JP2004176434A - Method for constructing structure and underground skeleton - Google Patents
Method for constructing structure and underground skeleton Download PDFInfo
- Publication number
- JP2004176434A JP2004176434A JP2002344889A JP2002344889A JP2004176434A JP 2004176434 A JP2004176434 A JP 2004176434A JP 2002344889 A JP2002344889 A JP 2002344889A JP 2002344889 A JP2002344889 A JP 2002344889A JP 2004176434 A JP2004176434 A JP 2004176434A
- Authority
- JP
- Japan
- Prior art keywords
- underground
- skeleton
- divided
- constructed
- ground
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
【0001】
【発明の属する技術分野】
本発明は、地下躯体と地上躯体とから構成された構造物の構築方法及び地下躯体に関する。
【0002】
【従来の技術】
従来、地下躯体と地上躯体とから構成された構造物の構築方法としては、地盤を掘削して構築された掘削溝の底面に基礎を構築し、この基礎に立設させた支柱により1階床を支持しながら、地上面と略同一高さに1階床を構築した後に、1階床を作業床として地下躯体及び地上躯体の構築作業を同時進行させる二段打ち工法が存在している(例えば、特許文献1参照。)。
【0003】
なお、本出願人は、先に特願2002−278958号に示すように、地盤を掘削して構築された掘削溝の底面に仮設基礎を構築し、この仮設基礎に立設した支柱に1階床を支持させ、1階床を作業床として地上躯体を構築しながら、仮設基礎と一体化するようにして本設基礎を構築した後に、地下躯体及び地上躯体の構築作業を同時進行させる構造物の構築方法を出願している。
【0004】
【特許文献1】
特許第3053938号公報(第1−3頁、第1図)
【0005】
【発明が解決しようとする課題】
しかしながら、従来の二段打ち工法及び構造物の構築方法では、以下の問題がある。
まず、従来の二段打ち工法では、基礎が地上躯体を支持可能な強度を備えている必要があるため、通常、基礎に構真柱を設けている。ところが、前記二段打ち工法では、完成した地下躯体が直接基礎となることから、地下躯体の構築後に構真柱が不必要となる。すなわち、完成した構造物に不必要な構造を設けるために施工費用が高くなってしまうとともに、施工期間が長期化してしまうという問題がある。
また、仮設基礎を用いた構造物の構築方法では、1階床を構築する際に、1階床は仮設基礎によって支持されており、構真柱を設ける必要はなくなるが、1階床が早期に構築されるため、地下躯体を構築する前に1階床によって掘削溝全体が塞がれてしまう。これにより、地上面に設置されたクレーン等の揚重機を用いて、掘削溝内に地下躯体の部材を搬入することが困難になり、施工効率が低くなってしまう場合があるという問題がある。
【0006】
本発明は、前記問題を解決するためになされたものであり、地下躯体と地上躯体とから構成される構造物において、地下躯体及び地上躯体の構築作業を同時進行させる場合に、構真柱を設けることなく、揚重機を用いて地下躯体を構築することができ、従来の構築方法と比較して、施工費用を削減することができるとともに、効率良く施工することができる構造物の構築方法及び地下躯体を提供することを課題としている。
【0007】
【課題を解決するための手段】
本発明は、前記課題を解決すべく構成されるものであり、請求項1に記載の発明は、地下躯体と地上躯体とから構成された構造物の構築方法であって、(1)地盤を掘削し、地下躯体を構築するための掘削溝を構築する掘削溝構築工程と、(2)掘削溝内の一部に、地盤に隣接するようにして分割地下躯体を構築し、分割地下躯体上に揚重機を設置する分割地下躯体構築工程と、(3)揚重機を用いて、分割地下躯体に隣接するようにして他の分割地下躯体を増築する分割地下躯体増築工程と、(4)必要回数分の分割地下躯体増築工程を繰り返すことにより、掘削溝内に複数の分割地下躯体から構成される地下躯体を構築するとともに、分割地下躯体上で地上躯体を構築する構造物構築工程とを含むことを特徴としている。
【0008】
また、請求項2に記載の発明は、請求項1に記載の構造物の構築方法であって、分割地下躯体は、掘削溝の底面上に構築された基礎部材と、基礎部材に立設された支柱と、地下躯体と地上躯体の境であり、支柱により支持された1階床とから構成されていることを特徴としている。
【0009】
また、請求項5に記載の発明は、地盤を掘削した掘削溝内に構築された地下躯体であって、複数の分割地下躯体に分割されており、複数の分割地下躯体は、地盤に隣接して最初に構築された分割地下躯体と、先行して直前に構築された分割地下躯体に隣接するようにして増築される1又は複数の他の分割地下躯体とから形成されることを特徴としている。
【0010】
ここで、揚重機とは、クレーン等の搬送装置であり、地下躯体の部材を搬送可能な吊上げ能力を備えていればよく、その構成は限定されるものではない。
また、1階床とは、地下躯体と地上躯体との境となる床であり、通常、地上面と略同一高さに構築されるが、地盤面最寄階であってもよい。
【0011】
請求項1、請求項2及び請求項5に記載の発明によれば、地下躯体及び地上躯体の構築作業を同時進行させる場合に、掘削溝内で分割地下躯体を順次に増築して地下躯体を構築することにより、分割地下躯体が地下躯体及び地上躯体全体の重量を支持する必要がないため、分割地下躯体に構真柱を設ける必要がなくなり、施工費用を削減することができる。
さらに、掘削溝内で分割地下躯体を順次に増築することにより、掘削溝全体が1階床によって早期に塞がれてしまうことがなくなる。これにより、揚重機を用いて掘削溝内に分割地下躯体を順次に増築することができるため、構造物を効率良く施工することができる。
【0012】
また、請求項3に記載の発明は、請求項1又は請求項2に記載の構造物の構築方法であって、分割地下躯体増築工程において、増築した分割地下躯体上に揚重機を移設し、揚重機を用いて他の分割地下躯体を構築することを特徴としている。
【0013】
この発明によれば、増築した分割地下躯体上に揚重機を移設し、この分割地下躯体に隣接させて構築する分割地下躯体の構築位置の近傍で作業を行うことができるため、作業範囲が小さい揚重機であっても、分割地下躯体を増築することができる。
【0014】
また、請求項4に記載の発明は、請求項2に記載の構造物の構築方法であって、分割地下躯体構築工程において、揚重機は、分割地下躯体の支柱に支持されており、支柱に沿って上昇可能であることを特徴としている。
【0015】
ここで、支柱に支持される揚重機としては、例えば、支柱に支持された本体に設けられた駆動モータや可倒式ジブ等の装置を用いて搬送物を吊上げるタワークレーン等の定置型の揚重機がある。
【0016】
この発明によれば、定置型の揚重機は、支柱に支持されることにより安定性が高くなっているため、移動式の揚重機と比較して、作業範囲及び吊上げ能力を大きくすることができ、地下躯体を効率良く構築することができる。また、揚重機は、支柱に沿って上昇可能であることから、地下躯体上に地上躯体を構築する場合には、地上躯体を効率良く構築することができる。
【0017】
したがって、本発明の構造物の構築方法及び地下躯体では、地下躯体及び地上躯体の構築作業を同時進行させる場合に、構真柱を設けることなく、揚重機を用いて掘削溝内に分割地下躯体を順次に増築し、地下躯体を効率良く構築することができるため、従来の構真柱や仮設基礎を設ける構築方法と比較して、施工費用を削減することができるとともに、施工期間を短縮することができる。
【0018】
【発明の実施の形態】
以下、添付図面を参照して、本発明の実施形態について詳細に説明する。
なお、各実施形態の説明において、同一の構成要素に関しては同一の符号を付し、重複した説明は省略するものとする。
【0019】
本発明の実施形態に係る構造物の構築方法及び地下躯体は、地下躯体を有する建物に適用可能である。
【0020】
[第1実施形態]
まず、本発明の第1実施形態に係る構造物の構築方法及び地下躯体について説明する。
図1は、本発明の第1実施形態に係る掘削溝構築工程を示した図で、(a)は山留め壁及び山留め支柱の施工後を示した側断面図、(b)は切梁の架設後を示した側断面図である。図2は、本発明の第1実施形態に係る分割地下躯体構築工程及び分割地下躯体増築工程を示した図で、(a)は第1分割地下躯体の構築後を示した側断面図、(b)は第2分割地下躯体の構築後を示した側断面図である。図3は、本発明の第1実施形態に係る構造物構築工程を示した図で、(a)は第3分割地下躯体の構築後を示した側断面図、(b)は第4分割地下躯体の構築後を示した側断面図である。図4は、本発明の第1実施形態に係る構造物構築工程を示した図で、地下躯体の構築後に切梁及び山留め支柱を撤去した様子を示した側断面図である。
【0021】
ここで、本発明の実施形態に係る建物について説明する。
本実施形態に係る建物1は、図4に示すように、地上面GLよりも上方に構築された地上躯体2と、地盤を掘削した掘削溝4内に構築された地下躯体3とから構成され、地上面GLと略同一高さの1階床13を境として各躯体2,3が区分されている。また、この建物1は、掘削溝4の底面の全域を覆うようにして構築された複数の基礎部材11による直接基礎によって支持されている。
【0022】
なお、第1実施形態に係る地下躯体3は、図4の左右方向において略同一の大きさで4個の分割地下躯体10に分割されており、地盤に隣接して最初に構築された分割地下躯体10と、先行して直前に構築された分割地下躯体10に隣接するようにして増築される3個の分割地下躯体10とから形成され、図4の左側から右側に向かって、第1分割地下躯体10a,第2分割地下躯体10b,第3分割地下躯体10c,第4分割地下躯体10dの順で連続している。
なお、第1実施形態では、地下躯体3を4個の分割地下躯体10に分割したが、地下躯体3を分割する個数は限定されるものではなく、地下躯体3の大きさや、施工に用いる建設機械の性能等を考慮して、効率良く施工を行えるように適宜に定めることが好ましい。
【0023】
分割地下躯体10は、掘削溝4の底面上の一部に構築された基礎部材11と、基礎部材11に立設された支柱12と、地下躯体3と地上躯体2の境であり、支柱12により支持された1階床13a及び地下1階床13bと、基礎部材11上に構築された最下階床13cとから構成される。ここで、分割地下躯体10は、複数(本実施形態では4個)の分割地下躯体10が連続することにより、地下躯体3を構成している。1個の分割地下躯体10の基礎部材11は、1階床13a上における地下躯体3及び地上躯体2の部材の搬入やその構築途中の荷重を支持するものであり、基礎部材11に構真柱を設けることなく、必要な強度が充分に確保されている。
【0024】
次に、本発明の第1実施形態に係る構造物の構築方法により建物1を構築する場合について説明する。
(1)掘削溝構築工程
まず、図1(a)に示すように、構築する地下躯体3(図4参照)の形状に対応させて山留め壁20及び山留支柱21を地盤内に施工しながら、図1(b)に示すように、山留め壁20に囲まれた区域の内側の地盤を掘削し、地下躯体3を構築するための掘削溝4を構築する。このとき、掘削溝4の深度に対応させて順次に切梁22を設置し、山留め壁20を補強しながら掘削作業を行う。
【0025】
(2)分割地下躯体構築工程
続いて、図2(a)に示すように、掘削溝4の近傍となる地上面GLに移動式のクローラクレーン30を設置する。
ここで、クローラクレーン30は、キャタピラ等の走行手段を備えた既存の揚重機であり、分割地下躯体10の各部材を搬送可能な吊上げ能力を備えていればよく、その構成は限定されるものではない。
そして、クローラクレーン30を用いて、図2(a)の左側となる側壁に隣接するようにして第1分割地下躯体10aの基礎部材11を掘削溝4の底面上に構築する。さらに、クローラクレーン30を用いて基礎部材11に支柱12を立設するとともに、支柱12に地下1階床13bの梁を設置した後に、地上面GLと略同一高さである各支柱12の上部に1階床13aを構築して支持させ、掘削溝4内に第1分割地下躯体10aを構築する。このとき、分割地下躯体10が鉄骨鉄筋コンクリート造である場合には、支柱12及び地下1階床13bの梁に本設の部材を適用する。また、分割地下躯体10が鉄筋コンクリート造である場合には、仮設の支柱12を適用し、地下1階床13bの梁を設けて適宜に水平方向の補強を行ってもよい。
その後、第1分割地下躯体10aの1階床13a上にクローラクレーン30を移動させて設置する。
【0026】
(3)分割地下躯体増築工程
さらに、図2(b)に示すように、第1分割地下躯体10aの1階床13a上のクローラクレーン30を用いて、第1分割地下躯体10aに隣接するようにして第2分割地下躯体10bを増築する。ここで、本発明では、掘削溝4内で分割地下躯体10を順次に増築することから、掘削溝4全体が1階床13aによって早期に塞がれてしまうことがないため、分割地下躯体10を増築する際に、クローラクレーン30を用いて各部材を掘削溝4内に搬入することができる。また、クローラクレーン30を第1分割地下躯体10aの1階床13a上に移動させ、第2分割地下躯体10bを構築する位置の近傍で作業を行うことができるため、作業範囲が小さいクローラクレーン30であっても、第2分割地下躯体10bを構築することができる。
【0027】
(4)構造物構築工程
また、図3(a)に示すように、第2分割地下躯体10bの構築後に、第2分割地下躯体10bの1階床13上にクローラクレーン30を移動させ、分割地下躯体増築工程を繰り返すことにより、第2分割地下躯体10bに隣接するようにして第3分割地下躯体10cを構築する。さらに、第1分割地下躯体10aの1階床13aを作業床として、第1分割地下躯体10aの支柱12及び地下1階13bの梁の周囲や、基礎部材11上にコンクリートを打設して地下躯体3を構築するとともに、第1分割地下躯体10a上で地上躯体2を構築する。ここで、分割地下躯体10が鉄筋コンクリート造である場合には、仮設の支柱12及び地下1階床13bの梁の周囲や、基礎部材11上に鉄筋を設置した後にコンクリートを打設する。
【0028】
続いて、図3(b)に示すように、分割地下躯体増築工程を繰り返すことにより、第3分割地下躯体10cに隣接させて第4分割地下躯体10dを構築するとともに、第1分割地下躯体10a及び第2分割地下躯体10bの1階床13aを作業床として地下躯体3及び地上躯体2を構築することができる。
最後に、クローラクレーン30を地上面GLに移動させ、図4に示すように、各分割地下躯体10の1階床13aを作業床として地下躯体3及び地上躯体2を同時進行で構築する。なお、地下躯体3の最下階床13cは、4個の分割地下躯体10を連続させた後に、各分割地下躯体10の基礎部材11上にコンクリートを打設して構築してもよい。
なお、地下躯体3によって掘削溝4の壁面の土圧を支持可能な状態になった時点で、山留め支柱21及び切梁22(図1参照)を撤去する。
【0029】
したがって、本発明の第1実施形態に係る構造物の構築方法及び地下躯体では、地下躯体3及び地上躯体2の構築作業を同時進行させる場合に、構真柱を設けることなく、クローラクレーン30を用いて掘削溝4内に分割地下躯体10を効率良く順次に構築することができるため、従来の構真柱や仮設基礎を用いて1階床を支持する構築方法と比較して、施工費用を削減することができるとともに、施工期間を短縮することができる。
【0030】
[第2実施形態]
次に、本発明の第2実施形態に係る構造物の構築方法について説明する。
図5は、本発明の第2実施形態に係る分割地下躯体構築工程を示した図で、(a)は第1分割地下躯体の構築後に、第1分割地下躯体にタワークレーンを設置した様子を示した側断面図、(b)は第3分割地下躯体の構築後を示した側断面図である。図6は、本発明の第2実施形態に係る分割地下躯体増築工程及び構造物構築工程を示した図で、(a)は第4分割地下躯体の構築後を示した側断面図、(b)は地下躯体及び地上躯体を構築する様子を示した側断面図である。
【0031】
本発明の第2実施形態に係る構造物の構築方法は、前記第1実施形態の構造物の構築方法と略同様の構成であり、分割地下躯体10を増築させる際に、タワークレーン40を用いて作業をすることが異なる。なお、以下の説明において、第1実施形態と同様の構成については、その説明を省略する。
【0032】
まず、本発明の第2実施形態に係る構造物の構築方法に用いられるタワークレーン40について説明する。
タワークレーン40は、図5及び図6に示すように、本体41に設けられた駆動モータ(図示せず)や可倒式ジブ42等の装置を用いて搬送物を吊上げる定置型の揚重機であり、本体41は分割地下躯体10の支柱12に支持されており、本体41は支柱12に沿って上昇可能である。タワークレーン40は、支柱12に支持されることにより安定性が高くなっているため、移動式のクローラクレーン等の揚重機と比較して、作業範囲及び吊上げ能力が大きくなっている。
【0033】
次に、本発明の第2実施形態に係る構造物の構築方法について説明する。
まず、図5(a)に示すように、第1実施形態の掘削溝構築工程及び分割地下躯体構築工程と同様にして、掘削溝4内に第1分割地下躯体10aを構築し、図5(a)において左側から2本目となる第1分割地下躯体10aの支柱12にタワークレーン40を設置する。なお、第2実施形態では、左側から2本目となる支柱12にタワークレーン40を設置しているが限定されるものではなく、タワークレーン40の作業範囲や吊り上げ能力に応じて、左側から2本目以降の支柱12に設置してもよい。そして、図5(b)に示すように、タワークレーン40を用いて第2分割地下躯体10b及び第3分割地下躯体10cを構築し、第2分割地下躯体10b及び第3分割地下躯体10cの1階床13aを作業床として、各分割地下躯体10の支柱12及び地下1階床13bの梁の周囲や、基礎部材11上にコンクリートを打設して地下躯体3を構築するとともに、各分割地下躯体10上で地上躯体2を構築する。このとき、定置型のタワークレーン40の作業範囲及び吊上げ能力が大きいことから、タワークレーン40を移動させる必要がないため、効率良く施工することができる。
【0034】
そして、図6(a)に示すように、第3分割地下躯体10cの構築と同様にして第4分割地下躯体10dを構築し、掘削溝4内に地下躯体3となる4個の分割地下躯体10を連続させる。なお、第1実施形態と同様にして、第2実施形態でも地下躯体3を4個の分割地下躯体10に分割したが、地下躯体3を分割する個数は限定されるものではなく、各種施工条件に応じて適宜に定めることが好ましい。
その後、図6(b)に示すように、タワークレーン40を用いて地下躯体3及び地上躯体2を同時進行で構築する。なお、地下躯体3の最下階床13cは、4個の分割地下躯体10を連続させた後に、各分割地下躯体10の基礎部材11上にコンクリートを打設して構築してもよい。
したがって、第2実施形態における構造物の構築方法では、地上躯体2の構築において、上方に延長された支柱12に沿ってタワークレーン40を上昇させることができるため、地上躯体2を効率良く施工することができる。
【0035】
以上、本発明の好適な実施形態についての一例を説明したが、本発明は前記実施形態に限定されず、本発明の趣旨を逸脱しない範囲で適宜設計変更が可能である。
例えば、基礎部材11の構成は限定されるものではなく、複数の分割地下躯体10によって建物1を確実に支持することができる構成であればよい。そのため、予め工場等で成形されたプレキャスト部材を用いることにより、施工期間を短くすることが好ましい。
【0036】
【発明の効果】
本発明の構造物の構築方法及び地下躯体によれば、地下躯体及び地上躯体の構築作業を同時進行させる場合に、充分な強度を備えた直接基礎を有する分割地下躯体を掘削溝内に順次に増築して地下躯体を構築している。これにより、分割地下躯体に構真柱を設ける必要がないため、従来の構真柱を設ける構築方法と比較して、施工費用を削減することができる。
また、掘削溝内で分割地下躯体を順次に増築するため、掘削溝全体が1階床によって早期に塞がれてしまうことがない。これにより、揚重機を用いて掘削溝内に分割地下躯体を簡易に増築することができるため、仮設基礎を設ける構築方法と比較して、構造物を効率良く施工することができ、施工期間を短縮することができる。
【図面の簡単な説明】
【図1】本発明の第1実施形態に係る掘削溝構築工程を示した図で、(a)は山留め壁及び山留め支柱の施工後を示した側断面図、(b)は切梁の架設後を示した側断面図である。
【図2】本発明の第1実施形態に係る分割地下躯体構築工程及び分割地下躯体増築工程を示した図で、(a)は第1分割地下躯体の構築後を示した側断面図、(b)は第2分割地下躯体の構築後を示した側断面図である。
【図3】本発明の第1実施形態に係る構造物構築工程を示した図で、(a)は第3分割地下躯体の構築後を示した側断面図、(b)は第4分割地下躯体の構築後を示した側断面図である。
【図4】本発明の第1実施形態に係る構造物構築工程を示した図で、地下躯体の構築後に切梁及び山留め支柱を撤去した様子を示した側断面図である。
【図5】本発明の第2実施形態に係る分割地下躯体構築工程を示した図で、(a)は第1分割地下躯体の構築後に、第1分割地下躯体にタワークレーンを設置した様子を示した側断面図、(b)は第3分割地下躯体の構築後を示した側断面図である。
【図6】本発明の第2実施形態に係る分割地下躯体増築工程及び構造物構築工程を示した図で、(a)は第4分割地下躯体の構築後を示した側断面図、(b)は地下躯体及び地上躯体を構築する様子を示した側断面図である。
【符号の説明】
1・・・・建物
2・・・・地上躯体
3・・・・地下躯体
4・・・・掘削溝
10・・・・分割地下躯体
11・・・・支持部材
12・・・・支柱
13・・・・1階床
30・・・・クローラクレーン
40・・・・タワークレーン[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a method for constructing a structure composed of an underground skeleton and an above-ground skeleton, and an underground skeleton.
[0002]
[Prior art]
2. Description of the Related Art Conventionally, as a method of constructing a structure composed of an underground frame and an above-ground frame, a foundation is constructed on a bottom surface of an excavated trench constructed by excavating the ground, and a first floor is provided by a column erected on the foundation. There is a two-step construction method in which the first floor is constructed at substantially the same height as the ground surface while supporting the ground floor, and then the construction work of the underground skeleton and the ground skeleton is simultaneously performed using the first floor as a work floor ( For example, see Patent Document 1.)
[0003]
In addition, as shown in Japanese Patent Application No. 2002-278958, the present applicant has constructed a temporary foundation on the bottom surface of an excavation trench constructed by excavating the ground, and has a first floor on a column erected on the temporary foundation. A structure that supports the floor and builds the main foundation in such a way that it is integrated with the temporary foundation while the ground floor is constructed with the first floor as the working floor, and then the construction work of the underground skeleton and the ground skeleton proceed simultaneously. Has applied for a construction method.
[0004]
[Patent Document 1]
Japanese Patent No. 3053938 (pages 1-3, FIG. 1)
[0005]
[Problems to be solved by the invention]
However, the conventional two-step construction method and the construction method of a structure have the following problems.
First, in the conventional two-step construction method, since the foundation needs to have a strength capable of supporting the ground frame, usually, the foundation is provided with a straight pillar. However, in the above-mentioned two-step construction method, since the completed underground skeleton is directly used as the foundation, the straight pillar is not required after the underground skeleton is constructed. That is, there is a problem in that an unnecessary structure is provided in the completed structure, thereby increasing the construction cost and prolonging the construction period.
In addition, in the method of constructing a structure using a temporary foundation, when the first floor is constructed, the first floor is supported by the temporary foundation, and there is no need to provide a timber pillar, but the first floor is quickly installed. Therefore, the entire excavation trench is closed by the first floor before the underground skeleton is constructed. As a result, it becomes difficult to carry the member of the underground skeleton into the excavation trench using a lifting machine such as a crane installed on the ground surface, and there is a problem that the construction efficiency may be reduced.
[0006]
The present invention has been made in order to solve the above-described problems, and in a structure composed of an underground skeleton and an above-ground skeleton, when the construction work of the underground skeleton and the above-ground skeleton is simultaneously performed, Without providing, it is possible to construct an underground skeleton using a lifting machine, and compared to the conventional construction method, it is possible to reduce the construction cost and to construct a structure that can be constructed efficiently and The task is to provide underground structures.
[0007]
[Means for Solving the Problems]
The present invention is configured to solve the above-described problem, and the invention according to claim 1 is a method for constructing a structure including an underground skeleton and an above-ground skeleton, and (1) a method for constructing a ground. Excavating and constructing an excavation trench for constructing an underground skeleton; and (2) constructing a divided underground skeleton in a part of the excavation trench so as to be adjacent to the ground, and on the divided underground skeleton. A divided underground skeleton building step of installing a lifting machine in a yard, and (3) a divided underground skeleton building extending step of using a lifting machine to extend another divided underground body adjacent to the divided underground skeleton, and (4) necessary Includes a structure construction step of constructing an underground skeleton composed of a plurality of divided underground skeletons in the excavation trench by repeating the divided underground skeleton extension process for the number of times, and constructing an aboveground skeleton on the divided underground skeleton It is characterized by:
[0008]
According to a second aspect of the present invention, there is provided the method for constructing a structure according to the first aspect, wherein the divided underground skeleton is erected on a base member constructed on the bottom surface of the excavation groove and on the foundation member. It is characterized by being composed of a supporting column and a first-floor floor which is a boundary between the underground frame and the above-ground frame and supported by the column.
[0009]
The invention according to claim 5 is an underground structure constructed in an excavation trench excavating the ground, wherein the underground structure is divided into a plurality of divided underground structures, and the plurality of divided underground structures are adjacent to the ground. , And is formed from one or a plurality of other underground skeletons that are expanded so as to be adjacent to the previously pre-constructed underground skeleton. .
[0010]
Here, the hoist is a transfer device such as a crane, and may have a lifting capability capable of transferring members of the underground skeleton, and the configuration is not limited.
In addition, the first floor is a floor serving as a boundary between the underground skeleton and the above-ground skeleton, and is usually constructed at substantially the same height as the ground surface, but may be the nearest floor on the ground surface.
[0011]
According to the first, second and fifth aspects of the present invention, in the case where the construction work of the underground skeleton and the above-ground skeleton is simultaneously proceeded, the divided underground skeleton is sequentially expanded in the excavation trench to form the underground skeleton. By constructing, the divided underground skeleton does not need to support the weight of the entire underground skeleton and the above-ground skeleton, so that it is not necessary to provide a straight pillar in the divided underground skeleton, and the construction cost can be reduced.
Further, by sequentially increasing the divided underground skeletons in the excavation trench, the entire excavation trench is not blocked by the first floor at an early stage. Thus, the divided underground skeleton can be sequentially expanded in the excavation trench by using the lifting machine, so that the structure can be constructed efficiently.
[0012]
Further, the invention according to
[0013]
According to the present invention, the lifting machine is relocated on the expanded underground skeleton, and work can be performed in the vicinity of the construction position of the divided underground skeleton to be constructed adjacent to the divided underground skeleton, so that the working range is small. Even with a hoist, a divided underground skeleton can be added.
[0014]
According to a fourth aspect of the present invention, there is provided the method for constructing a structure according to the second aspect, wherein the lifting machine is supported on the support of the divided underground skeleton in the divided underground skeleton building step. It is characterized by being able to ascend along.
[0015]
Here, as the lifting machine supported by the column, for example, a stationary type such as a tower crane that lifts a conveyed object using a device such as a drive motor or a collapsible jib provided on a main body supported by the column. There is a hoist.
[0016]
According to the present invention, since the stationary type lifting machine has high stability by being supported by the column, the working range and the lifting capacity can be increased as compared with the mobile type lifting machine. In addition, the underground skeleton can be efficiently constructed. Further, since the hoist can be lifted along the columns, the above-mentioned building can be efficiently constructed when building the above-ground building on the underground building.
[0017]
Therefore, in the method of constructing a structure and the underground skeleton according to the present invention, in the case where the construction work of the underground skeleton and the above-ground skeleton is simultaneously performed, without providing a straight pillar, the underground skeleton is divided into the excavation trench by using the lifting machine. Can be constructed sequentially, and the underground skeleton can be constructed efficiently, so that the construction cost can be reduced and the construction period can be shortened, compared to the conventional construction method of installing straight columns and temporary foundations. be able to.
[0018]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
In the description of each embodiment, the same components will be denoted by the same reference symbols, without redundant description.
[0019]
The structure construction method and underground skeleton according to the embodiment of the present invention are applicable to a building having an underground skeleton.
[0020]
[First Embodiment]
First, a method for constructing a structure and an underground skeleton according to the first embodiment of the present invention will be described.
Drawing 1 is a figure showing a digging trench construction process concerning a 1st embodiment of the present invention, (a) is a sectional side elevation showing after a pier and a pier are constructed, and (b) is erection of a cutting beam It is the sectional side view which showed the back. FIGS. 2A and 2B are views showing a divided underground skeleton building step and a divided underground skeleton extension step according to the first embodiment of the present invention. FIG. b) is a side sectional view showing a state after the construction of the second divided underground skeleton. 3A and 3B are views showing a structure building process according to the first embodiment of the present invention, wherein FIG. 3A is a side sectional view showing a state after the construction of a third divided underground skeleton, and FIG. FIG. 4 is a side cross-sectional view showing a state after a skeleton is constructed. FIG. 4 is a diagram showing a structure building process according to the first embodiment of the present invention, and is a side cross-sectional view showing a state in which a girder and a retaining pillar are removed after the construction of the underground skeleton.
[0021]
Here, a building according to the embodiment of the present invention will be described.
As shown in FIG. 4, the building 1 according to the present embodiment includes an above-
[0022]
The
In the first embodiment, the
[0023]
The divided
[0024]
Next, a case where the building 1 is constructed by the method for constructing a structure according to the first embodiment of the present invention will be described.
(1) Excavation Groove Construction Step First, as shown in FIG. 1A, while retaining the retaining
[0025]
(2) Split Underground Building Construction Step Subsequently, as shown in FIG. 2A, a
Here, the
Then, using the
Thereafter, the
[0026]
(3) Divided Underground Building Extension Step Further, as shown in FIG. 2 (b), using the
[0027]
(4) Structure Construction Step As shown in FIG. 3A, after the construction of the second divided underground frame 10b, the
[0028]
Subsequently, as shown in FIG. 3 (b), the fourth divided
Finally, the
When the
[0029]
Therefore, in the method for constructing a structure and the underground skeleton according to the first embodiment of the present invention, when the construction work of the
[0030]
[Second embodiment]
Next, a method for constructing a structure according to the second embodiment of the present invention will be described.
FIG. 5 is a diagram showing a divided underground skeleton building process according to the second embodiment of the present invention. FIG. 5A shows a state where a tower crane is installed in the first divided underground skeleton after the first divided underground skeleton is constructed. The side sectional view shown, (b) is a side sectional view showing after the construction of the third divided underground skeleton. 6A and 6B are views showing a divided underground skeleton extension step and a structure building step according to the second embodiment of the present invention. FIG. 6A is a side sectional view showing a state after the fourth divided underground skeleton is constructed, and FIG. ) Is a side sectional view showing a state of constructing an underground skeleton and an above-ground skeleton.
[0031]
The method for constructing a structure according to the second embodiment of the present invention has substantially the same configuration as the method for constructing a structure according to the first embodiment, and uses the
[0032]
First, a
The
[0033]
Next, a method for constructing a structure according to the second embodiment of the present invention will be described.
First, as shown in FIG. 5A, the first divided
[0034]
Then, as shown in FIG. 6A, the fourth divided
Thereafter, as shown in FIG. 6B, the
Therefore, in the method of constructing a structure according to the second embodiment, the
[0035]
As described above, an example of a preferred embodiment of the present invention has been described. However, the present invention is not limited to the above-described embodiment, and a design can be appropriately changed without departing from the gist of the present invention.
For example, the configuration of the
[0036]
【The invention's effect】
According to the construction method and the underground skeleton of the structure of the present invention, when simultaneously performing the construction work of the underground skeleton and the above-ground skeleton, the divided underground skeleton having a direct foundation having sufficient strength is sequentially placed in the excavation trench. The basement is being built by adding an extension. Accordingly, since it is not necessary to provide the timber columns in the divided underground skeleton, the construction cost can be reduced as compared with the conventional construction method of providing the timber columns.
In addition, since the divided underground skeletons are sequentially expanded in the excavation trench, the entire excavation trench is not immediately closed by the first floor. As a result, it is possible to easily expand the divided underground skeleton in the excavation trench using the lifting machine, so that the structure can be constructed more efficiently than the construction method of providing a temporary foundation, and the construction period can be reduced. Can be shortened.
[Brief description of the drawings]
FIGS. 1A and 1B are diagrams showing an excavation trench construction process according to a first embodiment of the present invention, in which FIG. 1A is a side sectional view showing a state after a mountain retaining wall and a mountain retaining column are constructed, and FIG. It is the sectional side view which showed the back.
FIGS. 2A and 2B are views showing a divided underground skeleton building step and a divided underground skeleton expanding step according to the first embodiment of the present invention, wherein FIG. b) is a side sectional view showing a state after the construction of the second divided underground skeleton.
3A and 3B are diagrams showing a structure building process according to the first embodiment of the present invention, wherein FIG. 3A is a side sectional view showing a state after a third divided underground skeleton is constructed, and FIG. FIG. 4 is a side cross-sectional view showing a state after a skeleton is constructed.
FIG. 4 is a side cross-sectional view showing a structure building process according to the first embodiment of the present invention, in which a cutting beam and a retaining pillar are removed after an underground skeleton is built.
FIG. 5 is a view showing a divided underground skeleton building process according to a second embodiment of the present invention, wherein (a) shows a state in which a tower crane is installed in the first divided underground skeleton after the first divided underground skeleton is constructed. The side sectional view shown, (b) is a side sectional view showing after the construction of the third divided underground skeleton.
FIGS. 6A and 6B are views showing a divided underground building extension step and a structure building step according to the second embodiment of the present invention, wherein FIG. 6A is a side sectional view showing a state after the fourth divided underground building is constructed, and FIG. ) Is a side sectional view showing a state of constructing an underground skeleton and an above-ground skeleton.
[Explanation of symbols]
1
Claims (5)
(1)地盤を掘削し、前記地下躯体を構築するための掘削溝を構築する掘削溝構築工程。
(2)前記掘削溝内の一部に、前記地盤に隣接するようにして分割地下躯体を構築し、前記分割地下躯体上に揚重機を設置する分割地下躯体構築工程。
(3)前記揚重機を用いて、前記分割地下躯体に隣接するようにして他の分割地下躯体を増築する分割地下躯体増築工程。
(4)必要回数分の前記分割地下躯体増築工程を繰り返すことにより、前記掘削溝内に複数の前記分割地下躯体から構成される前記地下躯体を構築するとともに、前記分割地下躯体上で前記地上躯体を構築する構造物構築工程。A method for constructing a structure composed of an underground skeleton and an above-ground skeleton, comprising the following steps.
(1) An excavation trench construction step of excavating the ground and constructing an excavation trench for constructing the underground skeleton.
(2) A divided underground frame construction step of constructing a divided underground frame in a part of the excavation trench so as to be adjacent to the ground and installing a lifting machine on the divided underground frame.
(3) A divided underground frame extension step of using the lifting machine to extend another divided underground frame so as to be adjacent to the divided underground frame.
(4) The underground skeleton composed of a plurality of the divided underground skeletons is constructed in the excavation trench by repeating the required number of times of the divided underground skeleton building process, and the aboveground skeleton is formed on the divided underground skeleton. A structure construction process for constructing
前記掘削溝の底面上に構築された基礎部材と、
前記基礎部材に立設された支柱と、
前記地下躯体と前記地上躯体の境であり、前記支柱により支持された1階床と、から構成されていることを特徴とする請求項1に記載の構造物の構築方法。The split underground skeleton,
Foundation members constructed on the bottom surface of the digging trench,
A column erected on the base member,
2. The method according to claim 1, further comprising a first floor, which is a boundary between the underground skeleton and the above-ground skeleton, and supported by the columns. 3.
複数の分割地下躯体に分割されており、
複数の前記分割地下躯体は、前記地盤に隣接して最初に構築された前記分割地下躯体と、先行して直前に構築された前記分割地下躯体に隣接するようにして増築される1又は複数の他の前記分割地下躯体と、から形成されることを特徴とする地下躯体。An underground skeleton built in a digging trench that excavated the ground,
It is divided into multiple substructures,
The plurality of divided underground structures are firstly constructed adjacent to the ground, and the one or more divided underground structures are constructed so as to be adjacent to the previously divided immediately underground structure. An underground skeleton formed from the other divided underground skeleton.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002344889A JP2004176434A (en) | 2002-11-28 | 2002-11-28 | Method for constructing structure and underground skeleton |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2002344889A JP2004176434A (en) | 2002-11-28 | 2002-11-28 | Method for constructing structure and underground skeleton |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2004176434A true JP2004176434A (en) | 2004-06-24 |
Family
ID=32706207
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2002344889A Pending JP2004176434A (en) | 2002-11-28 | 2002-11-28 | Method for constructing structure and underground skeleton |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2004176434A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100633471B1 (en) | 2005-03-11 | 2006-10-13 | 삼성물산 주식회사 | The simultaneous construction method of upper ? lower stories' frame, and the construction method of structure with cleanrooms thereof |
KR101447636B1 (en) | 2012-05-23 | 2014-10-06 | 삼성물산(주) | apartment house remodeling construction method for shortage of term to construct with ensuring stock yard |
JP2015161059A (en) * | 2014-02-25 | 2015-09-07 | 大成建設株式会社 | building construction method |
CN105401741A (en) * | 2015-11-24 | 2016-03-16 | 中建钢构有限公司 | Basement roof reinforcement construction device and construction method thereof |
CN108678415A (en) * | 2018-07-04 | 2018-10-19 | 浙江理工大学 | A kind of assembled underground layer reinforced structure and increasing layer construction technology |
CN115162756A (en) * | 2022-06-22 | 2022-10-11 | 中建钢构工程有限公司 | Basement operation reinforcing structure and construction method |
-
2002
- 2002-11-28 JP JP2002344889A patent/JP2004176434A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100633471B1 (en) | 2005-03-11 | 2006-10-13 | 삼성물산 주식회사 | The simultaneous construction method of upper ? lower stories' frame, and the construction method of structure with cleanrooms thereof |
KR101447636B1 (en) | 2012-05-23 | 2014-10-06 | 삼성물산(주) | apartment house remodeling construction method for shortage of term to construct with ensuring stock yard |
JP2015161059A (en) * | 2014-02-25 | 2015-09-07 | 大成建設株式会社 | building construction method |
CN105401741A (en) * | 2015-11-24 | 2016-03-16 | 中建钢构有限公司 | Basement roof reinforcement construction device and construction method thereof |
CN108678415A (en) * | 2018-07-04 | 2018-10-19 | 浙江理工大学 | A kind of assembled underground layer reinforced structure and increasing layer construction technology |
CN115162756A (en) * | 2022-06-22 | 2022-10-11 | 中建钢构工程有限公司 | Basement operation reinforcing structure and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4722783B2 (en) | Foundation reinforcement method for existing buildings | |
RU2414563C1 (en) | Method to erect multistory subsurface structure | |
KR100313720B1 (en) | Composite Underground Structure Construction Method | |
JP3850785B2 (en) | Caisson laying method using main foundation pile | |
JP5465086B2 (en) | Construction method of underground structure | |
JP4558145B2 (en) | Seismic isolation method for existing buildings | |
JP2004176434A (en) | Method for constructing structure and underground skeleton | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
CN108612129B (en) | Reverse construction method based on recyclable steel platform | |
CN109183805B (en) | Prefabricated foundation pit bracing system and construction method thereof | |
KR20130021949A (en) | Reinforcement structure for wall of underground structure and construction method of underground structure using the same | |
JP2020125630A (en) | Building construction method | |
JPH0684690B2 (en) | Building basement extension method | |
KR0179708B1 (en) | Working method for underground structure of a building | |
CN114215106A (en) | Multi-pile support column structure adopting upper steel structure full-reverse construction method and construction method | |
KR100615149B1 (en) | A method of construction top-down for the ground fabric construction | |
JPH11140892A (en) | Method for excavating ground and method for constructing underground structure using the same | |
KR100663109B1 (en) | Method for Constructing an Underground Structure Using Up-down Method | |
JP6938198B2 (en) | Construction method | |
KR20100118000A (en) | Using reclamation steel perimeter beam and girder which the basement infrastructure construction method | |
CN101942839B (en) | Construction method for entering inside of open caisson and transporting soil | |
JP4879582B2 (en) | How to extend the basement floor under the foundation of an existing building | |
JP4267175B2 (en) | Construction method of underground structure | |
JP7510328B2 (en) | Construction Method | |
CN217174813U (en) | Foundation pit supporting structure combining floor slab and steel pipe support above operation subway tunnel |