JP3360234B2 - Construction method of underground skeleton - Google Patents

Construction method of underground skeleton

Info

Publication number
JP3360234B2
JP3360234B2 JP31382594A JP31382594A JP3360234B2 JP 3360234 B2 JP3360234 B2 JP 3360234B2 JP 31382594 A JP31382594 A JP 31382594A JP 31382594 A JP31382594 A JP 31382594A JP 3360234 B2 JP3360234 B2 JP 3360234B2
Authority
JP
Japan
Prior art keywords
reinforcing bar
skeleton
wall
column
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP31382594A
Other languages
Japanese (ja)
Other versions
JPH08170344A (en
Inventor
崇 西村
雅樹 根本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP31382594A priority Critical patent/JP3360234B2/en
Publication of JPH08170344A publication Critical patent/JPH08170344A/en
Application granted granted Critical
Publication of JP3360234B2 publication Critical patent/JP3360234B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、例えば鉄筋コンクリー
ト造あるいは鉄骨鉄筋コンクリート造で構成する地下躯
体の、特に柱や壁を施工するのに好適な地下躯体の施工
方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground skeleton made of, for example, reinforced concrete or steel reinforced concrete, and particularly suitable for constructing pillars and walls.

【0002】[0002]

【従来の技術】一般に、都心部等において、ビル等の建
築構造物を敷地いっぱいに構築する場合等に、このビル
の地下躯体を地盤中に構築するに際し、地盤を徐々に根
切りしつつ、地下躯体を上層階から下層階へ向けて構築
していく逆打ち工法が多用されている。
2. Description of the Related Art Generally, when building structures such as buildings are built on the entire site in a city center or the like, when building an underground structure of the building in the ground, the ground is gradually cut off. The reverse construction method that builds the underground structure from the upper floor to the lower floor is often used.

【0003】このような逆打ち工法では、まず、地上1
階部(いわゆるトッププレート)の床,梁を、この本設
柱の柱鉄骨あるいは仮設の鉄骨柱で支持するように形成
し、これを、以降の構築作業の作業構台として用いる。
そして、地上1階部の床,梁の下方で、地盤の掘削工事
を続行し、さらに一定深さ、例えば1階分掘削した後
に、ここに直下階(地下1階部)の梁,床,柱,壁等を
構築する。これを繰り返すことによって、各階の躯体を
上層階から下層階に向けて順次施工していき、地下躯体
を構築するようにしている。
[0003] In such a reverse striking method, first, the ground 1
The floors and beams of the floor (the so-called top plate) are formed so as to be supported by the pillar steel frame of this main column or the temporary steel column, and this is used as a work gantry for the subsequent construction work.
Excavation of the ground is continued below the floors and beams on the first floor above the ground, and after excavation for a certain depth, for example, one floor, the beams, floors, Build pillars, walls, etc. By repeating this, the skeleton of each floor is constructed sequentially from the upper floor to the lower floor, so that the underground skeleton is constructed.

【0004】従来、このような地下躯体の施工方法で
は、柱,壁等、上下方向に連続する部材を施工するに際
しては、以下のようにしている。すなわち、図7に示す
ように、まず、掘削した根切底面1上に、サポート部材
2,2を介して底型枠3を水平に設置する。次いで、こ
の底型枠3上に形成すべき柱4の柱鉄筋5,壁6の壁鉄
筋7を配筋・組立し、その周囲に柱型枠8,壁型枠9を
所定の形状に組み立て、ここにコンクリートを打設する
ようにしている。そして、このようにして形成した柱
4,壁6の下方に、下層階の柱・壁(図示なし)を形成
するときには、根切底面1をさらに一定深さ掘削すると
ともに、サポート部材2,2、底型枠3を取り外して柱
4,壁6の底面を露出させる。その後、上記と同様にし
て下層階の柱・壁(図示なし)を形成する。このとき、
下層階の柱・壁(図示なし)の鉄筋を配筋するときに
は、その上端部を柱4,壁6の底面から突出した柱鉄筋
5,壁鉄筋7の差し筋5a,7aに接続するようにして
いる。
Conventionally, in such a method of constructing an underground skeleton, when vertically continuous members such as columns and walls are constructed, the following is performed. That is, as shown in FIG. 7, first, the bottom form 3 is horizontally placed on the excavated root cutting surface 1 via the support members 2 and 2. Next, the column reinforcement 5 of the column 4 to be formed on the bottom form 3 and the wall reinforcement 7 of the wall 6 are arranged and assembled, and the column form 8 and the wall form 9 are assembled around the periphery thereof in a predetermined shape. , And concrete is poured here. When columns and walls (not shown) of a lower floor are formed below the columns 4 and the walls 6 formed in this way, the root cutting bottom 1 is further excavated to a certain depth and the support members 2 and 2 are excavated. Then, the bottom form 3 is removed to expose the bottom surfaces of the pillars 4 and the walls 6. Thereafter, columns and walls (not shown) of the lower floor are formed in the same manner as above. At this time,
When arranging the reinforcing bars of the columns and walls (not shown) on the lower floor, the upper ends thereof are connected to the columns 4, the column reinforcing bars 5 protruding from the bottom of the wall 6, and the reinforcing bars 5a and 7a of the wall reinforcing bars 7. ing.

【0005】[0005]

【発明が解決しようとする課題】しかしながら、上述し
たような従来の地下躯体の施工方法には、以下のような
問題が存在する。まず、底型枠3を組み立てるには、サ
ポート部材2,2等を組み立てる必要があり、手間がか
かる。また、柱4,壁6の下方に下層階の柱・壁(図示
なし)を形成するときに上下の柱鉄筋5,壁鉄筋7を接
続するために、柱4,壁6の下面に差し筋5a,7aを
突出させておく必要がある。このため、底型枠3に穴を
あけてここに柱鉄筋5,壁鉄筋7を通さなければなら
ず、これにも非常に手間がかかる。これらによって、柱
4や壁6を形成するに際し、柱鉄筋5,壁鉄筋7および
底型枠3の組立作業が非常に面倒なものとなっている。
しかも、サポート部材2,2、底型枠3等を組み立てる
ためには根切底面1をその分深くする必要があるため、
工期の短縮化の妨げとなっている。さらには、柱鉄筋
5,壁型枠7を配筋・組立した後には、差し筋5a,7
aが下方に突出した状態となるため、危険であるという
問題もある。本発明は、以上のような点を考慮してなさ
れたもので、容易かつ安全に施工することのできる地下
躯体の施工方法を提供することを目的とする。
However, the above-mentioned conventional underground skeleton construction method has the following problems. First, in order to assemble the bottom formwork 3, it is necessary to assemble the support members 2, 2 and the like, which is troublesome. In order to connect the upper and lower column reinforcing bars 5 and the wall reinforcing bars 7 when forming columns and walls (not shown) of the lower floor below the columns 4 and the walls 6, a reinforcing bar is provided on the lower surface of the columns 4 and the walls 6. It is necessary to make 5a and 7a protrude. For this reason, it is necessary to make a hole in the bottom formwork 3 and pass the column reinforcing bar 5 and the wall reinforcing bar 7 therethrough, which also requires much labor. As a result, when forming the columns 4 and the walls 6, the assembling work of the column reinforcing bars 5, the wall reinforcing bars 7, and the bottom form 3 is very troublesome.
Moreover, in order to assemble the support members 2 and 2 and the bottom form 3 and the like, it is necessary to make the root bottom 1 deeper by that amount.
This is an obstacle to shortening the construction period. Furthermore, after the column reinforcing bars 5 and the wall form 7 are arranged and assembled, the reinforcing bars 5a, 7
There is also a problem that it is dangerous because a protrudes downward. The present invention has been made in consideration of the above points, and an object of the present invention is to provide a construction method of an underground skeleton that can be easily and safely constructed.

【0006】[0006]

【課題を解決するための手段】請求項1に係る発明は、
地盤中に地下躯体を構築するに際し、地盤を一定深さ掘
削する掘削工程と、掘削した根切底面上に各階の躯体を
構築する躯体構築工程とを交互に繰り返すことによっ
て、前記地下躯体を上層階から下層階に向けて順次構築
していく構成とし、前記各躯体構築工程では、根切底面
上に一定厚さの捨てコンクリート盤を形成するととも
に、該捨てコンクリート盤上でコンクリートが硬化する
前に筒状の鉄筋接続具を配置し、形成すべき柱や壁の主
鉄筋の下端部を前記鉄筋接続具に挿入接続して柱や壁の
鉄筋を定められた形状に組み立てた後、該鉄筋の周囲で
捨てコンクリート盤上に、柱や壁の側面を形成するよう
型枠を組み立てて該型枠内にコンクリートを打設する
ことによって柱や壁を一定長さ形成しておき、その下方
の根切底面を掘削するために前記掘削工程を行うとき
に、前記根切底面を掘削するとともに前記捨てコンクリ
ート盤を取り壊して前記柱や壁の下面と前記鉄筋接続具
とを露出させ、しかる後に下層階を構築するために前記
躯体構築工程を行うときに、前記鉄筋接続具に、下方に
形成すべき柱や壁の主鉄筋の上端部を挿入接続すること
を特徴としている。
The invention according to claim 1 is
In constructing the underground skeleton in the ground, the digging step of excavating the ground to a certain depth and the skeleton building step of constructing the skeleton of each floor on the excavated root bottom surface are alternately repeated, so that the underground skeleton is raised. The building is constructed sequentially from the floor to the lower floor, and in each of the skeleton building steps, a concrete disc having a constant thickness is formed on the root bottom surface, and concrete hardens on the discard concrete board.
Before disposing a tubular reinforcing bar connection, after inserting and connecting the lower end of the main reinforcing bar of the column or wall to be formed to the reinforcing bar connecting device to assemble the reinforcing bar of the column or wall into a predetermined shape, Around the rebar
Form pillars and side walls on discarded concrete boards
When assembling a formwork and casting concrete into the formwork to form pillars and walls with a fixed length, and when performing the excavation step to excavate the root bottom below, When excavating the bottom of the root and demolishing the discarded concrete board to expose the lower surfaces of the pillars and walls and the rebar connector, and then performing the skeleton building step to construct a lower floor, It is characterized in that the upper end of the main reinforcing bar of the pillar or wall to be formed below is inserted and connected to the connecting tool.

【0007】請求項2に係る発明は、請求項1記載の地
下躯体の施工方法において、前記躯体構築工程で前記捨
てコンクリート盤上に前記鉄筋接続具を配置するとき
に、該鉄筋接続具を前記捨てコンクリート盤内に一定長
さ埋め込むことを特徴としている。
According to a second aspect of the present invention, in the method of constructing an underground skeleton according to the first aspect, when the rebar connection fitting is disposed on the discarded concrete board in the skeleton construction step, the rebar connection fitting is connected to the underground skeleton. It is characterized in that it is embedded into a discarded concrete board for a certain length.

【0008】[0008]

【作用】請求項1記載の発明では、躯体構築工程で柱や
壁を一定長さ形成するときに、根切底面上に一定厚さの
捨てコンクリート盤を形成し、その上にコンクリートが
硬化する前に筒状の鉄筋接続具を配置するとともに主鉄
筋の下端部を鉄筋接続具に挿入接続しておく構成とし
た。これにより、従来のように底型枠を用いることな
く、鉄筋を捨てコンクリート盤上で支持して配筋・組立
することができる。そして、掘削工程で地盤をさらに一
定深さ掘削するときに捨てコンクリート盤を取り壊すこ
とによって、躯体構築工程で形成した柱や壁の下面に前
記鉄筋接続具を露出させ、しかる後に下層階の躯体を構
築するときに、鉄筋接続具に、下方に形成すべき柱や壁
の主鉄筋の上端部を挿入接続する構成とした。これによ
り、柱や壁の主鉄筋を容易に上下に接続することができ
る。
According to the first aspect of the present invention, when pillars and walls are formed to a fixed length in the frame building process, a concrete disc having a fixed thickness is formed on the bottom of the root, and concrete is placed thereon.
Before the hardening, a tubular rebar connector was arranged and the lower end of the main rebar was inserted and connected to the rebar connector. Thus, the reinforcing bar can be disposed on the concrete board and disposed and assembled without using the bottom formwork as in the related art. Then, by excavating the discarded concrete slab when excavating the ground further to a certain depth in the excavation process, the rebar connection fittings are exposed on the lower surfaces of the pillars and walls formed in the skeleton building process, and then the skeleton of the lower floor is removed. At the time of construction, the upper end of the main reinforcing bar of the pillar or wall to be formed below is inserted and connected to the reinforcing bar connecting tool. This makes it possible to easily connect the main reinforcing bars of columns and walls up and down.

【0009】請求項2記載の発明では、躯体構築工程で
捨てコンクリート盤上に鉄筋接続具を配置するときに、
鉄筋接続具を捨てコンクリート盤内に一定長さ埋め込む
構成とした。これにより、鉄筋接続具の位置決めを治具
等を用いることなく容易に行うことが可能となる。
According to the second aspect of the present invention, when arranging the reinforcing bar connecting piece on the discarded concrete board in the frame building step,
Reinforcing bar fittings were discarded and a certain length was embedded in a concrete board. This makes it possible to easily position the rebar connection tool without using a jig or the like.

【0010】[0010]

【実施例】以下、本発明を図面に示す一実施例を参照し
て説明する。ここでは、例えば、梁が鉄筋コンクリート
造で、柱が鉄骨鉄筋コンクリート造とされた、多層階を
有する地下躯体を構築する場合の実施例を用いて説明す
る。図1は、本発明に係る地下躯体の施工方法を適用し
て構築する地下躯体の一例を示すものである。図1に示
すように、地下躯体10は、地盤G中に形成された基礎
(図示なし)上に構築されており、地上一階部11の下
方に例えば5層からなる地下階を有した構成となってい
る。
DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below with reference to an embodiment shown in the drawings. Here, for example, an embodiment in the case of constructing an underground skeleton having a multi-story floor in which the beams are made of reinforced concrete and the columns are made of steel reinforced concrete will be described. FIG. 1 shows an example of an underground skeleton constructed by applying the underground skeleton construction method according to the present invention. As shown in FIG. 1, the underground skeleton 10 is constructed on a foundation (not shown) formed in the ground G, and has a basement floor composed of, for example, five layers below the ground floor 11. It has become.

【0011】この地下躯体10は、柱12が例えば鉄骨
鉄筋コンクリート造(以下「SRC造」と称する)で、
壁13,各階の梁14および床15が鉄筋コンクリート
造(以下「RC造」と称する)からなる構成とされてい
る。図1および図2に示すように、所定間隔で配置され
た各柱12は、基礎(図示なし)上に立設された柱鉄骨
16と、四隅に配筋された柱鉄筋17と、断面視矩形と
なるよう打設されたコンクリートCとから形成されてい
る。また、柱12,12,…間に、平面視格子状となる
よう配設された各壁13は、その厚さ方向中心部に沿っ
て配筋された壁鉄筋18と、その周囲に所定厚さに亘っ
て打設されたコンクリートCとから形成されている。
In this underground skeleton 10, the columns 12 are made of, for example, steel reinforced concrete (hereinafter referred to as "SRC").
The wall 13, the beams 14 on each floor, and the floor 15 are made of reinforced concrete (hereinafter, referred to as "RC"). As shown in FIGS. 1 and 2, each column 12 arranged at a predetermined interval includes a column steel frame 16 erected on a foundation (not shown), a column reinforcing bar 17 arranged at four corners, and a sectional view. It is formed from concrete C cast in a rectangular shape. Each of the walls 13 arranged between the columns 12, 12, ... so as to form a lattice shape in a plan view has a wall reinforcing bar 18 arranged along the center in the thickness direction, and a predetermined thickness around the wall reinforcing bar 18. It is formed from concrete C that has been cast over a long time.

【0012】次に、このような地下躯体10を構築する
施工方法について、図1ないし図6を参照して説明す
る。まず、図3に示すように、地盤Gの所定の位置(各
柱12を立設すべき位置)に各柱12の柱鉄骨16を、
その下端部が所定深さに到達するように打ち込む。
Next, a construction method for constructing such an underground skeleton 10 will be described with reference to FIGS. First, as shown in FIG. 3, a column steel frame 16 of each column 12 is placed at a predetermined position on the ground G (a position where each column 12 is to be erected).
The lower end is driven so as to reach a predetermined depth.

【0013】(掘削工程)次いで、地盤Gを一定深さ掘
削する。
(Excavation process) Next, the ground G is excavated at a constant depth.

【0014】(躯体構築工程)そして、掘削した一次根
切面(根切底面)G1上に突出した各柱鉄骨16の周辺
と、壁13を形成すべき位置の周辺とに、一定厚さに亘
ってコンクリート(無筋)を打設し、捨てコンクリート
盤21,21,…を形成する。そして、各捨てコンクリ
ート盤21のコンクリートが硬化する前に、捨てコンク
リート盤21上の所定の位置(柱鉄筋17の主筋17
a,壁鉄筋18の縦筋18aを配筋すべき位置)に、鉄
筋接続具22,22,…を、その長さの半分程度が捨て
コンクリート盤21内に埋没するように配置する。この
鉄筋接続具22は、筒状で内周面に雌ネジ部が形成され
たものである。このとき、各鉄筋接続具22の下端部に
は、内部にコンクリートが侵入するのを防ぐため、例え
ば樹脂製のキャップ(図示なし)をかぶせておく。
(Structural Construction Step) Around the steel columns 16 projecting above the excavated primary root cut surface (root cut bottom surface) G1 and the position where the wall 13 is to be formed, a predetermined thickness is provided. Concrete (straight) to form discarded concrete discs 21, 21,. Then, before the concrete of each discarded concrete board 21 is hardened, a predetermined position on the discarded concrete board 21 (the main reinforcement 17
a, the position where the vertical bars 18a of the wall reinforcing bars 18 are to be arranged), the reinforcing bar connectors 22, 22,... are disposed so that about half of the length thereof is buried in the discarded concrete board 21. The rebar connection tool 22 is cylindrical and has a female screw portion formed on the inner peripheral surface. At this time, for example, a resin cap (not shown) is put on the lower end of each rebar connection tool 22 in order to prevent concrete from entering the inside.

【0015】次いで、柱12の柱鉄筋17の主筋(主鉄
筋)17a,17a,…の下端部を、捨てコンクリート
盤21上の鉄筋接続具22,22,…に挿入・接続す
る。この主筋17aは、いわゆるネジ節鉄筋で、上下端
部の外周面に雄ネジ部が形成されたものである。続い
て、柱鉄筋17のフープ筋(図示なし)等を配筋し、柱
鉄筋17を所定の形状に組み立てる。そして、柱鉄筋1
7のフープ筋(図示なし)の内方の捨てコンクリート盤
21上に、例えばワインディングパイプ等の筒状のパイ
プ25を配置する。このパイプ25は、例えば100〜
200φ程度の管径を有し、かつその上端が形成すべき
床15の上方に露出あるいは突出するような長さを有し
たものである。次いで、この柱鉄筋17の周囲の捨てコ
ンクリート盤21上に、柱型枠(型枠)26を組み立て
る。この柱型枠26には底型枠は不要で、柱12の側面
のみを形成するように組み立てればよい。
Next, the lower ends of the main reinforcing bars (main reinforcing bars) 17a, 17a,... Of the column reinforcing bars 17 of the column 12 are inserted and connected to the reinforcing bar connecting tools 22, 22,. The main reinforcing bar 17a is a so-called threaded bar having a male screw portion formed on the outer peripheral surface of the upper and lower ends. Subsequently, hoop bars (not shown) of the column reinforcing bar 17 are arranged, and the column reinforcing bar 17 is assembled into a predetermined shape. And pillar reinforcement 1
For example, a tubular pipe 25 such as a winding pipe is disposed on the discarded concrete board 21 inside the hoop 7 (not shown). This pipe 25 is, for example, 100 to
It has a diameter of about 200φ and a length such that its upper end is exposed or protrudes above the floor 15 to be formed. Next, a column formwork (formwork) 26 is assembled on the discarded concrete board 21 around the column reinforcing bar 17. The column formwork 26 does not need a bottom formwork, and may be assembled so as to form only the side surfaces of the columns 12.

【0016】また、柱鉄筋17の組み立てと並行して、
壁鉄筋18,壁型枠(型枠)27の組み立て作業を、以
下のようにして行う。まず、壁鉄筋18の縦筋(主鉄
筋)18a,18a,…の下端部を、捨てコンクリート
盤21上の鉄筋接続具22,22,…に挿入・接続す
る。この縦筋18aは、前記主筋17aと同様に、いわ
ゆるネジ節鉄筋で上下端部に雄ネジ部が形成されたもの
である。続いて、壁鉄筋18の横筋(図示なし)を配筋
し、壁鉄筋18を所定の形状に組み立てる。そして、図
2および図3に示したように、パイプ25,25,…
を、形成すべき壁13に沿って一定間隔、例えば200
0mm毎に、捨てコンクリート盤21上に配置する。次
いで、図3に示したように、捨てコンクリート盤21上
に壁型枠27を組み立てる。この壁型枠27について
も、前記柱型枠26と同様に底型枠は不要で、壁13の
側面のみを形成するように組み立てればよい。
In parallel with the assembly of the column reinforcing bar 17,
The assembling work of the wall reinforcing bar 18 and the wall formwork (formwork) 27 is performed as follows. First, the lower ends of the vertical reinforcing bars (main reinforcing bars) 18a, 18a,... Of the wall reinforcing bars 18 are inserted and connected to the reinforcing bar connectors 22, 22,. The vertical streak 18a is a so-called threaded bar having male screw portions formed at upper and lower ends, similarly to the main streak 17a. Subsequently, a horizontal bar (not shown) of the wall reinforcing bar 18 is arranged, and the wall reinforcing bar 18 is assembled into a predetermined shape. Then, as shown in FIGS. 2 and 3, pipes 25, 25,.
At regular intervals along the wall 13 to be formed, for example 200
It is placed on the discarded concrete board 21 every 0 mm. Next, as shown in FIG. 3, the wall form 27 is assembled on the discarded concrete board 21. This wall form 27 does not need a bottom form as well as the column form 26, and may be assembled so as to form only the side surface of the wall 13.

【0017】次いで、前記柱型枠26,壁型枠27上
に、梁型枠28,床型枠(図示なし)を組み立てた後
に、梁14,床15の鉄筋(図示なし)を所定の形状に
組み立てる。
Next, after assembling the beam formwork 28 and the floor formwork (not shown) on the column formwork 26 and the wall formwork 27, the reinforcing bars (not shown) of the beams 14 and the floor 15 are formed into a predetermined shape. Assemble to

【0018】このようにして柱型枠26,壁型枠27,
梁型枠28,床型枠(図示なし)を組み立てた後、その
内方にコンクリートCを打設する。このとき、各パイプ
25内にはコンクリートCを打設しないようにする。そ
して、打設したコンクリートCが養生して所定の強度が
発現した後に、柱型枠26,壁型枠27,梁型枠28,
床型枠(図示なし)を解体する。このようにして、梁1
4,床15が形成され、その下面に、一定長の柱12お
よび壁13が形成されたことになり、地上一階部11の
構築が完了する。
Thus, the column formwork 26, the wall formwork 27,
After assembling the beam formwork 28 and the floor formwork (not shown), concrete C is cast inward. At this time, the concrete C is not poured into each pipe 25. After the cast concrete C is cured and a predetermined strength is developed, the column formwork 26, the wall formwork 27, the beam formwork 28,
Disassemble the floor formwork (not shown). Thus, beam 1
4, the floor 15 is formed, and the fixed length pillar 12 and the wall 13 are formed on the lower surface, and the construction of the ground floor 11 is completed.

【0019】次に、以下のようにして地上一階部11の
下方に地下一階部B1を構築する。 (掘削工程)まず、一次根切面G1を一定深さ掘削す
る。このとき、前記躯体構築工程で形成した捨てコンク
リート盤21を、掘削と同時に取り壊す。この捨てコン
クリート盤21は無筋コンクリートであるため、その上
面に形成した柱12,壁13を損傷することなく、容易
に取り壊すことが可能である。すると、柱12,壁13
の下面と鉄筋接続具22の下半部とが露出することにな
る。また、キャップ(図示なし)も取り外しておく。
Next, an underground first floor B1 is constructed below the first ground 11 as follows. (Excavation process) First, the primary root cut surface G1 is excavated to a certain depth. At this time, the discarded concrete board 21 formed in the frame building step is demolished simultaneously with excavation. Since the discarded concrete board 21 is made of plain concrete, the pillars 12 and the walls 13 formed on the upper surface thereof can be easily demolished without being damaged. Then, the pillar 12, the wall 13
And the lower half of the rebar connection tool 22 is exposed. The cap (not shown) is also removed.

【0020】(躯体構築工程)続いて、図4に示すよう
に、前記躯体構築工程と同様にして、掘削した二次根切
面(根切底面)G2上に地下一階部B1を構築する。す
なわち、 柱12,壁13を形成すべき位置に捨てコンクリー
ト盤21を形成する。 コンクリート盤21上の所定位置に鉄筋接続具2
2,22,…を埋め込むように配置する。 鉄筋接続具22,22,…に、柱鉄筋17の主筋1
7a,壁鉄筋18の縦筋18aの下端部を挿入・接続す
る。
(Building Construction Step) Subsequently, as shown in FIG. 4, the first basement B1 is constructed on the excavated secondary root cutting plane (root cutting bottom) G2 in the same manner as in the above-mentioned building construction step. That is, the discarded concrete board 21 is formed at the position where the column 12 and the wall 13 are to be formed. Reinforcing bar fitting 2 at a predetermined position on concrete board 21
Are arranged so as to be embedded. The main rebar 1 of the column rebar 17 is attached to the rebar connectors 22, 22,.
7a, the lower end of the vertical bar 18a of the wall reinforcing bar 18 is inserted and connected.

【0021】上記において、主筋17a,縦筋18a
の下端部を鉄筋接続具22,22,…に挿入・接続する
ときには、その上端部17b,18bを、前記躯体構築
工程で形成した柱12,壁13の下面に突出した鉄筋接
続具22,22,…に挿入・接続する。
In the above, the main bar 17a and the vertical bar 18a
Are inserted and connected to the reinforcing bar connectors 22, 22,..., The upper ends 17 b, 18 b of the reinforcing bar connectors 22, 22 projecting from the lower surfaces of the pillars 12 and the walls 13 formed in the frame building step. Insert and connect to, ...

【0022】続いて、 捨てコンクリート盤21上に、柱鉄筋17,壁鉄筋
18を組み立てるとともに、パイプ25を配置する。そ
して、このパイプ25と、上方のパイプ25との間に、
パイプ(コンクリート打設用パイプ)29を接続する。
このパイプ29には、パイプ25と同様、例えばワイン
ディングパイプが用いられている。 柱型枠26,壁型枠27を組み立てる。 梁型枠28,床型枠(図示なし)を組み立てた後、
梁鉄筋,床鉄筋を組み立てる。 柱型枠26,壁型枠27,梁型枠28,床型枠(図
示なし)にコンクリートCを打設し、このコンクリート
Cが硬化した後に各型枠を解体する。
Subsequently, the column reinforcing bar 17 and the wall reinforcing bar 18 are assembled on the discarded concrete board 21, and the pipe 25 is arranged. And between this pipe 25 and the upper pipe 25,
A pipe (concrete casting pipe) 29 is connected.
As the pipe 29, for example, a winding pipe is used like the pipe 25. The column formwork 26 and the wall formwork 27 are assembled. After assembling the beam formwork 28 and the floor formwork (not shown),
Assemble beam reinforcement and floor reinforcement. Concrete C is poured into the column formwork 26, the wall formwork 27, the beam formwork 28, and the floor formwork (not shown), and after the concrete C hardens, each formwork is dismantled.

【0023】このようにして、地下一階部B1の梁1
4,床15が形成され、その下面に、一定長の柱12お
よび壁13が形成される。このとき、地上一階部11の
下面に形成した柱12,壁13の下端部と地下一階部B
1の床15の上面との間は、柱12,壁13のコンクリ
ートCは打設されておらず、柱鉄骨16,柱鉄筋17,
壁鉄筋18が露出した状態となっている。
In this manner, the beam 1 on the first basement B1
4, a floor 15 is formed, and on the lower surface thereof, columns 12 and walls 13 having a fixed length are formed. At this time, the pillar 12 formed on the lower surface of the ground floor 11, the lower end of the wall 13, and the ground floor B
The concrete C of the columns 12 and the walls 13 is not cast between the upper surface of the floor 15 and the column 15, and the column steel frame 16, the column reinforcing bar 17,
The wall reinforcement 18 is exposed.

【0024】この後、上記と全く同様にして掘削工程と
躯体構築工程とを繰り返し、図5に示すように、地下躯
体10を最下階である地下五階部B5まで構築してい
く。なお、地下五階部B5の床15には、パイプ25を
埋設しない。
Thereafter, the excavation step and the skeleton building step are repeated in exactly the same manner as described above, and as shown in FIG. 5, the underground skeleton 10 is built up to the fifth floor B5 which is the lowest floor. The pipe 25 is not buried in the floor 15 of the fifth basement B5.

【0025】(柱・壁コンクリート打設工程)次に、図
6に示すように、地下五階部B5の柱12,13の、柱
鉄骨16,柱鉄筋17,壁鉄筋18が露出した部分の周
囲に、柱型枠30,壁型枠31を組み立てる。続いて、
地上一階部11上から、柱12,壁13に配設された各
パイプ25,29内に、ミキサー等のコンクリート供給
源(図示なし)からコンクリートCを送給するためのコ
ンクリート送給ホース32を通し、その先端を地下五階
部B5の柱型枠30,壁型枠31にまで到達させる。そ
して、コンクリート送給ホース32から前記柱型枠3
0,壁型枠31内にコンクリートCを打設し、地下五階
部B5の柱12,壁13を形成する。
(Column / Wall Concrete Casting Step) Next, as shown in FIG. 6, the portions of the columns 12 and 13 of the fifth basement B5 where the column steel frame 16, the column reinforcing bar 17, and the wall reinforcing bar 18 are exposed are shown. A column formwork 30 and a wall formwork 31 are assembled around the periphery. continue,
A concrete supply hose 32 for supplying concrete C from a concrete supply source (not shown) such as a mixer into the pipes 25 and 29 arranged on the pillars 12 and the walls 13 from above the ground floor 11. To reach the column formwork 30 and the wall formwork 31 of the fifth basement B5. Then, from the concrete feed hose 32, the column form 3
0, Concrete C is poured into the wall form 31 to form the columns 12 and the walls 13 of the fifth basement B5.

【0026】次いで、地下四階部B4のパイプ材29を
取り外す。そして、上記と同様にして、コンクリート送
給ホース32からコンクリートCを打設し、地下四階部
B4の柱12,壁13を形成する。このとき、この地下
四階部B4の柱12,壁13内に埋設された各パイプ2
5内にもコンクリートCを打設して、パイプ25を柱1
2,壁13内に埋め殺すようにする。
Next, the pipe member 29 on the fourth basement floor B4 is removed. Then, in the same manner as above, concrete C is cast from the concrete supply hose 32 to form the columns 12 and the walls 13 of the fourth basement B4. At this time, each pipe 2 buried in the pillar 12 and the wall 13 of the fourth basement B4
Concrete C is poured into the inside of the pipe 5 and the pipe 25 is
2. Try to bury in the wall 13.

【0027】この後、上記の作業を同様にして繰り返
し、各階の柱12,壁13に、下方から上方に向けてコ
ンクリートCを打設していく。そして、各階の柱12,
壁13のコンクリートCが養生して所定の強度が発現し
た後に、柱型枠30,壁型枠31を順次解体していくこ
とによって、図1に示した地下躯体10の構築が完了す
る。
Thereafter, the above operation is repeated in the same manner, and concrete C is poured into the columns 12 and the walls 13 of each floor from the lower side to the upper side. And pillars 12 on each floor,
After the concrete C of the wall 13 is cured and a predetermined strength is developed, the column formwork 30 and the wall formwork 31 are sequentially dismantled, whereby the construction of the underground skeleton 10 shown in FIG. 1 is completed.

【0028】上述した地下躯体10の施工方法では、躯
体構築工程で柱12,壁13を形成するときに、捨てコ
ンクリート盤21を形成し、この捨てコンクリート盤2
1上に鉄筋接続具22を配置するとともに、柱鉄筋17
の主筋17a,壁鉄筋18の縦筋18aの下端部を鉄筋
接続具22に挿入接続する構成とした。これにより、従
来のように底型枠3(図7参照)を用いることなく柱鉄
筋17,壁鉄筋18を配筋・組立することができるの
で、柱鉄筋17,壁鉄筋18および柱型枠26,壁型枠
27の組立作業を大幅に容易化することができ、工期の
短縮化を図ることが可能となり、そのうえ根切深さも最
小限とすることができる。しかも、鉄筋接続具22を捨
てコンクリート盤21に一定長さ埋め込む構成としたの
で、柱鉄筋17,壁鉄筋18の位置決めを治具等を用い
ることなく、容易かつ精度よく行うことができる。これ
によって作業効率を向上させることができ、この点から
も工期の短縮化を図ることが可能となる。また、掘削工
程において、躯体構築工程で形成した柱12,壁13の
下方に下層階の柱12,壁13を形成するために地盤G
をさらに一定深さ掘削するときに、捨てコンクリート盤
21を取り壊して柱12,壁13の下面に鉄筋接続具2
1を露出させておき、しかる後に躯体構築工程におい
て、この鉄筋接続具21に形成すべき柱12の主筋17
a,壁13の縦筋18aの上端部17b,18bを挿入
接続する構成とした。これにより、柱鉄筋17の主筋1
7a,壁鉄筋18の縦筋18aを上下に容易かつ確実に
接続することができる。また、掘削工程で捨てコンクリ
ート盤21を取り壊した状態で、柱鉄筋17の主筋17
a,壁鉄筋18の縦筋18a等が下方に突出することも
ないので、安全性の向上を図ることも可能となる。さら
には、柱12,壁13内にパイプ25を配設しておき、
このパイプ25からコンクリートCを打設する構成とし
たので、柱12,壁13に容易かつ品質よくコンクリー
トCを打設することができる。
In the construction method of the underground skeleton 10 described above, when the pillars 12 and the walls 13 are formed in the skeleton building process, the discarded concrete board 21 is formed, and the discarded concrete board 2 is formed.
1 and the rebar connection tool 22 on the
The main reinforcement 17a and the lower end of the vertical reinforcement 18a of the wall reinforcement 18 are inserted and connected to the reinforcement fitting 22. Thereby, the column reinforcing bar 17 and the wall reinforcing bar 18 can be arranged and assembled without using the bottom form 3 (see FIG. 7) as in the related art. Thus, the assembling work of the wall form 27 can be greatly facilitated, the construction period can be shortened, and the root cutting depth can be minimized. In addition, since the reinforcing bar connector 22 is discarded and embedded in the concrete board 21 at a fixed length, the positioning of the column reinforcing bar 17 and the wall reinforcing bar 18 can be performed easily and accurately without using a jig or the like. As a result, work efficiency can be improved, and from this point, the construction period can be shortened. Also, in the excavation process, the ground G is formed to form the pillars 12 and the walls 13 on the lower floor below the pillars 12 and the walls 13 formed in the frame building process.
When excavating a further depth to a certain depth, the discarded concrete board 21 is demolished, and the lower
1 is exposed, and then, in the frame building process, the main reinforcements 17 of the columns 12 to be formed on the rebar connection fittings 21 are formed.
a, the upper ends 17b and 18b of the vertical stripes 18a of the wall 13 are inserted and connected. Thereby, the main reinforcing bar 1 of the column reinforcing bar 17 is formed.
7a, the vertical bars 18a of the wall reinforcing bars 18 can be easily and reliably connected up and down. In addition, in a state where the discarded concrete board 21 is demolished in the excavation process, the main reinforcement 17
a, the vertical bars 18a of the wall reinforcing bar 18 do not protrude downward, so that it is possible to improve safety. Further, a pipe 25 is provided in the pillar 12 and the wall 13,
Since the concrete C is cast from the pipe 25, the concrete C can be cast on the columns 12 and the walls 13 easily and with high quality.

【0029】なお、上記実施例において、躯体構築工程
で、捨てコンクリート盤21に鉄筋接続具22を配置し
た後に、柱鉄筋17の主筋17a,壁鉄筋18の縦筋1
8aを鉄筋接続具22に挿入・接続する構成としたが、
予め鉄筋接続具22に柱鉄筋17の主筋17a,壁鉄筋
18の縦筋18aを挿入・接続しておいたものを、捨て
コンクリート盤21に配置する構成としてもよい。ま
た、鉄筋接続具22を捨てコンクリート盤21内に埋設
する構成としたが、これを捨てコンクリート盤21上に
単に載置する構成としてもよい。さらに、地下躯体10
を構築するに際し、図5に示した状態とした後に、柱1
2,壁13に下層階から上層階に順次コンクリートCを
打設していく構成としたが、これに限るものではなく、
各階の梁14,床15を上層階から下層階に向けて順次
施工するときに、同時に柱12,壁13にコンクリート
Cを打設する構成としてもよい。加えて、コンクリート
Cを打設するためにパイプ25,29を用いる構成とし
たが、これを用いずに、従来と同様にして、型枠の上端
側部からコンクリートCを打設するようにしてもよい。
また、上記実施例では、柱12,壁13の両方に、鉄筋
接続具22を用いた施工方法を適用する構成としたが、
もちろん、柱12,壁13のいずれか一方のみに上記の
施工方法を適用し、他方には、鉄筋接続具22を用いな
い従来の施工方法を適用するようにしてもよい。
In the above embodiment, after the reinforcing bars 22 are arranged on the discarded concrete board 21 in the frame building process, the main bars 17a of the column bars 17 and the vertical bars 1 of the wall bars 18 are formed.
8a is inserted and connected to the rebar connection tool 22,
A structure in which the main reinforcing bar 17a of the column reinforcing bar 17 and the longitudinal bar 18a of the wall reinforcing bar 18 are inserted and connected to the reinforcing bar connecting tool 22 in advance may be arranged on the discarded concrete board 21. Further, the rebar connection tool 22 is configured to be buried in the discarded concrete board 21, but may be configured to be simply placed on the discarded concrete board 21. Furthermore, the underground skeleton 10
In constructing the pillar, after the state shown in FIG.
2. The concrete C is cast on the wall 13 sequentially from the lower floor to the upper floor, but the present invention is not limited to this.
When the beams 14 and floors 15 of each floor are sequentially constructed from the upper floor to the lower floor, concrete C may be simultaneously poured into the columns 12 and the walls 13. In addition, although the pipes 25 and 29 are used to cast the concrete C, the concrete C is cast from the upper end side of the form in the same manner as before without using this. Is also good.
Also, in the above embodiment, the construction method using the rebar connection tool 22 is applied to both the pillar 12 and the wall 13.
Of course, the above-described construction method may be applied to only one of the column 12 and the wall 13, and a conventional construction method that does not use the rebar connector 22 may be applied to the other.

【0030】また、上記実施例の地下躯体10を構築す
るときに、予め本設の柱12の柱鉄骨16を打ち込んで
おき、この柱鉄骨16を支柱として地上一階部11等、
施工中の地下躯体10の荷重を支持する構成としたが、
もちろん、この柱鉄骨16に代えて仮設柱を打ち込み、
この仮設柱で施工中の地下躯体10の荷重を支持するよ
うにしてもよい。さらには、このように仮設柱を用いて
施工を行うのであれば、地下躯体10の柱12がRC造
の場合にも本発明を適用することが可能であり、このよ
うな場合においても上記と同様の効果を奏することがで
きる。上記以外にも、地下躯体10の構成や施工の手順
等、他の構成についても、本願の趣旨を逸脱しない範囲
であれば、これらをいかなる構成としても、上記と同様
の効果を奏することができるのは言うまでもない。
Further, when constructing the underground skeleton 10 of the above embodiment, the column steel frame 16 of the main column 12 is previously driven in, and the column steel frame 16 is used as a column, and the ground floor 11 and the like are used.
Although it was configured to support the load of the underground skeleton 10 during construction,
Of course, a temporary column is driven in place of this column steel frame 16,
The temporary column may support the load of the underground skeleton 10 under construction. Furthermore, if the construction is performed using the temporary columns as described above, the present invention can be applied to the case where the columns 12 of the underground skeleton 10 are made of RC. Similar effects can be obtained. In addition to the above, other configurations, such as the configuration of the underground skeleton 10 and the procedure of construction, may have the same effect as described above, regardless of the configuration, as long as the configuration does not deviate from the gist of the present application. Needless to say.

【0031】[0031]

【発明の効果】以上説明したように、請求項1に係る地
下躯体の施工方法によれば、躯体構築工程で柱や壁を一
定長さ形成するときに、根切底面上に一定厚さの捨てコ
ンクリート盤を形成し、その上にコンクリートが硬化す
る前に筒状の鉄筋接続具を配置するとともに主鉄筋の下
端部を鉄筋接続具に挿入接続しておく構成とした。これ
により、従来のように底型枠を用いることなく、鉄筋を
捨てコンクリート盤上で支持して柱や壁の鉄筋を配筋・
組立することができるので、柱や壁の鉄筋および型枠の
組立作業を大幅に容易化することができ、工期の短縮化
を図ることが可能となり、そのうえ根切深さも最小限と
することができる。そして、掘削工程で地盤をさらに一
定深さ掘削するときに捨てコンクリート盤を取り壊すこ
とによって、躯体構築工程で形成した柱や壁の下面に前
記鉄筋接続具を露出させ、しかる後に下層階の躯体を構
築するときに、鉄筋接続具に形成すべき柱や壁の主鉄筋
の上端部を挿入接続する構成とした。これにより、既に
形成した柱や壁の下方に連続して形成すべき柱や壁の主
鉄筋を容易かつ確実に接続することができる。また、掘
削工程で捨てコンクリート盤を取り壊したときに、鉄筋
が柱や壁の下方に突出することもないので、安全性の向
上を図ることも可能となる。
As described above, according to the method for constructing an underground skeleton according to the first aspect, when a column or a wall is formed to a fixed length in the skeleton building process, a fixed thickness is formed on the root cutting bottom. Form a discarded concrete board on which concrete hardens
Before the installation, a tubular rebar connector is arranged and the lower end of the main rebar is inserted and connected to the rebar connector. As a result, instead of using a bottom formwork as in the past, the steel bars were discarded and supported on concrete boards to reinforce the columns and walls.
Since it can be assembled, the work of assembling the reinforcing bars and formwork of columns and walls can be greatly facilitated, the construction period can be shortened, and the root cutting depth can be minimized. it can. Then, by excavating the discarded concrete slab when excavating the ground further to a certain depth in the excavation process, the rebar connection fittings are exposed on the lower surfaces of the pillars and walls formed in the skeleton building process, and then the skeleton of the lower floor is removed. At the time of construction, the upper end portion of the main reinforcing bar of the pillar or wall to be formed on the reinforcing bar connector is inserted and connected. This makes it possible to easily and reliably connect the main reinforcing bars of the columns and walls to be continuously formed below the already formed columns and walls. In addition, when the discarded concrete slab is demolished in the excavation process, the reinforcing bars do not protrude below the columns and walls, so that it is possible to improve safety.

【0032】請求項2に係る地下躯体の施工方法によれ
ば、躯体構築工程で捨てコンクリート盤上に鉄筋接続具
を配置するときに、鉄筋接続具を捨てコンクリート盤内
に一定長さ埋め込む構成とした。これにより、鉄筋接続
具の位置決めを治具等を用いることなく容易に行うこと
ができるので、鉄筋組立の作業効率を向上させることが
でき、この点からも工期の短縮化を図ることが可能とな
る。
According to the construction method of the underground skeleton according to the second aspect, when arranging the rebar connection fitting on the discarded concrete board in the skeleton building step, the rebar connection fitting is discarded and embedded in the concrete board with a fixed length. did. This makes it possible to easily position the rebar connection tool without using a jig or the like, so that the work efficiency of rebar assembly can be improved, and from this point, the construction period can be shortened. Become.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る地下躯体の施工方法を適用して構
築する地下躯体の一例を示す正断面図である。
FIG. 1 is a front sectional view showing an example of an underground skeleton constructed by applying an underground skeleton construction method according to the present invention.

【図2】前記地下躯体の一部を示す平断面図である。FIG. 2 is a plan sectional view showing a part of the underground skeleton.

【図3】前記地下躯体の施工工程を示す図であって、地
上一階部を構築した状態を示す正断面図である。
FIG. 3 is a front sectional view showing a construction process of the underground skeleton, showing a state where a first floor above ground is constructed.

【図4】前記地下躯体の施工工程を示す図であって、地
上一階部の下方に地下一階部を構築した状態を示す正断
面図である。
FIG. 4 is a front sectional view showing a construction process of the underground skeleton, in which a first basement is constructed below a first floor above the ground;

【図5】前記地下躯体の施工工程を示す図であって、地
下五階部まで構築した状態を示す正断面図である。
FIG. 5 is a front sectional view showing a construction process of the underground skeleton and showing a state where the underground skeleton is constructed up to the fifth floor underground.

【図6】前記地下躯体の施工工程を示す図であって、柱
・壁にコンクリートを打設している状態を示す正断面図
である。
FIG. 6 is a front sectional view showing a construction step of the underground skeleton, showing a state in which concrete is cast on columns and walls.

【図7】従来の地下躯体の施工方法の一例を示す正断面
図である。
FIG. 7 is a front sectional view showing an example of a conventional method of constructing an underground skeleton.

【符号の説明】[Explanation of symbols]

10 地下躯体 12 柱 13 壁 17 柱鉄筋 17a 主筋(主鉄筋) 17b,18b 上端部 18 壁鉄筋 18a 縦筋(主鉄筋) 21 捨てコンクリート盤 22 鉄筋接続具 26 柱型枠(型枠) 27 壁型枠(型枠) C コンクリート G 地盤 G1 一次根切面(根切底面) G2 二次根切面(根切底面) DESCRIPTION OF SYMBOLS 10 Underground frame 12 Column 13 Wall 17 Column reinforcing bar 17a Main reinforcing bar (main reinforcing bar) 17b, 18b Upper end portion 18 Wall reinforcing bar 18a Vertical reinforcing bar (main reinforcing bar) 21 Discarded concrete panel 22 Reinforcing bar connection 26 Column form (form) 27 Wall type Frame (Form) C Concrete G Ground G1 Primary root (root bottom) G2 Secondary root (root bottom)

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平5−179668(JP,A) 特開 平6−173283(JP,A) 特開 平7−82759(JP,A) 実開 平2−107632(JP,U) (58)調査した分野(Int.Cl.7,DB名) E02D 29/045 E04B 1/35 E21D 13/00 ──────────────────────────────────────────────────続 き Continuation of the front page (56) References JP-A-5-179668 (JP, A) JP-A-6-173283 (JP, A) JP-A-7-82759 (JP, A) 107632 (JP, U) (58) Fields investigated (Int. Cl. 7 , DB name) E02D 29/045 E04B 1/35 E21D 13/00

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地盤中に地下躯体を構築するに際し、地
盤を一定深さ掘削する掘削工程と、掘削した根切底面上
に各階の躯体を構築する躯体構築工程とを交互に繰り返
すことによって、前記地下躯体を上層階から下層階に向
けて順次構築していく構成とし、 前記各躯体構築工程では、根切底面上に一定厚さの捨て
コンクリート盤を形成するとともに、該捨てコンクリー
ト盤上でコンクリートが硬化する前に筒状の鉄筋接続具
を配置し、形成すべき柱や壁の主鉄筋の下端部を前記鉄
筋接続具に挿入接続して柱や壁の鉄筋を定められた形状
に組み立てた後、該鉄筋の周囲で捨てコンクリート盤上
に、柱や壁の側面を形成するように型枠を組み立てて該
型枠内にコンクリートを打設することによって柱や壁を
一定長さ形成しておき、 その下方の根切底面を掘削するために前記掘削工程を行
うときに、前記根切底面を掘削するとともに前記捨てコ
ンクリート盤を取り壊して前記柱や壁の下面と前記鉄筋
接続具とを露出させ、しかる後に下層階を構築するため
に前記躯体構築工程を行うときに、前記鉄筋接続具に、
下方に形成すべき柱や壁の主鉄筋の上端部を挿入接続す
ることを特徴とする地下躯体の施工方法。
When constructing an underground skeleton in the ground, an excavation step of excavating the ground to a certain depth and a skeleton construction step of constructing a skeleton of each floor on the excavated root bottom are alternately repeated. The underground skeleton is constructed sequentially from the upper floor to the lower floor, and in each of the skeleton building steps, while forming a discarded concrete board having a constant thickness on the root bottom, and on the discarded concrete board , Before the concrete is hardened, a tubular reinforcing bar connection is arranged, and the lower end of the main reinforcing bar of the column or wall to be formed is inserted and connected to the reinforcing bar connecting unit to assemble the column or wall reinforcing bar into a predetermined shape. After that, throw away the concrete around the rebar
Then, the formwork is assembled so as to form the side surfaces of the columns and walls , and concrete is poured into the formwork to form the columns and walls to have a fixed length, and the root cutting surface below them is excavated. When performing the excavation step, to excavate the root bottom and demolish the discarded concrete board to expose the lower surface of the pillars and walls and the rebar connector, and then to construct a lower floor When performing the skeleton building step, to the rebar connector,
A method for constructing an underground skeleton, comprising inserting and connecting an upper end of a main reinforcing bar of a pillar or a wall to be formed below.
【請求項2】 請求項1記載の地下躯体の施工方法にお
いて、前記躯体構築工程で前記捨てコンクリート盤上に
前記鉄筋接続具を配置するときに、該鉄筋接続具を前記
捨てコンクリート盤内に一定長さ埋め込むことを特徴と
する地下躯体の施工方法。
2. The method for constructing an underground skeleton according to claim 1, wherein when the reinforced joint is arranged on the discarded concrete board in the skeleton building step, the reinforced joint is fixed inside the discarded concrete board. A method of constructing an underground skeleton characterized by embedding the length.
JP31382594A 1994-12-16 1994-12-16 Construction method of underground skeleton Expired - Fee Related JP3360234B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP31382594A JP3360234B2 (en) 1994-12-16 1994-12-16 Construction method of underground skeleton

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP31382594A JP3360234B2 (en) 1994-12-16 1994-12-16 Construction method of underground skeleton

Publications (2)

Publication Number Publication Date
JPH08170344A JPH08170344A (en) 1996-07-02
JP3360234B2 true JP3360234B2 (en) 2002-12-24

Family

ID=18045971

Family Applications (1)

Application Number Title Priority Date Filing Date
JP31382594A Expired - Fee Related JP3360234B2 (en) 1994-12-16 1994-12-16 Construction method of underground skeleton

Country Status (1)

Country Link
JP (1) JP3360234B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6740064B2 (en) * 2016-09-09 2020-08-12 鹿島建設株式会社 Construction method of concrete frame

Also Published As

Publication number Publication date
JPH08170344A (en) 1996-07-02

Similar Documents

Publication Publication Date Title
WO2011114507A1 (en) Method of constructing underground structure to be newly built
KR200381303Y1 (en) Form system for joint between retaining wall and slab of basement floor
JPH09209451A (en) Joint construction of up and down columns with beam and joint method
KR200385376Y1 (en) Form system for construction of underground slab
JP3360234B2 (en) Construction method of underground skeleton
JP6855296B2 (en) Building foundation structure and its construction method
JP3185129B2 (en) Column-integrated column base fixed foundation structure and its construction method
JPH11343667A (en) Structure for fixing column base with underground beam made of reinforced concrete
KR100456192B1 (en) Composition of precast concrete wall and precast concrete column for outdoor to sustain external force
JP2010084460A (en) Construction method for underground structure
JP2000034732A (en) Steel column mounting hardware, steel column mounting structure and steel column building method
JPH07292683A (en) Anchor frame and foundation construction method using the frame
JPH08170345A (en) Execution of work of underground skeleton
JPH04185816A (en) Construction of beam in underground wall
KR100694762B1 (en) Method for constructing underground slabs and walls without preliminary wall-attached supports
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH11323958A (en) Execution method of building and concrete product used therefor
JPH10131300A (en) Execution method for building by preceding erection of steel frame
JPH0657769A (en) Underground concrete structure and working method thereof
JP3039260B2 (en) Building method using PC members
JPS63537A (en) Construction work of underground structure
JP2940451B2 (en) How to build underground structures
JPH11181807A (en) Construction method for underground story
JPH0868115A (en) Connecting structure for column/beam and construction method for underground skeleton using it
JPH0376929A (en) Steel-framed foundation

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20020910

LAPS Cancellation because of no payment of annual fees