JP6961898B2 - プレハブスラブ式防振軌道構造システム及びその施工方法 - Google Patents
プレハブスラブ式防振軌道構造システム及びその施工方法 Download PDFInfo
- Publication number
- JP6961898B2 JP6961898B2 JP2018535883A JP2018535883A JP6961898B2 JP 6961898 B2 JP6961898 B2 JP 6961898B2 JP 2018535883 A JP2018535883 A JP 2018535883A JP 2018535883 A JP2018535883 A JP 2018535883A JP 6961898 B2 JP6961898 B2 JP 6961898B2
- Authority
- JP
- Japan
- Prior art keywords
- slab
- track
- vibration
- track slab
- cushion layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000010276 construction Methods 0.000 title claims description 83
- 238000000034 method Methods 0.000 claims description 65
- 239000004567 concrete Substances 0.000 claims description 48
- 238000011049 filling Methods 0.000 claims description 37
- 238000002347 injection Methods 0.000 claims description 23
- 239000007924 injection Substances 0.000 claims description 23
- 239000000463 material Substances 0.000 claims description 14
- 238000007789 sealing Methods 0.000 claims description 14
- 239000002131 composite material Substances 0.000 claims description 7
- 230000003014 reinforcing effect Effects 0.000 claims description 5
- 238000004519 manufacturing process Methods 0.000 claims description 4
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims description 3
- 239000012530 fluid Substances 0.000 claims 1
- 230000008569 process Effects 0.000 description 37
- 230000032258 transport Effects 0.000 description 22
- 238000002955 isolation Methods 0.000 description 19
- 238000005259 measurement Methods 0.000 description 17
- 230000007246 mechanism Effects 0.000 description 17
- 238000005516 engineering process Methods 0.000 description 15
- 230000000694 effects Effects 0.000 description 9
- 230000006870 function Effects 0.000 description 9
- 238000012423 maintenance Methods 0.000 description 9
- 238000013461 design Methods 0.000 description 7
- 239000004570 mortar (masonry) Substances 0.000 description 7
- 229920001971 elastomer Polymers 0.000 description 6
- 239000011150 reinforced concrete Substances 0.000 description 6
- 238000001723 curing Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 5
- 230000001965 increasing effect Effects 0.000 description 5
- 238000009434 installation Methods 0.000 description 5
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 4
- 230000008901 benefit Effects 0.000 description 4
- 239000013013 elastic material Substances 0.000 description 4
- 230000007613 environmental effect Effects 0.000 description 4
- 239000004677 Nylon Substances 0.000 description 3
- 238000009415 formwork Methods 0.000 description 3
- 229920001778 nylon Polymers 0.000 description 3
- 230000008439 repair process Effects 0.000 description 3
- 230000008093 supporting effect Effects 0.000 description 3
- 238000012546 transfer Methods 0.000 description 3
- 230000007723 transport mechanism Effects 0.000 description 3
- 230000009471 action Effects 0.000 description 2
- 230000003139 buffering effect Effects 0.000 description 2
- 238000005336 cracking Methods 0.000 description 2
- 239000000428 dust Substances 0.000 description 2
- 230000003028 elevating effect Effects 0.000 description 2
- 238000007667 floating Methods 0.000 description 2
- 229910052742 iron Inorganic materials 0.000 description 2
- 229920002635 polyurethane Polymers 0.000 description 2
- 239000004814 polyurethane Substances 0.000 description 2
- 238000011160 research Methods 0.000 description 2
- 230000003068 static effect Effects 0.000 description 2
- 239000000853 adhesive Substances 0.000 description 1
- 230000001070 adhesive effect Effects 0.000 description 1
- 239000010426 asphalt Substances 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 239000000969 carrier Substances 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 239000011248 coating agent Substances 0.000 description 1
- 238000000576 coating method Methods 0.000 description 1
- 238000010835 comparative analysis Methods 0.000 description 1
- 238000013329 compounding Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000008034 disappearance Effects 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- -1 foreign matter Substances 0.000 description 1
- 239000003673 groundwater Substances 0.000 description 1
- 230000001771 impaired effect Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 230000013011 mating Effects 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 238000002156 mixing Methods 0.000 description 1
- 230000003020 moisturizing effect Effects 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
- 230000000149 penetrating effect Effects 0.000 description 1
- 239000004588 polyurethane sealant Substances 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- 239000003566 sealing material Substances 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 239000000243 solution Substances 0.000 description 1
- 238000005507 spraying Methods 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
- 238000012360 testing method Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/002—Ballastless track, e.g. concrete slab trackway, or with asphalt layers
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B1/00—Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
- E01B1/002—Ballastless track, e.g. concrete slab trackway, or with asphalt layers
- E01B1/004—Ballastless track, e.g. concrete slab trackway, or with asphalt layers with prefabricated elements embedded in fresh concrete or asphalt
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B29/00—Laying, rebuilding, or taking-up tracks; Tools or machines therefor
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B29/00—Laying, rebuilding, or taking-up tracks; Tools or machines therefor
- E01B29/005—Making of concrete parts of the track in situ
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/01—Elastic layers other than rail-pads, e.g. sleeper-shoes, bituconcrete
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/06—Height or lateral adjustment means or positioning means for slabs, sleepers or rails
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/10—Making longitudinal or transverse sleepers or slabs in situ or embedding them
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Machines For Laying And Maintaining Railways (AREA)
- Railway Tracks (AREA)
- Vibration Prevention Devices (AREA)
- Foundations (AREA)
Description
専用吊り上げ車に微調整機構と高精度制御システムが設計される。図8に示すように、主にフレーム構造20及び前後走行機構21を備え、前記フレーム構造20に調整シリンダ22が設けられ、前記調整シリンダ22は2つの縦方向調整シリンダ及び2つの横方向調整シリンダを含み、それぞれ軌道スラブに接続された調整レバーによって軌道スラブを調整し、測定装置によってデータを静的トロリー制御システムにフィードバックし、スラブ調整車は軌道スラブの標高、中心線特定及び高さ超過の調整を自動的に行うことで、軌道スラブの位置が微調整要件の精度を満たし、前記走行機構21は精密制御システム23を用いて、トータルステーションの測定を油圧装置25にフィードバックし、トータルステーションによって位置決めシステム24を測定し、それにより吊り上げ車の高精度位置決めを実現し、軌道スラブの微調整を実現する。微調整完了後、軌道スラブに軌道スラブサポート13を取り付け、軌道スラブの位置を固定することで、後続で下部充填層1を注入する時に軌道スラブの位置精度が常に誤差要件を満たすことを確保する。
明らかなように、上記説明と記載は例示的であり、本発明の開示内容、応用又は使用を限定するものではない。図面に示される実施例を参照して説明したが、本発明は図面に示された例及び実施例に説明された本発明を実施する従来の特定の最適実施例に限定されるものではなく、本発明の範囲は上記明細書及び添付特許請求の範囲に属するすべての実施例を含む。
Claims (8)
- 充填層、弾性クッション層及び軌道スラブを下から順に備え、並行する2本のレールがそれぞれ複数の締結具によって該軌道スラブに固定される、プレハブスラブ式防振軌道構造システムであって、
前記軌道スラブは、上面の幅方向両端から下方に延在する側面と、幅方向両側の前記側面の下端から幅方向中央部側へトンネル断面底部両側の湾曲に沿うよう斜め下方に延在する斜面と、前記幅方向両側の前記斜面の下端を結ぶよう水平に延在する下面と、を有し、
前記弾性クッション層は、前記軌道スラブの前記側面、前記斜面及び前記下面をすべて覆うよう配置され、
前記軌道スラブ及び前記弾性クッション層を、前記軌道スラブの前記幅方向中央部で前記上面から厚さ方向にトンネル断面底部中央部に向かって、前記軌道スラブにおける前記下面と前記弾性クッション層において前記下面を覆う部分とを含む最深部まで貫通して、前記充填層で終端するよう配置された、コンクリート材料を注入するための孔と、
前記孔内に取り付けられる弾性の密封スリーブであって、前記孔内への前記コンクリート材料の注入時に前記コンクリート材料が前記軌道スラブと前記弾性クッション層との間に入ることを回避するための密封スリーブと、
前記密封スリーブ内に配置される杭と、
を有する、プレハブスラブ式防振軌道構造システム。 - 前記弾性クッション層は面状支持又は点状支持又は帯状支持であり、面状支持において、前記軌道スラブの前記下面が前記弾性クッション層の上面に全面にわたって前記軌道スラブの前記上面が平らになるように敷設されることを特徴とする請求項1に記載の防振軌道構造システム。
- 前記軌道スラブに、仮設位置決め用の支持脚を取り付ける保留取付構造が設けられ、前記支持脚がスラブ内又はスラブ側面に位置する取付スリーブ装置と前記支持脚に付いたねじ山によってスリーブ内のねじ山と噛合して固定及び調整を実現することを特徴とする請求項1に記載の防振軌道構造システム。
- 前記軌道スラブにスラブ敷設位置決め用のセンタリングマークを有することを特徴とする請求項1に記載の防振軌道構造システム。
- 前記軌道スラブに埋め込み吊り上げ用の3−4個の専用吊り上げ部材を有することを特徴とする請求項1に記載の防振軌道構造システム。
- 前記軌道スラブの端部に縦方向接続用の埋め込み部材が設けられることを特徴とする請求項1に記載の防振軌道構造システム。
- スラブ内鉄筋の間隔は所定係数に応じて設定されることで、鉄筋網の自動生産に有利であることを特徴とする請求項1に記載の防振軌道構造システム。
- 請求項1−7のいずれか一項に記載のプレハブスラブ式防振軌道構造システムを施工するための方法であって、
前記軌道スラブの搬送及び敷設ステップ1と、
トンネルの基礎に溜まった水を排出し、且つ前記弾性クッション層と前記軌道スラブの複合状況及び前記弾性クッション層の周囲の密封状況を検査した後、コンクリート施工を行い、軌道スラブ下部コンクリートは流動性に優れた前記コンクリート材料を用いるコンクリート注入ステップ2と、
コンクリート養生ステップ3と、
締結具敷設ステップ4と、
レール敷設ステップ5と、を含み、
前記コンクリート注入ステップ2は、
前記軌道スラブ及び前記弾性クッション層を前記軌道スラブの前記幅方向中央部で前記上面から厚さ方向にトンネル断面底部中央部に向かって、前記軌道スラブにおける前記下面と前記弾性クッション層において前記下面を覆う部分とを含む最深部まで貫通して、前記充填層で終端する前記孔に、弾性の前記密封スリーブを取り付けるステップと、
前記コンクリート材料が前記軌道スラブと前記弾性クッション層との間に入ることを前記密封スリーブによって回避しつつ前記密封スリーブ内で前記孔を介して前記コンクリート材料を充填するステップと、
前記コンクリート材料の充填後、前記密封スリーブ内に前記杭を配置するステップと、
を含む、方法。
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610013534.7A CN105625104B (zh) | 2016-01-11 | 2016-01-11 | 一种预制板式减振轨道结构系统及配套施工方法 |
CN201610013534.7 | 2016-01-11 | ||
PCT/CN2016/078779 WO2017121044A1 (zh) | 2016-01-11 | 2016-04-08 | 一种预制板式减振轨道结构系统及配套施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2019501320A JP2019501320A (ja) | 2019-01-17 |
JP6961898B2 true JP6961898B2 (ja) | 2021-11-05 |
Family
ID=56040419
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2018535883A Active JP6961898B2 (ja) | 2016-01-11 | 2016-04-08 | プレハブスラブ式防振軌道構造システム及びその施工方法 |
Country Status (5)
Country | Link |
---|---|
EP (1) | EP3404142B1 (ja) |
JP (1) | JP6961898B2 (ja) |
CN (1) | CN105625104B (ja) |
ES (1) | ES2977385T3 (ja) |
WO (1) | WO2017121044A1 (ja) |
Families Citing this family (41)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106223137B (zh) * | 2016-08-29 | 2019-06-28 | 株洲长远铁路建机有限公司 | 一种隧道道床施工作业的混凝土精密整平作业车 |
CN106436495A (zh) * | 2016-11-21 | 2017-02-22 | 中铁第勘察设计院集团有限公司 | 宽枕板式粘结型有砟轨道 |
CN107653755B (zh) * | 2017-09-15 | 2019-05-07 | 中铁十七局集团有限公司铺架分公司 | 地铁区间分离式隧道内整体道床浇筑逆作式施工方法 |
CN107401091B (zh) * | 2017-09-19 | 2023-08-18 | 北京市轨道交通建设管理有限公司 | 一种装配式轨道结构及其施工方法 |
CN209323264U (zh) * | 2017-09-25 | 2019-08-30 | 洛阳双瑞橡塑科技有限公司 | 一种道床板弹性限位装置 |
CN108004854A (zh) * | 2017-11-30 | 2018-05-08 | 上海材料研究所 | 内嵌耗能装置的分层轨道板结构 |
CN107858869A (zh) * | 2017-12-14 | 2018-03-30 | 浙江天铁实业股份有限公司 | 橡胶与金属复合的道床板以及包含该道床板的组件 |
CN108005678A (zh) * | 2017-12-27 | 2018-05-08 | 中铁二院工程集团有限责任公司 | 具有低位泄水动能的π形隧底衬砌结构 |
CN108131162B (zh) * | 2018-02-11 | 2023-06-13 | 中铁二院工程集团有限责任公司 | 一种隧道排水装置及隧道整体道床 |
CN108678785B (zh) * | 2018-05-04 | 2023-06-13 | 中铁第五勘察设计院集团有限公司 | 一种用于铁路隧道预制仰拱侧箱涵吊装的箱涵吊机 |
CN108560330B (zh) * | 2018-06-26 | 2024-05-17 | 青岛科而泰环境控制技术有限公司 | 二次浇筑式可升级通用道床及其施工方法 |
CN109112901A (zh) * | 2018-09-14 | 2019-01-01 | 同济大学 | 一种预制橡胶混凝土减振轨道板 |
CN109881542A (zh) * | 2019-04-16 | 2019-06-14 | 郑州铁路职业技术学院 | 一种嵌入式交通轨道组件 |
CN110424194B (zh) * | 2019-08-26 | 2024-07-16 | 中铁二院工程集团有限责任公司 | 一种桥上隔振垫预制道床结构及其施工方法 |
CN110468628A (zh) * | 2019-08-28 | 2019-11-19 | 吴永芳 | 一种用于装配式轨道的限位结构及装配式轨道 |
CN110616634A (zh) * | 2019-10-24 | 2019-12-27 | 成都天府轨谷科技有限公司 | 一种内嵌拼装化连续支承轨板梁结构及生产方法 |
CN110909427A (zh) * | 2019-11-18 | 2020-03-24 | 广东博智林机器人有限公司 | 减震垫的结构参数的确定方法、装置以及自动导引运输车 |
CN110904739B (zh) * | 2019-12-30 | 2024-08-06 | 江西科技学院 | 一种自密实混凝土紧固装置及其施工方法 |
CN111576104B (zh) * | 2020-04-09 | 2021-07-27 | 重庆工程职业技术学院 | 自动调整轨道板安装位置的方法 |
CN111441198A (zh) * | 2020-04-30 | 2020-07-24 | 中铁四局集团第五工程有限公司 | 一种用于crtsⅲ型轨道板施工的精调机器人 |
CN111851184A (zh) * | 2020-07-01 | 2020-10-30 | 上海市政工程设计研究总院(集团)有限公司 | 一种盾构隧道内预制基座及其与管片的连接结构 |
CN111914356B (zh) * | 2020-07-30 | 2023-08-08 | 中车唐山机车车辆有限公司 | 减振支撑装置、轨道车辆及列车地板区域隔振设计方法 |
CN111877054A (zh) * | 2020-08-11 | 2020-11-03 | 北京城建设计发展集团股份有限公司 | 便于快速施工的预制板式轨道结构及其施工方法 |
RU2755804C1 (ru) * | 2020-11-10 | 2021-09-21 | Акционерное общество "РЖДстрой" | Безбалластный железнодорожный путь для грузопассажирского высокоскоростного движения и способ его сооружения |
CN112444235B (zh) * | 2020-11-17 | 2022-08-02 | 中铁十二局集团电气化工程有限公司 | 一种地铁隧道区间疏散平台无轨测量方法 |
CN112580210A (zh) * | 2020-12-22 | 2021-03-30 | 中国铁路设计集团有限公司 | 一种一维周期垫层减振道床隔振频段调控设计方法 |
KR20230153423A (ko) * | 2021-03-05 | 2023-11-06 | 오버레일 에스.알.엘. | 지하, 철도, 및 전차 라인용 트랙을 배치하기 위한 방법 및 시스템(process and system for laying tracks for underground, railway and tramway lines) |
CN113026435B (zh) * | 2021-03-12 | 2023-02-24 | 中铁二十三局集团轨道交通工程有限公司 | 一种地铁盾构区间板式无砟轨道施工方法 |
CN113481764A (zh) * | 2021-08-04 | 2021-10-08 | 洛阳双瑞橡塑科技有限公司 | 一种可更换减振垫的浮置板道床及减振垫更换方法 |
CN114542114A (zh) * | 2021-12-22 | 2022-05-27 | 上海市基础工程集团有限公司 | 盾构隧道内二结构的高精度快速拼装方法 |
CN114369976B (zh) * | 2021-12-23 | 2023-08-22 | 中国华冶科工集团有限公司 | 间隔支承的地面轨道铺设方法 |
CN114519286B (zh) * | 2022-02-17 | 2023-04-25 | 中铁二院工程集团有限责任公司 | 轨道交通车致振动的二次结构噪声快速计算方法 |
CN114481710A (zh) * | 2022-02-22 | 2022-05-13 | 河北中烁轨道科技有限公司 | 一种便于拆卸的复合轨道板及其生产工艺 |
CN114575878B (zh) * | 2022-03-10 | 2024-08-16 | 山东金岭矿业股份有限公司 | 矿山巷道爆破施工时的减震缓冲方法及装置 |
CN114525705A (zh) * | 2022-03-21 | 2022-05-24 | 成都天府轨谷科技有限公司 | 一种轮齿轨板梁钢轨埋入式结构与施工方法 |
CN114941264B (zh) * | 2022-05-31 | 2024-09-24 | 中国二十二冶集团有限公司 | 轨道与基础预埋板的安装方法 |
CN115366753A (zh) * | 2022-09-14 | 2022-11-22 | 中铁高铁电气装备股份有限公司 | 一种接触轨高差可调式连接接头 |
CN115595829A (zh) * | 2022-10-24 | 2023-01-13 | 西南交通大学(Cn) | 钢弹簧浮置板预制板轨道施工方法 |
CN115627665B (zh) * | 2022-12-06 | 2023-03-21 | 中国铁路设计集团有限公司 | 一种快速支撑的整体装配式预制轨道结构施工方法 |
CN116971223B (zh) * | 2023-09-22 | 2023-12-08 | 中铁三局集团有限公司 | 一种轨道板精调设备减震结构以及减震方法 |
CN118127863A (zh) * | 2024-04-08 | 2024-06-04 | 中铁一局集团有限公司 | 一种高铁钢轨铺设垫板自动放置装置及施工方法 |
Family Cites Families (29)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5237242B2 (ja) * | 1972-09-14 | 1977-09-21 | ||
JPS5326361B2 (ja) * | 1973-01-23 | 1978-08-02 | ||
JPS5322724B2 (ja) * | 1973-09-20 | 1978-07-11 | ||
JPS547085B2 (ja) * | 1974-02-04 | 1979-04-04 | ||
JPS5838002Y2 (ja) * | 1978-06-09 | 1983-08-27 | 日本国有鉄道 | 鉄道軌道における吸音板取付装置 |
US4303199A (en) * | 1978-08-22 | 1981-12-01 | Eisses Jacobus A | Restored vibration isolation for railway tracks |
DE2901283A1 (de) * | 1979-01-13 | 1980-07-24 | Erich Radler | Schotterloser oberbau fuer schienengebundene fahrzeuge |
JPS60246901A (ja) * | 1984-05-18 | 1985-12-06 | 財団法人鉄道総合技術研究所 | 線路地盤の安定化工法 |
JPH1181201A (ja) * | 1997-09-05 | 1999-03-26 | Kumagai Gumi Co Ltd | 地下鉄軌道スラブのパネル |
DE10303177A1 (de) * | 2003-01-27 | 2004-07-29 | Max Bögl Bauunternehmung GmbH & Co. KG | Verfahren zum Einrichten eines Fertigteiles und Vorrichtung zur Aufnahme von Messprismen |
AT413552B (de) * | 2004-04-08 | 2006-03-15 | Porr Technobau Und Umwelt Ag | Schotterloser oberbau für den schienengebundenen verkehr |
DE102005054820A1 (de) * | 2005-11-15 | 2007-05-24 | Rail.One Gmbh | Feste Fahrbahn für Schienenfahrzeuge |
CN1844578A (zh) * | 2005-12-09 | 2006-10-11 | 中铁八局集团有限公司 | 减振型板式无碴轨道 |
JP2009046821A (ja) * | 2007-08-14 | 2009-03-05 | Oriental Shiraishi Corp | 鉄道用のコンクリート構造物およびその補強構造 |
DE102008016953A1 (de) * | 2008-04-01 | 2009-10-08 | Railone Gmbh | Feste Fahrbahn für Schienenfahrzeuge |
JP4888737B2 (ja) * | 2008-09-01 | 2012-02-29 | 清水建設株式会社 | 軌道下搬送機構 |
JP2010255363A (ja) * | 2009-04-28 | 2010-11-11 | Mitsubishi Heavy Ind Ltd | 磁気浮上システムの枕木締結構造 |
JP5415240B2 (ja) * | 2009-11-30 | 2014-02-12 | 鹿島道路株式会社 | 両面供用可能なプレキャストコンクリート舗装版とその設置方法 |
CN101748665B (zh) * | 2009-12-22 | 2011-07-27 | 中铁二局股份有限公司 | 无砟轨道板铺设方法 |
CN101798786B (zh) * | 2010-04-08 | 2012-05-30 | 中铁二院工程集团有限责任公司 | 板式无砟轨道减振构造 |
CN201908236U (zh) * | 2010-12-17 | 2011-07-27 | 中国铁道科学研究院铁道建筑研究所 | 减振型板式无砟轨道 |
CN102182120A (zh) * | 2011-03-31 | 2011-09-14 | 中铁第四勘察设计院集团有限公司 | 一种预制板式无砟轨道结构 |
CN202055116U (zh) * | 2011-03-31 | 2011-11-30 | 中铁第四勘察设计院集团有限公司 | 一种预制板式无砟轨道结构 |
CN102767123A (zh) * | 2012-08-13 | 2012-11-07 | 浙江天铁实业股份有限公司 | 一种板式轨道减振结构 |
CN103669114B (zh) * | 2012-09-06 | 2015-07-22 | 隔而固(青岛)振动控制有限公司 | 一种道床基底预制板及其应用 |
ES2526840B1 (es) * | 2013-04-18 | 2015-12-15 | Idvia 2020 Horizonte 2020, S.L. | Vía ferroviaria en placa bituminosa y procedimiento de ejecución de dicha vía |
CN103255686B (zh) * | 2013-05-13 | 2015-05-06 | 西南交通大学 | 一种无砟轨道防脱空弹性减振垫层 |
CN103741561B (zh) * | 2014-01-26 | 2015-11-25 | 北京九州一轨隔振技术有限公司 | 轨道道床及其施工方法、高分子隔振支座更换方法 |
CN204435133U (zh) * | 2015-01-20 | 2015-07-01 | 北京宝曼科技有限公司 | 在有水条件下具有优异减振效果的减振系统 |
-
2016
- 2016-01-11 CN CN201610013534.7A patent/CN105625104B/zh active Active
- 2016-04-08 JP JP2018535883A patent/JP6961898B2/ja active Active
- 2016-04-08 WO PCT/CN2016/078779 patent/WO2017121044A1/zh active Application Filing
- 2016-04-08 EP EP16884604.6A patent/EP3404142B1/en active Active
- 2016-04-08 ES ES16884604T patent/ES2977385T3/es active Active
Also Published As
Publication number | Publication date |
---|---|
ES2977385T3 (es) | 2024-08-22 |
CN105625104B (zh) | 2018-08-24 |
JP2019501320A (ja) | 2019-01-17 |
WO2017121044A1 (zh) | 2017-07-20 |
EP3404142A1 (en) | 2018-11-21 |
EP3404142A4 (en) | 2019-09-25 |
CN105625104A (zh) | 2016-06-01 |
EP3404142B1 (en) | 2024-01-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6961898B2 (ja) | プレハブスラブ式防振軌道構造システム及びその施工方法 | |
CN101701439B (zh) | 钢弹簧浮置板轨道钢筋笼轨排法施工工艺 | |
EP0170631B1 (en) | Components for railway lines on pre-fabricated reinforced concrete slabs without ballast | |
CN107401091B (zh) | 一种装配式轨道结构及其施工方法 | |
CN101215812B (zh) | 客运专线长枕埋入式大号无砟道岔施工方法 | |
CN105625188A (zh) | 基于BIM技术的客运专线48m节段梁施工方法 | |
CN105625105B (zh) | 预制式减振轨道板施工方法 | |
KR101158466B1 (ko) | 교체가 용이한 3차원 입체형상의 궤도블록 및 그 제조방법, 이 궤도블록을 이용한 콘크리트 궤도 부설방법 및 안내궤도식 고무차륜 경전철의 궤도 부설방법 | |
CN109853381B (zh) | 一种防治桥头跳车的过渡结构及其施工方法 | |
CN206245139U (zh) | 预制板道床 | |
CN110230261B (zh) | 一种双层同步梁上架梁的安装施工方法 | |
CN102619144A (zh) | 一种预制装配式钢弹簧浮置板轨道施工工艺 | |
CN102912693B (zh) | 浮置道床预制板及预制板拼装式浮置道床的施工方法 | |
CN103352401A (zh) | 嵌入式轨道 | |
CN107313313B (zh) | 预制聚氨酯固化道床的排架施工方法 | |
CN105350409B (zh) | 城市轨道交通长枕式钢弹簧浮置板道床道岔施工方法 | |
CN102797223A (zh) | 海塘区客运专线膺架法现浇道岔连续梁施工方法 | |
RU2755804C1 (ru) | Безбалластный железнодорожный путь для грузопассажирского высокоскоростного движения и способ его сооружения | |
WO2024041054A1 (zh) | 轨道交通内置式泵房地段用预制轨道结构及施工方法 | |
CN112726293A (zh) | 便于更换的橡胶弹簧浮置板结构及其施工工法 | |
CN111877054A (zh) | 便于快速施工的预制板式轨道结构及其施工方法 | |
CN215289502U (zh) | 便于更换的橡胶弹簧浮置板结构 | |
CN113863174B (zh) | 一种地面站台结构及其施工方法 | |
CN115162071B (zh) | 一种能降低磁阻的超导磁悬浮轨道结构 | |
CN103485247A (zh) | 预制式浮置板道床中浮置板的安装调平方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20180906 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20190116 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20191004 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20191015 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20200114 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20200616 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20200915 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20210126 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20210422 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20210914 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20210922 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6961898 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |