JP3767347B2 - Reverse strike method - Google Patents

Reverse strike method Download PDF

Info

Publication number
JP3767347B2
JP3767347B2 JP2000251132A JP2000251132A JP3767347B2 JP 3767347 B2 JP3767347 B2 JP 3767347B2 JP 2000251132 A JP2000251132 A JP 2000251132A JP 2000251132 A JP2000251132 A JP 2000251132A JP 3767347 B2 JP3767347 B2 JP 3767347B2
Authority
JP
Japan
Prior art keywords
floor
basement
construction
floors
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000251132A
Other languages
Japanese (ja)
Other versions
JP2002061213A (en
Inventor
正則 綾
勝馬 角田
昭夫 丸山
徳亮 安藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2000251132A priority Critical patent/JP3767347B2/en
Publication of JP2002061213A publication Critical patent/JP2002061213A/en
Application granted granted Critical
Publication of JP3767347B2 publication Critical patent/JP3767347B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、建築物の地下構造体を施工するための逆打ち工法に関するものであり、従来の逆打ち工法を改良・高度化したスーパー逆打ち工法である。
【0002】
【従来の技術】
従来の逆打ち工法は、先ず1階床を施工した後、その下の地盤を掘削し、地下1階の床を施工すると、その下の地盤を掘削し、このような床構造の施工と下部の掘削とを交互に繰り返しながら順次下階へと工事を進め、最後に基礎梁を施工して地下構造体を完成させる工法である。各床構造が順次支保工として利用され、また、地下躯体が全て完成するまでの間、施工された地下躯体の荷重は、構真柱と呼ばれる鉄骨柱で仮支持される。
【0003】
このような逆打ち工法は、1階床の作業床としての利用、山留め架構の安定性、工期短縮などのメリットがあるため、近年大いに注目されるようになった。
【0004】
【発明が解決しようとする課題】
従来の逆打ち工法においても、地上と地下工事を並行して実施することにより、地下躯体を最下部から上方へと構築していく順打ち工法と比べて大幅な工期短縮が可能となる。
【0005】
しかし、施主から指定された工期が短い場合には、従来の逆打ち工法でも対応することができず、より工期の短縮を図ることのできる逆打ち工法が要望されている。また、建物の敷地が小さく、しかも地下部分が敷地一杯に構築され、地上鉄骨建方のためのヤードが非常に狭い場合などにおいては、地上と地下の同時施工を進めるに当り、地下工事の工期を短縮し、地上鉄骨建方開始を早めることが要望されている。
【0006】
本発明は、このような事情に鑑み、なされたものであり、従来の逆打ち工法よりもさらに工期の短縮を図ることのできる逆打ち工法を提供することにある。
【0007】
【課題を解決するための手段】
本発明の逆打ち工法は、建築物の地下構造体を上から下へと築造していく逆打ち工法であり、山留め壁内の掘削空間内に任意の階の床躯体を築造し、必要に応じて前記床躯体の床の下に切梁を架設した後、前記床躯体より下階の床を築造せずに飛ばして任意の複数フロア分を一気に掘削し、該任意の複数フロア下の床を先行して築造し、次いで該任意の複数フロア下の床を境に、下部で掘削工事と躯体工事を、上部で上階の床躯体の立ち上がり工事を、並行して行うことを特徴とする。
【0008】
例えば、図1に示すように、山留め壁内の上部を掘削し(1次掘削)、1階の床躯体を築造した後、必要に応じて2次掘削後に1階床の下に切梁(水平切梁支保工あるいは斜め切梁など)を架設し、地下1階を飛ばして地下2階の梁下まで一気に掘削し(3次掘削)、地下2階の床を先行して築造し、次いでこの地下2階の床を境に、下部で掘削工事(4次掘削)と地下3階以下の躯体工事を、上部で地下1階の床躯体の立ち上がり工事(地下1階の床と地下2階の外周壁)を、並行して行う。なお、図1では、1階の床躯体の築造から本発明の逆打ち工法を開始しているが、地下の任意の階から開始することも可能である。また、本発明の逆打ち工法を順次繰り返して地下構造体を築造することも可能である。
【0009】
前記切梁(1段目)は、山留め壁の上部の変形を極めて微小に抑えようとするものであり、地盤の硬軟条件や山留め壁の設定条件等によっては、この切梁無しで施工することができるものである。
【0010】
以上のような構成において、例えば地下1階の床躯体の築造を飛ばして地下2階の床スラブの築造を先行し、この地下2階の床スラブを境に、下部で4次掘削以降の工事を、上部で地下1階の床躯体の立ち上がり工事を並行して行うため、例えば図7に示すように、地下1階の床躯体の工事(地下2階の立ち上がり工事)がクリティカルパスから外れ、従来の本逆打ち工法と比較して約1.5カ月工期を短縮することが可能となる。また、地下1階の床躯体は、外壁逆打ち継ぎ部の無い順打ち工法で築造することができる。
【0011】
【発明の実施の形態】
以下、本発明を図示する一実施形態に基づいて説明する。この実施形態は、超高層ビルの地下3階の地下部分を築造する場合に本発明を適用した例である。図1は、本発明のスーパー逆打ち工法を工程順に示す断面図である。図2は、本発明における山留め壁・杭・構真柱の配置例を示す平面図である。図3は、各階の施工の詳細を示す断面図である。図4,図5は、本発明で用いる切梁の例を示す平面図である。図6は、1段目切梁の変形例を示す断面図である。図7は本発明と従来工法の各工程を比較した図である。
【0012】
本発明のスーパー逆打ち工法により、地下3階の地下部分を次に示すような手順で施工する(図1参照)。
【0013】
1 山留め壁(SMW)1を施工後、場所打ち杭2の打設と構真柱3の建込みを行う。山留め壁内の上部を1次掘削した後、1階の床躯体4を築造する。この床躯体4は、1階の床(梁を含む)4aと地下1階の外周壁(外周柱を含む)4bからなる。
【0014】
2 地下1階の床レベルまで2次掘削した後、外周壁4bに1段目切梁支保工11を架設する。
【0015】
3 地下1階の床躯体の築造を飛ばし、地下2階梁下まで一気に掘削し、2フロア分の3次掘削を行う。地下2階の床躯体6を築造し、その後、1段目切梁支保工11を解体する。この地下2階の床躯体6は、地下2階の床6aからなる。床躯体6の上方に大空間が形成される。
【0016】
4 地下3階の床レベルまで4次掘削し、地下3階の外周壁6bを築造した後、この外周壁6bに2段目切梁支保工12を架設する。同時に地下1階の床躯体5を順打ちで築造する。この地下1階の床躯体5は、地下1階の床5aと、地下2階の外周壁5bおよび内部柱・壁5cからなる。この時期から地上鉄骨建方工事が開始される。
【0017】
5 5次掘削・床付けの後、耐圧盤7を築造する。
【0018】
6 基礎・基礎梁8および地下3階床9を築造する。コンクリート硬化後、2段目切梁支保工12を解体する。地下1階と地下3階の外壁打ち継ぎ部を施工し、残りの内部柱・壁のコンクリートを打設すれば、地下躯体が完成する。
【0019】
次に、本発明の逆打ち工法の各要素技術について詳述する。図2に示すように、内部の杭2Aに構真柱3を設け、構真柱3を内部柱Aの柱鉄骨として利用し、外周部の杭2Bには構真柱3を設けない。これは、図3に示すように、外周部の杭2Bと外周柱Bが偏心し、外周柱Bの柱鉄骨を構真柱として使用できないためである。外周に構真柱が無いため、図3に示すように、外周躯体を頭部RCあご20・スタッドボルト21で山留め壁1に支持させる。さらに、山留め壁1の支持力には許容限界があるため、地下工事を早め、地上鉄骨の例えば5節建方前に耐圧盤7を打設し、外周柱Bの柱鉄骨の応力を外周部の杭2Bに伝達させる。
【0020】
コンクリートは、図3に示すように、普通コンクリートの順打ち部と、高性能AE減水剤を用いた特殊コンクリートのセミ圧入工法による後打ち部からなり、次の順番で打設される。
【0021】
1 1階の床躯体4(1階の床4a・地下1階の外周壁4b)の順打ち、 2 地下2階の床躯体6(地下2階の床6a)の順打ち、 3 地下3階の外周壁6bの圧入、 4 地下1階の床躯体5(地下1階の床5a・地下2階の外周壁5bと内部柱・壁5c)の順打ち(地下2階立ち上がり躯体工事)、 5 耐圧盤7の順打ち、 6 基礎・基礎梁8と地下3階床9の順打ち、 7 地下3階床9と地下3階の外周壁6bとの間の圧入、 8 地下1階の床5aと地下1階の外周壁4bとの間の圧入、および地下1階の内部柱・壁4cの圧入、 9 地下3階の内部柱・壁6cの圧入。
【0022】
なお、各部の水平打ち継ぎ,柱主筋の継手,壁主筋の継手などには通常の工法が採用されている。
【0023】
1段目切梁支保工11と2段目切梁支保工12は、図4,図5に示すように、縦横の切梁13と、腹起し14と、火打ち梁15と、コーナー火打ち梁16等からなる水平切梁であり、構真柱3および外周壁4b,6bに取付けた支持ブラケット17(図1参照)により支持される。
【0024】
本発明では、地下1階の床躯体の代わりとして1段目切梁支保工11を設けているが、この1段目切梁支保工11は、図6に示すように、1階の床4aの下面と地下1階の外周壁4bの間に斜めに設けた斜め切梁11’で代用することも可能である。
【0025】
また、1段目切梁支保工を架設したのは、山留め壁の変形を極めて微小に抑えようとしたものであり、地盤の硬軟の条件、あるいは山留め壁変形量の設定条件等によっては、1段目切梁無しで施工することも可能と考えられる。
【0026】
図7に示すように、本発明のスーパー逆打ち工法では、地下1階の床躯体4の築造を飛ばして地下2階の床スラブ6aの築造を先行し、この地下2階の床スラブを境に、下部で4次掘削以降の工事を、上部で地下1階の床躯体5の立ち上がり工事(地下2階立ち上がり躯体工事)を並行して行うため、地下1階の床躯体5の工事がクリティカルパスから外れ、従来の本逆打ち工法と比較して約1.5カ月工期を短縮することが可能となった。
【0027】
また、図3に示すように、地下1階の床躯体5(地下2階立ち上がり躯体)は順打ち工法で築造することができ、従来の本逆打ち工法に比べ、地下止水の弱点となり易い外壁逆打ち継ぎ部や、鉄筋継手・後打ちコンクリートを減らすことができる。
【0028】
なお、以上は地下3階の地下部分を築造する場合について説明したが、これに限らず、地下4階以上の地下部分の築造にも本発明を適用できることは言うまでもない。また、地下の任意の階から本発明の逆打ち工法を開始することもできる。さらに、本発明の逆打ち工法を順次繰り返して大規模な地下部分を築造することも可能である。
【0029】
【発明の効果】
本発明は、以上のような構成からなるので、次のような効果を奏することができる。
【0030】
(1) 例えば地下1階の床躯体の築造を飛ばして地下2階の床スラブの築造を先行し、この地下2階の床スラブを境に、下部で掘削工事とそれ以降の工事を、上部で地下1階の床躯体の立ち上がり工事を並行して行うため、大幅な工期短縮が可能な従来の本逆打ち工法に対して、さらに1.5カ月程度、工期の短縮を図ることができる。
【0031】
(2) 逆打ち工法の中に順打ち工法も加味されるため、従来の本逆打ち工法に比べ、地下止水の弱点となり易い外壁逆打ち継ぎ部や、鉄筋継手・後打ちコンクリートを減らすことができる。
【0032】
(3) 工期短縮に伴う工事経費を考慮すると、コストは従来の本逆打ち工法と同程度で済む。
【図面の簡単な説明】
【図1】 本発明の逆打ち工法を工程順に示す断面図である。
【図2】 本発明における山留め壁・杭・構真柱の配置例を示す平面図である。
【図3】 本発明の逆打ち工法における各階の施工の詳細を示す断面図である。
【図4】 本発明で用いる1段目切梁の1例を示す平面図である。
【図5】 本発明で用いる2段目切梁の1例を示す平面図である。
【図6】 1段目切梁の変形例を示す断面図である。
【図7】 本発明と従来工法の各工程を比較した図である。
【符号の説明】
1…山留め壁
2…場所打ち杭
3…構真柱
4…1階の床躯体
4a…1階の床
4b…地下1階の外周壁
4c…地下1階の内部柱・壁
5…地下1階の床躯体
5a…地下1階の床
5b…地下2階の外周壁
5c…地下2階の内部柱・壁
6…地下2階の床躯体
6a…地下2階の床
6b…地下3階の外周壁
6c…地下3階の内部柱・壁
7…耐圧盤
8…基礎・基礎梁
9…地下3階床
11…1段目切梁支保工
12…2段目切梁支保工
13…切梁
14…腹起し
15…火打ち梁
16…コーナー火打ち梁
17…支持ブラケット
20…頭部RCあご
21…スタッドボルト
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a reverse striking method for constructing an underground structure of a building, and is a super reverse striking method obtained by improving and upgrading a conventional reverse striking method.
[0002]
[Prior art]
In the conventional reverse driving method, after the first floor is first constructed, the ground below it is excavated, and when the first floor underground is constructed, the ground below is excavated. It is a construction method that completes the underground structure by constructing foundation beams at the end, while proceeding to the lower floor sequentially while repeating the excavation of the building. Each floor structure is used as a supporting structure in sequence, and the load of the constructed underground frame is temporarily supported by a steel column called a structural column until the entire underground frame is completed.
[0003]
Such a reverse driving method has gained much attention in recent years because it has advantages such as the use of the first floor as a work floor, the stability of a mountain retaining structure, and the shortening of the construction period.
[0004]
[Problems to be solved by the invention]
Even in the conventional reverse driving method, it is possible to significantly shorten the work period by executing the ground work and the underground work in parallel, compared with the conventional method in which the underground structure is constructed from the bottom to the upper part.
[0005]
However, when the construction period designated by the owner is short, the conventional reverse driving method cannot be used, and there is a demand for a reverse driving method that can further shorten the construction period. In addition, if the building site is small and the underground part is built to fill the site, and the yard for the construction of the steel frame is very narrow, the construction period of the underground work should be considered when proceeding with simultaneous construction on the ground and underground. It is demanded to shorten the construction time and accelerate the construction of the ground steel frame.
[0006]
This invention is made | formed in view of such a situation, and is providing the reverse hammering method which can aim at shortening of a construction period further than the conventional reverse hammering method.
[0007]
[Means for Solving the Problems]
The reverse driving method of the present invention is a reverse driving method in which an underground structure of a building is built from top to bottom, and a floor frame of an arbitrary floor is built in an excavation space in a retaining wall. Accordingly, after laying a beam under the floor of the floor frame, the floor floor is drilled without building a floor on the lower floor, and an arbitrary number of floors are excavated at once. Is built in advance, then, with the floor under any of the plurality of floors as a boundary, excavation work and frame work are performed in the lower part, and the floor structure of the upper floor is performed in the upper part in parallel. .
[0008]
For example, as shown in FIG. 1, after excavating the upper part of the retaining wall (primary excavation), building the first-floor floor frame, if necessary, after the second excavation, a beam (under the first floor) A horizontal beam support or diagonal beam), skip the first basement floor and excavate all the way down to the second basement beam (the third excavation). With this 2nd basement floor as a boundary, excavation work (fourth excavation) at the lower part and the 3rd floor and below floor structure work, and the upper floor 1st floor structure at the upper part (1st basement floor and 2nd basement floor) Of the outer peripheral wall) in parallel. In FIG. 1, the reverse striking method of the present invention is started from the construction of the floor frame on the first floor, but it is also possible to start from an arbitrary floor in the basement. It is also possible to build an underground structure by sequentially repeating the reverse driving method of the present invention.
[0009]
The above-mentioned beam (first stage) is intended to suppress the deformation of the upper part of the retaining wall to a very small extent, and depending on the ground hardness and the setting condition of the retaining wall, it should be constructed without this beam. Is something that can be done.
[0010]
In the configuration as described above, for example, the construction of the floor slab on the first basement floor is skipped and the construction of the floor slab on the second basement floor is preceded, and the construction after the fourth excavation is performed at the lower part of the floor slab on the second basement floor. In the upper part, the floor structure of the first basement floor is constructed in parallel. For example, as shown in FIG. 7, the construction of the floor structure of the first basement floor (the construction of the second basement floor) deviates from the critical path. Compared with the conventional reverse driving method, the construction period can be shortened by about 1.5 months. In addition, the floor frame on the first basement floor can be constructed by a forward casting method without an outer wall reverse joint.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described based on an embodiment shown in the drawings. This embodiment is an example in which the present invention is applied to the construction of an underground portion of the third floor of a skyscraper. FIG. 1 is a cross-sectional view showing the super counterstrike method of the present invention in the order of steps. FIG. 2 is a plan view showing an arrangement example of a retaining wall, a pile, and a true pillar in the present invention. FIG. 3 is a sectional view showing details of construction on each floor. 4 and 5 are plan views showing an example of a cutting beam used in the present invention. FIG. 6 is a cross-sectional view showing a modification of the first-stage beam. FIG. 7 is a diagram comparing the steps of the present invention and the conventional method.
[0012]
By the super reverse driving method of the present invention, the underground part of the third basement is constructed in the following procedure (see FIG. 1).
[0013]
( 1 ) After construction of the mountain retaining wall (SMW) 1, the cast-in-place pile 2 and the construction pillar 3 are installed. After the primary excavation of the upper part of the retaining wall, the floor frame 4 on the first floor is constructed. The floor frame 4 includes a floor (including beams) 4a on the first floor and an outer peripheral wall (including outer peripheral columns) 4b on the first basement.
[0014]
( 2 ) After the secondary excavation to the floor level of the first basement floor, the first-stage beam support work 11 is installed on the outer peripheral wall 4b.
[0015]
( 3 ) The construction of the floor structure on the first basement floor will be skipped and excavated to the bottom of the beam on the second basement floor, and the third floor excavation for two floors will be performed. The basement 6 on the second basement is built, and then the first-stage beam support 11 is dismantled. The floor structure 6 on the second basement floor comprises a floor 6a on the second basement floor. A large space is formed above the floor frame 6.
[0016]
( 4 ) After the fourth excavation to the floor level of the third basement floor to construct the outer peripheral wall 6b of the third basement floor, the second stage beam support 12 is installed on the outer peripheral wall 6b. At the same time, the floor frame 5 on the first basement is built in order. The first floor base 5 includes a floor 5a on the first basement floor, an outer peripheral wall 5b on the second basement floor, and internal pillars and walls 5c. From this time, construction work on the ground steel frame will begin.
[0017]
( 5 ) After the fifth excavation / flooring, the pressure platen 7 is constructed.
[0018]
( 6 ) Build foundation / foundation beam 8 and basement floor 3 9 After the concrete is hardened, the second stage beam supporting work 12 is dismantled. After constructing the outer wall joints on the first basement and the third basement and placing the concrete on the remaining internal pillars and walls, the basement is completed.
[0019]
Next, each elemental technology of the reverse driving method of the present invention will be described in detail. As shown in FIG. 2, the structural pillar 3 is provided in the internal pile 2 </ b> A, the structural pillar 3 is used as the column steel of the internal pillar A, and the structural pillar 3 is not provided in the pile 2 </ b> B in the outer peripheral portion. This is because, as shown in FIG. 3, the pile 2 </ b> B and the outer peripheral column B at the outer peripheral portion are eccentric, and the column steel frame of the outer peripheral column B cannot be used as a structural column. Since there is no true pillar on the outer periphery, the outer peripheral frame is supported on the retaining wall 1 by the head RC jaw 20 and the stud bolt 21 as shown in FIG. Furthermore, since the bearing capacity of the retaining wall 1 has a permissible limit, the underground work is expedited, and a pressure platen 7 is placed in front of the ground steel frame, for example, 5 sections, and the stress of the column steel of the outer column B is transferred to the outer periphery. To the pile 2B.
[0020]
As shown in FIG. 3, the concrete is composed of a normal concrete forward casting part and a special concrete semi-pressing part using a high-performance AE water reducing agent, and is placed in the following order.
[0021]
( 1 ) First floor floor 4 (first floor 4a, basement 1 outer wall 4b), ( 2 ) Second floor 6 (second floor 6a), ( 3 ) Press-fitting of the outer wall 6b on the third basement floor ( 4 ) Ordering of the floor frame 5 on the first basement floor (the floor 5a on the first basement floor, the outer peripheral wall 5b on the second basement floor and the inner pillar / wall 5c) (2) Standing frame construction on the second floor), ( 5 ) Ordering of the pressure platen 7, ( 6 ) Ordering of the foundation / foundation beam 8 and the third basement floor 9, ( 7 ) Outer wall of the third basement floor 9 and the third basement floor ( 8 ) Press-fitting between the floor 5a on the first basement floor and the outer peripheral wall 4b on the first basement floor, and press-fitting internal pillars and walls 4c on the first basement floor, ( 9 ) On the third basement floor Press-fitting internal pillar / wall 6c.
[0022]
It should be noted that ordinary methods are used for horizontal joints at each part, joints of column main bars, joints of wall main bars, and the like.
[0023]
As shown in FIG. 4 and FIG. 5, the first-stage cut beam support 11 and the second-stage cut beam support 12 include vertical and horizontal cut beams 13, bulges 14, fire beams 15, and corner fire beams. 16 and the like, and is supported by a support bracket 17 (see FIG. 1) attached to the structural pillar 3 and the outer peripheral walls 4b and 6b.
[0024]
In the present invention, a first-stage beam supporting work 11 is provided as a substitute for the floor structure of the first-floor underground, but the first-stage beam supporting work 11 is a floor 4a on the first floor as shown in FIG. It is also possible to substitute an oblique beam 11 ′ provided obliquely between the lower surface of the outer wall and the outer peripheral wall 4b of the first basement.
[0025]
In addition, the first-stage beam support work was erected in order to suppress the deformation of the retaining wall to a very small extent. Depending on the conditions of the hardness of the ground or the setting condition of the amount of deformation of the retaining wall, 1 It is also possible to construct without stepped beams.
[0026]
As shown in FIG. 7, in the super backlash method of the present invention, the construction of the floor slab 6a on the second basement is advanced by skipping the construction of the floor skeleton 4 on the first basement, and the floor slab on the second basement is bounded. In addition, the work after the fourth excavation is performed at the lower part and the floor structure 5 on the first basement floor (upper floor structure on the second basement) is performed in the upper part, so the construction of the floor structure 5 on the first basement floor is critical. It was possible to reduce the construction period by about 1.5 months compared with the conventional reverse driving method.
[0027]
In addition, as shown in FIG. 3, the first floor basement 5 (the second basement standing base) can be constructed by the forward casting method, which tends to be a weak point of underground water stoppage as compared with the conventional reverse driving method. The outer wall reverse joints, reinforced joints and post-cast concrete can be reduced.
[0028]
In addition, although the above demonstrated the case where the underground part of the 3rd basement was built, it cannot be overemphasized that this invention is applicable not only to this but to the construction of the underground part more than the 4th floor underground. Moreover, the reverse driving method of this invention can also be started from the arbitrary underground floors. Furthermore, it is also possible to build a large-scale underground part by sequentially repeating the reverse driving method of the present invention.
[0029]
【The invention's effect】
Since this invention consists of the above structures, there can exist the following effects.
[0030]
(1) For example, skip the construction of the floor slab on the first basement floor and precede the construction of the floor slab on the second basement floor. Therefore, the construction work can be further shortened by about 1.5 months compared to the conventional reverse striking method, which can significantly shorten the construction period, since the construction work for the first floor basement is performed in parallel.
[0031]
(2) Since the forward casting method is also included in the reverse casting method, the number of outer wall reverse joints, reinforced joints and post-cast concrete, which tend to be a weak point of underground water stoppage, is reduced compared to the conventional reverse casting method. Can do.
[0032]
(3) Considering the construction costs associated with shortening the construction period, the cost will be about the same as the conventional reverse driving method.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view showing a reverse driving method according to the present invention in the order of steps.
FIG. 2 is a plan view showing an arrangement example of a retaining wall, a pile, and a true pillar in the present invention.
FIG. 3 is a cross-sectional view showing details of construction on each floor in the reverse driving method of the present invention.
FIG. 4 is a plan view showing an example of a first stage beam used in the present invention.
FIG. 5 is a plan view showing an example of a second-stage cutting beam used in the present invention.
FIG. 6 is a cross-sectional view showing a modification of the first-stage beam.
FIG. 7 is a diagram comparing the steps of the present invention and a conventional method.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Mountain retaining wall 2 ... Cast-in-place pile 3 ... Construction pillar 4 ... First-floor floor frame 4a ... First-floor floor 4b ... Basement 1st floor outer wall 4c ... Basement 1st floor internal pillar / wall 5 ... Basement 1st floor 5a ... Basement 1st floor 5b ... 2nd basement outer wall 5c ... 2nd basement inner pillar / wall 6 ... 2nd basement floor housing 6a ... 2nd basement floor 6b ... 3rd basement outer periphery Wall 6c… Inner 3rd floor internal pillars and walls 7… Pressure panel 8… Basement / foundation beam 9… 3rd basement floor 11… 1st stage beam support 12… 2nd stage beam support 13… cut beam 14 ... Raising 15 ... Fire beam 16 ... Corner beam 17 ... Support bracket 20 ... Head RC jaw 21 ... Stud bolt

Claims (1)

建築物の地下構造体を上から下へと築造していく逆打ち工法であり、山留め壁内の掘削空間内に任意の階の床躯体を築造し、必要に応じて前記床躯体の床の下に切梁を架設した後、前記床躯体より下階の床を築造せずに飛ばして任意の複数フロア分を一気に掘削し、該任意の複数フロア下の床を先行して築造し、次いで該任意の複数フロア下の床を境に、下部で掘削工事と躯体工事を、上部で上階の床躯体の立ち上がり工事を、並行して行うことを特徴とする逆打ち工法。Underground structure of the building from the top is the inverse hit method to continue to construction to bottom, any floors drilling space in earth retaining walls floors precursor and construction, the floor skeleton optionally floors After laying the beam underneath, the floor below the floor frame is blown without building the floor below, excavating any multiple floors at once, building the floor under any multiple floors in advance, A reverse driving method characterized in that excavation work and frame work are carried out at the lower part and the upper floor work of the upper floor is carried out at the upper part in parallel with the floor below the plurality of arbitrary floors.
JP2000251132A 2000-08-22 2000-08-22 Reverse strike method Expired - Fee Related JP3767347B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000251132A JP3767347B2 (en) 2000-08-22 2000-08-22 Reverse strike method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000251132A JP3767347B2 (en) 2000-08-22 2000-08-22 Reverse strike method

Publications (2)

Publication Number Publication Date
JP2002061213A JP2002061213A (en) 2002-02-28
JP3767347B2 true JP3767347B2 (en) 2006-04-19

Family

ID=18740582

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000251132A Expired - Fee Related JP3767347B2 (en) 2000-08-22 2000-08-22 Reverse strike method

Country Status (1)

Country Link
JP (1) JP3767347B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4791997B2 (en) * 2007-04-04 2011-10-12 株式会社竹中工務店 Rebuilding method
JP5634931B2 (en) * 2011-03-30 2014-12-03 大成建設株式会社 Construction method of underground structure
JP6937205B2 (en) * 2017-09-21 2021-09-22 大成建設株式会社 How to build an underground structure

Also Published As

Publication number Publication date
JP2002061213A (en) 2002-02-28

Similar Documents

Publication Publication Date Title
JP2012107479A (en) Method for constructing underground and aboveground structure
JP2023104993A (en) Foundation construction method of underground structure
JP2000352296A (en) Method o constructing passage just under underground structure
JPH102126A (en) Base isolated building
JP3767347B2 (en) Reverse strike method
JP4115095B2 (en) Reverse strike method
JP2700811B2 (en) Construction method of structure including super frame
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JP4550534B2 (en) Building basic structure
JP2020125630A (en) Building construction method
JP3248458B2 (en) Shoring construction underground construction method
JP2964295B2 (en) Basement floor construction method
JP2006502324A (en) Prestressed temporary construction method
JP2003003690A (en) Base isolation building and method for base isolation of exisiting building
JP2018017041A (en) Foundation structure, and foundation construction method for the same
JP3882536B2 (en) Reconstruction method for existing buildings
JP2009002079A (en) Aseismatic reinforcing construction method for existing building
JP3109038B2 (en) Underground skeleton structure and construction method
JP2006188862A (en) Construction method of structure, and foundation structure used for the same
JPH05141004A (en) Two-step placing construction
JP7510328B2 (en) Construction Method
JP2894217B2 (en) Building structural frame
JPH0742179A (en) Modified inversion placing construction method
JP4657759B2 (en) Building pile foundation structure
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20051017

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20051025

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20051125

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060110

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060123

R150 Certificate of patent or registration of utility model

Ref document number: 3767347

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090210

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120210

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150210

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees