
JP2002300844A 2002-10-15 2002-10-15 Caisson laying method using main foundation pile Expired - Fee Related JP3850785B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002300844A JP3850785B2 (en) 2002-10-15 2002-10-15 Caisson laying method using main foundation pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002300844A JP3850785B2 (en) 2002-10-15 2002-10-15 Caisson laying method using main foundation pile

Publications (2)

Publication Number Publication Date
JP2004137685A JP2004137685A (en) 2004-05-13
JP3850785B2 true JP3850785B2 (en) 2006-11-29

Family

ID=32449416

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002300844A Expired - Fee Related JP3850785B2 (en) 2002-10-15 2002-10-15 Caisson laying method using main foundation pile

Country Status (1)

Country Link
JP (1) JP3850785B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106498951A (en) * 2016-11-30 2017-03-15 上海市机械施工集团有限公司 A kind of shaft excavation construction method

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4733476B2 (en) * 2005-09-02 2011-07-27 株式会社ピーエス三菱 Method for constructing suspended concrete frames
KR100999880B1 (en) 2010-05-25 2010-12-09 정관균 Apparatus for pressing steel pipe and method for well foundation construction using thereof
CN102322069B (en) * 2011-07-04 2013-09-04 浙江省交通规划设计研究院 Underwater combination base of open caisson and steel pipe piles and construction method
CN102561406A (en) * 2011-12-15 2012-07-11 上海市城市建设设计研究总院 Construction method for controlling back soil body deformation of open caisson
CN104141316B (en) * 2014-07-24 2016-06-29 中交公路长大桥建设国家工程研究中心有限公司 A kind of caisson composite foundation with suction type apron shell and varied rigid link stake
KR101719246B1 (en) * 2016-04-19 2017-03-23 한준수 Apparatus for pressing open caisson
JP6969901B2 (en) * 2017-05-24 2021-11-24 清水建設株式会社 Co-fall suppression structure and caisson sinking method
CN110761325A (en) * 2019-10-25 2020-02-07 中铁第四勘察设计院集团有限公司 Automatic control system and method for mud-water balance open caisson vehicle station in soft soil area
CN111809623A (en) * 2020-06-30 2020-10-23 中国二十冶集团有限公司 A anchor case and earth anchor for earth anchor press-in type open caisson engineering
CN115492144B (en) * 2022-09-15 2023-08-29 中国一冶集团有限公司 Construction method of pipe-jacking open caisson in sand area

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106498951A (en) * 2016-11-30 2017-03-15 上海市机械施工集团有限公司 A kind of shaft excavation construction method

Also Published As

Publication number Publication date
JP2004137685A (en) 2004-05-13

Similar Documents

Publication Publication Date Title
JP6830748B2 (en) Open caisson construction structure and its construction method
JP6010070B2 (en) Temporary closing method for existing underwater structures
KR101070426B1 (en) Improved Underpinning Method Using the micro pile
KR20090002344A (en) Land-side protection wall that use ground structure
CN108842798B (en) Static pressure sinking construction method of prefabricated pouring type open caisson
JP3850785B2 (en) Caisson laying method using main foundation pile
KR20190022132A (en) Top-down method using precast-concrete colum
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
JPH07268885A (en) Method of drive construction used for construction of subsurface structure
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
KR100912574B1 (en) Retaining wall system using strut assembly and excavating method using the same
JP2004285735A (en) Method of constructing temporary landing bridge by using truss frame
JP4226954B2 (en) Underpinning method and viaduct
JP2002364004A (en) Installation method for underwater foundation
KR100663109B1 (en) Method for Constructing an Underground Structure Using Up-down Method
JP6938198B2 (en) Construction method
JPH09144049A (en) Temporary holding method of construction
JPH0559728A (en) Sheathing work above underground structure
JP5852475B2 (en) Pile foundation reconstruction method
JPH06341154A (en) Construction of underground building frame
JP6000414B2 (en) Pile foundation reconstruction method and pile foundation structure
JP2005083123A (en) Earth retaining combined wall and method for constructing earth retaining combined wall
KR100593203B1 (en) a deck supportframe and a construction methed
JP6534026B2 (en) Seismic isolation building and its construction method
KR102601694B1 (en) Method for demolishing underground building

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060306

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060314

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060512

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060608

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20060628

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060822

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060830

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090908

Year of fee payment: 3

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090908

Year of fee payment: 3

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090908

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees