JP5465086B2 - Construction method of underground structure - Google Patents

Construction method of underground structure Download PDF

Info

Publication number
JP5465086B2
JP5465086B2 JP2010119239A JP2010119239A JP5465086B2 JP 5465086 B2 JP5465086 B2 JP 5465086B2 JP 2010119239 A JP2010119239 A JP 2010119239A JP 2010119239 A JP2010119239 A JP 2010119239A JP 5465086 B2 JP5465086 B2 JP 5465086B2
Authority
JP
Japan
Prior art keywords
slab
underground structure
ceiling slab
ceiling
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010119239A
Other languages
Japanese (ja)
Other versions
JP2011246910A (en
Inventor
泰夫 西田
悌朗 八浪
義昭 関根
泰司 森田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2010119239A priority Critical patent/JP5465086B2/en
Publication of JP2011246910A publication Critical patent/JP2011246910A/en
Application granted granted Critical
Publication of JP5465086B2 publication Critical patent/JP5465086B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、地盤の掘削にともない、地下構造物を上方から順に施工する逆巻き工法に改良を加えた地下構造物の構築方法に関するものである。   The present invention relates to a construction method for an underground structure obtained by improving the reverse winding method for constructing an underground structure in order from the top as the ground is excavated.

地下構造物の構築方法には、土留め壁の内側に腹起しや切梁等からなる土留め支保工を施工して土留め壁で包囲された地盤を床付けまで掘削し、下方の床スラブから順に上方に地下構造物を構築していく、いわゆる順巻き工法や、土留め壁を施工し、上方から支保工の設置と掘削を繰り返しながら、地下構造物の天井スラブを先行して施工し、下方に向かって順に側壁と床スラブを施工する、いわゆる逆巻き工法などが知られている。   The construction method of the underground structure is to dig a ground support structure made up of erections, beams, etc. inside the retaining wall, excavate the ground surrounded by the retaining wall to the floor, The so-called forward-winding method that builds the underground structure upward from the slab and the retaining wall, and the installation and excavation of the support structure from the top are repeated in advance to construct the ceiling slab of the underground structure. And what is called a reverse winding method etc. which construct a side wall and a floor slab in order toward the downward direction are known.

さらには、別途のヤードや工場などで予めコンクリート製もしくは鋼製のケーソンを製作し、これを施工ヤードへ搬送し、人力掘削や機械掘削にて地盤の掘削をおこないながらケーソンを沈設するケーソン工法(ニューマチックケーソン、潜函ケーソン、圧気ケーソンなど)も知られるところである。   In addition, a caisson method that constructs a concrete or steel caisson in a separate yard or factory in advance, transports it to the construction yard, and sinks the caisson while excavating the ground by manual or mechanical excavation ( Pneumatic caisson, submersible caisson, pressure caisson, etc.) are also known.

上記する順巻き工法では、床付けまで掘削をおこなって広範な施工空間を形成した後に地下構造物の構築をおこなうことから作業効率性に優れているというメリットがある一方で、地下構造物用の配筋作業に際して、支保工を構成する腹起しや切梁が往々にしてこの配筋作業の妨げになるといった問題や、この支保工が地下構造物の壁面に設けられる防水施工の障害になるといった問題が顕在化している。   The above-mentioned forward winding method has the merit that it is excellent in work efficiency because it constructs the underground structure after excavating to flooring and forming a wide construction space, but for the underground structure During bar arrangement work, problems such as the erection and cutting beams that make up the support work often interfere with this work, and this support work becomes an obstacle to the waterproof construction provided on the walls of underground structures. Such a problem has become apparent.

また、地下構造物の中でも天井スラブの構築が最後となるために、この天井スラブ上方への掘削残土の埋戻し作業が工程の最後とならざるを得ず、掘削残土用のヤードが工程の最初から最後まで残土で占有されてしまうといった問題もある。   In addition, since the construction of the ceiling slab is the last of the underground structures, the work of backfilling the excavated residual soil above the ceiling slab must be the last of the process, and the yard for the excavated residual soil is the first of the process. There is also a problem of being occupied by the remaining soil from the end to the end.

このような順巻き工法の有する課題に対して、上記する逆巻き工法を適用することで、地盤掘削に応じて支保工が設置され、地下構造物の構築も上方から順におこなわれることから、支保工が配筋作業や防水施工の妨げになることもなく、地下構造物の中でも天井スラブが最初に構築されることから残土の埋戻しも早期におこなうことができ、残土用ヤードを他の用途に有効利用することが可能となる。   By applying the reverse winding method described above to the problem of such a forward winding method, a support work is installed according to the ground excavation, and the construction of the underground structure is also performed in order from the top. Will not disturb the bar arrangement work and waterproofing work, and the ceiling slab will be built first in the underground structure, so the remaining soil can be backfilled early, and the remaining soil yard can be used for other purposes. It can be used effectively.

しかし、逆巻き工法を適用した場合には、下方に向かって側壁を構築していくために、側壁の打ち継目に施工不良が生じ易いという大きな課題があり、さらには、上方に構築された地下構造物のたとえば天井スラブと掘削床の間の限られた空間に資材や施工機械、施工材料を搬入し、この空間内でさらなる掘削をおこなったり、地下構造物の構築をおこなうことから非効率な施工が余儀なくされるといった問題がある。   However, when the reverse winding method is applied, in order to construct the side wall downward, there is a major problem that construction failure tends to occur at the joint of the side wall, and further, the underground structure constructed above For example, materials, construction machines, and construction materials are brought into a limited space between the ceiling slab and the excavation floor of the object, and further excavation and construction of underground structures are unavoidable in this space. There is a problem of being.

このように、順巻き工法や逆巻き工法にはそれぞれに固有のメリットとデメリットがあるが、たとえば逆巻き工法においては上記する固有のデメリットがあるが故に、我が国におけるアンダーパス工事にこの逆巻き工法が適用されず、ケーソン工法が多用されるに至っている。   In this way, the forward winding method and the reverse winding method have their own merits and demerits. For example, the reverse winding method has the inherent merits described above, so this reverse winding method is applied to underpass construction in Japan. First, the caisson method has been used frequently.

ここで、逆巻き工法に改良を加えた従来の公開技術が特許文献1に開示されている。この施工方法は、地下構造物の1階床スラブのうちで土留め壁を支保し得る必要最小限の部分のみを先行施工し、次いで掘削を進め、同様に地下構造物の地下1階床スラブのうちで土留め壁を支保し得る必要最小限の部分のみを先行施工し、これを繰り返して床付けまでの掘削を終了した後に上方へ向かって地下構造物を構築するものである。   Here, Patent Document 1 discloses a conventional published technique obtained by improving the reverse winding method. In this construction method, only the minimum necessary part of the 1st floor slab of the underground structure that can support the retaining wall is preliminarily constructed, and then excavation proceeds. Similarly, the underground 1st floor slab of the underground structure. Of these, only the minimum necessary part capable of supporting the earth retaining wall is preliminarily constructed, and this is repeated to complete the excavation up to the flooring and then build the underground structure upward.

特許文献1に開示の施工方法によれば、側壁を下方から上方へ向かって施工できることから、上記する逆巻き工法の有する課題、すなわち、側壁の打ち継目に施工不良が生じ易いという課題を解消することはできる。しかし、下方から上方へ地下構造物を構築していくに当たり、各階の床スラブが、支保工として使用される先行施工箇所と、この先行施工箇所と一体とされる後行施工箇所に分かれており、したがって各階の床スラブを2度に亘って施工する必要があることから、施工効率が極めて悪く、工期の長期化は否めない。   According to the construction method disclosed in Patent Document 1, since the side wall can be constructed from the bottom to the top, the problem of the reverse winding method described above, that is, the problem that the construction failure is likely to occur at the joint of the side wall is solved. I can. However, when constructing an underground structure from the bottom to the top, the floor slabs on each floor are divided into a preceding construction location used as a support construction and a subsequent construction location integrated with this preceding construction location. Therefore, since it is necessary to construct the floor slab of each floor twice, the construction efficiency is extremely poor and the construction period cannot be denied.

特開平11−280094号公報JP 11-280094 A

本発明は上記する問題に鑑みてなされたものであり、従来のいわゆる逆巻き工法に改良を加えることで、側壁の打ち継目に施工不良が生じ易いという課題を解消でき、さらには、工期を長期化させることのない地下構造物の構築方法を提供することを目的としている。   The present invention has been made in view of the above-mentioned problems, and by improving the conventional so-called reverse winding method, it is possible to eliminate the problem that construction failure tends to occur at the joint of the side walls, and further, the construction period is lengthened. It aims at providing the construction method of the underground structure which does not let it.

前記目的を達成すべく、本発明による地下構造物の構築方法は、地盤内で対向する位置に土留め壁を施工する第1の工程、対向する土留め壁で囲まれた地盤に対して地表から掘削を進め、対向する土留め壁の双方に腹起しを設置するとともに対向する腹起しの間に切梁を設置する第2の工程、さらに掘削を進めて、地下構造物のうちの少なくとも天井スラブを構築し、この天井スラブに土留め壁を支保させる第3の工程、さらに掘削を進めて床付け面を施工し、床付け面上に均しコンクリートスラブを構築し、腹起しおよび切梁を撤去して、均しコンクリートスラブ上に床スラブを構築し、側壁を上方に向かって構築して、少なくとも天井スラブと床スラブと側壁からなる地下構造物を構築する第4の工程、からなるものである。   In order to achieve the above-mentioned object, the construction method of an underground structure according to the present invention is a first step of constructing a retaining wall at an opposing position in the ground, the ground surface with respect to the ground surrounded by the opposing retaining wall. The second step of installing excavation from both sides of the opposite retaining wall and installing a beam between the opposing uprights, further excavation, Build at least a ceiling slab, and support the retaining wall to the ceiling slab, and proceed with excavation to construct the flooring surface, build a leveled concrete slab on the flooring surface, And cutting the beams, constructing a floor slab on the leveled concrete slab, constructing the side wall upward, and constructing an underground structure consisting of at least the ceiling slab, the floor slab and the side wall , Is made up of.

ここで、第1の工程における「対向する位置に土留め壁を施工する」とは、土留め壁を平面視で矩形、正方形、その他の多角形、円形、楕円形等の枠状(無端状)に施工することにより、2組もしくは3組以上の対向した土留め壁の組み合わせが形成されることを意味している。たとえば、平面視矩形の土留め壁の場合には、長辺の一組の対向する土留め壁と、短辺の一組の対向する土留め壁が存在することになる。   Here, “constructing the retaining wall at the opposite position” in the first step means that the retaining wall has a frame shape (endless shape) such as a rectangle, a square, other polygons, a circle, or an ellipse in plan view. This means that two or three or more pairs of earth retaining walls are formed. For example, in the case of a rectangular retaining wall in plan view, there is a pair of opposing retaining walls with a long side and a pair of opposing retaining walls with a short side.

施工される土留め壁の形態は、地中連続壁や柱列式連続壁、鋼矢板や親杭横矢板、鋼管矢板などのいずれであってもよい。また、必要に応じて土留め壁の所望深度領域に地盤改良をおこなってもよい。   The form of the earth retaining wall to be constructed may be an underground continuous wall, a columnar continuous wall, a steel sheet pile, a main pile horizontal sheet pile, a steel pipe sheet pile, or the like. Moreover, you may perform ground improvement to the desired depth area | region of a retaining wall as needed.

土留め壁の施工後、地表から掘削を進めて対向する土留め壁間に腹起しおよび切梁を設置し、さらに掘削を進めて、地下構造物を構成する少なくとも天井スラブを構築してこの天井スラブで土留め壁を支保させる。   After construction of the retaining wall, proceed with excavation from the surface of the earth, install upset and cut beams between the opposing retaining walls, and proceed with further excavation to construct at least a ceiling slab that constitutes the underground structure. Support the retaining wall with a ceiling slab.

ここで、天井スラブの上方に施工される腹起しおよび切梁は、1段であっても複数段であってもよい。   Here, the erection and the cutting beam constructed above the ceiling slab may be one stage or a plurality of stages.

また、構築される地下構造物の構成部材である天井スラブ等は、RC構造、SRC構造、SC構造のいずれであってもよく、コンクリート内に埋設される緊張材は、鉄筋、PC鋼材(PC鋼棒、PC鋼線、PC鋼より線)、鉄筋とPC鋼材の組み合わせなどのいずれであってもよい。   In addition, the ceiling slab, which is a component of the constructed underground structure, may be any of an RC structure, an SRC structure, and an SC structure, and the tension material embedded in the concrete is a reinforcing bar, a PC steel (PC) Any of a combination of steel bars, PC steel wires, PC steel strands), reinforcing bars and PC steel materials may be used.

構築される天井スラブが土留め壁を支保することから、この天井スラブを切梁と見なすことができ、この天井スラブ位置に設置されるはずの切梁を不要とできることで仮設に要する工費を節減することができる。なお、本発明の構築方法では、この段階で地下構造物として天井スラブの全てを施工する。   Since the ceiling slab to be built supports the retaining wall, this ceiling slab can be regarded as a cut beam, and it is possible to eliminate the need for a cut beam that should be installed at this ceiling slab position, thereby reducing the construction cost required for temporary construction. can do. In the construction method of the present invention, all the ceiling slabs are constructed as underground structures at this stage.

ここで、前記土留め壁には予め地下構造物内に埋設されるジベルが設けてあり、前記第3の工程において、少なくとも天井スラブがこのジベルを巻込みながら構築されることにより、土留め壁と天井スラブの相対変位が抑制され、天井スラブにて土留め壁の掘削側への変形を効果的に抑止することができる。さらには、ジベルを介して土留め壁と天井スラブからなる剛性の高い門型ラーメン構造が形成でき、この天井スラブ上に掘削残土等が埋戻された際の天井スラブの撓みを可及的に少なくすることができる。   Here, the retaining wall is provided with a pre-embedded divel in the underground structure in advance, and in the third step, at least the ceiling slab is constructed while winding the gibel, thereby retaining the retaining wall. The relative displacement of the ceiling slab is suppressed, and the ceiling slab can effectively suppress the deformation of the retaining wall to the excavation side. Furthermore, a rigid portal ramen structure consisting of a retaining wall and a ceiling slab can be formed via a gibber, and the bending of the ceiling slab as much as possible after the excavated soil is backfilled on this ceiling slab is made as much as possible. Can be reduced.

少なくとも天井スラブで土留め壁を支保させた後に、掘削を進めて床付け面を施工し、床付け面上に均しコンクリートスラブを構築し、腹起しおよび切梁を撤去して、均しコンクリートスラブ上に床スラブを構築し、側壁を上方に向かって構築することにより、少なくとも天井スラブと床スラブと側壁からなる地下構造物が構築される。ここで、「少なくとも天井スラブと床スラブと側壁からなる地下構造物」とは、これらの構成部材のみからなる地下構造物のほかにも、天井スラブと床スラブ(最下階の床スラブ)の間に複数階の床スラブを具備する地下構造物や、さらに各階に壁や柱を具備する地下構造物などを包含する意味である。   After supporting the retaining wall with at least the ceiling slab, proceed with excavation to construct the flooring surface, build a leveled concrete slab on the flooring surface, remove the flank and the cut beam, level By constructing a floor slab on the concrete slab and constructing the side walls upward, an underground structure composed of at least a ceiling slab, a floor slab, and a side wall is constructed. Here, “an underground structure consisting of at least a ceiling slab, a floor slab, and a side wall” means a ceiling slab and a floor slab (floor slab on the lowest floor) in addition to an underground structure consisting only of these components. It is meant to include underground structures having a plurality of floor slabs between them, and underground structures having walls and pillars on each floor.

均しコンクリートスラブを施工することでこれを土圧耐荷部材と見なし、この均しコンクリートスラブと天井スラブで土留め壁を支保することにより、この天井スラブと均しコンクリートスラブの間の腹起しおよび切梁のすべてを撤去することが可能となる。なお、均しコンクリートスラブを土圧耐荷部材と見なすに当たり、必要に応じて均しコンクリートスラブ内に鉄筋や網筋等を配設してもよい。   By constructing a leveled concrete slab, this is regarded as an earth pressure load-bearing member, and a retaining wall is supported by the leveled concrete slab and the ceiling slab. And all of the beams can be removed. In considering the leveled concrete slab as an earth pressure load bearing member, reinforcing bars, mesh bars, etc. may be provided in the leveled concrete slab as necessary.

天井スラブと均しコンクリートスラブの間の腹起しおよび切梁のすべてが撤去されたら、均しコンクリートスラブ上に床スラブを構築し、この床スラブから上方に側壁を立上げていく。すなわち、側壁を下方から上方に構築する点において、従来の逆巻き工法とは大きく異なっている。   When all of the erection and the beam between the ceiling slab and the leveled concrete slab are removed, a floor slab is constructed on the leveled concrete slab, and a side wall is raised upward from the floor slab. That is, it differs greatly from the conventional reverse winding method in that the side walls are constructed from the bottom to the top.

この従来の逆巻き工法が改良された本発明の構築方法によれば、側壁は順巻き工法のように下方から上方に向かって施工されることから、側壁の打ち継目における施工不良は生じ難い。   According to the construction method of the present invention in which the conventional reverse winding method is improved, since the side wall is constructed from the lower side to the upper side as in the forward winding method, it is difficult to cause poor construction at the joint of the side wall.

また、地下構造物を構成する天井スラブ、床スラブ等はそれぞれ、地下構造物の構築段階で一気にそれらの構築がおこなわれることから、各構成部材を2度に分けて構築することで齎される工期の長期化といった問題も生じ得ない。   In addition, the ceiling slab, floor slab, etc. that make up the underground structure are constructed at once in the construction stage of the underground structure. The problem of longevity cannot occur.

なお、従来の公開技術のように床スラブを2度に分けて施工する場合には、先行施工箇所と後行施工箇所の取合部の一体化と止水性確保を保証するために、先行施工箇所の取合部に面粗し施工をおこなったり、止水施工をおこなうなどの付加施工が余儀なくされることから、これらの付加施工も工期の長期化や工費の増大の原因となるのである。   In addition, when the floor slab is divided into two parts as in the conventional open technology, the prior construction is performed to ensure the integration of the joint part of the preceding construction part and the subsequent construction part and the securing of water stoppage. Since additional construction such as roughening construction or water stop construction at the joint portion of the location is unavoidable, these additional constructions also cause the construction period to be prolonged and the construction cost to increase.

また、本発明による地下構造物の構築方法の好ましい実施の形態において、天井スラブに加えて側壁の一部も構築し、対向する側壁の一部の間に別途の切梁を設置してプレロードを導入するものである。   Further, in a preferred embodiment of the method for constructing an underground structure according to the present invention, a part of the side wall is constructed in addition to the ceiling slab, and a separate beam is installed between a part of the opposite side walls to perform preloading. It is to be introduced.

この構築方法の実施の形態は、土留め壁の支保工として、地下構造物の天井スラブを適用することに加えて、この天井スラブと一体に側壁の一部を施工しておき、対向する側壁の一部の間に切梁を設置し、さらにこの切梁に所望するプレロードを導入して支保工とするものである。   In addition to applying the ceiling slab of the underground structure as a support for the retaining wall, the embodiment of this construction method is constructed such that a part of the side wall is constructed integrally with the ceiling slab, and the opposite side wall A beam is installed between a part of the beam, and a desired preload is introduced into the beam to provide a support work.

本実施の形態の施工方法によれば、地下構造物を構成する天井スラブと側壁の一部の間の切梁とから実質的に2段の切梁が土留め壁間に設置されることになる。   According to the construction method of the present embodiment, the two-stage beam is substantially installed between the retaining walls from the ceiling slab constituting the underground structure and the beam between a part of the side walls. Become.

ここで、導入されるプレロードの設定に際しては、天井スラブに予め歪計を配しておき(たとえばスラブ鉄筋に歪みゲージを設置しておく等)、歪計による計測データを参照してこのプレロードを設定するのが好ましい。このようにして導入プレロードを設定することで、掘削に伴う土留め壁周辺地盤の変位を効果的に抑制でき、これと同時に、既に構築されている地下構造物の構成部材である天井スラブや側壁の一部に生じ得る残留応力やクラックを最小限に制御することが可能となる。   Here, when setting the preload to be introduced, a strain gauge is arranged in advance on the ceiling slab (for example, a strain gauge is installed on the slab reinforcing bar), and this preload is referred to by referring to the measurement data from the strain gauge. It is preferable to set. By setting the introduction preload in this way, it is possible to effectively suppress the displacement of the ground around the retaining wall due to excavation, and at the same time, ceiling slabs and side walls that are components of the already constructed underground structure Residual stresses and cracks that can occur in a part of the surface can be controlled to a minimum.

なお、天井スラブよりも上方にある腹起しおよび切梁の撤去は、天井スラブが構築された後、もしくは別途の切梁にプレロードが導入された後におこなうことができる。   Note that the erection and the removal of the beam above the ceiling slab can be performed after the ceiling slab is constructed or after a preload is introduced into a separate beam.

そして、天井スラブよりも上方にある腹起しおよび切梁が撤去された後に、天井スラブの上方に掘削残土等の埋戻し施工をおこなうことにより、残土用ヤードの有効利用を図ることができる。さらには、この残土処理を早期に実施できることで、工期の短縮を図ることにも繋がる。   Then, after the uplift and the cut beam above the ceiling slab are removed, the backfilling of excavated residual soil and the like is performed above the ceiling slab, so that the remaining soil yard can be effectively used. Furthermore, this remaining soil treatment can be carried out at an early stage, which leads to shortening of the construction period.

以上の説明から理解できるように、本発明の地下構造物の構築方法によれば、地下構造物を構成する天井スラブを施工段階における切梁として適用すること、および、側壁を下方から上方に向かって施工することにより、仮設費用を節減でき、側壁の打ち継目において施工不良を生じ難くすることができる。さらには、地下構造物の構築過程において、構成部材を2度に分けて施工することもないことから、工期を長期化させることも工費を増大させることもない。   As can be understood from the above description, according to the construction method of an underground structure of the present invention, the ceiling slab constituting the underground structure is applied as a cut beam in the construction stage, and the side wall is directed upward from below. Thus, the temporary cost can be reduced and it is possible to make it difficult to cause a construction failure at the joint of the side walls. Furthermore, in the construction process of the underground structure, the construction members are not divided into two parts, so that the construction period is not prolonged and the construction cost is not increased.

本発明の地下構造物の構築方法の第1の工程を説明した図である。It is the figure explaining the 1st process of the construction method of the underground structure of the present invention. 図1に続き、第2の工程を説明した図である。FIG. 2 is a diagram for explaining a second step following FIG. 1. 図2に続き、第3の工程を説明した図である。FIG. 3 is a diagram for explaining a third step following FIG. 2. 図3と同様に、第3の工程を説明した図である。FIG. 4 is a diagram for explaining a third step as in FIG. 3. 図4に続き、第4の工程を説明した図である。FIG. 5 is a diagram for explaining a fourth step following FIG. 4. 図5と同様に、第4の工程を説明した図である。FIG. 6 is a diagram for explaining a fourth step as in FIG. 5. 図6と同様に、第4の工程を説明した図である。FIG. 7 is a diagram for explaining a fourth step, similar to FIG. 6. 図7と同様に、第4の工程を説明した図である。FIG. 8 is a diagram for explaining a fourth step, similar to FIG. 7. 図8と同様に、第4の工程を説明した図である。It is the figure explaining the 4th process like FIG. 図9と同様に、第4の工程を説明した図である。It is the figure explaining the 4th process like FIG.

以下、図面を参照して本発明の地下構造物の構築方法を説明する。なお、図示する地下構造物は天井スラブ、床スラブおよび側壁から構成されたものであるが、本発明の構築方法にて構築される地下構造物が図示例に限定されるものでないことは勿論のことであり、天井スラブと床スラブ(最下階の床スラブ)の間に複数階の床スラブを具備するものや、さらに各階に壁や柱を具備するものなど、多様な構造形態の地下構造物がその構築対象である。また、地下構造物のうち、最初に天井スラブのみを構築してこれで土留め壁を支保させ、側壁のすべてを床スラブ施工後に構築する方法であってもよい。   Hereinafter, the construction method of the underground structure of the present invention will be described with reference to the drawings. Although the illustrated underground structure is composed of a ceiling slab, a floor slab, and a side wall, the underground structure constructed by the construction method of the present invention is not limited to the illustrated example. Underground structures with various structural forms, such as those with multiple floor slabs between the ceiling slab and floor slab (bottom floor slab) and those with walls and pillars on each floor Things are the object of construction. Moreover, the method of constructing | assembling only the ceiling slab first in this underground structure and supporting a retaining wall by this, and constructing | assembling all the side walls after floor slab construction may be sufficient.

図1〜図10は順に、本発明の地下構造物の構築方法の第1の工程〜第4の工程を説明した図であり、より具体的には、図1は第1の工程を、図2は第2の工程を、図3,4は第3の工程を、図5〜10は第4の工程をそれぞれ説明した図である。   FIGS. 1-10 is the figure explaining the 1st process-the 4th process of the construction method of the underground structure of this invention in order, More specifically, FIG. 2 illustrates the second step, FIGS. 3 and 4 illustrate the third step, and FIGS. 5 to 10 illustrate the fourth step.

本発明の構築方法では、まず、図1で示すように、施工ヤードにおいて原地盤G内にたとえば平面視矩形の土留め壁1を専用の掘削機M1を使用して施工する。ここで、土留め壁1の形態は、土質性状や地下水位、地下構造物の床付け深度や工費、工期などによって適宜選定されるものであるが、地中連続壁や柱列式連続壁、鋼矢板や親杭横矢板、鋼管矢板などのいずれであってもよい。なお、図示例は、地下連続壁を適用し、原地盤Gの下層の支持地盤G1に土留め壁1を根入れしている。   In the construction method of the present invention, as shown in FIG. 1, first, a retaining wall 1 having a rectangular shape in plan view is constructed in the ground G in a construction yard using a dedicated excavator M1. Here, the form of the retaining wall 1 is appropriately selected according to soil properties, groundwater level, flooring depth of underground structure, construction cost, construction period, etc., but the underground continuous wall and columnar continuous wall, Any of a steel sheet pile, a main pile horizontal sheet pile, a steel pipe sheet pile, etc. may be sufficient. In the illustrated example, an underground continuous wall is applied, and the retaining wall 1 is embedded in the support ground G1 below the original ground G.

平面視矩形の土留め壁1において、図1ではそのうちの一組の対向する位置に配設された土留め壁1,1を示しており、その間には、後施工される切梁を土留め壁1,1間の途中位置で支持したり、仮設用の重機通路を支持するための中間杭2が複数設置されている。   In the rectangular retaining wall 1 in plan view, FIG. 1 shows the retaining walls 1 and 1 disposed at a pair of opposing positions, and in the meantime, post-constructed cut beams are retained. A plurality of intermediate piles 2 are installed to support the intermediate positions between the walls 1 and 1 and to support a heavy machinery passage for temporary installation.

土留め壁1,1を原地盤G内で対向する位置に施工したら、図2で示すように、その根入れ領域に地盤改良体3を造成用重機M2を使用して施工し、地下水の回り込みや盤膨れ等を抑制したり、土留め壁の受働土圧を高める等の措置を講じる。さらに、平面視矩形状の土留め壁1で包囲された地盤G内の地下水を揚水し(X1方向)、バックホーM3を使用して地盤Gの掘削を進める。   When the earth retaining walls 1 and 1 are constructed at positions facing each other in the original ground G, as shown in FIG. 2, the ground improvement body 3 is constructed in the rooting area using the heavy equipment M2 for creation, and the groundwater wraps around. Take measures such as suppressing wall swelling and increasing the passive earth pressure of the retaining wall. Furthermore, ground water in the ground G surrounded by the rectangular retaining wall 1 having a rectangular shape in plan view is pumped (X1 direction), and excavation of the ground G is advanced using the backhoe M3.

地表から深度1〜2m程度掘削が進行した段階で、1段目の支保工である腹起し4A,4Aを対向する土留め壁1,1の双方に設置し、この対向する腹起し4A,4A間に切梁5Aを中間杭2を介して掛け渡す。   At the stage where excavation has progressed about 1 to 2 m in depth from the ground surface, the uplift 4A, 4A, which is the first stage support, is installed on both opposing earth retaining walls 1, 1, and this upset 4A , 4A through the intermediate pile 2 between the cut beams 5A.

1段目の切梁5Aの施工が完了したら、図3で示すようにバケット式の掘削機M4やバックホーM3などを使用してさらに地盤の掘削を進め、所定深度までの掘削が完了した段階で、たとえば2段目の切梁5B、3段目の切梁5Cを掘削地盤面に吊り降ろしておく。   When the construction of the first stage beam 5A is completed, as shown in FIG. 3, the excavation of the ground is further advanced by using the bucket excavator M4, the backhoe M3, etc., and the excavation to the predetermined depth is completed. For example, the second stage beam 5B and the third stage beam 5C are suspended from the excavated ground surface.

そして、既に設置済みの1段目の切梁5Aの下方位置に地下構造物の天井スラブ11とこれと連続するようにして側壁の一部12’を施工し、この天井スラブ11および側壁の一部12’で土留め壁1を支保させる。   Then, the ceiling slab 11 of the underground structure and a part 12 'of the side wall are constructed so as to be continuous with the ceiling slab 11 of the underground structure below the first stage beam 5A that has already been installed. The retaining wall 1 is supported by the part 12 ′.

ここで、土留め壁1には予め不図示のジベルを内側に張り出させておき、このジベルを巻き込むようにして天井スラブ11や側壁の一部12’を施工することで、これらの地下構造物構成部材と土留め壁1との強固な接続構造を形成することができる。この強固な接続構造により、天井スラブ11等と土留め壁1の間の相対変位が抑止され、もって土留め壁1の変形抑制効果を高めることができるとともに、これに起因する土留め壁周辺の地盤の変形抑制効果を高めることもできる。   Here, the earth retaining wall 1 is preliminarily extended with a not-illustrated divel, and the ceiling slab 11 and the side wall part 12 'are constructed so as to enclose the divel. A strong connection structure between the object constituent member and the earth retaining wall 1 can be formed. With this strong connection structure, the relative displacement between the ceiling slab 11 and the retaining wall 1 is suppressed, so that the deformation suppressing effect of the retaining wall 1 can be enhanced, and the surrounding of the retaining wall due to this can be improved. The effect of suppressing the deformation of the ground can also be enhanced.

次に、図4で示すように、対向する側壁の一部12’、12’の内側に腹起し4B,4Bを設置し、腹起し4B,4B間に既に吊り降ろされている切梁5Bを設置し、この切梁5Bに所望のプレロードを導入する。   Next, as shown in FIG. 4, the raised beams 4B and 4B are installed inside the opposing side wall portions 12 'and 12', and the beams are already suspended between the raised portions 4B and 4B. 5B is installed, and a desired preload is introduced into this cut beam 5B.

このプレロードの導入に際しては、天井スラブ11を構成するスラブ筋等に予め不図示の歪みゲージを設置しておき、歪みゲージによる計測データを現場管理者が参照してこのプレロード値を設定するのがよい。このようにして導入プレロードを設定することで、掘削に伴う土留め壁周辺地盤の変位を効果的に抑制しながら、これと同時に、既に構築されている天井スラブ11や側壁の一部12’に生じ得る残留応力やクラックを最小限に制御することができる。   When this preload is introduced, a strain gauge (not shown) is installed in advance on the slab muscle constituting the ceiling slab 11, and the site manager sets the preload value by referring to the measurement data from the strain gauge. Good. By setting the introduction preload in this manner, the displacement of the ground around the retaining wall caused by excavation is effectively suppressed, and at the same time, the already constructed ceiling slab 11 and side wall part 12 ' Residual stresses and cracks that can occur can be controlled to a minimum.

図4で示す状態において、対向する土留め壁1,1を支保する天井スラブ11は実質的に高剛性の切梁と見なすことができ、1段目の切梁5Aと、天井スラブ11(実質的に2段目の切梁)と、側壁の一部12’、12’間に掛け渡された切梁5B(実質的に3段目の切梁)と、の3段の切梁で土留め壁1,1が支保されることとなる。このことより、この掘削段階で3段の切梁設置が余儀なくされていた従来の逆巻き工法に比して、1段分の切梁および腹起しの設置が不要となり、仮設費用の大幅な節減と工費の短縮を図ることができる。   In the state shown in FIG. 4, the ceiling slab 11 supporting the retaining walls 1 and 1 facing each other can be regarded as a substantially high-rigidity beam, and the first-stage beam 5A and the ceiling slab 11 (substantially The second stage of the beam) and the beam 5B (substantially the third stage of the beam) spanned between the side wall portions 12 ', 12', The retaining walls 1 and 1 are supported. Therefore, compared to the conventional reverse winding method, in which three stages of cut beams were inevitably installed at this excavation stage, the installation of one stage of cut beams and uplifts is no longer necessary, resulting in a significant reduction in temporary costs. This can reduce the construction cost.

実質的に3段の切梁で土留め壁1,1を支保したら、図5で示すように、まず、土留め壁の支保として不要となった1段目の切梁5A,腹起し4Aを撤去し、さらに地盤の掘削を進め、既に吊り降ろされている腹起し4Cを双方の土留め壁1,1に設置し、この腹起し4C,4C間に切梁5Cを掛け渡す。   If the retaining walls 1 and 1 are supported by substantially three-stage beams, as shown in FIG. 5, first, the first-stage beams 5A and the protuberance 4A that are no longer necessary for supporting the retaining walls are used. The excavation of the ground is further carried out, and the uplifted 4C that has already been hung is installed on both earth retaining walls 1 and 1, and the cut beam 5C is bridged between the uplifted 4C and 4C.

なお、1段目の切梁5A,腹起し4Aの撤去のタイミングは、図示例以外にも、図4で示す天井スラブ11にて土留め壁1,1を支保した後にこれらの撤去をおこなうこともでき、撤去のタイミングで決定される土留め壁1や天井スラブ11等の内部応力や、作業効率性等によって1段目の支保工の撤去のタイミングが決定される。   In addition to the illustrated example, the first stage beam 5A and the erection 4A are removed after the retaining walls 1 and 1 are supported by the ceiling slab 11 shown in FIG. In addition, the removal timing of the first stage support is determined by the internal stress of the retaining wall 1 and the ceiling slab 11 determined at the removal timing, work efficiency, and the like.

土留め壁1,1間に切梁5Cを掛け渡したら、さらに地盤の掘削を進め、図6で示すように、床付け面を形成し、この床付け面上に均しコンクリートスラブ6を施工する。   When the cut beam 5C is passed between the retaining walls 1 and 1, the ground is further excavated to form a flooring surface as shown in FIG. 6, and the leveled concrete slab 6 is constructed on the flooring surface. To do.

この均しコンクリートスラブ6内には鉄筋や網筋等が配設され、これを土圧耐荷部材と見なすことができる。すなわち、土留め壁1,1間に施工された均しコンクリートスラブ6が切梁と同様の土留め壁支保作用を奏するものである。   In the leveled concrete slab 6, reinforcing bars, mesh bars, and the like are disposed, and these can be regarded as earth pressure load bearing members. That is, the leveled concrete slab 6 constructed between the retaining walls 1 and 1 has the same retaining wall supporting action as that of the cut beam.

図7で示すように土留め壁1,1間に均しコンクリートスラブ6が施工されたら、これで土留め壁1,1の下端を支保させ、側壁の一部12’、12’間に掛け渡された切梁5Bおよび腹起し4Bと、その下方の切梁5Cおよび腹起し4Cを撤去する。   When the leveled concrete slab 6 is constructed between the retaining walls 1 and 1 as shown in FIG. 7, the lower ends of the retaining walls 1 and 1 are supported by this, and hung between the side walls 12 'and 12'. The cut beam 5B and the erection 4B which have been passed, and the lower beam 5C and the erection 4C below it are removed.

これらの支保工を撤去することにより、以後の地下構造物の構築施工に際して広範な作業スペースが確保され、効率のよい地下構造物の構築が保証される。   By removing these support works, a wide work space is secured in the subsequent construction of the underground structure, and an efficient construction of the underground structure is guaranteed.

次に、図8で示すように、施工ヤード内で残置されていた掘削残土を天井スラブ11上に埋戻し(埋戻し土7)、均しコンクリートスラブ6上に床スラブ13を施工する。   Next, as shown in FIG. 8, the excavated residual soil left in the construction yard is backfilled on the ceiling slab 11 (backfill soil 7), and the floor slab 13 is constructed on the leveled concrete slab 6.

なお、天井スラブ11上への掘削残土の埋戻しのタイミングは図示例に限定されるものではなく、最早は、図5で示す1段目の支保工を撤去した後のタイミングとなり得る。   In addition, the timing of the backfilling of the excavation residual soil on the ceiling slab 11 is not limited to the illustrated example, and can be the timing after removing the first stage support shown in FIG.

床スラブ13の施工が完了したら、図9で示すように側壁の残りを下方から上方に向かって施工し、既に施工済みの側壁の一部12’と一体化させることで側壁12の施工が完了し、少なくとも天井スラブ11、床スラブ13および側壁12からなる地下構造物10が構築される。   When the construction of the floor slab 13 is completed, the construction of the side wall 12 is completed by constructing the remainder of the side wall from the bottom to the top as shown in FIG. And the underground structure 10 which consists of the ceiling slab 11, the floor slab 13, and the side wall 12 at least is constructed.

なお、中間杭2は、天井スラブ11や床スラブ13の施工に際してこれらに設けられた不図示の開口内を通って地下構造物の上下に亘って残置されていることから、図10で示すように、地下構造物10と干渉する箇所を撤去し(未干渉箇所2’はそのまま残置)、不図示の開口を間詰め処理することにより、地下構造物の構築施工が完了する。   The intermediate pile 2 is left over the top and bottom of the underground structure through the openings (not shown) provided in the ceiling slab 11 and the floor slab 13 as shown in FIG. In addition, by removing the portion that interferes with the underground structure 10 (the non-interfering portion 2 ′ is left as it is), the construction of the underground structure is completed by performing a filling process on an unillustrated opening.

図示する本発明の地下構造物の構築方法によれば、従来の逆巻き工法に改良を加えて天井スラブに土留め壁を支保させ、さらにこれと一体に側壁の一部を施工してこの内部に切梁を設置するとともに所望のプレロードを導入したことにより、支保工の段数を低減することができ、さらには、土留め壁の変形やその周辺の地盤変形をより効果的に抑制することができる。   According to the construction method of the underground structure of the present invention shown in the figure, the conventional reverse winding method is improved to support the earth retaining wall on the ceiling slab, and further, a part of the side wall is constructed integrally with the ceiling retaining wall. By installing the desired beam and installing the desired preload, it is possible to reduce the number of steps of the support work, and more effectively suppress the deformation of the retaining wall and the surrounding ground deformation. .

また、床スラブを施工した後に側壁を下方から上方に向かって順巻き施工のごとく施工することから、側壁の打ち継目に施工不良を生じ難くすることができる。   Moreover, since a side wall is constructed like a forward winding construction from the lower side to the upper side after the floor slab is constructed, it is possible to make it difficult to cause a construction failure at the joint of the side walls.

さらに、高剛性の天井スラブにて土留め壁を支保することから、早期にこの天井スラブよりも上方の1段目の支保工を撤去することができ、掘削残土を早期にこの天井スラブ上に埋戻すことで残土ヤードを別目的に有効利用することも可能となる。   Furthermore, since the earth retaining wall is supported by a high-stiffness ceiling slab, the first stage of the support work above the ceiling slab can be removed at an early stage, and the excavated residual soil can be quickly put on the ceiling slab. By backfilling, the remaining soil yard can be effectively used for another purpose.

なお、逆巻き工法を適用した際に享受できる固有の効果、すなわち、支保工が配筋作業や防水施工の妨げにならないことで高効率な施工をおこなえること、したがって、地下構造物の外面防水の高い品質を保証できること、などの効果を本発明の構築方法が有していることは言うまでもないことである。   In addition, the unique effect that can be enjoyed when the reverse winding method is applied, that is, the support work can be performed efficiently because it does not interfere with the bar arrangement work and waterproof construction, and therefore the outer surface of the underground structure is highly waterproof. It goes without saying that the construction method of the present invention has effects such as quality assurance.

以上、本発明の実施の形態を図面を用いて詳述してきたが、具体的な構成はこの実施形態に限定されるものではなく、本発明の要旨を逸脱しない範囲における設計変更等があっても、それらは本発明に含まれるものである。   The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration is not limited to this embodiment, and there are design changes and the like without departing from the gist of the present invention. They are also included in the present invention.

1…土留め壁、2…中間杭、2’…切断後の中間杭、3…地盤改良体、4A,4B,4C…腹起し、5A,5B,5C…切梁、6…均しコンクリートスラブ、7…埋戻し土、10…地下構造物、11…天井スラブ、12…側壁、12’…側壁の一部、13…床スラブ、G…原地盤   DESCRIPTION OF SYMBOLS 1 ... Earth retaining wall, 2 ... Intermediate pile, 2 '... Intermediate pile after cutting, 3 ... Ground improvement body, 4A, 4B, 4C ... Raised, 5A, 5B, 5C ... Cut beam, 6 ... Leveling concrete Slab, 7 ... Backfill soil, 10 ... Underground structure, 11 ... Ceiling slab, 12 ... Side wall, 12 '... Part of side wall, 13 ... Floor slab, G ... Original ground

Claims (6)

地盤内で対向する位置に土留め壁を施工する第1の工程、
対向する土留め壁で囲まれた地盤に対して地表から掘削を進め、天井スラブが構築される位置よりも高い位置で対向する土留め壁の双方に腹起しを設置するとともに対向する腹起しの間に切梁を設置する第2の工程、
さらに掘削を進めて、地下構造物のうちの少なくとも天井スラブを構築し、この天井スラブに土留め壁を支保させる第3の工程、
さらに掘削を進め、掘削の進行にともなって天井スラブの下方にさらに別途の腹起しおよび切梁を設置して床付け面を施工し、床付け面上に均しコンクリートスラブを構築し、天井スラブと均しコンクリートスラブの間の前記別途の腹起しおよび切梁を撤去し、均しコンクリートスラブを土圧耐荷部材として天井スラブと均しコンクリートスラブで土留め壁を支保させ、均しコンクリートスラブ上に床スラブを構築し、側壁を上方に向かって構築して、少なくとも天井スラブと床スラブと側壁からなる地下構造物を構築する第4の工程、からなる地下構造物の構築方法。
A first step of constructing a retaining wall at an opposing position in the ground;
Proceed with excavation from the ground surface against the ground surrounded by the opposite retaining wall, and install a bulge on both opposing retaining walls at a position higher than the position where the ceiling slab is constructed and face the opposite flank A second step of installing a cutting beam between
A third step of further excavation to construct at least a ceiling slab of the underground structure and to support a retaining wall on the ceiling slab;
Further advance the drilling, with the progress of the excavation by installing a further separate wale and Setsuhari below the ceiling slab construction the floor with surface, to build a concrete slab leveling on the floor with surface, ceiling The above-mentioned separate uplift and slab between the slab and the leveled concrete slab are removed , the leveled concrete slab is used as an earth pressure load bearing member, and the retaining wall is supported by the leveled concrete slab and the leveled concrete slab. A method for constructing an underground structure comprising a fourth step of constructing a floor slab on a slab, constructing a side wall upward, and constructing an underground structure composed of at least a ceiling slab, a floor slab and a sidewall.
前記第3の工程では、天井スラブに加えて側壁の一部も構築し、対向する側壁の一部の間に別途の切梁を設置してプレロードを導入する、請求項1に記載の地下構造物の構築方法。   2. The underground structure according to claim 1, wherein, in the third step, a part of the side wall is constructed in addition to the ceiling slab, and a preload is introduced by installing a separate beam between parts of the opposing side wall. How to build things. 前記天井スラブに歪計を配しておき、歪計による計測データを参照して切梁に導入されるプレロードが設定される、請求項2に記載の地下構造物の構築方法。   The construction method of an underground structure according to claim 2, wherein a strain gauge is arranged on the ceiling slab, and a preload to be introduced to the cut beam is set with reference to measurement data obtained by the strain gauge. 前記第3の工程では、天井スラブが構築された後、もしくは別途の切梁にプレロードが導入された後に、天井スラブよりも上方にある腹起しおよび切梁が撤去される、請求項2又は3に記載の地下構造物の構築方法。 Wherein in the third step, after the ceiling slab is constructed, or after the preload it has been introduced into separate Setsuhari, the wale and Setsuhari lying above are removed than the ceiling slab, claim 2 or The construction method of the underground structure of 3 . 天井スラブよりも上方にある腹起しおよび切梁が撤去された後に、天井スラブの上方に埋戻し施工がおこなわれる、請求項に記載の地下構造物の構築方法。 The construction method of an underground structure according to claim 4 , wherein the backfilling operation is performed above the ceiling slab after the erection and the cut beam above the ceiling slab are removed. 前記土留め壁には予め地下構造物内に埋設されるジベルが設けてあり、前記第3の工程において、少なくとも天井スラブがこのジベルを巻込みながら構築される、請求項1〜のいずれかに記載の地下構造物の構築方法。 The said soil retaining wall is provided with a dowel which is embedded in the previously underground structures, in the third step, at least the ceiling slab is constructed with inclusion of the dowels, claim 1-5 Construction method of underground structure as described in 2.
JP2010119239A 2010-05-25 2010-05-25 Construction method of underground structure Active JP5465086B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010119239A JP5465086B2 (en) 2010-05-25 2010-05-25 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010119239A JP5465086B2 (en) 2010-05-25 2010-05-25 Construction method of underground structure

Publications (2)

Publication Number Publication Date
JP2011246910A JP2011246910A (en) 2011-12-08
JP5465086B2 true JP5465086B2 (en) 2014-04-09

Family

ID=45412511

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010119239A Active JP5465086B2 (en) 2010-05-25 2010-05-25 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JP5465086B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102518458B (en) * 2011-12-22 2014-04-16 中铁工程设计咨询集团有限公司 Construction method of top beam part of underground bus stop
CN103866789A (en) * 2014-03-19 2014-06-18 重庆大学 Control method for cracks generated during construction period of basement baseboard
CN106948350B (en) * 2017-05-10 2018-10-16 中铁隧道集团四处有限公司 The rapid constructing method of deep basal pit accessory structure
JP7284800B1 (en) 2021-11-18 2023-05-31 西武建設株式会社 Construction method of underpass under railroad tracks

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3390081B2 (en) * 1994-03-07 2003-03-24 株式会社フジタ How to build an underground parking
JP3248458B2 (en) * 1997-07-29 2002-01-21 鹿島建設株式会社 Shoring construction underground construction method
JP4083334B2 (en) * 1999-01-27 2008-04-30 株式会社奥村組 Underground structure having arch roof and method for constructing the same
JP2003171928A (en) * 2001-12-04 2003-06-20 Kawasaki Steel Corp Compound underground wall body and its construction method

Also Published As

Publication number Publication date
JP2011246910A (en) 2011-12-08

Similar Documents

Publication Publication Date Title
KR20090002344A (en) Land-side protection wall that use ground structure
KR100967497B1 (en) Method for constructing an underground structure
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
JP5465086B2 (en) Construction method of underground structure
JP4914062B2 (en) Two-tiered retaining wall and its construction method
JP5698405B1 (en) Ground improvement solid foundation method
JP5038170B2 (en) How to rebuild a structure
KR101262357B1 (en) Inclined Earth Retaining Structure Method
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
JP5681039B2 (en) Mountain fastening method
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
KR101310677B1 (en) Top down method using precast composite retaining wall and raker in slope
KR100967496B1 (en) Device for constructing an underground structure
JP5739051B1 (en) Liquefaction countermeasure structure for ground improvement solid foundation and correction method for occurrence of uneven settlement due to liquefaction
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
KR100615149B1 (en) A method of construction top-down for the ground fabric construction
JP2018091107A (en) Method for constructing underground structure
JP6052541B2 (en) Seismic isolation method for existing buildings
JP6710999B2 (en) Temporary receiving method for existing structures
CN105735324B (en) The platform disassembly method of steel sheet pile supporting
JP4749858B2 (en) Method for enhancing bearing capacity in extension or reconstruction of superstructures of existing buildings
JP4529631B2 (en) Underground structure and construction method of underground structure
JP2004176434A (en) Method for constructing structure and underground skeleton
JP2019157508A (en) Under-ground piled column and seismic base-isolated buildings
JP3879085B2 (en) Uneven settlement settlement method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120919

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130722

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130730

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130913

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140107

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140121

R150 Certificate of patent or registration of utility model

Ref document number: 5465086

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250