JP6740064B2 - Construction method of concrete frame - Google Patents
Construction method of concrete frame Download PDFInfo
- Publication number
- JP6740064B2 JP6740064B2 JP2016176998A JP2016176998A JP6740064B2 JP 6740064 B2 JP6740064 B2 JP 6740064B2 JP 2016176998 A JP2016176998 A JP 2016176998A JP 2016176998 A JP2016176998 A JP 2016176998A JP 6740064 B2 JP6740064 B2 JP 6740064B2
- Authority
- JP
- Japan
- Prior art keywords
- lot
- concrete
- constructing
- tubular member
- sheath
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Description
本発明は、逆巻き工法を用いてコンクリート躯体を構築する方法に関する。 The present invention relates to a method for constructing a concrete skeleton using a reverse winding method.
一般的には壁状又は柱状のコンクリート躯体は順巻き工法で下から上に向かって構築される。これは、支保工設置、型枠設置、コンクリート打設といったコンクリート躯体を構築するための部材及び材料を下から上に向かって積み上げていく作業のほうが合理的であるからである。 Generally, a wall-shaped or columnar concrete skeleton is constructed from the bottom to the top by a forward winding method. This is because it is more rational to stack members and materials for constructing a concrete skeleton, such as supporting work installation, formwork installation, and concrete placing, from bottom to top.
一方、例えば立坑や地下タンクなどの円筒形地下構造物の側壁(側壁コンクリート)の構築については、切梁などの支保工を不要とする山留が採用できることから、逆巻き工法で上から下に向かって構築するほうが有利な場合がある。この場合には、側壁コンクリートが支保工として機能し得る。逆巻き工法では、例えば鋼矢板を用いて又はSMW工法などの工法を用いて山留を構築した後に、山留によって囲まれた領域内の地盤を3〜5m程度掘り下げて、側壁コンクリートの打設を行う。この地盤の掘り下げと側壁コンクリートの打設とを繰り返すことで、所望の高さの側壁コンクリートが構築され得る。 On the other hand, for the construction of side walls (side wall concrete) of cylindrical underground structures such as vertical shafts and underground tanks, etc., it is possible to use mountain retaining that does not require support work such as cutting beams. It may be advantageous to build it by In this case, the sidewall concrete can function as a support work. In the reverse winding method, for example, after constructing a mountain retaining board using a steel sheet pile or a SMW method, the ground in the area surrounded by the mountain retaining station is dug down for about 3 to 5 m to pour sidewall concrete. To do. By repeating the excavation of the ground and the placement of the sidewall concrete, the sidewall concrete having a desired height can be constructed.
この側壁コンクリートの構築方法の一例では、まず、構築予定の側壁コンクリートを上下方向に複数のロットに分ける。次に、最上段のロットを、山留の側方に隣接するようにコンクリートを打設して構築する。次に、最上段のロットの下方にて、床型枠の設置と側部型枠の設置とを行う。ここで、側部型枠の上部には、最上段のロットの下端部の側方に位置するようにホッパー(コンクリート投入口)が設けられる。次に、ホッパーから、最上段のロットの下面と山留と床型枠と側部型枠とによって囲まれた空間内に、コンクリートを打設する。このようにして上から下に向かって順番にロットごとにコンクリートを打設して各ロットを順次構築することにより、側壁コンクリートが構築され得る。この点、特許文献1には、ホッパーから、山留と床型枠と側部型枠とによって囲まれた空間内に、コンクリートを打設することが記載されている。 In an example of this sidewall concrete construction method, first, the sidewall concrete to be constructed is vertically divided into a plurality of lots. Next, the top lot is constructed by pouring concrete so as to be adjacent to the side of the Yamadome. Next, the floor formwork and the side formwork are installed below the uppermost lot. Here, a hopper (concrete input port) is provided at an upper portion of the side formwork so as to be located at a side of a lower end portion of the uppermost lot. Next, concrete is poured from the hopper into the space surrounded by the lower surface of the uppermost lot, the mountain clasp, the floor formwork, and the side formwork. In this way, sidewall concrete can be constructed by placing concrete in each lot in order from top to bottom and constructing each lot sequentially. In this regard, Patent Document 1 describes that concrete is poured from the hopper into the space surrounded by the mountain dome, the floor formwork, and the side formwork.
しかしながら、前述のようにコンクリートの打設をホッパーを介して行うと、コンクリートの強度が発現した後にホッパーを撤去する必要があり、また、ホッパーが撤去された箇所で凸状に張り出して硬化した余分なコンクリートを斫って平らにして表面仕上げを行わなければならない。それゆえ、側壁コンクリートの構築に手間を要していた。 However, if the concrete is poured through the hopper as described above, it is necessary to remove the hopper after the strength of the concrete has developed, and at the place where the hopper has been removed, the hopper overhangs and is hardened. The concrete must be crushed and flattened for surface finish. Therefore, it took time and effort to construct the side wall concrete.
本発明は、このような実状に鑑み、壁状又は柱状のコンクリート躯体を効率良く構築することを目的とする。 In view of such an actual situation, the present invention aims to efficiently construct a wall-shaped or columnar concrete skeleton.
そのため本発明の第1〜第4態様におけるコンクリート躯体の構築方法は、構築予定のコンクリート躯体を上下方向に複数のロットに分け、上から下に向かって順番にロットごとに型枠を盛り替えてコンクリートを打設することにより、コンクリート躯体を構築する方法である。このコンクリート躯体の構築方法は、上下方向に延びるコンクリート打設作業用の第1管状部材を、第1ロット構築用型枠の内面によって囲まれる空間内に配置する第1工程と、第1ロット構築用型枠の内面によって囲まれる空間内にコンクリートを打設することにより第1ロットを構築する第2工程と、第1ロット構築用型枠を撤去する第3工程と、を含む。第1管状部材は、第1ロットの上方と第1ロットの下方とを連通する。
前記第1態様では、第2工程にて第1ロット構築用型枠内にコンクリートを打設するに先立って、第1管状部材の下面開口を塞ぐキャップである第1蓋部材を第1管状部材に取り付け、第3工程にて第1ロット構築用型枠を撤去した後に、第1蓋部材を第1管状部材から取り外す。
前記第2態様では、第1ロット構築用型枠を構成する床型枠には貫通孔が形成されており、第1工程では、第1管状部材の下端部が第1ロット構築用型枠の床型枠の貫通孔を貫通する。
前記第3態様では、前記コンクリート躯体の構築方法は、第3工程にて第1ロット構築用型枠を撤去した後に、第1管状部材の下端部に新たな管状部材の上端部を連結することにより、第1管状部材を下方に延長する第4工程と、第1ロットの下方に第2ロット構築用型枠を設置して、第2ロット構築用型枠の内面によって囲まれる空間内に第1管状部材の延長部を位置させる第5工程と、第2ロット構築用型枠の内面と第1ロットの下面とによって囲まれる空間内にコンクリートを打設することにより第2ロットを構築する第6工程と、第2ロット構築用型枠を撤去する第7工程と、を更に含み、第1管状部材及びその延長部は、第1ロットの上方と前記第2ロットの下方とを連通する。
前記第4態様では、前記コンクリート躯体の構築方法は、第3工程にて第1ロット構築用型枠を撤去した後に、第1ロットの下方に第2ロット構築用型枠を設置する第4工程と、第2ロット構築用型枠の内面と第1ロットの下面とによって囲まれる空間内にコンクリートを打設することにより第2ロットを構築する第5工程と、第2ロット構築用型枠を撤去する第6工程と、を更に含む。
Therefore, in the method for constructing a concrete skeleton according to the first to fourth aspects of the present invention , the concrete skeleton to be constructed is divided into a plurality of lots in the vertical direction, and the molds are rearranged in order from top to bottom. This is a method of constructing a concrete skeleton by placing concrete. This method for constructing a concrete skeleton comprises a first step of arranging a first tubular member extending vertically for concrete placing work in a space surrounded by an inner surface of a first lot construction mold, and a first lot construction. It includes a second step of constructing the first lot by placing concrete in a space surrounded by the inner surface of the mold for use for molding, and a third step of removing the formwork for constructing the first lot. The first tubular member connects the upper side of the first lot and the lower side of the first lot.
In the first aspect, the first lid member, which is a cap that closes the lower surface opening of the first tubular member, is placed in the first tubular member before the concrete is placed in the first lot building mold in the second step. And removing the first lot construction formwork in the third step, and then removing the first lid member from the first tubular member.
In the said 2nd aspect, the through-hole is formed in the floor formwork which comprises the 1st lot construction formwork, and the lower end part of a 1st tubular member is a 1st lot construction formwork in a 1st process. Penetrate through the through holes in the floor formwork.
In the third aspect, in the method for constructing the concrete skeleton, after removing the first lot construction formwork in the third step, the upper end of a new tubular member is connected to the lower end of the first tubular member. Thus, the fourth step of extending the first tubular member downward, and the second lot construction formwork is installed below the first lot, and the second lot construction formwork is installed in the space surrounded by the inner surface of the second lot construction formwork. (1) A fifth step of locating the extension of the tubular member, and a second lot is constructed by placing concrete in a space surrounded by the inner surface of the second lot construction mold and the lower surface of the first lot. The method further includes 6 steps and a 7th step of removing the second lot construction formwork, and the first tubular member and the extension thereof communicate between the upper side of the first lot and the lower side of the second lot.
In the fourth aspect, in the method for constructing a concrete skeleton, a fourth step is to install a second lot building mold below the first lot after removing the first lot building mold in the third step. And a fifth step of constructing a second lot by placing concrete in a space surrounded by the inner surface of the second lot constructing mold and the lower surface of the first lot, and a second lot constructing mold. And a sixth step of removing.
本発明によれば、第1管状部材が第1ロットの上方と下方とを連通する。これにより、第1ロットの下方に隣接して構築される新たなロットへのコンクリートの打設に第1管状部材を用いることができるので、前述のホッパーが不要となる。それゆえ、側部型枠をホッパーなしの平らな形状とすることができるので、通常の平板状の型枠を使用することができる。また、ホッパーが不要となることにより、前述のような余分なコンクリートの斫り作業や表面仕上げ作業を省略することができるので、コンクリート躯体を効率良く構築することができる。 According to the present invention, the first tubular member connects the upper side and the lower side of the first lot. Accordingly, the first tubular member can be used for placing concrete in a new lot that is adjacently constructed below the first lot, and thus the above-mentioned hopper is unnecessary. Therefore, since the side formwork can have a flat shape without a hopper, a normal flat formwork can be used. Further, since the hopper is not required, the above-mentioned extra concrete scrubbing work and surface finishing work can be omitted, so that the concrete skeleton can be efficiently constructed.
以下、本発明の実施の形態について、図面を参照して説明する。
図1は、本発明の第1実施形態における地下構造物の部分上面図である。尚、図1では、後述するコンクリート打設用シース管81,82の上端部及びバイブレータ用シース管91,92の上端部の図示を省略している。
本実施形態では、図1に示すように前後左右を規定して以下説明する。
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIG. 1 is a partial top view of an underground structure according to the first embodiment of the present invention. In addition, in FIG. 1, illustration of the upper end portions of the sheath pipes 81, 82 for concrete pouring and the upper end portions of the sheath pipes 91, 92 for vibrators, which will be described later, is omitted.
In the present embodiment, the front, rear, left and right are defined as shown in FIG. 1 and will be described below.
地下構造物1は、左右一対の側壁2,3と、側壁2,3間に位置する中仕切り壁4と、底部5とを有しており、上面が開口している。ここで、側壁2,3及び中仕切り壁4の各々が本発明の「コンクリート躯体」に対応する。すなわち、側壁2,3及び中仕切り壁4については、構築予定の側壁2,3及び中仕切り壁4の各々を上下方向に複数のロットに分け、上から下に向かって順番にロットごとに型枠を盛り替えてコンクリートを打設することにより、コンクリート躯体である側壁2,3及び中仕切り壁4の各々が構築される。尚、本実施形態では、構築予定の側壁2,3及び中仕切り壁4の各々を上下方向に3つのロットに分けているが、この他、2つのロットに分けてもよく、又は、4つ以上の任意の個数のロットに分けてもよい。また、1ロットの高さ(上下方向の長さ)は、3〜5m程度である。 The underground structure 1 has a pair of left and right side walls 2 and 3, a partition wall 4 located between the side walls 2 and 3, and a bottom portion 5, and the upper surface is open. Here, each of the side walls 2 and 3 and the partition wall 4 corresponds to the "concrete skeleton" of the present invention. That is, regarding the side walls 2 and 3 and the middle partition wall 4, each of the side walls 2 and 3 and the middle partition wall 4 to be constructed is divided into a plurality of lots in the vertical direction, and the lots are sequentially modeled from top to bottom. By refilling the frame and placing concrete, the side walls 2 and 3 and the intermediate partition wall 4, which are concrete skeletons, are constructed. In addition, in this embodiment, the side walls 2 and 3 and the partition wall 4 to be constructed are each divided into three lots in the vertical direction, but it may be divided into two lots or four lots. It may be divided into any number of lots described above. The height of one lot (length in the vertical direction) is about 3 to 5 m.
左側の側壁2の左側には山留6が構築されており、側壁2と山留6とは面接触して一体化されている。右側の側壁3の右側には山留7が構築されており、側壁3と山留7とは面接触して一体化されている。山留6,7の上下方向の長さは、側壁2,3の上下方向の長さよりも長い。換言すれば、山留6,7の下端は側壁2,3の下端よりも下方に位置する(後述する図12(a)参照)。 A mountain retainer 6 is constructed on the left side of the left side wall 2, and the side wall 2 and the mountain retainer 6 are in surface contact with each other and integrated. A mountain retaining member 7 is constructed on the right side of the right side wall 3, and the side wall 3 and the mountain retaining member 7 are in surface contact with each other and integrated. The vertical length of the ridges 6, 7 is longer than the vertical length of the side walls 2, 3. In other words, the lower ends of the mountain stays 6 and 7 are located below the lower ends of the side walls 2 and 3 (see FIG. 12A described later).
側壁2と中仕切り壁4と底部5とによって囲まれる空間8は地面10より下方に位置する。側壁3と中仕切り壁4と底部5とによって囲まれる空間9は地面10より下方に位置する。 A space 8 surrounded by the side wall 2, the partition wall 4, and the bottom portion 5 is located below the ground 10. A space 9 surrounded by the side wall 3, the partition wall 4, and the bottom portion 5 is located below the ground 10.
次に、右側の側壁3の構築方法について、図2〜図12を用いて説明する。図2〜図12は側壁3の構築方法を示す図である。ここで、図2及び図3(a)は図1のA−A断面に対応し、後述する支持杭12の設置位置に対応する。図4(a)〜図12(a)は図1のB−B断面に対応し、後述するコンクリート打設用シース管82の設置位置に対応する。図3(b)〜図12(b)は、図1のC−C断面に対応する。尚、図4(a)〜図12(a)については、図示簡略化のため、後述する支持杭12の図示を省略している。図4(b)〜図12(b)については、図示簡略化のため、後述する吊り鋼材14,14a,14bの図示を省略している。 Next, a method for constructing the right side wall 3 will be described with reference to FIGS. 2 to 12 are views showing a method of constructing the side wall 3. Here, FIG. 2 and FIG. 3A correspond to the AA cross section of FIG. 1 and correspond to the installation position of the support pile 12 described later. FIGS. 4A to 12A correspond to the BB cross section of FIG. 1 and correspond to the installation position of the sheath pipe 82 for concrete pouring described later. FIGS. 3B to 12B correspond to the C-C cross section of FIG. 1. 4(a) to 12(a), for simplification of illustration, illustration of a support pile 12 described later is omitted. 4(b) to 12(b), the hanging steel members 14, 14a, 14b, which will be described later, are omitted for simplification of the drawing.
本実施形態における側壁3の構築方法では、まず、構築予定の側壁3を上下方向の3つのロット(第1ロット31、第2ロット32、及び、第3ロット33)に分ける(後述する図12(a)参照)。
地盤11に山留6,7を構築する。ここで、図2は、地盤11に構築された右側の山留7を示している。
In the method of constructing the side wall 3 in the present embodiment, first, the side wall 3 to be constructed is divided into three vertical lots (first lot 31, second lot 32, and third lot 33) (FIG. 12 described later). (See (a)).
Yamadome 6 and 7 are built on the ground 11. Here, FIG. 2 shows the right mountain stay 7 built on the ground 11.
次に、図3(a)及び(b)に示すように、山留6,7間の地盤11aを数m程度掘り下げる。この掘り下げ深さは、第1ロット31の上下方向の長さよりも大きい。
また、図3(a)及び(b)に示すように、山留7の左側には、複数の支持杭12が、前後方向に間隔を空けて設置される。支持杭12は、第1ロット31、第2ロット32、及び、第3ロット33を支持するものである。尚、支持杭12の設置については、山留6,7の構築前に行ってもよく、又は、前述の地盤11aの掘り下げ後に行ってもよい。
Next, as shown in FIGS. 3(a) and 3(b), the ground 11a between the mountain retention points 6 and 7 is dug down by several meters. This digging depth is larger than the vertical length of the first lot 31.
Further, as shown in FIGS. 3A and 3B, a plurality of support piles 12 are installed on the left side of the mountain stay 7 at intervals in the front-rear direction. The support pile 12 supports the first lot 31, the second lot 32, and the third lot 33. Note that the support pile 12 may be installed before the construction of the mountain stays 6 and 7, or after the above-mentioned ground 11a is dug down.
次に、山留7の露出部分の左側面、及び、支持杭12の外周面に、スタッドボルトなどの、第1ロット31と一体化するための部材(図示せず)を取り付ける。
次に、第1ロット31を構成する主鉄筋(縦筋及び横筋)及びせん断補強鉄筋(いずれも図示せず)を設置する。これら鉄筋は例えば支持杭12に直接的又は間接的に取り付けられて、支持杭12によって支持され得る。
Next, a member (not shown) such as a stud bolt for integrating with the first lot 31 is attached to the left side surface of the exposed portion of the mountain stay 7 and the outer peripheral surface of the support pile 12.
Next, the main rebars (longitudinal rebars and horizontal rebars) and the shear reinforcing rebars (both not shown) that form the first lot 31 are installed. These reinforcing bars may be directly or indirectly attached to the support pile 12 and supported by the support pile 12, for example.
次に、図4(a)に示すように、各々が上下方向に延びる複数の吊り鋼材14を設置する。吊り鋼材14は例えばゲビンデ(登録商標)鋼棒である。吊り鋼材14の上端は、支持杭12によって支保される。 Next, as shown in FIG. 4A, a plurality of suspended steel members 14 each extending in the vertical direction are installed. The suspended steel material 14 is, for example, a Gebinde (registered trademark) steel rod. The upper end of the suspended steel material 14 is supported by the support pile 12.
次に、図4(a)及び(b)に示すように、第1ロット31の構築予定領域を山留7と共に囲むように第1ロット構築用型枠50を設置する。
第1ロット構築用型枠50は、前後方向に延びる板状の床型枠51と、前後方向に延びる板状の側部型枠52とにより構成されている。
Next, as shown in FIGS. 4A and 4B, the first lot construction mold 50 is installed so as to surround the construction planned region of the first lot 31 together with the yamadome 7.
The first lot construction mold 50 is composed of a plate-shaped floor mold 51 extending in the front-rear direction and a plate-shaped side part mold 52 extending in the front-rear direction.
床型枠51は、前述の吊り鋼材14によって吊られる吊り型枠である。床型枠51は、固定具53を介して、吊り鋼材14に着脱可能に固定される。
床型枠51は、右側端が山留7に接触しており、左側に向かうほど上方に向かうように傾斜している。床型枠51の左側端部には、側部型枠52の下端部と連結するための埋め込みアンカー(図示せず)が設けられている。
The floor formwork 51 is a hanging formwork that is hung by the above-mentioned hanging steel material 14. The floor form 51 is detachably fixed to the suspended steel material 14 via a fixture 53.
The right end of the floor form 51 is in contact with the mountain retainer 7, and the floor form 51 is inclined so as to move upward toward the left side. At the left end of the floor form 51, an embedded anchor (not shown) for connecting to the lower end of the side form 52 is provided.
側部型枠52は、その右側面が、山留7の露出部分の左側面に対向するように、山留7と間隔を空けて設置されている。側部型枠52は、その下端部で、前述の埋め込みアンカーを介して、床型枠51の左側端部に固定される。 The side frame 52 is installed at a distance from the mountain retainer 7 so that the right side surface thereof faces the left side surface of the exposed portion of the mountain retainer 7. The side form 52 is fixed to the left end of the floor form 51 at its lower end via the embedded anchor described above.
次に、図4(a)及び(b)に示すように、コンクリート打設用シース管81,82と、バイブレータ用シース管91,92とを、側部型枠52と山留7との間の中央位置に設置する。ここで、コンクリート打設用シース管81,82と、バイブレータ用シース管91,92との各々が、本発明の「コンクリート打設作業用の第1管状部材」に対応するものであり、上下方向に延びている。コンクリート打設用シース管81,82と、バイブレータ用シース管91,92との各々の下端は、床型枠51の上面の近傍に位置している。 Next, as shown in FIGS. 4(a) and 4(b), the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 are provided between the side mold 52 and the mountain retaining rod 7. Install in the center position of. Here, each of the sheathing pipes 81, 82 for concrete pouring and the sheathing pipes 91, 92 for vibrators corresponds to the "first tubular member for concrete pouring work" of the present invention, and the vertical direction. Extends to. The lower ends of the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 are located near the upper surface of the floor form 51.
側壁3の構築において、コンクリート打設用シース管81とバイブレータ用シース管91とは、第2ロット32を構築するときのコンクリート打設作業に用いられるものである。コンクリート打設用シース管82とバイブレータ用シース管92とは、第3ロット33を構築するときのコンクリート打設作業に用いられるものである。
本実施形態において、コンクリート打設用シース管81,82の直径は250mmであり、バイブレータ用シース管91,92の直径は100mmであるが、各シース管の直径はこれらに限らない。
In constructing the side wall 3, the concrete placing sheath tube 81 and the vibrator sheath tube 91 are used for concrete placing work when constructing the second lot 32. The sheath pipe 82 for concrete pouring and the sheath pipe 92 for vibrator are used for concrete pouring work when constructing the third lot 33.
In the present embodiment, the diameters of the concrete placing sheath pipes 81 and 82 are 250 mm, and the diameters of the vibrator sheath pipes 91 and 92 are 100 mm, but the diameter of each sheath pipe is not limited to these.
本実施形態において、複数のコンクリート打設用シース管81は、前後方向に例えば5mの間隔を空けて1列に並んでいる。隣り合うコンクリート打設用シース管81同士の間には、3つのバイブレータ用シース管91が、前後方向に例えば1.25mの間隔を空けて1列に並んでいる。 In the present embodiment, the plurality of sheathing pipes 81 for concrete pouring are arranged in a row in the front-rear direction at intervals of, for example, 5 m. Between the adjacent concrete pouring sheath pipes 81, three vibrator sheath pipes 91 are arranged in a line in the front-rear direction at intervals of, for example, 1.25 m.
本実施形態において、複数のコンクリート打設用シース管82は、前後方向に例えば5mの間隔を空けて1列に並んでいる。隣り合うコンクリート打設用シース管82同士の間には、3つのバイブレータ用シース管92が、前後方向に例えば1.25mの間隔を空けて1列に並んでいる。 In the present embodiment, the plurality of sheathing pipes 82 for concrete pouring are arranged in one row in the front-rear direction at intervals of, for example, 5 m. Between the adjacent concrete placing sheath pipes 82, three vibrator sheath pipes 92 are arranged in a line in the front-rear direction at intervals of, for example, 1.25 m.
コンクリート打設用シース管81,82と、バイブレータ用シース管91,92とは、例えば主鉄筋に直接的又は間接的に取り付けられて、主鉄筋によって支持され得る。
コンクリート打設用シース管81,82と、バイブレータ用シース管91,92とについては、各々の下面開口を塞ぐようにキャップなどの第1蓋部材(図示せず)が着脱可能に取り付けられている。尚、この第1蓋部材については、床型枠51に取り付けられて、床型枠51と一体的に着脱可能に構成されていてもよい。
The sheathing pipes 81, 82 for concrete pouring and the sheathing pipes 91, 92 for vibrators can be directly or indirectly attached to, for example, the main rebar and supported by the main rebar.
A first lid member (not shown) such as a cap is detachably attached to the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 so as to close the respective lower surface openings. .. The first lid member may be attached to the floor mold 51 so as to be detachable integrally with the floor mold 51.
従って、山留7の露出部分の左側面と、第1ロット構築用型枠50の内面(床型枠51の上面及び側部型枠52の右側面)とによって区画される(囲まれる)空間内に、主鉄筋、せん断補強鉄筋、吊り鋼材14、コンクリート打設用シース管81,82、及び、バイブレータ用シース管91,92が配置される。 Therefore, a space partitioned (enclosed) by the left side surface of the exposed portion of the mountain stay 7 and the inner surface of the first lot construction mold 50 (the upper surface of the floor mold 51 and the right surface of the side mold 52). Inside, a main reinforcing bar, a shear reinforcing reinforcing bar, a suspended steel material 14, concrete placing sheath tubes 81 and 82, and vibrator sheath tubes 91 and 92 are arranged.
尚、本実施形態では、第1ロット構築用型枠50の設置後にコンクリート打設用シース管81,82及びバイブレータ用シース管91,92を設置しているが、これに代えて、コンクリート打設用シース管81,82及びバイブレータ用シース管91,92を設置した後に第1ロット構築用型枠50の設置を設置してもよい。 In the present embodiment, the concrete placing sheath pipes 81, 82 and the vibrator sheath pipes 91, 92 are installed after the first lot construction form 50 is installed, but instead of this, concrete placing The first lot construction form 50 may be installed after the sheath tubes 81 and 82 for vibration and the sheath tubes 91 and 92 for vibrators are installed.
次に、山留7の露出部分の左側面と、第1ロット構築用型枠50の内面(床型枠51の上面及び側部型枠52の右側面)と、コンクリート打設用シース管81,82の外面(外周面)と、バイブレータ用シース管91,92の外面(外周面)とによって区画される(囲まれる)空間内に上方からコンクリートを打設して、鉄筋コンクリート製の第1ロット31を構築する。このときには、コンクリート打設用シース管81,82内とバイブレータ用シース管91,92内とにコンクリートが入ることはない。 Next, the left side surface of the exposed portion of the mountain stay 7, the inner surface of the first lot building formwork 50 (the upper surface of the floor formwork 51 and the right side surface of the side formwork 52), and the concrete pouring sheath pipe 81. , 82 outer surface (outer peripheral surface) and vibrator sheath tubes 91, 92 outer surface (outer peripheral surface) defined (enclosed) in a space from which concrete is poured from above to make a reinforced concrete first lot. Build 31. At this time, concrete does not enter into the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92.
次に、第1ロット31のコンクリートが硬化して強度が発現すると、図5(a)及び(b)に示すように、固定具53を取り外して、第1ロット構築用型枠50を撤去する。 Next, when the concrete in the first lot 31 is hardened and strength is developed, the fixture 53 is removed and the first lot construction form 50 is removed, as shown in FIGS. 5(a) and 5(b). ..
次に、図6(a)及び(b)に示すように、山留6,7間の地盤11aを数m程度掘り下げる。この掘り下げ深さは、第2ロット32の上下方向の長さよりも大きい。
次に、山留7の露出部分の左側面、及び、支持杭12の外周面に、スタッドボルトなどの、第2ロット32と一体化するための部材(図示せず)を取り付ける。
Next, as shown in FIGS. 6A and 6B, the ground 11a between the mountain retention points 6 and 7 is dug down by several meters. This digging depth is larger than the vertical length of the second lot 32.
Next, a member (not shown) such as a stud bolt for integrating with the second lot 32 is attached to the left side surface of the exposed portion of the mountain stay 7 and the outer peripheral surface of the support pile 12.
次に、図6(a)及び(b)に示すように、構築された第1ロット31のうち、コンクリート打設用シース管81,82及びバイブレータ用シース管91,92の各々の下端より下方のコンクリートを除去して、各シース管から第1蓋部材を取り外す。これにより、コンクリート打設用シース管81,82及びバイブレータ用シース管91,92の各々が、第1ロット31の上端部から下端部まで延びて第1ロット31を貫通する。また、コンクリート打設用シース管81,82及びバイブレータ用シース管91,92の各々が、第1ロット31の上方と第1ロット31の下方とを連通する。
また、このときに、構築された第1ロット31の下端では、吊り鋼材14の下端と縦筋の下端とが継手長分露出している。
Next, as shown in FIGS. 6A and 6B, in the constructed first lot 31, below the lower ends of the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92, respectively. Remove the concrete and remove the first lid member from each sheath tube. Thereby, the sheath pipes 81, 82 for concrete pouring and the sheath pipes 91, 92 for vibrators extend from the upper end portion to the lower end portion of the first lot 31 and penetrate the first lot 31. Further, each of the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 connects the upper side of the first lot 31 and the lower side of the first lot 31.
At this time, at the lower end of the constructed first lot 31, the lower end of the suspended steel material 14 and the lower end of the vertical streak are exposed by the joint length.
次に、図7(a)及び(b)に示すように、コンクリート打設用シース管82の下端部に新たなシース管82aの上端部を連結することにより、コンクリート打設用シース管82を下方に延長する。ここで、管状部材であるシース管82aが、本発明の「第1管状部材の延長部」に対応すると共に、コンクリート打設用シース管82の延長部に対応する。尚、コンクリート打設用シース管82の下端部とシース管82aの上端部との連結については、コンクリート打設用シース管82の下端部の内周面又は外周面にシース管82aの上端部の外周面又は内周面が螺合可能なようにスパイラルシース管を用いる。本実施形態では、コンクリート打設用シース管82の直径とシース管82aの直径とを異ならせてもよい。又は、コンクリート打設用シース管82の直径とシース管82aの直径とが同等である場合には、適宜の連結手段を用いて、コンクリート打設用シース管82の下端部とシース管82aの上端部とを連結してもよい。 Next, as shown in FIGS. 7A and 7B, by connecting the upper end of a new sheath pipe 82a to the lower end of the concrete pouring sheath pipe 82, the concrete pouring sheath pipe 82 is formed. Extend downward. Here, the sheath tube 82a, which is a tubular member, corresponds to the "extension portion of the first tubular member" of the present invention and also corresponds to the extension portion of the sheath pipe 82 for concrete pouring. Regarding the connection between the lower end of the concrete placing sheath pipe 82 and the upper end of the sheath pipe 82a, the upper end of the sheath pipe 82a is attached to the inner peripheral surface or the outer peripheral surface of the lower end of the concrete placing sheath pipe 82. A spiral sheath tube is used so that the outer peripheral surface or the inner peripheral surface can be screwed. In the present embodiment, the diameter of the sheath pipe 82 for concrete pouring may be different from the diameter of the sheath pipe 82a. Alternatively, when the diameter of the sheath pipe 82 for concrete pouring and the diameter of the sheath pipe 82a are the same, the lower end of the sheath pipe 82 for concrete pouring and the upper end of the sheath pipe 82a are used by using an appropriate connecting means. You may connect with a part.
また、図7(b)に示すように、バイブレータ用シース管92の下端部に新たなシース管92aの上端部を連結することにより、バイブレータ用シース管92を下方に延長する。ここで、管状部材であるシース管92aが、本発明の「第1管状部材の延長部」に対応すると共に、バイブレータ用シース管92の延長部に対応する。尚、バイブレータ用シース管92の下端部とシース管92aの上端部との連結については、バイブレータ用シース管92の下端部の内周面又は外周面にシース管92aの上端部の外周面又は内周面が螺合可能なようにスパイラルシース管を用いる。本実施形態では、バイブレータ用シース管92の直径とシース管92aの直径とを異ならせてもよい。又は、バイブレータ用シース管92の直径とシース管92aの直径とが同等である場合には、適宜の連結手段を用いて、バイブレータ用シース管92の下端部とシース管92aの上端部とを連結してもよい。 Further, as shown in FIG. 7B, by connecting the upper end of a new sheath tube 92a to the lower end of the vibrator sheath tube 92, the vibrator sheath tube 92 is extended downward. Here, the sheath tube 92a, which is a tubular member, corresponds to the "extension of the first tubular member" of the present invention and also corresponds to the extension of the vibrator sheath tube 92. Regarding the connection between the lower end of the vibrator sheath tube 92 and the upper end of the sheath tube 92a, the inner peripheral surface or the outer peripheral surface of the lower end of the vibrator sheath tube 92 should be attached to the outer peripheral surface or the inner peripheral surface of the upper end of the sheath tube 92a. A spiral sheath tube is used so that the peripheral surface can be screwed. In the present embodiment, the diameter of the vibrator sheath tube 92 and the diameter of the sheath tube 92a may be different. Alternatively, when the diameter of the vibrator sheath tube 92 and the diameter of the sheath tube 92a are the same, the lower end of the vibrator sheath tube 92 and the upper end of the sheath tube 92a are connected by using an appropriate connecting means. You may.
ここで、シース管82a,92aについては、各々の下面開口を塞ぐようにキャップなどの第2蓋部材(図示せず)が着脱可能に取り付けられている。尚、この第2蓋部材については、床型枠51に取り付けられて、床型枠51と一体的に着脱可能に構成されていてもよい。 Here, with respect to the sheath tubes 82a and 92a, a second lid member (not shown) such as a cap is detachably attached so as to close the respective lower surface openings. The second lid member may be attached to the floor mold 51 so as to be detachable integrally with the floor mold 51.
次に、図8(a)に示すように、吊り鋼材14の下端部に新たな吊り鋼材14aの上端部を連結することにより、吊り鋼材14を下方に延長する。この吊り鋼材14,14aの連結にはカップラーなどの適宜の連結手段が用いられる。 Next, as shown in FIG. 8A, the suspended steel material 14 is extended downward by connecting the upper end portion of a new suspended steel material 14 a to the lower end portion of the suspended steel material 14. Appropriate connecting means such as a coupler is used to connect the hanging steel members 14 and 14a.
次に、図8(a)及び(b)に示すように、前述と同様に傾斜した状態の床型枠51を、固定具53を介して、吊り鋼材14aの下端部に着脱可能に取り付ける。
次に、第1ロット31を構成する縦筋の下端部に、第2ロット32を構成する縦筋の上端部を接続しつつ、第2ロット32を構成する主鉄筋(縦筋及び横筋)及びせん断補強鉄筋(いずれも図示せず)を設置する。
Next, as shown in FIGS. 8(a) and 8(b), the floor form 51 in a tilted state as described above is detachably attached to the lower end portion of the hanging steel material 14a via the fixture 53.
Next, while connecting the upper end of the vertical bar forming the second lot 32 to the lower end of the vertical bar forming the first lot 31, the main reinforcing bars (vertical bar and horizontal bar) forming the second lot 32 and Install shear reinforcement bars (neither shown).
次に、図8(a)及び(b)に示すように、側部型枠62を、その下端部で、前述の埋め込みアンカーを介して、床型枠51の左側端部に固定する。ここで、側部型枠62は、その右側面が、山留7の露出部分の左側面に対向するように、山留7と間隔を空けて設置されている。 Next, as shown in FIGS. 8A and 8B, the side form 62 is fixed to the left end of the floor form 51 at its lower end via the aforementioned embedded anchor. Here, the side frame 62 is installed at a distance from the mountain retainer 7 such that the right side surface thereof faces the left side surface of the exposed portion of the mountain retainer 7.
ここで、第2ロット構築用型枠60は、床型枠51と、前後方向に延びる板状の側部型枠62とにより構成されている。第2ロット構築用型枠60は、第2ロット32の構築予定領域を囲むように設置される。また、第1ロット31の下面と、山留7の露出部分の左側面と、第2ロット構築用型枠60の内面(床型枠51の上面及び側部型枠62の右側面)とによって区画される(囲まれる)空間内に、主鉄筋、せん断補強鉄筋、吊り鋼材14a、コンクリート打設用シース管82の延長部(シース管82a)、及び、バイブレータ用シース管92の延長部(シース管92a)が位置する。 Here, the second lot construction mold 60 is composed of a floor mold 51 and a plate-shaped side mold 62 extending in the front-rear direction. The second lot construction form 60 is installed so as to surround the construction planned region of the second lot 32. In addition, by the lower surface of the first lot 31, the left side surface of the exposed portion of the mountain stay 7, and the inner surface of the second lot building mold 60 (the upper surface of the floor mold 51 and the right surface of the side mold 62). In the partitioned (enclosed) space, the main reinforcing bar, the shear reinforcing bar, the suspended steel material 14a, the extension part of the sheath pipe 82 for concrete placement (sheath pipe 82a), and the extension part (sheath of the sheath pipe 92 for vibrator). The tube 92a) is located.
次に、図8(a)及び(b)に示すように、第1ロット31の下面と、山留7の露出部分の左側面と、第2ロット構築用型枠60の内面(床型枠51の上面及び側部型枠62の右側面)と、コンクリート打設用シース管82の延長部(シース管82a)の外面(外周面)と、バイブレータ用シース管92の延長部(シース管92a)の外面(外周面)とによって区画される(囲まれる)空間内にコンクリートを打設して、鉄筋コンクリート製の第2ロット32を構築する。このときには、コンクリート打設用シース管82及びその延長部(シース管82a)内とバイブレータ用シース管92及びその延長部(シース管92a)内とにコンクリートが入ることはない。 Next, as shown in FIGS. 8A and 8B, the lower surface of the first lot 31, the left side surface of the exposed portion of the mountain retainer 7, and the inner surface of the second lot construction mold 60 (floor formwork). The upper surface of 51 and the right side surface of the side form 62, the outer surface (outer peripheral surface) of the extension portion (sheath tube 82a) of the concrete casting sheath tube 82, and the extension portion (sheath tube 92a) of the vibrator sheath tube 92. ), the second lot 32 made of reinforced concrete is constructed by placing concrete in a space defined (enclosed) by the outer surface (outer peripheral surface). At this time, concrete does not enter the concrete placing sheath tube 82 and its extension (sheath tube 82a) and the vibrator sheath tube 92 and its extension (sheath tube 92a).
ここで、第2ロット32の構築時のコンクリート打設作業について、図23〜図26を用いて説明する。
図23は、コンクリート打設用シース管81に挿入されたコンクリート打設配管85を示す。図24は、バイブレータ95の配置状況を示す。図25及び図26は、第2ロット構築時におけるコンクリートの打設方法を示す。尚、図23は図8の部分Pに対応する。図24は図8の部分Qに対応する。
Here, the concrete pouring work when constructing the second lot 32 will be described with reference to FIGS. 23 to 26.
FIG. 23 shows the concrete pouring pipe 85 inserted into the concrete pouring sheath pipe 81. FIG. 24 shows the arrangement of the vibrator 95. 25 and 26 show a concrete pouring method at the time of constructing the second lot. Note that FIG. 23 corresponds to the portion P of FIG. 24 corresponds to the portion Q of FIG.
図23に示すように、第2ロット32の構築時のコンクリート打設作業では、例えば5B(5インチ)の鋼管からなるコンクリート打設配管85をコンクリート打設用シース管81に挿入して、コンクリート打設配管85の上端部(第1ロット31の上方)にコンクリートの供給源からのコンクリートホースを接続する。コンクリート打設配管85の下端部が、第1ロット31の下面と、山留7の露出部分の左側面と、第2ロット構築用型枠60の内面(床型枠51の上面及び側部型枠62の右側面)と、コンクリート打設用シース管82の延長部(シース管82a)の外面(外周面)と、バイブレータ用シース管92の延長部(シース管92a)の外面(外周面)とによって区画される(囲まれる)空間内に位置した状態で、コンクリートの供給源から、コンクリートホース及びコンクリート打設配管85を介して、図23に示すように、当該空間内にコンクリートが供給される。ある1つのコンクリート打設用シース管81に挿入されたコンクリート打設配管85を用いて所定層厚のコンクリートの打設が完了すると、コンクリート打設配管85を当該コンクリート打設用シース管81から引き抜いて、隣の別の1つのコンクリート打設用シース管81に挿入して、コンクリートを打設する。このようにしてコンクリート打設配管85の移設とコンクリートの打設とを繰り返して、第1ロット31の下面にコンクリートが達したら、いわゆる片押し打設を行う。 As shown in FIG. 23, in the concrete pouring work at the time of constructing the second lot 32, for example, the concrete pouring pipe 85 made of a 5B (5 inch) steel pipe is inserted into the concrete pouring sheath pipe 81, and the concrete pouring is performed. A concrete hose from a concrete supply source is connected to the upper end of the casting pipe 85 (above the first lot 31). The lower end of the concrete pouring pipe 85 is the lower surface of the first lot 31, the left side surface of the exposed portion of the mountain stay 7, and the inner surface of the second lot construction mold 60 (the upper surface and the side mold of the floor mold 51). The right side surface of the frame 62), the outer surface (outer peripheral surface) of the extension portion (sheath tube 82a) of the concrete casting sheath tube 82, and the outer surface (outer peripheral surface) of the extension portion (sheath tube 92a) of the vibrator sheath tube 92. As shown in FIG. 23, the concrete is supplied from the concrete supply source through the concrete hose and the concrete placing pipe 85 while being positioned in the space partitioned (enclosed) by and. It When the placing of concrete of a predetermined layer thickness is completed using the concrete placing pipe 85 inserted in a certain concrete placing sheath pipe 81, the concrete placing pipe 85 is pulled out from the concrete placing sheath pipe 81. Then, it is inserted into another adjacent one of the sheath pipes 81 for concrete pouring, and concrete is poured. In this way, the transfer of the concrete placing pipe 85 and the placing of the concrete are repeated, and when the concrete reaches the lower surface of the first lot 31, the so-called one-sided placing is performed.
ここで、片押し打設について図25及び図26を用いて説明する。
コンクリート打設用シース管81−1に挿入されたコンクリート打設配管85を用いて打設されたコンクリートが第1ロット31の下面に達した状態でコンクリートの打設を継続すると(図25(a)及び(b)参照)、やがて、コンクリート打設用シース管81−1の隣の別のコンクリート打設用シース管81−2内にコンクリートが流入して、このコンクリートがコンクリート打設用シース管81−2内を上昇する(図25(c)参照)。このコンクリートの上昇を作業員が確認した後に、図26(a)に示すように、コンクリート打設配管85を、コンクリート打設用シース管81−1から引き抜いて、コンクリート打設用シース管81−2に挿入して、コンクリートの打設を再開する(図26(a)及び(b)参照)。このようにして、第2ロット32の構築時のコンクリート打設作業の終盤で、前から後に向かって順番にコンクリートを打設することにより、第1ロット31の下面と第2ロット32の上面との間に確実にコンクリートを充填できる。
Here, the single-sided driving will be described with reference to FIGS. 25 and 26.
If the concrete poured using the concrete placing pipe 85 inserted into the concrete placing sheath pipe 81-1 reaches the lower surface of the first lot 31, the concrete placing is continued (Fig. 25(a ) And (b)), eventually, the concrete flows into another concrete placing sheath pipe 81-2 next to the concrete placing sheath pipe 81-1 and the concrete is put into the concrete placing sheath pipe. The inside of 81-2 rises (see FIG. 25(c)). After the worker confirms the rise of the concrete, as shown in FIG. 26(a), the concrete placing pipe 85 is pulled out from the concrete placing sheath pipe 81-1 and the concrete placing sheath pipe 81- 2 and the concrete pouring is restarted (see FIGS. 26(a) and 26(b)). In this way, at the end of the concrete pouring work at the time of constructing the second lot 32, by pouring concrete in order from the front to the rear, the lower surface of the first lot 31 and the upper surface of the second lot 32 are You can surely fill the concrete in between.
尚、前述のように、コンクリート打設用シース管81にはコンクリート打設配管85が挿入され得るので、コンクリート打設用シース管81の内部をコンクリートが流通可能である。 As described above, since the concrete placing pipe 85 can be inserted into the concrete placing sheath pipe 81, concrete can flow through the inside of the concrete placing sheath pipe 81.
第2ロット32の構築時のコンクリートの締固めは、コンクリート打設に用いられている最中のコンクリート打設用シース管81に近く、かつ、当該コンクリート打設用シース管81より前方に位置する2つのバイブレータ用シース管91と、当該コンクリート打設用シース管81より後方に位置する2つのバイブレータ用シース管91との各々にバイブレータ95を吊り降ろして行う(図24参照)。ここで、バイブレータ95は、打設されたコンクリートに挿入されて、コンクリートに振動を与えて、コンクリートを締固めるものである。
従って、本実施形態では、バイブレータ95を第1ロット31の上方からバイブレータ用シース管91に挿入可能である。
The concrete compaction at the time of constructing the second lot 32 is located near the sheath pipe 81 for concrete pouring which is being used for pouring concrete and in front of the sheath pipe 81 for concrete pouring. The vibrator 95 is hung on each of the two vibrator sheath tubes 91 and the two vibrator sheath tubes 91 located behind the concrete placing sheath tube 81 (see FIG. 24 ). Here, the vibrator 95 is inserted into the cast concrete, gives vibration to the concrete, and compacts the concrete.
Therefore, in the present embodiment, the vibrator 95 can be inserted into the vibrator sheath tube 91 from above the first lot 31.
以上のようにして、第2ロット32の構築時のコンクリート打設作業が行われる。 As described above, the concrete pouring work at the time of constructing the second lot 32 is performed.
次に、第2ロット32のコンクリートが硬化して強度が発現すると、図9(a)及び(b)に示すように、固定具53を取り外して、第2ロット構築用型枠60を撤去する。 Next, when the concrete of the second lot 32 is hardened and strength is developed, the fixture 53 is removed and the second lot construction form 60 is removed as shown in FIGS. 9(a) and 9(b). ..
次に、図10(a)及び(b)に示すように、山留6,7間の地盤11aを数m程度掘り下げる。この掘り下げ深さは、第3ロット33の上下方向の長さよりも大きい。
次に、山留7の露出部分の左側面、及び、支持杭12の外周面に、スタッドボルトなどの、第3ロット33と一体化するための部材(図示せず)を取り付ける。
Next, as shown in FIGS. 10(a) and 10(b), the ground 11a between the mountain retention points 6 and 7 is dug down by several meters. This digging depth is larger than the vertical length of the third lot 33.
Next, a member (not shown), such as a stud bolt, for integrating with the third lot 33 is attached to the left side surface of the exposed portion of the mountain stay 7 and the outer peripheral surface of the support pile 12.
次に、図10(a)及び(b)に示すように、構築された第2ロット32のうち、コンクリート打設用シース管82の延長部(シース管82a)及びバイブレータ用シース管92の延長部(シース管92a)の各々の下端より下方のコンクリートを除去して、各シース管から第2蓋部材を取り外す。これにより、コンクリート打設用シース管82の延長部(シース管82a)及びバイブレータ用シース管92の延長部(シース管92a)の各々が、第2ロット32の上端部から下端部まで延びて第2ロット32を貫通する。また、コンクリート打設用シース管82の延長部(シース管82a)及びバイブレータ用シース管92の延長部(シース管92a)の各々が、第2ロット32の上方と第2ロット32の下方とを連通する。また、コンクリート打設用シース管82及びその延長部(シース管82a)と、バイブレータ用シース管92及びその延長部(シース管92a)と、の双方が、それぞれ、第1ロット31の上方と第2ロット32の下方とを連通する。
また、このときに、構築された第2ロット32の下端では、吊り鋼材14aの下端と縦筋の下端とが継手長分露出している。
Next, as shown in FIGS. 10A and 10B, in the constructed second lot 32, the extension portion of the sheath pipe 82 for concrete placing (sheath pipe 82a) and the extension of the sheath pipe 92 for vibrator are extended. The concrete below the lower end of each part (sheath tube 92a) is removed, and the second lid member is removed from each sheath tube. As a result, each of the extension portion of the sheath pipe 82 for concrete pouring (sheath pipe 82a) and the extension portion of the sheath pipe 92 for vibrator (sheath pipe 92a) extends from the upper end portion to the lower end portion of the second lot 32. Penetrate 2 lots 32. Further, the extension part of the sheath pipe 82 for concrete pouring (sheath pipe 82a) and the extension part of the sheath pipe 92 for vibrator (sheath pipe 92a) respectively extend above the second lot 32 and below the second lot 32. Communicate. Moreover, both the sheath pipe 82 for concrete pouring and its extension (sheath pipe 82a) and the sheath pipe 92 for vibrator and its extension (sheath pipe 92a) are above the first lot 31 and the first lot 31, respectively. It communicates with the lower side of the two lots 32.
At this time, at the lower end of the constructed second lot 32, the lower end of the suspended steel material 14a and the lower end of the vertical streak are exposed by the joint length.
次に、図11(a)に示すように、吊り鋼材14aの下端部に新たな吊り鋼材14bの上端部を連結することにより、吊り鋼材14,14aを下方に延長する。この吊り鋼材14a,14bの連結にはカップラーなどの適宜の連結手段が用いられる。 Next, as shown in FIG. 11A, the suspended steel materials 14 and 14a are extended downward by connecting the upper end of a new suspended steel material 14b to the lower end of the suspended steel material 14a. Appropriate connecting means such as a coupler is used to connect the hanging steel members 14a and 14b.
次に、図11(a)及び(b)に示すように、前述と同様に傾斜した状態の床型枠51を、固定具53を介して、吊り鋼材14bの下端部に着脱可能に取り付ける。
次に、第2ロット32を構成する縦筋の下端部に、第3ロット33を構成する縦筋の上端部を接続しつつ、第3ロット33を構成する主鉄筋(縦筋及び横筋)及びせん断補強鉄筋(いずれも図示せず)を設置する。
Next, as shown in FIGS. 11(a) and 11(b), the floor form 51 in a tilted state as described above is detachably attached to the lower end portion of the hanging steel material 14b via the fixture 53.
Next, while connecting the upper ends of the vertical bars forming the third lot 33 to the lower ends of the vertical bars forming the second lot 32, main reinforcing bars (vertical bars and horizontal bars) forming the third lot 33 and Install shear reinforcement bars (neither shown).
次に、図11(a)及び(b)に示すように、側部型枠72を、その下端部で、前述の埋め込みアンカーを介して、床型枠51の左側端部に固定する。ここで、側部型枠72は、その右側面が、山留7の露出部分の左側面に対向するように、山留7と間隔を空けて設置されている。 Next, as shown in FIGS. 11A and 11B, the side form 72 is fixed to the left end of the floor form 51 at the lower end thereof via the embedded anchor described above. Here, the side part form 72 is installed at a distance from the mountain retainer 7 such that the right side surface thereof faces the left side surface of the exposed portion of the mountain retainer 7.
尚、第3ロット構築用型枠70は、床型枠51と、前後方向に延びる板状の側部型枠72とにより構成されている。第3ロット構築用型枠70は、第3ロット33の構築予定領域を囲むように設置される。また、第2ロット32の下面と、山留7の露出部分の左側面と、第3ロット構築用型枠70の内面(床型枠51の上面及び側部型枠72の右側面)とによって区画される(囲まれる)空間内に、主鉄筋、せん断補強鉄筋、及び、吊り鋼材14bが位置する。 The third lot construction mold 70 is composed of a floor mold 51 and a plate-shaped side mold 72 extending in the front-rear direction. The third lot construction mold 70 is installed so as to surround the construction planned area of the third lot 33. In addition, by the lower surface of the second lot 32, the left side surface of the exposed portion of the mountain stay 7, and the inner surface of the third lot building form 70 (the upper surface of the floor form 51 and the right side of the side form 72). The main rebar, the shear reinforcing bar, and the suspended steel material 14b are located in the partitioned (enclosed) space.
次に、図11(a)及び(b)に示すように、第2ロット32の下面と、山留7の露出部分の左側面と、第3ロット構築用型枠70の内面(床型枠51の上面及び側部型枠72の右側面)とによって区画される(囲まれる)空間内に、コンクリートを打設して、鉄筋コンクリート製の第3ロット33を構築する。 Next, as shown in FIGS. 11(a) and 11(b), the lower surface of the second lot 32, the left side surface of the exposed portion of the mountain retainer 7, and the inner surface of the third lot building form 70 (floor formwork). Concrete is poured in a space defined (enclosed) by the upper surface of 51 and the right side surface of the side form 72 to construct the third lot 33 made of reinforced concrete.
第3ロット33の構築時のコンクリート打設作業では、コンクリート打設配管85をコンクリート打設用シース管82及びその延長部(シース管82a)に挿入して、コンクリート打設配管85の上端部(第1ロット31の上方)にコンクリートの供給源からのコンクリートホースを接続する。コンクリート打設配管85の下端部が、第2ロット32の下面と、山留7の露出部分の左側面と、第3ロット構築用型枠70の内面(床型枠51の上面及び側部型枠72の右側面)とによって区画される(囲まれる)空間内に位置した状態で、コンクリートの供給源から、コンクリートホース及びコンクリート打設配管85を介して、当該空間内にコンクリートが供給される。ある1つのコンクリート打設用シース管82及びその延長部(シース管82a)に挿入されたコンクリート打設配管85を用いて所定層厚のコンクリートの打設が完了すると、コンクリート打設配管85を当該コンクリート打設用シース管82及びその延長部(シース管82a)から引き抜いて、隣の別の1つのコンクリート打設用シース管82及びその延長部(シース管82a)に挿入して、コンクリートを打設する。このようにしてコンクリート打設配管85の移設とコンクリートの打設とを繰り返して、第2ロット32の下面にコンクリートが達したら、前述の第2ロット32の構築時のコンクリート打設作業と同様に、片押し打設を行う(前述の図25及び図26参照)。 In the concrete placing work at the time of constructing the third lot 33, the concrete placing pipe 85 is inserted into the concrete placing sheath pipe 82 and its extension (sheath pipe 82a), and the upper end portion of the concrete placing pipe 85 ( A concrete hose from a concrete supply source is connected to (above the first lot 31). The lower end of the concrete pouring pipe 85 is the lower surface of the second lot 32, the left side surface of the exposed portion of the mountain stay 7, and the inner surface of the third lot construction form 70 (the upper face and the side form of the floor form 51). Concrete is supplied from a concrete supply source into the space through a concrete hose and a concrete placing pipe 85 in a state of being positioned in (enclosed) by the right side surface of the frame 72). .. When the placing of concrete of a predetermined layer thickness is completed using a certain concrete placing sheath pipe 82 and the concrete placing pipe 85 inserted into its extension (sheath pipe 82a), the concrete placing pipe 85 is It is pulled out from the concrete pouring sheath pipe 82 and its extension (sheath pipe 82a) and inserted into another adjacent concrete pouring sheath pipe 82 and its extension (sheath pipe 82a) to pour concrete. Set up. In this way, the transfer of the concrete pouring pipe 85 and the pouring of concrete are repeated, and when the concrete reaches the lower surface of the second lot 32, the concrete pouring work at the time of constructing the second lot 32 described above is performed. Then, one-sided driving is performed (see FIGS. 25 and 26 described above).
尚、前述のように、コンクリート打設用シース管82及びその延長部(シース管82a)にはコンクリート打設配管85が挿入され得るので、コンクリート打設用シース管82及びその延長部(シース管82a)の内部をコンクリートが流通可能である。 As described above, since the concrete placing pipe 85 can be inserted into the concrete placing sheath pipe 82 and its extension (sheath pipe 82a), the concrete placing sheath pipe 82 and its extension (sheath pipe). Concrete can flow through the inside of 82a).
第3ロット33の構築時のコンクリートの締固めは、コンクリート打設に用いられている最中のコンクリート打設用シース管82及びその延長部(シース管82a)に近く、かつ、当該コンクリート打設用シース管82及びその延長部(シース管82a)より前方に位置する2つのバイブレータ用シース管92及びその延長部(シース管92a)と、当該コンクリート打設用シース管82及びその延長部(シース管82a)より後方に位置する2つのバイブレータ用シース管92及びその延長部(シース管92a)との各々にバイブレータ95を吊り降ろして行う。
従って、本実施形態では、バイブレータ95をバイブレータ用シース管92及びその延長部(シース管92a)に挿入可能である。
The concrete compaction at the time of constructing the third lot 33 is performed near the concrete placing sheath pipe 82 and its extension (sheath pipe 82a) which are being used for placing the concrete, and the concrete placing is performed. Two sheath tubes 92 for vibrator and its extension (sheath tube 92a) located in front of the sheath tube 82 for water and its extension (sheath tube 82a), and the sheath tube 82 for concrete pouring and its extension (sheath). The vibrator 95 is hung on each of the two vibrator sheath tubes 92 located behind the tube 82a) and its extension (sheath tube 92a).
Therefore, in the present embodiment, the vibrator 95 can be inserted into the vibrator sheath tube 92 and its extension (sheath tube 92a).
以上のようにして、第3ロット33の構築時のコンクリート打設作業が行われる。 As described above, the concrete pouring work at the time of constructing the third lot 33 is performed.
次に、第3ロット33のコンクリートが硬化して強度が発現すると、図12(a)及び(b)に示すように、固定具53を取り外して、第3ロット構築用型枠70を撤去する。 Next, when the concrete of the third lot 33 is hardened and strength is developed, the fixture 53 is removed and the third lot construction form 70 is removed, as shown in FIGS. 12(a) and 12(b). ..
尚、第2ロット32の構築時のコンクリート打設作業が完了した後の任意の時期に、コンクリート打設用シース管81の内部及びバイブレータ用シース管91の内部に、コンクリート又はモルタルを充填する。また、第3ロット33の構築時のコンクリート打設作業が完了した後の任意の時期に、コンクリート打設用シース管82及びその延長部(シース管82a)の内部と、バイブレータ用シース管92及びその延長部(シース管92a)の内部とに、コンクリート又はモルタルを充填する。 Incidentally, at an arbitrary time after the concrete placing work at the time of constructing the second lot 32 is completed, the inside of the concrete placing sheath pipe 81 and the inside of the vibrator sheath pipe 91 are filled with concrete or mortar. In addition, at any time after the concrete placing work at the time of constructing the third lot 33 is completed, the inside of the concrete placing sheath pipe 82 and its extension (sheath pipe 82a), the vibrator sheath pipe 92, and Concrete or mortar is filled inside the extension (sheath tube 92a).
そして、底部5の構築時に、第3ロット33の下端部と底部5とが連結される。このようにして、上から下に向かって順番に第1ロット31、第2ロット32、及び、第3ロット33が構築されることにより、側壁3が構築される。 Then, when the bottom portion 5 is constructed, the lower end portion of the third lot 33 and the bottom portion 5 are connected. In this way, the side wall 3 is constructed by constructing the first lot 31, the second lot 32, and the third lot 33 in order from top to bottom.
左側の側壁2の構築方法については、前述の右側の側壁3の構築方法において左右を入れ替えたものと同様であるので、その説明を省略する。 The method for constructing the left side wall 2 is the same as the method for constructing the right side wall 3 described above except that the left side and the right side are interchanged, and therefore description thereof will be omitted.
次に、中仕切り壁4の構築方法について、図13〜図22を用いて説明する。図13〜図22は中仕切り壁4の構築方法を示す図である。ここで、図13(a)は図1のD−D断面に対応し、支持杭12の設置位置に対応する。図14(a)〜図22(a)は図1のE−E断面に対応し、コンクリート打設用シース管82の設置位置に対応する。図13(b)〜図22(b)は、図1のF−F断面に対応する。尚、図14(a)〜図22(a)については、図示簡略化のため、後述する支持杭13の図示を省略している。図14(b)〜図22(b)については、図示簡略化のため、吊り鋼材14,14a,14bの図示を省略している。 Next, a method of constructing the partition wall 4 will be described with reference to FIGS. 13 to 22 are views showing a method of constructing the partition wall 4. Here, FIG. 13A corresponds to the DD cross section of FIG. 1 and corresponds to the installation position of the support pile 12. 14A to 22A correspond to the EE cross section of FIG. 1 and correspond to the installation position of the sheath pipe 82 for concrete pouring. 13B to 22B correspond to the FF cross section of FIG. 1. It should be noted that in FIGS. 14A to 22A, for simplification of the illustration, illustration of a support pile 13 described later is omitted. 14(b) to 22(b), the hanging steel materials 14, 14a, 14b are not shown for the sake of simplifying the illustration.
本実施形態における中仕切り壁4の構築方法では、まず、構築予定の中仕切り壁4を上下方向の3つのロット(第1ロット41、第2ロット42、及び、第3ロット43)に分ける(後述する図22(a)参照)。
次に、前述の図3(a)及び(b)に示したように、山留6,7間の地盤11aを数m程度掘り下げる(図13(a)及び(b)参照)。この掘り下げ深さは、第1ロット41の上下方向の長さよりも大きい。
In the method of constructing the partition wall 4 in the present embodiment, first, the partition wall 4 to be constructed is divided into three vertical lots (first lot 41, second lot 42, and third lot 43). FIG. 22A described later).
Next, as shown in FIGS. 3(a) and 3(b), the ground 11a between the mountain retention points 6 and 7 is dug down by about several meters (see FIGS. 13(a) and 13(b)). This digging depth is larger than the vertical length of the first lot 41.
また、図13(a)及び(b)に示すように、複数の支持杭13が、前後方向に間隔を空けて設置される。支持杭13は、第1ロット41、第2ロット42、及び、第3ロット43を支持するものである。尚、支持杭13の設置については、山留6,7の構築前に行ってもよく、又は、前述の地盤11aの掘り下げ後に行ってもよい。 In addition, as shown in FIGS. 13A and 13B, a plurality of support piles 13 are installed at intervals in the front-rear direction. The support pile 13 supports the first lot 41, the second lot 42, and the third lot 43. The support piles 13 may be installed before the construction of the mountain stays 6 and 7, or after the above-mentioned ground 11a is dug down.
次に、支持杭13の外周面に、スタッドボルトなどの、第1ロット41と一体化するための部材(図示せず)を取り付ける。
次に、第1ロット41を構成する主鉄筋(縦筋及び横筋)及びせん断補強鉄筋(いずれも図示せず)を設置する。これら鉄筋は例えば支持杭13に直接的又は間接的に取り付けられて、支持杭13によって支持され得る。
Next, a member (not shown) such as a stud bolt for integrating with the first lot 41 is attached to the outer peripheral surface of the support pile 13.
Next, the main rebars (longitudinal rebars and horizontal rebars) and the shear reinforcing bar (both not shown) that form the first lot 41 are installed. These reinforcing bars can be directly or indirectly attached to the support pile 13 and supported by the support pile 13, for example.
次に、図14(a)に示すように、各々が上下方向に延びる複数の吊り鋼材14を設置する。吊り鋼材14の上端は、支持杭13によって支保される。 Next, as shown in FIG. 14A, a plurality of hanging steel materials 14 each extending in the vertical direction are installed. The upper end of the suspended steel material 14 is supported by the support pile 13.
次に、図14(a)及び(b)に示すように、第1ロット41の構築予定領域を囲むように第1ロット構築用型枠50’を設置する。
第1ロット構築用型枠50’は、上に凸の山形状の断面を有して前後方向に延びる板状の床型枠51’と、前後方向に延びる左右一対の板状の側部型枠52とにより構成されている。
Next, as shown in FIGS. 14A and 14B, the first lot construction form 50' is installed so as to surround the construction planned region of the first lot 41.
The first lot construction mold 50' includes a plate-shaped floor mold 51' having an upward convex mountain-shaped cross section and extending in the front-rear direction, and a pair of left and right plate-shaped side molds extending in the front-rear direction. And a frame 52.
床型枠51’は、前述の吊り鋼材14によって吊られる吊り型枠である。床型枠51’は、固定具53を介して、吊り鋼材14に着脱可能に固定される。
床型枠51’は、左右両端から中央側(頂部51a’側)に向かうほど上方に向かうように傾斜している。床型枠51’の左右両端部には、それぞれ、側部型枠52の下端部と連結するための埋め込みアンカー(図示せず)が設けられている。
The floor form 51' is a suspension form suspended by the suspension steel material 14 described above. The floor form 51' is detachably fixed to the hanging steel material 14 via a fixture 53.
The floor form 51' is inclined so that it goes upward from the left and right ends toward the center (top 51a' side). Embedded anchors (not shown) for connecting to the lower ends of the side molds 52 are provided on both left and right ends of the floor mold 51′.
左右一対の側部型枠52は、互いに間隔を空けて対向するように設置されている。左右一対の側部型枠52は、各々の下端部で、前述の埋め込みアンカーを介して、床型枠51’の左右側端部にそれぞれ固定される。 The pair of left and right side molds 52 are installed so as to face each other with a space therebetween. The pair of left and right side molds 52 are fixed to the left and right ends of the floor mold 51' via the embedded anchors at their lower ends.
次に、図14(a)及び(b)に示すように、コンクリート打設用シース管81,82と、バイブレータ用シース管91,92とを、左右一対の側部型枠52間の中央位置に設置する。コンクリート打設用シース管81,82と、バイブレータ用シース管91,92との各々の下端は、床型枠51’の中央の頂部51a’の近傍に位置して、当該頂部51a’に対向している。 Next, as shown in FIGS. 14A and 14B, the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 are placed at a central position between the pair of left and right side molds 52. To install. The lower ends of the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 are located near the central top portion 51a′ of the floor form 51′ and face the top portion 51a′. ing.
中仕切り壁4の構築において、コンクリート打設用シース管81とバイブレータ用シース管91とは、第2ロット42を構築するときのコンクリート打設作業に用いられるものである。コンクリート打設用シース管82とバイブレータ用シース管92とは、第3ロット43を構築するときのコンクリート打設作業に用いられるものである。 In the construction of the intermediate partition wall 4, the concrete placing sheath tube 81 and the vibrator sheath tube 91 are used for concrete placing work when constructing the second lot 42. The sheath pipe 82 for concrete pouring and the sheath pipe 92 for vibrator are used for concrete pouring work when constructing the third lot 43.
本実施形態において、複数のコンクリート打設用シース管81は、前後方向に例えば5mの間隔を空けて1列に並んでいる。隣り合うコンクリート打設用シース管81同士の間には、3つのバイブレータ用シース管91が、前後方向に例えば1.25mの間隔を空けて1列に並んでいる。 In the present embodiment, the plurality of sheathing pipes 81 for concrete pouring are arranged in a row in the front-rear direction at intervals of, for example, 5 m. Between the adjacent concrete pouring sheath pipes 81, three vibrator sheath pipes 91 are arranged in a line in the front-rear direction at intervals of, for example, 1.25 m.
本実施形態において、複数のコンクリート打設用シース管82は、前後方向に例えば5mの間隔を空けて1列に並んでいる。隣り合うコンクリート打設用シース管82同士の間には、3つのバイブレータ用シース管92が、前後方向に例えば1.25mの間隔を空けて1列に並んでいる。 In the present embodiment, the plurality of sheathing pipes 82 for concrete pouring are arranged in one row in the front-rear direction at intervals of, for example, 5 m. Between the adjacent concrete placing sheath pipes 82, three vibrator sheath pipes 92 are arranged in a line in the front-rear direction at intervals of, for example, 1.25 m.
コンクリート打設用シース管81,82と、バイブレータ用シース管91,92とは、例えば,第1ロット41を構成する主鉄筋に直接的又は間接的に取り付けられて、当該主鉄筋によって支持され得る。
コンクリート打設用シース管81,82と、バイブレータ用シース管91,92とについては、各々の下面開口を塞ぐようにキャップなどの第1蓋部材(図示せず)が着脱可能に取り付けられている。尚、この第1蓋部材については、床型枠51’に取り付けられて、床型枠51’と一体的に着脱可能に構成されていてもよい。
The concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 may be directly or indirectly attached to the main rebars constituting the first lot 41 and supported by the main rebars, for example. ..
A first lid member (not shown) such as a cap is detachably attached to the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 so as to close the respective lower surface openings. .. The first lid member may be attached to the floor form 51' so as to be detachable integrally with the floor form 51'.
従って、第1ロット構築用型枠50’の内面(床型枠51’の上面、左側の側部型枠52の右側面、及び、右側の側部型枠52の左側面)によって区画される(囲まれる)空間内に、主鉄筋、せん断補強鉄筋、吊り鋼材14、コンクリート打設用シース管81,82、及び、バイブレータ用シース管91,92が配置される。 Therefore, it is partitioned by the inner surface of the first lot construction mold 50′ (the upper surface of the floor mold 51′, the right surface of the left side mold 52, and the left surface of the right side mold 52). In the (enclosed) space, main reinforcing bars, shear reinforcing reinforcing bars, suspended steel materials 14, sheath pipes 81, 82 for placing concrete, and sheath pipes 91, 92 for vibrators are arranged.
尚、本実施形態では、第1ロット構築用型枠50’の設置後にコンクリート打設用シース管81,82及びバイブレータ用シース管91,92を設置しているが、これに代えて、コンクリート打設用シース管81,82及びバイブレータ用シース管91,92を設置した後に第1ロット構築用型枠50’の設置を設置してもよい。 In this embodiment, the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 are installed after the first lot construction form 50' is installed. After installing the installation sheath tubes 81, 82 and the vibrator sheath tubes 91, 92, the installation of the first lot construction form 50' may be installed.
次に、第1ロット構築用型枠50’の内面(床型枠51’の上面、左側の側部型枠52の右側面、及び、右側の側部型枠52の左側面)と、コンクリート打設用シース管81,82の外面(外周面)と、バイブレータ用シース管91,92の外面(外周面)とによって区画される(囲まれる)空間内に上方からコンクリートを打設して、鉄筋コンクリート製の第1ロット41を構築する。このときには、コンクリート打設用シース管81,82内とバイブレータ用シース管91,92内とにコンクリートが入ることはない。 Next, the inner surface of the first lot building mold 50' (the upper surface of the floor mold 51', the right surface of the left side mold 52, and the left surface of the right side mold 52) and concrete. Concrete is poured from above into a space defined (enclosed) by the outer surfaces (outer peripheral surfaces) of the casting sheath tubes 81 and 82 and the outer surfaces (outer peripheral surfaces) of the vibrator sheath tubes 91 and 92, Build a first lot 41 made of reinforced concrete. At this time, concrete does not enter into the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92.
次に、第1ロット41のコンクリートが硬化して強度が発現すると、図15(a)及び(b)に示すように、固定具53を取り外して、第1ロット構築用型枠50’を撤去する。 Next, when the concrete in the first lot 41 hardens and strength develops, the fixture 53 is removed and the first lot construction form 50' is removed, as shown in FIGS. 15(a) and 15(b). To do.
次に、前述の図6(a)及び(b)に示したように、山留6,7間の地盤11aを数m程度掘り下げる(図16(a)及び(b)参照)。この掘り下げ深さは、第2ロット42の上下方向の長さよりも大きい。
次に、支持杭13の外周面に、スタッドボルトなどの、第2ロット42と一体化するための部材(図示せず)を取り付ける。
Next, as shown in FIGS. 6(a) and 6(b), the ground 11a between the mountain retention points 6 and 7 is dug down by about several meters (see FIGS. 16(a) and 16(b)). This digging depth is larger than the vertical length of the second lot 42.
Next, a member (not shown) such as a stud bolt for integrating with the second lot 42 is attached to the outer peripheral surface of the support pile 13.
次に、図16(a)及び(b)に示すように、構築された第1ロット41のうち、コンクリート打設用シース管81,82及びバイブレータ用シース管91,92の各々の下端より下方のコンクリートを除去して、各シース管から第1蓋部材を取り外す。これにより、コンクリート打設用シース管81,82及びバイブレータ用シース管91,92の各々が、第1ロット41の上端部から下端部まで延びて第1ロット41を貫通する。また、コンクリート打設用シース管81,82及びバイブレータ用シース管91,92の各々が、第1ロット41の上方と第1ロット41の下方とを連通する。
また、このときに、構築された第1ロット41の下端では、吊り鋼材14の下端と縦筋の下端とが継手長分露出している。
Next, as shown in FIGS. 16( a) and 16 (b ), in the constructed first lot 41, below the lower ends of the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92, respectively. Remove the concrete and remove the first lid member from each sheath tube. As a result, each of the sheath pipes 81 and 82 for concrete pouring and the sheath pipes 91 and 92 for vibrators extends from the upper end portion to the lower end portion of the first lot 41 and penetrates the first lot 41. Further, each of the concrete placing sheath pipes 81 and 82 and the vibrator sheath pipes 91 and 92 communicates between the upper side of the first lot 41 and the lower side of the first lot 41.
At this time, at the lower end of the constructed first lot 41, the lower end of the suspended steel material 14 and the lower end of the vertical streak are exposed by the joint length.
次に、図17(a)及び(b)に示すように、コンクリート打設用シース管82の下端部に新たなシース管82aの上端部を連結することにより、コンクリート打設用シース管82を下方に延長する。
また、図17(b)に示すように、バイブレータ用シース管92の下端部に新たなシース管92aの上端部を連結することにより、バイブレータ用シース管92を下方に延長する。
Next, as shown in FIGS. 17(a) and 17(b), the sheath pipe for concrete placing 82 is connected by connecting the upper end of a new sheath pipe 82a to the lower end of the sheath pipe 82 for concrete placing. Extend downward.
Further, as shown in FIG. 17B, the upper end of a new sheath tube 92a is connected to the lower end of the vibrator sheath tube 92 to extend the vibrator sheath tube 92 downward.
ここで、シース管82a,92aについては、各々の下面開口を塞ぐようにキャップなどの第2蓋部材(図示せず)が着脱可能に取り付けられている。尚、この第2蓋部材については、床型枠51’に取り付けられて、床型枠51’と一体的に着脱可能に構成されていてもよい。 Here, with respect to the sheath tubes 82a and 92a, a second lid member (not shown) such as a cap is detachably attached so as to close the respective lower surface openings. The second lid member may be attached to the floor form 51' so as to be detachable integrally with the floor form 51'.
次に、図18(a)に示すように、吊り鋼材14の下端部に新たな吊り鋼材14aの上端部を連結することにより、吊り鋼材14を下方に延長する。 Next, as shown in FIG. 18A, the suspended steel material 14 is extended downward by connecting the upper end portion of a new suspended steel material 14a to the lower end portion of the suspended steel material 14.
次に、図18(a)及び(b)に示すように、山形状の断面を有する床型枠51’を、固定具53を介して、吊り鋼材14aの下端部に着脱可能に取り付ける。
このときに、コンクリート打設用シース管82の延長部(シース管82a)と、バイブレータ用シース管92の延長部(シース管92a)との各々の下端は、床型枠51’の中央の頂部51a’の近傍に位置して、当該頂部51a’に対向している。
Next, as shown in FIGS. 18( a) and 18 (b ), a floor form 51 ′ having a mountain-shaped cross section is detachably attached to the lower end of the suspended steel material 14 a via a fixture 53.
At this time, the respective lower ends of the extension portion of the sheath pipe 82 for concrete pouring (sheath pipe 82a) and the extension portion of the sheath pipe 92 for vibrator (sheath pipe 92a) are at the central top portion of the floor form 51'. It is located in the vicinity of 51a' and faces the top portion 51a'.
次に、第1ロット41を構成する縦筋の下端部に、第2ロット42を構成する縦筋の上端部を接続しつつ、第2ロット42を構成する主鉄筋(縦筋及び横筋)及びせん断補強鉄筋(いずれも図示せず)を設置する。 Next, while connecting the upper end of the vertical bar forming the second lot 42 to the lower end of the vertical bar forming the first lot 41, the main reinforcing bars (vertical bar and horizontal bar) forming the second lot 42 and Install shear reinforcement bars (neither shown).
次に、図18(a)及び(b)に示すように、左右一対の側部型枠62を、各々の下端部で、前述の埋め込みアンカーを介して、床型枠51’の左右両端部にそれぞれ固定する。ここで、左右一対の側部型枠62は、互いに間隔を空けて対向するように設置されている。 Next, as shown in FIGS. 18(a) and 18(b), a pair of left and right side molds 62 are provided at the lower ends of the left and right ends of the floor form 51' through the embedded anchors. Fixed to each. Here, the pair of left and right side molds 62 are installed so as to face each other with a space therebetween.
尚、第2ロット構築用型枠60’は、床型枠51’と、前後方向に延びる左右一対の板状の側部型枠62とにより構成されている。第2ロット構築用型枠60’は、第2ロット42の構築予定領域を囲むように設置される。また、第1ロット41の下面と、第2ロット構築用型枠60’の内面(床型枠51’の上面、左側の側部型枠62の右側面、及び、右側の側部型枠62の左側面)とによって区画される(囲まれる)空間内に、主鉄筋、せん断補強鉄筋、吊り鋼材14a、コンクリート打設用シース管82の延長部(シース管82a)、及び、バイブレータ用シース管92の延長部(シース管92a)が位置する。 The second lot construction mold 60' is composed of a floor mold 51' and a pair of left and right plate-shaped side molds 62 extending in the front-rear direction. The second lot construction form 60 ′ is installed so as to surround the construction planned region of the second lot 42. Further, the lower surface of the first lot 41, the inner surface of the second lot building mold 60′ (the upper surface of the floor mold 51′, the right side surface of the left side mold 62, and the right side mold 62). In the space defined by (surrounded by the left side surface of), the main reinforcing bar, the shear reinforcing bar, the suspended steel material 14a, the extension part of the sheath pipe 82 for concrete placing (sheath pipe 82a), and the sheath pipe for vibrator. The extension (sheath tube 92a) of 92 is located.
次に、図18(a)及び(b)に示すように、第1ロット41の下面と、第2ロット構築用型枠60’の内面(床型枠51’の上面、左側の側部型枠62の右側面、及び、右側の側部型枠62の左側面)と、コンクリート打設用シース管82の延長部(シース管82a)の外面(外周面)と、バイブレータ用シース管92の延長部(シース管92a)の外面(外周面)とによって区画される(囲まれる)空間内にコンクリートを打設して、鉄筋コンクリート製の第2ロット42を構築する。このときには、コンクリート打設用シース管82及びその延長部(シース管82a)内とバイブレータ用シース管92及びその延長部(シース管92a)内とにコンクリートが入ることはない。 Next, as shown in FIGS. 18A and 18B, the lower surface of the first lot 41 and the inner surface of the second lot building mold 60′ (the upper surface of the floor mold 51′, the left side mold). The right side surface of the frame 62 and the left side surface of the right side form frame 62), the outer surface (outer peripheral surface) of the extension portion (sheath tube 82a) of the concrete placing sheath tube 82, and the vibrator sheath tube 92. Concrete is poured into a space defined (enclosed) by the outer surface (outer peripheral surface) of the extension portion (sheath tube 92a) to construct the second lot 42 made of reinforced concrete. At this time, concrete does not enter the concrete placing sheath tube 82 and its extension (sheath tube 82a) and the vibrator sheath tube 92 and its extension (sheath tube 92a).
第2ロット32の構築時のコンクリート打設作業では、コンクリート打設配管85をコンクリート打設用シース管81に挿入して、コンクリート打設配管85の上端部(第1ロット41の上方)にコンクリートの供給源からのコンクリートホースを接続する。コンクリート打設配管85の下端部が、第1ロット41の下面と、第2ロット構築用型枠60’の内面(床型枠51’の上面、左側の側部型枠62の右側面、及び、右側の側部型枠62の左側面)と、コンクリート打設用シース管82の延長部(シース管82a)の外面(外周面)と、バイブレータ用シース管92の延長部(シース管92a)の外面(外周面)とによって区画される(囲まれる)空間内に位置した状態で、コンクリートの供給源から、コンクリートホース及びコンクリート打設配管85を介して、当該空間内にコンクリートが供給される。ある1つのコンクリート打設用シース管81に挿入されたコンクリート打設配管85を用いて所定層厚のコンクリートの打設が完了すると、コンクリート打設配管85を当該コンクリート打設用シース管81から引き抜いて、隣の別の1つのコンクリート打設用シース管81に挿入して、コンクリートを打設する。このようにしてコンクリート打設配管85の移設とコンクリートの打設とを繰り返して、第1ロット41の下面にコンクリートが達したら、前述の第2ロット32の構築時のコンクリート打設作業と同様に、片押し打設を行う(前述の図25及び図26参照)。 In the concrete placing work at the time of constructing the second lot 32, the concrete placing pipe 85 is inserted into the concrete placing sheath pipe 81, and the concrete is placed on the upper end portion (above the first lot 41) of the concrete placing pipe 85. Connect concrete hoses from your source. The lower end of the concrete pouring pipe 85 includes the lower surface of the first lot 41, the inner surface of the second lot building mold 60′ (the upper surface of the floor mold 51′, the right surface of the left side mold 62, and , The left side surface of the right side mold 62), the outer surface (outer peripheral surface) of the extension portion (sheath tube 82a) of the concrete casting sheath tube 82, and the extension portion (sheath tube 92a) of the vibrator sheath tube 92. The concrete is supplied from the concrete supply source to the space through the concrete hose and the concrete placing pipe 85 while being positioned in the space defined (enclosed) by the outer surface (outer peripheral surface) of the concrete. .. When the placing of concrete of a predetermined layer thickness is completed using the concrete placing pipe 85 inserted in a certain concrete placing sheath pipe 81, the concrete placing pipe 85 is pulled out from the concrete placing sheath pipe 81. Then, it is inserted into another adjacent one of the sheath pipes 81 for concrete pouring, and concrete is poured. In this way, the transfer of the concrete placing pipe 85 and the placing of the concrete are repeated, and when the concrete reaches the lower surface of the first lot 41, as in the concrete placing work at the time of constructing the second lot 32 described above. Then, one-sided driving is performed (see FIGS. 25 and 26 described above).
第2ロット42の構築時のコンクリートの締固めは、コンクリート打設に用いられている最中のコンクリート打設用シース管81に近く、かつ、当該コンクリート打設用シース管81より前方に位置する2つのバイブレータ用シース管91と、当該コンクリート打設用シース管81より後方に位置する2つのバイブレータ用シース管91との各々にバイブレータ95を吊り降ろして行う。 The concrete compaction at the time of constructing the second lot 42 is located near the sheath pipe 81 for concrete pouring which is being used for pouring concrete, and in front of the sheath pipe 81 for concrete pouring. The vibrator 95 is suspended from each of the two vibrator sheath tubes 91 and the two vibrator sheath tubes 91 located behind the concrete placing sheath tube 81.
以上のようにして、第2ロット42の構築時のコンクリート打設作業が行われる。 As described above, the concrete placing work at the time of constructing the second lot 42 is performed.
次に、第2ロット42のコンクリートが硬化して強度が発現すると、図19(a)及び(b)に示すように、固定具53を取り外して、第2ロット構築用型枠60’を撤去する。 Next, when the concrete of the second lot 42 hardens and strength develops, as shown in FIGS. 19(a) and (b), the fixture 53 is removed and the second lot construction form 60' is removed. To do.
次に、図10(a)及び(b)に示したように、山留6,7間の地盤11aを数m程度掘り下げる(図20(a)及び(b)参照)。この掘り下げ深さは、第3ロット43の上下方向の長さよりも大きい。
次に、支持杭13の外周面に、スタッドボルトなどの、第3ロット43と一体化するための部材(図示せず)を取り付ける。
Next, as shown in FIGS. 10A and 10B, the ground 11a between the mountain retention points 6 and 7 is dug down by about several meters (see FIGS. 20A and 20B). This digging depth is larger than the vertical length of the third lot 43.
Next, a member (not shown) such as a stud bolt for integrating with the third lot 43 is attached to the outer peripheral surface of the support pile 13.
次に、図20(a)及び(b)に示すように、構築された第2ロット42のうち、コンクリート打設用シース管82の延長部(シース管82a)及びバイブレータ用シース管92の延長部(シース管92a)の各々の下端より下方のコンクリートを除去して、各シース管から第2蓋部材を取り外す。これにより、コンクリート打設用シース管82の延長部(シース管82a)及びバイブレータ用シース管92の延長部(シース管92a)の各々が、第2ロット42の上端部から下端部まで延びて第2ロット32を貫通する。また、コンクリート打設用シース管82の延長部(シース管82a)及びバイブレータ用シース管92の延長部(シース管92a)の各々が、第2ロット42の上方と第2ロット42の下方とを連通する。また、コンクリート打設用シース管82及びその延長部(シース管82a)と、バイブレータ用シース管92及びその延長部(シース管92a)と、の双方が、それぞれ、第1ロット41の上方と第2ロット42の下方とを連通する。
また、このときに、構築された第2ロット42の下端では、吊り鋼材14aの下端と縦筋の下端とが継手長分露出している。
Next, as shown in FIGS. 20( a) and 20 (b ), in the constructed second lot 42, the extension part (sheath pipe 82 a) of the sheath pipe 82 for concrete placing and the extension of the sheath pipe 92 for vibrator are extended. The concrete below the lower end of each part (sheath tube 92a) is removed, and the second lid member is removed from each sheath tube. As a result, the extension portion of the sheath pipe 82 for concrete pouring (sheath pipe 82a) and the extension portion of the sheath pipe 92 for vibrator (sheath pipe 92a) each extend from the upper end portion to the lower end portion of the second lot 42, and Penetrate 2 lots 32. Further, each of the extension portion of the sheath pipe 82 for concrete pouring (sheath pipe 82a) and the extension portion of the sheath pipe 92 for vibrator (sheath pipe 92a) is located above the second lot 42 and below the second lot 42. Communicate. Further, both the sheath pipe 82 for concrete pouring and its extension (sheath pipe 82a) and the sheath pipe 92 for vibrator and its extension (sheath pipe 92a) are above the first lot 41 and the first lot 41, respectively. It communicates with the lower part of the two lots 42.
Further, at this time, at the lower end of the constructed second lot 42, the lower end of the suspended steel material 14a and the lower end of the vertical streak are exposed by the joint length.
次に、図21(a)に示すように、吊り鋼材14aの下端部に新たな吊り鋼材14bの上端部を連結することにより、吊り鋼材14,14aを下方に延長する。 Next, as shown in FIG. 21(a), the hanging steel materials 14 and 14a are extended downward by connecting the upper end portion of a new hanging steel material 14b to the lower end portion of the hanging steel material 14a.
次に、図21(a)及び(b)に示すように、山形状の断面を有する床型枠51’を、固定具53を介して、吊り鋼材14bの下端部に着脱可能に取り付ける。
次に、第2ロット42を構成する縦筋の下端部に、第3ロット43を構成する縦筋の上端部を接続しつつ、第3ロット43を構成する主鉄筋(縦筋及び横筋)及びせん断補強鉄筋(いずれも図示せず)を設置する。
Next, as shown in FIGS. 21A and 21B, a floor form 51' having a mountain-shaped cross section is detachably attached to the lower end of the suspended steel material 14b via a fixture 53.
Next, while connecting the upper end of the vertical bar forming the third lot 43 to the lower end of the vertical bar forming the second lot 42, the main reinforcing bars (vertical bar and horizontal bar) forming the third lot 43 and Install shear reinforcement bars (neither shown).
次に、図21(a)及び(b)に示すように、左右一対の側部型枠72を、各々の下端部で、前述の埋め込みアンカーを介して、床型枠51’の左右両端部にそれぞれ固定する。ここで、左右一対の側部型枠72は、互いに間隔を空けて対向するように設置されている。 Next, as shown in FIGS. 21(a) and 21(b), a pair of left and right side molds 72 is provided at the lower end of each of the left and right end parts of the floor form 51' through the embedded anchors. Fixed to each. Here, the pair of left and right side molds 72 are installed so as to face each other with a space therebetween.
尚、第3ロット構築用型枠70’は、床型枠51’と、前後方向に延びる左右一対の板状の側部型枠72とにより構成されている。第3ロット構築用型枠70’は、第3ロット43の構築予定領域を囲むように設置される。また、第2ロット42の下面と、第3ロット構築用型枠70’の内面(床型枠51’の上面、左側の側部型枠72の右側面、及び、右側の側部型枠72の左側面)とによって区画される(囲まれる)空間内に、主鉄筋、せん断補強鉄筋、及び、吊り鋼材14bが位置する。 The third lot construction mold 70' is composed of a floor mold 51' and a pair of left and right plate-shaped side molds 72 extending in the front-rear direction. The third lot construction form 70 ′ is installed so as to surround the construction planned region of the third lot 43. Further, the lower surface of the second lot 42, the inner surface of the third lot building mold 70′ (the upper surface of the floor mold 51′, the right side surface of the left side mold 72, and the right side mold 72). The main rebar, the shear reinforcing rebar, and the hanging steel material 14b are located in a space defined (enclosed) by (left side surface of).
次に、図21(a)及び(b)に示すように、第2ロット42の下面と、第3ロット構築用型枠70’の内面(床型枠51’の上面、左側の側部型枠72の右側面、及び、右側の側部型枠72の左側面)とによって区画される(囲まれる)空間内に、コンクリートを打設して、鉄筋コンクリート製の第3ロット43を構築する。 Next, as shown in FIGS. 21A and 21B, the lower surface of the second lot 42 and the inner surface of the third lot building mold 70' (the upper surface of the floor mold 51', the left side mold). Concrete is poured into a space defined (enclosed) by the right side surface of the frame 72 and the left side surface of the right side form 72 to construct the third lot 43 made of reinforced concrete.
第3ロット43の構築時のコンクリート打設作業では、コンクリート打設配管85をコンクリート打設用シース管82及びその延長部(シース管82a)に挿入して、コンクリート打設配管85の上端部(第1ロット41の上方)にコンクリートの供給源からのコンクリートホースを接続する。コンクリート打設配管85の下端部が、第2ロット42の下面と、第3ロット構築用型枠70’の内面(床型枠51’の上面、左側の側部型枠72の右側面、及び、右側の側部型枠72の左側面)とによって区画される(囲まれる)空間内に位置した状態で、コンクリートの供給源から、コンクリートホース及びコンクリート打設配管85を介して、当該空間内にコンクリートが供給される。ある1つのコンクリート打設用シース管82及びその延長部(シース管82a)に挿入されたコンクリート打設配管85を用いて所定層厚のコンクリートの打設が完了すると、コンクリート打設配管85を当該コンクリート打設用シース管82及びその延長部(シース管82a)から引き抜いて、隣の別の1つのコンクリート打設用シース管82及びその延長部(シース管82a)に挿入して、コンクリートを打設する。このようにしてコンクリート打設配管85の移設とコンクリートの打設とを繰り返して、第2ロット42の下面にコンクリートが達したら、前述の第2ロット32の構築時のコンクリート打設作業と同様に、片押し打設を行う(前述の図25及び図26参照)。 In the concrete placing work at the time of constructing the third lot 43, the concrete placing pipe 85 is inserted into the concrete placing sheath pipe 82 and its extension (sheath pipe 82a), and the upper end portion of the concrete placing pipe 85 ( A concrete hose from a concrete supply source is connected to (above the first lot 41). The lower end of the concrete placing pipe 85 is the lower surface of the second lot 42, the inner surface of the third lot building form 70' (the upper surface of the floor form 51', the right side surface of the left side form 72, and , The left side surface of the right side mold 72), the interior of the space is surrounded (enclosed) by a concrete supply source through a concrete hose and a concrete placing pipe 85. Is supplied with concrete. When the placing of concrete of a predetermined layer thickness is completed using a certain concrete placing sheath pipe 82 and the concrete placing pipe 85 inserted into its extension (sheath pipe 82a), the concrete placing pipe 85 is It is pulled out from the concrete pouring sheath pipe 82 and its extension (sheath pipe 82a) and inserted into another adjacent concrete pouring sheath pipe 82 and its extension (sheath pipe 82a) to pour concrete. Set up. In this manner, the transfer of the concrete placing pipe 85 and the placing of the concrete are repeated, and when the concrete reaches the lower surface of the second lot 42, the concrete placing work at the time of constructing the second lot 32 described above is performed. Then, one-sided driving is performed (see FIGS. 25 and 26 described above).
第3ロット43の構築時のコンクリートの締固めは、コンクリート打設に用いられている最中のコンクリート打設用シース管82及びその延長部(シース管82a)に近く、かつ、当該コンクリート打設用シース管82及びその延長部(シース管82a)より前方に位置する2つのバイブレータ用シース管92及びその延長部(シース管92a)と、当該コンクリート打設用シース管82及びその延長部(シース管82a)より後方に位置する2つのバイブレータ用シース管92及びその延長部(シース管92a)との各々にバイブレータ95を吊り降ろして行う。 The compaction of concrete at the time of constructing the third lot 43 is performed near the sheath pipe 82 for concrete pouring and its extension (sheath pipe 82a) which is being used for concrete pouring, and the concrete pouring is performed. Two sheath tubes for vibrators 92 and their extended portions (sheath tubes 92a) located in front of the sheath tube for concrete 82 and their extended portions (sheath tube 82a), and the sheath tube for concrete pouring 82 and its extended portions (sheath). The vibrator 95 is hung on each of the two vibrator sheath tubes 92 located behind the tube 82a) and its extension (sheath tube 92a).
以上のようにして、第3ロット43の構築時のコンクリート打設作業が行われる。 As described above, the concrete placing work is performed when the third lot 43 is constructed.
次に、第3ロット43のコンクリートが硬化して強度が発現すると、図22(a)及び(b)に示すように、固定具53を取り外して、第3ロット構築用型枠70’を撤去する。 Next, when the concrete of the third lot 43 is hardened and strength is developed, the fixture 53 is removed and the third lot construction form 70' is removed as shown in FIGS. 22(a) and 22(b). To do.
尚、第2ロット42の構築時のコンクリート打設作業が完了した後の任意の時期に、コンクリート打設用シース管81の内部及びバイブレータ用シース管91の内部に、コンクリート又はモルタルを充填する。また、第3ロット43の構築時のコンクリート打設作業が完了した後の任意の時期に、コンクリート打設用シース管82及びその延長部(シース管82a)の内部と、バイブレータ用シース管92及びその延長部(シース管92a)の内部とに、コンクリート又はモルタルを充填する。 Incidentally, at an arbitrary time after the concrete placing work at the time of constructing the second lot 42 is completed, the inside of the concrete placing sheath pipe 81 and the inside of the vibrator sheath pipe 91 are filled with concrete or mortar. In addition, at any time after the concrete placing work at the time of constructing the third lot 43 is completed, the inside of the concrete placing sheath tube 82 and its extension (sheath tube 82a), the vibrator sheath tube 92, and Concrete or mortar is filled inside the extension (sheath tube 92a).
そして、底部5の構築時に、第3ロット43の下端部と底部5とが連結される。このようにして、上から下に向かって順番に第1ロット41、第2ロット42、及び、第3ロット43が構築されることにより、中仕切り壁4が構築される。 Then, when the bottom portion 5 is constructed, the lower end portion of the third lot 43 and the bottom portion 5 are connected. In this way, the first lot 41, the second lot 42, and the third lot 43 are constructed in order from the top to the bottom, so that the partition wall 4 is constructed.
次に、本実施形態におけるコンクリート躯体の構築方法の効果について、側壁3の構築方法(第2ロット32の構築方法)をその一例として挙げて、図27を用いて説明する。
図27(a)及び(b)は、従来の地下構造物1の側壁3の構築方法(第2ロット32の構築方法)を示しており、前述の図8(a)及び図9(a)に対応するものである。
Next, the effect of the method for constructing a concrete skeleton in the present embodiment will be described using the method for constructing the side wall 3 (the method for constructing the second lot 32) as an example with reference to FIG.
FIGS. 27(a) and 27(b) show a conventional method for constructing the side wall 3 of the underground structure 1 (method for constructing the second lot 32), which is shown in FIGS. 8(a) and 9(a) above. It corresponds to.
図27(a)及び(b)に示すように、従来の側壁3の構築方法では、コンクリート打設用シース管81及びバイブレータ用シース管91を用いることなく、側部型枠62の上部に、第1ロット31の下端部の側方に位置するように、前後方向に4〜5m程度の間隔で複数のホッパー(コンクリート投入口)64が設けられていた。そして、ホッパー64から、第1ロット31の下面と、山留7の露出部分の左側面と、床型枠51の上面と、側部型枠62の右側面とによって囲まれた空間内に、コンクリートを打設すると共に、ホッパー64から当該空間内にバイブレータ(図示せず)を挿入して、コンクリートの締固めを行っていた。ここで、コンクリートの充填の確認は、ホッパー64の上部までコンクリートが溢れることで行っていた。更に、ホッパー64箇所のコンクリート64aは硬化後に斫って平らにして、表面仕上げを行っていた。 As shown in FIGS. 27( a) and (b ), in the conventional method of constructing the side wall 3, without using the concrete placing sheath tube 81 and the vibrator sheath tube 91, on the upper portion of the side form 62, A plurality of hoppers (concrete input ports) 64 were provided in the front-rear direction at intervals of about 4 to 5 m so as to be located laterally to the lower end of the first lot 31. Then, from the hopper 64, in a space surrounded by the lower surface of the first lot 31, the left side surface of the exposed portion of the mountain clasp 7, the upper surface of the floor form 51, and the right side surface of the side form 62, While pouring concrete, a vibrator (not shown) was inserted from the hopper 64 into the space to compact the concrete. Here, the confirmation of the filling of the concrete was performed by overflowing the concrete to the upper part of the hopper 64. Further, the concrete 64a at 64 places of the hopper has been hardened and flattened after being hardened to finish the surface.
従来の側壁3の構築方法では、以下の問題点(1)〜(5)があった。
(1)ホッパー64の間隔が4〜5m程度であり、通常1.2m程度とされるバイブレータ間隔に対し、ホッパー64から挿入するバイブレータの間隔が空き過ぎていることから、隣り合うホッパー64同士の中間部に空洞やジャンカができやすい。それゆえ、別途、バイブレータ挿入孔の形成や型枠バイブレータの使用が必要となる。
The conventional method of constructing the side wall 3 has the following problems (1) to (5).
(1) Since the distance between the hoppers 64 is about 4 to 5 m, and the distance between the vibrators inserted from the hopper 64 is too large, the distance between the adjacent hoppers 64 is about 1.2 m. Cavities and junkers are easy to form in the middle. Therefore, it is necessary to separately form a vibrator insertion hole and use a form vibrator.
(2)第2ロット32の構築の終盤におけるホッパー64からのコンクリート投入では、コンクリートの高低差が30cm程度であり、圧力がかからないことから、コンクリートの流れが悪く、隣り合うホッパー64同士の中間部へのコンクリートの充填が難しい。この対策として、高流動コンクリートの使用が必要となることもあり、コストアップにつながる。 (2) When concrete is input from the hopper 64 in the final stage of the construction of the second lot 32, since the height difference of the concrete is about 30 cm and no pressure is applied, the concrete flow is poor and the intermediate portion between the adjacent hoppers 64 is low. It is difficult to fill the concrete with concrete. As a countermeasure against this, it may be necessary to use high-fluidity concrete, which leads to an increase in cost.
(3)ホッパー64からコンクリートを打設すると、主鉄筋及びせん断補強鉄筋を含む格子状鉄筋の外からコンクリートを打設することから、コンクリートが鉄筋にぶつかり、分離しやすく、ひいては、ジャンカができやすい。 (3) When concrete is cast from the hopper 64, the concrete is cast from the outside of the grid-shaped reinforcing bars including the main reinforcing bars and the shear reinforcing bars, so that the concrete easily hits the reinforcing bars and is easily separated, which in turn easily causes junkers. ..
(4)第2ロット32の構築の終盤においてホッパー64からコンクリートを打設すると、圧がかからない状態でのコンクリート打設となり、第1ロット31の下面との間に隙間ができやすく、コンクリートの硬化後に打継目にセメントミルクの注入が必要となることもある。 (4) When concrete is poured from the hopper 64 in the final stage of the construction of the second lot 32, the concrete is placed without applying pressure, and a gap is easily formed between the concrete and the lower surface of the first lot 31, so that the concrete is hardened. It may be necessary to inject cement milk at the joint afterwards.
(5)コンクリートの強度発現後、ホッパー64の撤去、コンクリート斫り、及び、表面仕上げの作業が必要となる。 (5) After the strength of the concrete develops, it is necessary to remove the hopper 64, scrape the concrete, and finish the surface.
この点、本実施形態における側壁3の構築方法によれば、以下の効果がある。
前記問題点(1)については、バイブレータ用シース管91が1.25m間隔で配置されることにより、1.25m間隔でバイブレータ95をかけることができるので、コンクリートの確実な締固めを実現することができる。それゆえ、別途、バイブレータ挿入孔を形成したり、型枠バイブレータを使用したりする必要がない。
In this respect, the method of constructing the side wall 3 according to this embodiment has the following effects.
Regarding the problem (1), since the vibrator sheath tubes 91 are arranged at intervals of 1.25 m, the vibrators 95 can be applied at intervals of 1.25 m, so that reliable concrete compaction is realized. You can Therefore, it is not necessary to separately form a vibrator insertion hole or use a form vibrator.
前記問題点(2)及び(4)については、コンクリート打設中の第2ロット32に関して、そのコンクリートの最上層は前述の片押し打設が行われることにより、第1ロット31の上下方向の長さ分(コンクリート打設用シース管81の上下方向の長さ分)、すなわち、3〜5m程度のコンクリート打設圧をかけながらコンクリートを打設することができ、ひいては、コンクリートの確実な打設及び充填を行うことができる。 Regarding the problems (2) and (4), regarding the second lot 32 during concrete pouring, the uppermost layer of the concrete is subjected to the above-mentioned one-sided pouring, so that the vertical direction of the first lot 31 is It is possible to pour the concrete while applying the concrete pouring pressure of the length (the vertical length of the concrete pouring sheath tube 81), that is, about 3 to 5 m, and thus the concrete pouring is surely performed. Installation and filling can be performed.
前記問題点(3)については、コンクリート打設用シース管81及びバイブレータ用シース管91をせん断補強鉄筋に重ならない位置に配置することができるので、打設コンクリートが鉄筋にぶつかって材料分離が発生することを抑制することができる。また、バイブレータがせん断補強鉄筋に絡むことも抑制することができる。 Regarding the problem (3), since the concrete placing sheath tube 81 and the vibrator sheath tube 91 can be arranged at positions not overlapping the shear reinforcing bar, the placing concrete hits the reinforcing bar and material separation occurs. Can be suppressed. Further, it is possible to prevent the vibrator from being entangled with the shear reinforcing bar.
前記問題点(5)については、コンクリート打設用シース管81及びバイブレータ用シース管91を用いることにより、ホッパー64が不要となる。それゆえ、側部型枠62をホッパー64なしの平らな形状とすることができるので、通常の金属製又は木製の平板状の型枠を使用することができる。また、ホッパー64が不要となることにより、前述のような余分なコンクリートの斫り作業や表面仕上げ作業を省略することができる。 Regarding the problem (5), the use of the concrete casting sheath pipe 81 and the vibrator sheath pipe 91 eliminates the need for the hopper 64. Therefore, since the side form 62 can be formed into a flat shape without the hopper 64, a normal metal or wooden flat form can be used. Further, since the hopper 64 is not necessary, it is possible to omit the above-mentioned extra concrete scrubbing work and surface finishing work.
尚、本実施形態には以下の効果(ア)〜(エ)がある。
(ア)床型枠51’はコンクリート打設用シース管81の下端近傍にて上に凸の形状になっており、第1ロット41の下面がその形状で仕上がるので、第2ロット42の構築時にコンクリート打設用シース管81の下端開口(コンクリートの排出口)の近傍までコンクリートを確実に充填することができる。また、床型枠51’はコンクリート打設用シース管82の延長部(シース管82a)の下端近傍にて上に凸の形状になっており、第2ロット42の下面がその形状で仕上がるので、第3ロット43の構築時にコンクリート打設用シース管82の延長部(シース管82a)の下端開口(コンクリートの排出口)の近傍までコンクリートを確実に充填することができる。
In addition, this embodiment has the following effects (a) to (d).
(A) The floor form 51' has a convex shape in the vicinity of the lower end of the sheath pipe 81 for concrete pouring, and the lower surface of the first lot 41 is finished in that shape. At some times, the concrete can be reliably filled up to the vicinity of the lower end opening (concrete discharge port) of the concrete placing sheath pipe 81. Further, the floor form 51' has a convex shape near the lower end of the extension portion (sheath pipe 82a) of the concrete casting sheath pipe 82, and the lower surface of the second lot 42 is finished in that shape. During the construction of the third lot 43, it is possible to reliably fill the concrete up to the vicinity of the lower end opening (concrete discharge port) of the extension portion (sheath tube 82a) of the concrete placing sheath tube 82.
(イ)前述のコンクリート打設用シース管81,82及びバイブレータ用シース管91,92を用いることにより、ピッチが300mm以下(ctc300以下)で配置された主鉄筋においても、鉄筋の切断、復旧の必要が無く、配筋の自由度が高くなる。 (A) By using the above-described concrete placing sheath pipes 81 and 82 and vibrator sheath pipes 91 and 92, even in the case of main reinforcing bars arranged at a pitch of 300 mm or less (ctc300 or less), cutting and restoration of the reinforcing bars can be performed. There is no need, and the degree of freedom in bar arrangement is increased.
(ウ)側部型枠52,62,72の各々の少なくとも一部を透明又は半透明なアクリル板などで構成することにより、コンクリートの打設高や締固め状況を目視しながら、コンクリートの確実な打設・締固めを行うことができる。 (C) By constructing at least a part of each of the side molds 52, 62, 72 with a transparent or semi-transparent acrylic plate or the like, it is possible to ensure the concrete while visually observing the casting height and compaction status of the concrete. Can be placed and compacted easily.
(エ)コンクリート打設作業に用いていないコンクリート打設用シース管81,82及びバイブレータ用シース管91,92を用いて、いわゆるレッドで、コンクリートの打設高や締固め状況を確認しながら、コンクリートの確実な打設・締固めを行うことができる。 (D) Using the sheath pipes 81, 82 for concrete pouring and the sheath pipes 91, 92 for vibrators that are not used for concrete pouring work, while confirming the pouring height and compaction status of concrete with so-called red, The concrete can be poured and compacted reliably.
本実施形態によれば、コンクリート躯体(側壁2,3、中仕切り壁4)の構築方法は、構築予定のコンクリート躯体(側壁2,3、中仕切り壁4)を上下方向に複数のロット(第1ロット31,41、第2ロット32,42、第3ロット33,43)に分け、上から下に向かって順番にロットごとに型枠を盛り替えてコンクリートを打設することにより(例えば、第1ロット構築用型枠50,50’の設置、第1ロット構築用型枠50,50’内へのコンクリートの打設、第1ロット構築用型枠50,50’の撤去、第2ロット構築用型枠60,60’の設置、第2ロット構築用型枠60,60’内へのコンクリートの打設、第2ロット構築用型枠60,60’の撤去、第3ロット構築用型枠70,70’の設置、第3ロット構築用型枠70,70’内へのコンクリートの打設、第3ロット構築用型枠70,70’の撤去をこの順に行うことにより)、コンクリート躯体(側壁2,3、中仕切り壁4)を構築する方法である。このコンクリート躯体(側壁2,3、中仕切り壁4)の構築方法は、上下方向に延びるコンクリート打設作業用の第1管状部材を、第1ロット構築用型枠50,50’の内面によって囲まれる空間内に配置する第1工程(図4及び図14参照)と、第1ロット構築用型枠50,50’の内面によって囲まれる空間内にコンクリートを打設することにより第1ロット31,41を構築する第2工程(図4及び図14参照)と、第1ロット構築用型枠50,50’を撤去する第3工程(図5及び図15参照)と、を含む。第1管状部材(コンクリート打設用シース管81,82、バイブレータ用シース管91,92)は、第1ロット31,41の上方と第1ロット31,41の下方とを連通する(図6及び図16参照)。これにより、第1ロット31,41の下方に隣接して構築される第2ロット32,42へのコンクリートの打設に第1管状部材(コンクリート打設用シース管81、バイブレータ用シース管91)を用いることができるので、前述のホッパー64が不要となる。それゆえ、側部型枠62をホッパー64なしの平らな形状とすることができるので、通常の平板状の型枠を使用することができる。また、ホッパー64が不要となることにより、前述のような余分なコンクリートの斫り作業や表面仕上げ作業を省略することができるので、コンクリート躯体(側壁2,3、中仕切り壁4)を効率良く構築することができる。 According to the present embodiment, the method of constructing a concrete skeleton (sidewalls 2, 3 and intermediate partition wall 4) is a method of constructing the concrete skeleton (sidewalls 2, 3 and intermediate partition wall 4) in a plurality of vertical lots (first By dividing into 1 lot 31, 41, 2nd lot 32, 42, 3rd lot 33, 43), the molds are rearranged in order from top to bottom and concrete is placed (for example, Installation of the first lot construction formwork 50, 50', placement of concrete in the first lot construction formwork 50, 50', removal of the first lot construction formwork 50, 50', second lot Installation of construction molds 60, 60', placement of concrete in the second lot construction molds 60, 60', removal of second lot construction molds 60, 60', third lot construction mold By installing the frames 70, 70', placing concrete in the third lot building form 70, 70', and removing the third lot building form 70, 70' in this order), the concrete frame This is a method of constructing (side walls 2 and 3, partition wall 4). The construction method of this concrete skeleton (side walls 2 and 3, partition wall 4) is such that the first tubular member for concrete placing work that extends in the vertical direction is surrounded by the inner surface of the first lot construction formwork 50, 50'. The first step (see FIGS. 4 and 14) of arranging the first lot 31, and the first lot 31 by placing concrete in the space surrounded by the inner surfaces of the first lot building molds 50, 50'. The second step of constructing 41 (see FIGS. 4 and 14) and the third step of removing the first lot constructing molds 50, 50' (see FIGS. 5 and 15) are included. The first tubular members (sheath pipes 81, 82 for concrete pouring, sheath pipes 91, 92 for vibrators) communicate between the upper side of the first lots 31, 41 and the lower side of the first lots 31, 41 (Fig. 6 and (See FIG. 16). As a result, the first tubular member (the sheath pipe 81 for concrete placing, the sheath pipe 91 for vibrator) is used for placing concrete in the second lots 32, 42 that are adjacently constructed below the first lots 31, 41. Can be used, the above-mentioned hopper 64 becomes unnecessary. Therefore, since the side part mold 62 can have a flat shape without the hopper 64, a normal flat plate-shaped mold can be used. Further, since the hopper 64 is not required, the above-mentioned extra concrete scrubbing work and surface finishing work can be omitted, so that the concrete skeleton (sidewalls 2, 3, the intermediate partition wall 4) can be efficiently used. Can be built.
また本実施形態によれば、前記第2工程にて第1ロット構築用型枠50,50’内にコンクリートを打設するに先立って、第1管状部材(コンクリート打設用シース管81,82、バイブレータ用シース管91,92)の下面開口を塞ぐ第1蓋部材を第1管状部材(コンクリート打設用シース管81,82、バイブレータ用シース管91,92)に取り付け、前記第3工程にて第1ロット構築用型枠50,50’を撤去した後に、前記第1蓋部材を第1管状部材(コンクリート打設用シース管81,82、バイブレータ用シース管91,92)から取り外す(図6及び図16参照)。これにより、第1ロット31,41の構築時におけるコンクリート打設作業中に第1管状部材(コンクリート打設用シース管81,82、バイブレータ用シース管91,92)の下面開口から内部にコンクリートが流入することを抑制することができる。 Further, according to the present embodiment, before the concrete is placed in the first lot construction molds 50, 50 ′ in the second step, the first tubular member (the concrete placement sheath pipes 81, 82 ). , A first lid member for closing the lower surface opening of the vibrator sheath tubes 91, 92) is attached to the first tubular member (concrete casting sheath tubes 81, 82, vibrator sheath tubes 91, 92), and the third step is performed. After removing the first lot construction molds 50, 50' by removing the first lid member, the first lid member is removed from the first tubular member (sheath pipes 81, 82 for placing concrete, sheath pipes 91, 92 for vibrator) (Fig. 6 and FIG. 16). As a result, during the concrete pouring work at the time of constructing the first lots 31, 41, concrete is introduced from the lower surface opening of the first tubular member (the sheath pipes 81, 82 for concrete pouring, the sheath pipes 91, 92 for vibrators) to the inside. Inflow can be suppressed.
また本実施形態によれば、コンクリート躯体(側壁2,3、中仕切り壁4)の構築方法は、前記第3工程にて第1ロット構築用型枠50,50’を撤去した後に、第1管状部材(コンクリート打設用シース管82、バイブレータ用シース管92)の下端部に新たな管状部材(シース管82a,92a)の上端部を連結することにより、第1管状部材(コンクリート打設用シース管82、バイブレータ用シース管92)を下方に延長する第4工程(図7及び図17参照)と、第1ロット31,41の下方に第2ロット構築用型枠60,60’を設置して、第2ロット構築用型枠60,60’の内面によって囲まれる空間内に第1管状部材の延長部(シース管82a,92a)を位置させる第5工程(図8及び図18参照)と、第2ロット構築用型枠60,60’の内面と第1ロット31,41の下面とによって囲まれる空間内にコンクリートを打設することにより第2ロット32,42を構築する第6工程(図8及び図18参照)と、第2ロット構築用型枠60,60’を撤去する第7工程(図9及び図19参照)と、を更に含む。第1管状部材(コンクリート打設用シース管82、バイブレータ用シース管92)及びその延長部(シース管82a,92a)は、第1ロット31,41の上方と第2ロット32,42の下方とを連通する(図10及び図20参照)。これにより、第2ロット32,42の下方に隣接して構築される第3ロット33,43へのコンクリートの打設に第1管状部材(コンクリート打設用シース管82、バイブレータ用シース管92)及びその延長部(シース管82a,92a)を用いることができるので、前述のホッパーが不要となる。それゆえ、側部型枠72をホッパーなしの平らな形状とすることができるので、通常の平板状の型枠を使用することができる。また、ホッパーが不要となることにより、前述のような余分なコンクリートの斫り作業や表面仕上げ作業を省略することができるので、コンクリート躯体(側壁2,3、中仕切り壁4)を効率良く構築することができる。 Further, according to the present embodiment, the method of constructing the concrete skeleton (sidewalls 2, 3, the partition wall 4) is the first method after removing the first lot construction formwork 50, 50' in the third step. By connecting the upper ends of the new tubular members (sheath pipes 82a, 92a) to the lower ends of the tubular members (the sheath pipe 82 for concrete pouring and the sheath pipe 92 for vibrators), the first tubular member (for concrete pouring) A fourth step (see FIGS. 7 and 17) of extending the sheath tube 82 and the vibrator sheath tube 92) downward, and installing the second lot construction molds 60 and 60′ below the first lots 31 and 41. Then, the fifth step of positioning the extension portion (sheath tube 82a, 92a) of the first tubular member in the space surrounded by the inner surfaces of the second lot building molds 60, 60' (see FIGS. 8 and 18). And a sixth step of constructing the second lots 32, 42 by placing concrete in a space surrounded by the inner surfaces of the second lot construction molds 60, 60' and the lower surfaces of the first lots 31, 41. (See FIGS. 8 and 18) and a seventh step (see FIGS. 9 and 19) of removing the second lot construction molds 60, 60′. The first tubular member (sheath pipe for concrete pouring 82, sheath pipe for vibrator 92) and its extension (sheath pipes 82a, 92a) are provided above the first lots 31, 41 and below the second lots 32, 42, respectively. To communicate with each other (see FIGS. 10 and 20). As a result, the first tubular member (the sheath pipe 82 for placing concrete, the sheath pipe 92 for vibrator) is used for placing concrete on the third lots 33, 43 that are adjacently constructed below the second lots 32, 42. Also, since the extension portion (sheath tubes 82a, 92a) can be used, the above-mentioned hopper is not necessary. Therefore, since the side part mold 72 can have a flat shape without a hopper, a normal flat plate-shaped mold can be used. In addition, since the hopper is not required, the above-mentioned extra concrete scrubbing work and surface finishing work can be omitted, so the concrete skeleton (sidewalls 2, 3 and partition wall 4) can be constructed efficiently. can do.
また本実施形態によれば、前記第6工程にて第2ロット構築用型枠60,60’内にコンクリートを打設するに先立って、第1管状部材の延長部(シース管82a,92a)の下面開口を塞ぐ第2蓋部材を第1管状部材の延長部(シース管82a,92a)に取り付け、前記第7工程にて第2ロット構築用型枠60,60’を撤去した後に、前記第2蓋部材を第1管状部材の延長部(シース管82a,92a)から取り外す(図10及び図20参照)。これにより、第2ロット32,42の構築時におけるコンクリート打設作業中に第1管状部材の延長部(シース管82a,92a)の下面開口から内部にコンクリートが流入することを抑制することができる。 Further, according to the present embodiment, before the concrete is placed in the second lot construction form 60, 60′ in the sixth step, the extension portion (sheath pipe 82a, 92a) of the first tubular member is formed. The second lid member that closes the lower surface opening of the first tubular member is attached to the extension portion (sheath tubes 82a, 92a) of the first tubular member, and after removing the second lot building molds 60, 60' in the seventh step, The second lid member is removed from the extension portion (sheath tubes 82a, 92a) of the first tubular member (see FIGS. 10 and 20). As a result, it is possible to suppress the inflow of concrete into the interior from the lower surface opening of the extension portion (sheath pipes 82a, 92a) of the first tubular member during the concrete placing operation during the construction of the second lots 32, 42. ..
また本実施形態によれば、コンクリート躯体(側壁2,3、中仕切り壁4)の構築方法は、前記第7工程にて第2ロット構築用型枠60,60’を撤去した後に、第2ロット32,42の下方に第3ロット構築用型枠70,70’を設置する第8工程(図11及び図21参照)と、第3ロット構築用型枠70,70’の内面と第2ロット32,42の下面とによって囲まれる空間内にコンクリートを打設することにより第3ロット33,43を構築する第9工程(図11及び図21参照)と、第3ロット構築用型枠70,70’を撤去する第10工程(図12及び図22参照)と、を更に含む。これにより、第3ロット構築用型枠70,70’内へのコンクリートの打設に第1管状部材(コンクリート打設用シース管82、バイブレータ用シース管92)及びその延長部(シース管82a,92a)を用いることができる。 Further, according to the present embodiment, the method of constructing the concrete skeleton (sidewalls 2, 3, the intermediate partition wall 4) is the second method after removing the second lot construction formwork 60, 60′ in the seventh step. The eighth step (see FIGS. 11 and 21) of installing the third lot building molds 70, 70′ below the lots 32, 42, and the inner surface and second surface of the third lot building molds 70, 70′. A ninth step (see FIGS. 11 and 21) of constructing the third lots 33, 43 by placing concrete in the space surrounded by the bottom surfaces of the lots 32, 42, and the third lot construction form 70 , 70' is removed (see FIGS. 12 and 22). As a result, the first tubular member (sheath pipe for concrete placement 82, sheath pipe for vibrator 92) and its extension (sheath pipe 82a, for placing concrete in the third lot building form 70, 70'). 92a) can be used.
また本実施形態によれば、各々が延長部(シース管82a)を有する複数の第1管状部材(コンクリート打設用シース管82)が水平一方向(前後方向)に間隔を空けて配置されており(図11及び図21参照)、前記第9工程では、1つの第1管状部材(コンクリート打設用シース管82)から第3ロット構築用型枠70,70’内にコンクリートを打設し、この打設されたコンクリートの一部が別の1つの第1管状部材の延長部(シース管82a)内に流入して前記別の1つの第1管状部材の延長部(シース管82a)内を上昇してきたことを確認した後に、前記別の1つの第1管状部材(コンクリート打設用シース管82)から第3ロット構築用型枠70,70’内にコンクリートを打設する(つまり、前述の片押し打設を行う)。これにより、第1ロット31,41及び第2ロット32,42の上下方向の長さ分(つまり、コンクリート打設用シース管82及びその延長部(シース管82a)の上下方向の長さ分)、コンクリート打設圧をかけながら、コンクリートの確実な打設及び充填を水平一方向(前後方向)に進めることができる。 Further, according to the present embodiment, a plurality of first tubular members (sheath pipes for concrete pouring 82) each having an extension portion (sheath pipe 82a) are arranged at intervals in one horizontal direction (front-back direction). 11 (see FIGS. 11 and 21), in the ninth step, concrete is poured from one first tubular member (sheath tube 82 for pouring concrete) into the third lot building forms 70, 70′. A part of the cast concrete flows into the extension (sheath tube 82a) of another one first tubular member, and the inside of the extension (sheath tube 82a) of another one first tubular member After confirming that the concrete has risen, concrete is poured into the third lot construction formwork 70, 70' from the other one first tubular member (concrete placement sheath tube 82) (that is, Do the above-mentioned one-sided driving). As a result, the vertical length of the first lot 31, 41 and the second lot 32, 42 (that is, the vertical length of the concrete placing sheath pipe 82 and its extension (sheath pipe 82a)). The concrete pouring and filling of concrete can be carried out in one horizontal direction (front-rear direction) while applying concrete pouring pressure.
また本実施形態によれば、第3ロット構築用型枠70,70’内へのコンクリートの打設が完了した後に、第1管状部材(コンクリート打設用シース管81、バイブレータ用シース管91)及びその延長部(シース管82a,92a)の内部にコンクリート又はモルタルを充填する。これにより、第1ロット31,41及び第2ロット32,42を中実構造とすることができる。 Further, according to the present embodiment, after the placement of the concrete into the third lot building molds 70, 70′ is completed, the first tubular member (the concrete placing sheath pipe 81, the vibrator sheath pipe 91). Then, concrete or mortar is filled inside the extension portion (sheath pipes 82a, 92a). Thereby, the first lots 31, 41 and the second lots 32, 42 can have a solid structure.
また本実施形態によれば、コンクリート躯体(側壁2,3、中仕切り壁4)の構築方法は、前記第3工程にて第1ロット構築用型枠50,50’を撤去した後に、第1ロット31,41の下方に第2ロット構築用型枠60,60’を設置する第4工程(図8及び図18参照)と、第2ロット構築用型枠60,60’の内面と第1ロット31,41の下面とによって囲まれる空間内にコンクリートを打設することにより第2ロット32,42を構築する第5工程(図8及び図18参照)と、第2ロット構築用型枠60,60’を撤去する第6工程(図9及び図19参照)と、を更に含む。これにより、第2ロット構築用型枠60,60’内へのコンクリートの打設に第1管状部材(コンクリート打設用シース管81、バイブレータ用シース管91)を用いることができる。 Further, according to the present embodiment, the method of constructing the concrete skeleton (sidewalls 2, 3, the partition wall 4) is the first method after removing the first lot construction formwork 50, 50' in the third step. The fourth step (see FIGS. 8 and 18) of installing the second lot building molds 60, 60′ below the lots 31, 41, and the inner surface and the first of the second lot building molds 60, 60′. A fifth step (see FIGS. 8 and 18) of constructing the second lots 32, 42 by placing concrete in the space surrounded by the lower surfaces of the lots 31, 41 (see FIGS. 8 and 18), and the second lot construction form 60. , 60' is removed (see FIGS. 9 and 19). Accordingly, the first tubular member (the sheath pipe 81 for concrete pouring, the sheath pipe 91 for vibrator) can be used for pouring concrete into the second lot building molds 60, 60'.
また本実施形態によれば、複数の第1管状部材(コンクリート打設用シース管81−1,81−2,…)が水平一方向(前後方向)に間隔を空けて配置されており(図25及び図26参照)、前記第5工程では、1つの第1管状部材(コンクリート打設用シース管81−1)から第2ロット構築用型枠60,60’内にコンクリートを打設し(図25(a)〜(c)参照)、この打設されたコンクリートの一部が別の1つの第1管状部材(コンクリート打設用シース管81−2)内に流入して前記別の1つの第1管状部材(コンクリート打設用シース管81−2)内を上昇してきたこと(図25(c)参照)を確認した後に、前記別の1つの第1管状部材(コンクリート打設用シース管81−2)から第2ロット構築用型枠60,60’内にコンクリートを打設する(図26(a)及び(b)参照)。これにより、第1ロット31,41の長さ分(つまり、コンクリート打設用シース管81の上下方向の長さ分)、コンクリート打設圧をかけながら、コンクリートの確実な打設及び充填を水平一方向(前後方向)に進めることができる。 Further, according to this embodiment, a plurality of first tubular members (sheath pipes 81-1 for the concrete pouring, 81-2,...) Are arranged at intervals in one horizontal direction (front-back direction) (see FIG. 25 and FIG. 26), in the fifth step, concrete is poured from one first tubular member (sheath pipe 81-1 for concrete pouring) into the second lot building molds 60, 60′ ( 25(a) to (c)), a part of the cast concrete flows into another one of the first tubular members (the sheath pipe 81-2 for placing concrete) and the other one After confirming that the two first tubular members (sheath pipes 81-2 for concrete pouring) have risen (see FIG. 25(c)), the other one first tubular member (sheath for concrete pouring) Concrete is poured from the pipe 81-2) into the second lot building molds 60, 60′ (see FIGS. 26A and 26B). As a result, the concrete pouring and filling can be performed horizontally while the concrete pouring pressure is applied by the length of the first lot 31, 41 (that is, the vertical length of the sheath pipe 81 for concrete pouring). You can proceed in one direction (front-back direction).
また本実施形態によれば、第2ロット構築用型枠60,60’内へのコンクリートの打設が完了した後に、第1管状部材(コンクリート打設用シース管81、バイブレータ用シース管91)の内部にコンクリート又はモルタルを充填する。これにより、第1ロット31,41を中実構造とすることができる。 Further, according to this embodiment, the first tubular member (the sheath pipe 81 for placing concrete, the sheath pipe 91 for vibrator) after the placement of the concrete into the second lot building molds 60, 60′ is completed. Fill the inside of with concrete or mortar. As a result, the first lots 31, 41 can have a solid structure.
また本実施形態によれば、第1管状部材(コンクリート打設用シース管81,82)の内部をコンクリートが流通可能である(図23参照)。これにより、第2ロット構築用型枠60,60’内へのコンクリートの供給をコンクリート打設用シース管81を用いて行うことができ、また、第3ロット構築用型枠70,70’内へのコンクリートの供給をコンクリート打設用シース管82を用いて行うことができる。 Further, according to this embodiment, concrete can flow through the inside of the first tubular member (the sheath pipes 81 and 82 for concrete pouring) (see FIG. 23 ). Thereby, the concrete can be supplied into the second lot building molds 60 and 60′ by using the concrete placing sheath tube 81, and the third lot building molds 70 and 70′ can be supplied. The concrete can be supplied to the concrete using the sheath pipe 82 for concrete pouring.
また本実施形態によれば、コンクリートを締固めるためのバイブレータ95を第1管状部材(バイブレータ用シース管91,92)に挿入可能である(図24参照)。これにより、バイブレータ用シース管91にバイブレータ95に挿入して、第2ロット構築用型枠60,60’内のコンクリートの締固めを行うことができ、また、バイブレータ用シース管92にバイブレータ95に挿入して、第3ロット構築用型枠70,70’内のコンクリートの締固めを行うことができる。 Further, according to this embodiment, the vibrator 95 for compacting concrete can be inserted into the first tubular member (vibrator sheath tubes 91, 92) (see FIG. 24 ). As a result, by inserting the vibrator sheath tube 91 into the vibrator 95, the concrete in the second lot building molds 60, 60′ can be compacted, and the vibrator sheath tube 92 can be connected to the vibrator 95. Insertion can be performed to compact the concrete in the third lot building form 70, 70'.
また本実施形態によれば、第1ロット31,41を構築するに先立って、各ロットを支持するための支持杭12,13を地盤に設置する(図3及び図13参照)。これにより、支持杭12,13は、コンクリート躯体(側壁2,3、中仕切り壁4)の構築後には、当該コンクリート躯体を支持する支持杭として機能し得る。 According to this embodiment, the support piles 12 and 13 for supporting each lot are installed on the ground before constructing the first lots 31 and 41 (see FIGS. 3 and 13). Accordingly, the support piles 12 and 13 can function as support piles that support the concrete skeletons after the construction of the concrete skeletons (side walls 2 and 3, the partition wall 4).
また本実施形態によれば、第1ロット構築用型枠50,50’の設置に先立って、地盤11aの掘削が行われる(図3及び図13参照)。また、第1ロット31,41の構築後(第1ロット構築用型枠50,50’の撤去後)であって、かつ、第2ロット構築用型枠60,60’の設置に先立って、地盤11aの掘削が行われる(図6及び図16参照)。また、第2ロット32,42の構築後(第2ロット構築用型枠60,60’の撤去後)であって、かつ、第3ロット構築用型枠70,70’の設置に先立って、地盤11aの掘削が行われる(図10及び図20参照)。それゆえ、コンクリート躯体(側壁2,3、中仕切り壁4)の全体をカバーするような地盤の掘削を行ったあとに順巻き工法でコンクリート躯体(側壁2,3、中仕切り壁4)を構築するのに比べて短期間でコンクリート躯体(側壁2,3、中仕切り壁4)を構築することができる。 Further, according to the present embodiment, the ground 11a is excavated prior to the installation of the first lot construction molds 50, 50' (see FIGS. 3 and 13). Further, after the first lots 31 and 41 are constructed (after the first lot construction molds 50 and 50′ are removed), and prior to the installation of the second lot construction molds 60 and 60′, The ground 11a is excavated (see FIGS. 6 and 16). Further, after the second lots 32, 42 are constructed (after the second lot construction forms 60, 60′ are removed), and prior to the installation of the third lot construction forms 70, 70′, The ground 11a is excavated (see FIGS. 10 and 20). Therefore, after excavating the ground to cover the entire concrete frame (side walls 2 and 3, partition wall 4), the concrete frame (side walls 2 and 3 and partition wall 4) is constructed by the normal winding method. It is possible to construct the concrete skeleton (side walls 2 and 3, the partition wall 4) in a short period of time compared to the above.
次に、本発明の第2実施形態における側壁3及び中仕切り壁4の構築方法について、図28〜図31を用いて説明する。
図28及び図29は、本実施形態における側壁3の構築方法を示す図であり、前述の図4及び図8に対応するものである。図30及び図31は、本実施形態における仕切り壁4の構築方法を示す図であり、前述の図14及び図18に対応するものである。
前述の第1実施形態と異なる点について説明する。
Next, a method for constructing the side wall 3 and the partition wall 4 according to the second embodiment of the present invention will be described with reference to FIGS. 28 to 31.
28 and 29 are diagrams showing a method of constructing the side wall 3 in the present embodiment, and correspond to FIGS. 4 and 8 described above. 30 and 31 are diagrams showing a method of constructing the partition wall 4 in the present embodiment, and correspond to FIGS. 14 and 18 described above.
Differences from the above-described first embodiment will be described.
図28に示すように、床型枠51には複数の貫通孔55が形成されており、コンクリート打設用シース管81,82と、バイブレータ用シース管91,92とについては、各々の下端部が、床型枠51の貫通孔55を貫通している。この状態で、第1ロット構築用型枠50内にコンクリートが打設される。尚、各貫通孔55の内周面とコンクリート打設用シース管81,82及びバイブレータ用シース管91,92の各々の外周面との間には、コンクリートの漏洩を抑制するためのシール材(図示せず)が介装されている。 As shown in FIG. 28, a plurality of through holes 55 are formed in the floor formwork 51, and the lower ends of the sheath pipes 81, 82 for concrete pouring and the sheath pipes 91, 92 for vibrators are respectively formed. Through the through hole 55 of the floor form 51. In this state, concrete is placed in the first lot construction mold 50. In addition, between the inner peripheral surface of each through hole 55 and the outer peripheral surface of each of the sheath pipes 81, 82 for concrete pouring and the sheath pipes 91, 92 for vibrators, a sealing material for suppressing the leakage of concrete ( (Not shown) is interposed.
図29に示すように、コンクリート打設用シース管82の延長部(シース管82a)と、バイブレータ用シース管92の延長部(シース管92a)とについては、各々の下端部が、床型枠51の貫通孔55を貫通している。この状態で、第2ロット構築用型枠60内にコンクリートが打設される。尚、各貫通孔55の内周面とシース管82a,92aの各々の外周面との間には、コンクリートの漏洩を抑制するためのシール材(図示せず)が介装されている。 As shown in FIG. 29, the lower end of each of the extension portion (sheath tube 82a) of the concrete placing sheath tube 82 and the extension portion (sheath tube 92a) of the vibrator sheath tube 92 has a floor formwork. The through hole 55 of 51 is penetrated. In this state, concrete is placed in the second lot construction mold 60. A sealant (not shown) is interposed between the inner peripheral surface of each through hole 55 and the outer peripheral surface of each of the sheath tubes 82a and 92a to prevent concrete from leaking.
図30に示すように、床型枠51’には複数の貫通孔55’が形成されており、コンクリート打設用シース管81,82と、バイブレータ用シース管91,92とについては、各々の下端部が、床型枠51’の貫通孔55’を貫通している。この状態で、第1ロット構築用型枠50’内にコンクリートが打設される。尚、各貫通孔55’の内周面とコンクリート打設用シース管81,82及びバイブレータ用シース管91,92の各々の外周面との間には、コンクリートの漏洩を抑制するためのシール材(図示せず)が介装されている。 As shown in FIG. 30, a plurality of through holes 55' are formed in the floor form 51', and the concrete placing sheath pipes 81, 82 and the vibrator sheath pipes 91, 92 are respectively provided. The lower end portion penetrates the through hole 55′ of the floor form 51′. In this state, concrete is placed in the first lot construction form 50'. In addition, a sealing material for suppressing the leakage of concrete is provided between the inner peripheral surface of each through hole 55′ and the outer peripheral surface of each of the sheath pipes 81, 82 for concrete pouring and the sheath pipes 91, 92 for vibrators. (Not shown) is interposed.
図31に示すように、コンクリート打設用シース管82の延長部(シース管82a)と、バイブレータ用シース管92の延長部(シース管92a)とについては、各々の下端部が、床型枠51’の貫通孔55’を貫通している。この状態で、第2ロット構築用型枠60’内にコンクリートが打設される。尚、各貫通孔55’の内周面とシース管82a,92aの各々の外周面との間には、コンクリートの漏洩を抑制するためのシール材(図示せず)が介装されている。 As shown in FIG. 31, with respect to the extension portion of the sheath pipe 82 for concrete pouring (sheath pipe 82a) and the extension portion of the sheath pipe 92 for vibrator (sheath pipe 92a), the lower end of each is the floor formwork. It passes through the through hole 55' of 51'. In this state, concrete is poured into the second lot construction mold 60'. A sealant (not shown) is interposed between the inner peripheral surface of each through hole 55' and the outer peripheral surface of each of the sheath tubes 82a and 92a to prevent concrete from leaking.
特に本実施形態によれば、第1ロット構築用型枠50,50’を構成する床型枠51,51’には貫通孔55,55’が形成されており、前記第1工程では、第1管状部材(コンクリート打設用シース管81,82、バイブレータ用シース管91,92)の下端部が第1ロット構築用型枠50,50’の床型枠51,51’の貫通孔55,55’を貫通する。これにより、前述の第1蓋部材が不要となるので、コンクリート躯体(側壁2,3、中仕切り壁4)を効率良く構築することができる。 Particularly, according to the present embodiment, the through-holes 55, 55' are formed in the floor formwork 51, 51' constituting the first lot-building formwork 50, 50', and in the first step, The lower end of one tubular member (sheath pipes 81, 82 for concrete pouring, sheath pipes 91, 92 for vibrators) has through holes 55 in the floor molds 51, 51' of the first lot building molds 50, 50'. Go through 55'. This eliminates the need for the above-mentioned first lid member, so that the concrete skeleton (side walls 2 and 3, the partition wall 4) can be efficiently constructed.
また本実施形態によれば、第2ロット構築用型枠60,60’を構成する床型枠51,51’には貫通孔55,55’が形成されており、前記第5工程では、第1管状部材の延長部(シース管82a,92a)の下端部が第2ロット構築用型枠60,60’の床型枠51,51’の貫通孔55,55’を貫通する。これにより、前述の第2蓋部材が不要となるので、コンクリート躯体(側壁2,3、中仕切り壁4)を効率良く構築することができる。 Further, according to the present embodiment, through-holes 55, 55' are formed in the floor formwork 51, 51' constituting the second lot construction formwork 60, 60', and in the fifth step, The lower end portion of the extension portion (sheath pipes 82a, 92a) of the one tubular member penetrates through holes 55, 55' of the floor molds 51, 51' of the second lot building molds 60, 60'. This eliminates the need for the second lid member described above, so that the concrete skeleton (side walls 2 and 3, the partition wall 4) can be efficiently constructed.
尚、前述の第1及び第2実施形態では、中仕切り壁4の構築に用いられる床型枠51’の最上部(頂部51a’の先端部)を、上に凸の線形(前後方向に直線状に延びる形状)としたが、コンクリート打設用シース管81の下端や、コンクリート打設用シース管82の延長部(シース管82a)の下端が当該最上部に隣接して対向する限りにおいて、床型枠51’の最上部の形状はこれに限らず、例えば、当該最上部の形状が、円錐形状の頂点に対応する点状であってもよい。 In addition, in the above-mentioned 1st and 2nd embodiment, the uppermost part of the floor formwork 51' used for the construction of the partition wall 4 (the tip part of the top part 51a') is linearly convex upward (straight in the front-back direction). However, as long as the lower end of the sheath pipe 81 for concrete pouring and the lower end of the extension part (sheath pipe 82a) of the sheath pipe 82 for concrete pouring are adjacent to and oppose the uppermost part, The shape of the uppermost portion of the floor form 51' is not limited to this, and for example, the shape of the uppermost portion may be a dot shape corresponding to the apex of the conical shape.
また、前述の第1及び第2実施形態では、コンクリート打設配管85が鋼管である例を示したが、コンクリート打設配管85の構成はこれに限らず、例えば、コンクリート打設配管85がゴムホースであってもよい。また、コンクリート打設配管85の上端部にホッパーを付けてコンクリートの打設を行ってもよい。 Further, in the above-described first and second embodiments, an example in which the concrete placing pipe 85 is a steel pipe is shown, but the configuration of the concrete placing pipe 85 is not limited to this, and for example, the concrete placing pipe 85 is a rubber hose. May be Further, concrete may be poured by attaching a hopper to the upper end of the concrete pouring pipe 85.
また、前述の第1及び第2実施形態では、コンクリート打設配管85をコンクリート打設用シース管81,82内に挿入してコンクリートを打設する例を示したが、この他、コンクリート打設配管85をコンクリート打設用シース管81,82内に挿入することなく、コンクリート打設用シース管81,82自体をコンクリート打設配管として使用してもよい。つまり、コンクリート打設用シース管81,82の内面にコンクリートが接触しつつ流通するようにしてもよい。 In addition, in the above-described first and second embodiments, an example in which the concrete pouring pipe 85 is inserted into the concrete pouring sheath pipes 81 and 82 to pour concrete is shown. The concrete pouring sheath pipes 81 and 82 themselves may be used as concrete pouring pipes without inserting the pipe 85 into the concrete pouring sheath pipes 81 and 82. That is, the concrete may flow while contacting the inner surfaces of the concrete placing sheath pipes 81 and 82.
また、前述の第1及び第2実施形態では、前述の片押し打設に用いられるコンクリートとして、スランプが12cm以下である普通のコンクリートを使用することができる。この点、前述の片押し打設に用いられるコンクリートとして高流動コンクリートを使用して、コンクリート打設用シース管81,82内(及びシース管82a内)にコンクリートを満たすことで、更に高圧でのコンクリート打設が可能となり、充填性を増すことができる。 In addition, in the above-described first and second embodiments, as the concrete used for the above-mentioned one-sided pressing, ordinary concrete having a slump of 12 cm or less can be used. In this respect, by using high-fluidity concrete as the concrete used for the above-mentioned one-sided pouring, and filling the concrete in the concrete pouring sheath pipes 81, 82 (and in the sheath pipe 82a), it is possible to further increase the pressure. It is possible to place concrete and increase the filling property.
また、前述の第1及び第2実施形態では、バイブレータ用シース管91,92の各々について、平面視で1列に配置する例を示したが、側壁2,3及び中仕切り壁4の厚さ(左右方向の長さ)が1.5m以上である場合には、バイブレータ用シース管91,92の各々について、平面視で2列に配置してもよく、又は、いわゆる千鳥配置としてもよい。 Further, in the above-described first and second embodiments, an example in which each of the vibrator sheath tubes 91, 92 is arranged in one row in a plan view is shown, but the thickness of the side walls 2, 3 and the partition wall 4 is shown. When (length in the left-right direction) is 1.5 m or more, each of the vibrator sheath tubes 91 and 92 may be arranged in two rows in a plan view, or may be so-called staggered arrangement.
また、前述の第1及び第2実施形態では、構築予定のコンクリート躯体(側壁2,3及び中仕切り壁4)を上下方向に3つのロットに分けているが、この他、2つのロットに分けてもよく、又は、4つ以上の任意の個数のロットに分けてもよい。ロット数の増減に応じて、コンクリート打設用シース管及びバイブレータ用シース管の本数が増減し得る。例えば、4つのロットに分ける場合には、前述の第3ロット33,43の下方に隣接して第4ロットが構築される。この場合には、第4ロットの構築のための、コンクリート打設用シース管とバイブレータ用シース管とを新たに第1ロット31の構築時に設置し、第2ロット32及び第3ロット33の構築時に、当該コンクリート打設用シース管とバイブレータ用シース管との各々について、新たなシース管を前述のように下方に継ぎ足して延長すればよい。 Further, in the above-described first and second embodiments, the concrete skeleton (sidewalls 2 and 3 and the partition wall 4) to be constructed is divided into three lots in the vertical direction, but in addition, it is divided into two lots. Alternatively, it may be divided into any number of lots of four or more. The number of sheath pipes for concrete placing and sheath pipes for vibrators may increase or decrease according to the increase or decrease in the number of lots. For example, when dividing into four lots, a fourth lot is constructed below and adjacent to the third lots 33 and 43. In this case, a sheath pipe for placing concrete and a sheath pipe for vibrator for constructing the fourth lot are newly installed at the time of constructing the first lot 31, and the second lot 32 and the third lot 33 are constructed. At this time, for each of the concrete placing sheath pipe and the vibrator sheath pipe, a new sheath pipe may be added downward to extend as described above.
また、前述の第1及び第2実施形態では、本発明に係るコンクリート躯体の構築方法を地下構造物1の側壁2,3及び中仕切り壁4に適用した例を説明したが、本発明に係るコンクリート躯体の構築方法の適用例はこれに限らない。例えば立坑や地下タンクなどの円筒形地下構造物の側壁(側壁コンクリート)の構築に、本発明に係るコンクリート躯体の構築方法を適用してもよいことはいうまでもない。 Moreover, in the above-mentioned 1st and 2nd embodiment, although the example which applied the construction method of the concrete skeleton which concerns on this invention to the side walls 2 and 3 and the partition wall 4 of the underground structure 1, it demonstrated. The application example of the concrete skeleton construction method is not limited to this. It goes without saying that the method of constructing a concrete skeleton according to the present invention may be applied to the construction of a side wall (side wall concrete) of a cylindrical underground structure such as a shaft or an underground tank.
また、前述の第1及び第2実施形態では、本発明に係るコンクリート躯体の構築方法を、側壁2,3及び中仕切り壁4などの壁状のコンクリート躯体の構築に適用したが、この他、柱状のコンクリート躯体に適用してもよいことは明らかである。 Moreover, in the above-mentioned 1st and 2nd embodiment, although the construction method of the concrete skeleton which concerns on this invention was applied to the construction of wall-shaped concrete skeletons, such as the side walls 2 and 3, and the partition wall 4, in addition to this, Obviously, it may be applied to a columnar concrete skeleton.
また、図示の実施形態はあくまで本発明を例示するものであり、本発明は、説明した実施形態により直接的に示されるものに加え、特許請求の範囲内で当業者によりなされる各種の改良・変更を包含するものであることは言うまでもない。
尚、出願当初の請求項は以下の通りであった。
[請求項1]
構築予定のコンクリート躯体を上下方向に複数のロットに分け、上から下に向かって順番にロットごとに型枠を盛り替えてコンクリートを打設することにより、コンクリート躯体を構築する方法であって、
上下方向に延びるコンクリート打設作業用の第1管状部材を、第1ロット構築用型枠の内面によって囲まれる空間内に配置する第1工程と、
前記第1ロット構築用型枠の内面によって囲まれる空間内にコンクリートを打設することにより第1ロットを構築する第2工程と、
前記第1ロット構築用型枠を撤去する第3工程と、
を含み、
前記第1管状部材は、前記第1ロットの上方と前記第1ロットの下方とを連通する、コンクリート躯体の構築方法。
[請求項2]
前記第2工程にて前記第1ロット構築用型枠内にコンクリートを打設するに先立って、前記第1管状部材の下面開口を塞ぐ第1蓋部材を前記第1管状部材に取り付け、
前記第3工程にて前記第1ロット構築用型枠を撤去した後に、前記第1蓋部材を前記第1管状部材から取り外す、請求項1に記載のコンクリート躯体の構築方法。
[請求項3]
前記第1ロット構築用型枠を構成する床型枠には貫通孔が形成されており、
前記第1工程では、第1管状部材の下端部が前記第1ロット構築用型枠の床型枠の貫通孔を貫通する、請求項1に記載のコンクリート躯体の構築方法。
[請求項4]
前記第3工程にて前記第1ロット構築用型枠を撤去した後に、前記第1管状部材の下端部に新たな管状部材の上端部を連結することにより、前記第1管状部材を下方に延長する第4工程と、
前記第1ロットの下方に第2ロット構築用型枠を設置して、第2ロット構築用型枠の内面によって囲まれる空間内に前記第1管状部材の延長部を位置させる第5工程と、
前記第2ロット構築用型枠の内面と前記第1ロットの下面とによって囲まれる空間内にコンクリートを打設することにより第2ロットを構築する第6工程と、
前記第2ロット構築用型枠を撤去する第7工程と、
を更に含み、
前記第1管状部材及びその延長部は、前記第1ロットの上方と前記第2ロットの下方とを連通する、請求項1〜請求項3のいずれか1つに記載のコンクリート躯体の構築方法。
[請求項5]
前記第6工程にて前記第2ロット構築用型枠内にコンクリートを打設するに先立って、前記第1管状部材の延長部の下面開口を塞ぐ第2蓋部材を前記第1管状部材の延長部に取り付け、
前記第7工程にて前記第2ロット構築用型枠を撤去した後に、前記第2蓋部材を前記第1管状部材の延長部から取り外す、請求項4に記載のコンクリート躯体の構築方法。
[請求項6]
前記第2ロット構築用型枠を構成する床型枠には貫通孔が形成されており、
前記第5工程では、第1管状部材の延長部の下端部が前記第2ロット構築用型枠の床型枠の貫通孔を貫通する、請求項4に記載のコンクリート躯体の構築方法。
[請求項7]
前記第7工程にて前記第2ロット構築用型枠を撤去した後に、前記第2ロットの下方に第3ロット構築用型枠を設置する第8工程と、
前記第3ロット構築用型枠の内面と前記第2ロットの下面とによって囲まれる空間内にコンクリートを打設することにより第3ロットを構築する第9工程と、
前記第3ロット構築用型枠を撤去する第10工程と、
を更に含む、請求項4〜請求項6のいずれか1つに記載のコンクリート躯体の構築方法。
[請求項8]
各々が前記延長部を有する複数の前記第1管状部材が水平一方向に間隔を空けて配置されており、
前記第9工程では、1つの前記第1管状部材から前記第3ロット構築用型枠内にコンクリートを打設し、この打設されたコンクリートの一部が別の1つの前記第1管状部材の前記延長部内に流入して前記別の1つの前記第1管状部材の前記延長部内を上昇してきたことを確認した後に、前記別の1つの前記第1管状部材から前記第3ロット構築用型枠内にコンクリートを打設する、請求項7に記載のコンクリート躯体の構築方法。
[請求項9]
前記第3ロット構築用型枠内へのコンクリートの打設が完了した後に、前記第1管状部材及びその前記延長部の内部にコンクリート又はモルタルを充填する、請求項7又は請求項8に記載のコンクリート躯体の構築方法。
[請求項10]
前記第3工程にて前記第1ロット構築用型枠を撤去した後に、前記第1ロットの下方に第2ロット構築用型枠を設置する第4工程と、
前記第2ロット構築用型枠の内面と前記第1ロットの下面とによって囲まれる空間内にコンクリートを打設することにより第2ロットを構築する第5工程と、
前記第2ロット構築用型枠を撤去する第6工程と、
を更に含む、請求項1〜請求項3のいずれか1つに記載のコンクリート躯体の構築方法。
[請求項11]
複数の前記第1管状部材が水平一方向に間隔を空けて配置されており、
前記第5工程では、1つの前記第1管状部材から前記第2ロット構築用型枠内にコンクリートを打設し、この打設されたコンクリートの一部が別の1つの前記第1管状部材内に流入して前記別の1つの前記第1管状部材内を上昇してきたことを確認した後に、前記別の1つの前記第1管状部材から前記第2ロット構築用型枠内にコンクリートを打設する、請求項10に記載のコンクリート躯体の構築方法。
[請求項12]
前記第2ロット構築用型枠内へのコンクリートの打設が完了した後に、前記第1管状部材の内部にコンクリート又はモルタルを充填する、請求項10又は請求項11に記載のコンクリート躯体の構築方法。
[請求項13]
前記第1管状部材の内部をコンクリートが流通可能である、請求項1〜請求項12のいずれか1つに記載のコンクリート躯体の構築方法。
[請求項14]
コンクリートを締固めるためのバイブレータを前記第1管状部材に挿入可能である、請求項1〜請求項7及び請求項10のいずれか1つに記載のコンクリート躯体の構築方法。
[請求項15]
前記第1ロットを構築するに先立って、各ロットを支持するための支持杭を地盤に設置する、請求項1〜請求項14のいずれか1つに記載のコンクリート躯体の構築方法。
Further, the illustrated embodiment is merely an example of the present invention, and the present invention is not limited to what is directly shown by the described embodiment, and various improvements made by those skilled in the art within the scope of the claims. It goes without saying that it includes changes.
The claims at the beginning of the application were as follows.
[Claim 1]
A method of constructing a concrete skeleton by dividing the concrete skeleton to be constructed into a plurality of lots in the vertical direction and placing the concrete by rearranging the formwork for each lot in order from top to bottom,
A first step of disposing a first tubular member extending in the vertical direction for concrete placing work in a space surrounded by the inner surface of the first lot-building formwork;
A second step of constructing the first lot by placing concrete in a space surrounded by the inner surface of the first lot construction formwork;
A third step of removing the first lot construction formwork,
Including
The said 1st tubular member is a construction method of a concrete skeleton which connects the upper part of said 1st lot, and the lower part of said 1st lot.
[Claim 2]
Prior to placing concrete in the first lot building mold in the second step, a first lid member for closing the lower surface opening of the first tubular member is attached to the first tubular member,
The method for constructing a concrete skeleton according to claim 1, wherein the first lid member is removed from the first tubular member after removing the first lot construction mold in the third step.
[Claim 3]
Through-holes are formed in the floor formwork forming the first lot construction formwork,
The method for constructing a concrete skeleton according to claim 1, wherein in the first step, a lower end portion of the first tubular member penetrates a through hole of a floor formwork of the first lot construction formwork.
[Claim 4]
The first tubular member is extended downward by connecting the upper end of a new tubular member to the lower end of the first tubular member after removing the first lot construction mold in the third step. A fourth step of
A fifth step of installing a second lot building mold below the first lot, and positioning an extension of the first tubular member in a space surrounded by an inner surface of the second lot building mold;
A sixth step of constructing a second lot by placing concrete in a space surrounded by the inner surface of the second lot construction mold and the lower surface of the first lot;
A seventh step of removing the second lot construction formwork,
Further including,
The said 1st tubular member and its extension part connect the upper part of the said 1st lot, and the lower part of the said 2nd lot, The construction method of the concrete skeleton according to any one of claims 1 to 3.
[Claim 5]
Prior to placing concrete in the second lot building mold in the sixth step, a second lid member for closing the lower surface opening of the extension portion of the first tubular member is extended to the first tubular member. Attached to the section,
The method for constructing a concrete skeleton according to claim 4, wherein the second lid member is removed from an extension portion of the first tubular member after removing the second lot construction mold in the seventh step.
[Claim 6]
Through-holes are formed in the floor formwork forming the second lot construction formwork,
The method for constructing a concrete skeleton according to claim 4, wherein in the fifth step, a lower end portion of the extension portion of the first tubular member penetrates a through hole of the floor formwork of the second lot construction formwork.
[Claim 7]
An eighth step of installing a third lot building mold below the second lot after removing the second lot building mold in the seventh step;
A ninth step of constructing a third lot by placing concrete in a space surrounded by the inner surface of the third lot construction mold and the lower surface of the second lot;
A tenth step of removing the third lot construction formwork,
The method for constructing a concrete skeleton according to any one of claims 4 to 6, further comprising:
[Claim 8]
A plurality of the first tubular members each having the extension are horizontally spaced apart in one direction,
In the ninth step, concrete is poured from one of the first tubular members into the third lot-building formwork, and a part of the cast concrete is another one of the first tubular members. After confirming that it has flowed into the extension part and has risen in the extension part of the another one of the first tubular members, the third lot-building formwork is started from the another one of the first tubular members. The method for constructing a concrete skeleton according to claim 7, wherein concrete is placed inside.
[Claim 9]
The concrete or mortar is filled into the inside of the first tubular member and the extension thereof after the placement of the concrete into the third lot building mold is completed. Construction method of concrete frame.
[Claim 10]
A fourth step of installing a second lot construction mold below the first lot after removing the first lot construction mold in the third step;
A fifth step of constructing a second lot by placing concrete in a space surrounded by the inner surface of the second lot construction mold and the lower surface of the first lot;
A sixth step of removing the second lot construction formwork,
The method for constructing a concrete skeleton according to any one of claims 1 to 3, further comprising:
[Claim 11]
A plurality of the first tubular members are arranged at intervals in one horizontal direction,
In the fifth step, concrete is poured from one of the first tubular members into the second lot-building formwork, and a part of the cast concrete is placed in another one of the first tubular members. After confirming that it has flowed into the other one of the first tubular members and has risen therein, concrete is poured from the another one of the first tubular members into the second lot construction formwork. The method for constructing a concrete skeleton according to claim 10.
[Claim 12]
The method for constructing a concrete skeleton according to claim 10 or 11, wherein concrete or mortar is filled inside the first tubular member after the placement of concrete into the second lot construction formwork is completed. ..
[Claim 13]
The method for constructing a concrete skeleton according to any one of claims 1 to 12, wherein concrete can flow inside the first tubular member.
[Claim 14]
The method for constructing a concrete skeleton according to any one of claims 1 to 7 and 10, wherein a vibrator for compacting concrete can be inserted into the first tubular member.
[Claim 15]
The method for constructing a concrete skeleton according to any one of claims 1 to 14, wherein a support pile for supporting each lot is installed on the ground prior to constructing the first lot.
1 地下構造物
2,3 側壁
4 中仕切り壁
5 底部
6,7 山留
8,9 空間
10 地面
11,11a 地盤
12,13 支持杭
14,14a,14b 吊り鋼材
31 第1ロット
32 第2ロット
33 第3ロット
41 第1ロット
42 第2ロット
43 第3ロット
50,50’ 第1ロット構築用型枠
51,51’ 床型枠
51a’ 頂部
52 側部型枠
53 固定具
55,55’ 貫通孔
60,60’ 第2ロット構築用型枠
62 側部型枠
64 ホッパー
64a コンクリート
70,70’ 第3ロット構築用型枠
72 側部型枠
81,81−1,81−2,81−3,82 コンクリート打設用シース管
82a シース管
85 コンクリート打設配管
91,92 バイブレータ用シース管
92a シース管
95 バイブレータ
1 Underground structure 2,3 Side wall 4 Partition wall 5 Bottom 6,7 Yamadome 8,9 Space 10 Ground 11, 11a Ground 12, 13 Support pile 14, 14a, 14b Suspended steel material 31 1st lot 32 2nd lot 33 Third lot 41 First lot 42 Second lot 43 Third lot 50, 50' First lot construction form 51, 51' Floor form 51a' Top 52 Side form 53 Fixture 55, 55' Through hole 60,60' 2nd lot construction formwork 62 side part formwork 64 hopper 64a concrete 70,70' 3rd lot construction formwork 72 side part formwork 81,81-1,81-2,81-3, 82 sheath pipe for concrete pouring 82a sheath pipe 85 concrete pouring pipes 91, 92 sheath pipe for vibrator 92a sheath pipe 95 vibrator
Claims (15)
上下方向に延びるコンクリート打設作業用の第1管状部材を、第1ロット構築用型枠の内面によって囲まれる空間内に配置する第1工程と、
前記第1ロット構築用型枠の内面によって囲まれる空間内にコンクリートを打設することにより第1ロットを構築する第2工程と、
前記第1ロット構築用型枠を撤去する第3工程と、
を含み、
前記第1管状部材は、前記第1ロットの上方と前記第1ロットの下方とを連通する、コンクリート躯体の構築方法において、
前記第2工程にて前記第1ロット構築用型枠内にコンクリートを打設するに先立って、前記第1管状部材の下面開口を塞ぐキャップである第1蓋部材を前記第1管状部材に取り付け、
前記第3工程にて前記第1ロット構築用型枠を撤去した後に、前記第1蓋部材を前記第1管状部材から取り外す、コンクリート躯体の構築方法。 A method of constructing a concrete skeleton by dividing the concrete skeleton to be constructed into a plurality of lots in the vertical direction and placing the concrete by rearranging the formwork for each lot in order from top to bottom,
A first step of disposing a first tubular member extending in the vertical direction for concrete placing work in a space surrounded by the inner surface of the first lot-building formwork;
A second step of constructing the first lot by placing concrete in a space surrounded by the inner surface of the first lot constructing mold;
A third step of removing the first lot construction formwork,
Including
In the method for constructing a concrete skeleton, the first tubular member connects the upper side of the first lot and the lower side of the first lot ,
Prior to placing concrete in the first lot construction mold in the second step, a first lid member, which is a cap that closes the lower surface opening of the first tubular member, is attached to the first tubular member. ,
The method for constructing a concrete skeleton, wherein the first lid member is removed from the first tubular member after removing the first lot construction mold in the third step .
上下方向に延びるコンクリート打設作業用の第1管状部材を、第1ロット構築用型枠の内面によって囲まれる空間内に配置する第1工程と、
前記第1ロット構築用型枠の内面によって囲まれる空間内にコンクリートを打設することにより第1ロットを構築する第2工程と、
前記第1ロット構築用型枠を撤去する第3工程と、
を含み、
前記第1管状部材は、前記第1ロットの上方と前記第1ロットの下方とを連通する、コンクリート躯体の構築方法において、
前記第1ロット構築用型枠を構成する床型枠には貫通孔が形成されており、
前記第1工程では、前記第1管状部材の下端部が前記第1ロット構築用型枠の床型枠の貫通孔を貫通する、コンクリート躯体の構築方法。 A method of constructing a concrete skeleton by dividing the concrete skeleton to be constructed into a plurality of lots in the vertical direction and placing the concrete by changing the formwork for each lot in order from top to bottom,
A first step of disposing a first tubular member extending in the vertical direction for concrete placing work in a space surrounded by the inner surface of the first lot-building formwork;
A second step of constructing the first lot by placing concrete in a space surrounded by the inner surface of the first lot constructing mold;
A third step of removing the first lot construction formwork,
Including
In the method for constructing a concrete skeleton, the first tubular member connects the upper side of the first lot and the lower side of the first lot,
Through-holes are formed in the floor formwork forming the first lot construction formwork,
In the first step, the lower end of the first tubular member penetrates the through hole of the bed frame of the first lot for building formwork, how to build a concrete building frame.
上下方向に延びるコンクリート打設作業用の第1管状部材を、第1ロット構築用型枠の内面によって囲まれる空間内に配置する第1工程と、
前記第1ロット構築用型枠の内面によって囲まれる空間内にコンクリートを打設することにより第1ロットを構築する第2工程と、
前記第1ロット構築用型枠を撤去する第3工程と、
を含み、
前記第1管状部材は、前記第1ロットの上方と前記第1ロットの下方とを連通する、コンクリート躯体の構築方法において、
前記第3工程にて前記第1ロット構築用型枠を撤去した後に、前記第1管状部材の下端部に新たな管状部材の上端部を連結することにより、前記第1管状部材を下方に延長する第4工程と、
前記第1ロットの下方に第2ロット構築用型枠を設置して、第2ロット構築用型枠の内面によって囲まれる空間内に前記第1管状部材の延長部を位置させる第5工程と、
前記第2ロット構築用型枠の内面と前記第1ロットの下面とによって囲まれる空間内にコンクリートを打設することにより第2ロットを構築する第6工程と、
前記第2ロット構築用型枠を撤去する第7工程と、
を更に含み、
前記第1管状部材及びその延長部は、前記第1ロットの上方と前記第2ロットの下方とを連通する、コンクリート躯体の構築方法。 A method of constructing a concrete skeleton by dividing the concrete skeleton to be constructed into a plurality of lots in the vertical direction and placing the concrete by changing the formwork for each lot in order from top to bottom,
A first step of disposing a first tubular member extending in the vertical direction for concrete placing work in a space surrounded by the inner surface of the first lot-building formwork;
A second step of constructing the first lot by placing concrete in a space surrounded by the inner surface of the first lot constructing mold;
A third step of removing the first lot construction formwork,
Including
In the method for constructing a concrete skeleton, the first tubular member connects the upper side of the first lot and the lower side of the first lot,
The first tubular member is extended downward by connecting the upper end of a new tubular member to the lower end of the first tubular member after removing the first lot construction mold in the third step. A fourth step of
A fifth step of installing a second lot building mold below the first lot, and positioning an extension of the first tubular member in a space surrounded by an inner surface of the second lot building mold;
A sixth step of constructing a second lot by placing concrete in a space surrounded by the inner surface of the second lot construction mold and the lower surface of the first lot;
A seventh step of removing the second lot construction formwork,
Further including,
Wherein the first tubular member and its extension, the communicating the lower upper and the second lot in the first lot, concrete building frame construction method of.
前記第7工程にて前記第2ロット構築用型枠を撤去した後に、前記第2蓋部材を前記第1管状部材の延長部から取り外す、請求項4に記載のコンクリート躯体の構築方法。 Prior to placing concrete in the second lot building mold in the sixth step, a second lid member for closing the lower surface opening of the extension portion of the first tubular member is extended to the first tubular member. Attached to the section,
The method for constructing a concrete skeleton according to claim 4, wherein the second lid member is removed from an extension portion of the first tubular member after removing the second lot construction mold in the seventh step.
前記第5工程では、前記第1管状部材の延長部の下端部が前記第2ロット構築用型枠の床型枠の貫通孔を貫通する、請求項4に記載のコンクリート躯体の構築方法。 Through-holes are formed in the floor formwork forming the second lot construction formwork,
Wherein in the fifth step, the lower end portion of the extension portion of the first tubular member penetrates the through hole of the bed frame of the second lot for building formwork, method for constructing a concrete skeleton according to claim 4.
前記第3ロット構築用型枠の内面と前記第2ロットの下面とによって囲まれる空間内にコンクリートを打設することにより第3ロットを構築する第9工程と、
前記第3ロット構築用型枠を撤去する第10工程と、
を更に含む、請求項4〜請求項6のいずれか1つに記載のコンクリート躯体の構築方法。 An eighth step of installing a third lot building mold below the second lot after removing the second lot building mold in the seventh step;
A ninth step of constructing a third lot by placing concrete in a space surrounded by the inner surface of the third lot construction mold and the lower surface of the second lot;
A tenth step of removing the third lot construction formwork,
The method for constructing a concrete skeleton according to any one of claims 4 to 6, further comprising:
前記第9工程では、1つの前記第1管状部材から前記第3ロット構築用型枠内にコンクリートを打設し、この打設されたコンクリートの一部が別の1つの前記第1管状部材の前記延長部内に流入して前記別の1つの前記第1管状部材の前記延長部内を上昇してきたことを確認した後に、前記別の1つの前記第1管状部材から前記第3ロット構築用型枠内にコンクリートを打設する、請求項7に記載のコンクリート躯体の構築方法。 A plurality of the first tubular members each having the extension are horizontally spaced apart in one direction,
In the ninth step, concrete is poured from one of the first tubular members into the third lot-building formwork, and a part of the cast concrete is another one of the first tubular members. After confirming that it has flowed into the extension part and has risen in the extension part of the another one of the first tubular members, the third lot-building formwork is started from the another one of the first tubular members. The method for constructing a concrete skeleton according to claim 7, wherein concrete is placed inside.
上下方向に延びるコンクリート打設作業用の第1管状部材を、第1ロット構築用型枠の内面によって囲まれる空間内に配置する第1工程と、
前記第1ロット構築用型枠の内面によって囲まれる空間内にコンクリートを打設することにより第1ロットを構築する第2工程と、
前記第1ロット構築用型枠を撤去する第3工程と、
を含み、
前記第1管状部材は、前記第1ロットの上方と前記第1ロットの下方とを連通する、コンクリート躯体の構築方法において、
前記第3工程にて前記第1ロット構築用型枠を撤去した後に、前記第1ロットの下方に第2ロット構築用型枠を設置する第4工程と、
前記第2ロット構築用型枠の内面と前記第1ロットの下面とによって囲まれる空間内にコンクリートを打設することにより第2ロットを構築する第5工程と、
前記第2ロット構築用型枠を撤去する第6工程と、
を更に含む、コンクリート躯体の構築方法。 A method of constructing a concrete skeleton by dividing the concrete skeleton to be constructed into a plurality of lots in the vertical direction and placing the concrete by changing the formwork for each lot in order from top to bottom,
A first step of disposing a first tubular member extending in the vertical direction for concrete placing work in a space surrounded by the inner surface of the first lot-building formwork;
A second step of constructing the first lot by placing concrete in a space surrounded by the inner surface of the first lot constructing mold;
A third step of removing the first lot construction formwork,
Including
In the method for constructing a concrete skeleton, the first tubular member connects the upper side of the first lot and the lower side of the first lot,
A fourth step of installing a second lot construction mold below the first lot after removing the first lot construction mold in the third step;
A fifth step of constructing a second lot by placing concrete in a space surrounded by the inner surface of the second lot construction mold and the lower surface of the first lot;
A sixth step of removing the second lot construction formwork,
Further comprising, a method for constructing a concrete building frame a.
前記第5工程では、1つの前記第1管状部材から前記第2ロット構築用型枠内にコンクリートを打設し、この打設されたコンクリートの一部が別の1つの前記第1管状部材内に流入して前記別の1つの前記第1管状部材内を上昇してきたことを確認した後に、前記別の1つの前記第1管状部材から前記第2ロット構築用型枠内にコンクリートを打設する、請求項10に記載のコンクリート躯体の構築方法。 A plurality of the first tubular members are arranged at intervals in one horizontal direction,
In the fifth step, concrete is poured from one of the first tubular members into the second lot-building formwork, and a part of the cast concrete is placed in another one of the first tubular members. After confirming that it has flowed into the other one of the first tubular members and has risen therein, concrete is poured from the another one of the first tubular members into the second lot construction formwork. The method for constructing a concrete skeleton according to claim 10.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2016176998A JP6740064B2 (en) | 2016-09-09 | 2016-09-09 | Construction method of concrete frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2016176998A JP6740064B2 (en) | 2016-09-09 | 2016-09-09 | Construction method of concrete frame |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2018040231A JP2018040231A (en) | 2018-03-15 |
JP6740064B2 true JP6740064B2 (en) | 2020-08-12 |
Family
ID=61625396
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2016176998A Active JP6740064B2 (en) | 2016-09-09 | 2016-09-09 | Construction method of concrete frame |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6740064B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP7214469B2 (en) * | 2018-12-25 | 2023-01-30 | 清水建設株式会社 | Concrete compaction device and concrete compaction method |
Family Cites Families (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS54139225A (en) * | 1978-04-21 | 1979-10-29 | Katsumoto Ueda | Concrete placing method to location where upper portion is restricted by means of obstacle |
JPS57169127A (en) * | 1981-04-10 | 1982-10-18 | Penta Ocean Constr Co Ltd | Construction of inverted lining concrete structure |
JPH0672422B2 (en) * | 1989-07-12 | 1994-09-14 | 株式会社大林組 | Installation method of bottom formwork in reverse winding method |
JP2829216B2 (en) * | 1993-03-18 | 1998-11-25 | 大阪瓦斯株式会社 | Concrete casting method and casting chute in reverse winding method |
JP2757107B2 (en) * | 1993-06-30 | 1998-05-25 | 株式会社国元商会 | Reinforcement arrangement structure in reverse hitting method |
JPH0748848A (en) * | 1993-08-10 | 1995-02-21 | Kajima Corp | Construction method for underground skeleton by inverted construction method |
JP3360234B2 (en) * | 1994-12-16 | 2002-12-24 | 清水建設株式会社 | Construction method of underground skeleton |
JPH101957A (en) * | 1996-06-14 | 1998-01-06 | Ohbayashi Corp | Underground construction method for building |
JP3310949B2 (en) * | 1999-04-01 | 2002-08-05 | カワシマ物産株式会社 | How to fill gaps in buildings |
JP3323470B2 (en) * | 2000-01-12 | 2002-09-09 | 西松建設株式会社 | Concrete placement method in reverse winding method |
KR101341679B1 (en) * | 2010-09-30 | 2013-12-16 | (주)바로건설기술 | Device for constructing an underground structure and method thereof |
JP5726496B2 (en) * | 2010-12-01 | 2015-06-03 | 大成建設株式会社 | Concrete placement equipment and concrete placement method |
JP2013181329A (en) * | 2012-03-01 | 2013-09-12 | Ohbayashi Corp | Placing-joint method of concrete in reversed placing method, construction method of skeleton using reversed placing method, and placing-joint structure of concrete in reversed placing method |
-
2016
- 2016-09-09 JP JP2016176998A patent/JP6740064B2/en active Active
Also Published As
Publication number | Publication date |
---|---|
JP2018040231A (en) | 2018-03-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100951097B1 (en) | Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket | |
KR20210119861A (en) | Slurry wall, construction method for the same and wire mesh assembly | |
JPH09242067A (en) | Building method for cast-in-place concrete pile | |
KR101169462B1 (en) | Top-down construction method using post member | |
JP5303381B2 (en) | Demolition method for existing buildings | |
KR101840226B1 (en) | The guide holes of the form for soil auger dredges | |
JP6740064B2 (en) | Construction method of concrete frame | |
JP7085464B2 (en) | How to build a retaining wall structure in the reverse striking method | |
KR100699359B1 (en) | Underground diaphragm wall with post-tensioning equipment and construction method the same | |
CN105064500A (en) | Balcony beam slab inner side filling wall body and main body structure integral casting construction method | |
JP2020513075A (en) | Field-placed reinforcement top type pile foundation and its construction method | |
KR20090043625A (en) | Method for constructing underground slabs using asymmetric girder | |
KR100562686B1 (en) | The underground structure and it's construction method is using sheet pile and cast in a place concrete | |
CN214615420U (en) | Manufacturing device for formwork splicing section | |
KR102127859B1 (en) | Pile wall, Construction method thereof | |
JP7230313B2 (en) | Basement structure and construction method of basement | |
JP6514739B2 (en) | Construction method for forming underground structure and underground structure completed thereby | |
KR101436132B1 (en) | Concrete placing apparatus for utility-pipe conduit | |
JP6882024B2 (en) | Joining structure of precast concrete slab and construction method of precast concrete slab | |
KR101077242B1 (en) | Construction method of basement structure using retaining wall and steel column | |
CN110670760B (en) | Construction process of small hollow building block steel concrete core column | |
KR102540577B1 (en) | Structure For Connecting Horizontal Rebars In Integrated Underground Wall Construction | |
CN214941328U (en) | Steel rib connecting node structure for prefabricated shear wall without rib discharging | |
JPH01315520A (en) | Underground outer wall constructing method for superstructure | |
CN215165650U (en) | Two-way pipe jacking pit supporting construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20190306 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20200108 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20200121 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20200218 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20200714 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20200722 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6740064 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |