JP5465086B2 - Construction method of underground structure - Google Patents
Construction method of underground structure Download PDFInfo
- Publication number
- JP5465086B2 JP5465086B2 JP2010119239A JP2010119239A JP5465086B2 JP 5465086 B2 JP5465086 B2 JP 5465086B2 JP 2010119239 A JP2010119239 A JP 2010119239A JP 2010119239 A JP2010119239 A JP 2010119239A JP 5465086 B2 JP5465086 B2 JP 5465086B2
- Authority
- JP
- Japan
- Prior art keywords
- slab
- underground structure
- ceiling slab
- ceiling
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims description 79
- 238000000034 method Methods 0.000 claims description 33
- 238000009412 basement excavation Methods 0.000 claims description 26
- 239000002689 soil Substances 0.000 claims description 17
- 230000036316 preload Effects 0.000 claims description 13
- 238000005520 cutting process Methods 0.000 claims description 5
- 238000005259 measurement Methods 0.000 claims description 3
- 238000005553 drilling Methods 0.000 claims 1
- 238000004804 winding Methods 0.000 description 22
- 230000002441 reversible effect Effects 0.000 description 15
- 229910000831 Steel Inorganic materials 0.000 description 10
- 239000010959 steel Substances 0.000 description 10
- 238000009408 flooring Methods 0.000 description 9
- 238000010586 diagram Methods 0.000 description 7
- 230000008569 process Effects 0.000 description 7
- 230000008093 supporting effect Effects 0.000 description 6
- 230000003014 reinforcing effect Effects 0.000 description 5
- 238000006073 displacement reaction Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 4
- 239000003673 groundwater Substances 0.000 description 3
- 230000006872 improvement Effects 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- 230000002035 prolonged effect Effects 0.000 description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 239000004035 construction material Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000005429 filling process Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 238000000275 quality assurance Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 230000000717 retained effect Effects 0.000 description 1
- 238000007788 roughening Methods 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- 230000008961 swelling Effects 0.000 description 1
- 230000032258 transport Effects 0.000 description 1
- 238000004078 waterproofing Methods 0.000 description 1
Images
Description
本発明は、地盤の掘削にともない、地下構造物を上方から順に施工する逆巻き工法に改良を加えた地下構造物の構築方法に関するものである。 The present invention relates to a construction method for an underground structure obtained by improving the reverse winding method for constructing an underground structure in order from the top as the ground is excavated.
地下構造物の構築方法には、土留め壁の内側に腹起しや切梁等からなる土留め支保工を施工して土留め壁で包囲された地盤を床付けまで掘削し、下方の床スラブから順に上方に地下構造物を構築していく、いわゆる順巻き工法や、土留め壁を施工し、上方から支保工の設置と掘削を繰り返しながら、地下構造物の天井スラブを先行して施工し、下方に向かって順に側壁と床スラブを施工する、いわゆる逆巻き工法などが知られている。 The construction method of the underground structure is to dig a ground support structure made up of erections, beams, etc. inside the retaining wall, excavate the ground surrounded by the retaining wall to the floor, The so-called forward-winding method that builds the underground structure upward from the slab and the retaining wall, and the installation and excavation of the support structure from the top are repeated in advance to construct the ceiling slab of the underground structure. And what is called a reverse winding method etc. which construct a side wall and a floor slab in order toward the downward direction are known.
さらには、別途のヤードや工場などで予めコンクリート製もしくは鋼製のケーソンを製作し、これを施工ヤードへ搬送し、人力掘削や機械掘削にて地盤の掘削をおこないながらケーソンを沈設するケーソン工法(ニューマチックケーソン、潜函ケーソン、圧気ケーソンなど)も知られるところである。 In addition, a caisson method that constructs a concrete or steel caisson in a separate yard or factory in advance, transports it to the construction yard, and sinks the caisson while excavating the ground by manual or mechanical excavation ( Pneumatic caisson, submersible caisson, pressure caisson, etc.) are also known.
上記する順巻き工法では、床付けまで掘削をおこなって広範な施工空間を形成した後に地下構造物の構築をおこなうことから作業効率性に優れているというメリットがある一方で、地下構造物用の配筋作業に際して、支保工を構成する腹起しや切梁が往々にしてこの配筋作業の妨げになるといった問題や、この支保工が地下構造物の壁面に設けられる防水施工の障害になるといった問題が顕在化している。 The above-mentioned forward winding method has the merit that it is excellent in work efficiency because it constructs the underground structure after excavating to flooring and forming a wide construction space, but for the underground structure During bar arrangement work, problems such as the erection and cutting beams that make up the support work often interfere with this work, and this support work becomes an obstacle to the waterproof construction provided on the walls of underground structures. Such a problem has become apparent.
また、地下構造物の中でも天井スラブの構築が最後となるために、この天井スラブ上方への掘削残土の埋戻し作業が工程の最後とならざるを得ず、掘削残土用のヤードが工程の最初から最後まで残土で占有されてしまうといった問題もある。 In addition, since the construction of the ceiling slab is the last of the underground structures, the work of backfilling the excavated residual soil above the ceiling slab must be the last of the process, and the yard for the excavated residual soil is the first of the process. There is also a problem of being occupied by the remaining soil from the end to the end.
このような順巻き工法の有する課題に対して、上記する逆巻き工法を適用することで、地盤掘削に応じて支保工が設置され、地下構造物の構築も上方から順におこなわれることから、支保工が配筋作業や防水施工の妨げになることもなく、地下構造物の中でも天井スラブが最初に構築されることから残土の埋戻しも早期におこなうことができ、残土用ヤードを他の用途に有効利用することが可能となる。 By applying the reverse winding method described above to the problem of such a forward winding method, a support work is installed according to the ground excavation, and the construction of the underground structure is also performed in order from the top. Will not disturb the bar arrangement work and waterproofing work, and the ceiling slab will be built first in the underground structure, so the remaining soil can be backfilled early, and the remaining soil yard can be used for other purposes. It can be used effectively.
しかし、逆巻き工法を適用した場合には、下方に向かって側壁を構築していくために、側壁の打ち継目に施工不良が生じ易いという大きな課題があり、さらには、上方に構築された地下構造物のたとえば天井スラブと掘削床の間の限られた空間に資材や施工機械、施工材料を搬入し、この空間内でさらなる掘削をおこなったり、地下構造物の構築をおこなうことから非効率な施工が余儀なくされるといった問題がある。 However, when the reverse winding method is applied, in order to construct the side wall downward, there is a major problem that construction failure tends to occur at the joint of the side wall, and further, the underground structure constructed above For example, materials, construction machines, and construction materials are brought into a limited space between the ceiling slab and the excavation floor of the object, and further excavation and construction of underground structures are unavoidable in this space. There is a problem of being.
このように、順巻き工法や逆巻き工法にはそれぞれに固有のメリットとデメリットがあるが、たとえば逆巻き工法においては上記する固有のデメリットがあるが故に、我が国におけるアンダーパス工事にこの逆巻き工法が適用されず、ケーソン工法が多用されるに至っている。 In this way, the forward winding method and the reverse winding method have their own merits and demerits. For example, the reverse winding method has the inherent merits described above, so this reverse winding method is applied to underpass construction in Japan. First, the caisson method has been used frequently.
ここで、逆巻き工法に改良を加えた従来の公開技術が特許文献1に開示されている。この施工方法は、地下構造物の1階床スラブのうちで土留め壁を支保し得る必要最小限の部分のみを先行施工し、次いで掘削を進め、同様に地下構造物の地下1階床スラブのうちで土留め壁を支保し得る必要最小限の部分のみを先行施工し、これを繰り返して床付けまでの掘削を終了した後に上方へ向かって地下構造物を構築するものである。
Here,
特許文献1に開示の施工方法によれば、側壁を下方から上方へ向かって施工できることから、上記する逆巻き工法の有する課題、すなわち、側壁の打ち継目に施工不良が生じ易いという課題を解消することはできる。しかし、下方から上方へ地下構造物を構築していくに当たり、各階の床スラブが、支保工として使用される先行施工箇所と、この先行施工箇所と一体とされる後行施工箇所に分かれており、したがって各階の床スラブを2度に亘って施工する必要があることから、施工効率が極めて悪く、工期の長期化は否めない。
According to the construction method disclosed in
本発明は上記する問題に鑑みてなされたものであり、従来のいわゆる逆巻き工法に改良を加えることで、側壁の打ち継目に施工不良が生じ易いという課題を解消でき、さらには、工期を長期化させることのない地下構造物の構築方法を提供することを目的としている。 The present invention has been made in view of the above-mentioned problems, and by improving the conventional so-called reverse winding method, it is possible to eliminate the problem that construction failure tends to occur at the joint of the side walls, and further, the construction period is lengthened. It aims at providing the construction method of the underground structure which does not let it.
前記目的を達成すべく、本発明による地下構造物の構築方法は、地盤内で対向する位置に土留め壁を施工する第1の工程、対向する土留め壁で囲まれた地盤に対して地表から掘削を進め、対向する土留め壁の双方に腹起しを設置するとともに対向する腹起しの間に切梁を設置する第2の工程、さらに掘削を進めて、地下構造物のうちの少なくとも天井スラブを構築し、この天井スラブに土留め壁を支保させる第3の工程、さらに掘削を進めて床付け面を施工し、床付け面上に均しコンクリートスラブを構築し、腹起しおよび切梁を撤去して、均しコンクリートスラブ上に床スラブを構築し、側壁を上方に向かって構築して、少なくとも天井スラブと床スラブと側壁からなる地下構造物を構築する第4の工程、からなるものである。 In order to achieve the above-mentioned object, the construction method of an underground structure according to the present invention is a first step of constructing a retaining wall at an opposing position in the ground, the ground surface with respect to the ground surrounded by the opposing retaining wall. The second step of installing excavation from both sides of the opposite retaining wall and installing a beam between the opposing uprights, further excavation, Build at least a ceiling slab, and support the retaining wall to the ceiling slab, and proceed with excavation to construct the flooring surface, build a leveled concrete slab on the flooring surface, And cutting the beams, constructing a floor slab on the leveled concrete slab, constructing the side wall upward, and constructing an underground structure consisting of at least the ceiling slab, the floor slab and the side wall , Is made up of.
ここで、第1の工程における「対向する位置に土留め壁を施工する」とは、土留め壁を平面視で矩形、正方形、その他の多角形、円形、楕円形等の枠状(無端状)に施工することにより、2組もしくは3組以上の対向した土留め壁の組み合わせが形成されることを意味している。たとえば、平面視矩形の土留め壁の場合には、長辺の一組の対向する土留め壁と、短辺の一組の対向する土留め壁が存在することになる。 Here, “constructing the retaining wall at the opposite position” in the first step means that the retaining wall has a frame shape (endless shape) such as a rectangle, a square, other polygons, a circle, or an ellipse in plan view. This means that two or three or more pairs of earth retaining walls are formed. For example, in the case of a rectangular retaining wall in plan view, there is a pair of opposing retaining walls with a long side and a pair of opposing retaining walls with a short side.
施工される土留め壁の形態は、地中連続壁や柱列式連続壁、鋼矢板や親杭横矢板、鋼管矢板などのいずれであってもよい。また、必要に応じて土留め壁の所望深度領域に地盤改良をおこなってもよい。 The form of the earth retaining wall to be constructed may be an underground continuous wall, a columnar continuous wall, a steel sheet pile, a main pile horizontal sheet pile, a steel pipe sheet pile, or the like. Moreover, you may perform ground improvement to the desired depth area | region of a retaining wall as needed.
土留め壁の施工後、地表から掘削を進めて対向する土留め壁間に腹起しおよび切梁を設置し、さらに掘削を進めて、地下構造物を構成する少なくとも天井スラブを構築してこの天井スラブで土留め壁を支保させる。 After construction of the retaining wall, proceed with excavation from the surface of the earth, install upset and cut beams between the opposing retaining walls, and proceed with further excavation to construct at least a ceiling slab that constitutes the underground structure. Support the retaining wall with a ceiling slab.
ここで、天井スラブの上方に施工される腹起しおよび切梁は、1段であっても複数段であってもよい。 Here, the erection and the cutting beam constructed above the ceiling slab may be one stage or a plurality of stages.
また、構築される地下構造物の構成部材である天井スラブ等は、RC構造、SRC構造、SC構造のいずれであってもよく、コンクリート内に埋設される緊張材は、鉄筋、PC鋼材(PC鋼棒、PC鋼線、PC鋼より線)、鉄筋とPC鋼材の組み合わせなどのいずれであってもよい。 In addition, the ceiling slab, which is a component of the constructed underground structure, may be any of an RC structure, an SRC structure, and an SC structure, and the tension material embedded in the concrete is a reinforcing bar, a PC steel (PC) Any of a combination of steel bars, PC steel wires, PC steel strands), reinforcing bars and PC steel materials may be used.
構築される天井スラブが土留め壁を支保することから、この天井スラブを切梁と見なすことができ、この天井スラブ位置に設置されるはずの切梁を不要とできることで仮設に要する工費を節減することができる。なお、本発明の構築方法では、この段階で地下構造物として天井スラブの全てを施工する。 Since the ceiling slab to be built supports the retaining wall, this ceiling slab can be regarded as a cut beam, and it is possible to eliminate the need for a cut beam that should be installed at this ceiling slab position, thereby reducing the construction cost required for temporary construction. can do. In the construction method of the present invention, all the ceiling slabs are constructed as underground structures at this stage.
ここで、前記土留め壁には予め地下構造物内に埋設されるジベルが設けてあり、前記第3の工程において、少なくとも天井スラブがこのジベルを巻込みながら構築されることにより、土留め壁と天井スラブの相対変位が抑制され、天井スラブにて土留め壁の掘削側への変形を効果的に抑止することができる。さらには、ジベルを介して土留め壁と天井スラブからなる剛性の高い門型ラーメン構造が形成でき、この天井スラブ上に掘削残土等が埋戻された際の天井スラブの撓みを可及的に少なくすることができる。 Here, the retaining wall is provided with a pre-embedded divel in the underground structure in advance, and in the third step, at least the ceiling slab is constructed while winding the gibel, thereby retaining the retaining wall. The relative displacement of the ceiling slab is suppressed, and the ceiling slab can effectively suppress the deformation of the retaining wall to the excavation side. Furthermore, a rigid portal ramen structure consisting of a retaining wall and a ceiling slab can be formed via a gibber, and the bending of the ceiling slab as much as possible after the excavated soil is backfilled on this ceiling slab is made as much as possible. Can be reduced.
少なくとも天井スラブで土留め壁を支保させた後に、掘削を進めて床付け面を施工し、床付け面上に均しコンクリートスラブを構築し、腹起しおよび切梁を撤去して、均しコンクリートスラブ上に床スラブを構築し、側壁を上方に向かって構築することにより、少なくとも天井スラブと床スラブと側壁からなる地下構造物が構築される。ここで、「少なくとも天井スラブと床スラブと側壁からなる地下構造物」とは、これらの構成部材のみからなる地下構造物のほかにも、天井スラブと床スラブ(最下階の床スラブ)の間に複数階の床スラブを具備する地下構造物や、さらに各階に壁や柱を具備する地下構造物などを包含する意味である。 After supporting the retaining wall with at least the ceiling slab, proceed with excavation to construct the flooring surface, build a leveled concrete slab on the flooring surface, remove the flank and the cut beam, level By constructing a floor slab on the concrete slab and constructing the side walls upward, an underground structure composed of at least a ceiling slab, a floor slab, and a side wall is constructed. Here, “an underground structure consisting of at least a ceiling slab, a floor slab, and a side wall” means a ceiling slab and a floor slab (floor slab on the lowest floor) in addition to an underground structure consisting only of these components. It is meant to include underground structures having a plurality of floor slabs between them, and underground structures having walls and pillars on each floor.
均しコンクリートスラブを施工することでこれを土圧耐荷部材と見なし、この均しコンクリートスラブと天井スラブで土留め壁を支保することにより、この天井スラブと均しコンクリートスラブの間の腹起しおよび切梁のすべてを撤去することが可能となる。なお、均しコンクリートスラブを土圧耐荷部材と見なすに当たり、必要に応じて均しコンクリートスラブ内に鉄筋や網筋等を配設してもよい。 By constructing a leveled concrete slab, this is regarded as an earth pressure load-bearing member, and a retaining wall is supported by the leveled concrete slab and the ceiling slab. And all of the beams can be removed. In considering the leveled concrete slab as an earth pressure load bearing member, reinforcing bars, mesh bars, etc. may be provided in the leveled concrete slab as necessary.
天井スラブと均しコンクリートスラブの間の腹起しおよび切梁のすべてが撤去されたら、均しコンクリートスラブ上に床スラブを構築し、この床スラブから上方に側壁を立上げていく。すなわち、側壁を下方から上方に構築する点において、従来の逆巻き工法とは大きく異なっている。 When all of the erection and the beam between the ceiling slab and the leveled concrete slab are removed, a floor slab is constructed on the leveled concrete slab, and a side wall is raised upward from the floor slab. That is, it differs greatly from the conventional reverse winding method in that the side walls are constructed from the bottom to the top.
この従来の逆巻き工法が改良された本発明の構築方法によれば、側壁は順巻き工法のように下方から上方に向かって施工されることから、側壁の打ち継目における施工不良は生じ難い。 According to the construction method of the present invention in which the conventional reverse winding method is improved, since the side wall is constructed from the lower side to the upper side as in the forward winding method, it is difficult to cause poor construction at the joint of the side wall.
また、地下構造物を構成する天井スラブ、床スラブ等はそれぞれ、地下構造物の構築段階で一気にそれらの構築がおこなわれることから、各構成部材を2度に分けて構築することで齎される工期の長期化といった問題も生じ得ない。 In addition, the ceiling slab, floor slab, etc. that make up the underground structure are constructed at once in the construction stage of the underground structure. The problem of longevity cannot occur.
なお、従来の公開技術のように床スラブを2度に分けて施工する場合には、先行施工箇所と後行施工箇所の取合部の一体化と止水性確保を保証するために、先行施工箇所の取合部に面粗し施工をおこなったり、止水施工をおこなうなどの付加施工が余儀なくされることから、これらの付加施工も工期の長期化や工費の増大の原因となるのである。 In addition, when the floor slab is divided into two parts as in the conventional open technology, the prior construction is performed to ensure the integration of the joint part of the preceding construction part and the subsequent construction part and the securing of water stoppage. Since additional construction such as roughening construction or water stop construction at the joint portion of the location is unavoidable, these additional constructions also cause the construction period to be prolonged and the construction cost to increase.
また、本発明による地下構造物の構築方法の好ましい実施の形態において、天井スラブに加えて側壁の一部も構築し、対向する側壁の一部の間に別途の切梁を設置してプレロードを導入するものである。 Further, in a preferred embodiment of the method for constructing an underground structure according to the present invention, a part of the side wall is constructed in addition to the ceiling slab, and a separate beam is installed between a part of the opposite side walls to perform preloading. It is to be introduced.
この構築方法の実施の形態は、土留め壁の支保工として、地下構造物の天井スラブを適用することに加えて、この天井スラブと一体に側壁の一部を施工しておき、対向する側壁の一部の間に切梁を設置し、さらにこの切梁に所望するプレロードを導入して支保工とするものである。 In addition to applying the ceiling slab of the underground structure as a support for the retaining wall, the embodiment of this construction method is constructed such that a part of the side wall is constructed integrally with the ceiling slab, and the opposite side wall A beam is installed between a part of the beam, and a desired preload is introduced into the beam to provide a support work.
本実施の形態の施工方法によれば、地下構造物を構成する天井スラブと側壁の一部の間の切梁とから実質的に2段の切梁が土留め壁間に設置されることになる。 According to the construction method of the present embodiment, the two-stage beam is substantially installed between the retaining walls from the ceiling slab constituting the underground structure and the beam between a part of the side walls. Become.
ここで、導入されるプレロードの設定に際しては、天井スラブに予め歪計を配しておき(たとえばスラブ鉄筋に歪みゲージを設置しておく等)、歪計による計測データを参照してこのプレロードを設定するのが好ましい。このようにして導入プレロードを設定することで、掘削に伴う土留め壁周辺地盤の変位を効果的に抑制でき、これと同時に、既に構築されている地下構造物の構成部材である天井スラブや側壁の一部に生じ得る残留応力やクラックを最小限に制御することが可能となる。 Here, when setting the preload to be introduced, a strain gauge is arranged in advance on the ceiling slab (for example, a strain gauge is installed on the slab reinforcing bar), and this preload is referred to by referring to the measurement data from the strain gauge. It is preferable to set. By setting the introduction preload in this way, it is possible to effectively suppress the displacement of the ground around the retaining wall due to excavation, and at the same time, ceiling slabs and side walls that are components of the already constructed underground structure Residual stresses and cracks that can occur in a part of the surface can be controlled to a minimum.
なお、天井スラブよりも上方にある腹起しおよび切梁の撤去は、天井スラブが構築された後、もしくは別途の切梁にプレロードが導入された後におこなうことができる。 Note that the erection and the removal of the beam above the ceiling slab can be performed after the ceiling slab is constructed or after a preload is introduced into a separate beam.
そして、天井スラブよりも上方にある腹起しおよび切梁が撤去された後に、天井スラブの上方に掘削残土等の埋戻し施工をおこなうことにより、残土用ヤードの有効利用を図ることができる。さらには、この残土処理を早期に実施できることで、工期の短縮を図ることにも繋がる。 Then, after the uplift and the cut beam above the ceiling slab are removed, the backfilling of excavated residual soil and the like is performed above the ceiling slab, so that the remaining soil yard can be effectively used. Furthermore, this remaining soil treatment can be carried out at an early stage, which leads to shortening of the construction period.
以上の説明から理解できるように、本発明の地下構造物の構築方法によれば、地下構造物を構成する天井スラブを施工段階における切梁として適用すること、および、側壁を下方から上方に向かって施工することにより、仮設費用を節減でき、側壁の打ち継目において施工不良を生じ難くすることができる。さらには、地下構造物の構築過程において、構成部材を2度に分けて施工することもないことから、工期を長期化させることも工費を増大させることもない。 As can be understood from the above description, according to the construction method of an underground structure of the present invention, the ceiling slab constituting the underground structure is applied as a cut beam in the construction stage, and the side wall is directed upward from below. Thus, the temporary cost can be reduced and it is possible to make it difficult to cause a construction failure at the joint of the side walls. Furthermore, in the construction process of the underground structure, the construction members are not divided into two parts, so that the construction period is not prolonged and the construction cost is not increased.
以下、図面を参照して本発明の地下構造物の構築方法を説明する。なお、図示する地下構造物は天井スラブ、床スラブおよび側壁から構成されたものであるが、本発明の構築方法にて構築される地下構造物が図示例に限定されるものでないことは勿論のことであり、天井スラブと床スラブ(最下階の床スラブ)の間に複数階の床スラブを具備するものや、さらに各階に壁や柱を具備するものなど、多様な構造形態の地下構造物がその構築対象である。また、地下構造物のうち、最初に天井スラブのみを構築してこれで土留め壁を支保させ、側壁のすべてを床スラブ施工後に構築する方法であってもよい。 Hereinafter, the construction method of the underground structure of the present invention will be described with reference to the drawings. Although the illustrated underground structure is composed of a ceiling slab, a floor slab, and a side wall, the underground structure constructed by the construction method of the present invention is not limited to the illustrated example. Underground structures with various structural forms, such as those with multiple floor slabs between the ceiling slab and floor slab (bottom floor slab) and those with walls and pillars on each floor Things are the object of construction. Moreover, the method of constructing | assembling only the ceiling slab first in this underground structure and supporting a retaining wall by this, and constructing | assembling all the side walls after floor slab construction may be sufficient.
図1〜図10は順に、本発明の地下構造物の構築方法の第1の工程〜第4の工程を説明した図であり、より具体的には、図1は第1の工程を、図2は第2の工程を、図3,4は第3の工程を、図5〜10は第4の工程をそれぞれ説明した図である。 FIGS. 1-10 is the figure explaining the 1st process-the 4th process of the construction method of the underground structure of this invention in order, More specifically, FIG. 2 illustrates the second step, FIGS. 3 and 4 illustrate the third step, and FIGS. 5 to 10 illustrate the fourth step.
本発明の構築方法では、まず、図1で示すように、施工ヤードにおいて原地盤G内にたとえば平面視矩形の土留め壁1を専用の掘削機M1を使用して施工する。ここで、土留め壁1の形態は、土質性状や地下水位、地下構造物の床付け深度や工費、工期などによって適宜選定されるものであるが、地中連続壁や柱列式連続壁、鋼矢板や親杭横矢板、鋼管矢板などのいずれであってもよい。なお、図示例は、地下連続壁を適用し、原地盤Gの下層の支持地盤G1に土留め壁1を根入れしている。
In the construction method of the present invention, as shown in FIG. 1, first, a
平面視矩形の土留め壁1において、図1ではそのうちの一組の対向する位置に配設された土留め壁1,1を示しており、その間には、後施工される切梁を土留め壁1,1間の途中位置で支持したり、仮設用の重機通路を支持するための中間杭2が複数設置されている。
In the
土留め壁1,1を原地盤G内で対向する位置に施工したら、図2で示すように、その根入れ領域に地盤改良体3を造成用重機M2を使用して施工し、地下水の回り込みや盤膨れ等を抑制したり、土留め壁の受働土圧を高める等の措置を講じる。さらに、平面視矩形状の土留め壁1で包囲された地盤G内の地下水を揚水し(X1方向)、バックホーM3を使用して地盤Gの掘削を進める。
When the
地表から深度1〜2m程度掘削が進行した段階で、1段目の支保工である腹起し4A,4Aを対向する土留め壁1,1の双方に設置し、この対向する腹起し4A,4A間に切梁5Aを中間杭2を介して掛け渡す。
At the stage where excavation has progressed about 1 to 2 m in depth from the ground surface, the
1段目の切梁5Aの施工が完了したら、図3で示すようにバケット式の掘削機M4やバックホーM3などを使用してさらに地盤の掘削を進め、所定深度までの掘削が完了した段階で、たとえば2段目の切梁5B、3段目の切梁5Cを掘削地盤面に吊り降ろしておく。
When the construction of the
そして、既に設置済みの1段目の切梁5Aの下方位置に地下構造物の天井スラブ11とこれと連続するようにして側壁の一部12’を施工し、この天井スラブ11および側壁の一部12’で土留め壁1を支保させる。
Then, the
ここで、土留め壁1には予め不図示のジベルを内側に張り出させておき、このジベルを巻き込むようにして天井スラブ11や側壁の一部12’を施工することで、これらの地下構造物構成部材と土留め壁1との強固な接続構造を形成することができる。この強固な接続構造により、天井スラブ11等と土留め壁1の間の相対変位が抑止され、もって土留め壁1の変形抑制効果を高めることができるとともに、これに起因する土留め壁周辺の地盤の変形抑制効果を高めることもできる。
Here, the
次に、図4で示すように、対向する側壁の一部12’、12’の内側に腹起し4B,4Bを設置し、腹起し4B,4B間に既に吊り降ろされている切梁5Bを設置し、この切梁5Bに所望のプレロードを導入する。
Next, as shown in FIG. 4, the raised
このプレロードの導入に際しては、天井スラブ11を構成するスラブ筋等に予め不図示の歪みゲージを設置しておき、歪みゲージによる計測データを現場管理者が参照してこのプレロード値を設定するのがよい。このようにして導入プレロードを設定することで、掘削に伴う土留め壁周辺地盤の変位を効果的に抑制しながら、これと同時に、既に構築されている天井スラブ11や側壁の一部12’に生じ得る残留応力やクラックを最小限に制御することができる。
When this preload is introduced, a strain gauge (not shown) is installed in advance on the slab muscle constituting the
図4で示す状態において、対向する土留め壁1,1を支保する天井スラブ11は実質的に高剛性の切梁と見なすことができ、1段目の切梁5Aと、天井スラブ11(実質的に2段目の切梁)と、側壁の一部12’、12’間に掛け渡された切梁5B(実質的に3段目の切梁)と、の3段の切梁で土留め壁1,1が支保されることとなる。このことより、この掘削段階で3段の切梁設置が余儀なくされていた従来の逆巻き工法に比して、1段分の切梁および腹起しの設置が不要となり、仮設費用の大幅な節減と工費の短縮を図ることができる。
In the state shown in FIG. 4, the
実質的に3段の切梁で土留め壁1,1を支保したら、図5で示すように、まず、土留め壁の支保として不要となった1段目の切梁5A,腹起し4Aを撤去し、さらに地盤の掘削を進め、既に吊り降ろされている腹起し4Cを双方の土留め壁1,1に設置し、この腹起し4C,4C間に切梁5Cを掛け渡す。
If the
なお、1段目の切梁5A,腹起し4Aの撤去のタイミングは、図示例以外にも、図4で示す天井スラブ11にて土留め壁1,1を支保した後にこれらの撤去をおこなうこともでき、撤去のタイミングで決定される土留め壁1や天井スラブ11等の内部応力や、作業効率性等によって1段目の支保工の撤去のタイミングが決定される。
In addition to the illustrated example, the
土留め壁1,1間に切梁5Cを掛け渡したら、さらに地盤の掘削を進め、図6で示すように、床付け面を形成し、この床付け面上に均しコンクリートスラブ6を施工する。
When the
この均しコンクリートスラブ6内には鉄筋や網筋等が配設され、これを土圧耐荷部材と見なすことができる。すなわち、土留め壁1,1間に施工された均しコンクリートスラブ6が切梁と同様の土留め壁支保作用を奏するものである。
In the leveled
図7で示すように土留め壁1,1間に均しコンクリートスラブ6が施工されたら、これで土留め壁1,1の下端を支保させ、側壁の一部12’、12’間に掛け渡された切梁5Bおよび腹起し4Bと、その下方の切梁5Cおよび腹起し4Cを撤去する。
When the leveled
これらの支保工を撤去することにより、以後の地下構造物の構築施工に際して広範な作業スペースが確保され、効率のよい地下構造物の構築が保証される。 By removing these support works, a wide work space is secured in the subsequent construction of the underground structure, and an efficient construction of the underground structure is guaranteed.
次に、図8で示すように、施工ヤード内で残置されていた掘削残土を天井スラブ11上に埋戻し(埋戻し土7)、均しコンクリートスラブ6上に床スラブ13を施工する。
Next, as shown in FIG. 8, the excavated residual soil left in the construction yard is backfilled on the ceiling slab 11 (backfill soil 7), and the
なお、天井スラブ11上への掘削残土の埋戻しのタイミングは図示例に限定されるものではなく、最早は、図5で示す1段目の支保工を撤去した後のタイミングとなり得る。
In addition, the timing of the backfilling of the excavation residual soil on the
床スラブ13の施工が完了したら、図9で示すように側壁の残りを下方から上方に向かって施工し、既に施工済みの側壁の一部12’と一体化させることで側壁12の施工が完了し、少なくとも天井スラブ11、床スラブ13および側壁12からなる地下構造物10が構築される。
When the construction of the
なお、中間杭2は、天井スラブ11や床スラブ13の施工に際してこれらに設けられた不図示の開口内を通って地下構造物の上下に亘って残置されていることから、図10で示すように、地下構造物10と干渉する箇所を撤去し(未干渉箇所2’はそのまま残置)、不図示の開口を間詰め処理することにより、地下構造物の構築施工が完了する。
The
図示する本発明の地下構造物の構築方法によれば、従来の逆巻き工法に改良を加えて天井スラブに土留め壁を支保させ、さらにこれと一体に側壁の一部を施工してこの内部に切梁を設置するとともに所望のプレロードを導入したことにより、支保工の段数を低減することができ、さらには、土留め壁の変形やその周辺の地盤変形をより効果的に抑制することができる。 According to the construction method of the underground structure of the present invention shown in the figure, the conventional reverse winding method is improved to support the earth retaining wall on the ceiling slab, and further, a part of the side wall is constructed integrally with the ceiling retaining wall. By installing the desired beam and installing the desired preload, it is possible to reduce the number of steps of the support work, and more effectively suppress the deformation of the retaining wall and the surrounding ground deformation. .
また、床スラブを施工した後に側壁を下方から上方に向かって順巻き施工のごとく施工することから、側壁の打ち継目に施工不良を生じ難くすることができる。 Moreover, since a side wall is constructed like a forward winding construction from the lower side to the upper side after the floor slab is constructed, it is possible to make it difficult to cause a construction failure at the joint of the side walls.
さらに、高剛性の天井スラブにて土留め壁を支保することから、早期にこの天井スラブよりも上方の1段目の支保工を撤去することができ、掘削残土を早期にこの天井スラブ上に埋戻すことで残土ヤードを別目的に有効利用することも可能となる。 Furthermore, since the earth retaining wall is supported by a high-stiffness ceiling slab, the first stage of the support work above the ceiling slab can be removed at an early stage, and the excavated residual soil can be quickly put on the ceiling slab. By backfilling, the remaining soil yard can be effectively used for another purpose.
なお、逆巻き工法を適用した際に享受できる固有の効果、すなわち、支保工が配筋作業や防水施工の妨げにならないことで高効率な施工をおこなえること、したがって、地下構造物の外面防水の高い品質を保証できること、などの効果を本発明の構築方法が有していることは言うまでもないことである。 In addition, the unique effect that can be enjoyed when the reverse winding method is applied, that is, the support work can be performed efficiently because it does not interfere with the bar arrangement work and waterproof construction, and therefore the outer surface of the underground structure is highly waterproof. It goes without saying that the construction method of the present invention has effects such as quality assurance.
以上、本発明の実施の形態を図面を用いて詳述してきたが、具体的な構成はこの実施形態に限定されるものではなく、本発明の要旨を逸脱しない範囲における設計変更等があっても、それらは本発明に含まれるものである。 The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration is not limited to this embodiment, and there are design changes and the like without departing from the gist of the present invention. They are also included in the present invention.
1…土留め壁、2…中間杭、2’…切断後の中間杭、3…地盤改良体、4A,4B,4C…腹起し、5A,5B,5C…切梁、6…均しコンクリートスラブ、7…埋戻し土、10…地下構造物、11…天井スラブ、12…側壁、12’…側壁の一部、13…床スラブ、G…原地盤
DESCRIPTION OF
Claims (6)
対向する土留め壁で囲まれた地盤に対して地表から掘削を進め、天井スラブが構築される位置よりも高い位置で対向する土留め壁の双方に腹起しを設置するとともに対向する腹起しの間に切梁を設置する第2の工程、
さらに掘削を進めて、地下構造物のうちの少なくとも天井スラブを構築し、この天井スラブに土留め壁を支保させる第3の工程、
さらに掘削を進め、掘削の進行にともなって天井スラブの下方にさらに別途の腹起しおよび切梁を設置して床付け面を施工し、床付け面上に均しコンクリートスラブを構築し、天井スラブと均しコンクリートスラブの間の前記別途の腹起しおよび切梁を撤去し、均しコンクリートスラブを土圧耐荷部材として天井スラブと均しコンクリートスラブで土留め壁を支保させ、均しコンクリートスラブ上に床スラブを構築し、側壁を上方に向かって構築して、少なくとも天井スラブと床スラブと側壁からなる地下構造物を構築する第4の工程、からなる地下構造物の構築方法。 A first step of constructing a retaining wall at an opposing position in the ground;
Proceed with excavation from the ground surface against the ground surrounded by the opposite retaining wall, and install a bulge on both opposing retaining walls at a position higher than the position where the ceiling slab is constructed and face the opposite flank A second step of installing a cutting beam between
A third step of further excavation to construct at least a ceiling slab of the underground structure and to support a retaining wall on the ceiling slab;
Further advance the drilling, with the progress of the excavation by installing a further separate wale and Setsuhari below the ceiling slab construction the floor with surface, to build a concrete slab leveling on the floor with surface, ceiling The above-mentioned separate uplift and slab between the slab and the leveled concrete slab are removed , the leveled concrete slab is used as an earth pressure load bearing member, and the retaining wall is supported by the leveled concrete slab and the leveled concrete slab. A method for constructing an underground structure comprising a fourth step of constructing a floor slab on a slab, constructing a side wall upward, and constructing an underground structure composed of at least a ceiling slab, a floor slab and a sidewall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010119239A JP5465086B2 (en) | 2010-05-25 | 2010-05-25 | Construction method of underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010119239A JP5465086B2 (en) | 2010-05-25 | 2010-05-25 | Construction method of underground structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2011246910A JP2011246910A (en) | 2011-12-08 |
JP5465086B2 true JP5465086B2 (en) | 2014-04-09 |
Family
ID=45412511
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2010119239A Active JP5465086B2 (en) | 2010-05-25 | 2010-05-25 | Construction method of underground structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5465086B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102518458B (en) * | 2011-12-22 | 2014-04-16 | 中铁工程设计咨询集团有限公司 | Construction method of top beam part of underground bus stop |
CN103866789A (en) * | 2014-03-19 | 2014-06-18 | 重庆大学 | Control method for cracks generated during construction period of basement baseboard |
CN106948350B (en) * | 2017-05-10 | 2018-10-16 | 中铁隧道集团四处有限公司 | The rapid constructing method of deep basal pit accessory structure |
JP7284800B1 (en) | 2021-11-18 | 2023-05-31 | 西武建設株式会社 | Construction method of underpass under railroad tracks |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3390081B2 (en) * | 1994-03-07 | 2003-03-24 | 株式会社フジタ | How to build an underground parking |
JP3248458B2 (en) * | 1997-07-29 | 2002-01-21 | 鹿島建設株式会社 | Shoring construction underground construction method |
JP4083334B2 (en) * | 1999-01-27 | 2008-04-30 | 株式会社奥村組 | Underground structure having arch roof and method for constructing the same |
JP2003171928A (en) * | 2001-12-04 | 2003-06-20 | Kawasaki Steel Corp | Compound underground wall body and its construction method |
-
2010
- 2010-05-25 JP JP2010119239A patent/JP5465086B2/en active Active
Also Published As
Publication number | Publication date |
---|---|
JP2011246910A (en) | 2011-12-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR20090002344A (en) | Land-side protection wall that use ground structure | |
KR100967497B1 (en) | Method for constructing an underground structure | |
KR20060092552A (en) | The non-strut down framework construction method of having used cast in place concrete pile | |
JP5465086B2 (en) | Construction method of underground structure | |
JP4914062B2 (en) | Two-tiered retaining wall and its construction method | |
JP5698405B1 (en) | Ground improvement solid foundation method | |
JP5038170B2 (en) | How to rebuild a structure | |
KR101262357B1 (en) | Inclined Earth Retaining Structure Method | |
KR101296857B1 (en) | Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same | |
JP5681039B2 (en) | Mountain fastening method | |
JP4228308B2 (en) | Reinforcement method for existing floors and seismic isolation method for existing buildings | |
KR101310677B1 (en) | Top down method using precast composite retaining wall and raker in slope | |
KR100967496B1 (en) | Device for constructing an underground structure | |
JP5739051B1 (en) | Liquefaction countermeasure structure for ground improvement solid foundation and correction method for occurrence of uneven settlement due to liquefaction | |
AU2020100004A4 (en) | A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method | |
KR100615149B1 (en) | A method of construction top-down for the ground fabric construction | |
JP2018091107A (en) | Method for constructing underground structure | |
JP6052541B2 (en) | Seismic isolation method for existing buildings | |
JP6710999B2 (en) | Temporary receiving method for existing structures | |
CN105735324B (en) | The platform disassembly method of steel sheet pile supporting | |
JP4749858B2 (en) | Method for enhancing bearing capacity in extension or reconstruction of superstructures of existing buildings | |
JP4529631B2 (en) | Underground structure and construction method of underground structure | |
JP2004176434A (en) | Method for constructing structure and underground skeleton | |
JP2019157508A (en) | Under-ground piled column and seismic base-isolated buildings | |
JP3879085B2 (en) | Uneven settlement settlement method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20120919 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20130722 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20130730 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20130913 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20140107 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20140121 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5465086 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |